DATA PROYEK ;
PEMBERI TUGAS : PT. ARJUNA BAME KARYA UTAMA
LOKASI PENERIMAAN MATERIAL : PROYEK PLTU-3, DESA PENGARENGAN, KAB. CIREBON
JENIS MATERIAL YANG DIBUTUHKAN : TANAH MERAH
TOTAL VOLUME PEKERJAAN (ASUMSI) : 500,000.00 M3 (CURAH)
HARGA PENJUALAN : Rp. 60,000.00 /M3
TOTAL NILAI PEKERJAAN : Rp. 30,000,000,000.00
TAHAPAN PEMBAYARAN PER INVOICE : PER 25,000.00 M3/INVOICE = 20 X INVOICE
NILAI PEKERJAAN PER INVOICE/PO : Rp. 1,500,000,000.00
JAMINAN SUPPLY (JAMINAN PELAKSANAAN) : Rp. 500,000,000.00
JAMINAN PEMBAYARAN : GIRO BILYET / BANK BCA KCU-CIREBON
NILAI JAMINAN PEMBAYARAN PER PO : Rp. 2,000,000,000.00
WAKTU PELAKSANAAN PER INVOICE/PO : 5.0 HARI KERJA TARGET FINISH : 100 HARI KERJA
JAM KERJA PROYEK/HARI : 12 JAM/HARI (07.00 s/d 16.00 + 19.00 s/d 22.00)
LOKASI PEMBELIAN MATERIAL (QUARRY) : DESA HALIMPU, KEC. BEBER, KAB. CIREBON
JARAK ANGKUT MATERIAL : 28.8 Km = 57.6 Km (PP)
JENIS ARMADA YANG DIGUNAKAN : DT TRONTON INDEKS : 24 M3
ANALISA PRODUKSI ;
A. TARGET SUPPLY : 5,000.00 M3/HARI
B. RATA-RATA KECEPATAN ARMADA : 31.0 KM/JAM
C. WAKTU SIKLUS ;
1 WAKTU LOADING (MUAT) : 0.39 JAM/RIT
2 WAKTU ANGKUTAN : 1.86 JAM/RIT
3 WAKTU UKUR & ANTRIAN : 0.17 JAM/RIT
4 WAKTU LEPAS (BUANG) : 0.08 JAM/RIT
WAKTU SIKLUS : 2.49 JAM/RIT
D. TARGET PRODUKSI DTT PER HARI/UNIT : 5.0 RIT/HARI/UNIT = 120 M3/HARI/UNIT
E. JUMLAH ALAT YANG DIBUTUHKAN ;
1 JUMLAH ARMADA : 42 UNIT DT TRONTON (INDEKS : 24 M3)
2 JUMLAH EXCAVATOR : 4 UNIT EXC PC-200 (BUCKET : 0.8 M3)
ANALISA BIAYA ;
A. BIAYA PERSIAPAN ;
1 BIAYA KONTRAK (NOTARIS) : Rp. 15,000,000.00
2 SEWA KANTOR DAN POOL ARMADA : Rp. 10,500,000.00
3 MEJA/KURSI, KOMPUTER, ATK, DLL. : Rp. 45,000,000.00
4 BIAYA MOB/DEMOB ARMADA : Rp. 54,000,000.00
JUMLAH : Rp. 124,500,000.00 = Rp. 249.00 /M3
MODAL KERJA ;
A JAMINAN SUPPLY (PELAKSANAAN) : Rp. 500,000,000.00
B BIAYA PELAKSANAAN ;
1 BIAYA PERSIAPAN : Rp. 124,500,000.00
2 BIAYA VARIABLE ;
a. Pembelian Material + Biaya Loading : Rp. 550,000,000.00
b. Ongkos Angkut Material : Rp. 569,690,476.19
3 BIAYA TETAP : Rp. 43,750,000.00
4 BIAYA OVERHEAD : Rp. 75,000,000.00
JUMLAH BIAYA PELAKSANAAN : Rp. 1,362,940,476.19
C PROFITABILITAS PROYEK ; :
