FORMAT DRAFT RAB/HPS PADA SAAT MENGAJUKAN LELANG KE ULP

No Jenis Barang/Jasa Satuan Vol Satuan 2 Vol 2 Harga Satuan Pajak(%) Total Keterangan
a b c d e f g h i=(d x f x g)+(d x f x g x 10%) j

1 Pondasi Batu Belah M3 12,50 1,00 530000 10,00 7.287.500,00 Analisa 2008 2887 3 6
2 Dinding Bata Camp. 1 : 4 M2 120,50 1,00 125000 10,00 16.568.750,00 Analisa 2008 2887 3 7
3 Plesteran Dinding Camp. 1 : 2 M2 241,00 1,00 34000 10,00 9.013.400,00 Analisa 2008 2887 3 8
4 Galian Pondasi M3 15,63 1,00 35000 10,00 601.755,00 Analisa 2008 2887 3 9
5 Pas. Kusen Pintu dan Jendela M3 0,57 1,00 1500000 10,00 940.500,00 Analisa 2008 2887 3 10
6 Pengecatan M2 241,00 1,00 25000 10,00 6.627.500,00 Analisa 2008 2887 3 11
7 Mobil Unit 5,00 1,00 150000000 10,00 825.000.000,00
8 Printer Unit 4,00 1,00 1500000 10,00 6.600.000,00
9 Ahli Bangunan Sipil Orang 3,00 Bulan 6,00 10000000 10,00 198.000.000,00
10 Ahli Arsitektur Orang 2,00 Bulan 12,00 10000000 10,00 264.000.000,00
TOTAL GENERAL 1.334.639.405,00

KETERANGAN :
- Dalam pembuatan RAB/HPS jangan sampai ada BARIS maupun KOLOM yang di HIDE/DISEMBUNYIKAN
- No. 1 s/d No. 6, merupakan contoh pembuatan RAB/HPS untuk PEKERJAAN KONSTRUKSI
- No. 7 s/d No. 8, merupakan contoh pembuatan RAB/HPS untuk PENGADAAN BARANG
- No. 9 s/d No. 10, merupakan contoh pembuatan RAB/HPS untuk JASA KONSULTANSI dan JASA LAINNYA
- Dalam Pembuatan RAB/HPS untuk PEKERJAAN KONSTRUKSI, Kolom ( e ) dibiarkan KOSONG/TIDAK PERLU DIISI dan Kolom ( f ) diisi dengan ANGKA/NILAI 1 (JANGAN DIBIARKAN KOSONG)
- Dalam Pembuatan RAB/HPS untuk PENGADAAN BARANG, Kolom ( e ) dibiarkan KOSONG/TIDAK PERLU DIISI dan Kolom ( f ) diisi dengan ANGKA/NILAI 1 (JANGAN DIBIARKAN KOSONG)
- Dalam Pembuatan RAB/HPS untuk JASA KONSULTANSI dan JASA LAINNYA, Kolom ( e ) dan Kolom ( f ) diisi sebagaimana Format/Draft Tabel diatas.