DAFTAR HARGA SATUAN BAHAN BANGUNAN

NO MATERIAL SAT HARGA (Rp)

A. AGRE
AGREGA
GAT
T KAS
KASAR
AR,B
,BAH
AHAN
AN PERE
PEREKA
KAT
T & BAHA
BAHAN
N JJAD
ADIN
INYA
YA

1 Pasir Urug m3 110,000.00


2 Tanah Urug Pilihan m3 57,857.14
3 Pasir Pasang Kali m3 220,000.00
4 Pasir Beton m3 225,000.00
5 Batu Pecah Mesin 1/2 m3 227,000.00
6 Batu Pecah Mesin 2/3 m3 230,000.00
7 Batu Belah Pondasi m3 150,000.00
8 Batu Koral Beton Kali m3 170,000.00
9 Batako Kecil 8 x 10 x 20 bh 2,000.00
10 Batako Besar 8 x 20 x 30 bh 2,400.00
11 Con Blok 8 x 20 x 40 bh 5,400.00
12 Bata Merah Bakar kelas I bh 700.00
13 Bata Merah Bakar kelas II bh 600.00
14 Semen PC /50 kg zak 64,000.00
Semen PC /50 kg kg 1,280.00

15 Semen Putih zak 92,700.00


16 Semen Warna kg 12,500.00

B LABU
LABURA
RAN,
N,PE
PENG
NGIS
ISII DAN
DAN ALAT
ALATNY
NYA
A
1 Pl
P lamir Tembok kg 18,000.00
2 Cat Tembok ICI Eksterior ( Beton ) lt 90,000.00
3 Cat Tembok ICI Interior ( Plafon Dan Dinding ) lt 75,000.00
4 Cat Tembok Vinilex kg 18,000.00
5 Cat Dasar kg 25,000.00
6 Pelapis Alkali ICI ( Cat Dasar Beton Ekterior ) kg 90,000.00
7 Water Profing Emulsion ml 70,000.00
8 Water Profing Membrance bh 62,500.00
9 Rool Cat Tembok bh 25,000.00
10 Kape Tembok bh 8,500.00
11 Kwas 3" bh 8,000.00
12 Me
Meni Kayu / Besi kg 30,400.00
13 Sincromat kg 40,900.00
14 Cat Kayu Sieve lt 41,700.00

C BAHA
BAHAN
N KAY
KAYU
U BERI
BERIKU
KUT
T BAH
BAHAN
AN JADI
JADINY
NYA
A
1 Ba
Bambu 5 s.d 7 bt 10,000.00
2 Kayu Balok Albasia m3 1,650,000.00
3 Kayu Papan Albasia m3 1,750,000.00
4 Do
Dolken 5 s/d 7 bt 14,000.00
5 Do
D olken 7 s/d 10 bt 17,000.00
6 Kayu Kaso 4/6 m3 1,872,000.00
7 Kayu Kaso 5/7 m3 1,890,000.00
8 Kayu Papan Terentang m3 2,000,000.00
9 Kayu Balok Terentang m3 1,900,000.00
DAFTAR HARGA SATUAN BAHAN BANGUNAN

NO MATERIAL SAT HARGA (Rp)

D BAHAN PENUTUP RANGKA PLAFOND


1 Gypsum 120 x 240 t= 9 mm ex DN lbr 55,000.00
2 Cotton Plester bh 15,000.00
3 GRC (120 x 240) cm, t = 4 mm lbr 45,000.00
4 Cornice Coumpound zak 75,000.00
5 List gypsum m' 8,000.00

E BAHAN KAYU LAPIS


1 Triplek 4 mm 120 x 240 lbr 50,000.00
2 Triplek 9 mm 120 x 240 lbr 105,000.00
3 MultiPlek 9 mm 120 x 240 lbr 110,000.00
4 MultiPlek 12 mm 120 x 240 lbr 132,000.00

F BAHA
BAHAN
N LAN
LANTA
TAII DAN
DAN PELA
PELAPI
PIS
S DIND
DINDIN
ING
G
1 Keramik 20 x 20 (KM) KW I DN Corak/Warna /Anti Slip Mulia m2 48,000.00
2 Keramik 20 x 20 (KM) KW I DN Putih Polos Mulia m2 42,000.00
3 Keramik 20 x 25 Dinding KM KW I DN Corak Mulia m2 48,000.00
4 Keramik 30 x 30 KWI DN Putih Polos Mulia m2 40,000.00
5 Keramik 30 x 30 KWI DN Warna/Corak (ANTI SLIP) Mulia m2 48,000.00
6 Keramik 40 x 40 KWI DN Putih Polos Mulia m2 52,000.00
7 Keramik 40 x 40 KWI DN Warna/Corak (ANTI SLIP) Mulia m2 58,000.00
8 Keramik 20 x 20 (KM) KW I DN Corak/Warna/Anti Slip Roman m2 75,200.00
9 Keramik 20 x 20 (KM) KW I DN Putih Polos Roman m2 72,900.00
10 Keramik 20 x 25 Dinding KM KW I DN Corak Roman m2 75,200.00
11 Keramik 20 x 25 KW I DN Putih Polos Roman m2 72,900.00
12 Keramik 30 x 30 KW I DN Polos Roman m2 68,900.00
13 Keramik 30 x 30 KW I DN Warna/Corak (ANTI SLIP) Roman m2 76,600.00
Keramik 40 x 40 KW I DN Polos setara MULIA m2 58,000.00
Keramik 40 x 40 KW I DN Warna/Corak (ANTI SLIP) setara MULIA m2 65,000.00
14 Keramik 40 x 40 KW I DN Polos Roman m2 72,500.00
15 Keramik 40 x 40 KW I DN Warna/Corak (ANTI SLIP) Roman m2 77,000.00
16 Granit Alam LN Ukuran Besar m2 1,848,400.00
17 Granit Alam LN Ukuran Kecil m2 1,612,900.00
18 Granit Alam DN Ukuran Besar m2 1,331,100.00
19 Granit Alam DN Ukuran Kecil m2 1,299,400.00
20 Granito Tile Essenza Ukuran 40 x 40 Polis m2 345,000.00
21 Granito Tile Essenza Ukuran 30 x 30 m2 322,800.00
22 Granito Tile Essenza Ukuran 40 x 40 UnPolis m2 204,900.00
23 Granito Tile Essenza 60 x 60 Polis m2 358,100.00
24 Granito Tile Essenza 60 x 60 UnPolis m2 231,800.00
25 Batu Tempel Hitam m2 96,500.00

G BAHA
BAHAN
N SAL
SALUR
URAN
AN AIR
AIR KOT
KOTOR
OR / BER
BERSI
SIH
H
1 Grafel U 20 cm' m1 44,300.00
2 Grafel U 30 cm' m1 56,400.00
3 Grafel U 40 cm' m1 74,200.00
4 Buis Beton 20 cm ( 1 M' ) m1 49,200.00
5 Buis Beton 30 cm ( 1 M' ) m1 61,700.00
6 Buis Beton 40 cm ( 1 M' ) m1 80,900.00
7 Buis Beton 50 cm ( 1 M' ) stk 94,300.00
8 Buis Beton 60 cm ( 1 M' ) stk 130,900.00
9 Buis Beton 100 cm ( 0.50 M' ) stk 299,800.00
10 Buis Beton 80 cm ( 0.50 M' ) stk 298,500.00
DAFTAR HARGA SATUAN BAHAN BANGUNAN

NO MATERIAL SAT HARGA (Rp)

H BAHAN LOGAM DAN BAHAN JADINYA


1 Besi Beton U-24 Rata-rata kg 10,000.00
2 Besi Beton U-39 / U-32 Rata-rata kg 10,000.00
3 Kawat Beton kg 18,000.00
4 Wiremesh M8 m2 51,900.00
5 Wiremesh M6 m2 37,000.00

