RAB Saluran Air Drainase Dan Irigasi Trapesium DANA DESA

Anda mungkin juga menyukai

Anda di halaman 1dari 10

GAMBAR TEKNIS

KEGIATAN : PEMBANGUNAN SALURAN DRAINASE


LOKASI : RT 1 RW 3 DESA TUNJUNGAN

Desain dan perhitungan volume

Panjang Saluran = 161.0 M Cor Beton camp 1 Pc : 2 Ps : 3 Kr


0.3 0.3
0.2 plesteran 0.2
0.10

2
0.60 1 0.6

0.20
3
0.3 0.2

0.2 0.4 0.2

TAKE OF SHEET ( TOS )


Volume Beton
V.1 = 0.20 x 0.80 x 161
= 25.76 m3

V.2 = 0.20 x 0.80 x 161.0


= 25.76 m3

V.3 = 0.20 x 0.40 x 161.0


= 12.88 m3

VOLUME TOTAL Beton = 25.8 + 25.76 + 12.88


= 64.4 m3

Volume Plesteran
P = 0.30 + 0.10 x 2
= 0.80 m'
Luas Plesteran = 0.80 x 161.0
= 128.80 M2

volume galian
v.1 = 0.80 x 0.80 x 161.0
= 103.04 m3
Volume 1/2 Pekerjaan galian
= 51.52 m3
DAFTAR HARGA BAHAN SATUAN BAHAN , ALAT DAN UPAH

DAFTAR HARGA UPAH

SATUAN
NO. JENIS UPAH VOLUME
HARGA SATUAN KETERANGAN

1 Pekerja Tidak terlatih OH 46,600


2 Pekerja Terlatih OH 53,800
3 Kepala Pekerja OH 53,800
4 Tukang OH 61,100
5 Kepala Tukang OH 82,600

DAFTAR HARGA BAHAN

SATUAN
NO. JENIS BAHAN VOLUME
HARGA SATUAN KETERANGAN

1 Semen Pc 40 kg Zak 65,500


2 Semen PC 50 kg Zak
3 Pasir Beton M3 274,300
4 Pasir Urug/Timbunan Pilihan M3
5 Sirtu m3 234,300
6 Batu Pecah 2/3 ( split ) M3 285,200
7 Batu pecah 5/7 + 3/5 M3
8 Batu Belah 10/15 M3
9 Batu Blondon M3
10 Tanah Urug M3
11 Air Kerja (Bila tidak butuh air kosongka liter

DAFTAR HARGA ALAT

SATUAN
NO. JENIS BAHAN VOLUME
HARGA SATUAN KETERANGAN

1 Bambu Batang 12,000


2 Plastik Cor roll 50,000
3 Paku Kg 18,000
4 Ember cor Bh 20,000
5 Benang roll 3,000
6 Kayu Begisting (Usuk panjang 300 cm) Batang 20,000
7 Papan Cor ( 2 cm x 12 cm x 2 m) Lbr 8,000
8 Mobilisasi molen Ls 150,000
9 Sewa molen Hari 150,000
10 Papan Nama Kegiatan Bh 200,000
11 Prasasti Bh 300,000
ANALISA PEKERJAAN
Rev-SNI 91-0007-2007
1 m3 Pekerjaan Beton Camp. 1 : 2 : 3
PC 40 Kg 8.4 sak 65,500 550,200
Pasir Beton 0.54 m3 274,300 148,122
Batu Split 2/3 cm 0.81 m3 285,200 231,012
Pekerja 2 hok 53,800 107,600
Tukang Batu 0.35 hok 61,100 21,385
Kepala Tukang 0.035 hok 82,600 2,891
1,061,210

64.4 m3 Pekerjaan Beton Camp. 1 : 2 : 3


PC 40 Kg 541 sak 65,500 35,432,880
Pasir Beton 35 m3 274,300 9,539,057
Batu Split 2/3 cm 52.16 m3 285,200 14,877,173
Pekerja 128.80 hok 53,800 6,929,440
Tukang Batu 22.54 hok 61,100 1,377,194
Kepala Tukang 2.25 hok 82,600 186,180
68,341,924
1 m3 pekerjaan galian
Pekerja Gali 1.500 hok 46,600 69,900
69,900
51.52 Pekerja Gali 77.280 hok 46,600 3,601,248
3,601,248
1M2 Pekerjaan Plesteran
PC 40 Kg 0.130 sak 65,500 8,515
Pasir 0.024 m3 274,300 6,583
Tk Batu 0.150 hok 61,100 9,165
Pekerja 0.300 hok 53,800 16,140
Kepala tukang 0.015 hok 82,600 1,239
41,642
128.80 M2 Pekerjaan Plesteran
PC 40 Kg 16.744 sak 65,500 1,096,732
Pasir 3.091 m3 274,300 847,916
Tk Batu 19.320 hok 61,100 1,180,452
Pekerja 38.640 hok 53,800 2,078,832
Kepala Tukang 1.932 hok 82,600 159,583
5,363,515

