PROJECT SUMMARY

PEKERJAAN PENGADAAN MATERIAL ALAM


UNTUK PROYEK PLTU-3 CIREBON

DATA PROYEK ;
PEMBERI TUGAS : PT. ARJUNA BAME KARYA UTAMA
LOKASI PENERIMAAN MATERIAL : PROYEK PLTU-3, DESA PENGARENGAN, KAB. CIREBON
JENIS MATERIAL YANG DIBUTUHKAN : TANAH MERAH
TOTAL VOLUME PEKERJAAN (ASUMSI) : 500,000.00 M3 (CURAH)
HARGA PENJUALAN : Rp. 60,000.00 /M3
TOTAL NILAI PEKERJAAN : Rp. 30,000,000,000.00
TAHAPAN PEMBAYARAN PER INVOICE : PER 25,000.00 M3/INVOICE = 20 X INVOICE
NILAI PEKERJAAN PER INVOICE/PO : Rp. 1,500,000,000.00
JAMINAN SUPPLY (JAMINAN PELAKSANAAN) : Rp. 500,000,000.00
JAMINAN PEMBAYARAN : GIRO BILYET / BANK BCA KCU-CIREBON
NILAI JAMINAN PEMBAYARAN PER PO : Rp. 2,000,000,000.00
WAKTU PELAKSANAAN PER INVOICE/PO : 5.0 HARI KERJA TARGET FINISH : 100 HARI KERJA
JAM KERJA PROYEK/HARI : 12 JAM/HARI (07.00 s/d 16.00 + 19.00 s/d 22.00)
LOKASI PEMBELIAN MATERIAL (QUARRY) : DESA HALIMPU, KEC. BEBER, KAB. CIREBON
JARAK ANGKUT MATERIAL : 28.8 Km = 57.6 Km (PP)
JENIS ARMADA YANG DIGUNAKAN : DT TRONTON INDEKS : 24 M3

ANALISA PRODUKSI ;
A. TARGET SUPPLY : 5,000.00 M3/HARI
B. RATA-RATA KECEPATAN ARMADA : 31.0 KM/JAM
C. WAKTU SIKLUS ;
1 WAKTU LOADING (MUAT) : 0.39 JAM/RIT
2 WAKTU ANGKUTAN : 1.86 JAM/RIT
3 WAKTU UKUR & ANTRIAN : 0.17 JAM/RIT
4 WAKTU LEPAS (BUANG) : 0.08 JAM/RIT
WAKTU SIKLUS : 2.49 JAM/RIT
D. TARGET PRODUKSI DTT PER HARI/UNIT : 5.0 RIT/HARI/UNIT = 120 M3/HARI/UNIT
E. JUMLAH ALAT YANG DIBUTUHKAN ;
1 JUMLAH ARMADA : 42 UNIT DT TRONTON (INDEKS : 24 M3)
2 JUMLAH EXCAVATOR : 4 UNIT EXC PC-200 (BUCKET : 0.8 M3)

ANALISA BIAYA ;
A. BIAYA PERSIAPAN ;
1 BIAYA KONTRAK (NOTARIS) : Rp. 15,000,000.00
2 SEWA KANTOR DAN POOL ARMADA : Rp. 10,500,000.00
3 MEJA/KURSI, KOMPUTER, ATK, DLL. : Rp. 45,000,000.00
4 BIAYA MOB/DEMOB ARMADA : Rp. 54,000,000.00
JUMLAH : Rp. 124,500,000.00 = Rp. 249.00 /M3

B. BIAYA VARIABLE (PER RIT);


PEMBELIAN MATERIAL (+ LOADING) : Rp. 528,000.00 = Rp. 22,000.00 /M3
ONGKOS ANGKUTAN ;
1 SEWA ARMADA : Rp. 257,142.86
2 CONSUMABLE BBM SOLAR : Rp. 149,760.00
3 BIAYA TOL + PENGATUR JALAN MASUK SITE : Rp. 50,000.00
4 UPAH SOPIR (DRIVER) + KERNET : Rp. 90,000.00
JUMLAH : Rp. 546,902.86 = Rp. 22,787.62 /M3