J BAHAN PAKU DAN MUR BAUT


1 Paku 1/2" s/d 2" kg 20,000.00
2 Paku 2" s/d 5" kg 15,000.00
3 Paku 8 cm s/d 15 cm kg 15,000.00

K BAHAN PERPIPAAN

M BAHAN PENUTUP ATAP


1 Genteng Keramik Natural Intan 14.5 / m2 m2 112,400.00
2 Genteng Keramik Glasur Standard 14.5 /m2 m2 142,200.00
3 Genteng Keramik Glasur Special 14.5 /m2 m2 139,300.00
4 Genteng Keramik Glasur Premium 14.5 /m2 m2 145,100.00
5 Genteng Murando Natural 1m2 = 18 bh bh 2,700.00
6 Genteng Murando Glasur 1m2 = 18 bh bh 4,000.00
7 Bubung Murando Natural bh 7,500.00
8 Bubung Murando Glasur bh 10,700.00
9 Bubungan Genteng Keramik bh 10,000.00
A. ANALISA HARGA SATUAN PEKERJAAN PERSIAPAN

A-04 1 M2 Pengukuran Dan Pasang Bouwplank


- Kayu kaso 5/7 M3   0.0120   1,650,000.00 19,800.00
- Paku Biasa 2" - 5" Kg   0.0200   15,000.00 300.00
- Kayu papan albasia M3   0.0070   1,750,000.00 12,250.00
- Pekerja Oh   0.1000   50,000.00 5,000.00
- Tukang Kayu Oh   0.1000   60,000.00 6,000.00
- Kepala Tukang Oh   0.0100   70,000.00 700.00
- Mandor Oh   0.0050   75,000.00 375.00
Jumlah 44,425.00
Dibulatkan 44,425.00

B. ANALISA HARGA SATUAN PEKERJAAN TANAH

No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA


(Rp) (Rp)
B-01 1 M3 Galian Tanah Biasa sedalam 1 m
- Pekerja Oh   0.4000   50,000.00 20,000.00
- Mandor Oh   0.0400   75,000.00 3,000.00
Jumlah 23,000.00
Dibulatkan 23,000.00
B-02 1 M3 Galian Tanah Biasa Sedalam 2 m
- Pekerja Oh   0.5260   50,000.00 26,300.00
- Mandor Oh   0.0520   75,000.00 3,900.00
Jumlah 30,200.00
Dibulatkan 30,200.00
B-08 1 M3 Urugan Kembali
- Pekerja Oh   0.1920   50,000.00 9,600.00
- Mandor Oh   0.0190   75,000.00 1,425.00
Jumlah 11,025.00
Dibulatkan 11,025.00
B-10 1 M3 Urugaan Pasir
- Pasir Urug M3   1.2000   110,000.00 132,000.00
- Pekerja Oh   0.3000   50,000.00 15,000.00
- Mandor Oh   0.0100   75,000.00 750.00
Jumlah 147,750.00
Dibulatkan 147,750.00
B-13 1 M3 Urugan Tanah Pilihan
- Tanah urug pilihan M3   1.2000   57,857.14 69,428.57
- Pekerja Oh   0.2500   50,000.00 12,500.00
- Mandor Oh   0.0250   75,000.00 1,875.00
Jumlah 83,803.57
Dibulatkan 83,804.00
C. ANALISA HARGA SATUAN PEKERJAAN PONDASI

C-03 1 M3 Pasang Pondasi Batu kali adk 1pc : 5ps


- Batu Belah M3   1.1000   150,000.00 165,000.00
- Semen Portland Kg   136.0000   1,280.00 174,080.00
- Pasir Pasang M3   0.5440   220,000.00 119,680.00
- Pekerja Oh   1.5000   50,000.00 75,000.00
- Tukang Batu Oh   0.6000   60,000.00 36,000.00
- Kepala Tukang Oh   0.0600   70,000.00 4,200.00
- Mandor Oh   0.0750   75,000.00 5,625.00
Jumlah 579,585.00
Dibulatkan 579,585.00
C-04 1 M3 Pasang Pondasi Batu Kosong (aanstamping)
- Batu Belah M3   1.2000   150,000.00 180,000.00
- Pasir Urug M3   0.3000   110,000.00 33,000.00
- Pekerja Oh   0.7800   50,000.00 39,000.00
- Tukang Batu Oh   0.3900   60,000.00 23,400.00
- Kepala Tukang Oh   0.0390   70,000.00 2,730.00
- Mandor Oh   0.0390   75,000.00 2,925.00
Jumlah 281,055.00
Dibulatkan 281,055.00

