DAFTAR PERHITUNGAN MATERIAL Halaman 1
PEKERJAAN SIPIL Tgl. Terbit 23/03/2018
PROJECT: Pembangunan Workshop dan Warehouse Facility
PAMA - BEKB, Kalimantan Timur Kode Project:
BEKB
NO : 0xx /III/PAMA BEKB/2018
NO JENIS MATERIAL VOLUME SAT MERK TYPE QTY KETERANGAN

Untuk : BANGUNAN OFFICE MAIN WORKSHOP


OFFICE LANTAI 1
1 Gypsum board 9 mm 41 lmbr Jayaboard Uk. 1200 x 2400 x 9 mm 41.00 lmbr
2 GRC board 7 lmbr GRC board Uk. 1220 x 2440 x 9 mm 7.00 lmbr
3 List Plafon (1 batang = 2 m) 155 m Gypsum Type C5, t = 7 cm 78 Btg
4 Rangka hollow 20x40 mm, P = 4 m 111 Btg Lokal uk. 20x40 , t=0.3 mm 111.00 Btg
Zincalume
5 Rangka Hollow 40x40 mm, P = 4 m 22 Btg Lokal uk. 40x40 , t=0.3 mm 22.00 Btg
Zincalume
6 Screw Gypsum ( isi 2000 / dus ) 2 dus Lokal isi 2000 / dus 1.96 dus
7 Compound, 40 m2 / zak (isi 20 kg) 3 zak Lokal 40 m2 / zak @ 20 kg 3.46 zak
8 Cutting Tape, 1 rol / 10 lembar 5 rol Lokal 1 rol = 10 lembar 4.80 rol

OFFICE LANTAI 2
1 Gypsum board 9 mm 44 lmbr Jayaboard Uk. 1200 x 2400 x 9 mm 44.00 lmbr
2 GRC board 9 lmbr GRC board Uk. 1220 x 2440 x 9 mm 9.00 lmbr
3 List Plafon (1 batang = 2 m) 154 m Gypsum Type C5, t = 7 cm 77 Btg
4 Rangka hollow 20x40 mm, P = 4 m 131 Btg Lokal uk. 20x40 , t=0.3 mm 131.00 Btg
Zincalume
5 Rangka Hollow 40x40 mm, P = 4 m 23 Btg Lokal uk. 40x40 , t=0.3 mm 23.00 Btg
Zincalume
6 Screw Gypsum ( isi 2000 / dus ) 2 dus Lokal isi 2000 / dus 2.06 dus
7 Compound, 40 m2 / zak (isi 20 kg) 4 zak Lokal 40 m2 / zak @ 20 kg 3.82 zak
8 Cutting Tape, 1 rol / 10 lembar 5 rol Lokal 1 rol = 10 lembar 5.30 rol

Disetujui Oleh, Mengetahui, Diperiksa Oleh, Dibuat Oleh,


Lilik Muflihun Mushoffa Jaja Hajar
Direktur Utama Manager Engineering Manager Engineering Engineering
Kode Dok. F-E
FORMULIR - 2B
Revisi 0
DAFTAR PERHITUNGAN MATERIAL Halaman 1
PEKERJAAN SIPIL Tgl. Terbit 23/03/2018
PROJECT: Pembangunan Workshop dan Warehouse Facility
PAMA - BEKB, Kalimantan Timur Kode Project:
BEKB
NO : 0xx /III/PAMA BEKB/2018
NO JENIS MATERIAL VOLUME SAT MERK TYPE QTY KETERANGAN

