Anda di halaman 1dari 1

REKAPITULASI PEKERJAAN TAMBAH KURANG

PEKERJAAN : REHABILTASI WORKSHOP EX. SEPEDA MOTOR


KEGIATAN : REHABILTASI WORKSHOP EX. SEPEDA MOTOR
LOKASI : BLK SAMARINDA

Total Nilai Kontrak Pekerjaan Kurang Pekerjaan Tambah Kontrak CCO


NO Job Unit (Item Pekerjaan) Ket
(Rp) Rp Rp

A SISTEM MANAJEMEN KESELAMATAN KONSTRUKSI 24,975,000.00 24,975,000.00


B REHAB EX. WORKSHOP SEPEDA MOTOR
I PENDAHULUAN 12,711,849.36 12,711,849.36
II PEKERJAAN PONDASI 286,428,881.00 67,358,287.78 219,070,593.22
III PEKERJAAN STRUKTUR 1,178,367,679.00 82,770,075.89 43,365,510.90 1,138,963,114.01
IV PEKERJAAN LANTAI 546,212,988.00 41,252,801.76 51,707,495.16 556,667,681.40
V PEKERJAAN DINDING 726,621,811.00 23,085,367.00 102,242,929.64 805,779,373.64
VI PEKERJAAN PINTU DAN JENDELA incl. Penggantung / Pengunci 160,091,200.00 - - 160,091,200.00
VII PEKERJAAN ATAP DAN PLAFOND 451,762,346.00 15,480,616.76 58,196,704.00 494,478,433.24
VIII PEKERJAAN SANITAIR 59,564,400.00 3,350,000.00 4,225,000.00 60,439,400.00
IX PEKERJAAN ELEKTRIKAL 220,541,400.00 - 11,645,200.00 232,186,600.00
X FIRE ALARM 84,336,000.00 - - 84,336,000.00
XI PEKERJAAN LAIN-LAIN 100,764,582.00 8,442,112.00 86,285,498.52 178,607,968.52

JUMLAH TOTAL 3,852,378,136.36 241,739,261.19 357,668,338.21 3,968,307,213.38


JUMLAH PPn 10 % 385,237,813.64 396,830,721.34
JUMLAH SETELAH PPn 4,237,615,950.00 4,365,137,934.72
PEMBULATAN 4,365,100,000.00

Mengetahui Oleh, Mengetahui Oleh, Diperiksa Oleh Dibuat Oleh


PEJABAT PEMBUAT KOMITMEN Pokja Pengadaan Konsultan Supervisi Kontraktor Pelaksana
( PPK ) CV. Afril Perdana Consultan PT. Areabangun Putra Sejati

Kukuh Eko Suhartanto, ST Andre Hermawan, ST Heri Purnomo, ST, MT Ade Irawan, ST
NIP. 19760706 200501 1 001 NIP.19740412 200501 1 001 Team Leader Site Manager

Anda mungkin juga menyukai