RENCANA S/D
S/D BULAN INI
NO URAIAN VOLUME SAT BOBOT BULAN KE 2
VOL BOBOT VOL BOBOT
PERSIAPAN, PERENCANAAN
DAN PENYELESAIAN 1.00 Ls 4.98 0.12 0.60 0.12 1.00
PELAKSANAAN FISIK
Pek. Pas. Batu 1:5 132.83 M3 59.93 64.69 29.19 90.01 40.61
Pek. Plesteran 1:4, t =1,5 cm 644.00 M2 23.62 282.47 10.36
Pek. Acian 644.00 M2 11.47 252.66 4.50
RENCANA S/D
S/D BULAN INI
NO URAIAN VOLUME SAT BOBOT BULAN KE 3
VOL BOBOT VOL BOBOT
PERSIAPAN, PERENCANAAN
DAN PENYELESAIAN 1.00 Ls 4.98 0.12 0.60 1.92 1.92
PELAKSANAAN FISIK
Pek. Pas. Batu 1:5 132.83 M3 59.93 95.11 42.92 75.20 56.61
Pek. Plesteran 1:4, t =1,5 cm 644.00 M2 23.62 283.83 10.41 130.28 20.23
Pek. Acian 644.00 M2 11.47 254.91 4.54 56.29 8.74
RENCANA S/D
S/D BULAN INI
NO URAIAN VOLUME SAT BOBOT BULAN KE 4
VOL BOBOT VOL BOBOT
PERSIAPAN, PERENCANAAN
DAN PENYELESAIAN 1.00 Ls 4.98 0.70 3.49 1.00 4.98
PELAKSANAAN FISIK
Pek. Pas. Batu 1:5 132.83 M3 59.93 132.83 59.93 132.83 59.93
Pek. Plesteran 1:4, t =1,5 cm 644.00 M2 23.62 461.10 16.91 644.00 23.62
Pek. Acian 644.00 M2 11.47 461.10 8.21 644.00 11.47
RENCANA S/D
S/D BULAN INI
NO URAIAN VOLUME SAT BOBOT BULAN KE
VOL BOBOT VOL BOBOT
PERSIAPAN, PERENCANAAN
DAN PENYELESAIAN 1.00 Ls 4.98 1.00 4.98 - -
PELAKSANAAN FISIK
Pek. Pas. Batu 1:5 132.83 M3 59.93 132.83 59.93 - -
Pek. Plesteran 1:4, t =1,5 cm 644.00 M2 23.62 644.00 23.62 - -
Pek. Acian 644.00 M2 11.47 644.00 11.47 - -