ANGGARAN 2022
DAFTAR ISI
i
PEKERJAAN STRUKTUR
STRUKTUR BETON
1. Pekerjaan Beton K 100 - f'c 7,4 Mpa LANTAI KERJA / m³ ............................................ 10
2. Pekerjaan Beton K 100 - f'c 7,4 Mpa LANTAI KERJA / m³ ............................................. 10
3. Pekerjaan Beton K 100 - f'c 7,4 Mpa / m³ ..................................................................... 10
4. Pekerjaan Beton K 125 - f'c 9,8 Mpa / m³ .................................................................... 11
5. Pekerjaan Beton K 150 - f'c 12,2 Mpa / m³ ................................................................... 11
6. Pekerjaan Beton K 175 - f'c 14,5 Mpa / m³ ................................................................... 11
7. Pekerjaan Beton K 200 - f'c 16,9 Mpa / m³ ................................................................... 11
8. Pekerjaan Beton K 225 - f'c 19,3 Mpa / m³ ................................................................... 11
9. Pekerjaan Beton K 250 - f'c 21,7 Mpa / m³ ................................................................... 12
10. Pekerjaan Beton K 275 - f'c 24 Mpa / m³ ...................................................................... 12
11. Pekerjaan Beton K 300 - f'c 26,4 Mpa / m³ ................................................................... 12
12. Pekerjaan Beton K 325 - f'c 28,8 Mpa / m³ ................................................................... 12
13. Pekerjaan Beton K 350 - f'c 31,2 Mpa / m³ ................................................................... 12
14. Pekerjaan Beton Kedap air dengan STROROX-100 / m³ ............................................... 13
15. Pemasangan 1 m¹ PVC waterstop lebar 150 mm / m¹ ................................................... 13
16. Pemasangan 1 m¹ PVC waterstop lebar 200 mm / m¹ ................................................... 13
17. Pemasangan 1 m¹ PVC waterstop lebar 250 mm / m¹ ................................................... 13
18. Pekerjaan Beton K 100 - f'c 7,4 Mpa menggunakan molen / m³ ................................... 13
19. Pekerjaan Beton K 125 - f'c 9,8 Mpa menggunakan molen / m³ ................................... 14
20. Pekerjaan Beton K 150 - f'c 12,2 Mpa menggunakan molen / m³ .................................. 14
21. Pekerjaan Beton K 175 - f'c 14,5 Mpa menggunakan molen / m³ .................................. 14
22. Pekerjaan Beton K 200 - f'c 16,9 Mpa menggunakan molen / m³ .................................. 14
23. Pekerjaan Beton K 225 - f'c 19,3 Mpa menggunakan molen / m³ .................................. 14
24. Pekerjaan Beton K 250 - f'c 21,7 Mpa menggunakan molen / m³ .................................. 15
25. Pekerjaan Beton K 275 - f'c 24 Mpa menggunakan molen / m³ ..................................... 15
26. Pekerjaan Beton K 300 - f'c 26,4 Mpa menggunakan molen / m³ .................................. 15
27. Pekerjaan Beton K 325 - f'c 28,8 Mpa menggunakan molen / m³ .................................. 15
28. Pekerjaan Beton K 350 - f'c 31,2 Mpa menggunakan molen / m³ .................................. 15
29. Pemadatan beton menggunakan Vibrator / m³ ............................................................. 16
30. Pembesian dengan besi polos / KG ............................................................................... 16
31. Pembesian dengan besi Ulir / kg................................................................................... 16
32. Pembesian dengan besi Jaring Kawat di las (Wire mesh) / kg ....................................... 16
33. Pekerjaan Bekisting Pondasi / m ² ................................................................................ 16
34. Pekerjaan Bekisting Sloof / m ² ..................................................................................... 17
35. Pekerjaan Bekisting Kolom / m ²................................................................................... 17
36. Pekerjaan Bekisting Balok / m ² ................................................................................... 17
37. Pekerjaan Bekisting Lantai / m ² .................................................................................. 17
38. Pekerjaan Bekisting Dinding / m ² ................................................................................ 18
39. Pekerjaan Bekisting Tangga / m ² ................................................................................. 18
40. Pekerjaan Bekisting Lantai pakai floor deck / m ² ......................................................... 18
41. Pekerjaan Pondasi Beton Bertulang (150 kg besi + Bekisting) / m ³ .............................. 18
42. Pekerjaan Sloof Beton Bertulang (200 kg besi + Bekisting) / m ³ ................................... 19
43. Pekerjaan Balok Beton Bertulang (200 kg besi + Bekisting) / m ³ ................................. 19
44. Pekerjaan Kolom Beton Bertulang (150 kg besi + Bekisting) / m ³ ................................. 19
45. Pekerjaan Kolom Beton Bertulang (300 kg besi + Bekisting) / m ³................................. 20
46. Pekerjaan Pelat Beton Bertulang (150 kg besi + Bekisting) / m ³ ................................... 20
47. Pekerjaan Dinding Beton Bertulang ( 150 kg besi + Bekisting) / m ³ ............................. 20
48. Pekerjaan Dinding Beton Bertulang ( 200 kg besi + Bekisting) / m ³ ............................. 21
49. Pekerjaan Kolom Praktis Beton Bertulang ( 11 x 11 cm) / m' ........................................ 21
50. Pekerjaan Balok Ring Praktis Beton Bertulang ( 10 x 15 cm) / m' ................................. 21
51. Grouting semen - screening / kg ................................................................................... 21
52. Pekerjaan Beton K 500 - f'c 41,5 Mpa Ready Mixed / m ³" ............................................ 22
53. Rabat Beton tebal 8 cm beton f’c 14,5 MPa, slump (120 ± 20) mm" ............................... 22
ii
STRUKTUR BESI & BAJA
1. Pemasangan Baja Profil / kg ....................................................................................... 22
2. Pemasangan Rangka Kuda-kuda Baja IWF / kg.......................................................... 22
3. Pengerjaan Pekerjaan Perakitan / kg .......................................................................... 22
4. Pekerjaan Pengelasan 10 CM dengan Las Listrik ........................................................ 23
5. Pemasangan Rangka Baja Kanal C / kg ...................................................................... 23
Pekerjaan Pemasangan Pelat - bordes ........................................................................ 23
6. Pekerjaan Brasing, trekstang lengkap dg mur ............................................................ 23
7. Pekerjaan Dinding Wiremesh rangka Hollow / m ² ...................................................... 23
8. Pekerjaan Dinding Zincallum rangka baja C / m ² ...................................................... 23
9. Pekerjaan Fabrikasi dan Elektroda Besi siku / kg ...................................................... 24
10. Pemasangan Rangka Atap Pelana Baja Ringan (Canai Dingin) profil C75 / m ² ........... 24
11. Pemasangan Rangka Atap Jurai Baja Ringan (Canai Dingin) profil C75 / m ² ............. 24
PEKERJAAN BESI DAN ALUMUNIUM
1. Pasang pintu besi plat baja tebal 2 mm rangkap, rangka baja siku / m ² ................... 24
2. Pasang rangka jendela besi Scuare Tube (25x5) cm / m ² ........................................... 24
3. Pasang pintu lipat (Folding Door) / m ² ....................................................................... 25
4. Pasang rolling door /m ² ............................................................................................. 25
5. Pasang kusen pintu aluminium / m ² ......................................................................... 25
6. Pasang Kusen P1A / unit ............................................................................................ 25
7. Pasang Kusen P1B / unit ........................................................................................... 26
8. Pasang Kusen P1 C / unit .......................................................................................... 26
9. Pasang Kusen P2 A / unit ........................................................................................... 26
10. Pasang Kusen PJ 1 / unit ........................................................................................... 26
11. Pasang Kusen J1 A / unit ........................................................................................... 27
12. Pasang Kusen J1 B / unit........................................................................................... 27
13. Pasang Kusen J1 C / unit........................................................................................... 27
14. Pasang Kusen J2 A / unit ........................................................................................... 27
15. Pasang Kusen J2 B / unit........................................................................................... 28
16. Pasang Kusen J3 A / unit ........................................................................................... 28
17. Pasang Kusen J3 B / unit........................................................................................... 28
18. Pasang Kusen J4 A / unit ........................................................................................... 28
19. Pasang Kusen J5 A / unit ........................................................................................... 29
20. Pasang kusen pintu alumunium P1 (GS) / unit .......................................................... 29
21. Pasang kusen pintu alumunium P2 (GS) / unit .......................................................... 29
Pasang kusen pintu alumunium P3 (GS) / unit .......................................................... 26
22. Pasang kusen pintu alumunium PJ1 (GS) / unit ........................................................ 30
23. Pasang kusen pintu alumunium PJ2 (GS) / unit ........................................................ 30
24. Pasang kusen jendela alumunium J1 (GS) / unit ....................................................... 30
25. Pasang kusen jendela alumunium J2 (GS) / unit ....................................................... 30
26. Pasang kusen jendela alumunium J3 (GS) / unit ....................................................... 31
27. Bouvenlight 1 Ukuran 50 x 85 / unit.......................................................................... 31
28. Bouvenlight 2 Ukuran 50 x 120 / unit ........................................................................ 31
29. Bouvenlight 3 Ukuran 20 x 200 / unit ........................................................................ 31
30. Memasang pintu/jendela/BV kaca, rangka allumunium / m ² ................................... 32
31. Pasang jendela nako dan teralis / m ²......................................................................... 32
32. Pasang talang datar, seng BJLS 28 (0,28 mm) lebar 90 cm / m¹................................. 32
33. Pemasangan 1 m talang ½ lingkaran D-15 cm, seng pelat bjls 30 lebar 45 cm" .......... 32
34. Pasang baut Ø 19 / bh ............................................................................................... 32
35. Pasang baut Ø 16 / bh ............................................................................................... 33
36. Pasang baut Ø 12 / bh ............................................................................................... 33
37. Pasang Angkur - baut Ø 16-19-22 mm / bh ............................................................... 33
38. Railing Tangga Besi Hollow / m ² ................................................................................ 33
39. Pagar Besi tempa / m ² ............................................................................................... 33
40. Dudukan tangki air / unit .......................................................................................... 34
iii
PEKERJAAN DINDING
1. Pasangan dinding bata merah 1 PC : 2 PP tebal 1 bata / m ² ...................................... 34
2. Pasangan dinding bata merah 1 PC : 3 PP tebal 1 bata / m ² ...................................... 34
3. Pasangan dinding bata merah 1 PC : 4 PP tebal 1 bata / m ² ...................................... 34
4. Pasangan dinding bata merah 1 PC : 5 PP tebal 1 bata / m ² ...................................... 34
5. Pasangan dinding bata merah 1 PC : 6 PP tebal 1 bata / m ² ...................................... 35
6. Pasangan dinding bata merah 1 PC : 2 PP tebal 1/2 bata / m ² .................................. 35
7. Pasangan dinding bata merah 1 PC : 3 PP tebal 1/2 bata / m ² .................................. 35
8. Pasangan dinding bata merah 1 PC : 4 PP tebal 1/2 bata / m ² .................................. 35
9. Pasangan dinding bata merah 1 PC : 5 PP tebal 1/2 bata / m ² .................................. 35
10. Pasangan dinding bata merah 1 PC : 6 PP tebal 1/2 bata / m ² .................................. 36
11. Pasangan dinding bata merah 1 PC : 8 PP tebal 1/2 bata / m ² .................................. 36
12. Pemasangan Bata Terawang - Rooster ( 24 x 7 x 1,5 ) spesi 1 PC : 3 PP / m ² ............. 36
13. Pemasangan Bata Terawang - Rooster ( 24 x 7 x1,5 ) spesi 1 PC : 4 PP / m ² .............. 36
14. Pemasangan Bata Berongga Exposed ( 24 x 7 x 1,5 ) spesi 1 PC : 3 PP / m ² .............. 36
15. Pemasangan Rollag bata / m ² .................................................................................... 37
16. Pemasangan Glass Block 20 20 x 11 cm spesi 1PC : 4 PP / m ² .................................. 37
17. Pemasangan Roster Beton 20 x 20 x 7 cm spesi 1PC : 4 PP / m ² ............................... 37
18. Pemasangan Roster Kayu 40 x 20 x 7 cm spesi 1PC : 4 PP / m ² ................................ 37
19. Pemasangan Bata Ringan tebal 75 mm dengan mortar siap pakai / m ² ..................... 37
20. Pemasangan Bata Ringan tebal 100 mm dengan prime mortar / m ² .......................... 38
21. Pemasangan Bata Ringan tebal 150 mm dengan prime mortar / m ² .......................... 38
22. Pekerjaan Plesteran dengan prime mortar / m ² ......................................................... 38
23. Pekerjaan Acian dengan prime mortar ........................................................................ 38
24. Plesteran Halus 1 PC : 1 PP tebal 1,5 cm / m ² ........................................................... 38
25. Plesteran Halus 1 PC : 2 PP tebal 1,5 cm / m ² ........................................................... 39
26. Plesteran Halus 1 PC : 3 PP tebal 1,5 cm / m ² ........................................................... 39
27. Plesteran Halus 1 PC : 4 PP tebal 1,5 cm / m ² ........................................................... 39
28. Plesteran Halus 1 PC : 5 PP tebal 1,5 cm / m ² ........................................................... 39
29. Plesteran Halus 1 PC : 6 PP tebal 1,5 cm / m ² ........................................................... 39
30. Plesteran Halus 1 PC : 7 PP tebal 1,5 cm / m ² ........................................................... 40
31. Plesteran Halus 1 PC : 8 PP tebal 1,5 cm / m ² ........................................................... 40
32. Plesteran 1 PC : 3 PP skoning lebar 10 cm / m¹ .......................................................... 40
33. Plesteran 1 Pc : 1 Ps tebal 20 mm / m ² ...................................................................... 40
34. Plesteran 1 Pc : 3 Ps tebal 20 mm / m ² ...................................................................... 40
35. Plesteran 1 Pc : 4 Ps tebal 20 mm / m ² ...................................................................... 41
36. Plesteran 1 Pc : 5 Ps tebal 20 mm / m ² ...................................................................... 41
37. Plesteran 1 Pc : 6 Ps tebal 20 mm / m ² ...................................................................... 41
38. Plesteran Berapen 1 Pc : 5 Ps tebal 15 mm ................................................................. 41
39. Plesteran Skoning (benangan/ tali air) 1 Pc : 2 Ps lebar 10 cm / m¹ ........................... 41
40. Plesteran Ciprat 1 Pc : 2 Ps / m ² ................................................................................ 42
41. Plesteran Finishing Siar 1 Pc : 2 Ps untuk pasangan batu kali / m ² .......................... 42
42. Acian / m ² ................................................................................................................. 42
v
35. Pintu Kamar Mandi PVC lengkap kusen PVC-kunci / unit ......................................... 56
36. Pasang kawat harmonika / m² ................................................................................... 57
37. Pasang kawat nyamuk / m² ....................................................................................... 57
38. Pasang kawat kasa / m² ............................................................................................ 57
PEKERJAAN SANITASI
1. Memasang 1 buah kloset duduk/monoblok (sederhana) / bh ..................................... 82
2. Memasang 1 buah kloset duduk/monoblok setara INA (sedang) / bh ......................... 82
3. Memasang 1 buah kloset duduk/monoblok (tidak sederhana) / bh ............................ 82
4. Memasang 1 buah kloset jongkok sederhana / bh ...................................................... 82
5. Memasang 1 buah kloset jongkok sedang / bh ........................................................... 83
6. Memasang 1 buah kloset jongkok tdk sederhana / bh ................................................ 83
7. Memasang 1 buah urinoir / bh ................................................................................... 83
8. Memasang 1 buah penyekat urinoir / bh.................................................................... 83
9. Memasang 1 buah wastafel sederhana / bh................................................................ 84
10. Memasang 1 buah wastafel sedang / bh ..................................................................... 84
11. Memasang 1 buah wastafel setara Toto / bh .............................................................. 84
12. Memasang 1 buah bak mandi fibreglass 60x60 cm / bh ............................................. 84
13. Memasang 1 buah bak mandi batu bata volume 0,3 m³ / bh...................................... 85
14. Memasang 1 buah bak cuci piring stainless steel / bh ............................................... 85
15. Memasang pipa galvanis dia 0,5 / m¹ ......................................................................... 85
16. Memasang pipa galvanis dia ¾" / m¹ .......................................................................... 85
17. Memasang pipa galvanis dia 1" / m¹ ........................................................................... 85
18. Memasang pipa galvanis dia 1 1/4 " / m¹ ................................................................... 86
19. Memasang pipa galvanis dia 1 ½" / m¹ ....................................................................... 86
20. Memasang pipa galvanis dia 2" / m¹ ........................................................................... 86
21. Memasang pipa galvanis dia 2 1/2 " / m¹ ................................................................... 86
22. Memasang pipa galvanis dia 3" / m¹ ........................................................................... 86
23. Memasang pipa galvanis dia 4" / m¹ ........................................................................... 87
viii
24. Memasang pipa PVC tipe AW dia 1/2" ........................................................................ 87
25. Memasang pipa PVC tipe AW dia 3/4" / m¹ ................................................................ 87
26. Memasang pipa PVC tipe AW dia 1" / m¹ .................................................................... 87
27. Memasang pipa PVC tipe AW dia 1 ¼" / m¹ ................................................................ 87
28. Memasang pipa PVC tipe D dia 1 ¼" / m¹ ................................................................... 88
29. Memasang pipa PVC tipe AW dia 1 1/2 "/ m¹ ............................................................. 88
30. Memasang pipa PVC tipe D dia 1 1/2 " / m¹ ............................................................... 88
31. Memasang pipa PVC tipe AW dia 2" / m¹ .................................................................... 88
32. Memasang pipa PVC tipe D dia 2" / m¹ ....................................................................... 88
33. Memasang pipa PVC tipe AW dia 2 ½" / m¹ ................................................................ 89
34. Memasang pipa PVC tipe D dia 2 1/2 " / m¹ ............................................................... 89
35. Memasang pipa PVC tipe AW dia 3" / m¹ .................................................................... 89
36. Memasang pipa PVC tipe D dia 3" / m¹ ....................................................................... 89
37. Memasang pipa PVC tipe AW dia 4" / m¹ .................................................................... 89
38. Memasang pipa PVC tipe D dia 4" / m¹ ....................................................................... 90
39. Memasang pipa PVC tipe AW dia 6" / m¹ .................................................................... 90
40. Memasang pipa PVC tipe D dia 6" / m¹ ....................................................................... 90
41. Memasang pipa PVC tipe AW dia 8" / m¹ .................................................................... 90
42. Memasang 1 buah Stop Valve 1,5 " / bh ..................................................................... 90
43. Memasang 1 buah kran dia 3/4" atau 1/2" sederhana / bh ....................................... 91
44. Memasang 1 buah kran dia 3/4" atau 1/2" stainless / bh.......................................... 91
45. Memasang 1 buah kran bebek dia 3/4" atau 1/2" sederhana / bh ............................. 91
46. Memasang 1 buah kran bebek dia 3/4" atau 1/2" stainless / bh ............................... 91
47. Memasang 1 buah hand shower setara TOTO / bh ..................................................... 91
48. Memasang Shower Spray Setara TOTO ....................................................................... 92
49. Memasang 1 buah tempat sabun / bh ........................................................................ 92
50. Memasang 1 buah gantungan baju / bh ..................................................................... 92
51. Memasang 1 floor drain sederhana / bh ..................................................................... 92
52. Memasang 1 floor drain stainless /bh ......................................................................... 92
53. Memasang Roof drain / bh ......................................................................................... 93
54. Memasang 1 clean out dia. 100 mm / bh ................................................................... 93
55. Memasang 1 clean out dia. 50 mm / bh ..................................................................... 93
56. Membuat 1 unit sumur air tanah bor manual dalam 12 m' + pompa air listrik / bh... 93
57. Membuat 1 unit tanki septik sederhana kapasitas Ø 1,2 m dalam 1,2 m / bh............ 94
58. Membuat 1 unit tanki septik kapasitas 1,7x0,85 m dalam 1,3 m (vol. 1,88 m³ u/ 5
pemakai) / bh ............................................................................................................. 94
59. Membuat tanki septik kapasitas tiap 1 m³ ................................................................. 94
60. Membuat 1 unit resapan Ø 0,8 m (digali 1 m) dalam 1 m (digali 1,9 m) kap. 0,5 m³ ... 95
61. Memasang 1 unit septictank pabrikasi kap. 1 m³ ....................................................... 95
62. Memasang 1 unit septictank pabrikasi kap. 2 m³ ....................................................... 95
63. Memasang 1 unit septictank pabrikasi kap. 3 m³ ....................................................... 95
64. Memasang 1 unit septictank pabrikasi kap. 6 m³ ....................................................... 95
65. Memasang 1 unit septictank pabrikasi kap. 8 m³ ....................................................... 96
66. Membuat tanki septik kapasitas tiap 3 m³ ................................................................. 96
Membuat tanki septik kapasitas tiap 6 m³
PEKERJAAN PENGECATAN
1. Mengikis/mengerok permukaan cat lama / m ² .......................................................... 96
2. Pengecatan dengan cat KW 1 bidang kayu baru / m ² ................................................ 96
3. Pengecatan dengan cat KW 2 bidang kayu baru / m ² ................................................ 97
4. Pengecatan dengan cat KW 1 bidang kayu lama ......................................................... 97
5. Pelaburan bidang kayu dgn teak oil / m ² ................................................................... 97
6. Pelaburan bidang kayu dgn politur / m ² .................................................................... 97
7. Pengecatan bidang kayu dengan melamik / m ² ......................................................... 98
8. Pelaburan bidang kayu dgn residu dan ter / m ² ........................................................ 98
9. Pelaburan bidang kayu dgn vernis / m ² ..................................................................... 98
ix
10. Pengecatan tembok baru dg cat KW 1 / m ² ................................................................ 98
11. Pengecatan tembok baru dg cat KW 2 / m ² ................................................................ 98
12. Pengecatan tembok baru dg wall sealer - cat penutup KW 1 / m ² .............................. 99
13. Pengecatan tembok baru dg cat Weathershield / m ² .................................................. 99
14. Pengecatan bidang tembok lama 1 m² dg cat KW 1 / m ² ............................................ 99
15. Pengecatan bidang tembok lama 1 m² dg cat KW 2 / m ² ............................................ 99
16. Memasang wallpaper / m ² ......................................................................................... 99
17. Pengecatan permukaan baja 1 m² dgn meni besi / m ² ..............................................100
18. Pengecatan permukaan kayu dgn meni / m ² ............................................................100
19. Pengecatan permukaan baja tiap 1 m² dengan zinchromate / m ² .............................100
20. Pengecatan permukaan baja tiap 1 m² dengan Cat KW 1 / m ² ..................................100
21. Pengecatan permukaan baja tiap 1 m² dengan Cat KW 2/ m ² ...................................101
22. Pengecatan permukaan baja 1 m² dgn meni besi & perancah / m ² ...........................101
23. Pekerjaan cat duko sistem semprot / m ² ..................................................................101
24. Pengecatan waterproofing (coating) / m ² ...................................................................101
x
34. Pasang 1 buah saklar ganda ......................................................................................109
35. Pasang 1 buah stop kontak .......................................................................................109
36. Pasang 1 buah Exhaust Fan ......................................................................................109
37. Pasang 1 buah out let TV ..........................................................................................110
38. Pemasangan AC 2 1/2 PK Split ..................................................................................110
39. Pemasangan AC 1 PK Split tiap unit ..........................................................................110
40. Pemasangan AC Cassete 4 PK tiap unit .....................................................................110
41. Pemasangan AC Standing 10 PK tiap unit .................................................................110
PEKERJAAN BONGKARAN
1. Bongkar beton bertulang / m³ ..................................................................................118
2. Bongkar dinding tembok bata merah / m³ ................................................................119
3. Bongkar dinding ½ bata / m ² ...................................................................................119
4. Bongkar pelat beton bertulang / m ²..........................................................................119
5. Bongkar batu kali / m ² .............................................................................................119
6. Bongkar lantai / m ² ..................................................................................................119
7. Bongkar paving block / m ² .......................................................................................119
8. Bongkar plesteran / m ² ............................................................................................120
xi
9. Bongkar atap genteng / m ² .......................................................................................120
10. Bongkar karpusan atap genteng / m¹ ........................................................................120
11. Bongkar atap seng/asbes / m ² .................................................................................120
12. Bongkar kaso dan reng kayu (kayu akan dipakai lagi) / m ² ......................................120
13. Bongkar kaso dan reng kayu (kayu tidak akan dipakai lagi) / m ² .............................120
14. Bongkar balok kuda-kuda & loteng (kayu akan dipakai lagi) / m³ ............................121
15. Bongkar balok kuda-kuda & loteng (kayu tidak akan dipakai lagi) / m³ ...................121
16. Bongkar rangka plafon / m ² .....................................................................................121
17. Bongkar penutup plafon / m ² ...................................................................................121
PEKERJAAN DRAINASE
1. Memasang pipa beton, dia 15-20 cm .........................................................................121
2. Memasang pipa beton, dia 30 cm / m¹.......................................................................122
3. Memasang pipa beton, dia 40 cm / m¹.......................................................................122
4. Memasang pipa beton, dia 50 cm / m¹.......................................................................122
5. Memasang pipa beton, dia 60 cm / m¹.......................................................................122
6. Memasang pipa beton, dia 80 cm / m¹.......................................................................123
7. Memasang pipa beton, dia 100 cm / m¹.....................................................................123
8. Memasang 1 buah bak kontrol pas.batu bata 30 x 30 cm tinggi 35 cm / bh .............123
9. Memasang 1 buah bak kontrol pas.batu bata 45 x 45 cm tinggi 50 cm bh ...............123
10. Memasang 1 buah bak kontrol pas.batu bata 60 x 60 cm tinggi 65 cm / bh .............124
11. Membuat saluran air buis beton ½ Ø 20 cm dinding bata dalam 15-25 cm / m¹ .......124
12. Membuat saluran air buis beton ½ Ø 30 cm dinding bata dalam 30-45 cm / m¹ .......124
13. Membuat saluran air dari batu kali lebar bawah 30 cm tinggi 60 cm / m¹ ................124
14. Membuat saluran air dari batu kali lebar bawah 60 cm tinggi 80 cm / m¹ ................125
15. Membuat saluran air dari batu kali lebar bawah 80 cm tinggi 100 cm / m¹ ..............125
16. Membuat saluran air dari batu kali lebar bawah 100 cm tinggi 120 cm / m¹ ............125
TAMAN
1. Penanaman Rumput Gajah Manila /m ² ....................................................................136
2. Pasang grassblock tebal 10 cm / m ² .........................................................................136
3. Gebalan rumput / m ² ...............................................................................................136
4. Geotektil untuk Perkuatan Tanah / m ².....................................................................137
PSDA
1. Kistdam pasir/tanah dibungkus karung plastik bagor 45 / m' ..................................137
2. Dokumentasi / ls .......................................................................................................137
3. Mutual Cek dan Survey / ls .......................................................................................137
4. Galian tanah biasa sedalam ≤ 1 m / m³ .....................................................................137
5. Galian tanah biasa sedalam ≤ 2 m / m³ .....................................................................138
6. Galian tanah berbatu sedalam ≤ 1 m / m³ .................................................................138
7. Galian tanah berbatu sedalam > 1 m s.d. 2 m / m³ ...................................................138
8. Galian tanah cadas atau tanah keras sedalam ≤ 1 m / m³ .........................................138
9. Galian tanah cadas atau tanah keras sedalam > 1 m s.d. 2 m / m³ ...........................138
10. Galian lumpur sedalam ≤ 1 m / m³............................................................................138
11. Timbunan tanah atau urugan tanah kembali / m³ ....................................................139
12. Pemadatan tanah / m³ ..............................................................................................139
13. Pembersihan dan Striping/Kosrekan / m2 ................................................................139
14. Galian untuk Selokan Drainase dan Saluran Air Pakai Buruh / m3 ..........................139
15. Galian untuk Selokan Drainase dan Saluran Air / m3 ..............................................139
16. Galian Biasa / m3 .....................................................................................................139
17. Galian Struktur dengan kedalaman 0 - 2 meter / m3 ................................................140
18. Galian Perkerasan berbutir / m3 ...............................................................................140
19. Galian Perkerasan Beton / m3 ..................................................................................140
20. Galian Batu / m3 ......................................................................................................140
21. Galian Struktur dengan kedalaman 2 - 4 meter / m3 ................................................140
22. Box Culver 1000 x 1000 HD / bh ..............................................................................141
23. Saluran U-Ditch 1000x1000 +Cover / bh ..................................................................141
24. Saluran U-Ditch 600x600 / bh ..................................................................................141
xiii
25. Saluran U-Ditch 400x400 +Cover / bh ......................................................................141
26. Beton K250 (fc’ 20) untuk struktur drainase beton minor / bh ..................................141
27. Baja Tulangan untuk struktur drainase beton minor / bh.........................................142
28. Saluran berbentuk U Tipe DS 2 / bh .........................................................................142
29. Timbunan Biasa Dari Sumber Galian / bh ................................................................142
30. Timbunan Pilihan dari Galian / bh ............................................................................142
31. Timbunan Pasir sebagai Lantai Kerja / m3 ................................................................142
32. Pasangan Batu Dengan Mortar / m3 .........................................................................143
33. Beton Mutu, f'c = 9,8 Mpa ( K125), slump (12 ±2) cm, w/c= 0,78
( Menggunakan Molen > 2 m³ ) / m3 ..........................................................................143
34. Beton struktur, fc’20 MPa (K250) / m3 ......................................................................143
35. Pasangan pipa suling-suling / m ...............................................................................143
36. Pipa Penyalur PVC / m ..............................................................................................143
37. Mortar tipe N ( untuk mutu PP setara dengan campuran 1 PC : 4 PP ) / m ................144
38. Plesteran tebal 1,5 cm, dengan mortar jenis PC-PP tipe S
(untuk mutu PP tertentu setara dengan campuran 1 PC : 3 PP ) / m2 .......................144
39. Siaran dengan mortar jenis PC-PP tipe M ( untuk mutu PP tertentu setara dengan
campuran 1 PC : 2 PP ) / m2 .....................................................................................144
40. Pemasangan Bronjong Kawat (Pabrikasi) / m3 ..........................................................144
41. Pemasangan Pintu Penguras / unit ...........................................................................144
42. Pemasangan Pintu Air / unit .....................................................................................145
43. Bekisting untuk permukaan beton biasa dengan papan ukuran 3/20 cm
(tanpa perancah ) / unit ............................................................................................145
44. Perbaikan Pintu Air ( 2 Drat reel pintu ) / unit ..........................................................145
xiv
HSPK UNTUK IPLT
1. Pekerjaan Tiang Pancang Mini Pile 250x250 mm pjg = 6 m1 ......................................151
2. Pek. 100 kg Pekerjaan Pelat baja stainless .................................................................151
3. Pek. 1 unit gutter Sedimentasi ...................................................................................151
4. Pek. 1 unit grill Sedimentasi ......................................................................................152
xv
47. Pagar Belakang Gedung Negara .................................................................................. 63
48. Rumah Negara Tipe A ................................................................................................. 64
49. Rumah Negara Tipe B ................................................................................................. 67
50. Rumah Negara Tipe C ................................................................................................. 70
51. Pagar Depan Rumah Negara ....................................................................................... 72
52. Pagar Samping Rumah Negara .................................................................................... 73
53. Pagar Belakang Rumah Negara ................................................................................... 74
54. Pembangunan Jalan Rigid Pavement K.350 T=25Cm .................................................. 75
55. Pembangunan TPt Jalan ............................................................................................. 76
56. Pembangunan TPt Frame ............................................................................................ 77
57. Peningkatan Trotoar Diatas Bahu Jalan ..................................................................... 78
58. Pelebaran Jalan .......................................................................................................... 79
59. Pembangunan Jembatan ........................................................................................... 80
60. Peningkatan Jalan Rigid Pavement K.350 T=25 Cm .................................................... 81
61. Peningkatan Jalan Rigid Pavement K.500 T=25 Cm .................................................... 82
62. Peningkatan Jalan Rigid Pavement K.350 T=20 Cm .................................................... 83
63. Rehabilitasi Jalan Laston AC-WC T= 4 CM.................................................................. 84
64. Stabilisasi Dan Penguatan Tebing Polimer .................................................................. 85
65. Rehabilitasi Jembatan ................................................................................................ 86
66. Pengadaan Dan Pemasangan Papan Pengenal Ruas Jalan .......................................... 87
67. Rehabilitasi Bendung .................................................................................................. 88
68. Rehabilitasi Jaringan Irigasi ....................................................................................... 89
69. Pembangunan Saluran Drainase................................................................................. 89
70. Rehabilitasi Saluran Drainase..................................................................................... 90
71. Pemeliharaan Saluran Drainase .................................................................................. 90
72. Pembangunan Embung ............................................................................................... 91
73. Pembangunan Kolam Retensi...................................................................................... 92
74. Rehabilitasu Station Pompa Banjir ............................................................................. 92
75. Normalisasi Sungai ..................................................................................................... 92
76. Pembangunan Perkuatan Tebing ................................................................................ 93
77. Rehabilitasi Bantaran Tanggul Sungai ........................................................................ 93
78. Rehabilitasi Saluran Drainase Gorong-Gorong ............................................................ 94
79. Pemeliharaan PJU....................................................................................................... 94
80. Peningkatan PJU Led 100-140 Watt............................................................................ 94
81. Penggantian BOX APP ................................................................................................. 95
82. Penggantian Komponen BOX APP ............................................................................... 95
83. Pemasangan Jaringan Kabel Bawah Tanah PJU ......................................................... 95
84. Pembangunan Tiang Bulat 7 M, Armature PJU Sodium 150 Watt,
Jaringan Kabel Udara, BOX APP Dan BPUJL .............................................................. 96
85. Pembangunan Tiang Bulat 7 M, Armature Led 60-90 WATT,
Jaringan Kabel Udara, BOX APP Dan BPUJL .............................................................. 97
86. Pembangunan Tiang Bulat 7 M, PJU Tenaga Surya All In One 40 Watt....................... 98
87. Pembangunan Tiang Bulat 3,5 M, Armature Led 12 WATT Jaringan
Kabel Udara, BOX APP Dan BPUJL............................................................................. 99
88. Pembangunan Tiang Oktagonal 9 M, Armature PJU Sodium 250 Watt Tipe Cobra,
Jaringan Kabel Udara, BOX APP Dan BPUJL .............................................................100
89. Pembangunan Tiang Oktagonal 9 M, Armature Led 100-140 Watt, Jaringan
Kabel Udara, BOX APP Dan BPUJL ............................................................................101
90. Pembangunan Tiang 11 M Stang Ganda, Armature PJU Sodium 250 Watt
Tipe Keong, Jaringan Kabel Bawah Tanah, BOX APP Dan BPUJL ..............................102
91. Pembangunan Tiang Oktagonal 9 M, Armature Led Smart 120 Watt, Jaringan Kabel
Udara, BOX APP Dan BPUJL .....................................................................................103
92. Sumur Resapan .........................................................................................................104
93. Instalasi Pemanen Air Hujan (IPAH) AM .....................................................................105
94. Instalasi Pemanen Air Hujan (IPAH) AB .....................................................................106
95. Pojok Edukasi Bersih Sampah (POKASIH)..................................................................107
96. TPS3R ........................................................................................................................108
97. Broncaptering ............................................................................................................111
xvi
98. Jaringan Kosntruksi Perpipaan Air Bersih .................................................................112
99. Sambungan Rumah Perdesaan ..................................................................................113
100. Sambungan Rumah Perkotaan ..................................................................................114
101. Sambungan Rumah Hibah Air Minum Perdesaan ......................................................115
102. Reservoir Kapasitas 2 M³............................................................................................116
103. Reservoir Kapasitas 5 M ³ ..........................................................................................118
104. Reservoir Kapasitas 10 M ³.........................................................................................120
105. Reservoir Kapasitas 20 M ³.........................................................................................122
106. Menara Besi Air 3m + Tangki Air Kap.2000 Lt ...........................................................124
107. Menara Besi Air 3m + Tangki Air Kap.2 X 2000 Lt .....................................................125
108. Menara Besi Air 4m + Tangki Air Kap.2000 Lt ...........................................................126
109. Menara Besi Air 4m + Tangki Air Kap.2 X 2000 Lt .....................................................127
110. Menara Besi Air 6m + Tangki Air Kap.5000 Lt ...........................................................128
111. Menara Besi Air 6m + Tangki Air Kap.2 X 5000 Lt .....................................................129
112. Menara Baja Wf Tinggi 6m + Tangki Air Kap.5000 Lt .................................................130
113. Menara Baja Wf Tinggi 6m + Tangki Air Kap.2 X 5000 Lt ...........................................131
114. Sumur Dangkal 60m..................................................................................................132
115. Sumur Dangkal 60m + Menara Air 4 M......................................................................133
116. Sumur Dangkal 60m + Jaringan Pipa ........................................................................135
117. Sumur Dangkal 60m + Menara Air 4 M + Jaringan Pipa+ Tangki Air
Kap.2000 + Sr ............................................................................................................136
118. Sumur Dangkal 60m X 2 Unit + Menara Air 4 M + Jaringan Pipa+ Tangki Air
Kap.2000 ...................................................................................................................138
119. Sumur Dangkal 70m..................................................................................................141
120. Sumur Dangkal 70m + Menara Air 4 M......................................................................142
121. Sumur Dangkal 70m + Jaringan Pipa ........................................................................144
122. Sumur Dangkal 70m + Menara Air 4 M + Jaringan Pipa+ Tangki Air
Kap.2000 + Sr ............................................................................................................145
123. Sumur Dangkal 70m X 2 Unit + Menara Air 4 M + Jaringan Pipa+ Tangki Air
Kap.2000 ...................................................................................................................147
124. Sumur Dangkal 80m..................................................................................................150
125. Sumur Dangkal 80m + Menara Air 4 M......................................................................151
126. Sumur Dangkal 80m + Jaringan Pipa ........................................................................153
127. Sumur Dangkal 80m + Menara Air 4 M + Jaringan Pipa+ Tangki Air
Kap.2000 + Sr ............................................................................................................154
128. Sumur Dangkal 80m + Menara Air 4 M + Jaringan Pipa+ Tangki Air
Kap.2000 + Sr Dak ....................................................................................................156
129. Sumur Dalam 100 M .................................................................................................158
130. Sumur Dalam 100 M + Menara Air 6 M Tangki Air Kap.5000 Lt ................................160
131. Sumur Dalam 100 M + Jaringan ................................................................................162
132. Sumur Dangkal 100m + Menara+Jaringan Pipa+Sr ...................................................170
133. Sumur Dangkal 100m + Reservoir 20 M3+Jaringan Pipa+Sr ......................................172
134. Sumur Dalam 150 M .................................................................................................164
135. Sumur Dalam 150m + Menara+Jaringan Pipa+Sr ......................................................165
