REKAPITULASI

RENCANA ANGGARAN BIAYA (RAB)


SUB BIDANG : MEKANIKAL ELEKTRIKAL PLAMBING
PEKERJAAN : PEMBANGUNAN GEDUNG UNIVERSITAS TANGERANG
LOKASI : TANGERANG BANTEN

HARGA JUMLAH TOTAL


NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

MEKANIKAL
I PENYEDIAAN, SUPLAI & INSTALASI PIPA AIR BERSIH 1,256,489,000.00

II SISTEM PEMIPAAN AIR BEKAS KOTOR & PENGOLAHAN LIMBAH 3,562,775,000.00

III DRAINASI BANGUNAN & INSTALASI AIR HUJAN 1,098,140,000.00

IV SISTEM TATA UDARA / VAC 3,572,317,500.00

V SISTEM PENANGGULANGAN KEBAKARAN 7,564,540,000.00

VI PASSANGER, FREIGHT ELEVATOR & GONDOLA 12,700,000,000.00

VII IJIN-IJIN PEKERJAAN ELEKTRIKAL 550,000,000.00

TOTAL MEKANIKAL 30,304,261,500.00

ELEKTRIKAL
VIII PENYEDIAAN JARINGAN & DISTRIBUSI LISTRIK 7,548,635,000.00

IX SISTEM BACKUP POWER (GENSET) & SISTEM GROUNDING 2,407,350,000.00

X INSTALASI PENERANGAN & KOTAK KONTAK 2,306,111,000.00

XI SISTEM TELEPON / VOICE COMMUNICATION 659,247,000.00

XII SISTEM KOMUNIKASI DATA / LOCAL AREA NETWORK (LAN) 4,842,165,000.00

XIII SISTEM DETEKSI KEBAKARAN (FIRE ALARM) 3,714,405,000.00

XIV INSTALASI KABEL TRAY 1,153,516,100.00

XV SISTEM PENYALUR PETIR 498,150,000.00

XVI SISTEM CCTV (CLOSED CIRCUIT TELEVISION) 1,211,764,500.00

XVII INSTALASI SISTEM TATA SUARA 1,752,750,000.00

XVIII IJIN-IJIN PEKERJAAN ELEKTRIKAL 4,120,000,000.00

TOTAL ELEKTRIKAL 30,214,093,600.00


GRAND TOTAL 60,518,355,100.00

Rekap RAB ME
Universitas Muhammadiyah Tangerang
Page 1 of 85
RENCANA ANGGARAN BIAYA (RAB) PEKERJAAN MEKANIKAL DAN ELEKTRIKAL
PEMBANGUNAN GEDUNG UNIVERSITAS TANGERANG
TAHUN 2017

HARGA JUMLAH TOTAL


NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

II PENGOLAHAN LIMBAH & INSTALASI PIPA AIR BEKAS, KOTOR & VENT
A Instalasi Pipa Tegak/Riser
1 Pipa PVC dim. 150mm m' 192.00 160,000.00 30,720,000.00
2 Pipa PVC dim. 100mm (termasuk pipa vent) m' 383.00 210,000.00 80,430,000.00
3 Pipa PVC dim. 75mm (termasuk pipa vent) m' 220.00 180,000.00 39,600,000.00
4 Fitting, Support & Aksesoris lot 1.00 5,000,000.00 5,000,000.00
Sub Total Instalasi Pipa Tegak/Riser 155,750,000.00
B Instalasi Pipa Air Bekas Kotor Lantai Basement 1
1 Pipa PVC dim. 150mm m' 62.00 160,000.00 9,920,000.00
2 Pipa PVC dim. 100mm m' 91.00 140,000.00 12,740,000.00
3 Pipa PVC dim. 75mm m' 28.00 120,000.00 3,360,000.00
4 Clean Out bh 6.00 75,000.00 450,000.00
5 Fitting &Aksesoris lot 1.00 5,000,000.00 5,000,000.00
Sub Total Instalasi Pipa Air Bekas Kotor Lantai Basement 1 31,470,000.00
C Instalasi Pipa Air Bekas Kotor Lantai Groundfloor
1 Pipa PVC dim. 100mm m' 29.00 140,000.00 4,060,000.00
2 Pipa PVC dim. 75mm m' 7.00 120,000.00 840,000.00
3 Pipa PVC dim. 65mm m' 16.00 110,000.00 1,760,000.00
4 Pipa PVC dim. 50mm m' 30.00 90,000.00 2,700,000.00
5 Floor Drain Stainless Steel bh 14.00 125,000.00 1,750,000.00
6 U-Trap bh 14.00 350,000.00 4,900,000.00
7 Clean Out bh 4.00 75,000.00 300,000.00
8 Fitting &Aksesoris lot 1.00 5,000,000.00 5,000,000.00
Sub Total Instalasi Pipa Air Bekas Kotor Lantai Groundfloor 21,310,000.00
D Instalasi Pipa Air Bekas Kotor Lantai 2
1 Pipa PVC dim. 100mm m' 22.00 140,000.00 3,080,000.00
2 Pipa PVC dim. 75mm m' 2.00 120,000.00 240,000.00
3 Pipa PVC dim. 65mm m' 10.00 110,000.00 1,100,000.00
4 Pipa PVC dim. 50mm m' 10.00 90,000.00 900,000.00
5 Pipa PVC dim. 40mm m' 3.00 78,000.00 234,000.00
6 Pipa PVC dim. 32mm m' 5.00 56,000.00 280,000.00
7 Floor Drain Stainless Steel bh 4.00 125,000.00 500,000.00
8 U-Trap bh 4.00 350,000.00 1,400,000.00
9 Clean Out bh 4.00 75,000.00 300,000.00
10 Fitting &Aksesoris lot 1.00 5,000,000.00 5,000,000.00
Sub Total Instalasi Pipa Air Bekas Kotor Lantai 2 13,034,000.00
E Instalasi Pipa Air Bekas Kotor Lantai 3
1 Pipa PVC dim. 100mm m' 22.00 140,000.00 3,080,000.00
2 Pipa PVC dim. 75mm m' 2.00 120,000.00 240,000.00
3 Pipa PVC dim. 65mm m' 10.00 110,000.00 1,100,000.00
4 Pipa PVC dim. 50mm m' 10.00 90,000.00 900,000.00
5 Pipa PVC dim. 40mm m' 3.00 78,000.00 234,000.00
6 Pipa PVC dim. 32mm m' 5.00 56,000.00 280,000.00
7 Floor Drain Stainless Steel bh 4.00 125,000.00 500,000.00
8 U-Trap bh 4.00 350,000.00 1,400,000.00
9 Clean Out bh 4.00 75,000.00 300,000.00
10 Fitting &Aksesoris lot 1.00 5,000,000.00 5,000,000.00
Sub Total Instalasi Pipa Air Bekas Kotor Lantai 3 13,034,000.00
F Instalasi Pipa Air Bekas Kotor Lantai 4
Sub Total Instalasi Pipa Air Bekas Kotor Lantai 4 13,034,000.00
G Instalasi Pipa Air Bekas Kotor Lantai 5
Sub Total Instalasi Pipa Air Bekas Kotor Lantai 5 13,034,000.00

Rincian RAB MEP (Pengolahan Limbah dan Instalasi Air Kotor)


Universitas Muhammadiyah Tangerang
Page 2
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

H Instalasi Pipa Air Bekas Kotor Lantai 6


Sub Total Instalasi Pipa Air Bekas Kotor Lantai 6 18,808,000.00
I Instalasi Pipa Air Bekas Kotor Lantai 8
Sub Total Instalasi Pipa Air Bekas Kotor Lantai 8 19,733,000.00
J Instalasi Pipa Air Bekas Kotor Lantai 9
Sub Total Instalasi Pipa Air Bekas Kotor Lantai 9 19,733,000.00
K Instalasi Pipa Air Bekas Kotor Lantai 10
Sub Total Instalasi Pipa Air Bekas Kotor Lantai 10 19,733,000.00
L Instalasi Pipa Air Bekas Kotor Lantai 11
Sub Total Instalasi Pipa Air Bekas Kotor Lantai 11 19,733,000.00
M Instalasi Pipa Air Bekas Kotor Lantai 12
Sub Total Instalasi Pipa Air Bekas Kotor Lantai 12 19,733,000.00
N Instalasi Pipa Air Bekas Kotor Lantai 13
Sub Total Instalasi Pipa Air Bekas Kotor Lantai 13 19,733,000.00
O Instalasi Pipa Air Bekas Kotor Lantai 14
Sub Total Instalasi Pipa Air Bekas Kotor Lantai 14 19,733,000.00
P Instalasi Pipa Air Bekas Kotor Lantai 15
Sub Total Instalasi Pipa Air Bekas Kotor Lantai 15 19,733,000.00
Q Instalasi Pipa Air Bekas Kotor Lantai 16
Sub Total Instalasi Pipa Air Bekas Kotor Lantai 16 19,733,000.00
R Instalasi Pipa Air Bekas Kotor Lantai 17
Sub Total Instalasi Pipa Air Bekas Kotor Lantai 17 19,733,000.00
S Instalasi Pipa Air Bekas Kotor Lantai 18
Sub Total Instalasi Pipa Air Bekas Kotor Lantai 18 19,733,000.00
T Instalasi Pipa Air Bekas Kotor Lantai 19
Sub Total Instalasi Pipa Air Bekas Kotor Lantai 19 28,332,000.00
U Instalasi Pipa STP & Sumpit
Sub Total Instalasi Pipa STP & Sumpit 731,620,000.00

TOTAL PENGOLAHAN LIMBAH & INSTALASI PIPA AIR BEKAS, KOTOR & VENT 1,256,489,000.00

Rincian RAB MEP (Pengolahan Limbah dan Instalasi Air Kotor)


Universitas Muhammadiyah Tangerang
Page 3
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

I PENYEDIAAN, SUPLAI & INSTALASI PIPA AIR BERSIH


A Instalasi suplai air bersih
A.1 Instalasi & Penyambungan PDAM
1 Pipa Suplai ke Groundtank PPR-PN dim. 50mm m' 200.00 130,000.00 26,000,000.00
2 Fitting & aksesoris lot 1.00 5,000,000.00 5,000,000.00
3 Meter Air PDAM bh 1.00 7,500,000.00 7,500,000.00
4 Perijinan Penyambungan PDAM lot 1.00 - masuk ijin-ijin
Sub Total Instalasi & Penyambungan PDAM 38,500,000.00
A.2 Peralatan Utama Sistem Pompa Air
1 Pompa Sumur Dalam
Vertical multistage submersible pump kap. 11,58 m3/jam unit 1.00 210,000,000.00 210,000,000.00
- Head 100 meter, Pin = 7,5 KW, 380V, 50 Hz
- Lengkap dengan panel control
- Bor , 150 M m 250.00 230,000.00 57,500,000.00
- Casing F 6 ", PPR-PN Medium m 100.00 190,000.00 19,000,000.00
- Casing F 4 ", PPR-PN Medium m 150.00 170,000.00 25,500,000.00
- Pipa discharge dim 2", PPR-PN Medium m 120.00 125,000.00 15,000,000.00
- Water Level Control, Power Panel dll unit 1.00 4,500,000.00 4,500,000.00
- Instalasi kabel m 290.00 48,000.00 13,920,000.00
- Bak Kontrol, Koral, kerikil jagung ls 1.00 6,000,000.00 6,000,000.00
- Meter Deep Well unit 1.00 8,000,000.00 8,000,000.00
- Testing comissioning ls 1.00 10,000,000.00 10,000,000.00
Sub Total 369,420,000.00
2 Pompa Transfer Clean Water (P2-1 & P2-2)
- Vertical Multistage Pump set 2.00 88,000,000.00 176,000,000.00
- Head 85 m, kap. 12 m3/jam
- 6,5 kW / 3phase / 380 V / 50 Hz
- Alternate system operation
- Automatic Water Level Control Panel set 1.00 5,400,000.00 5,400,000.00
Sub Total 181,400,000.00
A.3 Water Treatment Plant (WTP)
1 Cartridge Filter CF-01 (Clean Water)
- Kapasitas 10,0 m3/jam set 2.00 60,000,000.00 120,000,000.00
- Filter Media Size : 10 micron
- c/w bypass piping
2 Sand Filter SF-01 (Clean Water)
- Kapasitas 10,0 m3/jam set 2.00 55,000,000.00 110,000,000.00
- Bahan : Fiberglass
- Filter Media : Silica Sand, Silica Gravel
- Operating Pressure, max 4 Bar
- Automatic Backwash System
- c/w pressure indicator & interconnection pipe
3 Instalasi Pemipaan ls 1.00 15,000,000.00 15,000,000.00
4 Testing Comissioning ls 1.00 15,000,000.00 15,000,000.00
Sub Total Water Treatment Plant (WTP) 260,000,000.00
A.3 Acessories Pompa
1 Gate valve dia.65mm set 6.00 980,000.00 5,880,000.00
dia.50mm set 8.00 830,000.00 6,640,000.00
dia.40mm set 11.00 760,000.00 8,360,000.00
dia.32mm set 22.00 700,000.00 15,400,000.00

Rincian RAB MEP (Penyediaan Suplai dan Pipa Air Bersih)


Universitas Muhammadiyah Tangerang
Page 4
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

2 Strainer dia.50mm set 4.00 830,000.00 3,320,000.00


dia.40mm set 2.00 760,000.00 1,520,000.00
dia.32mm set 4.00 700,000.00 2,800,000.00
3 Ceck valve dia.50mm set 4.00 750,000.00 3,000,000.00
dia.40mm set 6.00 690,000.00 4,140,000.00
dia.32mm set 8.00 650,000.00 5,200,000.00
4 Foot Valve dia.40mm set 4.00 580,000.00 2,320,000.00
dia.32mm set 4.00 530,000.00 2,120,000.00
4 Flexible Joint dia.50mm set 8.00 570,000.00 4,560,000.00
dia.40mm set 4.00 450,000.00 1,800,000.00
dia.32mm set 8.00 430,000.00 3,440,000.00
5 Water Meter / Flow Meter
dia.40mm set 2.00 600,000.00 1,200,000.00
dia.32mm set 1.00 580,000.00 580,000.00
Sub Total Acessories Pompa 72,280,000.00
A.4 Instalasi Pemipaan Pompa Pompa ke Reservoir & Rooftank
1 Pipa GIP dia.80mm (Header) set 7.00 1,900,000.00 13,300,000.00
dia.65mm set 40.00 1,760,000.00 70,400,000.00
dia.50mm set 24.00 1,650,000.00 39,600,000.00
dia.40mm set 164.00 1,590,000.00 260,760,000.00
dia.32mm set 233.00 1,550,000.00 361,150,000.00
3 Pemasangan Pompa set 4.00 4,500,000.00 18,000,000.00
4 Pemasangan Filter bh 8.00 4,000,000.00 32,000,000.00
5 Acessories dan material bantu lot 1.00 15,000,000.00 15,000,000.00
Sub Total Instalasi Pemipaan Pompa Pompa ke Reservoir & Rooftank 810,210,000.00
A.5 Instalasi Booster Pump Set
1 Booster pump set dgn spesifikasi: set 1.00 280,000,000.00 280,000,000.00
- Kapasitas: 3m3/jam
- Vertical multistage pump
- 2 x 1550 W/380V/50Hz/3Phase
- Head : 20 m, head max: 40 m
- Maximum operating pressure : 4 bar
- Enclosure class ((EC 34-5) IP65
- Flanged pipe connection
- Pararel alternate operation
complete with :
a. Pressure tank kapasitas 300 liter
b. Pressure switch control
c. Check valve
d. Footklep
e. In-Out Header dia. 80mm
2 Gate valve unit 3.00 2,100,000.00 6,300,000.00
3 Fleksible joint bh 4.00 900,000.00 3,600,000.00
4 Strainer bh 2.00 750,000.00 1,500,000.00
5 Check valve bh 2.00 800,000.00 1,600,000.00
6 Pemipaan m 10.00 500,000.00 5,000,000.00
7 Fiting & aksesoris ls 1.00 15,000,000.00 15,000,000.00
8 Pemasangan, instalasi dan alat bantu ls 1.00 20,000,000.00 20,000,000.00
9 Testing Comissioning ls 1.00 15,000,000.00 15,000,000.00
Sub Total Instalasi Booster Pump Set 348,000,000.00
B Tangki Air/Rooftank & Konstruksinya
B.1 Tangki Air/Rooftank Clean Water
1 Roof Tank Clean Water System Kap. 12x1000 Liter set 1.00 660,000,000.00 660,000,000.00

Rincian RAB MEP (Penyediaan Suplai dan Pipa Air Bersih)


Universitas Muhammadiyah Tangerang
Page 5
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

- Bahan Fiberglass Reinforced Plastic (FRP)


2 Konstruksi Pendukung/Pedestal Tangki Air ls 1.00 35,000,000.00 35,000,000.00
3 Instalasi pipa overflow dan penguras
- Gate valve dia.65mm bh 1.00 980,000.00 980,000.00
- Pipa PVC dia.65mm m 10.00 110,000.00 1,100,000.00
4 Fiting & aksesoris ls 1.00 15,000,000.00 15,000,000.00
Sub Total Tangki Air/Rooftank & Konstruksinya 712,080,000.00
B.2 Pompa overflow/kuras groundtank
1 Pompa overflow/kuras groundtank set 1.00 180,000,000.00 180,000,000.00
- Submersible pump with horizontal discharge port (1 set 2 unit pompa)
- Kapasitas 2,0 liter/dtk
- Head max 20 mtr
- 1,5 kW/380V/3phasa/50Hz
- complete with control panel bh 1.00 7,500,000.00 7,500,000.00
2 Pemipaan dari groundtank menuju sumur resapan - riol kota
- PVC AW dia. 50mm m 40.00 46,000.00 1,840,000.00
- Fitting &Aksesoris lot 1.00 5,000,000.00 5,000,000.00
Sub Total 194,340,000.00
C Instalasi Pipa Utama Air Bersih
C.1 Instalasi Pipa Riser Utama
1 Pipa PPR-PN10 dim. 50mm m' 197.00 240,000.00 47,280,000.00
2 Gate valve dia.65mm bh 4.00 980,000.00 3,920,000.00
3 Gate valve dia.50mm bh 2.00 830,000.00 1,660,000.00
4 Water Hammer bh 4.00 2,300,000.00 9,200,000.00
5 Pressure reducer valve set set 4.00 3,000,000.00 12,000,000.00
6 Fitting &Aksesoris lot 1.00 15,000,000.00 15,000,000.00
Sub Total Instalasi Pipa Riser Utama 89,060,000.00
C.4 Instalasi Pipa Air Bersih Lantai Basement 01
1 Pipa PPR-PN10 dim. 50mm m' 28.00 240,000.00 6,720,000.00
2 Pipa PPR-PN10 dim. 40mm m' 10.00 200,000.00 2,000,000.00
3 Gate valve 40mm bh 1.00 760,000.00 760,000.00
4 Fitting &Aksesoris lot 1.00 7,500,000.00 7,500,000.00
Sub Total Instalasi Pipa Air Bersih Lantai Basement 01 16,980,000.00
C.6 Instalasi Pipa Air Bersih Lantai Groundfloor
1 Pipa PPR PN10 dim. 40mm m' 6.00 200,000.00 1,200,000.00
2 Pipa PPR PN10 dim. 32mm m' 20.00 180,000.00 3,600,000.00
3 Pipa PPR PN10 dim. 25mm m' 45.00 165,000.00 7,425,000.00
4 Pipa PPR PN10 dim. 20mm m' 12.00 155,000.00 1,860,000.00
5 Pipa PPR PN10 dim. 15mm m' 10.00 140,000.00 1,400,000.00
6 Gate valve 40mm bh 1.00 760,000.00 760,000.00
7 Fitting &Aksesoris lot 1.00 9,000,000.00 9,000,000.00
Sub Total Instalasi Pipa Air Bersih Lantai Groundfloor 25,245,000.00
C.7 Instalasi Pipa Air Bersih Lantai 1
1 Pipa PPR PN10 dim. 40mm m' 14.00 200,000.00 2,800,000.00
2 Pipa PPR PN10 dim. 32mm m' 41.00 180,000.00 7,380,000.00
3 Pipa PPR PN10 dim. 25mm m' 58.00 165,000.00 9,570,000.00
4 Pipa PPR PN10 dim. 20mm m' 62.00 155,000.00 9,610,000.00
5 Pipa PPR PN10 dim. 15mm m' 26.00 140,000.00 3,640,000.00
6 Gate valve 40mm bh 2.00 760,000.00 1,520,000.00
7 Fitting &Aksesoris lot 1.00 9,000,000.00 9,000,000.00
Sub Total Instalasi Pipa Air Bersih Lantai 1 43,520,000.00

Rincian RAB MEP (Penyediaan Suplai dan Pipa Air Bersih)


Universitas Muhammadiyah Tangerang
Page 6
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

C.8 Instalasi Pipa Air Bersih Lantai 2


1 Pipa PPR PN10 dim. 32mm m' 9.00 180,000.00 1,620,000.00
2 Pipa PPR PN10 dim. 25mm m' 9.00 165,000.00 1,485,000.00
3 Pipa PPR PN10 dim. 20mm m' 18.00 155,000.00 2,790,000.00
4 Pipa PPR PN10 dim. 15mm m' 5.00 140,000.00 700,000.00
5 Gate valve 40mm bh 1.00 760,000.00 760,000.00
6 Fitting &Aksesoris lot 1.00 9,000,000.00 9,000,000.00
Sub Total Instalasi Pipa Air Bersih Lantai 2 16,355,000.00
C.9 Instalasi Pipa Air Bersih Lantai 3
1 Pipa PPR PN10 dim. 32mm m' 9.00 180,000.00 1,620,000.00
2 Pipa PPR PN10 dim. 25mm m' 9.00 165,000.00 1,485,000.00
3 Pipa PPR PN10 dim. 20mm m' 18.00 155,000.00 2,790,000.00
4 Pipa PPR PN10 dim. 15mm m' 5.00 140,000.00 700,000.00
5 Gate valve 40mm bh 1.00 760,000.00 760,000.00
6 Fitting &Aksesoris lot 1.00 9,000,000.00 9,000,000.00
Sub Total Instalasi Pipa Air Bersih Lantai 3 16,355,000.00
C.10 Instalasi Pipa Air Bersih Lantai 4
1 Pipa PPR PN10 dim. 32mm m' 9.00 180,000.00 1,620,000.00
2 Pipa PPR PN10 dim. 25mm m' 9.00 165,000.00 1,485,000.00
3 Pipa PPR PN10 dim. 20mm m' 18.00 155,000.00 2,790,000.00
4 Pipa PPR PN10 dim. 15mm m' 5.00 140,000.00 700,000.00
5 Gate valve 40mm bh 1.00 760,000.00 760,000.00
6 Fitting &Aksesoris lot 1.00 9,000,000.00 9,000,000.00
Sub Total Instalasi Pipa Air Bersih Lantai 4 16,355,000.00
C.11 Instalasi Pipa Air Bersih Lantai 5
1 Pipa PPR PN10 dim. 32mm m' 9.00 180,000.00 1,620,000.00
2 Pipa PPR PN10 dim. 25mm m' 9.00 165,000.00 1,485,000.00
3 Pipa PPR PN10 dim. 20mm m' 18.00 155,000.00 2,790,000.00
4 Pipa PPR PN10 dim. 15mm m' 5.00 140,000.00 700,000.00
5 Gate valve 40mm bh 1.00 760,000.00 760,000.00
6 Fitting &Aksesoris lot 1.00 9,000,000.00 9,000,000.00
Sub Total Instalasi Pipa Air Bersih Lantai 5 16,355,000.00
C.12 Instalasi Pipa Air Bersih Lantai 6
1 Pipa PPR PN10 dim. 40mm m' 4.00 200,000.00 800,000.00
2 Pipa PPR PN10 dim. 32mm m' 10.00 180,000.00 1,800,000.00
3 Pipa PPR PN10 dim. 25mm m' 24.00 165,000.00 3,960,000.00
4 Pipa PPR PN10 dim. 20mm m' 24.00 155,000.00 3,720,000.00
5 Pipa PPR PN10 dim. 15mm m' 3.00 140,000.00 420,000.00
6 Gate valve 40mm bh 2.00 760,000.00 1,520,000.00
7 Fitting &Aksesoris lot 1.00 9,000,000.00 9,000,000.00
Sub Total Instalasi Pipa Air Bersih Lantai 6 21,220,000.00
C.14 Instalasi Pipa Air Bersih Lantai 8
1 Pipa PPR PN10 dim. 40mm m' 4.00 200,000.00 800,000.00
2 Pipa PPR PN10 dim. 32mm m' 10.00 180,000.00 1,800,000.00
3 Pipa PPR PN10 dim. 25mm m' 24.00 165,000.00 3,960,000.00
4 Pipa PPR PN10 dim. 20mm m' 24.00 155,000.00 3,720,000.00
5 Pipa PPR PN10 dim. 15mm m' 4.00 140,000.00 560,000.00
6 Gate valve 40mm bh 2.00 760,000.00 1,520,000.00
7 Fitting &Aksesoris lot 1.00 9,000,000.00 9,000,000.00
Sub Total Instalasi Pipa Air Bersih Lantai 8 21,360,000.00
C.15 Instalasi Pipa Air Bersih Lantai 9

Rincian RAB MEP (Penyediaan Suplai dan Pipa Air Bersih)


Universitas Muhammadiyah Tangerang
Page 7
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

1 Pipa PPR PN10 dim. 40mm m' 4.00 200,000.00 800,000.00


2 Pipa PPR PN10 dim. 32mm m' 10.00 180,000.00 1,800,000.00
3 Pipa PPR PN10 dim. 25mm m' 24.00 165,000.00 3,960,000.00
4 Pipa PPR PN10 dim. 20mm m' 24.00 155,000.00 3,720,000.00
5 Pipa PPR PN10 dim. 15mm m' 4.00 140,000.00 560,000.00
6 Gate valve 40mm bh 2.00 760,000.00 1,520,000.00
7 Fitting &Aksesoris lot 1.00 9,000,000.00 9,000,000.00
Sub Total Instalasi Pipa Air Bersih Lantai 9 21,360,000.00
C.16 Instalasi Pipa Air Bersih Lantai 10
1 Pipa PPR PN10 dim. 40mm m' 4.00 200,000.00 800,000.00
2 Pipa PPR PN10 dim. 32mm m' 10.00 180,000.00 1,800,000.00
3 Pipa PPR PN10 dim. 25mm m' 24.00 165,000.00 3,960,000.00
4 Pipa PPR PN10 dim. 20mm m' 24.00 155,000.00 3,720,000.00
5 Pipa PPR PN10 dim. 15mm m' 4.00 140,000.00 560,000.00
6 Gate valve 40mm bh 2.00 760,000.00 1,520,000.00
7 Fitting &Aksesoris lot 1.00 9,000,000.00 9,000,000.00
Sub Total Instalasi Pipa Air Bersih Lantai 10 21,360,000.00
C.17 Instalasi Pipa Air Bersih Lantai 11
1 Pipa PPR PN10 dim. 40mm m' 4.00 200,000.00 800,000.00
2 Pipa PPR PN10 dim. 32mm m' 10.00 180,000.00 1,800,000.00
3 Pipa PPR PN10 dim. 25mm m' 24.00 165,000.00 3,960,000.00
4 Pipa PPR PN10 dim. 20mm m' 24.00 155,000.00 3,720,000.00
5 Pipa PPR PN10 dim. 15mm m' 4.00 140,000.00 560,000.00
6 Gate valve 40mm bh 2.00 760,000.00 1,520,000.00
7 Fitting &Aksesoris lot 1.00 9,000,000.00 9,000,000.00
Sub Total Instalasi Pipa Air Bersih Lantai 11 21,360,000.00
C.18 Instalasi Pipa Air Bersih Lantai 12
1 Pipa PPR PN10 dim. 40mm m' 4.00 200,000.00 800,000.00
2 Pipa PPR PN10 dim. 32mm m' 10.00 180,000.00 1,800,000.00
3 Pipa PPR PN10 dim. 25mm m' 24.00 165,000.00 3,960,000.00
4 Pipa PPR PN10 dim. 20mm m' 24.00 155,000.00 3,720,000.00
5 Pipa PPR PN10 dim. 15mm m' 4.00 140,000.00 560,000.00
6 Gate valve 40mm bh 2.00 760,000.00 1,520,000.00
7 Fitting &Aksesoris lot 1.00 9,000,000.00 9,000,000.00
Sub Total Instalasi Pipa Air Bersih Lantai 12 21,360,000.00
C.19 Instalasi Pipa Air Bersih Lantai 13
1 Pipa PPR PN10 dim. 40mm m' 4.00 200,000.00 800,000.00
2 Pipa PPR PN10 dim. 32mm m' 10.00 180,000.00 1,800,000.00
3 Pipa PPR PN10 dim. 25mm m' 24.00 165,000.00 3,960,000.00
4 Pipa PPR PN10 dim. 20mm m' 24.00 155,000.00 3,720,000.00
5 Pipa PPR PN10 dim. 15mm m' 4.00 140,000.00 560,000.00
6 Gate valve 40mm bh 2.00 760,000.00 1,520,000.00
7 Fitting &Aksesoris lot 1.00 9,000,000.00 9,000,000.00
Sub Total Instalasi Pipa Air Bersih Lantai 13 21,360,000.00
C.20 Instalasi Pipa Air Bersih Lantai 14
1 Pipa PPR PN10 dim. 40mm m' 4.00 200,000.00 800,000.00
2 Pipa PPR PN10 dim. 32mm m' 10.00 180,000.00 1,800,000.00
3 Pipa PPR PN10 dim. 25mm m' 24.00 165,000.00 3,960,000.00
4 Pipa PPR PN10 dim. 20mm m' 24.00 155,000.00 3,720,000.00
5 Pipa PPR PN10 dim. 15mm m' 4.00 140,000.00 560,000.00
6 Gate valve 40mm bh 2.00 760,000.00 1,520,000.00

Rincian RAB MEP (Penyediaan Suplai dan Pipa Air Bersih)


Universitas Muhammadiyah Tangerang
Page 8
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

7 Fitting &Aksesoris lot 1.00 9,000,000.00 9,000,000.00


Sub Total Instalasi Pipa Air Bersih Lantai 14 21,360,000.00
C.21 Instalasi Pipa Air Bersih Lantai 16
1 Pipa PPR PN10 dim. 40mm m' 4.00 200,000.00 800,000.00
2 Pipa PPR PN10 dim. 32mm m' 10.00 180,000.00 1,800,000.00
3 Pipa PPR PN10 dim. 25mm m' 24.00 165,000.00 3,960,000.00
4 Pipa PPR PN10 dim. 20mm m' 24.00 155,000.00 3,720,000.00
5 Pipa PPR PN10 dim. 15mm m' 4.00 140,000.00 560,000.00
6 Gate valve 40mm bh 2.00 760,000.00 1,520,000.00
7 Fitting &Aksesoris lot 1.00 9,000,000.00 9,000,000.00
Sub Total Instalasi Pipa Air Bersih Lantai 16 21,360,000.00
C.21 Instalasi Pipa Air Bersih Lantai 17
1 Pipa PPR PN10 dim. 40mm m' 4.00 200,000.00 800,000.00
2 Pipa PPR PN10 dim. 32mm m' 10.00 180,000.00 1,800,000.00
3 Pipa PPR PN10 dim. 25mm m' 24.00 165,000.00 3,960,000.00
4 Pipa PPR PN10 dim. 20mm m' 24.00 155,000.00 3,720,000.00
5 Pipa PPR PN10 dim. 15mm m' 4.00 140,000.00 560,000.00
6 Gate valve 40mm bh 2.00 760,000.00 1,520,000.00
7 Fitting &Aksesoris lot 1.00 9,000,000.00 9,000,000.00
Sub Total Instalasi Pipa Air Bersih Lantai 17 21,360,000.00
C.21 Instalasi Pipa Air Bersih Lantai 18
1 Pipa PPR PN10 dim. 40mm m' 4.00 200,000.00 800,000.00
2 Pipa PPR PN10 dim. 32mm m' 10.00 180,000.00 1,800,000.00
3 Pipa PPR PN10 dim. 25mm m' 24.00 165,000.00 3,960,000.00
4 Pipa PPR PN10 dim. 20mm m' 24.00 155,000.00 3,720,000.00
5 Pipa PPR PN10 dim. 15mm m' 4.00 140,000.00 560,000.00
6 Gate valve 40mm bh 2.00 760,000.00 1,520,000.00
7 Fitting &Aksesoris lot 1.00 9,000,000.00 9,000,000.00
Sub Total Instalasi Pipa Air Bersih Lantai 18 21,360,000.00
C.21 Instalasi Pipa Air Bersih Lantai 19
1 Pipa PPR PN10 dim. 40mm m' 5.00 200,000.00 1,000,000.00
2 Pipa PPR PN10 dim. 32mm m' 12.00 180,000.00 2,160,000.00
3 Pipa PPR PN10 dim. 25mm m' 32.00 165,000.00 5,280,000.00
4 Pipa PPR PN10 dim. 20mm m' 57.00 155,000.00 8,835,000.00
5 Pipa PPR PN10 dim. 15mm m' 7.00 140,000.00 980,000.00
6 Gate valve 40mm bh 2.00 760,000.00 1,520,000.00
7 Fitting &Aksesoris lot 1.00 9,000,000.00 9,000,000.00
Sub Total Instalasi Pipa Air Bersih Lantai 19 28,775,000.00
C.21 Instalasi Pipa Air Bersih Lantai Atap
1 Pipa PPR-PN10 dim. 50mm m' 146.00 240,000.00 35,040,000.00
2 Gate valve 40mm bh 7.00 200,000.00 1,400,000.00
3 Fitting &Aksesoris lot 1.00 9,000,000.00 9,000,000.00
Sub Total Instalasi Pipa Air Bersih Lantai Atap 45,440,000.00
C.23 Instalasi Pipa Air Bersih Siteplan dan Kantin
1 Pipa PPR PN10 dim. 25mm m' 30.00 165,000.00 4,950,000.00
2 Pipa PPR PN10 dim. 20mm m' 57.00 155,000.00 8,835,000.00
3 Pipa PPR PN10 dim. 15mm m' 20.00 140,000.00 2,800,000.00
4 Gate valve 25mm bh 2.00 560,000.00 1,120,000.00
5 Water meter / Flow meter bh 1.00 580,000.00 580,000.00
5 Fitting &Aksesoris lot 1.00 9,000,000.00 9,000,000.00
Sub Total Instalasi Pipa Air Bersih Siteplan dan Kantin 27,285,000.00

Rincian RAB MEP (Penyediaan Suplai dan Pipa Air Bersih)


Universitas Muhammadiyah Tangerang
Page 9
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

TOTAL PENYEDIAAN, SUPLAI & INSTALASI PIPA AIR BERSIH 3,562,775,000.00

Rincian RAB MEP (Penyediaan Suplai dan Pipa Air Bersih)


Universitas Muhammadiyah Tangerang
Page 10
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

III DRAINASI BANGUNAN & INSTALASI AIR HUJAN


A Roofdrain & Instalasi Pipa Air Hujan Lantai Atap
1 Roofdrain dia. 100mm Cast Iron m' 22.00 3,200,000.00 70,400,000.00
2 Pipa PVC dim. 200mm m' 130.00 230,000.00 29,900,000.00
4 Pipa PVC dim. 100mm m' 1,540.00 140,000.00 215,600,000.00
5 Aksesoris, fitting, elbow dan alat bantu lot 1.00 5,000,000.00 5,000,000.00
sub total 320,900,000.00
C Saluran drainase & Sumur Resapan Site
1 Sumur Peresapan, Kapasitas 2,3 m³ unit 11.00 18,000,000.00 198,000,000.00
2 Saluran Drainase tutup beton uk.300x400mm m' 120.00 350,000.00 42,000,000.00
3 Saluran Drainase dgn tutup grill besi finishing anti karat uk.300x200mm m' 20.00 280,000.00 5,600,000.00
4 Bak Kontrol 400x400mm m' 24.00 4,500,000.00 108,000,000.00
5 Galian dan urugan lot 1.00 7,500,000.00 7,500,000.00
6 Gutter Basement - 01, ukuran 30cm x 5cm m' 90.00 230,000.00 20,700,000.00
sub total 381,800,000.00
D Instalasi Sumpit Drainase
1 Sumpit Drainase, Kapasitas 6,0m3, uk. 240cmx240cmx150cm, termasuk unit 1.00 160,000,000.00 160,000,000.00
- Bak kontrol 30x30cm
- Manhole 40x40cm
2 Pompa sumpit drainase set 1.00 190,000,000.00 190,000,000.00
- Submersible pump with horizontal discharge port
- Kapasitas 2,0 liter/dtk
- Head max 20 mtr
- 1,5 kW/380V/3phasa/50Hz
- complete with control panel
3 Pemipaan dari sumpit drainase menuju sumur resapan - riol kota
- PVC AW dia. 50mm m 40.00 46,000.00 1,840,000.00
- Fitting &Aksesoris lot 1.00 5,000,000.00 5,000,000.00
sub total 356,840,000.00
E Instalasi Pipa Drain AC
1 Pipa PVC dim. 75mm (riser) m' 280.00 120,000.00 33,600,000.00
2 Aksesoris, fitting, elbow dan alat bantu lot 1.00 5,000,000.00 5,000,000.00
sub total 38,600,000.00

TOTAL DRAINASI BANGUNAN & INSTALASI AIR HUJAN 1,098,140,000.00

Rincian RAB MEP (Drainase Bangunan dan Instalasi Air Hujan)


Universitas Muhammadiyah Tangerang
Page 11
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

IV SISTEM TATA UDARA & VENTILASI


A TATA UDARA TIPE SPLIT SYSTEM
A.1 Instalasi Tata Udara Lantai Ground
1 AC Ceilling Cassete 2,5 PK, 3 ph, 24900 Btu/h unit 9.00 35,000,000.00 315,000,000.00
2 Instalasi pipa refrigerant, dan pipa drain titik 9.00 650,000.00 5,850,000.00
3 Instalasi power dan kontrol AC titik 9.00 550,000.00 4,950,000.00
4 Ceiling Mount Exhaust Fan unit 6.00 2,500,000.00 15,000,000.00
5 Instalasi power, kontrol exhaust fan & ducting PVC titik 6.00 550,000.00 3,300,000.00
6 Ceiling Fan 50", 50Watt, 6250 CFM unit 4.00 1,500,000.00 6,000,000.00
7 Instalasi power ceiling fan titik 4.00 500,000.00 2,000,000.00
Sub Total Instalasi Tata Udara Lantai Ground 352,100,000.00
A.2 Instalasi Tata Udara Lantai 1
1 Ceiling Fan 50", 50Watt, 6250 CFM unit 1.00 1,500,000.00 1,500,000.00
2 Instalasi power ceiling fan titik 1.00 500,000.00 500,000.00
3 Ceiling Mount Exhaust Fan unit 4.00 2,500,000.00 10,000,000.00
4 Instalasi power, kontrol exhaust fan & ducting PVC titik 4.00 550,000.00 2,200,000.00
Sub Total Instalasi Tata Udara Lantai 1 14,200,000.00
A.3 Instalasi Tata Udara Lantai 2
1 Ceiling Mount Exhaust Fan unit 4.00 2,500,000.00 10,000,000.00
2 Instalasi power, kontrol exhaust fan & ducting PVC titik 4.00 550,000.00 2,200,000.00
Sub Total Instalasi Tata Udara Lantai 2 12,200,000.00
A.4 Instalasi Tata Udara Lantai 3
1 Ceiling Mount Exhaust Fan unit 4.00 2,500,000.00 10,000,000.00
2 Instalasi power, kontrol exhaust fan & ducting PVC titik 4.00 550,000.00 2,200,000.00
Sub Total Instalasi Tata Udara Lantai 3 12,200,000.00
A.5 Instalasi Tata Udara Lantai 4
1 Ceiling Mount Exhaust Fan unit 4.00 2,500,000.00 10,000,000.00
2 Instalasi power, kontrol exhaust fan & ducting PVC titik 4.00 550,000.00 2,200,000.00
Sub Total Instalasi Tata Udara Lantai 4 12,200,000.00
A.6 Instalasi Tata Udara Lantai 5
1 Ceiling Mount Exhaust Fan unit 4.00 2,500,000.00 10,000,000.00
2 Instalasi power, kontrol exhaust fan & ducting PVC titik 4.00 550,000.00 2,200,000.00
Sub Total Instalasi Tata Udara Lantai 5 12,200,000.00
A.7 Instalasi Tata Udara Lantai 6
1 AC Standing Floor 5,0 PK, 3 ph, 36000 Btu/h unit 4.00 24,000,000.00 96,000,000.00
2 AC Ceilling Cassete 3,0 PK, 3 ph, 28200 Btu/h unit 4.00 45,000,000.00 180,000,000.00
3 AC Split Wall Mounted 2,0 PK, 1 ph, 18000 Btu/h unit 1.00 7,600,000.00 7,600,000.00
4 Instalasi pipa refrigerant, dan pipa drain titik 9.00 650,000.00 5,850,000.00
5 Instalasi power dan kontrol AC titik 9.00 550,000.00 4,950,000.00
6 Ceiling Mount Exhaust Fan unit 8.00 2,500,000.00 20,000,000.00
7 Instalasi power, kontrol exhaust fan & ducting PVC titik 8.00 550,000.00 4,400,000.00
Sub Total Instalasi Tata Udara Lantai 6 318,800,000.00
A.8 Instalasi Tata Udara Lantai 7
1 AC Ceilling Cassete 3,0 PK, 3 ph, 28200 Btu/h unit 6.00 45,000,000.00 270,000,000.00
2 AC Ceilling Cassete 4,0 PK, 3 ph, 36000 Btu/h unit 5.00 55,000,000.00 275,000,000.00
3 Instalasi pipa refrigerant, dan pipa drain titik 11.00 650,000.00 7,150,000.00
4 Instalasi power dan kontrol AC titik 11.00 550,000.00 6,050,000.00
5 Ceiling Mount Exhaust Fan unit 8.00 2,500,000.00 20,000,000.00
6 Instalasi power, kontrol exhaust fan & ducting PVC titik 8.00 550,000.00 4,400,000.00
Sub Total Instalasi Tata Udara Lantai 7 582,600,000.00
A.9 Instalasi Tata Udara Lantai 8
1 AC Split Wall Mounted 2,5 PK, 1 ph, 21600 Btu/h unit 2.00 9,000,000.00 18,000,000.00
2 AC Split Wall Mounted 2,0 PK, 1 ph, 18000 Btu/h unit 8.00 7,600,000.00 60,800,000.00
3 Instalasi pipa refrigerant, dan pipa drain titik 10.00 650,000.00 6,500,000.00
4 Instalasi power dan kontrol AC titik 10.00 550,000.00 5,500,000.00