D. ANALISA HARGA SATUAN PEKERJAAN BETON

No. URAIAN SATUAN VOLUME HARGA SATUAN HARGA


(Rp) (Rp)
D-01 1 M3 Membuat Beton Tumbuk adk 1pc:3ps:5kr
- Semen Portland Kg   218.0000   1,280.00 279,040.00
- Pasir Beton M3   0.5200   225,000.00 117,000.00
- Batu Pecah Mesin 2/3 M3   0.8700   230,000.00 200,100.00
- Pekerja Oh   1.6500   50,000.00 82,500.00
- Tukang Batu Oh   0.2500   60,000.00 15,000.00
- Kepala Tukang Oh   0.0250   70,000.00 1,750.00
- Mandor Oh   0.0800   75,000.00 6,000.00
Jumlah 701,390.00
Dibulatkan 701,390.00
D-02 1 M3 Membuat Beton Tumbuk adk 1pc:3ps:6kr
- Semen Portland Kg   197.0000   1,280.00 252,160.00
- Pasir Beton M3   0.4700   225,000.00 105,750.00
- Batu Pecah Mesin 2/3 M3   0.9400   230,000.00 216,200.00
- Pekerja Oh   1.6500   50,000.00 82,500.00
- Tukang Batu Oh   0.2500   60,000.00 15,000.00
- Kepala Tukang Oh   0.0250   70,000.00 1,750.00
- Mandor Oh   0.0800   75,000.00 6,000.00
Jumlah 679,360.00
Dibulatkan 679,360.00
D-03 1 M3 Membuat Beton Tumbuk 1pc:2ps:3kr
- Semen Portland Kg   336.0000   1,280.00 430,080.00
- Pasir Beton M3   0.5400   225,000.00 121,500.00
- Batu Pecah Mesin 2/3 M3   0.8100   230,000.00 186,300.00
- Pekerja Oh   2.0000   50,000.00 100,000.00
- Tukang Batu Oh   0.3500   60,000.00 21,000.00
- Kepala Tukang Oh   0.0350   70,000.00 2,450.00
- Mandor Oh   1.0000   75,000.00 75,000.00
Jumlah 936,330.00
Dibulatkan 936,330.00
D-07 1 Kg Pembesian Dengan Besi Polos/ulir
- Besi Beton ( Polos / Ulir ) Kg   1.0500   10,000.00 10,500.00
- Kawat Beton Kg   0.0150   18,000.00 270.00
- Pekerja Oh   0.0070   50,000.00 350.00
- Tukang Besi Oh   0.0070   60,000.00 420.00
- Kepala Tukang Oh   0.0007   70,000.00 49.00
- Mandor Oh   0.0003   75,000.00 22.50
Jumlah 11,611.50
Dibulatkan 11,612.00
D-08 1 M2 Pasang Bekesting Untuk Pondasi
- Kayu papan terentang M3   0.0400   2,000,000.00 80,000.00
- Paku Biasa 2" - 5" Kg   0.3000   18,000.00 5,400.00
- Minyak Bekisting Ltr 55,000.00 -
- Pekerja Oh   0.3000   50,000.00 15,000.00
- Tukang Kayu Oh   0.2600   60,000.00 15,600.00
- Kepala Tukang Oh   0.0260   70,000.00 1,820.00
- Mandor Oh   0.0050   75,000.00 375.00
Jumlah 118,195.00
Dibulatkan 118,195.00
D-09 1 M2 Pasang Bekisting Untuk Sloof 
- Kayu papan terentang M3   0.0450   2,000,000.00 90,000.00
- Paku Biasa 2" - 5" Kg   0.3000   18,000.00 5,400.00
- Minyak Bekisting Ltr 55,000.00 -
- Pekerja Oh   0.3000   50,000.00 15,000.00
- Tukang Kayu Oh   0.2600   60,000.00 15,600.00
- Kepala Tukang Oh   0.0260   70,000.00 1,820.00
- Mandor Oh   0.0050   75,000.00 375.00
Jumlah 128,195.00
Dibulatkan 128,195.00
D-10 1 M2 Pasang Bekesting Untuk Kolom
- Kayu papan terentang M3   0.0400   2,000,000.00 80,000.00
- Paku Biasa 2" - 5" Kg   0.4000   18,000.00 7,200.00
- Minyak Bekisting Ltr 55,000.00 -
- Kayu balok terentang M3   0.0150   1,900,000.00 28,500.00
- MultiPlek 9 mm 120 x 240 Lbr   0.3500   110,000.00 38,500.00
- Dolken Ø-8-10/4m Btg   2.0000   17,000.00 34,000.00
- Pekerja Oh   0.3000   50,000.00 15,000.00
- Tukang Kayu Oh   0.3300   60,000.00 19,800.00
- Kepala Tukang Oh   0.0330   70,000.00 2,310.00
- Mandor Oh   0.0060   75,000.00 450.00
Jumlah 225,760.00
Dibulatkan 225,760.00
D-11 1 M2 Pasang Bekesting Untuk Balok
- Kayu papan terentang M3   0.0400   2,000,000.00 80,000.00
- Paku Biasa 2" - 5" Kg   0.4000   18,000.00 7,200.00
- Minyak Bekisting Ltr 55,000.00 -
- Kayu balok terentang M3   0.0180   1,900,000.00 34,200.00
- Multyplek 9 mm Lbr   0.3500   110,000.00 38,500.00
- Dolken Ø-8-10/4m Btg   2.0000   17,000.00 34,000.00
- Pekerja Oh   0.3000   50,000.00 15,000.00
- Tukang Kayu Oh   0.3300   60,000.00 19,800.00
- Kepala Tukang Oh   0.0330   70,000.00 2,310.00
- Mandor Oh   0.0060   75,000.00 450.00
Jumlah 231,460.00
Dibulatkan 231,460.00
D-12 1 M2 Pasang Bekesting Untuk Lantai
- Kayu papan terentang M3   0.0400   2,000,000.00 80,000.00
- Paku Biasa 2" - 5" Kg   0.4000   18,000.00 7,200.00
- Minyak Bekisting Ltr   0.2000   55,000.00 11,000.00
- Kayu balok terentang M3   0.0150   1,900,000.00 28,500.00
- Multyplek 9 mm Lbr   0.3500   110,000.00 38,500.00
- Dolken Ø-8-10/4m Btg   6.0000   17,000.00 102,000.00
- Pekerja Oh   0.3000   50,000.00 15,000.00
- Tukang Kayu Oh   0.3300   60,000.00 19,800.00
- Kepala Tukang Oh   0.0330   70,000.00 2,310.00
- Mandor Oh   0.0060   75,000.00 450.00
Jumlah 304,760.00
Dibulatkan 304,760.00
D-13 1 M2 Pasang Bekesting Untuk Tangga
- Kayu papan terentang M3   0.0300   2,000,000.00 60,000.00
- Paku Biasa 2" - 5" Kg   0.4000   18,000.00 7,200.00
- Minyak Bekisting Ltr   0.1500   55,000.00 8,250.00
- Kayu balok terentang M3   0.0150   1,900,000.00 28,500.00
- Multyplek 9 mm Lbr   0.3500   110,000.00 38,500.00
- Dolken Ø-8-10/4m Btg   2.0000   17,000.00 34,000.00
- Pekerja Oh   0.3200   50,000.00 16,000.00
- Tukang Kayu Oh   0.3300   60,000.00 19,800.00
- Kepala Tukang Oh   0.0330   70,000.00 2,310.00
- Mandor Oh   0.0060   75,000.00 450.00
Jumlah 215,010.00
Dibulatkan 215,010.00
D-14 1 M3 Membuat Beton Cor Mutu K-225
- Semen Portland Kg   388.0000   1,280.00 496,640.00
- Pasir Beton m3   0.6500   225,000.00 146,250.00
- Koral Beton 2/3 M3   0.6500   230,000.00 149,500.00
- Air ltr   215.0000   3.00 645.00
- Pekerja Oh   6.0000   50,000.00 300,000.00
- Tukang Batu Oh   1.0000   60,000.00 60,000.00
- Kepala Tukang Oh   0.1000   70,000.00 7,000.00
- Mandor Oh   0.3000   75,000.00 22,500.00
Jumlah 1,182,535.00
Dibulatkan 1,182,535.00
D-42 1 M3 Membuat Beton Cor Mutu K-200
- Semen Portland Kg   352.0000   1,280.00 450,560.00
- Pasir Beton M3   0.4569   225,000.00 102,796.88
- Koral Beton 2/3 M3   0.6873   230,000.00 158,086.67
- Pekerja Oh   1.6500   50,000.00 82,500.00
- Tukang Batu Oh   0.2750   60,000.00 16,500.00
- Kepala Tukang Oh   0.0280   70,000.00 1,960.00
- Mandor Oh   0.0830   75,000.00 6,225.00
Jumlah 818,628.54
Dibulatkan 818,629.00
D-43 1 M3 Membuat Beton Cor Mutu K-250
- Semen Portland Kg   384.0000   1,280.00 491,520.00
- Pasir Beton M3   0.4325   225,000.00 97,312.50
- Koral Beton 2/3 M3   0.6927   230,000.00 159,313.33
- Pekerja Oh   1.6500   50,000.00 82,500.00
- Tukang Batu Oh   0.2750   60,000.00 16,500.00
- Kepala Tukang Oh   0.0280   70,000.00 1,960.00
- Mandor Oh   0.0830   75,000.00 6,225.00
Jumlah 855,330.83
Dibulatkan 855,331.00
D-15 1 M3 Membuat Beton Cor Mutu K-275
- Semen Portland Kg   400.0000   1,280.00 512,000.00
- Pasir Beton M3   0.4000   225,000.00 90,000.00
- Koral Beton 2/3 M3   0.8200   230,000.00 188,600.00
- Air ltr   215.0000   3.00 645.00
- Pekerja Oh   6.0000   50,000.00 300,000.00
- Tukang Batu Oh   1.0000   60,000.00 60,000.00
- Kepala Tukang Oh   0.1000   70,000.00 7,000.00
- Mandor Oh   0.3000   75,000.00 22,500.00
Jumlah 1,180,745.00
Dibulatkan 1,180,745.00
D-16 1 M3 Pondasi Beton Tulang (150 kg besi + bekisting)
- Kayu papan terentang M3   0.2000   2,000,000.00 400,000.00
- Paku Biasa 2" - 5" Kg   1.5000   18,000.00 27,000.00
- Minyak Bekisting Ltr 55,000.00 -
- Besi Beton Kg   150.0000   11,612.00 1,741,800.00
- Kawat Beton Kg   2.2500   18,000.00 40,500.00
- Semen Portland Kg   323.0000   1,280.00 413,440.00
- Pasir Beton M3   0.5200   225,000.00 117,000.00
- Koral Beton 2/3 M3   0.7800   230,000.00 179,400.00
- Pekerja Oh   3.9000   50,000.00 195,000.00
- Tukang Batu Oh   0.3500   60,000.00 21,000.00
- Tukang Kayu Oh   1.0400   60,000.00 62,400.00
- Tukang Besi Oh   1.0500   60,000.00 63,000.00
- Kepala Tukang Oh   0.2450   70,000.00 17,150.00
- Mandor Oh   0.1650   75,000.00 12,375.00
Jumlah 3,290,065.00
Dibulatkan 3,290,065.00
1 M3 Sloof Beton Tulang 20/40 (240 kg besi + bekisting) Struktur bertingkat
- Kayu papan terentang M3   0.2700   2,000,000.00 540,000.00