136. Sumur Dalam 150m + Resevoar 20 M3+Pemagaran+Jaringan Pipa+Sr ......................167
137. Pembuatan Bank Sampah Tematik ............................................................................174
138. Instalasi Pengolahan Lumpur Tinja (IPLT) ..................................................................176
xviii
53. Pengadaan Peralatan praktek lembaga kursus .......................................................... 26
54. Pengadaan peralatan Laboratorium Komputer ............................................................ 26
55. Pengadaan peralatan teknologi, informasi dan komunikasi (TIK) untuk PKBM .......... 27
56. Sosialisasi Pemahaman dan Pengetahuan Perkoperasian ........................................... 27
57. Kemitraan Usaha bagi UMKM ..................................................................................... 28
58. Pelatihan Kewirausahaan bagi UMKM ........................................................................ 28
59. Pendampingan Usaha bagi UMKM .............................................................................. 29
60. Inkubasi Bisnis bagi UMKM ........................................................................................ 29
61. Penyelenggaraan Gelar Produk UMKM ........................................................................ 30
62. Pelatihan Ekonomi Kreatif .......................................................................................... 30
63. Pelatihan Tatakelola Destinasi Pariwisata ................................................................... 31
64. Pengadaan Sarana Prasarana Kesenian ( Pengadaan Matras) ..................................... 31
65. Pelatihan Sumber Daya Manusia Kesenian Tradisional sesuai dengan
kebutuhan dan Tuntutan ........................................................................................... 32
66. Fasilitasi Pagelaran Seni budaya bagi Kelompok seni yang berkontribusi
dalam pemajuan kebudayaan ..................................................................................... 33
67. Bimbingan Teknis (Bimtek) Pengelolaan Sampah dan Bank Sampah .......................... 33
68. Bimbingan Teknis Konservasi Sumber Daya Air (KSDA) ............................................. 34
69. Bimbingan Teknis Pengolahan Limbah Peternakan ( Rumah Budidaya Cacing) .......... 35
70. Sosialisasi dan Penanaman Pohon Multy Purpose Tree Species (MPTS)
Buah-buahan ............................................................................................................. 35
71. Dukungan Bantuan Pohon Multy Purpose Tree Species (MPTS) Kayu-kayuan ............ 36
72. Sosialisasi Gerakan Penanaman ................................................................................. 36
73. Sosialiasasi Pengendalian Pencemaran Lingkungan ................................................... 37
74. Pengembangan/Pembangunan Bank Sampah Tematik ............................................... 37
75. Pembuatan Persemaian .............................................................................................. 38
76. Pengolahan Hasil Pertanian ........................................................................................ 39
77. Konveksi ..................................................................................................................... 41
78. Pengolahan Sampah Plastik ........................................................................................ 43
79. Pengolahan Kopi ......................................................................................................... 44
80. Barista ........................................................................................................................ 45
81. Sound System ............................................................................................................. 46
82. Digital Printing ........................................................................................................... 47
83. Bimbingan Jabatan .................................................................................................... 48
84. Penyuluhan Bimbingan Jabatan ................................................................................. 49
85. Temu Konsultasi Pengelola Bkk .................................................................................. 50
86. Pelatihan Montir Sepeda Motor Unit Pelatihan Keliling ............................................... 51
87. Pelatihan Las Listrik Unit Pelatihan Keliling ............................................................... 52
88. Pelatihan Menjahit Unit Pelatihan Keliling .................................................................. 53
89. Pelatihan Service HP Unit Pelatihan Keliling ............................................................... 54
90. Pelatihan Tata Boga Unit Pelatihan Keliling ................................................................ 55
91. Pelatihan Tata Rias Unit Pelatihan Keliling ................................................................. 56
92. Pelatihan Sablon Unit Pelatihan Keliling ..................................................................... 58
93. Pelatihan Service Komputer Unit Pelatihan Keliling .................................................... 59
94. Pelatihan Mebeuler Unit Pelatihan Keliling ................................................................. 60
95. Pelatihan Daur Ulang Sampah Unit Pelatihan Keliling ................................................ 61
96. Pelatihan Design Grafis Unit Pelatihan Keliling ........................................................... 62
97. Bahasa Jepang ........................................................................................................... 63
98. Bahasa Korea ............................................................................................................. 64
99. Pelatihan Kewirausahaan Muda ................................................................................. 64
100. Pengambangan Usaha Pangan Masyarakat (PUPM) melalui Toko
Tani Indonesia (TTI) .................................................................................................... 65
101. Pekarangan Pangan Lestari (P2L) Konvensional .......................................................... 66
102. Pengembangan Industri pangan lokal (PIPL) ............................................................... 67
103. Pengembangan Budidaya Ikan Nila ............................................................................ 67
104. Pengembangan Budidaya Ikan Hias ............................................................................ 67
105. Pengembangan Budidaya Ikan Mas ............................................................................ 68
106. Pengembangan Budidaya Ikan Lele............................................................................. 68
xix
107. Sarana dan Prasarana Pengolahan Pemindangan Ikan ............................................... 68
108. Sarana dan Prasarana Pengolahan Ikan abon, nugget, bakso,
siomay, otak-otak ikan ............................................................................................... 69
109. Bimtek Diversifikasi Olahan Ikan ............................................................................... 69
110. Pemberian Bantuan Ternak Domba bagi KUBE KFM .................................................. 70
111. Pemberian Bantuan Warungan bagi KUBE KFM ......................................................... 70
112. Pemberian Bantuan Beras bagi KUBE KFM ................................................................ 70
113. Pemberian Bantuan Konveksi bagi KUBE KFM ........................................................... 71
114. Pemberian Bantuan Ternak Domba bagi KUBE WRSE ............................................... 71
115. Pemberian Bantuan Warungan bagi KUBE WRSE ...................................................... 71
116. Pemberian Bantuan Olah Pangan bagi KUBE WRSE................................................... 72
117. Pemberian Bantuan Bagi KUBE Beras ........................................................................ 72
118. Pemberian Bantuan Bagi KUBE Konveksi ................................................................... 73
119. Pemberian Bantuan UEP Ternak Domba bagi Orang Tua Penyandang Disabilitas ...... 73
120. Pemberian Bantuan UEP Warungan bagi Orang Tua Penyandang Disabilitas ............. 74
121. Pemberian Bantuan Bagi UEP Olah Pangan Gorengan ............................................... 74
122. Pemberian bantuan UEP Ternak Domba ..................................................................... 75
123. Pengadaan bahan baku bagi UEP Warungan ............................................................. 75
124. Pemberian Bantuan Bagi UEP Usaha Olah Pangan Kue.............................................. 76
125. Pemberian bantuan UEP Ternak Domba ..................................................................... 76
126. Pengadaan bahan baku bagi UEP Warungan ............................................................. 77
127. Pemberian Bantuan Bagi UEP Olah Pangan Kue ........................................................ 77
128. Pemberian bantuan UEP Ternak Domba ..................................................................... 78
129. Pemberian Bantuan Bagi UEP Mesin jahit .................................................................. 78
130. Pemberian Bantuan Bagi Orang Tua Balita Terlantar Usaha Warungan ..................... 79
131. Pemberian Bantuan Bagi Orang Tua Balita Terlantar Usaha Olah Pangan
Gorengan .................................................................................................................... 79
132. Pemberian Bantuan Usaha Olah Pangan Kue Bagi Orang Tua Balita Terlantar ......... 80
133. Pemberian Bantuan Ternak Domba Bagi Orang Tua Balita Terlantar ........................ 80
134. Pengadaan bahan baku Warungan bagi LUP .............................................................. 81
135. Pengadaan bahan baku Olah Pangan Gorengan bagi LUP .......................................... 81
136. Pengadaan bahan baku Olah Pangan Kue bagi LUP ................................................... 82
137. Pemberian bantuan Ternak Domba bagi LUP.............................................................. 82
138. Pemberian Bantuan Jaminan Hidup Bagi Lansia tanpa Bimsos ................................. 83
139. Pemberian Bantuan Jaminan Hidup Bagi Lansia tanpa Bimsos ................................. 83
140. Pemberian Bantuan Stimulan UEP Olah pangan Kue bagi Eks. Gelandangan dan
Pengemis (Gepeng) ...................................................................................................... 84
141. Pemberian Bantuan Stimulan UEP Warungan bagi Gelandangan
dan Pengemis (Gepeng) ............................................................................................... 84
142. Pemberian Bantuan Stimulan UEP Ternak Domba Bagi Eks. Narkoba ...................... 85
143. Pemberian Bantuan Stimulan UEP Warungan Bagi Eks. Narkoba ............................. 85
144. Pemberian Bantuan Stimulan UEP Ternak Domba Bagi Eks. Warga Binaan
Pemasyarakatan ........................................................................................................ 86
145. Pemberian Bantuan Stimulan UEP Warungan Bagi Eks. Warga Binaan
Pemasyarakatan ........................................................................................................ 86
146. Bimtek Rumah Siap Bangun Pasca Bencana .............................................................. 87
147. Bimtek Psikososial Trauma Healing ............................................................................ 88
148. Bimbingan Teknik Pemberdayaan Masyarakat Pembentukan Relawan Desa Tangguh
Bencana ..................................................................................................................... 89
xx
REKAP LAMPIRAN I HSPK
HARGA SATUAN
No URAIAN PEKERJAAN SPESIFIKASI SATUAN
(RP)
(1) (2) (3) (4) (5)
PEKERJAAN PONDASI
1 Pemasangan pondasi batu kosong - aanstamping / m³ m³ 650.982,000
2 Pemasangan pondasi batu belah campuran 1 PC : 3 PP / m³ m³ 1.237.730,000
3 Pemasangan pondasi batu belah campuran 1 PC : 4 PP / m³ m³ 1.182.760,000
4 Pemasangan pondasi batu belah campuran 1 PC : 5 PP / m³ m³ 1.144.638,000
5 Pemasangan pondasi batu belah campuran 1 PC : 6 PP / m³ m³ 1.117.843,000
6 Pemasangan pondasi batu belah campuran 1 PC : 8 PP / m³ m³ 1.081.100,000
Pemasangan pondasi cyclop 40 % batubelah + 60 % beton 1 SP:2PB: 3Kr /
7 m³ 3.220.490,000
m³
8 Pemasangan pondasi sumuran diameter 100 cm / m³ m³ 1.250.527,000
PEKERJAAN STRUKTUR
STRUKTUR BETON
1 Pekerjaan Beton K 100 - f'c 7,4 Mpa LANTAI KERJA / m³ m³ 1.078.544,000
2 Pekerjaan Beton K 100 - f'c 7,4 Mpa LANTAI KERJA / m³ m³ 1.016.351,000
3 Pekerjaan Beton K 100 - f'c 7,4 Mpa / m³ m³ 1.161.474,000
4 Pekerjaan Beton K 125 - f'c 9,8 Mpa / m³ m³ 1.198.734,000
5 Pekerjaan Beton K 150 - f'c 12,2 Mpa / m³ m³ 1.227.940,000
6 Pekerjaan Beton K 175 - f'c 14,5 Mpa / m³ m³ 1.269.586,000
7 Pekerjaan Beton K 200 - f'c 16,9 Mpa / m³ m³ 1.302.437,000
8 Pekerjaan Beton K 225 - f'c 19,3 Mpa / m³ m³ 1.320.118,000
9 Pekerjaan Beton K 250 - f'c 21,7 Mpa / m³ m³ 1.336.744,000
10 Pekerjaan Beton K 275 - f'c 24 Mpa / m³ m³ 1.365.557,000
11 Pekerjaan Beton K 300 - f'c 26,4 Mpa / m³ m³ 1.374.406,000
12 Pekerjaan Beton K 325 - f'c 28,8 Mpa / m³ m³ 1.408.148,000
13 Pekerjaan Beton K 350 - f'c 31,2 Mpa / m³ m³ 1.419.845,000
14 Pekerjaan Beton Kedap air dengan STROROX-100 / m³ m³ 1.520.723,000
15 Pemasangan 1 m¹ PVC waterstop lebar 150 mm / m¹ m¹ 331.672,000
16 Pemasangan 1 m¹ PVC waterstop lebar 200 mm / m¹ m¹ 393.181,000
17 Pemasangan 1 m¹ PVC waterstop lebar 250 mm / m¹ m¹ 490.290,000
18 Pekerjaan Beton K 100 - f'c 7,4 Mpa menggunakan molen / m³ m³ 1.130.065,000
19 Pekerjaan Beton K 125 - f'c 9,8 Mpa menggunakan molen / m³ m³ 1.167.223,000
20 Pekerjaan Beton K 150 - f'c 12,2 Mpa menggunakan molen / m³ m³ 1.196.426,000
21 Pekerjaan Beton K 175 - f'c 14,5 Mpa menggunakan molen / m³ m³ 1.219.480,000
22 Pekerjaan Beton K 200 - f'c 16,9 Mpa menggunakan molen / m³ m³ 1.255.198,000
23 Pekerjaan Beton K 225 - f'c 19,3 Mpa menggunakan molen / m³ m³ 1.288.543,000
24 Pekerjaan Beton K 250 - f'c 21,7 Mpa menggunakan molen / m³ m³ 1.309.131,000
25 Pekerjaan Beton K 275 - f'c 24 Mpa menggunakan molen / m³ m³ 1.334.046,000
26 Pekerjaan Beton K 300 - f'c 26,4 Mpa menggunakan molen / m³ m³ 1.342.896,000
27 Pekerjaan Beton K 325 - f'c 28,8 Mpa menggunakan molen / m³ m³ 1.448.974,000
28 Pekerjaan Beton K 350 - f'c 31,2 Mpa menggunakan molen / m³ m³ 1.460.671,000
29 Pemadatan beton menggunakan Vibrator / m³ m³ 50.395,000
30 Pembesian dengan besi polos / KG KG 17.596,000
31 Pembesian dengan besi Ulir / kg kg 20.011,000
32 Pembesian dengan besi Jaring Kawat di las ( Wire mesh) / kg kg 13.353,000
33 Pekerjaan Bekisting Pondasi / m ² m² 228.448,000
34 Pekerjaan Bekisting Sloof / m ² m² 238.798,000
35 Pekerjaan Bekisting Kolom / m ² m² 428.677,000
36 Pekerjaan Bekisting Balok / m ² m² 439.027,000
37 Pekerjaan Bekisting Lantai / m ² m² 491.697,000
38 Pekerjaan Bekisting Dinding / m ² m² 467.087,000
39 Pekerjaan Bekisting Tangga / m ² m² 406.683,000
40 Pekerjaan Bekisting Lantai pakai floor deck / m ² m² 174.819,000
41 Pekerjaan Pondasi Beton Bertulang ( 150 kg besi + Bekisting) / m ³ m³ 5.535.109,000
42 Pekerjaan Sloof Beton Bertulang ( 200 kg besi + Bekisting) / m ³ m³ 7.374.284,000
43 Pekerjaan Balok Beton Bertulang ( 200 kg besi + Bekisting) / m ³ m³ 8.001.566,000
44 Pekerjaan Kolom Beton Bertulang ( 150 kg besi + Bekisting) / m ³ m³ 7.581.467,000
45 Pekerjaan Kolom Beton Bertulang ( 300 kg besi + Bekisting) / m ³ m³ 10.666.017,000
46 Pekerjaan Pelat Beton Bertulang ( 150 kg besi + Bekisting) / m ³ m³ 7.384.259,000
47 Pekerjaan Dinding Beton Bertulang ( 150 kg besi + Bekisting) / m ³ m³ 7.027.625,000
48 Pekerjaan Dinding Beton Bertulang ( 200 kg besi + Bekisting) / m ³ m³ 7.882.624,000
49 Pekerjaan Kolom Praktis Beton Bertulang ( 11 x 11 cm) / m' m' 105.645,000
50 Pekerjaan Balok Ring Praktis Beton Bertulang ( 10 x 15 cm) / m' m' 135.210,000
51 Grouting semen - screening / kg kg 314.636,000
52 Pekerjaan Beton K 500 - f'c 41,5 Mpa Ready Mixed / m ³ m³ 1.779.519,000
Rabat Beton tebal 8 cm beton f’c 14,5
53 m³ 100.912,000
MPa, slump (120 ± 20) mm
PEKERJAAN DINDING
1 Pasangan dinding bata merah 1 PC : 2 PP tebal 1 bata / m ² m ² 370.596,000
2 Pasangan dinding bata merah 1 PC : 3 PP tebal 1 bata / m ² m ² 356.167,000
3 Pasangan dinding bata merah 1 PC : 4 PP tebal 1 bata / m ² m ² 346.070,000
4 Pasangan dinding bata merah 1 PC : 5 PP tebal 1 bata / m ² m ² 341.403,000
5 Pasangan dinding bata merah 1 PC : 6 PP tebal 1 bata / m ² m ² 335.234,000
6 Pasangan dinding bata merah 1 PC : 2 PP tebal 1/2 bata / m ² m ² 180.054,000
7 Pasangan dinding bata merah 1 PC : 3 PP tebal 1/2 bata / m ² m ² 172.992,000
8 Pasangan dinding bata merah 1 PC : 4 PP tebal 1/2 bata / m ² m ² 169.068,000
9 Pasangan dinding bata merah 1 PC : 5 PP tebal 1/2 bata / m ² m ² 166.609,000
10 Pasangan dinding bata merah 1 PC : 6 PP tebal 1/2 bata / m ² m ² 165.491,000
11 Pasangan dinding bata merah 1 PC : 8 PP tebal 1/2 bata / m ² m ² 162.743,000
Pemasangan Bata Terawang - Rooster ( 24 x 7 x 1,5 ) spesi 1 PC : 3 PP / m
12 m² 201.010,000
²
Pemasangan Bata Terawang - Rooster ( 24 x 7 x1,5 ) spesi 1 PC : 4 PP / m
13 m² 199.342,000
²
14 Pemasangan Bata Berongga Exposed ( 24 x 7 x 1,5 ) spesi 1 PC : 3 PP / m ² m² 383.400,000
15 Pemasangan Rollag bata / m ² m ² 335.234,000
16 Pemasangan Glass Block 20 20 x 11 cm spesi 1PC : 4 PP / m ² m ² 815.110,000
17 Pemasangan Roster Beton 20 x 20 x 7 cm spesi 1PC : 4 PP / m ² m ² 402.490,000
18 Pemasangan Roster Kayu 40 x 20 x 7 cm spesi 1PC : 4 PP / m ² m ² 398.005,000
19 Pemasangan Bata Ringan tebal 75 mm dengan mortar siap pakai / m ² m ² 164.949,000
20 Pemasangan Bata Ringan tebal 100 mm dengan prime mortar / m ² m ² 186.303,000
21 Pemasangan Bata Ringan tebal 150 mm dengan prime mortar / m ² m² 196.752,000
22 Pekerjaan Plesteran dengan prime mortar / m ² m² 97.521,000
23 Pekerjaan Acian dengan prime mortar m² 84.669,000
24 Plesteran Halus 1 PC : 1 PP tebal 1,5 cm / m ² m² 109.604,000
25 Plesteran Halus 1 PC : 2 PP tebal 1,5 cm / m ² m² 101.950,000
26 Plesteran Halus 1 PC : 3 PP tebal 1,5 cm / m ² m² 98.730,000
27 Plesteran Halus 1 PC : 4 PP tebal 1,5 cm / m ² m² 96.456,000
28 Plesteran Halus 1 PC : 5 PP tebal 1,5 cm / m ² m² 95.270,000
29 Plesteran Halus 1 PC : 6 PP tebal 1,5 cm / m ² m² 94.277,000
30 Plesteran Halus 1 PC : 7 PP tebal 1,5 cm / m ² m² 93.764,000
31 Plesteran Halus 1 PC : 8 PP tebal 1,5 cm / m ² m² 93.252,000
32 Plesteran 1 PC : 3 PP skoning lebar 10 cm / m¹ m¹ 98.012,000
33 Plesteran 1 Pc : 1 Ps tebal 20 mm / m ² m² 136.446,000
34 Plesteran 1 Pc : 3 Ps tebal 20 mm / m ² m² 132.153,000
35 Plesteran 1 Pc : 4 Ps tebal 20 mm / m ² m² 129.026,000
36 Plesteran 1 Pc : 5 Ps tebal 20 mm / m ² m² 127.540,000
37 Plesteran 1 Pc : 6 Ps tebal 20 mm / m ² m² 126.107,000
38 Plesteran Berapen 1 Pc : 5 Ps tebal 15 mm m² 93.764,000
39 Plesteran Skoning (benangan/ tali air) 1 Pc : 2 Ps lebar 10 cm / m¹ m¹ 98.012,000
40 Plesteran Ciprat 1 Pc : 2 Ps / m ² m² 93.558,000
41 Plesteran Finishing Siar 1 Pc : 2 Ps untuk pasangan batu kali / m ² m² 93.173,000
42 Acian / m ² m² 58.187,000
14 Pasang rangka plafon besi hollow 40x40x 0,4mm modul 60 x 120 cm / m² m² 156.499,000
15 Pasang rangka plafon besi hollow 40x40x 0,5mm modul 60 x 120 cm / m² m² 166.799,000
16 Pasang rangka plafon besi hollow 40x40x 0,6mm modul 60 x 120 cm / m² m² 179.081,000
17 List Plafon kayu profil / m¹ m¹ 32.900,000
18 List plafon bahan Kayu Kamper Samarinda papan 1x5 cm / m¹ m¹ 42.560,000
19 List plafon bahan triplek 0,3x5 cm / m¹ m¹ 22.033,000
20 Pasang list profil cornice gypsum lebar sampai 5 cm / m¹ m¹ 45.572,000
21 List profil cornice gypsum lebar 5-10 cm / m¹ m¹ 52.466,000
22 Pasang list profil cornice gypsum lebar lebih dari 10 cm / m¹ m¹ 54.174,000
23 Pasang list profil cornice wall aluminium / m¹ m¹ 34.108,000
24 Penutup plafon asbes (1,00 x 1,00) m tebal 3,5 mm / m² m² 45.726,000
25 Penutup plafon akustik (60 x 120) cm / m² m² 153.473,000
Pemasangan langit-langit akustik (60 x 120) cm, berikut rangka
26 m² 276.925,000
alumunium / m²
27 Penutup plafon gypsum board uk. 1200 x2400 x9 mm / m² m² 59.164,000
28 Penutup plafon gypsum board uk. 1200 x2400 x12 mm / m² m² 70.862,000
29 Penutup plafon GRC-board uk. 1200 x 2400 x tebal 4 mm / m² m² 57.280,000
30 Penutup plafon Kalsiboard 1200 x 2400 x tebal 4 mm / m² m² 70.466,000
Penutup plafon triplek/teakwood 120 X240 cm, tebal 3 mm, 4 mm dan 6
31 m² 113.089,000
mm / m²
Penutup plafon Gypsumboard 9 mm lengkap dgn rangka hollow tebal 0.4
m² 215.663,000
mm
Penutup plafon Gypsumboard 9 mm lengkap dgn rangka hollow tebal 0.6
m² 238.245,000
mm
Penutup plafon GRC-board 4 mm lengkap dgn rangka hollow tebal 0.6 mm m² 236.361,000
Penutup plafon Calsiboard 4 mm lengkap dgn rangka hollow tebal 0.6 mm m² 249.547,000
32 Penutup plafon Akustik ukuran 60x120 cm + rangka alumunium / m² m² 437.278,000
PEKERJAAN SANITASI
1 Memasang 1 buah kloset duduk/monoblok (sederhana) / bh bh 2.172.088,000
2 Memasang 1 buah kloset duduk/monoblok setara INA (sedang) / bh bh 2.903.488,000
3 Memasang 1 buah kloset duduk/monoblok (tidak sederhana) / bh bh 4.853.888,000
4 Memasang 1 buah kloset jongkok sederhana / bh bh 730.581,000
5 Memasang 1 buah kloset jongkok sedang / bh bh 845.581,000
6 Memasang 1 buah kloset jongkok tdk sederhana / bh bh 1.259.581,000
7 Memasang 1 buah urinoir / bh bh 4.273.382,000
8 Memasang 1 buah penyekat urinoir / bh bh 1.613.910,000
9 Memasang 1 buah wastafel sederhana / bh bh 1.452.432,000
10 Memasang 1 buah wastafel sedang / bh bh 1.895.182,000
11 Memasang 1 buah wastafel setara Toto / bh bh 2.717.432,000
12 Memasang 1 buah bak mandi fibreglass 60x60 cm / bh bh 1.221.816,000
13 Memasang 1 buah bak mandi batu bata volume 0,3 m³ / bh bh 1.954.538,000
14 Memasang 1 buah bak cuci piring stainless steel / bh bh 481.994,000
15 Memasang pipa galvanis dia 0,5 / m¹ m¹ 64.358,000
16 Memasang pipa galvanis dia ¾" / m¹ m¹ 73.908,000
17 Memasang pipa galvanis dia 1" / m¹ m¹ 79.881,000
18 Memasang pipa galvanis dia 1 1/4 " / m¹ m¹ 84.426,000
19 Memasang pipa galvanis dia 1 ½" / m¹ m¹ 130.910,000
20 Memasang pipa galvanis dia 2" / m¹ m¹ 135.901,000
21 Memasang pipa galvanis dia 2 1/2 " / m¹ m¹ 141.455,000
22 Memasang pipa galvanis dia 3" / m¹ m¹ 165.699,000
23 Memasang pipa galvanis dia 4" / m¹ m¹ 194.932,000
24 Memasang pipa PVC tipe AW dia 1/2" m¹ 24.351,000
25 Memasang pipa PVC tipe AW dia 3/4" / m¹ m¹ 26.802,000
26 Memasang pipa PVC tipe AW dia 1" / m¹ m¹ 30.233,000
27 Memasang pipa PVC tipe AW dia 1 ¼" / m¹ m¹ 33.932,000
28 Memasang pipa PVC tipe D dia 1 ¼" / m¹ m¹ 31.169,000
29 Memasang pipa PVC tipe AW dia 1 1/2 "/ m¹ m¹ 37.586,000
30 Memasang pipa PVC tipe D dia 1 1/2 " / m¹ m¹ 30.723,000
31 Memasang pipa PVC tipe AW dia 2" / m¹ m¹ 48.759,000
32 Memasang pipa PVC tipe D dia 2" / m¹ m¹ 42.342,000
33 Memasang pipa PVC tipe AW dia 2 ½" / m¹ m¹ 73.057,000
34 Memasang pipa PVC tipe D dia 2 1/2 " / m¹ m¹ 37.720,000
35 Memasang pipa PVC tipe AW dia 3" / m¹ m¹ 91.728,000
36 Memasang pipa PVC tipe D dia 3" / m¹ m¹ 68.868,000
37 Memasang pipa PVC tipe AW dia 4" / m¹ m¹ 120.248,000
38 Memasang pipa PVC tipe D dia 4" / m¹ m¹ 82.014,000
39 Memasang pipa PVC tipe AW dia 6" / m¹ m¹ 275.994,000
40 Memasang pipa PVC tipe D dia 6" / m¹ m¹ 146.941,000
41 Memasang pipa PVC tipe AW dia 8" / m¹ m¹ 592.602,000
42 Memasang 1 buah Stop Valve 1,5 " / bh bh 387.836,000
43 Memasang 1 buah kran dia 3/4" atau 1/2" sederhana / bh bh 135.986,000
44 Memasang 1 buah kran dia 3/4" atau 1/2" stainless / bh bh 326.886,000
45 Memasang 1 buah kran bebek dia 3/4" atau 1/2" sederhana / bh bh 255.586,000
46 Memasang 1 buah kran bebek dia 3/4" atau 1/2" stainless / bh bh 543.086,000
47 Memasang 1 buah hand shower setara TOTO / bh bh 2.612.943,000
48 Memasang Shower Spray Setara TOTO bh 399.193,000
49 Memasang 1 buah tempat sabun / bh bh 241.068,000
50 Memasang 1 buah gantungan baju / bh bh 234.743,000
51 Memasang 1 floor drain sederhana / bh bh 126.164,000
52 Memasang 1 floor drain stainless /bh bh 277.964,000
53 Memasang Roof drain / bh bh 208.964,000
54 Memasang 1 clean out dia. 100 mm / bh bh 166.874,000
55 Memasang 1 clean out dia. 50 mm / bh bh 122.024,000
Membuat 1 unit sumur air tanah bor manual dalam 12 m' + pompa air
56 bh 7.389.631,000
listrik / bh
Membuat 1 unit tanki septik sederhana kapasitas Ø 1,2 m dalam 1,2 m /
57 bh 2.831.527,000
bh
Membuat 1 unit tanki septik kapasitas 1,7x0,85 m dalam 1,3 m (vol. 1,88
58 bh 4.833.653,000
m³ u/ 5 pemakai) / bh
59 Membuat tanki septik kapasitas tiap 1 m³ m3 2.577.720,000
Membuat 1 unit resapan Ø 0,8 m (digali 1 m) dalam 1 m (digali 1,9 m) kap.
60 m3 341.981,000
0,5 m³
61 Memasang 1 unit septictank pabrikasi kap. 1 m³ m3 4.028.390,000
62 Memasang 1 unit septictank pabrikasi kap. 2 m³ m3 8.647.307,000
63 Memasang 1 unit septictank pabrikasi kap. 3 m³ m3 21.092.313,000
64 Memasang 1 unit septictank pabrikasi kap. 6 m³ m3 41.687.913,000
65 Memasang 1 unit septictank pabrikasi kap. 8 m³ m3 44.479.015,000
66 Membuat tanki septik kapasitas tiap 3 m³ m3 2.577.720,000
67 Membuat tanki septik kapasitas tiap 6 m³ m3 5.155.440,000
PEKERJAAN PENGECATAN
1 Mengikis/mengerok permukaan cat lama / m ² Pengecatan 1 lapis plamur, 1 lapis cat dasr, 2
cat lapis
m ²penutup 27.039,000
2 Pengecatan dengan cat KW 1 bidang kayu baru / m ² Pengecatan 1 lapis plamur, 1 lapis cat dasr, 2
cat lapis
m ²penutup 66.412,000
3 Pengecatan dengan cat KW 2 bidang kayu baru / m ² Pengecatan 1 lapis plamur, 1 lapis cat dasr, 2
cat lapis
m ²penutup 59.114,000
4 Pengecatan dengan cat KW 1 bidang kayu lama Pengecatan 1 lapis plamur, 1 lapis cat dasr, 2 lapis
cat penutup 75.002,000
5 Pelaburan bidang kayu dgn teak oil / m ² m² 39.954,000
6 Pelaburan bidang kayu dgn politur / m ² m² 97.325,000
7 Pengecatan bidang kayu dengan melamik / m ² Pengecatan 1 lapis plamur, 1 lapis cat dasr, 2 lapis cat
m ²penutup 140.820,000
8 Pelaburan bidang kayu dgn residu dan ter / m ² m² 16.735,000
9 Pelaburan bidang kayu dgn vernis / m ² m² 44.500,000
10 Pengecatan tembok baru dg cat KW 1 / m ² Pengecatan 1 lapis plamuur, 1 lapis cat dasar, 2 lapis
m cat
² penutup42.948,000
11 Pengecatan tembok baru dg cat KW 2 / m ² Pengecatan 1 lapis plamuur, 1 lapis cat dasar, 2 lapis
m cat
² penutup33.978,000
12 Pengecatan tembok baru dg wall sealer - cat penutup KW 1 / m ² Pengecatan 1 lapis plamuur, 1 lapis cat dasar, 2 lapis
m cat
² penutup45.145,000
13 Pengecatan tembok baru dg cat Weathershield / m ² Pengecatan 1 lapis plamuur, 1 lapis cat dasar, 2 lapis
m cat
² penutup51.842,000
14 Pengecatan bidang tembok lama 1 m² dg cat KW 1 / m ² Pengecatan 1 lapis cat dasar, 2 lapis cat penutup m ² 31.977,000
15 Pengecatan bidang tembok lama 1 m² dg cat KW 2 / m ² Pengecatan 1 lapis plamuur, 1 lapis cat dasar, 2 lapis
m cat
² penutup25.767,000
16 Memasang wallpaper / m ² m² 126.565,000
17 Pengecatan permukaan baja 1 m² dgn meni besi / m ² m² 51.350,000
18 Pengecatan permukaan kayu dgn meni / m ² m² 44.542,000
19 Pengecatan permukaan baja tiap 1 m² dengan zinchromate / m ² m² 47.655,000
20 Pengecatan permukaan baja tiap 1 m² dengan Cat KW 1 / m ² m² 53.359,000
21 Pengecatan permukaan baja tiap 1 m² dengan Cat KW 2/ m ² m² 51.680,000
22 Pengecatan permukaan baja 1 m² dgn meni besi & perancah / m ² m² 72.050,000
23 Pekerjaan cat duko sistem semprot / m ² m² 300.381,000
24 Pengecatan waterproofing (coating) / m ² m² 132.922,000
PEKERJAAN BONGKARAN
1 Bongkar beton bertulang / m³ m³ 579.287,000
2 Bongkar dinding tembok bata merah / m³ m³ 108.914,000
3 Bongkar dinding ½ bata / m ² m² 11.999,000
4 Bongkar pelat beton bertulang / m ² m² 130.699,000
5 Bongkar batu kali / m ² m² 245.062,000
6 Bongkar lantai / m ² m² 8.689,000
7 Bongkar paving block / m ² m² 8.689,000
8 Bongkar plesteran / m ² m² 8.272,000
9 Bongkar atap genteng / m ² m² 5.143,000
10 Bongkar karpusan atap genteng / m¹ m¹ 7.715,000
11 Bongkar atap seng/asbes / m ² m² 9.800,000
12 Bongkar kaso dan reng kayu (kayu akan dipakai lagi) / m ² m² 21.459,000
13 Bongkar kaso dan reng kayu (kayu tidak akan dipakai lagi) / m ² m² 16.337,000
14 Bongkar balok kuda-kuda & loteng (kayu akan dipakai lagi) / m³ m³ 1.239.206,000
15 Bongkar balok kuda-kuda & loteng (kayu tidak akan dipakai lagi) / m³ m³ 435.494,000
16 Bongkar rangka plafon / m ² m² 16.337,000
17 Bongkar penutup plafon / m ² m² 5.213,000
PEKERJAAN DRAINASE
1 Memasang pipa beton, dia 15-20 cm m' 402.442,000
2 Memasang pipa beton, dia 30 cm / m¹ m¹ 632.668,000
3 Memasang pipa beton, dia 40 cm / m¹ m¹ 714.640,000
4 Memasang pipa beton, dia 50 cm / m¹ m¹ 859.482,000
5 Memasang pipa beton, dia 60 cm / m¹ m¹ 923.365,000
6 Memasang pipa beton, dia 80 cm / m¹ m¹ 1.183.114,000
7 Memasang pipa beton, dia 100 cm / m¹ m¹ 1.277.541,000
8 Memasang 1 buah bak kontrol pas.batu bata 30 x 30 cm tinggi 35 cm / bh bh 702.123,000
14 Membuat saluran air dari batu kali lebar bawah 60 cm tinggi 80 cm / m¹ m¹ 972.204,000
15 Membuat saluran air dari batu kali lebar bawah 80 cm tinggi 100 cm / m¹ m¹ 1.414.797,000
Membuat saluran air dari batu kali lebar bawah 100 cm tinggi 120 cm /
16 m¹ 1.845.928,000
m¹
TAMAN
1 Penanaman Rumput Gajah Manila /m ² m ² 59.667,000
2 Pasang grassblock tebal 10 cm / m ² m ² 194.666,000
3 Gebalan rumput / m ² m ² 52.396,000
4 Geotektil untuk Perkuatan Tanah / m ² m ² 246.897,000
PSDA
1 Kistdam pasir/tanah dibungkus karung plastik bagor 45 / m' m' 38.571,000
2 Dokumentasi / ls ls 137.856,000
3 Mutual Cek dan Survey / ls ls 1.416.340,000
4 Galian tanah biasa sedalam ≤ 1 m / m³ m³ 119.924,000
5 Galian tanah biasa sedalam ≤ 2 m / m³ m³ 117.314,000
6 Galian tanah berbatu sedalam ≤ 1 m / m³ m³ 234.803,000
7 Galian tanah berbatu sedalam > 1 m s.d. 2 m / m³ m³ 260.699,000
8 Galian tanah cadas atau tanah keras sedalam ≤ 1 m / m³ m³ 217.249,000
9 Galian tanah cadas atau tanah keras sedalam > 1 m s.d. 2 m / m³ m³ 241.928,000
10 Galian lumpur sedalam ≤ 1 m / m³ m³ 144.253,000
11 Timbunan tanah atau urugan tanah kembali / m³ m³ 57.353,000
12 Pemadatan tanah / m³ m³ 92.051,000
13 Pembersihan dan Striping/Kosrekan / m2 m2 10.427,000
14 Galian untuk Selokan Drainase dan Saluran Air Pakai Buruh / m3 m3 95.833,000
15 Galian untuk Selokan Drainase dan Saluran Air / m3 m3 36.827,000
16 Galian Biasa / m3 m3 95.529,000
17 Galian Struktur dengan kedalaman 0 - 2 meter / m3 m3 88.666,000
18 Galian Perkerasan berbutir / m3 m3 178.134,000
19 Galian Perkerasan Beton / m3 m3 200.733,000
20 Galian Batu / m3 m3 189.451,000
21 Galian Struktur dengan kedalaman 2 - 4 meter / m3 m3 706.902,000
22 Box Culver 1000 x 1000 HD / bh bh 5.884.750,000
23 Saluran U-Ditch 1000x1000 +Cover / bh bh 4.064.792,000
24 Saluran U-Ditch 600x600 / bh bh 1.260.517,000
25 Saluran U-Ditch 400x400 +Cover / bh bh 1.294.557,000
26 Beton K250 (fc’ 20) untuk struktur drainase beton minor / bh bh 2.024.315,000
27 Baja Tulangan untuk struktur drainase beton minor / bh bh 21.187,000
28 Saluran berbentuk U Tipe DS 2 / bh bh 2.170.020,000
29 Timbunan Biasa Dari Sumber Galian / bh bh 283.259,000
30 Timbunan Pilihan dari Galian / bh bh 325.436,000
31 Timbunan Pasir sebagai Lantai Kerja / m3 m3 354.931,000
32 Pasangan Batu Dengan Mortar / m3 m3 908.220,000
Beton Mutu, f'c = 9,8 Mpa ( K125), slump (12 ±2) cm, w/c= 0,78 (
33 m3 1.318.446,000
Menggunakan Molen > 2 m³ ) / m3
34 Beton struktur, fc’20 MPa (K250) / m3 m3 2.205.831,000
35 Pasangan pipa suling-suling / m m 41.686,000
36 Pipa Penyalur PVC / m m 534.349,000
37 Mortar tipe N ( untuk mutu PP setara dengan campuran 1 PC : 4 PP ) / m m 1.419.273,000
Plesteran tebal 1,5 cm, dengan mortar jenis PC-PP tipe S ( untuk mutu PP
38 m2 107.343,000
tertentu setara dengan campuran 1 PC : 3 PP ) / m2
Siaran dengan mortar jenis PC-PP tipe M ( untuk mutu PP tertentu setara
39 m2 115.044,000
dengan campuran 1 PC : 2 PP ) / m2
40 Pemasangan Bronjong Kawat (Pabrikasi) / m3 m3 681.477,000
41 Pemasangan Pintu Penguras / unit unit 857.555,000
42 Pemasangan Pintu Air / unit unit 3.617.555,000
Bekisting untuk permukaan beton biasa dengan papan ukuran 3/20 cm (
43 unit 160.019,000
tanpa perancah ) / unit
44 Perbaikan Pintu Air ( 2 Drat reel pintu ) / unt unt 6.963.583,000
4 Pembuatan Lubang Bor Sumur Dalam dia. 8' kedalaman 100-150 m / m¹ Kedalaman 100 m - 150 m m¹ 618.340,000
5 Perbesaran Lubang Bor Sumur Dalam dia. 10 " kedalaman 0-50 m / m¹ Kedalaman 0 m - 50 m m¹ 319.210,000
6 Perbesaran Lubang Bor Sumur Dalam dia. 10' kedalaman 50-100 m / m¹ Kedalaman 50 m - 100 m m¹ 399.797,000
7 Perbesaran Lubang Bor Sumur Dalam dia. 10' kedalaman 100-150 m / m¹ Kedalaman 100 m - 150 m m¹ 485.684,000
8 Pembuatan Sambungan Rumah Perdesaan / unit Sambungan Rumah Perdesaan unit 833.001,000
9 Pembuatan Sambungan Rumah Perkotaan / unit Sambungan Rumah Perkotaan unit 948.001,000
10 Pembuatan Sambungan Rumah HIBAH / unit Sambungan Rumah Hibah unit 1.318.165,000
11 Tutup Manhole Pelat Bordes / unit unit 525.734,000
12 Tangga Monyet / unit unit 296.293,000
13 Pipa Galvanis Vent Dia. 63 mm (2") / unit unit 721.804,000
14 Pagar BRC tinggi 120 cm berikut pintu / m¹ m¹ 409.350,000
15 Wall Pipe All Flange Dia. 63 mm (2") / unit unit 368.421,000
16 Wall Pipe All Flange Dia. 90 mm (3") / unit unit 431.889,000
17 Crossing Jalan Aspal Pipa 63 mm (2"), L = 6 m / unit unit 1.561.591,000
18 Pemasangan Water Meter Induk Dia. 2" / unit unit 3.049.936,000
19 Memasang pipa PVC tipe SNI RRJ Ø 1" diameter 32 mm / m¹ m¹ 45.785,000
20 Memasang pipa PVC tipe SNI RRJ Ø 2" diameter 63 mm / m¹ m¹ 106.266,000
21 Memasang pipa PVC tipe SNI RRJ dia 3" diameter 90 mm / m¹ m¹ 218.847,000
22 Memasang pipa PVC tipe SNI RRJ dia 4" diameter 110 mm m¹ 302.750,000
23 Memasang pipa PVC tipe SNI RRJ dia 6" diameter 150 mm m¹ 580.320,000
33 PEMBANGUNAN RUANG KELAS BARU, RUANG GURU, RUANG KEPSEK, DAN LAINNYA m² 3.047.000,00
34 PEMBANGUNAN PERPUSTAKAAN m² 4.359.000,00
35 PEMBANGUNAN RUANG KELAS BERTINGKAT m² 5.581.000,00
36 PEMBANGUNAN SARANA AIR BERSIH DAN SANITASI m² 3.347.000,00
37 GEDUNG NEGARA TIDAK SEDERHANA m² 5.971.000,00
38 REHAB RINGAN GEDUNG NEGARA TIDAK SEDERHANA m² 2.089.850,00
39 REHAB SEDANG GEDUNG NEGARA TIDAK SEDERHANA m² 2.686.950,00
40 REHAB BERAT GEDUNG NEGARA TIDAK SEDERHANA m² 3.881.150,00
41 GEDUNG NEGARA SEDERHANA m² 5.655.000,00
42 REHAB RINGAN GEDUNG NEGARA SEDERHANA m² 1.979.250,00
43 REHAB SEDANG GEDUNG NEGARA SEDERHANA m² 2.544.750,00
44 REHAB BERAT GEDUNG NEGARA SEDERHANA m² 3.675.750,00
45 PAGAR DEPAN GEDUNG NEGARA m' 2.989.000,00
46 PAGAR SAMPING GEDUNG NEGARA m' 2.545.000,00
47 PAGAR BELAKANG GEDUNG NEGARA m' 2.652.000,00
48 RUMAH NEGARA TIPE A m² 6.364.000,00
49 RUMAH NEGARA TIPE B m² 6.647.000,00
50 RUMAH NEGARA TIPE C m² 4.904.000,00
51 PAGAR DEPAN RUMAH NEGARA m' 1.669.000,00
52 PAGAR SAMPING RUMAH NEGARA m' 1.426.000,00
53 PAGAR BELAKANG RUMAH NEGARA m' 1.589.000,00
54 PEMBANGUNAN JALAN RIGID PAVEMENT K.350 T=25Cm m² 930.662,00
55 PEMBANGUNAN TPT JALAN m² 1.240.309,00
56 PEMBANGUNAN TPT FRAME m² 2.381.553,00
57 PENINGKATAN TROTOAR DIATAS BAHU JALAN m² 559.171,00
58 PELEBARAN JALAN m² 397.470,00
59 PEMBANGUNAN JEMBATAN m² 13.121.292,00
60 PENINGKATAN JALAN RIGID PAVEMENT K.350 T=25 Cm m² 758.770,00
61 PENINGKATAN JALAN RIGID PAVEMENT K.500 T=25 Cm m² 791.744,00
62 PENINGKATAN JALAN RIGID PAVEMENT K.350 T=20 Cm m² 631.083,00
63 REHABILITASI JALAN LASTON AC-WC T= 4 CM m² 271.931,00
64 STABILISASI DAN PENGUATAN TEBING POLIMER m² 186.216,00
65 REHABILITASI JEMBATAN m² 5.320.222,00
66 PENGADAAN DAN PEMASANGAN PAPAN PENGENAL RUAS JALAN Unit 3.367.000,00
67 REHABILITASI BENDUNG m' 6.586.500,00
68 REHABILITASI JARINGAN IRIGASI m³ 3.741.449,00
69 PEMBANGUNAN SALURAN DRAINASE m 567.145,00
70 REHABILITASI SALURAN DRAINASE m 341.360,00
71 PEMELIHARAAN SALURAN DRAINASE m 241.000,00
72 PEMBANGUNAN EMBUNG m² 563.425,00
73 PEMBANGUNAN KOLAM RETENSI m² 622.260,00
74 REHABILITASU STATION POMPA BANJIR m² 622.260,00
75 NORMALISASI SUNGAI m³ 135.000,00
76 PEMBANGUNAN PERKUATAN TEBING m³ 2.181.000,00
77 REHABILITASI BANTARAN TANGGUL SUNGAI m 3.857.000,00
78 REHABILITASI SALURAN DRAINASE GORONG-GORONG m 3.631.000,00
79 PEMELIHARAAN PJU TC 1.030.000,00
80 PENINGKATAN PJU LED 100-140 Watt TC 4.832.000,00
81 PENGGANTIAN BOX APP Set 4.237.000,00
82 PENGGANTIAN KOMPONEN BOX APP Set 1.286.000,00
83 PEMASANGAN JARINGAN KABEL BAWAH TANAH PJU m 277.000,00
PEMBANGUNAN TIANG BULAT 7 M, ARMATURE PJU SODIUM 150 WATT, JARINGAN
84 KABEL UDARA, BOX APP DAN BPUJL TC 17.983.000,00
PEMBANGUNAN TIANG BULAT 7 M, ARMATURE LED 60-90 WATT, JARINGAN KABEL
85 TC 18.030.000,00
UDARA, BOX APP DAN BPUJL
86 PEMBANGUNAN TIANG BULAT 7 M, PJU TENAGA SURYA ALL IN ONE 40 WATT TC 23.103.000,00
PEMBANGUNAN TIANG BULAT 3,5 M, ARMATURE LED 12 WATT, JARINGAN KABEL
87 TC 16.020.000,00
UDARA, BOX APP DAN BPUJL
PEMBANGUNAN TIANG OKTAGONAL 9 M, ARMATURE PJU SODIUM 250 WATT TIPE
88 TC 20.575.000,00
COBRA, JARINGAN KABEL UDARA, BOX APP DAN BPUJL
PEMBANGUNAN TIANG OKTAGONAL 9 M, ARMATURE LED 100-140 WATT, JARINGAN
89 TC 22.394.000,00
KABEL UDARA, BOX APP DAN BPUJL
PEMBANGUNAN TIANG 11 M STANG GANDA, ARMATURE PJU SODIUM 250 WATT TIPE
90 TC 43.939.000,00
KEONG, JARINGAN KABEL BAWAH TANAH, BOX APP DAN BPUJL
PEMBANGUNAN TIANG OKTAGONAL 9 M, ARMATURE LED SMART 120 WATT, JARINGAN
91 TC 27.543.000,00
KABEL UDARA, BOX APP DAN BPUJL
92 SUMUR RESAPAN Unit 10.773.000,00
93 INSTALASI PEMANEN AIR HUJAN (IPAH) AM Unit 41.021.000,00
94 INSTALASI PEMANEN AIR HUJAN (IPAH) AB Unit 25.386.000,00
95 POJOK EDUKASI BERSIH SAMPAH (POKASIH) Unit 30.376.000,00
96 TPS3R m' 3.320.000,00
97 BRONCAPTERING Unit 27.134.000,00
98 JARINGAN KOSNTRUKSI PERPIPAAN AIR BERSIH m' 124.465,00
99 SAMBUNGAN RUMAH PERDESAAN Unit 1.530.000,00
100 SAMBUNGAN RUMAH PERKOTAAN Unit 1.656.000,00
101 SAMBUNGAN RUMAH HIBAH AIR MINUM PERDESAAN Unit 2.063.000,00
102 RESERVOIR KAPASITAS 2 m ³ Unit 53.832.000,00
103 RESERVOIR KAPASITAS 5 m ³ Unit 74.544.000,00
104 RESERVOIR KAPASITAS 10 m ³ Unit 104.045.000,00
105 RESERVOIR KAPASITAS 20 m ³ Unit 153.858.000,00
106 MENARA BESI AIR 3M + TANGKI AIR KAP.2000 Lt Unit 25.422.000,00
107 MENARA BESI AIR 3M + TANGKI AIR KAP.2 X 2000 Lt Unit 37.900.000,00
108 MENARA BESI AIR 4M + TANGKI AIR KAP.2000 Lt Unit 27.367.000,00
109 MENARA BESI AIR 4M + TANGKI AIR KAP.2 x 2000 Lt Unit 40.850.000,00
110 MENARA BESI AIR 6M + TANGKI AIR KAP.5000 Lt Unit 47.941.000,00
111 MENARA BESI AIR 6M + TANGKI AIR KAP.2 x 5000 Lt Unit 71.751.000,00
112 MENARA BAJA WF TINGGI 6M + TANGKI AIR KAP.5000 Lt Unit 107.743.000,00
113 MENARA BAJA WF TINGGI 6M + TANGKI AIR KAP.2 x 5000 Lt Unit 152.227.000,00
114 SUMUR DANGKAL 60M Unit 55.631.000,00
115 SUMUR DANGKAL 60M + MENARA AIR 4 M Paket 78.803.000,00
116 SUMUR DANGKAL 60M + JARINGAN PIPA Paket 115.457.000,00
SUMUR DANGKAL 60M + MENARA AIR 4 M + JARINGAN PIPA+ TANGKI AIR KAP.2000 +
117 Paket 135.015.000,00
SR
SUMUR DANGKAL 60M x 2 UNIT + MENARA AIR 4 M + JARINGAN PIPA+ TANGKI AIR
118 Paket 203.904.000,00
KAP.2000
119 SUMUR DANGKAL 70M Paket 74.090.000,00
120 SUMUR DANGKAL 70M + MENARA AIR 4 M Paket 93.412.000,00
121 SUMUR DANGKAL 70M + JARINGAN PIPA Paket 125.535.000,00
SUMUR DANGKAL 70M + MENARA AIR 4 M + JARINGAN PIPA+ TANGKI AIR KAP.2000 +
122 Paket 154.075.000,00
SR
SUMUR DANGKAL 70M x 2 UNIT + MENARA AIR 4 M + JARINGAN PIPA+ TANGKI AIR
123 Paket 198.620.000,00
KAP.2000
124 SUMUR DANGKAL 80M Unit 84.949.000,00
125 SUMUR DANGKAL 80M + MENARA AIR 4 M Paket 104.271.000,00
126 SUMUR DANGKAL 80M + JARINGAN PIPA Paket 140.495.000,00
SUMUR DANGKAL 80M + MENARA AIR 4 M + JARINGAN PIPA+ TANGKI AIR KAP.2000 +
127 Paket 179.780.000,00
SR
SUMUR DANGKAL 80M + MENARA AIR 4 M + JARINGAN PIPA+ TANGKI AIR KAP.2000 +
128 Paket 199.945.000,00
SR DAK
129 SUMUR DALAM 100 M Unit 199.989.000,00
130 SUMUR DALAM 100 M + MENARA AIR 6 M TANGKI AIR KAP.5000 Lt Paket 233.417.000,00
131 SUMUR DALAM 100 M + JARINGAN Paket 261.551.000,00
132 SUMUR DANGKAL 100M + MENARA+JARINGAN PIPA+SR Paket 604.911.000,00
133 SUMUR DANGKAL 100M + RESERVOIR 20 M3+JARINGAN PIPA+SR Paket 666.191.000,00
134 SUMUR DALAM 150 M Unit 305.770.000,00
135 SUMUR DALAM 150M + MENARA+JARINGAN PIPA+SR Paket 755.406.000,00
136 SUMUR DALAM 150M + RESEVOAR 20 M3+PEMAGARAN+JARINGAN PIPA+SR Paket 739.678.000,00
137 PEMBUATAN BANK SAMPAH TEMATIK unit 81.051.000,00
138 INSTALASI PENGOLAHAN LUMPUR TINJA (IPLT) m² 5.682.000,00
REKAP LAMPIRAN III ASB NON KONSTRUKSI
16 Sosialisasi Tipe Y.8 Sosialisasi di Kantor Pemda selama satu hari, Narasumber internal, Peserta PNS Peserta 78.000,00
Sosialisasi di Lingkungan Kantor Pemda selama satu hari, Narasumber Praktisi,
17 Sosialisasi Tipe X.8 Peserta 336.000,00
Peserta Non PNS
Sosialisasi di Lingkungan Kantor Pemda selama satu hari, Narasumber Praktisi,
18 Sosialisasi Tipe X.9 Peserta 282.000,00
Peserta Non PNS
Pengukuran dan Pemeriksaan Faktor Risiko Penyakit Tidak
19 Peserta 36.528,00
Menular Penduduk Usia 15 - 59 tahun
20 Peningkatan Perlindungan Tanaman Padi/Jagung (Handsprayer) Kelompok 6.250.000,00
21 Pengembangan usaha budidaya Ternak Domba Kelompok 35.255.000,00
22 Pengembangan Budidaya jeruk siam madu Kelompok 26.640.000,00
23 Pengembangan usaha budidaya Itik Dewasa petelur Kelompok 31.372.000,00
24 Pengembangan Budidaya padi inbrida Kelompok 10.775.000,00
25 Pengembangan Budidaya Jagung hibrida Kelompok 14.470.500,00
Peningkatan alat pemupukan dan pengendalian OPT Perkebunan
26 Kelompok 8.800.000,00
(Mistblower)
Peremajaan dan perluasan kopi (bibit kopi, pupuk, APK, obat-
27 Ha 13.350.000,00
obatan)
Penunjang peningkatan produksi sapi perah (Karpet kandang,
28 Kelompok 20.350.000,00
Milkcan)
Fasilitasi pengobatan cacing pada Ternak Domba dan ruminansia
29 Kelompok 2.206.600,00
kecil
30 Fasilitasi pengobatan cacing pada Ternak Sapi dan kerbau Kelompok 2.106.500,00
31 Fasilitasi Pengendalian OPT Kopi set 110.000,00
32 Fasilitasi Pengendalian OPT Teh Set 105.000,00
33 Bahan Baku Praktek Olahan hasil Peternakan kelompok 1.279.800,00
34 Sarana Pengolahan Kompos Kelompok 16.992.400,00
35 Sarana Pengolahan Hasil Peternakan Kelompok 21.580.650,00
36 Pelatihan dan Sosialisasi masyarakat Peserta 433.213,57
37 Pembentukan dan Pembinaan Relawan Pemadam Kebakaran Peserta 3.364.350,00
38 Pengadaan Meubelair Sekolah Lembaga 41.000.000,00
39 Pengadaan Meubelair PKBM Lembaga 16.507.650,00
40 Pengadaan Alat Peraga olahraga PAUD Lembaga 6.376.600,00
41 Penyediaan meubelair di lembaga PAUD Lembaga 8.940.000,00
42 Pengadaan Buku Buku dan Alat Tulis PAUD Lembaga 7.386.000,00
43 Pengadaan Komputer dan printer untuk lembaga PAUD Lembaga 7.426.768,00
Pengadaan Media Interaktif untuk Meningkatkan Minat Literasi
44 Lembaga 110.660.000,00
di Perpustakaan SMP
Pengadaan Media Bahan Ajar Digital Interaktif dalam rangka
45 Lembaga 58.595.000,00
proses penguatan belajar mengajar jenjang PAUD
Pengadaan Media Inovasi Kreatifitas Guru dan Siswa Jenjang
46 Lembaga 207.740.000,00
SMP
47 Pengadaan Media Interaktif Pembelajaran Berbasis Digital Lembaga 207.740.000,00
Meubelair Indoor untuk Anak Usia Dini Yang Aktif Bermain dan
48 Lembaga 37.499.780,00
Belajar
Furniture Kelas Elegant Design untuk Peningkatan Keaktifan
49 Lembaga 64.085.720,00
Belajar Siswa SMP
50 Pengadaan Peralatan Media Pendidikan Lembaga 44.934.800,00
Pengadaan peralatan teknologi, informasi dan komunikasi (TIK)
51 Lembaga 322.507.200,00
untuk SMP
52 Pengadaan Peralatan praktek lembaga kursus Lembaga 25.230.980,00
53 Pengadaan peralatan Laboratorium Komputer Lembaga 348.604.368,00
Pengadaan peralatan teknologi, informasi dan komunikasi (TIK)
54 Lembaga 208.185.850,00
untuk PKBM
55 Sosialisasi Pemahaman dan Pengetahuan Perkoperasian Peserta 555.000,00
56 Kemitraan Usaha bagi UMKM Peserta 2.817.000,00
57 Pelatihan Kewirausahaan bagi UMKM Peserta 942.857,14
58 Pendampingan Usaha bagi UMKM Peserta 1.818.000,00
59 Inkubasi Bisnis bagi UMKM Peserta 3.457.000,00
60 Penyelenggaraan Gelar Produk UMKM Peserta 17.430.000,00
61 Pelatihan Ekonomi Kreatif Peserta 927.230,00
62 Pelatihan Tatakelola Destinasi Pariwisata Peserta 927.230,00
63 Pengadaan Sarana Prasarana Kesenian ( Pengadaan Matras) Kelompok 25.025.000,00
Pelatihan Sumber Daya Manusia Kesenian Tradisional sesuai
64 Peserta 944.230,00
dengan kebutuhan dan Tuntutan
Fasilitasi Pagelaran Seni budaya bagi Kelompok seni yang
65 Kegiatan 62.098.450,00
berkontribusi dalam pemajuan kebudayaan
Bimbingan Teknis (Bimtek) Pengelolaan Sampah dan Bank
66 Peserta 445.960,00
Sampah
67 Bimbingan Teknis Konservasi Sumber Daya Air (KSDA) Peserta 475.400,00
Bimbingan Teknis Pengolahan Limbah Peternakan ( Rumah
68 Kelompok 28.363.715,50
Budidaya Cacing)
Sosialisasi dan Penanaman Pohon Multy Purpose Tree Species
69 Peserta 51.540,00
(MPTS) Buah-buahan
Dukungan Bantuan Pohon Multy Purpose Tree Species (MPTS)
70 Peserta 14.540,00
Kayu-kayuan
71 Sosialisasi Gerakan Penanaman Peserta 217.160,00
72 Sosialiasasi Pengendalian Pencemaran Lingkungan Peserta 343.800,00
73 Pengembangan/Pembangunan Bank Sampah Tematik Unit 32.979.500,00
74 Pembuatan Persemaian Unit 49.974.150,00
75 PENGOLAHAN HASIL PERTANIAN Peserta 5.207.539,50
76 KONVEKSI Peserta 5.373.052,00
77 PENGOLAHAN SAMPAH PLASTIK Peserta 5.357.781,00
78 PENGOLAHAN KOPI Peserta 6.049.036,00
79 BARISTA Peserta 5.923.559,50
80 SOUND SYSTEM Peserta 6.150.591,25
81 DIGITAL PRINTING Peserta 5.143.977,00
82 BIMBINGAN JABATAN Peserta 408.439,00
83 PENYULUHAN BIMBINGAN JABATAN Peserta 385.689,00
84 TEMU KONSULTASI PENGELOLA BKK Peserta 705.064,00
85 Pelatihan Montir Sepeda Motor Unit Pelatihan Keliling Peserta 4.833.990,00
86 Pelatihan Las Listrik Unit Pelatihan Keliling Peserta 5.191.700,00
87 Pelatihan Menjahit Unit Pelatihan Keliling Peserta 3.444.290,00
88 Pelatihan Service HP Unit Pelatihan Keliling Peserta 3.550.865,00
89 Pelatihan Tata Boga Unit Pelatihan Keliling Peserta 3.458.790,00
90 Pelatihan Tata Rias Unit Pelatihan Keliling Peserta 3.681.627,50
91 Pelatihan Sablon Unit Pelatihan Keliling Peserta 3.559.055,00
92 Pelatihan Service Komputer Unit Pelatihan Keliling Peserta 3.702.070,00
93 Pelatihan Mebeuler Unit Pelatihan Keliling Peserta 5.053.585,00
94 Pelatihan Daur Ulang Sampah Unit Pelatihan Keliling Peserta 3.428.815,00
95 Pelatihan Design Grafis Unit Pelatihan Keliling Peserta 3.570.690,00
96 Bahasa Jepang Peserta 6.145.800,00
97 Bahasa Korea Peserta 6.145.800,00
98 Pelatihan Kewirausahaan Muda Peserta 647.250,00
Pengambangan Usaha Pangan Masyarakat (PUPM) melalui Toko
99 Kelompok 32.288.800,00
Tani Indonesia (TTI)
100 Pekarangan Pangan Lestari (P2L) Konvensional Kelompok 34.237.400,00
101 Pengembangan Industri pangan lokal (PIPL) Kelompok 33.350.000,00
102 Pengembangan Budidaya Ikan Nila Kelompok 19.000.000,00
103 Pengembangan Budidaya Ikan Hias Kelompok 17.545.000,00
104 Pengembangan Budidaya Ikan Mas Kelompok 24.000.000,00
105 Pengembangan Budidaya Ikan Lele Kelompok 12.600.000,00
106 Sarana dan Prasarana Pengolahan Pemindangan Ikan Kelompok 9.085.000,00
Sarana dan Prasarana Pengolahan Ikan abon, nugget, bakso,
107 Kelompok 9.360.500,00
siomay, otak-otak ikan
108 Bimtek Diversifikasi Olahan Ikan Peserta 326.150,00
109 Pemberian Bantuan Ternak Domba bagi KUBE KFM Peserta 23.050.000,00
110 Pemberian Bantuan Warungan bagi KUBE KFM Peserta 15.650.000,00
111 Pemberian Bantuan Beras bagi KUBE KFM Peserta 15.000.000,00
112 Pemberian Bantuan Konveksi bagi KUBE KFM Peserta 16.930.000,00
113 Pemberian Bantuan Ternak Domba bagi KUBE WRSE Peserta 23.050.000,00
114 Pemberian Bantuan Warungan bagi KUBE WRSE Peserta 15.650.000,00
115 Pemberian Bantuan Olah Pangan bagi KUBE WRSE Peserta 15.664.800,00
116 Pemberian Bantuan Bagi KUBE Beras Peserta 15.000.000,00
117 Pemberian Bantuan Bagi KUBE Konveksi Peserta 16.930.000,00
Pemberian Bantuan UEP Ternak Domba bagi Orang Tua
118 Peserta 6.000.000,00
Penyandang Disabilitas
Pemberian Bantuan UEP Warungan bagi Orang Tua Penyandang
119 Peserta 3.326.500,00
Disabilitas
120 Pemberian Bantuan Bagi UEP Olah Pangan Gorengan Peserta 3.989.200,00
121 Pemberian bantuan UEP Ternak Domba Peserta 6.000.000,00
122 Pengadaan bahan baku bagi UEP Warungan Peserta 3.040.200,00
123 Pemberian Bantuan Bagi UEP Usaha Olah Pangan Kue Peserta 3.851.600,00
124 Pemberian bantuan UEP Ternak Domba Peserta 6.000.000,00
125 Pengadaan bahan baku bagi UEP Warungan Peserta 2.980.000,00
126 Pemberian Bantuan Bagi UEP Olah Pangan Kue Peserta 4.094.320,00
127 Pemberian bantuan UEP Ternak Domba Peserta 6.900.000,00
128 Pemberian Bantuan Bagi UEP Mesin jahit Peserta 3.386.000,00
Pemberian Bantuan Bagi Orang Tua Balita Terlantar Usaha
129 Peserta 3.040.200,00
Warungan
Pemberian Bantuan Bagi Orang Tua Balita Terlantar Usaha Olah
130 Peserta 3.635.000,00
Pangan Gorengan
Pemberian Bantuan Usaha Olah Pangan Kue Bagi Orang Tua
131 Peserta 2.805.550,00
Balita Terlantar
Pemberian Bantuan Ternak Domba Bagi Orang Tua Balita
132 Peserta 6.000.000,00
Terlantar
133 Pengadaan bahan baku Warungan bagi LUP Peserta 2.978.000,00
134 Pengadaan bahan baku Olah Pangan Gorengan bagi LUP Peserta 4.094.320,00
135 Pengadaan bahan baku Olah Pangan Kue bagi LUP Peserta 3.389.400,00
136 Pemberian bantuan Ternak Domba bagi LUP Peserta 6.900.000,00
137 Pemberian Bantuan Jaminan Hidup Bagi Lansia tanpa Bimsos Peserta 2.500.000,00
138 Pemberian Bantuan Jaminan Hidup Bagi Lansia tanpa Bimsos Peserta 2.059.750,00
Pemberian Bantuan Stimulan UEP Olah pangan Kue bagi Eks.
