Pipe Report MGG 4
Pipe Report MGG 4
PROGRES KERJA
BOBOT MGG
KONTRAK LALU
NO URAIAN MGG INI S.D MGG INI
KONTRA
K
% bobot bobot bobot
`
III INSTALASI LUAR BANGUNAN AIR BERSIH GRAVITAS
PROGRES KERJA
BOBOT MGG
NO URAIAN KONTRAK LALU MGG INI S.D MGG INI
KONTRA
K
% bobot bobot bobot
`
III INSTALASI LUAR BANGUNAN AIR BERSIH GRAVITAS
Pekerjaan Pengadaan dan Pemasangan Pipa HDPE PN-10
lengkap dengan material bantu & sesuai dengan Spesifikasi
Teknis :
1 - dia. 75 mm 0.6524 0.130 0.130 0.130 0.130 0.130
2 - dia. 90 mm 1.7504 0.350 0.350 0.350 0.350 0.350
1.3
3 - dia. 160 mm 21.5237 1.266 1.266 1.266 1.266 1.266 1.266 1.266 1.266 1.266 1.266 1.266 1.266 1.266 1.266 1.266 1.266
Accessories :
Gate Valve
4 - dia. 65 mm 0.1134 0.057 0.057
5 - dia. 80 mm 0.0804 0.080
6 - dia. 150 mm 0.5085 0.254 0.254
Tee
9 - dia. 160 x 160 mm 0.0378 0.019 0.019
Tee - Reducer
10 - dia. 160 x 75 mm 0.1029 0.051 0.051
11 - dia. 160 x 90 mm 0.0215 0.022
Elbow 90°
- dia. 160 x 90 mm 0.0093 0.009
Elbow 45°
18 - dia. 90 mm 0.0185 0.019
19 - dia. 160 mm 0.1745 0.044 0.044 0.044 0.044
20 Material bantu, Siku, Cat Coating Suport, Dynabot dll 0.8927 0.446 0.446
Pekerjaan Tanah
24 - Gali Tanah 1.9384 0.114 0.114 0.114 0.114 0.114 0.114 0.114 0.114 0.114 0.114 0.114 0.114 0.114 0.114 0.114 0.114 0.114
25 - Urugan kembali Tanah dan Dipadatkan 0.9007 0.056 0.056 0.056 0.056 0.056 0.056 0.056 0.056 0.056 0.056 0.056 0.056 0.056 0.056 0.056 0.056
Pekerjaan Aspal
26 - Gali aspal 0.8449 0.211 0.211 0.211 0.211
27 - Finishing kembali dengan aspal 0.8079 0.269 0.269 0.269
28 - Pembungan tanah sisa galian 0.2282 0.114 0.114
100.000
Progress Rencana (Kontrak) 0.067 0.067 0.087 0.087 0.024 0.138 0.703 2.031 2.869 6.094 6.308 6.277 6.364 6.530 6.609 7.135 7.126 6.700 6.180 6.106 5.394 5.563 5.308 5.251 0.265 0.717
Progress Rencana Komulatif (Kontrak) 0.067 0.133 0.220 0.307 0.331 0.469 1.172 3.203 6.072 12.167 18.475 24.752 31.116 37.645 44.254 51.389 58.515 65.216 71.395 77.501 82.896 88.459 93.766 99.018 99.283 100.000
BULAN : Maret
TANGGAL 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
WAKTU
05:00:00 C C B C B C B C C C B C B C B C B C
06:00:00 C C B C B C B C C C B C B C B C B C
07:00:00 C C C C C C C C C C C C C C C C C C
08:00:00 C C C C C C C C C C C C C C C C C C
09:00:00 C C C C C C C C C C C C C C C C C C
10:00:00 C C C C C C C C C C C C C C C C C C
11:00:00 B C C C C B C C B B C B C C C C C C
12:00:00 B B C B C B C B B B C B C B C B C B
13:00:00 C B C B C C L C B C C C C L C B C B C B L
14:00:00 C B C B C C I C B C C C C I C B C B C B I
B B B
15:00:00 B B C B C B U C B B B C B U C B C B C B U
16:00:00 B B C B C B R C B B B C B R C B C B C B R
16:59:59 B H C H C B C H B B C B C H C H C H
17:59:59 C H C H C C C H C C C C C H C H C H
18:59:59 C H B H B C B H C C B C B H B H B H
19:59:59 H B B B B H B B H H B H B B B B B B
20:59:59 H C H C H H H C H H H H H C H C H C
21:59:59 B B H B H B H B B B H B H B H B H B
22:59:59 H H H H H H H H H H H H H H H H H H
23:59:59 H H H H H H H H H H H H H H H H H H
Dibuat Oleh,
Catatan : Kontraktor
PT. GARUDA NUSANTARA CONSTRUCTION
C : Cerah
B : Berawan
H : Hujan
Meita Rebby Farizzi, SE.
Direktur
Pekrjaan Rumah Dinas Dan Wadan Denhanud Madiun
Week :1
Keadaan Cuaca
Pagi Siang Sore Catatan
Cerah Mendung Cerah
Pelaksana
LAPORAN HARIAN PEKERJAAN
Keadaan Cuaca
Pagi Siang Sore Catatan
Cerah Mendung Cerah
Pelaksana
LAPORAN HARIAN PEKERJAAN
Keadaan Cuaca
Pagi Siang Sore Catatan
Cerah Mendung Cerah
Pelaksana
LAPORAN HARIAN PEKERJAAN
Keadaan Cuaca
Pagi Siang Sore Catatan
Cerah Mendung Cerah
Pelaksana
LAPORAN HARIAN PEKERJAAN
Keadaan Cuaca
Pagi Siang Sore Catatan
Cerah Mendung Cerah
Pelaksana
LAPORAN HARIAN PEKERJAAN
Keadaan Cuaca
Pagi Siang Sore Catatan
Cerah Mendung Cerah
Pelaksana
LAPORAN HARIAN PEKERJAAN
Keadaan Cuaca
Pagi Siang Sore Catatan
Cerah Mendung Cerah
Pelaksana