II BAHAN PEREKAT
1 Semen (50 Kg) Semen Tonasa zak 65,000
2 Semen Warna Pigmen Warna kg 20,000
IV BAHAN KAYU
1 Kayu Klas I Bayam (Balok) m3 15,000,000
2 Kayu Klas II Samarinda (Balok) m3 3,500,000
3 Kayu Klas III Kapur/kemiri(Balok) m3 2,500,000
4 Kayu Klas IV Terentang m3 2,000,000
5 Dolken dia 8 s/d 10 cm p. 4 m btg -
V BAHAN ALMUNIUM
1 Profil Kusen Almunium 4" m' 135,000
2 Rangka Jendela Almunium 4" m' 135,000
3 Rangka Pintu Almunium 4" m' 135,000
4 Kusen & Pintu Aluminium toilet unt 250,800
5 Engsel 4" bh 35,000
7 Handle pintu ex. yale bh 350,000
8 Selinder type 08510 ex. Cisa bh 75,000
9 Door Stoper ex. Belucci bh 50,000
10 Door closer ex.belucci bh 185,000
11 Slot Tanam ex.Belucci bh 150,000
12 Kait Angin bh 68,000
13 Grendel bh 150,000
14 Lem Silikon Kaca Aluminium Neutral Silicone Sealant bh 28,000
15 Karet Kaca bh 1,000
VI BAHAN PELAPIS :
1 Triplek t. 3 mm Uk 120x240 cm lbr 50,000
2 Triplex t. 4 mm Uk 120x240 cm lbr 60,000
3 Triplex t. 9 mm Uk 120x240 cm lbr 120,000
IX BAHAN KACA :
1 Kaca Polos 3 mm m2 110,000
2 Kaca Polos 5 mm m2 135,000
3 Kaca Polos 8 mm m2 330,000
XI BAHAN FINISHING :
1 Cat kayu/Besi ex. Mowilex Kg 70,000
2 Plamir Kayu ex. Impra Kg 40,000
3 Meni kayu ex. Glatik kg 39,143
4 Wood Filler Impra Kg 65,000
5 Thinner ex. Avian Ltr 28,100
6 Amplas Kayu Kertas gosok Lbr 5,000
7 Kwas cat 4" ex. Eterna bh 18,000
8 Cat Tembok kw1 ex. Dulux ; luar Kg 104,000
9 Cat Tembok kw2 ex. Mowilex ; Luar Kg 52,000
10 Plamir Tembok ex. Boyo Kg 9,000
11 Lem Kayu ex. Fox kg 145,000
12 Seal tape bh 5,000
13 Minyak bekisting Ltr 24,000
XV PERALATAN ELEKTRIKAL
1 Box panel PVC isi 4 MCB bh 22,000 -
2 MCB 6 A bh 60,000 -
3 MCB 4 A bh 60,000 -
4 Kabel NYM 2 x 2,5 mm2 NYY m' 9,000 -
5 Kabel telephone 4 x 0.5 mm m' 15,000 -
6 Isolasi bh 8,500 -
7 Saklar tunggal Clipsal bh 16,700 -
8 Saklar ganda Clipsal bh 26,500 Panasonic
9 Stop kontak Clipsal bh 33,400 -
10 Outlet TV Broco bh 43,575 -
11 Outlet Telephone Broco bh 43,575 -
12 Down light / PLC 10 W 3000k ex Meson Gen 2 bh 87,500 Philips
12 Down light / PLC 12 W 6500k ex Eridani bh 95,000 Philips
12 Down light / PLC 17 W 6500k ex Meson G3 bh 120,000 Philips
13 Fitting plafond + lampu SL eletra + led 12 watt bh 62,900 -
14 Rumah lampu RM 2x18 W TL 2 x 18 W + Mirror Reflector bh 125,000 -
Satuan Kerja
Pekerjaan
Lokasi
Provinsi Sulawesi Selatan
Kota/Kabupaten Kota Makassar
Tahun Anggaran 2021
0
Overhead
I. PEKERJAAN PERSIAPAN :
M2 Pemasangan Spanduk Konstruksi 2,200 13,870 10% 17,677 17,700
Banner Flexi China 280 GSM m2 0.100 20,000 2,000
Paku 1 s/d 3 cm kg 0.010 20,000 200
Pekerja org/hr 0.100 128,700 12,870
Mandor org/hr 0.005 200,000 1,000
M2 Pek. Partisi Kaca Rangka Aluminium - 308,050 288,384 10% 656,077 656,100
M2 Pas. Dinding batu bata; ad 1:2 - 103,185 59,340 10% 178,778 178,800
