Anda di halaman 1dari 16

RENCANA ANGGARAN BIAYA

( RAB )
DESA : BAYANGAN
KEGIATAN : PEKERJAAN Jl. TANI
SUB KEGIATAN : PEKERJAAN RABAT BETO ( 250 x 2,50 M²)
TAHUN ANGG. : 2019

RENCANA ANGGARAN SESUAI RENCANA

NO URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH

1 2 3 4 5 6
I BAHAN
1 Semen Portland 50 Kg Zak 1,131.00 80,800.00 91,384,800.00
2 Pasir Urug M³ 95.00 95,800.00 9,101,000.00
3 Pasir Pasang M³ 153.00 186,400.00 28,519,200.00
4 Batu Khali/Pecah M³ 101.00 181,000.00 18,281,000.00
5 Kerikil M³ 180.00 186,400.00 33,552,000.00
6 Kayu Kelas III M³ 1.50 2,030,000.00 3,045,000.00
7 Tbl 3 mm Lbr 172.00 62,100.00 10,681,200.00
8 Papan proyek Bh 1.00 200,000.00 200,000.00
Sub Total I 194,764,200.00
II ALAT
Cangkul Bh 6.00 77,000.00 462,000.00
Sekop Bh 7.00 102,800.00 719,600.00
Ember Bh 11.00 15,300.00 168,300.00
Benang Nilon Bh 4.00 10,000.00 40,000.00
Argo Bh 3.00 565,500.00 1,696,500.00
Terpal Bh 1.00 269,800.00 269,800.00
Sub Total II 3,356,200.00
III UPAH
1 Pekerja OH 1,345.00 90,000.00 121,050,000.00
2 Tukang OH 150.00 110,000.00 16,500,000.00
Sub Total III 137,550,000.00

Total Sub. I + II + III 335,670,400.00


IV Operasional Kegiatan
HOK Pelaksana Kegiatan ( 1.5 %) 5,035,056.00

HOK Pengawas Kegiatan ( 0.5 %) 1,678,352.00

HOK Perencanaan ( 0.5 %) 1,678,352.00


JUMLAH TOTAL 344,062,160.00
Perhitungan Volume Pekerjaan

I Pekerjaan Persiapan
Panjang Galian
Tingi Galian
Lebar Galian
Volume

II Pekerjaan Galian Tanah


Panjang Galian
Tingi Galian
Lebar Galian
Volume

III Pekerjaan Pasangan Batu SP. 1 : 5


Panjang
0.20 2.40 0.20 Tingi Rata-rata

Total Tgg Rata


Lebar Atas

Volume

IV Pekerjaan Urugan Pasir


0.15 A Vol. Pasir Urug Dibawah Pondasi
Panjang
0.35 Tingi
0.15 Lebar
0.20
Volume

B Vol. Pasir Urug Dibawah Rabat Beton


Panjang
Tingi
Lebar
III
Volume
C Total Volume Pasir Urug

IV
V Pekerjaan Cor Rabat SP. 1 : 3 : 5
A Vol. Pasir Urug Dibawah Pondasi
Panjang
Tingi/ Tbl
Lebar

Volume
e Pekerjaan

Panjang Galian : 1436 M¹ ( 2 Sisi )


: 0.15 Cm
: 0.20 Cm
: (P) X (L) X (T)
1436 X 0.20 X 0.15 = 43.08 M³ ###

Panjang Galian : 1436 M¹ ( 2 Sisi )


: 0.15 Cm
: 0.20 Cm
: (P) X (L) X (T)
1436 X 0.20 X 0.15 = 43.08 M³ ###

n Batu SP. 1 : 5
: 1436 M¹ ( 2 Sisi )
Tingi Rata-rata : 0.85 0.80 0.84 0.82 0.73 0.80 0.80 0.70 0.78 0.78 0.74 = 8.64
0.76 0.78 0.79 0.75 0.79 = 3.87 + 8.64 = 12.51
12.51 ÷ 16 = 0.7819
Total Tgg Rata : 0.35 Cm
: 0.15 Cm Lebar Bawah : 0.20 = 0.25 M² ( Vol. Luas Pas. Batu )

: (P) X (L) X (T)

: 1436 X 0.25 X 0.35 = 125.65 M³ ###

bawah Pondasi
: 1436 M¹ ( 2 Sisi ) `
: 0.05 Cm
: 0.20 Cm

: : (P) X (L) X (T)

