PROGRESS PKERJAAN

KPP MADYA BOGOR & KPP PRATAMA BOGOR


BOGOR - JAWA BARAT
TAHAP II (2019)
PEKERJAAN : MARMER DAN GRANIT
MANDOR/SUBKON : SARNO
NO JENIS PEKERJAAN VOLUME VOLUME SAT HARGA JUMLAH VOLUME VOLUME JUMLAH VOLUME JUMLAH
KONTRAK CCO SISA OPNAME 1 OPNAME 1 OPNAME 2 OPNAME 2
DINDING MARMER
1 BAHAN MARMER STATUARIO tbl 2 cm 17.57 17.57 M² 2,550,000 44,798,400 - 17.57 44,798,400 - -
2 TENAGA PASANG DINDNING STATUARIO 17.57 17.57 M² 450,000 7,905,600 - 17.57 7,905,600 - -
3 BAHAN NERO MARQUINA tbl 2 cm 3.60 3.60 M² 950,000 3,420,000 - 3.60 3,420,000 - -
4 PASANG MARMER LIST ( NERO MARQUINA ) tbl 2 cm 7.20 7.20 M¹ 95,000 684,000 - 7.20 684,000 - -
5 COATING MARMER ( BAHAN ISINOL) 21.17 21.17 M² 65,000 1,375,920 - - 21.17 1,375,920
6 POLES WOLL 21.17 21.17 M² 35,000 740,880 - - 21.17 740,880
7 Pasang Sistem Kering ex Siku 40x40x4 21.17 21.17 M² 45,000 952,560 - 21.17 952,560 - -
59,877,360 57,760,560 2,116,800

MEJA WESTAPEL
1 BAHAN GRANIT NERO INDIA 14.45 15.96 M² 925,000 14,760,031 - 12.77 11,808,025 3.19 2,952,006
2 TENAGA PASANG GRANIT MEJA ESTAPEL 36.35 40.11 M¹ 275,000 11,030,250 - 5.42 1,490,500 34.69 9,539,750
25,790,281 13,298,525 12,491,756

POLA ( MOTIF) MARMER


1 BAHAN MARMER CARARA WHITE 7.82 7.82 M² 1,600,000 12,513,000 - 7.82 12,513,000 - -
2 BAHAN MARMER GIALOW SIENA 3.72 3.72 M² 3,900,000 14,508,000 - 2.60 10,155,600 1.12 4,352,400
3 BAHAN MARMER NERO MARQUINA 8.59 8.59 M² 950,000 8,159,906 - 8.59 8,159,906 - -
4 BIKIN DAN PASANG MOTIF 1.00 1.00 UNIT 6,000,000 6,000,000 - 0.30 1,800,000 0.70 4,200,000
5 PASANG BORDER 38.20 38.20 M¹ 35,000 1,337,000 - 11.46 401,100 26.74 935,900
6 COATING MARMER ( BAHAN ISINOL) 17.64 17.64 M² 65,000 1,146,327 - - 17.64 1,146,327
7 POLES MARMER 17.64 17.64 M² 65,000 1,146,327 - - 17.64 1,146,327
8 KRISTALISASI 17.64 17.64 M² 55,000 969,969 - - 17.64 969,969
45,780,529 33,029,606 12,750,923
TOTAL 131,448,170 104,088,691 27,359,479

DP 30% Rp 39,434,451
Opname 1 Rp 104,088,691
Retensi Rp 5,204,435
Yang Perlu Dibayarkan Rp 59,449,805
Sisa Tagihan Rp 32,563,914

Opname 2 Rp 27,359,479
Retensi Rp 1,367,974
Yang Perlu Dibayarkan Rp 25,991,505
Sisa Tagihan Rp 6,572,409

Disetujui Oleh Diperiksa Oleh Dibuat Oleh Diajukan Oleh

AHMAD FIRDAUS Antonius Soni Denny Arif Sarno


Project Manager Project Control
PROGRESS PKERJAAN
KPP MADYA BOGOR & KPP PRATAMA BOGOR
BOGOR - JAWA BARAT
TAHAP II (2019)
PEKERJAAN : MARMER DAN GRANIT
MANDOR/SUBKON : SARNO

