NO.

RAB URAIAN PEKERJAAN SAT VOL

1 Bore Pile dia. 80cm, K-350 m' 672.00


2 Memotong/Bobok Borepile dia. 80 cm bh 24.00
3 Mamancang SSP untuk Shoring Penahan Tanah m' 3,834.00
4 Mencabut SSP untuk Shoring m' 3,834.00
5 Pemasangan H-Beam untuk Bracing Keliling Shoring m' 2,130.00
6 Urugan Pasir m3 286.00
7 Lantai Kerja Beton K-175 m3 140.36
8 Bekesting Pondasi m2 785.64
9 Bekesting Dinding, Wingwall dan Parapet m2 4,690.00
10 Bekesting Lantai m2 241.26
11 Pembesian U-32 Kg 255,119.70
12 Pembesian BJTD 40 Kg 31,350.60
13 Beton K-300 m3 2,182.22
14 Beton K-350 m3 14.90
15 Drainase Suling-Suling Pipa Galvanis 2" bh 1,132.00
NILAI BOBOT PRODUKTIVITAS jumlah koefisien
(%) HARIAN (SAT./HARI) pekerja produktivitas

4.415 10.67 10 0.938


0.117 1.71 10 5.833
4.747 78.24 10 0.128
1.470 91.29 10 0.110
1.356 50.71 10 0.197
0.140 5.84 10 1.713
0.288 2.86 10 3.491
0.339 16.03 10 0.624
2.741 60.91 10 0.164
0.157 2.87 10 3.482
6.129 1,518.57 10 0.007
0.838 373.22 10 0.027
5.141 14.85 10 0.674
0.038 0.53 10 18.792
0.172 40.43 10 0.247
4.3.1 Menghitung Produktifitas Harian
Produktifitas Harian =

NO. URAIAN PEKERJAAN SAT

1 Bore Pile dia. 80cm, K-350 m'


2 Memotong/Bobok Borepile dia. 80 cm bh
3 Mamancang SSP untuk Shoring Penahan Tanah m'
4 Mencabut SSP untuk Shoring m'
5 Pemasangan H-Beam untuk Bracing Keliling Shoring m'
6 Urugan Pasir m3
7 Lantai Kerja Beton K-175 m3
8 Bekesting Pondasi m2
9 Bekesting Dinding, Wingwall dan Parapet m2
10 Bekesting Lantai m2
11 Pembesian U-32 Kg
12 Pembesian BJTD 40 Kg
13 Beton K-300 m3
14 Beton K-350 m3
15 Drainase Suling-Suling Pipa Galvanis 2" bh
Volume
Durasi Normal

PRODUKTIVITAS HARIAN
DUR (HARI) VOL
(SAT./HARI)

63 672.00 10.67
14 24.00 1.71
49 3,834.00 78.24
42 3,834.00 91.29
42 2,130.00 50.71
49 286.00 5.84
49 140.36 2.86
49 785.64 16.03
77 4,690.00 60.91
84 241.26 2.87
168 255,119.70 1,518.57
84 31,350.60 373.22
147 2,182.22 14.85
28 14.90 0.53
28 1,132.00 40.43
4.3.2 Menghitung Produktifitas Perjam
Produktifitas Perjam =

NO. URAIAN PEKERJAAN SAT

1 Bore Pile dia. 80cm, K-350 m'


2 Memotong/Bobok Borepile dia. 80 cm bh
3 Mamancang SSP untuk Shoring Penahan Tanah m'
4 Mencabut SSP untuk Shoring m'
5 Pemasangan H-Beam untuk Bracing Keliling Shoring m'
6 Urugan Pasir m3
7 Lantai Kerja Beton K-175 m3
8 Bekesting Pondasi m2
9 Bekesting Dinding, Wingwall dan Parapet m2
10 Bekesting Lantai m2
11 Pembesian U-32 Kg
12 Pembesian BJTD 40 Kg
13 Beton K-300 m3
14 Beton K-350 m3
15 Drainase Suling-Suling Pipa Galvanis 2" bh
Produktivitas Harian
8 Jam

PRODUKTIVITAS PRODUKTIVITAS
HARIAN (SAT./HARI) PERJAM (SAT./JAM)

10.67 1.33
1.71 0.21
78.24 9.78
91.29 11.41
50.71 6.34
5.84 0.73
2.86 0.36
16.03 2.00
60.91 7.61
2.87 0.36
1,518.57 189.82
373.22 46.65
14.85 1.86
0.53 0.07
40.43 5.05
4.3.3 Menghitung Produktifitas Harian Sesudah Crash
Produktifitas Harian Sesudah Crash =
Koef. Produktivitas =
t (jam) =
durasi kerja perhari =

NO. URAIAN PEKERJAAN SAT

1 Bore Pile dia. 80cm, K-350 m'


2 Memotong/Bobok Borepile dia. 80 cm bh
3 Mamancang SSP untuk Shoring Penahan Tanah m'
4 Mencabut SSP untuk Shoring m'
5 Pemasangan H-Beam untuk Bracing Keliling Shoring m'
6 Urugan Pasir m3
7 Lantai Kerja Beton K-175 m3
8 Bekesting Pondasi m2
9 Bekesting Dinding, Wingwall dan Parapet m2
10 Bekesting Lantai m2
11 Pembesian U-32 Kg
12 Pembesian BJTD 40 Kg
13 Beton K-300 m3
14 Beton K-350 m3
15 Drainase Suling-Suling Pipa Galvanis 2" bh
(8 Jam x Prod. Perjam) + (t(jam) x Koef. Produktivitas x Prod. Perjam)
Jumlah Pekerja / Produktivitas Perhari
4 3 2 1
8

PRODUKTIVITAS PERJAM PRODUKTIVITAS JUMLAH KOEF.