: 1436 X 0.20 X 0.05 = 14.36 M³

bawah Rabat Beton


: 689 M¹
: 0.05 Cm
: 2.40 Cm

: : (P) X (L) X (T)


: 689 X 2.40 X 0.05 = 82.68 M³

: 97.04 M³ ###

at SP. 1 : 3 : 5
bawah Pondasi
: 689 M¹ ( 2 Sisi )
: 0.11 Cm
: 2.45 Cm

: : (P) X (L) X (T)

: 689 X 2.45 X 0.11 = 185.69 M³ ###


( A.2.2.1.4 ) Pek. Pengukuran dan Pemasangan 1 M' Papan Bowplank

No Uraian Kode satuan Keofisien Volume


A Tenaga
Pekerja L.01 OH 0.100 1436.000
Tukang Kayu L.02 OH 0.100 1436.000
Kepala Tukang L.03 OH 0.010
Mandor L.04 OH 0.005
Sub Total ( a )
B Bahan
Kayu Balok 5/7 M³ 0.120 1436.000
Paku 2"-3" Kg 0.020 1436.000
Kayu Papan 3/20 M³ 0.007 1436.000
Sub Total ( b )
C Peralatan
Sub Total ( c )
Jumlah ( a + b + C )
Overhead & Profit ( 15 %)
Jumlah Total

( A.2.3.1.1 ) Pek. Galian Pondasi Untuk Kedalaman Kurang Lebih Dari 1 Meter Tanah Biasa

No Uraian Kode satuan Keofisien Volume


A Tenaga
Pekerja L.01 OH 0.750 43.080
Mandor L.04 OH 0.025
Sub Total ( a )
B Bahan

Kg

Sub Total ( b )
C Peralatan
Sub Total ( c )
Jumlah ( a + b + C )
Overhead & Profit ( 15 %)
Jumlah Total

(A.2.3.1.1.1) Pek. Pengurukan 1 M³ Dengan Pasir Urug


No Uraian Kode satuan Keofisien Volume
A Tenaga
Pekerja L.01 OH 0.300 97.040
Mandor L.04 OH 0.01
Sub Total ( a )
B Bahan
Pasir Urug M³ 1.200 97.040

Sub Total ( b )
C Peralatan
Sub Total ( c )
Jumlah ( a + b + C )
Overhead & Profit ( 15 %)
Jumlah Total

(A.3.2.1.3) Pekerjaan 1 m³ Pondasi Batu Pecah/Belah SP 1 : 5

No Uraian Kode satuan Keofisien Volume


A Tenaga
Pekerja L.01 OH 1.500 125.650
Tukang Batu L.02 OH 0.750 125.650
Kepala Tukang L.03 OH 0.075
Mandor L.04 OH 0.075
Sub Total ( a )
B Bahan
Batu Belah M³ 1.200 125.650
Semen Portland Kg 136.000 125.650
Pasir Pasang M³ 0.544 125.650
Sub Total ( b )
C Peralatan
Sub Total ( c )
Jumlah ( a + b + C )
Overhead & Profit ( 15 %)
Jumlah Total

Pek. Cor Rabat Beton SP. 1 : 3 : 5

No Uraian Kode satuan Keofisien Volume


A Tenaga
Pekerja L.01 OH 0.777 185.686
Tukang Batu L.02 OH 0.236 185.686
Kepala Tukang L.03 OH 0.010
Mandor L.04 OH 0.010
Sub Total ( a )
B Bahan
Semen Portland Kg 4.360 185.686
Kerikil M³ 0.870 185.686
Pasir Pasang M³ 0.520 185.686
Sub Total ( b )
C Peralatan
Sub Total ( c )
Jumlah ( a + b + C )
Overhead & Profit ( 15 %)
Jumlah Total

Pek. 1 M² Polesteran Siar Batu Mortal SP 1 : 3 Tebal 15 MM

No Uraian Kode satuan Keofisien Volume


A Tenaga
Pekerja L.01 OH 0.300
Tukang Batu L.02 OH 0.150
Kepala Tukang L.03 OH
Mandor L.04 OH
Sub Total ( a )
B Bahan
Semen Portland Kg 4.8400 0.0000
Pasir Pasang M³ 0.0180 0.0000
Sub Total ( b )
C Peralatan
Sub Total ( c )
Jumlah ( a + b + C )
Overhead & Profit ( 15 %)
Jumlah Total