C. BIAYA TETAP (PER MINGGU/PO) ;


1 UPAH PEKERJA (9 ORANG) : Rp. 27,000,000.00
2 BIAYA LISTRIK, LEDENG, DLL. : Rp. 1,050,000.00
3 BIAYA TRANSPORT & UM PEKERJA TETAP : Rp. 4,500,000.00
4 KENDARAAN OPERASIONAL + BBM (4 UNIT) : Rp. 11,200,000.00
JUMLAH : Rp. 43,750,000.00 = Rp. 1,750.00 /M3

D. BIAYA OVERHEAD (PER PO) ;


1 JASA FASILITATOR & MEDIATOR : Rp. 1,000,000,000.00
2 BIAYA KOORDINASI & KEAMANAN : Rp. 500,000,000.00
JUMLAH : Rp. 1,500,000,000.00 = Rp. 3,000.00 /M3
JML. BIAYA PELAKSANAAN = Rp. 49,786.62 /M3
HARGA PENERIMAAN = Rp. 60,000.00 /M3
SALDO ( - ) = Rp. 10,213.38 /M3
SYARAT-SYARAT KONTRAK & PENGAJUAN PO ;
1 Mengadakan Ikatan Perjanjian Kerja / Kontrak dengan Pemberi Tugas, (Notarial).
2 Menyetorkan Jaminan Supply (Rp. 1.000,00/M3 X Volume Kontrak).
3 Menunjukan Bukti Pembayaran Deposit Tanah (Minimal = Volume Invoice).
4 Menyampaikan Daftar Armada DTT Indeks 24 M3 (Minimal 40 Unit) & Nama Drivernya, dilampiri Copy STNK & SIM.
5 Menyampaikan Daftar Personil yang ditugaskan di lapangan.

MODAL KERJA ;
A JAMINAN SUPPLY (PELAKSANAAN) : Rp. 500,000,000.00

B BIAYA PELAKSANAAN ;
1 BIAYA PERSIAPAN : Rp. 124,500,000.00
2 BIAYA VARIABLE ;
a. Pembelian Material + Biaya Loading : Rp. 550,000,000.00
b. Ongkos Angkut Material : Rp. 569,690,476.19
3 BIAYA TETAP : Rp. 43,750,000.00
4 BIAYA OVERHEAD : Rp. 75,000,000.00
JUMLAH BIAYA PELAKSANAAN : Rp. 1,362,940,476.19

5 MODAL CADANGAN (3 HARI KERJA) : Rp. 746,799,285.71 (Waktu Proses Pencairan)

MODAL KERJA MINIMUM : Rp. 2,609,739,761.90

C PROFITABILITAS PROYEK ; :

I 1 PENERIMAAN PER INVOICE : Rp. 1,500,000,000.00


2 PENGELUARAN PER PO (/MINGGU) : Rp. 1,362,940,476.19
SALDO ( - ) INVOICE - I : Rp. 137,059,523.81 = 5% / MINGGU

II 1 PENERIMAAN PER INVOICE : Rp. 1,500,000,000.00


2 PENGELUARAN PER PO (/MINGGU) : Rp. 1,238,440,476.19
SALDO ( - ) INVOICE - II : Rp. 261,559,523.81 = 17% / MINGGU

III 1 PENERIMAAN PER INVOICE : Rp. 1,500,000,000.00


2 PENGELUARAN PER PO (/MINGGU) : Rp. 1,238,440,476.19
SALDO ( - ) INVOICE - III : Rp. 261,559,523.81 = 17% / MINGGU

IV 1 PENERIMAAN PER INVOICE : Rp. 1,500,000,000.00


2 PENGELUARAN PER PO (/MINGGU) : Rp. 1,238,440,476.19
SALDO ( - ) INVOICE - IV : Rp. 261,559,523.81 = 17% / MINGGU

V 1 PENERIMAAN PER INVOICE : Rp. 1,500,000,000.00


2 PENGELUARAN PER PO (/MINGGU) : Rp. 1,238,440,476.19
SALDO ( - ) INVOICE - V : Rp. 261,559,523.81 = 17% / MINGGU

TOTAL PROFIT : Rp. 1,183,297,619.05 = 45% / BULAN

Cash Flow terlampir

Indramayu, 11 Januari 2018


PT. MUTIARA DAYA GUMIWANG

Ir. HARRIS SOLIHIN


Direktur Utama
LAMPIRAN

DAFTAR HARGA SATUAN BAHAN/UPAH/SEWA ALAT;