139 Peserta 3.422.400,00
Gelandangan dan Pengemis (Gepeng)
Pemberian Bantuan Stimulan UEP Warungan bagi Gelandangan
140 Peserta 2.978.200,00
dan Pengemis (Gepeng)
Pemberian Bantuan Stimulan UEP Ternak Domba Bagi Eks.
141 Peserta 6.900.000,00
Narkoba
142 Pemberian Bantuan Stimulan UEP Warungan Bagi Eks. Narkoba Peserta 2.957.200,00
Pemberian Bantuan Stimulan UEP Ternak Domba Bagi Eks.
143 Peserta 6.900.000,00
Warga Binaan Pemasyarakatan
Pemberian Bantuan Stimulan UEP Warungan Bagi Eks. Warga
144 Peserta 2.979.200,00
Binaan Pemasyarakatan
145 Bimtek Rumah Siap Bangun Pasca Bencana Peserta 4.682.281,25
146 Bimtek Psikososial Trauma Healing Peserta 1.999.412,50
Bimbingan Teknik Pemberdayaan Masyarakat Pembentukan
147 Peserta 3.420.861,25
Relawan Desa Tangguh Bencana
BERDASARKAN PERATURAN MENTERI PUPR NO 24 TAHUN 2008 Tentang
“PEDOMAN PEMELIHARAAN DAN PERAWATAN BANGUNAN GEDUNG”
D. TINGKAT KERUSAKAN
a. Kerusakan ringan
1) Kerusakan ringan adalah kerusakan terutama pada komponen nonstruktural,
seperti penutup atap, langit-langit, penutup lantai, dan dinding pengisi.
2) Perawatan untuk tingkat kerusakan ringan, biayanya maksimum adalah
sebesar 35% dari harga satuan tertinggi pembangunan bangunan gedung
baru yang berlaku, untuk tipe/klas dan lokasi yang sama.
b. Kerusakan sedang
1) Kerusakan sedang adalah kerusakan pada sebagian komponen pada sebagian
komponen non-struktural, dan atau komponen struktural seperti struktur
atap, lantai, dan lain-lain.
2) Perawatan untuk tingkat kerusakan sedang, biayanya maksimum adalah
sebesar 45% dari harga satuan tertinggi pembangunan bangunan gedung
baru yang berlaku, untuk tipe/klas dan lokasi yang sama.
c. Kerusakan berat
1) Kerusakan berat adalah kerusakan pada sebagian besar komponen bangunan,
baik struktural maupun non-struktural yang apabila setelah diperbaiki masih
dapat berfungsi dengan baik sebagaimana mestinya.
2) Biayanya maksimum adalah sebesar 65% dari harga satuan tertinggi
pembangunan bangunan gedung baru yang berlaku, untuk tipe/klas dan
lokasi yang sama.
LAMPIRAN I PERATURAN BUPATI BANDUNG
1
4 Pembuatan pagar sementara kawat berduri tinggi 1,8 m / m²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,2000 133.000 26.600,00
Tukang L.02 OH 0,4000 157.500 63.000,00
Kepala Tukang L.03 OH 0,0400 172.200 6.888,00
Mandor L.04 OH 0,0100 181.300 1.813,00
Jumlah Tenaga Kerja (A) 98.301,00
B BAHAN
Dolken dia 8 s/d 10 cm M.29 b btg 1,0000 35.000 35.000,00
Kawat duri M.68 c kg 25,0000 7.750 193.750,00
Semen Portland M.15 a kg 2,0000 1.450 2.900,00
Pasir Beton M.14 m³ 0,0050 311.000 1.555,00
Kerikil M.12 m³ 0,0090 275.000 2.475,00
Paku biasa 2"-5" M.71 a kg 0,0600 17.000 1.020,00
Jumlah Harga Bahan (B) 236.700,00
C PERALATAN
2
8 Pembuatan gudang semen dan peralatan /m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 1,0000 133.000 133.000,00
Tukang Kayu L.03b OH 2,0000 157.500 315.000,00
Kepala Tukang L.03 OH 0,2000 172.200 34.440,00
Mandor L.04 OH 0,0500 181.300 9.065,00
Jumlah Tenaga Kerja (A) 491.505,00
B BAHAN
Dolken dia 8 s/d 10 cm M.29 b btg 1,7000 35.000 59.500,00
Kayu balok, kaso-kaso Klas IV M.35 b m³ 0,2100 1.800.000 378.000,00
Paku biasa 2"-5" M.71 a kg 0,3000 17.000 5.100,00
Semen Portland M.15 a Zak 10,5000 1.450 15.225,00
Pasir Beton M.14 m³ 0,0300 311.000 9.330,00
Kerikil M.12 m³ 0,0500 275.000 13.750,00
Seng gelombang 3x6 ft BJLS 20 (0,2 mm) M.88 a Lbr 1,5000 50.000 75.000,00
Seng plat 3x6 ft BJLS 20 (0,2 mm) M.90 a Lbr 0,2500 40.900 10.225,00
Jumlah Harga Bahan (B) 566.130,00
C PERALATAN
3
13 Pekerjaan Pembuatan Jalan sementara / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 1,0000 133.000 133.000,00
Mandor L.04 OH 0,0050 181.300 906,50
Jumlah Tenaga Kerja (A) 133.906,50
B BAHAN
Batu belah pondasi M.06 a m³ 0,1500 265.000 39.750,00
Batu Pecah - 5 - 7 Cm M.12 e m³ 0,0900 155.000 13.950,00
Pasir Pasang M.14 b m³ 0,0100 250.000 2.500,00
Jumlah Harga Bahan (B) 56.200,00
C PERALATAN
4
19 Galian tanah Lumpur sedalam 1 meter / m³
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 1,2000 133.000 159.600,00
Mandor L.04 OH 0,0450 181.300 8.158,50
Jumlah Tenaga Kerja (A) 167.758,50
B BAHAN
5
25 Urugan Sirtu Padat / m³
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,2500 133.000 33.250,00
Mandor L.04 OH 0,0250 181.300 4.532,50
Jumlah Tenaga Kerja (A) 37.782,50
B BAHAN
Sirtu M.16 m³ 1,2000 125.000 150.000,00
Jumlah Harga Bahan (B) 150.000,00
C PERALATAN
6
30 Analisa : Galian Perkerasan berbutir / m³
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OJ 1,5000 19.000 28.500,00
Mandor L.04 OJ 0,2500 25.900 6.475,00
Jumlah Tenaga Kerja (A) 34.975,00
B BAHAN
7
35 Analisa : Galian Struktur dengan kedalaman 4 - 6 meter / m³
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OJ 0,0460 19.000 874,00
Mandor L.04 OJ 0,0040 25.900 103,60
Jumlah Tenaga Kerja (A) 977,60
B BAHAN
Timbunan Pilihan /urugan Porous M.08 m³ - 246.000 -
Bahan Pengaman Tebing galian m.br-1 ls 0,6000 1.250.000 750.000,00
Jumlah Harga Bahan (B) 750.000,00
C PERALATAN
Excavator 80-140 Hp E.10 jam 0,0040 368.200 1.472,80
Dump Truck 6-8 M3 E.09 jam 0,0330 314.200 10.368,60
Alat Bantu ls 0,0100 682.400 6.824,00
Jumlah Harga Alat (C) 18.665,40
D Jumlah ( A + B + C ) 769.643,00
E Overhead & Profit 15% xD 115.446,45
F Harga Satuan Pekerjaan (D + E) 885.089,45
G Dibulatkan 885.089,00
PEKERJAAN PONDASI
1 Pemasangan pondasi batu kosong - aanstamping / m³
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,7800 133.000 103.740,00
Tukang Batu L.03a OH 0,3900 157.500 61.425,00
Kepala Tukang Batu L.03aa OH 0,0390 172.200 6.715,80
Mandor L.04 OH 0,0390 181.300 7.070,70
Jumlah Tenaga Kerja (A) 178.951,50
B BAHAN
Batu belah pondasi M.06 a m³ 1,2000 265.000 318.000,00
Pasir Urug M.14 d m³ 0,4320 160.000 69.120,00
Jumlah Harga Bahan (B) 387.120,00
C PERALATAN
8
4 Pemasangan pondasi batu belah campuran 1 PC : 5 PP / m³
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 1,5000 133.000 199.500,00
Tukang Batu L.03a OH 0,7500 157.500 118.125,00
Kepala Tukang Batu L.03aa OH 0,0750 172.200 12.915,00
Mandor L.04 OH 0,0750 181.300 13.597,50
Jumlah Tenaga Kerja (A) 344.137,50
B BAHAN
Batu belah pondasi M.06 a m³ 1,2000 265.000 318.000,00
Semen Portland M.15 a kg 136,0000 1.450 197.200,00
Pasir Pasang M.14 b m³ 0,5440 250.000 136.000,00
Jumlah Harga Bahan (B) 651.200,00
C PERALATAN
9
8 Pemasangan pondasi sumuran diameter 100 cm / m³
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 2,4000 133.000 319.200,00
Tukang Batu L.03a OH 0,8000 157.500 126.000,00
Kepala Tukang Batu L.03aa OH 0,0800 172.200 13.776,00
Mandor L.04 OH 0,0119 181.300 2.157,47
Jumlah Tenaga Kerja (A) 461.133,47
B BAHAN
Batu belah pondasi M.06 a m³ 0,4500 265.000 119.250,00
Semen Portland M.15 a kg 194,0000 1.450 281.300,00
Pasir Beton M.14 m³ 0,3120 311.000 97.032,00
Kerikil M.12 m³ 0,4680 275.000 128.700,00
Jumlah Harga Bahan (B) 626.282,00
C PERALATAN
PEKERJAAN STRUKTUR
STRUKTUR BETON
1 Pekerjaan Beton K 100 - f'c 7,4 Mpa LANTAI KERJA / m³
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 1,3200 133.000 175.560,00
Tukang Batu L.03a OH 0,2200 157.500 34.650,00
Kepala Tukang Batu L.03aa OH 0,0220 172.200 3.788,40
Mandor L.04 OH 0,0132 181.300 2.393,16
Jumlah Tenaga Kerja (A) 216.391,56
B BAHAN
Semen Portland 50 kg M.15 Zak 4,9400 67.000 330.980,00
Pasir Beton M.14 m³ 0,5880 311.000 182.868,00
Kerikil M.12 m³ 0,7550 275.000 207.625,00
Jumlah Harga Bahan (B) 721.473,00
C PERALATAN
10
4 Pekerjaan Beton K 125 - f'c 9,8 Mpa / m³
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 1,6500 133.000 219.450,00
Tukang Batu L.03a OH 0,2750 157.500 43.312,50
Kepala Tukang Batu L.03aa OH 0,0275 172.200 4.735,50
Mandor L.04 OH 0,0825 181.300 14.957,25
Jumlah Tenaga Kerja (A) 282.455,25
B BAHAN
Semen Portland 50 kg M.15 Zak 5,5200 67.000 369.840,00
Pasir Beton M.14 m³ 0,5914 311.000 183.934,29
Kerikil M.12 m³ 0,7496 275.000 206.148,15
Jumlah Harga Bahan (B) 759.922,43
C PERALATAN
11
9 Pekerjaan Beton K 250 - f'c 21,7 Mpa / m³
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 1,6500 133.000 219.450,00
Tukang Batu L.03a OH 0,2750 157.500 43.312,50
Kepala Tukang Batu L.03aa OH 0,0275 172.200 4.735,50
Mandor L.04 OH 0,0825 181.300 14.957,25
Jumlah Tenaga Kerja (A) 282.455,25
B BAHAN
Semen Portland 50 kg M.15 Zak 7,6800 67.000 514.560,00
Pasir Beton M.14 m³ 0,4943 311.000 153.722,86
Kerikil M.12 m³ 0,7696 275.000 211.648,15
Jumlah Harga Bahan (B) 879.931,01
C PERALATAN
12
14 Pekerjaan Beton Kedap air dengan STROROX-100 / m³
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 2,1000 133.000 279.300,00
Tukang Batu L.03a OH 0,3500 157.500 55.125,00
Kepala Tukang Batu L.03aa OH 0,0350 172.200 6.027,00
Mandor L.04 OH 0,1050 181.300 19.036,50
Jumlah Tenaga Kerja (A) 359.488,50
B BAHAN
Semen Portland 50 kg M.15 Zak 8,0000 67.000 536.000,00
Pasir Beton M.14 m³ 0,4800 311.000 149.280,00
Kerikil M.12 m³ 0,8000 275.000 220.000,00
Aditif beton M.04 kg 1,2000 48.000 57.600,00
Jumlah Harga Bahan (B) 962.880,00
C PERALATAN
13
19 Pekerjaan Beton K 125 - f'c 9,8 Mpa menggunakan molen / m³
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 1,3230 133.000 175.959,00
Tukang Batu L.03a OH 0,1890 157.500 29.767,50
Kepala Tukang Batu L.03aa OH 0,0190 172.200 3.271,80
Mandor L.04 OH 0,1320 181.300 23.931,60
Jumlah Tenaga Kerja (A) 232.929,90
B BAHAN
Semen Portland 50 kg M.15 Zak 5,5200 67.000 369.840,00
Pasir Beton M.14 m³ 0,5914 311.000 183.934,29
Kerikil M.12 m³ 0,7496 275.000 206.148,15
Jumlah Harga Bahan (B) 759.922,43
C PERALATAN
Concrete Mixer 0.3-0.6 M3 E.06 jam 0,2500 88.500 22.125,00
Jumlah Harga Alat (C) 22.125,00
D Jumlah ( A + B + C ) 1.014.977,33
E Overhead & Profit 15% xD 152.246,60
F Harga Satuan Pekerjaan (D + E) 1.167.223,93
G Dibulatkan 1.167.223,00
14
24 Pekerjaan Beton K 250 - f'c 21,7 Mpa menggunakan molen / m³
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 1,3230 133.000 175.959,00
Tukang Batu L.03a OH 0,1890 157.500 29.767,50
Kepala Tukang Batu L.03aa OH 0,0190 172.200 3.271,80
Mandor L.04 OH 0,1320 181.300 23.931,60
Jumlah Tenaga Kerja (A) 232.929,90
B BAHAN
Semen Portland 50 kg M.15 Zak 7,6800 67.000 514.560,00
Pasir Beton M.14 m³ 0,5052 311.000 157.112,59
Kerikil M.12 m³ 0,7696 275.000 211.648,15
Jumlah Harga Bahan (B) 883.320,74
C PERALATAN
Concrete Mixer 0.3-0.6 M3 E.06 jam 0,2500 88.500 22.125,00
Jumlah Harga Alat (C) 22.125,00
D Jumlah ( A + B + C ) 1.138.375,64
E Overhead & Profit 15% xD 170.756,35
F Harga Satuan Pekerjaan (D + E) 1.309.131,99
G Dibulatkan 1.309.131,00
15
29 Pemadatan beton menggunakan Vibrator / m³
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,2500 133.000 33.250,00
Mandor L.04 OH 0,0250 181.300 4.532,50
Jumlah Tenaga Kerja (A) 37.782,50
B BAHAN
16
34 Pekerjaan Bekisting Sloof / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,5200 133.000 69.160,00
Tukang Kayu L.03b OH 0,2600 157.500 40.950,00
Kepala Tukang L.03 OH 0,0260 172.200 4.477,20
Mandor L.04 OH 0,0260 181.300 4.713,80
Jumlah Tenaga Kerja (A) 119.301,00
B BAHAN
Kayu balok, kaso-kaso Klas IV M.35 b m³ 0,0450 1.800.000 81.000,00
Paku biasa 2"-5" M.71 a kg 0,3000 17.000 5.100,00
Minyak Bekisting M.129 Ltr 0,1000 22.500 2.250,00
Jumlah Harga Bahan (B) 88.350,00
C PERALATAN
17
38 Pekerjaan Bekisting Dinding / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,6600 133.000 87.780,00
Tukang Kayu L.03b OH 0,3300 157.500 51.975,00
Kepala Tukang L.03 OH 0,0330 172.200 5.682,60
Mandor L.04 OH 0,0330 181.300 5.982,90
Jumlah Tenaga Kerja (A) 151.420,50
B BAHAN
Kayu balok, kaso-kaso Klas IV M.35 b m³ 0,0300 1.800.000 54.000,00
Paku biasa 2"-5" M.71 a kg 0,4000 17.000 6.800,00
Minyak Bekisting M.129 Ltr 0,2000 22.500 4.500,00
Kayu balok, kaso-kaso Klas III M.34 a m³ 0,0200 3.000.000 60.000,00
Multiplek tebal 9 mm M 39 d Lbr 0,3500 187.550 65.642,50
Dolken dia 5 s/d 7 cm M.29 a btg 4,0000 13.700 54.800,00
Jumlah Harga Bahan (B) 245.742,50
C PERALATAN
Specer- Penjaga jarak bekisting T.09 3,0000 3.000 9.000,00
Jumlah Harga Alat (C) 9.000,00
D Jumlah ( A + B + C ) 406.163,00
E Overhead & Profit 15% xD 60.924,45
F Harga Satuan Pekerjaan (D + E) 467.087,45
G Dibulatkan 467.087,00
18
42 Pekerjaan Sloof Beton Bertulang ( 200 kg besi + Bekisting) / m ³
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 5,6500 133.000 751.450,00
Tukang Batu L.03a OH 0,2750 157.500 43.312,50
Tukang Besi L.03c OH 1,4000 157.500 220.500,00
Tukang Kayu L.03b OH 1,5600 157.500 245.700,00
Kepala Tukang L.03 OH 0,3230 172.200 55.620,60
Mandor L.04 OH 0,2830 181.300 51.307,90
Jumlah Tenaga Kerja (A) 1.367.891,00
B BAHAN
Kayu papan-reng Klas IV M.35 c m³ 0,2700 2.500.000 675.000,00
Paku biasa 2"-5" M.71 a kg 2,0000 17.000 34.000,00
Multiplek tebal 9 mm M 39 d Lbr 2,8000 187.550 525.140,00
Baja Polos U-30 - 32 M.55 d kg 210,0000 13.500 2.835.000,00
Kawat Beton M.68 Kg 3,0000 28.000 84.000,00
Pasir Beton M.14 m³ 0,5400 311.000 167.940,00
Kerikil M.12 m³ 0,8100 275.000 222.750,00
Semen Portland M.15 a kg 336,0000 1.450 487.200,00
Minyak Bekisting M.129 Ltr 0,6000 22.500 13.500,00
Jumlah Harga Bahan (B) 5.044.530,00
C PERALATAN
19
45 Pekerjaan Kolom Beton Bertulang ( 300 kg besi + Bekisting) / m ³
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 7,0500 133.000 937.650,00
Tukang Batu L.03a OH 0,2750 157.500 43.312,50
Tukang Besi L.03c OH 2,1000 157.500 330.750,00
Tukang Kayu L.03b OH 1,6500 157.500 259.875,00
Kepala Tukang L.03 OH 0,4030 172.200 69.396,60
Mandor L.04 OH 0,3530 181.300 63.998,90
Jumlah Tenaga Kerja (A) 1.704.983,00
B BAHAN
Kayu papan-reng Klas IV M.35 c m³ 0,4000 2.500.000 1.000.000,00
Kayu balok, kaso-kaso Klas IV M.35 b m³ 0,1500 1.800.000 270.000,00
Paku biasa 2"-5" M.71 a kg 4,0000 17.000 68.000,00
Multiplek tebal 9 mm M 39 d Lbr 3,5000 187.550 656.425,00
Baja Polos U-30 - 32 M.55 d kg 315,0000 13.500 4.252.500,00
Kawat Beton M.68 Kg 4,5000 28.000 126.000,00
Pasir Beton M.14 m³ 0,5400 311.000 167.940,00
Kerikil M.12 m³ 0,8100 275.000 222.750,00
Semen Portland M.15 a kg 336,0000 1.450 487.200,00
Dolken dia 5 s/d 7 cm M.29 a btg 20,0000 13.700 274.000,00
Minyak Bekisting M.129 Ltr 2,0000 22.500 45.000,00
Jumlah Harga Bahan (B) 7.569.815,00
C PERALATAN
20
48 Pekerjaan Dinding Beton Bertulang ( 200 kg besi + Bekisting) / m ³
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 5,6500 133.000 751.450,00
Tukang Batu L.03a OH 0,2750 157.500 43.312,50
Tukang Besi L.03c OH 1,4000 157.500 220.500,00
Tukang Kayu L.03b OH 1,5600 157.500 245.700,00
Kepala Tukang L.03 OH 0,3230 172.200 55.620,60
Mandor L.04 OH 0,2830 181.300 51.307,90
Jumlah Tenaga Kerja (A) 1.367.891,00
B BAHAN
Kayu papan-reng Klas IV M.35 c m³ 0,2500 2.500.000 625.000,00
Kayu balok, kaso-kaso Klas IV M.35 b m³ 0,1050 1.800.000 189.000,00
Paku biasa 2"-5" M.71 a kg 3,0000 17.000 51.000,00
Multiplek tebal 9 mm M 39 d Lbr 2,5000 187.550 468.875,00
Baja Polos U-30 - 32 M.55 d kg 210,0000 13.500 2.835.000,00
Kawat Beton M.68 Kg 3,0000 28.000 84.000,00
Pasir Beton M.14 m³ 0,5400 311.000 167.940,00
Kerikil M.12 m³ 0,8100 275.000 222.750,00
Semen Portland M.15 a kg 336,0000 1.450 487.200,00
Dolken dia 5 s/d 7 cm M.29 a btg 24,0000 13.700 328.800,00
Minyak Bekisting M.129 Ltr 1,2000 22.500 27.000,00
Jumlah Harga Bahan (B) 5.486.565,00
C PERALATAN
21
52 Pekerjaan Beton K 500 - f'c 41,5 Mpa Ready Mixed / m ³
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 1,0000 133.000 133.000,00
Tukang Batu L.03a OH 0,2500 157.500 39.375,00
Kepala Tukang L.03 OH 0,0250 172.200 4.305,00
Mandor L.04 OH 0,1000 181.300 18.130,00
Jumlah Tenaga Kerja (A) 194.810,00
B BAHAN
Beton Ready Mixed - K 500 ( NFA ) M.09 n m³ 1,0200 1.222.100 1.246.542,00
Jumlah Harga Bahan (B) 1.246.542,00
C PERALATAN
Concrete Pump E.28 jam 0,1200 883.800 106.056,00
Jumlah Harga Alat (C) 106.056,00
D Jumlah ( A + B + C ) 1.547.408,00
E Overhead & Profit 15% xD 232.111,20
F Harga Satuan Pekerjaan (D + E) 1.779.519,20
G Dibulatkan 1.779.519,00
D Jumlah ( A + B + C ) 87.749,67
E Overhead & Profit 15% xD 13.162,45
F Harga Satuan Pekerjaan (D + E) 100.912,13
G Dibulatkan 100.912,00
22
4 Pekerjaan Pengelasan 10 CM dengan Las Listrik
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,0400 133.000 5.320,00
Tukang Besi L.03c OH 0,0200 157.500 3.150,00
Kepala Tukang Besi L.03ab OH 0,0020 172.200 344,40
Mandor L.04 OH 0,0020 181.300 362,60
Jumlah Tenaga Kerja (A) 9.177,00
B BAHAN
Kawat Las listrik M.69 a kg 0,4000 43.200 17.280,00
Solar Non Subsidi M.137 b Ltr 0,3000 9.400 2.820,00
Pelumas M.132 Ltr 0,0400 34.500 1.380,00
Jumlah Harga Bahan (B) 21.480,00
C PERALATAN
23
9 Pekerjaan Fabrikasi dan Elektroda Besi siku / kg
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,0600 133.000 7.980,00
Tukang Besi L.03c OH 0,0600 157.500 9.450,00
Kepala Tukang Besi L.03ab OH 0,0060 172.200 1.033,20
Mandor L.04 OH 0,0030 181.300 543,90
Jumlah Tenaga Kerja (A) 19.007,10
B BAHAN
Besi Baja Profil Siku M.54 g kg 1,1500 12.500 14.375,00
Plat simpul-baut-las m.br-4c ls 0,2000 12.500 2.500,00
Jumlah Harga Bahan (B) 16.875,00
C PERALATAN
10 Pemasangan Rangka Atap Pelana Baja Ringan (Canai Dingin) profil C75 / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,5505 133.000 73.216,50
Tukang Besi L.03c OH 0,5505 157.500 86.703,75
Kepala Tukang Besi L.03ab OH 0,0548 172.200 9.427,95
Mandor L.04 OH 0,0278 181.300 5.031,08
Jumlah Tenaga Kerja (A) 174.379,28
B BAHAN
Baja Ringan M.72 kg 3,0650 22.100 67.736,50
Self Drilling Screw besar-kecil M.71 n bh 6,0000 1.400 8.400,00
Jumlah Harga Bahan (B) 76.136,50
C PERALATAN
11 Pemasangan Rangka Atap Jurai Baja Ringan (Canai Dingin) profil C75 / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,5703 133.000 75.849,90
Tukang Besi L.03c OH 0,5703 157.500 89.822,25
Kepala Tukang Besi L.03ab OH 0,0570 172.200 9.815,40
Mandor L.04 OH 0,0285 181.300 5.167,05
Jumlah Tenaga Kerja (A) 180.654,60
B BAHAN
Baja Ringan M.72 kg 4,0500 22.100 89.505,00
Self Drilling Screw besar-kecil M.71 n bh 8,0000 1.400 11.200,00
Jumlah Harga Bahan (B) 100.705,00
C PERALATAN
24
3 Pasang pintu lipat (Folding Door) / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,4400 133.000 58.520,00
Tukang Besi L.03c OH 0,4400 157.500 69.300,00
Kepala Tukang Besi L.03ab OH 0,0440 172.200 7.576,80
Mandor L.04 OH 0,0220 181.300 3.988,60
Jumlah Tenaga Kerja (A) 139.385,40
B BAHAN
Pintu lipat M.70 e m² 1,0000 512.100 512.100,00
Jumlah Harga Bahan (B) 512.100,00
C PERALATAN
25
7 Pasang Kusen P1B / unit
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,0430 133.000 5.719,00
Tukang Batu L.03a OH 0,0430 157.500 6.772,50
Kepala Tukang Batu L.03aa OH 0,0040 172.200 688,80
Mandor L.04 OH 0,0020 181.300 362,60
Jumlah Tenaga Kerja (A) 13.542,90
B BAHAN
Pintu Kamar Mandi PVC lengkap kusen
M.173 b bh 1,0000 750.000 750.000,00
PVC-kunci
Jumlah Harga Bahan (B) 750.000,00
C PERALATAN
26
11 Pasang Kusen J1 A / unit
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,0430 133.000 5.719,00
Tukang Batu L.03a OH 0,0430 157.500 6.772,50
Kepala Tukang Batu L.03aa OH 0,0040 172.200 688,80
Mandor L.04 OH 0,0020 181.300 362,60
Jumlah Tenaga Kerja (A) 13.542,90
B BAHAN
Profil Allumunium Kusen M.74 b m' 4,2800 112.500 481.500,00
Profil Allumunium Rangka pintu-jendela
M.74 c m' 4,2000 135.000 567.000,00
Natural
Kaca Polos 8 mm M.140 c m² 0,5600 175.000 98.000,00
Grendel M.172 l bh 2,0000 35.250 70.500,00
Kait angin kuningan M.172 b bh 2,0000 27.000 54.000,00
Jumlah Harga Bahan (B) 1.271.000,00
C PERALATAN
27
15 Pasang Kusen J2 B / unit
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,0430 133.000 5.719,00
Tukang Batu L.03a OH 0,0430 157.500 6.772,50
Kepala Tukang Batu L.03aa OH 0,0040 172.200 688,80
Mandor L.04 OH 0,0020 181.300 362,60
Jumlah Tenaga Kerja (A) 13.542,90
B BAHAN
Profil Allumunium Kusen M.74 b m' 10,2000 112.500 1.147.500,00
Profil Allumunium Rangka pintu-jendela
M.74 c m' 10,2000 135.000 1.377.000,00
Natural
Kaca Polos 8 mm M.140 c m² 2,0800 175.000 364.000,00
Grendel M.172 l bh 4,0000 35.250 141.000,00
Kait angin kuningan M.172 b bh 4,0000 27.000 108.000,00
Jumlah Harga Bahan (B) 3.137.500,00
C PERALATAN
28
19 Pasang Kusen J5 A / unit
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,0430 133.000 5.719,00
Tukang Batu L.03a OH 0,0430 157.500 6.772,50
Kepala Tukang Batu L.03aa OH 0,0040 172.200 688,80
Mandor L.04 OH 0,0020 181.300 362,60
Jumlah Tenaga Kerja (A) 13.542,90
B BAHAN
Profil Allumunium Kusen M.74 b m' 37,8000 112.500 4.252.500,00
Profil Allumunium Rangka pintu-jendela
M.74 c m' 20,5000 135.000 2.767.500,00
Natural
Kaca Polos 8 mm M.140 c m² 8,5500 175.000 1.496.250,00
Grendel M.172 l bh 10,0000 35.250 352.500,00
Kait angin kuningan M.172 b bh 10,0000 27.000 270.000,00
Jumlah Harga Bahan (B) 9.138.750,00
C PERALATAN
29
22 Pasang kusen pintu alumunium PJ1 (GS) / unit
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,0430 133.000 5.719,00
Tukang Batu L.03a OH 0,0430 157.500 6.772,50
Kepala Tukang Batu L.03aa OH 0,0040 172.200 688,80
Mandor L.04 OH 0,0020 181.300 362,60
Jumlah Tenaga Kerja (A) 13.542,90
B BAHAN
Profil Allumunium Kusen M.74 b m' 19,2000 112.500 2.160.000,00
Profil Allumunium Rangka pintu-jendela
M.74 c m' 20,8000 135.000 2.808.000,00
Natural
Kaca Polos 5 mm M.140 b m² 8,8200 90.000 793.800,00
Grendel M.172 l bh 4,0000 35.250 141.000,00
Kait angin kuningan M.172 b bh 4,0000 27.000 108.000,00
Handel Pintu / pull handle M.172 g ps 1,0000 300.000 300.000,00
Kunci silinder pintu aluminium M.170 e set 1,0000 158.400 158.400,00
Kunci tanam pintu sederhana M.170 a set 1,0000 108.500 108.500,00
Karet m.br-5 m 13,2000 20.000 264.000,00
Jumlah Harga Bahan (B) 6.841.700,00
C PERALATAN
30
26 Pasang kusen jendela alumunium J3 (GS) / unit
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,0430 133.000 5.719,00
Tukang Batu L.03a OH 0,0430 157.500 6.772,50
Kepala Tukang Batu L.03aa OH 0,0040 172.200 688,80
Mandor L.04 OH 0,0020 181.300 362,60
Jumlah Tenaga Kerja (A) 13.542,90
B BAHAN
Profil Allumunium Kusen M.74 b m' 8,4000 112.500 945.000,00
Profil Allumunium Rangka pintu-jendela
M.74 c m' 11,2000 135.000 1.512.000,00
Natural
Kaca Polos 5 mm M.140 b m² 1,9200 90.000 172.800,00
Grendel M.172 l bh 4,0000 35.250 141.000,00
Kait angin kuningan M.172 b bh 4,0000 27.000 108.000,00
Karet m.br-5 m 4,6000 20.000 92.000,00
Jumlah Harga Bahan (B) 2.970.800,00
C PERALATAN
31
30 Memasang pintu/jendela/BV kaca, rangka allumunium / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,0850 133.000 11.305,00
Tukang Batu L.03a OH 0,0850 157.500 13.387,50
Kepala Tukang Batu L.03aa OH 0,0080 172.200 1.377,60
Mandor L.04 OH 0,0040 181.300 725,20
Jumlah Tenaga Kerja (A) 26.795,30
B BAHAN
Profil Allumunium Rangka pintu-jendela
M.74 c m' 4,4000 135.000 594.000,00
Natural
Kaca Polos 5 mm M.140 b m² 1,0500 90.000 94.500,00
Sealant M.75 a tube 0,2700 29.500 7.965,00
Jumlah Harga Bahan (B) 696.465,00
C PERALATAN
34 Pasang baut Ø 19 / bh
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,0040 133.000 532,00
Tukang Besi L.03c OH 0,0380 157.500 5.985,00
Kepala Tukang Besi L.03ab OH 0,0040 172.200 688,80
Jumlah Tenaga Kerja (A) 7.205,80
B BAHAN
Baut diameter 19 mm M.71 x c bh 1,0000 17.500 17.500,00
Jumlah Harga Bahan (B) 17.500,00
C PERALATAN
32
35 Pasang baut Ø 16 / bh
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,0040 133.000 532,00
Tukang Besi L.03c OH 0,0380 157.500 5.985,00
Kepala Tukang Besi L.03ab OH 0,0040 172.200 688,80
Jumlah Tenaga Kerja (A) 7.205,80
B BAHAN
Baut diameter 16 mm M.71 x b bh 1,0000 16.000 16.000,00
Jumlah Harga Bahan (B) 16.000,00
C PERALATAN
36 Pasang baut Ø 12 / bh
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,0040 133.000 532,00
Tukang Besi L.03c OH 0,0380 157.500 5.985,00
Kepala Tukang Besi L.03ab OH 0,0040 172.200 688,80
Jumlah Tenaga Kerja (A) 7.205,80
B BAHAN
Baut diameter 12 mm M.71 x a bh 1,0000 15.000 15.000,00
Jumlah Harga Bahan (B) 15.000,00
C PERALATAN
33
40 Dudukan tangki air / unit
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 2,0000 133.000 266.000,00
Tukang Besi L.03c OH 1,0000 157.500 157.500,00
Kepala Tukang Besi L.03ab OH 0,2200 172.200 37.884,00
Kepala Tukang Besi L.03ab OH 0,0320 172.200 5.510,40
Jumlah Tenaga Kerja (A) 466.894,40
B BAHAN
Besi Baja Profil Siku M.54 g kg 180,0000 12.500 2.250.000,00
Cat penutup kayu/besi kw 1 M.115 n kg 0,5000 79.600 39.800,00
Jumlah Harga Bahan (B) 2.289.800,00
C PERALATAN
PEKERJAAN DINDING
1 Pasangan dinding bata merah 1 PC : 2 PP tebal 1 bata / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,6000 133.000 79.800,00
Tukang Batu L.03a OH 0,2000 157.500 31.500,00
Kepala Tukang Batu L.03aa OH 0,0200 172.200 3.444,00
Mandor L.04 OH 0,0300 181.300 5.439,00
Jumlah Tenaga Kerja (A) 120.183,00
B BAHAN
Bata Merah Bakar Kelas II M.05 b bh 140,0000 850 119.000,00
Semen Portland M.15 a kg 43,5000 1.450 63.075,00
Pasir Pasang M.14 b m³ 0,0800 250.000 20.000,00
Jumlah Harga Bahan (B) 202.075,00
C PERALATAN
34
5 Pasangan dinding bata merah 1 PC : 6 PP tebal 1 bata / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,6000 133.000 79.800,00
Tukang Batu L.03a OH 0,2000 157.500 31.500,00
Kepala Tukang Batu L.03aa OH 0,0200 172.200 3.444,00
Mandor L.04 OH 0,0300 181.300 5.439,00
Jumlah Tenaga Kerja (A) 120.183,00
B BAHAN
Bata Merah Bakar Kelas II M.05 b bh 140,0000 850 119.000,00
Semen Portland M.15 a kg 18,5000 1.450 26.825,00
Pasir Pasang M.14 b m³ 0,1020 250.000 25.500,00
Jumlah Harga Bahan (B) 171.325,00
C PERALATAN
35
10 Pasangan dinding bata merah 1 PC : 6 PP tebal 1/2 bata / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,3000 133.000 39.900,00
Tukang Batu L.03a OH 0,1000 157.500 15.750,00
Kepala Tukang Batu L.03aa OH 0,0100 172.200 1.722,00
Mandor L.04 OH 0,0150 181.300 2.719,50
Jumlah Tenaga Kerja (A) 60.091,50
B BAHAN
Bata Merah Bakar Kelas II M.05 b bh 70,0000 850 59.500,00
Semen Portland M.15 a kg 8,3200 1.450 12.064,00
Pasir Pasang M.14 b m³ 0,0490 250.000 12.250,00
Jumlah Harga Bahan (B) 83.814,00
C PERALATAN
36
15 Pemasangan Rollag bata / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,6000 133.000 79.800,00
Tukang Batu L.03a OH 0,2000 157.500 31.500,00
Kepala Tukang Batu L.03aa OH 0,0200 172.200 3.444,00
Mandor L.04 OH 0,0300 181.300 5.439,00
Jumlah Tenaga Kerja (A) 120.183,00
B BAHAN
Bata Merah Bakar Kelas II M.05 b bh 140,0000 850 119.000,00
Semen Portland M.15 a kg 18,5000 1.450 26.825,00
Pasir Pasang M.14 b m³ 0,1020 250.000 25.500,00
Jumlah Harga Bahan (B) 171.325,00
C PERALATAN
37
20 Pemasangan Bata Ringan tebal 100 mm dengan prime mortar / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,1678 133.000 22.310,75
Tukang Batu L.03a OH 0,3250 157.500 51.187,50
Kepala Tukang Batu L.03aa OH 0,0325 172.200 5.596,50
Mandor L.04 OH 0,0008 181.300 135,98
Jumlah Tenaga Kerja (A) 79.230,73
B BAHAN
Semen Instan Perekat Bata ringan M.15 d zak 0,0640 98.000 6.272,00
Bata ringan uk.60x20x10 M.05 k bh 8,5000 9.000 76.500,00
Jumlah Harga Bahan (B) 82.772,00
C PERALATAN
38
25 Plesteran Halus 1 PC : 2 PP tebal 1,5 cm / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,3000 133.000 39.900,00
Tukang Batu L.03a OH 0,1500 157.500 23.625,00
Kepala Tukang Batu L.03aa OH 0,0150 172.200 2.583,00
Mandor L.04 OH 0,0150 181.300 2.719,50
Jumlah Tenaga Kerja (A) 68.827,50
B BAHAN
Semen Portland M.15 a kg 10,2240 1.450 14.824,80
Pasir Pasang M.14 b m³ 0,0200 250.000 5.000,00
Jumlah Harga Bahan (B) 19.824,80
C PERALATAN
39
30 Plesteran Halus 1 PC : 7 PP tebal 1,5 cm / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,3000 133.000 39.900,00
Tukang Batu L.03a OH 0,1500 157.500 23.625,00
Kepala Tukang Batu L.03aa OH 0,0150 172.200 2.583,00
Mandor L.04 OH 0,0150 181.300 2.719,50
Jumlah Tenaga Kerja (A) 68.827,50
B BAHAN
Semen Portland M.15 a kg 3,9360 1.450 5.707,20
Pasir Pasang M.14 b m³ 0,0280 250.000 7.000,00
Jumlah Harga Bahan (B) 12.707,20
C PERALATAN
33 Plesteran 1 Pc : 1 Ps tebal 20 mm / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,4000 133.000 53.200,00
Tukang Batu L.03a OH 0,2000 157.500 31.500,00
Kepala Tukang Batu L.03aa OH 0,0200 172.200 3.444,00
Mandor L.04 OH 0,0220 181.300 3.988,60
Jumlah Tenaga Kerja (A) 92.132,60
B BAHAN
Semen Portland M.15 a kg 13,6320 1.450 19.766,40
Pasir Pasang M.14 b m³ 0,0270 250.000 6.750,00
Jumlah Harga Bahan (B) 26.516,40
C PERALATAN
34 Plesteran 1 Pc : 3 Ps tebal 20 mm / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,4000 133.000 53.200,00
Tukang Batu L.03a OH 0,2000 157.500 31.500,00
Kepala Tukang Batu L.03aa OH 0,0200 172.200 3.444,00
Mandor L.04 OH 0,0220 181.300 3.988,60
Jumlah Tenaga Kerja (A) 92.132,60
B BAHAN
Semen Portland M.15 a kg 10,3680 1.450 15.033,60
Pasir Pasang M.14 b m³ 0,0310 250.000 7.750,00
Jumlah Harga Bahan (B) 22.783,60
C PERALATAN
40
35 Plesteran 1 Pc : 4 Ps tebal 20 mm / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,4000 133.000 53.200,00
Tukang Batu L.03a OH 0,2000 157.500 31.500,00
Kepala Tukang Batu L.03aa OH 0,0200 172.200 3.444,00
Mandor L.04 OH 0,0220 181.300 3.988,60
Jumlah Tenaga Kerja (A) 92.132,60
B BAHAN
Semen Portland M.15 a kg 8,3200 1.450 12.064,00
Pasir Pasang M.14 b m³ 0,0320 250.000 8.000,00
Jumlah Harga Bahan (B) 20.064,00
C PERALATAN
36 Plesteran 1 Pc : 5 Ps tebal 20 mm / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,4000 133.000 53.200,00
Tukang Batu L.03a OH 0,2000 157.500 31.500,00
Kepala Tukang Batu L.03aa OH 0,0200 172.200 3.444,00
Mandor L.04 OH 0,0220 181.300 3.988,60
Jumlah Tenaga Kerja (A) 92.132,60
B BAHAN
Semen Portland M.15 a kg 6,9120 1.450 10.022,40
Pasir Pasang M.14 b m³ 0,0350 250.000 8.750,00
Jumlah Harga Bahan (B) 18.772,40
C PERALATAN
37 Plesteran 1 Pc : 6 Ps tebal 20 mm / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,4000 133.000 53.200,00
Tukang Batu L.03a OH 0,2000 157.500 31.500,00
Kepala Tukang Batu L.03aa OH 0,0200 172.200 3.444,00
Mandor L.04 OH 0,0220 181.300 3.988,60
Jumlah Tenaga Kerja (A) 92.132,60
B BAHAN
Semen Portland M.15 a kg 5,8800 1.450 8.526,00
Pasir Pasang M.14 b m³ 0,0360 250.000 9.000,00
Jumlah Harga Bahan (B) 17.526,00
C PERALATAN
41
40 Plesteran Ciprat 1 Pc : 2 Ps / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,3000 133.000 39.900,00
Tukang Batu L.03a OH 0,1000 157.500 15.750,00
Kepala Tukang Batu L.03aa OH 0,0100 172.200 1.722,00
Mandor L.04 OH 0,0150 181.300 2.719,50
Jumlah Tenaga Kerja (A) 60.091,50
B BAHAN
Semen Portland M.15 a kg 4,3200 1.450 6.264,00
Pasir Pasang M.14 b m³ 0,0600 250.000 15.000,00
Jumlah Harga Bahan (B) 21.264,00
C PERALATAN
42 Acian / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,2000 133.000 26.600,00
Tukang Batu L.03a OH 0,1000 157.500 15.750,00
Kepala Tukang Batu L.03aa OH 0,0100 172.200 1.722,00
Mandor L.04 OH 0,0100 181.300 1.813,00
Jumlah Tenaga Kerja (A) 45.885,00
B BAHAN
Semen Portland M.15 a kg 3,2500 1.450 4.712,50
Jumlah Harga Bahan (B) 4.712,50
C PERALATAN
42
3 Pasang lantai Ubin PC abu-abu ukuran 20 x 20 cm / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,2500 133.000 33.250,00
Tukang Batu L.03a OH 0,1250 157.500 19.687,50
Kepala Tukang Batu L.03aa OH 0,0125 172.200 2.152,50
Mandor L.04 OH 0,0125 181.300 2.266,25
Jumlah Tenaga Kerja (A) 57.356,25
B BAHAN
Ubin pc abu-abu 20 x 20 M.80 c bh 25,0000 3.000 75.000,00
Semen Warna M.15 c kg 1,0000 18.500 18.500,00
Semen Portland M.15 a kg 9,8000 1.450 14.210,00
Pasir Pasang M.14 b m³ 0,0450 250.000 11.250,00
Jumlah Harga Bahan (B) 118.960,00
C PERALATAN
43
7 Pasang lantai Ubin Marmer ukuran 40 x 40 cm / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,2500 133.000 33.250,00
Tukang Batu L.03a OH 0,1250 157.500 19.687,50
Kepala Tukang Batu L.03aa OH 0,0125 172.200 2.152,50
Mandor L.04 OH 0,0125 181.300 2.266,25
Jumlah Tenaga Kerja (A) 57.356,25
B BAHAN
Marmer M.81 b m² 1,0500 412.000 432.600,00
Semen Warna M.15 c kg 1,0000 18.500 18.500,00
Semen Portland M.15 a kg 9,8000 1.450 14.210,00
Pasir Pasang M.14 b m³ 0,0450 250.000 11.250,00
Jumlah Harga Bahan (B) 476.560,00
C PERALATAN
44
11 Pasang lantai Keramik Granito/Indogress ukuran 40 x 40 cm / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,2500 133.000 33.250,00
Tukang Batu L.03a OH 0,1250 157.500 19.687,50
Kepala Tukang Batu L.03aa OH 0,0125 172.200 2.152,50
Mandor L.04 OH 0,0125 181.300 2.266,25
Jumlah Tenaga Kerja (A) 57.356,25
B BAHAN
Granite Homogeneus tile 40 x 40 cm M.82 b m² 1,0500 205.000 215.250,00
Semen Warna M.15 c kg 1,0000 18.500 18.500,00
Semen Portland M.15 a kg 9,8000 1.450 14.210,00
Pasir Pasang M.14 b m³ 0,0450 250.000 11.250,00
Jumlah Harga Bahan (B) 259.210,00
C PERALATAN
45
15 Pasang lantai keramik ukuran 33 x 33 cm Roman / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,2500 133.000 33.250,00
Tukang Batu L.03a OH 0,1250 157.500 19.687,50
Kepala Tukang Batu L.03aa OH 0,0125 172.200 2.152,50
Mandor L.04 OH 0,0125 181.300 2.266,25
Jumlah Tenaga Kerja (A) 57.356,25
B BAHAN
Keramik Lantai 33,3 x 33,3 cm kw 1 M.83 ab m² 1,0500 145.500 152.775,00
Semen Warna M.15 c kg 1,0000 18.500 18.500,00
Semen Portland M.15 a kg 9,8000 1.450 14.210,00
Pasir Pasang M.14 b m³ 0,0450 250.000 11.250,00
Jumlah Harga Bahan (B) 196.735,00
C PERALATAN
46
19 Pasang lantai keramik ukuran 30 x 30 cm KW 2 / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,2500 133.000 33.250,00
Tukang Batu L.03a OH 0,1250 157.500 19.687,50
Kepala Tukang Batu L.03aa OH 0,0125 172.200 2.152,50
Mandor L.04 OH 0,0125 181.300 2.266,25
Jumlah Tenaga Kerja (A) 57.356,25
B BAHAN
Keramik Lantai 30 x 30 cm kw 2 M.83 b a m² 1,0500 60.000 63.000,00
Semen Warna M.15 c kg 1,0000 18.500 18.500,00
Semen Portland M.15 a kg 10,4000 1.450 15.080,00
Pasir Pasang M.14 b m³ 0,0450 250.000 11.250,00
Jumlah Harga Bahan (B) 107.830,00
C PERALATAN
47
24 Pasang dinding keramik 20 x 25 cm KW 2 / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,4500 133.000 59.850,00
Tukang Batu L.03a OH 0,2250 157.500 35.437,50
Kepala Tukang Batu L.03aa OH 0,0225 172.200 3.874,50
Mandor L.04 OH 0,0225 181.300 4.079,25
Jumlah Tenaga Kerja (A) 103.241,25
B BAHAN
Keramik dinding 20 x 25 cm KW 2 M.83 fa m² 1,0500 80.000 84.000,00
Semen Warna M.15 c kg 1,9400 18.500 35.890,00
Semen Portland M.15 a kg 9,3000 1.450 13.485,00
Pasir Pasang M.14 b m³ 0,0180 250.000 4.500,00
Jumlah Harga Bahan (B) 137.875,00
C PERALATAN
48
2 Pembuatan dan pasang kusen pintu dan jendela Kayu Kamper Samarinda Oven / m³
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 7,0000 133.000 931.000,00
Tukang Kayu L.03b OH 21,0000 157.500 3.307.500,00
Kepala Tukang L.03 OH 2,1000 172.200 361.620,00
Mandor L.04 OH 0,3500 181.300 63.455,00
Jumlah Tenaga Kerja (A) 4.663.575,00
B BAHAN
Kayu balok - kaso-kaso Klas II M.33 n m³ 1,1000 11.319.420 12.451.362,00
Paku biasa 2"-5" M.71 a kg 1,2500 17.000 21.250,00
Lem Kayu M.125 a kg 1,0000 22.000 22.000,00
Jumlah Harga Bahan (B) 12.494.612,00
C PERALATAN
3 Pembuatan dan pasang kusen pintu dan jendela Kayu Kamper Medan/Kruing / m³
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 6,0000 133.000 798.000,00
Tukang Kayu L.03b OH 18,0000 157.500 2.835.000,00
Kepala Tukang L.03 OH 1,8000 172.200 309.960,00
Mandor L.04 OH 0,3000 181.300 54.390,00
Jumlah Tenaga Kerja (A) 3.997.350,00
B BAHAN
Kayu balok - kaso-kaso Klas II M.33 n m³ 1,2000 11.319.420 13.583.304,00
Paku biasa 2"-5" M.71 a kg 1,2500 17.000 21.250,00
Lem Kayu M.125 a kg 1,0000 22.000 22.000,00
Jumlah Harga Bahan (B) 13.626.554,00
C PERALATAN
4 Pembuatan dan pasang kusen pintu dan jendela Kayu Meranti Palembang / m³
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 6,0000 133.000 798.000,00
Tukang Kayu L.03b OH 18,0000 157.500 2.835.000,00
Kepala Tukang L.03 OH 1,8000 172.200 309.960,00
Mandor L.04 OH 0,3000 181.300 54.390,00
Jumlah Tenaga Kerja (A) 3.997.350,00
B BAHAN
Kayu balok, kaso-kaso Klas III M.34 a m³ 1,2000 3.000.000 3.600.000,00
Paku biasa 2"-5" M.71 a kg 1,2500 17.000 21.250,00
Lem Kayu M.125 a kg 1,0000 22.000 22.000,00
Jumlah Harga Bahan (B) 3.643.250,00
C PERALATAN
49
6 Pasang Kusen Kayu P1 / unit
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,0430 133.000 5.719,00
Tukang Batu L.03a OH 0,0430 157.500 6.772,50
Kepala Tukang Batu L.03aa OH 0,0040 172.200 688,80
Mandor L.04 OH 0,0020 181.300 362,60
Jumlah Tenaga Kerja (A) 13.542,90
B BAHAN
Kayu balok - kaso-kaso Klas II M.33 n m³ 0,0676 11.319.420 765.011,68
Kayu papan, reng Klas II M.33 o m³ 0,0294 11.468.225 337.165,82
Kaca Polos 8 mm M.140 c m² 2,1600 175.000 378.000,00