VOLUME VOLUME JUMLAH


NO JENIS PEKERJAAN VOLUME SATUAN HARGA JUMLAH SISA OPNAME 1 OPNAME 1
DINDING MARMER
1 BAHAN MARMER STATUARIO tbl 2 cm 17.57 M² 2,550,000 44,798,400 - 17.57 44,798,400
2 TENAGA PASANG DINDNING STATUARIO 17.57 M² 450,000 7,905,600 - 17.57 7,905,600
3 BAHAN NERO MARQUINA tbl 2 cm 3.60 M² 950,000 3,420,000 - 3.60 3,420,000
4 PASANG MARMER LIST ( NERO MARQUINA ) tbl 2 7.20 M¹ 95,000 684,000 - 7.20 684,000
5 COATING MARMER ( BAHAN ISINOL) 21.17 M² 65,000 1,375,920 21.17 -
6 POLES WOLL 21.17 M² 35,000 740,880 21.17 -
7 Pasang Sistem Kering ex Siku 40x40x4 21.17 M² 45,000 952,560 - 21.17 952,560
59,877,360 57,760,560

MEJA WESTAPEL
1 BAHAN GRANIT NERO INDIA 14.45 M² 925,000 13,368,831 2.89 11.56 10,695,065
2 TENAGA PASANG GRANIT MEJA ESTAPEL 36.35 M¹ 275,000 9,996,250 30.93 5.42 1,490,500
23,365,081 12,185,565

POLA ( MOTIF) MARMER


1 BAHAN MARMER CARARA WHITE 7.82 M² 1,600,000 12,513,000 - 7.82 12,513,000
2 BAHAN MARMER GIALOW SIENA 3.72 M² 3,900,000 14,508,000 1.12 2.60 10,155,600
3 BAHAN MARMER NERO MARQUINA 8.59 M² 950,000 8,159,906 - 8.59 8,159,906
4 BIKIN DAN PASANG MOTIF 1.00 UNIT 6,000,000 6,000,000 0.70 0.30 1,800,000
5 PASANG BORDER 38.20 M¹ 35,000 1,337,000 26.74 11.46 401,100
6 COATING MARMER ( BAHAN ISINOL) 17.64 M² 65,000 1,146,327 17.64 -
7 POLES MARMER 17.64 M² 65,000 1,146,327 17.64 -
8 KRISTALISASI 17.64 M² 55,000 969,969 17.64 -
45,780,529 33,029,606
TOTAL 129,022,970 102,975,731

DP 30% Rp 38,706,891
Opname 1 Rp 102,975,731
Retensi Rp 5,148,787
Yang Perlu Dibayarkan Rp 59,120,053
Sisa Tagihan Rp 31,196,026

Opname 1 Rp -
Retensi Rp -
Yang Perlu Dibayarkan Rp -
Sisa Tagihan Rp -
Disetujui Oleh Diperiksa Oleh Dibuat Oleh

AHMAD FIRDAUS Antonius Soni Denny Arif


Project Manager Project Control
PENAWARAN PEKERJAAN DINDING LIFF, DINDING MARMER, MEJA WESTAPEL DAN POLA (MOTIF MARMAER LANTA

NO JENIS PEKERJAAN VOLUME SATUAN


DINDING MARMER
1 BAHAN MARMER STATUARIO tbl 2 cm 17.57 M²
2 TENAGA PASANG DINDNING STATUARIO 17.57 M²
3 BAHAN NERO MARQUINA tbl 2 cm 3.60 M²
4 PASANG MARMER LIST ( NERO MARQUINA ) tbl 2 cm 7.20 M¹
5 COATING MARMER ( BAHAN ISINOL) 21.17 M²
6 POLES WOLL 21.17 M²
7 Pasang Sistem Kering ex Siku 40x40x4 21.17 M²

NO JENIS PEKERJAAN VOLUME SATUAN


MEJA WASTAFEL ( 24 Unit ) lt 1 s/d 6
1 BAHAN GRANIT NERO INDIA 14.45 M²
2 TENAGA PASANG GRANIT MEJA ESTAPEL 36.35 M¹

NO JENIS PEKERJAAN VOLUME SATUAN

POLA ( MOTIF) MARMER


1 BAHAN MARMER CARARA WHITE 7.82 M²
2 BAHAN MARMER GIALOW SIENA 3.72 M²
3 BAHAN MARMER NERO MARQUINA 8.59 M²
4 BIKIN DAN PASANG MOTIF 1.00 UNIT
5 PASANG BORDER 38.20 M¹
6 COATING MARMER ( BAHAN ISINOL) 17.64 M²
7 POLES MARMER 17.64 M²
8 KRISTALISASI 17.64 M²
KEPADA YTH
BPK SONY
DITEMPAT