M2 Pas. Dinding partisi Rangka Metal - 114,500 206,384 10% 352,972 353,000
Rangka Metal furing termasuk ripet m2 1.000 50,000 50,000
M2 Pas. Plester acian; ad. 1:2 t.15 mm; tanpa acian - 17,791 68,205 10% 94,596 94,600
M2 Pas. Plester acian; ad. 1:4 t.15 mm; tanpa acian - 13,512 68,205 10% 89,889 89,900
M2 Pas. Lantai Beton; finish acian beton 1:3:5, t. 10 cm - 195,364 58,340 10% 279,074 279,100
m2 1.766
Pas. Lantai kerja beton tumbuk 1:3:5 69,000 121,854
Semen (50 Kg) zak 0.454 65,000 29,510
Pasir Beton m3 0.054 225,000 12,150
Batu Split Pecah Mesin 1/2 m3 0.091 350,000 31,850
Pekerja org/hr 0.300 128,700 38,610
Tukang Batu Kasar org/hr 0.100 160,000 16,000
Kepala Tukang Batu org/hr 0.010 173,000 1,730
Mandor org/hr 0.010 200,000 2,000
-
M2 Pas. Rangka Plafond Hollow 3x3 - 22,500 80,540 10% 113,344 113,300
Rangka Hollow m' 1.000 22,500 22,500
Pekerja org/hr 0.200 128,700 25,740
Tukang Besi Konstruksi org/hr 0.300 160,000 48,000
Kepala Tukang Besi org/hr 0.030 160,000 4,800
Mandor org/hr 0.010 200,000 2,000
-
M2 Cat dinding dalam acry. Emu. KW.II Interior - 19,620 14,244 10% 37,250 37,300
( 1 Lapis Plamir + 1
Plamir Tembok Lapis Cat Dasar + 2 kg 0.100 9,000 900
Lapis + 2 Lapis Cat
Cat Tembok kw2 Penutup ) kg 0.100 52,000 5,200
Cat Tembok kw2 kg 0.260 52,000 13,520
Pekerja org/hr 0.020 128,700 2,574
Tukang Cat Biasa org/hr 0.063 160,000 10,080
Kepala Tukang Cat org/hr 0.006 173,000 1,090
Mandor org/hr 0.003 200,000 500
M2 Cat plafond acrylic emulsion KW.I Interior - 38,340 14,244 10% 57,842 57,800
( 1 Lapis Plamir + 1
Plamir Tembok Lapis Cat Dasar + 2 kg 0.100 9,000 900
Lapis + 2 Lapis Cat
Cat Tembok kw1 Penutup ) kg 0.100 104,000 10,400
Cat Tembok kw1 kg 0.260 104,000 27,040
Pekerja org/hr 0.020 128,700 2,574
Tukang Cat Biasa org/hr 0.063 160,000 10,080
Kepala Tukang Cat org/hr 0.006 173,000 1,090
Mandor org/hr 0.003 200,000 500
-
VIII. PEKERJAAN KUSEN -
M Kusen Pintu dan Jendela Alumunium CA 133.333 - 152,000 13,578 10% 182,136 182,100
Profil Kusen Almunium m 1.100 135,000 148,500
Paku Skrup bh 2.000 1,750 3,500
Pekerja org/hr 0.043 128,700 5,534
Tukang Kayu Halus org/hr 0.043 160,000 6,880
Kepala Tukang Kayu org/hr 0.004 173,000 744
Mandor org/hr 0.002 200,000 420
-
M Kusen Pintu dan Jendela Alumunium PC 133.333 - 152,000 13,578 10% 182,136 182,100
Profil Kusen Almunium m 1.100 135,000 148,500
Paku Skrup bh 2.000 1,750 3,500
Pekerja org/hr 0.043 128,700 5,534
Tukang Kayu Halus org/hr 0.043 160,000 6,880
Kepala Tukang Kayu org/hr 0.004 173,000 744
Mandor org/hr 0.002 200,000 420
-
Unt Kusen & Pintu PVC toilet 133.333 - 261,300 30,177 10% 320,625 320,600
Kusen & Pintu Aluminium toilet m 1.000 250,800 250,800
Paku Skrup bh 6.000 1,750 10,500
Pekerja org/hr 0.045 128,700 5,792
Tukang Kayu Halus org/hr 0.135 160,000 21,600
