DAFTAR HARGA BAHAN UPAH KERJA DAN SEWA ALAT

TAHUN 2019

NO JENIS BAHAN SATUAN


HARGA SATUAN KETERANGAN

.1. .2. .3. 4 5

A. BAHAN DASAR
1. Batu.
a. Kali M3. 198,000.00 -
b. Gunung/ Belah/ Karang M3. 241,500.00 -
c. Kerikil M3. 352,500.00 -
d. Batu koral M3. 324,000.00 -
e. Batu mangga M3. 312,000.00 -
f. Batu bolder M3.
g. Pecah : - 10 - 15 Cm. 216,000.00 -
- 5-7 Cm. M3. 264,000.00 -
- 3-5 Cm. M3. 324,000.00 -
- 2-3 Cm. M3. 384,000.00 -
- 1-2 Cm. (Split). M3. 360,000.00 -
- 0,5 - 1 Cm. (Chiping). M3.

h. Batu alam (hias-tempel) M2 249,000.00 -


i. Batu karang M3. 594,000.00 -
j. Batu agregat halus (fine agregat) M3. 432,000.00 -
j. Batu agregat kasar (coarse agregat) M3. 424,800.00 -

2. Pasir: - Timbunan/ Urug. M3. 84,300.00 -


- Pasang M3. 87,300.00 -
- Beton. M3. 105,000.00 -
- Plesteran/ Halus. M3. 130,500.00 -

3. Tanah. - Timbunan/ tanah urug biasa M3. 91,800.00 -


- Tanah urug pilihan M3. 109,500.00 -

4. Pasir Batu (Sirtu). M3. 143,250.00 -


5. Batu Olahan : - Bata/ Merah Buah 1,180.00 -
- Paving Block abu-abu 6x10,5x21 Buah 3,000.00 -
- Paving Block warna 6x10,5x21 Buah 3,480.00 -
- Paving Block ( K.400 ) + 8 Cm. M2. - -
- Paving Block ( K.350 ) + 8 Cm. M2. 126,000.00
- Roster Keramik 20 x 20 cm Buah 39,690.00 -
- Roster biasa 20 x 20 cm Buah 35,920.00 -
- Batako Buah 1,600.00 -
- Canstein Buah 77,400.00 -
- Hollow brick Buah 2,760.00 -
- Batu alam Buah 210,000.00
6. Semen (PC)
a. Tonasa : - 50 Kg. Sak 62,000.00
b. Bosowa : - 50 kg. Sak 60,000.00
c. Tiga Roda Sak 60,000.00
d. Semen Putih Kg. 5,000.00
e. Semen Warna Kg. 15,000.00
NO JENIS BAHAN SATUAN
HARGA SATUAN KETERANGAN

.1. .2. .3. 4 .5.


B. BAHAN KAYU
1. Kayu Kelas I (satu)
a. Balok gergaji M3. 12,500,000.00
b. Papan gergaji M3. 11,000,000.00

2. Kayu Kelas II (dua)


a. Balok. M3. 5,500,000.00
b. Papan. M3. 5,500,000.00
c. List Profil 2 x 3 cm. M'. 10,000.00

3. Kayu Kelas III (tiga)


a. Balok. M3. 3,500,000.00
b. Papan. M3. 3,500,000.00

C. BAHAN BAMBU
a. Besar Batang 24,000.00
b. Sedang Batang 15,600.00
c. Kecil Batang 9,600.00

D. BAHAN LANTAI
1. Tegel PC :
a. PC abu-abu 20 x 20 cm. Dos 73,950.00
b. PC abu-abu 30 x 30 cm. Dos 75,200.00
c. PC warna 20 x 20 cm. Dos 75,400.00
d. PC badak 30 x 30 cm. Dos 67,800.00
e. PC wafel 20 x 20 cm. Dos 78,000.00
f. PC wafel 30 x 30 cm. Dos 54,900.00