DAN POLA (MOTIF MARMAER LANTAI

HARGA JUMLAH

2,650,000 46,555,200
470,000 8,256,960
950,000 3,420,000
95,000 684,000
65,000 1,375,920
35,000 740,880
175,000 3,704,400
64,737,360

HARGA JUMLAH

925,000 13,368,831
300,000 10,905,000
24,273,831

HARGA JUMLAH

1,700,000 13,295,063
4,000,000 14,880,000
950,000 8,159,906
6,500,000 6,500,000
35,000 1,337,000
65,000 1,146,327
65,000 1,146,327
55,000 969,969
47,434,592
PENAWARAN PEKERJAAN DINDING LIFF, DINDING MARMER, MEJA WESTAPEL DAN POLA (MOTIF MARMAER LAN

NO JENIS PEKERJAAN VOLUME SATUAN HARGA


MARMER DINDING LIFF
1 BAHAN MARMER CARARA WHAITE 4.965 M² 1,700,000
2 TENAGA PASANG 7.05 M¹ 350,000
3 SIKADUR UNTUK PASANG 7.05 M¹ 75,000
4 COATING MARMER ( BAHAN ISINOL) 4.965 M² 65,000
5 POLES WOLL 4.965 M² 35,000

NO JENIS PEKERJAAN VOLUME SATUAN HARGA


DINDING MARMER
1 BAHAN MARMER CARARA WHAITE 12.6 M² 1,700,000
2 TENAGA PASANG DINDNING CARARA WHAITE 12.6 M² 525,000
3 BAHAN MARMER CARARA GIALO SIENA 6.84 M² 2,235,000
4 PASNAR MARMER LIST ( BORDER GIALI SIENA 15.18 M¹ 95,000
5 COATING MARMER ( BAHAN ISINOL) 20.026 M² 65,000
6 POLES WOLL 20.026 M² 35,000

NO JENIS PEKERJAAN VOLUME SATUAN HARGA


MEJA WESTAPEL
1 BAHAN GRANIT NERO INDIA 2.782 M² 95,000
2 TENAGA PASANG GRANIT MEJA ESTAPEL 5.42 M¹ 350,000

NO JENIS PEKERJAAN VOLUME SATUAN HARGA


POLA ( MOTIF) MARMER )
1 BAHAN MARMER CARARA WHAITE 7.82 M² 1,700,000
2 BAHAN MARMER CARARA GIALO SIENA 3.72 M² 2,235,000
3 BAHAN MARMER NERO MARQUINA 14.01 M² 95,000
4 BIKIN DAN PASANG MOTIF 1 UNIT 7,500,000
5 PASANG BORDER 38.2 M¹ 35,000
6 COATING MARMER ( BAHAN ISINOL) 17.6358 M² 65,000
7 POLES MARMER 17.6358 M² 65,000
8 KRISTALISASI 17.6358 M² 55,000

JAKARTA TGL 235-09-2019


(SARNO)
KEPADA YTH
BPK SONY
DITEMPAT

DAN POLA (MOTIF MARMAER LANTAI

JUMLAH

-
-
-
-
-
-

JUMLAH

21,420,000
6,615,000
15,287,400
1,442,100
1,301,690
700,910
46,767,100

JUMLAH

264,290
1,897,000
2,161,290

JUMLAH

13,294,000
8,314,200
1,330,950
7,500,000
1,337,000
1,146,327
1,146,327
969,969
35,038,773
PENAWARAN PEKERJAAN DINDING LIFF, DINDING MARMER, MEJA WESTAPEL DAN POLA (MOTIF MARMAER LANTA

