2
0.60 1 0.6
0.20
3
0.3 0.2
Volume Plesteran
P = 0.30 + 0.10 x 2
= 0.80 m'
Luas Plesteran = 0.80 x 161.0
= 128.80 M2
volume galian
v.1 = 0.80 x 0.80 x 161.0
= 103.04 m3
Volume 1/2 Pekerjaan galian
= 51.52 m3
DAFTAR HARGA BAHAN SATUAN BAHAN , ALAT DAN UPAH
SATUAN
NO. JENIS UPAH VOLUME
HARGA SATUAN KETERANGAN
SATUAN
NO. JENIS BAHAN VOLUME
HARGA SATUAN KETERANGAN
SATUAN
NO. JENIS BAHAN VOLUME
HARGA SATUAN KETERANGAN
1 M2 Pekerjaan Acian
PC 40 Kg 0.080 sak 65,500 5,240
Tk Batu 0.100 hok 61,100 6,110
Pekerja 0.200 hok 53,800 10,760
Kepala Tukang 0.010 hok 82,600 826
22,936
128.80 M2 Pekerjaan Acian
PC 40 Kg 10.304 sak 65,500 674,912
Tk Batu 12.880 hok 61,100 786,968
Pekerja 25.760 hok 53,800 1,385,888
Kepala Tukang 1.288 hok 82,600 106,389
2,954,157
REKAPITULASI KEBUTUHAN BAHAN DAN UPAH
Uraian Pas. Batu 1:5 Plesteran GALIAN Acian BETON total Dibulatkan sat
Pekerja 52.16 38.64 25.76 128.80 245.36 246.00 HOK
Tukang Batu 34.78 19.32 12.88 22.54 89.52 90.00 HOK
Kepala Tukang 128.80 1.93 1.288 2.25 134.27 135.00 HOK
Pekerja gali 77.28 77.28 78.00 HOK
RENCANA ANGGARAN BIAYA DAN KEGIATAN DANA DESA (RAB-DANA DESA)
DESA TUNJUNGAN KECAMATAN NGOMBOL
TAHUN ANGGARAN 2018
Rincian Pendanaan :
HARGA
NO URAIAN VOLUME JUMLAH ( Rp )
SATUAN ( Rp )
Kegiatan Pembangunan Talud Jalan 108,496,400
1 Belanja Barang dan Jasa 36,087,400
1.1. Operasional Kegiatan
1.1.1. ATK Kegiatan 0
0
0
0
1.1.2. Cetak Pengandaan 0
Foto copy lbr 300 0
Cetak Foto 3R lbr 3000 0
Jilid bendel 7000 0
JUMLAH 108,496,400
TAKE OF SHEET ( TOS )
Kemiringan 1:4
I
0.80
1 Pasangan Batu Camp. 1:4
I1 0.6
3 0.10
2
2
0.10
0.35 0.40
II 0.35
= 57.96 m3
V.2 = 0.10 x 0.35 x 161 x 2
= 11.27 m3
Volume Plesteran
= 0.25 + 0.60 + 0.3 + 0.6 x 161.0
= 273.7 m2
volume galian
V = 0.80 x 1.10 x 161.0
= 141.68 m3
Pasir 41.16 m3
1 m3 pekerjaan galian
Pekerja Gali 0.750 hok
1 M2 Acian
PC 50 Kg 0.065 zak
Tk Batu 0.100 hok
Pekerja 0.200 hok
Mandor 0.010 hok
273.7 M2 Acian 1 m2
PC 40 Kg 17.791 zak
Tk Batu 27.370 hok
Pekerja 54.74 hok
Mandor 2.737 hok
Rekapitulasi Kebutuhan Bahan
Uraian Pas. Batu 1:5 Plesteran GALIAN Acian BETON total Dibulatkan sat
Batu Blondon 90.80 90.80 91.00 m3
PC @ 50 kg 205.82 34.16 17.79 257.77 258.00 zak
Pasir pas 41.16 6.57 47.73 48.00 m3
Uraian Pas. Batu 1:5 Plesteran GALIAN Acian BETON total Dibulatkan sat
Pekerja 113.51 41.06 27.37 181.93 182.00 HOK
Tukang Batu 56.75 6.57 17.79 81.11 82.00 HOK
Mandor 5.68 82.11 54.74 142.53 143.00 HOK
Pekerja gali 106.26 106.26 107.00 HOK
RENCANA ANGGARAN BIAYA DAN KEGIATAN DANA DESA (RAB-DANA DESA)
DESA ................... KECAMATAN ...............
TAHUN ANGGARAN 2018
HARGA
NO URAIAN VOLUME JUMLAH ( Rp )
SATUAN ( Rp )
Kegiatan Pembangunan
Drainasi/Selokan 83,027,800
1 Belanja Barang dan Jasa 33,206,300
1.1. Operasional Kegiatan
1.1.1. ATK Kegiatan 355,800
Kertas HVS 70 gram 2 rim 49,500 99,000
Tinta Computer 1 bh 49,000 49,000
Materai 5 lbr 6,000 30,000
Materai 5 lbr 3,000 15,000
Lakban 2 glg 11,000 22,000
Data Prin Warna 3 btl 37,600 112,800
Pensil 2B 7 bh 4,000 28,000
JUMLAH 83,027,800