Rincian RAB MEP (Sistem Udara dan Ventilasi)


Universitas Muhammadiyah Tangerang
Page 12
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

5 Ceiling Mount Exhaust Fan unit 10.00 2,500,000.00 25,000,000.00


6 Instalasi power, kontrol exhaust fan & ducting PVC titik 10.00 550,000.00 5,500,000.00
Sub Total Instalasi Tata Udara Lantai 8 121,300,000.00
A.10 Instalasi Tata Udara Lantai 9
1 AC Split Wall Mounted 2,5 PK, 1 ph, 21600 Btu/h unit 2.00 9,000,000.00 18,000,000.00
2 AC Split Wall Mounted 2,0 PK, 1 ph, 18000 Btu/h unit 8.00 7,600,000.00 60,800,000.00
3 Instalasi pipa refrigerant, dan pipa drain titik 10.00 650,000.00 6,500,000.00
4 Instalasi power dan kontrol AC titik 10.00 550,000.00 5,500,000.00
5 Ceiling Mount Exhaust Fan unit 10.00 2,500,000.00 25,000,000.00
6 Instalasi power, kontrol exhaust fan & ducting PVC titik 10.00 550,000.00 5,500,000.00
Sub Total Instalasi Tata Udara Lantai 9 121,300,000.00
A.11 Instalasi Tata Udara Lantai 10
1 AC Split Wall Mounted 2,5 PK, 1 ph, 21600 Btu/h unit 2.00 9,000,000.00 18,000,000.00
2 AC Split Wall Mounted 2,0 PK, 1 ph, 18000 Btu/h unit 8.00 7,600,000.00 60,800,000.00
3 Instalasi pipa refrigerant, dan pipa drain titik 10.00 650,000.00 6,500,000.00
4 Instalasi power dan kontrol AC titik 10.00 550,000.00 5,500,000.00
5 Ceiling Mount Exhaust Fan unit 10.00 2,500,000.00 25,000,000.00
6 Instalasi power, kontrol exhaust fan & ducting PVC titik 10.00 550,000.00 5,500,000.00
Sub Total Instalasi Tata Udara Lantai 10 121,300,000.00
A.12 Instalasi Tata Udara Lantai 11
1 AC Split Wall Mounted 2,5 PK, 1 ph, 21600 Btu/h unit 2.00 9,000,000.00 18,000,000.00
2 AC Split Wall Mounted 2,0 PK, 1 ph, 18000 Btu/h unit 8.00 7,600,000.00 60,800,000.00
3 Instalasi pipa refrigerant, dan pipa drain titik 10.00 650,000.00 6,500,000.00
4 Instalasi power dan kontrol AC titik 10.00 550,000.00 5,500,000.00
5 Ceiling Mount Exhaust Fan unit 10.00 2,500,000.00 25,000,000.00
6 Instalasi power, kontrol exhaust fan & ducting PVC titik 10.00 550,000.00 5,500,000.00
Sub Total Instalasi Tata Udara Lantai 11 121,300,000.00
A.13 Instalasi Tata Udara Lantai 12
1 AC Split Wall Mounted 2,5 PK, 1 ph, 21600 Btu/h unit 2.00 9,000,000.00 18,000,000.00
2 AC Split Wall Mounted 2,0 PK, 1 ph, 18000 Btu/h unit 8.00 7,600,000.00 60,800,000.00
3 Instalasi pipa refrigerant, dan pipa drain titik 10.00 650,000.00 6,500,000.00
4 Instalasi power dan kontrol AC titik 10.00 550,000.00 5,500,000.00
5 Ceiling Mount Exhaust Fan unit 10.00 2,500,000.00 25,000,000.00
6 Instalasi power, kontrol exhaust fan & ducting PVC titik 10.00 550,000.00 5,500,000.00
Sub Total Instalasi Tata Udara Lantai 12 121,300,000.00
A.14 Instalasi Tata Udara Lantai 13
1 AC Split Wall Mounted 2,5 PK, 1 ph, 21600 Btu/h unit 2.00 9,000,000.00 18,000,000.00
2 AC Split Wall Mounted 2,0 PK, 1 ph, 18000 Btu/h unit 8.00 7,600,000.00 60,800,000.00
3 Instalasi pipa refrigerant, dan pipa drain titik 10.00 650,000.00 6,500,000.00
4 Instalasi power dan kontrol AC titik 10.00 550,000.00 5,500,000.00
5 Ceiling Mount Exhaust Fan unit 10.00 2,500,000.00 25,000,000.00
6 Instalasi power, kontrol exhaust fan & ducting PVC titik 10.00 550,000.00 5,500,000.00
Sub Total Instalasi Tata Udara Lantai 13 121,300,000.00
A.15 Instalasi Tata Udara Lantai 14
1 AC Split Wall Mounted 2,5 PK, 1 ph, 21600 Btu/h unit 2.00 9,000,000.00 18,000,000.00
2 AC Split Wall Mounted 2,0 PK, 1 ph, 18000 Btu/h unit 8.00 7,600,000.00 60,800,000.00
3 Instalasi pipa refrigerant, dan pipa drain titik 10.00 650,000.00 6,500,000.00
4 Instalasi power dan kontrol AC titik 10.00 550,000.00 5,500,000.00
5 Ceiling Mount Exhaust Fan unit 10.00 2,500,000.00 25,000,000.00
6 Instalasi power, kontrol exhaust fan & ducting PVC titik 10.00 550,000.00 5,500,000.00
Sub Total Instalasi Tata Udara Lantai 14 121,300,000.00
A.16 Instalasi Tata Udara Lantai 15
1 AC Split Wall Mounted 2,5 PK, 1 ph, 21600 Btu/h unit 2.00 9,000,000.00 18,000,000.00
2 AC Split Wall Mounted 2,0 PK, 1 ph, 18000 Btu/h unit 8.00 7,600,000.00 60,800,000.00
3 Instalasi pipa refrigerant, dan pipa drain titik 10.00 650,000.00 6,500,000.00
4 Instalasi power dan kontrol AC titik 10.00 550,000.00 5,500,000.00

Rincian RAB MEP (Sistem Udara dan Ventilasi)


Universitas Muhammadiyah Tangerang
Page 13
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

5 Ceiling Mount Exhaust Fan unit 10.00 2,500,000.00 25,000,000.00


6 Instalasi power, kontrol exhaust fan & ducting PVC titik 10.00 550,000.00 5,500,000.00
Sub Total Instalasi Tata Udara Lantai 15 121,300,000.00
A.17 Instalasi Tata Udara Lantai 16
1 AC Split Wall Mounted 2,5 PK, 1 ph, 21600 Btu/h unit 2.00 9,000,000.00 18,000,000.00
2 AC Split Wall Mounted 2,0 PK, 1 ph, 18000 Btu/h unit 8.00 7,600,000.00 60,800,000.00
3 Instalasi pipa refrigerant, dan pipa drain titik 10.00 650,000.00 6,500,000.00
4 Instalasi power dan kontrol AC titik 10.00 550,000.00 5,500,000.00
5 Ceiling Mount Exhaust Fan unit 10.00 2,500,000.00 25,000,000.00
6 Instalasi power, kontrol exhaust fan & ducting PVC titik 10.00 550,000.00 5,500,000.00
Sub Total Instalasi Tata Udara Lantai 16 121,300,000.00
A.18 Instalasi Tata Udara Lantai 17
1 AC Split Wall Mounted 2,5 PK, 1 ph, 21600 Btu/h unit 2.00 9,000,000.00 18,000,000.00
2 AC Split Wall Mounted 2,0 PK, 1 ph, 18000 Btu/h unit 8.00 7,600,000.00 60,800,000.00
3 Instalasi pipa refrigerant, dan pipa drain titik 10.00 650,000.00 6,500,000.00
4 Instalasi power dan kontrol AC titik 10.00 550,000.00 5,500,000.00
5 Ceiling Mount Exhaust Fan unit 10.00 2,500,000.00 25,000,000.00
6 Instalasi power, kontrol exhaust fan & ducting PVC titik 10.00 550,000.00 5,500,000.00
Sub Total Instalasi Tata Udara Lantai 17 121,300,000.00
A.19 Instalasi Tata Udara Lantai 18
1 AC Split Wall Mounted 2,5 PK, 1 ph, 21600 Btu/h unit 2.00 9,000,000.00 18,000,000.00
2 AC Split Wall Mounted 2,0 PK, 1 ph, 18000 Btu/h unit 8.00 7,600,000.00 60,800,000.00
3 Instalasi pipa refrigerant, dan pipa drain titik 10.00 650,000.00 6,500,000.00
4 Instalasi power dan kontrol AC titik 10.00 550,000.00 5,500,000.00
5 Ceiling Mount Exhaust Fan unit 10.00 2,500,000.00 25,000,000.00
6 Instalasi power, kontrol exhaust fan & ducting PVC titik 10.00 550,000.00 5,500,000.00
Sub Total Instalasi Tata Udara Lantai 18 121,300,000.00
A.20 Instalasi Tata Udara Lantai 19
1 AC Ceilling Cassete 2,5 PK, 3 ph, 24000 Btu/h unit 4.00 35,000,000.00 140,000,000.00
2 AC Split Wall Mounted 2,5 PK, 1 ph, 21600 Btu/h unit 1.00 9,000,000.00 9,000,000.00
3 AC Split Wall Mounted 2,0 PK, 1 ph, 18000 Btu/h unit 2.00 7,600,000.00 15,200,000.00
4 AC Split Wall Mounted 1,5 PK, 1 ph, 9900 Btu/h unit 4.00 5,800,000.00 23,200,000.00
5 Instalasi pipa refrigerant, dan pipa drain titik 11.00 650,000.00 7,150,000.00
6 Instalasi power dan kontrol AC titik 11.00 550,000.00 6,050,000.00
7 Ceiling Mount Exhaust Fan unit 12.00 2,500,000.00 30,000,000.00
8 Instalasi power, kontrol exhaust fan & ducting PVC titik 12.00 550,000.00 6,600,000.00
Sub Total Instalasi Tata Udara Lantai 19 237,200,000.00
B SISTEM EXHAUST FAN
B.1 LANTAI BASEMENT - 1 ( PARKIR )
1 Peralatan Utama
Pengadaan dan pemasangan peralatan utama lengkap dengan support & accessories.
Exhaust Fan 01 unit 1.00 27,500,000.00 27,500,000.00
Tipe : Centrifugal Inline Duct
Kap : 9.500 CFM
2 Pemasangan, Support & Aksesories ls 1.00 8,000,000.00 8,000,000.00
3 Pekerjaan instalasi ducting tanpa isolasi ( dicat ), Baja Lapis Seng
- BJLS - 50 m2 16.00 340,000.00 5,440,000.00
- BJLS - 60 m2 122.00 365,000.00 44,530,000.00
- BJLS - 80 m2 68.00 380,000.00 25,840,000.00
- BJLS - 100 m2 8.00 420,000.00 3,360,000.00
4 Pekerjaan instalasi Supply Air Grille ( SAG ) dan Exhaust Air Grille ( EAG )
Alluminium Anodized, Fixed Griile ( horisontal blade didepan dan vertikal
blade dibelakang )
Supply Air Grille ( SAG )
- 900 x 500 bh 6.00 2,300,000.00 13,800,000.00
- 1200 x 750 bh 2.00 4,500,000.00 9,000,000.00

Rincian RAB MEP (Sistem Udara dan Ventilasi)


Universitas Muhammadiyah Tangerang
Page 14
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

Exhaust Air Grille ( EAG )


- 700 x 350 bh 22.00 2,600,000.00 57,200,000.00
Pressure Air Grille ( PAR )
- 500 x 400 bh 2.00 3,000,000.00 6,000,000.00
5 Material Bantu lot 1.00 7,500,000.00 7,500,000.00
6 Instalasi Exhaust Fan Toilet Lantai Basement 1
- Wall Mount Exhaust Fan 8", 480 CMH, 25 Watt unit 2.00 6,500,000.00 13,000,000.00
- Instalasi power dan kontrol Fan titik 2.00 550,000.00 1,100,000.00
Sub Total SISTEM EXHAUST FAN 222,270,000.00
C EXHAUST & SUPPLY PRESSURIZED FAN
Pengadaan dan pemasangan unit fan / blower, lengkap dengan support, spring vibration mounting, accessories,
semua material bantu yang diperlukannya sesuai petunjuk dari pabrik dan spesifikasi teknis maupun seperti terlihat dalam data teknis gambar perencanaan
Harga satuan unit sudah termasuk upah
1 LANTAI - ATAP
a KODE UNIT : PF-1, PF-2 & PF-3 unit 3.00 37,000,000.00 111,000,000.00
- Type : Centrifugal Exhaust Fan Duct Conn. Belt Drive
- Kapasitas 20.750 CFM
- Static pressure : 3,0 Inch/wg
- Noise Level : 72
- 15 kW, 3ph, 380V
- Rpm : 1450 max
2 Panel Kontrol Pressurized Fan titik 3.00 760,000.00 2,280,000.00
3 Instalasi kontrol interkoneksi ke sistem Fire Alarm & Hydrant ls 3.00 8,000,000.00 24,000,000.00
4 Pekerjaan instalasi ducting tanpa isolasi ( dicat ), Baja Lapis Seng
- BJLS - 50 m2 152.00 340,000.00 51,680,000.00
- BJLS - 60 m2 237.50 365,000.00 86,687,500.00
6 Pekerjaan instalasi Pressure Air Grille (PAG ) dan Pressure Air Diffuser (PAD)
Alluminium Anodized, Fixed Griile ( horisontal blade didepan dan vertikal
blade dibelakang )
Pressure Air Grille ( PAR )
- 800 x 500 bh 58.00 2,300,000.00 133,400,000.00
7 Material Bantu lot 1.00 5,000,000.00 5,000,000.00
b KODE UNIT : EF-A unit 2.00 9,000,000.00 18,000,000.00
- Type : Centrifugal Exhaust Fan Duct Conn.
- Kapasitas 4500 CFM
- termasuk instalasi pemasangan
- c/w control panel
c Ducting exhaust vertical (posisi di shaft) set 2.00 15,000,000.00 30,000,000.00
(ukuran sesuai gambar perencanaan)
Sub Total EXHAUST & SUPPLY PRESSURIZED FAN 462,047,500.00

TOTAL SISTEM TATA UDARA & VENTILASI 3,572,317,500.00

Rincian RAB MEP (Sistem Udara dan Ventilasi)


Universitas Muhammadiyah Tangerang
Page 15
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

IV SISTEM PENANGGULANGAN KEBAKARAN


A RUANG POMPA HYDRANT
A.1 Main Equipment Hydrant
Pompa sudah lengkap terkopel dengan motor diatas baseplate dan lengkap dengan
1 (satu) set Panel Control Automatic, Standard NFPA 20 .
1 Electric Fire Pump (EFP)
Pengadaan dan Pemasangan Pompa Electric Fire Pump unit 1.00 75,000,000.00 75,000,000.00
- Type Centrifugal Horizontal Split Case Pump
- Kapasitas : 750 GPM
- Head : 177 meter
- Daya : 167 KW, 3 Ph / 380 V / 50 Hz
- Putaran : 2900 rpm
- Lengkap dengan Panel Controller NPFA Standard
2 Diesel Fire Pump (DFP)
Pengadaan dan Pemasangan Pompa Diesel Fire Pump unit 1.00 98,000,000.00 98,000,000.00
- Type Centrifugal Horizontal Split Case Pump
- Kapasitas : 750 GPM
- Head : 177 meter
- Daya : 200 KW, 3 Ph / 380 V / 50 Hz
- Putaran : 2900 rpm
- Lengkap dengan Panel Controller NPFA Standard
Spesifikasi Pompa :
Pompa sudah lengkap terkopel dengan diesel engine diatas baseplate, lengkap dengan
Radiator, Muffler, Flexible pipe, Fuel tank, Accu, Panel Electric Starting Manual, Panel Control
Starting Manual dan Panel Control Automatic, Standard NPFA 20
3 Jockey Hydrant Pump (JFP)
Pompa Jockey / Jockey Hydrant Pump (JFP) unit 1.00 65,000,000.00 65,000,000.00
- Type Vertical Multistage Centrifugal Pump
- Kapasitas : 25 GPM
- Head : 187 meter
- Daya : 5,8 KW, 3 Ph / 380 V / 50 Hz
- Putaran : 2900 rpm
- Lengkap dengan Jocky Controller NPFA Standard
Sub Total Main Equipment Hydrant 238,000,000.00
A.2 Instalasi & Pemipaan Ruang Pompa
1 Header dia. 200 mm lot 1.00 18,000,000.00 18,000,000.00
2 Pengadaan dan Pemasangan Pipa BS sch 40
- dia. 40 mm m 2.00 650,000.00 1,300,000.00
- dia. 50 mm m 2.00 760,000.00 1,520,000.00
- dia. 100 mm m 3.00 1,150,000.00 3,450,000.00
- dia. 150 mm m 3.00 1,230,000.00 3,690,000.00
3 Pengadaan dan Pemasangan kabel power dari panel PP
Hidran ke panel kontrol pompa (MCC) ke motor pompa
2 x FRC 4 x 1 x 240 mm² ( pompa elektrik ) m 120.00 450,000.00 54,000,000.00
FRC 4 x 6 mm² m 15.00 32,000.00 480,000.00
4 Gate Valve
- dia. 40 mm bh 1.00 2,400,000.00 2,400,000.00
- dia. 50 mm bh 1.00 2,800,000.00 2,800,000.00
- dia. 100 mm bh 4.00 3,400,000.00 13,600,000.00
- dia. 150 mm bh 5.00 4,200,000.00 21,000,000.00
5 Strainer Valve
- dia .50 mm bh 1.00 3,200,000.00 3,200,000.00
- dia 150 mm bh 2.00 5,700,000.00 11,400,000.00
6 Check Valve
- dia. 40 mm bh 1.00 2,600,000.00 2,600,000.00

Rincian RAB MEP (Sistem Penanggulangan Kebakaran)


Universitas Muhammadiyah Tangerang
Page 16
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

- dia. 150 mm bh 2.00 4,800,000.00 9,600,000.00


7 Flexible Joint
- dia. 40 mm bh 1.00 1,800,000.00 1,800,000.00
- dia. 50 mm bh 1.00 2,200,000.00 2,200,000.00
- dia. 100 mm bh 2.00 3,500,000.00 7,000,000.00
- dia. 150 mm bh 2.00 5,300,000.00 10,600,000.00
8 Safety Valve dia 100 mm, lengkap dengan instalasi set 1.00 9,500,000.00 9,500,000.00
9 Perpipaan ke ground tank
- Alarm gong bh 1.00 25,000,000.00 25,000,000.00
- Pressure Switch bh 2.00 12,000,000.00 24,000,000.00
- Pressure Gauge bh 1.00 9,500,000.00 9,500,000.00
10 Testing & comissioning ls 1.00 - -
Sub Total Instalasi & Pemipaan Ruang Pompa 238,640,000.00
B INSTALASI PEMIPAAN HYDRANT
B.1 Instalasi Pemipaan Hydrant Luar
1 Outdoor Hydrant Box bh 4.00 5,500,000.00 22,000,000.00
2 Hidrant Pillar bh 4.00 9,000,000.00 36,000,000.00
3 Seammese Connection bh 2.00 800,000.00 1,600,000.00
4 Pengadaan dan Pemasangan BS sch 40 lengkap dengan isolasi
gali urug dan peralatan bantu
- dia. 100 mm m 160.00 1,150,000.00 184,000,000.00
- dia. 150 mm m 98.00 1,350,000.00 132,300,000.00
5 Accessories
- Gate valve dia 65 mm bh 4.00 3,100,000.00 12,400,000.00
-Check valve dia.150mm bh 1.00 4,800,000.00 4,800,000.00
6 Material Bantu lot 1.00 8,000,000.00 8,000,000.00
6 Galian-urugan ls 1.00 15,000,000.00 15,000,000.00
Sub Total Instalasi Pemipaan Hydrant Luar 416,100,000.00
B.2 Instalasi Indoor Hydrant Lantai Basement 1
1 Pengadaan dan Pemasangan Pipa BS sch 40
- dia. 65 mm m 35.00 820,000.00 28,700,000.00
- dia. 80 mm m 8.00 930,000.00 7,440,000.00
2 Indoor Hydrant Box lengkap dengan nozzel dan Accessories sbb : unit 2.00 15,000,000.00 30,000,000.00
- Gate valve dia 65 mm
- Valve Vander Hyder
3 Gate Valve
- dia 80 mm bh 1.00 1,250,000.00 1,250,000.00
4 Material Bantu ls 1.00 8,000,000.00 8,000,000.00
Sub Total Instalasi Indoor Hydrant Lantai Basement 1 75,390,000.00
B.3 Instalasi Indoor Hydrant Lantai Groundfloor
1 Pengadaan dan Pemasangan Pipa BS sch 40
- dia. 65 mm m 44.00 820,000.00 36,080,000.00
- dia. 80 mm m 8.00 930,000.00 7,440,000.00
2 Indoor Hydrant Box lengkap dengan nozzel dan Accessories sbb : unit 2.00 15,000,000.00 30,000,000.00
- Gate valve dia 65 mm
- Valve Vander Hyder
3 Gate Valve
- dia 80 mm bh 1.00 1,250,000.00 1,250,000.00
4 Material Bantu ls 1.00 8,000,000.00 8,000,000.00
Sub Total Instalasi Indoor Hydrant Lantai Groundfloor 82,770,000.00
B.4 Instalasi Indoor Hydrant Lantai 1
1 Pengadaan dan Pemasangan Pipa BS sch 40
- dia. 65 mm m 30.00 820,000.00 24,600,000.00
- dia. 80 mm m 8.00 930,000.00 7,440,000.00
2 Indoor Hydrant Box lengkap dengan nozzel dan Accessories sbb : unit 2.00 15,000,000.00 30,000,000.00

Rincian RAB MEP (Sistem Penanggulangan Kebakaran)


Universitas Muhammadiyah Tangerang
Page 17
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

- Gate valve dia 65 mm


- Valve Vander Hyder
3 Gate Valve
- dia 80 mm bh 1.00 1,250,000.00 1,250,000.00
4 Material Bantu ls 1.00 8,000,000.00 8,000,000.00
Sub Total Instalasi Indoor Hydrant Lantai 1 71,290,000.00
B.5 Instalasi Indoor Hydrant Lantai 2
1 Pengadaan dan Pemasangan Pipa BS sch 40
- dia. 65 mm m 46.00 820,000.00 37,720,000.00
- dia. 80 mm m 4.00 930,000.00 3,720,000.00
2 Indoor Hydrant Box lengkap dengan nozzel dan Accessories sbb : unit 2.00 15,000,000.00 30,000,000.00
- Gate valve dia 65 mm
- Valve Vander Hyder
3 Gate Valve
- dia 80 mm bh 1.00 1,250,000.00 1,250,000.00
4 Material Bantu ls 1.00 8,000,000.00 8,000,000.00
Sub Total Instalasi Indoor Hydrant Lantai 2 80,690,000.00
B.6 Instalasi Indoor Hydrant Lantai 3
1 Pengadaan dan Pemasangan Pipa BS sch 40
- dia. 65 mm m 46.00 820,000.00 37,720,000.00
- dia. 80 mm m 4.00 930,000.00 3,720,000.00
2 Indoor Hydrant Box lengkap dengan nozzel dan Accessories sbb : unit 2.00 15,000,000.00 30,000,000.00
- Gate valve dia 65 mm
- Valve Vander Hyder
3 Gate Valve
- dia 80 mm bh 1.00 1,250,000.00 1,250,000.00
4 Material Bantu ls 1.00 8,000,000.00 8,000,000.00
Sub Total Instalasi Indoor Hydrant Lantai 3 80,690,000.00
B.7 Instalasi Indoor Hydrant Lantai 4
1 Pengadaan dan Pemasangan Pipa BS sch 40
- dia. 65 mm m 46.00 820,000.00 37,720,000.00
- dia. 80 mm m 4.00 930,000.00 3,720,000.00
2 Indoor Hydrant Box lengkap dengan nozzel dan Accessories sbb : unit 2.00 15,000,000.00 30,000,000.00
- Gate valve dia 65 mm
- Valve Vander Hyder
3 Gate Valve
- dia 80 mm bh 1.00 1,250,000.00 1,250,000.00
4 Material Bantu ls 1.00 8,000,000.00 8,000,000.00
Sub Total Instalasi Indoor Hydrant Lantai 4 80,690,000.00
B.8 Instalasi Indoor Hydrant Lantai 5
1 Pengadaan dan Pemasangan Pipa BS sch 40
- dia. 65 mm m 46.00 820,000.00 37,720,000.00
- dia. 80 mm m 4.00 930,000.00 3,720,000.00
2 Indoor Hydrant Box lengkap dengan nozzel dan Accessories sbb : unit 2.00 15,000,000.00 30,000,000.00
- Gate valve dia 65 mm
- Valve Vander Hyder
3 Gate Valve
- dia 80 mm bh 1.00 1,250,000.00 1,250,000.00
4 Material Bantu ls 1.00 8,000,000.00 8,000,000.00
Sub Total Instalasi Indoor Hydrant Lantai 5 80,690,000.00
B.9 Instalasi Indoor Hydrant Lantai 6
1 Pengadaan dan Pemasangan Pipa BS sch 40
- dia. 65 mm m 40.00 820,000.00 32,800,000.00
- dia. 80 mm m 4.00 930,000.00 3,720,000.00
2 Indoor Hydrant Box lengkap dengan nozzel dan Accessories sbb : unit 2.00 15,000,000.00 30,000,000.00

Rincian RAB MEP (Sistem Penanggulangan Kebakaran)


Universitas Muhammadiyah Tangerang
Page 18
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

- Gate valve dia 65 mm


- Valve Vander Hyder
3 Gate Valve
- dia 80 mm bh 1.00 1,250,000.00 1,250,000.00
4 Material Bantu ls 1.00 8,000,000.00 8,000,000.00
Sub Total Instalasi Indoor Hydrant Lantai 6 75,770,000.00
B.10 Instalasi Indoor Hydrant Lantai 7
1 Pengadaan dan Pemasangan Pipa BS sch 40
- dia. 65 mm m 42.00 820,000.00 34,440,000.00
- dia. 80 mm m 4.00 930,000.00 3,720,000.00
2 Indoor Hydrant Box lengkap dengan nozzel dan Accessories sbb : unit 2.00 15,000,000.00 30,000,000.00
- Gate valve dia 65 mm
- Valve Vander Hyder
3 Gate Valve
- dia 80 mm bh 1.00 1,250,000.00 1,250,000.00
4 Material Bantu ls 1.00 8,000,000.00 8,000,000.00
Sub Total Instalasi Indoor Hydrant Lantai 7 77,410,000.00
B.11 Instalasi Indoor Hydrant Lantai 8
1 Pengadaan dan Pemasangan Pipa BS sch 40
- dia. 65 mm m 42.00 820,000.00 34,440,000.00
- dia. 80 mm m 4.00 930,000.00 3,720,000.00
2 Indoor Hydrant Box lengkap dengan nozzel dan Accessories sbb : unit 2.00 15,000,000.00 30,000,000.00
- Gate valve dia 65 mm
- Valve Vander Hyder
3 Gate Valve
- dia 80 mm bh 1.00 1,250,000.00 1,250,000.00
4 Material Bantu ls 1.00 8,000,000.00 8,000,000.00
Sub Total Instalasi Indoor Hydrant Lantai 8 77,410,000.00
B.12 Instalasi Indoor Hydrant Lantai 9
1 Pengadaan dan Pemasangan Pipa BS sch 40
- dia. 65 mm m 42.00 820,000.00 34,440,000.00
- dia. 80 mm m 4.00 930,000.00 3,720,000.00
2 Indoor Hydrant Box lengkap dengan nozzel dan Accessories sbb : unit 2.00 15,000,000.00 30,000,000.00
- Gate valve dia 65 mm
- Valve Vander Hyder
3 Gate Valve
- dia 80 mm bh 1.00 1,250,000.00 1,250,000.00
4 Material Bantu ls 1.00 8,000,000.00 8,000,000.00
Sub Total Instalasi Indoor Hydrant Lantai 9 77,410,000.00
B.13 Instalasi Indoor Hydrant Lantai 10
1 Pengadaan dan Pemasangan Pipa BS sch 40
- dia. 65 mm m 42.00 820,000.00 34,440,000.00
- dia. 80 mm m 4.00 930,000.00 3,720,000.00
2 Indoor Hydrant Box lengkap dengan nozzel dan Accessories sbb : unit 2.00 15,000,000.00 30,000,000.00
- Gate valve dia 65 mm
- Valve Vander Hyder
3 Gate Valve
- dia 80 mm bh 1.00 1,250,000.00 1,250,000.00
4 Material Bantu ls 1.00 8,000,000.00 8,000,000.00
Sub Total Instalasi Indoor Hydrant Lantai 10 77,410,000.00
B.14 Instalasi Indoor Hydrant Lantai 11
1 Pengadaan dan Pemasangan Pipa BS sch 40
- dia. 65 mm m 42.00 820,000.00 34,440,000.00
- dia. 80 mm m 4.00 930,000.00 3,720,000.00
2 Indoor Hydrant Box lengkap dengan nozzel dan Accessories sbb : unit 2.00 15,000,000.00 30,000,000.00

Rincian RAB MEP (Sistem Penanggulangan Kebakaran)


Universitas Muhammadiyah Tangerang
Page 19
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

- Gate valve dia 65 mm


- Valve Vander Hyder
3 Gate Valve
- dia 80 mm bh 1.00 1,250,000.00 1,250,000.00
4 Material Bantu ls 1.00 8,000,000.00 8,000,000.00
Sub Total Instalasi Indoor Hydrant Lantai 11 77,410,000.00
B.15 Instalasi Indoor Hydrant Lantai 12
1 Pengadaan dan Pemasangan Pipa BS sch 40
- dia. 65 mm m 42.00 820,000.00 34,440,000.00
- dia. 80 mm m 4.00 930,000.00 3,720,000.00
2 Indoor Hydrant Box lengkap dengan nozzel dan Accessories sbb : unit 2.00 15,000,000.00 30,000,000.00
- Gate valve dia 65 mm
- Valve Vander Hyder
3 Gate Valve
- dia 80 mm bh 1.00 1,250,000.00 1,250,000.00
4 Material Bantu ls 1.00 8,000,000.00 8,000,000.00
Sub Total Instalasi Indoor Hydrant Lantai 12 77,410,000.00
B.16 Instalasi Indoor Hydrant Lantai 13
1 Pengadaan dan Pemasangan Pipa BS sch 40
- dia. 65 mm m 42.00 820,000.00 34,440,000.00
- dia. 80 mm m 4.00 930,000.00 3,720,000.00
2 Indoor Hydrant Box lengkap dengan nozzel dan Accessories sbb : unit 2.00 15,000,000.00 30,000,000.00
- Gate valve dia 65 mm
- Valve Vander Hyder
3 Gate Valve
- dia 80 mm bh 1.00 1,250,000.00 1,250,000.00
4 Material Bantu ls 1.00 8,000,000.00 8,000,000.00
Sub Total Instalasi Indoor Hydrant Lantai 13 77,410,000.00
B.17 Instalasi Indoor Hydrant Lantai 14
1 Pengadaan dan Pemasangan Pipa BS sch 40
- dia. 65 mm m 42.00 820,000.00 34,440,000.00
- dia. 80 mm m 4.00 930,000.00 3,720,000.00
2 Indoor Hydrant Box lengkap dengan nozzel dan Accessories sbb : unit 2.00 15,000,000.00 30,000,000.00
- Gate valve dia 65 mm
- Valve Vander Hyder
3 Gate Valve
- dia 80 mm bh 1.00 1,250,000.00 1,250,000.00
4 Material Bantu ls 1.00 8,000,000.00 8,000,000.00
Sub Total Instalasi Indoor Hydrant Lantai 14 77,410,000.00
B.18 Instalasi Indoor Hydrant Lantai 15
1 Pengadaan dan Pemasangan Pipa BS sch 40
- dia. 65 mm m 42.00 820,000.00 34,440,000.00
- dia. 80 mm m 4.00 930,000.00 3,720,000.00
2 Indoor Hydrant Box lengkap dengan nozzel dan Accessories sbb : unit 2.00 15,000,000.00 30,000,000.00
- Gate valve dia 65 mm
- Valve Vander Hyder
3 Gate Valve
- dia 80 mm bh 1.00 1,250,000.00 1,250,000.00
4 Material Bantu ls 1.00 8,000,000.00 8,000,000.00
Sub Total Instalasi Indoor Hydrant Lantai 15 77,410,000.00
B.19 Instalasi Indoor Hydrant Lantai 16
1 Pengadaan dan Pemasangan Pipa BS sch 40
- dia. 65 mm m 42.00 820,000.00 34,440,000.00
- dia. 80 mm m 4.00 930,000.00 3,720,000.00
2 Indoor Hydrant Box lengkap dengan nozzel dan Accessories sbb : unit 2.00 15,000,000.00 30,000,000.00

Rincian RAB MEP (Sistem Penanggulangan Kebakaran)


Universitas Muhammadiyah Tangerang
Page 20
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

- Gate valve dia 65 mm


- Valve Vander Hyder
3 Gate Valve
- dia 80 mm bh 1.00 1,250,000.00 1,250,000.00
4 Material Bantu ls 1.00 8,000,000.00 8,000,000.00
Sub Total Instalasi Indoor Hydrant Lantai 16 77,410,000.00
B.20 Instalasi Indoor Hydrant Lantai 17
1 Pengadaan dan Pemasangan Pipa BS sch 40
- dia. 65 mm m 42.00 820,000.00 34,440,000.00
- dia. 80 mm m 4.00 930,000.00 3,720,000.00
2 Indoor Hydrant Box lengkap dengan nozzel dan Accessories sbb : unit 2.00 15,000,000.00 30,000,000.00
- Gate valve dia 65 mm
- Valve Vander Hyder
3 Gate Valve
- dia 80 mm bh 1.00 1,250,000.00 1,250,000.00
4 Material Bantu ls 1.00 8,000,000.00 8,000,000.00
Sub Total Instalasi Indoor Hydrant Lantai 17 77,410,000.00
B.21 Instalasi Indoor Hydrant Lantai 18
1 Pengadaan dan Pemasangan Pipa BS sch 40
- dia. 65 mm m 42.00 820,000.00 34,440,000.00
- dia. 80 mm m 4.00 930,000.00 3,720,000.00
2 Indoor Hydrant Box lengkap dengan nozzel dan Accessories sbb : unit 2.00 15,000,000.00 30,000,000.00
- Gate valve dia 65 mm
- Valve Vander Hyder
3 Gate Valve
- dia 80 mm bh 1.00 1,250,000.00 1,250,000.00
4 Material Bantu ls 1.00 8,000,000.00 8,000,000.00
Sub Total Instalasi Indoor Hydrant Lantai 18 77,410,000.00
B.22 Instalasi Indoor Hydrant Lantai 19
1 Pengadaan dan Pemasangan Pipa BS sch 40
- dia. 65 mm m 42.00 820,000.00 34,440,000.00
- dia. 80 mm m 4.00 930,000.00 3,720,000.00
2 Indoor Hydrant Box lengkap dengan nozzel dan Accessories sbb : unit 2.00 15,000,000.00 30,000,000.00
- Gate valve dia 65 mm
- Valve Vander Hyder
3 Gate Valve
- dia 80 mm bh 1.00 1,250,000.00 1,250,000.00
4 Material Bantu ls 1.00 8,000,000.00 8,000,000.00
Sub Total Instalasi Indoor Hydrant Lantai 19 77,410,000.00
B.23 Instalasi Pipa Riser Hydrant
1 Pengadaan dan Pemasangan Pipa BS sch 40
2 - dia. 100mm m 100.00 1,150,000.00 115,000,000.00
3 - dia. 150 mm m 150.00 1,350,000.00 202,500,000.00
4 Fitting & Consumable material ls 1.00 9,000,000.00 9,000,000.00
Sub Total Instalasi Pipa Riser Hydrant 326,500,000.00
C INSTALASI PEMIPAAN SPRINKLER
C.1 Instalasi Pipa Sprinkler Lantai Basement 01
1 Head Sprinkler tipe Upright ttk 28.00 680,000.00 19,040,000.00
2 Pengadaan Dan Pemasangan Pipa BS sch 40
- dia. 25 mm m 104.00 480,000.00 49,920,000.00
- dia. 32 mm m 5.00 550,000.00 2,750,000.00
- dia. 40 mm m 28.00 650,000.00 18,200,000.00
- dia. 50 mm m 24.00 760,000.00 18,240,000.00
- dia. 65 mm m 9.00 820,000.00 7,380,000.00
- dia. 80 mm m 3.00 930,000.00 2,790,000.00

Rincian RAB MEP (Sistem Penanggulangan Kebakaran)


Universitas Muhammadiyah Tangerang
Page 21
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

- dia. 100 mm m - - -
4 Branch Control Valve Lengkap Dengan Accessories sbb : set 1.00 18,000,000.00 18,000,000.00
- Branch Valve dia. 100 mm
- Flow Switch dia. 100 mm
- Test Valve dia. 25 mm
- Sight Glass dia. 25 mm
- Drain Pipe dia. 25 mm
5 Fitting, Hanger & Consumable material ls 1.00 9,000,000.00 9,000,000.00
Sub Total Instalasi Pipa Sprinkler Lantai Basement 01 145,320,000.00
C.2 Instalasi Pipa Sprinkler Lantai Ground
1 Head Sprinkler tipe Pendant ttk 40.00 560,000.00 22,400,000.00
Pengadaan Dan Pemasangan Pipa BS sch 40
- dia. 25 mm m 114.00 480,000.00 54,720,000.00
- dia. 32 mm m 14.00 550,000.00 7,700,000.00
- dia. 40 mm m 24.00 650,000.00 15,600,000.00
- dia. 50 mm m 25.00 760,000.00 19,000,000.00
- dia. 65 mm m 9.00 820,000.00 7,380,000.00
- dia. 80 mm m 6.00 930,000.00 5,580,000.00
- dia. 100 mm m - - -
4 Branch Control Valve Lengkap Dengan Accessories sbb : set 1.00 18,000,000.00 18,000,000.00
- Branch Valve dia. 100 mm
- Flow Switch dia. 100 mm
- Test Valve dia. 25 mm
- Sight Glass dia. 25 mm
- Drain Pipe dia. 25 mm
5 Fitting, Hanger & Consumable material ls 1.00 9,000,000.00 9,000,000.00
Sub Total Instalasi Pipa Sprinkler Lantai Ground 159,380,000.00
C.3 Instalasi Pipa Sprinkler Lantai 1
1 Head Sprinkler tipe Upright ttk 32.00 680,000.00 21,760,000.00
2 Pengadaan Dan Pemasangan Pipa BS sch 40
- dia. 25 mm m 101.00 480,000.00 48,480,000.00
- dia. 32 mm m 8.00 550,000.00 4,400,000.00
- dia. 40 mm m 22.00 650,000.00 14,300,000.00
- dia. 50 mm m 18.00 760,000.00 13,680,000.00
- dia. 65 mm m 19.00 820,000.00 15,580,000.00
- dia. 80 mm m 3.00 930,000.00 2,790,000.00
- dia. 100 mm m - - -
4 Branch Control Valve Lengkap Dengan Accessories sbb : set 1.00 18,000,000.00 18,000,000.00
- Branch Valve dia. 100 mm
- Flow Switch dia. 100 mm
- Test Valve dia. 25 mm
- Sight Glass dia. 25 mm
- Drain Pipe dia. 25 mm
5 Fitting, Hanger & Consumable material ls 1.00 9,000,000.00 9,000,000.00
Sub Total Instalasi Pipa Sprinkler Lantai 1 147,990,000.00
C.4 Instalasi Pipa Sprinkler Lantai 2
1 Head Sprinkler tipe Upright ttk 40.00 680,000.00 27,200,000.00
2 Pengadaan Dan Pemasangan Pipa BS sch 40
- dia. 25 mm m 185.00 480,000.00 88,800,000.00
- dia. 32 mm m 8.00 550,000.00 4,400,000.00
- dia. 40 mm m 26.00 650,000.00 16,900,000.00
- dia. 50 mm m 82.00 760,000.00 62,320,000.00
- dia. 65 mm m 10.00 820,000.00 8,200,000.00
- dia. 80 mm m 3.00 930,000.00 2,790,000.00
4 Branch Control Valve Lengkap Dengan Accessories sbb : set 1.00 18,000,000.00 18,000,000.00

Rincian RAB MEP (Sistem Penanggulangan Kebakaran)


Universitas Muhammadiyah Tangerang
Page 22
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

