ESTIMASI ANGGARAN BIAYA PEMBANGUNAN RUANG KELAS DAN ASRAMA SELATAN


3 x 7 x 8 (meter)
PP ARRAHMAH DI GOLOKAN, SIDAYU, GRESIK - JAWA TIMUR
Nama Proyek : Pembangunan Ruang Asrama PP ArRahmah
Lokasi : Desa Golokan, Kec. Sidayu, Gresik - Jawa Timur

Volume Unit Harga


No. URAIAN PEKERJAAN Total (Rp) Keterangan
Q'ty Unit Satuan (Rp)

A Pekerjaan Persiapan Subtotal A 14,400,000


Survey & Pengukuran 1.00 ls 1,680,000 1,680,000
Pembersihan Lokasi Kerja 1.00 ls 1,260,000 1,260,000
Pemasangan utilitas bowplank 78.00 m' 50,000 3,900,000
Mobilisasi peralatan 1.00 ls 3,360,000 3,360,000
Sarana & prasarana sementara 1.00 ls 4,200,000 4,200,000
B Pekerjaan Tanah Subtotal B 22,244,498
Galian Tanah pondasi & Sloof 52.88 m3 95,000 5,023,980
Urug pasir bawah pondasi & sloop 6.22 m3 124,000 771,528
Urug tanah kembali 31.73 m3 26,000 824,990
Urug pedel 100.80 m3 124,000 12,499,200
Urug pasir bawah lantai 25.20 m3 124,000 3,124,800
C Pekerjaan Beton Subtotal C 712,564,563
Lantai 1 Dasar LT 1 712,564,563
Pondasi setempat 1,2/1,2 x 0,3 (m) 7.78 m3 5,875,000 45,684,000
Pasangan Umpak 121.00 m' 110,000 13,310,000
Pekerjaan sloof 40/60 (b8;12;16) 18.24 m3 5,875,000 107,160,000
Pekerjaan sloof 20/40 (b6;10;12) 6.08 m3 5,875,000 35,720,000
Pekerjaan kolom 40/40 (b8;12;16) 14.40 m3 5,875,000 84,600,000
Pekerjaan kolom/balok dinding 10x10 (b6;8) 1.08 m3 5,875,000 6,345,000
Pekerjaan balok 35/60 (b8;12;16) 25.41 m3 5,875,000 149,283,750
Pekerjaan cantilever 15/50/130 (b6;8;12) 2.62 m3 5,875,000 15,377,813
Rabat 5 cm 11.55 m3 1,250,000 14,437,500
Plat lantai dasar, t=8 cm (b10) 18.48 m3 5,175,000 95,634,000
Plat lantai 1, t=10 cm (b10) 23.10 m3 5,875,000 135,712,500
Plat Tangga ke lantai 2 1.20 m3 7,750,000 9,300,000
Lantai 2 LT 2 -
Lantai 3 LT 3 -
Atap Atap -
2/2
Volume Unit Harga
No. URAIAN PEKERJAAN Total (Rp) Keterangan
Q'ty Unit Satuan (Rp)

D Pekerjaan Dinding dan Lantai Subtotal D 168,983,150


Lantai 1 Dasar LT 1 168,983,150
Pasang dinding 304.00 m2 112,500 34,200,000
Plasteran dinding 608.00 m2 45,000 27,360,000
Plasteran kolom 57.60 m2 45,500 2,620,800
Acian Plamir Dinding & Kolom 665.60 m2 16,000 10,649,600
Benangan 1,152.00 m' 10,000 11,520,000
Keramik Lantai 40x40 cm (kasar) 216.75 m2 150,000 32,512,500
Keramik Nosing Tangga 8x25 cm (kasar) 4.00 m2 215,000 860,000
Cat Dinding Interior 528.00 m2 20,500 10,824,000
Cat Dinding Exterior 253.50 m2 29,500 7,478,250
Pintu 120 x 220 3.00 lot 3,960,000 11,880,000
Jendela 340 x 150 2.00 lot 4,335,000 8,670,000
Jendela 255 x 150 2.00 lot 3,252,000 6,504,000
Jendela 255 x 0.45 4.00 lot 976,000 3,904,000
Lantai 2 LT 2 -
Lantai 3 LT 3 -
E Pekerjaan Sanitasi Subtotal E -
F Pekerjaan Atap dan pagar Subtotal F -
G Sarana Utilitas Asrama Subtotal H -
H Pekerjaan M/E Subtotal I -
TOTAL A + B + C + D + E + F + G + H 918,192,210
PEMBULATAN 918,100,000