Nomor : 11 / 03 / HAR / SIPIL / 17

Tanggal : 20 MARET 2017


Halaman : 01 HALAMAN
Group : PEK. FASILITAS SIPIL
( Gedung Kantor & Workshop,
Emplasement & Jalan,
MCK & Drainase )
RENCANA ANGGARAN BIAYA MATERIAL / JASA
( ESTIMASI HARGA / OWNER ESTIMATE )

DEPARTEMEN PEMELIHARAAN
NO MACAM / LOKASI / RENCANA KEBUTUHAN MATERIAL / PART / JASA ESTIMASI HARGA NO. SPR / KETERANGAN
URAIAN PEKERJAAN BAGIAN No Nama (Material / Part / Jasa) dan Spesifikasi Jml Sat Per Satuan Total OKR / MEMO (SKOPE OF WORK)
01 02 03 04 05 06 07 08 09 10 11 12
NORMALISASI STOP KRAN I MATERIAL & JASA
SELURUH WORKSHOP 1 PERSIAPAN (PREPARE), 1.00 LS 1,500,000.00 1,500,000.00 (RUSH ORDER) U/. PERBAIKAN SESUAI
(Mobilisasi, Equipment, Tools, Cleaning Area) DENGAN PERMINTAAN

LOKASI : 2 PENGGANTIAN STOP KRAN 191.00 pcs 170,000.00 32,470,000.00


WS. WELD 1, WS. WELD. 2, PRKB, PRKT ( Stop kran / ball valve jenis Brass Valve ᴓ 3/4 merk ONDA,
GEDUNG L, GEDUNG N, INTERIOR TIMUR pembongkaran & penggantian baru)
2.1 WS. Welding 1 divisi Fabrikasi :
# stop kran angin (Ball Valve), ᴓ 3/4" 22.00 pcs
VOLUME : 2.2 WS. Welding 2 divisi Fabrikasi :
STOP KRAN : 191 PCS # stop kran angin (Ball Valve), ᴓ 3/4" 7.00 pcs
2.3 PRKB div. Fabrikasi
# stop kran angin (Ball Valve), ᴓ 3/4" 72.00 pcs
# stop kran air (Ball Valve), ᴓ 3/4" 4.00 pcs
2.4 PRKT div Fabrikasi
# stop kran angin (Ball Valve), ᴓ 3/4" 26.00 pcs
PEKERJAAN : # stop kran air (Ball Valve), ᴓ 3/4" 14.00 pcs
1. PERSIAPAN 2.5 Gedung L div. Final
2. PENGGANTIAN STOP KRAN # stop kran angin (Ball Valve), ᴓ 3/4" 43.00 pcs
3. FINISH 2.6 Gedung N div. QA
# stop kran angin (Ball Valve), ᴓ 3/4" 2.00 pcs
2.7 Interior Timur div. Final
# stop kran angin (Ball Valve), ᴓ 3/4" 1.00 pcs
Total : 191.00 pcs

Catatan :
1. PEKERJAAN OLEH PIHAK LUAR (SUBKONT) JUMLAH RP. 33,970,000.00
( Incl. material, equipment, tools)
2. PEKERJAAN SEGERA STAFF MANAGER SENIOR MANAGER
3. REFERENSI HARGA SATUAN POKOK KOTA MADIUN TAHUN 2017 FASILITAS DEPT HAR
Tanggal 17/03/2017 17/03/2017 17/03/2017
Nama PUPUT INDRA PRAJITNO

Tanda Tangan

Page 1 of 3 463617230.xls
PERHITUNGAN PENAMBAHAN JALUR REL HUTAN LINDUNG (18 M x 12)
PANJANG JALUR / TRACK : 18M x 12 = 216 M
PANJANG REL : 216 x 2 = 432 M

No Skope Pekerjaan Panjang Lebar Tebal/Tinggi Luas Volume Berat Jenis Jumlah Total Qty Satuan Harga/Sat Total Harga
(Nama Object) (m) (m) (m) (m2) (m3) (kg/m3) (Qty) (Rp) (Rp)

1 PREPARE (PERSIAPAN) 1.00 LS 1,500,000.00 1,500,000.00


(Mobilisasi, Equipment, Tools)

2 RABAT BETON,
(Perabatan Beton tanpa tulangan, K-300, Ready mix)
- WorkShop Har & Fas : 17.50 20.00 0.050 17.500 1.00 17.50 M3 1,350,000.00 23,625,000.00
(Panjang 17,5m, Lebar 20m, Tebal 5cm, Qty : 1 Bh)
- WorkShop Forklift :
(Panjang 20m, Lebar 10m, Tebal 8,5cm, Qty : 1 Bh) 20.00 10.00 0.085 17.000 1.00 17.00 M3 1,350,000.00 22,950,000.00
- Tempat Parkir Forklift :
(Panjang 11,3m, Lebar 4,6m, Tebal 10cm, Qty : 1 Bh) 11.30 4.60 0.100 5.198 1.00 5.20 M3 1,350,000.00 7,017,300.00

3 PENGECATAN LANTAI WORKSHOP,


(Pengecatan Lantai WorkShop, Jenis Cat :Epoxy Coating)
- Lantai WorkShop Har & Fas : 22.50 20.00 450.00 1.00 450.00 M2 75,000.00 33,750,000.00
(Panjang 22,5m, Lebar 20m, Epoxy Coating, Qty : 1 Bh)
- Lantai WorkShop Forklift :
(Panjang 20m, Lebar 10m, Epoxy Coating, Qty : 1 Bh) 20.00 10.00 200.00 1.00 200.00 M2 75,000.00 15,000,000.00

103,842,300.00

Catatan :
1. Refference Harga Berdasarkan :
Daftar Rekapitulasi Harga Satuan Pokok Kegiatan Tahun 2015 (Zona 1)
Kabupaten Madiun & Kodya Madiun

MADIUN, 10 NOVEMBER 2015

STAFF FAS-HAR

JOKO HARIYANTO
INKA
PT. INDUSTRI KERETA API (PERSERO)
Jl. Yos Sudarso No. 71 Madiun. Telp. 0351 452271-74 Fax. 0351 452274
Website : www.inka.co.id
E-mail : sekretaris@inka.co.id

PERBAIKAN KEMBALI SELOKAN


LOKASI SEBELAH UTARA WORKSHOP T (MO)

1. LATAR BELAKANG

Kondisi sekarang selokan mengalami kerusakan :


- Dinding samping sebelah utara roboh menimpa sisi sebelah selatan
- Aliran air yang keluar INKA menjadi tidak lancar
- Menimbulkan erosi tanah di sebelah dalam dinding

2. LANGKAH PERBAIKAN

Selokan direncanakan di perbaiki untuk di kembalikan ke fungsi


semula dengan langkah perbaikan sebagai berikut :
- Pembongkaran dinding bekas selokan yang roboh
- Di lakukan penambahan betonan bertulang
(Sloof Ring dan Kolom) untuk menambah kekuatan
structure dinding samping
- Dinding di kembalikan tetap dengan pasangan batu gibal
- Penambahan penguat dinding samping dengan rel bekas
untuk tambahan penyangga dinding agar tidak roboh
(seperti yang sudah di lakukan dengan structure selokan
yang lain)
- Foto kerusakan dan RAB terlampir

Demikian rencana perbaikan kembali selokan dan atas perhatianya


terima kasih.

Pekerjaan Sipil

Joko Hariyanto