- Branch Valve dia. 100 mm


- Flow Switch dia. 100 mm
- Test Valve dia. 25 mm
- Sight Glass dia. 25 mm
- Drain Pipe dia. 25 mm
5 Fitting, Hanger & Consumable material ls 1.00 9,000,000.00 9,000,000.00
Sub Total Instalasi Pipa Sprinkler Lantai 2 237,610,000.00
C.5 Instalasi Pipa Sprinkler Lantai 3
1 Head Sprinkler tipe Upright ttk 40.00 680,000.00 27,200,000.00
2 Pengadaan Dan Pemasangan Pipa BS sch 40
- dia. 25 mm m 185.00 480,000.00 88,800,000.00
- dia. 32 mm m 8.00 550,000.00 4,400,000.00
- dia. 40 mm m 26.00 650,000.00 16,900,000.00
- dia. 50 mm m 82.00 760,000.00 62,320,000.00
- dia. 65 mm m 10.00 820,000.00 8,200,000.00
- dia. 80 mm m 3.00 930,000.00 2,790,000.00
4 Branch Control Valve Lengkap Dengan Accessories sbb : set 1.00 18,000,000.00 18,000,000.00
- Branch Valve dia. 100 mm
- Flow Switch dia. 100 mm
- Test Valve dia. 25 mm
- Sight Glass dia. 25 mm
- Drain Pipe dia. 25 mm
5 Fitting, Hanger & Consumable material ls 1.00 9,000,000.00 9,000,000.00
Sub Total 237,610,000.00
C.6 Instalasi Pipa Sprinkler Lantai 4
1 Head Sprinkler tipe Upright ttk 40.00 680,000.00 27,200,000.00
2 Pengadaan Dan Pemasangan Pipa BS sch 40
- dia. 25 mm m 185.00 480,000.00 88,800,000.00
- dia. 32 mm m 8.00 550,000.00 4,400,000.00
- dia. 40 mm m 26.00 650,000.00 16,900,000.00
- dia. 50 mm m 82.00 760,000.00 62,320,000.00
- dia. 65 mm m 10.00 820,000.00 8,200,000.00
- dia. 80 mm m 3.00 930,000.00 2,790,000.00
4 Branch Control Valve Lengkap Dengan Accessories sbb : set 1.00 18,000,000.00 18,000,000.00
- Branch Valve dia. 100 mm
- Flow Switch dia. 100 mm
- Test Valve dia. 25 mm
- Sight Glass dia. 25 mm
- Drain Pipe dia. 25 mm
5 Fitting, Hanger & Consumable material ls 1.00 9,000,000.00 9,000,000.00
Sub Total Instalasi Pipa Sprinkler Lantai 4 237,610,000.00
C.7 Instalasi Pipa Sprinkler Lantai 5
1 Head Sprinkler tipe Upright ttk 40.00 680,000.00 27,200,000.00
2 Pengadaan Dan Pemasangan Pipa BS sch 40
- dia. 25 mm m 185.00 480,000.00 88,800,000.00
- dia. 32 mm m 8.00 550,000.00 4,400,000.00
- dia. 40 mm m 26.00 650,000.00 16,900,000.00
- dia. 50 mm m 82.00 760,000.00 62,320,000.00
- dia. 65 mm m 10.00 820,000.00 8,200,000.00
- dia. 80 mm m 3.00 930,000.00 2,790,000.00
4 Branch Control Valve Lengkap Dengan Accessories sbb : set 1.00 18,000,000.00 18,000,000.00
- Branch Valve dia. 100 mm
- Flow Switch dia. 100 mm
- Test Valve dia. 25 mm
- Sight Glass dia. 25 mm

Rincian RAB MEP (Sistem Penanggulangan Kebakaran)


Universitas Muhammadiyah Tangerang
Page 23
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

- Drain Pipe dia. 25 mm


5 Fitting, Hanger & Consumable material ls 1.00 9,000,000.00 9,000,000.00
Sub Total Instalasi Pipa Sprinkler Lantai 5 237,610,000.00
C.8 Instalasi Pipa Sprinkler Lantai 6
1 Head Sprinkler tipe Pendant ttk 30.00 560,000.00 16,800,000.00
2 Pengadaan Dan Pemasangan Pipa BS sch 40
- dia. 25 mm m 125.00 480,000.00 60,000,000.00
- dia. 32 mm m 7.00 550,000.00 3,850,000.00
- dia. 40 mm m 26.00 650,000.00 16,900,000.00
- dia. 50 mm m 26.00 760,000.00 19,760,000.00
- dia. 65 mm m 10.00 820,000.00 8,200,000.00
- dia. 80 mm m 11.00 930,000.00 10,230,000.00
4 Branch Control Valve Lengkap Dengan Accessories sbb : set 1.00 18,000,000.00 18,000,000.00
- Branch Valve dia. 100 mm
- Flow Switch dia. 100 mm
- Test Valve dia. 25 mm
- Sight Glass dia. 25 mm
- Drain Pipe dia. 25 mm
5 Fitting, Hanger & Consumable material ls 1.00 9,000,000.00 9,000,000.00
Sub Total Instalasi Pipa Sprinkler Lantai 6 162,740,000.00
C.9 Instalasi Pipa Sprinkler Lantai 7
1 Head Sprinkler tipe Pendant ttk 42.00 560,000.00 23,520,000.00
2 Pengadaan Dan Pemasangan Pipa BS sch 40
- dia. 25 mm m 114.00 480,000.00 54,720,000.00
- dia. 32 mm m 3.00 550,000.00 1,650,000.00
- dia. 40 mm m 18.00 650,000.00 11,700,000.00
- dia. 50 mm m 41.00 760,000.00 31,160,000.00
- dia. 65 mm m 9.00 820,000.00 7,380,000.00
- dia. 80 mm m 3.00 930,000.00 2,790,000.00
- dia. 100 mm m - - -
4 Branch Control Valve Lengkap Dengan Accessories sbb : set 1.00 18,000,000.00 18,000,000.00
- Branch Valve dia. 100 mm
- Flow Switch dia. 100 mm
- Test Valve dia. 25 mm
- Sight Glass dia. 25 mm
- Drain Pipe dia. 25 mm
5 Fitting, Hanger & Consumable material ls 1.00 9,000,000.00 9,000,000.00
Sub Total Instalasi Pipa Sprinkler Lantai 7 159,920,000.00
C.10 Instalasi Pipa Sprinkler Lantai 8
1 Head Sprinkler tipe Pendant ttk 39.00 560,000.00 21,840,000.00
2 Pengadaan Dan Pemasangan Pipa BS sch 40
- dia. 25 mm m 152.00 480,000.00 72,960,000.00
- dia. 32 mm m 7.00 550,000.00 3,850,000.00
- dia. 40 mm m 26.00 650,000.00 16,900,000.00
- dia. 50 mm m 29.00 760,000.00 22,040,000.00
- dia. 65 mm m 3.00 820,000.00 2,460,000.00
- dia. 80 mm m 12.00 930,000.00 11,160,000.00
- dia. 100 mm m 2.00 1,150,000.00 2,300,000.00
4 Branch Control Valve Lengkap Dengan Accessories sbb : set 1.00 18,000,000.00 18,000,000.00
- Branch Valve dia. 100 mm
- Flow Switch dia. 100 mm
- Test Valve dia. 25 mm
- Sight Glass dia. 25 mm
- Drain Pipe dia. 25 mm
5 Fitting, Hanger & Consumable material ls 1.00 9,000,000.00 9,000,000.00

Rincian RAB MEP (Sistem Penanggulangan Kebakaran)


Universitas Muhammadiyah Tangerang
Page 24
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

Sub Total Instalasi Pipa Sprinkler Lantai 8 180,510,000.00


C.11 Instalasi Pipa Sprinkler Lantai 9
1 Head Sprinkler tipe Pendant ttk 39.00 560,000.00 21,840,000.00
2 Pengadaan Dan Pemasangan Pipa BS sch 40
- dia. 25 mm m 152.00 480,000.00 72,960,000.00
- dia. 32 mm m 7.00 550,000.00 3,850,000.00
- dia. 40 mm m 26.00 650,000.00 16,900,000.00
- dia. 50 mm m 29.00 760,000.00 22,040,000.00
- dia. 65 mm m 3.00 820,000.00 2,460,000.00
- dia. 80 mm m 12.00 930,000.00 11,160,000.00
- dia. 100 mm m 2.00 1,150,000.00 2,300,000.00
4 Branch Control Valve Lengkap Dengan Accessories sbb : set 1.00 18,000,000.00 18,000,000.00
- Branch Valve dia. 100 mm
- Flow Switch dia. 100 mm
- Test Valve dia. 25 mm
- Sight Glass dia. 25 mm
- Drain Pipe dia. 25 mm
5 Fitting, Hanger & Consumable material ls 1.00 9,000,000.00 9,000,000.00
Sub Total Instalasi Pipa Sprinkler Lantai 9 180,510,000.00
C.12 Instalasi Pipa Sprinkler Lantai 10
1 Head Sprinkler tipe Pendant ttk 39.00 560,000.00 21,840,000.00
2 Pengadaan Dan Pemasangan Pipa BS sch 40
- dia. 25 mm m 152.00 480,000.00 72,960,000.00
- dia. 32 mm m 7.00 550,000.00 3,850,000.00
- dia. 40 mm m 26.00 650,000.00 16,900,000.00
- dia. 50 mm m 29.00 760,000.00 22,040,000.00
- dia. 65 mm m 3.00 820,000.00 2,460,000.00
- dia. 80 mm m 12.00 930,000.00 11,160,000.00
- dia. 100 mm m 2.00 1,150,000.00 2,300,000.00
4 Branch Control Valve Lengkap Dengan Accessories sbb : set 1.00 18,000,000.00 18,000,000.00
- Branch Valve dia. 100 mm
- Flow Switch dia. 100 mm
- Test Valve dia. 25 mm
- Sight Glass dia. 25 mm
- Drain Pipe dia. 25 mm
5 Fitting, Hanger & Consumable material ls 1.00 9,000,000.00 9,000,000.00
Sub Total Instalasi Pipa Sprinkler Lantai 10 180,510,000.00
C.13 Instalasi Pipa Sprinkler Lantai 11
1 Head Sprinkler tipe Pendant ttk 39.00 560,000.00 21,840,000.00
2 Pengadaan Dan Pemasangan Pipa BS sch 40
- dia. 25 mm m 152.00 480,000.00 72,960,000.00
- dia. 32 mm m 7.00 550,000.00 3,850,000.00
- dia. 40 mm m 26.00 650,000.00 16,900,000.00
- dia. 50 mm m 29.00 760,000.00 22,040,000.00
- dia. 65 mm m 3.00 820,000.00 2,460,000.00
- dia. 80 mm m 12.00 930,000.00 11,160,000.00
- dia. 100 mm m 2.00 1,150,000.00 2,300,000.00
4 Branch Control Valve Lengkap Dengan Accessories sbb : set 1.00 18,000,000.00 18,000,000.00
- Branch Valve dia. 100 mm
- Flow Switch dia. 100 mm
- Test Valve dia. 25 mm
- Sight Glass dia. 25 mm
- Drain Pipe dia. 25 mm
5 Fitting, Hanger & Consumable material ls 1.00 9,000,000.00 9,000,000.00
Sub Total Instalasi Pipa Sprinkler Lantai 11 180,510,000.00

Rincian RAB MEP (Sistem Penanggulangan Kebakaran)


Universitas Muhammadiyah Tangerang
Page 25
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

C.14 Instalasi Pipa Sprinkler Lantai 12


1 Head Sprinkler tipe Pendant ttk 39.00 560,000.00 21,840,000.00
2 Pengadaan Dan Pemasangan Pipa BS sch 40
- dia. 25 mm m 152.00 480,000.00 72,960,000.00
- dia. 32 mm m 7.00 550,000.00 3,850,000.00
- dia. 40 mm m 26.00 650,000.00 16,900,000.00
- dia. 50 mm m 29.00 760,000.00 22,040,000.00
- dia. 65 mm m 3.00 820,000.00 2,460,000.00
- dia. 80 mm m 12.00 930,000.00 11,160,000.00
- dia. 100 mm m 2.00 1,150,000.00 2,300,000.00
4 Branch Control Valve Lengkap Dengan Accessories sbb : set 1.00 18,000,000.00 18,000,000.00
- Branch Valve dia. 100 mm
- Flow Switch dia. 100 mm
- Test Valve dia. 25 mm
- Sight Glass dia. 25 mm
- Drain Pipe dia. 25 mm
5 Fitting, Hanger & Consumable material ls 1.00 9,000,000.00 9,000,000.00
Sub Total Instalasi Pipa Sprinkler Lantai 12 180,510,000.00
C.15 Instalasi Pipa Sprinkler Lantai 13
1 Head Sprinkler tipe Pendant ttk 39.00 560,000.00 21,840,000.00
2 Pengadaan Dan Pemasangan Pipa BS sch 40
- dia. 25 mm m 152.00 480,000.00 72,960,000.00
- dia. 32 mm m 7.00 550,000.00 3,850,000.00
- dia. 40 mm m 26.00 650,000.00 16,900,000.00
- dia. 50 mm m 29.00 760,000.00 22,040,000.00
- dia. 65 mm m 3.00 820,000.00 2,460,000.00
- dia. 80 mm m 12.00 930,000.00 11,160,000.00
- dia. 100 mm m 2.00 1,150,000.00 2,300,000.00
4 Branch Control Valve Lengkap Dengan Accessories sbb : set 1.00 18,000,000.00 18,000,000.00
- Branch Valve dia. 100 mm
- Flow Switch dia. 100 mm
- Test Valve dia. 25 mm
- Sight Glass dia. 25 mm
- Drain Pipe dia. 25 mm
5 Fitting, Hanger & Consumable material ls 1.00 9,000,000.00 9,000,000.00
Sub Total Instalasi Pipa Sprinkler Lantai 13 180,510,000.00
C.16 Instalasi Pipa Sprinkler Lantai 14
1 Head Sprinkler tipe Pendant ttk 39.00 560,000.00 21,840,000.00
2 Pengadaan Dan Pemasangan Pipa BS sch 40
- dia. 25 mm m 152.00 480,000.00 72,960,000.00
- dia. 32 mm m 7.00 550,000.00 3,850,000.00
- dia. 40 mm m 26.00 650,000.00 16,900,000.00
- dia. 50 mm m 29.00 760,000.00 22,040,000.00
- dia. 65 mm m 3.00 820,000.00 2,460,000.00
- dia. 80 mm m 12.00 930,000.00 11,160,000.00
- dia. 100 mm m 2.00 1,150,000.00 2,300,000.00
4 Branch Control Valve Lengkap Dengan Accessories sbb : set 1.00 18,000,000.00 18,000,000.00
- Branch Valve dia. 100 mm
- Flow Switch dia. 100 mm
- Test Valve dia. 25 mm
- Sight Glass dia. 25 mm
- Drain Pipe dia. 25 mm
5 Fitting, Hanger & Consumable material ls 1.00 9,000,000.00 9,000,000.00
Sub Total Instalasi Pipa Sprinkler Lantai 14 180,510,000.00
C.17 Instalasi Pipa Sprinkler Lantai 15

Rincian RAB MEP (Sistem Penanggulangan Kebakaran)


Universitas Muhammadiyah Tangerang
Page 26
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

1 Head Sprinkler tipe Pendant ttk 39.00 560,000.00 21,840,000.00


2 Pengadaan Dan Pemasangan Pipa BS sch 40
- dia. 25 mm m 152.00 480,000.00 72,960,000.00
- dia. 32 mm m 7.00 550,000.00 3,850,000.00
- dia. 40 mm m 26.00 650,000.00 16,900,000.00
- dia. 50 mm m 29.00 760,000.00 22,040,000.00
- dia. 65 mm m 3.00 820,000.00 2,460,000.00
- dia. 80 mm m 12.00 930,000.00 11,160,000.00
- dia. 100 mm m 2.00 1,150,000.00 2,300,000.00
4 Branch Control Valve Lengkap Dengan Accessories sbb : set 1.00 18,000,000.00 18,000,000.00
- Branch Valve dia. 100 mm
- Flow Switch dia. 100 mm
- Test Valve dia. 25 mm
- Sight Glass dia. 25 mm
- Drain Pipe dia. 25 mm
5 Fitting, Hanger & Consumable material ls 1.00 9,000,000.00 9,000,000.00
Sub Total Instalasi Pipa Sprinkler Lantai 15 180,510,000.00
C.18 Instalasi Pipa Sprinkler Lantai 16
1 Head Sprinkler tipe Pendant ttk 39.00 560,000.00 21,840,000.00
2 Pengadaan Dan Pemasangan Pipa BS sch 40
- dia. 25 mm m 152.00 480,000.00 72,960,000.00
- dia. 32 mm m 7.00 550,000.00 3,850,000.00
- dia. 40 mm m 26.00 650,000.00 16,900,000.00
- dia. 50 mm m 29.00 760,000.00 22,040,000.00
- dia. 65 mm m 3.00 820,000.00 2,460,000.00
- dia. 80 mm m 12.00 930,000.00 11,160,000.00
- dia. 100 mm m 2.00 1,150,000.00 2,300,000.00
4 Branch Control Valve Lengkap Dengan Accessories sbb : set 1.00 18,000,000.00 18,000,000.00
- Branch Valve dia. 100 mm
- Flow Switch dia. 100 mm
- Test Valve dia. 25 mm
- Sight Glass dia. 25 mm
- Drain Pipe dia. 25 mm
5 Fitting, Hanger & Consumable material ls 1.00 9,000,000.00 9,000,000.00
Sub Total Instalasi Pipa Sprinkler Lantai 16 180,510,000.00
C.19 Instalasi Pipa Sprinkler Lantai 17
1 Head Sprinkler tipe Pendant ttk 39.00 560,000.00 21,840,000.00
2 Pengadaan Dan Pemasangan Pipa BS sch 40
- dia. 25 mm m 152.00 480,000.00 72,960,000.00
- dia. 32 mm m 7.00 550,000.00 3,850,000.00
- dia. 40 mm m 26.00 650,000.00 16,900,000.00
- dia. 50 mm m 29.00 760,000.00 22,040,000.00
- dia. 65 mm m 3.00 820,000.00 2,460,000.00
- dia. 80 mm m 12.00 930,000.00 11,160,000.00
- dia. 100 mm m 2.00 1,150,000.00 2,300,000.00
4 Branch Control Valve Lengkap Dengan Accessories sbb : set 1.00 18,000,000.00 18,000,000.00
- Branch Valve dia. 100 mm
- Flow Switch dia. 100 mm
- Test Valve dia. 25 mm
- Sight Glass dia. 25 mm
- Drain Pipe dia. 25 mm
5 Fitting, Hanger & Consumable material ls 1.00 9,000,000.00 9,000,000.00
Sub Total Instalasi Pipa Sprinkler Lantai 17 180,510,000.00
C.20 Instalasi Pipa Sprinkler Lantai 18
1 Head Sprinkler tipe Pendant ttk 39.00 560,000.00 21,840,000.00

Rincian RAB MEP (Sistem Penanggulangan Kebakaran)


Universitas Muhammadiyah Tangerang
Page 27
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

2 Pengadaan Dan Pemasangan Pipa BS sch 40


- dia. 25 mm m 152.00 480,000.00 72,960,000.00
- dia. 32 mm m 7.00 550,000.00 3,850,000.00
- dia. 40 mm m 26.00 650,000.00 16,900,000.00
- dia. 50 mm m 29.00 760,000.00 22,040,000.00
- dia. 65 mm m 3.00 820,000.00 2,460,000.00
- dia. 80 mm m 12.00 930,000.00 11,160,000.00
- dia. 100 mm m 2.00 1,150,000.00 2,300,000.00
4 Branch Control Valve Lengkap Dengan Accessories sbb : set 1.00 18,000,000.00 18,000,000.00
- Branch Valve dia. 100 mm
- Flow Switch dia. 100 mm
- Test Valve dia. 25 mm
- Sight Glass dia. 25 mm
- Drain Pipe dia. 25 mm
5 Fitting, Hanger & Consumable material ls 1.00 9,000,000.00 9,000,000.00
Sub Total Instalasi Pipa Sprinkler Lantai 18 180,510,000.00
C.21 Instalasi Pipa Sprinkler Lantai 19
1 Head Sprinkler tipe Pendant ttk 39.00 560,000.00 21,840,000.00
2 Pengadaan Dan Pemasangan Pipa BS sch 40
- dia. 25 mm m 149.00 480,000.00 71,520,000.00
- dia. 32 mm m 12.00 550,000.00 6,600,000.00
- dia. 40 mm m 30.00 650,000.00 19,500,000.00
- dia. 50 mm m 20.00 760,000.00 15,200,000.00
- dia. 65 mm m 18.00 820,000.00 14,760,000.00
- dia. 80 mm m 9.00 930,000.00 8,370,000.00
- dia. 100 mm m 2.00 1,150,000.00 2,300,000.00
4 Branch Control Valve Lengkap Dengan Accessories sbb : set 1.00 18,000,000.00 18,000,000.00
- Branch Valve dia. 100 mm
- Flow Switch dia. 100 mm
- Test Valve dia. 25 mm
- Sight Glass dia. 25 mm
- Drain Pipe dia. 25 mm
5 Fitting, Hanger & Consumable material ls 1.00 9,000,000.00 9,000,000.00
Sub Total Instalasi Pipa Sprinkler Lantai 19 187,090,000.00
C.22 Instalasi Pipa Riser Sprinkler
Pengadaan dan Pemasangan Pipa BS sch 40
1 - dia. 150mm m 100.00 1,230,000.00 123,000,000.00
2 - dia. 100mm m 150.00 1,150,000.00 172,500,000.00
3 - dia. 65 mm ( Pipa drain ) m 100.00 820,000.00 82,000,000.00
4 Fitting & Consumable material ls 1.00 9,000,000.00 9,000,000.00
Sub Total Instalasi Pipa Riser Sprinkler 386,500,000.00

D PENGADAAN DAN PEMASANGAN FIRE EXTINGUISHER


1 Lantai Basement 1 -
FE kap. 5 kg bh 2.00 9,000,000.00 18,000,000.00
2 Lantai Dasar -
FE kap. 5 kg bh 2.00 9,000,000.00 18,000,000.00
FE kap. 25 kg (Diruang Genset ) bh 1.00 30,000,000.00 30,000,000.00
3 Lantai 1 -
FE kap. 5 kg bh 2.00 9,000,000.00 18,000,000.00
4 Lantai 2 -
FE kap. 5 kg bh 2.00 9,000,000.00 18,000,000.00
5 Lantai 3 -
FE kap. 5 kg bh 2.00 9,000,000.00 18,000,000.00
6 Lantai 4 -

Rincian RAB MEP (Sistem Penanggulangan Kebakaran)


Universitas Muhammadiyah Tangerang
Page 28
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

FE kap. 5 kg bh 2.00 9,000,000.00 18,000,000.00


7 Lantai 5 -
FE kap. 5 kg bh 2.00 9,000,000.00 18,000,000.00
8 Lantai 6 -
FE kap. 5 kg bh 2.00 9,000,000.00 18,000,000.00
9 Lantai 7 -
FE kap. 5 kg bh 2.00 9,000,000.00 18,000,000.00
10 Lantai 8 -
FE kap. 5 kg bh 2.00 9,000,000.00 18,000,000.00
11 Lantai 9 -
FE kap. 5 kg bh 2.00 9,000,000.00 18,000,000.00
12 Lantai 10 -
FE kap. 5 kg bh 2.00 9,000,000.00 18,000,000.00
13 Lantai 11 -
FE kap. 5 kg bh 2.00 9,000,000.00 18,000,000.00
14 Lantai 12 -
FE kap. 5 kg bh 2.00 9,000,000.00 18,000,000.00
15 Lantai 13 -
FE kap. 5 kg bh 2.00 9,000,000.00 18,000,000.00
16 Lantai 14 -
FE kap. 5 kg bh 2.00 9,000,000.00 18,000,000.00
17 Lantai 15 -
FE kap. 5 kg bh 2.00 9,000,000.00 18,000,000.00
18 Lantai 16 -
FE kap. 5 kg bh 2.00 9,000,000.00 18,000,000.00
19 Lantai 17 -
FE kap. 5 kg bh 2.00 9,000,000.00 18,000,000.00
20 Lantai 18 -
FE kap. 5 kg bh 2.00 9,000,000.00 18,000,000.00
21 Lantai 19 -
FE kap. 5 kg bh 2.00 9,000,000.00 18,000,000.00
22 Lantai 20 Atap ruang lift -
FE kap. 5 kg bh 2.00 9,000,000.00 18,000,000.00
Sub Total PENGADAAN DAN PEMASANGAN FIRE EXTINGUISHER 426,000,000.00

E TEST COMMISIONING SISTEM PENANGGULANGAN KEBAKARAN ls 1.00 - -


Sub Total TEST COMMISIONING SISTEM PENANGGULANGAN KEBAKARAN -

TOTAL SISTEM PENANGGULANGAN KEBAKARAN 7,564,540,000.00

Rincian RAB MEP (Sistem Penanggulangan Kebakaran)


Universitas Muhammadiyah Tangerang
Page 29
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp. ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

VI PASSANGER, FREIGHT ELEVATOR & GONDOLA


A Persiapan, mob-demob, Shop Drawing, test commissioning, pelatihan ls 1.00 250,000,000.00 250,000,000.00
B Elevator 01-03 unit 3.00 1,800,000,000.00 5,400,000,000.00
- Type : Passanger Elevator
- Capacity (Kg) : 1650 Kg/ 24 Person
- Speed (m/s) : 105 mpm
- Stop / Opening : 20 Opening/ 20 Floor
- Control : AC-VVVF
- Doors : 2 Panels Center Opening - Automatic Door
- Main Power : 35 kW, 3f, 380V, 50Hz
- Lighting : 1f, 220V, 50Hz
- Car size (mm) : ---- (W) x ---- (D) x ---- (H)
- Hoistway (mm) : ---- (W) x ---- (D)
- Entrance (mm) : ---- (W) x ---- (H)
- Finishing : Standard
- Optional Function : Emergency Exit, FE, ELD, GC

B Elevator 04-05 unit 2.00 1,800,000,000.00 3,600,000,000.00


- Type : Passanger Elevator
- Capacity (Kg) : 1650 Kg/ 24 Person
- Speed (m/s) : 105 mpm
- Stop / Opening : 21 Opening/ 21 Floor
- Control : AC-VVVF
- Doors : 2 Panels Center Opening - Automatic Door
- Main Power : 35 kW, 3f, 380V, 50Hz
- Lighting : 1f, 220V, 50Hz
- Car size (mm) : ---- (W) x ---- (D) x ---- (H)
- Hoistway (mm) : ---- (W) x ---- (D)
- Entrance (mm) : ---- (W) x ---- (H)
- Finishing : Standard
- Optional Function : Emergency Exit, FE, ELD, GC

C Elevator 06 (Emergency) unit 1.00 1,800,000,000.00 1,800,000,000.00


- Type : Passanger Elevator
- Capacity (Kg) : 1650 Kg/ 24 Person
- Speed (m/s) : 105 mpm
- Stop / Opening : 21 Opening/ 21 Floor
- Control : AC-VVVF
- Doors : 2 Panels Center Opening - Automatic Door
- Main Power : 35 kW, 3f, 380V, 50Hz
- Lighting : 1f, 220V, 50Hz
- Car size (mm) : ---- (W) x ---- (D) x ---- (H)
- Hoistway (mm) : ---- (W) x ---- (D)
- Entrance (mm) : ---- (W) x ---- (H)
- Finishing : Standard
- Optional Function : Emergency Exit, FE, ELD, GC

D Local Content lot 1.00 800,000,000.00 800,000,000.00


Biaya Pemasangan
Testing Comissioning
Ijin Depnaker
sub total 11,850,000,000.00

E Gondola
E.1 Gondola Permanent (Fix Arm) unit 1.00 850,000,000.00 850,000,000.00
MODEL : GONDOLA PERMANENT
SYSTEM : Fix Arm

Rincian RAB MEP (Lift Passenger dan Gondola)


Universitas Muhammadiyah Tangerang
Page 30
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp. ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

Slewing Arm
Turn Table
LOADING CAPACITY : 300 Kg
LIFTING HEIGHT : 80 Meter
CRADLE : 3000 x 650 x 1000
POWER : 380 V/ 3 Ph/ 50 Hz
SUSPENSION ROPE : 2 X 9 mm
LIFTING SPEED : 8.0 M/ Min
TRAVELING SPEED : 4 M/ Min
TURNING SPEED : 2.0 M/ Min
CONTROLLING : Push Button Switch
ACCESSORIES : Handy Talky
SAFETY DEVICE : Up/ Down/ L/ S
Turning L/ S
Final L/ S
Travelling L/ S
Luffing Arm L/ S
Anti Collision Bar
Emergency Stop
Turn Table
sub total 850,000,000.00

TOTAL PASSANGER, FREIGHT ELEVATOR & GONDOLA 12,700,000,000.00

Rincian RAB MEP (Lift Passenger dan Gondola)


Universitas Muhammadiyah Tangerang
Page 31
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

IJIN-IJIN PEKERJAAN MEKANIKAL


A Perijinan Penyambungan PDAM lot 1.00 150,000,000.00 150,000,000.00

B Biaya Sertifikasi & Perijinan Pemadam Kebakaran ls 1.00 250,000,000.00 250,000,000.00

C Perijinan Lift dan Gondola lot 1.00 150,000,000.00 150,000,000.00

TOTAL IJIN-IJIN PEKERJAAN MEKANIKAL Rp 550,000,000.00

Rincian RAB MEP (Ijin-Ijin Mekanikal)


Universitas Muhammadiyah Tangerang
Page 32
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

V PENYEDIAAN JARINGAN & DISTRIBUSI LISTRIK


A JARINGAN LISTRIK SISTEM 20 KV
Instalasi Sistem Tegangan 20 KV, lengkap terpasang
1 Cublicle 20 kV
Incoming Cubicle Circuit Breaker (CB-SF6) 24kV, 16kA, 630 A set 1.00 750,000,000.00 750,000,000.00
IM - SM 6 type Cubicle lengkap dengan :
- Circuit Breaker (CB-SF6) 24kV, 16kA, 630 A
- Voltage Indicators 3 Pcs
- Busbar 630 A 3 unit
- Heater 50 W, 220 VAC
- CIT Operating Mechanism
Trafo Protection Cublicle Circuit Breaker (CB-SF6) 24kV, 16kA, 630 A set 1.00 550,000,000.00 550,000,000.00
QM - SM6 type Cubicle lengkap dengan :
- Circuit Breaker (CB-SF6) 24kV, 16kA, 630 A
- Voltage Indicators 3 Pcs
- Busbar 630A 3 unit
- Heater 50 W, 220 VAC
- Shunt Trip 220 VAC 50 Hz
- Solefuse x 3
Surge Arrester Cubicle Gamla set 1.00 25,000,000.00 25,000,000.00
- Casing Cubicle 20 kV
- Lighning Arrester 24 kV 3 buah
- Busbar 630A 3 buah
- Asesoris
2 Transformator set 1.00 2,400,000,000.00 2,400,000,000.00
- Kapasitas 800 kVA, 20 kV/400 Volt
- Vector Group : DYn5
3 Kabel Tegangan Menengah
- N2XSEFGbY 3x50 mm2 m 50.00 280,000.00 14,000,000.00
- NSXSY 1x50 mm2 m 25.00 170,000.00 4,250,000.00
sub total 3,743,250,000.00
B PANEL TEGANGAN RENDAH & KABEL TOEVOER
B.1 PANEL TEGANGAN RENDAH
Standing Floor cubicle, steel sheet metal ( 4 mm min), cat bakar . Komponen sesuai
dengan diagram satu garis pada gbr rencana, lengkap dgn grounding panel (netral+body).
1 Panel LVMDP
- Panel Box Uk. 2000(H) x 2(700)+4(600)(W) x 1000(D)MM unit 1.00 690,000,000.00 690,000,000.00
Type : Free Standing
Material Plat : 2 MM
Painting : Powder Coating
Incoming
- ACB 6300 4P 65KA, NW32 F/T bh 2.00
- Motor For ACB NW bh 2.00
- Closing Release ForACB NW bh 6.00
- UVT For ACB NW bh 2.00
- Auxs Switches (4 OF) U/ACB bh 6.00
- CT 6000/5A, 15VA, CLASS 1 bh 15.00
- Frequency Meter 220V bh 2.00
- Ampere Meter MI CT .../5A bh 6.00
- Voltmeter 0-500 V bh 2.00
- Surge Arrester 3P+N 40KA bh 2.00
- Volt Selector Switch 7 Posisi bh 2.00
- Push Button Switch 25mm bh 6.00
- Power Factor Meter CT .../5A bh 1.00
- Selector Switch M-O-A 2P bh 1.00
- Relay + Timer lot 1.00
- Pilot Lamp 220 VAC bh 12.00
- Miniature Fuse Link 4A lot 1.00
Outgoing

Rincian RAB MEP (Penyediaan Jaringan dan Distribusi Listrik)


Universitas Muhammadiyah Tangerang
Page 33
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

- ACB 1600A 3P 65KA, NW 10 F/T Type H1 MIC 2.0A bh 1.00


- Shunt Trip For ACB Type NW bh 1.00
- MCCB 252-650A 3P 50KA, NSX630N bh 2.00
- Shunt Trip For NS400 bh 2.00
- MCCB 160-400A 3P 36KA, NSX400F bh 3.00
- Shunt Trip For NS400 bh 3.00
- MCCB 87.5-125A 3P 36KA, NSX160F bh 1.00
- Shunt Trip For NS100 bh 2.00
- LBS 2500A 3P 36KA bh 1.00
- LBS 1600A 3P 36KA bh 1.00
- Three Phase Energy Meter (LCD) ST/DT CT.../5A bh 11.00
- CT 1000/5A, 15VA Class 1 bh 3.00
- CT 600/5A, 5VA Class 1 bh 6.00
- CT 400/5A, 5VA Class 1 bh 12.00
- CT 150/5A, 2.5VA Class 1 bh 3.00
- CT 150/5A, 2.5VA Class 1 bh 3.00
- CT 50/5A, 2.5VA Class 1 bh 3.00
- CU Busbar lot 1.00
- Sub Material lot 1.00
- Cable Wiring & Accessories lot 1.00
sub total 690,000,000.00
2 Panel AMF PKG
- Panel Box Uk. 2000(H) x 2(700)+4(600)(W) x 1000(D)MM unit 1.00 540,000,000.00 540,000,000.00
Type : Free Standing
Material Plat : 2 MM
Painting : Powder Coating
Incoming
- ACB 1600A 4P 65KA, NW16 F/T bh 2.00
- Motor For ACB NW bh 2.00
- UVT For ACB NW bh 2.00
- Closing Release For ACB NW bh 2.00
- Auxs Switches (4 OF) U/ACB bh 6.00
- Auto Synchroniser & Load Sharing Type 7510 bh 2.00
c/w: A, V, F, KW, KWH, KVA, KVAH, KVARH & PF
- CT 1600/5A, 15VA Class 1 bh 14.00
- Ampere Meter MI CT .../5A bh 6.00
- Voltmeter (0-500V) bh 2.00
- Volt Selector Switch 7 Posisi bh 2.00
- Frequency Meter 220V bh 2.00
- Kilowatt Meter 3 Phase 4 Wire CT .../5A 400V bh 1.00
- Power Factor Meter CT .../5A bh 1.00
- Double Volt Meter bh 1.00
- Double Frequency Meter bh 1.00
- Zero Volt Meter bh 1.00
- Hour Counter 220V bh 2.00
- Battery Charger 24VDC bh 2.00
- Ampere Meter 0-10VDC bh 2.00
- Volt Meter 0-30 VDC bh 2.00
- Emergency Push Button bh 2.00
- Baby Sirene 24VDC bh 1.00
- Relay + Timer lot 1.00
- Push Button Switch 25MM bh 4.00
- Pilot Lamp 220VAC bh 15.00
- Miniature Fuse Link 4A lot 1.00
Outgoing
- LBS 3200A 3P Type Sirco bh 1.00
- CU Busbar lot 1.00
- Sub Material lot 1.00
- Cable Wiring & Accessories lot 1.00
sub total 540,000,000.00

Rincian RAB MEP (Penyediaan Jaringan dan Distribusi Listrik)


Universitas Muhammadiyah Tangerang
Page 34
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

3 Capacitor Bank 250 KVAR unit 1.00 250,000,000.00 250,000,000.00


sub total 250,000,000.00
Box Panel - Wall mounted cubicle, steel sheet metal ( 2 mm min), cat bakar . Komponen sesuai
dengan diagram satu garis pada gbr rencana, lengkap dgn grounding panel (netral+body).
4 PANEL SDP LIGHTING GROUNDFLOOR (SDP.LP-01) 35,000,000.00
- Panel Box Uk. 80 x 60 x 25cm bh 1.00
- Pilot lamp & fuse bh 3.00
- CT 500/5A bh 3.00
- Ampere meter bh 3.00
- Voltmeter (0-500V) bh 1.00
- Frequency Meter 220V bh 1.00
- KWH Meter 3 Phase, Digital bh 1.00
- Selector switch bh 1.00
- MCCB 18kA 3P 125 A bh 1.00
- MCCB 7,5kA 3P 25 A bh 12.00
- Grounding panel lokal set 1.00
- Busbar RSTN-GND set 1.00
- Kabel, Wiring & Pemasangan set 1.00
- Material Bantu set 1.00
Sub Total PANEL SDP LIGHTING GROUNDFLOOR (SDP.LP-01) 35,000,000.00
5 PANEL SDP LIGHTING LANTAI 10 (SDP.LP-02) 35,000,000.00
- Panel Box Uk. 80 x 60 x 25cm bh 1.00
- Pilot lamp & fuse bh 3.00
- CT 500/5A bh 3.00
- Ampere meter bh 3.00
- Voltmeter (0-500V) bh 1.00
- Frequency Meter 220V bh 1.00
- KWH Meter 3 Phase, Digital bh 1.00
- Selector switch bh 1.00
- MCCB 18kA 3P 225 A bh 1.00
- MCCB 7,5kA 3P 25 A bh 11.00
- Grounding panel lokal set 1.00
- Busbar RSTN-GND set 1.00
- Kabel, Wiring & Pemasangan set 1.00
- Material Bantu set 1.00
Sub Total PANEL SDP LIGHTING LANTAI 10 (SDP.LP-02) 35,000,000.00
6 PANEL SDP AC LANTAI 2 (SDP.AC-01) 35,000,000.00
- Panel Box Uk. 80 x 60 x 25cm bh 1.00
- Pilot lamp & fuse bh 3.00
- CT 500/5A bh 3.00
- Ampere meter bh 3.00
- Voltmeter (0-500V) bh 1.00
- Frequency Meter 220V bh 1.00
- KWH Meter 3 Phase, Digital bh 1.00
- Selector switch bh 1.00
- MCCB 18kA 3P 250 A bh 1.00
- MCCB 7,5kA 3P 50 A bh 7.00
- MCCB 7,5kA 3P 20 A bh 1.00
- Grounding panel lokal set 1.00
- Busbar RSTN-GND set 1.00
- Kabel, Wiring & Pemasangan set 1.00
- Material Bantu set 1.00
Sub Total PANEL SDP AC LANTAI 2 (SDP.AC-01) 35,000,000.00
7 PANEL SDP AC LANTAI 12 (SDP.AC-02) 35,000,000.00
- Panel Box Uk. 80 x 60 x 25cm bh 1.00
- Pilot lamp & fuse bh 3.00
- CT 500/5A bh 3.00
- Ampere meter bh 3.00
- Voltmeter (0-500V) bh 1.00

Rincian RAB MEP (Penyediaan Jaringan dan Distribusi Listrik)


Universitas Muhammadiyah Tangerang
Page 35
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

- Frequency Meter 220V bh 1.00


- KWH Meter 3 Phase, Digital bh 1.00
- Selector switch bh 1.00
- MCCB 18kA 3P 250 A bh 1.00
- MCCB 7,5kA 3P 40 A bh 8.00
- MCCB 7,5kA 3P 20 A bh 1.00
- Grounding panel lokal set 1.00
- Busbar RSTN-GND set 1.00
- Kabel, Wiring & Pemasangan set 1.00
- Material Bantu set 1.00
Sub Total PANEL SDP AC LANTAI 12 (SDP.AC-02) 35,000,000.00
8 Panel Emergency (SDP-E) 35,000,000.00
- Panel Box Uk. 80 x 60 x 25cm bh 1.00
- Pilot lamp & fuse bh 3.00
- CT 500/5A bh 3.00
- Ampere meter bh 3.00
- Voltmeter (0-500V) bh 1.00
- Frequency Meter 220V bh 1.00
- KWH Meter 3 Phase, Digital bh 1.00
- Selector switch bh 1.00
- MCCB 18kA 3P 75 A bh 1.00
- MCCB 7,5kA 3P 60 A bh 2.00
- MCCB 7,5kA 3P 20 A bh 1.00
- Grounding panel lokal set 1.00
- Busbar RSTN-GND set 1.00
- Kabel, Wiring & Pemasangan set 1.00
- Material Bantu set 1.00
Sub Total Panel Emergency (SDP-E) 35,000,000.00
9 Panel Lantai Atap (P-LA) 27,500,000.00
- Panel Box Uk. 60 x 40 x 25cm bh 1.00
- Pilot lamp & fuse bh 3.00
- CT 500/5A bh 3.00
- Ampere meter bh 3.00
- Voltmeter (0-500V) bh 1.00
- Frequency Meter 220V bh 1.00
- KWH Meter 3 Phase, Digital bh 1.00
- Selector switch bh 1.00
- MCCB 16k 3P 60 A bh 1.00
- MCCB 10k 3P 60 A bh 1.00
- MCCB 7,5kA 3P 25 A bh 1.00
- MCCB 7,5kA 3P 20 A bh 1.00
- MCCB 7,5kA 3P 16 A bh 8.00
- Grounding panel lokal set 1.00
- Busbar RSTN-GND set 1.00
- Kabel, Wiring & Pemasangan set 1.00
- Material Bantu set 1.00
Sub Total Panel Lantai Atap (P-LA) 27,500,000.00
10 Panel Hydrant 35,000,000.00
- Panel Box Uk. 80 x 60 x 25cm bh 1.00
- Pilot lamp & fuse bh 3.00
- CT 500/5A bh 3.00
- Ampere meter bh 3.00
- Voltmeter (0-500V) bh 1.00
- Frequency Meter 220V bh 1.00
- KWH Meter 3 Phase, Digital bh 1.00
- Selector switch bh 1.00
- MCCB 36kA 3P 350 A bh 1.00
- MCCB 18kA 3P 320 A bh 1.00
- MCCB 7,5kA 3P 25 A bh 2.00
- MCCB 7,5kA 3P 20 A bh 1.00