- Paku Biasa 2" - 5" Kg   2.0000   18,000.00 36,000.00
- Minyak Bekisting Ltr   0.6000   55,000.00 33,000.00
- Besi Beton Kg   240.0000   11,612.00 2,786,880.00
- Kawat Beton Kg   3.0000   18,000.00 54,000.00
- Semen Portland Kg   323.0000   1,280.00 413,440.00
- Pasir Beton M3   0.5200   225,000.00 117,000.00
- Koral Beton 2/3 M3   0.7800   230,000.00 179,400.00
- Pekerja Oh   4.8500   50,000.00 242,500.00
- Tukang Batu Oh   0.3500   60,000.00 21,000.00
- Tukang Kayu Oh   1.5600   60,000.00 93,600.00
- Tukang Besi Oh   1.4000   60,000.00 84,000.00
- Kepala Tukang Oh   0.3310   70,000.00 23,170.00
- Mandor Oh   0.1700   75,000.00 12,750.00
Jumlah 4,636,740.00
Dibulatkan 4,636,740.00
1 M3 Kolom Beton Tulang 30/30 (175 kg besi + bekisting) Struktur bertingkat 8dia.16, 8-15
- Kayu papan terentang M3   0.4000   2,000,000.00 800,000.00
- Paku Biasa 2" - 5" Kg   4.0000   15,000.00 60,000.00
- Minyak Bekisting Ltr 55,000.00 -
- Besi Beton Kg   175.0000   11,612.00 2,032,100.00
- Kawat Beton Kg   1.8000   18,000.00 32,400.00
- Semen Portland Kg   323.0000   1,280.00 413,440.00
- Pasir Beton M3   0.5200   225,000.00 117,000.00
- Koral Beton 2/3 M3   0.7800   230,000.00 179,400.00
- Kayu Balok Terentang M3   0.1500   1,900,000.00 285,000.00
- Multyplek 9 mm Lbr   3.5000   110,000.00 385,000.00
- Dolken Ø-8-10/4m Btg   20.0000   17,000.00 340,000.00
- Pekerja Oh   7.3000   50,000.00 365,000.00
- Tukang Batu Oh   0.3500   60,000.00 21,000.00
- Tukang Kayu Oh   3.3000   60,000.00 198,000.00
- Tukang Besi Oh   2.1000   60,000.00 126,000.00
- Kepala Tukang Oh   0.5700   70,000.00 39,900.00
- Mandor Oh   0.2500   75,000.00 18,750.00
Jumlah 5,412,990.00
Dibulatkan 5,412,990.00
1 M3 Kolom Beton Tulang Praktis 12/12 (175 kg besi + bekisting)
- Kayu papan terentang M3   0.4000   2,000,000.00 800,000.00
- Paku Biasa 2" - 5" Kg   4.0000   15,000.00 60,000.00
- Minyak Bekisting Ltr 55,000.00 -
- Besi Beton Kg   175.0000   11,612.00 2,032,100.00
- Kawat Beton Kg   1.8000   18,000.00 32,400.00
- Semen Portland Kg   323.0000   1,280.00 413,440.00
- Pasir Beton M3   0.5200   225,000.00 117,000.00
- Koral Beton 2/3 M3   0.7800   230,000.00 179,400.00
- Kayu Balok Terentang M3 1,900,000.00 -
- Multyplek 9 mm Lbr 110,000.00 -
- Dolken Ø-8-10/4m Btg   20.0000   17,000.00 340,000.00
- Pekerja Oh   7.3000   50,000.00 365,000.00
- Tukang Batu Oh   0.3500   60,000.00 21,000.00
- Tukang Kayu Oh   3.3000   60,000.00 198,000.00
- Tukang Besi Oh   2.1000   60,000.00 126,000.00
- Kepala Tukang Oh   0.5700   70,000.00 39,900.00
- Mandor Oh   0.2500   75,000.00 18,750.00
Jumlah 4,742,990.00
Dibulatkan 4,742,990.00
1 M3 Balok Beton Tulang 25/55 (140 kg besi + bekisting) Struktur bertingkat 8dia.16 +2dia.12, 8-15
- Kayu papan terentang M3   0.3200   2,000,000.00 640,000.00
- Paku Biasa 2" - 5" Kg   3.2000   15,000.00 48,000.00
- Minyak Bekisting Ltr 55,000.00 -
- Besi Beton Kg   140.0000   11,612.00 1,625,680.00
- Kawat Beton Kg   3.0000   18,000.00 54,000.00
- Semen Portland Kg   323.0000   1,280.00 413,440.00
- Pasir Beton M3   0.5200   225,000.00 117,000.00
- Koral Beton 2/3 M3   0.7800   230,000.00 179,400.00
- Kayu Balok Terentang M3   0.1400   1,900,000.00 266,000.00
- Multyplek 9 mm Lbr   2.8000   110,000.00 308,000.00
- Dolken Ø-8-10/4m Btg   16.0000   17,000.00 272,000.00
- Pekerja Oh   5.9600   50,000.00 298,000.00
- Tukang Batu Oh   0.3500   60,000.00 21,000.00
- Tukang Kayu Oh   2.8000   60,000.00 168,000.00
- Tukang Besi Oh   1.4000   60,000.00 84,000.00
- Kepala Tukang Oh   0.4550   70,000.00 31,850.00
- Mandor Oh   0.2080   75,000.00 15,600.00
Jumlah 4,541,970.00
Dibulatkan 4,541,970.00
1 M3 Balok Beton Tulang 20/30 (200 kg besi + bekisting) Struktur bertingkat 6dia. 16, 8-15
- Kayu papan terentang M3   0.3200   2,000,000.00 640,000.00
- Paku Biasa 2" - 5" Kg   3.2000   15,000.00 48,000.00
- Minyak Bekisting Ltr 55,000.00 -
- Besi Beton Kg   200.0000   11,612.00 2,322,400.00
- Kawat Beton Kg   3.0000   18,000.00 54,000.00
- Semen Portland Kg   323.0000   1,280.00 413,440.00
- Pasir Beton M3   0.5200   225,000.00 117,000.00
- Koral Beton 2/3 M3   0.7800   230,000.00 179,400.00
- Kayu Balok Terentang M3   0.1400   1,900,000.00 266,000.00
- Multyplek 9 mm Lbr   2.8000   110,000.00 308,000.00
- Dolken Ø-8-10/4m Btg   16.0000   17,000.00 272,000.00
- Pekerja Oh   5.9600   50,000.00 298,000.00
- Tukang Batu Oh   0.3500   60,000.00 21,000.00
- Tukang Kayu Oh   2.8000   60,000.00 168,000.00
- Tukang Besi Oh   1.4000   60,000.00 84,000.00
- Kepala Tukang Oh   0.4550   70,000.00 31,850.00
- Mandor Oh   0.2080   75,000.00 15,600.00
Jumlah 5,238,690.00
Dibulatkan 5,238,690.00
1 M3 Balok Beton Lintel 11/11 (300 kg besi + bekisting) 4dia.10 8-15
- Kayu papan terentang M3   0.4000   2,000,000.00 800,000.00
- Paku Biasa 2" - 5" Kg   4.0000   15,000.00 60,000.00
- Minyak Bekisting Ltr 55,000.00 -
- Besi Beton Kg   300.0000   11,612.00 3,483,600.00
- Kawat Beton Kg   1.8000   18,000.00 32,400.00
- Semen Portland Kg   323.0000   1,280.00 413,440.00
- Pasir Beton M3   0.5200   225,000.00 117,000.00
- Koral Beton 2/3 M3   0.7800   230,000.00 179,400.00
- Kayu Balok Terentang M3 1,900,000.00 -
- Multyplek 9 mm Lbr 110,000.00 -
- Dolken Ø-8-10/4m Btg   20.0000   17,000.00 340,000.00
- Pekerja Oh   7.3000   50,000.00 365,000.00
- Tukang Batu Oh   0.3500   60,000.00 21,000.00
- Tukang Kayu Oh   3.3000   60,000.00 198,000.00
- Tukang Besi Oh   2.1000   60,000.00 126,000.00
- Kepala Tukang Oh   0.5700   70,000.00 39,900.00
- Mandor Oh   0.2500   75,000.00 18,750.00
Jumlah 6,194,490.00
Dibulatkan 6,194,490.00
D-29 1 M3 Tangga Beton Tulang (200 kg besi + bekisting)
- Kayu papan terentang M3   0.2500   2,000,000.00 500,000.00
- Paku Biasa 2" - 5" Kg   3.0000   15,000.00 45,000.00
- Minyak Bekisting Ltr   1.2000   55,000.00 66,000.00
- Besi Beton Kg   200.0000   11,612.00 2,322,400.00
- Kawat Beton Kg   3.0000   18,000.00 54,000.00
- Semen Portland Kg   323.0000   1,280.00 413,440.00
- Pasir Beton M3   0.5200   225,000.00 117,000.00
- Koral Beton 2/3 M3   0.7800   230,000.00 179,400.00
- Kayu Balok Terentang M3   0.1050   1,900,000.00 199,500.00
- Multyplek 9 mm Lbr   2.5000   110,000.00 275,000.00
- Dolken Ø-8-10/4m Btg   14.0000   17,000.00 238,000.00
- Pekerja Oh   5.6000   50,000.00 280,000.00
- Tukang Batu Oh   0.3500   60,000.00 21,000.00
- Tukang Kayu Oh   2.3000   60,000.00 138,000.00
- Tukang Besi Oh   1.4000   60,000.00 84,000.00
- Kepala Tukang Oh   0.4050   70,000.00 28,350.00
- Mandor Oh   0.2020   75,000.00 15,150.00
Jumlah 4,976,240.00
Dibulatkan 4,976,240.00
D-31 1 M3 Pelat Lantai Beton Tulang T= 12 cm (110 kg besi + bekisting) dia.8-12,5
- Beton bertulang ad. 1Pc : 2Ps : 3Kr M3   1.0000   855,331.00 855,331.00
- Floor Deck / Bondek M2   9.1667   149,500.00 1,370,416.67
- Wire Mesh M-8 M2   9.1667   51,587.30 472,883.60
- Alat Bantu ls   1.0000   5,000.00 5,000.00
Jumlah 2,703,631.26
Dibulatkan 2,703,631.00
1 M3 Pelat Lantai Beton Tulang T= 12 cm (130 kg besi + bekisting) dia.10-20
- Beton bertulang ad. 1Pc : 2Ps : 3Kr M3   1.0000   855,331.00 855,331.00
- Pasang Bekisting untuk lantai M2   8.3300   149,500.00 1,245,335.00
- Besi Beton Polos Kg   130.0000   5,000.00 650,000.00
Jumlah 2,750,666.00
Dibulatkan 2,750,666.00
D-30 1 M3 Pelat Lantai Beton Tulang T= 10 cm (90 kg besi + bekisting)
- Beton tulang ad. 1Pc : 2Ps : 3Kr M3   1.0000   855,331.00 855,331.00
- Pasang Bekisting untuk lantai M2   10.0000   149,500.00 1,495,000.00
- Besi Beton Polos Kg   90.0000   5,000.00 450,000.00
Jumlah 2,800,331.00
Dibulatkan 2,800,331.00
E. ANALISA HARGA SATUAN PEKERJAAN DINDING

