Nomor :
Tanggal : Juli 2020
I. BIAYA LANGSUNG PERSONEL (REMUNERATION)
Vol/Satuan HPS/OE Penawaran Harga Negosiasi Harga
A TENAGA AHLI
1 Ahli Arsitek 1 1 17,000,000 17,000,000 17,250,000 17,250,000 17,000,000 17,000,000
2 Ahli Desain Interior 1 1 15,000,000 15,000,000 14,800,000 14,800,000 14,800,000 14,800,000
3 Ahli Mekanikal - Elektrikal 1 0.5 15,000,000 7,500,000 14,800,000 7,400,000 14,800,000 7,400,000
B TENAGA PENDUKUNG
1 Drafter 2 1 6,000,000 12,000,000 5,900,000 11,800,000 5,900,000 11,800,000
2 Surveyor 1 0.5 6,000,000 3,000,000 5,900,000 2,950,000 5,900,000 2,950,000
3 Estimator 1 0.5 6,000,000 3,000,000 5,900,000 2,950,000 5,900,000 2,950,000
Sub-Jumlah A 57,500,000 57,150,000 56,900,000
JUMLAH TOTAL I 57,500,000 57,150,000 56,900,000
Terbilang: Tujuh puluh empat juta seratus delapan puluh empat ribu rupiah
Catatan : harga tersebut sudah termasuk PPn 10 % dan pajak-pajak lain yang berlaku
A TENAGA AHLI
1 Ahli Arsitek 1 1 17,000,000 17,000,000
2 Ahli Desain Interior 1 1 14,800,000 14,800,000
3 Ahli Mekanikal - Elektrikal 1 0.5 14,800,000 7,400,000
B TENAGA PENDUKUNG
1 Drafter 2 1 5,900,000 11,800,000
2 Surveyor 1 0.5 5,900,000 2,950,000
3 Estimator 1 0.5 5,900,000 2,950,000
Sub-Jumlah A 56,900,000
JUMLAH TOTAL I 56,900,000
A BIAYA
1 Alat Tulis Kantor + Tinta 1 1 3,450,000 3,450,000
Sub-Jumlah A 3,450,000
B PELAPORAN
1 Laporan Pendahuluan 5 buku 310,000 1,550,000
2 Laporan Antara 5 buku 410,000 2,050,000
3 Gambar rencana teknis 5 buku 560,000 2,800,000
4 Laporan Akhir 1 buku 475,000 475,000
5 Softcopy dalam bentuk CD 5 buah 50,000 250,000
Sub-Jumlah B 7,125,000
JUMLAH TOTAL II 10,575,000
JUMLAH TOTAL I + II 67,475,000
PPn 10% 6,747,500
JUMLAH 74,222,500
DIBULATKAN 74,184,000
Terbilang: Tujuh puluh empat juta seratus delapan puluh empat ribu rupiah
Catatan : harga tersebut sudah termasuk PPn 10 % dan pajak-pajak lain yang berlaku
Dian Kreshnadjati 0
NIP. 19741006 199903 2 002 Direktur Utama
PENAWARAN HARGA
PERENCANAAN RENOVASI RUANG KANTOR
KEMENTERIAN KETENAGAKERJAAN
Tahun 2020
I. BIAYA LANGSUNG PERSONEL (REMUNERATION)
Jumlah Waktu Jumlah
No PERSONIL Personil Keterlibatan SBOB (Rp)
Orang (Bulan) (Rp.)
A TENAGA AHLI
1 Ahli Arsitek 1 1 17,250,000 17,250,000
2 Ahli Desain Interior 1 1 14,800,000 14,800,000
3 Ahli Mekanikal - Elektrikal 1 0.5 14,800,000 7,400,000
B TENAGA PENDUKUNG
1 Drafter 2 1 5,900,000 11,800,000
2 Surveyor 1 0.5 5,900,000 2,950,000
3 Estimator 1 0.5 5,900,000 2,950,000
Sub-Jumlah A 57,150,000
JUMLAH TOTAL I 57,150,000
A BIAYA
1 Alat Tulis Kantor + Tinta 1 1.0 3,450,000 3,450,000
Sub-Jumlah A 3,450,000
B PELAPORAN
1 Laporan Pendahuluan 5 buku 310,000 1,550,000
2 Laporan Antara 5 buku 410,000 2,050,000
3 Gambar rencana teknis 5 buku 560,000 2,800,000
4 Laporan Akhir 1 buku 480,000 480,000
5 Softcopy dalam bentuk CD 5 buah 73,000 365,000
Sub-Jumlah B 7,245,000
JUMLAH TOTAL II 10,695,000
JUMLAH TOTAL I + II 67,845,000
PPn 10% 6,784,500
JUMLAH 74,629,500
DIBULATKAN 74,629,000
Terbilang : Tujuh puluh empat juta enam ratus dua puluh sembilan ribu rupiah
Catatan : harga tersebut sudah termasuk PPn 10 % dan pajak-pajak lain yang berlaku
0.00
0
Direktur Utama
HARGA PERKIRAAN SENDIRI (HPS)
PERENCANAAN RENOVASI RUANG KANTOR
KEMENTERIAN KETENAGAKERJAAN
Tahun 2020
I. BIAYA LANGSUNG PERSONEL (REMUNERATION)
Jumlah Waktu Jumlah
No PERSONIL Personil Keterlibatan SBOB (Rp)
Orang (Bulan) (Rp.)