Engsel pintu 4 " biasa/sederhana M.171 a psg 3,0000 37.500 112.500,00
Handel Pintu / pull handle M.172 g ps 1,0000 300.000 300.000,00
Kunci silinder pintu aluminium M.170 e set 1,0000 158.400 158.400,00
Door closer stainless steel M.172 j bh 1,0000 521.700 521.700,00
Door stop stainless steel M.172 n bh 1,0000 107.600 107.600,00
Kunci tanam pintu sederhana M.170 a set 1,0000 108.500 108.500,00
Jumlah Harga Bahan (B) 2.788.877,50
C PERALATAN
50
10 Pasang Jendela J2 Kusen Kayu Kelas II
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,0430 133.000 5.719,00
Tukang Batu L.03a OH 0,0430 157.500 6.772,50
Kepala Tukang Batu L.03aa OH 0,0040 172.200 688,80
Mandor L.04 OH 0,0020 181.300 362,60
Jumlah Tenaga Kerja (A) 13.542,90
B BAHAN -
Kayu balok - kaso-kaso Klas II M.33 n m³ 0,0093 11.319.420 105.270,61
Kayu papan, reng Klas II M.33 o m³ 0,0013 11.468.225 15.138,06
Kaca Polos 5 mm M.140 b m² 9,6000 90.000 864.000,00
Grendel M.172 l ps 6,0000 35.250 211.500,00
Kait angin kuningan M.172 b set 6,0000 27.000 162.000,00
51
14 Pembuatan dan pasang pintu panel Kayu Kamper Medan/Kruing / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 1,0000 133.000 133.000,00
Tukang Kayu L.03b OH 3,0000 157.500 472.500,00
Kepala Tukang L.03 OH 0,3000 172.200 51.660,00
Mandor L.04 OH 0,0500 181.300 9.065,00
Jumlah Tenaga Kerja (A) 666.225,00
B BAHAN
Kayu papan, reng Klas II M.33 o m³ 0,0400 11.468.225 458.729,00
Lem Kayu M.125 a kg 0,5000 22.000 11.000,00
Jumlah Harga Bahan (B) 469.729,00
C PERALATAN
18 Pembuatan dan pasang pintu dan jendela kaca Kayu Kamper Samarinda Oven / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,8000 133.000 106.400,00
Tukang Kayu L.03b OH 2,4000 157.500 378.000,00
Kepala Tukang L.03 OH 0,2400 172.200 41.328,00
Mandor L.04 OH 0,0400 181.300 7.252,00
Jumlah Tenaga Kerja (A) 532.980,00
B BAHAN
Kayu papan, reng Klas II M.33 o m³ 0,0240 11.468.225 275.237,40
Lem Kayu M.125 a kg 0,3000 22.000 6.600,00
Jumlah Harga Bahan (B) 281.837,40
C PERALATAN
52
19 Pembuatan dan pasang pintu dan jendela kaca Kayu Meranti Sampit / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,8000 133.000 106.400,00
Tukang Kayu L.03b OH 2,4000 157.500 378.000,00
Kepala Tukang L.03 OH 0,2400 172.200 41.328,00
Mandor L.04 OH 0,0400 181.300 7.252,00
Jumlah Tenaga Kerja (A) 532.980,00
B BAHAN
Kayu reng- papan Klas III M.34 b m³ 0,0240 3.500.000 84.000,00
Lem Kayu M.125 a kg 0,3000 22.000 6.600,00
Jumlah Harga Bahan (B) 90.600,00
C PERALATAN
53
24 Pasang pintu teakwood rangkap, rangka Kayu Kamper Samarinda oven / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,7000 133.000 93.100,00
Tukang Kayu L.03b OH 2,1000 157.500 330.750,00
Kepala Tukang L.03 OH 0,2100 172.200 36.162,00
Mandor L.04 OH 0,3500 181.300 63.455,00
Jumlah Tenaga Kerja (A) 523.467,00
B BAHAN
Kayu papan, reng Klas II M.33 o m³ 0,0640 11.468.225 733.966,40
Teakwood 4 mm- 90 x210 cm - ukuran
M.41 a Lbr 1,0640 132.000 140.448,00
pintu
Paku biasa 1/2"- 1" M.71 b kg 0,0300 22.000 660,00
Lem Kayu M.125 a kg 0,5000 22.000 11.000,00
Jumlah Harga Bahan (B) 886.074,40
C PERALATAN
54
28 Pasang pintu triplek rangkap, rangka Kayu Meranti Palembang / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,7000 133.000 93.100,00
Tukang Kayu L.03b OH 2,1000 157.500 330.750,00
Kepala Tukang L.03 OH 0,2100 172.200 36.162,00
Mandor L.04 OH 0,3500 181.300 63.455,00
Jumlah Tenaga Kerja (A) 523.467,00
B BAHAN
Kayu reng- papan Klas III M.34 b m³ 0,0640 3.500.000 224.000,00
Multiplek tebal 4 mm M 39 b Lbr 1,0640 75.000 79.800,00
Paku biasa 1/2"- 1" M.71 b kg 0,0300 22.000 660,00
Lem Kayu M.125 a kg 0,5000 22.000 11.000,00
Jumlah Harga Bahan (B) 315.460,00
C PERALATAN
29 Pasang pintu teakwood dan formika, rangka Kayu Kamper Samarinda oven / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,8500 133.000 113.050,00
Tukang Kayu L.03b OH 2,5500 157.500 401.625,00
Kepala Tukang L.03 OH 0,2550 172.200 43.911,00
Mandor L.04 OH 0,0430 181.300 7.795,90
Jumlah Tenaga Kerja (A) 566.381,90
B BAHAN
Kayu papan, reng Klas II M.33 o m³ 0,0250 11.468.225 286.705,63
Teakwood 4 mm- 90 x210 cm - ukuran
M.41 a Lbr 1,0000 132.000 132.000,00
pintu
Formika 3x7 ft M 41 d Lbr 0,5000 210.000 105.000,00
Paku biasa 1/2"- 1" M.71 b kg 0,0300 22.000 660,00
Lem Kayu M.125 a kg 0,5000 22.000 11.000,00
Jumlah Harga Bahan (B) 535.365,63
C PERALATAN
55
32 Pasang pintu triplek dan formika, rangka Kayu Kamper Medan/Kruing / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,8500 133.000 113.050,00
Tukang Kayu L.03b OH 2,5500 157.500 401.625,00
Kepala Tukang L.03 OH 0,2550 172.200 43.911,00
Mandor L.04 OH 0,0430 181.300 7.795,90
Jumlah Tenaga Kerja (A) 566.381,90
B BAHAN
Kayu papan, reng Klas II M.33 o m³ 0,0250 11.468.225 286.705,63
Multiplek tebal 4 mm M 39 b Lbr 1,0000 75.000 75.000,00
Formika 3x7 ft M 41 d Lbr 0,5000 210.000 105.000,00
Paku biasa 1/2"- 1" M.71 b kg 0,0300 22.000 660,00
Lem Kayu M.125 a kg 0,5000 22.000 11.000,00
Jumlah Harga Bahan (B) 478.365,63
C PERALATAN
34 Pasang pintu triplek dan double formika, rangka Kayu Meranti Palembang / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,8500 133.000 113.050,00
Tukang Kayu L.03b OH 2,5500 157.500 401.625,00
Kepala Tukang L.03 OH 0,2550 172.200 43.911,00
Mandor L.04 OH 0,0430 181.300 7.795,90
Jumlah Tenaga Kerja (A) 566.381,90
B BAHAN
Kayu reng- papan Klas III M.34 b m³ 0,0250 3.500.000 87.500,00
Multiplek tebal 4 mm M 39 b Lbr 1,0000 75.000 75.000,00
Formika 3x7 ft M 41 d Lbr 1,0000 210.000 210.000,00
Paku biasa 1/2"- 1" M.71 b kg 0,0300 22.000 660,00
Lem Kayu M.125 a kg 0,5000 22.000 11.000,00
Jumlah Harga Bahan (B) 384.160,00
C PERALATAN
56
36 Pasang kawat harmonika / m²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,2000 133.000 26.600,00
Tukang Besi L.03c OH 0,4000 157.500 63.000,00
Kepala Tukang Besi L.03ab OH 0,0200 172.200 3.444,00
Mandor L.04 OH 0,0100 181.300 1.813,00
Jumlah Tenaga Kerja (A) 94.857,00
B BAHAN
Kawat harmonika Ø 2 mm spasi 40x40
M.68 d m² 1,1000 35.750 39.325,00
mm
Pekerjaan Pengelasan 10 CM dengan Las
A. 4.2.1.5 cm 1,1000 18.902 20.792,20
Listrik
Besi Plat M.54 i Kg 1,7160 14.100 24.195,60
Jumlah Harga Bahan (B) 84.312,80
C PERALATAN
57
3 Pasang 1 buah kunci pintu tanam KW 1 / bh
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,0600 133.000 7.980,00
Tukang Kayu L.03b OH 0,6000 157.500 94.500,00
Kepala Tukang L.03 OH 0,0600 172.200 10.332,00
Mandor L.04 OH 0,0030 181.300 543,90
Jumlah Tenaga Kerja (A) 113.355,90
B BAHAN
Kunci tanam pintu kw 1 M.170 c set 1,0000 397.000 397.000,00
Jumlah Harga Bahan (B) 397.000,00
C PERALATAN
58
8 Pasang 1 pasang engsel jendela kuningan/stainless / psg
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,0015 133.000 199,50
Tukang Kayu L.03b OH 0,1500 157.500 23.625,00
Kepala Tukang L.03 OH 0,0150 172.200 2.583,00
Mandor L.04 OH 0,0075 181.300 1.359,75
Jumlah Tenaga Kerja (A) 27.767,25
B BAHAN
Engsel jendela kuningan/stainless 3" M.171 c psg 1,0000 35.000 35.000,00
Jumlah Harga Bahan (B) 35.000,00
C PERALATAN
59
13 Pasang 1 buah rambuncis / bh
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,0500 133.000 6.650,00
Tukang Kayu L.03b OH 0,5000 157.500 78.750,00
Kepala Tukang L.03 OH 0,0500 172.200 8.610,00
Mandor L.04 OH 0,0030 181.300 543,90
Jumlah Tenaga Kerja (A) 94.553,90
B BAHAN
Rambuncis M.172 e bh 1,0000 68.000 68.000,00
Jumlah Harga Bahan (B) 68.000,00
C PERALATAN
60
18 Pasang 1 buah kunci selot / bh
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,0200 133.000 2.660,00
Tukang Kayu L.03b OH 0,2000 157.500 31.500,00
Kepala Tukang L.03 OH 0,0200 172.200 3.444,00
Mandor L.04 OH 0,0010 181.300 181,30
Jumlah Tenaga Kerja (A) 37.785,30
B BAHAN
Kunci selot M.172 k bh 1,0000 34.600 34.600,00
Jumlah Harga Bahan (B) 34.600,00
C PERALATAN
61
23 Pasang kaca es tebal 3 mm / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,0150 133.000 1.995,00
Tukang Kayu L.03b OH 0,1500 157.500 23.625,00
Kepala Tukang L.03 OH 0,0150 172.200 2.583,00
Mandor L.04 OH 0,0010 181.300 181,30
Jumlah Tenaga Kerja (A) 28.384,30
B BAHAN
Kaca es 3 mm M.140 i m² 1,1000 100.000 110.000,00
Jumlah Harga Bahan (B) 110.000,00
C PERALATAN
62
28 Pasang kaca tebal 8 mm / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,0170 133.000 2.261,00
Tukang Kayu L.03b OH 0,1650 157.500 25.987,50
Kepala Tukang L.03 OH 0,0170 172.200 2.927,40
Mandor L.04 OH 0,0010 181.300 181,30
Jumlah Tenaga Kerja (A) 31.357,20
B BAHAN
Kaca Polos 8 mm M.140 c m² 1,1000 175.000 192.500,00
Jumlah Harga Bahan (B) 192.500,00
C PERALATAN
63
33 Pasang Kaca Tempered polos 5 mm / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,0150 133.000 1.995,00
Tukang Kayu L.03b OH 0,1500 157.500 23.625,00
Kepala Tukang L.03 OH 0,0150 172.200 2.583,00
Mandor L.04 OH 0,0010 181.300 181,30
Jumlah Tenaga Kerja (A) 28.384,30
B BAHAN
Kaca Tempered polos 5 mm M.142 a m² 1,1000 270.000 297.000,00
Jumlah Harga Bahan (B) 297.000,00
C PERALATAN
64
3 Pasang konstruksi kuda-kuda expose Kayu Samarinda / m³
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 6,7000 133.000 891.100,00
Tukang Kayu L.03b OH 20,1000 157.500 3.165.750,00
Kepala Tukang L.03 OH 2,1000 172.200 361.620,00
Mandor L.04 OH 0,3350 181.300 60.735,50
Jumlah Tenaga Kerja (A) 4.479.205,50
B BAHAN
Kayu balok - kaso-kaso Klas II M.33 n m³ 1,2000 11.319.420 13.583.304,00
Paku biasa 2"-5" M.71 a kg 5,6000 17.000 95.200,00
Besi Plat M.54 i Kg 15,0000 14.100 211.500,00
Jumlah Harga Bahan (B) 13.890.004,00
C PERALATAN
65
8 Pasang kaso + reng genteng keramik Kayu Kamper Medan/Kruing / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,1000 133.000 13.300,00
Tukang Kayu L.03b OH 0,1000 157.500 15.750,00
Kepala Tukang L.03 OH 0,0100 172.200 1.722,00
Mandor L.04 OH 0,0050 181.300 906,50
Jumlah Tenaga Kerja (A) 31.678,50
B BAHAN
Kayu balok - kaso-kaso Klas II M.33 n m³ 0,0140 11.319.420 158.471,88
Kayu papan, reng Klas II M.33 o m³ 0,0072 11.468.225 82.571,22
Paku biasa 2"-5" M.71 a kg 0,2500 17.000 4.250,00
Jumlah Harga Bahan (B) 245.293,10
C PERALATAN
66
13 Pasang lisplank (3 x 20) cm Kayu Kamper Samarinda / m¹
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,1000 133.000 13.300,00
Tukang Kayu L.03b OH 0,2000 157.500 31.500,00
Kepala Tukang L.03 OH 0,0200 172.200 3.444,00
Mandor L.04 OH 0,0050 181.300 906,50
Jumlah Tenaga Kerja (A) 49.150,50
B BAHAN
Kayu papan, reng Klas II M.33 o m³ 0,0108 11.468.225 123.856,83
Paku biasa 2"-5" M.71 a kg 0,1000 17.000 1.700,00
Jumlah Harga Bahan (B) 125.556,83
C PERALATAN
67
18 Pasang lisplank (3 x 30) cm Kayu Meranti Palembang / m¹
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,1000 133.000 13.300,00
Tukang Kayu L.03b OH 0,2000 157.500 31.500,00
Kepala Tukang L.03 OH 0,0200 172.200 3.444,00
Mandor L.04 OH 0,0050 181.300 906,50
Jumlah Tenaga Kerja (A) 49.150,50
B BAHAN
Kayu papan, reng Klas II M.33 o m³ 0,0113 11.468.225 129.017,53
Paku biasa 2"-5" M.71 a kg 0,0500 17.000 850,00
Jumlah Harga Bahan (B) 129.867,53
C PERALATAN
68
PEKERJAAN PENUTUP ATAP
1 Pasang atap genteng plentong kecil natural / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,1500 133.000 19.950,00
Tukang Kayu L.03b OH 0,0750 157.500 11.812,50
Kepala Tukang L.03 OH 0,0080 172.200 1.377,60
Mandor L.04 OH 0,0080 181.300 1.450,40
Jumlah Tenaga Kerja (A) 34.590,50
B BAHAN
Genteng Palentong Natural, M.91 a bh 25,0000 7.000 175.000,00
Jumlah Harga Bahan (B) 175.000,00
C PERALATAN
69
6 Pasang atap genteng metal pelana 80 x100 cm / m²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,2000 133.000 26.600,00
Tukang Kayu L.03b OH 0,1000 157.500 15.750,00
Kepala Tukang L.03 OH 0,0100 172.200 1.722,00
Mandor L.04 OH 0,0010 181.300 181,30
Jumlah Tenaga Kerja (A) 44.253,30
B BAHAN
Genteng Metal M.91 j m² 1,3000 55.000 71.500,00
Paku biasa 2"-5" M.71 a kg 0,2000 17.000 3.400,00
Jumlah Harga Bahan (B) 74.900,00
C PERALATAN
70
11 Pasang atap spandek alumunium / m²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,1200 133.000 15.960,00
Tukang Kayu L.03b OH 0,0600 157.500 9.450,00
Kepala Tukang L.03 OH 0,0060 172.200 1.033,20
Mandor L.04 OH 0,0060 181.300 1.087,80
Jumlah Tenaga Kerja (A) 27.531,00
B BAHAN
Atap Zincalum t = 0,35mm M.88 g a m² 1,0500 120.000 126.000,00
Paku seng M.71 f kg 0,0400 35.000 1.400,00
Jumlah Harga Bahan (B) 127.400,00
C PERALATAN
15 Pasang glasswool / m²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,1500 133.000 19.950,00
Tukang Kayu L.03b OH 0,0500 157.500 7.875,00
Kepala Tukang L.03 OH 0,0050 172.200 861,00
Mandor L.04 OH 0,0080 181.300 1.450,40
Jumlah Tenaga Kerja (A) 30.136,40
B BAHAN
Glasswool BG 50 M.111 e m² 1,0500 33.200 34.860,00
Jumlah Harga Bahan (B) 34.860,00
C PERALATAN
71
16 Pasang Nok genteng beton / m¹
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,4000 133.000 53.200,00
Tukang Kayu L.03b OH 0,2000 157.500 31.500,00
Kepala Tukang L.03 OH 0,0200 172.200 3.444,00
Mandor L.04 OH 0,0020 181.300 362,60
Jumlah Tenaga Kerja (A) 88.506,60
B BAHAN
Nok Genteng Beton M.92 g bh 3,5000 7.000 24.500,00
Paku biasa 2"-5" M.71 a kg 0,0500 17.000 850,00
Semen Portland M.15 a kg 10,8000 1.450 15.660,00
Pasir Pasang M.14 b m³ 0,0320 250.000 8.000,00
Semen Warna M.15 c kg 1,0000 18.500 18.500,00
Jumlah Harga Bahan (B) 67.510,00
C PERALATAN
72
21 Pasang nok genteng metal / m¹
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,2500 133.000 33.250,00
Tukang Kayu L.03b OH 0,1500 157.500 23.625,00
Kepala Tukang L.03 OH 0,0150 172.200 2.583,00
Mandor L.04 OH 0,0130 181.300 2.356,90
Jumlah Tenaga Kerja (A) 61.814,90
B BAHAN
Nok genteng metal M.92 h m' 1,0500 41.300 43.365,00
Paku Genteng Metal M.71 q duz 0,0500 27.800 1.390,00
Jumlah Harga Bahan (B) 44.755,00
C PERALATAN
73
26 Pasang nok asbes / m¹
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,1500 133.000 19.950,00
Tukang Kayu L.03b OH 0,0700 157.500 11.025,00
Kepala Tukang L.03 OH 0,0080 172.200 1.377,60
Mandor L.04 OH 0,0060 181.300 1.087,80
Jumlah Tenaga Kerja (A) 33.440,40
B BAHAN
Nok Asbes M.92 i psg 1,1000 75.000 82.500,00
Paku asbes M.71 g bh 6,0000 2.500 15.000,00
Jumlah Harga Bahan (B) 97.500,00
C PERALATAN
28 Pasang Flashing / m¹
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,1500 133.000 19.950,00
Tukang Kayu L.03b OH 0,0700 157.500 11.025,00
Kepala Tukang L.03 OH 0,0080 172.200 1.377,60
Mandor L.04 OH 0,0060 181.300 1.087,80
Jumlah Tenaga Kerja (A) 33.440,40
B BAHAN
Flashing M.92 k m' 1,1000 59.900 65.890,00
Paku Genteng Metal M.71 q duz 0,4000 27.800 11.120,00
Jumlah Harga Bahan (B) 77.010,00
C PERALATAN
74
3 Pasang rangka plafon (50 x 100) cm Kayu Meranti Palembang / m²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,1500 133.000 19.950,00
Tukang Kayu L.03b OH 0,3000 157.500 47.250,00
Kepala Tukang L.03 OH 0,0300 172.200 5.166,00
Mandor L.04 OH 0,0750 181.300 13.597,50
Jumlah Tenaga Kerja (A) 85.963,50
B BAHAN
Kayu balok, kaso-kaso Klas III M.34 a m³ 0,0154 3.000.000 46.200,00
Paku biasa 2"-5" M.71 a kg 0,2000 17.000 3.400,00
Jumlah Harga Bahan (B) 49.600,00
C PERALATAN
75
8 Pasang rangka plafon (60 x 60) cm Kayu Kamper Medan/Kruing / m²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,2000 133.000 26.600,00
Tukang Kayu L.03b OH 0,3000 157.500 47.250,00
Kepala Tukang L.03 OH 0,0300 172.200 5.166,00
Mandor L.04 OH 0,0750 181.300 13.597,50
Jumlah Tenaga Kerja (A) 92.613,50
B BAHAN
Kayu balok - kaso-kaso Klas II M.33 n m³ 0,0163 11.319.420 184.506,55
Paku biasa 2"-5" M.71 a kg 0,2500 17.000 4.250,00
Jumlah Harga Bahan (B) 188.756,55
C PERALATAN
76
13 Pasang rangka plafon besi hollow 40x40x 2 mm modul 60 x 120 cm / m²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,2500 133.000 33.250,00
Tukang Kayu L.03b OH 0,2500 157.500 39.375,00
Kepala Tukang L.03 OH 0,0250 172.200 4.305,00
Mandor L.04 OH 0,0013 181.300 226,63
Jumlah Tenaga Kerja (A) 77.156,63
B BAHAN
Paku peluru ramset M.71 p bh 0,3900 3.000 1.170,00
Hollow 4x4 cm tbl 0.4 mm M.73 b btg 0,4590 60.000 27.540,00
Hollow 2x4 cm tbl 0.35 mm M.73 a btg 0,4310 40.000 17.240,00
Paku beton M.71 e kg 0,0100 42.000 420,00
Sekrup 6x1-1,5 M.71 l bh 4,3900 2.000 8.780,00
Jumlah Harga Bahan (B) 55.150,00
C PERALATAN
77
17 List Plafon kayu profil / m¹
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,0500 133.000 6.650,00
Tukang Kayu L.03b OH 0,0500 157.500 7.875,00
Kepala Tukang L.03 OH 0,0050 172.200 861,00
Mandor L.04 OH 0,0025 181.300 453,25
Jumlah Tenaga Kerja (A) 15.839,25
B BAHAN
List Kayu Profil M.44 a m' 1,0500 12.000 12.600,00
Paku biasa 2"-5" M.71 a kg 0,0100 17.000 170,00
Jumlah Harga Bahan (B) 12.770,00
C PERALATAN
78
22 Pasang list profil cornice gypsum lebar lebih dari 10 cm / m¹
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,1125 133.000 14.962,50
Tukang Kayu L.03b OH 0,0400 157.500 6.300,00
Kepala Tukang L.03 OH 0,0040 172.200 688,80
Mandor L.04 OH 0,0065 181.300 1.178,45
Jumlah Tenaga Kerja (A) 23.129,75
B BAHAN
List profil cornice gypsum lebih dari 10
M.44 f m' 1,1000 18.800 20.680,00
cm
Compound gypsum M.75 b zak 0,0525 60.000 3.150,00
Alkasit M.75 e kg 0,0053 28.000 148,40
Jumlah Harga Bahan (B) 23.978,40
C PERALATAN
79
27 Penutup plafon gypsum board uk. 1200 x2400 x9 mm / m²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,1000 133.000 13.300,00
Tukang Kayu L.03b OH 0,0500 157.500 7.875,00
Kepala Tukang L.03 OH 0,0050 172.200 861,00
Mandor L.04 OH 0,0050 181.300 906,50
Jumlah Tenaga Kerja (A) 22.942,50
B BAHAN
Gypsumboard 1200 x2400 x 9 mm M.43 c Lbr 0,3640 70.000 25.480,00
Paku - Sekrup gypsum M.71 m kg 0,1100 27.500 3.025,00
Jumlah Harga Bahan (B) 28.505,00
C PERALATAN
80
32 Penutup plafon Akustik ukuran 60x120 cm + rangka alumunium / m²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,5000 133.000 66.500,00
Tukang Kayu L.03b OH 0,5000 157.500 78.750,00
Kepala Tukang L.03 OH 0,0500 172.200 8.610,00
Mandor L.04 OH 0,0250 181.300 4.532,50
Jumlah Tenaga Kerja (A) 158.392,50
B BAHAN
Profil alumunium "T" M.74 a m' 3,6000 17.000 61.200,00
Kawat diameter 4 mm M. 68 b kg 0,1500 14.000 2.100,00
Ramset M.71 s a bh 1,0500 1.000 1.050,00
Akustik 60 x 120 cm M.43 i Lbr 1,5000 105.000 157.500,00
Jumlah Harga Bahan (B) 221.850,00
C PERALATAN
81
5 1m ² Pekerjaan Konstruksi Lantai Bambu / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,1500 133.000 19.950,00
Tukang Kayu L.03b OH 0,4500 157.500 70.875,00
Kepala Tukang L.03 OH 0,0450 172.200 7.749,00
Mandor L.04 OH 0,0080 181.300 1.450,40
Jumlah Tenaga Kerja (A) 100.024,40
B BAHAN
Bambu dia 5 - 7 Cm M.28 a btg 0,0280 14.400 403,20
Paku biasa 2"-5" M.71 a kg 0,1300 17.000 2.210,00
Jumlah Harga Bahan (B) 2.613,20
C PERALATAN
PEKERJAAN SANITASI
1 Memasang 1 buah kloset duduk/monoblok (sederhana) / bh
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 3,3000 133.000 438.900,00
Tukang Batu L.03a OH 1,1000 157.500 173.250,00
Kepala Tukang Batu L.03aa OH 0,0100 172.200 1.722,00
Mandor L.04 OH 0,0160 181.300 2.900,80
Jumlah Tenaga Kerja (A) 616.772,80
B BAHAN
Kloset duduk− sederhana M.150 a unit 1,0000 1.200.000 1.200.000,00
Perlengkapan % 0,0600 1.200.000 72.000,00
Jumlah Harga Bahan (B) 1.272.000,00
C PERALATAN
82
5 Memasang 1 buah kloset jongkok sedang / bh
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 1,0000 133.000 133.000,00
Tukang Batu L.03a OH 1,5000 157.500 236.250,00
Kepala Tukang Batu L.03aa OH 0,1500 172.200 25.830,00
Mandor L.04 OH 0,1600 181.300 29.008,00
Jumlah Tenaga Kerja (A) 424.088,00
B BAHAN
Kloset Jongkok - porselin M.150 e unit 1,0000 300.000 300.000,00
Semen Portland M.15 a kg 6,0000 1.450 8.700,00
Pasir Pasang M.14 b m³ 0,0100 250.000 2.500,00
Jumlah Harga Bahan (B) 311.200,00
C PERALATAN
83
9 Memasang 1 buah wastafel sederhana / bh
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 1,0000 133.000 133.000,00
Tukang Batu L.03a OH 1,0000 157.500 157.500,00
Kepala Tukang Batu L.03aa OH 0,1000 172.200 17.220,00
Mandor L.04 OH 0,0500 181.300 9.065,00
Jumlah Tenaga Kerja (A) 316.785,00
B BAHAN
Wastafel biasa standar lengkap M.152 c unit 1,0000 850.000 850.000,00
Semen Portland M.15 a kg 6,0000 1.450 8.700,00
Pasir Pasang M.14 b m³ 0,0100 250.000 2.500,00
Perlengkapan ls 0,1000 850.000 85.000,00
Jumlah Harga Bahan (B) 946.200,00
C PERALATAN
84
13 Memasang 1 buah bak mandi batu bata volume 0,3 m³ / bh
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 3,0000 133.000 399.000,00
Tukang Batu L.03a OH 1,5000 157.500 236.250,00
Kepala Tukang Batu L.03aa OH 0,3000 172.200 51.660,00
Mandor L.04 OH 0,0300 181.300 5.439,00
Jumlah Tenaga Kerja (A) 692.349,00
B BAHAN
Bata Merah Bakar Kelas II M.05 b bh 150,0000 850 127.500,00
Semen Portland M.15 a kg 120,0000 1.450 174.000,00
Pasir Pasang M.14 b m³ 0,3000 250.000 75.000,00
Keramik dinding 20 x 20 cm KW 1 M.83 g m² 4,5000 115.500 519.750,00
Semen Warna M.15 c kg 6,0000 18.500 111.000,00
Jumlah Harga Bahan (B) 1.007.250,00
C PERALATAN
85
18 Memasang pipa galvanis dia 1 1/4 " / m¹
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,0540 133.000 7.182,00
Tukang Batu L.03a OH 0,0900 157.500 14.175,00
Kepala Tukang Batu L.03aa OH 0,0090 172.200 1.549,80
Mandor L.04 OH 0,0270 181.300 4.895,10
Jumlah Tenaga Kerja (A) 27.801,90
B BAHAN
Pipa galvanis Ø 1 ¼" M.106 d m' 1,2000 37.900 45.480,00
Perlengkapan % 0,3500 37.900 132,65
Jumlah Harga Bahan (B) 45.612,65
C PERALATAN
86
23 Memasang pipa galvanis dia 4" / m¹
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,1350 133.000 17.955,00
Tukang Batu L.03a OH 0,2250 157.500 35.437,50
Kepala Tukang Batu L.03aa OH 0,0025 172.200 430,50
Mandor L.04 OH 0,0070 181.300 1.269,10
Jumlah Tenaga Kerja (A) 55.092,10
B BAHAN
Pipa galvanis Ø 4 " M.106 j m' 1,2000 73.816 88.579,20
Perlengkapan % 35,0000 73.816 25.835,60
Jumlah Harga Bahan (B) 114.414,80
C PERALATAN
87
28 Memasang pipa PVC tipe D dia 1 ¼" / m¹
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,0360 133.000 4.788,00
Tukang Batu L.03a OH 0,0600 157.500 9.450,00
Kepala Tukang Batu L.03aa OH 0,0060 172.200 1.033,20
Mandor L.04 OH 0,0020 181.300 362,60
Jumlah Tenaga Kerja (A) 15.633,80
B BAHAN
Pipa PVC Ø 1 ¼" D M.107 e m' 1,2000 7.400 8.880,00
Perlengkapan % 35,0000 7.400 2.590,00
Jumlah Harga Bahan (B) 11.470,00
C PERALATAN
88
33 Memasang pipa PVC tipe AW dia 2 ½" / m¹
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,0810 133.000 10.773,00
Tukang Batu L.03a OH 0,1350 157.500 21.262,50
Kepala Tukang Batu L.03aa OH 0,0135 172.200 2.324,70
Mandor L.04 OH 0,0040 181.300 725,20
Jumlah Tenaga Kerja (A) 35.085,40
B BAHAN
Pipa PVC dia 2 ½" AW M.107 j m' 1,2000 18.350 22.020,00
Perlengkapan % 35,0000 18.350 6.422,50
Jumlah Harga Bahan (B) 28.442,50
C PERALATAN
89
38 Memasang pipa PVC tipe D dia 4" / m¹
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,0810 133.000 10.773,00
Tukang Batu L.03a OH 0,1350 157.500 21.262,50
Kepala Tukang Batu L.03aa OH 0,0135 172.200 2.324,70
Mandor L.04 OH 0,0040 181.300 725,20
Jumlah Tenaga Kerja (A) 35.085,40
B BAHAN
Pipa PVC dia 4" D M.107 o m' 1,2000 23.375 28.050,00
Perlengkapan % 35,0000 23.375 8.181,25
Jumlah Harga Bahan (B) 36.231,25
C PERALATAN
90
43 Memasang 1 buah kran dia 3/4" atau 1/2" sederhana / bh
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,0100 133.000 1.330,00
Tukang Batu L.03a OH 0,4000 157.500 63.000,00
Kepala Tukang Batu L.03aa OH 0,0400 172.200 6.888,00
Mandor L.04 OH 0,0050 181.300 906,50
Jumlah Tenaga Kerja (A) 72.124,50
B BAHAN
Kran air sederhana M.153 a unit 1,0000 46.000 46.000,00
Seal Tape M.157 bh 0,0250 5.000 125,00
Jumlah Harga Bahan (B) 46.125,00
C PERALATAN
91
48 Memasang Shower Spray Setara TOTO
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,0100 133.000 1.330,00
Tukang Batu L.03a OH 0,4000 157.500 63.000,00
Kepala Tukang Batu L.03aa OH 0,0400 172.200 6.888,00
Mandor L.04 OH 0,0050 181.300 906,50
Jumlah Tenaga Kerja (A) 72.124,50
B BAHAN
Shower Spray−setara TOTO M.153 g unt 1,0000 250.000 250.000,00
Perlengkapan ls 10,0000 250.000 25.000,00
Jumlah Harga Bahan (B) 275.000,00
C PERALATAN
92
53 Memasang Roof drain / bh
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,0100 133.000 1.330,00
Tukang Batu L.03a OH 0,1000 157.500 15.750,00
Kepala Tukang Batu L.03aa OH 0,0100 172.200 1.722,00
Mandor L.04 OH 0,0050 181.300 906,50
Jumlah Tenaga Kerja (A) 19.708,50
B BAHAN
Roofdrain - M.154 e bh 1,2000 135.000 162.000,00
Jumlah Harga Bahan (B) 162.000,00
C PERALATAN
56 Membuat 1 unit sumur air tanah bor manual dalam 12 m' + pompa air listrik / bh
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 3,1620 133.000 420.546,00
Tukang Pipa L.03d OH 2,3100 157.500 363.825,00
Kepala Tukang L.03 OH 0,2320 172.200 39.950,40
Mandor L.04 OH 0,1580 181.300 28.645,40
Jumlah Tenaga Kerja (A) 852.966,80
B BAHAN
Pipa PVC dia 3/4" AW M.107 b m' 14,0000 4.950 69.300,00
Pipa PVC dia 2" D M.107 i m' 12,0000 8.625 103.500,00
Mesin Jet Pump kap.250 watt M.211 p bh 1,0000 4.000.000 4.000.000,00
Perlengkapan ls 0,3500 4.000.000 1.400.000,00
Jumlah Harga Bahan (B) 5.572.800,00
C PERALATAN
93
57 Membuat 1 unit tanki septik sederhana kapasitas Ø 1,2 m dalam 1,2 m / bh
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 5,4400 133.000 723.520,00
Tukang Batu L.03a OH 2,1810 157.500 343.507,50
Tukang Pipa L.03d OH 0,3200 157.500 50.400,00
Kepala Tukang L.03 OH 0,2500 172.200 43.050,00
Mandor L.04 OH 0,3080 181.300 55.840,40
Jumlah Tenaga Kerja (A) 1.216.317,90
B BAHAN
Bata Merah Bakar Kelas I M.05 a bh 441,0000 1.150 507.150,00
Semen Portland M.15 a kg 126,1700 1.450 182.946,50
Pasir Pasang M.14 b m³ 0,4390 250.000 109.750,00
Batu Pecah - Koral 2/3 M.12 c m³ 0,1300 365.000 47.450,00
Baja Polos U 24 M.55 e kg 11,4400 12.000 137.280,00
Kawat Beton M.68 Kg 0,1640 28.000 4.592,00
Pasir Beton M.14 m³ 0,0930 311.000 28.923,00
Pasir Urug M.14 d m³ 0,1060 160.000 16.960,00
Kayu balok, kaso-kaso Klas IV M.35 b m³ 0,0070 1.800.000 12.600,00
Multiplek tebal 9 mm M 39 d Lbr 0,6750 187.550 126.596,25
Paku biasa 2"-5" M.71 a kg 0,7100 17.000 12.070,00
Pipa PVC dia 2" D M.107 i m' 1,0000 8.625 8.625,00
Pipa PVC dia 4" D M.107 o m' 1,7000 23.375 39.737,50
Perlengkapan Pipa pipa % 0,3500 32.000 11.200,00
Jumlah Harga Bahan (B) 1.245.880,25
C PERALATAN
58 Membuat 1 unit tanki septik kapasitas 1,7x0,85 m dalam 1,3 m (vol. 1,88 m³ u/ 5 pemakai) / bh
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 8,6480 133.000 1.150.184,00
Tukang Batu L.03a OH 3,4860 157.500 549.045,00
Tukang Pipa L.03d OH 0,5000 157.500 78.750,00
Kepala Tukang L.03 OH 0,3990 172.200 68.707,80
Mandor L.04 OH 0,4820 181.300 87.386,60
Jumlah Tenaga Kerja (A) 1.934.073,40
B BAHAN
Bata Merah Bakar Kelas I M.05 a bh 722,0000 1.150 830.300,00
Semen Portland M.15 a kg 304,8600 1.450 442.047,00
Pasir Pasang M.14 b m³ 0,5890 250.000 147.250,00
Batu Pecah - Koral 2/3 M.12 c m³ 0,2000 365.000 73.000,00
Baja Polos U 24 M.55 e kg 31,7000 12.000 380.400,00
Kawat Beton M.68 Kg 0,4450 28.000 12.460,00
Pasir Beton M.14 m³ 0,1340 311.000 41.674,00
Pasir Urug M.14 d m³ 0,1380 160.000 22.080,00
Kayu balok, kaso-kaso Klas IV M.35 b m³ 0,0430 1.800.000 77.400,00
Multiplek tebal 9 mm M 39 d Lbr 0,8000 187.550 150.040,00
Paku biasa 2"-5" M.71 a kg 0,9200 17.000 15.640,00
Pipa PVC dia 2" D M.107 i m' 3,0000 8.625 25.875,00
Pipa PVC dia 4" D M.107 o m' 1,7000 23.375 39.737,50
Perlengkapan Pipa pipa ls 0,3500 32.000 11.200,00
Jumlah Harga Bahan (B) 2.269.103,50
C PERALATAN
94
60 Membuat 1 unit resapan Ø 0,8 m (digali 1 m) dalam 1 m (digali 1,9 m) kap. 0,5 m³
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 1,0500 133.000 139.650,00
Tukang Pipa L.03d OH 0,2700 157.500 42.525,00
Kepala Tukang L.03 OH 0,0270 172.200 4.649,40
Mandor L.04 OH 0,0970 181.300 17.586,10
Jumlah Tenaga Kerja (A) 204.410,50
B BAHAN
Batu Pecah - Koral 2/3 M.12 c m³ 0,1070 365.000 39.055,00
Ijuk M.30 a kg 0,7160 10.000 7.160,00
Pipa PVC dia 4" D M.107 o m' 2,0000 23.375 46.750,00
Jumlah Harga Bahan (B) 92.965,00
C PERALATAN
95
65 Memasang 1 unit septictank pabrikasi kap. 8 m³
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 1,2000 133.000 159.600,00
Mandor L.04 OH 0,5500 181.300 99.715,00
Galian Tanah
Pekerja L.01 OH 12,1500 133.000 1.615.950,00
Mandor L.04 OH 0,6075 181.300 110.139,75
Jumlah Tenaga Kerja (A) 1.985.404,75
B BAHAN
Septic Tank pabrikasi kapasitas 8 m³ M.160 f bh 1,0000 36.500.000 36.500.000,00
Pasir Urug M.14 d m³ 1,2000 160.000 192.000,00
Jumlah Harga Bahan (B) 36.692.000,00
C PERALATAN
PEKERJAAN PENGECATAN
1 Mengikis/mengerok permukaan cat lama / m ²
Pengecatan 1 lapis plamur, 1 lapis cat dasr, 2 lapis cat penutup
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,1500 133.000 19.950,00
Mandor L.04 OH 0,0030 181.300 543,90
Jumlah Tenaga Kerja (A) 20.493,90
B BAHAN
Soda api M.125 d kg 0,2000 15.000 3.000,00
Amplas Sedang M.03 b m 0,2000 9.500 19,00
Jumlah Harga Bahan (B) 3.019,00
C PERALATAN
96
3 Pengecatan dengan cat KW 2 bidang kayu baru / m ²
Pengecatan 1 lapis plamur, 1 lapis cat dasr, 2 lapis cat penutup
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,0700 133.000 9.310,00
Tukang Cat L.03f OH 0,0090 157.500 1.417,50
Kepala Tukang Cat L.03ae OH 0,0063 172.200 1.076,25
Mandor L.04 OH 0,0031 181.300 566,56
Jumlah Tenaga Kerja (A) 12.370,31
B BAHAN
Cat meni kayu M.115 h kg 0,2000 35.000 7.000,00
Plamir kayu M.115c kg 0,1500 45.000 6.750,00
Cat dasar kayu/besi KW 2 M.115 k kg 0,1700 45.000 7.650,00
Cat penutup kayu/besi KW 2 M.115 l kg 0,2600 65.000 16.900,00
Kuas M.116 w bh 0,0100 17.500 175,00
Thinner B M.115 q Ltr 0,0300 18.000 540,00
Amplas Sedang M.03 b m 0,2000 9.500 19,00
Jumlah Harga Bahan (B) 39.034,00
C PERALATAN
97
7 Pengecatan bidang kayu dengan melamik / m ²
Pengecatan 1 lapis plamur, 1 lapis cat dasr, 2 lapis cat penutup
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,0700 133.000 9.310,00
Tukang Cat L.03f OH 0,3000 157.500 47.250,00
Kepala Tukang Cat L.03ae OH 0,0300 172.200 5.166,00
Mandor L.04 OH 0,0150 181.300 2.719,50
Jumlah Tenaga Kerja (A) 64.445,50
B BAHAN
Wood Filler M.115 v kg 0,1500 45.000 6.750,00
Sanding sealer M.115 v a kg 0,1700 65.000 11.050,00
Wood Stain M.115 v b kg 0,2600 80.000 20.800,00
Melamic M.115 v c kg 0,0500 75.000 3.750,00
Thinner A M.115 r Ltr 0,6000 26.000 15.600,00
Amplas Sedang M.03 b m 0,6000 9.500 57,00
Jumlah Harga Bahan (B) 58.007,00
C PERALATAN
98
12 Pengecatan tembok baru dg wall sealer - cat penutup KW 1 / m ²
Pengecatan 1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,0200 133.000 2.660,00
Tukang Cat L.03f OH 0,0625 157.500 9.843,75
Kepala Tukang Cat L.03ae OH 0,0063 172.200 1.076,25
Mandor L.04 OH 0,0031 181.300 566,56
Jumlah Tenaga Kerja (A) 14.146,56
B BAHAN
Wall sealer M.115 g kg 0,1000 39.100 3.910,00
Cat dasar tembok - beton M.116 a kg 0,1000 30.000 3.000,00
Cat Tembok - Acrylic Emulsion kw1 M.116 h kg 0,2600 70.000 18.200,00
Jumlah Harga Bahan (B) 25.110,00
C PERALATAN
16 Memasang wallpaper / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,0200 133.000 2.660,00
Tukang Cat L.03f OH 0,2000 157.500 31.500,00
Kepala Tukang Cat L.03ae OH 0,0200 172.200 3.444,00
Mandor L.04 OH 0,0025 181.300 453,25
Jumlah Tenaga Kerja (A) 38.057,25
B BAHAN
Lem Kuning M.125 b kg 0,2000 60.000 12.000,00
Wall Paper M.125 e m² 1,2000 50.000 60.000,00
Jumlah Harga Bahan (B) 72.000,00
C PERALATAN
Jumlah Harga Alat (C) -
D Jumlah ( A + B + C ) 110.057,25
E Overhead & Profit 15% xD 16.508,59
F Harga Satuan Pekerjaan (D + E) 126.565,84
G Dibulatkan 126.565,00
99
17 Pengecatan permukaan baja 1 m² dgn meni besi / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,0200 133.000 2.660,00
Tukang Cat L.03f OH 0,2000 157.500 31.500,00
Kepala Tukang Cat L.03ae OH 0,0200 172.200 3.444,00
Mandor L.04 OH 0,0025 181.300 453,25
Jumlah Tenaga Kerja (A) 38.057,25
B BAHAN
Kuas M.116 w bh 0,0100 17.500 175,00
Terpentin M.115 r a Ltr 0,0100 15.000 150,00
Cat meni besi M.115 i kg 0,1000 62.700 6.270,00
Jumlah Harga Bahan (B) 6.595,00
C PERALATAN
100
21 Pengecatan permukaan baja tiap 1 m² dengan Cat KW 2/ m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,0200 133.000 2.660,00
Tukang Cat L.03f OH 0,2000 157.500 31.500,00
Kepala Tukang Cat L.03ae OH 0,0200 172.200 3.444,00
Mandor L.04 OH 0,0025 181.300 453,25
Jumlah Tenaga Kerja (A) 38.057,25
B BAHAN
Kuas M.116 w bh 0,0100 17.500 175,00
Terpentin M.115 r a Ltr 0,0100 15.000 150,00
Amplas Sedang M.03 b m 0,6000 9.500 57,00
Cat penutup kayu/besi KW 2 M.115 l kg 0,1000 65.000 6.500,00
Jumlah Harga Bahan (B) 6.882,00
C PERALATAN
101
PEKERJAAN INSTALASI LISTRIK
1 Pasang instalasi lampu dg NYM 3x2,5 mm² tiap 1 titik (tidak termasuk fitting, sakelar & lampu) / ttk
Catatan: Tdk termasuk fitting lampu, sakelar & lampu. Asumsi tinggi plafond 4 m', bentang ruang 8 m', uk. Kabel standar PUIL 2000
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Tukang Las Listrik L.03i OH 0,3000 157.500 47.250,00
Pekerja L.01 OH 0,1500 133.000 19.950,00
Mandor L.04 OH 0,0150 181.300 2.719,50
Jumlah Tenaga Kerja (A) 69.919,50
B BAHAN
Kabel NYM 3x2,5 mm² M.200 h m' 10,0000 17.000 170.000,00
Conduit pipa PVC dia ⅝" C M.204 b m' 10,0000 10.900 109.000,00
Tee dos M.204 c bh 1,0000 2.800 2.800,00
Inbow doos M.204 d bh 1,0000 2.600 2.600,00
Sock M.204 e bh 3,0000 1.200 3.600,00
Klem conduit M.204 f bh 9,0000 1.200 10.800,00
Lastdop M.204 i bh 3,0000 800 2.400,00
Flexible pipe M.204 k m' 1,0000 9.000 9.000,00
Elbow M.204 l bh 2,0000 5.400 10.800,00
Paku, sekrup, fisher (10% harga conduit) 0,1000 42.800 42,80
Jumlah Harga Bahan (B) 321.042,80
C PERALATAN
2 Pasang instalasi lampu dg NYM 2x2,5 mm² tiap 1 titik (tidak termasuk fitting, sakelar & lampu) / ttk
Catatan: Tdk termasuk fitting lampu, sakelar & lampu. Asumsi tinggi plafond 4 m', bentang ruang 8 m', uk. Kabel standar PUIL 2000
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Tukang Las Listrik L.03i OH 0,3000 157.500 47.250,00
Pekerja L.01 OH 0,1500 133.000 19.950,00
Mandor L.04 OH 0,0150 181.300 2.719,50
Jumlah Tenaga Kerja (A) 69.919,50
B BAHAN
Kabel NYM 2x2,5 mm² M.200 i m' 10,0000 15.900 159.000,00
Conduit pipa PVC dia ⅝" C M.204 b m' 10,0000 10.900 109.000,00
Tee dos M.204 c bh 1,0000 2.800 2.800,00
Inbow doos M.204 d bh 1,0000 2.600 2.600,00
Sock M.204 e bh 3,0000 1.200 3.600,00
Klem conduit M.204 f bh 9,0000 1.200 10.800,00
Lastdop M.204 i bh 3,0000 800 2.400,00
Flexible pipe M.204 k m' 1,0000 9.000 9.000,00
Elbow M.204 l bh 2,0000 5.400 10.800,00
Paku, sekrup, fisher (10% harga conduit) 0,1000 109.000 109,00
Jumlah Harga Bahan (B) 310.109,00
C PERALATAN
3 Pasang instalasi lampu dg NYM 2x1,5 mm² tiap 1 titik (tidak termasuk fitting, sakelar & lampu) / ttk
Catatan: Tdk termasuk fitting lampu, sakelar & lampu. Asumsi tinggi plafond 4 m', bentang ruang 8 m', uk. Kabel standar PUIL 2000
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Tukang Las Listrik L.03i OH 0,3000 157.500 47.250,00
Pekerja L.01 OH 0,1500 133.000 19.950,00
Mandor L.04 OH 0,0150 181.300 2.719,50
Jumlah Tenaga Kerja (A) 69.919,50
B BAHAN
Kabel NYM 2x1,5 mm² M.200 j m' 10,0000 11.300 113.000,00
Conduit pipa PVC dia ⅝" C M.204 b m' 10,0000 10.900 109.000,00
Tee dos M.204 c bh 1,0000 2.800 2.800,00
Inbow doos M.204 d bh 1,0000 2.600 2.600,00
Sock M.204 e bh 3,0000 1.200 3.600,00
Klem conduit M.204 f bh 9,0000 1.200 10.800,00
Lastdop M.204 i bh 3,0000 800 2.400,00
Flexible pipe M.204 k m' 1,0000 9.000 9.000,00
Elbow M.204 l bh 2,0000 5.400 10.800,00
Paku, sekrup, fisher (10% harga conduit) 0,1000 109.000 109,00
Jumlah Harga Bahan (B) 264.109,00
C PERALATAN
102
5 Pasang instalasi stop kontak tiap 1 titik (tidak termasuk stop kontak)
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Tukang Las Listrik L.03i OH 0,3000 157.500 47.250,00
Pekerja L.01 OH 0,1500 133.000 19.950,00
Mandor L.04 OH 0,0150 181.300 2.719,50
Jumlah Tenaga Kerja (A) 69.919,50
B BAHAN
Kabel NYM 3x2,5 mm² M.200 h m' 10,0000 17.000 170.000,00
Conduit pipa PVC dia ⅝" C M.204 b m' 10,0000 10.900 109.000,00
Tee dos M.204 c bh 1,0000 2.800 2.800,00
Inbow doos M.204 d bh 1,0000 2.600 2.600,00
Sock M.204 e bh 3,0000 1.200 3.600,00
Klem conduit M.204 f bh 9,0000 1.200 10.800,00
Lastdop M.204 i bh 3,0000 800 2.400,00
Flexible pipe M.204 k m' 2,0000 9.000 18.000,00
Elbow M.204 l bh 10,0000 5.400 54.000,00
Paku, sekrup, fisher (10% harga conduit) % 10,0000 42.800 4.280,00
Jumlah Harga Bahan (B) 377.480,00
C PERALATAN
6 Pasang instalasi stop kontak lebih dari 500 watt tiap 1 titik (tidak termasuk stop kontak)
Catatan: Stop kontak tidak dimasukkan dalam analisis, tergantung spesifikasi teknis dan merek yang diinginkan.