1 Harga Material/Tanah Merah di Quarry : Rp. 22,000.00 /M3 (Diatas Truck)


2 Sewa DT Tronton (Indeks 24 M3) : Rp. 36,000,000.00 /Unit/Bulan (28 Hari)
3 Harga BBM Solar untuk Angkutan Umum : Rp. 5,200.00 /Liter
4 UM & Upah Kerja Sopir & Kernet DTT : Rp. 450,000.00 /Hari/Unit
5 Mob/Demob Armada : Rp. 1,285,714.29 /Unit
6 Sewa Kantor/Mess & Pool Armada : Rp. 2,100,000.00 /Hari
7 Biaya Listrik/Ledeng Mess : Rp. 210,000.00 /Hari
8 Upah Pekerja Tetap : Rp. 3,000,000.00 /Orang/PO
9 Biaya Transport & UM Pekerja Tetap : Rp. 100,000.00 /Orang/Hari
10 Tiket Jalan Tol Ciperna - Kanci untuk DTT : Rp. 20,000.00 (Tiap Masuk Tol)

PT. MUTIARA DAYA GUMIWANG


CONTRACTOR - SUPPLIER - GENERAL TRADER

CASH FLOW
PEKERJAAN PENGADAAN TANAH MERAH
PROYEK PLTU - 3 CIREBON

Anggaran Biaya Biaya dan Waktu Pelaksanaan (5 Hari/Invoice) Sub Jumlah


No Uraian
(Rp) Invoice-I Invoice-II Invoice-III Invoice-IV Invoice-V (Rp)
(a) (b) (c) (d) (e) (f) (g) (h) (i)
A JAMINAN PELAKSANAAN / PO 500,000,000.00 500,000,000.00 500,000,000.00 500,000,000.00 500,000,000.00 500,000,000.00 500,000,000.00
B BIAYA PELAKSANAAN / PO ;
1 Biaya Persiapan 124,500,000.00 124,500,000.00 - - - - 124,500,000.00
2 Biaya Variable 1,119,690,476.19 1,119,690,476.19 1,119,690,476.19 1,119,690,476.19 1,119,690,476.19 1,119,690,476.19 5,598,452,380.95
3 Biaya Tetap 43,750,000.00 43,750,000.00 43,750,000.00 43,750,000.00 43,750,000.00 43,750,000.00 218,750,000.00
4 Biaya Overhead 75,000,000.00 75,000,000.00 75,000,000.00 75,000,000.00 75,000,000.00 75,000,000.00 375,000,000.00
Jml. Biaya Pelaksanaan / PO 1,362,940,476.19 1,362,940,476.19 1,238,440,476.19 1,238,440,476.19 1,238,440,476.19 1,238,440,476.19 6,316,702,380.95
C JUMLAH PENGELUARAN 1,862,940,476.19 1,862,940,476.19 1,738,440,476.19 1,738,440,476.19 1,738,440,476.19 1,738,440,476.19 8,816,702,380.95
D JUMLAH PENERIMAAN - 1,500,000,000.00 1,500,000,000.00 1,500,000,000.00 1,500,000,000.00 1,500,000,000.00 7,500,000,000.00
SALDO ( - ) - 137,059,523.81 261,559,523.81 261,559,523.81 261,559,523.81 261,559,523.81 1,183,297,619.05