CASH FLOW
PEKERJAAN PENGADAAN TANAH MERAH
PROYEK PLTU - 3 CIREBON
LOKASI
SITE
LOKASI
QUARRY
B. RUTE JALAN YANG DILALUI ARMADA (DTT) ; KELAS JALAN JARAK TEMPUH
1. DARI LOKASI QUARRY KE JALAN RAYA BEBER (CIREBON/KUNINGAN) JALAN QUARRY 0.50 Km.
2. DARI PINTU KELUAR/MASUK QUARRY KE GERBANG TOL CIPERNA JALAN PROVINSI 10.30 Km.
3. DARI GERBANG TOL CIPERNA KE GERBANG TOL KANCI (JALAN TOL) JALAN TOL 11.80 Km.
4. DARI GERBANG TOL KANCI KE PINTU KELUAR/MASUK PROYEK PLTU 3 JALAN NASIONAL 3.80 Km.
5. DARI PINTU KELUAR/MASUK PROYEK KE SITE PLTU-3 JALAN PROYEK 2.40 Km.
TOTAL = 28.80 Km. = 57.60 Km (PP)
C. RATA-RATA KECEPATAN ARMADA (DTT INDEKS 24 M3) ; KOSONG BERMUATAN RATA-RATA
1. DARI LOKASI QUARRY KE JALAN RAYA BEBER (CIREBON/KUNINGAN) 10.00 Km/Jam. 5 Km/Jam. 7.50 Km/Jam.
2. DARI PINTU KELUAR/MASUK QUARRY KE GERBANG TOL CIPERNA 50.00 Km/Jam. 40 Km/Jam. 45.00 Km/Jam.
3. DARI GERBANG TOL CIPERNA KE GERBANG TOL KANCI (JALAN TOL) 70.00 Km/Jam. 55 Km/Jam. 62.50 Km/Jam.
4. DARI GERBANG TOL KANCI KE PINTU KELUAR/MASUK PROYEK PLTU 3 60.00 Km/Jam. 50 Km/Jam. 55.00 Km/Jam.
5. DARI PINTU KELUAR/MASUK PROYEK PLTU 3 KE SITE PLTU-3 10.00 Km/Jam. 5 Km/Jam. 7.50 Km/Jam.
D. RATA-RATA WAKTU TEMPUH (MOVING DISTANCE AVERAGE) ; KOSONG BERMUATAN JUMLAH (PP)
1. DARI LOKASI QUARRY KE JALAN RAYA BEBER (CIREBON/KUNINGAN) 0.05 Jam 0.10 Jam 0.15 Jam/Rit
2. DARI PINTU KELUAR/MASUK QUARRY KE GERBANG TOL CIPERNA 0.21 Jam 0.26 Jam 0.46 Jam/Rit
3. DARI GERBANG TOL CIPERNA KE GERBANG TOL KANCI (JALAN TOL) 0.17 Jam 0.21 Jam 0.38 Jam/Rit
4. DARI GERBANG TOL KANCI KE PINTU KELUAR/MASUK PROYEK PLTU 3 0.06 Jam 0.08 Jam 0.14 Jam/Rit
5. DARI PINTU KELUAR/MASUK PROYEK PLTU 3 KE SITE PLTU-3 0.24 Jam 0.48 Jam 0.72 Jam/Rit
Jumlah = 0.73 Jam 1.13 Jam 1.86 Jam/Rit
A. ASUMSI ;
VOLUME PEKERJAAN : 25,000.0 M3 / INVOICE TARGET SUPPLY = 5,000.00 M3/HARI
WAKTU PELAKSANAAN : 5.00 HARI
t b
d
+ 30 - 10
- 15
P PANJANG (BAGIAN DALAM) 605 Cm 605 605 605 605 6.05 M'
L LEBAR (BAGIAN DALAM) 235 Cm 235 235 235 235 2.35 M'
T TINGGI (BAGIAN DALAM) 170 Cm 155 200 160 172 1.72 M'
VOLUME INDEKS = 24.17 M3 VOLUME MUATAN = 24.41 M3
ANALISA PEMBIAYAAN
PENGADAAN DUMP TRUCK TRONTON PER UNIT
B SKEMA PEMBIAYAAN ;
TENOR TIME (JANGKA WAKTU PEMBIAYAAN) : 60 BULAN
DOWN PAYMENT 0.00% : Rp. - /UNIT
BIAYA ADMINISTRASI & PROVISI (1.00%) : Rp. 9,250,000.00 /UNIT
JUMLAH : Rp. 9,250,000.00 /UNIT
C RINCIAN PEMBIAYAAN ;
JUMLAH POKOK PEMBIAYAAN : Rp. 925,000,000.00
JASA BANK (18.7% / TAHUN) X TENOR TIME (THN) : Rp. 864,875,000.00
TOTAL PEMBIAYAAN : Rp. 1,789,875,000.00 /UNIT
RESUME
1 RENCANA PEMBELIAN ARMADA : 42 UNIT
2 HARGA ARMADA PER UNIT (LENGKAP) : Rp. 925,000,000.00 /UNIT
3 MODAL INVESTASI ;
- TOTAL ANGGARAN BIAYA PEMBELIAN ARMADA : Rp. 38,850,000,000.00
- TOTAL BIAYA OPERASIONAL ARMADA / BULAN : Rp. 1,263,494,400.00
- BIAYA CADANGAN PENGGANTIAN SPARE PART : Rp. 500,000,000.00
JUMLAH MODAL DIBUTUHKAN : Rp. 40,613,494,400.00
BIAYA ADM & PROVISI (1.00%) : Rp. 388,500,000.00
TOTAL MODAL INVESTASI : Rp. 41,001,994,400.00