Nomor : 04 / 04 / HAR / SIPIL / 17

Tanggal : 06 APRIL 2017


Halaman : 01 HALAMAN
Group : PEK. FASILITAS SIPIL
( Gedung Kantor & Workshop,
Emplasement & Jalan,
MCK & Drainase )
RENCANA ANGGARAN BIAYA MATERIAL / JASA
( ESTIMASI HARGA / OWNER ESTIMATE )
DEPARTEMEN PEMELIHARAAN
NO MACAM / LOKASI / RENCANA KEBUTUHAN MATERIAL / PART / JASA ESTIMASI HARGA NO. SPR / KETERANGAN
URAIAN PEKERJAAN BAGIAN No Nama (Material / Part / Jasa) dan Spesifikasi Jml Sat Per Satuan Total OKR / MEMO (SKOPE OF WORK)
01 02 03 04 05 06 07 08 09 10 11 12
RENOVASI WORKSHOP BOGIE I MATERIAL & JASA
1 PERSIAPAN (PREPARE), 1.00 LS 2,500,000.00 2,500,000.00 (RUSH ORDER) U/. PERBAIKAN SESUAI
(Mobilisasi, Equipment, Tools, Cleaning Area) DENGAN PERMINTAAN

LOKASI : 2 PENGECATAN LANTAI 5,211.25 m2 127,000.00 661,828,750.00


GD. J - WS BOGIE (Spec cat menggunakan cat Propan epoxy, warna, jenis & ketebalan
mengikuti aproval dari INKA)
# Pengecatan 2 tahap. Primer coat & finishing coat.
# Luas area besar : 151 m x 30 m = 4530 m2
VOLUME : # Luas area kecil : 54,5 m x 12,5 m = 681,25 m2
LUAS LANTAI = 5211,25 M2 # Total Luas : 4530 + 681,25 = 5211,25 m2

3 PENGECATAN DINDING 85,500,000.00


(Cat propan dengan warna mengacu pada gedung H sebagai standart)
PEKERJAAN : 3.1 Cat Eksterior 855.00 m2 60,000.00 51,300,000.00
1. PERSIAPAN # Utara : 355 m2
2. PENGECATAN LANTAI # selatan : 200 m2
3. PENGECATAN DINDING # barat : 150 m2
4. PENGGANTIAN KACA JENDELA # timur : 150 m2
5. FINISH # total luas : 855 m2
# NB : Jendela kaca tidak dicat
3.2 Cat Interior 855.00 m2 40,000.00 34,200,000.00
# total luas : 855 m2

4 PENGGANTIAN KACA 3,891,300.00


(Penggantian kaca eksisting yang rusak, Lebar : 95 cm, tinggi : 130 cm
Qty : 15 bh, kaca bening tebal 5 mm)
# Total Luas : 1,3 x 0,95 x 15 = 18,53 m2
# Pembongkaran kaca 18.53 m2 50,000.00 926,500.00
# Pemasangan kaca 18.53 m2 160,000.00 2,964,800.00
# NB : Kaca sliding mengikuti eksisting
Catatan :
1. PEKERJAAN OLEH PIHAK LUAR (SUBKONT) JUMLAH RP. 753,720,050.00
( Incl. material, equipment, tools)
2. PEKERJAAN SEGERA STAFF MANAGER SENIOR MANAGER
3. REFERENSI HARGA SATUAN POKOK KOTA MADIUN TAHUN 2017 HAR FASILITAS DEPT HAR
Tanggal 06 APRIL 2017 06 APRIL 2017 06 APRIL 2017
Nama PUPUT INDRA SUMONO PRAJITNO

Tanda Tangan

Page 1 of 3 464285120.xls
PERHITUNGAN PENAMBAHAN JALUR REL HUTAN LINDUNG (18 M x 12)
PANJANG JALUR / TRACK : 18M x 12 = 216 M
PANJANG REL : 216 x 2 = 432 M

No Skope Pekerjaan Panjang Lebar Tebal/Tinggi Luas Volume Berat Jenis Jumlah Total Qty Satuan Harga/Sat Total Harga
(Nama Object) (m) (m) (m) (m2) (m3) (kg/m3) (Qty) (Rp) (Rp)

1 PREPARE (PERSIAPAN) 1.00 LS 1,500,000.00 1,500,000.00


(Mobilisasi, Equipment, Tools)

2 RABAT BETON,
(Perabatan Beton tanpa tulangan, K-300, Ready mix)
- WorkShop Har & Fas : 17.50 20.00 0.050 17.500 1.00 17.50 M3 1,350,000.00 23,625,000.00
(Panjang 17,5m, Lebar 20m, Tebal 5cm, Qty : 1 Bh)
- WorkShop Forklift :
(Panjang 20m, Lebar 10m, Tebal 8,5cm, Qty : 1 Bh) 20.00 10.00 0.085 17.000 1.00 17.00 M3 1,350,000.00 22,950,000.00
- Tempat Parkir Forklift :
(Panjang 11,3m, Lebar 4,6m, Tebal 10cm, Qty : 1 Bh) 11.30 4.60 0.100 5.198 1.00 5.20 M3 1,350,000.00 7,017,300.00

3 PENGECATAN LANTAI WORKSHOP,


(Pengecatan Lantai WorkShop, Jenis Cat :Epoxy Coating)
- Lantai WorkShop Har & Fas : 22.50 20.00 450.00 1.00 450.00 M2 75,000.00 33,750,000.00
(Panjang 22,5m, Lebar 20m, Epoxy Coating, Qty : 1 Bh)
- Lantai WorkShop Forklift :
(Panjang 20m, Lebar 10m, Epoxy Coating, Qty : 1 Bh) 20.00 10.00 200.00 1.00 200.00 M2 75,000.00 15,000,000.00

103,842,300.00

Catatan :
1. Refference Harga Berdasarkan :
Daftar Rekapitulasi Harga Satuan Pokok Kegiatan Tahun 2015 (Zona 1)
Kabupaten Madiun & Kodya Madiun

MADIUN, 10 NOVEMBER 2015

STAFF FAS-HAR

JOKO HARIYANTO
INKA
PT. INDUSTRI KERETA API (PERSERO)
Jl. Yos Sudarso No. 71 Madiun. Telp. 0351 452271-74 Fax. 0351 452274
Website : www.inka.co.id
E-mail : sekretaris@inka.co.id

PERBAIKAN KEMBALI SELOKAN


LOKASI SEBELAH UTARA WORKSHOP T (MO)

1. LATAR BELAKANG

Kondisi sekarang selokan mengalami kerusakan :


- Dinding samping sebelah utara roboh menimpa sisi sebelah selatan
- Aliran air yang keluar INKA menjadi tidak lancar
- Menimbulkan erosi tanah di sebelah dalam dinding

2. LANGKAH PERBAIKAN

Selokan direncanakan di perbaiki untuk di kembalikan ke fungsi


semula dengan langkah perbaikan sebagai berikut :
- Pembongkaran dinding bekas selokan yang roboh
- Di lakukan penambahan betonan bertulang
(Sloof Ring dan Kolom) untuk menambah kekuatan
structure dinding samping
- Dinding di kembalikan tetap dengan pasangan batu gibal
- Penambahan penguat dinding samping dengan rel bekas
untuk tambahan penyangga dinding agar tidak roboh
(seperti yang sudah di lakukan dengan structure selokan
yang lain)
- Foto kerusakan dan RAB terlampir

Demikian rencana perbaikan kembali selokan dan atas perhatianya


terima kasih.

Pekerjaan Sipil

Joko Hariyanto