Staff In Charge Responsible Dept. Mgr. Prod. Dept. Mgr. or Project Leader
*) Only for design and modification job
Z:\FromDepartment\SAF\FORM S&H (CONTROL)\Simple Hazard Identification and Risk Assessment (FRM-SFT-0056)/10/20/2011/Fie
No : FRM - SFT - 0066, Rev. : 1, Date : August 25, 2010
No. : HIRAC/JGC/1111/006
Simple Hazard Identification and Risk Assessment Rev. :0
(Excavation and Compaction Work) Date : 1-Dec-2011
Page : 2 of 3
Result of Modification Job
No. Name of Job / Step of Activity Hazard Risk Counter Measure
Evaluation Effectiveness *)
3 Pemadatan Tanah Galian dengan baby roller 3.1. Getaran yang kontinyu 3.1. Pekerja merasa pusing, mual, 3.1. - Ikuti ambang batas getaran sesuai
dan atau tamping reamer 3.2. Kebisingan tidak nyaman, nyeri dada, dsb Kepmenaker 5/1999 yaitu 4 m/det2
3.3. Pergerakan baby roller dan 3.2. Gangguan pendengaran - Operasi stamper secara bergantian
atau stamper 3.3. Kaki tertimpa baby roller / setiap 15 menit
3.4. Ruang terbatas (confined stamper 3.2. Gunakan ear plug
space) jika kedalaman > 3 ft 3.4. - Kematian / pingsan karena 3.3. Jaga jarak aman kaki dari gerakan
3.5. Genangan air dan licin kekurangan oksigen atau alat
(jika hujan) menghirup gas beracun 3.4. - Pastikan izin confined space ada dan
- Dehidrasi sudah disetujui pihak berwenang
- Tertimpa longsoran tanah - Lakukan pengukuran gas dengan gas
3.5. - Pekerja terjatuh / tergelincir detector sebelum masuk ke ruang
terbatas dan secara reguler
- Gunakan exhaust fan dan blower jika
hasil deteksi gas melebihi ambang
batas
- Pastikan pekerja selalu cukup minum
- Siapkan akses turun naik galian yang
aman.
- Watchman harus selalu ada di sekitar
area galian untuk mengawasi
- sama dengan item 2.3.
Staff In Charge Responsible Dept. Mgr. Prod. Dept. Mgr. or Project Leader
*) Only for design and modification job
Z:\FromDepartment\SAF\FORM S&H (CONTROL)\Simple Hazard Identification and Risk Assessment (FRM-SFT-0056)/10/20/2011/Fie
No : FRM - SFT - 0066, Rev. : 1, Date : August 25, 2010
No. : HIRAC/JGC/1111/006
Simple Hazard Identification and Risk Assessment Rev. :0
(Excavation and Compaction Work) Date : 1-Dec-2011
Page : 3 of 3
Result of Modification Job
No. Name of Job / Step of Activity Hazard Risk Counter Measure
Evaluation Effectiveness *)
3.5. Genangan air dan licin 3.5. - Pekerja terjatuh / tergelincir 3.5. - Pompa air hingga kering jika ada
(jika hujan) - Pekerja sakit karena berada genangan air
dalam genangan air (basah) - Pastikan pompa air sudah diinspeksi
Asahimas sebelum digunakan
- Pastikan grounding mesin pompa
air terpasang
- Pastikan akses turun naik galian
kering sebelum digunakan pekerja
serta area galian bebas dari genangan
- Pekerja menggunakan rubber boot
Staff In Charge Responsible Dept. Mgr. Prod. Dept. Mgr. or Project Leader
*) Only for design and modification job
Z:\FromDepartment\SAF\FORM S&H (CONTROL)\Simple Hazard Identification and Risk Assessment (FRM-SFT-0056)/10/20/2011/Fie