Pek. Polesteran 1 M² SP 1 : 3 Tebal 15 MM

No Uraian Kode satuan Keofisien Volume


A Tenaga
Pekerja L.01 OH 0.150 0.000
Tukang Batu L.02 OH 0.075 0.000
Kepala Tukang L.03 OH 0.015
Mandor L.04 OH 0.030
Sub Total ( a )
B Bahan
Semen Portland Kg 4.4500 0.0000
Pasir Pasang M³ 0.0180 0.0000
Sub Total ( b )
C Peralatan
Sub Total ( c )
Jumlah ( a + b + C )
Overhead & Profit ( 15 %)
Jumlah Total

Pek. Acian 1 M²
No Uraian Kode satuan Keofisien Volume
A Tenaga
Pekerja L.01 OH 0.150 0.000
Tukang Batu L.02 OH 0.075 0.000
Kepala Tukang L.03 OH 0.015
Mandor L.04 OH 0.030
Sub Total ( a )
B Bahan
Semen Portland Kg 0.3500 0.0000
Sub Total ( b )
C Peralatan
Sub Total ( c )
Jumlah ( a + b + C )
Overhead & Profit ( 15 %)
Jumlah Total
Jumlah Harga Sat Jumlah Harga

143.600 900,000.00 129,240,000.00


143.600 110,000.00 15,796,000.00

120,000.00 -
145,036,000.00

172.320 247,451.52 42,640,845.93


28.720 41,241.92 1,184,467.94
10.052 14,434.67 145,097.32
43,970,411.19

189,006,411.19
5 %)
189,006,411.19

Tanah Biasa

Jumlah Harga Sat Jumlah Harga

32.310 900,000.00 29,079,000.00


110,000.00 -
29,079,000.00

-
-
-
-

29,079,000.00
5 %)

29,079,000.00
Jumlah Harga Sat Jumlah Harga

29.112 100,000.00 2,911,200.00


0.000 120,000.00 -
2,911,200.00

116.448 90,000.00 10,480,320.00

10,480,320.00

13,391,520.00
5 %)

13,391,520.00

Jumlah Harga Sat Jumlah Harga

188.475 100,000.00 18,847,500.00


94.238 125,000.00 11,779,687.50
-
-
30,627,187.50

150.780 181,000.00 27,291,180.00


17088.400 1,616.00 27,614,854.40
68.354 186,400.00 12,741,111.04
67,647,145.44

98,274,332.94
5 %)

98,274,332.94

Jumlah Harga Sat Jumlah Harga


144.278 100,000.00 14,427,763.35
43.822 125,000.00 5,477,722.25
-
-
19,905,485.60

809.589 1,616.00 1,308,295.47


161.546 186,400.00 30,112,246.16
96.556 186,400.00 17,998,124.14
49,418,665.78

69,324,151.38
5 %)
210,069,004.32
69,324,151.38

Jumlah Harga Sat Jumlah Harga

0.000 100,000.00 -
0.000 125,000.00 -
-
-
-

0.0000 1,540.00 -
0.0000 175,000.00 -
-

-
5 %)
-

Jumlah Harga Sat Jumlah Harga

0.000 100,000.00 -
0.000 125,000.00 -
-
-
-

0.0000 1,540.00 -
0.0000 175,000.00 -
-

-
5 %)
-

Jumlah Harga Sat Jumlah Harga

0.000 100,000.00 -
0.000 125,000.00 -
-
-
-

0.0000 1,540.00 -
-

-
5 %)
-
Tabel Koreksi Pek. Jl. Rabat Beton

Pek. Cor Rabat


Pek. Urugan Pek. Pasangan
No Uraian Pek. Bowplank Pek. Galian SP. 1 : 3
Pasir Batu SP. 1 : 5
:5

A TENAGA

Pekerja 32.310 29.112 188.475 144.278

Tukang 94.238 43.822

Mandor

B BAHAN

Batu Belah 150.78

Semen Portland 17088.4000 809.5888

Pasir Pasang 68.3536 96.55646

Pasir Urug 116.4480

Kerikil 809.58878
Pek. Pas. Jumlah
Pek. Acian Ket.
Pelesteran Realisasi

394.175 394.175 HOK

138.059 138.059 HOK

150.780 150.780 M³

17897.989 357.959776 Kg/Zak

164.910 164.910 M³

116.448 116.448 M³

809.589 809.589 M³

Anda mungkin juga menyukai