REKAPITULASI BIAYA

PEKERJAAN
PEMASANGAN BATU BRONJONG BREAK WATER PENAHAN ABRASI
PANTAI KARANGSONG

JUMLAH HARGA
No. URAIAN PEKERJAAN
(Rp.)

1 PEKERJAAN PERSIAPAN 46,214,500.00

2 PEKERJAAN BREAK WATER 4,499,240,101.05

JUMLAH BIAYA 4,545,454,601.05

PAJAK PERTAMBAHAN NILAI (PPN ) = 10% 454,545,460.10

JUMLAH BIAYA (TERMASUK PPN 10%) 5,000,000,061.15

JUMLAH BIAYA DIBULATKAN (TERMASUK PPN 10%) 5,000,000,000.00

Indramayu, Maret 2022

MUHAMMAD ROYANI
…..................
DAFTAR KUANTITAS DAN HARGA
PEKERJAAN
PEMASANGAN BATU BRONJONG BREAK WATER PENAHAN ABRASI
PANTAI KARANGSONG

No. URAIAN VOL SAT HARGA SATUAN JUMLAH HARGA

I PEKERJAAN PERSIAPAN
1 Dokumentasi 1.00 Ls 2,000,000.00 2,000,000.00

2 Mobilisasi 1.00 Ls 44,214,500.00 44,214,500.00

II PEKERJAAN BREAK WATER


1 Urugan Material Berbutir 562.22 m3 219,560.00 123,440,101.05

2 Pasangan Batu Bronjong 9,000.00 m3 486,200.00 4,375,800,000.00

JUMLAH 4,545,454,601.05
DIBULATKAN 4,545,454,610.00

PPN 10% 454,545,461.00

SUB TOTAL 5,000,000,071.00

TOTAL 5,000,000,000.00

TERBILANG : Lima Milyar Rupiah


ANALISA TERINCI HARGA SATUAN PEKERJAAN

PEKERJAAN
PEMASANGAN BATU BRONJONG BREAK WATER PENAHAN ABRASI
PANTAI KARANGSONG

Pekerjaan : Pemasangan Batu Bronjong dan Retaining Wall Nomor Mata Pembayaran : Rupiah
Jenis Pekerjaan : Mobilisasi
Volume Total : 49
(A) = Volume Prod. Per : Hari

MATERIAL/
TENAGA KERJA PERALATAN BBM/PELUMAS
HARGA LAIN-LAIN
No. URAIAN SATUAN QUANTITY SATUAN TOTAL (Rp.)
(Rp.)
(Rp.) (Rp.) (Rp.)
(Rp.)

B TENAGA KERJA
- Supir Hok 49.00 7,350,000.00 150,000.00 7,350,000.00

C PERALATAN
- Kend. Pick Up Hr 49.00 24,500,000.00 500,000.00 24,500,000.00
- Rubber Cone Hr 1,800.00 2,700,000.00 1,500.00 2,700,000.00
- Rambu Tanda Panah Hr 49.00 122,500.00 2,500.00 122,500.00
- Rambu Hati Hati Hr 49.00 122,500.00 2,500.00 122,500.00

D BBM/ PELUMAS
- Premium Ltr 600.00 5,400,000.00 9,000.00 5,400,000.00

E MATERIAL/LAIN-LAIN
- Biaya Tol Ls 1.00 - - -

F SUB JUMLAH 40,195,000.00


G OVERHEAD & PROFIT 10% 4,019,500.00
H JUMLAH 44,214,500.00
ANALISA TERINCI HARGA SATUAN PEKERJAAN

PEKERJAAN
PEMASANGAN BATU BRONJONG BREAK WATER PENAHAN ABRASI
PANTAI KARANGSONG

Pekerjaan : Pemasangan Batu Bronjong dan Retaining Wall Nomor Mata Pembayaran : Rupiah
Jenis Pekerjaan : Galian Tanah Untuk Dibuang
Volume Total : 1
(A) = Volume Prod. Per : M3

MATERIAL/
TENAGA KERJA PERALATAN BBM/PELUMAS
HARGA LAIN-LAIN
No. URAIAN SATUAN QUANTITY SATUAN TOTAL (Rp.)
(Rp.)
(Rp.) (Rp.) (Rp.)
(Rp.)