Kepala Tukang Kayu org/hr 0.014 173,000 2,336
Mandor org/hr 0.002 200,000 450
-
BH Pas. Kunci tanam pintu Almunium - 350,000 88,650 10% 482,515 482,500
Handle pintu bh 1.000 350,000 350,000
Pekerja org/hr 0.000 128,700 -
Tukang Kayu Halus org/hr 0.500 160,000 80,000
Kepala Tukang Kayu org/hr 0.050 173,000 8,650
Mandor org/hr 0.000 200,000 -
-
BH Pas. Kunci knob pintu kamar mandi - 350,000 106,380 10% 502,018 502,000
Handle pintu bh 1.000 350,000 350,000
Pekerja org/hr 0.000 128,700 -
Tukang Kayu Halus org/hr 0.600 160,000 96,000
Kepala Tukang Kayu org/hr 0.060 173,000 10,380
Mandor org/hr 0.000 200,000 -
-
BH Pas. Kitchen Sink stainlees steel - 1,018,940 326,000 10% 1,479,434 1,479,400
Kitchen sink 1 lubang bh 1.000 783,800 783,800
Fitting, Stop valve & support set 0.300 783,800 235,140
Pekerja 1.000 128,700
org/hr 128,700
Tukang Batu Halus 1.000 160,000
org/hr 160,000
Kepala Tukang Batu 0.100 173,000
org/hr 17,300
Mandor org/hr 0.100 200,000 20,000
-
TTK Pas. Instalasi stop kontak - 58,700 46,935 10% 116,199 116,200
Kabel NYM 2 x 2,5 mm2 m 6.000 9,000 54,000
Isolasi bh 0.500 8,500 4,250
Klem bh 3.000 150 450
Pekerja org/hr 0.050 128,700 6,435
Tukang Listrik org/hr 0.020 160,000 3,200
Kepala Tukang Listrik org/hr 0.100 173,000 17,300
Mandor org/hr 0.100 200,000 20,000
-
Satuan Kerja
Pekerjaan
Lokasi
Provinsi Sulawesi Selatan
Kota/Kabupaten Kota Makassar
Tahun Anggaran 2021
I. PEKERJAAN PERSIAPAN
K3 dan Safety Tools 1.00 Ls 2,500,000.00 2,500,000.00
Pemugaran Area Protek dengan Banner 1.00 Ls 2,000,000.00 2,000,000.00
Pengamanan Inventaris Kantor 1.00 Ls 2,000,000.00 2,000,000.00
SUB JUMLAH I 6,500,000.00
II. PEKERJAAN PENDAHULUAN
Laporan dan Dokumentasi 3.00 Rangkap Tanggung Jawab Rekanan
Pek. Pembongkaran Dinding Partisi 84.60 m2 82,300 6,962,580.00
Pek. Bongkar Dinding Bata (Void) 9.90 m2 82,300 814,770.00
Pek. Bongkar Plat Lantai Lama 63.00 m2 18,600 1,171,800.00
Pek. Pembongkaran Plafond + Rangka 250.48 m2 82,300 20,614,504.00
SUB JUMLAH II 29,563,654.00
III. PEKERJAAN KONSTRUKSI LANTAI
1. Penutupan Area Void
Tulangan besi beton U-39 261.89 Kg 23,500 6,154,368.00
Bekisting Beton Plat Lantai 5.04 m2 391,500 1,973,160.00
Beton K - 250 1.49 m3 1,273,300 1,890,850.50
2. Penambahan Level Elevasi Lantai
Tulangan besi beton U-39 1249.92 Kg 23,500 29,373,120.00
Bekisting Beton Plat Lantai 25.20 m2 391,500 9,865,800.00
Beton K - 250 9.45 m3 1,273,300 12,032,685.00
3. Pekerjaan Tangga Koridor
Tulangan besi beton U-39 132.28 Kg 23,500 3,108,655.20
Tulangan besi beton U-24 46.57 Kg 147,100 6,850,388.16
Bekisting beton plat lantai 1.98 m2 391,500 775,170.00
Beton K - 225 0.49 m3 1,258,100 616,469.00
SUB JUMLAH III 72,640,665.86
IV. PEKERJAAN REHABILITASI RUANG
Pek. Partisi Kaca Rangka Aluminium 22.05 m2 656,100 14,467,005.00
Pas. Dinding partisi Rangka Metal 20.01 m2 353,000 7,063,530.00