2. Tegel Keramik :
a. Putih 10 x 20 cm. Dos 70,000.00
b. Warna 10 x 20 cm. Dos 70,000.00
c. Putih 20 x 20 cm. Dos 70,000.00
d. Arwana 20 x 20 cm Dos 70,000.00
e. Antislip 20 x 20 cm Dos 70,000.00
f. Putih 20 x 25 cm Dos 70,000.00
g. Arwana 20 x 25 cm. Dos 70,000.00
h. Putih 30 x 30 cm. Dos 65,000.00
i. Arwana 30 x 30 cm. Dos 65,000.00
j. Antislip 30 x 30 cm Dos 90,000.00
k. Putih 40 x 40 cm. Dos 65,850.00
l. Arwana 40 x 40 cm. Dos 77,100.00
m. Antislip 40 x 40 cm Dos 90,300.00
n. Putih 60 x 60 cm. Dos 189,000.00
o. 50 x 50 cm. Dos 122,000.00
p. Tegel kuku / tegel bok Dos 108,000.00
r. Tegel plint polos 10 x 20 cm. Dos 72,000.00
s. Tegel plint bermotif 10 x 20 cm. Dos 74,400.00
t. Granito 60 x60 cm Dos 174,000.00
t. Granito 60 x60 cm permukaan kasar Dos 228,000.00
E. BAHAN KACA
1 Kaca Bening +. 3 mm. Meter 174,000.00
2 Kaca Bening +. 5 mm. Meter 189,000.00
3 Kaca Bening +. 8 mm. Meter 276,000.00
4 Kaca Bayang +. 2 mm.(1,2x0,5) m Potong 368,000.00
5 Kaca Bayang +. 3 mm.(1 x 0,5) m Potong 204,000.00
6 Kaca Ray band +. 3 mm. Meter 264,000.00
7 Kaca Ray band +. 5 mm. Meter 228,000.00
8 Kaca es kembang +.3 mm. Meter 300,000.00
9 Kaca es kembang + 5 mm. Meter
10 Rangka Nako (lengkap trali) Trap
11 Kaca Bayang Biasa Set
Kaca Bayang dgn Gambar Set
NO JENIS BAHAN SATUAN
HARGA SATUAN KETERANGAN

.1. .2. .3. 4 .5.


1 Bahan Besi
a. d. 4 mm. Kg. 14,570.00
b. d. 6 mm. Kg. 14,570.00
c. d. 8 mm. Kg. 14,570.00
d. d. 10 mm. Kg. 14,570.00
e. d. 12 mm. Kg. 14,570.00
f. d. 14 mm. Kg. 14,570.00
g. d. 16 mm. Kg. 14,570.00
h. d. 19 mm. Kg. 14,570.00
i. Harga per kilogram Kg. 14,570.00
2. Paku
a. Biasa 1/2" s/d 1" Kg. 18,000.00
b. Biasa 2" s/d 5" Kg. 20,000.00
c. Seng Kg. 32,000.00
d. Asbes/ Kait Kg. 36,000.00
e. Seng (besar) Kg. 39,000.00
f. Skrup buah 900.00
g. Beton Dos 26,000.00
h. Paku Gypsum Dos 80,000.00
i. Fisher Dinabold Dos 190,000.00
j. Skrup 3,5 " Dos 65,000.00
k. Spikot buah 600
l. Mur buah 600
Self drilling screw dia. 6 x 20 mm (truss screw) buah 600
Self drilling screw dia. 4 x 16 mm (roof bottom screw) buah 900
Dynabol dia. 12 x 120 mm buah 6,000
3. Kawat
a. Beton Kg. 24,000.00
b. Harmonika M2.
c. Nyamuk M2. 14,000.00
d. Ayakan kecil M2. 14,000.00
e. Duri besar 6 kg Roll 90,000.00
f. Duri besar 4 kg Roll 78,000.00
g. Las Kg. 40,800.00
4. Besi Plat
a. +. 2 mm = 120 x 240 cm. Lbr. 615,000.00
b. +. 3 mm = 120 x 240 cm. Lbr. 1,020,000.00
c. +. 10 mm = 120 x 240 cm. Lbr. 3,150,000.00

5. Besi Strip
a. 30 x 3 mm Btg. 105,000.00
b. 35 x 4 mm Btg.
c. 46 x 6 mm Btg.
d. 40 x 6 mm Btg.
e. Harga per kilogram Kg.
6. Besi Siku
a. 30.30.3 Btg. 121,000.00
b. 40.40.4 Btg. 91,500.00
c. 50.50.3 Btg. 291,400.00
d. 40.40.3 Btg. 126,000.00
e. 70.70.3 Btg. 629,000.00
f. Harga per kilogram Kg.
NO JENIS BAHAN SATUAN
HARGA SATUAN KETERANGAN

.1. .2. .3. 4 .5.