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Tukang Las Listrik L.03i OH 0,5000 157.500 78.750,00
Pekerja L.01 OH 0,2500 133.000 33.250,00
Mandor L.04 OH 0,0250 181.300 4.532,50
Jumlah Tenaga Kerja (A) 116.532,50
B BAHAN
Kabel NYM 3x4 mm² M.200 g m' 12,0000 34.000 408.000,00
Conduit pipa PVC dia ⅝" C M.204 b m' 12,0000 10.900 130.800,00
Outlet Box Metal M.203 i bh 1,0000 23.000 23.000,00
Tee dos M.204 c bh 1,0000 2.800 2.800,00
Inbow doos M.204 d bh 1,0000 2.600 2.600,00
Sock M.204 e bh 9,0000 1.200 10.800,00
Klem conduit M.204 f bh 20,0000 1.200 24.000,00
Lastdop M.204 i bh 3,0000 800 2.400,00
Elbow M.204 l bh 4,0000 5.400 21.600,00
Paku, sekrup, fisher (10% harga conduit) % 10,0000 81.900 8.190,00
Jumlah Harga Bahan (B) 634.190,00
C PERALATAN
8 Pasang instalasi + tiang antena TV tiap 1 titik (tidak termasuk socket & antena)
Catatan: Socket & antena tidak dimasukkan dalam analisis, tergantung spesifikasi teknis dan merek yang diinginkan.
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Tukang Las Listrik L.03i OH 0,3000 157.500 47.250,00
Pekerja L.01 OH 0,1500 133.000 19.950,00
Mandor L.04 OH 0,0150 181.300 2.719,50
Jumlah Tenaga Kerja (A) 69.919,50
B BAHAN
Kabel antena TV M.201 a m' 20,0000 4.500 90.000,00
Conduit pipa PVC dia ⅝" C M.204 b m' 20,0000 10.900 218.000,00
Inbow doos M.204 d bh 1,0000 2.600 2.600,00
Sock M.204 e bh 5,0000 1.200 6.000,00
Klem conduit M.204 f bh 14,0000 1.200 16.800,00
Klem pipa besi 3/4" M.204 g bh 2,0000 5.500 11.000,00
Pipa galvanis Ø ¾ " M.106 b m' 2,0000 30.300 60.600,00
Paku, sekrup, fisher (10% harga conduit) % 10,0000 56.200 5.620,00
Jumlah Harga Bahan (B) 410.620,00
C PERALATAN
Jumlah Harga Alat (C) -
D Jumlah ( A + B + C ) 480.539,50
E Overhead & Profit 15% xD 72.080,93
F Harga Satuan Pekerjaan (D + E) 552.620,43
G Dibulatkan 552.620,00
103
9 Pasang instalasi penangkal petir / ttk
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Tukang Las Listrik L.03i OH 0,3000 157.500 47.250,00
Pekerja L.01 OH 0,1500 133.000 19.950,00
Mandor L.04 OH 0,0150 181.300 2.719,50
Jumlah Tenaga Kerja (A) 69.919,50
B BAHAN
Kabel BC 50 mm M.201 d m' 20,0000 51.800 1.036.000,00
Splitzen dia. 25 mm tinggi tiang 1m Solid
M.208 a bh 2,0000 122.800 245.600,00
Copper
Grounding Sistem M.208 b bh 1,0000 1.500.000 1.500.000,00
Bak kontrol pas.batu bata 30 x 30 cm
A.5.1.1.15 bh 1,0000 702.123 702.123,00
tinggi 35 cm
Klem BC 50 mm2 M.208 d bh 20,0000 4.000 80.000,00
Pipa galvanis Ø 1" M.106 c m' 2,0000 34.616 69.232,00
Material bantu % 35,0000 2.415.339 845.368,65
Jumlah Harga Bahan (B) 4.478.323,65
C PERALATAN
10 Pasang instalasi telepon tiap 1 titik (tidak termasuk outlet, pesawat telepon & sambungan Telkom)
Catatan: Outlet & pesawat telepon tidak dimasukkan dalam analisis, tergantung spesifikasi teknis dan merek yang diinginkan.
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Tukang Las Listrik L.03i OH 0,3000 157.500 47.250,00
Pekerja L.01 OH 0,1500 133.000 19.950,00
Mandor L.04 OH 0,0150 181.300 2.719,50
Jumlah Tenaga Kerja (A) 69.919,50
B BAHAN
Kabel telepon M.201 b m' 20,0000 4.000 80.000,00
Conduit pipa PVC dia ⅝" C M.204 b m' 20,0000 10.900 218.000,00
Inbow doos M.204 d bh 1,0000 2.600 2.600,00
Sock M.204 e bh 6,0000 1.200 7.200,00
Klem conduit M.204 f bh 14,0000 1.200 16.800,00
Klem pipa besi 3/4" M.204 g bh 2,0000 5.500 11.000,00
Paku, sekrup, fisher (10% harga conduit) % 10,0000 25.400 2.540,00
Jumlah Harga Bahan (B) 338.140,00
C PERALATAN
11 Pasang instalasi telepon paralel/extension line tiap 1 titik (tidak termasuk outlet, pesawat telepon)
Catatan: Outlet & pesawat telepon tidak dimasukkan dalam analisis, tergantung spesifikasi teknis dan merek yang diinginkan.
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Tukang Las Listrik L.03i OH 0,3000 157.500 47.250,00
Pekerja L.01 OH 0,1500 133.000 19.950,00
Mandor L.04 OH 0,0150 181.300 2.719,50
Jumlah Tenaga Kerja (A) 69.919,50
B BAHAN
Kabel telepon M.201 b m' 12,0000 4.000 48.000,00
Conduit pipa PVC dia ⅝" C M.204 b m' 12,0000 10.900 130.800,00
Inbow doos M.204 d bh 1,0000 2.600 2.600,00
Sock M.204 e bh 3,0000 1.200 3.600,00
Klem conduit M.204 f bh 9,0000 1.200 10.800,00
Klem pipa besi 3/4" M.204 g bh 2,0000 5.500 11.000,00
Paku, sekrup, fisher (10% harga conduit) % 10,0000 25.400 2.540,00
Jumlah Harga Bahan (B) 209.340,00
C PERALATAN
104
13 Pasang Panel Pembagi Daya 2200 VA / 10 A (3 grup @ 10 A) tiap 1 unit
Catatan: Belum termasuk penyambungan daya listrik PLN
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Tukang Las Listrik L.03i OH 0,8000 157.500 126.000,00
Pekerja L.01 OH 0,4000 133.000 53.200,00
Mandor L.04 OH 0,0400 181.300 7.252,00
Jumlah Tenaga Kerja (A) 186.452,00
B BAHAN
Kabel NYM 3x4 mm² M.200 g m' 10,0000 34.000 340.000,00
Kabel NYM 3x2,5 mm² M.200 h m' 30,0000 17.000 510.000,00
Conduit pipa PVC dia ⅝" C M.204 b m' 40,0000 10.900 436.000,00
MCB box isi 4 M.202 a bh 1,0000 85.000 85.000,00
MCB 10 A M.202 d bh 4,0000 90.000 360.000,00
Tee dos M.204 c bh 4,0000 2.800 11.200,00
Sock M.204 e bh 10,0000 1.200 12.000,00
Klem conduit M.204 f bh 27,0000 1.200 32.400,00
Lastdop M.204 i bh 12,0000 800 9.600,00
Elbow M.204 l bh 2,0000 5.400 10.800,00
Paku, sekrup, fisher (10% harga conduit) % 10,0000 248.300 24.830,00
Jumlah Harga Bahan (B) 1.831.830,00
C PERALATAN
105
17 Pasang 1 buah lampu down light PLC 18 watt
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Tukang Las Listrik L.03i OH 0,1000 157.500 15.750,00
Pekerja L.01 OH 0,0500 133.000 6.650,00
Jumlah Tenaga Kerja (A) 22.400,00
B BAHAN
Lampu down light PLC 18 watt M.206 d bh 1,0000 120.000 120.000,00
Asesori % 1,0000 120.000 1.200,00
Jumlah Harga Bahan (B) 121.200,00
C PERALATAN
106
22 Pasang 1 buah lampu PLC 18 W + battery nicad
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Tukang Las Listrik L.03i OH 0,1000 157.500 15.750,00
Pekerja L.01 OH 0,0500 133.000 6.650,00
Jumlah Tenaga Kerja (A) 22.400,00
B BAHAN
Lampu Downlight PLC 18 Watt with
M.206 t bh 1,0000 712.000 712.000,00
battery Nicad
Asesori % 1,0000 712.000 7.120,00
Jumlah Harga Bahan (B) 719.120,00
C PERALATAN
107
27 Pasang 1 buah lampu TL 2x18 Balk
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Tukang Las Listrik L.03i OH 0,1200 157.500 18.900,00
Pekerja L.01 OH 0,0600 133.000 7.980,00
Jumlah Tenaga Kerja (A) 26.880,00
B BAHAN
Lampu TL 2x18 watt Balk M.206 l bh 1,0000 141.000 141.000,00
Asesori % 1,0000 141.000 1.410,00
Jumlah Harga Bahan (B) 142.410,00
C PERALATAN
108
32 Pasang 1 buah lampu Taman
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Tukang Las Listrik L.03i OH 0,3500 157.500 55.125,00
Pekerja L.01 OH 0,1750 133.000 23.275,00
Jumlah Tenaga Kerja (A) 78.400,00
B BAHAN
Lampu taman M.206 q bh 1,0000 1.105.000 1.105.000,00
Asesori % 1,0000 1.105.000 11.050,00
Jumlah Harga Bahan (B) 1.116.050,00
C PERALATAN
109
37 Pasang 1 buah out let TV
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Tukang Las Listrik L.03i OH 0,3500 157.500 55.125,00
Pekerja L.01 OH 0,1750 133.000 23.275,00
Jumlah Tenaga Kerja (A) 78.400,00
B BAHAN
Outlet TV−Broco M.202 qa bh 1,0000 45.000 45.000,00
Asesori % 1,0000 45.000 450,00
Jumlah Harga Bahan (B) 45.450,00
C PERALATAN
110
Penerangan Jalan Umum (PJU)
1 Pekerjaan Pemasangan Tiang Bulat 7 m / Unit
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,7500 133.000 99.750,00
Tukang L.02 OH 0,2500 157.500 39.375,00
Mandor L.04 OH 0,0625 181.300 11.331,25
Jumlah Tenaga Kerja (A) 150.456,25
B BAHAN
Tiang Bulat Parabola Cabang 1 h=7 m M.226 d Bh 1,0000 3.118.500 3.118.500,00
Anchor Bolt d=19 mm M.227 c Bh 4,0000 63.500 254.000,00
Jumlah Harga Bahan (B) 3.372.500,00
C PERALATAN
Mobil Pick Up E.107 Jam 0,3500 350.000 122.500,00
Alat Bantu K3 dan Tanda Lalu Lintas E.106 jam 0,2500 25.000 6.250,00
Jumlah Harga Alat (C) 128.750,00
D Jumlah ( A + B + C ) 3.651.706,25
E Overhead & Profit 15% xD 547.755,94
F Harga Satuan Pekerjaan (D + E) 4.199.462,19
G Dibulatkan 4.199.462,00
111
6 Pekerjaan Pemasangan Armatur Lengkap Sodium 150 Watt Tipe Cobra / Unit
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,3000 133.000 39.900,00
Tukang L.02 OH 0,1000 157.500 15.750,00
Mandor L.04 OH 0,0250 181.300 4.532,50
Jumlah Tenaga Kerja (A) 60.182,50
B BAHAN
Armature Lengkap Sodium 150 Watt M.221 a Set 1,0000 2.258.000 2.258.000,00
Jumlah Harga Bahan (B) 2.258.000,00
C PERALATAN
Mobil Pick Up E.107 m² 0,5000 350.000 175.000,00
Alat Bantu K3 dan Tanda Lalu Lintas E.106 jam 0,2500 25.000 6.250,00
Jumlah Harga Alat (C) 181.250,00
D Jumlah ( A + B + C ) 2.499.432,50
E Overhead & Profit 15% xD 374.914,88
F Harga Satuan Pekerjaan (D + E) 2.874.347,38
G Dibulatkan 2.874.347,00
7 Pekerjaan Pemasangan Armatur Lengkap Sodium 250 Watt Tipe Cobra / Unit
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,3000 133.000 39.900,00
Tukang L.02 OH 0,1000 157.500 15.750,00
Mandor L.04 OH 0,0250 181.300 4.532,50
Jumlah Tenaga Kerja (A) 60.182,50
B BAHAN
Armature Lengkap Sodium 250 Watt M.221 b Set 1,0000 2.324.000 2.324.000,00
Jumlah Harga Bahan (B) 2.324.000,00
C PERALATAN
Mobil Pick Up E.107 m² 0,5000 350.000 175.000,00
Alat Bantu K3 dan Tanda Lalu Lintas E.106 jam 0,2500 25.000 6.250,00
Jumlah Harga Alat (C) 181.250,00
D Jumlah ( A + B + C ) 2.565.432,50
E Overhead & Profit 15% xD 384.814,88
F Harga Satuan Pekerjaan (D + E) 2.950.247,38
G Dibulatkan 2.950.247,00
8 Pekerjaan Pemasangan Armatur Lengkap Sodium 250 Watt Tipe Keong / Unit
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,3000 133.000 39.900,00
Tukang L.02 OH 0,1000 157.500 15.750,00
Mandor L.04 OH 0,0250 181.300 4.532,50
Jumlah Tenaga Kerja (A) 60.182,50
B BAHAN
Armature Lengkap Sodium 250 Watt
M.221 c Set 1,0000 4.966.500 4.966.500,00
Keong
Jumlah Harga Bahan (B) 4.966.500,00
C PERALATAN
Mobil Pick Up E.107 m² 0,5000 350.000 175.000,00
Alat Bantu K3 dan Tanda Lalu Lintas E.106 jam 0,2500 25.000 6.250,00
Jumlah Harga Alat (C) 181.250,00
D Jumlah ( A + B + C ) 5.207.932,50
E Overhead & Profit 15% xD 781.189,88
F Harga Satuan Pekerjaan (D + E) 5.989.122,38
G Dibulatkan 5.989.122,00
112
11 Pekerjaan Pemasangan Aksesoris jaringan / Unit
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,1000 133.000 13.300,00
Tukang L.02 OH 0,0500 157.500 7.875,00
Mandor L.04 OH 0,0167 181.300 3.027,71
Jumlah Tenaga Kerja (A) 24.202,71
B BAHAN
Wedge Cable Clamp M.227 b Bh 2,0000 8.650 17.300,00
Stainless Steel Strip M.225 i m' 1,0000 9.200 9.200,00
Stopping Buckle M.227 f Bh 1,0000 3.450 3.450,00
Link 25 x 25 mm M.225 f Bh 2,0000 3.450 6.900,00
Jumlah Harga Bahan (B) 36.850,00
C PERALATAN
Mobil Pick Up E.107 m² 0,0300 350.000 10.500,00
Alat Bantu K3 dan Tanda Lalu Lintas E.106 jam 0,2500 25.000 6.250,00
Jumlah Harga Alat (C) 16.750,00
D Jumlah ( A + B + C ) 77.802,71
E Overhead & Profit 15% xD 11.670,41
F Harga Satuan Pekerjaan (D + E) 89.473,12
G Dibulatkan 89.473,00
113
15 Pekerjaan Pemasangan Box APP Gendong daya 1300 VA / Unit
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,9857 133.000 131.098,10
Tukang L.02 OH 0,9857 157.500 155.247,75
Mandor L.04 OH 0,4929 181.300 89.362,77
Jumlah Tenaga Kerja (A) 375.708,62
B BAHAN
Wedge Cable Clamp M.227 b Bh 2,0000 8.650 17.300,00
Stainless Steel Strip M.225 i m' 6,0000 9.200 55.200,00
Stopping Buckle M.227 f Bh 8,0000 3.450 27.600,00
Link 25 x 25 mm M.225 f Bh 6,0000 3.450 20.700,00
Tap Connector 10 - 35 mm M.227 g Bh 4,0000 10.500 42.000,00
Kabel TIC 2 x 10 mm M.201 f m' 18,0000 7.500 135.000,00
Box APP 20x30x15 Cm Tebal Plat 1,2 mm M.223 a Bh 1,0000 393.750 393.750,00
Box APP 30x40x20 Cm Tebal Plat 1,2 mm M.223 b Bh 1,0000 719.250 719.250,00
Foto Cell 6 A m.225 d Bh 1,0000 112.600 112.600,00
Contactor Magnet 220 VAC 40 A M.225 Bh 1,0000 693.000 693.000,00
Kabel NYM 3x1,5 mm² M.200 o m' 2,0000 15.000 30.000,00
Selang Fleksibel 1,25 " M.225 h m' 1,0000 14.400 14.400,00
Pipa PVC dia 1" AW M.107 c m' 1,0000 6.875 6.875,00
Isolasi M.204 j glg 1,0000 5.000 5.000,00
BPUJL-1300 VA M.212 c SS 0,8000 3.273.600 2.618.880,00
Jumlah Harga Bahan (B) 4.891.555,00
C PERALATAN
Mobil Pick Up E.107 m² 0,9860 350.000 345.100,00
Alat Bantu K3 dan Tanda Lalu Lintas E.106 jam 0,2500 25.000 6.250,00
Jumlah Harga Alat (C) 351.350,00
D Jumlah ( A + B + C ) 5.618.613,62
E Overhead & Profit 15% xD 842.792,04
F Harga Satuan Pekerjaan (D + E) 6.461.405,66
G Dibulatkan 6.461.405,00
114
19 Pekerjaan Pemasangan Kabel NYGBY 3 x 2,5 mm / Unit
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,0286 133.000 3.799,81
Tukang L.02 OH 0,0143 157.500 2.250,68
Mandor L.04 OH 0,0048 181.300 862,99
Jumlah Tenaga Kerja (A) 6.913,47
B BAHAN
Kabel NYFGBY 3x2,5 mm² M.200 d m' 1,0000 35.000 35.000,00
Jumlah Harga Bahan (B) 35.000,00
C PERALATAN
Mobil Pick Up E.107 m² 0,1000 350.000 35.000,00
Alat Bantu K3 dan Tanda Lalu Lintas E.106 jam 0,2500 25.000 6.250,00
Jumlah Harga Alat (C) 41.250,00
D Jumlah ( A + B + C ) 83.163,47
E Overhead & Profit 15% xD 12.474,52
F Harga Satuan Pekerjaan (D + E) 95.637,99
G Dibulatkan 95.637,00
115
23 Pekerjaan Pemasangan Jaringan Kabel Bawah Tanah Tiang Dekoratif / Unit
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,0286 133.000 3.799,81
Tukang L.02 OH 0,0143 157.500 2.250,68
Mandor L.04 OH 0,0048 181.300 862,99
Jumlah Tenaga Kerja (A) 6.913,47
B BAHAN
Kabel NYYGBY 4x 4 mm² NYR/FGbY M.200 c m' 1,0000 46.300 46.300,00
CCO M.227 p bh 3,0000 6.500 19.500,00
Heatshrink M.227 e Bh 0,5000 12.600 6.300,00
Jumlah Harga Bahan (B) 72.100,00
C PERALATAN
Mobil Pick Up E.107 m² 0,1000 350.000 35.000,00
Alat Bantu K3 dan Tanda Lalu Lintas E.106 jam 0,2500 25.000 6.250,00
Jumlah Harga Alat (C) 41.250,00
D Jumlah ( A + B + C ) 120.263,47
E Overhead & Profit 15% xD 18.039,52
F Harga Satuan Pekerjaan (D + E) 138.302,99
G Dibulatkan 138.302,00
116
27 Pekerjaan Galian Kabel / m3
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,1500 133.000 19.950,00
Tukang Gali L.03e OH 0,0060 157.500 945,00
Jumlah Tenaga Kerja (A) 20.895,00
B BAHAN
Jumlah Harga Bahan (B)
C PERALATAN
Jumlah Harga Alat (C) -
D Jumlah ( A + B + C ) 20.895,00
E Overhead & Profit 15% xD 3.134,25
F Harga Satuan Pekerjaan (D + E) 24.029,25
G Dibulatkan 24.029,00
117
32 Pekerjaan Penggantian Box APP Gendong / Unit
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,9857 133.000 131.098,10
Tukang L.02 OH 0,9857 157.500 155.247,75
Mandor L.04 OH 0,4929 181.300 89.362,77
Jumlah Tenaga Kerja (A) 375.708,62
B BAHAN
Stainless Steel Strip M.225 i m' 6,0000 9.200 55.200,00
Stopping Buckle M.227 f Bh 8,0000 3.450 27.600,00
Link 25 x 25 mm M.225 f Bh 6,0000 3.450 20.700,00
Box APP 20x30x15 Cm Tebal Plat 1,2 mm M.223 a Bh 1,0000 393.750 393.750,00
Box APP 30x40x20 Cm Tebal Plat 1,2 mm M.223 b Bh 1,0000 719.250 719.250,00
Foto Cell 6 A M.225 d Bh 1,0000 112.600 112.600,00
Contactor Magnet 220 VAC 40 A M.225 Bh 1,0000 693.000 693.000,00
Kabel NYM 3x1,5 mm² M.200 o m' 2,0000 15.000 30.000,00
Ignitor SN 58 M.227 h glg 1,0000 58.200 58.200,00
Jumlah Harga Bahan (B) 2.110.300,00
C PERALATAN
Mobil Pick Up E.107 m² 2,4500 350.000 857.500,00
Alat Bantu K3 dan Tanda Lalu Lintas E.106 jam 0,2500 25.000 6.250,00
Jumlah Harga Alat (C) 863.750,00
D Jumlah ( A + B + C ) 3.349.758,62
E Overhead & Profit 15% xD 502.463,79
F Harga Satuan Pekerjaan (D + E) 3.852.222,41
G Dibulatkan 3.852.222,00
O PEKERJAAN BONGKARAN
1 Bongkar beton bertulang / m³
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 3,3335 133.000 443.355,50
Mandor L.04 OH 0,3330 181.300 60.372,90
Jumlah Tenaga Kerja (A) 503.728,40
B BAHAN
118
2 Bongkar dinding tembok bata merah / m³
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,6667 133.000 88.671,10
Mandor L.04 OH 0,0333 181.300 6.037,29
Jumlah Tenaga Kerja (A) 94.708,39
B BAHAN
6 Bongkar lantai / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,0500 133.000 6.650,00
Mandor L.04 OH 0,0050 181.300 906,50
Jumlah Tenaga Kerja (A) 7.556,50
B BAHAN
119
8 Bongkar plesteran / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,0500 133.000 6.650,00
Mandor L.04 OH 0,0030 181.300 543,90
Jumlah Tenaga Kerja (A) 7.193,90
B BAHAN
13 Bongkar kaso dan reng kayu (kayu tidak akan dipakai lagi) / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,1000 133.000 13.300,00
Mandor L.04 OH 0,0050 181.300 906,50
Jumlah Tenaga Kerja (A) 14.206,50
B BAHAN
120
14 Bongkar balok kuda-kuda & loteng (kayu akan dipakai lagi) / m³
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 2,6660 133.000 354.578,00
Tukang Kayu L.03b OH 4,0000 157.500 630.000,00
Kepala Tukang L.03 OH 0,4000 172.200 68.880,00
Mandor L.04 OH 0,1330 181.300 24.112,90
Jumlah Tenaga Kerja (A) 1.077.570,90
B BAHAN
15 Bongkar balok kuda-kuda & loteng (kayu tidak akan dipakai lagi) / m³
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 2,6660 133.000 354.578,00
Mandor L.04 OH 0,1330 181.300 24.112,90
Jumlah Tenaga Kerja (A) 378.690,90
B BAHAN
PEKERJAAN DRAINASE
1 Memasang pipa beton, dia 15-20 cm
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,3800 133.000 50.540,00
Tukang Batu L.03a OH 0,1900 157.500 29.925,00
Kepala Tukang Batu L.03aa OH 0,0190 172.200 3.271,80
Mandor L.04 OH 0,0070 181.300 1.269,10
Jumlah Tenaga Kerja (A) 85.005,90
B BAHAN
Buis beton dia 20 panj. 100 cm M.10 g bh 1,1000 61.400 67.540,00
Bata Merah Bakar Kelas I M.05 a bh 151,2000 1.150 173.880,00
Semen Portland M.15 a kg 3,9200 1.450 5.684,00
Pasir Pasang M.14 b m³ 0,0560 250.000 14.000,00
Pasir Urug M.14 d m³ 0,0240 160.000 3.840,00
Jumlah Harga Bahan (B) 264.944,00
C PERALATAN
121
2 Memasang pipa beton, dia 30 cm / m¹
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,3800 133.000 50.540,00
Tukang Batu L.03a OH 0,1900 157.500 29.925,00
Kepala Tukang Batu L.03aa OH 0,0190 172.200 3.271,80
Mandor L.04 OH 0,0190 181.300 3.444,70
Jumlah Tenaga Kerja (A) 87.181,50
B BAHAN
Buis beton dia 20 panj. 100 cm M.10 g bh 1,1000 61.400 67.540,00
Bata Merah Bakar Kelas I M.05 a bh 308,0000 1.150 354.200,00
Semen Portland M.15 a kg 10,3000 1.450 14.935,00
Pasir Pasang M.14 b m³ 0,0610 250.000 15.250,00
Pasir Urug M.14 d m³ 0,0690 160.000 11.040,00
Jumlah Harga Bahan (B) 462.965,00
C PERALATAN
122
6 Memasang pipa beton, dia 80 cm / m¹
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,6600 133.000 87.780,00
Tukang Batu L.03a OH 0,3300 157.500 51.975,00
Kepala Tukang Batu L.03aa OH 0,0330 172.200 5.682,60
Mandor L.04 OH 0,0330 181.300 5.982,90
Jumlah Tenaga Kerja (A) 151.420,50
B BAHAN
Buis beton dia 80 panj. 50 cm M.10 b 2,1000 229.500 481.950,00
Bata Merah Bakar Kelas I M.05 a bh 308,0000 1.150 354.200,00
Semen Portland M.15 a kg 10,3000 1.450 14.935,00
Pasir Pasang M.14 b m³ 0,0610 250.000 15.250,00
Pasir Urug M.14 d m³ 0,0690 160.000 11.040,00
Jumlah Harga Bahan (B) 877.375,00
C PERALATAN
123
10 Memasang 1 buah bak kontrol pas.batu bata 60 x 60 cm tinggi 65 cm / bh
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 3,2000 133.000 425.600,00
Tukang Batu L.03a OH 1,1500 157.500 181.125,00
Kepala Tukang Batu L.03aa OH 0,0110 172.200 1.894,20
Mandor L.04 OH 0,0160 181.300 2.900,80
Jumlah Tenaga Kerja (A) 611.520,00
B BAHAN
Bata Merah Bakar Kelas I M.05 a bh 123,0000 1.150 141.450,00
Semen Portland M.15 a kg 114,0000 1.450 165.300,00
Pasir Pasang M.14 b m³ 0,1840 250.000 46.000,00
Pasir Beton M.14 m³ 0,1200 311.000 37.320,00
Kerikil M.12 m³ 0,0330 275.000 9.075,00
Baja Polos U 24 M.55 e kg 4,8500 12.000 58.200,00
Jumlah Harga Bahan (B) 457.345,00
C PERALATAN
124
14 Membuat saluran air dari batu kali lebar bawah 60 cm tinggi 80 cm / m¹
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 1,9250 133.000 256.025,00
Tukang Batu L.03a OH 0,5240 157.500 82.530,00
Kepala Tukang Batu L.03aa OH 0,0520 172.200 8.954,40
Mandor L.04 OH 0,1350 181.300 24.475,50
Jumlah Tenaga Kerja (A) 371.984,90
B BAHAN
Batu belah pondasi M.06 a m³ 0,7040 265.000 186.560,00
Semen Portland M.15 a kg 136,8400 1.450 198.418,00
Pasir Pasang M.14 b m³ 0,3290 250.000 82.250,00
Jumlah Harga Bahan (B) 467.228,00
C PERALATAN
Stamper/Hand Compactor E.25 jam 0,0690 89.600 6.182,40
Jumlah Harga Alat (C) 6.182,40
D Jumlah ( A + B + C ) 845.395,30
E Overhead & Profit 15% xD 126.809,30
F Harga Satuan Pekerjaan (D + E) 972.204,60
G Dibulatkan 972.204,00
15 Membuat saluran air dari batu kali lebar bawah 80 cm tinggi 100 cm / m¹
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 2,9830 133.000 396.739,00
Tukang Batu L.03a OH 0,6920 157.500 108.990,00
Kepala Tukang Batu L.03aa OH 0,0690 172.200 11.881,80
Mandor L.04 OH 0,2190 181.300 39.704,70
Jumlah Tenaga Kerja (A) 557.315,50
B BAHAN
Batu belah pondasi M.06 a m³ 1,0120 265.000 268.180,00
Semen Portland M.15 a kg 193,4000 1.450 280.430,00
Pasir Pasang M.14 b m³ 0,4640 250.000 116.000,00
Jumlah Harga Bahan (B) 664.610,00
C PERALATAN
Stamper/Hand Compactor E.25 jam 0,0930 89.600 8.332,80
Jumlah Harga Alat (C) 8.332,80
D Jumlah ( A + B + C ) 1.230.258,30
E Overhead & Profit 15% xD 184.538,75
F Harga Satuan Pekerjaan (D + E) 1.414.797,05
G Dibulatkan 1.414.797,00
16 Membuat saluran air dari batu kali lebar bawah 100 cm tinggi 120 cm / m¹
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 4,1050 133.000 545.965,00
Tukang Batu L.03a OH 0,8620 157.500 135.765,00
Kepala Tukang Batu L.03aa OH 0,0860 172.200 14.809,20
Mandor L.04 OH 0,3090 181.300 56.021,70
Jumlah Tenaga Kerja (A) 752.560,90
B BAHAN
Batu belah pondasi M.06 a m³ 1,2870 265.000 341.055,00
Semen Portland M.15 a kg 244,9800 1.450 355.221,00
Pasir Pasang M.14 b m³ 0,5880 250.000 147.000,00
Jumlah Harga Bahan (B) 843.276,00
C PERALATAN
Stamper/Hand Compactor E.25 jam 0,1040 89.600 9.318,40
Jumlah Harga Alat (C) 9.318,40
D Jumlah ( A + B + C ) 1.605.155,30
E Overhead & Profit 15% xD 240.773,30
F Harga Satuan Pekerjaan (D + E) 1.845.928,60
G Dibulatkan 1.845.928,00
125
2 Analisa : Timbunan Biasa Dari Sumber Galian / m³
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OJ 0,0403 19.000 765,70
Mandor L.04 OJ 0,0101 25.900 261,59
Jumlah Tenaga Kerja (A) 1.027,29
B BAHAN
Timbunan Pilihan /urugan Porous M.08 m³ 1,4330 246.000 352.518,00
126
7 Analisa : Pasangan Batu kosong / m³
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OJ 5,2500 19.000 99.750,00
Tukang L.02 OJ 1,7500 22.500 39.375,00
Mandor L.04 OJ 0,8750 25.900 22.662,50
Jumlah Tenaga Kerja (A) 161.787,50
B BAHAN
Batu belah pondasi M.06 a m³ 1,1700 265.000 310.050,00
127
11 Analisa : Lapis Pondasi Agregat Kelas B / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OJ 0,0595 19.000 1.130,50
Mandor L.04 OJ 0,0085 25.900 220,15
Jumlah Tenaga Kerja (A) 1.350,65
B BAHAN
Agregat Kelas B M.16 h m³ 1,2586 277.200 348.883,92
128
15 Lapis Resap Ikat (Prime Coat) / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OJ 0,0021 19.000 39,90
Mandor L.04 OJ 0,0004 25.900 10,36
Jumlah Tenaga Kerja (A) 50,26
B BAHAN
Prime Coat M.111 k Ltr 0,6420 14.300 9.180,60
Minyak tanah M.130 a Ltr 0,4890 11.220 5.486,58
129
19 Analisa : Baja Tulangan Polos U 32 - TS 280 / kg
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OJ 0,1050 19.000 1.995,00
Tukang L.02 OJ 0,0350 22.500 787,50
Mandor L.04 OJ 0,0350 25.900 906,50
Jumlah Tenaga Kerja (A) 3.689,00
B BAHAN
Baja Tulangan U30 Ulir M.55 a kg 1,1000 13.500 14.850,00
Kawat Beton M.68 Kg 0,0025 28.000 70,00
130
23 Perkerasan Jalan Beton K 350 / m³
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OJ 1,4056 19.000 26.706,40
Tukang L.02 OJ 0,7028 22.500 15.813,00
Mandor L.04 OJ 0,1506 25.900 3.900,54
Jumlah Tenaga Kerja (A) 46.419,94
B BAHAN
Beton Ready Mixed - K 350 ( NFA ) M.09 h m³ 1,0500 1.122.800 1.178.940,00
Baja Polos U 24 M.55 e kg 15,7750 12.000 189.300,00
Joint Sealent M 144 d Kg 0,9653 34.100 32.916,73
Cat Anti Karat M.127 c kg 0,0200 36.000 720,00
Expansion Cap M 144 e Kg 0,1700 6.050 1.028,50
Polytene 125 mikron M 144 f Kg 0,4375 19.250 8.421,88
Curing Compound M 144 g Ltr 0,8700 38.500 33.495,00
Aditif beton M.04 kg 0,9139 48.000 43.867,20
Multiplek tebal 12 mm M 39 e Lbr 0,1600 181.500 29.040,00
Kayu reng- papan Klas III M.34 b m³ 0,0960 3.500.000 336.000,00
Paku biasa 2"-5" M.71 a kg 1,0240 17.000 17.408,00
Jumlah Harga Bahan (B) 1.871.137,31
C PERALATAN
Wheel Loader 1.0-1.6 M3 E.15 jam 0,0244 429.500 10.479,80
Truk Mixer (Agitator) E.49 jam 0,0244 511.700 12.470,13
Concrete Vibrator E.20 jam 0,0502 60.400 3.032,08
Water Tanker 3000-4500 L. E.23 jam 0,0422 297.300 12.546,06
Slip Form Paver E.42 jam 0,0074 2.343.400 17.341,16
Alat Bantu Ls 0,0500 364.230 18.211,50
131
26 Beton mutu sedang f'c 31,7 MPa Lantai Jembatan / m³
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OJ 0,7028 19.000 13.353,20
Tukang L.02 OJ 1,7570 22.500 39.532,50
Mandor L.04 OJ 0,0502 25.900 1.300,18
Jumlah Tenaga Kerja (A) 54.185,88
B BAHAN
Beton Ready Mixed - K 350 ( NFA ) M.09 h m³ 1,0500 1.122.800 1.178.940,00
Aditif beton M.04 kg 0,9139 48.000 43.867,20
Kayu papan-reng Klas IV M.35 c m³ 0,4000 2.500.000 1.000.000,00
Paku biasa 2"-5" M.71 a kg 3,2000 17.000 54.400,00
Air M.02 Ltr 182,2450 100 18.224,50
Jumlah Harga Bahan (B) 2.295.431,70
C PERALATAN
Wheel Loader 1.0-1.6 M3 E.15 jam 0,0244 429.500 10.479,80
Truk Mixer (Agitator) E.49 jam 0,0244 511.700 12.470,13
Concrete Vibrator E.20 jam 0,0502 60.400 3.032,08
Water Tanker 3000-4500 L. E.23 jam 0,0422 297.300 12.546,06
Slip Form Paver E.42 jam 0,0074 2.343.400 17.341,16
Alat Bantu Ls 0,0500 364.230 18.211,50
27 Analisa : Tiang bor beton diameter 600 mm K 250 (fc' 21,7 MPa) / m³
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OJ 0,0099 19.000 188,10
Tukang L.02 OJ 0,0050 22.500 112,50
Mandor L.04 OJ 0,0017 25.900 44,03
Jumlah Tenaga Kerja (A) 344,63
B BAHAN
Beton Ready Mixed - K 250 ( FA ) M.09 d a m³ 0,2827 850.000 240.295,00
Baja Polos U 24 M.55 e kg 42,4115 12.000 508.938,00
Casing E.108 m² 1,8850 80.000 150.800,00
Jumlah Harga Bahan (B) 900.033,00
C PERALATAN
Bore Pile Machine E.33 jam 0,0017 541.700 920,89
Concrete Pump E.28 jam 0,0427 883.800 37.738,26
Alat Bantu Ls 0,0100 142.550 1.425,50
132
30 Lapis Permukaan Pendetrasi Macadam - LAPEN MACADAM / ton
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OJ 0,1417 19.000 2.692,30
Mandor L.04 OJ 0,0142 25.900 367,78
Jumlah Tenaga Kerja (A) 3.060,08
B BAHAN
Kerikil M.12 m³ 1,2478 275.000 343.145,00
Pasir Beton M.14 m³ 0,0179 311.000 5.566,90
Aspal M.111 kg 95,5625 12.750 1.218.421,88
Jumlah Harga Bahan (B) 1.567.133,78
C PERALATAN
Wheel Loader 1.0-1.6 M3 E.15 jam 0,0071 429.500 3.049,45
Dump Truck 6-8 M3 E.09 jam 0,1823 314.200 57.278,66
Three Wheel Roller 6-8 T E.16 jam 0,0380 221.500 8.417,00
Asphalt Sprayer E.03 jam 0,3788 73.200 27.728,16
Alat Bantu Ls 0,0500 103.840 5.192,00
33 Analisa : Pipa Berlubang Banyak (Perforated Pipe) untuk Pekerjaan Drainase Bawah Permukaan, diameter 2 inch / m1
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OJ 1,1667 19.000 22.166,67
Tukang L.02 OJ - 22.500
Mandor L.04 OJ 0,5833 25.900 15.108,33
Jumlah Tenaga Kerja (A) 37.275,00
B BAHAN
Pipa Porous 2 " M.107 c i m³ 1,0250 16.200 16.605,00
Jumlah Harga Bahan (B) 16.605,00
C PERALATAN
Alat Bantu Ls 0,0500 - -
133
35 Analisa : Pengangkutan Struktur Jembatan Rangka Baja Standar …… m / Kg
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OJ 0,0099 19.000 188,10
Tukang L.02 OJ 0,0050 22.500 112,50
Mandor L.04 OJ 0,0017 25.900 44,03
Jumlah Tenaga Kerja (A) 344,63
B BAHAN
36 Landasan Elastomerik Karet Sintetis Berlapis Baja Ukuran ….. Mm x ….. Mm x…….. Mm / Kg
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OJ 2,3333 19.000 44.333,33
Tukang L.02 OJ 0,5833 22.500 13.125,00
Mandor L.04 OJ 0,5833 25.900 15.108,33
Jumlah Tenaga Kerja (A) 72.566,67
B BAHAN
Elastomer sintetis elastomer jenis 3;
M 144 h m³ 1,0000 838.000 838.000,00
(450x400x45) mm3
Jumlah Harga Bahan (B) 838.000,00
C PERALATAN
Crane 10-15 Ton E.07 jam 0,0001 514.500 51,45
Trailer 20 Ton E.29 jam 0,0003 357.000 107,10
Alat Bantu Ls 0,0100 87.150 871,50
134
40 Guiding Block (difabel stone) / m2
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OJ 1,7500 19.000 33.250,00
Tukang L.02 OJ 0,8750 22.500 19.687,50
Mandor L.04 OJ 0,0875 25.900 2.266,25
Jumlah Tenaga Kerja (A) 55.203,75
B BAHAN
Tegel Difablestone Warna Kuning - M.80 i bh 11,0000 15.000 165.000,00
Semen Portland M.15 a kg 10,0000 1.450 14.500,00
Pasir Beton M.14 m³ 0,0450 311.000 13.995,00
Jumlah Harga Bahan (B) 193.495,00
C PERALATAN
Alat Bantu Ls 0,1000 325.450 32.545,00
135
45 Pekerjaan paving blok natural tebal 8 cm / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,5000 133.000 66.500,00
Tukang Batu L.03a OH 0,5000 157.500 78.750,00
Kepala Tukang Batu L.03aa OH 0,0050 172.200 861,00
Mandor L.04 OH 0,0013 181.300 226,63
Jumlah Tenaga Kerja (A) 146.337,63
B BAHAN
Paving natural tebal 8 cm M.20 b m² 1,0100 85.000 85.850,00
Pasir Beton M.14 m³ 0,1000 311.000 31.100,00
Jumlah Harga Bahan (B) 116.950,00
C PERALATAN
TAMAN
1 Penanaman Rumput Gajah Manila /m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,0400 133.000 5.320,00
Mandor L.04 OH 0,0040 181.300 725,20
Jumlah Tenaga Kerja (A) 6.045,20
B BAHAN
Pupuk, Campuran P.006 Kg 0,0400 21.000 840,00
Rumput Gajah Mini, P.007 m2 0,5000 30.000 15.000,00
Tanah Lembang M.14 e m³ 0,3000 100.000 30.000,00
Jumlah Harga Bahan (B) 45.840,00
C PERALATAN
3 Gebalan rumput / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,0500 133.000 6.650,00
Mandor L.04 OH 0,0250 181.300 4.532,50
Jumlah Tenaga Kerja (A) 11.182,50
B BAHAN
Bambu dia 5 - 7 Cm M.28 a btg 0,2000 14.400 2.880,00
Gebalan Rumput M. 136 a m2 1,0000 31.500 31.500,00
Jumlah Harga Bahan (B) 34.380,00
C PERALATAN
136
4 Geotektil untuk Perkuatan Tanah / m ²
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 0 0,9333 133.000 124.128,90
Tukang Batu L.03a OH 0,2333 157.500 36.744,75
Mandor L.04 0 0,1167 181.300 21.157,71
Jumlah Tenaga Kerja (A) 182.031,36
B BAHAN
Geotekstile M.77 a m² 1,0000 32.500 32.500,00
Jumlah Harga Bahan (B) 32.500,00
C PERALATAN
Alat Bantu Ls 0,0500 3.250 162,50
Jumlah Harga Alat (C) 162,50
D Jumlah ( A + B + C ) 214.693,86
E Overhead & Profit 15% xD 32.204,08
F Harga Satuan Pekerjaan (D + E) 246.897,94
G Dibulatkan 246.897,00
PSDA
1 Kistdam pasir/tanah dibungkus karung plastik bagor 45 / m'
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,1000 133.000 13.300,00
Tukang Batu L.03a OH 0,0250 157.500 3.937,50
Kepala Tukang Batu L.03aa OH 0,0100 172.200 1.722,00
Mandor L.04 OH 0,0010 181.300 181,30
Jumlah Tenaga Kerja (A) 19.140,80
B BAHAN
Karung plastik diisi tanah M.300 bh 1,3000 5.500 7.150,00
Tali rapia/Plastik M.301 m 2,0000 500 1.000,00
Pasir Pasang M.14 b m³ 0,0250 250.000 6.250,00
Jumlah Harga Bahan (B) 14.400,00
C PERALATAN
2 Dokumentasi / ls
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,1000 133.000 13.300,00
Tukang Poto L.03g OH 0,0100 157.500 1.575,00
Jumlah Tenaga Kerja (A) 14.875,00
B BAHAN
Cetak Foto M.303 lbr 30,0000 1.000 30.000,00
Album Foto isi 40 M.304 bh 1,0000 75.000 75.000,00
137
5 Galian tanah biasa sedalam ≤ 2 m / m³
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,6750 133.000 89.775,00
Mandor L.04 OH 0,0675 181.300 12.237,75
Jumlah Tenaga Kerja (A) 102.012,75
B BAHAN
138
11 Timbunan tanah atau urugan tanah kembali / m³
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,3300 133.000 43.890,00
Mandor L.04 OH 0,0330 181.300 5.982,90
Jumlah Tenaga Kerja (A) 49.872,90
B BAHAN
12 Pemadatan tanah / m³
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,5000 133.000 66.500,00
Mandor L.04 OH 0,0500 181.300 9.065,00
Jumlah Tenaga Kerja (A) 75.565,00
B BAHAN
16 Galian Biasa / m3
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,0073 133.000 970,90
Tukang L.02 OH 0,0037 157.500 576,00
Jumlah Tenaga Kerja (A) 1.546,90
B BAHAN
139
17 Galian Struktur dengan kedalaman 0 - 2 meter / m3
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,0030 133.000 393,30
Tukang L.02 OH 0,0007 157.500 117,00
Jumlah Tenaga Kerja (A) 510,30
B BAHAN
Urugan Pilihan M.230 g m3 0,5000 140.000 70.000,00
Jumlah Harga Bahan (B) 70.000,00
C PERALATAN
Excavator 80-140 Hp E.10 jam 0,0052 368.200 1.914,64
Bulldozer 100-150 Hp E.04 jam 0,0145 322.487 4.676,06
Jumlah Harga Alat (C) 6.590,70
D Jumlah ( A + B + C ) 77.101,00
E Overhead & Profit 15% xD 11.565,15
F Harga Satuan Pekerjaan (D + E) 88.666,15
G Dibulatkan 88.666,00
20 Galian Batu / m3
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,0843 133.000 11.213,80
Tukang L.02 OH 0,0105 157.500 1.660,50
Jumlah Tenaga Kerja (A) 12.874,30
B BAHAN
-
Jumlah Harga Bahan (B) -
C PERALATAN
Excavator 80-140 Hp E.10 jam 0,0738 368.200 27.173,16
Wheel Loader 1.0-1.6 M3 E.15 jam 0,0738 429.500 31.697,10
Compressor 4000-6500 L\M E.05 jam 0,0738 129.400 9.549,72
Jack Hammer E.26 jam 0,0738 56.500 4.169,70
Dump Truck 3 - 4 M3 E.08 jam 0,3677 215.600 79.276,12
Jumlah Harga Alat (C) 151.865,80
D Jumlah ( A + B + C ) 164.740,10
E Overhead & Profit 15% xD 24.711,02
F Harga Satuan Pekerjaan (D + E) 189.451,12
G Dibulatkan 189.451,00
140
22 Box Culver 1000 x 1000 HD / bh
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,5737 133.000 76.305,90
Tukang L.02 OH 0,1147 157.500 18.072,00
Mandor L.04 OH 0,0164 181.300 2.978,50
Jumlah Tenaga Kerja (A) 97.356,40
B BAHAN
Box Culver 1000 x 1000 HD M.122 bh 1,0000 4.517.000 4.517.000,00
