KABUPATEN ENREKANG
BULAN : SEPTEMBER 2017
KABUPATEN ENREKANG
Harga
No. Uraian Satuan Ket.
( Rp. )
1 2 3 5 6
A. UPAH
1 Kepala Tukang Hari 1.10
2 Mandor Hari 1.10
3 Operator Hari 1.10
4 Pekerja Hari 1.10
5 Pembantu Operator Hari 1.10
6 Pembantu Sopir Hari 1.10
7 Penjaga Malam Hari 1.10
8 Sopir Hari 1.10
9 Tukang Hari 1.10
1.2
B. BAHAN 1.00
1 Accessories Listrik Set 3,000.00
2 Alumunium Voil M2 3,000.00
3 Amplas Lbr 3,000.00
4 Asbes Gelombang Kecil Lbr 3,000.00
5 Aspal Kg 400.00
6 Baja Ringan m2 1.07
7 Bak Mandi Fiber 50.50.5 Bh 3,000.00
8 Bak Mandi Fiber 60.60.6 Bh 3,000.00
9 Balok kayu kls. I M3
10 Balok kayu kls. II M3 1.07
11 Balok kayu kls. III M3 1.07
12 Balok Kayu kls. IV M3 1.07
13 Bambu Dia 6-8cm /600cm Btg 3,000.00
14 Batako Bh 1.07
15 Bata beton ringan ex Celcon
16 Batu Bata Bh 1.07
17 Batu Belah Hitam M3 1.07
18 Batu Belah Hitam 10/15 Cm M3 1.07
19 Batu Belah Hitam 5/7 Cm M3 1.07
20 Batu Belah Putih 20-40 cm M3 1.07
21 Batu Split 1/2 Cm M3 1.07
22 Batu Split 2/3 Cm M3 1.07
23 Batu Split 3/5 Cm M3 1.07
24 Bensin Ltr 1.07
25 Besi Baja IWF Kg 1.07
26 Besi Baja Siku Kg 1.07
KABUPATEN ENREKANG
1 2 3 5
27 Besi Beton Polos Kg
28 Besi Beton Ulir Kg 1.07
29 Besi Tempa M2
30 Block Glass Bh 3,000.00
31 Block Gress Bh 3,000.00
32 Box Meter Unit 3,000.00
33 Box Zekering/ Termis 2 Group Bh 3,000.00
34 Box Zekering/ Termis 3 Group Bh 3,000.00
35 Bumbungan Genteng Zincalume Pasir M 3,000.00
36 Bumbungan Genteng Zincalume polos M' 3,000.00
37 Cat Dasar Kg 3,000.00
38 Cat Genteng Kg 3,000.00
39 Cat Kayu Kg 3,000.00
40 Cat Meni Kg 3,000.00
41 Cat Taman Kg 3,000.00
42 Cat Tembok kualitas 1 Kg 3,000.00
43 Cat Tembok kualitas 2 Kg
44 Dempul Kg 3,000.00
45 Door closer Bh
46 Door Stoper Bh
47 Down light / PLC 13 W Bh
48 Engsel Jendela Bh 3,000.00
49 Engsel Pintu Bh 3,000.00
50 Eternit (240x120x0,3)cm M2 3,000.00
51 Floordrain Bh
52
53 Genteng Beton Bh 3,000.00
54 Genteng Keramik Bh
55 Genteng Keramik Glazur Bh
56 Genteng Mantili Bh 3,000.00
57 Genteng Metal Zicalume Polos M2 3,000.00
58 Genteng Metal Zincalume pasir M2 3,000.00
59 Genteng Plentong Bh 3,000.00
60 Gipsum 9mm M2 3,000.00
61 Granite Tile 40/40 M2
62 Grendel Jendela Set 3,000.00
63 Grendel Pintu Bh 3,000.00
64 Gypsumboard t.9 mm Lbr
65 Hak Angin / pengkait Set 3,000.00
66 Handle pintu Bh
67 Harplek 1 x 1 m Lbr 3,000.00
68 Hong Tanah Bh 3,000.00
69 Kabel Pompa M' 3,000.00
70 Kabel NYM 2 x 2,5 mm2 M'
71 Kabel NYM 3 x 2,5 mm2 M'
72 Kaca Bening 3 mm M2 3,000.00
73 Kaca Bening 5mm M2 3,000.00
74 Kaca Bening 8mm M2
75 Kaca Es 3 mm M2 3,000.00
76 Kaca Patri M2 3,000.00
77 Kaca Ryband 5mm M2 3,000.00
78 Kanstin Cetak Bh 3,000.00
KABUPATEN ENREKANG
1 2 3 5
79 Kawat Beton Kg
80 Kawat Bronjong Kg 3,000.00
81 Kawat Duri Kg 3,000.00
82 Kawat Harmonika M2 3,000.00
83 Kawat Nyamuk M2 3,000.00
84 Kayu Bakar M3 1.07
85 Kayu Dolken Btg 30.00
86 Kayu Kasau Kelas I M3 1.07
87 Kayu Kasau Kelas II M3 1.07
88 Kayu Kasau Kelas III M3 1.07
89 Kayu Kasau Kelas IV M3 1.07
90 Kayu Reng 2/3 - 4 m' Ikat 1.07
91 Kayu Reng 3/4 - 4 m' Ikat 1.07
92 Kayu Reng Kelas I M3 1.07
93 Kayu Reng Kelas II M3 1.07
94 Kayu Reng Kelas III M3 1.07
95 Kayu Reng Kelas IV M3 1.07
96 Keramik 10/20 Polos M2 3,000.00
97 Keramik 20/20 Polos M2 3,000.00
98 Keramik 20/20 Warna M2 3,000.00
99 Keramik 20/25 Polos M2 3,000.00
100 Keramik 20/25 Warna M2 3,000.00
101 Keramik 30/30 Warna M2 3,000.00
102 Keramik 40/40 Polos M2 3,000.00
103 Keramik 40/40 Warna M2 3,000.00
104 Keramik 50/50 Polos M2 3,000.00
105 Keramik 50/50 Warna M2 3,000.00
106 Kerpus Asbes Gel. Kecil Lbr 3,000.00
107 Kerpus Genteng Beton Bh 3,000.00
108 Kerpus Genteng Mantili Bh 3,000.00
109 Kerpus Genteng Plentong Bh 3,000.00
110 Kloset Duduk Keramik (Natural) Bh 3,000.00
111 Kitchenzink Bh
112 Kloset Jongkok Keramik Bh 3,000.00
113 Knie PVC 1/2" Bh 3,000.00
114 Knie PVC 3/4" Bh 3,000.00
115 Knie PVC 1" Bh 3,000.00
116 Knie PVC 2" Bh 3,000.00
117 Knie PVC 3" Bh 3,000.00
118 Kusen Almunium 3" M'
119 Kusen & Pintu PVC toilet Unit
120 Kran Leideng 1/2" (stenlis) Bh 3,000.00
121 Kran Leideng 3/4" (stenlis) Bh 3,000.00
122 Kran zink Bh
123 Kunci Tanam 1 x Putar Bh 3,000.00
124 Kunci Tanam 2 x Putar Bh 3,000.00
125 Kwas cat Bh
126 Lampu Hias/Sorot Bh 3,000.00
127 Lampu Pijar 25 Watt Bh 3,000.00
128 Lampu SL 18 Watt Bh 3,000.00
129 Lampu Tl 2 x 20 Watt Bh 3,000.00
KABUPATEN ENREKANG
1 2 3 5
130 Lampu Tl 25 Watt Bh 3,000.00
131 Lampu TL 2 x 36 watt grille Bh
132 Lem Kayu Kg
133 Lis Gibsum 10 cm M' 3,000.00
134 Lis Gibsum 15 cm M' 3,000.00
135 Lis Gibsum 5 cm M' 3,000.00
136 Lis Gibsun 20 cm M' 3,000.00
137 Mangkokan Listrik (Durados) Bh 3,000.00
138 Marmer 30/30 m2 3,000.00
139 Marmer 40/40 m2 3,000.00
140 Marmer 50/50 m2 3,000.00
141 Marmer 60/60 m2 3,000.00
142 Mesin Jet Pump kap.250 watt Unit
143 Mesin Pompa tekan kap. 150 watt Unit
144 Minyak bekisting Ltr
145 Minyak Cat Ltr 3,000.00
146 Minyak Pelumas Ltr 3,000.00
147 Multiplek 12 mm Lbr 3,000.00
148 Multiplek 9 mm Lbr 3,000.00
149 Nok Asbes Set 3,000.00
150 Nok Genteng Keramik Bh
151 Nok Genteng Keramik Glasur Bh
152 P a k u Kg 3,000.00
153 Paku Asbes Kg 3,000.00
154 Paku Cacing Kg 3,000.00
155 Paku Seng Kg 3,000.00
156 Paku Skrup Kg 3,000.00
157 Paku Triplek Kg 3,000.00
158 Panel Pompa Unit 3,000.00
159 Papan kayu kls. I M3 1.07
160 Papan kayu kls. II M3 1.07
161 Papan kayu kls. III M3 1.07
162 Papan Kayu kls. IV M3 1.07
163 Pas. Instalasi Listrik Titik 3,000.00
164 Pasir Beton M3 1.07
165 Pasir Pasang M3 1.07
166 Pasir Urug M3 1.07
167 Paving Block T = 6 Cm Bh 3,000.00
168 Paving Block T = 8 Cm Bh 3,000.00
169 Penangkal Petir Unit 3,000.00
170 Pipa GIP Diameter 0,50" (Galvanis) Btg 3,000.00
171 Pipa GIP Diameter 0,75" (Galvanis) Btg 3,000.00
172 Pipa GIP Diameter 1,00" (Galvanis) Btg 3,000.00
173 Pipa GIP Diameter 1,25" (Galvanis) Btg 3,000.00
174 Pipa GIP Diameter 2,00" (Galvanis) Btg 3,000.00
175 Pipa GIP Diameter 4,00" (Galvanis) Btg 3,000.00
176 Pipa GIP Diameter 6,00" (Galvanis) Btg 3,000.00
177 Pipa Leideng 1 1/2" Btg 3,000.00
178 Pipa Leideng 1" Btg 3,000.00
179 Pipa PVC 1" Btg 3,000.00
180 Pipa PVC 1/2" Btg 3,000.00
181 Pipa PVC 2" Btg 3,000.00
182 Pipa PVC 3" Btg 3,000.00
KABUPATEN ENREKANG
1 2 3 5
183 Pipa PVC 3/4" Btg 3,000.00
184 Pipa PVC 4" Btg 3,000.00
185 Plamir Tembok Kg 3,000.00
186 Plint Abu - abu 10/30 Bh 3,000.00
187 Plint Traso 10/30 Bh 3,000.00
188 Plint Granitetile 10/40 cm Bh
189 Plint Keramik 10/30 cm Bh
190 Plitur Jadi Ltr
191 Poly Carbonat Lbr 3,000.00
192 Rangka Jendela Almunium M'
193 Rangka Pintu Almunium M'
194 Rangka plafond Metal furing M2
195 Reservoir Tower Air Fiber 0,50 M3 Bh 3,000.00
196 Reservoir Tower Air Fiber 1,00 M3 Bh 3,000.00
197 Rolling Door M2 3,000.00
198 Roster Beton 15/20 Bh 3,000.00
199 Roof Drain Metal Bh
200 Rumput Gajah Australia M2 3,000.00
201 Rumput Golf M2 3,000.00
202 Saklar Double Bh 3,000.00
203 Saklar Engkel Bh 3,000.00
204 Saklar triple Bh 3,000.00
205 Saringan Air / Fool Drain Bh 3,000.00
206 Seal tape Bh
207 Semen PC Zak 3,000.00
208 Semen Putih Zak 3,000.00
209 Semen Warna
210 Seng Gelombang BJLS 27 Lbr 3,000.00
211 Seng Gelombang BJLS 30 Lbr 3,000.00
212 Seng Plat BJLS 27 Lbr 3,000.00
213 Seng Plat BJLS 30 Lbr 3,000.00
214 Sewa Stemper Kodok Hk 3,000.00
215 Selinder Bh
216 Shower Spray Unit
217 Shower Set Unit
218 Sock derat luar 1/2" Bh 3,000.00
219 Sock derat luar 3/4" Bh 3,000.00
220 Sock derat luar 1" Bh 3,000.00
221 Sock derat luar 2" Bh 3,000.00
222 Soda Api Kg 3,000.00
223 Slot Tanam Bh
224 Stop Kontak Bh 3,000.00
225 Stop kran dia 1" Bh
226 Talang Fiber M' 3,000.00
227 Tali Ijuk Kg 3,000.00
228 Tanah Urug Pilihan M3 3,000.00
229 Tarikan Jendela Bh 3,000.00
230 Tempat Sabun Bh
231 Teakwood 5 mm Lbr 3,000.00
232 Teer Ltr 3,000.00
233 Thinner Ltr
234 Triplek 3 mm Lbr 3,000.00
235 Triplek 4 mm Lbr 3,000.00
236 Triplek 5 mm Lbr 3,000.00
KABUPATEN ENREKANG
1 2 3 5
237 Triplek 9 mm Lbr
238 Ubin Abu - abu 30/30 Bh 3,000.00
239 Ubin Granito 30 x 30 cm Bh 3,000.00
240 Ubin Traso 30/30 Bh 3,000.00
241 Ubin Wafel 20/20 Bh 3,000.00
242 Urinoir Keramik Bh 3,000.00
243 Washtafel keramik lengkap Bh 3,000.00
244 Water Meter Bh
245 Wood Filler Kg
Panduan Penggunaan
Formula disusun dengan perangkat lunak Microsoft Excel yang sederhana agar mudah dioperasikan.
Berikut langkah-langkah penggunaan formula HSBGN:
1. Pengertian
1) Biaya Pembangunan Bangunan Gedung Negara adalah biaya yang dikeluarkan untuk membangun suatu bangunan gedung ba
berdasarkan formula yang telah ditetapkan.
2) Harga Satuan Tertinggi Bangunan Gedung Negara adalah harga satuan tertinggi pembangunan gedung negara per m2 lantai
bangunan gedung.
3) Penyusunan Harga Satuan Pembangunan Gedung Negara adalah memasukkan harga satuan bahan & upah kepada Formula
pembangunan gedung negara yang telah ditetapkan.
4) Gedung Negara adalah bangunan gedung untuk keperluan dinas yang menjadi/akan menjadi kekayaan milik negara dan
diadakan dengan sumber pembiayaan yang berasal dari dana APBN/perolehan lainnya yang sah, antara lain seperti: gedung kanto
gedung sekolah, gedung rumah sakit, gudang dan lain-lain.
3. Klasifikasi HSBGN
1) Bangunan Sederhana
2) Bangunan Tidak Sederhana
3) Rumah Negara
a. Tipe A
b. Tipe B
c. Tipe C dan D
4) Pagar Bangunan Negara
a. Pagar Depan
b. Pagar Belakang
c. Pagar Samping
1. Model teknis berupa data gambar arsitektur masing-masing klasifikasi bangunan gedung negara disiapkan- lihat lampiran 1
2. Menghitung volume pekerjaan (standar) masing-masing model – lihat lampiran.2
3. Menganalisa harga satuan pekerjaan.
- Mencari data standar SNI untuk pekerjaan standar (nomor sumber data SNI, uraian pekerjaan, satuan, koefisien)
- Meng-link harga satuan dan upah dengan lembar “input data”
- Meng-link total harga satuan (pembulatan) dengan harga satuan pada lembar “RAB”
4. Memperoleh RAB total pekerjaan standard an harga bangunan /m2 pada lembar “RAB”
5. Harga bangunan /m2 ter-link ke lembar HSBGN dan Surat Keputusan.
Provinsi SULAWESI SELATAN
Kota/Kabupaten Kabupaten Enrekang
Tahun 2021
Nomor SK.