Rincian RAB MEP (Penyediaan Jaringan dan Distribusi Listrik)


Universitas Muhammadiyah Tangerang
Page 36
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

- Grounding panel lokal set 1.00


- Busbar RSTN-GND set 1.00
- Kabel, Wiring & Pemasangan set 1.00
- Material Bantu set 1.00
Sub Total Panel Hydrant 35,000,000.00
11 Panel Pompa (P-P) 27,500,000.00
- Panel Box Wall Mounted 60 x 40 x 20cm bh 1.00
- Pilot lamp & fuse bh 3.00
- MCCB 7,5kA 3P 30 A bh 1.00
- MCB 4,5kA 1P 16 A bh 3.00
- Busbar RSTN-GND ls 1.00
- Kabel, Wiring & Pemasangan ls 1.00
- Material Bantu ls 1.00
Sub Total Panel Pompa (P-P) 27,500,000.00
12 Panel Presurrized Fan (P-PS) 27,500,000.00
- Panel Box Wall Mounted 60 x 40 x 20cm bh 1.00
- Pilot lamp & fuse bh 3.00
- MCCB 7,5kA 3P 50 A bh 1.00
- MCCB 7,5kA 3P 40 A bh 1.00
- MCB 4,5kA 1P 10 A bh 1.00
- Busbar RSTN-GND ls 1.00
- Kabel, Wiring & Pemasangan ls 1.00
- Material Bantu ls 1.00
Sub Total Panel Presurrized Fan (P-PS) 27,500,000.00
13 Panel Exhaust Fan (P-ES) 27,500,000.00
- Panel Box Wall Mounted 60 x 40 x 20cm bh 1.00
- Pilot lamp & fuse bh 3.00
- MCCB 7,5kA 3P 50 A bh 1.00
- MCCB 7,5kA 3P 40 A bh 1.00
- MCB 4,5kA 1P 10 A bh 1.00
- Busbar RSTN-GND ls 1.00
- Kabel, Wiring & Pemasangan ls 1.00
- Material Bantu ls 1.00
Sub Total Panel Exhaust Fan (P-ES) 27,500,000.00
14 Panel Gondola (P-G) 27,500,000.00
- Panel Box Wall Mounted 60 x 40 x 20cm bh 1.00
- Pilot lamp & fuse bh 3.00
- MCCB 10k 3P 50 A bh 1.00
- MCCB 7,5kA 3P 50 A bh 1.00
- MCB 4,5kA 1P 10 A bh 1.00
- Busbar RSTN-GND ls 1.00
- Kabel, Wiring & Pemasangan ls 1.00
- Material Bantu ls 1.00
Sub Total Panel Gondola (P-G) 27,500,000.00
15 Panel Lift Service (P-LS) 27,500,000.00
- Panel Box Wall Mounted 60 x 40 x 20cm bh 1.00
- Pilot lamp & fuse bh 3.00
- MCCB 10k 3P 50 A bh 1.00
- MCCB 7,5kA 3P 40 A bh 1.00
- MCB 4,5kA 1P 10 A bh 1.00
- Busbar RSTN-GND ls 1.00
- Kabel, Wiring & Pemasangan ls 1.00
- Material Bantu ls 1.00
Sub Total Panel Lift Service (P-LS) 27,500,000.00
16 Panel Lift (P-LIFT) 27,500,000.00
- Panel Box Wall Mounted 60 x 40 x 20cm bh 1.00
- Pilot lamp & fuse bh 3.00
- MCCB 18k 3P 225 A bh 1.00
- MCCB 10k 3P 50 A bh 6.00
- MCB 4,5kA 1P 10 A bh 1.00

Rincian RAB MEP (Penyediaan Jaringan dan Distribusi Listrik)


Universitas Muhammadiyah Tangerang
Page 37
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

- Busbar RSTN-GND ls 1.00


- Kabel, Wiring & Pemasangan ls 1.00
- Material Bantu ls 1.00
Sub Total Panel Lift (P-LIFT) 27,500,000.00
17 Panel AC Basement 1 (PAC.B1) 35,000,000.00
- Panel Box Wall Mounted 80 x 60 x 20cm bh 1.00
- Pilot lamp & fuse bh 3.00
- MCCB 7,5kA 3P 40 A bh 1.00
- MCB 4,5kA 1P 16 A bh 12.00
- Busbar RSTN-GND ls 1.00
- Kabel, Wiring & Pemasangan ls 1.00
- Material Bantu ls 1.00
Sub Total Panel AC Basement 1 (PAC.B1) 35,000,000.00
18 Panel AC Ground Floor (PAC.G) 35,000,000.00
- Panel Box Wall Mounted 80 x 60 x 20cm bh 1.00
- Pilot lamp & fuse bh 3.00
- MCCB 7,5kA 3P 40 A bh 1.00
- MCB 4,5kA 1P 16 A bh 12.00
- Busbar RSTN-GND ls 1.00
- Kabel, Wiring & Pemasangan ls 1.00
- Material Bantu ls 1.00
Sub Total Panel AC Ground Floor (PAC.G) 35,000,000.00
19 Panel AC Lantai 6 (PAC.6) 35,000,000.00
- Panel Box Wall Mounted 80 x 60 x 20cm bh 1.00
- Pilot lamp & fuse bh 3.00
- MCCB 7,5kA 3P 40 A bh 1.00
- MCB 4,5kA 1P 16 A bh 10.00
- Busbar RSTN-GND ls 1.00
- Kabel, Wiring & Pemasangan ls 1.00
- Material Bantu ls 1.00
Sub Total Panel AC Lantai 6 (PAC.6) 35,000,000.00
20 Panel AC Lantai 7 (PAC.7) 35,000,000.00
- Panel Box Wall Mounted 80 x 60 x 20cm bh 1.00
- Pilot lamp & fuse bh 3.00
- MCCB 7,5kA 3P 40 A bh 1.00
- MCB 4,5kA 1P 16 A bh 12.00
- Busbar RSTN-GND ls 1.00
- Kabel, Wiring & Pemasangan ls 1.00
- Material Bantu ls 1.00
Sub Total Panel AC Lantai 7 (PAC.7) 35,000,000.00
21 Panel AC Lantai 8 (PAC.8) 35,000,000.00
- Panel Box Wall Mounted 80 x 60 x 20cm bh 1.00
- Pilot lamp & fuse bh 3.00
- MCCB 7,5kA 3P 40 A bh 1.00
- MCB 4,5kA 1P 16 A bh 14.00
- Busbar RSTN-GND ls 1.00
- Kabel, Wiring & Pemasangan ls 1.00
- Material Bantu ls 1.00
Sub Total Panel AC Lantai 8 (PAC.8) 35,000,000.00
22 Panel AC Lantai 9 (PAC.9) 35,000,000.00
- Panel Box Wall Mounted 80 x 60 x 20cm bh 1.00
- Pilot lamp & fuse bh 3.00
- MCCB 7,5kA 3P 40 A bh 1.00
- MCB 4,5kA 1P 16 A bh 14.00
- Busbar RSTN-GND ls 1.00
- Kabel, Wiring & Pemasangan ls 1.00
- Material Bantu ls 1.00
Sub Total Panel AC Lantai 9 (PAC.9) 35,000,000.00
23 Panel AC Lantai 10 (PAC.10) 35,000,000.00
- Panel Box Wall Mounted 80 x 60 x 20cm bh 1.00

Rincian RAB MEP (Penyediaan Jaringan dan Distribusi Listrik)


Universitas Muhammadiyah Tangerang
Page 38
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

- Pilot lamp & fuse bh 3.00


- MCCB 7,5kA 3P 40 A bh 1.00
- MCB 4,5kA 1P 16 A bh 14.00
- Busbar RSTN-GND ls 1.00
- Kabel, Wiring & Pemasangan ls 1.00
- Material Bantu ls 1.00
Sub Total Panel AC Lantai 10 (PAC.10) 35,000,000.00
24 Panel AC Lantai 11 (PAC.11) 35,000,000.00
- Panel Box Wall Mounted 80 x 60 x 20cm bh 1.00
- Pilot lamp & fuse bh 3.00
- MCCB 7,5kA 3P 40 A bh 1.00
- MCB 4,5kA 1P 16 A bh 14.00
- Busbar RSTN-GND ls 1.00
- Kabel, Wiring & Pemasangan ls 1.00
- Material Bantu ls 1.00
Sub Total Panel AC Lantai 11 (PAC.11) 35,000,000.00
25 Panel AC Lantai 12 (PAC.12) 35,000,000.00
- Panel Box Wall Mounted 80 x 60 x 20cm bh 1.00
- Pilot lamp & fuse bh 3.00
- MCCB 7,5kA 3P 40 A bh 1.00
- MCB 4,5kA 1P 16 A bh 14.00
- Busbar RSTN-GND ls 1.00
- Kabel, Wiring & Pemasangan ls 1.00
- Material Bantu ls 1.00
Sub Total Panel AC Lantai 12 (PAC.12) 35,000,000.00
26 Panel AC Lantai 13 (PAC.13) 35,000,000.00
- Panel Box Wall Mounted 80 x 60 x 20cm bh 1.00
- Pilot lamp & fuse bh 3.00
- MCCB 7,5kA 3P 40 A bh 1.00
- MCB 4,5kA 1P 16 A bh 14.00
- Busbar RSTN-GND ls 1.00
- Kabel, Wiring & Pemasangan ls 1.00
- Material Bantu ls 1.00
Sub Total Panel AC Lantai 13 (PAC.13) 35,000,000.00
27 Panel AC Lantai 14 (PAC.14) 35,000,000.00
- Panel Box Wall Mounted 80 x 60 x 20cm bh 1.00
- Pilot lamp & fuse bh 3.00
- MCCB 7,5kA 3P 40 A bh 1.00
- MCB 4,5kA 1P 16 A bh 14.00
- Busbar RSTN-GND ls 1.00
- Kabel, Wiring & Pemasangan ls 1.00
- Material Bantu ls 1.00
Sub Total Panel AC Lantai 14 (PAC.14) 35,000,000.00
28 Panel AC Lantai 15 (PAC.15) 35,000,000.00
- Panel Box Wall Mounted 80 x 60 x 20cm bh 1.00
- Pilot lamp & fuse bh 3.00
- MCCB 7,5kA 3P 40 A bh 1.00
- MCB 4,5kA 1P 16 A bh 14.00
- Busbar RSTN-GND ls 1.00
- Kabel, Wiring & Pemasangan ls 1.00
- Material Bantu ls 1.00
Sub Total Panel AC Lantai 15 (PAC.15) 35,000,000.00
29 Panel AC Lantai 16 (PAC.16) 35,000,000.00
- Panel Box Wall Mounted 80 x 60 x 20cm bh 1.00
- Pilot lamp & fuse bh 3.00
- MCCB 7,5kA 3P 40 A bh 1.00
- MCB 4,5kA 1P 16 A bh 14.00
- Busbar RSTN-GND ls 1.00
- Kabel, Wiring & Pemasangan ls 1.00
- Material Bantu ls 1.00

Rincian RAB MEP (Penyediaan Jaringan dan Distribusi Listrik)


Universitas Muhammadiyah Tangerang
Page 39
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

Sub Total Panel AC Lantai 16 (PAC.16) 35,000,000.00


30 Panel AC Lantai 17 (PAC.17) 35,000,000.00 -
- Panel Box Wall Mounted 80 x 60 x 20cm bh 1.00
- Pilot lamp & fuse bh 3.00
- MCCB 7,5kA 3P 40 A bh 1.00
- MCB 4,5kA 1P 16 A bh 14.00
- Busbar RSTN-GND ls 1.00
- Kabel, Wiring & Pemasangan ls 1.00
- Material Bantu ls 1.00
Sub Total Panel AC Lantai 17 (PAC.17) 35,000,000.00
31 Panel AC Lantai 18 (PAC.18) 35,000,000.00
- Panel Box Wall Mounted 80 x 60 x 20cm bh 1.00
- Pilot lamp & fuse bh 3.00
- MCCB 7,5kA 3P 40 A bh 1.00
- MCB 4,5kA 1P 16 A bh 14.00
- Busbar RSTN-GND ls 1.00
- Kabel, Wiring & Pemasangan ls 1.00
- Material Bantu ls 1.00
Sub Total Panel AC Lantai 18 (PAC.18) 35,000,000.00
32 Panel AC Lantai 19 (PAC.19) 35,000,000.00
- Panel Box Wall Mounted 80 x 60 x 20cm bh 1.00
- Pilot lamp & fuse bh 3.00
- MCCB 7,5kA 3P 40 A bh 1.00
- MCB 4,5kA 1P 16 A bh 14.00
- Busbar RSTN-GND ls 1.00
- Kabel, Wiring & Pemasangan ls 1.00
- Material Bantu ls 1.00
Sub Total Panel AC Lantai 19 (PAC.19) 35,000,000.00
33 Panel Penerangan Basement 1 (LP.B1) 35,000,000.00
- Panel Box Wall Mounted 80 x 60 x 20cm bh 1.00
- Pilot lamp & fuse bh 3.00
- MCCB 7,5kA 3P 20 A bh 1.00
- MCB 4,5kA 1P 10 A bh 4.00
- MCB 4,5kA 1P 6A bh 3.00
- Busbar RSTN-GND ls 1.00
- Kabel, Wiring & Pemasangan ls 1.00
- Material Bantu ls 1.00
Sub Total Panel Penerangan Basement 1 (LP.B1) 35,000,000.00
34 Panel Penerangan Ground Floor (LP.G) 35,000,000.00
- Panel Box Wall Mounted 80 x 60 x 20cm bh 1.00
- Pilot lamp & fuse bh 3.00
- MCCB 7,5kA 3P 20 A bh 1.00
- MCB 4,5kA 1P 10 A bh 7.00
- MCB 4,5kA 1P 6A bh 7.00
- Busbar RSTN-GND ls 1.00
- Kabel, Wiring & Pemasangan ls 1.00
- Material Bantu ls 1.00
Sub Total Panel Penerangan Ground Floor (LP.G) 35,000,000.00
35 Panel Penerangan Lantai 1 (LP.1) 35,000,000.00
- Panel Box Wall Mounted 80 x 60 x 20cm bh 1.00
- Pilot lamp & fuse bh 3.00
- MCCB 7,5kA 3P 20 A bh 1.00
- MCB 4,5kA 1P 10 A bh 3.00
- MCB 4,5kA 1P 6A bh 4.00
- Busbar RSTN-GND ls 1.00
- Kabel, Wiring & Pemasangan ls 1.00
- Material Bantu ls 1.00
Sub Total Panel Penerangan Lantai 1 (LP.1) 35,000,000.00
36 Panel Penerangan Lantai 2 (LP.2) 35,000,000.00
- Panel Box Wall Mounted 80 x 60 x 20cm

Rincian RAB MEP (Penyediaan Jaringan dan Distribusi Listrik)


Universitas Muhammadiyah Tangerang
Page 40
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

- Pilot lamp & fuse bh 3.00


- MCCB 7,5kA 3P 20 A bh 1.00
- MCB 4,5kA 1P 10 A bh 3.00
- MCB 4,5kA 1P 6A bh 4.00
- Busbar RSTN-GND ls 1.00
- Kabel, Wiring & Pemasangan ls 1.00
- Material Bantu ls 1.00
Sub Total Panel Penerangan Lantai 2 (LP.2) 35,000,000.00
37 Panel Penerangan Lantai 3 (LP.3) 35,000,000.00
- Panel Box Wall Mounted 80 x 60 x 20cm bh 1.00
- Pilot lamp & fuse bh 3.00
- MCCB 7,5kA 3P 20 A bh 1.00
- MCB 4,5kA 1P 10 A bh 4.00
- MCB 4,5kA 1P 6A bh 3.00
- Busbar RSTN-GND ls 1.00
- Kabel, Wiring & Pemasangan ls 1.00
- Material Bantu ls 1.00
Sub Total Panel Penerangan Lantai 3 (LP.3) 35,000,000.00
38 Panel Penerangan Lantai 4 (LP.4) 35,000,000.00
- Panel Box Wall Mounted 80 x 60 x 20cm bh 1.00
- Pilot lamp & fuse bh 3.00
- MCCB 7,5kA 3P 20 A bh 1.00
- MCB 4,5kA 1P 10 A bh 4.00
- MCB 4,5kA 1P 6A bh 3.00
- Busbar RSTN-GND ls 1.00
- Kabel, Wiring & Pemasangan ls 1.00
- Material Bantu ls 1.00
Sub Total Panel Penerangan Lantai 4 (LP.4) 35,000,000.00
39 Panel Penerangan Lantai 5 (LP.5) 35,000,000.00
- Panel Box Wall Mounted 80 x 60 x 20cm bh 1.00
- Pilot lamp & fuse bh 3.00
- MCCB 7,5kA 3P 20 A bh 1.00
- MCB 4,5kA 1P 10 A bh 4.00
- MCB 4,5kA 1P 6A bh 3.00
- Busbar RSTN-GND ls 1.00
- Kabel, Wiring & Pemasangan ls 1.00
- Material Bantu ls 1.00
Sub Total Panel Penerangan Lantai 5 (LP.5) 35,000,000.00
40 Panel Penerangan Lantai 6 (LP.6) 35,000,000.00
- Panel Box Wall Mounted 80 x 60 x 20cm bh 1.00
- Pilot lamp & fuse bh 3.00
- MCCB 7,5kA 3P 20 A bh 1.00
- MCB 4,5kA 1P 10 A bh 6.00
- MCB 4,5kA 1P 6A bh 5.00
- Busbar RSTN-GND ls 1.00
- Kabel, Wiring & Pemasangan ls 1.00
- Material Bantu ls 1.00
Sub Total Panel Penerangan Lantai 6 (LP.6) 35,000,000.00
41 Panel Penerangan Lantai 7 (LP.7) 35,000,000.00
- Panel Box Wall Mounted 80 x 60 x 20cm bh 1.00
- Pilot lamp & fuse bh 3.00
- MCCB 7,5kA 3P 20 A bh 1.00
- MCB 4,5kA 1P 10 A bh 5.00
- MCB 4,5kA 1P 6A bh 6.00
- Busbar RSTN-GND ls 1.00
- Kabel, Wiring & Pemasangan ls 1.00
- Material Bantu ls 1.00
Sub Total Panel Penerangan Lantai 7 (LP.7) 35,000,000.00
42 Panel Penerangan Lantai 8 (LP.8) 35,000,000.00
- Panel Box Wall Mounted 80 x 60 x 20cm bh 1.00

Rincian RAB MEP (Penyediaan Jaringan dan Distribusi Listrik)


Universitas Muhammadiyah Tangerang
Page 41
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

- Pilot lamp & fuse bh 3.00


- MCCB 7,5kA 3P 20 A bh 1.00
- MCB 4,5kA 1P 10 A bh 10.00
- MCB 4,5kA 1P 6A bh 6.00
- Busbar RSTN-GND ls 1.00
- Kabel, Wiring & Pemasangan ls 1.00
- Material Bantu ls 1.00
Sub Total Panel Penerangan Lantai 8 (LP.8) 35,000,000.00
43 Panel Penerangan Lantai 9 (LP.9) 35,000,000.00
- Panel Box Wall Mounted 80 x 60 x 20cm bh 1.00
- Pilot lamp & fuse bh 3.00
- MCCB 7,5kA 3P 20 A bh 1.00
- MCB 4,5kA 1P 10 A bh 10.00
- MCB 4,5kA 1P 6A bh 6.00
- Busbar RSTN-GND ls 1.00
- Kabel, Wiring & Pemasangan ls 1.00
- Material Bantu ls 1.00
Sub Total Panel Penerangan Lantai 9 (LP.9) 35,000,000.00
44 Panel Penerangan Lantai 10 (LP.10) 35,000,000.00
- Panel Box Wall Mounted 80 x 60 x 20cm bh 1.00
- Pilot lamp & fuse bh 3.00
- MCCB 7,5kA 3P 20 A bh 1.00
- MCB 4,5kA 1P 10 A bh 10.00
- MCB 4,5kA 1P 6A bh 6.00
- Busbar RSTN-GND ls 1.00
- Kabel, Wiring & Pemasangan ls 1.00
- Material Bantu ls 1.00
Sub Total Panel Penerangan Lantai 10 (LP.10) 35,000,000.00
45 Panel Penerangan Lantai 11 (LP.11) 35,000,000.00
- Panel Box Wall Mounted 80 x 60 x 20cm bh 1.00
- Pilot lamp & fuse bh 3.00
- MCCB 7,5kA 3P 20 A bh 1.00
- MCB 4,5kA 1P 10 A bh 10.00
- MCB 4,5kA 1P 6A bh 6.00
- Busbar RSTN-GND ls 1.00
- Kabel, Wiring & Pemasangan ls 1.00
- Material Bantu ls 1.00
Sub Total Panel Penerangan Lantai 11 (LP.11) 35,000,000.00
46 Panel Penerangan Lantai 12 (LP.12) 35,000,000.00
- Panel Box Wall Mounted 80 x 60 x 20cm bh 1.00
- Pilot lamp & fuse bh 3.00
- MCCB 7,5kA 3P 20 A bh 1.00
- MCB 4,5kA 1P 10 A bh 10.00
- MCB 4,5kA 1P 6A bh 6.00
- Busbar RSTN-GND ls 1.00
- Kabel, Wiring & Pemasangan ls 1.00
- Material Bantu ls 1.00
Sub Total Panel Penerangan Lantai 12 (LP.12) 35,000,000.00
47 Panel Penerangan Lantai 13 (LP.13) 35,000,000.00
- Panel Box Wall Mounted 80 x 60 x 20cm bh 1.00
- Pilot lamp & fuse bh 3.00
- MCCB 7,5kA 3P 20 A bh 1.00
- MCB 4,5kA 1P 10 A bh 10.00
- MCB 4,5kA 1P 6A bh 6.00
- Busbar RSTN-GND ls 1.00
- Kabel, Wiring & Pemasangan ls 1.00
- Material Bantu ls 1.00
Sub Total Panel Penerangan Lantai 13 (LP.13) 35,000,000.00
48 Panel Penerangan Lantai 14 (LP.14) 35,000,000.00
- Panel Box Wall Mounted 80 x 60 x 20cm bh 1.00

Rincian RAB MEP (Penyediaan Jaringan dan Distribusi Listrik)


Universitas Muhammadiyah Tangerang
Page 42
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

- Pilot lamp & fuse bh 3.00


- MCCB 7,5kA 3P 20 A bh 1.00
- MCB 4,5kA 1P 10 A bh 10.00
- MCB 4,5kA 1P 6A bh 6.00
- Busbar RSTN-GND ls 1.00
- Kabel, Wiring & Pemasangan ls 1.00
- Material Bantu ls 1.00
Sub Total Panel Penerangan Lantai 14 (LP.14) 35,000,000.00
49 Panel Penerangan Lantai 15 (LP.15) 35,000,000.00
- Panel Box Wall Mounted 80 x 60 x 20cm bh 1.00
- Pilot lamp & fuse bh 3.00
- MCCB 7,5kA 3P 20 A bh 1.00
- MCB 4,5kA 1P 10 A bh 10.00
- MCB 4,5kA 1P 6A bh 6.00
- Busbar RSTN-GND ls 1.00
- Kabel, Wiring & Pemasangan ls 1.00
- Material Bantu ls 1.00
Sub Total Panel Penerangan Lantai 15 (LP.15) 35,000,000.00
50 Panel Penerangan Lantai 16 (LP.16) 35,000,000.00
- Panel Box Wall Mounted 80 x 60 x 20cm bh 1.00
- Pilot lamp & fuse bh 3.00
- MCCB 7,5kA 3P 20 A bh 1.00
- MCB 4,5kA 1P 10 A bh 10.00
- MCB 4,5kA 1P 6A bh 6.00
- Busbar RSTN-GND ls 1.00
- Kabel, Wiring & Pemasangan ls 1.00
- Material Bantu ls 1.00
Sub Total Panel Penerangan Lantai 16 (LP.16) 35,000,000.00
51 Panel Penerangan Lantai 17 (LP.17) 35,000,000.00
- Panel Box Wall Mounted 80 x 60 x 20cm bh 1.00
- Pilot lamp & fuse bh 3.00
- MCCB 7,5kA 3P 20 A bh 1.00
- MCB 4,5kA 1P 10 A bh 10.00
- MCB 4,5kA 1P 6A bh 6.00
- Busbar RSTN-GND ls 1.00
- Kabel, Wiring & Pemasangan ls 1.00
- Material Bantu ls 1.00
Sub Total Panel Penerangan Lantai 17 (LP.17) 35,000,000.00
52 Panel Penerangan Lantai 18 (LP.18) 35,000,000.00
- Panel Box Wall Mounted 80 x 60 x 20cm bh 1.00
- Pilot lamp & fuse bh 3.00
- MCCB 7,5kA 3P 20 A bh 1.00
- MCB 4,5kA 1P 10 A bh 10.00
- MCB 4,5kA 1P 6A bh 6.00
- Busbar RSTN-GND ls 1.00
- Kabel, Wiring & Pemasangan ls 1.00
- Material Bantu ls 1.00
Sub Total Panel Penerangan Lantai 18 (LP.18) 35,000,000.00
53 Panel Penerangan Lantai 19 (LP.19) 35,000,000.00
- Panel Box Wall Mounted 80 x 60 x 20cm bh 1.00
- Pilot lamp & fuse bh 3.00
- MCCB 7,5kA 3P 20 A bh 1.00
- MCB 4,5kA 1P 10 A bh 16.00
- MCB 4,5kA 1P 6A bh 6.00
- Busbar RSTN-GND ls 1.00
- Kabel, Wiring & Pemasangan ls 1.00
- Material Bantu ls 1.00
Sub Total Panel Penerangan Lantai 19 (LP.19) 35,000,000.00
B.2 INSTALASI KABEL TOEVOER
Instalasi kabel dibawah tanah dengan menggunakan pelindung tekanan mekanis berupa pipa

Rincian RAB MEP (Penyediaan Jaringan dan Distribusi Listrik)


Universitas Muhammadiyah Tangerang
Page 43
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

besi atau buis beton dengan diameter menyesuaikan ukuran kabel toevoer
1 Kabel dari Transformator ke LVMDP -- NYY 8x4cx120mm2 m' 30.00 4,320,000.00 129,600,000.00
2 Kabel dari LVMDP ke Panel PKG -- NYY 8x4cx120mm2 m' 20.00 4,320,000.00 86,400,000.00
3 Kabel dari LVMDP ke Panel Capasitor Bank -- NYY 4x4cx120mm2 m' 10.00 2,160,000.00 21,600,000.00
4 Kabel dari LVMDP ke Panel AC.B1 -- NYY (4x10mm2) m' 25.00 120,000.00 3,000,000.00
5 Kabel dari LVMDP ke Panel P-P -- FRC (4x10mm2) m' 50.00 95,000.00 4,750,000.00
- Kabel dari Panel P-P ke Panel Pompa Transfer -- NYY (4x2,5mm2) m' 10.00 45,000.00 450,000.00
- Kabel dari Panel P-P ke Panel Pompa Deepwell -- NYY (4x4mm2) m' 10.00 60,000.00 600,000.00
6 Kabel dari LVMDP ke Panel P-HYDRANT -- FRC (4x1cx240mm2) m' 50.00 1,360,000.00 68,000,000.00
- Kabel dari Panel P-HYDRANT ke Panel P-JP -- NYY (4x6mm2) m' 10.00 85,000.00 850,000.00
- Kabel dari Panel P-HYDRANT ke Panel P-EH -- NYY (4x240mm2) m' 10.00 540,000.00 5,400,000.00
- Kabel dari Panel P-HYDRANT ke Panel P-JFP -- NYY (4x6mm2) m' 10.00 85,000.00 850,000.00
7 Kabel dari LVMDP ke Panel SDP.AC-1 -- NYY 4x120mm2 m' 30.00 540,000.00 16,200,000.00
- Kabel dari Panel SDP.AC-01 ke Panel PAC.G -- NYY (4x10mm2) m' 17.00 120,000.00 2,040,000.00
- Kabel dari Panel SDP.AC-01 ke Panel PAC.6 -- NYY (4x10mm2) m' 27.00 120,000.00 3,240,000.00
- Kabel dari Panel SDP.AC-01 ke Panel PAC.7 -- NYY (4x10mm2) m' 32.00 120,000.00 3,840,000.00
- Kabel dari Panel SDP.AC-01 ke Panel PAC.8 -- NYY (4x10mm2) m' 37.00 120,000.00 4,440,000.00
- Kabel dari Panel SDP.AC-01 ke Panel PAC.9 -- NYY (4x10mm2) m' 42.00 120,000.00 5,040,000.00
- Kabel dari Panel SDP.AC-01 ke Panel PAC.10 -- NYY (4x10mm2) m' 47.00 120,000.00 5,640,000.00
- Kabel dari Panel SDP.AC-01 ke Panel PAC.11 -- NYY (4x10mm2) m' 52.00 120,000.00 6,240,000.00
8 Kabel dari LVMDP ke Panel SDP.AC-2 -- NYY 4x120mm2 m' 65.00 120,000.00 7,800,000.00
- Kabel dari Panel SDP.AC-02 ke Panel PAC.12 -- NYY (4x10mm2) m' 17.00 120,000.00 2,040,000.00
- Kabel dari Panel SDP.AC-02 ke Panel PAC.13 -- NYY (4x10mm2) m' 22.00 120,000.00 2,640,000.00
- Kabel dari Panel SDP.AC-02 ke Panel PAC.14 -- NYY (4x10mm2) m' 27.00 120,000.00 3,240,000.00
- Kabel dari Panel SDP.AC-02 ke Panel PAC.15 -- NYY (4x10mm2) m' 32.00 120,000.00 3,840,000.00
- Kabel dari Panel SDP.AC-02 ke Panel PAC.16 -- NYY (4x10mm2) m' 37.00 120,000.00 4,440,000.00
- Kabel dari Panel SDP.AC-02 ke Panel PAC.17 -- NYY (4x10mm2) m' 42.00 120,000.00 5,040,000.00
- Kabel dari Panel SDP.AC-02 ke Panel PAC.18 -- NYY (4x10mm2) m' 47.00 120,000.00 5,640,000.00
9 Kabel dari LVMDP ke Panel SDP.LP-1 -- NYY (4x95mm2) m' 15.00 360,000.00 5,400,000.00
- Kabel dari Panel SDP.LP-01 ke Panel LP-.B -- NYY (4x6mm2) m' 15.00 85,000.00 1,275,000.00
- Kabel dari Panel SDP.LP-01 ke Panel LP-.G -- NYY (4x6mm2) m' 5.00 85,000.00 425,000.00
- Kabel dari Panel SDP.LP-01 ke Panel LP-.1 -- NYY (4x6mm2) m' 15.00 85,000.00 1,275,000.00
- Kabel dari Panel SDP.LP-01 ke Panel LP-.2 -- NYY (4x6mm2) m' 20.00 85,000.00 1,700,000.00
- Kabel dari Panel SDP.LP-01 ke Panel LP-.3 -- NYY (4x6mm2) m' 25.00 85,000.00 2,125,000.00
- Kabel dari Panel SDP.LP-01 ke Panel LP-.4 -- NYY (4x6mm2) m' 30.00 85,000.00 2,550,000.00
- Kabel dari Panel SDP.LP-01 ke Panel LP-.5 -- NYY (4x6mm2) m' 35.00 85,000.00 2,975,000.00
- Kabel dari Panel SDP.LP-01 ke Panel LP-.6 -- NYY (4x6mm2) m' 40.00 85,000.00 3,400,000.00
- Kabel dari Panel SDP.LP-01 ke Panel LP-.7 -- NYY (4x6mm2) m' 45.00 85,000.00 3,825,000.00
- Kabel dari Panel SDP.LP-01 ke Panel LP-.8 -- NYY (4x6mm2) m' 50.00 85,000.00 4,250,000.00
- Kabel dari Panel SDP.LP-01 ke Panel LP-.9 -- NYY (4x6mm2) m' 55.00 85,000.00 4,675,000.00
10 Kabel dari LVMDP ke Panel SDP.LP-2 -- NYY (4x120mm2) m' 70.00 540,000.00 37,800,000.00
- Kabel dari Panel SDP.LP-01 ke Panel LP-.10 -- NYY (4x6mm2) m' 5.00 85,000.00 425,000.00
- Kabel dari Panel SDP.LP-01 ke Panel LP-.11 -- NYY (4x6mm2) m' 15.00 85,000.00 1,275,000.00
- Kabel dari Panel SDP.LP-01 ke Panel LP-.12 -- NYY (4x6mm2) m' 20.00 85,000.00 1,700,000.00
- Kabel dari Panel SDP.LP-01 ke Panel LP-.13 -- NYY (4x6mm2) m' 25.00 85,000.00 2,125,000.00
- Kabel dari Panel SDP.LP-01 ke Panel LP-.14 -- NYY (4x6mm2) m' 30.00 85,000.00 2,550,000.00
- Kabel dari Panel SDP.LP-01 ke Panel LP-.15 -- NYY (4x6mm2) m' 35.00 85,000.00 2,975,000.00
- Kabel dari Panel SDP.LP-01 ke Panel LP-.16 -- NYY (4x6mm2) m' 40.00 85,000.00 3,400,000.00
- Kabel dari Panel SDP.LP-01 ke Panel LP-.17 -- NYY (4x6mm2) m' 45.00 85,000.00 3,825,000.00
- Kabel dari Panel SDP.LP-01 ke Panel LP-.18 -- NYY (4x6mm2) m' 50.00 85,000.00 4,250,000.00
- Kabel dari Panel SDP.LP-01 ke Panel LP-.19 -- NYY (4x6mm2) m' 55.00 85,000.00 4,675,000.00
11 Kabel dari LVMDP ke Panel P-LIFT -- NYY (4x95mm2) m' 130.00 360,000.00 46,800,000.00
- Kabel dari Panel P-LIFT ke Panel MCC-LIFT 1 -- NYY (4x10mm2) m' 10.00 120,000.00 1,200,000.00
- Kabel dari Panel P-LIFT ke Panel MCC-LIFT 2 -- NYY (4x10mm2) m' 10.00 120,000.00 1,200,000.00
- Kabel dari Panel P-LIFT ke Panel MCC-LIFT 3 -- NYY (4x10mm2) m' 10.00 120,000.00 1,200,000.00
- Kabel dari Panel P-LIFT ke Panel MCC-LIFT 4 -- NYY (4x10mm2) m' 10.00 120,000.00 1,200,000.00
- Kabel dari Panel P-LIFT ke Panel MCC-LIFT 5 -- NYY (4x10mm2) m' 10.00 120,000.00 1,200,000.00
- Kabel dari Panel P-LIFT ke Panel MCC-LIFT 6 -- NYY (4x10mm2) m' 10.00 120,000.00 1,200,000.00
12 Kabel dari LVMDP ke Panel P-LA -- NYY (4x16mm2) m' 130.00 160,000.00 20,800,000.00
- Kabel dari Panel P-LA ke Panel P-G -- NYY (4x10mm2) m' 10.00 120,000.00 1,200,000.00

Rincian RAB MEP (Penyediaan Jaringan dan Distribusi Listrik)


Universitas Muhammadiyah Tangerang
Page 44
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

- Kabel dari Panel P-LA ke Panel P-B -- NYY (4x10mm2) m' 10.00 120,000.00 1,200,000.00
13 Kabel dari LVMDP ke Panel P-Emergency -- NYY (4x25mm2) m' 130.00 210,000.00 27,300,000.00
- Kabel dari Panel P-Emergency ke Panel P-PF -- NYY (4x10mm2) m' 20.00 120,000.00 2,400,000.00
- Kabel dari Panel P-Emergency ke Panel P-LS -- NYY (4x10mm2) m' 10.00 120,000.00 1,200,000.00
Sub Total INSTALASI KABEL TOEVOER 609,835,000.00
Instalasi kabel di dalam atau dibawah plat dengan menggunakan high impact conduit
dengan diameter pipa menyesuaikan ukuran kabel toevoer
B.3 Kabel Toevoer Dari Panel ke Equipment
- Kabel dari Panel Lift Service ke unit Lift Service -- NYY (4x6mm2) m' 50.00 85,000.00 4,250,000.00
- Kabel dari Panel Lift Passanger ke unit Lift Passenger -- NYY (4x6mm2) m' 10.00 85,000.00 850,000.00
- Kabel dari Panel Gondola ke unit Gondola -- NYY (4x6mm2) m' 50.00 85,000.00 4,250,000.00
- Kabel dari Panel Pressurized Fan ke unit Pressurized Fan -- NYY (4x4mm2) m' 50.00 60,000.00 3,000,000.00
- Kabel dari Panel Pompa Booster ke unit Pompa Booster -- NYY 2(4x2,5mm2) m' 20.00 45,000.00 900,000.00
- Kabel dari Panel Water Pump ke unit Pompa Air -- NYY (4x2,5mm2) m' 20.00 45,000.00 900,000.00
- Kabel dari Panel Fuel Pump ke unit Pompa Fuel Pompa -- NYY (4x4mm2) m' 20.00 60,000.00 1,200,000.00
- Kabel dari Panel Jockey ke unit Jockey Pump -- NYY (4x2,5mm2) m' 20.00 45,000.00 900,000.00
- Kabel dari Panel Deepwell ke unit Deepwell -- NYY (4x4mm2) m' 30.00 60,000.00 1,800,000.00
Sub Total Kabel Toevoer Dari Panel ke Equipment 18,050,000.00

TOTAL PENYEDIAAN JARINGAN & DISTRIBUSI LISTRIK 7,548,635,000.00

Rincian RAB MEP (Penyediaan Jaringan dan Distribusi Listrik)


Universitas Muhammadiyah Tangerang
Page 45
HARGA JUMLAH TOTAL
SAT VOL SATUAN HARGA HARGA
NO. URAIAN PEKERJAAN
( Rp ) ( Rp ) ( Rp )

1 2 3 4 5 6 7

V INSTALASI GENSET & SISTEM PEMBUMIAN


A. PEKERJAAN GENSET
1 Diesel Generator Set
Type : Standby, 380/220V, 50 Hz, 1500 RPM
Kapasitas : 650 KVA 3 Phase lengkap dengan unit 1.00 1,350,000,000.00 1,350,000,000.00
- Spring Vibration Residential Silencer
- Radiator
- Accessories
2 Tanki bahan bakar mingguan, kapasitas : 1000 Liter unit 1.00 250,000,000.00 250,000,000.00
- Termasuk konstruksi penyangga
3 Pompa Solar Elektrik unit 1.00 35,000,000.00 35,000,000.00
4 Pompa Manual / Tangan unit 1.00 15,000,000.00 15,000,000.00
5 Pemipaan Bahan Bakar lengkap dengan Gate Valve lot 1.00 25,000,000.00 25,000,000.00
- Termasuk Fitting, Check Valve, Foot Valve dan accessories
6 Kabel Ladder 1000 x100 mm2 m 10.00 450,000.00 4,500,000.00
7 Straight Ladder
- 800 x 100mm2 m 20.00 450,000.00 9,000,000.00
8 Sistem Peredam Suara
- Residental Silencer/shuffer + Pemipaan set 2.00 20,000,000.00 40,000,000.00
- Intake Sound Attenuator set 2.00 35,000,000.00 70,000,000.00
- Discharge Sound Attenuator set 2.00 45,000,000.00 90,000,000.00
- Soundproof Rock Wool 5 cm + Wire Mesh + Glasscoe m2 370.00 280,000.00 103,600,000.00
9 Peralatan bantu Sound Profing dan Ventilasi di ruang genset
- Exhaust fan industrial type 2500 cfm + accessories unit 5.00 9,500,000.00 47,500,000.00
- Grill dan accessories lot 2.00 7,500,000.00 15,000,000.00
10 Instalasi Cerobong Asap dari Genset kearea luar /pembuangan dan Silincer lot 2.00 7,500,000.00 15,000,000.00
11 Pengadaan Solar 600 liter pada saat serah terima liter 500.00 11,500.00 5,750,000.00
12 Biaya Training Operator ls 2.00 1,000,000.00 2,000,000.00
13 Testing & Commisioning ls 2.00 15,000,000.00 30,000,000.00
14 Perijinan ls 1.00 25,000,000.00 masuk ijin-ijin
sub total 2,107,350,000.00
B PEKERJAAN PEMBUMIAN
Pengadaan, pemasangan dan pengujian seluruh pekerjaan instalasi pembumian
lengkap dengan bak control /eletroda dan accessories, sesuai gambar rencana
dan spesifikasi teknis.
1 Pembumian titik netral alternator lot 2.00 45,000,000.00 90,000,000.00
BC 70 mm2 + bak kontrol lengkap dengan elektroda-pembumian
2 Pembumian body Genset lot 2.00 45,000,000.00 90,000,000.00
BC 70 mm2 + bak kontrol lengkap dengan elektroda-pembumian
3 Grounding netral trafo 1 lot 1.00 20,000,000.00 20,000,000.00
4 Grounding body trafo lot 1.00 20,000,000.00 20,000,000.00
5 Grounding Panel TM 1 titik lot 1.00 20,000,000.00 20,000,000.00
6 Grounding Panel LVMDP lot 1.00 20,000,000.00 20,000,000.00
7 Grounding Elektronik lot 1.00 20,000,000.00 20,000,000.00
7 Grounding panel-panel sub distribusi lot 1.00 20,000,000.00 20,000,000.00
sub total 300,000,000.00

TOTAL INSTALASI GENSET & SISTEM PEMBUMIAN 2,407,350,000.00

Rincian RAB MEP (Instalasi Genset)


Universitas Muhammadiyah Tangerang
Page 46
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