E-06 1 M2 Pasang Bata Merah Tebal 1/2 Bata, 1pc : 5ps


- Bata Merah Bh   70.0000   700.00 49,000.00
- Semen Portland Kg   9.6800   1,280.00 12,390.40
- Pasir Pasang M3   0.0450   220,000.00 9,900.00
- Pekerja Oh   0.3200   50,000.00 16,000.00
- Tukang Batu Oh   0.1000   60,000.00 6,000.00
- Kepala Tukang Oh   0.0100   70,000.00 700.00
- Mandor Oh   0.0150   75,000.00 1,125.00
Jumlah 95,115.40
Dibulatkan 95,115.00
F-06 1 M2 Plesteran adk. 1pc:5ps tebal 20 mm
- Semen Portland Kg   7.2900   1,280.00 9,331.20
- Pasir Pasang M3   0.0260   220,000.00 5,720.00
- Pekerja Oh   0.2500   50,000.00 12,500.00
- Tukang Batu Oh   0.2000   60,000.00 12,000.00
- Kepala Tukang Oh   0.0200   70,000.00 1,400.00
- Mandor Oh   0.0125   75,000.00 937.50
Jumlah 41,888.70
Dibulatkan 41,889.00
1 M2 Plesteran adk. 1pc:5ps tebal 15 mm + Acian
- Semen Portland Kg 4.3200   1,280.00 5,529.60
- Pasir Pasang M3 0.0220   220,000.00 4,840.00
- Pekerja Oh 0.2000   50,000.00 10,000.00
- Tukang Batu Oh 0.1500   60,000.00 9,000.00
- Kepala Tukang Oh 0.0150   70,000.00 1,050.00
- Mandor Oh 0.0100   75,000.00 750.00
Jumlah 31,169.60
Dibulatkan 31,170.00
F-09 1 M2 Plesteran Beton adk. 1pc : 3ps Tebal 15 mm
- Semen Portland Kg   7.0700   1,280.00 9,049.60
- Pasir Pasang M3   0.0210   220,000.00 4,620.00
- Pekerja Oh   0.2600   50,000.00 13,000.00
- Tukang Batu Oh   0.2000   60,000.00 12,000.00
- Kepala Tukang Oh   0.0200   70,000.00 1,400.00
- Mandor Oh   0.0130   75,000.00 975.00
Jumlah 41,044.60
Dibulatkan 41,045.00