Ditetapkan oleh KEPALA DINAS PU KAB. ENREKANG
Nama A. SAPADA, S.IP. M.Si
Ditetapkan di ENREKANG
Tanggal
II BAHAN PEREKAT
1 Semen (50 Kg) Semen Indonesia zak Rp 70,000
2 Semen Warna Semen Indonesia kg Rp 2,000
IV BAHAN KAYU
1 Kayu Klas I Jati m3 Rp 12,000,000
2 Kayu Klas II Kamper m3 Rp 4,500,000
3 Kayu Klas III Meranti m3 Rp 3,500,000
4 Kayu Klas IV Terentang m3 Rp 2,200,000
5 Dolken dia 8 s/d 10 cm p. 4 m btg Rp 32,500
V BAHAN ALMUNIUM
1 Kusen Almunium 3", Alexindo m' Rp 289,600
2 Rangka Jendela Almunium Alexindo m' Rp 325,000
3 Rangka Pintu Almunium Alexindo m' Rp 325,000
4 Kusen & Pintu PVC toilet Maspion unt Rp 243,750
5 Engsel 3", ex Bos bh Rp 27,000
7 Handle pintu type HRE 75.01 ex. Cisa bh Rp 216,700
8 Selinder type 08510 ex. Cisa bh Rp 170,600
9 Door Stoper bh Rp 89,900
10 Door closer bh Rp 112,700
11 Slot Tanam bh Rp 106,000
12 Kait Angin bh Rp 7,000
13 Grendel bh Rp 5,500
10 dari 296
NO URAIAN KETERANGAN SATUAN
VI BAHAN PELAPIS :
1 Triplek t. 3 mm Uk 120x240 cm lbr Rp 54,100
2 Triplex t. 4 mm Uk 120x240 cm lbr Rp 75,000
3 Triplex t. 9 mm Uk 120x240 cm lbr Rp 130,000
IX BAHAN KACA :
1 Kaca Polos 3 mm m2 Rp 78,500
2 Kaca Polos 5 mm m2 Rp 127,200
3 Kaca Polos 8 mm m2 Rp 281,500
XI BAHAN FINISHING :
1 Cat kayu/Besi ex. SEIV Kg Rp 67,700
2 Plamir Kayu Kg Rp 31,000
3 Meni kayu ex. Nippon kg Rp 32,000
4 Wood Filler Impra Kg Rp 25,800
5 Thinner ND IMPALA Ltr Rp 41,900
6 Amplas Kayu Lbr Rp 6,700
7 Kwas cat bh Rp 18,400
8 Cat Tembok kw1 ex. Dulux ; Warna standard Kg Rp 32,500
9 Cat Tembok kw2 ex. Vinilex ; Warna standard Kg Rp 31,300
10 Plamir Tembok Kg Rp 74,600
11 Lem Kayu kg Rp 11,600
12 Seal tape bh Rp 13,400
13 Minyak bekisting Ltr Rp 36,800
11 dari 296
NO URAIAN KETERANGAN SATUAN
XV PERALATAN ELEKTRIKAL
1 Box panel PVC isi 4 MCB Legran bh Rp 150,000
2 MCB 6 A Legran bh Rp 51,400
3 MCB 4 A Legran bh Rp 51,400
4 Kabel NYM 2 x 2,5 mm2 m' Rp 25,000
5 Kabel NYM 3 x 2,5 mm2 m' Rp 30,000
6 Kabel telephone 4 x 0.5 mm m' Rp 37,900
7 Isolasi bh Rp 10,000
8 Saklar tunggal Broco bh Rp 43,300
9 Saklar ganda Broco bh Rp 59,500
10 Stop kontak Broco bh Rp 43,300
11 Outlet TV Broco bh Rp 48,750
12 Outlet Telephone Broco bh Rp 51,400
13 Down light / PLC 13 W bh Rp 75,800
14 Fitting plafond + lampu SL Panasonic bh Rp 137,000
15 Lampu TL 2 x 18 watt grille Panasonic bh Rp 104,000
16 Lampu TL 2 x 36 watt grille Panasonic bh Rp 208,000
12 dari 296
NO URAIAN KETERANGAN SATUAN
XVI UPAH PEKERJA :
1 Tukang Besi Konstruksi Org/Hari 138,000
2 Tukang Besi Tulangan Org/Hari 138,000
3 Kepala Tukang Besi Org/Hari 170,000
4 Tukang Kayu Kasar (Plafond , Kuda/Gording, R.Atap) Org/Hari 138,888
5 Tukang Kayu Halus (Kusen) Org/Hari 138,000
6 Kepala Tukang Kayu Org/Hari 170,000
7 Tukang Batu Kasar Tukang Batu Kasar Org/Hari 138,000
8 Tukang Batu Halus Tukang Batu Halus (Bata,Plester,Acian list2) Org/Hari 138,000
9 Kepala Tukang Batu Org/Hari 170,000
10 Tukang Cat Biasa Org/Hari 138,000
11 Kepala Tukang Cat Org/Hari 170,000
12 Tukang Listrik Org/Hari 138,000
13 Kepala Tukang Listrik Org/Hari 170,000
14 Pekerja Org/Hari 117,000
15 Mandor Org/Hari 203,000
XVII LAIN-lAIN
1 IMB m2
13 dari 296
7.00
14 dari 296
1 Nanggroe Aceh Darussalam 2 Sumatera Utara 3
1 2
520 875
bataco 5,000 3,000 Kerawang merah
250,000 146,400
320,000 217,400
300,000 217,400
150,000 190,000
80,000 101,000
80,000 101,000
75,000 79,600
75,000 79,600
67,500 61,250
2,400 3,440
11,000 15,000
13,500 15,000
13,500 23,500
BRC T.90 x 2,40 m 120,313 besi strip 300,000 BRC
120,000 240,000
6,500 16,140
3,500,000 8,796,600
Merbou 3,000,000 6,493,900
2,800,000 3,460,700
sembarang 2,300,000 2,650,000 klas III
16,600 20,000
62,000 62,000
90,000 90,000
155,000 155,000
850,000 850,000 panil kering oven
25,000 8,000
135,000 150,000
242,000 33,600
63,000 100,000
450,000 200,000
75,000 57,000
9,009 7,500
22,523 5,000
52,500 67,000
62,000 100,000
105,000 123,000
65,000 51,500
marmer 1,062,500 282,000
10,072 10,072
20,000 20,000
2,500 8,000
gtg beton 9,000 10,570
2,500 2,500
12,463 16,000
46,300 73,000
140,000 62,500
170,000 114,350
170,000 125,000
16,000 18,000
16,000 18,000
16,000 18,000
8,000 3,700
25,000 33,600
21,025 7,700
30,030 33,600
27,500 21,000
19,000 11,410
3,500 3,000
7,500 15,000
35,000 23,670
22,000 18,160
27,000 7,700
36,400 15,000
15,000 15,000
residu 11,000 4,500
600,000 500,000
1,200,000 1,350,000
200,000 159,800
1,217,000 800,000
545,738 417,500
181,000 181,000
598,000 598,000
297,000 20,180
44,000 37,000
299,000 140,000
bak cuci piring 225,225 250,000
21,450 6,500
220,000 65,000
8,500 13,450
50,000 76,000
3,430 4,800
4,718 6,500
6,470 6,470
22,000 20,000
25,000 28,000
30,000 43,000
16,500 45,000
35,000 35,000
1,864,000 500,000
1,116,500 1,116,500
58,500 25,000
35,000 35,000
950,000 950,000
585,000 550,000
150,000 150,000
84,500 50,000
71,500 50,000
14,025 14,025
18,900 18,900
15,000 15,000
3,003 5,000
13,970 7,300
25,025 7,300
20,350 15,000
43,575 43,575
43,575 43,575
173,460 173,460
49,400 75,000
250,000 250,000
375,000 375,000
120,000 80,000
120,000 80,000
150,000 90,000
120,000 55,000
120,000 80,000
150,000 90,000
120,000 80,000
120,000 55,000
150,000 90,000
120,000 80,000
150,000 90,000
120,000 80,000
150,000 90,000
90,000 55,000
120,000 80,000
15,000 15,000
Sumatera Barat 4 Jambi 5 Riau
3 4 5
1,400 527
3,000 2,805
180,000 297,330
350,000 297,330
350,000 297,330
185,000 263,670 batu kacang
160,000 92,656 pasir kasar
150,000 92,656
130,000 80,784
35,000 38,148 tanah timbunan
64,000 81,345
1,800 1,459 semen putih
10,000 12,566
10,500 12,566
10,500 12,566
225,000 225,000
120,000 196,350
17,500 19,074
6,500,000 6,732,000
6,300,000 4,488,000
5,400,000 3,394,050
2,650,000 1,626,900
16,600 16,600
62,000 62,000
90,000 90,000
155,000 155,000
850,000 504,900
30,000 6,171
253,000 253,000
242,000 242,000
63,000 24,684
450,000 426,360
75,000 75,000
7,500 5,610
10,000 15,147
42,000 42,636
52,000 66,198
110,000 129,030
34,100 38,148
282,000 195,228
10,072 3,927
20,000 20,000
62,500 81,345
90,000 137,445
125,000 159,885
18,000 18,513
12,000 18,513
12,000 18,513
3,700 505
47,000 23,001
21,025 26,928
11,615 11,615
27,500 28,050
11,410 13,464
6,850 7,854
7,500 8,415
35,000 67,881
11,800 15,708
17,500 25,245
25,000 21,879
15,000 2,244
4,500 11,220
1,636,000 1,907,400
1,950,000 1,924,230
259,000 195,350
1,217,000 1,365,474
300,000 252,450
181,000 364,650
598,000 598,000
297,000 297,000
44,000 44,000
299,000 299,000
250,000 250,000
115,000 115,000
70,000 62,832
8,500 15,708
50,000 50,000
3,430 14,025
4,718 19,074
6,470 26,367
14,213 58,344
14,213 123,701
46,460 188,777
45,000 45,000
35,000 35,000
1,864,000 1,864,000
1,116,500 1,116,500
25,000 25,000
35,000 35,000
950,000 950,000
550,000 550,000
150,000 150,000
50,000 16,830
50,000 50,000
14,025 8,135
18,900 18,900
15,000 15,000
5,000 5,000
15,000 19,074
18,900 8,976
15,000 6,732
43,575 43,575
43,575 43,575
173,460 173,460
75,000 75,000
250,000 72,930
375,000 84,150
80,000 77,000
75,000 77,000
85,000 88,000
80,000 77,000
80,000 77,000
85,000 88,000
65,700 77,000
70,000 77,000
75,600 88,000
80,000 77,000
85,000 88,000
100,000 77,000
110,000 88,000
60,000 49,500
120,000 110,000
15,000 15,000
Bangka Belitung 9 Bengkulu 10 Lampung
8 9 10
750 500
1,500 8,500
175,000 264,900
206,000 242,400
185,000 216,200
190,000 282,000
250,000 268,900
185,000 274,400
67,500 196,500
60,000 118,500
65,000 70,100
1,800 1,600
9,000 15,500
9,500 15,500
11,000 15,500
BRC 120cm 162,500 225,000
130,000 120,000
16,625 23,500
71,000 87,800
71,000 225,300
71,000 225,300
85,000 850,000
12,000 10,500
350,000 397,600
242,000 125,800
63,000 63,000
330,000 229,300
35,000 75,000
58,000 23,600
20,000 52,400
48,000 59,000
58,000 72,100
125,000 121,800
42,000 62,900
162,000 235,800
35,000 10,072
40,500 20,000
1,800 7,900
14,000 6,600
5,000 11,000
7,500 10,500
38,000 49,800
85,000 98,600
95,000 107,800
85,000 235,800
17,500 27,500
15,000 28,200
15,000 28,200
18,500 3,700
45,000 51,000
25,500 34,100
25,000 11,615
30,000 27,500
15,000 28,800
6,850 3,900
10,000 11,800
75,000 183,400
19,000 74,700
15,000 17,500
15,000 25,000
2,000 3,900
residu 4,400 4,500
1,757,800 1,636,000
1,716,000 1,552,400
120,000 157,200
990,000 2,777,200
125,000 421,800
50,000 181,000
375,000 598,000
70,000 297,000
35,000 44,000
275,000 144,100
192,500 1,141,300
165,000 115,000
59,000 69,000
8,500 22,900
50,000 50,000
150,000 569,237
16,500 28,015
15,000 23,969
7,500 22,214
9,700 22,214
15,000 4,970
5,000 5,000
13,000 11,374
15,000 15,191
13,000 12,595
43,575 43,575
43,575 43,575
100,000 326,300
75,000 75,000
250,000 89,008
310,000 120,076
62,700 82,730
62,700 82,730
68,900 82,730
62,700 82,730
62,700 82,730
68,900 82,730
62,700 82,730
62,700 82,730
68,900 82,730
62,700 82,730
68,900 82,730
62,700 82,730
68,900 82,730
53,400 76,360
75,300 89,090
15,000 15,000
DKI Jakarta 14 Jawa Tengah 15 DI Yogyakarta
13 14 15
800 425
5,000 3,000
105,700 batu kong 320,250
207,800 634,095
234,650 516,670
112,250 657,580
168,050 126,819
144,050 126,819
107,200 126,819
96,300 187,880 tanah merah
73,900 95,818
2,200 1,800
14,200 19,022
14,500 19,022
18,050 19,022
Pagar BRC 1,2 x 2,4 m 124,800 225,000 BRC
baja rangka galvalume 212,950 250,819
18,050 23,954
62,450 109,909
62,450 109,909
62,450 109,909
750,000 3,180,338
18,250 29,872
kunci tanam 199,500 197,274
89,250 133,864
119,600 93,000
160,650 281,820
94,500 107,091
19,900 18,318
14,300 10,000
52,250 77,500
66,100 132,455
120,050 218,410
45,650 70,455
394,150 246,592
15,217 14,091
98,538 61,648
2,000 2,500
10,250 5,816
6,050 2,500
10,500 12,463
48,250 65,500
80,000 62,500
95,000 162,046
190,000 380,457
14,500 25,363
14,500 25,363
14,500 25,363
3,700 3,700
50,650 55,659
24,050 36,213
24,050 78,909
36,050 27,500
24,050 31,704
4,900 3,522
7,300 25,081
21,010 219,819
15,000 89,477
35,500 36,213
11,000 26,068
2,400 15,000
4,400 4,500
372,050 1,636,000
2,400,150 2,254,560
141,050 472,500
658,240 1,217,000
275,000 300,000
181,000 181,000
598,000 598,000
51,900 297,000
44,000 44,000
299,000 299,000
700,900 250,000
115,000 46,500
71,850 81,727
18,050 8,500
50,000 178,955
7,008 5,460
12,763 8,384
10,617 12,330
29,008 18,671
53,017 35,580
76,017 53,898
45,000 45,000
35,000 35,000
1,864,000 2,091,751
1,116,500 1,045,875
25,000 25,000
35,000 35,000
950,000 950,000
550,000 550,000
150,000 150,000
50,000 50,000
50,000 50,000
14,025 14,025
18,900 18,900
15,000 15,000
5,000 5,000
14,700 15,000
14,700 18,900
24,500 15,000
43,575 43,575
43,575 43,575
173,460 173,460
75,000 75,000
80,850 250,000
110,513 375,000
42,000 77,000
42,000 77,000
52,500 82,500
52,500 77,000
52,500 77,000
52,500 82,500
42,000 77,000
42,000 77,000
52,500 82,500
47,250 77,000
52,500 82,500
50,000 77,000
52,500 82,500
35,000 71,500
63,000 82,500
15,000 15,000
Kalimantan Selatan 19 Kalimantan Tengah 20 Kalimantan Timur
18 19 20
86,570
24,200
24,420
33,880
21,010
BRC 569,250
120,000
31,570
5,060,000
3,478,750
2,213,750
2,213,750
8,800
62,000
90,000
155,000
850,000
19,800
253,000
242,000
63,000
165,000
165,000
9,900
8,250
82,170
121,440
227,700
59,400
282,000
19,800
70,500
palentong 4,400
5,816
nok palentong 2,750
12,463
37,950
62,500
107,470
125,000
23,980
23,980
23,980
3,700
13,750
17,050
3,960
27,500
11,410
5,280
4,510
103,070
10,780
9,350
25,000
11,660
8,800
253,000
2,530,000
221,320
1,897,500
379,500
181,000
598,000
31,570
44,000
299,000
250,000
56,870
98,670
list kayu 6,270
50,000
3,430
31,570
37,950
72,710
88,770
131,230
56,870
35,000
1,864,000
1,116,500
25,000
35,000
950,000
550,000
150,000
50,000
50,000
14,025
18,900
15,000
5,000
16,390
19,690
16,390
43,575
43,575
73,920
75,000
250,000
213,730
75,240
75,240
111,320
75,240
75,240
111,320
75,240
75,240
111,320
75,240
111,320
75,240
111,320
73,920
90,640
15,000
Gorontalo 24 Sulawesi Tengah 25
23 24
450 425
4,000 3,750 bataco
130,000 130,000
135,000 150,000
130,000 150,000
120,000 112,000
90,000 110,000
90,000 110,000
75,000 95,000
57,000 86,625
67,500 58,000
9,000 1,600 semen putih
9,479 9,193
9,514 7,911
9,750 10,500
225,000 225,000 BRC T.90 x 2,40 m
220,000 120,000
20,000 20,000
3,500,000 2,500,000
2,450,000 1,500,000 Merbou
200,000 1,200,000
1,865,900 1,200,000 sembarang
31,600 bambu 17,325
80,000 62,000
80,000 90,000
80,000 155,000
300,000 850,000
8,000 11,261
95,000 253,000
242,000 242,000
63,000 63,000
450,000 450,000
75,000 75,075
4,500 17,325
2,200 8,663
45,000 51,975
65,000 63,525
115,000 110,000
42,500 87,369
282,000 282,000 marmer
10,072 10,072
20,000 20,000
2,500 2,500
5,816 5,816 gtg beton
2,500 2,500
12,463 12,463
100,000 49,613
70,000 79,696
90,000 109,725
125,000 125,000
15,000 14,000
15,000 14,000
15,000 14,000
250 3,700
100,000 34,073
34,000 21,025
100,000 11,615
27,500 27,500
11,410 11,410
3,000 6,850
7,500 7,000
17,000 40,425
9,000 11,800
34,000 12,128
25,000 43,313
15,000 15,000
11,500 4,500 residu
200,000 653,730
200,000 1,559,250
120,000 214,830
360,000 329,175
300,000 300,000
181,000 181,000
598,000 598,000
25,000 297,000
44,000 44,000
299,000 299,000
225,000 250,000 bak cuci piring
26,000 115,000
62,500 86,626
19,500 8,500
50,000 50,000
3,500 3,750
4,250 5,000
6,470 6,470
7,500 13,138
15,000 21,656
22,500 23,750
26,000 45,000
35,000 35,000
1,864,000 3,869,250
1,116,500 1,116,500
25,000 25,000
35,000 35,000
780,000 854,700
500,000 550,000
150,000 150,000
18,000 50,000
18,000 50,000
4,000 14,025
7,000 18,900
15,000 15,000
5,000 5,000
8,000 15,000
8,500 15,246
9,000 16,170
43,575 43,575
43,575 43,575
34,000 173,460
75,000 75,000
250,000 250,000
375,000 375,000
80,000 75,000
80,000 75,000
90,000 80,000
80,000 75,000
80,000 75,000
90,000 80,000
80,000 75,000
80,000 75,000
90,000 80,000
80,000 75,000
90,000 80,000
80,000 75,000
90,000 80,000
50,000 45,000
60,000 80,000
15,000 15,000
Sulawesi Selatan 26 Sulawesi Barat 27 Sulawesi Tenggara
25 26 27
1,320 550
3,000 2,596
181,440 161,920
189,000 279,400
189,000 259,050
189,000 131,450
122,500 126,115
177,660 126,115
128,520 111,947
85,050 35,000
78,600 59,565
13,860 13,310
10,962 16,610
10,784 16,610
23,940 10,500
225,000 225,000 BRC
120,000 120,000
22,680 20,009
62,000 62,000
90,000 90,000
155,000 155,000
850,000 850,000
25,200 10,010
253,000 323,675
242,000 242,000
63,000 63,000
450,000 450,000
126,000 75,000
13,860 6,127
11,844 10,241
59,193 58,300
marmer 283,500 marmer 346,533
8,820 10,072
20,000 20,000
2,520 1,540
3,780 5,816
2,500 2,500
12,463 12,463
62,553 100,991
80,042 88,000
186,480 122,100
6 mm 206,168 125,000
20,160 22,363
17,640 21,428
17,640 20,603
3,700 3,700
52,038 56,496
23,940 27,071
28,602 26,609
39,060 27,500
34,020 11,410
3,276 4,125
3,780 7,500
49,140 34,100
26,082 11,800
13,860 9,185
25,000 41,195
1,638 15,000
4,500 4,500
1,455,300 1,765,500
1,701,000 2,824,800
157,500 176,550
1,638,000 2,059,750
258,300 882,750
157,500 181,000
94,500 598,000
41,580 297,000
44,100 44,000
299,000 299,000
250,000 250,000
25,200 115,000
78,120 70,620
8,500 8,500
50,000 50,000
7,182 5,225
10,332 7,007
11,088 10,802
28,980 14,213
51,282 14,213
68,985 46,460
25,200 45,000
35,000 35,000
1,512,000 1,864,000
932,400 1,116,500
25,000 25,000
35,000 35,000
3,465,000 950,000
1,386,000 550,000
150,000 150,000
75,600 50,000
75,600 50,000
14,025 14,025
8,820 18,900
15,000 15,000
5,000 5,000
16,380 16,500
25,200 18,900
25,200 129,470
43,575 43,575
43,575 43,575
173,460 173,460
75,000 75,000
250,000 250,000
375,000 375,000
69,300 62,150
69,300 62,150
75,600 68,360
75,600 64,630
75,600 64,630
81,900 70,950
69,300 62,150
69,300 62,150
75,600 68,360
69,300 62,150
75,600 62,150
69,300 67,100
75,600 72,090
53,000 45,070
85,000 66,000
15,000 15,000
Nusa Tenggara Timur 31 Maluku 32 Maluku Utara
30 31 32
425 2,500
bata tela 10,700 bata tela 6,000
374,500 400,000
2,140,000 650,000
2,140,000 650,000
267,500 400,000
588,500 400,000
588,500 400,000
588,500 300,000
267,500 100,000
133,800 108,400
18,200 20,000
14,067 15,038
14,067 11,859
14,067 10,500
225,000 225,000
120,000 120,000
32,100 30,000
20,587,000 20,587,000
2,086,500 kayu besi 2,000,000
1,926,000 matoa 1,400,000
1,926,000 begesting 1,400,000
42,800 16,600
62,000 62,000
90,000 90,000
155,000 155,000
850,000 850,000
21,400 22,500
208,700 253,000
242,000 242,000
63,000 63,000
450,000 450,000
75,000 125,000
24,000 12,000
17,000 16,000
82,500 67,275
95,000 80,500
157,300 97,750
191,000 60,500
205,300 281,000
16,100 10,072
20,000 20,000
2,500 2,500
5,816 5,816
2,500 2,500
12,463 12,463
91,000 97,750
299,600 62,500
417,300 90,000
rayben 5mm 438,700 125,000
26,800 21,500
26,800 22,500
26,800 12,000
1,900 16,500
53,500 39,500
26,800 21,025
26,800 11,615
27,500 27,500
17,900 11,410
6,500 10,000
7,500 8,750
171,200 48,750
42,800 11,800
26,800 70,000
25,700 22,500
15,000 15,000
16,600 4,500
963,000 750,000
2,398,500 500,000
925,600 183,000
1,235,900 1,217,000
1,235,900 2,739,000
181,000 70,000
598,000 598,000
297,000 297,000
44,000 44,000
299,000 299,000
963,000 250,000
115,000 50,000
120,000 143,750
8,500 20,125
50,000 50,000
6,250 7,500
8,033 9,375
8,567 11,250
15,167 26,875
22,300 37,500
33,000 47,500
46,100 45,000
35,000 35,000
3,745,000 1,800,000
2,664,900 1,300,000
25,000 25,000
35,000 35,000
5,329,700 826,000
802,500 2,026,000
150,000 150,000
80,300 50,000
80,300 50,000
14,025 11,400
18,900 15,000
15,000 15,000
5,000 5,000
32,100 18,750
35,400 22,500
27,900 17,500
43,575 43,575
43,575 43,575
173,460 173,460
75,000 75,000
250,000 250,000
375,000 375,000
125,000 85,000
125,000 85,000
150,000 95,000
125,000 85,000
125,000 85,000
150,000 95,000
125,000 85,000
125,000 85,000
150,000 95,000
125,000 85,000
150,000 95,000
125,000 85,000
150,000 95,000
90,000 70,000
175,000 100,000
15,000 15,000
HARGA SATUAN BANGUNAN GEDUNG NEGARA
Tahun 2021
Provinsi SULAWESI SELATAN
Kabupaten Enrekang
( dalam Rupiah)
GEDUNG NEGARA
TIDAK SEDERHANA SEDERHANA
6,610,000 6,220,000
RUMAH NEGARA
TIPE A TIPE B TIPE C,D,E
6,350,000 6,270,000 4,830,000
NOMOR :
TENTANG
Mengingat :
1. Bahwa bangunan gedung negara merupakan Tanggung jawab pemerintah.
2. Bahwa di dalam penyusunan program dan pelaksanaan pembangunan gedung negara perlu ditetapkan harga
satuan.
3. Bahwa KEPALA DINAS PU KAB. ENREKANG perlu menerbitkan harga satuan untuk pembangunan gedung negara.
Menimbang :
1. Undang-Undang RI Nomor 25 Tahun 2000 tentang Kewenangan Pemerintah dan Kewenangan Provinsi sebagai
Daerah Otonomi.
