ANALISA RENCANA ANGGARA BIAYA (RAB)

PEKERJAAN PAGAR PROYEK TINGGI 2M BAHAN SENG GELOMBANG PER 1 M1

KOEFISIEN SATUAN URAIAN HARGA SAT. JUMLAH


0.5000 btg Baja ringan C75.65 95,000 47,500
0.0750 zak Portland cement 48,000 3,600
1.2000 lbr Seng gelombang 182x91x0,3mm 59,000 70,800
0.0070 m3 Pasir pasang 295,000 2,065
0.0090 m3 Batu split 285,000 2,565
4.0000 pcs Bat ringan 7,5 cm 7,000 28,000
0.1500 btg Reng baja ringan 35,000 5,250
36.0000 pcs Screew baja ringan 75 2,700
0.4500 kg Cat minyak 75,000 33,750
1.0000 ls Peralatan 10,000 10,000
1.0000 m1 Upah pasang 65,000 65,000
271,230
PPh & Diskkonto 6% 16,274
Resiko & laba 15% 40,685
Ohc 4% 10,849
339,038