URAIAN LANGKAH
POTENSI BAHAYA EFEK BAHAYA PENGENDALI RISIKO
No KERJA (Hazard) (Consequence) (Risk Reduction Measure)
(Task Step)
5 Charging scissor Lift. 5.1. Electric Shock / 4.1.1. Injury / Cidera. 4.1.1.1. Baricade area when scissor lift charging/ Barikade
/ Pengecasan Tersetrum. 4.1.2. Burns / Luka bakar area ketika scissor lift di cas.
scissor lift. 5.2. Fire / Kebakar 4.1.3. Fire / Kebakaran 4.1.1.2. Do not operate scissor lift when charging. /
5.3. Slip / Terpleset Dilarang mengoperasikan scissor lift Ketika di cas.
5.4. Pinch / Terjepit 4.1.1.3. Ensure when charging someone guard /
Ketika di cas harus ada yang jaga.
4.1.1.4. Ensure operator have SIO / Pastikan operator
memiliki sertifikasi SIO
4.1.1.5. Use PPE / Gunakan APD (Sepatu safety, helmet,
sarung tangan)
4 Weekly Scissor Lift 4.1. Electric Shock / 4.1.1. Injury / Cidera. 4.1.1.1. Baricade area when scissor lift charging/ Barikade
Inspection. / Tersetrum. 4.1.2. Burns / Luka bakar area ketika scissor lift di cas.
pengecekan 4.2. Fire / Kebakar 4.1.3. Fire / Kebakaran 4.1.1.2. Do not operate scissor lift when charging. /
mingguan scissor lift
Dilarang mengoperasikan scissor lift Ketika di cas.
4.1.1.3. Ensure when charging someone guard /
Ketika di cas harus ada yang jaga.
4.1.1.4. Ensure operator have SIO / Pastikan operator
memiliki sertifikasi SIO
4.1.1.5. Use PPE / Gunakan APD (Sepatu safety, helmet,
sarung tangan)
Note: Job Safety Analysis (JSA) harus disampaikan ke seluruh pekerja sebelum memulai pekerjaan / JSA should be inform to all workers before working started