OPERASIONAL KANTOR
TOTAL HARGA
NO. URAIAN KEGIATAN
(Rp)
Terbilang : DUA MILYAR SEMBILAN RATUS TUJUH PULUH DELAPAN JUTA TIGA RATUS RIBU RUPIAH
PERHITUNGAN RENCANA ANGGARAN BIAYA
OPERASIONAL KANTOR
I. BIAYA PERSONIL
VOLUME WAKTU
NO. TENAGA AHLI M/M Salary (Rp) JUMLAH (Rp)
(MAN) (MONTH)
A. PROFESSIONAL STAFF
1 Direktur Utama 1 12.00 12.00 15,000,000.00 180,000,000.00
2 Direktur Teknik 1 12.00 12.00 10,000,000.00 120,000,000.00
3 Direktur Keuangan 1 12.00 12.00 10,000,000.00 120,000,000.00
4 Staf Teknik 2 12.00 24.00 5,000,000.00 120,000,000.00
5 Staf Keuangan 2 12.00 24.00 5,000,000.00 120,000,000.00
6 Projeck Manager 1 12.00 12.00 8,500,000.00 102,000,000.00
7 Site Manager 1 12.00 12.00 7,500,000.00 90,000,000.00
8 Logistik 1 12.00 12.00 5,000,000.00 60,000,000.00
9 Surveyor 2 12.00 24.00 5,000,000.00 120,000,000.00
10 Administrasi 2 12.00 24.00 5,000,000.00 120,000,000.00
JUMLAH 1,152,000,000.00
JUMLAH 1,650,000,000.00
JUMLAH 169,200,000.00
IV. BIAYA LAIN-LAIN
JUMLAH 7,100,000.00
224,176,875.00
2,978,300,000.00