1 M2 Pekerjaan Acian
PC 40 Kg 0.080 sak 65,500 5,240
Tk Batu 0.100 hok 61,100 6,110
Pekerja 0.200 hok 53,800 10,760
Kepala Tukang 0.010 hok 82,600 826
22,936
128.80 M2 Pekerjaan Acian
PC 40 Kg 10.304 sak 65,500 674,912
Tk Batu 12.880 hok 61,100 786,968
Pekerja 25.760 hok 53,800 1,385,888
Kepala Tukang 1.288 hok 82,600 106,389
2,954,157
REKAPITULASI KEBUTUHAN BAHAN DAN UPAH

Rekapitulasi Kebutuhan Bahan


Uraian Pas. Batu 1:5 Plesteran GALIAN Acian BETON total Dibulatkan sat
Split 2/3 - 52.16 52.16 53.00 m3
PC @ 40 kg - 16.74 10.30 540.96 568.01 569.00 zag
Pasir pas 34.78 3.09 34.8 72.64 73.00 m3

Rekapitulasi Kebutuhan Alat dan Upah

Uraian Pas. Batu 1:5 Plesteran GALIAN Acian BETON total Dibulatkan sat
Pekerja 52.16 38.64 25.76 128.80 245.36 246.00 HOK
Tukang Batu 34.78 19.32 12.88 22.54 89.52 90.00 HOK
Kepala Tukang 128.80 1.93 1.288 2.25 134.27 135.00 HOK
Pekerja gali 77.28 77.28 78.00 HOK
RENCANA ANGGARAN BIAYA DAN KEGIATAN DANA DESA (RAB-DANA DESA)
DESA TUNJUNGAN KECAMATAN NGOMBOL
TAHUN ANGGARAN 2018

BIDANG : Pelaksanaan Pembangunan Desa


REKENING :
KEGIATAN : Pembangunan Drainase/ selokan
WAKTU PELAKSANAAN :

Rincian Pendanaan :

HARGA
NO URAIAN VOLUME JUMLAH ( Rp )
SATUAN ( Rp )
Kegiatan Pembangunan Talud Jalan 108,496,400
1 Belanja Barang dan Jasa 36,087,400
1.1. Operasional Kegiatan
1.1.1. ATK Kegiatan 0
0
0
0
1.1.2. Cetak Pengandaan 0
Foto copy lbr 300 0
Cetak Foto 3R lbr 3000 0
Jilid bendel 7000 0

1.1.2. Uang Sidang Kegiatan 0


Penaggung Jawab kli 150,000 0
Ketua 1 x 3 kali sidang kli 130,000 0
Sekretaris 1 x 3 kali sidang kli 125,000 0
Anggota 3 x 3 kali sidang kli 100,000 0
1.2. Alat Kegiatan 772,000
Ember B 15 bh 26,000 390,000
Ember K 15 bh 11,000 165,000

Benang 10 glg 3,000 30,000


Paku reng 1 kg 18,000 18,000
Bambu 10 btg 15,000 150,000

Bedrat 1 kg 19,000 19,000


1.3. Upah Kerja 35,315,400
Kepala Tukang 135 Hok 82,600 11,151,000
Tukang 90 Hok 61,100 5,499,000
Pekerja 246 Hok 61,100 15,030,600
Pekerja galian 78.00 Hok 46,600 3,634,800
2 Belanja Modal 72,409,000
Semen/PC 40 kg 569 zak 65,500 37,269,500
Batu Pecah 2/3 ( split ) 53 m3 285,200 15,115,600
Pasir Pasang 73 m3 274,300 20,023,900

JUMLAH 108,496,400
TAKE OF SHEET ( TOS )

KEGIATAN : PEMBANGUNAN SALURAN DRAINASE


LOKASI : RT ..... RW ...Desa .................... Kecamatan ................

Desain dan perhitungan volume

Panjang Saluran = 161.0 m


Plesteran Tebal 2cm Camp. 1:6
0.25 0.25
0.15

Kemiringan 1:4

I
0.80
1 Pasangan Batu Camp. 1:4
I1 0.6

3 0.10
2
2
0.10

0.35 0.40
II 0.35

volume pasangan batu


V.1 = 0.35 + 0.25
X 0.60 X 161 x 2
2

= 57.96 m3
V.2 = 0.10 x 0.35 x 161 x 2
= 11.27 m3

V.3 = 0.10 x 0.4 x 161.0


= 6.44 m3

volume total = 57.96 + 11.27 + 6.44


= 75.67 m3

Volume Plesteran
= 0.25 + 0.60 + 0.3 + 0.6 x 161.0
= 273.7 m2

volume galian
V = 0.80 x 1.10 x 161.0
= 141.68 m3

catatan : Volume galian menyesuaikan kondisi lapangan


ANALISA PEKERJAAN
SNI 2836 2008
1 m3 Pasang batu belah 1Pc : 5Pasir
1 Batu Blondon 1.200 m3
PC 50 Kg 2.720 sak
Pasir 0.544 m3
Tk Batu 0.750 hok
Pekerja 1.500 hok
Mandor 0.075 hok