Pas. Dinding batu bata; ad 1:2 66.96 m2 178,800 11,972,448.00
Pas. Plester acian; ad. 1:4 66.96 m2 89,900 6,019,704.00
SUB JUMLAH IV 39,522,687.00
V. PEKERJAAN LANGIT - LANGIT
Pas. Rangka Plafond Hollow 3x3 250.48 m2 113,300 28,379,384.00
Pas. Penutup Plafond Gypsum t. 9 mm 250.48 m2 55,300 13,851,544.00
SUB JUMLAH V 42,230,928.00
VI. PEKERJAAN KUSEN
Kusen Pintu KP1 (900 x 2100 mm) 3.00 Unit 2,230,500 6,691,500.00
Kusen Pintu KP2 (800 x 2100 mm) 3.00 Unit 2,230,500 6,691,500.00
Kusen Pintu KP3 (PVC) 2.00 Unit 885,600 1,771,200.00
Kusen Pintu KP4 (900 x 2100 mm) 1.00 Unit 2,230,500 2,230,500.00
Kusen Pintu KP5 (1600 x 2100 mm) 1.00 Unit 2,624,100 2,624,100.00
Kusen Jendela KJ1 30.00 Unit 805,000 24,150,000.00
Kusen Jendela KJ2 13.00 Unit 1,790,000 23,270,000.00
Kusen Jendela KJ3 2.00 Unit 8,620,000 17,240,000.00
SUB JUMLAH VI 84,668,800.00
VII. PEKERJAAN UTILITAS
1. Utilitas Kamar Mandi
Pas. Kloset Duduk Keramik 2.00 Unit 3,969,800 7,939,600.00
Pas. Shower spray 2.00 Unit 239,600 479,200.00
Pas. Kran dinding 2.00 Unit 63,600 127,200.00
Pipa PVC dia. 4" 1.00 m' 136,700 136,700.00
Pipa PVC dia. 3" 2.20 m' 85,600 188,320.00
Pipa PVC dia. 1/2" 6.20 m' 25,400 157,480.00
Pas. Floor Drain 2.00 Unit 256,900 513,800.00
2. Utilitas Dapur (Kitchen)
Pas. Kitchen Sink stainlees steel 1.00 Unit 1,479,400 1,479,400.00
Pas. Kran Sink 1.00 Unit 195,600 195,600.00
Pas. Meja Pantry uk. 600x 1500 mm 1.00 Unit 2,004,600 2,004,600.00
Pipa PVC dia. 3" 7.50 m' 85,600 642,000.00
Pipa PVC dia. 1/2" 9.50 m' 25,400 241,300.00
SUB JUMLAH VII 14,105,200.00
VIII. PEKERJAAN ELEKTRIKAL
Pemindahan Komponen Elektrik Vital 1.00 Ls 2,175,200 2,175,200.00
Pas. Box Panel 1.00 Unit 998,100 998,100.00
Pas. Instalasi stop kontak 12.00 ttk 116,200 1,394,400.00
Pas. Instalasi Lampu 22.00 ttk 116,200 2,556,400.00
Pas. Saklar engkel 8.00 ttk 68,600 548,800.00
Pas. Saklar double 14.00 ttk 79,400 1,111,600.00
Pas. Stop kontak 12.00 ttk 86,900 1,042,800.00
#NAME? 77.00 Bh - -
Pas. Lampu Bidang 3.00 Bh 1,787,100 5,361,300.00
Pas. Lampu Sorot 8.00 Bh 109,600 876,800.00
Pas. Uplight 8.00 Bh 153,600 1,228,800.00
SUB JUMLAH VIII 15,119,000.00
IX. PEKERJAAN FINISHING
1. Pekerjaan Finishing Lantai
Pas. Lantai kerja beton tumbuk 1:3:5 6.49 m3 69,000 448,113.60
Pas. Urugan pasir 10.82 m3 232,600 2,517,662.40
Pas. Lantai Keramik 600x600 217.09 m2 256,500 55,683,585.00
Pas. Lantai Keramik 250x250 9.48 m2 298,100 2,825,988.00
2. Pekerjaan Finishing Dinding
Cat eksterior waterproof 3 in 1 429.78 m2 23,900 10,271,742.00
3. Pekerjaan Finishing Plafond
Cat plafond acrylic emulsion KW.I 250.48 m2 57,800 14,477,744.00
SUB JUMLAH IX 86,224,835.00
X. PEKERJAAN AKHIR
Pembersihan Wilayah Kerja 250.48 m2 15,300 3,832,344.00
Administrasi 1.00 Ls 2,000,000 2,000,000.00
