Ongkos Jumlah
No Uraian Kegiatan Volume Satuan Harga PPN 10% PPh Angkut (Rp) Jumlah Harga
Satuan Satuan (Rp) (Rp.)
1 2 3 4 5 6 7 8 9 10
I. Pembangunan:
TIMBUNAN JALAN SIRTU
A. Bahan
d. Pembelian Sirtu 188.00 Ret 700,000.00 700,000.00 131,600,000.00
Sub. Total I
131,600,000.00
II. B. Alat
a. Pembelian Nilon 10.00 Kpl 25,000.00 2,272.73 27,272.73 272,727.27
b. Pembelian Paku 1.00 Kg 25,000.00 2,272.73 27,272.73 27,272.73
c. Balok 5/5 Kayu Klas III 7.00 Btg 34,000.00 3,090.91 37,090.91 259,636.36
d. Papan Kegiatan 1.00 Bh 100,000.00 9,090.91 109,090.91 109,090.91
e. Grobak 1.00 BH 750,000.00 68,181.82 818,181.82 818,181.82
f. Skop 4.00 BH 150,000.00 13,636.36 163,636.36 654,545.45
g. Cangkul 4.00 BH 150,000.00 13,636.36 163,636.36 654,545.45
Sub. Total II 2,796,000.00
C. UPAH
III.
c. Pekerja 300 HOK 185,000.00 185,000.00 55,500,000.00
Sub. Total III 55,500,000.00
TOTAL (I+II+III) 189,896,000.00
PROGRAM DANA DESA
Desa : DEMINI
TAHUN ANGGARAN 2019
DISTRIK : MOMIWAREN
Harga
No. Nama Bahan Satuan Satuan Ket
( Rp. )
BAHAN
1 Semen Conch Zak 75,000.00 1,500.00
2 Pasir Cor M3 240,000.00
3 Pasir Pasang M3 240,000.00
4 Sirtu Ret 700,000.00
5 Papan Kayu Putih M3 1,700,000.00 34,000.00
6 Paku Campur Kg 24,000.00
7 Tali Nillon Kpl 25,000.00
ALAT
1 Cangkul Buah 150,000.00
2 Sekop Buah 150,000.00
3 Ember Cor Buah 25,000.00
4 Gerobak Dorong (Arco) Buah 750,000.00
5 Papan Proyek Buah 100,000.00
UPAH
1 Pekerja HOK 185,000.00
2 Tukang HOK 200,000.00
3
4
RENCANA ANGGARAN BELANJA (RAB)
Harga Jumlah
No Uraian Kegiatan Volume Satuan
Satuan (Rp.)
1 2 3 4 5 6
I. Pembangunan:
TIMBUNAN JALAN SIRTU
A. Bahan
d. Pembelian Sirtu 187.20 Ret 700,000 131,040,000
Sub. Total I 131,040,000
II. B. Alat
a. Pembelian Nilon 10 Kpl 30,000 300,000
b. Pembelian Paku 1 Kg 25,000 25,000
c. Balok 5/5 Kayu Klas III 7 Btg 50,000 350,000
d. Papan Kegiatan 1 Bh 100,000 100,000
e. Grobak 3 BH 750,000 2,250,000
f. Skop 2 BH 150,000 300,000
g. Cangkul 4 BH 150,000 600,000
Sub. Total II 3,925,000
III. C. UPAH
c. Pekerja 300 HOK 185,000 55,500,000
Sub. Total III 55,500,000
TOTAL (I+II+III) 190,465,000
TAKE OF SHEET
PEMBUKAAN JALAN PRODUKSI P.100 M : L 4M
KEBUTUHAN
JENIS BAHAN / PEKERJA KEBUTU SATUAN SATUAN KET
TOTAL
HAN / m3
A B BxCxDxF
C D E CxE CxDxF
SIRTU / GROSOK 1000 0.30 4.00 4000 1560.00
KEUNTUNGAN Rp : H Rp :
JUMLAH TOTAL Rp :
PEMBULATAN Rp :
Harga Satuan
Harga Satuan Jumlah Harga Satuan
Uraian Satuan Indeks
Bahan (Rp) Upah (Rp)Bahan (Rp) Upah (Rp)
Bahan :
Paving Blok Abu-abu p m2 1.0000 95,000.00 95,000.00
Pasir Pasang m3 0.0800 ### 14,376.00
Tenaga Kerja :
Pekerja oh 0.2000 0.00 0.00
Tukang Batu oh 0.1000 50,000.00 5,000.00
Kepala Tukang oh 0.0100 0.00 0.00
Mandor oh 0.0200 0.00 0.00
### 5,000.00
Harga per satuan pekerjaan dibulatkan
ah Harga Satuan
Total (Rp)
###
###