( DAERAH ATAS)
A.4.1.1.8 1 m3 Membuat Beton mutu fc=20 Mpa (K250), Slump (12±2) cm, w/c = 0,56
Tenaga
Pekerja / Buruh tak terlatih 1.2.7.10 oh 1.6500 70,000.00 115,500.00
Tukang batu 1.2.7.16 oh 0.2750 72,000.00 19,800.00
Kepala Tukang 1.2.7.3 oh 0.0280 72,000.00 2,016.00
Mandor 1.2.7.5 oh 0.0830 75,000.00 6,225.00
Bahan
PC / Portland cement 2.2.1.52 kg 384.0000 1,200.00 460,800.00
Pasir pasang / beton 2.2.1.50 m3 0.4943 225,000.00 111,217.50
Batu pecah 2-3 cm 2.2.1.32 m3 0.7696 270,000.00 207,792.00
Air bersih 2.2.6.1 ltr 215.0000 100.00 21,500.00
143,541.00 801,309.50 - 944,850.50
Overhead dan profit 0.0100 1,435.41 8,013.10 - 9,448.51
144,976.41 809,322.60 - 954,299.01