I. ANALISA HARGA SATUAN PEKERJAAN PENUTUP LANTAI DAN DINDING

I-06 1 M2 Lantai Keramik corak 20 x 20 cm setara Mulia


- Keramik corak 20 x 20 cm m2   1.0000   48,000.00 48,000.00
- Semen portland Kg   8.0000   1,280.00 10,240.00
- Pasir pasang M3   0.0215   220,000.00 4,730.00
- Semen warna Kg   0.0130   12,500.00 162.50
- Pekerja Oh   0.2500   50,000.00 12,500.00
- Tukang batu Oh   0.1200   60,000.00 7,200.00
- Kepala tukang Oh   0.0120   70,000.00 840.00
- Mandor Oh   0.0125   75,000.00 937.50
Jumlah 84,610.00
Dibulatkan 84,610.00
I-07 1 M2 Lantai Keramik polos 30 x 30 cm setara Mulia
- Keramik polos 30 x 30 cm m2   1.0000   40,000.00 40,000.00
- Semen portland Kg   8.0000   1,280.00 10,240.00
- Pasir pasang M3   0.0215   220,000.00 4,730.00
- Semen warna Kg   0.0130   12,500.00 162.50
- Pekerja Oh   0.2500   50,000.00 12,500.00
- Tukang batu Oh   0.1200   60,000.00 7,200.00
- Kepala tukang Oh   0.0120   70,000.00 840.00
- Mandor Oh   0.0125   75,000.00 937.50
Jumlah 76,610.00
Dibulatkan 76,610.00
I-08 1 M2 Lantai Keramik corak 30 x 30 cm Setara Mulia
- Keramik corak 30 x 30 cm m2   1.0000   48,000.00 48,000.00
- Semen portland Kg   8.0000   1,280.00 10,240.00
- Pasir pasang M3   0.0215   220,000.00 4,730.00
- Semen warna Kg   0.0130   12,500.00 162.50
- Pekerja Oh   0.2500   50,000.00 12,500.00
- Tukang batu Oh   0.1200   60,000.00 7,200.00
- Kepala tukang Oh   0.0120   70,000.00 840.00
- Mandor Oh   0.0125   75,000.00 937.50
Jumlah 84,610.00
Dibulatkan 84,610.00
I-09 1 M2 Lantai Keramik polos 40 x 40 cm Setara Mulia
- Keramik polos 40 x 40 cm m2   1.0000   58,000.00 58,000.00
- Semen portland Kg   8.0000   1,280.00 10,240.00
- Pasir pasang M3   0.0215   220,000.00 4,730.00
- Semen warna Kg   0.0130   12,500.00 162.50
- Pekerja Oh   0.2500   50,000.00 12,500.00
- Tukang batu Oh   0.1200   60,000.00 7,200.00
- Kepala tukang Oh   0.0120   70,000.00 840.00
- Mandor Oh   0.0125   75,000.00 937.50
Jumlah 94,610.00
Dibulatkan 94,610.00
I-10 1 M2 Lantai Keramik corak 40 x 40 cm Setara Mulia
- Keramik corak 40 x 40 cm m2   1.0000   65,000.00 65,000.00
- Semen portland Kg   8.0000   1,280.00 10,240.00
- Pasir pasang M3   0.0215   220,000.00 4,730.00
- Semen warna Kg   0.0130   12,500.00 162.50
- Pekerja Oh   0.2500   50,000.00 12,500.00
- Tukang batu Oh   0.1200   60,000.00 7,200.00
- Kepala tukang Oh   0.0120   70,000.00 840.00
- Mandor Oh   0.0125   75,000.00 937.50
Jumlah 101,610.00
Dibulatkan 101,610.00

N. ANALISA HARGA SATUAN PEKERJAAN PENGECATAN

N-07 1 M2 Pengecatan Tembok Baru Setara ICI


- Plamir tembok Kg 0.1000 18,000.00 1,800.00
- Cat dasar Kg 0.1000 25,000.00 2,500.00
- Cat penutup 2x setara ICI Kg 0.2600 75,000.00 19,500.00
- Pekerja Oh 0.0200 50,000.00 1,000.00
- Tukang cat Oh 0.0630 60,000.00 3,780.00
- Kepala tukang Oh   0.0063 70,000.00 441.00
- Mandor Oh   0.0025 75,000.00 187.50
Jumlah 29,208.50
Dibulatkan 29,209.00
N-10 1 M2 Pengecatan Plafond ( 3x ) Setara Vinilex
- Cat tembok setara Vinilex Kg 0.2000 18,000.00 3,600.00
- Plamir tembok Kg 0.1600 18,000.00 2,880.00
- Rol cat Bh   0.0100 25,000.00 250.00
- Steger werk Ls 1.0000 1,000.00 1,000.00
- Ampelas Lbr 0.5000 5,000.00 2,500.00
- Pekerja Oh 0.2000 50,000.00 10,000.00
- Tukang cat Oh 0.3000 60,000.00 18,000.00
- Kepala tukang Oh 0.0300 70,000.00 2,100.00
- Mandor Oh   0.0100 75,000.00 750.00
Jumlah 41,080.00
Dibulatkan 41,080.00
N-15r' 1 M2 Pengecatan Tembok Baru Setara Vinilex (3 x laburan)
- Plamir tembok Kg 0.1000 18,000.00 1,800.00
- Cat dasar Kg 0.1000 25,000.00 2,500.00
- Cat penutup 3x setara vinilex Kg 0.3900 18,000.00 7,020.00
- Pekerja Oh 0.0300 50,000.00 1,500.00
- Tukang cat Oh 0.0945 60,000.00 5,670.00
- Kepala tukang Oh   0.0095 70,000.00 665.00
- Mandor Oh   0.0038 75,000.00 285.00
Jumlah 19,440.00
Dibulatkan 19,440.00
REKAPITULASI
RENCANA ANGGARAN BIAYA ( RAB )
PEKERJAAN : PEMBANGUNAN MESJID YAYASAN FATHAN MUBIINA
LOKASI : CIAWI - BOGOR
TAHUN : 2012

NO. URAIAN PEKERJAAN JUMLAH HARGA

a. b. c.
A. PEKERJAAN LANTAI DASAR (lantai 1)

I. PEKERJAAN PERSIAPAN Rp 533,100.00

II PEKERJAAN GALIAN DAN URUGAN Rp 15,529,938.24

III PEKERJAAN BETON STRUKTUR Rp 126,811,519.97

IV PEKERJAAN PASANGAN Rp 36,708,927.15

V PEKERJAAN PENGECATAN Rp 9,465,141.60

JUMLAH Rp 189,048,626.96
DIBULATKAN Rp 189,000,000.00

Ter i ang :
RENCANA ANGGARAN BIAYA ( RAB )
PEKERJAAN : PEMBANGUNAN MESJID YAYASAN FATHAN MUBIINA
LOKASI : CIAWI - BOGOR
TAHUN : 2012

HARGA JUMLAH
NO. URAIAN PEKERJAAN VOLUME SATUAN SATUAN HARGA
( Rp ) ( Rp )
a. b. c. d. e. f.
A. PEKERJAAN LANTAI DASAR (lantai 1)
I. PEKERJAAN PERSIAPAN
1 Pek. Papan bouwplank   12.00 m¹ 44,425.00 533,100.00
Sub Total 1 Rp 533,100.00
II PEKERJAAN GALIAN DAN URUGAN
1 Pek. galian tanah untuk pondasi   13.82 m³   30,200.00 417,484.80
2 Pek. galian tanah untuk tie-beam   8.16 m³   23,000.00 187,680.00
3 Pek urugan tanah kembali bekas galian   4.15 m³   11,025.00 45,722.88
4 Pek. urugan tanah peninggian lantai bangunan   100.80 m³   83,804.00 8,447,443.20
5 Pek. urugan pasir bawah pondasi dan lantai   7.78 m³   147,750.00 1,148,904.00
6 Pek. Lantai Kerja Pondasi dan Lantai   7.78 m³   679,360.00 5,282,703.36
Sub Total 2 Rp 15,529,938.24
III PEKERJAAN BETON STRUKTUR
1 Pek. pondasi plat beton bertulang (150kg besi + bekisting )   2.88 m³ 3,290,065.00 9,475,387.20
2 Pek. beton tie-beam 20/40 (240kg besi + bekisting )   2.56 m³   4,636,740.00 11,870,054.40
3 Pek. kolom beton struktur 30/30 (175 kg besi + bekisting )   3.89 m³   4,742,990.00 18,440,745.12
4 Pek. kolom praktis 12/12 ( 175kg besi + bekisting )   0.20 m³   4,742,990.00 967,569.96
5 Pek. balok induk 25/60 ( 230kg besi + bekisting )   8.10 m³   4,541,970.00 36,789,957.00
6 Pek. balok anak 20/40 + Lispank 10/70 ( 200kg besi + bekisting )   3.87 m³   5,238,690.00 20,263,252.92
7 Pek. Plat lantai tb=12cm + Lisplang (Bondek + Wire Mesh )   10.73 m³   2,703,631.00 29,004,553.37
Sub Total 3 32.23 Rp 126,811,519.97
IV PEKERJAAN PASANGAN
1 Pas. bata merah ad 1 : 5   77.53 m²   95,115.00 7,373,790.38
2 Plesteran + acian ad 1 : 5   155.05 m²   31,170.00 4,832,908.50
3 Plesteran + acian Finishing Beton ad 1 : 3   139.84 m²   41,045.00 5,739,732.80
4 Plesteran Rellif Lisplank beton   48.00 m²   41,045.00 1,970,160.00

