I MATERIAL
Air ton 0.158 20,000 3,160 0.16 3,160
Semen ton 0.609 936,360 570,243 0.61 570,243
Aggregate
Abu Batu ton 0.469 137,931 64,690 0.47 64,690
Aggregate 05/10 ton 0.483 155,000 74,865 0.48 74,865
Aggregate 10/20 ton 0.722 187,000 135,014 0.72 135,014
Additive Plastiment Kg - - - - -
Additive Sikament NN HE Ltr 7.800 10,500 81,900 7.80 81,900
MATERIAL 929,872 929,872
II ALAT
OC m3 1.000 10,120 10,120 1.00 10,120
Batching Plant jam 0.033 102,852 3,428
Loader jam 0.025 39,965 999
Genset 135 jam 0.040 18,753 750
Truck Mixer jam 0.147 33,606 4,942
RM m3 1.000 13,041 13,041 1.00 13,041
Batching Plant jam 0.033 140,685 4,690
Loader jam 0.025 47,455 1,186
Genset 135 jam 0.040 18,383 735
Truck Mixer jam 0.147 43,720 6,429
BBM m3 3.043 6,400 19,478 3.04 19,478
Batching Plant ltr - 6,400 -
Loader ltr 0.338 6,400 2,160
Genset 135 ltr 0.50 6,400 3,200
Truck Mixer ltr 2.206 6,400 14,118
ALAT 42,638 42,638
III UPAH
Upah m3 1.00 10,896 10,896 1.00 10,896
Operator BP jam 0.067 24,517 1,634
Operator Loader jam 0.025 24,517 613
Driver TM jam 0.147 18,737 2,755
Harian jam 0.167 11,786 1,964
Harian Lapangan jam 0.333 11,786 3,929
UPAH 10,896 10,896
IV BIAYA TIDAK LANGSUNG
Biaya Tidak langsung m3 - 15,000 - 1.00 15,000
BIAYA TIDAK LANGSUNG - 15,000
BIAYA BETON K 250 983,405 998,405
ANALISA HARGA SATUAN : PRODUKSI SHEET PILE (Proyek Sosok Tayan PONTIANAK)
CCSP TIPE W325 x 1000 L 15m (12 strand)
Produksi Di UPP Tambun
Volume Produksi : 7.000 Batang ( 105.000 m)
Tipe W325x 1000 L 10 m = 105,000 m' = 7,000 btg
Cetakan = 12.00 set 1 batang = 15.0 m'
Biaya Angkutan ke Site (Sub Angkutan) btg 1.000 7,000.00 185,000 12,333.33 185,000.00 1,295,000,000.00
BIAYA INVESTASI 4,800.00 72,000.00 504,000,000.00
BIAYA PRODUKSI 341,843.21 5,127,648.09 35,893,536,655.08
BIAYA ANGKUTAN 12,333.33 185,000.00 1,295,000,000.00
TOTAL BIAYA 358,976.54 5,384,648.09 37,692,536,655.08
PT. YASA PATRIA PERKASA
UNIT PRODUKSI PRECAST
I MATERIAL
Air ton 0.158 20,000 3,160 0.16 3,160
Semen ton 0.609 1,036,360 631,143 0.61 631,143
Aggregate
Pasir ton 0.469 128,205 60,128 0.47 60,128
Aggregate 05/10 ton 0.483 245,614 118,632 0.48 118,632
Aggregate 10/20 ton 0.722 245,614 177,333 0.72 177,333
Additive Plastiment Kg - - - - -
Additive Sikament NN HE Ltr 7.800 10,500 81,900 7.80 81,900
MATERIAL 1,072,296 1,072,296
II ALAT
OC m3 1.000 10,120 10,120 1.00 10,120
Batching Plant jam 0.033 102,852 3,428
Loader jam 0.025 39,965 999
Genset 135 jam 0.040 18,753 750
Truck Mixer jam 0.147 33,606 4,942
RM m3 1.000 13,041 13,041 1.00 13,041
Batching Plant jam 0.033 140,685 4,690
Loader jam 0.025 47,455 1,186
Genset 135 jam 0.040 18,383 735
Truck Mixer jam 0.147 43,720 6,429
BBM m3 3.043 6,400 19,478 3.04 19,478
Batching Plant ltr - 6,400 -
Loader ltr 0.338 6,400 2,160
Genset 135 ltr 0.50 6,400 3,200
Truck Mixer ltr 2.206 6,400 14,118
ALAT 42,638 42,638
III UPAH
Upah m3 1.00 10,896 10,896 1.00 10,896
Operator BP jam 0.067 24,517 1,634
Operator Loader jam 0.025 24,517 613
Driver TM jam 0.147 18,737 2,755
Harian jam 0.167 11,786 1,964
Harian Lapangan jam 0.333 11,786 3,929
UPAH 10,896 10,896
IV BIAYA TIDAK LANGSUNG
Biaya Tidak langsung m3 - 15,000 - 1.00 15,000
BIAYA TIDAK LANGSUNG - 15,000
BIAYA BETON K 250 1,125,830 1,140,830
ANALISA HARGA SATUAN : PRODUKSI SHEET PILE (Proyek Sosok Tayan PONTIANAK)
CCSP TIPE W325 x 1000 L 15m (12 strand)
Produksi Di Site ( Pontianak )
Volume Produksi : 7.000 Batang ( 105.000 m)
Tipe W325x 1000 L 10 m = 105,000 m' = 7,000 btg
Cetakan = 12.00 set 1 batang = 15.0 m'
Biaya Angkutan ke Site (Sub Angkutan) btg 1.000 7,000.00 185,000 12,333.33 185,000.00 1,295,000,000.00
BIAYA INVESTASI 4,800.00 72,000.00 504,000,000.00
BIAYA PRODUKSI 361,319.74 5,419,796.06 37,938,572,431.76
BIAYA ANGKUTAN 12,333.33 185,000.00 1,295,000,000.00
TOTAL BIAYA 378,453.07 5,676,796.06 39,737,572,431.76
UNIT PRODUKSI
PRECAST
1 PRODUKSI DI UP PRECAST
Biaya Formwork
a. Biaya Bongkar FW Tiang Pancang Ls 1 16,320,000 16,320,000 155.43
(8 Bed x 2 hari x 6 org)
b. Biaya Pasang FW Sheetpile CCSP Ls 1 20,400,000 20,400,000 194.29
(10 Bed x 2 hari x 6 orang)
c. Biaya Bongkar pasang side-beam modifikasi Ls 1 8,160,000 8,160,000 77.71
(8 Sb x 1 hari x 6 orang)
d. Biaya pasang side-beam baru (inner) Ls 1 10,200,000 10,200,000 97.14
(2 bed x 5 hari x 6 orang)
e. Biaya mobilisasi Side beam Ls 1 1,020,000 1,020,000 9.71
(2 bed x 1 hari x 6 orang)
f. Biaya pembuatan side-beam modifikasi Mtr 168 679,583 114,170,000 1,087.33
L = 9 Mtr x 16 Btg = 144 mtr
L = 6 Mtr x 4 Btg = 24 mtr
g. Biaya bongkar pasang abutment Titik 20 250,000 5,000,000 47.62