2. Undang-Undang RI Nomor 28 Tahun 2002 tentang Bangunan Gedung.
3. Undang-Undang RI Nomor 32 Tahun 2002 tentang Pemerintah Daerah.
4. Undang-Undang RI Nomor 32 Tahun 2004 tentang Pemerintah Daerah
5. PP Nomor 36 Tahun 2007 tentang Pelaksanaan UUBG
6. Keputusan Presiden Republik Indonesia Nomor 42 tahun 2002 tentang Pelaksanaan APBN
7. Peraturan Menteri Pekerjaan Umum Nomor 45/PRT/M/2008 tanggal 27 Desember 2008 tentang Pedoman
Teknis Pembangunan Bangunan Gedung Negara
Menetapkan :
Harga Satuan Pembangunan Gedung Negara, Rumah Negara & Pagar Sebagai Acuan Penyusunan Program
Anggaran Dan Pedoman Pelaksanaan, Daftar Isian Pelaksanaan Kegiatan Tahun Anggaran 2021
4. Harga satuan tersebut termasuk pajak-pajak, IMB, jasa kontraktor, overhead, asuransi, perijinan, tingkat
keselamatan dan kesehatan kerja
Ditetapkan di : ENREKANG
Pada Tanggal : 30 Desember 1899
72 dari 296
menu
I. PEKERJAAN PERSIAPAN :
RSNI T-12-2002 M2 Pembersihan lapangan & Perataan tanah - 12,715 10% 13,987
Pekerja org/hr 0.100 117,000 11,700
Mandor org/hr 0.005 203,000 1,015
-
RSNI T-12-2002 M Pengukuran & Pasang bouwplank - 480 17,631 10% 19,922
Kayu Kaso 5 / 7 (borneo) m3 0.012 - -
Kayu Papan 3 / 20 borneo m3 0.007 - -
Paku 5 s/d 10 cm kg 0.020 24,000 480
Pekerja org/hr 0.080 117,000 9,360
Tukang Kayu Kasar org/hr 0.040 138,888 5,556
Kepala Tukang Kayu org/hr 0.010 170,000 1,700
Mandor org/hr 0.005 203,000 1,015
-
gelombang+
RSNI T-12-2002 M2 Pembuatan direksi keet 120,300 214,935 10% 368,759
plafond asbes
Kaso kamper medan semen 3 mm) m3 0.050 - -
Triplex t. 4 mm Dinding lbr 0.800 75,000 60,000
Triplex t. 4 mm Plafond lbr 0.700 75,000 52,500
Paku 4 s/d 7 cm kg 0.500 - -
Paku payung bh 9.000 - -
Triplex t. 9 mm Pintu m2 0.060 130,000 7,800
Cat plafond acrylic emulsion KW.III m2 1.000 - -
Pekerja org/hr 1.200 117,000 140,400
Tukang Kayu Kasar org/hr 0.400 138,888 55,555
Kepala Tukang Kayu org/hr 0.040 170,000 6,800
Mandor org/hr 0.060 203,000 12,180
-
PEKERJAAN TANAH : -
-
SNI DT 91-0006-2007 M2 Stripping tanah tebal 20 cm - - 6,865 10% 7,552
Pekerja org/hr 0.050 117,000 5,850
Mandor org/hr 0.005 203,000 1,015
-
SNI 2835:2008 - 6.1 M3 Galian tanah, dalam s/d 1 m - - 92,825 10% 102,108
Pekerja org/hr 0.750 117,000 87,750
Mandor org/hr 0.025 203,000 5,075
-
SNI 2835:2008 - 6.9 M3 Urugan tanah kembali 1/3 dari harga galian - - 30,942 10% 34,036
Pekerja org/hr 0.250 117,000 29,250
Mandor org/hr 0.008 203,000 1,692
-
-
SNI 2835:2008 - 6.11 M3 Pas. Urugan pasir - 115,200 37,130 152,330
Pasir Urug m3 1.200 96,000 115,200
Pekerja org/hr 0.300 117,000 35,100
Mandor org/hr 0.010 203,000 2,030
-
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL
DAN MATERIAL
Material Upah lain-lain
-
SNI 2835:2008 - 6.8 M3 Buang tanah Jarak angkut +/- 15 M - - 40,640 10% 44,704
Pekerja org/hr 0.330 117,000 38,610
Mandor org/hr 0.010 203,000 2,030
PEKERJAAN PONDASI :
PEKERJAAN BETON : -
SNI 7394:2008-6.5 M3 Beton K - 175 Sitemix - 806,800 252,609 10% 1,165,350
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL
DAN MATERIAL
Material Upah lain-lain
Semen (50 Kg) zak 6.520 70,000 456,400
Pasir Beton m3 0.543 140,000 76,000
Batu Split Pecah Mesin 1/2 m3 0.762 360,000 274,400
Pekerja org/hr 1.650 117,000 193,050
Tukang Batu Kasar org/hr 0.275 138,000 37,950
Kepala Tukang Batu org/hr 0.028 170,000 4,760
Mandor org/hr 0.083 203,000 16,849
-
SNI 7394:2008-6.6 M3 Beton K - 200 Sitemix - 840,833 252,609 10% 1,202,787
Semen (50 Kg) zak 7.040 70,000 492,800
Pasir Beton m3 0.522 140,000 73,100
Batu Split Pecah Mesin 1/2 m3 0.764 360,000 274,933
Pekerja org/hr 1.650 117,000 193,050
Tukang Batu Kasar org/hr 0.275 138,000 37,950
Kepala Tukang Batu org/hr 0.028 170,000 4,760
Mandor org/hr 0.083 203,000 16,849
-
SNI 7394:2008-6.7 M3 Beton K - 225 Sitemix - 868,400 252,609 10% 1,233,110
Semen (50 Kg) zak 7.420 70,000 519,400
Pasir Beton m3 0.499 140,000 69,800
Batu Split Pecah Mesin 1/2 m3 0.776 360,000 279,200
Pekerja org/hr 1.650 117,000 193,050
Tukang Batu Kasar org/hr 0.275 138,000 37,950
Kepala Tukang Batu org/hr 0.028 170,000 4,760
Mandor org/hr 0.083 203,000 16,849
-
SNI 7394:2008-6.8 M3 Beton K - 250 Sitemix - 883,867 252,609 10% 1,250,123
Semen (50 Kg) zak 7.680 70,000 537,600
Pasir Beton m3 0.494 140,000 69,200
Batu Split Pecah Mesin 1/2 m3 0.770 360,000 277,067
Pekerja org/hr 1.650 117,000 193,050
Tukang Batu Kasar org/hr 0.275 138,000 37,950
Kepala Tukang Batu org/hr 0.028 170,000 4,760
Mandor org/hr 0.083 203,000 16,849
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL
DAN MATERIAL
Material Upah lain-lain
-
SNI 7394:2008-6.17 Kg Tulangan besi beton U-24 - 18,815 1,985 10% 22,880
Besi Beton U-24 kg 1.0500 17,500 18,375
Kawat beton kg 0.0150 29,300 440
Pekerja org/hr 0.0070 117,000 819
Tukang Besi Tulangan org/hr 0.0070 138,000 966
Kepala Tukang Besi org/hr 0.0007 170,000 119
Mandor org/hr 0.0004 203,000 81
-
SNI 7394:2008-6.17 Kg Tulangan besi beton U-39 - 18,815 1,985 10% 22,880
Besi Beton U-39 kg 1.0500 17,500 18,375
Kawat beton kg 0.0150 29,300 440
Pekerja org/hr 0.0070 117,000 819
Tukang Besi Tulangan org/hr 0.0070 138,000 966
Kepala Tukang Besi org/hr 0.0007 170,000 119
Mandor org/hr 0.0004 203,000 81
-
SNI 7394:2008-6.21 M2 Bekisting sloof beton - 168,380 106,649 10% 302,532
Kayu Klas III m3 0.045 3,500,000 157,500
Paku 5 s/d 10 cm kg 0.300 24,000 7,200
Minyak bekisting ltr 0.100 36,800 3,680
Pekerja org/hr 0.520 117,000 60,840
Tukang Kayu Kasar org/hr 0.260 138,888 36,111
Kepala Tukang Kayu org/hr 0.026 170,000 4,420
Mandor org/hr 0.026 203,000 5,278
-
SNI DT 91-0006-2007 M2 Bekisting Praktis beton - 8,320 106,649 10% 126,466
Kayu Klas IV Kayu klas IV m3 0.002 2,200,000 4,400
Paku 5 s/d 10 cm kg 0.010 24,000 240
Minyak bekisting ltr 0.100 36,800 3,680
Pekerja org/hr 0.520 117,000 60,840
Tukang Kayu Kasar org/hr 0.260 138,888 36,111
Kepala Tukang Kayu org/hr 0.026 170,000 4,420
Mandor org/hr 0.026 203,000 5,278
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL
DAN MATERIAL
Material Upah lain-lain
-
-
SNI 7394:2008-6.24 M2 Bekisting beton plat lantai 464,960 135,362 10% 660,354
Triplex t. 9 mm lbr 0.350 130,000 45,500
Paku 5 s/d 10 cm kg 0.400 24,000 9,600
Kayu Klas II Balok,Kayu klas III m3 0.015 4,500,000 67,500
Kayu Klas III Kaso, Kayu klas IV m3 0.040 3,500,000 140,000
Dolken dia 8 s/d 10 cm btg 6.000 32,500 195,000
Minyak bekisting ltr 0.200 36,800 7,360
Pekerja org/hr 0.660 117,000 77,220
Tukang Kayu Kasar org/hr 0.330 138,888 45,833
Kepala Tukang Kayu org/hr 0.033 170,000 5,610
Mandor org/hr 0.033 203,000 6,699
-
SNI 7394:2008-6.22 M2 Bekisting kolom beton - 334,960 135,362 10% 517,354
Triplex t. 9 mm lbr 0.350 130,000 45,500
Paku 5 s/d 10 cm kg 0.400 24,000 9,600
Kayu Klas II Balok, Kayu klas IV m3 0.015 4,500,000 67,500
Kayu Klas III Kaso, Kayu klas IV m3 0.040 3,500,000 140,000
Dolken dia 8 s/d 10 cm btg 2.000 32,500 65,000
Minyak bekisting ltr 0.200 36,800 7,360
Pekerja org/hr 0.660 117,000 77,220
Tukang Kayu Kasar org/hr 0.330 138,888 45,833
Kepala Tukang Kayu org/hr 0.033 170,000 5,610
Mandor org/hr 0.033 203,000 6,699
-
SNI 7394:2008-6.23 M2 Bekisting balok beton - 348,460 135,362 10% 532,204
Triplex t. 9 mm lbr 0.350 130,000 45,500
Paku 5 s/d 10 cm kg 0.400 24,000 9,600
Kayu Klas II Balok,Kayu klas III m3 0.018 4,500,000 81,000
Kayu Klas III Kaso, Kayu klas IV m3 0.040 3,500,000 140,000
Dolken dia 8 s/d 10 cm btg 2.000 32,500 65,000
Minyak bekisting ltr 0.200 36,800 7,360
Pekerja org/hr 0.660 117,000 77,220
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL
DAN MATERIAL
Material Upah lain-lain
Tukang Kayu Kasar org/hr 0.330 138,888 45,833
Kepala Tukang Kayu org/hr 0.033 170,000 5,610
Mandor org/hr 0.033 203,000 6,699
-
M2 Pas. Lantai kerja beton tumbuk 1:3:5 t. 10 cm - 59,700 - 10% 65,670
Semen (50 Kg) zak 0.300 70,000 21,000
Pasir Beton m3 0.063 140,000 8,820
Batu Split Pecah Mesin 1/2 m3 0.083 360,000 29,880
Pekerja org/hr 0.130 117,000 15,210
Tukang Batu Kasar org/hr 0.100 138,000 13,800
Kepala Tukang Batu org/hr 0.010 170,000 1,700
Mandor org/hr 0.010 203,000 2,030
-
PEKERJAAN DINDING -
SNI 6897:2008-6.16 M2 Pas. Dinding bata beton ringan; ad 1:3 - 272,754 67,854 10% 374,669
Bata beton ringan ex Celcon bh 12.500 11,000 137,500
Semen (50 Kg) zak 0.606 70,000 42,448
Besi angkur d= 8 mm kg 0.280 14,250 3,990
Pasir Pasang m3 0.728 122,000 88,816
Pekerja org/hr 0.350 117,000 40,950
Tukang Batu Kasar org/hr 0.150 138,000 20,700
Kepala Tukang Batu org/hr 0.015 170,000 2,550
Mandor org/hr 0.018 203,000 3,654
-
SNI 6897:2008-6.17 M2 Pas. Dinding bata beton ringan; ad 1:4 - 269,638 67,854 10% 371,241
Bata beton ringan ex Celcon bh 12.500 11,000 137,500
Semen (50 Kg) zak 0.485 70,000 33,964
Pasir Pasang m3 0.772 122,000 94,184
Besi angkur d= 8 mm kg 0.280 14,250 3,990
Pekerja org/hr 0.350 117,000 40,950
Tukang Batu Kasar org/hr 0.150 138,000 20,700
Kepala Tukang Batu org/hr 0.015 170,000 2,550
Mandor org/hr 0.018 203,000 3,654
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL
DAN MATERIAL
Material Upah lain-lain
-
SNI 6897:2008-6.7 M2 Pas. Dinding batu bata; ad 1:2 - 83,666 53,645 10% 151,042
Bata Merah bh 70.000 750 52,500
Semen (50 Kg) zak 0.379 70,000 26,530
Pasir Pasang m3 0.038 122,000 4,636
Pekerja org/hr 0.300 117,000 35,100
Tukang Batu Kasar org/hr 0.100 138,000 13,800
Kepala Tukang Batu org/hr 0.010 170,000 1,700
Mandor org/hr 0.015 203,000 3,045
-
SNI 6897:2008-6.7 M3 Pas. Dinding batu bata; ad 1:4 - 73,846 53,645 10% 140,240
Bata Merah bh 70.000 750 52,500
Semen (50 Kg) zak 0.230 70,000 16,100
Pasir Pasang m3 0.043 122,000 5,246
Pekerja org/hr 0.300 117,000 35,100
Tukang Batu Kasar org/hr 0.100 138,000 13,800
Kepala Tukang Batu org/hr 0.010 170,000 1,700
Mandor org/hr 0.015 203,000 3,045
-
M2 Pas. Dinding partisi gypsumboard Rangka Kayu - 180,166 283,856 10% 510,424
Kayu Klas III Balok m3 0.028 3,500,000 98,000
Paku 8 s/d 12 cm kg 0.150 20,000 3,000
Gypsumboard t.9 mm lbr 0.860 84,500 72,670
Lem Kayu kg 0.560 11,600 6,496
Pekerja org/hr 0.028 117,000 3,276
Tukang Kayu Halus org/hr 0.150 138,000 20,700
Kepala Tukang Kayu org/hr 0.860 170,000 146,200
Mandor org/hr 0.560 203,000 113,680
-
M2 Pas. Dinding partisi gypsumboard Rangka Metal Furing - 163,670 283,856 10% 492,279
Rangka plafond Metal furing termasuk ripet m2 1.000 91,000 91,000
Gypsumboard t.9 mm lbr 0.860 84,500 72,670
Pekerja org/hr 0.028 117,000 3,276
Tukang Kayu Halus org/hr 0.150 138,000 20,700
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL
DAN MATERIAL
Material Upah lain-lain
Kepala Tukang Kayu org/hr 0.860 170,000 146,200
Mandor org/hr 0.560 203,000 113,680
-
M2 Pas. Dinding partisi Toilet;triplek 9 mm - 217,796 283,856 10% 551,817
Kayu Klas III m3 0.028 3,500,000 98,000
Triplex t. 9 mm lbr 0.860 130,000 111,800
Paku Skrup bh 6.000 250 1,500
Lem Kayu kg 0.560 11,600 6,496
Pekerja org/hr 0.028 117,000 3,276
Tukang Kayu Halus org/hr 0.150 138,000 20,700
Kepala Tukang Kayu org/hr 0.860 170,000 146,200
Mandor org/hr 0.560 203,000 113,680
-
-
PEKERJAAN PLESTERAN : -
-
SNI 2837:2008-6.2 M2 Pas. Plester acian; ad. 1:2 t.15 mm; tanpa aci - 16,754 61,395 10% 85,963
Semen (50 Kg) zak 0.204 70,000 14,314
Pasir Pasang m3 0.020 122,000 2,440
Pekerja org/hr 0.300 117,000 35,100
Tukang Batu Kasar org/hr 0.150 138,000 20,700
Kepala Tukang Batu org/hr 0.015 170,000 2,550
Mandor org/hr 0.015 203,000 3,045
-
SNI 2837:2008-6.4 M2 Pas. Plester acian; ad. 1:4 t.15 mm; tanpa aci - 11,664 61,395 10% 80,365
Semen (50 Kg) zak 0.125 70,000 8,736
Pasir Pasang m3 0.024 122,000 2,928
Pekerja org/hr 0.300 117,000 35,100
Tukang Batu Kasar org/hr 0.150 138,000 20,700
Kepala Tukang Batu org/hr 0.015 170,000 2,550
Mandor org/hr 0.015 203,000 3,045
-
SNI 2837:2008-6.27 M2 Pas. Acian PC - 4,550 40,930 10% 50,028
Semen (50 Kg) zak 0.065 70,000 4,550
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL
DAN MATERIAL
Material Upah lain-lain
Pekerja org/hr 0.200 117,000 23,400
Tukang Batu Kasar org/hr 0.100 138,000 13,800
Kepala Tukang Batu org/hr 0.010 170,000 1,700
Mandor org/hr 0.010 203,000 2,030
-
-
PEKERJAAN LANGIT-LANGIT -
M2 Pas. Rangka Plafond Metal furing 95,550 71,930 10% 184,228
Rangka plafond Metal furing m2 1.050 91,000 95,550
Pekerja org/hr 0.200 117,000 23,400
Tukang Besi Konstruksi org/hr 0.300 138,000 41,400
Kepala Tukang Besi org/hr 0.030 170,000 5,100
Mandor org/hr 0.010 203,000 2,030
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL
DAN MATERIAL
Material Upah lain-lain
-
SNI 3434:2008-6.19 M2 Pas. Rangka Plafond Kayu Meranti - 74,100 85,391 10% 175,441
Kayu Klas II kaso m3 0.015 4,500,000 69,300
Paku 5 s/d 10 cm kg 0.200 24,000 4,800
Pekerja org/hr 0.200 117,000 23,400
Tukang Kayu Kasar org/hr 0.300 138,888 41,666
Kepala Tukang Kayu org/hr 0.030 170,000 5,100
Mandor org/hr 0.075 203,000 15,225
-
SNI 3434:2008-6.19 M2 Pas. Rangka Plafond Kayu - 58,700 85,391 10% 158,501
Kayu Klas III kaso m3 0.015 3,500,000 53,900
Paku 5 s/d 10 cm kg 0.200 24,000 4,800
Pekerja org/hr 0.200 117,000 23,400
Tukang Kayu Kasar org/hr 0.300 138,888 41,666
Kepala Tukang Kayu org/hr 0.030 170,000 5,100
Mandor org/hr 0.075 203,000 15,225
-
SNI 2839:2008-6.7 M2 Pas. Penutup Plafond Gypsumboard t. 9 mm - 30,786 20,509 10% 56,424
Gypsumboard t.9 mm lbr 0.364 84,500 30,758
Paku Skrup kg 0.110 250 28
Pekerja org/hr 0.100 117,000 11,700
Tukang Kayu Kasar org/hr 0.050 138,888 6,944
Kepala Tukang Kayu org/hr 0.005 170,000 850
Mandor org/hr 0.005 203,000 1,015
-
SNI 2839:2008-6.5 M2 Pas. Penutup Plafond Triplex t. 4 mm - 28,133 28,304 10% 62,080
Triplex t. 4 mm lbr 0.375 75,000 28,125
Paku Skrup kg 0.030 250 8
Pekerja org/hr 0.100 117,000 11,700
Tukang Kayu Kasar org/hr 0.100 138,888 13,889
Kepala Tukang Kayu org/hr 0.010 170,000 1,700
Mandor org/hr 0.005 203,000 1,015
-
SNI 2839:2008-6.8 M Pas. List Profil Gypsum t. 5 cm - 39,798 16,982 10% 62,458
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL
DAN MATERIAL
Material Upah lain-lain
List Profil 5 cm Gypsum m 1.050 37,900 39,795
Paku Skrup kg 0.010 250 3
Pekerja org/hr 0.060 117,000 7,020
Tukang Kayu Kasar org/hr 0.060 138,888 8,333
Kepala Tukang Kayu org/hr 0.006 170,000 1,020
Mandor org/hr 0.003 203,000 609
-
-
PEKERJAAN RANGKA & PENUTUP ATAP -
-
M2 Rangka atap baja ringan Zingkalume 250,000 250,000 47,585 10% 327,344
Rangka atap baja ringan m2 1.000 250,000 250,000
Pekerja org/hr 0.080 117,000 9,360
