Ukuran = 35 x 35 cm
Tulangan = 12 D13
Kait = 7 cm
Berat = panjang kolom x berat besi D13 x jumlah besi D13 x jumlah
kolom
4,39 x 12 x 3
= =13,17 ≈ 14 batang
12 m
Beugel K1 35 x 35 cm:
Kait = 4 cm
Beugel = Ø8-100
Selimut = 4 cm
As- 2
Ukuran = 35 x 35 cm
Tulangan = 12 D13
Kait = 7 cm
Berat = panjang kolom x berat besi D13 x jumlah besi D13 x jumlah
kolom
4,39 x 12 x 1
= =4,39 ≈ 5 batang
12 m
Beugel K1 35 x 35 cm:
Kait = 4 cm
Beugel = Ø8-100
Selimut = 4 cm
3,50
Jumlah beugel = =35 beugel x 1 kolom = 35 beugel
0,10
Kolom 30x30 cm
As- 1
Ukuran = 30 x 30 cm
Tulangan = 4 D13
Kait = 7 cm
Berat = panjang kolom x berat besi D13 x jumlah besi D13 x jumlah
kolom
3,24 x 4 x 1
= =1,08 ≈ 2 batang
12m
Ukuran = 30 x 30 cm
Tulangan = 4 Ø12
Kait = 6 cm
Berat = panjang kolom x berat besi Ø12 x jumlah besi Ø12 x jumlah
kolom
3,19 x 4 x 1
= =1,06 ≈ 2batang
12 m
Beugel K2 30 x 30 cm:
Kait = 4 cm
Beugel = Ø8-100
Selimut = 4 cm
2,35
Jumlah beugel = =23,5 ≈ 24 beugel + 1 x 1 kolom = 25 beugel
0,10
panjang 1beugel x jumlah beugel
Jumlah besi 12 m =
12
As- 2
Ukuran = 30 x 30 cm
Tulangan = 4 D13
Kait = 7 cm
Berat = panjang kolom x berat besi D13 x jumlah besi D13 x jumlah
kolom
3,24 x 4 x 1
= =1,08 ≈ 2 batang
12m
Ukuran = 30 x 30 cm
Tulangan = 4 Ø12
Kait = 6 cm
Berat = panjang kolom x berat besi Ø12 x jumlah besi Ø12 x jumlah
kolom
3,19 x 4 x 1
= =1,06 ≈ 2batang
12 m
Beugel K2 30 x 30 cm:
Kait = 4 cm
Beugel = Ø8-100
Selimut = 4 cm
2,35
Jumlah beugel = =23,5 ≈ 24 beugel + 1 x 1 kolom = 25 beugel
0,10
Ukuran = 35 x 35 cm
Tulangan = 12 D13
Kait = 7 cm
Berat = panjang kolom x berat besi D13 x jumlah besi D13 x jumlah
kolom
4,39 x 12 x 2
= =8,78 ≈ 9 batang
12 m
Beugel K1 35 x 35 cm:
Kait = 4 cm
Beugel = Ø8-100
Selimut = 4 cm
3,50
Jumlah beugel = =35 beugel x 2 kolom = 70 beugel
0,10
panjang 1beugel x jumlah beugel
Jumlah besi 12 m =
12
As- 9
Ukuran = 35 x 35 cm
Tulangan = 12 D13
Kait = 7 cm
Berat = panjang kolom x berat besi D13 x jumlah besi D13 x jumlah
kolom
4,39 x 12 x 3
= =13,17 ≈ 14 batang
12 m
Beugel K1 35 x 35 cm:
Kait = 4 cm
Beugel = Ø8-100
Selimut = 4 cm
3,50
Jumlah beugel = =35 beugel x 3 kolom = 105 beugel
0,10
Kolom 30x30 cm
As- 8
Ukuran = 30 x 30 cm
Tulangan = 4 D13
Kait = 7 cm
Berat = panjang kolom x berat besi D13 x jumlah besi D13 x jumlah
kolom
Ukuran = 30 x 30 cm
Tulangan = 4 Ø12
Kait = 6 cm
Berat = panjang kolom x berat besi Ø12 x jumlah besi Ø12 x jumlah
kolom
3,19 x 4 x 1
= =1,06 ≈ 2batang
12 m
Beugel K2 30 x 30 cm:
Kait = 4 cm
Beugel = Ø8-100
Selimut = 4 cm
2,35