Sub Jumlah Biaya dan Waktu Pelaksanaan (5 Hari/Invoice) Sub Jumlah


No Uraian
(Rp) Invoice-VI Invoice-VII Invoice-VIII Invoice-IX Invoice-X (Rp)
(a) (b) (c) (d) (e) (f) (g) (h) (i)
A JAMINAN PELAKSANAAN / PO 500,000,000.00 500,000,000.00 500,000,000.00 500,000,000.00 500,000,000.00 500,000,000.00 500,000,000.00
B BIAYA PELAKSANAAN / PO ;
1 Biaya Persiapan 124,500,000.00 - - - - - 124,500,000.00
2 Biaya Variable 5,598,452,380.95 1,119,690,476.19 1,119,690,476.19 1,119,690,476.19 1,119,690,476.19 1,119,690,476.19 11,196,904,761.90
3 Biaya Tetap 218,750,000.00 43,750,000.00 43,750,000.00 43,750,000.00 43,750,000.00 43,750,000.00 437,500,000.00
4 Biaya Overhead 375,000,000.00 75,000,000.00 75,000,000.00 75,000,000.00 75,000,000.00 75,000,000.00 750,000,000.00
Jml. Biaya Pelaksanaan / PO 6,316,702,380.95 1,238,440,476.19 1,238,440,476.19 1,238,440,476.19 1,238,440,476.19 1,238,440,476.19 12,508,904,761.90
C JUMLAH PENGELUARAN 8,816,702,380.95 1,738,440,476.19 1,738,440,476.19 1,738,440,476.19 1,738,440,476.19 1,738,440,476.19 17,508,904,761.90
D JUMLAH PENERIMAAN 7,500,000,000.00 1,500,000,000.00 1,500,000,000.00 1,500,000,000.00 1,500,000,000.00 1,500,000,000.00 15,000,000,000.00
SALDO ( - ) 1,183,297,619.05 261,559,523.81 261,559,523.81 261,559,523.81 261,559,523.81 261,559,523.81 2,491,095,238.10
Sub Jumlah Biaya dan Waktu Pelaksanaan (5 Hari/Invoice) Sub Jumlah
No Uraian
(Rp) Invoice-XI Invoice-XII Invoice-XIII Invoice-XIV Invoice-XV (Rp)
(a) (b) (c) (d) (e) (f) (g) (h) (i)
A JAMINAN PELAKSANAAN / PO 500,000,000.00 500,000,000.00 500,000,000.00 500,000,000.00 500,000,000.00 500,000,000.00 500,000,000.00
B BIAYA PELAKSANAAN / PO ;
1 Biaya Persiapan 124,500,000.00 - - - - - 124,500,000.00
2 Biaya Variable 11,196,904,761.90 1,119,690,476.19 1,119,690,476.19 1,119,690,476.19 1,119,690,476.19 1,119,690,476.19 16,795,357,142.86
3 Biaya Tetap 437,500,000.00 43,750,000.00 43,750,000.00 43,750,000.00 43,750,000.00 43,750,000.00 656,250,000.00
4 Biaya Overhead 750,000,000.00 75,000,000.00 75,000,000.00 75,000,000.00 75,000,000.00 75,000,000.00 1,125,000,000.00
Jml. Biaya Pelaksanaan / PO 12,508,904,761.90 1,238,440,476.19 1,238,440,476.19 1,238,440,476.19 1,238,440,476.19 1,238,440,476.19 18,701,107,142.86
C JUMLAH PENGELUARAN 17,508,904,761.90 1,738,440,476.19 1,738,440,476.19 1,738,440,476.19 1,738,440,476.19 1,738,440,476.19 26,201,107,142.86
D JUMLAH PENERIMAAN 15,000,000,000.00 1,500,000,000.00 1,500,000,000.00 1,500,000,000.00 1,500,000,000.00 1,500,000,000.00 22,500,000,000.00
SALDO ( - ) 2,491,095,238.10 261,559,523.81 261,559,523.81 261,559,523.81 261,559,523.81 261,559,523.81 3,798,892,857.14

Sub Jumlah Biaya dan Waktu Pelaksanaan (5 Hari/Invoice) Sub Jumlah


No Uraian
(Rp) Invoice-XVI Invoice-XVII Invoice-XVIII Invoice-XIX Invoice-XX (Rp)
(a) (b) (c) (d) (e) (f) (g) (h) (i)
A JAMINAN PELAKSANAAN / PO 500,000,000.00 500,000,000.00 500,000,000.00 500,000,000.00 500,000,000.00 500,000,000.00 500,000,000.00
B BIAYA PELAKSANAAN / PO ;
1 Biaya Persiapan 124,500,000.00 - - - - - 124,500,000.00
2 Biaya Variable 16,795,357,142.86 1,119,690,476.19 1,119,690,476.19 1,119,690,476.19 1,119,690,476.19 1,119,690,476.19 22,393,809,523.81
3 Biaya Tetap 656,250,000.00 43,750,000.00 43,750,000.00 43,750,000.00 43,750,000.00 43,750,000.00 875,000,000.00
4 Biaya Overhead 1,125,000,000.00 75,000,000.00 75,000,000.00 75,000,000.00 75,000,000.00 75,000,000.00 1,500,000,000.00
Jml. Biaya Pelaksanaan / PO 18,701,107,142.86 1,238,440,476.19 1,238,440,476.19 1,238,440,476.19 1,238,440,476.19 1,238,440,476.19 24,893,309,523.81
C JUMLAH PENGELUARAN 26,201,107,142.86 1,738,440,476.19 1,738,440,476.19 1,738,440,476.19 1,738,440,476.19 1,738,440,476.19 34,893,309,523.81
D JUMLAH PENERIMAAN 22,500,000,000.00 1,500,000,000.00 1,500,000,000.00 1,500,000,000.00 1,500,000,000.00 1,500,000,000.00 30,000,000,000.00
SALDO ( - ) 3,798,892,857.14 261,559,523.81 261,559,523.81 261,559,523.81 261,559,523.81 261,559,523.81 5,106,690,476.19

