SUMARY RAB CV.

ADI MULTI GLOBAL

Project : Penimbunan Lokasi Pembangunan Smelter


Lokasi : Desa Molores, Kec . Petasia Timur, Kab. Morowali Utara, Provinsi Sulteng

Daftar kebutuhan sewa kendaraan dan alat berat, Genset, Perlengkapan tambahan pada
kendaraan operasional :
1.Excavator PC 200 = 4 Unit
2.Excavator PC 300 = 2 Unit
3.Dozer D 6 Cat = 1 Unit
4.Greder =1 Unit (Road maintenance)
5.Dump Truck 10 Roda = 24 Unit (2 unit Cadangan)
6.Dump Truck 6 Roda =1 Unit
7.Hilux Doble cabin = 2 Unit
8.Genset 45 kwa = 1 Unit
9.Tandon 5000 liter =2 buah
10.Pompa air (Alcon) set =1 buah

Daftar harga sewa kendaraan dan alat berat, Genset, Perlengkapan tambahan pada
kendaraan operasional :
1.Excavator PC 200 = Rp 300.000/jam
2.Excavator PC 300 = Rp 425.000/jam
3.Dozer D 6 Cat = Rp 400.000/jam
4.Greder =Rp 400.000/jam
5.Dump Truck 10 Roda = Rp 54.000.000/bln
6.Dump Truck 6 Roda = Rp 15.000.000/bln
7.Hilux Doble cabin = Rp 20.000.000/bln
8.Genset 45 kwa = Rp 25.000.000/bln
9.Tandon 5000 liter 2 buah =Rp 6.000.000
10. Pompa air (Alcon) set = Rp 2.000.000
Estimasi biaya sewa kendaraan dan alat berat, Genset, peralatan tambahan pada kendaraan
operasional.
1.Excavator PC 200 = 4 Unit x 16 jam x Rp 300.000 x 25 hari = Rp 480.000.000
2.Excavator PC 300 = 2 Unit x 16 jam xRp 450.000 x 25 hari =Rp 360.000.000
3.Dozer D 6 Cat = 1 Unit x 16 jam x Rp 400.000 x 25 hari = Rp 320.000.000
4.Greder = 1 Unit x 16 jam x Rp 400.000 x 25 hari = Rp 320.000.000
5.Dump Truck 10 Roda = 24 Unit (2 unit Cadangan) x Rp 54.000.000/bln =Rp 1.296.000.000

6.Dump Truck 6 Roda = 1 Unit x Rp 15.000.000/bln =Rp 15.000.000


7.Hilux Doble cabin = 2 Unit x Rp 20.000.000/bln = Rp 40.000.000
8.Genset 45 kwa = 1 Unit Rp 25.000.000/bln =Rp 25.000.000
9. Tandon 5000 liter 2 buah =Rp 6.000.000
10. Pompa air(Alcon) set = Rp 2.000.000

Total estimasi biaya sewa kendaraan dan alat berat = Rp 2.544.000.000

Kebutuhan man power


1. Operator = 62 org
2. Helper = 6 org
3. Sequrity = 6 0rg
4. ADM = 3 org
5. Cleaning service = 2 org

Estimasi biaya upah man power


1. Operator = 62 org x (Rp 6.000.000) = Rp 372.000.000
2. Helper = 6 org x (Rp 4.000.000) = Rp 24.000.000
3. Sequrity = 6 0rg x (Rp 5.000.000) = Rp 30.000.000
4. ADM = 3 org x (Rp 4.500.000) = Rp 13.500.000
5. Cleaning service = 2 org x (Rp 3.000.000) = Rp 6.000.000

Total estimasi biaya upah main power = Rp 445.500.000


Estimasi Kebutuhan pemakaian BBM
1.Excavator PC 200 = 16 liter/ jam
2.Excavator PC 300 = 28 liter/ jam
3.Dozer D 6 Cat (1 Unit) = 30 liter/ jam/Unit x 2 Unit =60 liter/ jam
4.Greder (1 Unit) = 30 liter/ jam/Unit x 2 Unit =60 liter/ jam
5.Dump Truck 10 Roda (1 liter 2 km) = 7 liter x24 ret (16 jam) x 22 Unit x 25 hr = 92.400 liter/hr
6.Dump Truck 6 Roda = (1,5 liter/jam) x 16 jam = 24 liter/hr

Estimasi biaya pemakaian BBM


1.Excavator PC 200 = 16 ltr x 16 jam x 25 hr x 4 unit = Rp 230.400.000
2.Excavator PC 300 = 28 ltr x 16 jam x 25 hr x 2 unit = Rp 201.600.000
3.Dozer D 6 Cat = 60 ltr (1 Unit) x 16 jam x 25 hr = Rp 216.000.000
3.Greder = 60 ltr (1 Unit) x 16 jam x 25 hr = Rp 216.000.000
4.Dump Truck 10 Roda = (14 km : 2 = 7 ltr) x 24 ret x 22 unit x 25 hr = Rp 831.600.000
5. Hilux Doble cabin = 2 x 15 ltr x 25 hr x Rp 9.000 = Rp 6.750.000
6. Genset = 1 x 30 ltrx 25 hr x Rp 9.000 = Rp 6.750.000
Total estimasi jumlah pemakaian BBM (solar Rp 9.000/liter) Perhitungan 25 hari kerja,
(2 shift) = Rp 1.493.000.000

Estimasi biaya catering


80 org x (3x mkn) x Rp60.000/hr x 30 hari = Rp 144.000.000

Total jumlah pengeluaran


1. Biaya sewa kendaraan dan alat berat , dll = Rp 2.544.000.000
2. Biaya BBM = Rp 1.493.000.000
3. Biaya upah = Rp 445.500.000
4. Biaya catering = Rp 144.000.000
5. Over head dll 10 % = Rp 500.000.000
Jumlah total = Rp 5.126.500.000

Note :
Pemasukan M3/bulan = 22 unit x 24 ret x 15m3/ret x 25 hr = 198.000 m3/bln
Tagihan bersih = 198.000 m3 x Rp 40.000 (Harga Subcont) = Rp 7.920.000.000
-------JUMLAH PENGAHSILAN – JUMLAH PENGELUARAN = KEUNTUNGAN BERSIH
------------------------ Rp 7.92.000.000 - Rp 5.126.500.000 = Rp 2.794.500.000