G. BAHAN PIPA
1. Pipa Besi galvanis
a. 1/2 " - 6 m. Btg. 106,800.00
b. 3/4 " - 6 m. Btg. 148,800.00
c. 1 " - 6 m. Btg. 203,600.00
d. 1,5 " - 6 m. Btg. 320,000.00
e. 2 " - 6 m Btg. 186,000.00
f. 2,5 " - 6 m Btg. 246,000.00
g. 3 " - 6 m Btg. 298,000.00
h. 4 " - 6 m Btg. 327,000.00
i. 6 " - 6 m. Btg. 540,000.00
Kg.
2. Pipa PVC AW
a. 1/2 " - 4 m. Btg. 18,600.00
b. 3/4 " - 4 m Btg. 25,500.00
c. 1 " - 4 m Btg. 35,100.00
c. 1,5 " - 4 m Btg. 62,400.00
d. 2 " - (50 mm) Btg. 256,200.00
e. 2,5 " - 4 m. Btg. 355,800.00
f. 3 " - (75 mm) Btg. 546,300.00
g. 4 " - (100 mm) Btg. 730,500.00
h. 5 " - 4 m. Btg. 354,000.00
i. 6 " - 150 mm. Btg. 1,538,000.00
j. 8 " - 4 m. Btg.
k. 2 " - 4 m. (biasa) Btg. 27,000.00
k. 2,5 " - 4 m. (biasa) Btg. 85,200.00
k. 4 " - 4 m.(biasa) Btg. 177,600.00

3. Jenis Batang "C" untuk saluran


Pembuangan Air
a. 1/2 " - 4 m. Btg. 18,000.00
b. 3/4 " - 4 m. Btg. 8,400.00
c. 1 " - 4 m. Btg.
d. 1,5 " - 4 m. Btg.
e. 2 " - 4 m. Btg.
f. 2,5 " - 4 m. Btg.
g. 3 " - 4 m. Btg.
h. 4 " - 4 m. Btg.
i. 5 " - 4 m. Btg.

4. Pipa Jenis Batang "C" untuk Instalasi


Listrik
a. 5/8 " - 4 m. Btg. 21,000.00
b. 3/4 " - 4 m. Btg.
c. 1 " - 4 m. Btg.
d. 1,5 " - 4 m. Btg.

H. BAHAN LANGIT-LANGIT
1. Eternit 100 x 100 cm. Set
2. Tripleks :
- 122 x 244 x 0,30 cm. Lbr. 60,400.00
- 122 x 244 x 0,40 cm. Lbr. 83,700.00
- 122 x 244 x 0,60 cm. Lbr. 99,800.00
- 122 x 244 x 0,90 cm. Lbr. 142,000.00
3. Calsiboard - 122 x 244 x 0,90 cm. Lbr. 84,000.00
4. Calsiboard - 120 x - 0,60 x 0,30 cm. Lbr. 100,200.00
5. Gypsum +. 9 mm (1,20 x 2,40 x 0,90 cm) Lbr. 78,000.00
6. Multipleks +. 18 mm. Lbr. 289,500.00
7. Hard Board 122 x 244 cm Lbr. 288,000.00
8. tripleks meranti +. 8 mm Lbr. 318,000.00
9. Gypsum Lbr. 78,600.00
10 GRC Lbr. 94,800.00
11 Playwood 4 x 8 inch Lbr. 114,000.00
NO JENIS BAHAN SATUAN
HARGA SATUAN KETERANGAN