NO JENIS PEKERJAAN VOLUME SATUAN


DINDING MARMER
1 BAHAN MARMER STATUARIO tbl 2 cm 17.57 M²
2 TENAGA PASANG DINDNING STATUARIO 17.57 M²
3 BAHAN NERO MARQUINA tbl 2 cm 3.60 M²
4 PASANG MARMER LIST ( NERO MARQUINA ) tbl 2 cm 7.20 M¹
5 COATING MARMER ( BAHAN ISINOL) 21.17 M²
6 POLES WOLL 21.17 M²
7 Pasang Sistem Kering ex Siku 40x40x4 21.17 M²

NO JENIS PEKERJAAN VOLUME SATUAN


MEJA WASTAFEL ( 24 Unit ) lt 1 s/d 6
1 BAHAN GRANIT NERO INDIA 14.45 M²
2 TENAGA PASANG GRANIT MEJA ESTAPEL 36.35 M¹

NO JENIS PEKERJAAN VOLUME SATUAN

POLA ( MOTIF) MARMER


1 BAHAN MARMER CARARA WHITE 7.82 M²
2 BAHAN MARMER GIALOW SIENA 3.72 M²
3 BAHAN MARMER NERO MARQUINA 8.59 M²
4 BIKIN DAN PASANG MOTIF 1.00 UNIT
5 PASANG BORDER 38.20 M¹
6 COATING MARMER ( BAHAN ISINOL) 17.64 M²
7 POLES MARMER 17.64 M²
8 KRISTALISASI 17.64 M²
KEPADA YTH
BPK SONY
DITEMPAT

DAN POLA (MOTIF MARMAER LANTAI

HARGA JUMLAH

2,650,000 46,555,200
470,000 8,256,960
950,000 3,420,000
95,000 684,000
65,000 1,375,920
35,000 740,880
175,000 3,704,400
64,737,360

HARGA JUMLAH

925,000 13,368,831
300,000 10,905,000
24,273,831

HARGA JUMLAH

1,700,000 13,295,063
4,000,000 14,880,000
950,000 8,159,906
6,500,000 6,500,000
35,000 1,337,000
65,000 1,146,327
65,000 1,146,327
55,000 969,969
47,434,592
NO URAIAN PEKERJAAN DIMENSI
P L

1 Dinding Marmer ( Utama ) ex Statuario 4.88 3.6


2 Border Marmer Ex Nero Marquina 1 3.6
Total Luas
VOL SAT

17.568 m2
3.6 m2
21.168 m2
Meja Washtafel
uraian L P Unit Vol Keterangan
Meja Washtafel 0.32 0.94 2.00 0.59 Area Difabel
Plint Meja Washtafel 0.10 0.94 2.00 0.19 Area Difabel
Meja Washtafel 0.29 2.47 6.00 4.25 Toilet Wanita
Plint Meja Washtafel 0.10 2.47 6.00 1.48 Toilet Wanita
Meja Washtafel 0.32 2.03 6.00 3.83 Toilet Pria
Plint Meja Washtafel 0.10 2.03 6.00 1.22 Toilet Pria
Meja Washtafel 0.29 0.75 10.00 2.15 Eselon
Plint Meja Washtafel 0.10 0.75 10.00 0.75 Tot Panjang
14.45

Dinding Marmer

14.45
Upah Pasang Meja Jumlah Harga Luas 1 Slab Total Slab Harga Sat / Slab
1.88 350,000.00 658,000.00 2.43 7.00 3,278,880.00

14.82 350,000.00 5,187,000.00

12.15 350,000.00 4,252,500.00

7.50 350,000.00 2,625,000.00


36.35 12,722,500.00
Total Harga Bahan Total Harga Bahan + Upah
22,952,160.00 35,674,660.00
NO URAIAN DIM
VOL
P L

1 Pola 2.04 2.04 4.16

1 List Kuning ex Gialow Siena 2.375 0.1 0.95


Kotak ex Gialow Siena 0.3 0.3 0.36
1.31
2 BORDER HITAM EX NIRO MARQUINNA 4.2 4.2 17.64
3.175 3.175 10.08
2.575 0.1 1.03

3 CARARA WHITE 2.175 2.175 4.73

BORDER EX CARARA WHITE 2.575 0.3 3.09


KET HARGA SAT
TOT VOL

4.16 CARARA WHITE 1,550,000.00 6,450,480.00


GIALOW SIENA
NERO MARQUINA

1.31
8.59

4.73

3.09
7.82