I. BAHAN
1. Batu Split 2/3 457 M3 386.591 159.950.000 176.672.045
2. Pasir Beton 326 M3 386.591 114.100.000 126.028.636
3. Sirtu 219 m3 331.364 65.700.000 72.568.636
4. Semen Pc 3913 Zak 77.318 273.910.000 302.546.045
5. Papan Terentang 120 Lbr 27.614 3.000.000 3.313.636
6. Kaso 5/7 80 Btg 22.091 1.600.000 1.767.273
7. Paku 72 Kg 27.614 1.800.000 1.988.182
11. Plastik 334 Kg 29.823 9.018.000 9.960.791
65.400.000 72.314.754
III. UPAH
1. Pekerja 1143 HOK 130.000 148.590.000 148.590.000
2. Tukang 219 HOK 150.000 32.850.000 32.850.000
3. Upah Operator Mesin 7 HOK 200.000 1.400.000 1.400.000
Sub Total III) 182.840.000 182.840.000
IV. OPERSIONAL TPK
Honor Ketua 1 Paket 10.500.000 10.000.000
Honor Sekretaris 1 Paket 9.450.000 9.000.000
Honor Anggota 3 Paket 7.875.000 22.500.000
Biaya Pemb. RAB & Desain 1 Paket 1.837.500 1.750.000
Biaya Dokumentasi Kegiatan 1 Paket 1.837.500 1.750.000
Biaya Survey lapangan 1 Paket 3.150.000 3.000.000
Biaya ATK Pembuatan Laporan 1 Paket 2.100.000 2.000.000
- -
Sub Total IV) 50.000.000 -
927.318.000 950.000.000
927.318.000
SUMBER DANA
72.682.000