5 Pas. keramik lantai 40/40   158.40 m²   94,610.00 14,986,224.00


6 Pas. keramik lantai 30/30   15.08 m²   84,610.00 1,275,707.28
7 Pas. keramik ornamen dinding 40/40   5.22 m²   101,610.00 530,404.20
Sub Total 4 Rp 36,708,927.15
V PEKERJAAN PENGECATAN
1 Pengecatan Dinding   294.89 m²   19,440.00 5,732,661.60
2 Pengecatan Plafon beton   144.00 m²   19,440.00 2,799,360.00
3 Pengecatan Lispank Beton   48.00 m²   19,440.00 933,120.00
Sub Total 5 Rp 9,465,141.60
REKAPITULASI
RENCANA ANGGARAN BIAYA ( RAB )
PEKERJAAN : PEMBANGUNAN MASJID PUTRI FATHAN MUBIINA
LOKASI : CIAWI - BOGOR
TAHUN : 2012

NO. URAIAN PEKERJAAN JUMLAH HARGA

a. b. c.
A. PEKERJAAN LANTAI DASAR / BAWAH

I. PEKERJAAN PERSIAPAN Rp 533,100.00

II PEKERJAAN GALIAN DAN URUGAN Rp 15,529,938.24

III PEKERJAAN BETON STRUKTUR Rp 126,811,519.97

IV PEKERJAAN PASANGAN Rp 36,708,927.15

V PEKERJAAN PENGECATAN Rp 18,131,104.80

Jumlah Rp 197,714,590.16

B. PEKERJAAN LANTAI ATAS

I PEKERJAAN BETON STRUKTUR Rp 59,332,457.12

II PEKERJAAN ATAP DAN PLAFOND Rp 55,173,680.00

III PEKERJAAN PASANGAN Rp 71,831,927.32

IV PEKERJAAN PENGECATAN Rp 8,114,054.40

Jumlah Rp 194,452,118.84

JUMLAH Rp 392,166,709.00
DIBULATKAN Rp 392,000,000.00

Ter i ang : Tiga Ratus Sem i an Pu u Dua Juta Rupia


RENCANA ANGGARAN BIAYA ( RAB )
PEKERJAAN : PEMBANGUNAN MASJID PUTRI FATHAN MUBIINA
LOKASI : CIAWI - BOGOR
TAHUN : 2012

HARGA JUMLAH
NO. URAIAN PEKERJAAN VOLUME SATUAN SATUAN HARGA
( Rp ) ( Rp )
a. b. c. d. e. f.
A. PEKERJAAN LANTAI DASAR / BAWAH
I. PEKERJAAN PERSIAPAN
1 Pek. Papan bouwplank   12.00 m¹   44,425.00 533,100.00
Sub Total 1 Rp 533,100.00
II PEKERJAAN GALIAN DAN URUGAN
1 Pek. galian tanah untuk pondasi   13.82 m³   30,200.00 417,484.80
2 Pek. galian tanah untuk tie-beam   8.16 m³   23,000.00 187,680.00
3 Pek urugan tanah kembali bekas galian   4.15 m³   11,025.00 45,722.88
4 Pek. urugan tanah peninggian lantai bangunan   100.80 m³   83,804.00 8,447,443.20
5 Pek. urugan pasir bawah pondasi dan lantai   7.78 m³   147,750.00 1,148,904.00
6 Pek. Lantai Kerja Pondasi dan Lantai   7.78 m³   679,360.00 5,282,703.36

Sub Total 2 Rp 15,529,938.24


III PEKERJAAN BETON STRUKTUR
1 Pek. pondasi plat beton bertulang (150kg besi + bekisting )   2.88 m³   3,290,065.00 9,475,387.20
2 Pek. beton tie-beam 20/40 (240kg besi + bekisting )   2.56 m³   4,636,740.00 11,870,054.40
3 Pek. kolom beton struktur 30/30 (175 kg besi + bekisting )   3.89 m³   4,742,990.00 18,440,745.12
4 Pek. kolom praktis 12/12 ( 175kg besi + bekisting )   0.20 m³   4,742,990.00 967,569.96
5 Pek. balok induk 25/55 ( 230kg besi + bekisting )   8.10 m³   4,541,970.00 36,789,957.00
6 Pek. balok anak 20/40 ( 200kg besi + bekisting )   3.87 m³   5,238,690.00 20,263,252.92
7 Pek. plat lantai tb=12cm (Floor Deck + Wire Mesh)   10.73 m³   2,703,631.00 29,004,553.37
Sub Total 3 Rp 126,811,519.97
IV PEKERJAAN PASANGAN
1 Pas. bata merah ad 1 : 5   77.53 m²   95,115.00 7,373,790.38
2 Plesteran + acian ad 1 : 5   155.05 m²   31,170.00 4,832,908.50
3 Plesteran + acian Finishing Beton ad 1 : 3   139.84 m²   41,045.00 5,739,732.80
4 Plesteran Rellif Lisplank beton   48.00 m²   41,045.00 1,970,160.00
5 Pas. keramik lantai 40/40   158.40 m²   94,610.00 14,986,224.00
6 Pas. keramik lantai 30/30   15.08 m²   84,610.00 1,275,707.28
7 Pas. keramik ornamen dinding 40/40   5.22 m²   101,610.00 530,404.20
Sub Total 4 Rp 36,708,927.15
V PEKERJAAN PENGECATAN
1 Pengecatan Dinding   294.89 m²   19,440.00 5,732,661.60
2 Pengecatan Plafon beton   589.78 m²   19,440.00 11,465,323.20
3 Pengecatan Lispank Beton   48.00 m²   19,440.00 933,120.00
Sub Total 5 Rp 18,131,104.80
HARGA JUMLAH
NO. URAIAN PEKERJAAN VOLUME SATUAN SATUAN HARGA
( Rp ) ( Rp )
a. b. c. d. e. f.
B. PEKERJAAN LANTAI ATAS
I PEKERJAAN BETON STRUKTUR
1 Pek. kolom beton struktur 20/30 (175 kg besi + bekisting )   1.54 m³   4,742,990.00 7,285,232.64
2 Pek. kolom praktis 12/12 ( 175kg besi + bekisting )   0.19 m³   4,742,990.00 910,654.08
3 Pek. balok 20/40 ( 230kg besi + bekisting )   2.70 m³   5,238,690.00 14,165,417.76
4 Pek. plat lantai tb=10 cm (150kg besi + bekisting )   4.10 m³   2,800,331.00 11,481,357.10
5 Pek. Lisplank Beton 10/50 (150kg besi + bekisting )   2.46 m³   2,800,331.00 6,888,814.26
Pek. Beton Tangga   6.88 m³   2,703,631.00 18,600,981.28
Sub Total 1 Rp 59,332,457.12
II. PEKERJAAN ATAP DAN PLAFOND
1 Rangka Atap Baja Ringan   225.60 m²   115,000.00 25,944,000.00
2 Penutup atap Genteng Metal   225.60 m²   75,000.00 16,920,000.00
3 Nok/Bubungan Genteng Metal   26.00 m'   55,000.00 1,430,000.00
4 Lisplank GRC   48.00 m'   65,250.00 3,132,000.00
5 Plafond GRC Rangka Hollo 4/4 Galvanis   70.56 m²   78,000.00 5,503,680.00
6 List Plafon gipsum   149.60 m'   15,000.00 2,244,000.00
Sub Total 2 Rp 55,173,680.00
III PEKERJAAN PASANGAN
1 Pas. bata merah ad 1 : 5   40.80 m²   95,115.00 3,880,692.00
2 Plesteran + acian ad 1 : 5   81.60 m²   31,170.00 2,543,472.00
3 Plesteran + acian Finishing Beton ad 1 : 3   97.60 m²   41,045.00 4,005,992.00
4 Plesteran Rellif Lisplank beton   48.00 m²   41,045.00 1,970,160.00
5 Pas. keramik lantai 40/40   73.19 m²   94,610.00 6,924,695.12
6 Pas. keramik Tangga   19.20 m²   94,610.00 1,816,512.00
7 Pas. keramik ornamen dinding 40/40   5.22 m²   101,610.00 530,404.20
8 Pas. Ralling Balkon   50.40 m²   550,000.00 27,720,000.00
9 Pas. Ralling Tangga   40.80 m²   550,000.00 22,440,000.00
Sub Total 3 Rp 71,831,927.32
IV PEKERJAAN PENGECATAN
1 Pengecatan Dinding   227.20 m²   19,440.00 4,416,768.00
2 Pengecatan Plafond   70.56 m²   19,440.00 1,371,686.40
3 Pengecatan Besi Ralling   91.20 m²   25,500.00 2,325,600.00
Sub Total IV  Rp 8,114,054.40