A TENAGA AHLI
1 Ahli Arsitek 1 1 17,000,000 17,000,000
2 Ahli Desain Interior 1 1 15,000,000 15,000,000
3 Ahli Mekanikal - Elektrikal 1 0.5 15,000,000 7,500,000
B TENAGA PENDUKUNG
1 Drafter 2 1 6,000,000 12,000,000
2 Surveyor 1 0.5 6,000,000 3,000,000
3 Estimator 1 0.5 6,000,000 3,000,000
Sub-Jumlah A 57,500,000
JUMLAH TOTAL I 57,500,000
A BIAYA
1 Alat Tulis Kantor + Tinta 1 1.0 3,500,000 3,500,000
Sub-Jumlah A 3,500,000
B PELAPORAN
1 Laporan Pendahuluan 5 buku 300,000 1,500,000
2 Laporan Antara 5 buku 400,000 2,000,000
3 Gambar rencana teknis 5 buku 550,000 2,750,000
4 Laporan Akhir 1 buku 475,000 475,000
5 Softcopy dalam bentuk CD 5 buah 75,000 375,000
Sub-Jumlah B 7,100,000
JUMLAH TOTAL II 10,600,000
JUMLAH TOTAL I + II 68,100,000
PPn 10% 6,810,000
JUMLAH 74,910,000
DIBULATKAN 74,910,000
Terbilang : Tujuh puluh empat juta sembilan ratus sepuluh ribu rupiah
Catatan : harga tersebut sudah termasuk PPn 10 % dan pajak-pajak lain yang berlaku
Dian Kreshnadjati
NIP. 19741006 199903 2 002
DAFTAR KUANTITAS DAN HARGA
PERENCANAAN RENOVASI RUANG KANTOR
Jl. Jend. Gatot Subroto Kav. 51 Jakarta Selatan
Tahun 2020
Jumlah Waktu
SBOB Jumlah
No PERSONIL Personil Keterlibatan
(Rp) (Rp.)
Orang (Bulan)
A TENAGA AHLI
1 Ahli Arsitek 1 1
2 Ahli Desain Interior 1 1
3 Ahli Mekanikal - Elektrikal 1 0.5
B TENAGA PENDUKUNG
1 Drafter 2 1
2 Surveyor 1 0.5
3 Estimator 1 0.5
Sub-Jumlah A
JUMLAH TOTAL I
A BIAYA
1 Alat Tulis Kantor + Tinta 1 1.0 ###
Sub-Jumlah A
B PELAPORAN
1 Laporan Pendahuluan 5 buku
2 Laporan Antara 5 buku
3 Gambar rencana teknis 5 buku
4 Laporan Akhir 1 buku
5 Softcopy dalam bentuk CD 5 buah
Sub-Jumlah B
JUMLAH TOTAL II
JUMLAH TOTAL I + II
PPn 10%
JUMLAH
; DIBULATKAN
Terbilang
Catatan : harga tersebut sudah termasuk PPn 10 % dan pajak-pajak lain yang berlaku
......................................
Direktur
NILAI PEKERJAAN
I. BIAYA LANGSUNG PERSONEL (REMUNERATION)
Jumlah
Waktu Keterlibatan Jumlah
No PERSONIL Personil SBOB (Rp)
(Bulan) (Rp.)
Orang
A TENAGA AHLI
1 Ahli Arsitek 1 1 17,000,000 17,000,000
2 Ahli Desain Interior 1 1 14,800,000 14,800,000
3 Ahli Mekanikal - Elektrikal 1 0.5 14,800,000 7,400,000
B TENAGA PENDUKUNG
1 Drafter 2 1 5,900,000 11,800,000
2 Surveyor 1 0.5 6,000,000 3,000,000
3 Estimator 1 0.5 5,900,000 2,950,000
Sub-Jumlah A 56,950,000
JUMLAH TOTAL I 56,950,000
A BIAYA
1 Alat Tulis Kantor + Tinta 1 1 3,450,000 3,450,000
Sub-Jumlah A 3,450,000
B PELAPORAN
1 Laporan Pendahuluan 5 buku 310,000 1,550,000
2 Laporan Antara 5 buku 410,000 2,050,000
3 Gambar rencana teknis 5 buku 560,000 2,800,000
4 Laporan Akhir 1 buku 475,000 475,000
5 Softcopy dalam bentuk CD 5 buah 50,000 250,000
Sub-Jumlah B 7,125,000
JUMLAH TOTAL II 10,575,000
JUMLAH TOTAL I + II 67,525,000
PPn 10% 6,752,500
JUMLAH 74,277,500
DIBULATKAN 74,184,000
Terbilang: Tujuh puluh empat juta seratus delapan puluh empat ribu rupiah
Catatan : harga tersebut sudah termasuk PPn 10 % dan pajak-pajak lain yang berlaku