Untuk : BANGUNAN OFFICE MAIN WORKSHOP


1 Gypsum board 9 mm 85 lmbr Jayaboard Uk. 1200 x 2400 x 9 mm 85.00 lmbr

2 GRC board 16 lmbr GRC board Uk. 1220 x 2440 x 9 mm 16.00 lmbr

3 List Plafon (1 batang = 2 m) 313 m Gypsum Type C5, t = 7 cm 157 Btg

4 Rangka hollow 20x40 mm, P = 4 m 246 Btg Lokal uk. 20x40 , t=0.3 mm 246.00 Btg
Zincalume

5 Rangka Hollow 40x40 mm, P = 4 m 48 Btg Lokal uk. 40x40 , t=0.3 mm 48.00 Btg
Zincalume

6 Screw Gypsum ( isi 2000 / dus ) 3 dus Lokal isi 2000 / dus dus

7 Compound, 40 m2 / zak (isi 20 kg) 7 zak Lokal 40 m2 / zak @ 20 kg zak

8 Cutting Tape, 1 rol / 10 lembar 10 rol Lokal 1 rol = 10 lembar rol

Disetujui Oleh, Mengetahui, Diperiksa Oleh, Dibuat Oleh,

Lilik Muflihun Mushoffa Jaja Hajar


Direktur Utama Managet Engineering Managet Engineering Engineering
PLAFOND OFFICE MAIN WORKSHOP
Rangka hollow 20x40 mm, P = 4 m
Lantai 1
R.Mekanik = 4.9 x 11 = 53.9
R.GL = 4.9 x 7= 34.3
Area Toilet = 4.9 x 2= 9.8
1.9 x 3= 5.7
1.4 x 4= 5.6
Area Toilet = 1.9 x 2= 3.8
R.Panel = 2.9 x 2= 5.8
R.Komponen = 2.9 x 4= 11.6
Area Koridor = 2.9 x 3= 8.7
Area Koridor = 1.9 x 15 = 28.5
2x 6= 12
R.tools Room = 2.9 x 7= 20.3
Keliling ruangan
R.Mekanik = 23.6 x 1= 23.6
R.GL = 18.6 x 1= 18.6
Area Toilet = 16.6 x 1= 16.6
12.4 x 1= 12.4
Area Toilet = 7.6 x 1= 7.6
R.Panel = 9.6 x 1= 9.6
R.Komponen = 11.6 x 1= 11.6
Area Koridor = 9.6 x 1= 9.6
Area Koridor = 29.85 x 1= 29.85
R.tools Room = 14.6 x 1= 14.6
Pengait = 1.2 x 73 = 87.6
441.65 m
110.4125 btg
111 btg

Lantai 2
R. Meeting = 4.9 x 11 = 53.9
R. Planner = 4.9 x 7= 34.3
Area Toilet = 4.9 x 2= 9.8
1.9 x 3= 5.7
1.4 x 4= 5.6
Dept Head = 4.9 x 4= 19.6
R.Admin = 4.9 x 2= 9.8
Balkon = 1.4 x 6= 8.4
R.Server = 2.9 x 3= 8.7
Area Koridor = 3.4 x 6= 20.4
1.9 x 4= 7.6
4.9 x 6= 29.4
Keliling ruangan
R. Meeting = 22.8 x 1= 22.8
R. Planner = 18.6 x 1= 18.6
Area Toilet = 16.6 x 1= 16.6
12.4 x 1= 12.4
Dept Head = 15.4 x 1= 15.4
R.Admin = 13.6 x 1= 13.6
Balkon = 10.6 x 1= 10.6
R.Server = 10.6 x 1= 10.6
Area Koridor = 32.9 x 1= 32.9
Pengait = 2x 77 = 154
520.7 m
130.175 btg
131 btg

Total Hollow 20x40 mm, P = 4 m = 242 btg

Rangka Hollow 40x40 mm, P = 4 m


Lantai 1
R.Mekanik = 6.9 x 3= 20.7
R.GL = 4.4 x 3= 13.2
Area Toilet = 1.6 x 2= 3.2
3.4 x 2= 6.8
1.7 x 2= 3.4
Area Toilet = 1.9 x 1= 1.9
R.Panel = 1.9 x 2= 3.8
R.Komponen = 2.9 x 2= 5.8
Area Koridor = 1.9 x 2= 3.8
Area Koridor = 12.9 x 1= 12.9
R.tools Room = 4.4 x 2= 8.8
84.3 m
21.075 btg
22 btg

Lantai 2
R. Meeting = 6.5 x 3= 19.5
R. Planner = 4.4 x 3= 13.2
Area Toilet = 1.6 x 2= 3.2
3.4 x 2= 6.8
1.7 x 2= 3.4
Dept Head = 2.8 x 3= 8.4
R.Admin = 1.9 x 3= 5.7
Balkon = 3.9 x 1= 3.9
R.Server = 2.4 x 2= 4.8
Area Koridor = 3.9 x 1= 3.9
9.9 x 1= 9.9
3.4 x 2= 6.8
89.5 m
22.375 btg
23 btg

Total Hollow 40x40 mm, P = 4 m = 45 btg

List Plafond
Lantai 1
Keliling ruangan
R.Mekanik = 23.6 x 1= 23.6
R.GL = 18.6 x 1= 18.6
Area Toilet = 16.6 x 1= 16.6
12.4 x 1= 12.4
Area Toilet = 7.6 x 1= 7.6
R.Panel = 9.6 x 1= 9.6
R.Komponen = 11.6 x 1= 11.6
Area Koridor = 9.6 x 1= 9.6
Area Koridor = 29.85 x 1= 29.85
R.tools Room = 14.6 x 1= 14.6
154.05 m
155 m
155 m

Lantai 2
Keliling ruangan
R. Meeting = 22.8 x 1= 22.8
R. Planner = 18.6 x 1= 18.6
Area Toilet = 16.6 x 1= 16.6
12.4 x 1= 12.4
Dept Head = 15.4 x 1= 15.4
R.Admin = 13.6 x 1= 13.6
Balkon = 10.6 x 1= 10.6
R.Server = 10.6 x 1= 10.6
Area Koridor = 32.9 x 1= 32.9