Tukang Kayu Kasar org/hr 0.240 138,888 33,333
Kepala Tukang Kayu org/hr 0.024 170,000 4,080
Mandor org/hr 0.004 203,000 812
-
SNI 3434:2008-6.13 M3 Pas. Kuda kuda Kayu Konvensional - 5,275,750 2,379,256 10% 8,420,507
Kayu Klas II balok m3 1.100 4,500,000 4,950,000
Besi Plat rata2 kg 15.000 14,250 213,750
Paku 8 s/d 12 cm kg 5.600 20,000 112,000
Pekerja org/hr 4.000 117,000 468,000
Tukang Kayu Kasar org/hr 12.000 138,888 1,666,656
Kepala Tukang Kayu org/hr 1.200 170,000 204,000
Mandor org/hr 0.200 203,000 40,600
-
SNI 3434:2008-6.15 M3 Gording Kayu - 5,223,750 1,427,554 10% 7,316,434
Kayu Klas II Balok m3 1.100 4,500,000 4,950,000
Besi Plat rata2 kg 15.000 14,250 213,750
Paku 8 s/d 12 cm kg 3.000 20,000 60,000
Pekerja org/hr 2.400 117,000 280,800
Tukang Kayu Kasar org/hr 7.200 138,888 999,994
Kepala Tukang Kayu org/hr 0.720 170,000 122,400
Mandor org/hr 0.120 203,000 24,360
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL
DAN MATERIAL
Material Upah lain-lain
-
SNI 3434:2008-6.16 M2 Rangka Atap kayu - 231,000 28,304 10% 285,234
Kayu Klas II kaso m3 0.014 4,500,000 63,000
Kayu Klas II reng (0,036 m3) m3 0.036 4,500,000 162,000
Paku 5 s/d 10 cm kg 0.250 24,000 6,000
Pekerja org/hr 0.100 117,000 11,700
Tukang Kayu Kasar org/hr 0.100 138,888 13,889
Kepala Tukang Kayu org/hr 0.010 170,000 1,700
Mandor org/hr 0.005 203,000 1,015
-
SNI 02-3436-1994 M2 Penutup atap Genteng Keramik ex Jatiwangi - 270,000 30,884 10% 330,972
Genteng Keramik bh 25.000 10,800 270,000
Pekerja org/hr 0.150 117,000 17,550
Tukang Batu Kasar org/hr 0.075 138,000 10,350
Kepala Tukang Batu org/hr 0.008 170,000 1,360
Mandor org/hr 0.008 203,000 1,624
-
SNI 02-3436-1994 M2 Penutup atap Genteng Keramik Glazur ex KANMURI - 235,625 30,884 10% 293,160
Genteng Keramik Glazur bh 14.500 16,250 235,625
Pekerja org/hr 0.150 117,000 17,550
Tukang Batu Kasar org/hr 0.075 138,000 10,350
Kepala Tukang Batu org/hr 0.008 170,000 1,360
Mandor org/hr 0.008 203,000 1,624
-
SNI 02-3436-1994 M2 Bubungan Genteng Keramik - 73,024 78,206 10% 166,353
Nok Genteng Keramik bh 5.000 10,800 54,000
Semen (50 Kg) zak 0.216 70,000 15,120
Pasir Pasang m3 0.032 122,000 3,904
Pekerja org/hr 0.400 117,000 46,800
Tukang Batu Kasar org/hr 0.200 138,000 27,600
Kepala Tukang Batu org/hr 0.020 170,000 3,400
Mandor org/hr 0.002 203,000 406
-
SNI 02-3436-1994 M2 Bubungan Genteng Keramik Glazur - 100,274 78,206 10% 196,328
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL
DAN MATERIAL
Material Upah lain-lain
Nok Genteng Keramik Glasur bh 5.000 16,250 81,250
Semen (50 Kg) zak 0.216 70,000 15,120
Pasir Pasang m3 0.032 122,000 3,904
Pekerja org/hr 0.400 117,000 46,800
Tukang Batu Kasar org/hr 0.200 138,000 27,600
Kepala Tukang Batu org/hr 0.020 170,000 3,400
Mandor org/hr 0.002 203,000 406
-
SNI DT 91-0011-2007 M1 Pas. Lisplank Kayu 3/20 mm - 51,000 43,893 10% 104,382
Kayu Klas II papan uk. 3/20 m3 0.011 4,500,000 48,600
Paku 5 s/d 10 cm kg 0.100 24,000 2,400
Pekerja org/hr 0.100 117,000 11,700
Tukang Kayu Kasar org/hr 0.200 138,888 27,778
Kepala Tukang Kayu org/hr 0.020 170,000 3,400
Mandor org/hr 0.005 203,000 1,015
-
M1 Pas. Fleshing seng plat - 11,400 43,893 10% 60,822
Seng Plat BJLS 30 uk. 3/20 m2 0.450 20,000 9,000
Paku 5 s/d 10 cm kg 0.100 24,000 2,400
Pekerja org/hr 0.100 117,000 11,700
Tukang Kayu Kasar org/hr 0.200 138,888 27,778
Kepala Tukang Kayu org/hr 0.020 170,000 3,400
Mandor org/hr 0.005 203,000 1,015
-
SNI 7393:2008-6.19 M1 Pas. Talang seng plat - 28,365 65,940 10% 103,736
Seng Plat BJLS 30 uk. 3/20 m2 1.050 20,000 21,000
Paku 1 s/d 3 cm kg 0.010 24,000 240
Besi Plat rata2 kg 0.500 14,250 7,125
Pekerja org/hr 0.150 117,000 17,550
Tukang Kayu Kasar org/hr 0.300 138,888 41,666
Kepala Tukang Kayu org/hr 0.030 170,000 5,100
Mandor org/hr 0.008 203,000 1,624
-
-
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL
DAN MATERIAL
Material Upah lain-lain
PEKERJAAN PENGECATAN -
PT T-38-2000-C M2 Cat dinding dalam acrylic emulsion KW.I Interior - 19,160 12,613 10% 34,950
Lapis Cat Dasar + 2
Plamir Tembok kg 0.100 74,600 7,460
Lapis + 2 Lapis Cat
Cat Tembok kw1 Penutup ) kg 0.100 32,500 3,250
Cat Tembok kw1 kg 0.260 32,500 8,450
Pekerja org/hr 0.020 117,000 2,340
Tukang Cat Biasa org/hr 0.063 138,000 8,694
Kepala Tukang Cat org/hr 0.006 170,000 1,071
Mandor org/hr 0.003 203,000 508
-
PT T-38-2000-C M2 Cat dinding dalam acrylic emulsion KW.II Interior - 18,728 12,613 10% 34,475
Lapis Cat Dasar + 2
Plamir Tembok kg 0.100 74,600 7,460
Lapis + 2 Lapis Cat
Cat Tembok kw2 Penutup ) kg 0.100 31,300 3,130
Cat Tembok kw2 kg 0.260 31,300 8,138
Pekerja org/hr 0.020 117,000 2,340
Tukang Cat Biasa org/hr 0.063 138,000 8,694
Kepala Tukang Cat org/hr 0.006 170,000 1,071
Mandor org/hr 0.003 203,000 508
-
-
PT T-38-2000-C M2 Cat dinding luar weathershiled KW.I Eksterior - 19,160 12,613 10% 34,950
Lapis Cat Dasar + 2
Plamir Tembok kg 0.100 74,600 7,460
Lapis + 2 Lapis Cat
Cat Tembok kw1 Penutup ) kg 0.100 32,500 3,250
Cat Tembok kw1 kg 0.260 32,500 8,450
Pekerja org/hr 0.020 117,000 2,340
Tukang Cat Biasa org/hr 0.063 138,000 8,694
Kepala Tukang Cat org/hr 0.006 170,000 1,071
Mandor org/hr 0.003 203,000 508
-
PT T-38-2000-C M2 Cat dinding luar weathershiled KW.II Eksterior - 18,728 12,613 10% 34,475
Lapis Cat Dasar + 2
Plamir Tembok kg 0.100 74,600 7,460
Lapis + 2 Lapis Cat
Cat Tembok kw2 Penutup ) kg 0.100 31,300 3,130
Cat Tembok kw2 kg 0.260 31,300 8,138
Pekerja org/hr 0.020 117,000 2,340
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL
DAN MATERIAL
Material Upah lain-lain
Tukang Cat Biasa org/hr 0.063 138,000 8,694
Kepala Tukang Listrik org/hr 0.006 170,000 1,071
Mandor org/hr 0.003 203,000 508
-
-
PT T-38-2000-C M2 Cat plafond acrylic emulsion KW.I Interior - 19,160 12,613 10% 34,950
Lapis Cat Dasar + 2
Plamir Tembok kg 0.100 74,600 7,460
Lapis + 2 Lapis Cat
Cat Tembok kw1 Penutup ) kg 0.100 32,500 3,250
Cat Tembok kw1 kg 0.260 32,500 8,450
Pekerja org/hr 0.020 117,000 2,340
Tukang Cat Biasa org/hr 0.063 138,000 8,694
Kepala Tukang Cat org/hr 0.006 170,000 1,071
Mandor org/hr 0.003 203,000 508
-
PT T-38-2000-C M2 Cat plafond acrylic emulsion KW.II Interior - 18,728 12,613 10% 34,475
Lapis Cat Dasar + 2
Plamir Tembok kg 0.100 74,600 7,460
Lapis + 2 Lapis Cat
Cat Tembok kw2 Penutup ) kg 0.100 31,300 3,130
Cat Tembok kw2 kg 0.260 31,300 8,138
Pekerja org/hr 0.020 117,000 2,340
Tukang Cat Biasa org/hr 0.063 138,000 8,694
Kepala Tukang Cat org/hr 0.006 170,000 1,071
Mandor org/hr 0.003 203,000 508
-
-
( 1 Lapis Plamir + 1
PT T-38-2000-C M2 Cat kayu synthetic - 40,161 35,885 10% 83,651
Lapis Cat Dasar + 2
Plamir Kayu Lapis Cat Penutup ) kg 0.150 31,000 4,650
Meni kayu kg 0.200 32,000 6,400
Cat kayu/Besi Cat dasar 1x kg 0.170 67,700 11,509
Cat kayu/Besi Cat akhir 2x kg 0.260 67,700 17,602
Pekerja org/hr 0.070 117,000 8,190
Tukang Cat Biasa org/hr 0.090 138,000 12,420
Kepala Tukang Cat org/hr 0.060 170,000 10,200
Mandor org/hr 0.025 203,000 5,075
-
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL
DAN MATERIAL
Material Upah lain-lain
( 1 Lapis Plamir + 1
PT T-38-2000-C M2 Cat besi synthetic - 40,161 35,885 10% 83,651
Lapis Cat Dasar + 2
Plamir Kayu Lapis Cat Penutup ) kg 0.150 31,000 4,650
Meni kayu kg 0.200 32,000 6,400
Cat kayu/Besi Cat dasar 1x kg 0.170 67,700 11,509
Cat kayu/Besi Cat akhir 2x kg 0.260 67,700 17,602
Pekerja org/hr 0.070 117,000 8,190
Tukang Cat Biasa org/hr 0.090 138,000 12,420
Kepala Tukang Cat org/hr 0.060 170,000 10,200
Mandor org/hr 0.025 203,000 5,075
-
-
PEKERJAAN KUSEN -
SNI 7393:2008-6.11 M Kusen Pintu dan Jendela Alumunium CA 133.333 319,060 12,122 10% 364,301
Kusen Almunium m 1.100 289,600 318,560
Paku Skrup bh 2.000 250 500
Pekerja org/hr 0.043 117,000 5,031
Tukang Kayu Halus org/hr 0.043 138,000 5,934
Kepala Tukang Kayu org/hr 0.004 170,000 731
Mandor org/hr 0.002 203,000 426
-
SNI 7393:2008-6.11 M Kusen Pintu dan Jendela Alumunium PC 133.333 319,060 12,122 10% 364,301
Kusen Almunium m 1.100 289,600 318,560
Paku Skrup bh 2.000 250 500
Pekerja org/hr 0.043 117,000 5,031
Tukang Kayu Halus org/hr 0.043 138,000 5,934
Kepala Tukang Kayu org/hr 0.004 170,000 731
Mandor org/hr 0.002 203,000 426
-
unt Kusen & Pintu PVC toilet 133.333 245,250 26,647 10% 299,086
Kusen & Pintu PVC toilet m 1.000 243,750 243,750
Paku Skrup bh 6.000 250 1,500
Pekerja org/hr 0.045 117,000 5,265
Tukang Kayu Halus org/hr 0.135 138,000 18,630
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL
DAN MATERIAL
Material Upah lain-lain
Kepala Tukang Kayu org/hr 0.014 170,000 2,295
Mandor org/hr 0.002 203,000 457
-
SNI 7393:2008-6.11 M RangkaPintu Alumunium CA 133.333 - 358,000 12,122 10% 407,135
Rangka Pintu Almunium m 1.100 325,000 357,500
Paku Skrup bh 2.000 250 500
Pekerja org/hr 0.043 117,000 5,031
Tukang Kayu Halus org/hr 0.043 138,000 5,934
Kepala Tukang Kayu org/hr 0.004 170,000 731
Mandor org/hr 0.002 203,000 426
-
SNI 7393:2008-6.11 M Rangka Pintu Alumunium PC 133.333 - 358,000 12,122 10% 407,135
Rangka Pintu Almunium m 1.100 325,000 357,500
Paku Skrup bh 2.000 250 500
Pekerja org/hr 0.043 117,000 5,031
Tukang Batu Halus org/hr 0.043 138,000 5,934
Kepala Tukang Kayu org/hr 0.004 170,000 731
Mandor org/hr 0.002 203,000 426
-
-
M Rangka Jendela Alumunium 133.333 - 341,500 26,647 10% 404,961
Rangka Jendela Almunium m 1.050 325,000 341,250
Paku Skrup bh 1.000 250 250
Pekerja org/hr 0.045 117,000 5,265
Tukang Kayu Halus org/hr 0.135 138,000 18,630
Kepala Tukang Kayu org/hr 0.014 170,000 2,295
Mandor org/hr 0.002 203,000 457
-
M Rangka Jendela Alumunium 133.333 - 341,500 26,647 10% 404,961
Rangka Pintu Almunium m 1.050 325,000 341,250
Paku Skrup bh 1.000 250 250
Pekerja org/hr 0.045 117,000 5,265
Tukang Kayu Halus org/hr 0.135 138,000 18,630
Kepala Tukang Kayu org/hr 0.014 170,000 2,295
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL
DAN MATERIAL
Material Upah lain-lain
Mandor org/hr 0.002 203,000 457
-
-
SNI 3434:2008-6.1 M3 Kusen Pintu dan Jendela Kayu KW.I - 13,241,600 4,145,050 10% 19,125,315
Kayu Klas I Balok m3 1.100 12,000,000 13,200,000
Paku 5 s/d 10 cm kg 1.250 24,000 30,000
Lem Kayu kg 1.000 11,600 11,600
Pekerja org/hr 7.000 117,000 819,000
Tukang Kayu Halus org/hr 21.000 138,000 2,898,000
Kepala Tukang Kayu org/hr 2.100 170,000 357,000
Mandor org/hr 0.350 203,000 71,050
-
SNI 3434:2008-6.2 M3 Kusen Pintu dan Jendela Kayu KW.II - 5,441,600 3,552,900 10% 9,893,950
Kayu Klas II balok m3 1.200 4,500,000 5,400,000
Paku 5 s/d 10 cm kg 1.250 24,000 30,000
Lem Kayu kg 1.000 11,600 11,600
Pekerja org/hr 6.000 117,000 702,000
Tukang Kayu Halus org/hr 18.000 138,000 2,484,000
Kepala Tukang Kayu org/hr 1.800 170,000 306,000
Mandor org/hr 0.300 203,000 60,900
-
SNI 3434:2008-6.2 M3 Kusen Pintu dan Jendela Kayu KW.III - 4,241,600 3,552,900 10% 8,573,950
Kayu Klas III balok m3 1.200 3,500,000 4,200,000
Paku 5 s/d 10 cm kg 1.250 24,000 30,000
Lem Kayu kg 1.000 11,600 11,600
Pekerja org/hr 6.000 117,000 702,000
Tukang Kayu Halus org/hr 18.000 138,000 2,484,000
Kepala Tukang Kayu org/hr 1.800 170,000 306,000
Mandor org/hr 0.300 203,000 60,900
-
SNI 3434:2008-6.6 M2 Daun Pintu dan Jendela Kayu KW.I Pintu & jendela kaca - 291,480 473,720 10% 841,720
Kayu Klas I Papan m3 0.024 12,000,000 288,000
Lem Kayu kg 0.300 11,600 3,480
Pekerja org/hr 0.800 117,000 93,600
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL
DAN MATERIAL
Material Upah lain-lain
Tukang Kayu Halus org/hr 2.400 138,000 331,200
Kepala Tukang Kayu org/hr 0.240 170,000 40,800
Mandor org/hr 0.040 203,000 8,120
-
SNI 3434:2008-6.6 M2 Daun Pintu dan Jendela Kayu KW.II Pintu & jendela kaca - 111,480 473,720 10% 643,720
Kayu Klas II Papan m3 0.024 4,500,000 108,000
Lem Kayu kg 0.300 11,600 3,480
Pekerja org/hr 0.800 117,000 93,600
Tukang Kayu Halus org/hr 2.400 138,000 331,200
Kepala Tukang Kayu org/hr 0.240 170,000 40,800
Mandor org/hr 0.040 203,000 8,120
-
SNI 3434:2008-6.4 M2 Daun Pintu dan Jendela Kayu KW.III Pintu & jendela kaca - 152,000 191,289 10% 377,618
Kayu Klas III Papan m3 0.040 3,500,000 140,000
Paku 5 s/d 10 cm kg 0.500 24,000 12,000
Pekerja org/hr 0.350 117,000 40,950
Tukang Kayu Halus org/hr 1.050 138,000 144,900
Kepala Tukang Kayu org/hr 0.011 170,000 1,785
Mandor org/hr 0.018 203,000 3,654
-
SNI 3434:2008-6.5 M2 Daun Pintu Panel KW.I - 485,800 592,150 10% 1,185,745
Kayu Klas I papan m3 0.040 12,000,000 480,000
Lem Kayu kg 0.500 11,600 5,800
Pekerja org/hr 1.000 117,000 117,000
Tukang Kayu Halus org/hr 3.000 138,000 414,000
Kepala Tukang Kayu org/hr 0.300 170,000 51,000
Mandor org/hr 0.050 203,000 10,150
-
SNI 3434:2008-6.5 M2 Daun Pintu Panel KW.II - 185,800 592,150 10% 855,745
Kayu Klas II papan m3 0.040 4,500,000 180,000
Lem Kayu kg 0.500 11,600 5,800
Pekerja org/hr 1.000 117,000 117,000
Tukang Kayu Halus org/hr 3.000 138,000 414,000
Kepala Tukang Kayu org/hr 0.300 170,000 51,000
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL
DAN MATERIAL
Material Upah lain-lain
Mandor org/hr 0.050 203,000 10,150
-
SNI DT 91-0011-2007 M2 Daun Pintu Panel KW.III - 145,800 592,150 10% 811,745
Kayu Klas III papan m3 0.040 3,500,000 140,000
Lem Kayu kg 0.500 11,600 5,800
Pekerja org/hr 1.000 117,000 117,000
Tukang Kayu Halus org/hr 3.000 138,000 414,000
Kepala Tukang Kayu org/hr 0.300 170,000 51,000
Mandor org/hr 0.050 203,000 10,150
-
SNI 3434:2008-6.8 M2 Daun Pintu double teakwood; rangka kayu KW.II tertutup - 173,120 478,450 10% 716,727
Kayu Klas II papan m3 0.025 4,500,000 112,500
Lem Kayu kg 0.500 11,600 5,800
Paku 1 s/d 3 cm kg 0.030 24,000 720
Triplek t. 3 mm uk. 90x220 lbr 1.000 54,100 54,100
Pekerja org/hr 0.700 117,000 81,900
Tukang Kayu Halus org/hr 2.100 138,000 289,800
Kepala Tukang Kayu org/hr 0.210 170,000 35,700
Mandor org/hr 0.350 203,000 71,050
-
SNI DT 91-0011-2007 M2 Daun Pintu double triplex; rangka kayu KW.III tertutup - 244,020 473,720 10% 789,514
Kayu Klas III papan m3 0.025 3,500,000 87,500
Lem Kayu kg 0.500 11,600 5,800
Paku 1 s/d 3 cm kg 0.030 24,000 720
Triplex t. 4 mm uk. 90x220 lbr 2.000 75,000 150,000
Pekerja org/hr 0.800 117,000 93,600
Tukang Kayu Halus org/hr 2.400 138,000 331,200
Kepala Tukang Kayu org/hr 0.240 170,000 40,800
Mandor org/hr 0.040 203,000 8,120
-
SNI 7393:2008-6.4 M2 Pintu besi plat baja t. 2 mm rangkap; rangka besi siku - 682,615 296,156 10% 1,076,648
Besi Plat rata2 besi siku 30.30.3 m kg 15.000 14,250 213,750
