PLANING MANPOWER - CIVIL WORK

PROJECT TITLE : Pek. Pembangunan Jetty Port & Conveyor System PLTU 2 x 7 MW TJ. Balai Karimun Kepri
OWNER : PT. PLN (Persero)
Consortium Of PT.ETI - PT.PDP
Progress As Of September 2019

BULAN / MINGGU KE

No. DESCRIPTION Sep '19 Okt '19 Nov '19 Des '19 Jan '20 Feb '20 Mar '20 Apr '20

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35

I PEKERJAAN SIPIL WORK


1 JETTY & TRESTEL
A STEEL PIPE PILE DIA 609 TEBAL 14 MM
Material Tiang Pancang (89 titik x 27 m) 12 12 12 12
B Pile Dia. 600 mm Trestel
Material Spun pile Dia. 600 (12 Titik x 27 m) 12 12 12 12 12 12
C HDPE JACKETING
HDPE Jacketing Untuk Steel Pile(3 m panjang) 6 6 6 6 6
D PILE HEAD TREATMENT (PHT) STEEL PIPE PILE
Pekerjaan Beton K300 6
Pembesian 8
E PILE CAP
Pile Cap/titik
Pekerjaan Beton K300 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6 6
Bekisting 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12
Pembesian 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10 10
F BALOK (900X600)m
Balok 900x600/m
Pekerjaan Beton K300 9 9 9 9 9 9 9 9 9
Bekisting 7 5 5 5 5 5 5 5 5
Pembesian 10 12 12 12 12 12 12 12 12
G Plat Beton Jetty Tipe 1
Pekerjaan Beton K300 4 4 4 4 4 4 4 4
Bekisting 10 10 10 10 10 10 10 10
Pembesian 9 9 9 9 9 9 9 9
I Plat Trestle
Pekerjaan Beton K300 8 8 8 8 8 8 8 8 8
Bekisting 7 7 7 7 7 7 7 7 7
Pembesian 10 10 10 10 10 10 10 10 10
J BALOK
Balok 900x600/m
Pekerjaan Beton K300 4 4 4 4 4 4 4 4 4 4 4 4 4
Bekisting 5 5 5 5 5 5 5 5 5 5 5 5 5
Pembesian 13 13 13 13 13 13 13 13 13 13 13 13 13
2 Aksesories Jetty
a Cansteen
Pekerjaan Beton K300 3 3
Bekisting 3 3
b Pondasi Lampu Penerangan
Pekerjaan Beton K300 4 4 4
Bekisting 3 3 3
Pembesian 3 3 3
3 Causeway
Pekerjaan Compact Soil 2 2 2 2 2 2 2 2
Geotextile 4 4 4 4
Pek. Pasangan Batu 50 kg 3 3 3 3 3 3 3 3

Pek. Pasangan Batu 150 kg 3 3 3 3 3 3 3


Pekerjaan Beton K300 5 5
Lean Concrete 3
Bekisting 8 8
Pembesian 11 11
4 Struktur Pendukung Jetty
Fender karet type V 6 6

Bollard 75 ton 6

5 Conveyor
A Pile Cap/titik Conveyor
Pekerjaan Beton K300 4 4 4 4 4 4 4 4 4 4
Bekisting 8 8 8 8 8 8 8 8 8 8
Pembesian 8 8 8 8 8 8 8 8 8 8
B Pile Dia. 400 mm
Material Spun Spun Pile Dia. 400 8 8 8 8
C Pile Dia. 600 mm
Material Spun Spun Pile Dia. 600 8

Plan 59 89 93 93 85 89 104 106 116 112 94 78 80 79 81 81 65 43 75 82 49 49 32 23 23 51 32 16 6 6 6 0 0 0 0


Actual 31 31 31
Dev -28 -58 -62