Anda di halaman 1dari 4

BULAN 1

PROGRES FISIK (%)


P3A ALALE JAYA RENCANA S/D
BULAN
BULAN LALU S/D BULAN INI BULAN DEPAN
INI
DEPAN

Rencana Komulatif 0.00 28.40 28.40 56.47

Realisasi Komulatif 0.00 29.79 29.79

Deviasi (+/-) 0.00 1.39 1.39

RENCANA S/D
S/D BULAN INI
NO URAIAN VOLUME SAT BOBOT BULAN KE 2
VOL BOBOT VOL BOBOT

PERSIAPAN, PERENCANAAN
DAN PENYELESAIAN 1.00 Ls 4.98 0.12 0.60 0.12 1.00

PELAKSANAAN FISIK
Pek. Pas. Batu 1:5 132.83 M3 59.93 64.69 29.19 90.01 40.61
Pek. Plesteran 1:4, t =1,5 cm 644.00 M2 23.62 282.47 10.36
Pek. Acian 644.00 M2 11.47 252.66 4.50

JUMLAH 29.79 56.47


BULAN 2
PROGRES FISIK (%)
RENCANA S/D
P3A ALALE JAYA BULAN
BULAN LALU S/D BULAN INI BULAN DEPAN
INI
DEPAN

Rencana Komulatif 28.40 28.07 56.47 87.50

Realisasi Komulatif 29.79 28.68 58.47

Deviasi (+/-) 1.39 0.61 2.00

RENCANA S/D
S/D BULAN INI
NO URAIAN VOLUME SAT BOBOT BULAN KE 3
VOL BOBOT VOL BOBOT
PERSIAPAN, PERENCANAAN
DAN PENYELESAIAN 1.00 Ls 4.98 0.12 0.60 1.92 1.92

PELAKSANAAN FISIK
Pek. Pas. Batu 1:5 132.83 M3 59.93 95.11 42.92 75.20 56.61
Pek. Plesteran 1:4, t =1,5 cm 644.00 M2 23.62 283.83 10.41 130.28 20.23
Pek. Acian 644.00 M2 11.47 254.91 4.54 56.29 8.74

JUMLAH 58.47 87.50


BULAN 3
PROGRES FISIK (%)
RENCANA S/D
P3A ALALE JAYA BULAN
BULAN LALU S/D BULAN INI BULAN DEPAN
INI
DEPAN

Rencana Komulatif 56.47 31.03 87.50 100.00

Realisasi Komulatif 58.47 30.07 88.54

Deviasi (+/-) 2.00 -0.96 1.04

RENCANA S/D
S/D BULAN INI
NO URAIAN VOLUME SAT BOBOT BULAN KE 4
VOL BOBOT VOL BOBOT

PERSIAPAN, PERENCANAAN
DAN PENYELESAIAN 1.00 Ls 4.98 0.70 3.49 1.00 4.98

PELAKSANAAN FISIK
Pek. Pas. Batu 1:5 132.83 M3 59.93 132.83 59.93 132.83 59.93
Pek. Plesteran 1:4, t =1,5 cm 644.00 M2 23.62 461.10 16.91 644.00 23.62
Pek. Acian 644.00 M2 11.47 461.10 8.21 644.00 11.47

JUMLAH 100 88.54 100.00


BULAN 3
PROGRES FISIK (%)
RENCANA S/D
P3A ALALE JAYA BULAN
BULAN LALU S/D BULAN INI BULAN DEPAN
INI
DEPAN

Rencana Komulatif 87.50 100.00 100.00

Realisasi Komulatif 88.54 100.00 100.00

Deviasi (+/-) 1.04 0.00 0.00

RENCANA S/D
S/D BULAN INI
NO URAIAN VOLUME SAT BOBOT BULAN KE
VOL BOBOT VOL BOBOT

PERSIAPAN, PERENCANAAN
DAN PENYELESAIAN 1.00 Ls 4.98 1.00 4.98 - -

PELAKSANAAN FISIK
Pek. Pas. Batu 1:5 132.83 M3 59.93 132.83 59.93 - -
Pek. Plesteran 1:4, t =1,5 cm 644.00 M2 23.62 644.00 23.62 - -
Pek. Acian 644.00 M2 11.47 644.00 11.47 - -

JUMLAH 100 100 0.00

Anda mungkin juga menyukai