Besi Plat rata2 besi plat kg 32.800 14,250 467,400
Kawat beton kg 0.050 29,300 1,465
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL
DAN MATERIAL
Material Upah lain-lain
Pekerja org/hr 1.050 117,000 122,850
Tukang Besi Konstruksi org/hr 1.050 138,000 144,900
Kepala Tukang Besi org/hr 0.105 170,000 17,850
Mandor org/hr 0.052 203,000 10,556
PEKERJAAN SANITER
RSNI T-15-2002 BH Pas. Washtafel keramik - 430,400 386,300 10% 898,370
Wastafel bh 1.000 417,000 417,000
Seal tape bh 1.000 13,400 13,400
Pekerja org/hr 1.200 117,000 140,400
Tukang Batu Halus org/hr 1.450 138,000 200,100
Kepala Tukang Batu org/hr 0.150 170,000 25,500
Mandor org/hr 0.100 203,000 20,300
RSNI T-15-2002 BH Pas. Kloset Duduk Keramik 2,500,000 559,848 10% 3,365,833
Kloset duduk bh 1.000 2,500,000 2,500,000
Pekerja org/hr 3.300 117,000 386,100
Tukang Batu Halus org/hr 1.100 138,000 151,800
Kepala Tukang Batu org/hr 0.110 170,000 18,700
Mandor org/hr 0.016 203,000 3,248
-
RSNI T-15-2002 BH Pas. Urinoir Keramik 1,202,500 559,848 10% 1,938,583
Urinoir bh 1.000 1,202,500 1,202,500
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL
DAN MATERIAL
Material Upah lain-lain
Pekerja org/hr 3.300 117,000 386,100
Tukang Batu Halus org/hr 1.100 138,000 151,800
Kepala Tukang Batu org/hr 0.110 170,000 18,700
Mandor org/hr 0.016 203,000 3,248
-
RSNI T-15-2002 BH Pas. Kloset Jongkok Keramik - 425,400 173,748 10% 659,063
Kloset Jongkok bh 1.000 417,000 417,000
Semen (50 Kg) zak 0.120 70,000 8,400
Pekerja org/hr 0.000 117,000 -
Tukang Batu Halus org/hr 1.100 138,000 151,800
Kepala Tukang Batu org/hr 0.110 170,000 18,700
Mandor org/hr 0.016 203,000 3,248
Perlengkapan -
-
RSNI T-15-2002 BH Pas. Bak Air Fiberglass - 812,500 697,330 10% 1,660,813
Bak air fibreglass bh 1.000 812,500 812,500
Pekerja org/hr 1.800 117,000 210,600
Tukang Batu Halus org/hr 2.700 138,000 372,600
Kepala Tukang Batu org/hr 0.540 170,000 91,800
Mandor org/hr 0.110 203,000 22,330
Perlengkapan harga 0.180 -
-
RSNI T-15-2002 BH Pas. Shower spray - 195,335 15,500 10% 231,919
Shower Spray bh 1.000 195,000 195,000
Seal tape bh 0.025 13,400 335
Pekerja org/hr 0.000 117,000 -
Tukang Batu Halus org/hr 0.100 138,000 13,800
Kepala Tukang Batu org/hr 0.010 170,000 1,700
Mandor org/hr 0.000 203,000 -
-
RSNI T-15-2002 BH Pas. Shower set - 162,835 173,748 10% 370,241
Shower Set bh 1.000 162,500 162,500
Seal tape bh 0.025 13,400 335
Pekerja org/hr 0.000 117,000 -
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL
DAN MATERIAL
Material Upah lain-lain
Tukang Batu Halus org/hr 1.100 138,000 151,800
Kepala Tukang Batu org/hr 0.110 170,000 18,700
Mandor org/hr 0.016 203,000 3,248
-
RSNI T-15-2002 BH Pas. Tempat sabun keramik - 116,700 36,200 10% 168,190
Tempat Sabun bh 1.000 108,300 108,300
Semen (50 Kg) zak 0.120 70,000 8,400
Pekerja org/hr 0.000 117,000 -
Tukang Batu Halus org/hr 0.250 138,000 34,500
Kepala Tukang Batu org/hr 0.010 170,000 1,700
Mandor org/hr 0.000 203,000 -
-
RSNI T-15-2002 BH Pas. Kitchenzink stainlees stell 1 lubang - 316,875 292,300 10% 670,093
Kitchenzink bh 1.000 243,750 243,750
Fitting, Stop valve & support set 0.300 243,750 73,125
Pekerja org/hr 1.000 117,000 117,000
Tukang Batu Halus org/hr 1.000 138,000 138,000
Kepala Tukang Batu org/hr 0.100 170,000 17,000
Mandor org/hr 0.100 203,000 20,300
-
RSNI T-15-2002 BH Pas. Kran zink - 189,835 15,500 10% 225,869
Kran zink bh 1.000 189,500 189,500
Seal tape bh 0.025 13,400 335
Pekerja org/hr 0.000 117,000 -
Tukang Batu Halus org/hr 0.100 138,000 13,800
Kepala Tukang Batu org/hr 0.010 170,000 1,700
Mandor org/hr 0.000 203,000 -
-
RSNI T-15-2002 BH Pas. Kran dinding - 135,335 15,500 10% 165,919
Kran dinding bh 1.000 135,000 135,000
Seal tape bh 0.025 13,400 335
Pekerja org/hr 0.000 117,000 -
Tukang Batu Halus org/hr 0.100 138,000 13,800
Kepala Tukang Batu org/hr 0.010 170,000 1,700
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL
DAN MATERIAL
Material Upah lain-lain
Mandor org/hr 0.000 203,000 -
-
RSNI T-15-2002 BH Pas. Floor Drain - 35,400 173,748 10% 230,063
Floordrain bh 1.000 27,000 27,000
Semen (50 Kg) zak 0.120 70,000 8,400
Pekerja org/hr 0.000 117,000 -
Tukang Batu Halus org/hr 1.100 138,000 151,800
Kepala Tukang Batu org/hr 0.110 170,000 18,700
Mandor org/hr 0.016 203,000 3,248
-
RSNI T-15-2002 BH Pas. Roof Drain - 111,400 173,748 10% 313,663
Roof Drain Metal bh 1.000 103,000 103,000
Semen (50 Kg) zak 0.120 70,000 8,400
Pekerja org/hr 0.000 117,000 -
Tukang Batu Halus org/hr 1.100 138,000 151,800
Kepala Tukang Batu org/hr 0.110 170,000 18,700
Mandor org/hr 0.016 203,000 3,248
-
unt Pas. Meja Pantry uk. 600x 1500 mm 1,288,908 - 10% 1,417,799
Beton K - 200 m3 0.090 1,202,800 108,252
Tulangan besi beton U-24 kg 9.000 22,900 206,100
Bekisting beton plat lantai m2 0.990 660,400 653,796
Pas. Dinding Keramik 300x300 m2 0.990 324,000 320,760
PEKERJAAN PIPA
RSNI T-15-2002 M1 Pipa PVC dia. 4" 285,200 31,234 10% 348,078
Pipa PVC dia 4" m 1.200 184,000 220,800
Perlengkapan m 0.350 184,000 64,400
Pekerja org/hr 0.081 117,000 9,477
Tukang Batu Halus org/hr 0.135 138,000 18,630
Kepala Tukang Batu org/hr 0.014 170,000 2,295
Mandor org/hr 0.004 203,000 832
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL
DAN MATERIAL
Material Upah lain-lain
RSNI T-15-2002 M1 Pipa PVC dia. 3" 224,750 31,214 10% 281,560
Pipa PVC dia 3" m 1.200 145,000 174,000
Perlengkapan m 0.350 145,000 50,750
Pekerja org/hr 0.081 117,000 9,477
Tukang Batu Halus org/hr 0.135 138,000 18,630
Kepala Tukang Batu org/hr 0.014 170,000 2,295
Mandor org/hr 0.004 203,000 812
RSNI T-15-2002 M1 Pipa PVC dia. 2" 155,000 20,816 10% 193,398
Pipa PVC dia 2" m 1.200 100,000 120,000
Perlengkapan m 0.350 100,000 35,000
Pekerja org/hr 0.054 117,000 6,318
Tukang Batu Halus org/hr 0.090 138,000 12,420
Kepala Tukang Batu org/hr 0.009 170,000 1,530
Mandor org/hr 0.003 203,000 548
RSNI T-15-2002 M1 Pipa PVC dia. 1" 74,400 13,877 10% 97,105
Pipa PVC dia 1" m 1.200 48,000 57,600
Perlengkapan m 0.350 48,000 16,800
Pekerja org/hr 0.036 117,000 4,212
Tukang Batu Halus org/hr 0.060 138,000 8,280
Kepala Tukang Batu org/hr 0.006 170,000 1,020
Mandor org/hr 0.002 203,000 365
RSNI T-15-2002 M1 Pipa PVC dia. 3/4" 58,900 13,877 10% 80,055
Pipa PVC dia 3/4" m 1.200 38,000 45,600
Perlengkapan m 0.350 38,000 13,300
Pekerja org/hr 0.036 117,000 4,212
Tukang Batu Halus org/hr 0.060 138,000 8,280
Kepala Tukang Batu org/hr 0.006 170,000 1,020
Mandor org/hr 0.002 203,000 365
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL
DAN MATERIAL
Material Upah lain-lain
RSNI T-15-2002 M1 Pipa PVC dia. 1/2" 41,075 13,877 10% 60,448
Pipa PVC dia 1/2" m 1.200 26,500 31,800
Perlengkapan m 0.350 26,500 9,275
Pekerja org/hr 0.036 117,000 4,212
Tukang Batu Halus org/hr 0.060 138,000 8,280
Kepala Tukang Batu org/hr 0.006 170,000 1,020
Mandor org/hr 0.002 203,000 365
UNIT Septictank Pas. Bata kap. 3,00 m3 + Rembesanuk. 2 X 1,5 X 1 m + Rembesan 4,134,161 - 10% 4,547,577
Galian tanah, dalam s/d 1 m 3 m3 3.000 102,100 306,300
Pas. Urugan pasir m3 0.300 152,300 45,690
Pas. Lantai kerja beton tumbuk 1:3:5 m2 3.000 65,700 197,100
Pas. Dinding batu bata; ad 1:2 m2 10.500 151,000 1,585,500
Pas. Plester acian; ad. 1:2 m2 12.000 86,000 1,032,000
Beton K - 200 Balok & Tutup manh m3 0.360 1,202,800 433,008
Pipa PVC dia. 4" AW m' 5.400 - -
Pipa PVC dia. 1" AW m' 1.200 - -
Galian tanah, dalam s/d 1 m m3 3.375 102,100 344,588
Batu Kerikil urugan m3 1.050 144,500 151,725
Pipa PVC dia. 4" AW perforated m' 9.000 - -
Urugan tanah kembali m3 1.125 34,000 38,250
UNIT Septictank Pas. Bata + Rembesan kap. 6,00 m3 uk. 2 X 1,5 X 2 m + Rembesan 6,109,961 - 10% 6,720,957
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL
DAN MATERIAL
Material Upah lain-lain
Galian tanah, dalam s/d 1 m 6 m3 6.000 102,100 612,600
Pas. Urugan pasir m3 0.300 152,300 45,690
Pas. Lantai kerja beton tumbuk 1:3:5 m2 3.000 65,700 197,100
Pas. Dinding batu bata; ad 1:2 m2 17.000 151,000 2,567,000
Pas. Plester acian; ad. 1:2 m2 20.000 86,000 1,720,000
Beton K - 200 Balok & Tutup manh m3 0.360 1,202,800 433,008
Pipa PVC dia. 4" AW m' 5.400 - -
Pipa PVC dia. 1" AW m' 1.200 - -
Galian tanah, dalam s/d 1 m m3 3.375 102,100 344,588
Batu Kerikil urugan m3 1.050 144,500 151,725
Pipa PVC dia. 4" AW berlobang m' 9.000 - -
Urugan tanah kembali m3 1.125 34,000 38,250
PEKERJAAN ELEKTRIKAL
TTK TTK Pas. Instalasi stop kontak 185,450 45,910 10% 254,496
Kabel NYM 3 x 2,5 mm2 m 6.000 30,000 180,000
Isolasi bh 0.500 10,000 5,000
Klem bh 3.000 150 450
Pekerja org/hr 0.050 117,000 5,850
Tukang Listrik org/hr 0.020 138,000 2,760
Kepala Tukang Listrik org/hr 0.100 170,000 17,000
Mandor org/hr 0.100 203,000 20,300
menu ANALISA HARSA SATUAN
Berdasarkan SNI 2007 - 2008
10%
Overhead
HARGA UPAH JUMLAH HARGA
SUMBER DATA UNIT URAIAN SATUAN KOEFISIEN Asuransi TOTAL
DAN MATERIAL
Material Upah lain-lain
14,000
19,900
368,800
539,200
PEMBULATAN
7,600
102,100
34,000
152,300
PEMBULATAN
44,700
136,800
545,700
962,100
1,165,300
PEMBULATAN
1,202,800
1,233,100
1,250,100
PEMBULATAN
22,900
22,900
302,500
126,500
PEMBULATAN
660,400
517,400
532,200
PEMBULATAN
65,700
374,700
371,200
PEMBULATAN
151,000
140,200
510,400
492,300
PEMBULATAN
551,800
86,000
80,400
50,000
PEMBULATAN
346,200
324,000
343,600
PEMBULATAN
137,200
184,800
265,000
PEMBULATAN
89,000
92,900
184,200
PEMBULATAN
175,400
158,500
56,400
62,100
62,500
PEMBULATAN
327,300
8,420,500
7,316,400
PEMBULATAN
285,200
331,000
293,200
166,400
196,300
PEMBULATAN
104,400
60,800
103,700
PEMBULATAN
34,900
34,500
34,900
34,500
PEMBULATAN
34,900
34,500
83,700
PEMBULATAN
83,700
364,300
364,300
299,100
PEMBULATAN
407,100
407,100
405,000
405,000
PEMBULATAN
19,125,300
9,894,000
8,574,000
841,700
PEMBULATAN
643,700
377,600
1,185,700
855,700
PEMBULATAN
811,700
716,700
789,500
1,076,600
PEMBULATAN
719,300
492,400
323,600
323,600
PEMBULATAN
323,600
272,900
340,700
201,200
226,300
PEMBULATAN
3,536,500
48,700
48,700
159,200
21,400
PEMBULATAN
51,100
46,800
24,800
140,300
PEMBULATAN
196,600
374,800
898,400
3,365,800
1,938,600
PEMBULATAN
659,100
1,660,800
231,900
370,200
PEMBULATAN
168,200
670,100
225,900
165,900
PEMBULATAN
230,100
313,700
1,417,800
348,100
PEMBULATAN
281,600
193,400
97,100
80,100
PEMBULATAN
60,400
232,400
107,300
336,300
PEMBULATAN
3,088,500
1,086,700
2,144,400
1,381,500
1,326,000
PEMBULATAN
1,242,400
4,547,600
edit
edit
edit
6,721,000
PEMBULATAN
992,300
254,500
PEMBULATAN
221,500
56,500
473,400
94,500
PEMBULATAN
112,300
94,500
100,500
103,400
PEMBULATAN
47,900
129,100
196,400
160,100
PEMBULATAN
274,500
SPESIFIKASI BG BERTINGKAT
GEDUNG
NO. URAIAN BERTINGKAT TIDAK BERTINGKAT Keterangan
TIDAK SEDERHANA SEDERHANA TIDAK SEDERHANA SEDERHANA
A PEKERJAAN SRUKTUR
A.1 Pekerjaan Pondasi Rp. 442,408,018
A.2 PEKERJAAN STRUKTUR Rp. 1,345,287,666
B. PEKERJAAN ARSITEKTUR
B.1 Pekerjaan Lantai Rp. 205,051,318
B.2 Pekerjaan Dinding Rp. 603,480,181
B.3 Pekerjaan Plafond Rp. 210,743,946
B.4 Pekerjaan Atap Rp. 453,742,134
B.5 Pekerjaan Kusen Rp. 689,456,517
C. PEKERJAAN UTILITAS
C.1 Pekerjaan Plumbing Rp. 190,742,976
C.2 Pekerjaan Elektrikal Rp. 58,619,560
D. PEKERJAAN FINISHING Rp. 111,801,244
A PEKERJAAN SRUKTUR
A.1 Pekerjaan Pondasi
1 Pas. Urugan tanah Peninggian lantai m3 824.72 136,800 112,821,012
2 Galian tanah, dalam s/d 1 m m3 58.72 102,100 5,995,557
3 Pas. Urugan pasir t. 10 cm; Pondasi m3 11.81 152,300 1,799,382
4 Aanstamping batu kali t. 15 cm m3 96.90 545,700 52,878,330
5 Pas. pondasi batu kali 1:4 m3 14.14 962,100 13,607,461 187,101,742
6 Pas. Lantai kerja beton tumbuk 1:3:5 t. 5 cm m3 5.91 65,700 388,114
7 Bekisting sloof beton m2 66.00 302,500 19,965,000
8 Tulangan besi beton U-39 Besi beton dia 19 kg 1,856.61 22,900 42,516,369
9 Tulangan besi beton U-39 Besi beton dia 13 kg 755.47 22,900 17,300,206
0 Tulangan besi beton U-24 Besi beton 10 kg 135.52 22,900 3,103,408
10 Beton K - 250 m3 39.46 1,250,100 49,323,946 132,597,042
12 Bekisting sloof beton m2 118.30 302,500 35,785,750
13 Tulangan besi beton U-39 Besi beton dia 16 kg 1,832.21 22,900 41,957,563
14 Tulangan besi beton U-24 Besi beton dia 10 kg 826.06 22,900 18,916,682
15 Beton K - 225 m3 21.13 1,233,100 26,049,238 122,709,233
Pekerjaan Tangga
1 Bekisting beton plat lantai m2 24.16 660,400 15,953,613
2 Tulangan besi beton U-39 Besi beton dia 13 kg 202.67 22,900 4,641,042
3 Tulangan besi beton U-24 Besi beton dia 10 kg 186.14 22,900 4,262,531
4 Beton K - 250 m3 3.86 1,250,100 4,822,167 29,679,353
Pekerjaan Balok
1 Bekisting balok beton m2 198.49 532,200 105,633,717
2 Tulangan besi beton U-39 Besi beton dia 19 kg 259.56 22,900 5,943,924
3 Tulangan besi beton U-39 Besi beton dia 16 kg 2,604.10 22,900 59,633,842
4 Tulangan besi beton U-39 Besi beton dia 13 kg 101.66 22,900 2,328,005
5 Tulangan besi beton U-24 Besi beton dia 10 kg 1,050.53 22,900 24,057,055
6 Beton K - 250 m3 26.40 1,250,100 33,002,640 230,599,183
Pekerjaan Ringbalk
1 Beton K - 250 m3 11.81 1,250,100 16,085,855
2 Tulangan besi beton U-39 Besi beton dia 16 kg 1,101.19 22,900 27,486,913
3 Tulangan besi beton U-39 Besi beton dia 13 kg 257.52 22,900 6,428,037
4 Tulangan besi beton U-24 Besi beton dia 10 kg 665.28 22,900 16,606,054
5 Bekisting Praktis beton m2 148.36 126,500 20,456,963 87,063,822
C. PEKERJAAN UTILITAS
C.1 Pekerjaan Plumbing
C.1.2 Pekerjaan Sanitary, Lantai dasar
1 Pas. Kloset Duduk Keramik TOTO CW 660 J / SW 660 J unit 4.00 3,365,800 13,463,200
2 Pas. Urinoir Keramik TOTO U 57 M umit 2.00 1,938,600 3,877,200
3 Pas. Floor Drain TOTO TX 1 BN bh 7.00 230,100 1,610,700
4 Pas. Kran dinding TOTO T 23 B 13 bh 4.00 165,900 663,600
5 Pas. Meja Pantry uk. 600x 1500 mm Beton bertulang + keramik 200x200 unit 1.00 1,417,800 1,417,800 21,032,500
C.1.2 Pekerjaan Sanitary, Lantai atas
1 Pas. Kloset Duduk Keramik TOTO CW 660 J / SW 660 J unit 2.00 3,365,800 7,337,444
2 Pas. Kloset Jongkok Keramik TOTO CE 7 bh 2.00 659,100 1,436,838
3 Pas. Floor Drain TOTO TX 1 BN bh 6.00 230,100 1,504,854
4 Pas. Kran dinding TOTO T 23 B 13 bh 10.00 165,900 1,808,310 12,087,446
C.1.3 SUMUR DALAM
1 Pengeboran sumur m' 36.00 75,000 2,700,000
2 Pipa PVC dia. 3" Casing; ex Wavin m' 28.00 281,600 7,884,800
3 Pipa PVC dia. 2" Casing; ex Wavin m' 8.00 193,400 1,547,200
4 Pipa PVC dia. 3/4" ex Wavin m' 64.00 80,100 5,126,400
5 Klep diameter 3/4" bh 1.00 107,300 107,300
6 Stop kran dia. 1" bh 1.00 232,400 232,400