VII INSTALASI PENERANGAN & KOTAK KONTAK


A Instalasi Penerangan Lantai Basement 1
1 Lampu TL Balk 2x36 Watt Outbouw bh 4.00 680,000.00 2,720,000.00
2 Lampu TL Balk 1x36 Watt Outbouw bh 32.00 550,000.00 17,600,000.00
3 Lampu TL Balk 2x18 Watt Outbouw bh 12.00 520,000.00 6,240,000.00
4 Lampu TL Balk 1x18 Watt Outbouw bh 6.00 460,000.00 2,760,000.00
5 Lampu Baret Square 22 Watt + Batteray bh 2.00 1,230,000.00 2,460,000.00
6 Lampu Downlight 1x18 Watt Inbouw bh 5.00 450,000.00 2,250,000.00
7 Lampu Downlight 1x13 Watt Inbouw bh 5.00 420,000.00 2,100,000.00
8 Saklar Tunggal bh 1.00 98,000.00 98,000.00
9 Saklar Ganda bh 10.00 120,000.00 1,200,000.00
10 Saklar Tukar bh 1.00 120,000.00 120,000.00
11 Instalasi penerangan ttk 66.00 450,000.00 29,700,000.00
12 Outlet stopkontak, tunggal, 1ph, 10A/250VA bh 7.00 80,000.00 560,000.00
13 Instalasi stopkontak ttk 7.00 450,000.00 3,150,000.00
Sub Total Instalasi Penerangan Lantai Basement 1 70,958,000.00
B Instalasi Penerangan Lantai Ground
1 Lampu TL Balk 2x18 Watt Outbouw bh 7.00 520,000.00 3,640,000.00
2 Lampu TL Balk 1x18 Watt Outbouw bh 4.00 460,000.00 1,840,000.00
3 Lampu Baret Square 22 Watt + Batteray bh 3.00 1,230,000.00 3,690,000.00
4 Lampu Baret SCB ACR 22 W bh 2.00 350,000.00 700,000.00
5 Lampu Downlight 1x18 Watt Inbouw bh 66.00 450,000.00 29,700,000.00
6 Lampu Downlight 1x13 Watt Inbouw bh 21.00 420,000.00 8,820,000.00
7 Saklar Tunggal bh 7.00 98,000.00 686,000.00
8 Saklar Ganda bh 9.00 120,000.00 1,080,000.00
9 Saklar Tukar bh 2.00 120,000.00 240,000.00
10 Instalasi penerangan ttk 103.00 450,000.00 46,350,000.00
11 Outlet stopkontak, tunggal, 1ph, 10A/250VA bh 14.00 80,000.00 1,120,000.00
12 Outlet stopkontak, ganda, 1ph, 16A/500VA bh 6.00 95,000.00 570,000.00
13 Instalasi stopkontak ttk 20.00 450,000.00 9,000,000.00
Sub Total Instalasi Penerangan Lantai Ground 107,436,000.00
C Instalasi Penerangan Lantai 1
1 Lampu TL Balk 1x36 Watt Outbouw bh 28.00 550,000.00 15,400,000.00
2 Lampu Baret Square 22 Watt + Batteray bh 3.00 1,230,000.00 3,690,000.00
3 Lampu Downlight 1x18 Watt Inbouw bh 3.00 450,000.00 1,350,000.00
4 Lampu Downlight 1x13 Watt Inbouw bh 12.00 420,000.00 5,040,000.00
5 Lampu Exit Slimline c/w Nicad Battery bh 2.00 1,600,000.00 3,200,000.00
6 Saklar Tunggal bh 4.00 98,000.00 392,000.00
7 Saklar Ganda bh 3.00 120,000.00 360,000.00
8 Saklar Tukar bh 2.00 120,000.00 240,000.00
9 Instalasi penerangan ttk 48.00 450,000.00 21,600,000.00
10 Outlet stopkontak, tunggal, 1ph, 10A/250VA bh 2.00 80,000.00 160,000.00
11 Instalasi stopkontak ttk 2.00 450,000.00 900,000.00
Sub Total Instalasi Penerangan Lantai 1 52,332,000.00
D Instalasi Penerangan Lantai 2
1 Lampu TL Balk 1x36 Watt Outbouw bh 42.00 550,000.00 23,100,000.00
2 Lampu TL Balk 1x18 Watt Outbouw bh 2.00 460,000.00 920,000.00
3 Lampu Baret Square 22 Watt + Batteray bh 3.00 1,230,000.00 3,690,000.00
4 Lampu Downlight 1x18 Watt Inbouw bh 1.00 450,000.00 450,000.00

Rincian RAB MEP (Instalasi Penerangan)


Universitas Muhammadiyah Tangerang
Page 47
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

5 Lampu Downlight 1x13 Watt Inbouw bh 14.00 420,000.00 5,880,000.00


6 Lampu Exit Slimline c/w Nicad Battery bh 2.00 1,600,000.00 3,200,000.00
7 Saklar Tunggal bh 4.00 98,000.00 392,000.00
8 Saklar Ganda bh 3.00 120,000.00 360,000.00
9 Saklar Tukar bh 2.00 120,000.00 240,000.00
10 Instalasi penerangan ttk 64.00 450,000.00 28,800,000.00
11 Outlet stopkontak, tunggal, 1ph, 10A/250VA bh 2.00 80,000.00 160,000.00
12 Instalasi stopkontak ttk 2.00 450,000.00 900,000.00
Sub Total Instalasi Penerangan Lantai 2 68,092,000.00
E Instalasi Penerangan Lantai 3
1 Lampu TL Balk 1x36 Watt Outbouw bh 42.00 550,000.00 23,100,000.00
2 Lampu TL Balk 1x18 Watt Outbouw bh 2.00 460,000.00 920,000.00
3 Lampu Baret Square 22 Watt + Batteray bh 3.00 1,230,000.00 3,690,000.00
4 Lampu Downlight 1x18 Watt Inbouw bh 1.00 450,000.00 450,000.00
5 Lampu Downlight 1x13 Watt Inbouw bh 14.00 420,000.00 5,880,000.00
6 Lampu Exit Slimline c/w Nicad Battery bh 2.00 1,600,000.00 3,200,000.00
7 Saklar Tunggal bh 4.00 98,000.00 392,000.00
8 Saklar Ganda bh 3.00 120,000.00 360,000.00
9 Saklar Tukar bh 2.00 120,000.00 240,000.00
10 Instalasi penerangan ttk 64.00 450,000.00 28,800,000.00
11 Outlet stopkontak, tunggal, 1ph, 10A/250VA bh 2.00 80,000.00 160,000.00
12 Instalasi stopkontak ttk 2.00 450,000.00 900,000.00
Sub Total Instalasi Penerangan Lantai 3 68,092,000.00
F Instalasi Penerangan Lantai 4
1 Lampu TL Balk 1x36 Watt Outbouw bh 42.00 550,000.00 23,100,000.00
2 Lampu TL Balk 1x18 Watt Outbouw bh 2.00 460,000.00 920,000.00
3 Lampu Baret Square 22 Watt + Batteray bh 3.00 1,230,000.00 3,690,000.00
4 Lampu Downlight 1x18 Watt Inbouw bh 1.00 450,000.00 450,000.00
5 Lampu Downlight 1x13 Watt Inbouw bh 14.00 420,000.00 5,880,000.00
6 Lampu Exit Slimline c/w Nicad Battery bh 2.00 1,600,000.00 3,200,000.00
7 Saklar Tunggal bh 4.00 98,000.00 392,000.00
8 Saklar Ganda bh 3.00 120,000.00 360,000.00
9 Saklar Tukar bh 2.00 120,000.00 240,000.00
10 Instalasi penerangan ttk 64.00 450,000.00 28,800,000.00
11 Outlet stopkontak, tunggal, 1ph, 10A/250VA bh 2.00 80,000.00 160,000.00
12 Instalasi stopkontak ttk 2.00 450,000.00 900,000.00
Sub Total Instalasi Penerangan Lantai 4 68,092,000.00
G Instalasi Penerangan Lantai 5
1 Lampu TL Balk 1x36 Watt Outbouw bh 42.00 550,000.00 23,100,000.00
2 Lampu TL Balk 1x18 Watt Outbouw bh 2.00 460,000.00 920,000.00
3 Lampu Baret Square 22 Watt + Batteray bh 3.00 1,230,000.00 3,690,000.00
4 Lampu Downlight 1x18 Watt Inbouw bh 1.00 450,000.00 450,000.00
5 Lampu Downlight 1x13 Watt Inbouw bh 14.00 420,000.00 5,880,000.00
6 Lampu Exit Slimline c/w Nicad Battery bh 2.00 1,600,000.00 3,200,000.00
7 Saklar Tunggal bh 4.00 98,000.00 392,000.00
8 Saklar Ganda bh 3.00 120,000.00 360,000.00
9 Saklar Tukar bh 2.00 120,000.00 240,000.00
10 Instalasi penerangan ttk 64.00 450,000.00 28,800,000.00
11 Outlet stopkontak, tunggal, 1ph, 10A/250VA bh 2.00 80,000.00 160,000.00

Rincian RAB MEP (Instalasi Penerangan)


Universitas Muhammadiyah Tangerang
Page 48
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

12 Instalasi stopkontak ttk 2.00 450,000.00 900,000.00


Sub Total Instalasi Penerangan Lantai 5 68,092,000.00
H Instalasi Penerangan Lantai 6
1 Lampu Hallogen 200 Watt bh 2.00 2,400,000.00 4,800,000.00
2 Lampu TL Balk 1x18 Watt Outbouw bh 4.00 460,000.00 1,840,000.00
3 Lampu Baret Square 22 Watt + Batteray bh 7.00 1,230,000.00 8,610,000.00
4 Lampu Downlight 1x18 Watt Inbouw bh 55.00 450,000.00 24,750,000.00
5 Lampu Downlight 1x13 Watt Inbouw bh 24.00 420,000.00 10,080,000.00
6 Lampu Exit Slimline c/w Nicad Battery bh 1.00 1,600,000.00 1,600,000.00
7 Saklar Tunggal bh 1.00 98,000.00 98,000.00
8 Saklar Ganda bh 8.00 120,000.00 960,000.00
9 Saklar Tukar bh 4.00 120,000.00 480,000.00
10 Instalasi penerangan ttk 93.00 450,000.00 41,850,000.00
11 Outlet stopkontak, tunggal, 1ph, 10A/250VA bh 12.00 80,000.00 960,000.00
12 Outlet stopkontak, ganda, 1ph, 16A/500VA bh 3.00 95,000.00 285,000.00
13 Instalasi stopkontak ttk 15.00 450,000.00 6,750,000.00
Sub Total Instalasi Penerangan Lantai 6 103,063,000.00
I Instalasi Penerangan Lantai 7
1 Lampu TL Balk 1x18 Watt Outbouw bh 3.00 460,000.00 1,380,000.00
2 Lampu Baret Square 22 Watt + Batteray bh 5.00 1,230,000.00 6,150,000.00
3 Lampu Downlight 1x23 Watt Inbouw bh 15.00 520,000.00 7,800,000.00
4 Lampu Downlight 1x18 Watt Inbouw bh 69.00 450,000.00 31,050,000.00
5 Lampu Exit Slimline c/w Nicad Battery bh 3.00 1,600,000.00 4,800,000.00
6 Saklar Tunggal bh 1.00 98,000.00 98,000.00
7 Saklar Ganda bh 7.00 120,000.00 840,000.00
8 Saklar Tukar bh 4.00 120,000.00 480,000.00
9 Instalasi penerangan ttk 95.00 450,000.00 42,750,000.00
10 Outlet stopkontak, tunggal, 1ph, 10A/250VA bh 13.00 80,000.00 1,040,000.00
11 Outlet stopkontak, ganda, 1ph, 16A/500VA bh 2.00 95,000.00 190,000.00
12 Instalasi stopkontak ttk 15.00 450,000.00 6,750,000.00
Sub Total Instalasi Penerangan Lantai 7 103,328,000.00
J Instalasi Penerangan Lantai 8
1 Lampu TL 2x36 Watt Inbouw Louvre bh 44.00 680,000.00 29,920,000.00
2 Lampu TL Balk 1x18 Watt Outbouw bh 1.00 460,000.00 460,000.00
3 Lampu Baret Square 22 Watt + Batteray bh 3.00 1,230,000.00 3,690,000.00
4 Lampu Downlight 1x18 Watt Inbouw bh 1.00 450,000.00 450,000.00
5 Lampu Downlight 1x13 Watt Inbouw bh 39.00 420,000.00 16,380,000.00
6 Lampu Exit Slimline c/w Nicad Battery bh 1.00 1,600,000.00 1,600,000.00
7 Saklar Tunggal bh 12.00 98,000.00 1,176,000.00
8 Saklar Ganda bh 14.00 120,000.00 1,680,000.00
9 Saklar Tukar bh 2.00 120,000.00 240,000.00
10 Instalasi penerangan ttk 89.00 450,000.00 40,050,000.00
11 Outlet stopkontak, tunggal, 1ph, 10A/250VA bh 13.00 80,000.00 1,040,000.00
12 Outlet stopkontak, ganda, 1ph, 16A/500VA bh 11.00 95,000.00 1,045,000.00
13 Instalasi stopkontak ttk 24.00 450,000.00 10,800,000.00
Sub Total Instalasi Penerangan Lantai 8 108,531,000.00
K Instalasi Penerangan Lantai 9
1 Lampu TL 2x36 Watt Inbouw Louvre bh 44.00 680,000.00 29,920,000.00
2 Lampu TL Balk 1x18 Watt Outbouw bh 1.00 460,000.00 460,000.00

Rincian RAB MEP (Instalasi Penerangan)


Universitas Muhammadiyah Tangerang
Page 49
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

3 Lampu Baret Square 22 Watt + Batteray bh 3.00 1,230,000.00 3,690,000.00


4 Lampu Downlight 1x18 Watt Inbouw bh 1.00 450,000.00 450,000.00
5 Lampu Downlight 1x13 Watt Inbouw bh 39.00 420,000.00 16,380,000.00
6 Lampu Exit Slimline c/w Nicad Battery bh 1.00 1,600,000.00 1,600,000.00
7 Saklar Tunggal bh 12.00 98,000.00 1,176,000.00
8 Saklar Ganda bh 14.00 120,000.00 1,680,000.00
9 Saklar Tukar bh 2.00 120,000.00 240,000.00
10 Instalasi penerangan ttk 89.00 450,000.00 40,050,000.00
11 Outlet stopkontak, tunggal, 1ph, 10A/250VA bh 13.00 80,000.00 1,040,000.00
12 Outlet stopkontak, ganda, 1ph, 16A/500VA bh 11.00 95,000.00 1,045,000.00
13 Instalasi stopkontak ttk 24.00 450,000.00 10,800,000.00
Sub Total Instalasi Penerangan Lantai 9 108,531,000.00
L Instalasi Penerangan Lantai 10
1 Lampu TL 2x36 Watt Inbouw Louvre bh 44.00 680,000.00 29,920,000.00
2 Lampu TL Balk 1x18 Watt Outbouw bh 1.00 460,000.00 460,000.00
3 Lampu Baret Square 22 Watt + Batteray bh 3.00 1,230,000.00 3,690,000.00
4 Lampu Downlight 1x18 Watt Inbouw bh 1.00 450,000.00 450,000.00
5 Lampu Downlight 1x13 Watt Inbouw bh 39.00 420,000.00 16,380,000.00
6 Lampu Exit Slimline c/w Nicad Battery bh 1.00 1,600,000.00 1,600,000.00
7 Saklar Tunggal bh 12.00 98,000.00 1,176,000.00
8 Saklar Ganda bh 14.00 120,000.00 1,680,000.00
9 Saklar Tukar bh 2.00 120,000.00 240,000.00
10 Instalasi penerangan ttk 89.00 450,000.00 40,050,000.00
11 Outlet stopkontak, tunggal, 1ph, 10A/250VA bh 13.00 80,000.00 1,040,000.00
12 Outlet stopkontak, ganda, 1ph, 16A/500VA bh 11.00 95,000.00 1,045,000.00
13 Instalasi stopkontak ttk 24.00 450,000.00 10,800,000.00
Sub Total Instalasi Penerangan Lantai 10 108,531,000.00
M Instalasi Penerangan Lantai 11
1 Lampu TL 2x36 Watt Inbouw Louvre bh 44.00 680,000.00 29,920,000.00
2 Lampu TL Balk 1x18 Watt Outbouw bh 1.00 460,000.00 460,000.00
3 Lampu Baret Square 22 Watt + Batteray bh 3.00 1,230,000.00 3,690,000.00
4 Lampu Downlight 1x18 Watt Inbouw bh 1.00 450,000.00 450,000.00
5 Lampu Downlight 1x13 Watt Inbouw bh 39.00 420,000.00 16,380,000.00
6 Lampu Exit Slimline c/w Nicad Battery bh 1.00 1,600,000.00 1,600,000.00
7 Saklar Tunggal bh 12.00 98,000.00 1,176,000.00
8 Saklar Ganda bh 14.00 120,000.00 1,680,000.00
9 Saklar Tukar bh 2.00 120,000.00 240,000.00
10 Instalasi penerangan ttk 89.00 450,000.00 40,050,000.00
11 Outlet stopkontak, tunggal, 1ph, 10A/250VA bh 13.00 80,000.00 1,040,000.00
12 Outlet stopkontak, ganda, 1ph, 16A/500VA bh 11.00 95,000.00 1,045,000.00
13 Instalasi stopkontak ttk 24.00 450,000.00 10,800,000.00
Sub Total Instalasi Penerangan Lantai 11 108,531,000.00
N Instalasi Penerangan Lantai 12
1 Lampu TL 2x36 Watt Inbouw Louvre bh 44.00 680,000.00 29,920,000.00
2 Lampu TL Balk 1x18 Watt Outbouw bh 1.00 460,000.00 460,000.00
3 Lampu Baret Square 22 Watt + Batteray bh 3.00 1,230,000.00 3,690,000.00
4 Lampu Downlight 1x18 Watt Inbouw bh 1.00 450,000.00 450,000.00
5 Lampu Downlight 1x13 Watt Inbouw bh 39.00 420,000.00 16,380,000.00
6 Lampu Exit Slimline c/w Nicad Battery bh 1.00 1,600,000.00 1,600,000.00

Rincian RAB MEP (Instalasi Penerangan)


Universitas Muhammadiyah Tangerang
Page 50
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

7 Saklar Tunggal bh 12.00 98,000.00 1,176,000.00


8 Saklar Ganda bh 14.00 120,000.00 1,680,000.00
9 Saklar Tukar bh 2.00 120,000.00 240,000.00
10 Instalasi penerangan ttk 89.00 450,000.00 40,050,000.00
11 Outlet stopkontak, tunggal, 1ph, 10A/250VA bh 13.00 80,000.00 1,040,000.00
12 Outlet stopkontak, ganda, 1ph, 16A/500VA bh 11.00 95,000.00 1,045,000.00
13 Instalasi stopkontak ttk 24.00 450,000.00 10,800,000.00
Sub Total Instalasi Penerangan Lantai 12 108,531,000.00
O Instalasi Penerangan Lantai 13
1 Lampu TL 2x36 Watt Inbouw Louvre bh 44.00 680,000.00 29,920,000.00
2 Lampu TL Balk 1x18 Watt Outbouw bh 1.00 460,000.00 460,000.00
3 Lampu Baret Square 22 Watt + Batteray bh 3.00 1,230,000.00 3,690,000.00
4 Lampu Downlight 1x18 Watt Inbouw bh 1.00 450,000.00 450,000.00
5 Lampu Downlight 1x13 Watt Inbouw bh 39.00 420,000.00 16,380,000.00
6 Lampu Exit Slimline c/w Nicad Battery bh 1.00 1,600,000.00 1,600,000.00
7 Saklar Tunggal bh 12.00 98,000.00 1,176,000.00
8 Saklar Ganda bh 14.00 120,000.00 1,680,000.00
9 Saklar Tukar bh 2.00 120,000.00 240,000.00
10 Instalasi penerangan ttk 89.00 450,000.00 40,050,000.00
11 Outlet stopkontak, tunggal, 1ph, 10A/250VA bh 13.00 80,000.00 1,040,000.00
12 Outlet stopkontak, ganda, 1ph, 16A/500VA bh 11.00 95,000.00 1,045,000.00
13 Instalasi stopkontak ttk 24.00 450,000.00 10,800,000.00
Sub Total Instalasi Penerangan Lantai 13 108,531,000.00
P Instalasi Penerangan Lantai 14
1 Lampu TL 2x36 Watt Inbouw Louvre bh 44.00 680,000.00 29,920,000.00
2 Lampu TL Balk 1x18 Watt Outbouw bh 1.00 460,000.00 460,000.00
3 Lampu Baret Square 22 Watt + Batteray bh 3.00 1,230,000.00 3,690,000.00
4 Lampu Downlight 1x18 Watt Inbouw bh 1.00 450,000.00 450,000.00
5 Lampu Downlight 1x13 Watt Inbouw bh 39.00 420,000.00 16,380,000.00
6 Lampu Exit Slimline c/w Nicad Battery bh 1.00 1,600,000.00 1,600,000.00
7 Saklar Tunggal bh 12.00 98,000.00 1,176,000.00
8 Saklar Ganda bh 14.00 120,000.00 1,680,000.00
9 Saklar Tukar bh 2.00 120,000.00 240,000.00
10 Instalasi penerangan ttk 89.00 450,000.00 40,050,000.00
11 Outlet stopkontak, tunggal, 1ph, 10A/250VA bh 13.00 80,000.00 1,040,000.00
12 Outlet stopkontak, ganda, 1ph, 16A/500VA bh 11.00 95,000.00 1,045,000.00
13 Instalasi stopkontak ttk 24.00 450,000.00 10,800,000.00
Sub Total Instalasi Penerangan Lantai 14 108,531,000.00
Q Instalasi Penerangan Lantai 15
1 Lampu TL 2x36 Watt Inbouw Louvre bh 44.00 680,000.00 29,920,000.00
2 Lampu TL Balk 1x18 Watt Outbouw bh 1.00 460,000.00 460,000.00
3 Lampu Baret Square 22 Watt + Batteray bh 3.00 1,230,000.00 3,690,000.00
4 Lampu Downlight 1x18 Watt Inbouw bh 1.00 450,000.00 450,000.00
5 Lampu Downlight 1x13 Watt Inbouw bh 39.00 420,000.00 16,380,000.00
6 Lampu Exit Slimline c/w Nicad Battery bh 1.00 1,600,000.00 1,600,000.00
7 Saklar Tunggal bh 12.00 98,000.00 1,176,000.00
8 Saklar Ganda bh 14.00 120,000.00 1,680,000.00
9 Saklar Tukar bh 2.00 120,000.00 240,000.00
10 Instalasi penerangan ttk 89.00 450,000.00 40,050,000.00

Rincian RAB MEP (Instalasi Penerangan)


Universitas Muhammadiyah Tangerang
Page 51
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

11 Outlet stopkontak, tunggal, 1ph, 10A/250VA bh 13.00 80,000.00 1,040,000.00


12 Outlet stopkontak, ganda, 1ph, 16A/500VA bh 11.00 95,000.00 1,045,000.00
13 Instalasi stopkontak ttk 24.00 450,000.00 10,800,000.00
Sub Total Instalasi Penerangan Lantai 15 108,531,000.00
R Instalasi Penerangan Lantai 16
1 Lampu TL 2x36 Watt Inbouw Louvre bh 44.00 680,000.00 29,920,000.00
2 Lampu TL Balk 1x18 Watt Outbouw bh 1.00 460,000.00 460,000.00
3 Lampu Baret Square 22 Watt + Batteray bh 3.00 1,230,000.00 3,690,000.00
4 Lampu Downlight 1x18 Watt Inbouw bh 1.00 450,000.00 450,000.00
5 Lampu Downlight 1x13 Watt Inbouw bh 39.00 420,000.00 16,380,000.00
6 Lampu Exit Slimline c/w Nicad Battery bh 1.00 1,600,000.00 1,600,000.00
7 Saklar Tunggal bh 12.00 98,000.00 1,176,000.00
8 Saklar Ganda bh 14.00 120,000.00 1,680,000.00
9 Saklar Tukar bh 2.00 120,000.00 240,000.00
10 Instalasi penerangan ttk 89.00 450,000.00 40,050,000.00
11 Outlet stopkontak, tunggal, 1ph, 10A/250VA bh 13.00 80,000.00 1,040,000.00
12 Outlet stopkontak, ganda, 1ph, 16A/500VA bh 11.00 95,000.00 1,045,000.00
13 Instalasi stopkontak ttk 24.00 450,000.00 10,800,000.00
Sub Total Instalasi Penerangan Lantai 16 108,531,000.00
S Instalasi Penerangan Lantai 17
1 Lampu TL 2x36 Watt Inbouw Louvre bh 44.00 680,000.00 29,920,000.00
2 Lampu TL Balk 1x18 Watt Outbouw bh 1.00 460,000.00 460,000.00
3 Lampu Baret Square 22 Watt + Batteray bh 3.00 1,230,000.00 3,690,000.00
4 Lampu Downlight 1x18 Watt Inbouw bh 1.00 450,000.00 450,000.00
5 Lampu Downlight 1x13 Watt Inbouw bh 39.00 420,000.00 16,380,000.00
6 Lampu Exit Slimline c/w Nicad Battery bh 1.00 1,600,000.00 1,600,000.00
7 Saklar Tunggal bh 12.00 98,000.00 1,176,000.00
8 Saklar Ganda bh 14.00 120,000.00 1,680,000.00
9 Saklar Tukar bh 2.00 120,000.00 240,000.00
10 Instalasi penerangan ttk 89.00 450,000.00 40,050,000.00
11 Outlet stopkontak, tunggal, 1ph, 10A/250VA bh 13.00 80,000.00 1,040,000.00
12 Outlet stopkontak, ganda, 1ph, 16A/500VA bh 11.00 95,000.00 1,045,000.00
13 Instalasi stopkontak ttk 24.00 450,000.00 10,800,000.00
Sub Total Instalasi Penerangan Lantai 17 108,531,000.00
T Instalasi Penerangan Lantai 18
1 Lampu TL 2x36 Watt Inbouw Louvre bh 44.00 680,000.00 29,920,000.00
2 Lampu TL Balk 1x18 Watt Outbouw bh 1.00 460,000.00 460,000.00
3 Lampu Baret Square 22 Watt + Batteray bh 3.00 1,230,000.00 3,690,000.00
4 Lampu Downlight 1x18 Watt Inbouw bh 1.00 450,000.00 450,000.00
5 Lampu Downlight 1x13 Watt Inbouw bh 39.00 420,000.00 16,380,000.00
6 Lampu Exit Slimline c/w Nicad Battery bh 1.00 1,600,000.00 1,600,000.00
7 Saklar Tunggal bh 12.00 98,000.00 1,176,000.00
8 Saklar Ganda bh 14.00 120,000.00 1,680,000.00
9 Saklar Tukar bh 2.00 120,000.00 240,000.00
10 Instalasi penerangan ttk 89.00 450,000.00 40,050,000.00
11 Outlet stopkontak, tunggal, 1ph, 10A/250VA bh 13.00 80,000.00 1,040,000.00
12 Outlet stopkontak, ganda, 1ph, 16A/500VA bh 11.00 95,000.00 1,045,000.00
13 Instalasi stopkontak ttk 24.00 450,000.00 10,800,000.00
Sub Total Instalasi Penerangan Lantai 18 108,531,000.00

Rincian RAB MEP (Instalasi Penerangan)


Universitas Muhammadiyah Tangerang
Page 52
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

U Instalasi Penerangan Lantai 19


1 Lampu TL Balk 2x18 Watt Outbouw bh 11.00 520,000.00 5,720,000.00
2 Lampu TL Balk 1x18 Watt Outbouw bh 3.00 460,000.00 1,380,000.00
3 Lampu Baret Square 22 Watt + Batteray bh 5.00 1,230,000.00 6,150,000.00
4 Lampu Downlight 1x18 Watt Inbouw bh 14.00 450,000.00 6,300,000.00
5 Lampu Downlight 1x13 Watt Inbouw bh 88.00 420,000.00 36,960,000.00
6 Lampu Dinding 1x18 Watt bh 4.00 650,000.00 2,600,000.00
7 Lampu Exit Slimline c/w Nicad Battery bh 1.00 1,600,000.00 1,600,000.00
8 Saklar Tunggal bh 23.00 98,000.00 2,254,000.00
9 Saklar Ganda bh 16.00 120,000.00 1,920,000.00
10 Saklar Tukar bh 3.00 120,000.00 360,000.00
11 Instalasi penerangan ttk 126.00 450,000.00 56,700,000.00
12 Outlet stopkontak, tunggal, 1ph, 10A/250VA bh 29.00 80,000.00 2,320,000.00
13 Outlet stopkontak, ganda, 1ph, 16A/500VA bh 7.00 95,000.00 665,000.00
14 Instalasi stopkontak ttk 36.00 450,000.00 16,200,000.00
Sub Total Instalasi Penerangan Lantai 19 141,129,000.00
V Instalasi Penerangan Lantai 20
1 Lampu TL Balk 2x18 Watt Outbouw bh 12.00 520,000.00 6,240,000.00
1 Lampu TL Balk 2x18 Watt Outbouw (rooftank) bh 8.00 460,000.00 3,680,000.00
2 Lampu Baret Square 22 Watt + Batteray bh 2.00 1,230,000.00 2,460,000.00
3 Saklar Tunggal bh 1.00 98,000.00 98,000.00
4 Saklar Ganda bh 1.00 120,000.00 120,000.00
5 Saklar Tukar bh 3.00 120,000.00 360,000.00
6 Instalasi penerangan ttk 22.00 450,000.00 9,900,000.00
7 Outlet stopkontak, tunggal, 1ph, 10A/250VA bh 4.00 80,000.00 320,000.00
8 Instalasi stopkontak ttk 4.00 95,000.00 380,000.00
Sub Total Instalasi Penerangan Lantai 20 23,558,000.00
U Instalasi Lampu Ruang Genset
1 Lampu TL Balk 1x36 Watt Outbouw bh 6.00 550,000.00 3,300,000.00
2 Saklar Tunggal bh 1.00 98,000.00 98,000.00
3 Saklar Ganda bh 3.00 120,000.00 360,000.00
4 Instalasi penerangan ttk 14.00 450,000.00 6,300,000.00
5 Outlet stopkontak, tunggal, 1ph, 10A/250VA bh 2.00 80,000.00 160,000.00
6 Instalasi stopkontak ttk 4.00 95,000.00 380,000.00
Sub Total Instalasi Lampu Ruang Genset 10,598,000.00
V Instalasi Lampu Site
1 Lampu Jalan Tiang Tunggal SON 1x250 Watt bh 5.00 14,500,000.00 72,500,000.00
2 Lampu Spot Light MHN-TD 150 Watt bh 2.00 3,000,000.00 6,000,000.00
3 Lampu Pagar CFL 18Watt E-27 bh 33.00 3,500,000.00 115,500,000.00
4 Instalasi lampu jalan ttk 9.00 750,000.00 6,750,000.00
5 Instalasi lampu taman ttk 35.00 550,000.00 19,250,000.00
6 Kontrol Lampu photocell relay unit 5.00 1,500,000.00 7,500,000.00
Sub Total Instalasi Lampu Site 227,500,000.00

TOTAL INSTALASI PENERANGAN & KOTAK KONTAK 2,306,111,000.00

Rincian RAB MEP (Instalasi Penerangan)


Universitas Muhammadiyah Tangerang
Page 53
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

IX SISTEM TELEPON / VOICE COMMUNICATION


A Main Equipment
1 PBX 12 CO/PTT 200 Extension (KX-TD Series): unit 1.00 198,000,000.00 198,000,000.00
Central Unit terdiri dari komponen sbb:
- Main unit 10slot + 1 Optional slot    
- Expansion Card
- DHLC Card
- LCOT 8 Port Card (4 Unit)
- ECLC 16 Port Card (8 Unit)
- L-Type Power Supply
- Standard Key Telephone
- DSS Control
2 MDF 200 Line bh 1.00 45,000,000.00 45,000,000.00
3 Battery Backup 2 hour c/w Box & Accesories bh 1.00 75,000,000.00 75,000,000.00
Sub Total Main Equipment 318,000,000.00
B Instalasi Kabel Feeder
- Kabel Feeder dari MDF ke TBT Groundfloor m 24.00 33,500.00 804,000.00
- Kabel Feeder dari MDF ke TBT Lantai 01 m 30.00 33,500.00 1,005,000.00
- Kabel Feeder dari MDF ke TBT Lantai 03 m 36.00 33,500.00 1,206,000.00
- Kabel Feeder dari MDF ke TBT Lantai 04 m 42.00 33,500.00 1,407,000.00
- Kabel Feeder dari MDF ke TBT Lantai 05 m 48.00 33,500.00 1,608,000.00
- Kabel Feeder dari MDF ke TBT Lantai 06 m 54.00 33,500.00 1,809,000.00
- Kabel Feeder dari MDF ke TBT Lantai 07 m 60.00 33,500.00 2,010,000.00
- Kabel Feeder dari MDF ke TBT Lantai 08 m 66.00 33,500.00 2,211,000.00
- Kabel Feeder dari MDF ke TBT Lantai 09 m 72.00 33,500.00 2,412,000.00
- Kabel Feeder dari MDF ke TBT Lantai 10 m 78.00 33,500.00 2,613,000.00
- Kabel Feeder dari MDF ke TBT Lantai 11 m 84.00 33,500.00 2,814,000.00
- Kabel Feeder dari MDF ke TBT Lantai 12 m 90.00 33,500.00 3,015,000.00
- Kabel Feeder dari MDF ke TBT Lantai 13 m 96.00 33,500.00 3,216,000.00
- Kabel Feeder dari MDF ke TBT Lantai 14 m 102.00 33,500.00 3,417,000.00
- Kabel Feeder dari MDF ke TBT Lantai 15 m 108.00 33,500.00 3,618,000.00
- Kabel Feeder dari MDF ke TBT Lantai 16 m 114.00 33,500.00 3,819,000.00
- Kabel Feeder dari MDF ke TBT Lantai 17 m 120.00 33,500.00 4,020,000.00
- Kabel Feeder dari MDF ke TBT Lantai 18 m 126.00 33,500.00 4,221,000.00
- Kabel Feeder dari MDF ke TBT Lantai 19 m 132.00 33,500.00 4,422,000.00
Sub Total Instalasi Kabel Feeder 49,647,000.00
C Instalasi Telepon Lantai Ground
Instalasi Kabel ITC 2x0.6mm dalam High Impact conduit dia. 20mm
1 Outlet single line telephone bh 4.00 650,000.00 2,600,000.00
2 Baseline Standard unit 4.00 550,000.00 2,200,000.00
3 Instalasi pengkabelan ekstensi telephone ttk 4.00 600,000.00 2,400,000.00
4 Terminal Box Telepon (TBT) kap. 20 pair bh 1.00 4,500,000.00 4,500,000.00
Sub Total Instalasi Telepon Lantai Ground 11,700,000.00
D Instalasi Telepon Lantai 6-7
Instalasi Kabel ITC 2x0.6mm dalam High Impact conduit dia. 20mm

Rincian RAB MEP (Sistem Telepon)


Universitas Muhammadiyah Tangerang
Page 54
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

1 Outlet single line telephone bh 4.00 650,000.00 2,600,000.00


2 Baseline Standard unit 4.00 550,000.00 2,200,000.00
3 Instalasi pengkabelan ekstensi telephone ttk 4.00 600,000.00 2,400,000.00
4 Terminal Box Telepon (TBT) kap. 20 pair bh 1.00 4,500,000.00 4,500,000.00
Sub Total Instalasi Telepon Lantai 6-7 11,700,000.00
E Instalasi Telepon Lantai 8
Instalasi Kabel ITC 2x0.6mm dalam High Impact conduit dia. 20mm
1 Outlet single line telephone bh 10.00 650,000.00 6,500,000.00
2 Baseline Standard unit 10.00 550,000.00 5,500,000.00
3 Instalasi pengkabelan ekstensi telephone ttk 10.00 600,000.00 6,000,000.00
4 Terminal Box Telepon (TBT) kap. 20 pair bh 1.00 4,500,000.00 4,500,000.00
Sub Total Instalasi Telepon Lantai 8 22,500,000.00
F Instalasi Telepon Lantai 9
Instalasi Kabel ITC 2x0.6mm dalam High Impact conduit dia. 20mm
1 Outlet single line telephone bh 10.00 650,000.00 6,500,000.00
2 Baseline Standard unit 10.00 550,000.00 5,500,000.00
3 Instalasi pengkabelan ekstensi telephone ttk 10.00 600,000.00 6,000,000.00
4 Terminal Box Telepon (TBT) kap. 20 pair bh 1.00 4,500,000.00 4,500,000.00
Sub Total Instalasi Telepon Lantai 9 22,500,000.00
G Instalasi Telepon Lantai 10
Instalasi Kabel ITC 2x0.6mm dalam High Impact conduit dia. 20mm
1 Outlet single line telephone bh 10.00 650,000.00 6,500,000.00
2 Baseline Standard unit 10.00 550,000.00 5,500,000.00
3 Instalasi pengkabelan ekstensi telephone ttk 10.00 600,000.00 6,000,000.00
4 Terminal Box Telepon (TBT) kap. 20 pair bh 1.00 4,500,000.00 4,500,000.00
Sub Total Instalasi Telepon Lantai 10 22,500,000.00
H Instalasi Telepon Lantai 11
Instalasi Kabel ITC 2x0.6mm dalam High Impact conduit dia. 20mm
1 Outlet single line telephone bh 10.00 650,000.00 6,500,000.00
2 Baseline Standard unit 10.00 550,000.00 5,500,000.00
3 Instalasi pengkabelan ekstensi telephone ttk 10.00 600,000.00 6,000,000.00
4 Terminal Box Telepon (TBT) kap. 20 pair bh 1.00 4,500,000.00 4,500,000.00
Sub Total Instalasi Telepon Lantai 11 22,500,000.00
I Instalasi Telepon Lantai 12
Instalasi Kabel ITC 2x0.6mm dalam High Impact conduit dia. 20mm
1 Outlet single line telephone bh 10.00 650,000.00 6,500,000.00
2 Baseline Standard unit 10.00 550,000.00 5,500,000.00
3 Instalasi pengkabelan ekstensi telephone ttk 10.00 600,000.00 6,000,000.00
4 Terminal Box Telepon (TBT) kap. 20 pair bh 1.00 4,500,000.00 4,500,000.00
Sub Total Instalasi Telepon Lantai 12 22,500,000.00
J Instalasi Telepon Lantai 13
Instalasi Kabel ITC 2x0.6mm dalam High Impact conduit dia. 20mm
1 Outlet single line telephone bh 10.00 650,000.00 6,500,000.00
2 Baseline Standard unit 10.00 550,000.00 5,500,000.00
3 Instalasi pengkabelan ekstensi telephone ttk 10.00 600,000.00 6,000,000.00
4 Terminal Box Telepon (TBT) kap. 20 pair bh 1.00 4,500,000.00 4,500,000.00

Rincian RAB MEP (Sistem Telepon)


Universitas Muhammadiyah Tangerang
Page 55
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

Sub Total Instalasi Telepon Lantai 13 22,500,000.00


K Instalasi Telepon Lantai 14
Instalasi Kabel ITC 2x0.6mm dalam High Impact conduit dia. 20mm
1 Outlet single line telephone bh 10.00 650,000.00 6,500,000.00
2 Baseline Standard unit 10.00 550,000.00 5,500,000.00
3 Instalasi pengkabelan ekstensi telephone ttk 10.00 600,000.00 6,000,000.00
4 Terminal Box Telepon (TBT) kap. 20 pair bh 1.00 4,500,000.00 4,500,000.00
Sub Total Instalasi Telepon Lantai 14 22,500,000.00
L Instalasi Telepon Lantai 15
Instalasi Kabel ITC 2x0.6mm dalam High Impact conduit dia. 20mm
1 Outlet single line telephone bh 10.00 650,000.00 6,500,000.00
2 Baseline Standard unit 10.00 550,000.00 5,500,000.00
3 Instalasi pengkabelan ekstensi telephone ttk 10.00 600,000.00 6,000,000.00
4 Terminal Box Telepon (TBT) kap. 20 pair bh 1.00 4,500,000.00 4,500,000.00
Sub Total Instalasi Telepon Lantai 15 22,500,000.00
M Instalasi Telepon Lantai 16
Instalasi Kabel ITC 2x0.6mm dalam High Impact conduit dia. 20mm
1 Outlet single line telephone bh 10.00 650,000.00 6,500,000.00
2 Baseline Standard unit 10.00 550,000.00 5,500,000.00
3 Instalasi pengkabelan ekstensi telephone ttk 10.00 600,000.00 6,000,000.00
4 Terminal Box Telepon (TBT) kap. 20 pair bh 1.00 4,500,000.00 4,500,000.00
Sub Total Instalasi Telepon Lantai 16 22,500,000.00
N Instalasi Telepon Lantai 17
Instalasi Kabel ITC 2x0.6mm dalam High Impact conduit dia. 20mm
1 Outlet single line telephone bh 10.00 650,000.00 6,500,000.00
2 Baseline Standard unit 10.00 550,000.00 5,500,000.00
3 Instalasi pengkabelan ekstensi telephone ttk 10.00 600,000.00 6,000,000.00
4 Terminal Box Telepon (TBT) kap. 20 pair bh 1.00 4,500,000.00 4,500,000.00
Sub Total Instalasi Telepon Lantai 17 22,500,000.00
O Instalasi Telepon Lantai 18
Instalasi Kabel ITC 2x0.6mm dalam High Impact conduit dia. 20mm
1 Outlet single line telephone bh 10.00 650,000.00 6,500,000.00
2 Baseline Standard unit 10.00 550,000.00 5,500,000.00
3 Instalasi pengkabelan ekstensi telephone ttk 10.00 600,000.00 6,000,000.00
4 Terminal Box Telepon (TBT) kap. 20 pair bh 1.00 4,500,000.00 4,500,000.00
Sub Total Instalasi Telepon Lantai 18 22,500,000.00
P Instalasi Telepon Lantai 19
Instalasi Kabel ITC 2x0.6mm dalam High Impact conduit dia. 20mm
1 Outlet single line telephone bh 9.00 650,000.00 5,850,000.00
2 Baseline Standard unit 9.00 550,000.00 4,950,000.00
3 Instalasi pengkabelan ekstensi telephone ttk 9.00 600,000.00 5,400,000.00
4 Terminal Box Telepon (TBT) kap. 20 pair bh 1.00 4,500,000.00 4,500,000.00
Sub Total Instalasi Telepon Lantai 19 20,700,000.00