B TENAGA KERJA
- Pekerja Hok 0.34 40,800.00 120,000.00 40,800.00
- Mandor Hok 0.03 6,000.00 200,000.00 6,000.00

C PERALATAN
- Alat Bantu Ls 1.00 5,000.00 5,000.00 5,000.00

D BBM/ PELUMAS
-

E MATERIAL/LAIN-LAIN
- -

F SUB JUMLAH 51,800.00


G OVERHEAD & PROFIT 10% 5,180.00
H JUMLAH 56,980.00
ANALISA TERINCI HARGA SATUAN PEKERJAAN

PEKERJAAN
PEMASANGAN BATU BRONJONG BREAK WATER PENAHAN ABRASI
PANTAI KARANGSONG

Pekerjaan : Pemasangan Batu Bronjong dan Retaining Wall Nomor Mata Pembayaran : Rupiah
Jenis Pekerjaan : Urugan Material Berbutir
Volume Total : 1.00
(A) = Volume Prod. Per : M3

MATERIAL/
TENAGA KERJA PERALATAN BBM/PELUMAS
HARGA LAIN-LAIN
No. URAIAN SATUAN QUANTITY SATUAN TOTAL (Rp.)
(Rp.)
(Rp.) (Rp.) (Rp.)
(Rp.)

B TENAGA KERJA
- Pekerja Hok 0.09 10,800.00 120,000.00 10,800.00
- Mandor Hok 0.01 2,000.00 200,000.00 2,000.00

C PERALATAN
- Alat Bantu Ls 1.00 5,000.00 5,000.00 5,000.00

D BBM/ PELUMAS
-

E MATERIAL/LAIN-LAIN
- Pasir Urug M3 1.01 181,800.00 180,000.00 181,800.00

F SUB JUMLAH 199,600.00


G OVERHEAD & PROFIT 10% 19,960.00
H JUMLAH 219,560.00
ANALISA TERINCI HARGA SATUAN PEKERJAAN

PEKERJAAN
PEMASANGAN BATU BRONJONG BREAK WATER PENAHAN ABRASI
PANTAI KARANGSONG

Pekerjaan : Pemasangan Batu Bronjong dan Retaining Wall Nomor Mata Pembayaran : Rupiah
Jenis Pekerjaan : Saluran Talud Beton 1/2 lingkaran dia 30cm
Volume Total : 1.00
(A) = Volume Prod. Per : M

MATERIAL/
TENAGA KERJA PERALATAN BBM/PELUMAS
HARGA LAIN-LAIN
No. URAIAN SATUAN QUANTITY SATUAN TOTAL (Rp.)
(Rp.)
(Rp.) (Rp.) (Rp.)
(Rp.)

B TENAGA KERJA
- Pekerja Hok 0.32 38,400.00 120,000.00 38,400.00
- Tukang Hok 0.05 7,500.00 150,000.00 7,500.00
- Mandor Hok 0.06 12,000.00 200,000.00 12,000.00

C PERALATAN
- Alat Bantu Ls 1.00 5,000.00 5,000.00 5,000.00

D BBM/ PELUMAS
-

E MATERIAL/LAIN-LAIN
- Buis Beton dia 1/2 30cm M 1.01 19,190.00 19,000.00 19,190.00
- Pasir Urug M3 0.01 1,800.00 180,000.00 1,800.00
- Pasir Pasang M3 0.02 3,800.00 200,000.00 3,800.00
- Semen PC 50 Kg zak 0.03 1,950.00 65,000.00 1,950.00

F SUB JUMLAH 89,640.00


G OVERHEAD & PROFIT 10% 8,964.00
ANALISA TERINCI HARGA SATUAN PEKERJAAN

PEKERJAAN
PEMASANGAN BATU BRONJONG BREAK WATER PENAHAN ABRASI
PANTAI KARANGSONG

H JUMLAH 98,604.00
ANALISA TERINCI HARGA SATUAN PEKERJAAN

PEKERJAAN
PEMASANGAN BATU BRONJONG BREAK WATER PENAHAN ABRASI
PANTAI KARANGSONG

Pekerjaan : Pemasangan Batu Bronjong dan Retaining Wall Nomor Mata Pembayaran : Rupiah
Jenis Pekerjaan : Pasangan Batu Kali Untuk Retaining Wall
Volume Total : 1.00
(A) = Volume Prod. Per : M3

MATERIAL/
TENAGA KERJA PERALATAN BBM/PELUMAS
HARGA LAIN-LAIN
No. URAIAN SATUAN QUANTITY SATUAN TOTAL (Rp.)
(Rp.)
(Rp.) (Rp.) (Rp.)
(Rp.)

B TENAGA KERJA
- Pekerja Hok 1.20 144,000.00 120,000.00 144,000.00
- Tukang Hok 0.47 70,500.00 150,000.00 70,500.00
- Mandor Hok 0.03 6,000.00 200,000.00 6,000.00

C PERALATAN
- Alat Bantu Ls 1.00 5,000.00 5,000.00 5,000.00

D BBM/ PELUMAS
-

E MATERIAL/LAIN-LAIN
- Batu Kali M3 1.01 202,000.00 200,000.00 202,000.00
- Pasir Pasang M3 0.43 86,000.00 200,000.00 86,000.00
- Semen PC 50 Kg zak 1.87 121,550.00 65,000.00 121,550.00