Jumlah Harga Bahan (B) 4.517.000,00
C PERALATAN
Excavator 80-140 Hp E.10 jam 1,2500 368.200 460.250,00
Bulldozer 100-150 Hp E.04 jam 0,1320 322.487 42.568,28
Jumlah Harga Alat (C) 502.818,28
D Jumlah ( A + B + C ) 5.117.174,68
E Overhead & Profit 15% xD 767.576,20
F Harga Satuan Pekerjaan (D + E) 5.884.750,89
G Dibulatkan 5.884.750,00
141
27 Baja Tulangan untuk struktur drainase beton minor / bh
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,0150 133.000 1.995,00
Tukang L.02 OH 0,0050 157.500 787,50
Mandor L.04 OH 0,0050 181.300 906,50
Jumlah Tenaga Kerja (A) 3.689,00
B BAHAN
Baja Polos U-30 - 32 M.55 d kg 1,0500 13.500 14.175,00
Kawat Beton M.68 Kg 0,0200 28.000 560,00
Jumlah Harga Bahan (B) 14.735,00
C PERALATAN
-
Jumlah Harga Alat (C) -
D Jumlah ( A + B + C ) 18.424,00
E Overhead & Profit 15% xD 2.763,60
F Harga Satuan Pekerjaan (D + E) 21.187,60
G Dibulatkan 21.187,00
142
32 Pasangan Batu Dengan Mortar / m3
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,5737 133.000 76.305,90
Tukang L.02 OH 0,1721 157.500 27.108,00
Mandor L.04 OH 0,0574 181.300 10.401,44
Jumlah Tenaga Kerja (A) 113.815,34
B BAHAN
Batu belah pondasi M.06 a m³ 1,0800 265.000 286.200,00
Semen Portland M.15 a kg 161,0000 1.450 233.450,00
Pasir Pasang M.14 b m³ 0,4830 250.000 120.750,00
Jumlah Harga Bahan (B) 640.400,00
C PERALATAN
Concrete Mixer 0.3-0.6 M3 E.06 jam 0,4016 88.500 35.541,60
Jumlah Harga Alat (C) 35.541,60
D Jumlah ( A + B + C ) 789.756,94
E Overhead & Profit 15% xD 118.463,54
F Harga Satuan Pekerjaan (D + E) 908.220,48
G Dibulatkan 908.220,00
33 Beton Mutu, f'c = 9,8 Mpa ( K125), slump (12 ±2) cm, w/c= 0,78 ( Menggunakan Molen > 2 m³ ) / m3
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 1,3230 133.000 175.959,00
Tukang L.02 OH 0,1890 157.500 29.767,50
Kepala Tukang L.03 OH 0,0190 172.200 3.271,80
Mandor L.04 OH 0,1320 181.300 23.931,60
Jumlah Tenaga Kerja (A) 232.929,90
B BAHAN
Pasir Beton M.14 m³ 0,5200 311.000 161.720,00
Semen Portland M.15 a kg 276,0000 1.450 400.200,00
Batu Pecah - Koral 1/2 M.12 b m³ 0,5600 550.000 308.000,00
Air M.02 Ltr 215,0000 100 21.500,00
Jumlah Harga Bahan (B) 891.420,00
C PERALATAN
Concrete Mixer 0.3-0.6 M3 E.06 jam 0,2500 88.500 22.125,00
Jumlah Harga Alat (C) 22.125,00
D Jumlah ( A + B + C ) 1.146.474,90
E Overhead & Profit 15% xD 171.971,24
F Harga Satuan Pekerjaan (D + E) 1.318.446,14
G Dibulatkan 1.318.446,00
143
37 Mortar tipe N ( untuk mutu PP setara dengan campuran 1 PC : 4 PP ) / m
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 2,7000 133.000 359.100,00
Tukang L.02 OH 0,9000 157.500 141.750,00
Mandor L.04 OH 0,2700 181.300 48.951,00
Jumlah Tenaga Kerja (A) 549.801,00
B BAHAN
Batu belah pondasi M.06 a m³ 1,2000 265.000 318.000,00
Semen Portland M.15 a kg 163,0000 1.450 236.350,00
Pasir Pasang M.14 b m³ 0,5200 250.000 130.000,00
Jumlah Harga Bahan (B) 684.350,00
C PERALATAN
-
Jumlah Harga Alat (C) -
D Jumlah ( A + B + C ) 1.234.151,00
E Overhead & Profit 15% xD 185.122,65
F Harga Satuan Pekerjaan (D + E) 1.419.273,65
G Dibulatkan 1.419.273,00
38 Plesteran tebal 1,5 cm, dengan mortar jenis PC-PP tipe S ( untuk mutu PP tertentu setara dengan campuran 1 PC : 3 PP ) / m2
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,3200 133.000 42.560,00
Tukang L.02 OH 0,1600 157.500 25.200,00
Kepala Tukang L.03 OH 0,0160 172.200 2.755,20
Mandor L.04 OH 0,0320 181.300 5.801,60
Jumlah Tenaga Kerja (A) 76.316,80
B BAHAN
Pasir Pasang M.14 b m³ 0,0230 250.000 5.750,00
Semen Portland M.15 a kg 7,7760 1.450 11.275,20
Jumlah Harga Bahan (B) 17.025,20
C PERALATAN
-
Jumlah Harga Alat (C) -
D Jumlah ( A + B + C ) 93.342,00
E Overhead & Profit 15% xD 14.001,30
F Harga Satuan Pekerjaan (D + E) 107.343,30
G Dibulatkan 107.343,00
39 Siaran dengan mortar jenis PC-PP tipe M ( untuk mutu PP tertentu setara dengan campuran 1 PC : 2 PP ) / m2
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,4000 133.000 53.200,00
Tukang L.02 OH 0,2000 157.500 31.500,00
Kepala Tukang L.03 OH 0,0200 172.200 3.444,00
Mandor L.04 OH 0,0400 181.300 7.252,00
Jumlah Tenaga Kerja (A) 95.396,00
B BAHAN
Pasir Pasang M.14 b m³ 0,0050 250.000 1.250,00
Semen Portland M.15 a kg 2,3400 1.450 3.393,00
Jumlah Harga Bahan (B) 4.643,00
C PERALATAN
-
Jumlah Harga Alat (C) -
D Jumlah ( A + B + C ) 100.039,00
E Overhead & Profit 15% xD 15.005,85
F Harga Satuan Pekerjaan (D + E) 115.044,85
G Dibulatkan 115.044,00
144
42 Pemasangan Pintu Air / unit
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 1,0000 133.000 133.000,00
Tukang L.02 OH 1,0000 157.500 157.500,00
Jumlah Tenaga Kerja (A) 290.500,00
B BAHAN
Pintu Air M.230 l bh 1,0000 2.750.000 2.750.000,00
Jumlah Harga Bahan (B) 2.750.000,00
C PERALATAN
Mesin Las E.59 jam 2,0000 52.600 105.200,00
Jumlah Harga Alat (C) 105.200,00
D Jumlah ( A + B + C ) 3.145.700,00
E Overhead & Profit 15% xD 471.855,00
F Harga Satuan Pekerjaan (D + E) 3.617.555,00
G Dibulatkan 3.617.555,00
43 Bekisting untuk permukaan beton biasa dengan papan ukuran 3/20 cm ( tanpa perancah ) / unit
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,3000 133.000 39.900,00
Tukang L.02 OH 0,1500 157.500 23.625,00
Kepala Tukang L.03 OH 0,0150 172.200 2.583,00
Mandor L.04 OH 0,0300 181.300 5.439,00
Jumlah Tenaga Kerja (A) 71.547,00
B BAHAN
Kayu reng- papan Klas III M.34 b bh 0,0140 3.500.000 49.000,00
Kayu balok, kaso-kaso Klas III M.34 a bh 0,0030 3.000.000 9.000,00
Paku biasa 2"-5" M.71 a bh 0,3000 17.000 5.100,00
Minyak Bekisting M.129 bh 0,2000 22.500 4.500,00
Jumlah Tenaga Kerja (A) 67.600,00
C PERALATAN
-
Jumlah Harga Alat (C) -
D Jumlah ( A + B + C ) 139.147,00
E Overhead & Profit 15% xD 20.872,05
F Harga Satuan Pekerjaan (D + E) 160.019,05
G Dibulatkan 160.019,00
145
3 Pembuatan Lubang Bor Sumur Dalam dia. 8' kedalaman 50-100 m / m'
Kedalaman 50 m - 100 m
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Juru Bor L.07 OH 0,1540 155.800 23.993,20
Asisten Juru Bor L.11 OH 0,1540 136.500 21.021,00
Mekanik L.08 OH 0,1540 161.000 24.794,00
Pekerja L.01 OH 0,4620 133.000 61.446,00
Jumlah Tenaga Kerja (A) 131.254,20
B BAHAN
Solar Non Subsidi M.137 b Ltr 18,4620 9.400 173.542,80
Pelumas M.132 Ltr 0,3080 34.500 10.626,00
Grease Trap M.108 J Kg 0,1540 150.000 23.100,00
Karet piston M.108 K Pasang 0,1540 41.400 6.375,60
Bentonit M.07 a ZAK 0,3080 200.000 61.600,00
Jumlah Harga Bahan (B) 275.244,40
C PERALATAN
Alat Pemboran Sumur E.109 Hari 0,1540 300.000 46.200,00
Mata Bor E.110 Set 0,0080 282.000 2.256,00
Jumlah Harga Alat (C) 48.456,00
D Jumlah ( A + B + C ) 454.954,60
E Overhead & Profit 15% 68243,19
F Harga Satuan Pekerjaan (D + E) 523.197,79
G Dibulatkan 523.197,00
146
7 Perbesaran Lubang Bor Sumur Dalam dia. 10' kedalaman 100-150 m / m¹
Kedalaman 100 m - 150 m
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Juru Bor L.07 OH 0,1430 155.800 22.279,40
Asisten Juru Bor L.11 OH 0,1430 136.500 19.519,50
Mekanik L.08 OH 0,1430 161.000 23.023,00
Pekerja L.01 OH 0,4290 133.000 57.057,00
Jumlah Tenaga Kerja (A) 121.878,90
B BAHAN
Solar Non Subsidi M.137 b Ltr 17,1430 9.400 161.144,20
Pelumas M.132 Ltr 0,2860 34.500 9.867,00
Grease Trap M.108 J Kg 0,1430 150.000 21.450,00
Karet piston M.108 K Pasang 0,1430 41.400 5.920,20
Bentonit M.07 a ZAK 0,2860 200.000 57.200,00
Jumlah Harga Bahan (B) 255.581,40
C PERALATAN
Alat Pemboran Sumur E.109 Hari 0,1430 300.000 42.900,00
Mata Bor E.110 Set 0,0070 282.000 1.974,00
Jumlah Harga Alat (C) 44.874,00
D Jumlah ( A + B + C ) 422.334,30
E Overhead & Profit 15% 63.350,15
F Harga Satuan Pekerjaan (D + E) 485.684,45
G Dibulatkan 485.684,00
147
10 Pembuatan Sambungan Rumah HIBAH / unit
Sambungan Rumah Hibah
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,6000 133.000 79.800,00
Tukang Pipa L.03d OH 0,1000 157.500 15.750,00
Mandor L.04 OH 0,0500 181.300 9.065,00
Jumlah Tenaga Kerja (A) 104.615,00
B BAHAN
Pipa HDPE PE100, SDR 17 OD.20 Mm,
M.107 c a Meter 10,0000 8.100 81.000,00
Tebal = 1,6 Mm
Pipa galvanis Ø ½ " M.106 a m' 2,0000 23.400 46.800,00
Tee PVC Dia. 1" x 1/2" M.108 l bh 1,0000 7.690 7.690,00
Fitting Pipa PVC - 1/2 " M.105 a bh 1,0000 3.500 3.500,00
Male Socket Drat Luar HDPE Dia. 1/2" M.105 r b bh 3,0000 26.400 79.200,00
Faucet Elbow (GI) Dia. 1/2" M.108 o bh 3,0000 4.780 14.340,00
Check Valve, 1/2" M.108 ga bh 1,0000 65.000 65.000,00
Plug Kran Dia. 1/2" (Kuningan) M.105 rc bh 1,0000 75.000 75.000,00
Double Nepple Dia. 1/2" M.108 q bh 1,0000 4.950 4.950,00
Water Meter (Kuningan) Dia. 1/2 " M.108 r bh 1,0000 250.000 250.000,00
Stop Kran Dia. 1/2" M.108 s bh 1,0000 65.000 65.000,00
Atap Kran Dia. 1/2" M.108 t bh 1,0000 27.000 27.000,00
Tee GI, 2" x 2" M.105 q bh 1,0000 204.600 204.600,00
Fitting Pipa PVC - 1/2 " M.105 a bh 1,0000 3.500 3.500,00
Pipa PVC dia 1/2" AW M.107 a m' 0,1500 3.575 536,25
Fitting Pipa PVC - 1/2 " M.105 a bh 1,0000 3.500 3.500,00
Box Meter M.108 u bh 1,0000 100.000 100.000,00
Seal Tape M.157 bh 2,0000 5.000 10.000,00
Jumlah Harga Bahan (B) 1.041.616,25
C PERALATAN
148
14 Pagar BRC tinggi 120 cm berikut pintu / m¹
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 1,5000 133.000 199.500,00
Tukang Besi L.03c OH 0,5000 157.500 78.750,00
Mandor L.04 OH 0,0500 181.300 9.065,00
Jumlah Tenaga Kerja (A) 287.315,00
B BAHAN
Tiang pagar BRC tinggi 1,2 m' M.70 c bh 9,0000 147.600 1.328.400,00
Pagar BRC tinggi 1,2 m' M.70 a m' 15,6000 221.700 3.458.520,00
Asesori dan perlengkapan ls 0,1000 4.786.920 478.692,00
Jumlah Harga Bahan (B) 5.265.612,00
C PERALATAN
149
19 Memasang pipa PVC tipe SNI RRJ Ø 1" diameter 32 mm / m¹
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,0360 133.000 4.788,00
Tukang Batu L.03a OH 0,0600 157.500 9.450,00
Kepala Tukang Batu L.03aa OH 0,0060 172.200 1.033,20
Mandor L.04 OH 0,0020 181.300 362,60
Jumlah Tenaga Kerja (A) 15.633,80
B BAHAN
PVC SNI 0600842002, 1" M.107 a c m' 1,2000 15.600 18.720,00
Perlengkapan % 35,0000 15.600 5.460,00
Jumlah Harga Bahan (B) 24.180,00
C PERALATAN
22 Memasang pipa PVC tipe SNI RRJ dia 4" diameter 110 mm
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,0810 133.000 10.773,00
Tukang Batu L.03a OH 0,1350 157.500 21.262,50
Kepala Tukang Batu L.03aa OH 0,0135 172.200 2.324,70
Mandor L.04 OH 0,0040 181.300 725,20
Jumlah Tenaga Kerja (A) 35.085,40
B BAHAN
PVC SNI 0600842002, 4" M.107 a i m' 1,2000 147.210 176.652,00
Perlengkapan % 35,0000 147.210 51.523,50
Jumlah Harga Bahan (B) 228.175,50
C PERALATAN
23 Memasang pipa PVC tipe SNI RRJ dia 6" diameter 150 mm
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,0810 133.000 10.773,00
Tukang Batu L.03a OH 0,1350 157.500 21.262,50
Kepala Tukang Batu L.03aa OH 0,0135 172.200 2.324,70
Mandor L.04 OH 0,0040 181.300 725,20
Jumlah Tenaga Kerja (A) 35.085,40
B BAHAN
PVC SNI 0600842002, 6" M.107 a j m' 1,2000 302.930 363.516,00
Perlengkapan % 35,0000 302.930 106.025,50
Jumlah Harga Bahan (B) 469.541,50
C PERALATAN
150
1 Pemasangan Jaring Plastik Alas Kotoran Sedang
PERALATAN JUMLAH HARGA
NO. URAIAN KODE SATUAN KOEFISIEN HARGA SATUAN (Rp) UPAH KERJA (Rp) BAHAN (Rp)
(Rp) (Rp)
(1) (2) (3) (4) (5) (6) (7) (8) (9) ( 10 )
A TENAGA
Pekerja L.01 OH 0,0500 133.000 6.650,00
Tukang Kayu L.03b OH 0,0120 157.500 1.890,00
Kepala Tukang Kayu L.03ac OH 0,0150 172.200 2.583,00
Mandor L.04 OH 0,0250 181.300 4.532,50
Jumlah Tenaga Kerja (A) 15.655,50
B BAHAN
Jaring Plastik m.br-19 Roll 1,0000 15.000 15.000,00
Alat Bantu Ls 0,1200 2.500 300,00
Jumlah Harga Bahan (B) 15.300,00
C PERALATAN
151
152
LAMPIRAN II PERATURAN BUPATI BANDUNG
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
SEPTICTANK INDIVIDU 10KK
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 184.018,50
II PEKERJAAN JARINGAN PERPIPAAN & SR 4.031.463,71
III PEKERJAAN BANGUNAN IPAL 5.847.340,37
JUMLAH (Rp) 10.062.822,58
PPN 10% 1.006.282,26
JUMLAH TOTAL (Rp) 11.069.104,84
JUMLAH DIBULATKAN (Rp) 11.069.000,00
1
ANALISIS STANDAR BELANJA (ASB)
MCK + SEPTIK TANK PABRIKASI TIPE I
1 KELOMPOK : Kontruksi
2 SUB KELOMPOK : Membangun MCK + SEPTIK TANK PABRIKASI TIPE I
3 SUB- SUB KELOMPOK : Membangun MCK + SEPTIK TANK PABRIKASI TIPE I
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Membangun MCK + SEPTIK TANK PABRIKASI TIPE I
6 DESKRIPSI AKTIVITAS : Membangun MCK + SEPTIK TANK PABRIKASI TIPE I
7 SATUAN AKTIVITAS : Unit
8 KOMPONEN/RINCIAN KOMPONEN :
NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
I PEKERJAAN PERSIAPAN
1 Pekerjaan Pengukuran dan pemasangan bouwplank m¹ 24,480 81.786,00 2.002.121,28
2 Pembuatan nama pekerjaan ls 1,000 251.059,00 251.059,00
Jumlah 2.253.180,28
II PEKERJAAN TANAH
1 Galian tanah biasa sedalam 1 meter / m³ m³ 6,500 119.924,00 779.506,00
2 Urugan Kembali Tanah Bekas Galian m³ 2,000 86.899,00 173.798,00
Jumlah 953.304,00
III PEKERJAAN PONDASI
1 Pasangan Batu belah kosong ( Aanstamping) m³ 1,500 650.982,00 976.473,00
2 Pasangan Batu belah 15/20 ( 1 PC: 5 PP) m³ 3,750 1.144.638,00 4.292.392,50
Jumlah 5.268.865,50
IV PEKERJAAN STRUKTUR
1 Pek kolom 15x15
a. Pek. Beton campuran 1 sp : 2 ps : 3 kr m³ 0,540 1.320.118,00 712.863,72
b. Pek. tulangan besi Ø 10, sk Ø 8-150 kg 60,110 17.596,00 1.057.695,56
c. pek Bekisting m² 6,720 428.677,00 2.880.709,44
2 Pek kolom 15x20
a. Pek. Beton campuran 1 sp : 2 ps : 3 kr m³ 0,360 1.320.118,00 475.242,48
b. Pek. tulangan besi Ø 10, sk Ø 8-150 kg 60,110 17.596,00 1.057.695,56
c. pek Bekisting m² 6,720 428.677,00 2.880.709,44
3 Pek sloof 15x15
a. Pek. Beton campuran 1 sp : 2 ps : 3 kr m³ 0,450 1.320.118,00 594.053,10
b. Pek. tulangan besi Ø 10, sk Ø 8-150 kg 42,800 17.596,00 753.108,80
c. pek Bekisting m² 6,000 238.798,00 1.432.788,00
4 Pek ring balok 15x20
a. Pek. Beton campuran 1 sp : 2 ps : 3 kr m³ 0,510 1.320.118,00 673.260,18
b. Pek. tulangan besi Ø 10, sk Ø 8-150 kg 38,420 17.596,00 676.038,32
c. pek Bekisting m² 8,480 439.027,00 3.722.948,96
5 Pek balok 15x20
a. Pek. Beton campuran 1 sp : 2 ps : 3 kr m³ 0,210 1.320.118,00 277.224,78
b. Pek. tulangan besi Ø 10, sk Ø 8-150 kg 15,640 17.596,00 275.201,44
c. pek Bekisting m² 3,450 439.027,00 1.514.643,15
Jumlah 18.984.182,93
V PEKERJAAN DINDING DAN LANTAI
1 Pekerjaan Dinding Bata Merah Spesi 1 : 5 m² 31,940 166.609,00 5.321.491,46
2 Pekerjaan Plesteran m² 38,200 95.270,00 3.639.314,00
3 Pekerjaan Acian m² 38,200 58.187,00 2.222.743,40
Pekerjaan Dinding Keramik Toilet/WC, 20x25 cm, tinggi 1,20
4 m² 12,840 277.283,00 3.560.313,72
m
Pekerjaan Lantai Keramik Toilet/WC, Uk. 20 x 20 cm, Anti
5 m² 8,780 185.580,00 1.629.392,40
Slip
6 Pekerjaan batu tempel - 340.842,00 -
7 Pek. Pas Glass Block m² 0,480 815.110,00 391.252,80
8 Pek. Pas. Roster lubang angin m² 0,240 398.005,00 95.521,20
9 Pek. Pas. Roster beton m² 8,400 402.490,00 3.380.916,00
10 Pekerjaan spesi m² 10,080 95.270,00 960.321,60
Jumlah 21.201.266,58
VI PEKERJAAN ATAP
1 Pekerjaan atap beton
a. Pek. Beton campuran 1 sp : 2 ps : 3 kr m³ 1,470 1.320.118,00 1.940.573,46
b. Pek. tulangan besi Ø 10-150 kg 62,000 17.596,00 1.090.952,00
c. pek floordeck/bondeck m² 12,240 174.819,00 2.139.784,56
2 Pekerjaan Dinding Bata Merah Spesi 1 : 5 m² 1,800 166.609,00 299.896,20
3 Pekerjaan Plesteran m² 3,600 95.270,00 342.972,00
4 Pekerjaan Acian m² 3,600 58.187,00 209.473,20
Jumlah 6.023.651,42
VII PEKERJAAN PLAFON
1 Pekerjaan Rangka Plafond m² 12,240 155.898,00 1.908.191,52
2 Penutup Plafond m² 12,240 59.164,00 724.167,36
Jumlah 2.632.358,88
VIII PEKERJAAN KUSEN DAN PINTU
1 Kusen Dan Pintu Pvc Toilet (Royal), bh 2,000 717.117,00 1.434.234,00
Jumlah 1.434.234,00
2
IX PEKERJAAN PENGECATAN
1 Pekerjaan Pengecatan Dinding full m² 76,400 33.978,00 2.595.919,20
Jumlah 2.595.919,20
X PEKERJAAN SANITAIR
1 Pekerjaan Kloset jongkok bh 2,000 730.581,00 1.461.162,00
2 Pekerjaan Kran 1/2" bh 5,000 135.986,00 679.930,00
3 Floor Drain bh 3,000 126.164,00 378.492,00
4 Ember 20 lt bh 1,000 70.000,00 70.000,00
Jumlah 2.589.584,00
XI PEKERJAAN AIR BERSIH DAN AIR KOTOR
1 Pekerjaan Air bersih
a. Pek. Pipa PVC AW Ø 3/4" m' 4,000 26.802,00 107.208,00
b. Pek Pipa PVC AW Ø 1/2" m' 6,000 24.351,00 146.106,00
c. Pek. Knee PVC Ø 1/2" bh 2,000 2.500,00 5.000,00
d. Pek. Tee PVC Ø 1/2" bh 3,000 3.500,00 10.500,00
e. Pek. SDD PVC Ø 1/2" bh 5,000 3.500,00 17.500,00
f. Pek. Torn 800 lt bh 1,000 1.248.500,00 1.248.500,00
2 Pekerjaan air kotor
a. Pek. Pipa PVC AW Ø 3" m' 7,000 91.728,00 642.096,00
b. Pek. Pipa PVC AW Ø 4" bh 10,000 120.248,00 1.202.480,00
c. Knee PVC AW Ø 3" bh 3,000 23.000,00 69.000,00
Jumlah 3.448.390,00
XII PEKERJAAN ELEKTRIKAL
1 Instalasi titik penerangan NYM 3x2,5 mm2+Conduit dia.20mm m' 3,000 449.606,00 1.348.818,00
2 Pas. Lampu xl ESS Philips 14 watt + Armateur bh 3,000 62.000,00 186.000,00
4 Saklar tunggal bh 2,000 104.678,00 209.356,00
5 saklar ganda bh 1,000 110.486,00 110.486,00
6 Stop kontak bh 1,000 113.390,00 113.390,00
7 Pemasangan PLN 450 watt bh 1,000 1.519.200,00 1.519.200,00
Jumlah 3.487.250,00
XIII PEKERJAAN SEPTIK TANK
1 Pek. Galian tanah biasa m³ 12,590 119.924,00 1.509.843,16
2 Pek. Pembuangan tanah m³ 7,550 52.558,00 396.812,90
3 Pek. Pas bata merah 1:5 m² 12,200 166.609,00 2.032.629,80
4 Pek. Lantai Beton campuran 1 sp : 2 ps : 3 kr m³ 0,660 1.320.118,00 871.277,88
5 Pekerjaan pelat tutup septik tank
a. Pek. Beton campuran 1 sp : 2 ps : 3 kr m³ 1,010 1.320.118,00 1.333.319,18
b. Pek. tulangan besi Ø 10-150 kg 58,360 17.596,00 1.026.902,56
c. pek floordeck/bondeck m² 8,100 174.819,00 1.416.033,90
6 Pek. Tutup manhole
a. Pek. Beton campuran 1 sp : 2 ps : 3 kr m³ 0,080 1.320.118,00 105.609,44
b. Pek. tulangan besi Ø 10-150 kg 29,760 17.596,00 523.656,96
c. Bekisting m² 0,130 491.697,00 63.920,61
7 Pek kolom 15x15
a. Pek. Beton campuran 1 sp : 2 ps : 3 kr m³ 0,200 1.320.118,00 264.023,60
b. Pek. tulangan besi Ø 10, sk Ø 8-150 kg 34,320 17.596,00 603.894,72
c. pek Bekisting m² 1,350 428.677,00 578.713,95
7 Septik tank pabrikasi 3 m3 bh 1,000 17.500.000,00 17.500.000,00
8 Pek. Bak inlet
a. Pekerjaan Dinding Bata Merah Spesi 1 : 4 m² 0,360 169.068,00 60.864,48
b. Pekerjaan Plesteran m² 0,360 96.456,00 34.724,16
c. Pekerjaan Acian m² 0,360 58.187,00 20.947,32
d. Pek. Tutup bak inlet
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m³ 0,010 1.320.118,00 13.201,18
- Pek. tulangan besi Ø 10-150 kg 4,960 17.596,00 87.276,16
- Bekisting m² 0,080 491.697,00 39.335,76
9 Pek. Bak outlet
a. Pekerjaan Dinding Bata Merah Spesi 1 : 4 m² 0,420 169.068,00 71.008,56
b. Pekerjaan Plesteran m² 0,420 96.456,00 40.511,52
c. Pekerjaan Acian m² 0,420 58.187,00 24.438,54
d. Pek. Tutup bak inlet
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m³ 0,010 1.320.118,00 13.201,18
- Pek. tulangan besi Ø 10-150 kg 4,960 17.596,00 87.276,16
- Bekisting m² 0,130 491.697,00 63.920,61
Jumlah 28.783.344,29
3
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
MCK + SEPTIK TANK PABRIKASI TIPE I
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 2.253.180,28
II PEKERJAAN TANAH 953.304,00
III PEKERJAAN PONDASI 5.268.865,50
IV PEKERJAAN STRUKTUR 18.984.182,93
V PEKERJAAN DINDING DAN LANTAI 21.201.266,58
VI PEKERJAAN ATAP 6.023.651,42
VII PEKERJAAN PLAFON 2.632.358,88
VIII PEKERJAAN KUSEN DAN PINTU 1.434.234,00
IX PEKERJAAN PENGECATAN 2.595.919,20
X PEKERJAAN SANITAIR 2.589.584,00
XI PEKERJAAN AIR BERSIH DAN AIR KOTOR 3.448.390,00
XII PEKERJAAN ELEKTRIKAL 3.487.250,00
XIII PEKERJAAN SEPTIK TANK 28.783.344,29
JUMLAH (Rp) 99.655.531,08
PPN 10% 9.965.553,11
JUMLAH TOTAL (Rp) 109.621.084,19
JUMLAH DIBULATKAN (Rp) 109.621.000,00
4
ANALISIS STANDAR BELANJA (ASB)
MCK + SEPTIK TANK PABRIKASI TIPE II
1 KELOMPOK : Kontruksi
2 SUB KELOMPOK : Membangun MCK + Septictank Pabrikasi TIPE II
3 SUB- SUB KELOMPOK : Membangun MCK + Septictank Pabrikasi TIPE II
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Membangun MCK + Septictank Pabrikasi TIPE II
6 DESKRIPSI AKTIVITAS : Membangun MCK + Septictank Pabrikasi TIPE II
7 SATUAN AKTIVITAS : Unit
8 KOMPONEN/RINCIAN KOMPONEN :
NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
I PEKERJAAN PERSIAPAN
1 Pekerjaan Pengukuran dan pemasangan bouwplank m¹ 30,000 81.786,00 2.453.580,00
2 Pembuatan nama pekerjaan ls 1,000 251.059,00 251.059,00
Jumlah 2.704.639,00
II PEKERJAAN TANAH -
1 Galian tanah biasa sedalam 1 meter / m³ m³ 6,720 119.924,00 805.889,28
2 Urugan Kembali Tanah Bekas Galian m³ 2,070 86.899,00 179.880,93
Jumlah 985.770,21
III PEKERJAAN PONDASI -
1 Pasangan Batu belah kosong ( Aanstamping) m³ 1,550 650.982,00 1.009.022,10
2 Pasangan Batu belah 15/20 ( 1 PC: 5 PP) m³ 3,880 1.144.638,00 4.441.195,44
Jumlah 5.450.217,54
IV PEKERJAAN STRUKTUR -
1 Pek kolom 15x15 -
a. Pek. Beton campuran 1 sp : 2 ps : 3 kr m³ 0,610 1.320.118,00 805.271,98
b. Pek. tulangan besi Ø 10, sk Ø 8-150 kg 67,060 17.596,00 1.179.987,76
c. pek Bekisting m² 7,560 428.677,00 3.240.798,12
2 Pek kolom 15x20 -
a. Pek. Beton campuran 1 sp : 2 ps : 3 kr m³ 0,360 1.320.118,00 475.242,48
b. Pek. tulangan besi Ø 10, sk Ø 8-150 kg 32,720 17.596,00 575.741,12
c. pek Bekisting m² 4,480 428.677,00 1.920.472,96
3 Pek sloof 15x15 -
a. Pek. Beton campuran 1 sp : 2 ps : 3 kr m³ 0,470 1.320.118,00 620.455,46
b. Pek. tulangan besi Ø 10, sk Ø 8-150 kg 44,280 17.596,00 779.150,88
c. pek Bekisting m² 6,210 238.798,00 1.482.935,58
4 Pek ring balok 15x20 -
a. Pek. Beton campuran 1 sp : 2 ps : 3 kr m³ 0,360 1.320.118,00 475.242,48
b. Pek. tulangan besi Ø 10, sk Ø 8-150 kg 27,200 17.596,00 478.611,20
c. pek Bekisting m² 6,000 439.027,00 2.634.162,00
5 Pek balok 15x20 -
a. Pek. Beton campuran 1 sp : 2 ps : 3 kr m³ 0,260 1.320.118,00 343.230,68
b. Pek. tulangan besi Ø 10, sk Ø 8-150 kg 19,720 17.596,00 346.993,12
c. pek Bekisting m² 4,350 439.027,00 1.909.767,45
Jumlah 17.268.063,27
V PEKERJAAN DINDING DAN LANTAI -
1 Pekerjaan Dinding Bata Merah Spesi 1 : 5 m² 18,140 166.609,00 3.022.287,26
2 Pekerjaan Plesteran m² 3,880 95.270,00 369.647,60
3 Pekerjaan Acian m² 3,880 58.187,00 225.765,56
Pekerjaan Dinding Keramik Toilet/WC, 20x25 cm, tinggi 1,20
4 m² 12,840 277.283,00 3.560.313,72
m
Pekerjaan Lantai Keramik Toilet/WC, Uk. 20 x 20 cm, Anti
5 m² 9,000 185.580,00 1.670.220,00
Slip
6 Pekerjaan batu tempel m² 3,360 340.842,00 1.145.229,12
7 Pek. Pas Glass Block m² 0,640 815.110,00 521.670,40
8 Pek. Pas. Roster lubang angin m² 0,160 398.005,00 63.680,80
9 Pek. Pas. Roster beton m² 2,920 402.490,00 1.175.270,80
10 Pekerjaan spesi m² 11,840 95.270,00 1.127.996,80
Jumlah 12.882.082,06
VI PEKERJAAN ATAP -
1 Pekerjaan atap beton -
a. Pek. Beton campuran 1 sp : 2 ps : 3 kr m³ 2,850 1.320.118,00 3.762.336,30
b. Pek. tulangan besi Ø 10-150 kg 80,600 17.596,00 1.418.237,60
c. pek floordeck/bondeck m² 23,750 174.819,00 4.151.951,25
2 Pekerjaan Dinding Bata Merah Spesi 1 : 5 m² 3,000 166.609,00 499.827,00
3 Pekerjaan Plesteran m² 6,000 95.270,00 571.620,00
4 Pekerjaan Acian m² 6,000 58.187,00 349.122,00
Jumlah 10.753.094,15
VII PEKERJAAN PLAFON -
1 Pekerjaan Rangka Plafond m² 23,750 155.898,00 3.702.577,50
2 Penutup Plafond m² 23,750 59.164,00 1.405.145,00
Jumlah 5.107.722,50
VIII PEKERJAAN KUSEN DAN PINTU -
1 Kusen Dan Pintu Pvc Toilet (Royal), bh 2,000 717.117,00 1.434.234,00
Jumlah 1.434.234,00
5
IX PEKERJAAN PENGECATAN -
1 Pekerjaan Pengecatan Dinding full m² 7,760 33.978,00 263.669,28
Jumlah 263.669,28
X PEKERJAAN SANITAIR -
1 Pekerjaan Kloset jongkok bh 2,000 730.581,00 1.461.162,00
2 Pekerjaan Kran 1/2" bh 7,000 135.986,00 951.902,00
3 Floor Drain bh 3,000 126.164,00 378.492,00
4 Pek Bak fiber 60 x 60 bh 2,000 1.221.816,00 2.443.632,00
5 Pekerjaan wastafel set 1,000 2.717.432,00 2.717.432,00
Jumlah 7.952.620,00
XI PEKERJAAN AIR BERSIH DAN AIR KOTOR -
a Pekerjaan Air bersih -
a. Pek. Pipa PVC AW Ø 3/4" m' 6,000 26.802,00 160.812,00
b. Pek Pipa PVC AW Ø 1/2" m' 6,000 24.351,00 146.106,00
c. Pek. Knee PVC Ø 1/2" bh 2,000 2.500,00 5.000,00
d. Pek. Tee PVC Ø 1/2" bh 3,000 3.500,00 10.500,00
e. Pek. SDD PVC Ø 1/2" bh 5,000 3.500,00 17.500,00
f. Pek. Torn 800 lt bh 1,000 1.248.500,00 1.248.500,00
-
b Pengeboran -
Pekerjaaan pengadaan dan pemasangan 'Pipa casing PVC AW
m 30,000 48.759,00 1.462.770,00
2 inch
Pekerjaaan pengadaan dan pemasangan 'Pipa PVC AW 1 inch m 1,000 30.233,00 30.233,00
Knee PVC 1" m' 1,000 5.000,00 5.000,00
Sock Drat Luar (SDL) PVC 1" bh 2,000 5.000,00 10.000,00
Sock Drat Dalam (SDD) PVC 1" bh 3,000 5.000,00 15.000,00
Knee Drat Dalam (Faucet Elbow) PVC 1" bh 4,000 5.000,00 20.000,00
Water mur PVC 1" bh 5,000 39.500,00 197.500,00
Tusen klep 1" bh 6,000 69.500,00 417.000,00
Saringan 1" bh 7,000 2.500,00 17.500,00
Pengadaan pompa jet pump bh 1,000 4.000.000,00 4.000.000,00
-
2 Pekerjaan air kotor -
a. Pek. Pipa PVC AW Ø 3" m' 10,000 91.728,00 917.280,00
b. Pek. Pipa PVC AW Ø 4" bh 8,000 120.248,00 961.984,00
c. Knee PVC AW Ø 3" bh 3,000 23.000,00 69.000,00
Jumlah 9.711.685,00
XII PEKERJAAN ELEKTRIKAL -
1 Instalasi titik penerangan NYM 3x2,5 mm2+Conduit dia.20mm m' 4,000 449.606,00 1.798.424,00
2 Pas. Lampu xl ESS Philips 14 watt + Armateur bh 4,000 62.000,00 248.000,00
4 Saklar tunggal bh 2,000 104.678,00 209.356,00
5 saklar ganda bh 1,000 110.486,00 110.486,00
6 Stop kontak bh 1,000 113.390,00 113.390,00
7 Pemasangan PLN 900 watt bh 1,000 2.101.400,00 2.101.400,00
Jumlah 4.581.056,00
XIII PEKERJAAN IPAL -
1 Pek. Galian tanah biasa 2 m m³ 20,000 147.037,00 2.940.740,00
2 Pek. Pembuangan tanah m³ 12,000 52.558,00 630.696,00
3 Pek. Pas bata merah 1:5 m² 13,800 166.609,00 2.299.204,20
4 Pek. Urugan pasir dengan pasir urug m³ 0,800 268.769,00 215.015,20
5 Pekerjaan beton -
a. Pek. Lantai kerja Beton campuran 1 sp : 3 ps : 5 kr m³ 0,800 1.016.351,00 813.080,80
b. Pek. Lantai IPAL -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m³ 1,200 1.320.118,00 1.584.141,60
- Pek. tulangan besi Ø 10-150 kg 127,350 17.596,00 2.240.850,60
c. Pekerjaan atap IPAL -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m³ 0,900 1.320.118,00 1.188.106,20
- Pek. tulangan besi Ø 10-150 kg 105,810 17.596,00 1.861.832,76
- Pek floordeck/bondeck m² 8,000 174.819,00 1.398.552,00
d. Pekerjaan dinding IPAL -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m³ 3,240 1.320.118,00 4.277.182,32
- Pek. tulangan besi Ø 10-150 kg 173,690 17.596,00 3.056.249,24
- Bekisting m² 10,800 467.087,00 5.044.539,60
- acian m² 9,900 58.187,00 576.051,30
e. Pekerjaan dinding kompartemen -
- Pekerjaan Dinding Bata Merah Spesi 1 : 4 m² 11,400 169.068,00 1.927.375,20
- Plesteran m² 22,800 96.456,00 2.199.196,80
- acian m² 22,800 58.187,00 1.326.663,60
f. Pek. Tutup manhole -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m³ 0,060 1.320.118,00 79.207,08
- Pek. tulangan besi Ø 10-150 kg 24,800 17.596,00 436.380,80
- Bekisting m² 0,130 491.697,00 63.920,61
g. Pek. Dududukan media bakteri dan penyangga -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m³ 0,160 1.320.118,00 211.218,88
- Pek. tulangan besi Ø 8-150 kg 17,570 17.596,00 309.161,72
- Bekisting m² 0,110 491.697,00 54.086,67
- beton penyangga campuran 1 sp : 2 ps : 3 kr kg 0,100 1.320.118,00 132.011,80
6
6 Pek. Bak inlet -
a. Pekerjaan Dinding Bata Merah Spesi 1 : 4 m² 1,440 169.068,00 243.457,92
b. Pekerjaan Plesteran m² 1,440 96.456,00 138.896,64
c. Pekerjaan Acian m² 1,440 58.187,00 83.789,28
d. Pek. Tutup bak inlet dan bak penangkap lemak -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m³ 0,020 1.320.118,00 26.402,36
- Pek. tulangan besi Ø 10-150 kg 8,600 17.596,00 151.325,60
- Bekisting m² 0,170 491.697,00 83.588,49
- Screen bh 1,000 100.000,00 100.000,00
7 Pek. Bak outlet -
a. Pekerjaan Dinding Bata Merah Spesi 1 : 4 m² 0,420 169.068,00 71.008,56
b. Pekerjaan Plesteran m² 0,420 96.456,00 40.511,52
c. Pekerjaan Acian m² 0,420 58.187,00 24.438,54
d. Pek. Tutup bak inlet -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m³ 0,010 1.320.118,00 13.201,18
- Pek. tulangan besi Ø 10-150 kg 4,960 17.596,00 87.276,16
- Bekisting m² 0,130 491.697,00 63.920,61
8 Pekerjaan pipa kompartemen -
a. Pipa PVC AW Ø 3" m' 20,400 91.728,00 1.871.251,20
b. Pipa PVC AW Ø 4" m' 1,000 120.248,00 120.248,00
c. Tee PVC AW Ø 4" bh 2,000 140.000,00 280.000,00
e. Tee PVC AW Ø 3" bh 24,000 52.000,00 1.248.000,00
f. Pipa GI medium Ø 2" untuk ventilasi m' 3,000 108.500,00 325.500,00
g. Tee GI Ø 2" untuk ventilasi bh 3,000 204.600,00 613.800,00
h. Media bakteri m³ 2,000 300.000,00 600.000,00
i. Pengecatan IPAL m² 8,000 42.948,00 343.584,00
Jumlah 41.395.665,04
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
MCK + SEPTIK TANK PABRIKASI TIPE II
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 2.704.639,00
II PEKERJAAN TANAH 985.770,21
III PEKERJAAN PONDASI 5.450.217,54
IV PEKERJAAN STRUKTUR 17.268.063,27
V PEKERJAAN DINDING DAN LANTAI 12.882.082,06
VI PEKERJAAN ATAP 10.753.094,15
VII PEKERJAAN PLAFON 5.107.722,50
VIII PEKERJAAN KUSEN DAN PINTU 1.434.234,00
IX PEKERJAAN PENGECATAN 263.669,28
X PEKERJAAN SANITAIR 7.952.620,00
XI PEKERJAAN AIR BERSIH DAN AIR KOTOR 9.711.685,00
XII PEKERJAAN ELEKTRIKAL 4.581.056,00
XIII PEKERJAAN IPAL 41.395.665,04
JUMLAH (Rp) 120.490.518,05
PPN 10% 12.049.051,81
JUMLAH TOTAL (Rp) 132.539.569,86
JUMLAH DIBULATKAN (Rp) 132.539.000,00
7
ANALISIS STANDAR BELANJA (ASB)
MCK + SEPTIK TANK PABRIKASI TIPE III
1 KELOMPOK : Kontruksi
2 SUB KELOMPOK : Membangun MCK + Septictank Pabrikasi TIPE III
3 SUB- SUB KELOMPOK : Membangun MCK + Septictank Pabrikasi TIPE III
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Membangun MCK + Septictank Pabrikasi TIPE III
6 DESKRIPSI AKTIVITAS : Membangun MCK + Septictank Pabrikasi TIPE III
7 SATUAN AKTIVITAS : Unit
8 KOMPONEN/RINCIAN KOMPONEN :
NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
I PEKERJAAN PERSIAPAN
1 Pekerjaan Pengukuran dan pemasangan bouwplank m¹ 28,500 81.786,00 2.330.901,00
2 Pembuatan nama pekerjaan ls 1,000 251.059,00 251.059,00
Jumlah 2.581.960,00
-
II PEKERJAAN TANAH -
1 Galian tanah biasa sedalam 1 meter / m³ m³ 8,100 119.924,00 971.384,40
2 Urugan Kembali Tanah Bekas Galian m³ 2,490 86.899,00 216.378,51
Jumlah 1.187.762,91
III PEKERJAAN PONDASI -
1 Pasangan Batu belah kosong ( Aanstamping) m³ 1,870 650.982,00 1.217.336,34
2 Pasangan Batu belah 15/20 ( 1 PC: 5 PP) m³ 4,670 1.144.638,00 5.345.459,46
Jumlah 6.562.795,80
IV PEKERJAAN STRUKTUR -
1 Pek kolom 15x15 -
a. Pek. Beton campuran 1 sp : 2 ps : 3 kr m³ 0,540 1.320.118,00 712.863,72
b. Pek. tulangan besi Ø 10, sk Ø 8-150 kg 67,060 17.596,00 1.179.987,76
c. pek Bekisting m2 6,720 428.677,00 2.880.709,44
2 Pek kolom 15x20 -
a. Pek. Beton campuran 1 sp : 2 ps : 3 kr m³ 0,360 1.320.118,00 475.242,48
b. Pek. tulangan besi Ø 10, sk Ø 8-150 kg 32,720 17.596,00 575.741,12
c. pek Bekisting m2 4,480 428.677,00 1.920.472,96
3 Pek sloof 15x15 -
a. Pek. Beton campuran 1 sp : 2 ps : 3 kr m³ 0,560 1.320.118,00 739.266,08
b. Pek. tulangan besi Ø 10, sk Ø 8-150 kg 53,330 17.596,00 938.394,68
c. pek Bekisting m2 7,480 238.798,00 1.786.209,04
4 Pek ring balok 15x20 -
a. Pek. Beton campuran 1 sp : 2 ps : 3 kr m³ 0,500 1.320.118,00 660.059,00
b. Pek. tulangan besi Ø 10, sk Ø 8-150 kg 37,850 17.596,00 666.008,60
c. pek Bekisting m2 8,350 439.027,00 3.665.875,45
5 Pek balok 15x20 -
a. Pek. Beton campuran 1 sp : 2 ps : 3 kr m³ 0,240 1.320.118,00 316.828,32
b. Pek. tulangan besi Ø 10, sk Ø 8-150 kg 18,020 17.596,00 317.079,92
c. pek Bekisting m2 3,980 439.027,00 1.747.327,46
Jumlah 18.582.066,03
V PEKERJAAN DINDING DAN LANTAI -
1 Pekerjaan Dinding Bata Merah Spesi 1 : 5 m² 47,580 166.609,00 7.927.256,22
2 Pekerjaan Plesteran m² 35,600 95.270,00 3.391.612,00
3 Pekerjaan Acian m² 35,600 58.187,00 2.071.457,20
Pekerjaan Dinding Keramik Toilet/WC, 20x25 cm, tinggi 1,20
4 m² 22,280 277.283,00 6.177.865,24
m
Pekerjaan Lantai Keramik Toilet/WC, Uk. 20 x 20 cm, Anti
5 m² 10,360 185.580,00 1.922.608,80
Slip
6 Pekerjaan batu tempel m2 7,500 340.842,00 2.556.315,00
7 Pek. Pas Glass Block m² 1,120 815.110,00 912.923,20
8 Pek. Pas. Roster lubang angin m² 0,240 398.005,00 95.521,20
9 Pek. Pas. Roster beton m² 1,310 402.490,00 527.261,90
10 Pekerjaan spesi m² 13,100 95.270,00 1.248.037,00
Jumlah 26.830.857,76
VI PEKERJAAN ATAP -
1 Pekerjaan atap beton -
a. Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 2,770 1.320.118,00 3.656.726,86
b. Pek. tulangan besi Ø 10-150 kg 72,330 17.596,00 1.272.718,68
c. pek floordeck/bondeck m2 23,100 174.819,00 4.038.318,90
2 Pekerjaan Dinding Bata Merah Spesi 1 : 5 m² 3,750 166.609,00 624.783,75
3 Pekerjaan Plesteran m² 7,500 95.270,00 714.525,00
4 Pekerjaan Acian m² 7,500 58.187,00 436.402,50
Jumlah 10.743.475,69
VII PEKERJAAN PLAFON -
1 Pekerjaan Rangka Plafond m² 23,100 155.898,00 3.601.243,80
2 Penutup Plafond m² 23,100 59.164,00 1.366.688,40
Jumlah 4.967.932,20
8
VIII PEKERJAAN KUSEN DAN PINTU -
1 Kusen Dan Pintu Pvc Toilet (Royal), bh 3,000 717.117,00 2.151.351,00
Jumlah 2.151.351,00
IX PEKERJAAN PENGECATAN -
1 Pekerjaan Pengecatan Dinding full m2 71,200 33.978,00 2.419.233,60
Jumlah 2.419.233,60
X PEKERJAAN SANITAIR -
1 Pekerjaan Kloset jongkok bh 3,000 730.581,00 2.191.743,00
2 Pekerjaan Kran 1/2" bh 7,000 135.986,00 951.902,00
3 Floor Drain bh 4,000 126.164,00 504.656,00
4 Pek Bak fiber 60 x 60 bh 3,000 1.221.816,00 3.665.448,00
5 Pekerjaan wastafel set 1,000 2.717.432,00 2.717.432,00
Jumlah 10.031.181,00
XI PEKERJAAN AIR BERSIH DAN AIR KOTOR -