7 Mesin Jet Pump kap.250 watt Groundfos m' 1.00 3,088,500 3,088,500 20,686,600
C.1.4 TANKI AIR
1 Pipa PVC dia. 1" Sparing pam; ex Wavin m' 12.00 97,100 1,165,200
2 Pipa PVC dia. 1" Inst. d/ pompa ke tanki air; ex Wavin m' 8.00 97,100 776,800
3 Pipa PVC dia. 3/4" ex Wavin m' 4.00 80,100 320,400
4 Tangki air 1000 liter Exel bh 1.00 2,144,400 2,144,400
5 Dudukan tangki air Besi siku bh 1.00 1,326,000 1,326,000
6 Stop kran dia. 1" ex Onda bh 2.00 232,400 464,800
7 Stop kran dia. 1" ex Onda bh 1.00 232,400 232,400
8 Stop kran dia. 1" ex Onda bh 1.00 232,400 232,400 6,662,400
C.1.5 BAK PENAMPUNGAN AIR (RESERVOIR)
1 Galian tanah, dalam s/d 1 m m3 5.63 102,100 574,823
2 Pas. Urugan pasir t. 10 cm m3 0.12 152,300 18,276
3 Pas. Lantai kerja beton tumbuk 1:3:5 t. 5 cm m2 3.75 65,700 246,375
4 Bekisting beton plat lantai m2 21.00 660,400 13,868,400
5 Tulangan besi beton U-24 kg 315.00 22,900 7,213,500
6 Beton K - 200 m3 2.10 1,202,800 2,525,880 24,447,254
C.1.6 Instalasi Air Bersih, Lantai dasar
1 Pipa PVC dia. 2" ex Wavin m 45.00 193,400 8,703,000
2 Pipa PVC dia. 1" ex Wavin m 37.00 97,100 3,592,700
3 Pipa PVC dia. 3/4" ex Wavin m 10.00 80,100 801,000 13,096,700
NO ITEM PEKERJAAN PANJANG LEBAR LEBAR TINGGI JML VOLUME SAT HARGA JUMLAH
atas bawah BERAT SATUAN HARGA
1 P1A
Kusen alumunium 3" PC 2.52 2.00 5.04
1.00 2.00 2.00
7.04 m1 364,300 2,564,672
Rangka pintu alumunium 4" PC 2.40 2.00 4.80
0.90 4.00 3.60
8.40 m1 407,100 3,419,640
Kaca 8 mm 2.40 0.90 1.00 2.16 m2 374,800 809,568
Engsel 4" 3.00 bh 51,100 153,300
Handle pintu type HRE 75.01 ex CISA 1.00 bh 323,600 323,600
Selinder CISA type 08510 ex CISA 1.00 bh 272,900 272,900
Door Stoper 1.00 bh 201,200 201,200
Door closer 1.00 bh 226,300 226,300
Slot Tanam pintu doble 1.00 1.00 set 159,200 159,200
jumlah 5,565,708
di bulatkan 5,565,700
2 P1B
Kusen & Pintu PVC toilet 1.00 1.00 1.00 unit 299,100 299,100
jumlah 299,100
di bulatkan 299,100
3 P1C
Kusen & Pintu PVC toilet 1.00 1.00 1.00 unit 299,100 299,100
jumlah 299,100
di bulatkan 299,100
-
4 P2A
Kusen alumunium 3" PC 2.52 2.00 5.04
1.90 2.00 3.80
8.84 m1 364,300 3,220,412
Alumunium standart 3" PC rangka daun jendela 2.08 2.00 4.16
1.80 2.00 3.60
7.76 m1 405,000 3,142,800
Kaca 8 mm 2.40 1.80 1.00 4.32 m2 374,800 1,619,136
Engsel 4" 3.00 set 51,100 153,300
Handle pintu type HRE 75.01 ex CISA 1.00 bh 323,600 323,600
Selinder CISA type 08510 ex CISA 1.00 bh 272,900 272,900
Door Stoper 1.00 bh 201,200 201,200
Door closer 1.00 bh 226,300 226,300
Slot tanam 1.00 1.00 set 159,200 159,200
jumlah 9,318,848
di bulatkan 9,318,800
5 PJ1
Alumunium standart 3" PC 3.20 2.00 6.40
0.65 2.00 1.30
2.30 2.00 4.60
2.52 2.00 5.04
0.50 1.00 0.50
17.84 m1 364,300 6,499,112
Alumunium standart 3" PC rangka daun jendela 2.40 4.00 9.60
0.40 8.00 3.20
0.65 4.00 2.60
0.90 4.00 3.60
19.00 m1 405,000 7,695,000
Kaca 8 mm 2.40 1.80 1.00 4.32 m2 374,800 1,619,136
0.60 2.30 2.00 2.76 m2 374,800 1,034,448
Engsel pintu 3.00 set 51,100 153,300
Handle pintu type HRE 75.01 ex CISA 1.00 bh 323,600 323,600
Selinder CISA type 08510 ex CISA 1.00 bh 272,900 272,900
Door Stoper 1.00 bh 201,200 201,200
Door closer 1.00 bh 226,300 226,300
Slot tanam 1.00 1.00 set 159,200 159,200
jumlah 18,184,196
di bulatkan 18,184,200
6 J1A
Alumunium standart 3" PC 0.62 4.00 2.48
0.45 4.00 1.80
4.28 m1 364,300 1,559,204
Alumunium standart 3" PC rangka daun jendela 0.60 4.00 2.40
0.45 4.00 1.80
4.20 m1 405,000 1,701,000
Kaca 8 mm 0.62 0.45 2.00 0.56 m2 374,800 209,138
Grendel 2.00 2.00 set 48,700 97,400
Kait angin 2.00 2.00 set 7,000 14,000
jumlah 3,580,742
di bulatkan 3,580,700
7 J1B
Alumunium standart 3" PC 1.62 2.00 3.24
0.62 3.00 1.86
5.10 m1 364,300 1,857,930
Alumunium standart 3" PC rangka daun jendela 1.60 2.00 3.20
0.60 4.00 2.40
5.60 m1 405,000 2,268,000
Kaca 8 mm 1.60 0.60 1.00 0.96 m2 374,800 359,808
Grendel 2.00 2.00 set 48,700 97,400
Kait angin 2.00 2.00 set 7,000 14,000
jumlah 4,597,138
di bulatkan 4,597,100
8 J1C
Alumunium standart 3" PC 1.67 2.00 3.34
0.62 4.00 2.48
5.82 m1 364,300 2,120,226
Alumunium standart 3" PC rangka daun jendela 1.67 2.00 3.34
0.60 4.00 2.40
5.74 m1 405,000 2,324,700
Kaca 8 mm 1.60 0.60 1.00 0.96 m2 374,800 359,808
Grendel 2.00 2.00 set 48,700 97,400
Kait angin 2.00 2.00 set 7,000 14,000
jumlah 4,916,134
di bulatkan 4,916,134
9 J2A
Alumunium standart 3" PC 1.67 3.00 5.01
1.35 3.00 4.05
9.06 m1 364,300 3,300,558
Alumunium standart 3" PC rangka daun jendela 1.67 4.00 6.68
1.35 4.00 5.40
12.08 m1 405,000 4,892,400
Kaca 8 mm 1.60 1.30 1.00 2.08 m2 374,800 779,584
Grendel 4.00 4.00 set 48,700 194,800
Kait angin 4.00 4.00 set 7,000 28,000
jumlah 9,195,342
di bulatkan 9,195,300
10 J 2 B
Alumunium standart 3" PC 1.60 3.00 4.80
1.35 4.00 5.40
10.20 m1 364,300 3,715,860
Alumunium standart 3" PC rangka daun jendela 1.60 3.00 4.80
1.35 4.00 5.40
10.20 m1 405,000 4,131,000
Kaca 8 mm 1.60 1.30 1.00 2.08 m2 374,800 779,584
Grendel 4.00 4.00 set 48,700 194,800
Kait angin 4.00 4.00 set 7,000 28,000
jumlah 8,849,244
di bulatkan 8,849,200
11 J 3 A
Alumunium standart 3" PC 1.67 4.00 6.68
2.00 3.00 6.00
12.68 m1 364,300 4,619,324
Alumunium standart 3" PC rangka daun jendela 1.67 6.00 10.02
2.00 4.00 8.00
18.02 m1 405,000 7,298,100
Kaca 8 mm 1.60 1.90 1.00 3.04 m2 374,800 1,139,392
Grendel 6.00 6.00 set 48,700 292,200
Kait angin 6.00 6.00 set 7,000 42,000
jumlah 13,391,016
di bulatkan 13,391,000
12 J 3 B
Alumunium standart 3" PC 1.90 4.00 7.60
2.00 5.00 10.00
17.60 m1 364,300 6,411,680
Alumunium standart 3" PC rangka daun jendela 0.43 6.00 2.55
0.61 6.00 3.66
6.21 m1 405,000 2,515,050
Kaca 8 mm 1.80 1.90 1.00 3.42 m2 374,800 1,281,816
Grendel 6.00 6.00 set 48,700 292,200
Kait angin 6.00 6.00 set 7,000 42,000
jumlah 10,542,746
di bulatkan 10,542,700
13 J 4 A
Alumunium standart 3" PC 1.67 5.00 8.35
3.40 3.00 10.20
18.55 m1 364,300 6,757,765
Kaca 8 mm 1.60 3.40 1.00 5.44 m2 374,800 2,038,912
jumlah 8,796,677
di bulatkan 8,796,700
14 J 5 A
Alumunium standart 3" PC 1.90 8.00 15.20
4.52 5.00 22.60
37.80 m1 364,300 13,770,540
Alumunium standart 3" rangka daun jendela 0.43 20.00 8.50
0.60 20.00 12.00
20.50 m1 405,000 8,302,500
Kaca 8 mm 1.90 4.50 1.00 8.55 m2 374,800 3,204,540
Grendel 10.00 10.00 set 48,700 487,000
Kait angin 10.00 10.00 set 7,000 70,000
jumlah 25,834,580
di bulatkan 25,834,600
ANALISA HARGA SATUAN KUSEN
BANGUNAN GEDUNG BETINGKAT SEDERHANA
NO ITEM PEKERJAAN PANJANG LEBAR LEBAR TINGGI JML VOLUME SAT HARGA JUMLAH
atas bawah BERAT SATUAN HARGA
1 P1A
Kusen alumunium 3" CA 2.52 2.00 5.04
1.00 2.00 2.00
7.04 m1 364,300 2,564,672
Frame pintu alumunium 4" CA 2.40 2.00 4.80
0.90 4.00 3.60
8.40 m1 407,100 3,419,640
Kaca 8 mm 2.40 0.90 1.00 2.16 m2 374,800 809,568
Engsel 4" 3.00 bh 51,100 153,300
Handle pintu type HRE 75.01 ex CISA 1.00 bh 323,600 323,600
Selinder CISA type 08510 ex CISA 1.00 bh 272,900 272,900
Door Stoper 1.00 bh 201,200 201,200
Door closer 1.00 bh 226,300 226,300
Slot pengunci 1.00 1.00 set 159,200 159,200
jumlah 8,130,380
di bulatkan 8,130,400
2 P1B
Kusen & Pintu PVC toilet 1.00 1.00 1.00 unit 299,100 299,100
jumlah 299,100
di bulatkan 299,100
3 P1C
Kusen & Pintu PVC toilet 1.00 1.00 1.00 unit 299,100 299,100
jumlah 299,100
di bulatkan 299,100
-
4 P2A
Alumunium standart 3" CA 2.52 2.00 5.04
1.90 2.00 3.80
8.84 m1 364,300 3,220,412
Alumunium standart 3" CA rangka daun jendela 2.08 2.00 4.16
1.80 2.00 3.60
7.76 m1 405,000 3,142,800
Kaca 8 mm 2.40 1.80 1.00 4.32 m2 374,800 1,619,136
Engsel 4" 3.00 bh 51,100 153,300
Handle pintu type HRE 75.01 ex CISA 1.00 bh 323,600 323,600
Selinder CISA type 08510 ex CISA 1.00 bh 272,900 272,900
Door Stoper 1.00 bh 201,200 201,200
Door closer 1.00 bh -
Slot pengunci 1.00 1.00 set 159,200 159,200
jumlah 9,092,548
di bulatkan 9,092,500
5 PJ1
Alumunium standart 3" CA 3.20 2.00 6.40
0.65 2.00 1.30
2.30 2.00 4.60
2.52 2.00 5.04
0.50 1.00 0.50
17.84 m1 364,300 6,499,112
Alumunium standart 3" CA rangka daun jendela 2.40 4.00 9.60
0.40 8.00 3.20
0.65 4.00 2.60
0.90 4.00 3.60
19.00 m1 405,000 7,695,000
Kaca 8 mm 2.40 1.80 1.00 4.32 m2 374,800 1,619,136
0.60 2.30 2.00 2.76 m2 374,800 1,034,448
Engsel 4" 3.00 bh 51,100 153,300
Handle pintu type HRE 75.01 ex CISA 1.00 bh 323,600 323,600
Selinder CISA type 08510 ex CISA 1.00 bh 272,900 272,900
Slot pengunci 1.00 1.00 set 159,200 159,200
jumlah 17,756,696
di bulatkan 17,756,700
6 J1A
Alumunium standart 3" CA 0.62 4.00 2.48
0.45 4.00 1.80
4.28 m1 364,300 1,559,204
Alumunium standart 3" CA rangka daun jendela 0.60 4.00 2.40
0.45 4.00 1.80
4.20 m1 405,000 1,701,000
Kaca 8 mm 0.62 0.45 2.00 0.56 m2 374,800 209,138
Grendel 2.00 2.00 set 48,700 97,400
Kait angin 2.00 2.00 set 7,000 14,000
jumlah 3,580,742
di bulatkan 3,580,700
7 J1B
Alumunium standart 3" CA 1.62 2.00 3.24
0.62 3.00 1.86
5.10 m1 364,300 1,857,930
Alumunium standart 3" CA rangka daun jendela 1.60 2.00 3.20
0.60 4.00 2.40
5.60 m1 325,000 1,820,000
Kaca 8 mm 1.60 0.60 1.00 0.96 m2 374,800 359,808
Grendel 2.00 2.00 set 48,700 97,400
Kait angin 2.00 2.00 set 7,000 14,000
jumlah 4,149,138
di bulatkan 4,149,100
8 J1C
Alumunium standart 3" CA 1.67 2.00 3.34
0.62 4.00 2.48
5.82 m1 364,300 2,120,226
Alumunium standart 3" CA rangka daun jendela 1.67 2.00 3.34
0.60 4.00 2.40
5.74 m1 325,000 1,865,500
Kaca 8 mm 1.60 0.60 1.00 0.96 m2 374,800 359,808
Grendel 2.00 2.00 set 48,700 97,400
Kait angin 2.00 2.00 set 7,000 14,000
jumlah 4,456,934
di bulatkan 4,456,934
9 J2A
Alumunium standart 3" CA 1.67 3.00 5.01
1.35 3.00 4.05
9.06 m1 364,300 3,300,558
Alumunium standart 3" CA rangka daun jendela 1.67 4.00 6.68
1.35 4.00 5.40
12.08 m1 325,000 3,926,000
Kaca 8 mm 1.60 1.30 1.00 2.08 m2 374,800 779,584
Grendel 4.00 4.00 set 48,700 194,800
Kait angin 4.00 4.00 set 7,000 28,000
jumlah 8,228,942
di bulatkan 8,228,900
10 J 2 B
Alumunium standart 3" CA 1.60 3.00 4.80
1.35 4.00 5.40
10.20 m1 364,300 3,715,860
Alumunium standart 3" CA rangka daun jendela 1.60 3.00 4.80
1.35 4.00 5.40
10.20 m1 325,000 3,315,000
Kaca 8 mm 1.60 1.30 1.00 2.08 m2 374,800 779,584
Grendel 4.00 4.00 set 48,700 194,800
Kait angin 4.00 4.00 set 7,000 28,000
jumlah 8,033,244
di bulatkan 8,033,200
11 J 3 A
Alumunium standart 3" CA 1.67 4.00 6.68
2.00 3.00 6.00
12.68 m1 364,300 4,619,324
Alumunium standart 3" CA rangka daun jendela 1.67 6.00 10.02
2.00 4.00 8.00
18.02 m1 325,000 5,856,500
Kaca 8 mm 1.60 1.90 1.00 3.04 m2 374,800 1,139,392
Grendel 6.00 6.00 set 48,700 292,200
Kait angin 6.00 6.00 set 7,000 42,000
jumlah 11,949,416
di bulatkan 11,949,400
12 J 3 B
Alumunium standart 3" CA 1.90 4.00 7.60
2.00 5.00 10.00
17.60 m1 364,300 6,411,680
Alumunium standart 3" CA rangka daun jendela 0.43 6.00 2.55
0.61 6.00 3.66
6.21 m1 325,000 2,018,250
Kaca 8 mm 1.80 1.90 1.00 3.42 m2 374,800 1,281,816
Grendel 6.00 6.00 set 48,700 292,200
Kait angin 6.00 6.00 set 7,000 42,000
jumlah 10,045,946
di bulatkan 10,045,900
13 J 4 A
Alumunium standart 3" CA 1.67 5.00 8.35
3.40 3.00 10.20
18.55 m 364,300 6,757,765
Kaca 8 mm 1.60 3.40 1.00 5.44 m2 374,800 2,038,912
jumlah 8,796,677
di bulatkan 8,796,700
14 J 5 A
Alumunium standart 3" CA 1.90 8.00 15.20
4.52 5.00 22.60
37.80 m 364,300 13,770,540
Alumunium standart 3" CA rangka daun jendela 0.43 20.00 8.50
0.60 20.00 12.00
20.50 m 325,000 6,662,500
Kaca 8 mm 1.90 4.50 1.00 8.55 m2 374,800 3,204,540
Grendel 10.00 10.00 set 48,700 487,000
Kait angin 10.00 10.00 set 7,000 70,000
jumlah 24,194,580
di bulatkan 24,194,600
menu
QTY-GTS
NO ITEM PEKERJAAN NO KODE PANJANG LEBAR LEBAR TINGGI JML VOLUME SAT
GAMBAR atas bawah BERAT
I PEKERJAAN PERSIAPAN
1 Mobilisasi & Demobilisasi 1 ls
2 Direksi keet & gudang 5 3 1 15 m2
3 Papan nama proyek 1 ls
4 Setting Out dan Pengukuran 32 15 480 m2
5 Bowplank 100 100 m1
6 Pembersihan lahan 32 15 1 480 m2
7 Pagar sementara seng + rangka kaso 50 50 m
8 Dokumen Kontrak, foto progres, As Built Drawing, laporan-laporan 1 ls
II PEKERJAAN BANGUNAN
A PEKERJAAN TANAH
1 Urugan tanah merah kantor 14.9 41 1.35 1 824.715
824.715 m3
B PEKERJAAN PONDASI
1 PEKERJAAN TIANG PANCANG
1.01 Pengadaan tiang pancang 280x280cmx280 x 13 m P2 13 2 20 520
P3 13 3 4 156
24 676 m1
3 Lantai kerja ad. 1:3:5, tebal 5 cm P2 S-1001 2.04 1.2 0.05 20 2.448
P3 1.42 2.04 0.05 4 0.57936
T B1 30 0.3 0.05 4 1.8
12 0.3 0.05 6 1.08
5.90736 m3
4 Pilecap
Beton K 250 P2 1.54 0.7 0.75 20 16.17
P3 1.54 0.5 0.75 4 2.31
0.95 0.92 0.75 32 20.976
39.456 m3
Kolom Pedestal
Beton K 225 P1/P2 0.35 0.35 1.3 24 3.822 m3
6 Sloof ( TB 1 )
Beton K 225 A-F 10.5 0.25 0.5 6 7.875
1-4 26.5 0.25 0.5 4 13.25
21.125 m3
C PEKERJAAN STRUKTUR
1 LANTAI DASAR
1.01 Kolom
Beton K 250 K1 0.35 0.35 3.5 24 10.29
bordes 0.2 0.2 2 1 0.08
Praktis 0.13 0.2 3.5 10 0.91
10.37 m3
1.04 Tangga
Beton K 250 plat 3.6 1.625 0.13 2 1.521
bordes 3.35 1.675 0.13 2 1.458925
trap 1.625 0.0225 24 0.8775
3.857425 m3
51.849 90 4666.41 kg
D PEKERJAAN ARSITEKTUR
LANTAI DASAR
1 PEKERJAAN DINDING
1.01 Pasangan 1/2 batu bata ad 1:2 5 1.5 2 15
4.2 1.5 1 6.3
4 1.5 1 6
2 1.5 1 3
1.3 1.5 1 1.95
32.25
2 1.35 1 2.7
34.95 m2
870.374 m2
Overstek 1 8 1 8
2 13 1 13
3 8 1 8
8 1 8
4 8 1 8
1 0.8 45 m
menu
QTY-GTS
NO ITEM PEKERJAAN NO KODE PANJANG LEBAR LEBAR TINGGI JML VOLUME SAT
GAMBAR atas bawah BERAT
3 PEKERJAAN LANTAI
3.01 Lantai keramik 20 x20 2 5 1 10
2 3.5 1 7
17 m2
Lantai kerja ad. 1:3:5 alas keramik, tebal 3 cm 487.71 0.03 1 14.6313 m3
Plint keramik 10x30 ex Roman a 10 1 10
2 2 4
b 5 2 10
1 1 1
1 1 1
c 1 2 2
d 6 2 12
6 2 12
1 1 1
e 5 2 10
5 2 10
5 1 5
2 2 4
f 5 2 10
0 3.5 2 7
6 2 12
1 8.5 2 17
6 1 6
2 8.5 2 17
5 2 10
3 23 2 46
4 24 1 24
231
P1 pintu 3 2 6
P2 1.8 6 10.8
P3 0.9 20 18
34.8
196.2 m1
5.02 Railing 4 2 8
2 1 2
10 m
5.03 Pengecatan 3.5 7.5 1 26.25 m2
6 PEKERJAAN SANITASI
6.01 Closed jongkok CE - 7 ex Toto 4 unit
6.02 Urinoir U 57 M termasuk accesoriesnya 2 umit
Wastafel 2 unit
6.03 Floor drain TX 1BN 7 bh
6.04 Kran dinding T 23 B 13 4 bh
6.05 Meja Pantry 1 unit
6.06 Septictank 2 unit
6.07 Rembesan 2 unit
LANTAI DUA
1 PEKERJAAN DINDING
1.01 Pasangan 1/2 batu bata ad 1:2 toilet camat 1.5 1.5 3 6.75
2 1.5 2 6
1.1 1.5 2 3.3
toilet kar 5 1.5 2 15
3 1.5 1 4.5
1.2 1.5 1 1.8
1.5 1.5 1 2.25
2.5 1.5 1 3.75
2.5 0.5 2 2.5
1 1.5 1 1.5
47.35 m2
1.5 0.83 2 2.49
49.84 m2
1246.548 m2
3 PEKERJAAN LANTAI
3.01 Lantai keramik 20x20 4 1.5 1 6
4.15 3 1 12.45
18.45 m2
4 PEKERJAAN PLAFOND
4.01 Plafond calsi board + rangka hollow + cat 13 1 1 13
1 1 2 2
9.5 1 4 38
12 1 2 24
2 0.5 2 2
1 1 2 2
