PROJECT TITLE : Pek. Pembangunan Jetty Port & Conveyor System PLTU 2 x 7 MW TJ. Balai Karimun Kepri
OWNER : PT. PLN (Persero)
Consortium Of PT.ETI - PT.PDP
Progress As Of September 2019
BULAN / MINGGU KE
No. DESCRIPTION Sep '19 Okt '19 Nov '19 Des '19 Jan '20 Feb '20 Mar '20 Apr '20
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35
Bollard 75 ton 6
5 Conveyor
A Pile Cap/titik Conveyor
Pekerjaan Beton K300 4 4 4 4 4 4 4 4 4 4
Bekisting 8 8 8 8 8 8 8 8 8 8
Pembesian 8 8 8 8 8 8 8 8 8 8
B Pile Dia. 400 mm
Material Spun Spun Pile Dia. 400 8 8 8 8
C Pile Dia. 600 mm
Material Spun Spun Pile Dia. 600 8