ANALISA HARGA SATUAN PEKERJAAN ( AHSP )

( DAERAH ATAS)

NAMA KEGIATAN : PEMBUATAN TEMPAT PARKIR DI PANTAI GEMAH


LOKASI KEGIATAN : DESA KEBOIRENG KECAMATAN BESUKI KABUPATEN TULUNGAGUNG

Overhead dan profit = 0.0100

HARGA JUMLAH HARGA


NO URAIAN KEGIATAN KODE SAT KOEFISIEN SATUAN UPAH BAHAN PERALATAN JUMLAH
(Rp) (Rp) (Rp) (Rp) (Rp)
1 2 3 4 5 6 7= (5x6) 8= (5x6) 9=(5X6) 10 = ( 7 + 8 + 9 )

A.2.3.1 PEKERJAAN TANAH

A.2.3.1.14 1 m3 Pengurugan sirtu padat


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.2500 70,000.00 17,500.00
Mandor 1.2.7.5 oh 0.0250 75,000.00 1,875.00
Bahan
Sirtu Urug 2.2.1.56 m3 1.2000 175,000.00 210,000.00
ALAT
peralatan 0.1000 50,000.00 5,000.00
19,375.00 210,000.00 5,000.00 234,375.00
Overhead dan profit 0.0100 193.75 2,100.00 50.00 2,343.75
19,568.75 212,100.00 5,050.00 236,718.75

A.2.3.1.11 1 m3 Pengurugan dengan pasir urug


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.3000 70,000.00 21,000.00
Mandor 1.2.7.5 oh 0.0100 75,000.00 750.00
Bahan
Pasir urug 2.2.1.51 m3 1.2000 150,000.00 180,000.00
21,750.00 180,000.00 - 201,750.00
Overhead dan profit 0.0100 217.50 1,800.00 - 2,017.50
21,967.50 181,800.00 - 203,767.50

A.4.1.1.8 1 m3 Membuat Beton mutu fc=20 Mpa (K250), Slump (12±2) cm, w/c = 0,56
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.6500 70,000.00 115,500.00
Tukang batu 1.2.7.16 oh 0.2750 72,000.00 19,800.00
Kepala Tukang 1.2.7.3 oh 0.0280 72,000.00 2,016.00
Mandor 1.2.7.5 oh 0.0830 75,000.00 6,225.00
Bahan
PC / Portland cement 2.2.1.52 kg 384.0000 1,200.00 460,800.00
Pasir pasang / beton 2.2.1.50 m3 0.4943 225,000.00 111,217.50
Batu pecah 2-3 cm 2.2.1.32 m3 0.7696 270,000.00 207,792.00
Air bersih 2.2.6.1 ltr 215.0000 100.00 21,500.00
143,541.00 801,309.50 - 944,850.50
Overhead dan profit 0.0100 1,435.41 8,013.10 - 9,448.51
144,976.41 809,322.60 - 954,299.01

A.4.1.1.20 1 m2 Pemasangan bekisting untuk pondasi


Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 0.5200 70,000.00 36,400.00
Tukang kayu 1.2.7.19 oh 0.2600 72,000.00 72,000.00
Kepala Tukang 1.2.7.3 oh 0.0260 72,000.00 72,000.00
Mandor 1.2.7.5 oh 0.0260 75,000.00 75,000.00
Bahan
Kayu bekisting 2.2.2.15 m3 0.0400 2,850,000.00 114,000.00
Paku biasa 2.2.12.1 kg 0.3000 15,000.00 4,500.00
Minyak bekisting 2.2.6.27 ltr 0.1000 6,000.00 600.00
255,400.00 119,100.00 - 374,500.00
Overhead dan profit 0.0100 2,554.00 1,191.00 - 3,745.00
257,954.00 120,291.00 - 378,245.00
Pemakainan 2x 189,122.50

A.4.4.3 PEKERJAAN PENUTUP LANTAI DAN PENUTUP DINDING

A.4.4.3.63b 1 m2 Pasang Paving Stone Abu abu Tebal 8 Cm K300


Tenaga
Tukang batu 1.2.7.16 Oh 0.0600 72,000.00 4,320.00
Pekerja / Buruh tak terlatih 1.2.7.10 Oh 0.2000 70,000.00 14,000.00
Bahan
Paving Stone abu - abu t= 8 cm, K300 2.2.5.59 M2 1.1000 70,000.00 77,000.00
Pasir pasang / beton 2.2.1.50 M3 0.0350 225,000.00 7,875.00
18,320.00 84,875.00 - 103,195.00
Overhead dan profit 0.0100 183.20 848.75 - 1,031.95
18,503.20 85,723.75 - 104,226.95

Tulungagung, 26 Juni 2019


Dibuat Oleh
CV. ANDARU PERSADA

ANOM SANJAYA
Direktur