4 1 2 8
1 1 2 2
8 1 1 8
4 1.5 1 6
4.15 3 1 12.45
117.45 m2
5 PEKERJAAN ATAP
5.01 Rangka atap baja ringan 1 smp 14.15 4 2 113.2
2 8.5 6.5 4 221
9 1.5 4 54
3 15.15 4.25 2 128.775
1.5 11 4 66
3 4 2 24
606.975 m2
5.04 Nok 10 4 40
7.5 2 15
11 4 44
5 2 10
2 1 2
1 1 1
112 m
6 PEKERJAAN SANITARY
6.01 Closed duduk CW 660 J/SW 660J termasuk accesoriesnya 2 unit
6.02 Closed jongkok 2 bh
Urinoir U 57 M termasuk accesoriesnya 3 unit
6.03 Floor drain TX 1BN 6 bh
menu
QTY-GTS
NO ITEM PEKERJAAN NO KODE PANJANG LEBAR LEBAR TINGGI JML VOLUME SAT
GAMBAR atas bawah BERAT
6.04 Kran dinding T 23 B 13 10 bh
E PEKERJAAN M & E
LANTAI DASAR
1 Pekerjaan Listrik
1.01 Instalasi penerangan 43 1 43 ttk
1.02 Instalasi stop kontak 14 1 14 ttk
1.03 Stop kontak 14 1 14 ttk
1.04 lampu TL 2X18 watt 13 1 13 bh
1.05 Lampu Downlight 24 1 24 bh
1.06 Box Panel 1 1 1 unit
2 Pekerjaan plumbing
2.01 Intaslasi air bersih
Pipa PVC dia 32 AW 45 1 45 m
Pipa PVC dia 25 AW 37 1 37 m
Pipa PVC dia 15 AW 10 1 10 m
Fitting 1 ls
Jet Pump 1 unit
Water Tank 1 unit
2.02 Instalasi air kotor
Pipa PVC dia 100 AW 6 1 6m
Pipa PVC dia 150 AW 12 1 12 m
Fitting 1 ls
2.03 Instalasi air bekas kotor & air hujan
Pipa PVC dia 80 AW 48 1 48 m
Pipa PVC dia 150 AW 75 1 75 m
Fitting 1 ls
Bak kontrol 4 unit
Resapan 2 unit
LANTAI DUA
1 Pekerjaan Listrik
1.01 Instalasi penerangan 30 1 30 ttk
1.02 Instalasi stop kontak 15 1 15 ttk
1.03 Stop kontak 15 5 75 ttk
1.04 lampu TL 2X18 watt 18 1 18 bh
1.05 Lampu Downlight 27 1 27 bh
1.06 Box Panel 1 1 1 unit
2 Pekerjaan plumbing
2.01 Intaslasi air bersih
Pipa PVC dia 32 AW
Pipa PVC dia 25 AW 45 1 45 m
Pipa PVC dia 15 AW 28 1 28 m
Fitting 1 ls
2.02 Instalasi air kotor
Pipa PVC dia 100 AW 3 1 3m
Pipa PVC dia 150 AW 45 1 45 m
Fitting 1 ls
2.03 Instalasi air bekas kotor & Air hujan
Pipa PVC dia 80 AW 28 1 28 m
Pipa PVC dia 150 AW
Fitting 1 ls
QTY-GTS
QUANTITY
1
15
1
480
100
480
50
1
824.715
58.7224
676
676
96
96
52
11.81472
5.90736
39.456
QTY-GTS
QUANTITY
1856.61
755.46752
135.52
66
14.1435
3.822
508.5312
195.1488
43.68
21.125
1832.208
826.056
118.3
10.37
1121.76
153.5616
QTY-GTS
QUANTITY
591.8528
133.2
43.875
21.9375
62.9625
9334.1248
14.1
0.36
11.904
18.48
3.9
3.857425
202.6656
186.13672
24.1575
QTY-GTS
QUANTITY
26.4
259.56
2604.09792
101.6596
1050.5264
198.485
QTY-GTS
QUANTITY
11.2
942.2784
144.832
678.9552
131.6
51.849
643.68
4666.41
343.9975
11.8051875
QTY-GTS
QUANTITY
1101.1944
257.5232
665.28
148.3625
1.68
14
34.95
QTY-GTS
QUANTITY
455.437
66
63.72
870.374
50.1
16
45
QTY-GTS
QUANTITY
870.374
66
9
6
2
1
8
10
4
2
1
17
470.71
24.3855
14.6313
partisi
beton
partisi
196.2
96.9
17
QTY-GTS
QUANTITY
325.9
36
26.61
10
26.25
4
2
2
7
4
1
2
2
47.35
49.84
666.124
QTY-GTS
QUANTITY
62.9
61.37
1246.548
56.7
29
44
1246.548
68.4
9
4
1
6
2
12
2
2
2
18.45
350.55
QTY-GTS
QUANTITY
272.1
117.45
371.55
606.975
606.975
46
112
123.5
2
2
3
6
QTY-GTS
QUANTITY
10
43
14
14
13
24
1
45
37
10
1
1
1
6
12
1
48
75
1
4
2
30
15
75
18
27
1
45
28
1
3
45
1
28
1
RAB BG TDK BERTINGKAT SEDERHANA 213 / 296
A PEKERJAAN STRUKTUR
A.1 Pekerjaan Pondasi 94,500,510
A.2 Pekerjaan Struktur 152,734,980
B PEKERJAAN ARSITEKTUR
B.1 Pekerjaan Lantai 84,553,980
B.2 Pekerjaan Dinding 162,051,985
B.3 Pekerjaan Plafond 80,711,676
B.4 Pekerjaan Atap 289,494,175
B.5 Pekerjaan Kusen 287,250,892
C PEKERJAAN UTILITAS
C.1 Pekerjaan Plumbing 107,040,804
C.2 Pekerjaan Elektrikal 25,492,400
D. PEKERJAAN FINISHING 62,970,210
B PEKERJAAN ARSITEKTUR
B.1 Pekerjaan Lantai
1 Pas. Urugan pasir t. 10 cm m3 17.70 152,300 2,696,467
2 Pas. Lantai kerja beton tumbuk 1:3:5 t. 5 cm m3 7.56 65,700 496,692
3 Pas. Lantai Keramik 300x300 ex Masterina m2 243.40 265,000 64,501,000
4 Pas. Rabat beton; finish acian Beton spesi 1 : 3 : 5 m2 54.87 137,200 7,528,109
5 Pas. Dinding batu bata; ad 1:4 Rolagh bata m 66.56 140,200 9,331,712
Jumlah B.1.... Rp 84,553,980
B.2 Pekerjaan Dinding
1 Pas. Dinding batu bata; ad 1:2 Batu bata merah m2 21.50 151,000 3,246,500
2 Pas. Dinding batu bata; ad 1:4 Batu bata merah m2 484.21 140,200 67,885,541
3 Pas. Dinding partisi gypsumboard Rangka Kayu m2 28.50 510,400 14,546,400
4 Pas. Dinding batu bata; ad 1:4 Penebalan kolom m3 1.60 140,200 224,292
5 Pas. Plester acian; ad. 1:4 t. 15 mm; Interior m2 947.13 80,400 76,149,252
Jumlah B.2.... Rp 162,051,985
B.3 Pekerjaan Plafond
1 Pas. Rangka Plafond Metal furing Metal furing m2 335.46 184,200 61,791,732
2 Pas. Penutup Plafond Gypsumboard t. 9 mm ex Jayaboard m2 335.46 56,400 18,919,944
Jumlah B.3.... Rp 80,711,676
B.4 Pekerjaan Atap
1 Rangka atap baja ringan ex Smartruss m2 397.87 327,300 130,222,033
2 Penutup atap Genteng Keramik ex Jatiwangi m2 397.87 331,000 131,694,143
3 Bubungan Genteng Keramik ex Jatiwangi m 75.25 166,400 12,521,600
4 Pas. Lisplank Kayu 3/20 mm Kayu kamper medan m 102.50 104,400 10,701,000
5 Pas. Talang seng plat Seng bjls 35 m 42.00 103,700 4,355,400
Jumlah B.4.... Rp 289,494,175
RAB BG TDK BERTINGKAT SEDERHANA 214 / 296
NO ITEM PEKERJAAN PANJANG LEBAR LEBAR TINGGI JML VOLUME SAT HARGA
atas bawah BERAT SATUAN
NO ITEM PEKERJAAN PANJANG LEBAR LEBAR TINGGI JML VOLUME SAT HARGA
atas bawah BERAT SATUAN
9.00 BV 1 uk. 50 x 85
Alumunium standart 3" CA 0.85 2.00 1.70
0.50 2.00 1.00
2.70 m1 364,300.00
Alumunium standart 3" CA rangka daun jendela 0.80 2.00 1.60
0.50 2.00 1.00
2.60 m1 405,000.00
Kaca 6 mm 0.85 0.45 1.00 0.38 m2 196,600.00
Karet 0.85 2.00 1.70
0.50 2.00 1.00
2.70 m1 20,000.00
Grendel 1.00 1.00 set 5,500.00
Kait angin 1.00 1.00 set 24,800.00
jumlah
di bulatkan
NO ITEM PEKERJAAN PANJANG LEBAR LEBAR TINGGI JML VOLUME SAT HARGA
atas bawah BERAT SATUAN
NO ITEM PEKERJAAN PANJANG LEBAR LEBAR TINGGI JML VOLUME SAT HARGA JUMLAH
atas bawah BERAT SATUAN HARGA
NO ITEM PEKERJAAN PANJANG LEBAR LEBAR TINGGI JML VOLUME SAT HARGA JUMLAH
atas bawah BERAT SATUAN HARGA
9.00 BV 1 uk. 50 x 85
Alumunium standart 3" CA 0.85 2.00 1.70
0.50 2.00 1.00
2.70 m1 364,300.00 983,610.00
Alumunium standart 3" CA rangka daun jendela 0.80 2.00 1.60
0.50 2.00 1.00
2.60 m1 405,000.00 1,053,000.00
Kaca 6 mm 0.85 0.45 1.00 0.38 m2 196,600.00 75,199.50
Karet 0.85 2.00 1.70
0.50 2.00 1.00
2.70 m1 20,000.00 54,000.00
Grendel 1.00 1.00 set 5,500.00 5,500.00
Kait angin 1.00 1.00 set 24,800.00 24,800.00
jumlah 2,196,109.50
di bulatkan 2,196,100.00
NO ITEM PEKERJAAN PANJANG LEBAR LEBAR TINGGI JML VOLUME SAT HARGA JUMLAH
atas bawah BERAT SATUAN HARGA
NO ITEM PEKERJAAN NO KODE PANJANG LEBAR LEBAR TINGGI JML VOLUME SAT
GAMBAR atas bawah BERAT
I PEKERJAAN PERSIAPAN
1.00 Mobilisasi & Demobilisasi 1.00 ls
2.00 Direksi keet & gudang 5.00 3.00 1.00 15.00 m2
3.00 Papan nama proyek 1.00 ls
4.00 Setting Out dan Pengukuran 261.00 1.00 261.00 m2
5.00 Bowplank 74.00 1.00 74.00 m1
6.00 Pembersihan lahan 261.00 1.00 1.00 261.00 m2
7.00 Pagar sementara seng + rangka kaso 50.00 50.00 m
8.00 Dokumen Kontrak, foto progres, As Built Drawing, laporan-laporan 1.00 ls
II PEKERJAAN BANGUNAN
A PEKERJAAN URUGAN
1.00 Urugan tanah merah kantor 3.00 1.50 0.30 1.00 1.35
9.00 6.50 0.30 1.00 17.55
20.00 12.00 0.30 1.00 72.00
90.90 m3
B PEKERJAAN PONDASI
1.00 Galian tanah A 10.00 0.80 0.70 1.00 5.60
2.00 0.80 0.70 1.00 1.12
B 7.50 0.80 0.70 1.00 4.20
2.00 0.80 0.70 1.00 1.12
C 1.50 0.80 0.70 1.00 0.84
5.00 0.80 0.70 1.00 2.80
10.00 0.80 0.70 1.00 5.60
4.00 0.80 0.70 1.00 2.24
D 1.50 0.80 0.70 1.00 0.84
5.00 0.80 0.70 1.00 2.80
4.00 0.80 0.70 -
E 7.50 0.80 0.70 1.00 4.20
F 10.00 0.80 0.70 1.00 5.60
2.00 0.80 0.70 1.00 1.12
2.00 0.80 0.70 1.00 1.12
G 10.00 0.80 0.70 1.00 5.60
o 3.00 0.80 0.70 1.00 1.68
o' 9.00 0.80 0.70 1.00 5.04
1 9.00 0.80 0.70 1.00 5.04
2 18.00 0.80 0.70 1.00 10.08
2.50 0.80 0.70 1.00 1.40
3 18.00 0.80 0.70 1.00 10.08
4 18.00 0.80 0.70 1.00 10.08
2.50 0.80 0.70 1.00 1.40
5 18.00 0.80 0.70 1.00 10.08
99.68 m3
NO ITEM PEKERJAAN NO KODE PANJANG LEBAR LEBAR TINGGI JML VOLUME SAT
GAMBAR atas bawah BERAT
3.00 Pondasi batu kali 1:4 A 10.00 0.60 0.15 1.00 0.90
2.00 0.60 0.15 1.00 0.18
B 7.50 0.60 0.15 1.00 0.68
2.00 0.60 0.15 1.00 0.18
C 1.50 0.60 0.15 1.00 0.14
5.00 0.60 0.15 1.00 0.45
10.00 0.60 0.15 1.00 0.90
4.00 0.60 0.15 1.00 0.36
D 1.50 0.60 0.15 1.00 0.14
5.00 0.60 0.15 1.00 0.45
4.00 0.60 0.15 1.00 0.36
E 7.50 0.60 0.15 1.00 0.68
f 10.00 0.60 0.15 1.00 0.90
2.00 0.60 0.15 1.00 0.18
2.00 0.60 0.15 1.00 0.18
G 10.00 0.60 0.15 1.00 0.90
o 3.00 0.60 0.15 1.00 0.27
o' 9.00 0.60 0.15 1.00 0.81
1 9.00 0.60 0.15 1.00 0.81
2 18.00 0.60 0.15 1.00 1.62
2.50 0.60 0.15 1.00 0.23
3 18.00 0.60 0.15 1.00 1.62
4 18.00 0.60 0.15 1.00 1.62
2.50 0.60 0.15 1.00 0.23
5 18.00 0.60 0.15 1.00 1.62
Pondasi batu kali A 10.00 0.45 0.65 1.00 2.93
2.00 0.45 0.65 1.00 0.59
B 7.50 0.45 0.65 1.00 2.19
2.00 0.45 0.65 1.00 0.59
C 1.50 0.45 0.65 1.00 0.44
5.00 0.45 0.65 1.00 1.46
10.00 0.45 0.65 1.00 2.93
4.00 0.45 0.65 1.00 1.17
D 1.50 0.45 0.65 1.00 0.44
5.00 0.45 0.65 1.00 1.46
4.00 0.45 0.65 -
E 7.50 0.45 0.65 1.00 2.19
F 10.00 0.45 0.65 1.00 2.93
2.00 0.45 0.65 1.00 0.59
2.00 0.45 0.65 1.00 0.59
G 10.00 0.45 0.65 1.00 2.93
o 3.00 0.45 0.65 1.00 0.88
o' 9.00 0.45 0.65 1.00 2.63
1 9.00 0.45 0.65 1.00 2.63
2 18.00 0.45 0.65 1.00 5.27
2.50 0.45 0.65 1.00 0.73
3 18.00 0.45 0.65 1.00 5.27
4 18.00 0.45 0.65 1.00 5.27
2.50 0.45 0.65 1.00 0.73
5 18.00 0.45 0.65 1.00 5.27
68.45 m3
4.00 Sloof
Beton K 200 A 10.00 0.15 0.20 1.00 0.30
2.00 0.15 0.20 1.00 0.06
B 7.50 0.15 0.20 1.00 0.23
2.00 0.15 0.20 1.00 0.06
C 1.50 0.15 0.20 1.00 0.05
5.00 0.15 0.20 1.00 0.15
10.00 0.15 0.20 1.00 0.30
4.00 0.15 0.20 1.00 0.12
D 1.50 0.15 0.20 1.00 0.05
5.00 0.15 0.20 1.00 0.15
4.00 0.15 0.20 -
E 7.50 0.15 0.20 1.00 0.23
F 10.00 0.15 0.20 1.00 0.30
menu
QTY-GS
TAKING OFF
PERHITUNGAN VOLUME
BANGUNAN GEDUNG TIDAK BERTINGKAT
NO ITEM PEKERJAAN NO KODE PANJANG LEBAR LEBAR TINGGI JML VOLUME SAT
GAMBAR atas bawah BERAT
NO ITEM PEKERJAAN NO KODE PANJANG LEBAR LEBAR TINGGI JML VOLUME SAT
GAMBAR atas bawah BERAT
C PEKERJAAN STRUKTUR
1.00 Kolom
Beton K 200 0.13 0.20 4.00 12.00 1.25
0.13 0.20 5.30 2.00 0.28
0.13 0.20 6.30 4.00 0.66
0.13 0.20 3.50 32.00 2.91
5.09 m3
NO ITEM PEKERJAAN NO KODE PANJANG LEBAR LEBAR TINGGI JML VOLUME SAT
GAMBAR atas bawah BERAT
NO ITEM PEKERJAAN NO KODE PANJANG LEBAR LEBAR TINGGI JML VOLUME SAT
GAMBAR atas bawah BERAT
3.00 Plat
Beton K 200 3.00 0.90 0.13 1.00 0.34 m3
1.02 Pasangan 1/2 batu bata ad 1:4 A 10.00 3.50 1.00 35.00
2.00 3.50 1.00 7.00
menu
QTY-GS
TAKING OFF
PERHITUNGAN VOLUME
BANGUNAN GEDUNG TIDAK BERTINGKAT
NO ITEM PEKERJAAN NO KODE PANJANG LEBAR LEBAR TINGGI JML VOLUME SAT
GAMBAR atas bawah BERAT
1.04 Pasangan bata penebalan kolom 0.53 0.25 3.80 4.00 2.00
0.13 0.20 3.80 4.00 0.40
1.60 m3
NO ITEM PEKERJAAN NO KODE PANJANG LEBAR LEBAR TINGGI JML VOLUME SAT
GAMBAR atas bawah BERAT
947.13 m2
1.06 Keramik dinding 20x25 toil wanita 5.50 2.00 1.00 11.00
toil lurah 7.20 2.00 1.00 14.40
toil pria 5.50 2.00 1.00 11.00
36.40 m2
3.05 Beton alas keramik ad. 1:3:5 tebal 3 cm 3.00 1.50 0.03 1.00 0.14
9.00 7.50 0.03 1.00 2.03
menu
QTY-GS
TAKING OFF
PERHITUNGAN VOLUME
BANGUNAN GEDUNG TIDAK BERTINGKAT
NO ITEM PEKERJAAN NO KODE PANJANG LEBAR LEBAR TINGGI JML VOLUME SAT
GAMBAR atas bawah BERAT
4.02 Plafond gypsum board + rangka hollow + cat 3.00 1.50 1.00 4.50
9.00 7.50 1.00 67.50
18.00 10.00 1.00 180.00
252.00
dikurangi toilet 8.60 1.00 1.00 8.60
243.40 m2
menu
QTY-GS
TAKING OFF
PERHITUNGAN VOLUME
BANGUNAN GEDUNG TIDAK BERTINGKAT
NO ITEM PEKERJAAN NO KODE PANJANG LEBAR LEBAR TINGGI JML VOLUME SAT
GAMBAR atas bawah BERAT
E PEKERJAAN M & E
1.00 Pekerjaan Listrik
1.01 Instalasi penerangan 37.00 1.00 37.00 ttk
1.02 Instalasi stop kontak 18.00 1.00 18.00 ttk
1.03 Stop kontak 18.00 1.00 18.00 ttk
1.04 lampu TL 2 x 18 watt grille 8.00 1.00 8.00 bh
1.05 lampu TL 2 x 36 watt grille 8.00 1.00 8.00 bh
1.06 Lampu Downlight 21.00 1.00 21.00 bh
1.07 Box Panel 1.00 1.00 1.00 unit
NO ITEM PEKERJAAN NO KODE PANJANG LEBAR LEBAR TINGGI JML VOLUME SAT
GAMBAR atas bawah BERAT
NO ITEM PEKERJAAN NO KODE PANJANG LEBAR LEBAR TINGGI JML VOLUME SAT
GAMBAR atas bawah BERAT
QTY-GS
QUANTITY
1.00
15.00
1.00
261.00
74.00
261.00
50.00
1.00
90.90
99.68
QTY-GS
QUANTITY
6.23
68.45
QTY-GS
QUANTITY
5.34
730.11
382.47
QTY-GS
QUANTITY
71.20
0.17
0.59
128.56
2.70
5.09
856.29
494.38
78.32
QTY-GS
QUANTITY
7.21
755.51
QTY-GS
QUANTITY
478.57
96.74
0.34
63.52
3.00
21.50
QTY-GS
QUANTITY
484.21
28.50
1.60
QTY-GS
QUANTITY
947.13
36.40
9.20
947.13
7.00
4.00
3.00
1.00
1.00
2.00
5.00
1.00
8.00
3.00
3.00
2.00
2.00
2.00
8.60
243.40
54.87
17.70
QTY-GS
QUANTITY
7.56
94.40
66.56
92.06
243.40
QTY-GS
QUANTITY
397.87
397.87
42.00
75.25
102.50
1.00
2.00
1.00
1.00
3.00
3.00
1.00
1.00
1.00
37.00
18.00
18.00
8.00
8.00
21.00
1.00
40.00
35.00
8.00
1.00
1.00
1.00
40.00
1.00
QTY-GS
QUANTITY
63.50
9.00
1.00
2.00
1.00
QTY-GS
QUANTITY
SPESIFIKASI RUMAH NEGARA
TABEL A2
SPESIFIKASI TEKNIS BANGUNAN RUMAH NEGARA
RUMAH
NO. URAIAN Keterangan
TIPE A TIPE B TIPE C,D,E
10. Tata Udara 6-10% bukaan atau dengan tata udara buatan (AC) 6-10% bukaan
A. PEKERJAAN STRUKTUR
A.1 Pekerjaan Pondasi 95,149,945
A.2 Pekerjaan Struktur 197,358,462
B. PEKERJAAN ARSITEKTUR
B.1 Pekerjaan Lantai 146,968,716
B.2 Pekerjaan Dinding 317,896,760
B.3 Pekerjaan Plafond 95,735,466
B.4 Pekerjaan Atap 257,271,600
B.5 Pekerjaan Kusen 96,923,432
C. PEKERJAAN UTILITAS
C.1 Pekerjaan Plumbing 103,373,554
C.2 Pekerjaan Elektrikal 19,466,800
D. PEKERJAAN FINISHING 113,731,658
C. PEKERJAAN UTILITAS
C.1 Pekerjaan Plumbing
C.1.1 Pekerjaan Sanitary
1 Pas. Washtafel keramik TOTO LW 240 CJ bh 2.00 898,400 1,796,800
2 Pas. Kloset Duduk Keramik TOTO CW 660 J / SW 660 J bh 2.00 3,365,800 6,731,600
3 Pas. Kloset Jongkok Keramik TOTO CE 7 bh 1.00 659,100 659,100
4 Pas. Bak Air Fiberglass Fibre glass bh 1.00 1,660,800 1,660,800
5 Pas. Shower spray TOTO THX 20 NBP1V bh 2.00 231,900 463,800
6 Pas. Shower set TOTO TX423SZ bh 2.00 370,200 740,400
7 Pas. Floor Drain TOTO TX 1 BN bh 4.00 230,100 920,400
8 Pas. Tempat sabun keramik TOTO S 11 N bh 3.00 168,200 504,600
9 Pas. Kitchenzink stainlees stell 1 lubang HWACO bh 1.00 670,100 670,100
10 Pas. Kran zink TOTO T 30 AR13V7N bh 1.00 225,900 225,900
11 Pas. Kran dinding TOTO T 23 B 13 bh 3.00 165,900 497,700 14,871,200
C.1.2 Pekerjaan Sumur Dalam
1 Pengeboran Sumur m' 36.00 75,000 2,700,000
2 Pipa PVC dia. 3" Casing; Wavin m' 36.00 281,600 10,137,600
3 Pipa PVC dia. 2" Casing; Wavin m' 10.00 193,400 1,934,000
4 Pipa PVC dia. 3/4" ex Wavin m' 36.00 80,100 2,883,600