TOTAL SISTEM TELEPON / VOICE COMMUNICATION 659,247,000.00

Rincian RAB MEP (Sistem Telepon)


Universitas Muhammadiyah Tangerang
Page 56
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

XIII SISTEM DETEKSI KEBAKARAN (FIRE ALARM)


A Main Equipment Fire Alarm
1 Master control fire alarm (MCFA), unit 1.00 180,000,000.00 180,000,000.00
- Fire alarm Semi Adressable system, 4 Loop
- c/w LCD Display back up battery & charger
- Control relay module for Pressuration Fan, Lift & Fire pump, Automatic Dial
2 Control relay module for Lift / Elevator, Fire Pump & Electrical Switch Board
3 Announciator Panel unit 1.00 34,000,000.00 34,000,000.00
4 Surge Arrester unit 1.00 7,500,000.00 7,500,000.00
5 MTB unit 1.00 9,000,000.00 9,000,000.00
6 Rackmount UPS 2000VA unit 1.00 17,500,000.00 17,500,000.00
7 Testing & Comissioning ls 1.00 15,000,000.00 15,000,000.00
Sub Total Main Equipment Fire Alarm 263,000,000.00
B Instalasi Kabel Feeder dari MTB ke TBFA
1 Instalasi interkoneksi dari MCPFA ke Panel PABX FRC 3x1,5 mm ls 1.00 18,000,000.00 18,000,000.00
2 Instalasi interkoneksi dari MCPFA ke Panel Sound FRC 3x1,5 mm ls 1.00 18,000,000.00 18,000,000.00
3 Instalasi interkoneksi dari MCPFA ke Panel Lift FRC 3x1,5 mm ls 1.00 18,000,000.00 18,000,000.00
4 Instalasi interkoneksi dari MCPFA ke Panel Lift Service FRC 3x1,5 mm ls 1.00 18,000,000.00 18,000,000.00
5 Instalasi interkoneksi dari MCPFA ke Panel Hydrant FRC 3x1,5 mm ls 1.00 18,000,000.00 18,000,000.00
6 Instalasi interkoneksi dari MCPFA ke Panel Press Fan FRC 3x1,5 mm ls 1.00 18,000,000.00 18,000,000.00
7 Feeder cable Twisted Shelded 4x18 AWG, from MCFA to MTB m 10.00 275,000.00 2,750,000.00
8 Feeder cable Twisted Shelded 18 AWG+NYA 2x1,5mm, from MTB to TBT Lantai Base 1 m 25.00 275,000.00 6,875,000.00
9 Feeder cable Twisted Shelded 18 AWG+NYA 2x1,5mm, from MTB to TBT Lantai Ground m 15.00 275,000.00 4,125,000.00
10 Feeder cable Twisted Shelded 18 AWG+NYA 2x1,5mm, from MTB to TBT Lantai 1 m 25.00 275,000.00 6,875,000.00
11 Feeder cable Twisted Shelded 18 AWG+NYA 2x1,5mm, from MTB to TBT Lantai 2 m 35.00 275,000.00 9,625,000.00
12 Feeder cable Twisted Shelded 18 AWG+NYA 2x1,5mm, from MTB to TBT Lantai 3 m 45.00 275,000.00 12,375,000.00
13 Feeder cable Twisted Shelded 18 AWG+NYA 2x1,5mm, from MTB to TBT Lantai 4 m 55.00 275,000.00 15,125,000.00
14 Feeder cable Twisted Shelded 18 AWG+NYA 2x1,5mm, from MTB to TBT Lantai 5 m 65.00 275,000.00 17,875,000.00
15 Feeder cable Twisted Shelded 18 AWG+NYA 2x1,5mm, from MTB to TBT Lantai 6 m 75.00 275,000.00 20,625,000.00
16 Feeder cable Twisted Shelded 18 AWG+NYA 2x1,5mm, from MTB to TBT Lantai 7 m 85.00 275,000.00 23,375,000.00
17 Feeder cable Twisted Shelded 18 AWG+NYA 2x1,5mm, from MTB to TBT Lantai 8 m 95.00 275,000.00 26,125,000.00
18 Feeder cable Twisted Shelded 18 AWG+NYA 2x1,5mm, from MTB to TBT Lantai 9 m 105.00 275,000.00 28,875,000.00
19 Feeder cable Twisted Shelded 18 AWG+NYA 2x1,5mm, from MTB to TBT Lantai 10 m 115.00 275,000.00 31,625,000.00
20 Feeder cable Twisted Shelded 18 AWG+NYA 2x1,5mm, from MTB to TBT Lantai 11 m 125.00 275,000.00 34,375,000.00
21 Feeder cable Twisted Shelded 18 AWG+NYA 2x1,5mm, from MTB to TBT Lantai 12 m 135.00 275,000.00 37,125,000.00
22 Feeder cable Twisted Shelded 18 AWG+NYA 2x1,5mm, from MTB to TBT Lantai 13 m 145.00 275,000.00 39,875,000.00
23 Feeder cable Twisted Shelded 18 AWG+NYA 2x1,5mm, from MTB to TBT Lantai 14 m 155.00 275,000.00 42,625,000.00
24 Feeder cable Twisted Shelded 18 AWG+NYA 2x1,5mm, from MTB to TBT Lantai 15 m 165.00 275,000.00 45,375,000.00
25 Feeder cable Twisted Shelded 18 AWG+NYA 2x1,5mm, from MTB to TBT Lantai 16 m 175.00 275,000.00 48,125,000.00
26 Feeder cable Twisted Shelded 18 AWG+NYA 2x1,5mm, from MTB to TBT Lantai 17 m 185.00 275,000.00 50,875,000.00
27 Feeder cable Twisted Shelded 18 AWG+NYA 2x1,5mm, from MTB to TBT Lantai 18 m 195.00 275,000.00 53,625,000.00
28 Feeder cable Twisted Shelded 18 AWG+NYA 2x1,5mm, from MTB to TBT Lantai 19 m 205.00 275,000.00 56,375,000.00
Sub Total Instalasi Kabel Feeder dari MTB ke TBFA 722,625,000.00
C Instalasi Fire Alarm Lantai Base 1
1 Photoelectric Smoke Detector bh 1.00 1,800,000.00 1,800,000.00
2 Heat Detector (Rate Of Rise) bh 14.00 2,500,000.00 35,000,000.00
3 Alarm Lamp bh 2.00 800,000.00 1,600,000.00
4 Alarm Bell bh 2.00 900,000.00 1,800,000.00
5 Manual Push Button bh 2.00 75,000.00 150,000.00
6 Installasi detector, STP 18 AWG, dalam PVC Conduit dia.3 / 4" ttk 15.00 700,000.00 10,500,000.00
7 Instalasi Manual push button, alarm bell, indicator lamp ttk 2.00 450,000.00 900,000.00
- NYA 2(1 x 1,5 mm2) dalam PVC Conduit dia.3 / 4"
8 Instalasi Flow Switch (NYA 2(1 x 1,5 mm2) dalam PVC Conduit dia.3 / 4") ttk 1.00 650,000.00 650,000.00
9 Instalasi Outlet Intercom dengan kabel ITC (2 (2 x 0.6 mm2) dalam PVC Conduit dia 3 / 4") ttk 1.00 680,000.00 680,000.00
10 Zone Control bh 2.00 4,000,000.00 8,000,000.00
11 Monitor Module bh 2.00 7,600,000.00 15,200,000.00
12 Control Relay Module bh 1.00 8,000,000.00 8,000,000.00
13 End Of Line (Resistant 10 KW) bh 2.00 7,000,000.00 14,000,000.00
14 Fire Extinguisher type ABC kap. 4 kg bh 2.00 8,000,000.00 16,000,000.00
15 Terminal Box bh 1.00 2,500,000.00 2,500,000.00

Rincian RAB MEP (Fire Alarm)


Universitas Muhammadiyah Tangerang
Page 57
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

Sub Total Instalasi Fire Alarm Lantai Base 1 116,780,000.00


D Instalasi Fire Alarm Lantai Ground
1 Photoelectric Smoke Detector bh 4.00 1,800,000.00 7,200,000.00
2 Heat Detector (Rate Of Rise) bh 15.00 2,500,000.00 37,500,000.00
3 Alarm Lamp bh 2.00 800,000.00 1,600,000.00
4 Alarm Bell bh 2.00 900,000.00 1,800,000.00
5 Manual Push Button bh 2.00 75,000.00 150,000.00
6 Installasi detector, STP 18 AWG, dalam PVC Conduit dia.3 / 4" ttk 19.00 700,000.00 13,300,000.00
7 Instalasi Manual push button, alarm bell, indicator lamp ttk 2.00 450,000.00 900,000.00
- NYA 2(1 x 1,5 mm2) dalam PVC Conduit dia.3 / 4"
8 Instalasi Flow Switch (NYA 2(1 x 1,5 mm2) dalam PVC Conduit dia.3 / 4") ttk 1.00 650,000.00 650,000.00
9 Instalasi Outlet Intercom dengan kabel ITC (2 (2 x 0.6 mm2) dalam PVC Conduit dia 3 / 4") ttk 1.00 680,000.00 680,000.00
10 Zone Control bh 2.00 4,000,000.00 8,000,000.00
11 Monitor Module bh 2.00 7,600,000.00 15,200,000.00
12 Control Relay Module bh 1.00 8,000,000.00 8,000,000.00
13 End Of Line (Resistant 10 KW) bh 2.00 7,000,000.00 14,000,000.00
14 Fire Extinguisher type ABC kap. 4 kg bh 2.00 8,000,000.00 16,000,000.00
15 Terminal Box bh 1.00 2,500,000.00 2,500,000.00
Sub Total Instalasi Fire Alarm Lantai Ground 127,480,000.00
E Instalasi Fire Alarm Lantai 1
1 Photoelectric Smoke Detector bh 2.00 1,800,000.00 3,600,000.00
2 Heat Detector (Rate Of Rise) bh 15.00 2,500,000.00 37,500,000.00
3 Alarm Lamp bh 2.00 800,000.00 1,600,000.00
4 Alarm Bell bh 2.00 900,000.00 1,800,000.00
5 Manual Push Button bh 2.00 75,000.00 150,000.00
6 Installasi detector, STP 18 AWG, dalam PVC Conduit dia.3 / 4" ttk 17.00 700,000.00 11,900,000.00
7 Instalasi Manual push button, alarm bell, indicator lamp ttk 2.00 450,000.00 900,000.00
- NYA 2(1 x 1,5 mm2) dalam PVC Conduit dia.3 / 4"
8 Instalasi Flow Switch (NYA 2(1 x 1,5 mm2) dalam PVC Conduit dia.3 / 4") ttk 1.00 650,000.00 650,000.00
9 Instalasi Outlet Intercom dengan kabel ITC (2 (2 x 0.6 mm2) dalam PVC Conduit dia 3 / 4") ttk 1.00 680,000.00 680,000.00
10 Zone Control bh 2.00 4,000,000.00 8,000,000.00
11 Monitor Module bh 2.00 7,600,000.00 15,200,000.00
12 Control Relay Module bh 1.00 8,000,000.00 8,000,000.00
13 End Of Line (Resistant 10 KW) bh 2.00 7,000,000.00 14,000,000.00
14 Fire Extinguisher type ABC kap. 4 kg bh 2.00 8,000,000.00 16,000,000.00
15 Terminal Box bh 1.00 2,500,000.00 2,500,000.00
Sub Total Instalasi Fire Alarm Lantai 1 122,480,000.00
F Instalasi Fire Alarm Lantai 2
1 Photoelectric Smoke Detector bh 1.00 1,800,000.00 1,800,000.00
2 Heat Detector (Rate Of Rise) bh 16.00 2,500,000.00 40,000,000.00
3 Alarm Lamp bh 2.00 800,000.00 1,600,000.00
4 Alarm Bell bh 2.00 900,000.00 1,800,000.00
5 Manual Push Button bh 2.00 75,000.00 150,000.00
6 Installasi detector, STP 18 AWG, dalam PVC Conduit dia.3 / 4" ttk 17.00 700,000.00 11,900,000.00
7 Instalasi Manual push button, alarm bell, indicator lamp ttk 2.00 450,000.00 900,000.00
- NYA 2(1 x 1,5 mm2) dalam PVC Conduit dia.3 / 4"
8 Instalasi Flow Switch (NYA 2(1 x 1,5 mm2) dalam PVC Conduit dia.3 / 4") ttk 1.00 650,000.00 650,000.00
9 Instalasi Outlet Intercom dengan kabel ITC (2 (2 x 0.6 mm2) dalam PVC Conduit dia 3 / 4") ttk 1.00 680,000.00 680,000.00
10 Zone Control bh 2.00 4,000,000.00 8,000,000.00
11 Monitor Module bh 2.00 7,600,000.00 15,200,000.00
12 Control Relay Module bh 1.00 8,000,000.00 8,000,000.00
13 End Of Line (Resistant 10 KW) bh 2.00 7,000,000.00 14,000,000.00
14 Fire Extinguisher type ABC kap. 4 kg bh 2.00 8,000,000.00 16,000,000.00
15 Terminal Box bh 1.00 2,500,000.00 2,500,000.00
Sub Total Instalasi Fire Alarm Lantai 2 123,180,000.00
G Instalasi Fire Alarm Lantai 3
1 Photoelectric Smoke Detector bh 1.00 1,800,000.00 1,800,000.00
2 Heat Detector (Rate Of Rise) bh 16.00 2,500,000.00 40,000,000.00
3 Alarm Lamp bh 2.00 800,000.00 1,600,000.00
4 Alarm Bell bh 2.00 900,000.00 1,800,000.00
5 Manual Push Button bh 2.00 75,000.00 150,000.00

Rincian RAB MEP (Fire Alarm)


Universitas Muhammadiyah Tangerang
Page 58
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

6 Installasi detector, STP 18 AWG, dalam PVC Conduit dia.3 / 4" ttk 17.00 700,000.00 11,900,000.00
7 Instalasi Manual push button, alarm bell, indicator lamp ttk 2.00 450,000.00 900,000.00
- NYA 2(1 x 1,5 mm2) dalam PVC Conduit dia.3 / 4"
8 Instalasi Flow Switch (NYA 2(1 x 1,5 mm2) dalam PVC Conduit dia.3 / 4") ttk 1.00 650,000.00 650,000.00
9 Instalasi Outlet Intercom dengan kabel ITC (2 (2 x 0.6 mm2) dalam PVC Conduit dia 3 / 4") ttk 1.00 680,000.00 680,000.00
10 Zone Control bh 2.00 4,000,000.00 8,000,000.00
11 Monitor Module bh 2.00 7,600,000.00 15,200,000.00
12 Control Relay Module bh 1.00 8,000,000.00 8,000,000.00
13 End Of Line (Resistant 10 KW) bh 2.00 7,000,000.00 14,000,000.00
14 Fire Extinguisher type ABC kap. 4 kg bh 2.00 8,000,000.00 16,000,000.00
15 Terminal Box bh 1.00 2,500,000.00 2,500,000.00
Sub Total Instalasi Fire Alarm Lantai 3 123,180,000.00
H Instalasi Fire Alarm Lantai 4
1 Photoelectric Smoke Detector bh 1.00 1,800,000.00 1,800,000.00
2 Heat Detector (Rate Of Rise) bh 16.00 2,500,000.00 40,000,000.00
3 Alarm Lamp bh 2.00 800,000.00 1,600,000.00
4 Alarm Bell bh 2.00 900,000.00 1,800,000.00
5 Manual Push Button bh 2.00 75,000.00 150,000.00
6 Installasi detector, STP 18 AWG, dalam PVC Conduit dia.3 / 4" ttk 17.00 700,000.00 11,900,000.00
7 Instalasi Manual push button, alarm bell, indicator lamp ttk 2.00 450,000.00 900,000.00
- NYA 2(1 x 1,5 mm2) dalam PVC Conduit dia.3 / 4"
8 Instalasi Flow Switch (NYA 2(1 x 1,5 mm2) dalam PVC Conduit dia.3 / 4") ttk 1.00 650,000.00 650,000.00
9 Instalasi Outlet Intercom dengan kabel ITC (2 (2 x 0.6 mm2) dalam PVC Conduit dia 3 / 4") ttk 1.00 680,000.00 680,000.00
10 Zone Control bh 2.00 4,000,000.00 8,000,000.00
11 Monitor Module bh 2.00 7,600,000.00 15,200,000.00
12 Control Relay Module bh 1.00 8,000,000.00 8,000,000.00
13 End Of Line (Resistant 10 KW) bh 2.00 7,000,000.00 14,000,000.00
14 Fire Extinguisher type ABC kap. 4 kg bh 2.00 8,000,000.00 16,000,000.00
15 Terminal Box bh 1.00 2,500,000.00 2,500,000.00
Sub Total Instalasi Fire Alarm Lantai 4 123,180,000.00
I Instalasi Fire Alarm Lantai 5
1 Photoelectric Smoke Detector bh 1.00 1,800,000.00 1,800,000.00
2 Heat Detector (Rate Of Rise) bh 16.00 2,500,000.00 40,000,000.00
3 Alarm Lamp bh 2.00 800,000.00 1,600,000.00
4 Alarm Bell bh 2.00 900,000.00 1,800,000.00
5 Manual Push Button bh 2.00 75,000.00 150,000.00
6 Installasi detector, STP 18 AWG, dalam PVC Conduit dia.3 / 4" ttk 17.00 700,000.00 11,900,000.00
7 Instalasi Manual push button, alarm bell, indicator lamp ttk 2.00 450,000.00 900,000.00
- NYA 2(1 x 1,5 mm2) dalam PVC Conduit dia.3 / 4"
8 Instalasi Flow Switch (NYA 2(1 x 1,5 mm2) dalam PVC Conduit dia.3 / 4") ttk 1.00 650,000.00 650,000.00
9 Instalasi Outlet Intercom dengan kabel ITC (2 (2 x 0.6 mm2) dalam PVC Conduit dia 3 / 4") ttk 1.00 680,000.00 680,000.00
10 Zone Control bh 2.00 4,000,000.00 8,000,000.00
11 Monitor Module bh 2.00 7,600,000.00 15,200,000.00
12 Control Relay Module bh 1.00 8,000,000.00 8,000,000.00
13 End Of Line (Resistant 10 KW) bh 2.00 7,000,000.00 14,000,000.00
14 Fire Extinguisher type ABC kap. 4 kg bh 2.00 8,000,000.00 16,000,000.00
15 Terminal Box bh 1.00 2,500,000.00 2,500,000.00
Sub Total Instalasi Fire Alarm Lantai 5 123,180,000.00
J Instalasi Fire Alarm Lantai 6
1 Photoelectric Smoke Detector bh 6.00 1,800,000.00 10,800,000.00
2 Heat Detector (Rate Of Rise) bh 14.00 2,500,000.00 35,000,000.00
3 Alarm Lamp bh 2.00 800,000.00 1,600,000.00
4 Alarm Bell bh 2.00 900,000.00 1,800,000.00
5 Manual Push Button bh 2.00 75,000.00 150,000.00
6 Installasi detector, STP 18 AWG, dalam PVC Conduit dia.3 / 4" ttk 20.00 700,000.00 14,000,000.00
7 Instalasi Manual push button, alarm bell, indicator lamp ttk 2.00 450,000.00 900,000.00
- NYA 2(1 x 1,5 mm2) dalam PVC Conduit dia.3 / 4"
8 Instalasi Flow Switch (NYA 2(1 x 1,5 mm2) dalam PVC Conduit dia.3 / 4") ttk 1.00 650,000.00 650,000.00
9 Instalasi Outlet Intercom dengan kabel ITC (2 (2 x 0.6 mm2) dalam PVC Conduit dia 3 / 4") ttk 1.00 680,000.00 680,000.00
10 Zone Control bh 2.00 4,000,000.00 8,000,000.00
11 Monitor Module bh 2.00 7,600,000.00 15,200,000.00

Rincian RAB MEP (Fire Alarm)


Universitas Muhammadiyah Tangerang
Page 59
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

12 Control Relay Module bh 1.00 8,000,000.00 8,000,000.00


13 End Of Line (Resistant 10 KW) bh 2.00 7,000,000.00 14,000,000.00
14 Fire Extinguisher type ABC kap. 4 kg bh 2.00 8,000,000.00 16,000,000.00
15 Terminal Box bh 1.00 2,500,000.00 2,500,000.00
Sub Total Instalasi Fire Alarm Lantai 6 129,280,000.00
K Instalasi Fire Alarm Lantai 7
1 Photoelectric Smoke Detector bh - 1,800,000.00 -
2 Heat Detector (Rate Of Rise) bh 16.00 2,500,000.00 40,000,000.00
3 Alarm Lamp bh 2.00 800,000.00 1,600,000.00
4 Alarm Bell bh 2.00 900,000.00 1,800,000.00
5 Manual Push Button bh 2.00 75,000.00 150,000.00
6 Installasi detector, STP 18 AWG, dalam PVC Conduit dia.3 / 4" ttk 16.00 700,000.00 11,200,000.00
7 Instalasi Manual push button, alarm bell, indicator lamp ttk 2.00 450,000.00 900,000.00
- NYA 2(1 x 1,5 mm2) dalam PVC Conduit dia.3 / 4"
8 Instalasi Flow Switch (NYA 2(1 x 1,5 mm2) dalam PVC Conduit dia.3 / 4") ttk 1.00 650,000.00 650,000.00
9 Instalasi Outlet Intercom dengan kabel ITC (2 (2 x 0.6 mm2) dalam PVC Conduit dia 3 / 4") ttk 1.00 680,000.00 680,000.00
10 Zone Control bh 2.00 4,000,000.00 8,000,000.00
11 Monitor Module bh 2.00 7,600,000.00 15,200,000.00
12 Control Relay Module bh 1.00 8,000,000.00 8,000,000.00
13 End Of Line (Resistant 10 KW) bh 2.00 7,000,000.00 14,000,000.00
14 Fire Extinguisher type ABC kap. 4 kg bh 2.00 8,000,000.00 16,000,000.00
15 Terminal Box bh 1.00 2,500,000.00 2,500,000.00
Sub Total Instalasi Fire Alarm Lantai 7 120,680,000.00
L Instalasi Fire Alarm Lantai 8
1 Photoelectric Smoke Detector bh 6.00 1,800,000.00 10,800,000.00
2 Heat Detector (Rate Of Rise) bh 14.00 2,500,000.00 35,000,000.00
3 Alarm Lamp bh 2.00 800,000.00 1,600,000.00
4 Alarm Bell bh 2.00 900,000.00 1,800,000.00
5 Manual Push Button bh 2.00 75,000.00 150,000.00
6 Installasi detector, STP 18 AWG, dalam PVC Conduit dia.3 / 4" ttk 20.00 700,000.00 14,000,000.00
7 Instalasi Manual push button, alarm bell, indicator lamp ttk 2.00 450,000.00 900,000.00
- NYA 2(1 x 1,5 mm2) dalam PVC Conduit dia.3 / 4"
8 Instalasi Flow Switch (NYA 2(1 x 1,5 mm2) dalam PVC Conduit dia.3 / 4") ttk 1.00 650,000.00 650,000.00
9 Instalasi Outlet Intercom dengan kabel ITC (2 (2 x 0.6 mm2) dalam PVC Conduit dia 3 / 4") ttk 1.00 680,000.00 680,000.00
10 Zone Control bh 2.00 4,000,000.00 8,000,000.00
11 Monitor Module bh 2.00 7,600,000.00 15,200,000.00
12 Control Relay Module bh 1.00 8,000,000.00 8,000,000.00
13 End Of Line (Resistant 10 KW) bh 2.00 7,000,000.00 14,000,000.00
14 Fire Extinguisher type ABC kap. 4 kg bh 2.00 8,000,000.00 16,000,000.00
15 Terminal Box bh 1.00 2,500,000.00 2,500,000.00
Sub Total Instalasi Fire Alarm Lantai 8 129,280,000.00
M Instalasi Fire Alarm Lantai 9
1 Photoelectric Smoke Detector bh 6.00 1,800,000.00 10,800,000.00
2 Heat Detector (Rate Of Rise) bh 14.00 2,500,000.00 35,000,000.00
3 Alarm Lamp bh 2.00 800,000.00 1,600,000.00
4 Alarm Bell bh 2.00 900,000.00 1,800,000.00
5 Manual Push Button bh 2.00 75,000.00 150,000.00
6 Installasi detector, STP 18 AWG, dalam PVC Conduit dia.3 / 4" ttk 20.00 700,000.00 14,000,000.00
7 Instalasi Manual push button, alarm bell, indicator lamp ttk 2.00 450,000.00 900,000.00
- NYA 2(1 x 1,5 mm2) dalam PVC Conduit dia.3 / 4"
8 Instalasi Flow Switch (NYA 2(1 x 1,5 mm2) dalam PVC Conduit dia.3 / 4") ttk 1.00 650,000.00 650,000.00
9 Instalasi Outlet Intercom dengan kabel ITC (2 (2 x 0.6 mm2) dalam PVC Conduit dia 3 / 4") ttk 1.00 680,000.00 680,000.00
10 Zone Control bh 2.00 4,000,000.00 8,000,000.00
11 Monitor Module bh 2.00 7,600,000.00 15,200,000.00
12 Control Relay Module bh 1.00 8,000,000.00 8,000,000.00
13 End Of Line (Resistant 10 KW) bh 2.00 7,000,000.00 14,000,000.00
14 Fire Extinguisher type ABC kap. 4 kg bh 2.00 8,000,000.00 16,000,000.00
15 Terminal Box bh 1.00 2,500,000.00 2,500,000.00
Sub Total Instalasi Fire Alarm Lantai 9 129,280,000.00
N Instalasi Fire Alarm Lantai 10
1 Photoelectric Smoke Detector bh 10.00 1,800,000.00 18,000,000.00

Rincian RAB MEP (Fire Alarm)


Universitas Muhammadiyah Tangerang
Page 60
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

2 Heat Detector (Rate Of Rise) bh 13.00 2,500,000.00 32,500,000.00


3 Alarm Lamp bh 2.00 800,000.00 1,600,000.00
4 Alarm Bell bh 2.00 900,000.00 1,800,000.00
5 Manual Push Button bh 2.00 75,000.00 150,000.00
6 Installasi detector, STP 18 AWG, dalam PVC Conduit dia.3 / 4" ttk 23.00 700,000.00 16,100,000.00
7 Instalasi Manual push button, alarm bell, indicator lamp ttk 2.00 450,000.00 900,000.00
- NYA 2(1 x 1,5 mm2) dalam PVC Conduit dia.3 / 4"
8 Instalasi Flow Switch (NYA 2(1 x 1,5 mm2) dalam PVC Conduit dia.3 / 4") ttk 1.00 650,000.00 650,000.00
9 Instalasi Outlet Intercom dengan kabel ITC (2 (2 x 0.6 mm2) dalam PVC Conduit dia 3 / 4") ttk 1.00 680,000.00 680,000.00
10 Zone Control bh 2.00 4,000,000.00 8,000,000.00
11 Monitor Module bh 2.00 7,600,000.00 15,200,000.00
12 Control Relay Module bh 1.00 8,000,000.00 8,000,000.00
13 End Of Line (Resistant 10 KW) bh 2.00 7,000,000.00 14,000,000.00
14 Fire Extinguisher type ABC kap. 4 kg bh 2.00 8,000,000.00 16,000,000.00
15 Terminal Box bh 1.00 2,500,000.00 2,500,000.00
Sub Total Instalasi Fire Alarm Lantai 10 136,080,000.00
O Instalasi Fire Alarm Lantai 11
1 Photoelectric Smoke Detector bh 10.00 1,800,000.00 18,000,000.00
2 Heat Detector (Rate Of Rise) bh 13.00 2,500,000.00 32,500,000.00
3 Alarm Lamp bh 2.00 800,000.00 1,600,000.00
4 Alarm Bell bh 2.00 900,000.00 1,800,000.00
5 Manual Push Button bh 2.00 75,000.00 150,000.00
6 Installasi detector, STP 18 AWG, dalam PVC Conduit dia.3 / 4" ttk 23.00 700,000.00 16,100,000.00
7 Instalasi Manual push button, alarm bell, indicator lamp ttk 2.00 450,000.00 900,000.00
- NYA 2(1 x 1,5 mm2) dalam PVC Conduit dia.3 / 4"
8 Instalasi Flow Switch (NYA 2(1 x 1,5 mm2) dalam PVC Conduit dia.3 / 4") ttk 1.00 650,000.00 650,000.00
9 Instalasi Outlet Intercom dengan kabel ITC (2 (2 x 0.6 mm2) dalam PVC Conduit dia 3 / 4") ttk 1.00 680,000.00 680,000.00
10 Zone Control bh 2.00 4,000,000.00 8,000,000.00
11 Monitor Module bh 2.00 7,600,000.00 15,200,000.00
12 Control Relay Module bh 1.00 8,000,000.00 8,000,000.00
13 End Of Line (Resistant 10 KW) bh 2.00 7,000,000.00 14,000,000.00
14 Fire Extinguisher type ABC kap. 4 kg bh 2.00 8,000,000.00 16,000,000.00
15 Terminal Box bh 1.00 2,500,000.00 2,500,000.00
Sub Total Instalasi Fire Alarm Lantai 11 136,080,000.00
P Instalasi Fire Alarm Lantai 12
1 Photoelectric Smoke Detector bh 10.00 1,800,000.00 18,000,000.00
2 Heat Detector (Rate Of Rise) bh 13.00 2,500,000.00 32,500,000.00
3 Alarm Lamp bh 2.00 800,000.00 1,600,000.00
4 Alarm Bell bh 2.00 900,000.00 1,800,000.00
5 Manual Push Button bh 2.00 75,000.00 150,000.00
6 Installasi detector, STP 18 AWG, dalam PVC Conduit dia.3 / 4" ttk 23.00 700,000.00 16,100,000.00
7 Instalasi Manual push button, alarm bell, indicator lamp ttk 2.00 450,000.00 900,000.00
- NYA 2(1 x 1,5 mm2) dalam PVC Conduit dia.3 / 4"
8 Instalasi Flow Switch (NYA 2(1 x 1,5 mm2) dalam PVC Conduit dia.3 / 4") ttk 1.00 650,000.00 650,000.00
9 Instalasi Outlet Intercom dengan kabel ITC (2 (2 x 0.6 mm2) dalam PVC Conduit dia 3 / 4") ttk 1.00 680,000.00 680,000.00
10 Zone Control bh 2.00 4,000,000.00 8,000,000.00
11 Monitor Module bh 2.00 7,600,000.00 15,200,000.00
12 Control Relay Module bh 1.00 8,000,000.00 8,000,000.00
13 End Of Line (Resistant 10 KW) bh 2.00 7,000,000.00 14,000,000.00
14 Fire Extinguisher type ABC kap. 4 kg bh 2.00 8,000,000.00 16,000,000.00
15 Terminal Box bh 1.00 2,500,000.00 2,500,000.00
Sub Total Instalasi Fire Alarm Lantai 12 136,080,000.00
Q Instalasi Fire Alarm Lantai 13
1 Photoelectric Smoke Detector bh 10.00 1,800,000.00 18,000,000.00
2 Heat Detector (Rate Of Rise) bh 13.00 2,500,000.00 32,500,000.00
3 Alarm Lamp bh 2.00 800,000.00 1,600,000.00
4 Alarm Bell bh 2.00 900,000.00 1,800,000.00
5 Manual Push Button bh 2.00 75,000.00 150,000.00
6 Installasi detector, STP 18 AWG, dalam PVC Conduit dia.3 / 4" ttk 23.00 700,000.00 16,100,000.00
7 Instalasi Manual push button, alarm bell, indicator lamp ttk 2.00 450,000.00 900,000.00
- NYA 2(1 x 1,5 mm2) dalam PVC Conduit dia.3 / 4"

Rincian RAB MEP (Fire Alarm)


Universitas Muhammadiyah Tangerang
Page 61
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

8 Instalasi Flow Switch (NYA 2(1 x 1,5 mm2) dalam PVC Conduit dia.3 / 4") ttk 1.00 650,000.00 650,000.00
9 Instalasi Outlet Intercom dengan kabel ITC (2 (2 x 0.6 mm2) dalam PVC Conduit dia 3 / 4") ttk 1.00 680,000.00 680,000.00
10 Zone Control bh 2.00 4,000,000.00 8,000,000.00
11 Monitor Module bh 2.00 7,600,000.00 15,200,000.00
12 Control Relay Module bh 1.00 8,000,000.00 8,000,000.00
13 End Of Line (Resistant 10 KW) bh 2.00 7,000,000.00 14,000,000.00
14 Fire Extinguisher type ABC kap. 4 kg bh 2.00 8,000,000.00 16,000,000.00
15 Terminal Box bh 1.00 2,500,000.00 2,500,000.00
Sub Total Instalasi Fire Alarm Lantai 13 136,080,000.00
R Instalasi Fire Alarm Lantai 14
1 Photoelectric Smoke Detector bh 10.00 1,800,000.00 18,000,000.00
2 Heat Detector (Rate Of Rise) bh 13.00 2,500,000.00 32,500,000.00
3 Alarm Lamp bh 2.00 800,000.00 1,600,000.00
4 Alarm Bell bh 2.00 900,000.00 1,800,000.00
5 Manual Push Button bh 2.00 75,000.00 150,000.00
6 Installasi detector, STP 18 AWG, dalam PVC Conduit dia.3 / 4" ttk 23.00 700,000.00 16,100,000.00
7 Instalasi Manual push button, alarm bell, indicator lamp ttk 2.00 450,000.00 900,000.00
- NYA 2(1 x 1,5 mm2) dalam PVC Conduit dia.3 / 4"
8 Instalasi Flow Switch (NYA 2(1 x 1,5 mm2) dalam PVC Conduit dia.3 / 4") ttk 1.00 650,000.00 650,000.00
9 Instalasi Outlet Intercom dengan kabel ITC (2 (2 x 0.6 mm2) dalam PVC Conduit dia 3 / 4") ttk 1.00 680,000.00 680,000.00
10 Zone Control bh 2.00 4,000,000.00 8,000,000.00
11 Monitor Module bh 2.00 7,600,000.00 15,200,000.00
12 Control Relay Module bh 1.00 8,000,000.00 8,000,000.00
13 End Of Line (Resistant 10 KW) bh 2.00 7,000,000.00 14,000,000.00
14 Fire Extinguisher type ABC kap. 4 kg bh 2.00 8,000,000.00 16,000,000.00
15 Terminal Box bh 1.00 2,500,000.00 2,500,000.00
Sub Total Instalasi Fire Alarm Lantai 14 136,080,000.00
S Instalasi Fire Alarm Lantai 15
1 Photoelectric Smoke Detector bh 10.00 1,800,000.00 18,000,000.00
2 Heat Detector (Rate Of Rise) bh 13.00 2,500,000.00 32,500,000.00
3 Alarm Lamp bh 2.00 800,000.00 1,600,000.00
4 Alarm Bell bh 2.00 900,000.00 1,800,000.00
5 Manual Push Button bh 2.00 75,000.00 150,000.00
6 Installasi detector, STP 18 AWG, dalam PVC Conduit dia.3 / 4" ttk 23.00 700,000.00 16,100,000.00
7 Instalasi Manual push button, alarm bell, indicator lamp ttk 2.00 450,000.00 900,000.00
- NYA 2(1 x 1,5 mm2) dalam PVC Conduit dia.3 / 4"
8 Instalasi Flow Switch (NYA 2(1 x 1,5 mm2) dalam PVC Conduit dia.3 / 4") ttk 1.00 650,000.00 650,000.00
9 Instalasi Outlet Intercom dengan kabel ITC (2 (2 x 0.6 mm2) dalam PVC Conduit dia 3 / 4") ttk 1.00 680,000.00 680,000.00
10 Zone Control bh 2.00 4,000,000.00 8,000,000.00
11 Monitor Module bh 2.00 7,600,000.00 15,200,000.00
12 Control Relay Module bh 1.00 8,000,000.00 8,000,000.00
13 End Of Line (Resistant 10 KW) bh 2.00 7,000,000.00 14,000,000.00
14 Fire Extinguisher type ABC kap. 4 kg bh 2.00 8,000,000.00 16,000,000.00
15 Terminal Box bh 1.00 2,500,000.00 2,500,000.00
Sub Total Instalasi Fire Alarm Lantai 15 136,080,000.00
T Instalasi Fire Alarm Lantai 16
1 Photoelectric Smoke Detector bh 10.00 1,800,000.00 18,000,000.00
2 Heat Detector (Rate Of Rise) bh 13.00 2,500,000.00 32,500,000.00
3 Alarm Lamp bh 2.00 800,000.00 1,600,000.00
4 Alarm Bell bh 2.00 900,000.00 1,800,000.00
5 Manual Push Button bh 2.00 75,000.00 150,000.00
6 Installasi detector, STP 18 AWG, dalam PVC Conduit dia.3 / 4" ttk 23.00 700,000.00 16,100,000.00
7 Instalasi Manual push button, alarm bell, indicator lamp ttk 2.00 450,000.00 900,000.00
- NYA 2(1 x 1,5 mm2) dalam PVC Conduit dia.3 / 4"
8 Instalasi Flow Switch (NYA 2(1 x 1,5 mm2) dalam PVC Conduit dia.3 / 4") ttk 1.00 650,000.00 650,000.00
9 Instalasi Outlet Intercom dengan kabel ITC (2 (2 x 0.6 mm2) dalam PVC Conduit dia 3 / 4") ttk 1.00 680,000.00 680,000.00
10 Zone Control bh 2.00 4,000,000.00 8,000,000.00
11 Monitor Module bh 2.00 7,600,000.00 15,200,000.00
12 Control Relay Module bh 1.00 8,000,000.00 8,000,000.00
13 End Of Line (Resistant 10 KW) bh 2.00 7,000,000.00 14,000,000.00
14 Fire Extinguisher type ABC kap. 4 kg bh 2.00 8,000,000.00 16,000,000.00

Rincian RAB MEP (Fire Alarm)


Universitas Muhammadiyah Tangerang
Page 62
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

15 Terminal Box bh 1.00 2,500,000.00 2,500,000.00


Sub Total Instalasi Fire Alarm Lantai 16 136,080,000.00
U Instalasi Fire Alarm Lantai 17
1 Photoelectric Smoke Detector bh 10.00 1,800,000.00 18,000,000.00
2 Heat Detector (Rate Of Rise) bh 13.00 2,500,000.00 32,500,000.00
3 Alarm Lamp bh 2.00 800,000.00 1,600,000.00
4 Alarm Bell bh 2.00 900,000.00 1,800,000.00
5 Manual Push Button bh 2.00 75,000.00 150,000.00
6 Installasi detector, STP 18 AWG, dalam PVC Conduit dia.3 / 4" ttk 23.00 700,000.00 16,100,000.00
7 Instalasi Manual push button, alarm bell, indicator lamp ttk 2.00 450,000.00 900,000.00
- NYA 2(1 x 1,5 mm2) dalam PVC Conduit dia.3 / 4"
8 Instalasi Flow Switch (NYA 2(1 x 1,5 mm2) dalam PVC Conduit dia.3 / 4") ttk 1.00 650,000.00 650,000.00
9 Instalasi Outlet Intercom dengan kabel ITC (2 (2 x 0.6 mm2) dalam PVC Conduit dia 3 / 4") ttk 1.00 680,000.00 680,000.00
10 Zone Control bh 2.00 4,000,000.00 8,000,000.00
11 Monitor Module bh 2.00 7,600,000.00 15,200,000.00
12 Control Relay Module bh 1.00 8,000,000.00 8,000,000.00
13 End Of Line (Resistant 10 KW) bh 2.00 7,000,000.00 14,000,000.00
14 Fire Extinguisher type ABC kap. 4 kg bh 2.00 8,000,000.00 16,000,000.00
15 Terminal Box bh 1.00 2,500,000.00 2,500,000.00
Sub Total Instalasi Fire Alarm Lantai 17 136,080,000.00
V Instalasi Fire Alarm Lantai 18
1 Photoelectric Smoke Detector bh 10.00 1,800,000.00 18,000,000.00
2 Heat Detector (Rate Of Rise) bh 13.00 2,500,000.00 32,500,000.00
3 Alarm Lamp bh 2.00 800,000.00 1,600,000.00
4 Alarm Bell bh 2.00 900,000.00 1,800,000.00
5 Manual Push Button bh 2.00 75,000.00 150,000.00
6 Installasi detector, STP 18 AWG, dalam PVC Conduit dia.3 / 4" ttk 23.00 700,000.00 16,100,000.00
7 Instalasi Manual push button, alarm bell, indicator lamp ttk 2.00 450,000.00 900,000.00
- NYA 2(1 x 1,5 mm2) dalam PVC Conduit dia.3 / 4"
8 Instalasi Flow Switch (NYA 2(1 x 1,5 mm2) dalam PVC Conduit dia.3 / 4") ttk 1.00 650,000.00 650,000.00
9 Instalasi Outlet Intercom dengan kabel ITC (2 (2 x 0.6 mm2) dalam PVC Conduit dia 3 / 4") ttk 1.00 680,000.00 680,000.00
10 Zone Control bh 2.00 4,000,000.00 8,000,000.00
11 Monitor Module bh 2.00 7,600,000.00 15,200,000.00
12 Control Relay Module bh 1.00 8,000,000.00 8,000,000.00
13 End Of Line (Resistant 10 KW) bh 2.00 7,000,000.00 14,000,000.00
14 Fire Extinguisher type ABC kap. 4 kg bh 2.00 8,000,000.00 16,000,000.00
15 Terminal Box bh 1.00 2,500,000.00 2,500,000.00
Sub Total Instalasi Fire Alarm Lantai 18 136,080,000.00
W Instalasi Fire Alarm Lantai 19
1 Photoelectric Smoke Detector bh 10.00 1,800,000.00 18,000,000.00
2 Heat Detector (Rate Of Rise) bh 13.00 2,500,000.00 32,500,000.00
3 Alarm Lamp bh 2.00 800,000.00 1,600,000.00
4 Alarm Bell bh 2.00 900,000.00 1,800,000.00
5 Manual Push Button bh 2.00 75,000.00 150,000.00
6 Installasi detector, STP 18 AWG, dalam PVC Conduit dia.3 / 4" ttk 23.00 700,000.00 16,100,000.00
7 Instalasi Manual push button, alarm bell, indicator lamp ttk 2.00 450,000.00 900,000.00
- NYA 2(1 x 1,5 mm2) dalam PVC Conduit dia.3 / 4"
8 Instalasi Flow Switch (NYA 2(1 x 1,5 mm2) dalam PVC Conduit dia.3 / 4") ttk 1.00 650,000.00 650,000.00
9 Instalasi Outlet Intercom dengan kabel ITC (2 (2 x 0.6 mm2) dalam PVC Conduit dia 3 / 4") ttk 1.00 680,000.00 680,000.00
10 Zone Control bh 2.00 4,000,000.00 8,000,000.00
11 Monitor Module bh 2.00 7,600,000.00 15,200,000.00
12 Control Relay Module bh 1.00 8,000,000.00 8,000,000.00
13 End Of Line (Resistant 10 KW) bh 2.00 7,000,000.00 14,000,000.00
14 Fire Extinguisher type ABC kap. 4 kg bh 2.00 8,000,000.00 16,000,000.00
15 Terminal Box bh 1.00 2,500,000.00 2,500,000.00
Sub Total Instalasi Fire Alarm Lantai 19 136,080,000.00