F SUB JUMLAH 635,050.00


G OVERHEAD & PROFIT 10% 63,505.00
H JUMLAH 698,555.00
ANALISA TERINCI HARGA SATUAN PEKERJAAN

PEKERJAAN
PEMASANGAN BATU BRONJONG BREAK WATER PENAHAN ABRASI
PANTAI KARANGSONG

Pekerjaan : Pemasangan Batu Bronjong dan Retaining Wall Nomor Mata Pembayaran : Rupiah
Jenis Pekerjaan : Pasangan Batu Bronjong
Volume Total : 1.00
(A) = Volume Prod. Per : M3

MATERIAL/
TENAGA KERJA PERALATAN BBM/PELUMAS
HARGA LAIN-LAIN
No. URAIAN SATUAN QUANTITY SATUAN TOTAL (Rp.)
(Rp.)
(Rp.) (Rp.) (Rp.)
(Rp.)

B TENAGA KERJA
- Pekerja Hok 0.30 36,000.00 120,000.00 36,000.00
- Tukang Hok 0.10 15,000.00 150,000.00 15,000.00
- Mandor Hok 0.02 4,000.00 200,000.00 4,000.00

C PERALATAN
- Alat Bantu Ls 1.00 5,000.00 5,000.00 5,000.00

D BBM/ PELUMAS

E MATERIAL/LAIN-LAIN
- Batu Kali M3 1.01 202,000.00 200,000.00 202,000.00
- Kawat Bronjong SNI M3 1.00 180,000.00 180,000.00 180,000.00

F SUB JUMLAH 442,000.00


G OVERHEAD & PROFIT 10% 44,200.00
H JUMLAH 486,200.00
KETERANGAN DASAR HARGA SATUAN

PEKERJAAN
PEMASANGAN BATU BRONJONG BREAK WATER PENAHAN ABRASI
PANTAI KARANGSONG

STANDAR HARGA HARGA SATUAN


NO. URAIAN SATUAN
SUMBER ( Rp. )

A. UPAH TENAGA KERJA


- Supir Hok Cirebon 150,000.00
- Pekerja Hok Cirebon 120,000.00
- Tukang Batu Hok Cirebon 150,000.00
- Mandor Hok Cirebon 200,000.00

B. MATERIAL/ BAHAN
- Buis Beton dia 1/2 30cm M Cirebon 19,000.00
- Pasir Urug M³ Kepuh - Crb 180,000.00
- Pasir Pasang M³ Kepuh - Crb 200,000.00
- Pasir Beton M³ Kepuh - Crb 210,000.00
- Split Pecah Mesin 2/3 M³ Kepuh - Crb 250,000.00
- Semen PC 50 Kg Zak Cirebon 65,000.00
- Batu Kali M³ Kepuh - Crb 200,000.00
- Kawat Bronjong SNI M³ Jakarta 180,000.00

C. LAIN-LAIN
- Rubber Cone Hr 1,500.00
- Rambu Tanda Panah Hr 2,500.00
- Rambu Hati Hati Hr 2,500.00
- Cetak Photo Ls 187,500.00
- Pick Up Hr 500,000.00
- Premium Ltr 9,000.00
- Alat Bantu Lainnya Ls 5,000.00
JADWAL RENCANA KERJA (MASTER SCHEDULE)

JASA PEMBORONGAN
PEKERJAAN PEMASANGAN BATU BRONJONG DAN RETAINING WALL
PADA JALAN TOL PALIMANAN - KANCI

MINGGU
1 2 3 4 5 6 7
KET.
No. URAIAN PEKERJAAN SATUAN KUANTITAS
BOBOT HARI KE
(%)
PENGUKURAN 1-7 8-14 15-21 22-28 29-35 36-42 43-49
TANGGAL

I PEKERJAAN PERSIAPAN 100%

1 Dokumentasi Ls 1.00 0.044 0.015 0.015 0.015

2 Mobilisasi Ls 1.00 0.973 0.139 0.139 0.139 0.139 0.139 0.139 0.139
50%

II PEKERJAAN BREAK WATER

1 Galian Tanah untuk dibuang M3 - - - - -

2 Urugan Material Berbutir M3 562.22 2.716 0.905 0.905 0.905


3 Saluran Talud Beton 1/2 lingkaran dia 30cm M3 - - - - -

4 Pasangan Batu Kali untuk Retaining Wall M3 - - - - -

5 Pasangan Batu Bronjong M3 9,000.00 96.268 32.089 32.089 32.089 0%

Jumlah Nilai Pekerjaan 100.000


Mingguan 0.154 0.139 1.044 1.059 33.133 32.228 32.243
RENCANA
Kumulatif 0.154 0.293 1.337 2.396 35.529 67.757 100.000
Mingguan
REALISASI
Kumulatif
DEVIASI

Indramayu, 9 Juni 2011


CV. SWADESI

LIES HIKMAWATI
Direktur Utama