5 Klep diameter 3/4" bh 1.00 107,300 107,300
6 Stop kran dia. 1" bh 1.00 232,400 232,400
7 Mesin Jet Pump kap.250 watt Groundfos bh 1.00 3,088,500 3,088,500 21,083,400
RAB RUMAH NEGARA TYPE A 249/296
A. RUMAH
1 Ruang keluarga+dapur r.tamu 4.000 4.500 18.000
6.000 10.500 63.000
3.000 1.500 4.500
2.500 1.500 3.750
4.000 2.500 10.000
2 Kamar tidur.1 4.500 3.000 13.500
3 Kamar tidur.2 4.500 3.000 13.500
4 Kamar tidur.3 4.500 3.000 13.500
5 Kamar tidur.4 4.500 3.000 13.500
6 Kamar tidur.5 3.000 2.000 6.000
7 Kamar tidur.6 3.000 2.000 6.000
8 R.Kerja 4.000 3.000 12.000
9 Kamar mandi.1 3.000 2.500 7.500
10 Kamar mandi.2 2.500 2.500 6.250
11 Kamar mandi.2 3.000 1.250 3.750
12 Garasi 6.000 4.500 27.000
13 Gudang 3.000 1.500 4.500
14 T.Cuci 1.250 1.500 1.875
15 Teras depan 4.500 3.500 15.750
16 Koridor 2.000 2.500 5.000
6.000 1.500 9.000
3.000 2.000 6.000
1.500 1.250 1.875
17 Teras belakang 20.000 1.250 25.000
6.000 1.000 6.000
4.000 2.500 10.000
306.750
No Uraian Pekerjaan PANJANG LEBAR JUMLAH
B. LAND SCAPE
1 Carport 6.000 6.000 36.000
1.500 1.500 2.250
2 Beton deuker 6.000 0.600 3.600
3 Pagar depan 20.000 2.000 40.000
4 Benteng samping depan 21.500 2.500 53.750
5 Benteng samping belakang 10.000 2.500 25.000
6 Benteng belakang 20.000 2.500 50.000
A. PEKERJAAN STRUKTUR
A.1 Pekerjaan Pondasi 36,721,032
A.2 Pekerjaan Struktur 70,705,004
B. PEKERJAAN ARSITEKTUR
B.1 Pekerjaan Lantai 62,960,742
B.2 Pekerjaan Dinding 189,209,845
B.3 Pekerjaan Plafond 44,502,039
B.4 Pekerjaan Atap 114,381,405
B.5 Pekerjaan Kusen 42,063,284
C. PEKERJAAN UTILITAS
C.1 Pekerjaan Plumbing 54,362,300
C.2 Pekerjaan Elektrikal 11,265,200
D. PEKERJAAN FINISHING 58,110,782
A. RUMAH
1 Ruang keluarga+dapur r.tamu 5.925 5.400 31.995
8.925 2.000 17.850
3.250 0.975 3.169
2 Kamar tidur utama 3.075 3.050 9.379
3 Kamar tidur anak.1 4.000 2.950 11.800
4 Kamar tidur anak.2 3.050 3.075 9.379
5 Kamar tidur pembantu 2.000 2.000 4.000
6 Kamar mandi.1 2.250 2.000 4.500
7 Kamar mandi.2 2.000 1.500 3.000
8 R.Setrika 2.000 2.000 4.000
9 Garasi 5.450 3.200 17.440
10 Tempat Cuci 2.000 1.200 2.400
11 Teras depan 2.000 2.000 4.000
12 Teras belakang 5.000 1.800 9.000
131.911
No Uraian Pekerjaan PANJANG LEBAR JUMLAH
B. LAND SCAPE
1 Carport 5.000 7.500 37.500
2 Beton deuker 7.500 0.600 4.500
3 Pagar depan 12.050 2.000 24.100
4 Benteng samping depan 8.150 1.500 12.225
5 Benteng belakang 5.000 2.500 12.500
m m m2
Summary 71.48
No Grid L H AREA
m m m2
64.75
II. ACCESSORIES
1 Kaca polos 5 mm m2 2.89
2 Engsel pintu bh 24.00
3 Engsel jendela bh 14.00
4 Kunci pintu utama bh 1.00
5 Kunci pintu kamar bh 5.00
6 Kunci pintu kamar mandi bh 2.00
7 Slot tanam ps -
8 Kait angin bh 7.00
9 Slot jendela bh 14.00
Type
Jumlah 1.00
Vol.Pasir / m3 -
Vol.Lantai kerja / m2
Vol.Beton / m3 1.94
Vol.Begisting / m2 25.90
Vol.Stoot Werk / m2
Total Berat Besi / kg
Dia. 10 mm 231.36
Dia.8 mm 89.71
Tulangan sengkang
- Juml.Bentang 64.75
- Jenis Besi U-24
- Jarak Pemasangan 0.175
- Diameter 8
0.008
- Berat/m' 0.39
- Panjang tulangan 64.75
- Panjang Begel 0.54
- Bengkokan 0.08
- Jml Begel 371.00
- Jumlah Berat Besi 89.71
TAKING OFF KOLOM
Tulangan sengkang
Jml Kolom 21.00 2.00
Jenis Besi U-24 U-24
Jarak Pemasangan 0.200 0.200
Diameter 8 8
0.008 0.008
Berat/m' 0.39 0.39
Panjang Begel 0.40 0.40
Panjang Tul Overlap 0.08 0.08
Panjang/ Tinggi Kolom 3.00 1.75
Jml Begel dlm 1 Kolom 16 9
Jumlah Berat 62.90 3.37
TAKING OFF BALOK
Tulangan Sengkang
- Jml.Bentang 2.00 3.00 1.00
- Jenis Besi U-24 U-24 U-24
- Jarak Pemasangan 0.175 0.175 0.175
- Diameter 8 8 8
0.008 0.008 0.008
- Berat/m' 0.39 0.39 0.39
- Panjang Bentang 8.50 8.50 86.75
- Panjang Begel 0.40 0.40 0.40
- Bengkokan 0.08 0.08 0.08
- Jml Begel dlm 1 bentang 49.00 49.00 496.00
- Jumlah Berat Besi 18.35 27.52 92.85
TAKING OFF KANOPI
Kanopi Beton
DDT Opening
4.93 3.15
1.38
1.58 0.65
3 1 1 1 1 1 1 2
P.1 P.2
VOLUME BANYAK JUMLAH VOLUME BANYAK JUMLAH VOLUME BANYAK JUMLAH
1.000 3 3.000
1.000 2 2.000
4.000 -
3.000 3 9.000 3.000 2 6.000 12.000 -
2.707 -
0.32
5.32
4.01
-
-
-
33.27
Wall finish
Background Finishing
Plaster Plaster Plaster Batu Tempel Keramik Painting
BG Fin Int. 1:5 Int. 1:3 Int. 1:5 20/20; T.1,6 Interior
1A 1B 1C 1 2 3
m2 m3 m2 m2 m2 m2
2.00
172.84 10.32 153.38 10.09 12.19 183.16
1A 3 18.06 - 18.06
1C 4 12.18 -
1A 3 19.41 - 19.41
1C 4 1.77 -
1A 3 23.01 - 23.01
1C 4 13.18 - -
1A 3 12.97 - - 12.97
1C 4 3.61 - -
- - -
1A 3 29.18 - 29.18
1C 4 14.01 - -
1A 3 29.18 - 29.18
1C 4 5.40 - -
1A 3 33.80 - 33.80
1C 4 24.58 - -
NF 2 - - 7.71 -
1B 3 6.96 - 6.96
1C 4 4.06 - -
NF 2 - - 4.48 -
1B 3 3.36 - 3.36
1C 4 2.24 - -
1A 3 7.24 - - 7.24
-
1C 4 - - 6.47 - - -
NF 1 - - - 10.09 - -
1C 4 - - 5.90 - - -
-
1C 4 - - 60.00 - - -
Sum
169.99
18.39
6.30
9.93
18.30
4.36
4.53
2.40
38.14
-
15.06
10.70
1.80
16.58
10.02
13.50
J.1
VOLUME BANYAK JUMLAH TOTAL
Finishing
Painting Sand Bed Lean concreate Keramik Keramik Screed
Exterior Fin t. 10 cm t. 5 cm 30/30 20/20 BG
4 1 2 3 4 5
m2 m3 m2 m2 m2 m2
0.1
153.38 7.61 76.06 71.79 4.27 -
3 8.08 - 8.08 -
- - - -
3 7.68 - 7.68 -
- - - -
3 13.28 - 13.28 -
- - - -
3 3.05 - 3.05 -
- - - -
- - - -
- - - -
3 9.38 - 9.38 -
- - - -
3 9.38 - 9.38 -
- - - -
3 11.80 - 11.80 -
- - - -
3 2.83 - 2.83 -
- - - -
- - - -
4 - 0.96 - 0.96
- - - -
- - - -
3 0.48 - 0.48 -
4 - 3.15 - 3.15
-
-
-
4 - 6.00 - 6.00
-
RAB Rumah type C, D E 276/296
A. PEKERJAAN STRUKTUR
A.1 Pekerjaan Pondasi 23,028,823
A.2 Pekerjaan Struktur 55,779,684
B. PEKERJAAN ARSITEKTUR
B.1 Pekerjaan Lantai 27,564,400
B.2 Pekerjaan Dinding 50,947,278
B.3 Pekerjaan Plafond 14,172,655
B.4 Pekerjaan Atap 61,460,613
B.5 Pekerjaan Kusen 22,788,200
C. PEKERJAAN UTILITAS
C.1 Pekerjaan Plumbing 29,278,560
C.2 Pekerjaan Elektrikal 6,334,100
D. PEKERJAAN FINISHING 15,842,084
B. PEKERJAAN ARSITEKTUR
B.1 Pekerjaan Lantai
1 Pas. Urugan pasir t. 10 cm m3 7.61 152,300 1,158,318
2 Pas. Lantai kerja beton tumbuk 1:3:5 t. 5 cm m2 76.06 65,700 4,996,814
3 Pas. Lantai Keramik 300x300 ex Masterina m2 76.06 265,000 20,154,575
4 Pas. Rabat beton; finish acian Beton 1:3:5 m2 9.15 137,200 1,254,694
Jumlah B.1 .... Rp 27,564,400
B.2 Pekerjaan Dinding
1 Pas. Dinding batu bata; ad 1:4 Batu bata merah m2 169.99 140,200 23,832,072
2 Pas. Plester acian; ad. 1:2 t. 15 mm; tanpa acian; interior m2 10.32 86,000 887,520
3 Pas. Plester acian; ad. 1:4 t. 15 mm; tanpa acian; eksterior m2 326.22 80,400
26,227,686
Jumlah B.2 .... Rp 50,947,278
B.3 Pekerjaan Plafond
1 Pas. Rangka Plafond Kayu Kayu klas III m2 65.95 158,500 10,453,075
2 Pas. Penutup Plafond Gypsumboard t. 9 mm m2 65.95 56,400 3,719,580
Jumlah B.3 .... Rp 14,172,655
B.4 Pekerjaan Atap
1 Pas. Kuda kuda Kayu Kayu klas III m3 1.43 8,420,500 11,999,213
2 Rangka Atap kayu m2 70.00 285,200 19,964,000
3 Penutup atap Genteng Keramik ex Jatiwangi m2 70.00 331,000 23,170,000
4 Bubungan Genteng Keramik ex Jatiwangi m' 9.50 166,400 1,580,800
5 Pas. Lisplank Kayu 3/20 mm Kayu kamper medan m' 24.50 104,400 2,557,800
6 Pas. Fleshing seng plat Seng bjls 35 m' 36.00 60,800 2,188,800
Jumlah B.4 .... Rp 61,460,613
RAB Rumah type C, D E 277/296
PAGAR
NO. URAIAN Keterangan
GEDUNG RUMAH
2 UKURAN PONDASI
Lebar Atas m 0.300 0.300 0.300
Lebar Bawah m 0.600 0.600 0.600
Tinggi m 0.700 0.700 0.700
1 UKURAN
Lebar m 0.150 0.150 0.150
Tebal m 0.200 0.200 0.200
Panjang m' 12.000 8.150 5.000
Banyaknya bh 1.000 1.000 1.000
2 TULANGAN MENERUS
Diameter mm 12.000 12.000 12.000
Berat kg/m 0.887 0.887 0.887
Sambungan % 5% 5% 5%
Panjang tulan m 12.600 8.558 5.250
Jumlah tulanga bh 4.000 4.000 4.000
Jumlah berat kg 44.70 30.36 18.63
Jumlah batang bt 4.200 2.853 1.750
3 TULANGAN TUMPUAN
Diameter mm 12.000 12.000 12.000
Berat kg/m 0.887 0.887 0.887
Sambungan % 5% 5% 5%
Panjang tulan m 3.360 2.349 1.523
Jumlah tulanga bh
Jumlah berat kg - - -
Jumlah batang bt - - -
4 TULANGAN LAPANGAN
Diameter mm 12.000 12.000 12.000
Berat kg/m 0.887 0.887 0.887
Sambungan % 5% 5% 5%
Panjang tulan m 7.560 5.135 3.150
Jumlah tulanga bh
Jumlah berat kg - - -
Jumlah batang bt - - -
6 TULANGAN SENGKANG
Diameter mm 8.000 8.000 8.000
Berat kg/m 0.393 0.393 0.393
Sambungan % 5% 5% 5%
Jarak sengkan m 0.150 0.150 0.150
Panjang sengk m' 0.735 0.735 0.735
Jumlah sengka bh 81.000 55.000 34.000
Jumlah berat kg 23.397 15.887 9.821
Jumlah batang bt 4.961 3.369 2.083
1 UKURAN
Lebar m 0.150 0.150 0.150
Panjang m 0.150 0.150 0.150
Tinggi m' 1.500 2.500 2.500
Banyaknya bh 3.000 4.000 2.000
2 TULANGAN UTAMA
Diameter mm 12.000 12.000 12.000
Berat kg/m' 0.887 0.887 0.887
Tiggi ring balk m 0.110 0.110 0.110
Panjang stek 4 m' 0.480 0.480 0.480
Sambungan % 5% 5% 5%
Panjang tulan m' 2.195 3.245 3.245
Jumlah tulanga bh 4.000 4.000 4.000
Jumlah berat kg 23.358 46.046 23.023
Jumlah batang bt 2.195 4.326 2.163
3 TULANGAN SENGKANG
Diameter mm 8.000 8.000 8.000
Berat kg/m' 0.393 0.393 0.393
Sambungan % 5% 5% 5%
Jarak sengkan m 0.150 0.150 0.150
Panjang sengk m' 0.630 0.630 0.630
Jumlah sengka bh 11.000 17.000 17.000
Jumlah berat kg 8.170 16.836 8.418
Jumlah batang bt 1.733 3.570 1.785
1 UKURAN
Lebar m 0.150 0.150 0.150
Tebal m 0.200 0.150 0.150
Panjang m' 8.150 5.000
Banyaknya bh 1.000 1.000 1.000
2 TULANGAN MENERUS
Diameter mm 12.000 12.000 12.000
Berat kg/m 0.887 0.887 0.887
Sambungan % 5% 5% 5%
Panjang tula m - 8.558 5.250
Jumlah tulan bh 4.000 4.000 4.000
Jumlah bera kg - 30.36 18.63
Jumlah batan bt - 2.853 1.750
3 TULANGAN TUMPUAN
Diameter mm 10.000 10.000 10.000
Berat kg/m 0.620 0.620 0.620
Sambungan % 5% 5% 5%
Panjang tula m 0.210 2.297 1.470
Jumlah tulan bh
Jumlah bera kg - - -
Jumlah batan bt - - -
4 TULANGAN LAPANGAN
Diameter mm 10.000 10.000 10.000
Berat kg/m 0.620 0.620 0.620
Sambungan % 5% 5% 5%
Panjang tula m - 5.135 3.150
Jumlah tulan bh
Jumlah bera kg - - -
Jumlah batan bt - - -
6 TULANGAN SENGKANG
Diameter mm 8.000 8.000 8.000
Berat kg/m 0.393 0.393 0.393
Sambungan % 5% 5% 5%
Jarak sengka m 0.150 0.150 0.150
Panjang seng m' 0.735 0.630 0.630
Jumlah sengk bh 1.000 55.000 34.000
Jumlah bera kg 0.289 13.617 8.418
Jumlah batan bt 0.061 2.888 1.785
12.50
RAB PAGAR BANGUNAN GEDUNG NEGARA
I BIAYA KONSTRUKSI
A PAGAR DEPAN tinggi 1,50 m Rp. 2,680,000
I BIAYA KONSTRUKSI
B PAGAR SAMPING tinggi 2 m Rp. 2,250,000
I BIAYA KONSTRUKSI
C PAGAR BELAKANG tinggi 3,00 m Rp. 2,350,000
pilar ;
3 Pas. Dinding batu bata; ad 1:4 Spesi 1 : 4 m2 15.60 140,200 2,187,120
4 Pas. Plester acian; ad. 1:4 Spesi 1 : 4 m2 31.20 80,400 2,508,480
5 Cat dinding dalam acrylic emulsion KW.II ex Mowilex m2 31.20 34,500 1,076,400
V. Pekerjaan Dinding
1 Pas. Dinding batu bata; ad 1:4 Spesi 1 : 4 m2 16.30 140,200 2,285,260
2 Pas. Plester acian; ad. 1:4 Spesi 1 : 4 m2 32.60 80,400 2,621,040
3 Cat dinding dalam acrylic emulsion KW.II ex Mowilex m2 32.60 34,500 1,124,700 6,031,000
V. Pekerjaan Dinding
1 Pas. Dinding batu bata; ad 1:4 Spesi 1 : 4 m2 12.50 140,200 1,752,500
2 Pas. Plester acian; ad. 1:4 Spesi 1 : 4 m2 25.00 80,400 2,010,000
3 Cat dinding dalam acrylic emulsion KW.II ex Mowilex m2 25.00 34,500 862,500 4,625,000
2 UKURAN PONDASI
Lebar Atas m 0.200 0.200 0.200
Lebar Bawah m 0.400 0.400 0.400
Tinggi m 0.600 0.600 0.600
1 UKURAN
Lebar m 0.100 0.100 0.100
Tebal m 0.150 0.150 0.150
Panjang m' 6.000 6.000 6.000
Banyaknya bh 1.000 1.000 1.000
2 TULANGAN MENERUS
Diameter mm 12.000 12.000 12.000
Berat kg/m 0.887 0.887 0.887
Sambungan % 5% 5% 5%
Panjang tulangan m 6.300 6.300 6.300
Jumlah tulangan bh 4.000 4.000 4.000
Jumlah berat kg 22.35 22.35 22.35
Jumlah batang bt 2.100 2.100 2.100
3 TULANGAN TUMPUAN
Diameter mm 12.000 12.000 12.000
Berat kg/m 0.887 0.887 0.887
Sambungan % 5% 5% 5%
Panjang tulangan m 1.733 1.733 1.733
Jumlah tulangan bh
Jumlah berat kg - - -
Jumlah batang bt - - -
4 TULANGAN LAPANGAN
Diameter mm 12.000 12.000 12.000
Berat kg/m 0.887 0.887 0.887
Sambungan % 5% 5% 5%
Panjang tulangan m 3.780 3.780 3.780
Jumlah tulangan bh
Jumlah berat kg - - -
Jumlah batang bt - - -
6 TULANGAN SENGKANG
Diameter mm 8.000 8.000 8.000
Berat kg/m 0.393 0.393 0.393
Sambungan % 5% 5% 5%
Jarak sengkang m 0.150 0.150 0.150
Panjang sengkang m' 0.525 0.525 0.525
Jumlah sengkang bh 41.000 41.000 41.000
Jumlah berat kg 8.459 8.459 8.459
Jumlah batang bt 1.794 1.794 1.794
1 UKURAN
Lebar m 0.100 0.100 0.100
Panjang m 0.100 0.100 0.100
Tinggi m' 1.500 2.000 2.500
Banyaknya bh 2.000 2.000 2.000
2 TULANGAN UTAMA
Diameter mm 12.000 12.000 12.000
Berat kg/m' 0.887 0.887 0.887
Tiggi ring balk m 0.110 0.110 0.110
Panjang stek 40 d m' 0.480 0.480 0.480
Sambungan % 5% 5% 5%
Panjang tulangan m' 2.195 2.720 3.245
Jumlah tulangan bh 4.000 4.000 4.000
Jumlah berat kg 15.572 19.298 23.023
Jumlah batang bt 1.463 1.813 2.163
3 TULANGAN SENGKANG
Diameter mm 8.000 8.000 8.000
Berat kg/m' 0.393 0.393 0.393
Sambungan % 5% 5% 5%
Jarak sengkang m 0.150 0.150 0.150
Panjang sengkang m' 0.420 0.420 0.420
Jumlah sengkang bh 11.000 14.000 17.000
Jumlah berat kg 3.631 4.622 5.612
Jumlah batang bt 0.770 0.980 1.190
1 UKURAN
Lebar m 0.100 0.100 0.100
Tebal m 0.100 0.100 0.100
Panjang m' 6.000 6.000
Banyaknya bh 1.000 1.000 1.000
2 TULANGAN MENERUS
Diameter mm 12.000 12.000 12.000
Berat kg/m 0.887 0.887 0.887
Sambungan % 5% 5% 5%
Panjang tulangan m - 6.300 6.300
Jumlah tulangan bh 4.000 4.000 4.000
Jumlah berat kg - 22.35 22.35
Jumlah batang bt - 2.100 2.100
3 TULANGAN TUMPUAN
Diameter mm 10.000 10.000 10.000
Berat kg/m 0.620 0.620 0.620
Sambungan % 5% 5% 5%
Panjang tulangan m 0.105 1.680 1.680
Jumlah tulangan bh
Jumlah berat kg - - -
Jumlah batang bt - - -
4 TULANGAN LAPANGAN
Diameter mm 10.000 10.000 10.000
Berat kg/m 0.620 0.620 0.620
Sambungan % 5% 5% 5%
Panjang tulangan m - 3.780 3.780
Jumlah tulangan bh
Jumlah berat kg - - -
Jumlah batang bt - - -
6 TULANGAN SENGKANG
Diameter mm 8.000 8.000 8.000
Berat kg/m 0.393 0.393 0.393
Sambungan % 5% 5% 5%
Jarak sengkang m 0.150 0.150 0.150
Panjang sengkang m' 0.420 0.420 0.420
Jumlah sengkang bh 1.000 41.000 41.000
Jumlah berat kg 0.165 6.767 6.767
Jumlah batang bt 0.035 1.435 1.435
6.00 15.00
RAB PAGAR RUMAH NEGARA
I BIAYA KONSTRUKSI
A PAGAR DEPAN tinggi 1,50 m Rp. 2,490,000
I BIAYA KONSTRUKSI
B PAGAR SAMPING tinggi 2 m Rp. 1,420,000
I BIAYA KONSTRUKSI
C PAGAR BELAKANG tinggi 2,50 m Rp. 1,590,000
pilar ;
3 Pas. Dinding batu bata; ad 1:4 Spesi 1 : 4 m2 8.70 140,200 1,219,740
4 Pas. Plester acian; ad. 1:4 Spesi 1 : 4 m2 17.40 80,400 1,398,960
Cat dinding dalam acrylic emulsion
5 ex Mowilex m2 17.40 34,500 600,300 3,219,000
KW.II