REKAPITULASI RENCANA ANGGARAN BIAYA

PEMBANGUNAN PENGADAAN SARANA AIR BERSIH

Jenis Kegiatan ; Pekerjaan Pembangunan Sarana Air Bersih


Lokasi ; Kabupaten Bogor Jawa Barat

NO URAIAN VOLUME Satuan Harga Satuan (Rp) Jumlah Total (Rp)

I GEOLISTRIK 1.00 Unit 14,275,000.00 14,275,000.00


JUMLAH 14,275,000.00
II PEKERJAAN PERSIAPAN
1. Pembuatan Izin SIP/SIPA 1.00 Ls 10,000,000.00 10,000,000.00
2. Pembuatan Izin Warga 1.00 Ls 10,000,000.00 10,000,000.00
3. Perencanaan teknis 1.00 Ls 7,500,000.00 7,500,000.00
4. Pembersihan Lokasi 1.00 Ls 4,500,000.00 4,500,000.00
5. Dokumentasi Dan Pelaporan 1.00 Ls 5,500,000.00 5,500,000.00
JUMLAH 37,500,000.00
III PEKERJAAN PENGEBORAN SUMUR DALAM (DEEPWELL)
Pekerjaan Pembuatan Sumur Termasuk Pengadaan
Betonnit,Barit,Air Surpace Casing
1. Pengeboran Filot Hole Ø 8''
a. Dari Kedalaman 0-50 M 50.00 M 575,000.00 28,750,000.00
2. Pembesaran Lubang Bor (REAMING Ø 8-10)
a. Dari Kedalaman 0-50 M 50.00 M 640,000.00 32,000,000.00
JUMLAH 60,750,000.00
IV PENGADAAN DAN PEMASANGAN KONTRUKSI SUMUR
a. PIPA GI Ø 8'' Berikut Pengelasan 2.00 M 457,300.00 914,600.00
b. PIPA PVC Ø 8'' Untuk Casing 50.00 M 358,750.00 17,937,500.00
c. PIPA PVC Ø 8'' Untuk Saringan 70.00 M 358,750.00 25,112,500.00
d. Sentralizer 45.00 BH 105,000.00 4,725,000.00
e. GREPEL Ukuran 3-7 3.00 M3 295,350.00 886,050.00
f. Cement Groting 2.00 M3 2,375,000.00 4,750,000.00
g. Beton Cor 1;2;3 Untuk SURPACE APRON 6.00 M3 930,000.00 5,580,000.00
JUMLAH 59,905,650.00
V PEKERJAAN POMPA (SPEEK TEKNIS)
a. Elektikaloging Pada Lubang Sumur 120.00 M 70,500.00 8,460,000.00
b. Uji Pompa Metode Step 24.00 Jam 260,500.00 6,252,000.00
c. Analisa Kimia Contoh Air 3.00 SPL 350,000.00 1,050,000.00
d. Pompa Sumer Sible Air Bersih 3PK Head Min 100 M 1.00 Unit 23,700,000.00 23,700,000.00
e. Panel Pompa OutDoor 1.00 Unit 7,435,000.00 7,435,000.00
f. Water Level Control Elektroda 3.00 Set 95,000.00 285,000.00
g. Kabel Power Pompa Jenis NYYHY 4X6MM 90.00 M 65,000.00 5,850,000.00
H. Presure Suit 1.00 Unit 1,200,000.00 1,200,000.00
JUMLAH 54,232,000.00
VI PEKERJAAN DAN PEMASANGAN SAMBUNGAN RUMAH TANGGA
a. PIPA GI Ø 2'' Atas HORIZONTAL 17.00 M 195,000.00 3,315,000.00
b. PIPA GI Ø 2'' Tekan VERTIKAL 72.00 M 195,000.00 14,040,000.00
c. HIDROPOOR Volume 2M 1.00 Unit 19,500,000.00 19,500,000.00
d. TOREN 2000 Ltr 1.00 BH 3,250,000 3,250,000.00
e. Pelampung 3/4'' 1.00 BH 350,000 350,000.00
f. Clamp Sadle Ø 2x1'' 2.00 BH 275,000 550,000.00
g. Kendi PVC Ø 1'' 6.00 BH 5,000 30,000.00
h. SDD Ø 1'' 2.00 BH 17,000 34,000.00
i. SDL Ø 1'' 3.00 BH 17,000 51,000.00
j. SDL Ø 2'' 3.00 BH 25,000 75,000.00
K. METERAN AIR SAMBUNGAN RUMAH 45.00 BH 720,000 32,400,000.00
JUMLAH 73,595,000.00
VII PENGADAAN ACSESORIS
a. BOUGHT Ø 2'' 1.00 BH 105,000.00 105,000.00
b. TEE GI Ø 2X1/2'' 1.00 BH 65,000.00 65,000.00
c. DOUBLE NAPLE Ø 2'' 1.00 BH 82,500.00 82,500.00
d. DOUBLE NAPLE Ø 1,5'' 1.00 BH 55,500.00 55,500.00
e. BRASS VALVE Ø 2'' 1.00 BH 470,000.00 470,000.00
f. BRASS VALVE Ø 1,5'' 1.00 BH 340,000.00 340,000.00
g. CEK VALVE Ø 2'' 1.00 BH 505,000.00 505,000.00
h. SEAL TAPE 1.00 Dus 27,000.00 27,000.00
i. PLANG LAS Ø 8'' 2.00 BH 265,000.00 530,000.00
JUMLAH 2,180,000.00
JUMLAH TOTAL I+II+III+IV+V+VI+VII 302,437,650.00
Terbilang ; Tiga Ratus dUA Juta EMPAT RATUS Tiga Puluh Tujuh Ribu Enam Ratus Lima Puluh Rupiah

Cipanas, 04 April 2019


Perencana Teknis

…………………………………..
RENCANA ANGGARAN BIAYA
PEMBANGUNAN PENGADAAN SARANA AIR BERSIH

Jenis Kegiatan ; Pekerjaan Pembangunan Sarana Air Bersih


Lokasi ; Kabupaten Bogor Jawa Barat

JUMLAH
NO URAIAN KEGIATAN
BIAYA
1 GEOLISTRIK 14,275,000.00

2 PEKERJAAN PERSIAPAN 37,500,000.00

3 PEKERJAAN PENGEBORAN SUMUR DALAM (DEEPWELL) 60,750,000.00

4 PEKERJAAN PEMASANGAN KONTRUKSI SUMUR 59,905,650.00

5 PEKERJAAN POMPA (SPEEK TEKNIS) 54,232,000.00

6 PEKERJAAN DAN PEMASANGAN SAMBUNGAN RUMAH TANGGA 73,595,000.00

7 PENGADAAN AKSESORIS 2,180,000.00


JUMLAH 302,437,650.00

Cipanas, 04 April 2019


Perencana Teknis

…………………………….