.1. .2. .3. 4 5

I. BAHAN ATAP
1. Genteng : - Beton Bh. 12,000
- Asbes Lbr. -
- Methal Lbr. 114,000

2. Asbes Gelombang lbr 54,000

3. Seng Gelombang :
- BWG 34" BJLS 0.30 mm Lbr. 57,600.00
- BWG 33" BJLS 0.20 mm Lbr. 54,000.00
- plastik Lbr. 114,000.00
- Seng gelombang 3" x 6" BJLS 0,25 mm Warna Lbr. 324,000.00
- Seng gelombang spandek lebar = 80 cm tebal M' 266,400.00
- Seng gelombang spandek lebar = 80 cm tipis M' 164,400.00

4. Seng Plat :
- BJLS 0.20 mm Lbr. 54,600.00
- BJLS 0.30 mm Lbr. 60,000.00
5. Seng Alumunium Gelombang : 0,25
- SWG 32" - 0,27 mm. M2 58,800
- SWG 30" - 0,31 mm M2 66,000

6. - Atap Fiber tebal 2 mm. Feet


- Polycarbonat lbr
7. Nok/ Bubungan :
a. Genteng Beton Bh. 38,400

8. Nok Steel gabungan :


a. Mini 80 cm Bh.

9. Nak 1/2 (setengah) Lingkaran Bh. 30,000


10. Rangkap atap sakura truss+pasang M2.

J. BAHAN PENGGANTUNG
1. Kunci Tanam
a. Union 2 lovers Pasang
b. Union 3 lovers Pasang
c. Yale 2 lovers Pasang
d. Yale 3 lovers Pasang
e. Kunci tanam biasa set 78,000.00
f. Kunci tanam lemari set 21,600.00
g. Kunci silinder set 144,000.00
h. Kunci selot buah 42,000.00
i. Kunci lemari buah 24,000.00
2. Penggantung :
a. Hak angin Psg. 26,800.00
b. Grendel kuningan Psg. 10,200.00
c. Grendel vernekel Psg. 10,500.00
d. Grendel kupu-kupu Psg. 24,000.00
e. Grendel hitam Psg. 17,400.00
f. Expanyolet Psg.
g. Door Closer Bh. 192,000.00
h. Engsel kupu-kupu biasa besar Pasang 60,000.00
i. Engsel kupu-kupu biasa kecil Pasang 30,000.00
j. Engsel harmonika Ujung
k. Engsel antik Pasang
l. Engsel kupu-kupu kuningan besar Pasang
m. Tarikan jendela / ventilasi buah 7,500.00
n. Tarikan pintu buah 180,000.00

K. BAHAN SANITAIR
1 Kloset duduk:
- standar tanpa tabung Bh. 1,170,000.00
- standar dengan tabung lengkap merek Amerikan Bh. 2,190,000.00
2. Kloset jongkok merek toto Bh. 366,000.00
Kloset jongkok merek global Bh. 141,000.00
3. Wastafel gantung biasa Bh. 549,000.00
Wastafel gantung lengkap Bh. 810,000.00
Wastafel pakai kaki lengkap Bh.
4. bak cuci piring aluminium :
1 lubang+meja Bh. 219,000.00
2 lubang+meja Bh. 441,000.00
5. Pompa tangan terpasang Bh.
6. Urinoir:
body Bh.
spesifik Bh.
body standart Bh.
lengkap Bh.
7. Bak mandi:
standar Bh. 420,000.00
spesial Bh.
bath tube steel Set.
bath tube fibre glass Set.
bath tube TOTO std Bh.
bath tube TOTO spc Bh.
8. Stop kran Bh. 75,600.00
9. Kran air Bh. 98,800.00
10 Seal tape besar Bh. 11,100.00
11 Seal tape kecil Bh. 4,500.00
NO JENIS BAHAN SATUAN
HARGA SATUAN KETERANGAN

.1. .2. .3. 4 .5.