Indramayu, 11 Januari 2018


PT. MUTIARA DAYA GUMIWANG

Ir. HARRIS SOLIHIN


Direktur Utama
ANALISA TEKNIS

WAKTU ANGKUTAN (MOVING TIME) ;

A. ROAD MAP & MOVING DISTANCE ;

LOKASI
SITE

LOKASI
QUARRY

B. RUTE JALAN YANG DILALUI ARMADA (DTT) ; KELAS JALAN JARAK TEMPUH
1. DARI LOKASI QUARRY KE JALAN RAYA BEBER (CIREBON/KUNINGAN) JALAN QUARRY 0.50 Km.
2. DARI PINTU KELUAR/MASUK QUARRY KE GERBANG TOL CIPERNA JALAN PROVINSI 10.30 Km.
3. DARI GERBANG TOL CIPERNA KE GERBANG TOL KANCI (JALAN TOL) JALAN TOL 11.80 Km.
4. DARI GERBANG TOL KANCI KE PINTU KELUAR/MASUK PROYEK PLTU 3 JALAN NASIONAL 3.80 Km.
5. DARI PINTU KELUAR/MASUK PROYEK KE SITE PLTU-3 JALAN PROYEK 2.40 Km.
TOTAL = 28.80 Km. = 57.60 Km (PP)
C. RATA-RATA KECEPATAN ARMADA (DTT INDEKS 24 M3) ; KOSONG BERMUATAN RATA-RATA
1. DARI LOKASI QUARRY KE JALAN RAYA BEBER (CIREBON/KUNINGAN) 10.00 Km/Jam. 5 Km/Jam. 7.50 Km/Jam.
2. DARI PINTU KELUAR/MASUK QUARRY KE GERBANG TOL CIPERNA 50.00 Km/Jam. 40 Km/Jam. 45.00 Km/Jam.
3. DARI GERBANG TOL CIPERNA KE GERBANG TOL KANCI (JALAN TOL) 70.00 Km/Jam. 55 Km/Jam. 62.50 Km/Jam.
4. DARI GERBANG TOL KANCI KE PINTU KELUAR/MASUK PROYEK PLTU 3 60.00 Km/Jam. 50 Km/Jam. 55.00 Km/Jam.
5. DARI PINTU KELUAR/MASUK PROYEK PLTU 3 KE SITE PLTU-3 10.00 Km/Jam. 5 Km/Jam. 7.50 Km/Jam.

D. RATA-RATA WAKTU TEMPUH (MOVING DISTANCE AVERAGE) ; KOSONG BERMUATAN JUMLAH (PP)
1. DARI LOKASI QUARRY KE JALAN RAYA BEBER (CIREBON/KUNINGAN) 0.05 Jam 0.10 Jam 0.15 Jam/Rit
2. DARI PINTU KELUAR/MASUK QUARRY KE GERBANG TOL CIPERNA 0.21 Jam 0.26 Jam 0.46 Jam/Rit
3. DARI GERBANG TOL CIPERNA KE GERBANG TOL KANCI (JALAN TOL) 0.17 Jam 0.21 Jam 0.38 Jam/Rit
4. DARI GERBANG TOL KANCI KE PINTU KELUAR/MASUK PROYEK PLTU 3 0.06 Jam 0.08 Jam 0.14 Jam/Rit
5. DARI PINTU KELUAR/MASUK PROYEK PLTU 3 KE SITE PLTU-3 0.24 Jam 0.48 Jam 0.72 Jam/Rit
Jumlah = 0.73 Jam 1.13 Jam 1.86 Jam/Rit

WAKTU MUAT (LOADING TIME) ;