75.67 m3 Batu Blondon 90.80 m3


PC 50 Kg 205.82 sak

Pasir 41.16 m3

Tk Batu 56.75 hok


Pekerja 113.51 hok
Mandor 5.675 hok

1 m3 pekerjaan galian
Pekerja Gali 0.750 hok

141.68 Pekerja Gali 106.260 hok

1M2 Plesteran 1 : 4, tebal 1,5 cm


PC 50 Kg 0.125 sak
Pasir 0.024 m3
Tk Batu 0.150 hok
Pekerja 0.300 hok
Mandor 0.015 hok

273.70 M2 Plesteran 1 : 4, tebal 1,5 cm


PC 50 Kg 34.158 sak
Pasir 6.569 m3
Tk Batu 41.055 hok
Pekerja 82.110 hok
Mandor 4.106 hok

1 M2 Acian
PC 50 Kg 0.065 zak
Tk Batu 0.100 hok
Pekerja 0.200 hok
Mandor 0.010 hok

273.7 M2 Acian 1 m2
PC 40 Kg 17.791 zak
Tk Batu 27.370 hok
Pekerja 54.74 hok
Mandor 2.737 hok
Rekapitulasi Kebutuhan Bahan
Uraian Pas. Batu 1:5 Plesteran GALIAN Acian BETON total Dibulatkan sat
Batu Blondon 90.80 90.80 91.00 m3
PC @ 50 kg 205.82 34.16 17.79 257.77 258.00 zak
Pasir pas 41.16 6.57 47.73 48.00 m3

Rekapitulasi Kebutuhan Alat dan Upah

Uraian Pas. Batu 1:5 Plesteran GALIAN Acian BETON total Dibulatkan sat
Pekerja 113.51 41.06 27.37 181.93 182.00 HOK
Tukang Batu 56.75 6.57 17.79 81.11 82.00 HOK
Mandor 5.68 82.11 54.74 142.53 143.00 HOK
Pekerja gali 106.26 106.26 107.00 HOK
RENCANA ANGGARAN BIAYA DAN KEGIATAN DANA DESA (RAB-DANA DESA)
DESA ................... KECAMATAN ...............
TAHUN ANGGARAN 2018

BIDANG : Pelaksanaan Pembangunan Desa

KEGIATAN : Pembangunan Drainase/ selokan


WAKTU PELAKSANAAN :

Lokasi Kegiatan RT ..... RW ...Desa .................... Kecamatan ................

HARGA
NO URAIAN VOLUME JUMLAH ( Rp )
SATUAN ( Rp )

Kegiatan Pembangunan
Drainasi/Selokan 83,027,800
1 Belanja Barang dan Jasa 33,206,300
1.1. Operasional Kegiatan
1.1.1. ATK Kegiatan 355,800
Kertas HVS 70 gram 2 rim 49,500 99,000
Tinta Computer 1 bh 49,000 49,000
Materai 5 lbr 6,000 30,000
Materai 5 lbr 3,000 15,000
Lakban 2 glg 11,000 22,000
Data Prin Warna 3 btl 37,600 112,800
Pensil 2B 7 bh 4,000 28,000

1.1.2. Cetak Pengandaan 143,000


Foto copy 300 lbr 300 90000
Cetak Foto 3R 6 lbr 3000 18000
Jilid 5 bendel 7000 35000

1.1.2. Uang Sidang Kegiatan 790,000

Ketua 2 kli 150,000 300,000


Sekretaris 2 kli 130,000 260,000
Anggota 2 kli 115,000 230,000
1.2. Alat Kegiatan 603,000
Ember B 15 bh 26,000 390,000
Ember K 15 bh 11,000 165,000
Benang 10 glg 3,000 30,000
Paku reng 1 kg 18,000 18,000

1.3. Upah Kerja 31,314,500


Mandor 143 Hok 82,000 11,726,000
Tukang 82 Hok 75,000 6,150,000
Pekerja 182 Hok 46,500 8,463,000
Pekerja galian 107.00 Hok 46,500 4,975,500
2 Belanja Modal 49,821,500
Semen/PC 50 kg 258 zak 70,000 18,060,000
Batu Blondon 91 m3 204,500 18,609,500
Pasir Pasang 48 m3 274,000 13,152,000

JUMLAH 83,027,800

Anda mungkin juga menyukai