(SAT./JAM) HARIAN (SAT./HARI) PEKERJA PRODUKTIVITAS

1.33 10.67 10 0.938


0.21 1.71 10 5.833
9.78 78.24 10 0.128
11.41 91.29 10 0.110
6.34 50.71 10 0.197
0.73 5.84 10 1.713
0.36 2.86 10 3.491
2.00 16.03 10 0.624
7.61 60.91 10 0.164
0.36 2.87 10 3.482
189.82 1,518.57 10 0.007
46.65 373.22 10 0.027
1.86 14.85 10 0.674
0.07 0.53 10 18.792
5.05 40.43 10 0.247
PRODUKTIVITAS HARIAN PRODUKTIVITAS HARIAN PRODUKTIVITAS HARIAN
SESUDAH CRASH (SAT./HARI) SESUDAH CRASH (SAT./HARI) SESUDAH CRASH (SAT./HARI)
(t=4) (t=3) (t=4)
15.67 14.42 13.17
6.71 5.46 4.21
83.24 81.99 80.74
96.29 95.04 93.79
55.71 54.46 53.21
10.84 9.59 8.34
7.86 6.61 5.36
21.03 19.78 18.53
65.91 64.66 63.41
7.87 6.62 5.37
1,523.57 1,522.32 1,521.07
378.22 376.97 375.72
19.85 18.60 17.35
5.53 4.28 3.03
45.43 44.18 42.93
PRODUKTIVITAS
HARIAN SESUDAH
CRASH (SAT./HARI)
(t=4)
11.92
2.96
79.49
92.54
51.96
7.09
4.11
17.28
62.16
4.12
1,519.82
374.47
16.10
1.78
41.68
4.3.4 Menghitung Waktu Percepatan Proyek (Crash Duration)
Crash Duration =
Koef. Produktivitas =

NO. URAIAN PEKERJAAN SAT

1 Bore Pile dia. 80cm, K-350 m'


2 Memotong/Bobok Borepile dia. 80 cm bh
3 Mamancang SSP untuk Shoring Penahan Tanah m'
4 Mencabut SSP untuk Shoring m'
5 Pemasangan H-Beam untuk Bracing Keliling Shoring m'
6 Urugan Pasir m3
7 Lantai Kerja Beton K-175 m3
8 Bekesting Pondasi m2
9 Bekesting Dinding, Wingwall dan Parapet m2
10 Bekesting Lantai m2
11 Pembesian U-32 Kg
12 Pembesian BJTD 40 Kg
13 Beton K-300 m3
14 Beton K-350 m3
15 Drainase Suling-Suling Pipa Galvanis 2" bh
Volume
Produktifitas Harian Sesudah Crash

PROD. HARIAN PROD. HARIAN PROD. HARIAN


VOL SESUDAH CRASH SESUDAH CRASH SESUDAH CRASH
(SAT./HARI) (t=4) (SAT./HARI) (t=3) (SAT./HARI) (t=2)
672.00 15.67 14.42 13.17
24.00 6.71 5.46 4.21
3,834.00 83.24 81.99 80.74
3,834.00 96.29 95.04 93.79
2,130.00 55.71 54.46 53.21
286.00 10.84 9.59 8.34
140.36 7.86 6.61 5.36
785.64 21.03 19.78 18.53
4,690.00 65.91 64.66 63.41
241.26 7.87 6.62 5.37
255,119.70 1,523.57 1,522.32 1,521.07
31,350.60 378.22 376.97 375.72
2,182.22 19.85 18.60 17.35
14.90 5.53 4.28 3.03
1,132.00 45.43 44.18 42.93
PROD. HARIAN CRASH CRASH CRASH
PEMBULA PEMBUL
SESUDAH CRASH DURATION DURATION DURATION
TAN ATAN
(SAT./HARI) (t=1) (HARI) (t=4) (HARI) (t=3) (HARI) (t=2)
11.92 42.89 43 46.61 47 51.04
2.96 100.09 101 122.98 123 159.46
79.49 8.07 9 8.20 9 8.32
92.54 6.98 7 7.07 8 7.17
51.96 12.06 13 12.34 13 12.63
7.09 62.01 63 70.10 71 80.61
4.11 85.45 86 101.60 102 125.27
17.28 31.95 32 33.97 34 36.26
62.16 10.20 11 10.39 11 10.60
4.12 85.36 86 101.48 102 125.09
1,519.82 0.44 1 0.44 1 0.44
374.47 1.78 2 1.78 2 1.79
16.10 33.86 34 36.14 37 38.74
1.78 121.47 122 156.93 157 221.63
41.68 14.79 15 15.21 16 15.65
CRASH
PEMBUL PEMBUL
DURATION
ATAN ATAN
(HARI) (t=1)
52 56.39 57
160 226.70 227
9 8.45 9
8 7.26 8
13 12.93 13
81 94.83 95
126 163.33 164
37 38.88 39
11 10.81 11
126 163.02 164
1 0.44 1
2 1.79 2
39 41.75 42
222 377.07 378
16 16.12 17