L. BAHAN CAT
1. a. Avitex kg 14,160.00
b. Metrolite/Catylag kg 23,640.00
c. Dullux Catylag kg 21,480.00
d. Dullux Weathershield kg 58,800.00
e. Kimex kg 20,400.00
f. Cat Marka Non Termoplasti Kg 100,000.00
g. Cat Marka Termoplastik Kg 20,000.00
h. Glass Bit kg 17,500.00
i. Cat Marking Kg 25,000.00

2 Cat Kayu :
a. Glotex kg 66,000.00
b. Avian kg 71,400.00
c. Platoone kg 67,200.00
e. Politur kg 32,400.00
f. Politur jadi kg
g. Menie kayu kaleng 42,000.00
h. Menie besi kaleng 39,000.00

3 Cat Atap
a. AGA kg -
b. Lem Seng m' 63,000.00
c. Plamur kg 39,000.00
d. Amplas/ Kertas Gosok Lbr 30,000.00
e. Dempul kayu kaleng 42,000
f. Residu kg 30,000.00
e. Dempul besi kaleng 135,000.00

4 Cat minyak
Platon Kg 64,800.00
Avian Kg 76,800.00
jotun Kg 102,000.00
N. BAHAN BBM, MINYAK DAN PELUMAS
1 Thiner Ltr 30,000
2 Minyak Cat Ltr 12,000
3 Bensin Ltr 12,000
4 Solar Ltr 7,800.00 9,000.00
5 Minyak Tanah Ltr 24,000.00
6 Oli/Pelumas Ltr 40,800.00
7 Grease / Fet kg 78,000.00
8 LPG kg 21,600.00
9 Minyak bekisting liter 12,000.00
10 Minyak Perekat kg 30,000.00

O. BAHAN ASPAL
1 Bitumen Aspal kg
2 Aspal kg 13,000.00
3 Laston ton 2,100,000.00
4 Ter kg
5 Filler 1,200.00
NO JENIS BAHAN SATUAN
HARGA SATUAN KETERANGAN

.1. .2. .3. 4 .5.


P. BAHAN LAIN - LAIN
1 Kayu Bakar m3 12,000.00
2 Air 1.100 liter liter 350,001
3 Amplas M' 16,800
4 Lem Fox klg 24,000
5 Lem Kaca klg 28,500
6 Wallpaper m2 120,000
7 Rangka Hollow 1 x 2 m2 72,000
9 Bahan Duco Clear untuk Sungkai m2 -
10 Slang flexible m' -
11 lem kayu liter 18,000.00
12 Pintu, pagar besi M2 621,000
13 Jendela besi M2 483,000
14 Sabun Kg 18,000.00
15 Kuas Buah 20,000.00
16 Sikat besi Buah 12,000.00
17 Tabung gas elpiji 12 kg tabung 228,000.00
18 Dolken kayu batang 18,000.00
19 alcopan indoor lembar 780,000
20 alcopan outdoor lembar 1,020,000
21 Minyak bekisting liter 12,000.00
22 Tabung gas elpiji 3 kg tabung 24,000.00
23 Tabung oksigen tabung 216,000.00 12,500.00
24 soda api kg 30,000.00
Q. UPAH KERJA
1 Pekerja Org/Hr 100,000
2 Pekerja Kebersihan/ Cleaning Service Org/Hr 100,000
3 Tukang
a. Tukang Kayu Org/Hr 150,000
b. Tukang Batu/ Aspal Org/Hr 150,000
c. Tukang Cat Org/Hr 150,000
d. Tukang Listrik Org/Hr 150,000
e. Tukang Pipa Org/Hr 150,000
f. Tukang Besi Org/Hr 150,000
g. Tukang Las Org/Hr 150,000
h. Tukang Pancang Org/Hr 150,000
4 Kepala Tukang :
a. Kayu dan Las Org/Hr 175,000
b. Batu, Cat, Listrik, Pipa, Besi dan Pancang Org/Hr 175,000
5 Mandor Org/Hr 150,000
6 Mandor Kebersihan/ Cleaning Service Org/Hr 150,000
7 Masinis/ Operator Org/Hr 175,000
8 Pembantu Masinis Org/Hr 100,000
9 Penjaga Gudang Org/Hr 175,000
10 Penjaga Malam Org/Hr 175,000
R. SEWA ALAT
1 Buldozer Jam 512,000
2 Shovel Jam 300,000
3 Wheel Loader Jam 463,050
4 Grader Jam 394,100
5 Excavator Jam 360,000
6 Three Whell Roller (Walls) Jam 193,100
7 Tired Roller Jam 429,390
8 Tandem Roller Jam 389,800
9 Vibrator Roller Jam 364,600
10 Baby Roller Jam 83,700
11 Asphal Finisher Jam 389,800
12 Asphal Sprayer Jam 58,500
13 Compressor Jam 146,800
14 Dump Truck Jam 212,700
15 Tangki Air Jam 209,350
16 Mesin Las Jam 94,000
17 Molen Jam 300,000
18 Bar Cutter Jam 65,000
19 Bar Binder Jam 65,000
20 Jack Hammer Jam 34,300
21 Ponton dengan mesin Pancang h.a 5,000,000
22 Ponton Kerja Jam 300,000
23 AMP ( Asphal Mixing Plant) Jam 3,820,800
24 Stamper Jam 44,500
25 Vibrator Beton 4 hp Jam 200,000
26 Pompa Air 50 mm - 30 m3/jam Jam 160,000
27 Bone pile Jam 731,100
28 flat bad truck Jam 159,000
29 Crane vehicle Jam 215,040
30 Crane Jam 251,160
31 Pile driver + hammer Jam 86,400
32 Generator Jam 270,360
33 Chain loader Jam 695,160
34 Welding set Jam 56,160
35 Blender potong h.a 150,000
36 Alat Thermoplastic Jam 107,000
37 Alat Bantu Jam 50,000