a Pekerjaan Instalasi Air bersih -
a. Pek. Pipa PVC AW Ø 3/4" m' 6,000 26.802,00 160.812,00
b. Pek Pipa PVC AW Ø 1/2" m' 7,000 24.351,00 170.457,00
c. Pek. Knee PVC Ø 1/2" bh 2,000 3.500,00 7.000,00
d. Pek. Tee PVC Ø 1/2" bh 4,000 3.500,00 14.000,00
e. Pek. SDD PVC Ø 1/2" bh 8,000 3.500,00 28.000,00
f. Pek. Torn 800 lt bh 1,000 1.248.500,00 1.248.500,00
-
b Pengeboran air bersih -
Pekerjaaan pengadaan dan pemasangan 'Pipa casing PVC AW
m 27,000 48.759,00 1.316.493,00
2 inch
Pekerjaaan pengadaan dan pemasangan 'Pipa PVC AW 1 inch m 1,000 30.233,00 30.233,00
Knee PVC 1" m' 1,000 5.000,00 5.000,00
Sock Drat Luar (SDL) PVC 1" bh 2,000 5.000,00 10.000,00
Sock Drat Dalam (SDD) PVC 1" bh 3,000 5.000,00 15.000,00
Knee Drat Dalam (Faucet Elbow) PVC 1" bh 4,000 5.000,00 20.000,00
Water mur PVC 1" bh 5,000 39.500,00 197.500,00
Tusen klep 1" bh 6,000 69.500,00 417.000,00
Saringan 1" bh 7,000 2.500,00 17.500,00
Pengadaan pompa jet pump bh 1,000 4.000.000,00 4.000.000,00
-
2 Pekerjaan air kotor -
a. Pek. Pipa PVC AW Ø 3" m' 7,000 91.728,00 642.096,00
b. Pek. Pipa PVC AW Ø 4" bh 7,000 120.248,00 841.736,00
c. Knee PVC AW Ø 3" bh 3,000 23.000,00 69.000,00
Jumlah 9.210.327,00
XII PEKERJAAN ELEKTRIKAL -
1 Instalasi titik penerangan NYM 3x2,5 mm2+Conduit dia.20mm m' 5,000 449.606,00 2.248.030,00
2 Pas. Lampu xl ESS Philips 14 watt + Armateur bh 5,000 62.000,00 310.000,00
4 Saklar tunggal bh 3,000 104.678,00 314.034,00
5 saklar ganda bh 1,000 110.486,00 110.486,00
6 Stop kontak bh 1,000 113.390,00 113.390,00
7 Pemasangan PLN 900 watt bh 1,000 2.101.400,00 2.101.400,00
Jumlah 5.197.340,00
XIII PEKERJAAN IPAL -
1 Pek. Galian tanah biasa 2 m m3 22,500 147.037,00 3.308.332,50
2 Pek. Pembuangan tanah m3 13,500 52.558,00 709.533,00
3 Pek. Pas bata merah 1:5 m2 14,100 166.609,00 2.349.186,90
4 Pek. Urugan pasir dengan pasir urug m3 0,900 268.769,00 241.892,10
5 Pekerjaan beton -
a. Pek. Lantai kerja Beton campuran 1 sp : 3 ps : 5 kr m3 - 1.016.351,00 -
b. Pek. Lantai IPAL -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 1,800 1.320.118,00 2.376.212,40
- Pek. tulangan besi Ø 10-150 kg 143,670 17.596,00 2.528.017,32
c. Pekerjaan atap IPAL -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 1,020 1.320.118,00 1.346.520,36
- Pek. tulangan besi Ø 10-150 kg 118,870 17.596,00 2.091.636,52
- Pek floordeck/bondeck m2 9,000 1.288.543,00 11.596.887,00
d. Pekerjaan dinding IPAL -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 3,570 1.320.118,00 4.712.821,26
- Pek. tulangan besi Ø 10-150 kg 191,430 17.596,00 3.368.402,28
- Bekisting m2 11,300 467.087,00 5.278.083,10
- acian dinding m2 10,400 58.187,00 605.144,80
e. Pekerjaan dinding kompartemen -
- Pekerjaan Dinding Bata Merah Spesi 1 : 4 m2 12,400 169.068,00 2.096.443,20
- Plesteran m2 24,800 96.456,00 2.392.108,80
- acian m2 24,800 58.187,00 1.443.037,60
e. Pek. Tutup manhole -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 0,060 1.320.118,00 79.207,08
- Pek. tulangan besi Ø 10-150 kg 24,800 17.596,00 436.380,80
- Bekisting m2 0,130 491.697,00 63.920,61
9
f. Pek. Dududukan media bakteri dan penyangga -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 0,740 1.320.118,00 976.887,32
- Pek. tulangan besi Ø 8-150 kg 26,220 17.596,00 461.367,12
- Bekisting m2 0,310 491.697,00 152.426,07
- beton penyangga campuran 1 sp : 2 ps : 3 kr kg 0,100 1.320.118,00 132.011,80
6 Pek. Bak inlet -
a. Pekerjaan Dinding Bata Merah Spesi 1 : 4 m² 0,360 169.068,00 60.864,48
b. Pekerjaan Plesteran m² 0,360 96.456,00 34.724,16
c. Pekerjaan Acian m² 0,360 58.187,00 20.947,32
d. Pek. Tutup bak inlet -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 0,010 1.320.118,00 13.201,18
- Pek. tulangan besi Ø 10-150 kg 4,960 17.596,00 87.276,16
- Bekisting m2 0,080 491.697,00 39.335,76
Screen bh 1,000 100.000,00 100.000,00
7 Pek. Bak outlet -
a. Pekerjaan Dinding Bata Merah Spesi 1 : 4 m² 0,420 169.068,00 71.008,56
b. Pekerjaan Plesteran m² 0,420 96.456,00 40.511,52
c. Pekerjaan Acian m² 0,420 58.187,00 24.438,54
d. Pek. Tutup bak inlet -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 0,010 1.320.118,00 13.201,18
- Pek. tulangan besi Ø 10-150 kg 4,960 17.596,00 87.276,16
- Bekisting m2 0,130 491.697,00 63.920,61
8 Pekerjaan pipa kompartemen -
a. Pipa PVC AW Ø 3" m' 20,400 91.728,00 1.871.251,20
b. Pipa PVC AW Ø 4" m' 1,000 120.248,00 120.248,00
c. Tee PVC AW Ø 4" bh 2,000 140.000,00 280.000,00
e. Tee PVC AW Ø 3" bh 24,000 52.000,00 1.248.000,00
f. Pipa GI medium Ø 2" untuk ventilasi m' 3,000 108.500,00 325.500,00
g. Tee GI Ø 2" untuk ventilasi bh 3,000 204.600,00 613.800,00
h. Media bakteri m3 3,000 300.000,00 900.000,00
i. Pengecatan IPAL m2 11,000 42.948,00 472.428,00
Jumlah 55.234.392,77
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
MCK + Septictank Pabrikasi TIPE III
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 2.581.960,00
II PEKERJAAN TANAH 1.187.762,91
III PEKERJAAN PONDASI 6.562.795,80
IV PEKERJAAN STRUKTUR 18.582.066,03
V PEKERJAAN DINDING DAN LANTAI 26.830.857,76
VI PEKERJAAN ATAP 10.743.475,69
VII PEKERJAAN PLAFON 4.967.932,20
VIII PEKERJAAN KUSEN DAN PINTU 2.151.351,00
IX PEKERJAAN PENGECATAN 2.419.233,60
X PEKERJAAN SANITAIR 10.031.181,00
XI PEKERJAAN AIR BERSIH DAN AIR KOTOR 9.210.327,00
XII PEKERJAAN ELEKTRIKAL 5.197.340,00
XIII PEKERJAAN IPAL 55.234.392,77
JUMLAH (Rp) 155.700.675,76
PPN 10% 15.570.067,58
JUMLAH TOTAL (Rp) 171.270.743,34
JUMLAH DIBULATKAN (Rp) 171.270.000,00
10
ANALISIS STANDAR BELANJA (ASB)
MCK + SEPTIK TANK PABRIKASI TIPE IV
1 KELOMPOK : Kontruksi
2 SUB KELOMPOK : Membangun MCK + Septictank Pabrikasi TIPE IV
3 SUB- SUB KELOMPOK : Membangun MCK + Septictank Pabrikasi TIPE IV
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Membangun MCK + Septictank Pabrikasi TIPE IV
6 DESKRIPSI AKTIVITAS : Membangun MCK + Septictank Pabrikasi TIPE IV
7 SATUAN AKTIVITAS : Unit
8 KOMPONEN/RINCIAN KOMPONEN :
NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
I PEKERJAAN PERSIAPAN
1 Pekerjaan Pengukuran dan pemasangan bouwplank m¹ 33,990 81.786,00 2.779.906,14
2 Pembuatan nama pekerjaan ls 1,000 251.059,00 251.059,00
Jumlah 3.030.965,14
-
II PEKERJAAN TANAH -
1 Galian tanah biasa sedalam 1 meter / m³ m³ 8,990 119.924,00 1.078.116,76
2 Urugan Kembali Tanah Bekas Galian m³ 2,770 86.899,00 240.710,23
Jumlah 1.318.826,99
III PEKERJAAN PONDASI -
1 Pasangan Batu belah kosong ( Aanstamping) m³ 2,070 650.982,00 1.347.532,74
2 Pasangan Batu belah 15/20 ( 1 PC: 5 PP) m³ 5,180 1.144.638,00 5.929.224,84
Jumlah 7.276.757,58
IV PEKERJAAN STRUKTUR -
1 Pek kolom 15x15 -
a. Pek. Beton campuran 1 sp : 2 ps : 3 kr m³ 0,740 1.320.118,00 976.887,32
b. Pek. tulangan besi Ø 10, sk Ø 8-150 kg 67,060 17.596,00 1.179.987,76
c. pek Bekisting m2 9,240 428.677,00 3.960.975,48
2 Pek kolom 15x20 -
a. Pek. Beton campuran 1 sp : 2 ps : 3 kr m³ 0,360 1.320.118,00 475.242,48
b. Pek. tulangan besi Ø 10, sk Ø 8-150 kg 32,720 17.596,00 575.741,12
c. pek Bekisting m2 4,480 428.677,00 1.920.472,96
3 Pek sloof 15x15 -
a. Pek. Beton campuran 1 sp : 2 ps : 3 kr m³ 0,620 1.320.118,00 818.473,16
b. Pek. tulangan besi Ø 10, sk Ø 8-150 kg 59,170 17.596,00 1.041.155,32
c. pek Bekisting m2 8,300 238.798,00 1.982.023,40
4 Pek ring balok 15x20 -
a. Pek. Beton campuran 1 sp : 2 ps : 3 kr m³ 0,420 1.320.118,00 554.449,56
b. Pek. tulangan besi Ø 10, sk Ø 8-150 kg 31,730 17.596,00 558.321,08
c. pek Bekisting m2 7,000 439.027,00 3.073.189,00
5 Pek balok 15x20 -
a. Pek. Beton campuran 1 sp : 2 ps : 3 kr m³ 0,640 1.320.118,00 844.875,52
b. Pek. tulangan besi Ø 10, sk Ø 8-150 kg 48,170 17.596,00 847.599,32
c. pek Bekisting m2 10,630 439.027,00 4.666.857,01
Jumlah 23.476.250,49
V PEKERJAAN DINDING DAN LANTAI -
1 Pekerjaan Dinding Bata Merah Spesi 1 : 5 m² 51,850 166.609,00 8.638.676,65
2 Pekerjaan Plesteran m² 39,980 95.270,00 3.808.894,60
3 Pekerjaan Acian m² 39,980 58.187,00 2.326.316,26
Pekerjaan Dinding Keramik Toilet/WC, 20x25 cm, tinggi 1,20
4 m² 25,440 277.283,00 7.054.079,52
m
Pekerjaan Lantai Keramik Toilet/WC, Uk. 20 x 20 cm, Anti
5 m² 11,970 185.580,00 2.221.392,60
Slip
6 Pekerjaan batu tempel m2 6,420 340.842,00 2.188.205,64
7 Pek. Pas Glass Block m² 0,480 815.110,00 391.252,80
8 Pek. Pas. Roster lubang angin m² 0,240 398.005,00 95.521,20
9 Pek. Pas. Roster beton m² 3,430 402.490,00 1.380.540,70
10 Pekerjaan spesi m² 13,910 95.270,00 1.325.205,70
Jumlah 29.430.085,67
VI PEKERJAAN ATAP -
1 Pekerjaan atap beton -
a. Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 3,170 1.320.118,00 4.184.774,06
b. Pek. tulangan besi Ø 10-150 kg 85,560 17.596,00 1.505.513,76
c. pek floordeck/bondeck m2 26,450 174.819,00 4.623.962,55
2 Pekerjaan Dinding Bata Merah Spesi 1 : 5 m² 3,860 166.609,00 643.110,74
3 Pekerjaan Plesteran m² 7,730 95.270,00 736.437,10
4 Pekerjaan Acian m² 7,730 58.187,00 449.785,51
Jumlah 12.143.583,72
VII PEKERJAAN PLAFON -
1 Pekerjaan Rangka Plafond m² 26,450 155.898,00 4.123.502,10
2 Penutup Plafond m² 26,450 59.164,00 1.564.887,80
Jumlah 5.688.389,90
VII PEKERJAAN KUSEN DAN PINTU -
1 Kusen Dan Pintu Pvc Toilet (Royal), bh 3,000 717.117,00 2.151.351,00
Jumlah 2.151.351,00
11
VIII PEKERJAAN PENGECATAN -
1 Pekerjaan Pengecatan Dinding full m2 79,950 33.978,00 2.716.541,10
Jumlah 2.716.541,10
IX PEKERJAAN SANITAIR -
1 Pekerjaan Kloset jongkok bh 3,000 730.581,00 2.191.743,00
2 Pekerjaan Kran 1/2" bh 7,000 135.986,00 951.902,00
3 Floor Drain bh 4,000 126.164,00 504.656,00
4 Pek Bak fiber 60 x 60 bh 3,000 1.221.816,00 3.665.448,00
5 Pekerjaan wastafel set 1,000 2.717.432,00 2.717.432,00
Jumlah 10.031.181,00
X PEKERJAAN AIR BERSIH DAN AIR KOTOR -
a Pekerjaan Air bersih -
a. Pek. Pipa PVC AW Ø 3/4" m' 6,000 26.802,00 160.812,00
b. Pek Pipa PVC AW Ø 1/2" m' 8,000 24.351,00 194.808,00
c. Pek. Knee PVC Ø 1/2" bh 3,000 3.500,00 10.500,00
d. Pek. Tee PVC Ø 1/2" bh 4,000 3.500,00 14.000,00
e. Pek. SDD PVC Ø 1/2" bh 8,000 3.500,00 28.000,00
f. Pek. Torn 800 lt bh 1,000 1.248.500,00 1.248.500,00
-
b Pengeboran -
Pekerjaaan pengadaan dan pemasangan 'Pipa casing PVC AW
m 30,000 48.759,00 1.462.770,00
2 inch
Pekerjaaan pengadaan dan pemasangan 'Pipa PVC AW 1 inch m 1,000 30.233,00 30.233,00
Knee PVC 1" m' 1,000 5.000,00 5.000,00
Sock Drat Luar (SDL) PVC 1" bh 2,000 5.000,00 10.000,00
Sock Drat Dalam (SDD) PVC 1" bh 3,000 5.000,00 15.000,00
Knee Drat Dalam (Faucet Elbow) PVC 1" bh 4,000 5.000,00 20.000,00
Water mur PVC 1" bh 5,000 39.500,00 197.500,00
Tusen klep 1" bh 6,000 69.500,00 417.000,00
Saringan 1" bh 7,000 2.500,00 17.500,00
Pengadaan pompa jet pump bh 1,000 4.000.000,00 4.000.000,00
-
2 Pekerjaan air kotor -
a. Pek. Pipa PVC AW Ø 3" m' 10,000 91.728,00 917.280,00
b. Pek. Pipa PVC AW Ø 4" bh 8,000 120.248,00 961.984,00
c. Knee PVC AW Ø 3" bh 3,000 23.000,00 69.000,00
Jumlah 9.779.887,00
XI PEKERJAAN ELEKTRIKAL -
1 Instalasi titik penerangan NYM 3x2,5 mm2+Conduit dia.20mm m' 6,000 449.606,00 2.697.636,00
2 Pas. Lampu xl ESS Philips 14 watt + Armateur bh 6,000 62.000,00 372.000,00
4 Saklar tunggal bh 3,000 104.678,00 314.034,00
5 saklar ganda bh 2,000 110.486,00 220.972,00
6 Stop kontak bh 1,000 113.390,00 113.390,00
7 Pemasangan PLN 900 watt bh 1,000 2.101.400,00 2.101.400,00
Jumlah 5.819.432,00
XII PEKERJAAN IPAL -
1 Pek. Galian tanah biasa 2 m m3 27,500 147.037,00 4.043.517,50
2 Pek. Pembuangan tanah m3 16,500 52.558,00 867.207,00
3 Pek. Pas bata merah 1:5 m2 14,100 166.609,00 2.349.186,90
4 Pek. Urugan pasir dengan pasir urug m3 1,100 268.769,00 295.645,90
5 Pekerjaan beton -
a. Pek. Lantai kerja Beton campuran 1 sp : 3 ps : 5 kr m3 - 1.016.351,00 -
b. Pek. Lantai IPAL -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 2,200 1.320.118,00 2.904.259,60
- Pek. tulangan besi Ø 10-150 kg 176,330 17.596,00 3.102.702,68
c. Pekerjaan atap IPAL -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 1,260 1.320.118,00 1.663.348,68
- Pek. tulangan besi Ø 10-150 kg 151,530 17.596,00 2.666.321,88
- Pek floordeck/bondeck m2 11,000 174.819,00 1.923.009,00
d. Pekerjaan dinding IPAL -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 3,870 1.320.118,00 5.108.856,66
- Pek. tulangan besi Ø 10-150 kg 207,550 17.596,00 3.652.049,80
- Bekisting m2 12,300 467.087,00 5.745.170,10
- acian m2 19,220 58.187,00 1.118.354,14
e. Pekerjaan dinding kompartemen -
- Pekerjaan Dinding Bata Merah Spesi 1 : 4 m2 14,400 169.068,00 2.434.579,20
- Plesteran m2 28,800 96.456,00 2.777.932,80
- acian m2 28,800 58.187,00 1.675.785,60
e. Pek. Tutup manhole -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 0,060 1.320.118,00 79.207,08
- Pek. tulangan besi Ø 10-150 kg 24,800 17.596,00 436.380,80
- Bekisting m2 0,130 491.697,00 63.920,61
f. Pek. Dududukan media bakteri dan penyangga -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 0,740 1.320.118,00 976.887,32
- Pek. tulangan besi Ø 8-150 kg 26,220 17.596,00 461.367,12
- Bekisting m2 0,310 491.697,00 152.426,07
- beton penyangga campuran 1 sp : 2 ps : 3 kr kg 0,100 1.320.118,00 132.011,80
12
6 Pek. Bak inlet -
a. Pekerjaan Dinding Bata Merah Spesi 1 : 4 m² 0,360 169.068,00 60.864,48
b. Pekerjaan Plesteran m² 0,360 96.456,00 34.724,16
c. Pekerjaan Acian m² 0,360 58.187,00 20.947,32
d. Pek. Tutup bak inlet -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 0,010 1.320.118,00 13.201,18
- Pek. tulangan besi Ø 10-150 kg 4,960 17.596,00 87.276,16
- Bekisting m2 0,080 491.697,00 39.335,76
- Screen bh 1,000 100.000,00 100.000,00
7 Pek. Bak outlet -
a. Pekerjaan Dinding Bata Merah Spesi 1 : 4 m² 0,420 169.068,00 71.008,56
b. Pekerjaan Plesteran m² 0,420 96.456,00 40.511,52
c. Pekerjaan Acian m² 0,420 58.187,00 24.438,54
d. Pek. Tutup bak inlet -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 0,010 1.320.118,00 13.201,18
- Pek. tulangan besi Ø 10-150 kg 4,960 17.596,00 87.276,16
- Bekisting m2 0,130 491.697,00 63.920,61
8 Pekerjaan pipa kompartemen -
a. Pipa PVC AW Ø 3" m' 20,400 91.728,00 1.871.251,20
b. Pipa PVC AW Ø 4" m' 1,000 120.248,00 120.248,00
c. Tee PVC AW Ø 4" bh 2,000 140.000,00 280.000,00
e. Tee PVC AW Ø 3" bh 24,000 52.000,00 1.248.000,00
f. Pipa GI medium Ø 2" untuk ventilasi m' 3,000 108.500,00 325.500,00
g. Tee GI Ø 2" untuk ventilasi bh 3,000 204.600,00 613.800,00
h. Media bakteri m3 3,000 300.000,00 900.000,00
i. Pengecatan IPAL m2 11,000 42.948,00 472.428,00
Jumlah 51.118.061,07
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
MCK + SEPTIK TANK PABRIKASI TIPE IV
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 3.030.965,14
II PEKERJAAN TANAH 1.318.826,99
III PEKERJAAN PONDASI 7.276.757,58
IV PEKERJAAN STRUKTUR 23.476.250,49
V PEKERJAAN DINDING DAN LANTAI 29.430.085,67
VI PEKERJAAN ATAP 12.143.583,72
VII PEKERJAAN PLAFON 5.688.389,90
VIII PEKERJAAN KUSEN DAN PINTU 2.151.351,00
IX PEKERJAAN PENGECATAN 2.716.541,10
X PEKERJAAN SANITAIR 10.031.181,00
XI PEKERJAAN AIR BERSIH DAN AIR KOTOR 9.779.887,00
XII PEKERJAAN ELEKTRIKAL 5.819.432,00
XIII PEKERJAAN IPAL 51.118.061,07
JUMLAH (Rp) 163.981.312,66
PPN 10% 16.398.131,27
JUMLAH TOTAL (Rp) 180.379.443,93
JUMLAH DIBULATKAN (Rp) 180.379.000,00
13
ANALISIS STANDAR BELANJA (ASB)
IPAL KOMUNAL + JARINGAN (SR) 25 SR
1 KELOMPOK : Kontruksi
2 SUB KELOMPOK : Membangun IPAL Komunal + Jaringan (SR) 25 SR
3 SUB- SUB KELOMPOK : Membangun IPAL Komunal + Jaringan (SR) 25 SR
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Membangun IPAL Komunal + Jaringan (SR) 25 SR
6 DESKRIPSI AKTIVITAS : Membangun IPAL Komunal + Jaringan (SR) 25 SR
7 SATUAN AKTIVITAS : Unit
8 KOMPONEN/RINCIAN KOMPONEN :
NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
I PEKERJAAN PERSIAPAN
1 Pekerjaan Pengukuran dan pemasangan bouwplank m¹ 24,000 81.786,00 1.962.864,00
2 Pembuatan nama pekerjaan ls 1,000 251.059,00 251.059,00
Jumlah 2.213.923,00
II PEKERJAAN JARINGAN PIPA AIR LIMBAH -
1 Pekerjaan pipa -
a. Pek. Pipa PVC SNI Ø 3" m' 30,000 91.728,00 2.751.840,00
b. Pek. Pipa PVC SNII Ø 4" m' 70,000 120.248,00 8.417.360,00
c. Pekerjaan pipa PVC SNI Ø 6" m' 20,000 275.994,00 5.519.880,00
d. galian tanah biasa m3 12,000 119.924,00 1.439.088,00
e. Urugan tanah kembali m3 9,600 86.899,00 834.230,40
2 Pekerjaan bak kontrol precast D 40 cm bh 21,000 400.000,00 8.400.000,00
3 Pekerjaan bak penangkap lemak D 40 cm bh 20,000 400.000,00 8.000.000,00
Jumlah 35.362.398,40
III PEKERJAAN SEPTIK TANK -
1 Pek. Galian tanah biasa m3 54,000 119.924,00 6.475.896,00
2 Pek. Pembuangan tanah m3 54,000 52.558,00 2.838.132,00
3 Pek. Urugan pasir dengan pasir urug m3 1,800 268.769,00 483.784,20
4 Pekerjaan beton -
a. Pek. Lantai kerja Beton K 100 m3 1,800 1.016.351,00 1.829.431,80
b. Pek. Lantai IPAL -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 3,600 1.320.118,00 4.752.424,80
- Pek. tulangan besi Ø 10-150 kg 287,763 17.596,00 5.063.471,94
c. Pekerjaan atap IPAL -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 2,700 1.320.118,00 3.564.318,60
- Pek. tulangan besi Ø 10-150 kg 287,763 17.596,00 5.063.471,94
- Pek floordeck/bondeck m2 18,000 174.819,00 3.146.742,00
d. Pekerjaan dinding IPAL -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 6,010 1.320.118,00 7.933.579,15
- Pek. tulangan besi Ø 10-150 kg 506,023 17.596,00 8.903.986,51
- Bekisting m² 58,035 467.087,00 27.107.394,05
- acian m² 73,020 58.187,00 4.248.814,74
e. Pekerjaan dinding kompartemen -
- Pekerjaan Dinding Bata Merah Spesi 1 : 4 m² 34,715 169.068,00 5.869.195,62
- Plesteran m² 69,430 96.456,00 6.696.940,08
- acian m² 69,430 58.187,00 4.039.923,41
f. Pek. Sekat gantung -
- Pekerjaan Dinding Bata Merah Spesi 1 : 4 m² 1,350 169.068,00 228.241,80
- Plesteran m² 1,350 96.456,00 130.215,60
- acian m² 1,350 58.187,00 78.552,45
g. Pek. Balok Dududukan sekat gantung -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 0,061 1.320.118,00 80.197,17
- Pek. tulangan besi Ø 8-150 kg 10,116 17.596,00 178.001,14
- Bekisting m² 1,215 467.087,00 567.510,71
h. Pek. Sekat ruang lumpur -
- Pekerjaan Dinding Bata Merah Spesi 1 : 4 m² 8,100 169.068,00 1.369.450,80
- Plesteran m² 16,200 96.456,00 1.562.587,20
- acian m² 16,200 58.187,00 942.629,40
i. Pek.Ring Balok sekat ruang lumpur -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 0,061 1.320.118,00 80.197,17
- Pek. tulangan besi Ø 8-150 kg 10,116 17.596,00 178.001,14
- Bekisting m² 0,810 467.087,00 378.340,47
j. Pek. Gutter -
- Pekerjaan Dinding Bata Merah Spesi 1 : 4 m² 2,160 169.068,00 365.186,88
- Plesteran m² 4,320 96.456,00 416.689,92
- acian m² 4,320 58.187,00 251.367,84
k. Pek. Lantai gutter -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 0,162 1.320.118,00 213.859,12
- Pek. tulangan besi Ø 8-150 kg 8,370 17.596,00 147.278,52
- Bekisting m² 1,080 467.087,00 504.453,96
e. Pek. Tutup manhole -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 0,051 1.320.118,00 67.590,04
- Pek. tulangan besi Ø 10-150 kg 19,840 17.596,00 349.104,64
- Bekisting m² 0,128 491.697,00 62.937,22
14
f. Pek. Balok Dududukan media bakteri -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 0,527 1.320.118,00 695.042,13
- Pek. tulangan besi Ø 8-150 kg 87,672 17.596,00 1.542.676,51
- Bekisting m² 14,580 491.697,00 7.168.942,26
5 Pek. Bak inlet, grit chamber, dan equalisasi -
a. Pekerjaan Dinding Bata Merah Spesi 1 : 4 m² 2,120 169.068,00 358.424,16
b. Pekerjaan Plesteran m² 2,802 96.456,00 270.269,71
c. Pekerjaan Acian m² 2,802 58.187,00 163.039,97
d. Pek. Tutup bak inlet -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 0,222 1.320.118,00 293.066,20
- Pek. tulangan besi Ø 10-150 kg 32,447 17.596,00 570.931,61
- Bekisting m² 1,665 491.697,00 818.675,51
- Screen bh 1,000 100.000,00 100.000,00
6 Pek. Bak outlet -
a. Pekerjaan Dinding Bata Merah Spesi 1 : 4 m² 0,420 169.068,00 71.008,56
b. Pekerjaan Plesteran m² 0,420 96.456,00 40.511,52
c. Pekerjaan Acian m² 0,420 58.187,00 24.438,54
d. Pek. Tutup bak inlet -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 0,011 1.320.118,00 14.785,32
- Pek. tulangan besi Ø 10-150 kg 4,960 17.596,00 87.276,16
- Bekisting m2 0,128 491.697,00 62.937,22
7 Pekerjaan pipa kompartemen -
a. Pipa PVC AW Ø 3" m' 59,400 91.728,00 5.448.643,20
b. Pipa PVC AW Ø 4" m' 7,250 120.248,00 871.798,00
c. Tee PVC AW Ø 4" bh 40,000 93.500,00 3.740.000,00
f. Pipa GI medium Ø 2" untuk ventilasi m' 3,000 108.500,00 325.500,00
g. Tee GI Ø 2" untuk ventilasi bh 3,000 204.600,00 613.800,00
h. Media bakteri m3 5,000 1.500.000,00 7.500.000,00
8 Pek. Lantai keramik IPAL m² 14,000 185.580,00 2.598.120,00
9 Pekerjaan bak biokontrol -
- Pekerjaan Dinding Bata Merah Spesi 1 : 4 m² 4,970 169.068,00 840.267,96
- Plesteran m² 7,455 96.456,00 719.079,48
- acian m² 7,455 58.187,00 433.784,09
Jumlah 141.542.918,10
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
IPAL KOMUNAL + JARINGAN (SR) 25 SR
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 2.213.923,00
II PEKERJAAN JARINGAN PIPA AIR LIMBAH 35.362.398,40
III PEKERJAAN SEPTIK TANK 141.542.918,10
JUMLAH (Rp) 179.119.239,50
PPN 10% 17.911.923,95
JUMLAH TOTAL (Rp) 197.031.163,45
JUMLAH DIBULATKAN (Rp) 197.031.000,00
15
ANALISIS STANDAR BELANJA (ASB)
IPAL KOMUNAL + JARINGAN (SR) 10 SR
1 KELOMPOK : Kontruksi
2 SUB KELOMPOK : Membangun IPAL Komunal + Jaringan (SR) 10 SR
3 SUB- SUB KELOMPOK : Membangun IPAL Komunal + Jaringan (SR) 10 SR
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Membangun IPAL Komunal + Jaringan (SR) 10 SR
6 DESKRIPSI AKTIVITAS : Membangun IPAL Komunal + Jaringan (SR) 10 SR
7 SATUAN AKTIVITAS : Unit
8 KOMPONEN/RINCIAN KOMPONEN :
NO. URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH
I PEKERJAAN PERSIAPAN
1 Pekerjaan Pengukuran dan pemasangan bouwplank m¹ 10,000 81.786,00 817.860,00
2 Prasasti marmer grafir 25 x 30 cm ls 1,000 500.000,00 500.000,00
Jumlah 1.317.860,00
II PEKERJAAN JARINGAN PIPA AIR LIMBAH -
1 Pekerjaan pipa -
a. Pek. Pipa PVC SNI Ø 3" m' 10,000 91.728,00 917.280,00
b. Pek. Pipa PVC SNII Ø 4" m' 30,000 120.248,00 3.607.440,00
c. Pekerjaan pipa PVC SNI Ø 6" m' - 275.994,00 -
d. galian tanah biasa m3 4,000 119.924,00 479.696,00
e. Urugan tanah kembali m3 3,200 86.899,00 278.076,80
2 Pekerjaan bak kontrol precast D 40 cm bh 4,000 400.000,00 1.600.000,00
3 Pekerjaan bak penangkap lemak D 40 cm bh 3,000 400.000,00 1.200.000,00
Jumlah 8.082.492,80
III PEKERJAAN SEPTIK TANK -
1 Pek. Galian tanah biasa m3 13,800 119.924,00 1.654.951,20
2 Pek. Pembuangan tanah m3 8,280 52.558,00 435.180,24
3 Pek. Urugan pasir dengan pasir urug m3 0,300 268.769,00 80.630,70
4 Pekerjaan beton -
a. Pek. Lantai kerja Beton K 100 m3 0,600 1.016.351,00 609.810,60
b. Pek. Lantai IPAL -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 0,900 1.320.118,00 1.188.106,20
- Pek. tulangan besi Ø 10-150 kg 95,110 17.596,00 1.673.555,56
c. Pekerjaan atap IPAL -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 0,680 1.320.118,00 897.680,24
- Pek. tulangan besi Ø 10-150 kg 33,890 17.596,00 596.328,44
- Pek floordeck/bondeck m2 6,000 174.819,00 1.048.914,00
d. Pekerjaan dinding IPAL -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 2,380 1.320.118,00 3.141.880,84
- Pek. tulangan besi Ø 10-150 kg 128,390 17.596,00 2.259.150,44
- Bekisting m² 7,920 467.087,00 3.699.329,04
- acian m² 7,110 58.187,00 413.709,57
e. Pekerjaan dinding kompartemen -
- Pekerjaan Dinding Bata Merah Spesi 1 : 4 m² 9,180 169.068,00 1.552.044,24
- Plesteran m² 18,360 96.456,00 1.770.932,16
- acian m² 18,360 58.187,00 1.068.313,32
f. Pek. Tutup manhole -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 0,040 1.320.118,00 52.804,72
- Pek. tulangan besi Ø 10-150 kg 14,880 17.596,00 261.828,48
- Bekisting m² 0,130 491.697,00 63.920,61
g. Pek. Dududukan media bakteri dan penyangga -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 0,080 1.320.118,00 105.609,44
- Pek. tulangan besi Ø 8-150 kg 17,570 17.596,00 309.161,72
- Bekisting m² 0,050 491.697,00 24.584,85
- beton penyangga campuran 1 sp : 2 ps : 3 kr m3 0,100 1.320.118,00 132.011,80
5 Pek. Bak inlet -
a. Pekerjaan Dinding Bata Merah Spesi 1 : 4 m² 1,440 169.068,00 243.457,92
b. Pekerjaan Plesteran m² 1,440 96.456,00 138.896,64
c. Pekerjaan Acian m² 1,440 58.187,00 83.789,28
d. Pek. Tutup bak inlet -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 0,020 1.320.118,00 26.402,36
- Pek. tulangan besi Ø 10-150 kg 4,300 17.596,00 75.662,80
- Bekisting m² 0,080 491.697,00 39.335,76
- Screen bh 1,000 100.000,00 100.000,00
6 Pek. Bak outlet -
a. Pekerjaan Dinding Bata Merah Spesi 1 : 4 m² 0,420 169.068,00 71.008,56
b. Pekerjaan Plesteran m² 0,420 96.456,00 40.511,52
c. Pekerjaan Acian m² 0,420 58.187,00 24.438,54
d. Pek. Tutup bak inlet -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 0,010 1.320.118,00 13.201,18
- Pek. tulangan besi Ø 10-150 kg 4,300 17.596,00 75.662,80
- Bekisting m2 0,130 491.697,00 63.920,61
16
7 Pekerjaan pipa kompartemen -
a. Pipa PVC AW Ø 3" m' 1,500 91.728,00 137.592,00
b. Pipa PVC AW Ø 4" m' 0,500 120.248,00 60.124,00
c. Tee PVC AW Ø 4" bh 2,000 93.500,00 187.000,00
e. Tee PVC AW Ø 3" bh 12,000 46.500,00 558.000,00
f. Pipa GI medium Ø 2" untuk ventilasi m' 3,000 108.500,00 325.500,00
g. Tee GI Ø 2" untuk ventilasi bh 3,000 204.600,00 613.800,00
h. Media bakteri m3 1,000 1.500.000,00 1.500.000,00
i. Pengecatan IPAL 6,000 42.948,00 257.688,00
Jumlah 27.676.430,38
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
IPAL KOMUNAL + JARINGAN (SR) 10 SR
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 1.317.860,00
II PEKERJAAN JARINGAN PIPA AIR LIMBAH 8.082.492,80
III PEKERJAAN SEPTIK TANK 27.676.430,38
JUMLAH (Rp) 37.076.783,18
PPN 10% 3.707.678,32
JUMLAH TOTAL (Rp) 40.784.461,50
JUMLAH DIBULATKAN (Rp) 40.784.000,00
17
ANALISIS STANDAR BELANJA (ASB)
JAMBAN + SEPTIK TANK PABRIKASI
1 KELOMPOK : Kontruksi
2 SUB KELOMPOK : Membangun JAMBAN + SEPTIK TANK PABRIKASI
3 SUB- SUB KELOMPOK : Membangun JAMBAN + SEPTIK TANK PABRIKASI
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Membangun JAMBAN + SEPTIK TANK PABRIKASI
6 DESKRIPSI AKTIVITAS : Membangun JAMBAN + SEPTIK TANK PABRIKASI
7 SATUAN AKTIVITAS : Unit
8 KOMPONEN/RINCIAN KOMPONEN :
NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
I PEKERJAAN PERSIAPAN
1 Pekerjaan Pengukuran dan pemasangan bouwplank m¹ 5,400 81.786,00 441.644,40
Jumlah 441.644,40
II PEKERJAAN TANAH -
1 Galian tanah biasa sedalam 1 meter / m³ m³ 1,850 119.924,00 221.859,40
2 Urugan Kembali Tanah Bekas Galian m³ 0,570 86.899,00 49.532,43
Jumlah 271.391,83
III PEKERJAAN PONDASI -
1 Pasangan Batu belah kosong ( Aanstamping) m³ 0,430 650.982,00 279.922,26
2 Pasangan Batu belah 15/20 ( 1 PC: 5 PP) m³ 1,070 1.144.638,00 1.224.762,66
Jumlah 1.504.684,92
IV PEKERJAAN STRUKTUR -
1 Pek kolom 15x15 -
a. Pek. Beton campuran 1 sp : 2 ps : 3 kr m³ 0,230 1.320.118,00 303.627,14
b. Pek. tulangan besi Ø 10, sk Ø 8-150 kg 27,770 17.596,00 488.640,92
c. pek Bekisting m2 1,400 428.677,00 600.147,80
2 Pek sloof 15x15 -
a. Pek. Beton campuran 1 sp : 2 ps : 3 kr m³ 0,130 1.320.118,00 171.615,34
b. Pek. tulangan besi Ø 10, sk Ø 8-150 kg 7,870 17.596,00 138.480,52
c. pek Bekisting m2 0,770 238.798,00 183.874,46
3 Pek ring balok 15x15 -
a. Pek. Beton campuran 1 sp : 2 ps : 3 kr m³ 0,130 1.320.118,00 171.615,34
b. Pek. tulangan besi Ø 10, sk Ø 8-150 kg 18,470 17.596,00 324.998,12
c. pek Bekisting m2 0,770 439.027,00 338.050,79
Jumlah 2.721.050,43
V PEKERJAAN DINDING DAN LANTAI -
1 Pekerjaan Dinding Bata Merah Spesi 1 : 5 m² 13,710 166.609,00 2.284.209,39
2 Pekerjaan Plesteran m² 14,740 95.270,00 1.404.279,80
3 Pekerjaan Acian m² 14,740 58.187,00 857.676,38
Pekerjaan Dinding Keramik Toilet/WC, 20x25 cm, tinggi 1,20
4 m² 5,640 277.283,00 1.563.876,12
m
Pekerjaan Lantai Keramik Toilet/WC, Uk. 20 x 20 cm, Anti
5 m² 2,700 185.580,00 501.066,00
Slip
6 Pekerjaan batu tempel m2 0,700 340.842,00 238.589,40
7 Pek. Pas Glass Block m² 0,160 815.110,00 130.417,60
8 Pek. Pas. Roster lubang angin m² 0,080 398.005,00 31.840,40
9 Pek. Pas. Roster beton m² - 402.490,00 -
10 Pekerjaan spesi m² 3,780 95.270,00 360.120,60
Jumlah 7.372.075,69
VI PEKERJAAN ATAP -
Pek. Rangka Kuda - Kuda + Gording 8/12 Kayu Kelas II ( 50
1 m³ 0,160 7.212.340,00 1.153.974,40
%)
2 Pas. Penutup Atap Palentong m² 7,380 241.029,00 1.778.794,02
3 Pas. Genteng bubung m' 2,500 157.741,00 394.352,50
4 Pas. Lisplank GRC 8 mm / 20 cm m' 11,000 96.428,00 1.060.708,00
Jumlah 4.387.828,92
VII PEKERJAAN PLAFON -
1 Pekerjaan Rangka Plafond m² 5,400 155.898,00 841.849,20
2 Penutup Plafond gipsum board m² 5,400 59.164,00 319.485,60
Jumlah 1.161.334,80
VII PEKERJAAN KUSEN DAN PINTU -
1 Kusen Dan Pintu Pvc Toilet (Royal), bh 1,000 717.117,00 717.117,00
Jumlah 717.117,00
VIII PEKERJAAN PENGECATAN -
1 Pekerjaan Pengecatan Dinding full m2 14,740 33.978,00 500.835,72
Jumlah 500.835,72
IX PEKERJAAN SANITAIR -
1 Pas. Closet Jongkok Sekelas Toto bh 1,000 730.581,00 730.581,00
2 Pekerjaan Kran 1/2" bh 1,000 135.986,00 135.986,00
3 Pas. Floor Drain Sekelas Onda bh 1,000 126.164,00 126.164,00
4 Pek Bak fiber 60 x 60 bh 1,000 1.221.816,00 1.221.816,00
Jumlah 2.214.547,00
18
X PEKERJAAN AIR BERSIH DAN AIR KOTOR -
a Pekerjaan Air bersih -
a. Pek. Pipa PVC AW Ø 3/4" m' 4,000 26.802,00 107.208,00
b. Pek Pipa PVC AW Ø 1/2" m' 4,000 24.351,00 97.404,00
c. Pek. Knee PVC Ø 1/2" bh 1,000 3.500,00 3.500,00
d. Pek. Tee PVC Ø 1/2" bh - 3.500,00 -
e. Pek. SDD PVC Ø 1/2" bh 1,000 3.500,00 3.500,00
-
2 Pekerjaan air kotor -
a. Pek. Pipa PVC AW Ø 3" m' 3,000 91.728,00 275.184,00
b. Pek. Pipa PVC AW Ø 4" bh 3,000 120.248,00 360.744,00
c. Knee PVC AW Ø 3" bh 2,000 23.000,00 46.000,00
Jumlah 893.540,00
XI PEKERJAAN ELEKTRIKAL -
1 Instalasi titik penerangan NYM 3x2,5 mm2+Conduit dia.20mm m' 1,000 449.606,00 449.606,00
2 Pas. Lampu xl ESS Philips 14 watt + Armateur bh 1,000 62.000,00 62.000,00
4 pas. Saklar tunggal bh 1,000 104.678,00 104.678,00
Jumlah 616.284,00
XII PEKERJAAN SEPTIK TANK -
1 Pek. Galian tanah biasa 2 m m3 3,380 147.037,00 496.985,06
2 Pek. Pembuangan tanah m3 1,690 52.558,00 88.823,02
3 Pek. Pas bata merah 1:5 m2 1,620 166.609,00 269.906,58
4 Pek. Urugan pasir dengan pasir urug m3 0,140 268.769,00 37.627,66
5 Pekerjaan beton -
a. Pek. Lantai septik tank 1:2:3 m3 0,140 1.320.118,00 184.816,52
b. Pekerjaan atap septik tank -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 0,270 1.320.118,00 356.431,86
- Pek. tulangan besi Ø 10-150 kg 17,380 17.596,00 305.818,48
- Pek bekisting m2 1,440 491.697,00 708.043,68
6 Pek kolom 15x15 -
a. Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 0,120 1.320.118,00 158.414,16
b. Pek. tulangan besi Ø 10, sk Ø 8-150 kg 9,230 17.596,00 162.411,08
7 Pek. Septik tank kap 0,8 m3 bh 1,000 3.600.000,00 3.600.000,00
8 Pek. Tutup manhole septik tank + frame set 1,000 350.000,00 350.000,00
9 Pek. Bak inlet -
a. Pekerjaan Dinding Bata Merah Spesi 1 : 4 m² 0,420 169.068,00 71.008,56
b. Pekerjaan Plesteran m² 0,420 96.456,00 40.511,52
c. Pekerjaan Acian m² 0,420 58.187,00 24.438,54
d. Pek. Tutup bak inlet -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 0,010 1.320.118,00 13.201,18
- Pek. tulangan besi Ø 10-150 kg 4,960 17.596,00 87.276,16
- Bekisting m2 0,080 491.697,00 39.335,76
- Screen bh 1,000 100.000,00 100.000,00
10 Pek. Bak outlet -
a. Pekerjaan Dinding Bata Merah Spesi 1 : 4 m² 0,560 169.068,00 94.678,08
b. Pekerjaan Plesteran m² 0,560 96.456,00 54.015,36
c. Pekerjaan Acian m² 0,560 58.187,00 32.584,72
d. Pek. Tutup bak inlet -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 0,010 1.320.118,00 13.201,18
- Pek. tulangan besi Ø 10-150 kg 4,960 17.596,00 87.276,16
- Bekisting m2 0,080 491.697,00 39.335,76
11 Pekerjaan pipa ventilasi -
a. Pipa GI medium Ø 1" untuk ventilasi m' 2,000 55.000,00 110.000,00
b. Tee GI Ø 1" untuk ventilasi bh 2,000 72.000,00 144.000,00
c. Pengecatan septik tank m2 2,250 42.948,00 96.633,00
Jumlah 7.766.774,08
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
JAMBAN + SEPTIK TANK PABRIKASI
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 441.644,40
II PEKERJAAN TANAH 271.391,83
III PEKERJAAN PONDASI 1.504.684,92
IV PEKERJAAN STRUKTUR 2.721.050,43
V PEKERJAAN DINDING DAN LANTAI 7.372.075,69
VI PEKERJAAN ATAP 4.387.828,92
VII PEKERJAAN PLAFON 1.161.334,80
VIII PEKERJAAN KUSEN DAN PINTU 717.117,00
IX PEKERJAAN PENGECATAN 500.835,72
X PEKERJAAN SANITAIR 2.214.547,00
XI PEKERJAAN AIR BERSIH DAN AIR KOTOR 893.540,00
XII PEKERJAAN ELEKTRIKAL 616.284,00
XIII PEKERJAAN SEPTIK TANK 7.766.774,08
JUMLAH (Rp) 30.569.108,79
PPN 10% 3.056.910,88
JUMLAH TOTAL (Rp) 33.626.019,67
JUMLAH DIBULATKAN (Rp) 33.626.000,00
19
ANALISIS STANDAR BELANJA (ASB)
IPAL 50 KK + JARINGAN
1 KELOMPOK : Kontruksi
2 SUB KELOMPOK : Membangun IPAL 50 KK + JARINGAN
3 SUB- SUB KELOMPOK : Membangun IPAL 50 KK + JARINGAN
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Membangun IPAL 50 KK + JARINGAN
6 DESKRIPSI AKTIVITAS : Membangun IPAL 50 KK + JARINGAN
7 SATUAN AKTIVITAS : Unit
8 KOMPONEN/RINCIAN KOMPONEN :
NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
I PEKERJAAN PERSIAPAN
1 Pekerjaan Pengukuran dan pemasangan bouwplank m¹ 48,000 81.786,00 3.925.728,00
2 Pembuatan nama pekerjaan ls 1,000 251.059,00 251.059,00
3 Mobilisasi dan demobilisasi alat dan bahan ls 1,000 3.316.376,00 3.316.376,00