TOTAL SISTEM DETEKSI KEBAKARAN (FIRE ALARM) 3,714,405,000.00

Rincian RAB MEP (Fire Alarm)


Universitas Muhammadiyah Tangerang
Page 63
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 2 3 4 5 6 7

XII INSTALASI KABEL TRAY


A Instalasi Kabel Tray Lantai Basement 1
1 Kabel Tray Listrik uk.20x5cm m 48.00 289,800.00 13,910,400.00
2 Kabel Tray Listrik uk.30x5cm m 31.00 380,800.00 11,804,800.00
3 Kabel Tray Listrik uk.40x5cm m 28.00 472,100.00 13,218,800.00
4 Kabel Ladder di Shaft Listrik uk. 40x10cm m 15.00 410,300.00 6,154,500.00
5 Tee 40cm bh 4.00 459,400.00 1,837,600.00
6 Reducer 40cm 30cm bh 7.00 454,300.00 3,180,100.00
30cm 20cm bh 4.00 273,300.00 1,093,200.00
7 Aksesoris (Hanger & Support) ls 1.00 3,865,800.00 3,865,800.00
Sub Total Instalasi Kabel Tray Lantai Basement 1 55,065,200.00
B Instalasi Kabel Tray Lantai Ground
1 Kabel Tray Listrik uk.20x5cm m 77.00 289,800.00 22,314,600.00
2 Kabel Tray Listrik uk.30x5cm m 23.00 380,800.00 8,758,400.00
3 Kabel Tray Listrik uk.40x5cm m 40.00 472,100.00 18,884,000.00
4 Kabel Ladder di Shaft Listrik uk. 40x10cm m 15.00 410,300.00 6,154,500.00
5 Tee 40cm bh 4.00 459,500.00 1,838,000.00
6 Reducer 40cm 30cm bh 6.00 454,300.00 2,725,800.00
30cm 20cm bh 4.00 273,400.00 1,093,600.00
7 Elbow 40cm bh 1.00 413,100.00 413,100.00
7 Aksesoris (Hanger & Support) ls 1.00 4,694,900.00 4,694,900.00
Sub Total Instalasi Kabel Tray Lantai Ground 66,876,900.00
C Instalasi Kabel Tray Lantai 1
1 Kabel Tray Listrik uk.20x5cm m 19.00 289,800.00 5,506,200.00
2 Kabel Tray Listrik uk.30x5cm m 44.00 380,800.00 16,755,200.00
3 Kabel Tray Listrik uk.40x5cm m 29.00 472,100.00 13,690,900.00
4 Kabel Ladder di Shaft Listrik uk. 40x10cm m 15.00 410,300.00 6,154,500.00
5 Tee 40cm bh 2.00 459,500.00 919,000.00
6 Reducer 40cm 30cm bh 5.00 454,300.00 2,271,500.00
30cm 20cm bh 2.00 273,400.00 546,800.00
7 Elbow 40cm bh 5.00 413,100.00 2,065,500.00
7 Aksesoris (Hanger & Support) ls 1.00 3,617,400.00 3,617,400.00
Sub Total Instalasi Kabel Tray Lantai 1 51,527,000.00
D Instalasi Kabel Tray Lantai 2
1 Kabel Tray Listrik uk.20x5cm m 19.00 289,800.00 5,506,200.00
2 Kabel Tray Listrik uk.30x5cm m 44.00 380,800.00 16,755,200.00
3 Kabel Tray Listrik uk.40x5cm m 29.00 472,100.00 13,690,900.00
4 Kabel Ladder di Shaft Listrik uk. 40x10cm m 15.00 410,300.00 6,154,500.00
5 Tee 40cm bh 2.00 459,500.00 919,000.00
6 Reducer 40cm 30cm bh 5.00 454,300.00 2,271,500.00
30cm 20cm bh 2.00 273,400.00 546,800.00
7 Elbow 40cm bh 5.00 413,100.00 2,065,500.00

Rincian RAB MEP (Instalasi Kabel Tray)


Universitas Muhammadiyah Tangerang
Page 64
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 2 3 4 5 6 7

7 Aksesoris (Hanger & Support) ls 1.00 3,617,400.00 3,617,400.00


Sub Total Instalasi Kabel Tray Lantai 2 51,527,000.00
E Instalasi Kabel Tray Lantai 3
1 Kabel Tray Listrik uk.20x5cm m 19.00 289,800.00 5,506,200.00
2 Kabel Tray Listrik uk.30x5cm m 44.00 380,800.00 16,755,200.00
3 Kabel Tray Listrik uk.40x5cm m 29.00 472,100.00 13,690,900.00
4 Kabel Ladder di Shaft Listrik uk. 40x10cm m 15.00 410,300.00 6,154,500.00
5 Tee 40cm bh 2.00 459,500.00 919,000.00
6 Reducer 40cm 30cm bh 5.00 454,300.00 2,271,500.00
30cm 20cm bh 2.00 273,400.00 546,800.00
7 Elbow 40cm bh 5.00 413,100.00 2,065,500.00
7 Aksesoris (Hanger & Support) ls 1.00 3,617,400.00 3,617,400.00
Sub Total Instalasi Kabel Tray Lantai 3 51,527,000.00
F Instalasi Kabel Tray Lantai 4
1 Kabel Tray Listrik uk.20x5cm m 19.00 289,800.00 5,506,200.00
2 Kabel Tray Listrik uk.30x5cm m 44.00 380,800.00 16,755,200.00
3 Kabel Tray Listrik uk.40x5cm m 29.00 472,100.00 13,690,900.00
4 Kabel Ladder di Shaft Listrik uk. 40x10cm m 15.00 410,300.00 6,154,500.00
5 Tee 40cm bh 2.00 459,500.00 919,000.00
6 Reducer 40cm 30cm bh 5.00 454,300.00 2,271,500.00
30cm 20cm bh 2.00 273,400.00 546,800.00
7 Elbow 40cm bh 5.00 413,100.00 2,065,500.00
7 Aksesoris (Hanger & Support) ls 1.00 3,617,400.00 3,617,400.00
Sub Total Instalasi Kabel Tray Lantai 4 51,527,000.00
G Instalasi Kabel Tray Lantai 5
1 Kabel Tray Listrik uk.20x5cm m 19.00 289,800.00 5,506,200.00
2 Kabel Tray Listrik uk.30x5cm m 44.00 380,800.00 16,755,200.00
3 Kabel Tray Listrik uk.40x5cm m 29.00 472,100.00 13,690,900.00
4 Kabel Ladder di Shaft Listrik uk. 40x10cm m 15.00 410,300.00 6,154,500.00
5 Tee 40cm bh 2.00 459,500.00 919,000.00
6 Reducer 40cm 30cm bh 5.00 454,300.00 2,271,500.00
30cm 20cm bh 2.00 273,400.00 546,800.00
7 Elbow 40cm bh 5.00 413,100.00 2,065,500.00
7 Aksesoris (Hanger & Support) ls 1.00 3,617,400.00 3,617,400.00
Sub Total Instalasi Kabel Tray Lantai 5 51,527,000.00
H Instalasi Kabel Tray Lantai 6
1 Kabel Tray Listrik uk.20x5cm m 32.00 289,800.00 9,273,600.00
2 Kabel Tray Listrik uk.30x5cm m 33.00 380,800.00 12,566,400.00
3 Kabel Tray Listrik uk.40x5cm m 33.00 472,100.00 15,579,300.00
4 Kabel Ladder di Shaft Listrik uk. 40x10cm m 15.00 410,300.00 6,154,500.00
5 Tee 40cm bh 4.00 459,500.00 1,838,000.00
6 Reducer 40cm 30cm bh 7.00 454,300.00 3,180,100.00
30cm 20cm bh 2.00 273,400.00 546,800.00

Rincian RAB MEP (Instalasi Kabel Tray)


Universitas Muhammadiyah Tangerang
Page 65
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 2 3 4 5 6 7

7 Elbow 40cm bh 2.00 413,100.00 826,200.00


7 Aksesoris (Hanger & Support) ls 1.00 3,772,500.00 3,772,500.00
Sub Total Instalasi Kabel Tray Lantai 6 53,737,400.00
I Instalasi Kabel Tray Lantai 7
1 Kabel Tray Listrik uk.20x5cm m 60.00 289,800.00 17,388,000.00
2 Kabel Tray Listrik uk.30x5cm m 34.00 380,800.00 12,947,200.00
3 Kabel Tray Listrik uk.40x5cm m 28.00 472,100.00 13,218,800.00
4 Kabel Ladder di Shaft Listrik uk. 40x10cm m 15.00 410,300.00 6,154,500.00
5 Tee 40cm bh 4.00 459,500.00 1,838,000.00
6 Reducer 40cm 30cm bh 7.00 454,300.00 3,180,100.00
30cm 20cm bh 2.00 273,400.00 546,800.00
7 Elbow 40cm bh 1.00 413,100.00 413,100.00
7 Aksesoris (Hanger & Support) ls 1.00 4,204,600.00 4,204,600.00
Sub Total Instalasi Kabel Tray Lantai 7 59,891,100.00
J Instalasi Kabel Tray Lantai 8
1 Kabel Tray Listrik uk.20x5cm m 54.00 289,800.00 15,649,200.00
2 Kabel Tray Listrik uk.30x5cm m 17.00 380,800.00 6,473,600.00
3 Kabel Tray Listrik uk.40x5cm m 31.00 472,100.00 14,635,100.00
4 Kabel Ladder di Shaft Listrik uk. 40x10cm m 15.00 410,300.00 6,154,500.00
5 Tee 40cm bh 4.00 459,500.00 1,838,000.00
6 Reducer 40cm 30cm bh 7.00 454,300.00 3,180,100.00
30cm 20cm bh 6.00 273,400.00 1,640,400.00
7 Elbow 40cm bh 2.00 413,100.00 826,200.00
7 Aksesoris (Hanger & Support) ls 1.00 3,805,200.00 3,805,200.00
Sub Total Instalasi Kabel Tray Lantai 8 54,202,300.00
K Instalasi Kabel Tray Lantai 9
1 Kabel Tray Listrik uk.20x5cm m 54.00 289,800.00 15,649,200.00
2 Kabel Tray Listrik uk.30x5cm m 17.00 380,800.00 6,473,600.00
3 Kabel Tray Listrik uk.40x5cm m 31.00 472,100.00 14,635,100.00
4 Kabel Ladder di Shaft Listrik uk. 40x10cm m 15.00 410,300.00 6,154,500.00
5 Tee 40cm bh 4.00 459,500.00 1,838,000.00
6 Reducer 40cm 30cm bh 7.00 454,300.00 3,180,100.00
30cm 20cm bh 6.00 273,400.00 1,640,400.00
7 Elbow 40cm bh 2.00 413,100.00 826,200.00
7 Aksesoris (Hanger & Support) ls 1.00 3,805,200.00 3,805,200.00
Sub Total Instalasi Kabel Tray Lantai 9 54,202,300.00
L Instalasi Kabel Tray Lantai 10
1 Kabel Tray Listrik uk.20x5cm m 54.00 289,800.00 15,649,200.00
2 Kabel Tray Listrik uk.30x5cm m 17.00 380,800.00 6,473,600.00
3 Kabel Tray Listrik uk.40x5cm m 31.00 472,100.00 14,635,100.00
4 Kabel Ladder di Shaft Listrik uk. 40x10cm m 15.00 410,300.00 6,154,500.00
5 Tee 40cm bh 4.00 459,500.00 1,838,000.00
6 Reducer 40cm 30cm bh 7.00 454,300.00 3,180,100.00

Rincian RAB MEP (Instalasi Kabel Tray)


Universitas Muhammadiyah Tangerang
Page 66
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 2 3 4 5 6 7

30cm 20cm bh 6.00 273,400.00 1,640,400.00


7 Elbow 40cm bh 2.00 413,100.00 826,200.00
7 Aksesoris (Hanger & Support) ls 1.00 3,805,200.00 3,805,200.00
Sub Total Instalasi Kabel Tray Lantai 10 54,202,300.00
M Instalasi Kabel Tray Lantai 11
1 Kabel Tray Listrik uk.20x5cm m 54.00 289,800.00 15,649,200.00
2 Kabel Tray Listrik uk.30x5cm m 17.00 380,800.00 6,473,600.00
3 Kabel Tray Listrik uk.40x5cm m 31.00 472,100.00 14,635,100.00
4 Kabel Ladder di Shaft Listrik uk. 40x10cm m 15.00 410,300.00 6,154,500.00
5 Tee 40cm bh 4.00 459,500.00 1,838,000.00
6 Reducer 40cm 30cm bh 7.00 454,300.00 3,180,100.00
30cm 20cm bh 6.00 273,400.00 1,640,400.00
7 Elbow 40cm bh 2.00 413,100.00 826,200.00
7 Aksesoris (Hanger & Support) ls 1.00 3,805,200.00 3,805,200.00
Sub Total Instalasi Kabel Tray Lantai 11 54,202,300.00
N Instalasi Kabel Tray Lantai 12
1 Kabel Tray Listrik uk.20x5cm m 54.00 289,800.00 15,649,200.00
2 Kabel Tray Listrik uk.30x5cm m 17.00 380,800.00 6,473,600.00
3 Kabel Tray Listrik uk.40x5cm m 31.00 472,100.00 14,635,100.00
4 Kabel Ladder di Shaft Listrik uk. 40x10cm m 15.00 410,300.00 6,154,500.00
5 Tee 40cm bh 4.00 459,500.00 1,838,000.00
6 Reducer 40cm 30cm bh 7.00 454,300.00 3,180,100.00
30cm 20cm bh 6.00 273,400.00 1,640,400.00
7 Elbow 40cm bh 2.00 413,100.00 826,200.00
7 Aksesoris (Hanger & Support) ls 1.00 3,805,200.00 3,805,200.00
Sub Total Instalasi Kabel Tray Lantai 12 54,202,300.00
O Instalasi Kabel Tray Lantai 13
1 Kabel Tray Listrik uk.20x5cm m 54.00 289,800.00 15,649,200.00
2 Kabel Tray Listrik uk.30x5cm m 17.00 380,800.00 6,473,600.00
3 Kabel Tray Listrik uk.40x5cm m 31.00 472,100.00 14,635,100.00
4 Kabel Ladder di Shaft Listrik uk. 40x10cm m 15.00 410,300.00 6,154,500.00
5 Tee 40cm bh 4.00 459,500.00 1,838,000.00
6 Reducer 40cm 30cm bh 7.00 454,300.00 3,180,100.00
30cm 20cm bh 6.00 273,400.00 1,640,400.00
7 Elbow 40cm bh 2.00 413,100.00 826,200.00
7 Aksesoris (Hanger & Support) ls 1.00 3,805,200.00 3,805,200.00
Sub Total Instalasi Kabel Tray Lantai 13 54,202,300.00
P Instalasi Kabel Tray Lantai 14
1 Kabel Tray Listrik uk.20x5cm m 54.00 289,800.00 15,649,200.00
2 Kabel Tray Listrik uk.30x5cm m 17.00 380,800.00 6,473,600.00
3 Kabel Tray Listrik uk.40x5cm m 31.00 472,100.00 14,635,100.00
4 Kabel Ladder di Shaft Listrik uk. 40x10cm m 15.00 410,300.00 6,154,500.00
5 Tee 40cm bh 4.00 459,500.00 1,838,000.00

Rincian RAB MEP (Instalasi Kabel Tray)


Universitas Muhammadiyah Tangerang
Page 67
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 2 3 4 5 6 7

6 Reducer 40cm 30cm bh 7.00 454,300.00 3,180,100.00


30cm 20cm bh 6.00 273,400.00 1,640,400.00
7 Elbow 40cm bh 2.00 413,100.00 826,200.00
7 Aksesoris (Hanger & Support) ls 1.00 3,805,200.00 3,805,200.00
Sub Total Instalasi Kabel Tray Lantai 14 54,202,300.00
Q Instalasi Kabel Tray Lantai 15
1 Kabel Tray Listrik uk.20x5cm m 54.00 289,800.00 15,649,200.00
2 Kabel Tray Listrik uk.30x5cm m 17.00 380,800.00 6,473,600.00
3 Kabel Tray Listrik uk.40x5cm m 31.00 472,100.00 14,635,100.00
4 Kabel Ladder di Shaft Listrik uk. 40x10cm m 15.00 410,300.00 6,154,500.00
5 Tee 40cm bh 4.00 459,500.00 1,838,000.00
6 Reducer 40cm 30cm bh 7.00 454,300.00 3,180,100.00
30cm 20cm bh 6.00 273,400.00 1,640,400.00
7 Elbow 40cm bh 2.00 413,100.00 826,200.00
7 Aksesoris (Hanger & Support) ls 1.00 3,805,200.00 3,805,200.00
Sub Total Instalasi Kabel Tray Lantai 15 54,202,300.00
R Instalasi Kabel Tray Lantai 16
1 Kabel Tray Listrik uk.20x5cm m 54.00 289,800.00 15,649,200.00
2 Kabel Tray Listrik uk.30x5cm m 17.00 380,800.00 6,473,600.00
3 Kabel Tray Listrik uk.40x5cm m 31.00 472,100.00 14,635,100.00
4 Kabel Ladder di Shaft Listrik uk. 40x10cm m 15.00 410,300.00 6,154,500.00
5 Tee 40cm bh 4.00 459,500.00 1,838,000.00
6 Reducer 40cm 30cm bh 7.00 454,300.00 3,180,100.00
30cm 20cm bh 6.00 273,400.00 1,640,400.00
7 Elbow 40cm bh 2.00 413,100.00 826,200.00
7 Aksesoris (Hanger & Support) ls 1.00 3,805,200.00 3,805,200.00
Sub Total Instalasi Kabel Tray Lantai 16 54,202,300.00
S Instalasi Kabel Tray Lantai 17
1 Kabel Tray Listrik uk.20x5cm m 54.00 289,800.00 15,649,200.00
2 Kabel Tray Listrik uk.30x5cm m 17.00 380,800.00 6,473,600.00
3 Kabel Tray Listrik uk.40x5cm m 31.00 472,100.00 14,635,100.00
4 Kabel Ladder di Shaft Listrik uk. 40x10cm m 15.00 410,300.00 6,154,500.00
5 Tee 40cm bh 4.00 459,500.00 1,838,000.00
6 Reducer 40cm 30cm bh 7.00 454,300.00 3,180,100.00
30cm 20cm bh 6.00 273,400.00 1,640,400.00
7 Elbow 40cm bh 2.00 413,100.00 826,200.00
7 Aksesoris (Hanger & Support) ls 1.00 3,805,200.00 3,805,200.00
Sub Total Instalasi Kabel Tray Lantai 17 54,202,300.00
T Instalasi Kabel Tray Lantai 18
1 Kabel Tray Listrik uk.20x5cm m 54.00 289,800.00 15,649,200.00
2 Kabel Tray Listrik uk.30x5cm m 17.00 380,800.00 6,473,600.00
3 Kabel Tray Listrik uk.40x5cm m 31.00 472,100.00 14,635,100.00
4 Kabel Ladder di Shaft Listrik uk. 40x10cm m 15.00 410,300.00 6,154,500.00

Rincian RAB MEP (Instalasi Kabel Tray)


Universitas Muhammadiyah Tangerang
Page 68
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 2 3 4 5 6 7

5 Tee 40cm bh 4.00 459,500.00 1,838,000.00


6 Reducer 40cm 30cm bh 7.00 454,300.00 3,180,100.00
30cm 20cm bh 6.00 273,400.00 1,640,400.00
7 Elbow 40cm bh 2.00 413,100.00 826,200.00
7 Aksesoris (Hanger & Support) ls 1.00 3,805,200.00 3,805,200.00
Sub Total Instalasi Kabel Tray Lantai 18 54,202,300.00
U Instalasi Kabel Tray Lantai 19
1 Kabel Tray Listrik uk.20x5cm m 47.00 289,800.00 13,620,600.00
2 Kabel Tray Listrik uk.30x5cm m 17.00 380,800.00 6,473,600.00
3 Kabel Tray Listrik uk.40x5cm m 30.00 472,100.00 14,163,000.00
4 Kabel Ladder di Shaft Listrik uk. 40x10cm m 15.00 410,300.00 6,154,500.00
5 Tee 40cm bh 4.00 459,500.00 1,838,000.00
6 Reducer 40cm 30cm bh 7.00 454,300.00 3,180,100.00
30cm 20cm bh 6.00 273,400.00 1,640,400.00
7 Elbow 40cm bh 2.00 413,100.00 826,200.00
7 Aksesoris (Hanger & Support) ls 1.00 3,616,300.00 3,616,300.00
Sub Total Instalasi Kabel Tray Lantai 19 51,512,700.00
V Instalasi Kabel Tray & Ladder Ruang Panel & Ruang Genset
1 Kabel Tray Listrik uk.50x10cm m 12.00 638,800.00 7,665,600.00
2 Tee 50cm bh 2.00 720,300.00 1,440,600.00
3 Elbow 50cm bh 4.00 654,900.00 2,619,600.00
4 Aksesoris (Hanger & Support) ls 1.00 846,700.00 846,700.00
Sub Total Instalasi Kabel Tray & Ladder Ruang Panel & Ruang Genset 12,572,500.00

TOTAL INSTALASI KABEL TRAY 1,153,516,100.00

Rincian RAB MEP (Instalasi Kabel Tray)


Universitas Muhammadiyah Tangerang
Page 69
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

X SISTEM KOMUNIKASI DATA / LOCAL AREA NETWORK (LAN)


A Peralatan Utama Sistem Komunikasi Data / LAN
A.1 Ruang Server
1 Core Switch Catalyst WS-C3750X-24 T-L ls 1.00 125,000,000.00 125,000,000.00
- Catalyst 3750 24 Ethernet 10/100/1000
- 2T/SFP LAN Base Image
- Modular 4x1GE, 2x10GE, 2 x 10GB-T, and Service Module with two 10 GE SFP+ Interfaces
2 Reuter Bandwidth management ls 1.00 175,000,000.00 175,000,000.00
- Cisco 1941, 2GE, 2EHWIC, IP Base, 512DRAM
3 Racking System
- 19" Wallmounted Rack 24U, depth 381mm, include, set 1.00 78,000,000.00 78,000,000.00
- 1ea power outlet 6 socket, 1ea Dual Roof Fan, Cage Nut
- including wiring management, support rack & accessories
4 Vertical Sub System
5 Avaya Multimode FO 4 Core 50 Um, Laserspeed,
- FO 4 Core 50 Um, Laserspeed, dari ke Server ke Switch Lantai Ground m 30.00 900,000.00 27,000,000.00
- FO 4 Core 50 Um, Laserspeed, dari ke Server ke Switch Lantai 6 m 60.00 900,000.00 54,000,000.00
- FO 4 Core 50 Um, Laserspeed, dari ke Server ke Switch Lantai 7 m 90.00 900,000.00 81,000,000.00
- FO 4 Core 50 Um, Laserspeed, dari ke Server ke Switch Lantai 8 m 66.00 900,000.00 59,400,000.00
- FO 4 Core 50 Um, Laserspeed, dari ke Server ke Switch Lantai 9 m 72.00 900,000.00 64,800,000.00
- FO 4 Core 50 Um, Laserspeed, dari ke Server ke Switch Lantai 10 m 78.00 900,000.00 70,200,000.00
- FO 4 Core 50 Um, Laserspeed, dari ke Server ke Switch Lantai 11 m 84.00 900,000.00 75,600,000.00
- FO 4 Core 50 Um, Laserspeed, dari ke Server ke Switch Lantai 12 m 90.00 900,000.00 81,000,000.00
- FO 4 Core 50 Um, Laserspeed, dari ke Server ke Switch Lantai 13 m 96.00 900,000.00 86,400,000.00
- FO 4 Core 50 Um, Laserspeed, dari ke Server ke Switch Lantai 14 m 102.00 900,000.00 91,800,000.00
- FO 4 Core 50 Um, Laserspeed, dari ke Server ke Switch Lantai 15 m 108.00 900,000.00 97,200,000.00
- FO 4 Core 50 Um, Laserspeed, dari ke Server ke Switch Lantai 16 m 114.00 900,000.00 102,600,000.00
- FO 4 Core 50 Um, Laserspeed, dari ke Server ke Switch Lantai 17 m 120.00 900,000.00 108,000,000.00
- FO 4 Core 50 Um, Laserspeed, dari ke Server ke Switch Lantai 18 m 126.00 900,000.00 113,400,000.00
- FO 4 Core 50 Um, Laserspeed, dari ke Server ke Switch Lantai 19 m 132.00 900,000.00 118,800,000.00
Sub Total Ruang Server 1,609,200,000.00
A.2 FO & UTP Termination
1 FO patch panel set 1.00 37,000,000.00 37,000,000.00
2 FO patch cord 10 feet bh 4.00 45,000,000.00 180,000,000.00
3 UTP patch panel bh 2.00 21,000,000.00 42,000,000.00
4 UTP patch cord 4 feet bh 75.00 7,500,000.00 562,500,000.00
5 UTP patch cord 10 feet bh 4.00 14,000,000.00 56,000,000.00
6 Supporting Material ls 1.00 15,000,000.00 15,000,000.00
7 UPS 2000 VA ls 1.00 17,500,000.00 17,500,000.00
8 Professional Service lot 1.00 45,000,000.00 45,000,000.00
- Biaya Pemindahan
- Installation Fiber Optic
- Termination Fiber Optic
- Civil Work
- Testing and Commissioning
- Documentaton
9 Grounding System + Surge Arrester unit 1.00 17,500,000.00 17,500,000.00
10 Testing comissioning ls 1.00 15,000,000.00 15,000,000.00
Sub Total Peralatan Utama Sistem Komunikasi Data / LAN 987,500,000.00
B INSTALASI KABEL & OUTLET LAN/JARINGAN DATA
B.1 Instalasi LAN/Jaringan Data Lantai Ground
1 Outlet data RJ45 Wallmount, inbouw flush type ttk 4.00 175,000.00 700,000.00
Dual-Band Wireless N Access Point, 802.11b/g/n, 270Mbps
2 bh 4.00 9,000,000.00 36,000,000.00
3 Instalasi kabel data UTP Cat 6, termasuk ttk 8.00 680,000.00 5,440,000.00
- kabel UTP CAT 6, include port connector

Rincian RAB MEP (Sistem LAN)


Universitas Muhammadiyah Tangerang
Page 70
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

- kabel duct, ties, dan klem


4 Patch Panel 24 port UTP Cat.6 bh 1.00 4,500,000.00 4,500,000.00
5 UTP patch cord 4 feet bh 9.00 7,500,000.00 67,500,000.00
6 Access Switch Catalyst WS-C2960-24 TC-S unit 1.00 23,000,000.00 23,000,000.00
- 24 Ethernet 10/100Base- TX ports, 2 x SFP 10/100/1000Base-T Port
7 Racking System
- 19" Wallmounted Rack 6U, depth 381mm, include, set 1.00 16,000,000.00 16,000,000.00
- 1ea power outlet 6 socket, 1ea Dual Roof Fan, Cage Nut
- including wiring management, support rack & accessories
Sub Total Instalasi LAN/Jaringan Data Lantai Ground 153,140,000.00
B.2 Instalasi LAN/Jaringan Data Lantai 6-7
1 Outlet data RJ45 Wallmount, inbouw flush type ttk 1.00 175,000.00 175,000.00
Dual-Band Wireless N Access Point, 802.11b/g/n, 270Mbps
2 bh 10.00 9,000,000.00 90,000,000.00
3 Instalasi kabel data UTP Cat 6, termasuk ttk 11.00 680,000.00 7,480,000.00
- kabel UTP CAT 6, include port connector
- kabel duct, ties, dan klem
4 Patch Panel 24 port UTP Cat.6 bh 1.00 4,500,000.00 4,500,000.00
5 UTP patch cord 4 feet bh 12.00 7,500,000.00 90,000,000.00
6 Access Switch Catalyst WS-C2960-24 TC-S unit 2.00 23,000,000.00 46,000,000.00
- 24 Ethernet 10/100Base- TX ports, 2 x SFP 10/100/1000Base-T Port
7 Racking System
- 19" Wallmounted Rack 6U, depth 381mm, include, set 2.00 16,000,000.00 32,000,000.00
- 1ea power outlet 6 socket, 1ea Dual Roof Fan, Cage Nut
- including wiring management, support rack & accessories
Sub Total Instalasi LAN/Jaringan Data Lantai 6-7 270,155,000.00
B.3 Instalasi LAN/Jaringan Data Lantai 8
1 Outlet data RJ45 Wallmount, inbouw flush type ttk 10.00 175,000.00 1,750,000.00
Dual-Band Wireless N Access Point, 802.11b/g/n, 270Mbps
2 bh 1.00 9,000,000.00 9,000,000.00
3 Instalasi kabel data UTP Cat 6, termasuk ttk 11.00 680,000.00 7,480,000.00
- kabel UTP CAT 6, include port connector
- kabel duct, ties, dan klem
4 Patch Panel 24 port UTP Cat.6 bh 1.00 4,500,000.00 4,500,000.00
5 UTP patch cord 4 feet bh 12.00 7,500,000.00 90,000,000.00
6 Access Switch Catalyst WS-C2960-24 TC-S unit 1.00 23,000,000.00 23,000,000.00
- 24 Ethernet 10/100Base- TX ports, 2 x SFP 10/100/1000Base-T Port
7 Racking System
- 19" Wallmounted Rack 6U, depth 381mm, include, set 1.00 16,000,000.00 16,000,000.00
- 1ea power outlet 6 socket, 1ea Dual Roof Fan, Cage Nut
- including wiring management, support rack & accessories
Sub Total Instalasi LAN/Jaringan Data Lantai 8 151,730,000.00
B.4 Instalasi LAN/Jaringan Data Lantai 9
1 Outlet data RJ45 Wallmount, inbouw flush type ttk 10.00 175,000.00 1,750,000.00
Dual-Band Wireless N Access Point, 802.11b/g/n, 270Mbps
2 bh 1.00 9,000,000.00 9,000,000.00
3 Instalasi kabel data UTP Cat 6, termasuk ttk 11.00 680,000.00 7,480,000.00
- kabel UTP CAT 6, include port connector
- kabel duct, ties, dan klem
4 Patch Panel 24 port UTP Cat.6 bh 1.00 4,500,000.00 4,500,000.00
5 UTP patch cord 4 feet bh 12.00 7,500,000.00 90,000,000.00
6 Access Switch Catalyst WS-C2960-24 TC-S unit 1.00 23,000,000.00 23,000,000.00
- 24 Ethernet 10/100Base- TX ports, 2 x SFP 10/100/1000Base-T Port
7 Racking System
- 19" Wallmounted Rack 6U, depth 381mm, include, set 1.00 16,000,000.00 16,000,000.00
- 1ea power outlet 6 socket, 1ea Dual Roof Fan, Cage Nut
- including wiring management, support rack & accessories
Sub Total Instalasi LAN/Jaringan Data Lantai 9 151,730,000.00
B.5 Instalasi LAN/Jaringan Data Lantai 10

Rincian RAB MEP (Sistem LAN)


Universitas Muhammadiyah Tangerang
Page 71
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

1 Outlet data RJ45 Wallmount, inbouw flush type ttk 10.00 175,000.00 1,750,000.00
Dual-Band Wireless N Access Point, 802.11b/g/n, 270Mbps
2 bh 1.00 9,000,000.00 9,000,000.00
3 Instalasi kabel data UTP Cat 6, termasuk ttk 11.00 680,000.00 7,480,000.00
- kabel UTP CAT 6, include port connector
- kabel duct, ties, dan klem
4 Patch Panel 24 port UTP Cat.6 bh 1.00 4,500,000.00 4,500,000.00
5 UTP patch cord 4 feet bh 12.00 7,500,000.00 90,000,000.00
6 Access Switch Catalyst WS-C2960-24 TC-S unit 1.00 23,000,000.00 23,000,000.00
- 24 Ethernet 10/100Base- TX ports, 2 x SFP 10/100/1000Base-T Port
7 Racking System
- 19" Wallmounted Rack 6U, depth 381mm, include, set 1.00 16,000,000.00 16,000,000.00
- 1ea power outlet 6 socket, 1ea Dual Roof Fan, Cage Nut
- including wiring management, support rack & accessories
Sub Total Instalasi LAN/Jaringan Data Lantai 10 151,730,000.00
B.6 Instalasi LAN/Jaringan Data Lantai 11
1 Outlet data RJ45 Wallmount, inbouw flush type ttk 10.00 175,000.00 1,750,000.00
Dual-Band Wireless N Access Point, 802.11b/g/n, 270Mbps
2 bh 1.00 9,000,000.00 9,000,000.00
3 Instalasi kabel data UTP Cat 6, termasuk ttk 11.00 680,000.00 7,480,000.00
- kabel UTP CAT 6, include port connector
- kabel duct, ties, dan klem
4 Patch Panel 24 port UTP Cat.6 bh 1.00 4,500,000.00 4,500,000.00
5 UTP patch cord 4 feet bh 12.00 7,500,000.00 90,000,000.00
6 Access Switch Catalyst WS-C2960-24 TC-S unit 1.00 23,000,000.00 23,000,000.00
- 24 Ethernet 10/100Base- TX ports, 2 x SFP 10/100/1000Base-T Port
7 Racking System
- 19" Wallmounted Rack 6U, depth 381mm, include, set 1.00 16,000,000.00 16,000,000.00
- 1ea power outlet 6 socket, 1ea Dual Roof Fan, Cage Nut
- including wiring management, support rack & accessories
Sub Total Instalasi LAN/Jaringan Data Lantai 11 151,730,000.00
B.7 Instalasi LAN/Jaringan Data Lantai 12
1 Outlet data RJ45 Wallmount, inbouw flush type ttk 10.00 175,000.00 1,750,000.00
Dual-Band Wireless N Access Point, 802.11b/g/n, 270Mbps
2 bh 1.00 9,000,000.00 9,000,000.00
3 Instalasi kabel data UTP Cat 6, termasuk ttk 11.00 680,000.00 7,480,000.00
- kabel UTP CAT 6, include port connector
- kabel duct, ties, dan klem
4 Patch Panel 24 port UTP Cat.6 bh 1.00 4,500,000.00 4,500,000.00
5 UTP patch cord 4 feet bh 12.00 7,500,000.00 90,000,000.00
6 Access Switch Catalyst WS-C2960-24 TC-S unit 1.00 23,000,000.00 23,000,000.00
- 24 Ethernet 10/100Base- TX ports, 2 x SFP 10/100/1000Base-T Port
7 Racking System
- 19" Wallmounted Rack 6U, depth 381mm, include, set 1.00 16,000,000.00 16,000,000.00
- 1ea power outlet 6 socket, 1ea Dual Roof Fan, Cage Nut
- including wiring management, support rack & accessories
Sub Total Instalasi LAN/Jaringan Data Lantai 12 151,730,000.00
B.8 Instalasi LAN/Jaringan Data Lantai 13
1 Outlet data RJ45 Wallmount, inbouw flush type ttk 10.00 175,000.00 1,750,000.00
Dual-Band Wireless N Access Point, 802.11b/g/n, 270Mbps
2 bh 1.00 9,000,000.00 9,000,000.00
3 Instalasi kabel data UTP Cat 6, termasuk ttk 11.00 680,000.00 7,480,000.00
- kabel UTP CAT 6, include port connector
- kabel duct, ties, dan klem
4 Patch Panel 24 port UTP Cat.6 bh 1.00 4,500,000.00 4,500,000.00
5 UTP patch cord 4 feet bh 12.00 7,500,000.00 90,000,000.00
6 Access Switch Catalyst WS-C2960-24 TC-S unit 1.00 23,000,000.00 23,000,000.00
- 24 Ethernet 10/100Base- TX ports, 2 x SFP 10/100/1000Base-T Port
7 Racking System
- 19" Wallmounted Rack 6U, depth 381mm, include, set 1.00 16,000,000.00 16,000,000.00

Rincian RAB MEP (Sistem LAN)


Universitas Muhammadiyah Tangerang
Page 72
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

- 1ea power outlet 6 socket, 1ea Dual Roof Fan, Cage Nut
- including wiring management, support rack & accessories
Sub Total Instalasi LAN/Jaringan Data Lantai 13 151,730,000.00
B.9 Instalasi LAN/Jaringan Data Lantai 14
1 Outlet data RJ45 Wallmount, inbouw flush type ttk 10.00 175,000.00 1,750,000.00
Dual-Band Wireless N Access Point, 802.11b/g/n, 270Mbps
2 bh 1.00 9,000,000.00 9,000,000.00
3 Instalasi kabel data UTP Cat 6, termasuk ttk 11.00 680,000.00 7,480,000.00
- kabel UTP CAT 6, include port connector
- kabel duct, ties, dan klem
4 Patch Panel 24 port UTP Cat.6 bh 1.00 4,500,000.00 4,500,000.00
5 UTP patch cord 4 feet bh 12.00 7,500,000.00 90,000,000.00
6 Access Switch Catalyst WS-C2960-24 TC-S unit 1.00 23,000,000.00 23,000,000.00
- 24 Ethernet 10/100Base- TX ports, 2 x SFP 10/100/1000Base-T Port
7 Racking System
- 19" Wallmounted Rack 6U, depth 381mm, include, set 1.00 16,000,000.00 16,000,000.00
- 1ea power outlet 6 socket, 1ea Dual Roof Fan, Cage Nut
- including wiring management, support rack & accessories
Sub Total Instalasi LAN/Jaringan Data Lantai 14 151,730,000.00
B.10 Instalasi LAN/Jaringan Data Lantai 15
1 Outlet data RJ45 Wallmount, inbouw flush type ttk 10.00 175,000.00 1,750,000.00
Dual-Band Wireless N Access Point, 802.11b/g/n, 270Mbps
2 bh 1.00 9,000,000.00 9,000,000.00
3 Instalasi kabel data UTP Cat 6, termasuk ttk 11.00 680,000.00 7,480,000.00
- kabel UTP CAT 6, include port connector
- kabel duct, ties, dan klem
4 Patch Panel 24 port UTP Cat.6 bh 1.00 4,500,000.00 4,500,000.00
5 UTP patch cord 4 feet bh 12.00 7,500,000.00 90,000,000.00
6 Access Switch Catalyst WS-C2960-24 TC-S unit 1.00 23,000,000.00 23,000,000.00
- 24 Ethernet 10/100Base- TX ports, 2 x SFP 10/100/1000Base-T Port
7 Racking System
- 19" Wallmounted Rack 6U, depth 381mm, include, set 1.00 16,000,000.00 16,000,000.00
- 1ea power outlet 6 socket, 1ea Dual Roof Fan, Cage Nut
- including wiring management, support rack & accessories
Sub Total Instalasi LAN/Jaringan Data Lantai 15 151,730,000.00
B.11 Instalasi LAN/Jaringan Data Lantai 16
1 Outlet data RJ45 Wallmount, inbouw flush type ttk 10.00 175,000.00 1,750,000.00
Dual-Band Wireless N Access Point, 802.11b/g/n, 270Mbps
2 bh 1.00 9,000,000.00 9,000,000.00
3 Instalasi kabel data UTP Cat 6, termasuk ttk 11.00 680,000.00 7,480,000.00
- kabel UTP CAT 6, include port connector
- kabel duct, ties, dan klem
4 Patch Panel 24 port UTP Cat.6 bh 1.00 4,500,000.00 4,500,000.00
5 UTP patch cord 4 feet bh 12.00 7,500,000.00 90,000,000.00
6 Access Switch Catalyst WS-C2960-24 TC-S unit 1.00 23,000,000.00 23,000,000.00
- 24 Ethernet 10/100Base- TX ports, 2 x SFP 10/100/1000Base-T Port
7 Racking System
- 19" Wallmounted Rack 6U, depth 381mm, include, set 1.00 16,000,000.00 16,000,000.00
- 1ea power outlet 6 socket, 1ea Dual Roof Fan, Cage Nut
- including wiring management, support rack & accessories
Sub Total Instalasi LAN/Jaringan Data Lantai 16 151,730,000.00
B.12 Instalasi LAN/Jaringan Data Lantai 17
1 Outlet data RJ45 Wallmount, inbouw flush type ttk 10.00 175,000.00 1,750,000.00
Dual-Band Wireless N Access Point, 802.11b/g/n, 270Mbps
2 bh 1.00 9,000,000.00 9,000,000.00
3 Instalasi kabel data UTP Cat 6, termasuk ttk 11.00 680,000.00 7,480,000.00
- kabel UTP CAT 6, include port connector
- kabel duct, ties, dan klem
4 Patch Panel 24 port UTP Cat.6 bh 1.00 4,500,000.00 4,500,000.00
5 UTP patch cord 4 feet bh 12.00 7,500,000.00 90,000,000.00