Mengetahui/Menyetujui TIM PENYUSUN DAFTAR HARGA SATUAN UPAH


GENERAL MANAGER BAHAN DAN PEKERJAAN TAHUN 2019
PT PELABUHAN INDONESIA IV (PERSERO) 1. R.M Wisnu D. : Pensiun
TERMINAL PETIKEMAS BITUNG KETUA

2. Amingkul F. Simanjuntak : …………..


SEKRETARIS

MUHAMMAD AYUB RIZAL 3. Yani Manderos : …………..


ANGGOTA

4. Eko Viktor Singale : …………..


ANGGOTA

5. Aditya Ambuliling : …………..


ANGGOTA
ANALISA BIAYA PEKERJAAN

A. PEKERJAAN TANAH

A.1. 1 m3 Galian tanah biasa sedalam 1 meter


0.500 h.o pekerja Rp 100,000 Rp. 50,000.00
0.050 ho mandor Rp 150,000 Rp. 7,500.00
Rp. 57,500.00

A.2. 1 m3 Galian tanah biasa sedalam 2 meter


0.6575 h.o pekerja Rp 100,000 Rp. 65,750.00
0.0650 h.o mandor Rp 150,000 Rp. 9,750.00
Rp. 75,500.00

A.3. 1 m3 Galian tanah biasa sedalam 3 meter


0.9188 h.o pekerja Rp 100,000 Rp. 91,875.00
0.0913 h.o mandor Rp 150,000 Rp. 13,687.50
Rp. 105,562.50

A.4. 1 m3 Galian tanah keras sedalam 1 meter


0.8125 h.o pekerja Rp 100,000 Rp. 81,250.00
0.0775 h.o mandor Rp 150,000 Rp. 11,625.00
Rp. 92,875.00

A.5. 1 m3 Galian tanah lumpur sedalam 1 meter


0.8230 h.o pekerja Rp 100,000 Rp. 82,300.00
0.0830 h.o mandor Rp 150,000 Rp. 12,450.00
Rp. 94,750.00

A.6. 1 m3 Galian tanah cadas sedalam 1 meter


1.2500 h.o pekerja Rp 100,000 Rp. 125,000.00
0.1250 h.o mandor Rp 150,000 Rp. 18,750.00
Rp. 143,750.00

A.7. 1 m3 Pembuangan tanah sampai dengan sejauh 150 meter


0.5160 h.o pekerja Rp 100,000 Rp. 51,600.00
0.0500 h.o mandor Rp 150,000 Rp. 7,500.00
Rp. 59,100.00

A.8. 1 m3 Urugan pasir


0.3000 h.o pekerja Rp 100,000 Rp. 30,000.00
0.0100 h.o mandor Rp 150,000 Rp. 1,500.00
Jumlah Upah Kerja .......... ..................................... Rp. 31,500.00

1.2000 m3 pasir urug Rp 84,300 Rp. 101,160.00


Jumlah Biaya Bahan .......... ..................................... Rp.