SUB JUMLAH VIII 5,832,344.00
REKAPITULASI BIAYA PEKERJAAN
Satuan Kerja
Pekerjaan Desain Kawasan Taman Universitas Muslim Indonesia
Lokasi
Provinsi Sulawesi Selatan
Kota/Kabupaten Kota Makassar
Tahun Anggaran 2021
JUMLAH Rp 1,417,553,729
DIBULATKAN Rp 1,559,309,000
TERBILANG :
BILL OF QUANTITY
Satuan Kerja
Pekerjaan Desain Kawasan Taman Universitas Muslim Indonesia
Lokasi
Provinsi Sulawesi Selatan
Kota/Kabupaten Kota Makassar
Tahun Anggaran 2021
NO URAIAN PEKERJAAN SPESIFIKASI TEKNIS VOLUME SATUAN HARGA SATUAN JUMLAH HARGA
(RP) (RP)
I. PEKERJAAN PERSIAPAN
Persiapan K3 dan Safety Tools 1.00 Ls 2,500,000.00 2,500,000.00
Pekerjaan Pengukuran dan Pemetaan Wajah dan kontur tanah 1.00 Set 2,000,000.00 2,000,000.00
Pembuatan Papan Nama Proyek 1.00 Ls 587,800.00 587,800.00
Penyewaan Alat Berat (Excavator) Galian dan Pengurasan 1.00 Ls 4,800,000.00 4,800,000.00
Pembuatan Gudang dan Direksi Kit 1.00 Ls 1,000,000.00 1,000,000.00
SUB JUMLAH I 10,887,800.00
II. PEKERJAAN PENDAHULUAN
Laporan dan Dokumentasi 3.00 Set 1,000,000 3,000,000.00
Pek.Pembersihan Tahap Awal 3005.00 m2 15,300 45,976,500.00
SUB JUMLAH II 45,976,500.00
III. PEKERJAAN LANDASAN
1 Pembuatan Lanti Kerja ketebalan 3 cm 90.15 m3 94,900 8,555,235.00
2 Pekerjaan Sirkulasi Pengguna
Tulangan Besi Beton U-39 besi polos diameter 13 2005.82 kg 23,500 47,136,864.00
Bekisting Beton Plat Lantai 84.22 m2 137,300 11,563,406.00
Beton K-250 24.00 m3 1,176,000 28,224,000.00
3 Pekerjaan Dinding Taman
Pas. Dinding Batu Bata; ad 1:2 139.93 m2 178,800 25,019,484.00
Pas. Plester acian; ad 1:4 139.93 m2 89,900 12,579,707.00
SUB JUMLAH III 95,479,505.00
IV. PEMBUATAN KOLAM DAN OVERSTEK BETON
1 Pek. Galian Tanah kedalaman 90 cm 485.10 m3 111,700 54,185,670.00
Pas. Urugas pasir 26.95 m3 232,600 6,268,570.00
Pas. Lantai Kerja Beton Tumbuk 1:3:5 ketebalan 3 cm 16.17 m2 94,900 1,534,533.00
2 Pek. Pembuatan Dinding Kolam - overstek beton
Tulangan Besi Beton U-39 besi ulir diameter 13 2037.00 kg 147,100 299,642,700.00
Bekisting Beton Plat Lantai 433.15 m2 137,300 59,471,495.00
Beton K-250 210.48 m3 1,176,000 247,518,600.00
3 Pek. Drainase Kolam
Pipa PVC dia. 3" 55.00 m' 85,600 4,708,000.00
Pas. Floor Drain 5 Unit 256,900 1,284,500.00
4 Pek. Kolam Utama
Pek. Galian Tanah kedalaman 90 cm 180.00 m3 111,700 20,106,000.00
Pas. Urugas pasir 10.00 m3 232,600 2,326,000.00
Pas. Lantai Kerja Beton Tumbuk 1:3:5 ketebalan 3 cm 6.00 m2 94,900 569,400.00
Tulangan Besi Beton U-39 besi ulir diameter 13 333.33 kg 147,100 49,033,333.33
Bekisting Beton Plat Lantai 107.85 m2 137,300 14,807,805.00
Beton K-250 50.00 m3 1,176,000 58,800,000.00
Pas. Dinding Batu Bata; ad 1:2 12.5 m2 178,800 2,235,000.00
Pas. Plester acian; ad 1:4 12.5 m2 89,900 1,123,750.00
Pipa PVC dia. 3" 5.00 m' 85,600 428,000.00
Pas. Floor Drain 5 Unit 256,900 1,284,500.00