A. ALAT YANG DIGUNAKAN : EXCAVATOR PC-200 BUCKET CAPACITY : 0.80 M3/LOADING
OPTIMAL : 0.95 M3/LOADING
B. PRODUKTIFITAS ALAT (ASUMSI : KONDISI ALAT BAIK, OPERATOR : BAIK) ;
1 WAKTU GALI 25 DETIK 0.42 MENIT
2 WAKTU PUTAR (90o) 20 DETIK 0.33 MENIT
3 WAKTU LEPAS 5 DETIK 0.08 MENIT
4 WAKTU TERBUANG 5 DETIK 0.08 MENIT
JUMLAH : 55 DETIK 0.92 MENIT/LOADING PRODUKTIFITAS : 65.45 KALI LOADING / JAM

WAKTU SIKLUS (CYCLE TIME) ;


A. KAPASITAS ARMADA YANG DIGUNAKAN 24.00 M3 WAKTU LOADING : 23.16 MENIT/RIT
B. PRODUKTIFITAS EXCAVATOR PC-200 62.18 M3/JAM

C. WAKTU SIKLUS (CYCLE TIME) ;


1. WAKTU MUAT (LOADING TIME) 0.39 Jam/Rit
2. WAKTU ANGKUTAN (MOVING TIME) 1.86 Jam/Rit
4. WAKTU UKUR & ANTRI (DELAY TIME) 0.17 Jam/Rit
3. WAKTU BUANG (DUMPING TIME) 0.08 Jam/Rit
2.49 Jam/Rit
TARGET PRODUKSI ;

A. JAM KERJA PROYEK ;


Regular 07.00 16.00 9.00 Jam
Overtime 19.00 22.00 3.00 Jam
JUMLAH = 12.00 Jam/Hari

B. TARGET PRODUKSI ANGKUTAN : 4.82 RIT/HARI = 5.00 RIT/HARI = 120.00 M3/HARI


C. TARGET PRODUKSI EXCAVATOR : 746.18 M3/HARI

ANALISA KEBUTUHAN ALAT ;

A. ASUMSI ;
VOLUME PEKERJAAN : 25,000.0 M3 / INVOICE TARGET SUPPLY = 5,000.00 M3/HARI
WAKTU PELAKSANAAN : 5.00 HARI

B. JUMLAH ALAT YANG DIBUTUHKAN ;


- DUMP TRUCK TRONTON : 41.67 UNIT = 42 UNIT DTT INDEKS 24 M3
- EXCAVATOR : 3.35 UNIT = 4 UNIT EXCAVATOR PC-200

Indramayu, 11 Januari 2018


PT. MUTIARA DAYA GUMIWANG

Ir. HARRIS SOLIHIN


Direktur Utama
INDEKS DUMP TRUCK TRONTON

UKURAN BAK DUMP TRUCK TRONTON ;


P PANJANG (BAGIAN DALAM) 605 Cm 6.05 M'
L LEBAR (BAGIAN DALAM) 235 Cm 2.35 M'
T TINGGI (BAGIAN DALAM) 170 Cm 1.70 M'
KAPASITAS BAK DTT = 24.17 M3
CONTOH CARA PENGUKURAN MUATAN MATERIAL ALAM

t b
d
+ 30 - 10
- 15

CARA PENGUKURAN MUATAN ;

UKURAN UKURAN MUATAN UKURAN UKURAN


URAIAN
INDEKS d (depan) t (tengah) b (blk) RATA-RATA MUATAN

P PANJANG (BAGIAN DALAM) 605 Cm 605 605 605 605 6.05 M'
L LEBAR (BAGIAN DALAM) 235 Cm 235 235 235 235 2.35 M'
T TINGGI (BAGIAN DALAM) 170 Cm 155 200 160 172 1.72 M'
VOLUME INDEKS = 24.17 M3 VOLUME MUATAN = 24.41 M3
ANALISA PEMBIAYAAN
PENGADAAN DUMP TRUCK TRONTON PER UNIT

A HARGA DTT MITSUBISHI FN 257 (6X4) ML : Rp. 925,000,000.00 (Lengkap)

B SKEMA PEMBIAYAAN ;
TENOR TIME (JANGKA WAKTU PEMBIAYAAN) : 60 BULAN
DOWN PAYMENT 0.00% : Rp. - /UNIT
BIAYA ADMINISTRASI & PROVISI (1.00%) : Rp. 9,250,000.00 /UNIT
JUMLAH : Rp. 9,250,000.00 /UNIT