Jumlah Total Lantai Bawah dan Atas Rp 392,166,709.00


REKAPITULASI
RENCANA ANGGARAN BIAYA ( RAB )
PEKERJAAN : PEMBANGUNAN MESJID YAYASAN FATHAN MUBIINA
LOKASI : CIAWI - BOGOR
TAHUN : 2012

NO. URAIAN PEKERJAAN

a. b.
A. PEKERJAAN LANTAI DASAR (lantai 1)

I. PEKERJAAN PERSIAPAN

II PEKERJAAN GALIAN DAN URUGAN

III PEKERJAAN BETON STRUKTUR

IV PEKERJAAN PASANGAN

V PEKERJAAN PENGECATAN

JUMLAH
DIBULATKAN

Terbilang :

RENCANA ANGGARAN BIAYA ( RAB )


PEKERJAAN : PEMBANGUNAN MESJID YAYASAN FATHAN MUBIINA
LOKASI : CIAWI - BOGOR
TAHUN : 2012

NO. URAIAN PEKERJAAN VOLUME

a. b. c.
A. PEKERJAAN LANTAI DASAR (lantai 1)
I. PEKERJAAN PERSIAPAN
1 Pek. Papan bouwplank 12.00
Sub Total 1
II PEKERJAAN GALIAN DAN URUGAN
1 Pek. galian tanah untuk pondasi 13.82
2 Pek. galian tanah untuk tie-beam 8.16
3 Pek urugan tanah kembali bekas galian 4.15
4 Pek. urugan tanah peninggian lantai bangunan 86.40
5 Pek. urugan pasir bawah pondasi dan lantai 7.78
6 Pek. Lantai Kerja Pondasi dan Lantai 7.78
Sub Total 2
III PEKERJAAN BETON STRUKTUR
1 Pek. pondasi plat beton bertulang (150kg besi + bekisting ) 2.88
2 Pek. beton tie-beam 20/40 (240kg besi + bekisting ) 2.56
3 Pek. kolom beton struktur 30/30 (175 kg besi + bekisting ) 3.89
4 Pek. kolom praktis 12/12 ( 175kg besi + bekisting ) 0.20
5 Pek. balok induk 25/55 ( 230kg besi + bekisting ) 8.10
6 Pek. balok anak 20/40 ( 200kg besi + bekisting ) 3.87
7 Pek. Pasangan Bondek 144.00
8 Pek. Pembesian Wire Mesh 144.00
9 Beton Plat Dak 9.72

Sub Total 3
IV PEKERJAAN PASANGAN
1 Pas. bata merah ad 1 : 5 77.53
2 Plesteran + acian ad 1 : 5 155.05
3 Plesteran + acian Finishing Beton ad 1 : 3 139.84
4 Plesteran Rellif Lisplank beton 48.00
5 Pas. keramik lantai 40/40 158.40
6 Pas. keramik lantai 30/30 15.08
7 Pas. keramik ornamen dinding 40/40 5.22
Sub Total 4
V PEKERJAAN PENGECATAN
1 Pengecatan Dinding 294.89
2 Pengecatan Plafon beton 144.00
3 Pengecatan Lispank Beton 48.00
Sub Total 5
JUMLAH HARGA

c.

Rp 533,100.00

Rp 15,529,938.24

Rp 126,811,519.97

Rp 36,708,927.15

Rp 9,465,141.60

Rp 189,048,626.96
Rp 189,000,000.00

HARGA JUMLAH
SATUAN SATUAN HARGA
( Rp ) ( Rp )
d. e. f.
m¹ 44,425.00 533,100.00
Rp 533,100.00

m³   30,200.00 417,484.80
m³   23,000.00 187,680.00
m³   11,025.00 45,722.88
m³   83,804.00 7,240,665.60
m³   147,750.00 1,148,904.00
m³   679,360.00 5,282,703.36
Rp 14,323,160.64

m³ 3,290,065.00 9,475,387.20
m³   4,636,740.00 11,870,054.40
m³   4,742,990.00 18,440,745.12
m³   4,742,990.00 967,569.96
m³   4,541,970.00 36,789,957.00
m³   5,238,690.00 20,263,252.92
m2   125,000.00 18,000,000.00
m2   57,454.55 8,273,454.55
m³   742,240.00 7,214,572.80

Rp 131,294,993.95 Rp 145,618,154.59

m²   95,115.00 7,373,790.38
m²   31,170.00 4,832,908.50
m²   41,045.00 5,739,732.80
m²   41,045.00 1,970,160.00
m²   94,610.00 14,986,224.00
m²   84,610.00 1,275,707.28
m²   101,610.00 530,404.20
Rp 36,708,927.15

m²   19,440.00 5,732,661.60
m²   19,440.00 2,799,360.00
m²   19,440.00 933,120.00
Rp 9,465,141.60
144.00
1,300,000.00
0.17
  17.06   9.24 7.20

33.00
26.42
6.70
15.85
10.40
6.40

23.86

1.35

203,220.00
M' P BUAH UNIT UNIT

1 Besi Pondasi Plat   2.80   0.25 14 3.5 8

2 KOLOM 30 X 30
TUL. UTAMA   5.60 0.50 8 4 8

SENGKANG   36.00   1.10 288 3.6 8

3 SLOOF 20 X 40
TUL. UTAMA 36.00 4

TUL. EXTRA 35.00 4

SENGKANG 1.10 240

4 Balok Utama

TUL. UTAMA 54.00 5

TUL. EXTRA 54.00 2

SENGKANG   54.00   1.50 360.00

5 Balok Anak

TUL. UTAMA 27.02 4

TUL. EXTRA 27.02 2

SENGKANG   27.02   1.05 180.13


16 12 10 8 wire mesh

28.00

32.00

28.80

12.52

6.00

24.00

23.48

9.39

49.09

9.40

4.70

17.19 -

  91.49 34.00   - 119.09 - -