Jumlah beugel = =23,5 ≈ 24 beugel + 1 x 1 kolom = 25 beugel
0,10
As- 9
Ukuran = 30 x 30 cm
Tulangan = 4 D13
Kait = 7 cm
Berat = panjang kolom x berat besi D13 x jumlah besi D13 x jumlah
kolom
3,24 x 4 x 1
= =1,08 ≈ 2 batang
12m
Ukuran = 30 x 30 cm
Tulangan = 4 Ø12
Kait = 6 cm
Panjang kolom = 2,65 + 0,48 + 0,06 = 3,19 m
Berat = panjang kolom x berat besi Ø12 x jumlah besi Ø12 x jumlah
kolom
3,19 x 4 x 1
= =1,06 ≈ 2batang
12 m
Beugel K2 30 x 30 cm:
Kait = 4 cm
Beugel = Ø8-100
Selimut = 4 cm
2,35
Jumlah beugel = =23,5 ≈ 24 beugel + 1 x 1 kolom = 25 beugel
0,10
21,28
Multiplek 12 mm = =7,14 ≈ 8 multiplek
2,44 ×1,22
6,36
Multiplek 12 mm = =2,13 ≈ 3 multiplek
2,44 ×1,22
Volume = P x L x T x Unit
= 0,30 x 0,30 x 2,65 x 2
= 0,477 M3
21,28
Multiplek 12 mm = =5,76 ≈ 6 multiplek
2,44 ×1,22
6,36
Multiplek 12 mm = =2,13 ≈ 3 multiplek
2,44 ×1,22
Volume = P x L x T x Unit
= 0,35 x 0,35 x 3,80 x 3
= 1,3965 M3
Volume = P x L x T x Unit
= 0,30 x 0,30 x 2,65 x 1
= 0,2385 M3
7. Jum’at, 23 juli 2021
a. Pemasangan bekisting kolom lantai 2
Bekisting Kolom K1 35x35 cm
As- 5&6
Ukuran multiplek = P = 2,44 m, L = 1,22 m
10,64
Multiplek 12 mm = =3,57 ≈ 4 multiplek
2,44 ×1,22
6,36
Multiplek 12 mm = =2,13 ≈ 3 multiplek
2,44 ×1,22
Volume = P x L x T x Unit
= 0,35 x 0,35 x 3,80 x 4
= 1,862 m3
15,966
Multiplek 12 mm = =5,36 multiplek
2,44 ×1,22
6,36
Multiplek 12 mm = =2,13 ≈ 3 multiplek
2,44 ×1,22
= 0,06 x 21 = 1,26 m³
8,4
Multiplek 12 mm = =2 , 82≈ 3 multiplek
2,44 ×1,22
As- A’& D’
Ukuran multiplek = P = 2,44 m, L = 1,22 m
= 0,06 x 21 = 1,08 m³
7,2
Multiplek 12 mm = =2 , 41 ≈ 3 multiplek
2,44 ×1,22
As- 1&3
Ukuran multiplek = P = 2,44 m, L = 1,22 m
= 0,06 x 4 = 0,24 m³
1,6
Multiplek 12 mm = =0,53 ≈ 1 multiplek
2,44 ×1,22
Panjang Balok = 41 m
41 x 6
¿ = 20,5
12 m
Panjang = 3,50
Lebar = 0,20
Tinggi = 0,30
Unit = 8,00
Volume = P x L x T x Unit
Panjang = 3,00
Lebar = 0,20
Tinggi = 0,30
Unit = 9,00
Volume = P x L x T x Unit
As- 1’ & 3’
Panjang = 2,00
Lebar = 0,20
Tinggi = 0,30
Unit = 2,00
Volume = P x L x T x Unit
= 0,06 x 14 = 0,84 m³
5,6
Multiplek 12 mm = =1,88 ≈ 2 multiplek
2,44 ×1,22
= 0,06 x 4= 0,24 m³
1 ,6
Multiplek 12 mm = =0,53 ≈ 1 multiplek
2,44 ×1,22
As- A, C & D
Ukuran multiplek = P = 2,44 m, L = 1,22 m
= 0,06 x 9 = 0,54 m³
3,6
Multiplek 12 mm = =1,20 ≈ 2 multiplek
2,44 ×1,22
Panjang = 3,00
Lebar = 0,20
Tinggi = 0,30
Unit = 12,00
Volume = P x L x T x Unit
As- 6, 9 & 10
Panjang = 3,50
Lebar = 0,20
Tinggi = 0,30
Unit = 6,00
Volume = P x L x T x Unit
Panjang = 2,00
Lebar = 0,20
Tinggi = 0,30
Unit = 3,00
Volume = P x L x T x Unit
= 0,36 m3