C RINCIAN PEMBIAYAAN ;
JUMLAH POKOK PEMBIAYAAN : Rp. 925,000,000.00
JASA BANK (18.7% / TAHUN) X TENOR TIME (THN) : Rp. 864,875,000.00
TOTAL PEMBIAYAAN : Rp. 1,789,875,000.00 /UNIT

ANGSURAN PEMBIAYAAN : Rp. 29,831,250.00 /BLN/UNIT

D TARGET PRODUKSI ARMADA ;


1 JUMLAH HARI KERJA PER BULAN : 28 HARI/BULAN
2 KAPASITAS INDEKS BAK : 24 M3
3 TARGET PRODUKSI ARMADA : 5 RIT/HARI
PRODUKTIFITAS ARMADA = 120 M3/HARI/UNIT.
= 3,360 M3/BULAN/UNIT

E BIAYA OPERASIONAL ARMADA ;


1 CONSUMABLE BBM (4 Km/Ltr) : 4 Km/Liter
Jarak Angkut per Rit : 58 Km/Rit
Konsumable BBM Solar : 14 Ltr/Rit
: 72 Ltr/Hari/Unit
= 2,016 Ltr/Bulan/Unit

2 HARGA BBM SOLAR : Rp. 5,200.00 /Liter

3 JUMLAH BIAYA BBM SOLAR : Rp. 74,880.00 /Rit


: Rp. 374,400.00 /Hari
: Rp. 10,483,200.00 /Bln

4 UPAH SOPIR (+ KERNET) : Rp. 90,000.00 /Rit


: Rp. 450,000.00 /Hari
= Rp. 12,600,000.00 /Bln

5 BIAYA JALAN TOL + LL (Rp. 50.000/Rit) : Rp. 50,000.00 /Rit


= Rp. 250,000.00 /Hari
= Rp. 7,000,000.00 /Bln

TOTAL BIAYA OPERASIONAL ARMADA DTT = Rp. 214,880.00 /Rit


= Rp. 1,074,400.00 /Hari
= Rp. 30,083,200.00 /Bln
F PROVITABILITAS ANGKUTAN PER UNIT ;
1 HARGA ONGKOS ANGKUTAN : Rp. 21,000.00 /M3
2 TARGET PRODUKSI ARMADA : 3,360.00 M3/BLN
3 TOTAL PENERIMAAN ANGKUTAN : Rp. 70,560,000.00 /BLN
4 BIAYA OPERASIONAL ARMADA : Rp. 30,083,200.00 /BLN
BRUTTO PROFIT : Rp. 40,476,800.00 /BLN
5 ANGSURAN PEMBELIAN ARMADA : Rp. 29,831,250.00 /BLN
SALDO ( - ) : Rp. 10,645,550.00 /BLN

G DEPRESIASI ARMADA (12.00% PER TAHUN) ;


1 ALOKASI DANA DEPRESIASI PER UNIT/THN : Rp. 111,000,000.00 /TAHUN
2 SALDO PROFIT PER UNIT/TAHUN : Rp. 127,746,600.00 /UNIT/THN
3 NILAI EKONOMI ARMADA STLH TAHUN KE-5 : Rp. 370,000,000.00 /UNIT

RESUME
1 RENCANA PEMBELIAN ARMADA : 42 UNIT
2 HARGA ARMADA PER UNIT (LENGKAP) : Rp. 925,000,000.00 /UNIT
3 MODAL INVESTASI ;
- TOTAL ANGGARAN BIAYA PEMBELIAN ARMADA : Rp. 38,850,000,000.00
- TOTAL BIAYA OPERASIONAL ARMADA / BULAN : Rp. 1,263,494,400.00
- BIAYA CADANGAN PENGGANTIAN SPARE PART : Rp. 500,000,000.00
JUMLAH MODAL DIBUTUHKAN : Rp. 40,613,494,400.00
BIAYA ADM & PROVISI (1.00%) : Rp. 388,500,000.00
TOTAL MODAL INVESTASI : Rp. 41,001,994,400.00

Indramayu, 11 Januari 2018


PT. MUTIARA DAYA GUMIWANG

Ir. HARRIS SOLIHIN


Direktur Utama