Rincian RAB MEP (Sistem LAN)


Universitas Muhammadiyah Tangerang
Page 73
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

6 Access Switch Catalyst WS-C2960-24 TC-S unit 1.00 23,000,000.00 23,000,000.00


- 24 Ethernet 10/100Base- TX ports, 2 x SFP 10/100/1000Base-T Port
7 Racking System
- 19" Wallmounted Rack 6U, depth 381mm, include, set 1.00 16,000,000.00 16,000,000.00
- 1ea power outlet 6 socket, 1ea Dual Roof Fan, Cage Nut
- including wiring management, support rack & accessories
Sub Total Instalasi LAN/Jaringan Data Lantai 17 151,730,000.00
B.13 Instalasi LAN/Jaringan Data Lantai 18
1 Outlet data RJ45 Wallmount, inbouw flush type ttk 10.00 175,000.00 1,750,000.00
Dual-Band Wireless N Access Point, 802.11b/g/n, 270Mbps
2 bh 1.00 9,000,000.00 9,000,000.00
3 Instalasi kabel data UTP Cat 6, termasuk ttk 11.00 680,000.00 7,480,000.00
- kabel UTP CAT 6, include port connector
- kabel duct, ties, dan klem
4 Patch Panel 24 port UTP Cat.6 bh 1.00 4,500,000.00 4,500,000.00
5 UTP patch cord 4 feet bh 12.00 7,500,000.00 90,000,000.00
6 Access Switch Catalyst WS-C2960-24 TC-S unit 1.00 23,000,000.00 23,000,000.00
- 24 Ethernet 10/100Base- TX ports, 2 x SFP 10/100/1000Base-T Port
7 Racking System
- 19" Wallmounted Rack 6U, depth 381mm, include, set 1.00 16,000,000.00 16,000,000.00
- 1ea power outlet 6 socket, 1ea Dual Roof Fan, Cage Nut
- including wiring management, support rack & accessories
Sub Total Instalasi LAN/Jaringan Data Lantai 18 151,730,000.00
B.14 Instalasi LAN/Jaringan Data Lantai 19
1 Outlet data RJ45 Wallmount, inbouw flush type ttk 4.00 175,000.00 700,000.00
Dual-Band Wireless N Access Point, 802.11b/g/n, 270Mbps
2 bh 4.00 9,000,000.00 36,000,000.00
3 Instalasi kabel data UTP Cat 6, termasuk ttk 8.00 680,000.00 5,440,000.00
- kabel UTP CAT 6, include port connector
- kabel duct, ties, dan klem
4 Patch Panel 24 port UTP Cat.6 bh 1.00 4,500,000.00 4,500,000.00
5 UTP patch cord 4 feet bh 9.00 7,500,000.00 67,500,000.00
6 Access Switch Catalyst WS-C2960-24 TC-S unit 1.00 23,000,000.00 23,000,000.00
- 24 Ethernet 10/100Base- TX ports, 2 x SFP 10/100/1000Base-T Port
7 Racking System
- 19" Wallmounted Rack 6U, depth 381mm, include, set 1.00 16,000,000.00 16,000,000.00
- 1ea power outlet 6 socket, 1ea Dual Roof Fan, Cage Nut
- including wiring management, support rack & accessories
Sub Total Instalasi LAN/Jaringan Data Lantai 19 153,140,000.00

TOTAL SISTEM KOMUNIKASI DATA / LOCAL AREA NETWORK (LAN) 4,842,165,000.00

Rincian RAB MEP (Sistem LAN)


Universitas Muhammadiyah Tangerang
Page 74
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

XV SISTEM PENYALUR PETIR


Instalasi Penyalur Petir
1 Streamer system, 1 spit unit terminal. unit 1.00 75,000,000.00 75,000,000.00
- Radius proteksi minimal 150 meter
- Dilengkapi tiang penyangga pipa GIP, tinggi tiang 2000cm
- Dilengkapi lampu suar/lamp probe
- Dilengkapi lightning counter
2 Down Conductor Coaxial Cable 70mm2 m 170.00 75,000.00 12,750,000.00
3 Connecting sleeve unit 2.00 3,200,000.00 6,400,000.00
4 Klem & Aksesoris bh 340.00 800,000.00 272,000,000.00
5 Grounding dg tahanan pentanahan minimal 2 Ohm
- Dengan galian sumuran mencapai air tanah ttk 2.00 20,000,000.00 40,000,000.00
- Kawat BC 2x35mm2 dan Pipa GIP 1" pjg=2m, + Ground rood bh 2.00 27,000,000.00 54,000,000.00
- Panjang kawat dan pipa menyesuaikan sumuran
6 Bak kontrol bh 4.00 4,500,000.00 18,000,000.00
7 Peralatan bantu lot 1.00 5,000,000.00 5,000,000.00
8 Testing Comissioning ls 1.00 15,000,000.00 15,000,000.00
Sub Total Instalasi Penyalur Petir 498,150,000.00

TOTAL SISTEM PENYALUR PETIR 498,150,000.00

Rincian RAB MEP (Sistem Penyalur Petir)


Universitas Muhammadiyah Tangerang
Page 75
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

XIV SISTEM CCTV (CLOSED CIRCUIT TELEVISION)


A Peralatan Utama
Pengadaan dan pemasangan peralatan utama CCTV, lengkap terpasang dengan alat bantu dan accessories
1 Network Video Recorder (DVR) System unit 4.00 45,000,000.00 180,000,000.00
- Input 24 Channel Camera
- High Resolution, 720 x 480
- Data storage Hard drive 4 TB
- Recording speed at 30 fps
2 Kontrol Keyboard & Joystick unit 1.00 3,500,000.00 3,500,000.00
3 Colour monitor LED 22 " unit 4.00 5,800,000.00 23,200,000.00
4 Video Manager set 1.00 18,000,000.00 18,000,000.00
5 UPS 2 KVA, 30 menit unit 1.00 17,500,000.00 17,500,000.00
6 Rak Peralatan CCTV, 19", 32U unit 1.00 18,000,000.00 18,000,000.00
- Front glass door
- Key & lock
- 3x5 power outlet
7 Meja Console CCTV unit 1.00 4,000,000.00 4,000,000.00
8 Grounding + Surge Aresster ls 1.00 9,000,000.00 9,000,000.00
9 Test & Comissioning ls 1.00 15,000,000.00 15,000,000.00
Sub Total Peralatan Utama 288,200,000.00
B Instalasi Kabel Utama & CTB
1 NYM 3 x 2,5 mm² dalam PVC Conduit ø 3/4 " dari Main equipment ke CTB m 162.00 580,000.00 93,960,000.00
2 UTP CAT 6 dalam PVC Conduit ø 3/4 " dari Main equipment ke CTB m 1,920.00 11,500.00 22,080,000.00
3 UTP CAT 6 dalam PVC Conduit ø 3/4 " dari Main equipment ke CTB m 1,920.00 11,500.00 22,080,000.00
4 UTP CAT 6 dalam PVC Conduit ø 3/4 " dari Main equipment ke CTB m 1,920.00 11,500.00 22,080,000.00
5 UTP CAT 6 dalam PVC Conduit ø 3/4 " dari Main equipment ke CTB m 1,920.00 11,500.00 22,080,000.00
6 UTP CAT 6 dalam PVC Conduit ø 3/4 " dari Main equipment ke CTB m 1,920.00 11,500.00 22,080,000.00
7 Camera Terminal Box (CTB) unit 19.00 5,500.00 104,500.00
Sub Total Instalasi Kabel Utama & CTB 204,464,500.00
C Instalasi Switch Hub
1 Access Switch Catalyst WS-C2960-24 TC-S unit 6.0 23,000,000.00 138,000,000.00
- 24 Ethernet 10/100Base- TX ports, 2 x SFP 10/100/1000Base-T Port
2 Racking System
- 19" Wallmounted Rack 6U, depth 381mm, include, set 6.0 16,000,000.00 96,000,000.00
- 1ea power outlet 6 socket, 1ea Dual Roof Fan, Cage Nut
- including wiring management, support rack & accessories
Sub Total Instalasi Switch Hub 234,000,000.00
C Camera dan Instalasi Pengkabelan CCTV
Pengadaan dan pemasangan instalasi CCTV, lengkap terpasang
C.1 Instalasi CCTV Lantai Basement 1
1 Colour Indoor Dome Camera, Day/Night (NTSC, PAL) unit 1.00 5,500,000.00 5,500,000.00
2 Colour Indoor Fixed Bullet Camera, Day/Night, c/w housing unit 2.00 4,000,000.00 8,000,000.00
3 Instalasi camera, kabel NYM 2 x 1,5 mm² & UTP CAT 5E dalam PVC Conduit ø 3/4 " ttk 3.00 650,000.00 1,950,000.00
Sub Total Instalasi CCTV Lantai Basement 1 15,450,000.00
C.2 Instalasi CCTV Lantai Ground
1 Colour Indoor Dome Camera, Day/Night (NTSC, PAL) unit 7.00 4,000,000.00 28,000,000.00
2 Instalasi camera, kabel NYM 2 x 1,5 mm² & UTP CAT 5E dalam PVC Conduit ø 3/4 " ttk 7.00 650,000.00 4,550,000.00
Sub Total Instalasi CCTV Lantai Ground 32,550,000.00
C.3 Instalasi CCTV Lantai 1
1 Colour Indoor Dome Camera, Day/Night (NTSC, PAL) unit 5.00 4,000,000.00 20,000,000.00
2 Instalasi camera, kabel NYM 2 x 1,5 mm² & UTP CAT 5E dalam PVC Conduit ø 3/4 " ttk 5.00 650,000.00 3,250,000.00
Sub Total Instalasi CCTV Lantai 1 23,250,000.00
C.4 Instalasi CCTV Lantai 2
1 Colour Indoor Dome Camera, Day/Night (NTSC, PAL) unit 6.00 4,000,000.00 24,000,000.00
2 Instalasi camera, kabel NYM 2 x 1,5 mm² & UTP CAT 5E dalam PVC Conduit ø 3/4 " ttk 6.00 650,000.00 3,900,000.00
Sub Total Instalasi CCTV Lantai 2 27,900,000.00
C.5 Instalasi CCTV Lantai 3

Rincian RAB MEP (Sistem CCTV)


Universitas Muhammadiyah Tangerang
Page 76
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

1 Colour Indoor Dome Camera, Day/Night (NTSC, PAL) unit 6.00 4,000,000.00 24,000,000.00
2 Instalasi camera, kabel NYM 2 x 1,5 mm² & UTP CAT 5E dalam PVC Conduit ø 3/4 " ttk 6.00 650,000.00 3,900,000.00
Sub Total Instalasi CCTV Lantai 3 27,900,000.00
C.6 Instalasi CCTV Lantai 4
1 Colour Indoor Dome Camera, Day/Night (NTSC, PAL) unit 6.00 4,000,000.00 24,000,000.00
2 Instalasi camera, kabel NYM 2 x 1,5 mm² & UTP CAT 5E dalam PVC Conduit ø 3/4 " ttk 6.00 650,000.00 3,900,000.00
Sub Total Instalasi CCTV Lantai 4 27,900,000.00
C.7 Instalasi CCTV Lantai 5
1 Colour Indoor Dome Camera, Day/Night (NTSC, PAL) unit 6.00 4,000,000.00 24,000,000.00
2 Instalasi camera, kabel NYM 2 x 1,5 mm² & UTP CAT 5E dalam PVC Conduit ø 3/4 " ttk 6.00 650,000.00 3,900,000.00
Sub Total Instalasi CCTV Lantai 5 27,900,000.00
C.8 Instalasi CCTV Lantai 6
1 Colour Indoor Dome Camera, Day/Night (NTSC, PAL) unit 6.00 4,000,000.00 24,000,000.00
2 Instalasi camera, kabel NYM 2 x 1,5 mm² & UTP CAT 5E dalam PVC Conduit ø 3/4 " ttk 6.00 650,000.00 3,900,000.00
Sub Total Instalasi CCTV Lantai 6 27,900,000.00
C.9 Instalasi CCTV Lantai 7
1 Colour Indoor Dome Camera, Day/Night (NTSC, PAL) unit 6.00 4,000,000.00 24,000,000.00
2 Instalasi camera, kabel NYM 2 x 1,5 mm² & UTP CAT 5E dalam PVC Conduit ø 3/4 " ttk 6.00 650,000.00 3,900,000.00
Sub Total Instalasi CCTV Lantai 7 27,900,000.00
C.10 Instalasi CCTV Lantai 8
1 Colour Indoor Dome Camera, Day/Night (NTSC, PAL) unit 4.00 4,000,000.00 16,000,000.00
2 Instalasi camera, kabel NYM 2 x 1,5 mm² & UTP CAT 5E dalam PVC Conduit ø 3/4 " ttk 4.00 650,000.00 2,600,000.00
Sub Total Instalasi CCTV Lantai 8 18,600,000.00
C.11 Instalasi CCTV Lantai 9
1 Colour Indoor Dome Camera, Day/Night (NTSC, PAL) unit 4.00 4,000,000.00 16,000,000.00
2 Instalasi camera, kabel NYM 2 x 1,5 mm² & UTP CAT 5E dalam PVC Conduit ø 3/4 " ttk 4.00 650,000.00 2,600,000.00
Sub Total Instalasi CCTV Lantai 9 18,600,000.00
C.12 Instalasi CCTV Lantai 10
1 Colour Indoor Dome Camera, Day/Night (NTSC, PAL) unit 4.00 4,000,000.00 16,000,000.00
2 Instalasi camera, kabel NYM 2 x 1,5 mm² & UTP CAT 5E dalam PVC Conduit ø 3/4 " ttk 4.00 650,000.00 2,600,000.00
Sub Total Instalasi CCTV Lantai 10 18,600,000.00
C.13 Instalasi CCTV Lantai 11
1 Colour Indoor Dome Camera, Day/Night (NTSC, PAL) unit 4.00 4,000,000.00 16,000,000.00
2 Instalasi camera, kabel NYM 2 x 1,5 mm² & UTP CAT 5E dalam PVC Conduit ø 3/4 " ttk 4.00 650,000.00 2,600,000.00
Sub Total Instalasi CCTV Lantai 11 18,600,000.00
C.14 Instalasi CCTV Lantai 12
1 Colour Indoor Dome Camera, Day/Night (NTSC, PAL) unit 4.00 4,000,000.00 16,000,000.00
2 Instalasi camera, kabel NYM 2 x 1,5 mm² & UTP CAT 5E dalam PVC Conduit ø 3/4 " ttk 4.00 650,000.00 2,600,000.00
Sub Total Instalasi CCTV Lantai 12 18,600,000.00
C.15 Instalasi CCTV Lantai 13
1 Colour Indoor Dome Camera, Day/Night (NTSC, PAL) unit 4.00 4,000,000.00 16,000,000.00
2 Instalasi camera, kabel NYM 2 x 1,5 mm² & UTP CAT 5E dalam PVC Conduit ø 3/4 " ttk 4.00 650,000.00 2,600,000.00
Sub Total Instalasi CCTV Lantai 13 18,600,000.00
C.16 Instalasi CCTV Lantai 14
1 Colour Indoor Dome Camera, Day/Night (NTSC, PAL) unit 4.00 4,000,000.00 16,000,000.00
2 Instalasi camera, kabel NYM 2 x 1,5 mm² & UTP CAT 5E dalam PVC Conduit ø 3/4 " ttk 4.00 650,000.00 2,600,000.00
Sub Total Instalasi CCTV Lantai 14 18,600,000.00
C.17 Instalasi CCTV Lantai 15
1 Colour Indoor Dome Camera, Day/Night (NTSC, PAL) unit 4.00 4,000,000.00 16,000,000.00
2 Instalasi camera, kabel NYM 2 x 1,5 mm² & UTP CAT 5E dalam PVC Conduit ø 3/4 " ttk 4.00 650,000.00 2,600,000.00
Sub Total Instalasi CCTV Lantai 15 18,600,000.00
C.18 Instalasi CCTV Lantai 16
1 Colour Indoor Dome Camera, Day/Night (NTSC, PAL) unit 4.00 4,000,000.00 16,000,000.00
2 Instalasi camera, kabel NYM 2 x 1,5 mm² & UTP CAT 5E dalam PVC Conduit ø 3/4 " ttk 4.00 650,000.00 2,600,000.00
Sub Total Instalasi CCTV Lantai 16 18,600,000.00
C.19 Instalasi CCTV Lantai 17
1 Colour Indoor Dome Camera, Day/Night (NTSC, PAL) unit 4.00 4,000,000.00 16,000,000.00
2 Instalasi camera, kabel NYM 2 x 1,5 mm² & UTP CAT 5E dalam PVC Conduit ø 3/4 " ttk 4.00 650,000.00 2,600,000.00
Sub Total Instalasi CCTV Lantai 17 18,600,000.00

Rincian RAB MEP (Sistem CCTV)


Universitas Muhammadiyah Tangerang
Page 77
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

C.20 Instalasi CCTV Lantai 18


1 Colour Indoor Dome Camera, Day/Night (NTSC, PAL) unit 4.00 4,000,000.00 16,000,000.00
2 Instalasi camera, kabel NYM 2 x 1,5 mm² & UTP CAT 5E dalam PVC Conduit ø 3/4 " ttk 4.00 650,000.00 2,600,000.00
Sub Total Instalasi CCTV Lantai 18 18,600,000.00
C.21 Instalasi CCTV Lantai 19
1 Colour Indoor Dome Camera, Day/Night (NTSC, PAL) unit 3.00 4,000,000.00 12,000,000.00
2 Instalasi camera, kabel NYM 2 x 1,5 mm² & UTP CAT 5E dalam PVC Conduit ø 3/4 " ttk 3.00 650,000.00 1,950,000.00
Sub Total Instalasi CCTV Lantai 19 13,950,000.00
C.22 Instalasi CCTV dalam LIFT
1 Colour Indoor Dome Camera, Day/Night (NTSC, PAL) unit 6.00 4,000,000.00 24,000,000.00
2 Instalasi camera, kabel NYM 2 x 1,5 mm² & UTP CAT 5E dalam PVC Conduit ø 3/4 " ttk 6.00 650,000.00 3,900,000.00
Sub Total Instalasi CCTV dalam LIFT 27,900,000.00

TOTAL SISTEM CCTV (CLOSED CIRCUIT TELEVISION) 1,211,764,500.00

Rincian RAB MEP (Sistem CCTV)


Universitas Muhammadiyah Tangerang
Page 78
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

XII INSTALASI SISTEM TATA SUARA


A Main Equipment
1 Mixer Pre Amplifier unit 1.00 75,000,000.00 75,000,000.00
2 Zone Selector 16 Zone unit 1.00 68,000,000.00 68,000,000.00
3 Emergency Mic - 6 keypad unit 1.00 22,000,000.00 22,000,000.00
4 Paging Remote Microphone bh 1.00 7,600,000.00 7,600,000.00
5 Power Amplifier 480 watt unit 10.00 5,400,000.00 54,000,000.00
6 Cassette Deck unit 1.00 4,000,000.00 4,000,000.00
7 DVD/CD/MP3 player unit 1.00 5,000,000.00 5,000,000.00
8 Battery backup 2000 VA unit 1.00 17,500,000.00 17,500,000.00
9 Power Surge Arrester unit 1.00 11,000,000.00 11,000,000.00
10 MDF c/w Speaker Selector 5 zone unit 1.00 9,000,000.00 9,000,000.00
11 Cabinet rack c/w blower unit ( Lokal ) unit 1.00 8,000,000.00 8,000,000.00
12 Kabel Feeder NYMHY 2 x 2,5 mm ls 1.00 15,000,000.00 15,000,000.00
13 Wiring, Instalasi & Alat Bantu ls 1.00 7,000,000.00 7,000,000.00
14 Testing Comissioning ls 1.00 15,000,000.00 15,000,000.00
Sub Total Main Equipment 318,100,000.00
B Instalasi Tata Suara Lantai Basement 1
Kabel NYMHY 3x1,5mm dlm PVC Conduit 20mm
1 Ceiling Speaker 6 Watt bh 7.00 980,000.00 6,860,000.00
2 Ceiling Speaker 15 Watt bh 1.00 1,400,000.00 1,400,000.00
3 Paging Box Speaker, 10 Watt bh 1.00 500,000.00 500,000.00
4 Paging Horn Speaker, 10 Watt bh 4.00 500,000.00 2,000,000.00
5 Instalasi Ceiling Speaker ttk 8.00 600,000.00 4,800,000.00
6 Instalasi Paging Horn Speaker ttk 5.00 600,000.00 3,000,000.00
7 Terminal Box SS bh 1.00 750,000.00 750,000.00
Sub Total Instalasi Tata Suara Lantai Basement 1 19,310,000.00
C Instalasi Tata Suara Lantai Ground
Kabel NYMHY 3x1,5mm dlm PVC Conduit 20mm
1 Ceiling Speaker 6 Watt bh 17.00 980,000.00 16,660,000.00
2 Paging Box Speaker, 10 Watt bh 6.00 1,200,000.00 7,200,000.00
3 Instalasi Ceiling Speaker ttk 17.00 600,000.00 10,200,000.00
4 Instalasi Paging Horn Speaker ttk 6.00 600,000.00 3,600,000.00
5 Terminal Box SS bh 1.00 750,000.00 750,000.00
Sub Total Instalasi Tata Suara Lantai Ground 38,410,000.00
D Instalasi Tata Suara Lantai 1
Kabel NYMHY 3x1,5mm dlm PVC Conduit 20mm
1 Ceiling Speaker 6 Watt bh 3.00 980,000.00 2,940,000.00
2 Paging Box Speaker, 10 Watt bh 1.00 500,000.00 500,000.00
3 Paging Horn Speaker, 10 Watt bh 4.00 500,000.00 2,000,000.00
4 Volume Control bh 1.00 800,000.00 800,000.00
5 Instalasi Ceiling Speaker ttk 3.00 600,000.00 1,800,000.00
6 Instalasi Paging Horn Speaker ttk 5.00 600,000.00 3,000,000.00
7 Instalasi Volume Control ttk 1.00 600,000.00 600,000.00
8 Terminal Box SS bh 1.00 750,000.00 750,000.00
Sub Total Instalasi Tata Suara Lantai 1 12,390,000.00
E Instalasi Tata Suara Lantai 2
Kabel NYMHY 3x1,5mm dlm PVC Conduit 20mm
1 Ceiling Speaker 6 Watt bh 3.00 980,000.00 2,940,000.00

Rincian RAB MEP (Sistem Tata Suara)


Universitas Muhammadiyah Tangerang
Page 79
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

2 Paging Box Speaker, 10 Watt bh 1.00 500,000.00 500,000.00


3 Paging Horn Speaker, 10 Watt bh 4.00 500,000.00 2,000,000.00
4 Volume Control bh 1.00 800,000.00 800,000.00
5 Instalasi Ceiling Speaker ttk 3.00 600,000.00 1,800,000.00
6 Instalasi Paging Horn Speaker ttk 5.00 600,000.00 3,000,000.00
7 Instalasi Volume Control ttk 1.00 600,000.00 600,000.00
8 Terminal Box SS bh 1.00 750,000.00 750,000.00
Sub Total Instalasi Tata Suara Lantai 2 12,390,000.00
F Instalasi Tata Suara Lantai 3
Kabel NYMHY 3x1,5mm dlm PVC Conduit 20mm
1 Ceiling Speaker 6 Watt bh 3.00 980,000.00 2,940,000.00
2 Paging Box Speaker, 10 Watt bh 1.00 500,000.00 500,000.00
3 Paging Horn Speaker, 10 Watt bh 4.00 500,000.00 2,000,000.00
4 Volume Control bh 1.00 800,000.00 800,000.00
5 Instalasi Ceiling Speaker ttk 3.00 600,000.00 1,800,000.00
6 Instalasi Paging Horn Speaker ttk 5.00 600,000.00 3,000,000.00
7 Instalasi Volume Control ttk 1.00 600,000.00 600,000.00
8 Terminal Box SS bh 1.00 750,000.00 750,000.00
Sub Total Instalasi Tata Suara Lantai 3 12,390,000.00
G Instalasi Tata Suara Lantai 4
Kabel NYMHY 3x1,5mm dlm PVC Conduit 20mm
1 Ceiling Speaker 6 Watt bh 3.00 980,000.00 2,940,000.00
2 Paging Box Speaker, 10 Watt bh 1.00 500,000.00 500,000.00
3 Paging Horn Speaker, 10 Watt bh 4.00 500,000.00 2,000,000.00
4 Volume Control bh 1.00 800,000.00 800,000.00
5 Instalasi Ceiling Speaker ttk 3.00 600,000.00 1,800,000.00
6 Instalasi Paging Horn Speaker ttk 5.00 600,000.00 3,000,000.00
7 Instalasi Volume Control ttk 1.00 600,000.00 600,000.00
8 Terminal Box SS bh 1.00 750,000.00 750,000.00
Sub Total Instalasi Tata Suara Lantai 4 12,390,000.00
H Instalasi Tata Suara Lantai 5
Kabel NYMHY 3x1,5mm dlm PVC Conduit 20mm
1 Ceiling Speaker 6 Watt bh 3.00 980,000.00 2,940,000.00
2 Paging Box Speaker, 10 Watt bh 1.00 500,000.00 500,000.00
3 Paging Horn Speaker, 10 Watt bh 4.00 500,000.00 2,000,000.00
4 Volume Control bh 1.00 800,000.00 800,000.00
5 Instalasi Ceiling Speaker ttk 3.00 600,000.00 1,800,000.00
6 Instalasi Paging Horn Speaker ttk 5.00 600,000.00 3,000,000.00
7 Instalasi Volume Control ttk 1.00 600,000.00 600,000.00
8 Terminal Box SS bh 1.00 750,000.00 750,000.00
Sub Total Instalasi Tata Suara Lantai 5 12,390,000.00
I Instalasi Tata Suara Lantai 6
Kabel NYMHY 3x1,5mm dlm PVC Conduit 20mm
1 Ceiling Speaker 6 Watt bh 31.00 980,000.00 30,380,000.00
2 Paging Box Speaker, 10 Watt bh 2.00 500,000.00 1,000,000.00
3 Volume Control bh 3.00 800,000.00 2,400,000.00
4 Instalasi Ceiling Speaker ttk 31.00 600,000.00 18,600,000.00
5 Instalasi Paging Horn Speaker ttk 2.00 600,000.00 1,200,000.00
6 Instalasi Volume Control ttk 3.00 600,000.00 1,800,000.00
7 Terminal Box SS bh 1.00 750,000.00 750,000.00

Rincian RAB MEP (Sistem Tata Suara)


Universitas Muhammadiyah Tangerang
Page 80
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

Sub Total Instalasi Tata Suara Lantai 6 56,130,000.00


J Instalasi Tata Suara Lantai 7
Kabel NYMHY 3x1,5mm dlm PVC Conduit 20mm
1 Ceiling Speaker 6 Watt bh 31.00 980,000.00 30,380,000.00
2 Paging Box Speaker, 10 Watt bh 2.00 500,000.00 1,000,000.00
3 Volume Control bh 3.00 800,000.00 2,400,000.00
4 Instalasi Ceiling Speaker ttk 31.00 600,000.00 18,600,000.00
5 Instalasi Paging Horn Speaker ttk 2.00 600,000.00 1,200,000.00
6 Instalasi Volume Control ttk 3.00 600,000.00 1,800,000.00
7 Terminal Box SS bh 1.00 750,000.00 750,000.00
Sub Total Instalasi Tata Suara Lantai 7 56,130,000.00
K Instalasi Tata Suara Lantai 8
Kabel NYMHY 3x1,5mm dlm PVC Conduit 20mm
1 Ceiling Speaker 6 Watt bh 21.00 980,000.00 20,580,000.00
2 Paging Box Speaker, 10 Watt bh 2.00 500,000.00 1,000,000.00
3 Volume Control bh 11.00 800,000.00 8,800,000.00
4 Instalasi Ceiling Speaker ttk 21.00 600,000.00 12,600,000.00
5 Instalasi Paging Horn Speaker ttk 2.00 600,000.00 1,200,000.00
6 Instalasi Volume Control ttk 11.00 600,000.00 6,600,000.00
7 Terminal Box SS bh 1.00 750,000.00 750,000.00
Sub Total Instalasi Tata Suara Lantai 8 51,530,000.00
L Instalasi Tata Suara Lantai 9
Kabel NYMHY 3x1,5mm dlm PVC Conduit 20mm
1 Ceiling Speaker 6 Watt bh 21.00 980,000.00 20,580,000.00
2 Paging Box Speaker, 10 Watt bh 2.00 500,000.00 1,000,000.00
3 Volume Control bh 11.00 800,000.00 8,800,000.00
4 Instalasi Ceiling Speaker ttk 21.00 600,000.00 12,600,000.00
5 Instalasi Paging Horn Speaker ttk 2.00 600,000.00 1,200,000.00
6 Instalasi Volume Control ttk 11.00 600,000.00 6,600,000.00
7 Terminal Box SS bh 1.00 750,000.00 750,000.00
Sub Total Instalasi Tata Suara Lantai 9 51,530,000.00
M Instalasi Tata Suara Lantai 10
Kabel NYMHY 3x1,5mm dlm PVC Conduit 20mm
1 Ceiling Speaker 6 Watt bh 21.00 980,000.00 20,580,000.00
2 Paging Box Speaker, 10 Watt bh 2.00 500,000.00 1,000,000.00
3 Volume Control bh 11.00 800,000.00 8,800,000.00
4 Instalasi Ceiling Speaker ttk 21.00 600,000.00 12,600,000.00
5 Instalasi Paging Horn Speaker ttk 2.00 600,000.00 1,200,000.00
6 Instalasi Volume Control ttk 11.00 600,000.00 6,600,000.00
7 Terminal Box SS bh 1.00 750,000.00 750,000.00
Sub Total Instalasi Tata Suara Lantai 10 51,530,000.00
N Instalasi Tata Suara Lantai 11
Kabel NYMHY 3x1,5mm dlm PVC Conduit 20mm
1 Ceiling Speaker 6 Watt bh 21.00 980,000.00 20,580,000.00
2 Paging Box Speaker, 10 Watt bh 2.00 500,000.00 1,000,000.00
3 Volume Control bh 11.00 800,000.00 8,800,000.00
4 Instalasi Ceiling Speaker ttk 21.00 600,000.00 12,600,000.00
5 Instalasi Paging Horn Speaker ttk 2.00 600,000.00 1,200,000.00
6 Instalasi Volume Control ttk 11.00 600,000.00 6,600,000.00
7 Terminal Box SS bh 1.00 750,000.00 750,000.00

Rincian RAB MEP (Sistem Tata Suara)


Universitas Muhammadiyah Tangerang
Page 81
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

Sub Total Instalasi Tata Suara Lantai 11 51,530,000.00


O Instalasi Tata Suara Lantai 12
Kabel NYMHY 3x1,5mm dlm PVC Conduit 20mm
1 Ceiling Speaker 6 Watt bh 21.00 980,000.00 20,580,000.00
2 Paging Box Speaker, 10 Watt bh 2.00 500,000.00 1,000,000.00
3 Volume Control bh 11.00 800,000.00 8,800,000.00
4 Instalasi Ceiling Speaker ttk 21.00 600,000.00 12,600,000.00
5 Instalasi Paging Horn Speaker ttk 2.00 600,000.00 1,200,000.00
6 Instalasi Volume Control ttk 11.00 600,000.00 6,600,000.00
7 Terminal Box SS bh 1.00 750,000.00 750,000.00
Sub Total Instalasi Tata Suara Lantai 12 51,530,000.00
P Instalasi Tata Suara Lantai 13
Kabel NYMHY 3x1,5mm dlm PVC Conduit 20mm
1 Ceiling Speaker 6 Watt bh 21.00 980,000.00 20,580,000.00
2 Paging Box Speaker, 10 Watt bh 2.00 500,000.00 1,000,000.00
3 Volume Control bh 11.00 800,000.00 8,800,000.00
4 Instalasi Ceiling Speaker ttk 21.00 600,000.00 12,600,000.00
5 Instalasi Paging Horn Speaker ttk 2.00 600,000.00 1,200,000.00
6 Instalasi Volume Control ttk 11.00 600,000.00 6,600,000.00
7 Terminal Box SS bh 1.00 750,000.00 750,000.00
Sub Total Instalasi Tata Suara Lantai 13 51,530,000.00
Q Instalasi Tata Suara Lantai 14
Kabel NYMHY 3x1,5mm dlm PVC Conduit 20mm
1 Ceiling Speaker 6 Watt bh 21.00 980,000.00 20,580,000.00
2 Paging Box Speaker, 10 Watt bh 2.00 500,000.00 1,000,000.00
3 Volume Control bh 11.00 800,000.00 8,800,000.00
4 Instalasi Ceiling Speaker ttk 21.00 600,000.00 12,600,000.00
5 Instalasi Paging Horn Speaker ttk 2.00 600,000.00 1,200,000.00
6 Instalasi Volume Control ttk 11.00 600,000.00 6,600,000.00
7 Terminal Box SS bh 1.00 750,000.00 750,000.00
Sub Total Instalasi Tata Suara Lantai 14 51,530,000.00
R Instalasi Tata Suara Lantai 15
Kabel NYMHY 3x1,5mm dlm PVC Conduit 20mm
1 Ceiling Speaker 6 Watt bh 21.00 980,000.00 20,580,000.00
2 Paging Box Speaker, 10 Watt bh 2.00 500,000.00 1,000,000.00
3 Volume Control bh 11.00 800,000.00 8,800,000.00
4 Instalasi Ceiling Speaker ttk 21.00 600,000.00 12,600,000.00
5 Instalasi Paging Horn Speaker ttk 2.00 600,000.00 1,200,000.00
6 Instalasi Volume Control ttk 11.00 600,000.00 6,600,000.00
7 Terminal Box SS bh 1.00 750,000.00 750,000.00
Sub Total Instalasi Tata Suara Lantai 15 51,530,000.00
S Instalasi Tata Suara Lantai 16
Kabel NYMHY 3x1,5mm dlm PVC Conduit 20mm
1 Ceiling Speaker 6 Watt bh 21.00 980,000.00 20,580,000.00
2 Paging Box Speaker, 10 Watt bh 2.00 500,000.00 1,000,000.00
3 Volume Control bh 11.00 800,000.00 8,800,000.00
4 Instalasi Ceiling Speaker ttk 21.00 600,000.00 12,600,000.00
5 Instalasi Paging Horn Speaker ttk 2.00 600,000.00 1,200,000.00
6 Instalasi Volume Control ttk 11.00 600,000.00 6,600,000.00
7 Terminal Box SS bh 1.00 750,000.00 750,000.00

Rincian RAB MEP (Sistem Tata Suara)


Universitas Muhammadiyah Tangerang
Page 82
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

Sub Total Instalasi Tata Suara Lantai 16 51,530,000.00


T Instalasi Tata Suara Lantai 17
Kabel NYMHY 3x1,5mm dlm PVC Conduit 20mm
1 Ceiling Speaker 6 Watt bh 21.00 980,000.00 20,580,000.00
2 Paging Box Speaker, 10 Watt bh 2.00 500,000.00 1,000,000.00
3 Volume Control bh 11.00 800,000.00 8,800,000.00
4 Instalasi Ceiling Speaker ttk 21.00 600,000.00 12,600,000.00
5 Instalasi Paging Horn Speaker ttk 2.00 600,000.00 1,200,000.00
6 Instalasi Volume Control ttk 11.00 600,000.00 6,600,000.00
7 Terminal Box SS bh 1.00 750,000.00 750,000.00
Sub Total Instalasi Tata Suara Lantai 17 51,530,000.00
U Instalasi Tata Suara Lantai 18
Kabel NYMHY 3x1,5mm dlm PVC Conduit 20mm
1 Ceiling Speaker 6 Watt bh 21.00 980,000.00 20,580,000.00
2 Paging Box Speaker, 10 Watt bh 2.00 500,000.00 1,000,000.00
3 Volume Control bh 11.00 800,000.00 8,800,000.00
4 Instalasi Ceiling Speaker ttk 21.00 600,000.00 12,600,000.00
5 Instalasi Paging Horn Speaker ttk 2.00 600,000.00 1,200,000.00
6 Instalasi Volume Control ttk 11.00 600,000.00 6,600,000.00
7 Terminal Box SS bh 1.00 750,000.00 750,000.00
Sub Total Instalasi Tata Suara Lantai 18 51,530,000.00
V Instalasi Tata Suara Lantai 19
Kabel NYMHY 3x1,5mm dlm PVC Conduit 20mm
1 Ceiling Speaker 6 Watt bh 21.00 980,000.00 20,580,000.00
2 Paging Box Speaker, 10 Watt bh 2.00 500,000.00 1,000,000.00
3 Volume Control bh 5.00 800,000.00 4,000,000.00
4 Instalasi Ceiling Speaker ttk 21.00 600,000.00 12,600,000.00
5 Instalasi Paging Horn Speaker ttk 2.00 600,000.00 1,200,000.00
6 Instalasi Volume Control ttk 5.00 600,000.00 3,000,000.00
7 Terminal Box SS bh 1.00 750,000.00 750,000.00
Sub Total Instalasi Tata Suara Lantai 19 43,130,000.00
U Sound System Musholla
1 Desktop Microphone bh 1.00 980,000.00 980,000.00
2 Power Amplifier 120 watt unit 1.00 500,000.00 500,000.00
3 DVD/CD/MP3 player unit 1.00 800,000.00 800,000.00
4 Two Way Speaker 10W unit 2.00 600,000.00 1,200,000.00
5 Change-over switch bh 1.00 600,000.00 600,000.00
6 Cabinet rack unit 1.00 600,000.00 600,000.00
7 Wiring, Instalasi & Alat Bantu ls 1.00 750,000.00 750,000.00
Sub Total Sound System Musholla 5,430,000.00
XIII SISTEM TATA SUARA PROFESSIONAL
A Main Equipment
1 Mixing consule 16 input unit 1.00 14,000,000.00 14,000,000.00
2 Signal Prosessor unit 1.00 8,000,000.00 8,000,000.00
3 Graphic Equaliser unit 1.00 18,000,000.00 18,000,000.00
4 DVD/CD/MP3 player unit 1.00 4,500,000.00 4,500,000.00
5 Wireless Microphone c/w receiver unit 1.00 4,000,000.00 4,000,000.00
6 Active speaker for room monitor unit 1.00 6,000,000.00 6,000,000.00
7 Mixer + Call Station set 1.00 20,000,000.00 20,000,000.00
8 Power Amplifier 120 Watt unit 1.00 30,000,000.00 30,000,000.00

Rincian RAB MEP (Sistem Tata Suara)


Universitas Muhammadiyah Tangerang
Page 83
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7

9 Cabinet rack c/w blower unit ( Lokal ) unit 1.00 8,000,000.00 8,000,000.00
13 Wiring, Instalasi & Alat Bantu set 1.00 15,000,000.00 15,000,000.00
14 Testing Comissioning ls 1.00 15,000,000.00 15,000,000.00
Sub Total Main Equipment 142,500,000.00
B SPEAKER & MICROPHONE
1 2-Way Active Speaker System 200 watt unit 8.00 9,000,000.00 72,000,000.00
2 Subwoofer 12" 600 watt unit 4.00 19,000,000.00 76,000,000.00
3 Dyanmic Microphone unit 2.00 7,000,000.00 14,000,000.00
4 Floor stand ( Lokal ) unit 2.00 3,000,000.00 6,000,000.00
5 Microphone inlet 2-Input unit 2.00 4,500,000.00 9,000,000.00
-PEAKER & MICROPHONE 177,000,000.00
C Instalasi Pengabelan & Pemasangan -
1 Canare Audio Cable Untuk Speaker m 336.00 580,000.00 194,880,000.00
2 XLR Connector untuk Speaker set 8.00 700,000.00 5,600,000.00
3 Bracket and accessories Speaker ls 4.00 4,000,000.00 16,000,000.00
4 Snake kable untuk microphone m 80.00 150,000.00 12,000,000.00
5 Connector 8 Ch w/ box set 1.00 350,000.00 350,000.00
6 Jumper Cable & Acc set 1.00 400,000.00 400,000.00
7 Inlet Microphone bh 2.00 800,000.00 1,600,000.00
8 Power Cable ls 1.00 7,000,000.00 7,000,000.00
9 Biaya Instalasi pemasangan, penarikan Cable ls 1.00 15,000,000.00 15,000,000.00
10 Testing Comissioning ls 1.00 15,000,000.00 15,000,000.00
Sub Total Instalasi Pengabelan & Pemasangan 267,830,000.00

TOTAL INSTALASI SISTEM TATA SUARA 1,752,750,000.00

Rincian RAB MEP (Sistem Tata Suara)


Universitas Muhammadiyah Tangerang
Page 84
HARGA JUMLAH TOTAL
NO URAIAN PEKERJAAN SAT VOL SATUAN HARGA HARGA
( Rp ) ( Rp ) ( Rp )
1 2 3 4 5 6 7
IJIN-IJIN PEKERJAAN ELEKTRIKAL
A Penyambungan Daya & Perijinan PLN
1 Biaya Penyambungan (BP) PLN kVA 555.00 3,500,000.00 1,942,500,000.00
2 Uang Jaminan Langganan (UJL) kVA 555.00 3,500,000.00 1,942,500,000.00
3 Sertifikat Layak Operasi (SLO) Konsuil ls 1.00 75,000,000.00 75,000,000.00
4 Keur Gambar & Pengesahan Instalasi ls 1.00 25,000,000.00 25,000,000.00
5 Administrasi Perijinan & Hibah ls 1.00 50,000,000.00 50,000,000.00

B Perijinan penangkal petir lot 1.00 35,000,000.00 35,000,000.00

C Perijinan Genset lot 1.00 50,000,000.00 50,000,000.00

D Penyambungan Perumtel lot 1.00 - -

TOTAL IJIN-IJIN PEKERJAAN ELEKTRIKAL Rp 4,120,000,000.00

Rincian RAB MEP (Ijin-ijin Elektrikal)


Universitas Muhammadiyah Tangerang
Page 85