Jumlah Total Rp. 31,500.00


A.9. 1 m3 Urugan sirtu
0.2500 h.o pekerja Rp 100,000 Rp. 25,000.00
0.0250 h.o mandor Rp 150,000 Rp. 3,750.00
Jumlah Upah Kerja .......... ..................................... Rp. 28,750.00

1.2000 m3 sirtu Rp 143,250 Rp. 171,900.00


Jumlah Biaya Bahan .......... ..................................... Rp.

Jumlah Total Rp. 28,750.00

A.10. 1m3 Urugan kembali


0.1920 h.o pekerja Rp 100,000 Rp. 19,200.00
0.0190 h.o mandor Rp 150,000 Rp. 2,850.00
Rp. 22,050.00

A.11. 1 m3 Memindahkan dan meratakan tanah menggunakan bulldozer


0.0016 h.a Sewa bulldozer Rp 4,096,000 Rp 6,502
0.3365 ltr Solar Rp 7,800 Rp 2,625
0.0187 ltr Pelumas Rp 40,800 Rp 761
0.0004 kg Grease Rp 78,000 Rp 31
0.0016 h.o Operator Rp 175,000 Rp 278
Jumlah Total . . . . . . . . . . . . . . . Rp. 10,196

A.12. 1 m3 Mengeruk/leveling tanah menggunakan dozer shovel


0.0015 h.a Sewa shovel Rp 2,400,000 Rp 3,582
0.3216 ltr Solar Rp 7,800 Rp 2,509
0.0175 ltr Pelumas Rp 40,800 Rp 716
0.0004 kg Grease Rp 78,000 Rp 29
0.0015 h.o Operator Rp 175,000 Rp 261
Jumlah Total . . . . . . . . . . . . . . . Rp. 7,097

A.13. 1 m3 Mengeruk tanah menggunakan excavator hidraulic


0.0015 h.a Sewa excavator Rp 2,880,000 Rp 4,331
0.3241 ltr Solar Rp 7,800 Rp 2,528
0.0177 ltr Pelumas Rp 40,800 Rp 721
0.0004 kg Grease Rp 78,000 Rp 29
0.0015 h.o Operator Rp 175,000 Rp 263
Jumlah Total . . . . . . . . . . . . . . . Rp. 7,872

A.14. 1 m3 Memindahkan dan meratakan tanah menggunakan loader (bucket 1,7 m3)
0.0019 h.a Sewa loader Rp 3,704,400 Rp 7,056
0.4038 ltr Solar Rp 7,800 Rp 3,150
0.0224 ltr Pelumas Rp 40,800 Rp 913
0.0005 kg Grease Rp 78,000 Rp 37
0.0019 h.o Operator Rp 175,000 Rp 333
Jumlah Total . . . . . . . . . . . . . . . Rp. 11,489

A.15. 1 m3 Pengangkutan tanah menggunakan dump truck (Jarak angkut sampai dengan 1 km)
0.0187 h.a Sewa loader Rp 3,704,400 Rp 69,241
3.9626 ltr Solar Rp 7,800 Rp 30,908
0.2196 ltr Pelumas Rp 40,800 Rp 8,961
0.0047 kg Grease Rp 78,000 Rp 364
0.0187 h.o Operator Rp 175,000 Rp 3,271
Jumlah Total . . . . . . . . . . . . . . . Rp. 112,746

A.16. 1 m3 Air untuk pembasahan tanah menggunakan tangki air dengan pompa (jarak angkut + 10 km)
0.0800 h.a Sewa truk tangki air Rp 1,674,800 Rp 133,984
17.2400 ltr Solar Rp 7,800 Rp 134,472
0.9400 ltr Pelumas Rp 40,800 Rp 38,352
0.0200 kg Grease Rp 78,000 Rp 1,560
0.0800 h.o Operator Rp 175,000 Rp 14,000
Jumlah Total . . . . . . . . . . . . . . . Rp. 322,368