4 Prasasti marmer grafir 25 x 30 cm bh 1,000 500.000,00 500.000,00
5 Dokumentasi dan pelaporan ls 1,000 3.500.000,00 3.500.000,00
Jumlah 11.493.163,00
II PEKERJAAN JARINGAN PIPA AIR LIMBAH -
1 Pekerjaan pipa -
a. Pek. Pipa PVC SNI Ø 3" m' 40,000 91.728,00 3.669.120,00
b. Pek. Pipa PVC SNII Ø 4" m' 420,000 120.248,00 50.504.160,00
c. Pekerjaan pipa PVC SNI Ø 6" m' 150,000 275.994,00 41.399.100,00
d. galian tanah biasa m3 61,000 119.924,00 7.315.364,00
e. Urugan tanah kembali m3 48,800 86.899,00 4.240.671,20
2 Pekerjaan bak kontrol precast D 40 cm bh 50,000 400.000,00 20.000.000,00
3 Pekerjaan bak penangkap lemak D 40 cm bh 30,000 400.000,00 12.000.000,00
Jumlah 139.128.415,20
III PEKERJAAN SEPTIK TANK -
1 Pek. Galian tanah biasa m3 126,600 119.924,00 15.182.378,40
2 Pek. Pembuangan tanah m3 126,600 52.558,00 6.653.842,80
3 Pek. Urugan pasir dengan pasir urug m3 4,000 268.769,00 1.075.076,00
4 Pekerjaan beton -
a. Pek. Lantai kerja Beton K 100 m3 4,000 1.016.351,00 4.065.404,00
b. Pek. Lantai IPAL -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 8,000 1.320.118,00 10.560.944,00
- Pek. tulangan besi Ø 10-150 kg 646,536 17.596,00 11.376.447,46
c. Pekerjaan atap IPAL -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 6,000 1.320.118,00 7.920.708,00
- Pek. tulangan besi Ø 10-150 kg 646,536 17.596,00 11.376.447,46
- Pek floordeck/bondeck m2 40,000 174.819,00 6.992.760,00
d. Pekerjaan dinding IPAL -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 10,096 1.320.118,00 13.327.647,30
- Pek. tulangan besi Ø 10-150 kg 833,797 17.596,00 14.671.486,73
- Bekisting m² 96,535 467.087,00 45.090.243,55
- acian m² 131,870 58.187,00 7.673.119,69
e. Pekerjaan dinding kompartemen -
- Pekerjaan Dinding Bata Merah Spesi 1 : 4 m² 54,325 169.068,00 9.184.619,10
- Plesteran m² 108,650 96.456,00 10.479.944,40
- acian m² 108,650 58.187,00 6.322.017,55
f. Pek. Sekat gantung -
- Pekerjaan Dinding Bata Merah Spesi 1 : 4 m² 1,850 169.068,00 312.775,80
- Plesteran m² 1,850 96.456,00 178.443,60
- acian m² 1,850 58.187,00 107.645,95
g. Pek. Balok Dududukan sekat gantung -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 0,083 1.320.118,00 109.965,83
- Pek. tulangan besi Ø 8-150 kg 13,863 17.596,00 243.928,07
- Bekisting m² 1,665 467.087,00 777.699,86
h. Pek. Sekat ruang lumpur -
- Pekerjaan Dinding Bata Merah Spesi 1 : 4 m² 11,100 169.068,00 1.876.654,80
- Plesteran m² 22,200 96.456,00 2.141.323,20
- acian m² 22,200 58.187,00 1.291.751,40
i. Pek.Ring Balok sekat ruang lumpur -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 0,083 1.320.118,00 109.965,83
- Pek. tulangan besi Ø 8-150 kg 13,863 17.596,00 243.928,07
- Bekisting m² 1,110 467.087,00 518.466,57
j. Pek. Gutter -
- Pekerjaan Dinding Bata Merah Spesi 1 : 4 m² 2,960 169.068,00 500.441,28
- Plesteran m² 5,920 96.456,00 571.019,52
- acian m² 5,920 58.187,00 344.467,04
k. Pek. Lantai gutter -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 0,222 1.320.118,00 293.066,20
- Pek. tulangan besi Ø 8-150 kg 11,470 17.596,00 201.826,12
- Bekisting m² 1,480 467.087,00 691.288,76
e. Pek. Tutup manhole -
- tutup manhole besi bh 11,000 1.100.000,00 12.100.000,00
20
f. Pek. Balok Dududukan media bakteri -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 0,878 1.320.118,00 1.158.403,55
- Pek. tulangan besi Ø 8-150 kg 146,120 17.596,00 2.571.127,52
- Bekisting m² 19,980 491.697,00 9.824.106,06
5 Pek. Bak inlet, grit chamber, dan equalisasi -
a. Pekerjaan Dinding Bata Merah Spesi 1 : 4 m² 2,120 169.068,00 358.424,16
b. Pekerjaan Plesteran m² 2,802 96.456,00 270.269,71
c. Pekerjaan Acian m² 2,802 58.187,00 163.039,97
d. Pek. Tutup bak inlet -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 0,222 1.320.118,00 293.066,20
- Pek. tulangan besi Ø 10-150 kg 32,447 17.596,00 570.932,13
- Bekisting m² 1,665 491.697,00 818.675,51
- Screen bh 1,000 100.000,00 100.000,00
6 Pek. Bak outlet -
a. Pekerjaan Dinding Bata Merah Spesi 1 : 4 m² 0,420 169.068,00 71.008,56
b. Pekerjaan Plesteran m² 0,420 96.456,00 40.511,52
c. Pekerjaan Acian m² 0,420 58.187,00 24.438,54
d. Pek. Tutup bak inlet -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 0,011 1.320.118,00 14.785,32
- Pek. tulangan besi Ø 10-150 kg 4,960 17.596,00 87.276,16
- Bekisting m2 0,128 491.697,00 62.937,22
7 Pekerjaan pipa kompartemen -
a. Pipa PVC AW Ø 3" m' 59,400 91.728,00 5.448.643,20
b. Pipa PVC AW Ø 4" m' 8,000 120.248,00 961.984,00
c. Knee PVC AW Ø 3" bh 3,000 23.000,00 69.000,00
e. Tee PVC AW Ø 3" bh 69,000 46.500,00 3.208.500,00
f. Pipa GI medium Ø 2" untuk ventilasi m' 3,000 108.500,00 325.500,00
g. Tee GI Ø 2" untuk ventilasi bh 3,000 204.600,00 613.800,00
h. Media bakteri m3 15,000 1.500.000,00 22.500.000,00
8 Pek. Lantai keramik IPAL m2 40,000 185.580,00 7.423.200,00
9 Pekerjaan bak biokontrol -
- Pekerjaan Dinding Bata Merah Spesi 1 : 4 m² 4,970 169.068,00 840.267,96
- Plesteran m² 7,455 96.456,00 719.079,48
- acian m² 7,455 58.187,00 433.784,09
Jumlah 263.540.505,17
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
IPAL 50 KK + JARINGAN
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 11.493.163,00
II PEKERJAAN JARINGAN PIPA AIR LIMBAH 139.128.415,20
III PEKERJAAN SEPTIK TANK 263.540.505,17
JUMLAH (Rp) 414.162.083,37
PPN 10% 41.416.208,34
JUMLAH TOTAL (Rp) 455.578.291,71
JUMLAH DIBULATKAN (Rp) 455.578.000,00
21
ANALISIS STANDAR BELANJA (ASB)
IPAL 50 KK + MCK
1 KELOMPOK : Kontruksi
2 SUB KELOMPOK : Membangun IPAL 50 KK + MCK
3 SUB- SUB KELOMPOK : Membangun IPAL 50 KK + MCK
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Membangun IPAL 50 KK + MCK
6 DESKRIPSI AKTIVITAS : Membangun IPAL 50 KK + MCK
7 SATUAN AKTIVITAS : Unit
8 KOMPONEN/RINCIAN KOMPONEN :
NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
I PEKERJAAN PERSIAPAN
1 Pekerjaan Pengukuran dan pemasangan bouwplank m¹ 70,000 81.786,00 5.725.020,00
2 Prasasti marmer grafir 25 x 30 cm bh 1,000 500.000,00 500.000,00
Jumlah 6.225.020,00
II PEKERJAAN TANAH -
1 Galian tanah biasa sedalam 1 meter / m³ m³ 8,990 119.924,00 1.078.116,76
2 Urugan Kembali Tanah Bekas Galian m³ 2,770 86.899,00 240.710,23
Jumlah 1.318.826,99
III PEKERJAAN PONDASI -
1 Pasangan Batu belah kosong ( Aanstamping) m³ 2,070 650.982,00 1.347.532,74
2 Pasangan Batu belah 15/20 ( 1 PC: 5 PP) m³ 5,180 1.144.638,00 5.929.224,84
Jumlah 7.276.757,58
IV PEKERJAAN STRUKTUR -
1 Pek kolom 15x15 -
a. Pekerjaan beton mutu f'c = 19.3 MPa (K 225) m³ 0,950 1.320.118,00 1.254.112,10
b. Pek. tulangan besi Ø 10, sk Ø 8-150 kg 67,060 17.596,00 1.179.987,76
c. pek Bekisting m2 8,200 428.677,00 3.515.151,40
2 Pek kolom 15x20 -
a. Pekerjaan beton mutu f'c = 19.3 MPa (K 225) m³ 0,810 1.320.118,00 1.069.295,58
b. Pek. tulangan besi Ø 10, sk Ø 8-150 kg 32,720 17.596,00 575.741,12
c. pek Bekisting m2 4,480 428.677,00 1.920.472,96
3 Pek sloof 15x15 -
a. Pekerjaan beton mutu f'c = 19.3 MPa (K 225) m³ 1,320 1.320.118,00 1.742.555,76
b. Pek. tulangan besi Ø 10, sk Ø 8-150 kg 125,400 17.596,00 2.206.538,40
c. pek Bekisting m2 17,580 238.798,00 4.198.068,84
4 Pek ring balok 15x20 -
a. Pekerjaan beton mutu f'c = 19.3 MPa (K 225) m³ 1,210 1.320.118,00 1.597.342,78
b. Pek. tulangan besi Ø 10, sk Ø 8-150 kg 91,120 17.596,00 1.603.347,52
c. pek Bekisting m2 16,100 238.798,00 3.844.647,80
5 Pek balok 15x20 -
a. Pekerjaan beton mutu f'c = 19.3 MPa (K 225) m³ 1,040 1.320.118,00 1.372.922,72
b. Pek. tulangan besi Ø 10, sk Ø 8-150 kg 78,430 17.596,00 1.380.054,28
c. pek Bekisting m2 17,300 439.027,00 7.595.167,10
Jumlah 35.055.406,12
V PEKERJAAN DINDING DAN LANTAI -
1 Pekerjaan Dinding Bata Merah Spesi 1 : 5 m² 75,720 166.609,00 12.615.633,48
2 Pekerjaan Plesteran m² 45,190 95.270,00 4.305.251,30
3 Pekerjaan Acian m² 45,190 58.187,00 2.629.470,53
Pekerjaan Dinding Keramik Toilet/WC, 20x25 cm, tinggi 1,20
4 m² 42,620 277.283,00 11.817.801,46
m
Pekerjaan Lantai Keramik Toilet/WC, Uk. 20 x 20 cm, Anti
5 m² 23,970 185.580,00 4.448.352,60
Slip
6 Pekerjaan batu tempel m2 10,500 340.842,00 3.578.841,00
7 Pek. Pas Glass Block m² 0,960 815.110,00 782.505,60
8 Pek. Pas. Roster lubang angin m² 0,240 398.005,00 95.521,20
9 Pek. Pas. Roster beton m² 3,680 402.490,00 1.481.163,20
10 Pekerjaan spesi m² 32,640 95.270,00 3.109.612,80
11 Pekerjaan paving block natural 6 cm m2 15,900 235.045,00 3.737.215,50
Jumlah 48.601.368,67
VI PEKERJAAN ATAP -
a. Pekerjaan beton mutu f'c = 19.3 MPa (K 225) m3 5,930 1.320.118,00 7.828.299,74
b. Pek. tulangan besi Ø 10-150 kg 126,070 17.596,00 2.218.327,72
c. pek floordeck/bondeck m2 57,750 174.819,00 10.095.797,25
2 Pekerjaan Dinding Bata Merah Spesi 1 : 5 m² 6,400 166.609,00 1.066.297,60
3 Pekerjaan Plesteran m² 2,800 95.270,00 266.756,00
4 Pekerjaan Acian m² 2,800 58.187,00 162.923,60
Jumlah 21.638.401,91
VII PEKERJAAN PLAFON -
1 Pekerjaan Rangka Plafond m² 57,750 155.898,00 9.003.109,50
2 Penutup Plafond m² 57,750 59.164,00 3.416.721,00
Jumlah 12.419.830,50
VIII PEKERJAAN KUSEN DAN PINTU -
1 Kusen Dan Pintu Pvc Toilet (Royal), bh 6,000 717.117,00 4.302.702,00
Jumlah 4.302.702,00
22
IX PEKERJAAN PENGECATAN -
1 Pekerjaan Pengecatan Dinding full m2 90,380 33.978,00 3.070.931,64
Jumlah 3.070.931,64
X PEKERJAAN SANITAIR -
1 Pekerjaan Kloset jongkok bh 6,000 730.581,00 4.383.486,00
2 Pekerjaan Kran 1/2" bh 13,000 135.986,00 1.767.818,00
3 Floor Drain bh 8,000 126.164,00 1.009.312,00
4 Pek Bak fiber 60 x 60 bh 6,000 1.221.816,00 7.330.896,00
5 Pekerjaan wastafel set 1,000 1.452.432,00 1.452.432,00
Jumlah 15.943.944,00
XI PEKERJAAN AIR BERSIH DAN AIR KOTOR -
1 Pekerjaan Air bersih -
a. Pek. Pipa PVC AW Ø 3/4" m' 8,000 26.802,00 214.416,00
b. Pek Pipa PVC AW Ø 1/2" m' 24,000 24.351,00 584.424,00
c. Pek. Knee PVC Ø 1/2" bh 11,000 7.000,00 77.000,00
d. Pek. Tee PVC Ø 1/2" bh 6,000 3.500,00 21.000,00
e. Pek. Fitting 4 way PVC Ø 1/2" bh 2,000 3.500,00 7.000,00
f. Pek. SDD PVC Ø 1/2" bh 8,000 3.500,00 28.000,00
g. Pek. Torn 1000 lt bh 1,000 1.595.500,00 1.595.500,00
2 Pekerjaan air kotor -
a. Pek. Pipa PVC AW Ø 3" m' 18,000 28.825,00 518.850,00
b. Pek. Pipa PVC AW Ø 4" bh 18,000 44.825,00 806.850,00
c. Knee PVC AW Ø 3" bh 8,000 23.000,00 184.000,00
d. Knee dan tee PVC AW Ø 4" bh 6,000 46.500,00 279.000,00
Jumlah 4.316.040,00
XII PEKERJAAN ELEKTRIKAL -
1 Instalasi titik penerangan NYM 3x2,5 mm2+Conduit dia.20mm m' 11,000 449.606,00 4.945.666,00
2 Pas. Lampu xl ESS Philips 14 watt + Armateur bh 11,000 62.000,00 682.000,00
4 Saklar tunggal bh 6,000 104.678,00 628.068,00
5 saklar ganda bh 2,000 110.486,00 220.972,00
6 Stop kontak bh 1,000 113.390,00 113.390,00
7 Pemasangan PLN 1300 watt bh 1,000 2.297.449,00 2.297.449,00
Jumlah 8.887.545,00
XIII PEKERJAAN SEPTIK TANK -
1 Pek. Galian tanah biasa 3 m m3 133,000 119.924,00 15.949.892,00
2 Pek. Pembuangan tanah m3 133,000 52.558,00 6.990.214,00
3 Pek. Urugan pasir dengan pasir urug m3 4,200 268.769,00 1.128.829,80
4 Pekerjaan beton dan pasangan -
a. Pek. Lantai kerja Beton f'c 14,5 Mpa (K 175) m3 4,200 1.269.586,00 5.332.261,20
b. Pek. Lantai IPAL -
- Pek. Beton f'c 19,3 MPa (K 225) m3 8,400 1.320.118,00 11.088.991,20
- Pek. tulangan besi Ø 10-150 mm kg 566,540 17.596,00 9.968.837,84
c. Pekerjaan atap IPAL -
- Pek. Beton f'c 19,3 MPa (K 225) m3 6,300 1.320.118,00 8.316.743,40
- Pek. tulangan besi Ø 10-150 mm kg 679,190 17.596,00 11.951.027,24
- Pek floordeck/bondeck m2 42,000 174.819,00 7.342.398,00
d. Pekerjaan dinding IPAL -
- Pek. Beton f'c 19,3 MPa (K 225) m3 14,000 1.320.118,00 18.481.652,00
- Pek. tulangan besi Ø 10-150 mm kg 860,000 17.596,00 15.132.560,00
- Bekisting m² 47,000 467.087,00 21.953.089,00
- acian m² 84,000 58.187,00 4.887.708,00
e. Pekerjaan dinding kompartemen -
- Pekerjaan Dinding Bata Merah Spesi 1 : 5 m² 55,920 166.609,00 9.316.775,28
- Plesteran m² 111,830 95.270,00 10.654.044,10
- acian m² 111,830 58.187,00 6.507.052,21
f. Pek. Sekat gantung -
- Pekerjaan sekat gantung Dinding Bata Merah Spesi 1 : 5 m² 1,850 166.609,00 308.226,65
- Plesteran m² 1,850 95.270,00 176.249,50
- acian m² 1,850 58.187,00 107.645,95
g. Pek. Balok Dududukan sekat gantung -
- Pek. Beton f'c 19,3 MPa (K 225) m3 0,080 1.320.118,00 105.609,44
- Pek. tulangan besi Ø 10-150 mm kg 13,860 17.596,00 243.880,56
- Bekisting m² 1,670 467.087,00 780.035,29
h. Pek. Sekat ruang lumpur -
- Pekerjaan sekat gantung Dinding Bata Merah Spesi 1 : 5 m² 11,100 166.609,00 1.849.359,90
- Plesteran m² 22,200 95.270,00 2.114.994,00
- acian m² 22,200 58.187,00 1.291.751,40
i. Pek.Ring Balok sekat ruang lumpur -
- Pek. Beton f'c 19,3 MPa (K 225) m3 0,080 1.320.118,00 105.609,44
- Pek. tulangan besi Ø 10-150 mm kg 13,860 17.596,00 243.880,56
- Bekisting m² 1,110 467.087,00 518.466,57
j. Pek. Gutter -
- Pekerjaan pasangan Bata Merah Spesi 1 : 5 m² 2,960 166.609,00 493.162,64
- Plesteran m² 5,920 129.026,00 763.833,92
- acian m² 5,920 58.187,00 344.467,04
23
k. Pek. Lantai gutter -
- Pek. Beton f'c 19,3 MPa (K 225) m3 0,220 1.320.118,00 290.425,96
- Pek. tulangan besi Ø 10-150 mm kg 11,470 17.596,00 201.826,12
- Bekisting m² 1,480 467.087,00 691.288,76
e. Pek. Tutup manhole -
- tutup manhole besi bh 11,000 1.100.000,00 12.100.000,00
f. Pek. Balok Dududukan media bakteri -
- Pek. Beton f'c 19,3 MPa (K 225) m3 0,880 1.320.118,00 1.161.703,84
- Pek. tulangan besi Ø 10-150 mm kg 146,120 17.596,00 2.571.127,52
- Bekisting m² 19,980 491.697,00 9.824.106,06
5 Pek. Bak inlet, grit chamber, dan equalisasi -
a. Pekerjaan Dinding Bata Merah Spesi 1 : 5 m² 2,120 166.609,00 353.211,08
b. Pekerjaan Plesteran m² 2,800 95.270,00 266.756,00
c. Pekerjaan Acian m² 2,800 58.187,00 162.923,60
d. Pek. Tutup bak inlet -
- Pek. Beton f'c 19,3 MPa (K 225) m3 0,220 1.320.118,00 290.425,96
- Pek. tulangan besi Ø 10-150 mm kg 32,450 17.596,00 570.990,20
- Bekisting m² 1,670 491.697,00 821.133,99
- Screen bh 1,000 100.000,00 100.000,00
6 Pek. Bak outlet/sumur pantau -
a. Pekerjaan Dinding Bata Merah Spesi 1 : 5 m² 0,420 166.609,00 69.975,78
b. Pekerjaan Plesteran m² 0,420 95.270,00 40.013,40
c. Pekerjaan Acian m² 0,420 58.187,00 24.438,54
d. Pek. Tutup bak inlet -
- Pek. Beton f'c 19,3 MPa (K 225) m3 0,010 1.320.118,00 13.201,18
- Pek. tulangan besi Ø 10-150 mm kg 4,960 17.596,00 87.276,16
- Bekisting m2 0,130 491.697,00 63.920,61
7 Pekerjaan pipa kompartemen -
a. Pipa PVC AW Ø 3" m' 58,500 91.728,00 5.366.088,00
b. Pipa PVC AW Ø 4" m' 8,000 120.248,00 961.984,00
c. Knee PVC AW Ø 3" bh 3,000 23.000,00 69.000,00
e. Tee PVC AW Ø 3" bh 69,000 46.500,00 3.208.500,00
f. Pipa GI medium Ø 2" untuk ventilasi m' 2,000 108.500,00 217.000,00
g. Tee GI Ø 3" untuk ventilasi bh 3,000 204.600,00 613.800,00
h. Media bakteri m3 9,000 1.500.000,00 13.500.000,00
8 Pek. Lantai keramik IPAL m2 37,300 185.580,00 6.922.134,00
9 Pekerjaan bak biokontrol -
- Pekerjaan Dinding Bata Merah Spesi 1 : 5 m² 4,970 166.609,00 828.046,73
- Plesteran m² 7,460 95.270,00 710.714,20
- acian m² 7,455 58.187,00 433.784,09
Jumlah 236.985.043,91
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
IPAL 50 KK + MCK
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 6.225.020,00
II PEKERJAAN TANAH 1.318.826,99
III PEKERJAAN PONDASI 7.276.757,58
IV PEKERJAAN STRUKTUR 35.055.406,12
V PEKERJAAN DINDING DAN LANTAI 48.601.368,67
VI PEKERJAAN ATAP 21.638.401,91
VII PEKERJAAN PLAFON 12.419.830,50
VIII PEKERJAAN KUSEN DAN PINTU 4.302.702,00
IX PEKERJAAN PENGECATAN 3.070.931,64
X PEKERJAAN SANITAIR 15.943.944,00
XI PEKERJAAN AIR BERSIH DAN AIR KOTOR 4.316.040,00
XII PEKERJAAN ELEKTRIKAL 8.887.545,00
XIII PEKERJAAN SEPTIK TANK 236.985.043,91
JUMLAH (Rp) 406.041.818,32
PPN 10% 40.604.181,83
JUMLAH TOTAL (Rp) 446.646.000,15
JUMLAH DIBULATKAN (Rp) 446.646.000,00
24
ANALISIS STANDAR BELANJA (ASB)
SEPTICTANK KOMUNAL 5-10 KK
1 KELOMPOK : Kontruksi
2 SUB KELOMPOK : Membangun SEPTICTANK KOMUNAL 5-10 KK
3 SUB- SUB KELOMPOK : Membangun SEPTICTANK KOMUNAL 5-10 KK
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Membangun SEPTICTANK KOMUNAL 5-10 KK
6 DESKRIPSI AKTIVITAS : Membangun SEPTICTANK KOMUNAL 5-10 KK
7 SATUAN AKTIVITAS : Unit
8 KOMPONEN/RINCIAN KOMPONEN :
NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
I PEKERJAAN PERSIAPAN
1 Pekerjaan Pengukuran dan pemasangan bouwplank m¹ 6,000 81.786,00 490.716,00
2 Pembuatan nama pekerjaan ls 1,000 251.059,00 251.059,00
Jumlah 741.775,00
II PEKERJAAN JARINGAN PIPA AIR LIMBAH -
1 Pekerjaan pipa -
a. Pek. Pipa PVC SNI Ø 3" m' 10,000 91.728,00 917.280,00
b. Pek. Pipa PVC SNII Ø 4" m' 20,000 120.248,00 2.404.960,00
c. Pekerjaan pipa PVC SNI Ø 6" m' 20,000 275.994,00 5.519.880,00
d. galian tanah biasa m3 4,000 119.924,00 479.696,00
e. Urugan tanah kembali m3 3,200 86.899,00 278.076,80
2 Pekerjaan bak kontrol precast D 40 cm bh 5,000 400.000,00 2.000.000,00
3 Pekerjaan bak penangkap lemak D 40 cm bh 5,000 400.000,00 2.000.000,00
Jumlah 13.599.892,80
III PEKERJAAN SEPTIK TANK -
1 Pek. Galian tanah biasa m3 18,000 119.924,00 2.158.632,00
2 Pek. Pembuangan tanah m3 10,800 52.558,00 567.626,40
4 Pek. Urugan pasir dengan pasir urug m3 0,600 268.769,00 161.261,40
5 Pekerjaan beton -
a. Pek. Lantai kerja Beton K 100 m3 0,600 1.016.351,00 609.810,60
b. Pek. Lantai IPAL -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 1,200 1.320.118,00 1.584.141,60
- Pek. tulangan besi Ø 10-150 kg 95,110 17.596,00 1.673.555,56
c. Pekerjaan atap IPAL -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 0,660 1.320.118,00 871.277,88
- Pek. tulangan besi Ø 10-150 kg 70,310 17.596,00 1.237.174,76
- Pek floordeck/bondeck m2 6,000 174.819,00 1.048.914,00
d. Pekerjaan dinding IPAL -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 3,640 1.320.118,00 4.805.229,52
- Pek. tulangan besi Ø 10-150 kg 196,080 17.596,00 3.450.223,68
- Bekisting m2 9,800 467.087,00 4.577.452,60
- acian m2 27,290 58.187,00 1.587.923,23
e. Pekerjaan dinding kompartemen -
- Pekerjaan Dinding Bata Merah Spesi 1 : 4 m2 13,010 169.068,00 2.199.574,68
- Plesteran m2 26,010 96.456,00 2.508.820,56
- acian m2 26,010 58.187,00 1.513.443,87
e. Pek. Tutup manhole -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 0,060 1.320.118,00 79.207,08
- Pek. tulangan besi Ø 10-150 kg 24,800 17.596,00 436.380,80
- Bekisting m2 0,130 491.697,00 63.920,61
f. Pek. Dududukan media bakteri dan penyangga -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 0,740 1.320.118,00 976.887,32
- Pek. tulangan besi Ø 8-150 kg 26,220 17.596,00 461.367,12
- Bekisting m2 0,310 491.697,00 152.426,07
- beton penyangga campuran 1 sp : 2 ps : 3 kr kg 0,100 1.320.118,00 132.011,80
6 Pek. Bak inlet -
a. Pekerjaan Dinding Bata Merah Spesi 1 : 4 m² 0,360 169.068,00 60.864,48
b. Pekerjaan Plesteran m² 0,360 96.456,00 34.724,16
c. Pekerjaan Acian m² 0,360 58.187,00 20.947,32
d. Pek. Tutup bak inlet -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 0,010 1.320.118,00 13.201,18
- Pek. tulangan besi Ø 10-150 kg 4,960 17.596,00 87.276,16
- Bekisting m2 0,080 491.697,00 39.335,76
- Screen bh 1,000 100.000,00 100.000,00
7 Pek. Bak outlet -
a. Pekerjaan Dinding Bata Merah Spesi 1 : 4 m² 0,420 169.068,00 71.008,56
b. Pekerjaan Plesteran m² 0,420 96.456,00 40.511,52
c. Pekerjaan Acian m² 0,420 58.187,00 24.438,54
d. Pek. Tutup bak inlet -
- Pek. Beton campuran 1 sp : 2 ps : 3 kr m3 0,010 1.320.118,00 13.201,18
- Pek. tulangan besi Ø 10-150 kg 4,960 17.596,00 87.276,16
- Bekisting m2 0,130 491.697,00 63.920,61
25
8 Pekerjaan pipa kompartemen -
a. Pipa PVC AW Ø 3" m' 20,400 28.825,00 588.030,00
b. Pipa PVC AW Ø 4" m' 1,000 44.825,00 44.825,00
c. Tee PVC AW Ø 4" bh 2,000 93.500,00 187.000,00
e. Tee PVC AW Ø 3" bh 24,000 46.500,00 1.116.000,00
f. Pipa GI medium Ø 2" untuk ventilasi m' 3,000 108.500,00 325.500,00
g. Tee GI Ø 2" untuk ventilasi bh 3,000 204.600,00 613.800,00
h. Media bakteri m3 2,000 300.000,00 600.000,00
i. Pengecatan IPAL m2 8,000 42.948,00 343.584,00
Jumlah 37.332.707,77
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
SEPTICTANK KOMUNAL 5-10 KK
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 741.775,00
II PEKERJAAN JARINGAN PIPA AIR LIMBAH 13.599.892,80
III PEKERJAAN SEPTIK TANK 37.332.707,77
JUMLAH (Rp) 51.674.375,57
PPN 10% 5.167.437,56
JUMLAH TOTAL (Rp) 56.841.813,13
JUMLAH DIBULATKAN (Rp) 56.841.000,00
26
ANALISIS STANDAR BELANJA (ASB)
SPAL/DRAINASE DENGAN PASANGAN BATU BELAH DENGAN GREFFEL 1/2 DIA 20 CM TANPA TULANGAN
1 KELOMPOK : Kontruksi
2 SUB KELOMPOK : Membangun SPAL/DRAINASE
3 SUB- SUB KELOMPOK : Membangun SPAL/DRAINASE
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Membangun SPAL/DRAINASE
6 DESKRIPSI AKTIVITAS : Membangun SPAL/DRAINASE
7 SATUAN AKTIVITAS : m¹
8 KOMPONEN/RINCIAN KOMPONEN :
NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
I PEKERJAAN TANAH
1 Pemasangan Bouwplank m¹ 1,000 81.786,00 81.786,00
2 Galian Tanah Biasa m³ 0,320 119.924,00 38.375,68
3 Pembuangan Tanah Bekas Galian m³ 0,320 52.558,00 16.818,56
Jumlah 136.980,24
PEKERJAAN PAS. BATU BELAH DENGAN GREFFEL
II
1/2 DIA 20 CM TANPA TULANGAN
1 Pek. Pasangan Batu Belah m³ 0,160 1.144.638,00 183.142,08
2 Pek. Plesteran m² 0,550 98.730,00 54.301,50
3 Pek. Acian m² 0,550 58.187,00 32.002,85
4 Pek. Siaran m² 0,162 93.173,00 15.094,03
5 Pek. Urugan Pasir m³ 0,035 268.769,00 9.406,92
6 Pek. Grefel 1/2 dia 20 cm tanpa tulangan m¹ 1,000 402.442,00 402.442,00
Jumlah 696.389,37
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
SPAL/DRAINASE DENGAN PASANGAN BATU BELAH DENGAN GREFFEL 1/2 DIA 20 CM TANPA TULANGAN
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 136.980,24
II PEKERJAAN PAS. BATU BELAH DENGAN GREFFEL 1/2 DIA 20 CM TANPA TULANGAN 696.389,37
JUMLAH (Rp) 833.369,61
PPN 10% 83.336,96
JUMLAH TOTAL (Rp) 916.706,57
JUMLAH DIBULATKAN (Rp) 916.000,00
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
SPAL/DRAINASE DENGAN PASANGAN BATU BELAH
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 159.402,90
II PEKERJAAN PAS. BATU BELAH 464.899,07
JUMLAH (Rp) 624.301,97
PPN 10% 62.430,20
JUMLAH TOTAL (Rp) 686.732,16
JUMLAH DIBULATKAN (Rp) 686.000,00
27
ANALISIS STANDAR BELANJA (ASB)
SPAL/DRAINASE DENGAN PIPA PVC KHUSUS PEMBUANGAN DIA 8 "
1 KELOMPOK : Kontruksi
2 SUB KELOMPOK : Membangun SPAL/DRAINASE DENGAN PIPA PVC
3 SUB- SUB KELOMPOK : Membangun SPAL/DRAINASE DENGAN PIPA PVC
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Membangun SPAL/DRAINASE DENGAN PIPA PVC
6 DESKRIPSI AKTIVITAS : Membangun SPAL/DRAINASE DENGAN PIPA PVC
7 SATUAN AKTIVITAS : m¹
8 KOMPONEN/RINCIAN KOMPONEN :
NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
I PEKERJAAN TANAH
1 Galian Tanah Biasa m³ 0,160 119.924,00 19.187,84
2 Pembuangan Tanah Bekas Galian m³ 0,030 52.558,00 1.576,74
3 Urugan Tanah Bekas Galian m³ 0,130 86.899,00 11.296,87
Jumlah 32.061,45
PEKERJAAN PIPA PVC KHUSUS PEMBUANGAN DIA
II -
8"
1 Pek. Pipa PVC khusus Pembuangan dia 8" m¹ 1,000 592.602,00 592.602,00
2 Pek. Beton campuran 1Pc:2Ps:3Krl m³ 0,028 1.320.118,00 36.963,30
3 Pek. Urugan Pasir m³ 0,015 268.769,00 4.031,54
4 Bak Kontrol asumsi per 8 meter unit 0,125 1.229.194,00 153.649,25
Jumlah 787.246,09
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
SPAL/DRAINASE DENGAN PIPA PVC KHUSUS PEMBUANGAN DIA 8 "
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 32.061,45
II PEKERJAAN PIPA PVC KHUSUS PEMBUANGAN DIA 8" 787.246,09
JUMLAH (Rp) 819.307,54
PPN 10% 81.930,75
JUMLAH TOTAL (Rp) 901.238,29
JUMLAH DIBULATKAN (Rp) 901.000,00
28
ANALISIS STANDAR BELANJA (ASB)
RUMAH TIPE 1 ( RTLH TYPE 1)
1 KELOMPOK : Konstruksi
2 SUB KELOMPOK : Pembangunan Perumahan
3 SUB- SUB KELOMPOK : Pembangunan Rumah Tidak Layak Huni
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Pembangunan Rumah Tidak Layak Huni Tipe 1
6 DESKRIPSI AKTIVITAS : Membangun Rumah Tidak Layak Huni Tipe 1
7 SATUAN AKTIVITAS : Unit
8 KOMPONEN/RINCIAN KOMPONEN :
NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
A PEKERJAAN TANAH DAN PONDASI
1 Pek. Urugan m³ 0,420 268.769,00 112.882,98
2 Pas. Pondasi batu belah 1Pc : 5Ps m³ 2,880 1.144.638,00 3.296.557,44
Jumlah 3.409.440,42
B PEKERJAAN STRUKTUR -
1 Pek. Sloof -
a Pembesian dengan besi polos . kg 40,720 17.596,00 716.509,12
b Membuat beton mutu f'c = 26.4 MPa m³ 0,540 1.374.406,00 742.179,24
c Pasang bekisting untuk sloof. - 238.798,00 -
2 Pek. Kolom -
a Pembesian dengan besi polos . kg 40,720 17.596,00 716.509,12
b Membuat beton mutu f'c = 26.4 MPa m³ 0,598 1.374.406,00 821.894,79
c Pasang bekisting untuk kolom - 428.677,00 -
Jumlah 2.997.092,27
C PEKERJAAN DINDING -
1 Pas. Dinding bata biasa, 1 Pc : 5 Ps m² 16,380 166.609,00 2.729.055,42
Jumlah 2.729.055,42
D PEK. KUSEN, PINTU / JENDELA DAN KACA -
1 Pas. Pintu kayu bh 1,000 850.000,00 850.000,00
2 Pas. Pintu PVC KM/WC bh 1,000 490.000,00 490.000,00
Jumlah 1.340.000,00
E PEKERJAAN ATAP -
1 Pas. Penutup Atap Palentong m² 17,500 241.029,00 4.218.007,50
2 Pas. Capit gunting ls 1,000 200.000,00 200.000,00
Jumlah 4.418.007,50
F PEKERJAAN PENGECATAN -
1 Pek. Pengecatan Tembok m² 67,200 33.978,00 2.283.321,60
Jumlah 2.283.321,60
G PEKERJAAN SANITAIR -
1 Pas. Closet Jongkok bh 1,000 730.581,00 730.581,00
2 Pas. Kran Air bh 1,000 255.586,00 255.586,00
Jumlah 986.167,00
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
RUMAH TIPE 1 ( RTLH TYPE 1)
No PEKERJAAN JUMLAH (Rp)
A PEKERJAAN TANAH DAN PONDASI 3.409.440,42
B PEKERJAAN STRUKTUR 2.997.092,27
C PEKERJAAN DINDING 2.729.055,42
D PEK. KUSEN, PINTU / JENDELA DAN KACA 1.340.000,00
E PEKERJAAN ATAP 4.418.007,50
F PEKERJAAN PENGECATAN 2.283.321,60
G PEKERJAAN SANITAIR 986.167,00
JUMLAH (Rp) 18.163.084,21
PPN 10% 1.816.308,42
JUMLAH TOTAL (Rp) 19.979.392,63
JUMLAH DIBULATKAN (Rp) 19.979.000,00
29
ANALISIS STANDAR BELANJA (ASB)
RUMAH TIPE 2 ( RTLH TYPE 2)
1 KELOMPOK : Konstruksi
2 SUB KELOMPOK : Pembangunan Perumahan
3 SUB- SUB KELOMPOK : Pembangunan Rumah Tidak Layak Huni
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Pembangunan Rumah Tidak Layak Huni Tipe 2
6 DESKRIPSI AKTIVITAS : Membangun Rumah Tidak Layak Huni Tipe 2
7 SATUAN AKTIVITAS : Unit
8 KOMPONEN/RINCIAN KOMPONEN :
NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
A PEKERJAAN TANAH DAN PONDASI
1 Pek. Galian tanah biasa m³ - 119.924,00 -
2 Pek. Urugan m³ - 268.769,00 -
3 Pas. Pondasi batu belah 1Pc : 5Ps m³ - 1.144.638,00 -
Jumlah -
B PEKERJAAN STRUKTUR -
1 Pek. Sloof m³ - 7.374.284,00 -
2 Pek. Kolom m³ - 7.581.467,00 -
3 Pek. Ring Balk m³ - 8.001.566,00 -
Jumlah -
C PEKERJAAN DINDING -
1 Pas. Dinding bata biasa, 1 Pc : 5 Ps m² 18,070 166.609,00 3.010.624,63
2 Pek. Plesteran dan acian dinding biasa 1 Pc : 5 Ps m² - 95.270,00 -
Jumlah 3.010.624,63
D PEK. KUSEN, PINTU / JENDELA DAN KACA -
1 Pasang pintu dan jendela kaca, kayu Kls. II atau Kls. III m² - 939.808,00 -
2 Pas. Pintu kayu bh - 850.000,00 -
3 Pas. Pintu PVC KM/WC bh - 490.000,00 -
4 Pasang engsel pintu bh - 75.057,00 -
5 Pasang engsel jendela bh - 75.057,00 -
6 Kaca 6mm m² - 146.491,00 -
Jumlah -
E PEKERJAAN ATAP -
1 Pasang konstruksi kuda - kuda, kayu Kayu Lokal Kls. II. m³ 0,216 7.212.340,00 1.557.865,44
Pas. Penutup Atap Palentong m² 17,500 241.029,00 4.218.007,50
Pas. Genteng bubung m 3,500 157.741,00 552.093,50
Pas. Listplank m - 95.738,00 -
2 Pas. Capit gunting ls 1,000 200.000,00 200.000,00
Jumlah 6.527.966,44
F PEKERJAAN LANTAI DAN PLAFON -
1 Pasang lantai keramik, uk. 20 x 20 cm. m² - 244.301,00 -
2 Pasang lantai keramik, uk. 30 x 30 cm. m² - 189.964,00 -
3 Pasang rangka plafon m² 11,500 155.898,00 1.792.827,00
4 Pasang langit-langit gypsum m² 11,500 59.164,00 680.386,00
Jumlah 2.473.213,00
G PEKERJAAN PENGECATAN -
1 Pek. Pengecatan Tembok m² - 33.978,00 -
Jumlah -
H PEKERJAAN SANITAIR -
1 Pas. Closet Jongkok bh - 730.581,00 -
2 Pas. Floor Drain bh - 126.164,00 -
3 Pas. Kran Air bh - 255.586,00 -
Jumlah -
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
RUMAH TIPE 2 ( RTLH TYPE 2)
No PEKERJAAN JUMLAH (Rp)
A PEKERJAAN TANAH DAN PONDASI -
B PEKERJAAN STRUKTUR -
C PEKERJAAN DINDING 3.010.624,63
D PEK. KUSEN, PINTU / JENDELA DAN KACA -
E PEKERJAAN ATAP 6.527.966,44
F PEKERJAAN LANTAI DAN PLAFON 2.473.213,00
G PEKERJAAN PENGECATAN -
H PEKERJAAN SANITAIR -
JUMLAH (Rp) 12.011.804,07
PPN 10% 1.201.180,41
JUMLAH TOTAL (Rp) 13.212.984,48
JUMLAH DIBULATKAN (Rp) 13.212.000,00
30
ANALISIS STANDAR BELANJA (ASB)
RUMAH TIPE 3 ( RTLH TYPE 3)
1 KELOMPOK : Konstruksi
2 SUB KELOMPOK : Pembangunan Perumahan
3 SUB- SUB KELOMPOK : Pembangunan Rumah Tidak Layak Huni
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Pembangunan Rumah Tidak Layak Huni Tipe 3
6 DESKRIPSI AKTIVITAS : Membangun Rumah Tidak Layak Huni Tipe 3
7 SATUAN AKTIVITAS : Unit
8 KOMPONEN/RINCIAN KOMPONEN :
NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
A PEKERJAAN DINDING
1 Pas. Dinding bata biasa, 1 Pc : 5 Ps m² 10,692 166.609,00 1.781.383,43
2 Pek. Plesteran dan acian dinding biasa 1 Pc : 5 Ps m² 10,692 95.270,00 1.018.626,84
Jumlah 2.800.010,27
B PEKERJAAN ATAP -
1 Pasang konstruksi kuda - kuda, kayu Kayu Lokal Kls. II. m³ 0,060 7.212.340,00 434.904,10
2 Pas. Penutup Atap Palentong m² 17,500 241.029,00 4.218.007,50
Jumlah 4.652.911,60
C PEKERJAAN LANTAI DAN PLAFON -
1 Pasang langit-langit gypsum m² 5,630 59.164,00 333.093,32
Jumlah 333.093,32
D PEKERJAAN PENGECATAN -
1 Pek. Pengecatan Tembok m² 33,600 33.978,00 1.141.660,80
Jumlah 1.141.660,80
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
RUMAH TIPE 3
No PEKERJAAN JUMLAH (Rp)
A PEKERJAAN DINDING 2.800.010,27
B PEKERJAAN ATAP 4.652.911,60
C PEKERJAAN LANTAI DAN PLAFON 333.093,32
D PEKERJAAN PENGECATAN 1.141.660,80
JUMLAH (Rp) 8.927.675,99
PPN 10% 892.767,60
JUMLAH TOTAL (Rp) 9.820.443,59
JUMLAH DIBULATKAN (Rp) 9.820.000,00
31
ANALISIS STANDAR BELANJA (ASB)
RUMAH PASCA BENCANA
1 KELOMPOK : Konstruksi
2 SUB KELOMPOK : Pembangunan Perumahan
3 SUB- SUB KELOMPOK : Pembangunan Rumah Tidak Layak Huni
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Pembangunan Rumah Pasca Bencana
6 DESKRIPSI AKTIVITAS : Membangun Rumah Pasca Bencana
7 SATUAN AKTIVITAS : Unit
8 KOMPONEN/RINCIAN KOMPONEN :
NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
A PEKERJAAN TANAH DAN PONDASI
1 Pek. Galian tanah biasa m³ 4,410 119.924,00 528.864,84
2 Pek. Urugan m³ 0,490 268.769,00 131.696,81
3 Pas. Pondasi batu belah 1Pc : 5Ps m³ 3,360 1.144.638,00 3.845.983,68
Jumlah 4.506.545,33
B PEKERJAAN DINDING -
1 Pas. Dinding bata biasa, 1 Pc : 5 Ps m² 25,210 166.609,00 4.200.212,89
2 Pek. Plesteran dan acian dinding biasa 1 Pc : 5 Ps m² 25,210 95.270,00 2.401.756,70
Jumlah 6.601.969,59
C PEK. KUSEN, PINTU / JENDELA DAN KACA -
1 Pasang pintu dan jendela kaca m² 0,116 939.808,00 109.393,65
2 Pas. Daun Pintu bh 1,000 850.000,00 850.000,00
3 Pas. Pintu KM/WC bh 1,000 490.000,00 490.000,00
4 Pasang engsel pintu bh 1,000 75.057,00 75.057,00
5 Pasang engsel jendela bh 3,000 75.057,00 225.171,00
6 Kaca 5 mm m² 1,680 146.491,00 246.104,88
Jumlah 1.995.726,53
D PEKERJAAN ATAP -
1 Pasang rangka atap baja ringan m³ 31,570 288.093,00 9.095.096,01
2 Pasang genteng metal m² 31,570 137.026,00 4.325.910,82
3 Pas. Capit gunting bh 1,000 200.000,00 200.000,00
Jumlah 13.621.006,83
E PEKERJAAN LANTAI DAN PLAFON -
1 Pasang lantai keramik, uk. 20 x 20 cm. m² 12,738 244.301,00 3.111.906,14
2 Pasang rangka plafon m² 30,000 156.499,00 4.694.970,00
3 Pasang langit-langit gypsum m² 30,000 59.164,00 1.774.920,00
Jumlah 9.581.796,14
F PEKERJAAN PENGECATAN -
1 Pek. Pengecatan Tembok m² 13,520 33.978,00 459.382,56
Jumlah 459.382,56
G PEKERJAAN SANITAIR -
1 Pas. Closet Jongkok bh 1,000 730.581,00 730.581,00
2 Pas. Floor Drain bh 1,000 126.164,00 126.164,00
3 Pas. Kran Air bh 1,000 255.586,00 255.586,00
Jumlah 1.112.331,00
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
RUMAH PASCA BENCANA
No PEKERJAAN JUMLAH (Rp)
A PEKERJAAN TANAH DAN PONDASI 4.506.545,33
B PEKERJAAN DINDING 6.601.969,59
C PEK. KUSEN, PINTU / JENDELA DAN KACA 1.995.726,53
D PEKERJAAN ATAP 13.621.006,83
E PEKERJAAN LANTAI DAN PLAFON 9.581.796,14
F PEKERJAAN PENGECATAN 459.382,56
G PEKERJAAN SANITAIR 1.112.331,00
JUMLAH (Rp) 37.878.757,98
PPN 10% 3.787.875,80
JUMLAH TOTAL (Rp) 41.666.633,78
JUMLAH DIBULATKAN (Rp) 41.666.000,00
PANEL RUSPIN TIPE 36 20.500.000,00
TOTAL 62.166.000,00
32
ANALISIS STANDAR BELANJA (ASB)
TPT
1 KELOMPOK : Konstruksi
2 SUB KELOMPOK : Pembangunan Perumahan
3 SUB- SUB KELOMPOK : Pembangunan TPT
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Pembangunan TPT
6 DESKRIPSI AKTIVITAS : Membangun TPT
7 SATUAN AKTIVITAS : m³
8 KOMPONEN/RINCIAN KOMPONEN :
NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
A PEMBANGUNAN TPT
1 Pasang pondasi batu belah, 1 Pc. : 5 Ps. m³ 1,000 1.144.638,00 1.144.638,00
2 Plesteran 1 Pc. : 5 Ps; tebal 15 mm. m² 0,270 95.270,00 25.722,90
3 Galian Tanah m³ 0,460 119.924,00 55.165,04
4 Pipa Sulingan m' 1,550 41.686,00 64.613,30
Jumlah 1.290.139,24
JUMLAH (Rp) 1.290.139,24
PPN 10% 129.013,92
JUMLAH TOTAL (Rp) 1.419.153,16
JUMLAH DIBULATKAN (Rp) 1.419.000,00
33
ANALISIS STANDAR BELANJA (ASB)
TAMAN TIPE A
1 KELOMPOK : Kontruksi
2 SUB KELOMPOK : Membangun TAMAN
3 SUB- SUB KELOMPOK : Membangun TAMAN
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : MEMBANGUN TAMAN TIPE A
6 DESKRIPSI AKTIVITAS : Membangun TAMAN
7 SATUAN AKTIVITAS : m²
8 KOMPONEN/RINCIAN KOMPONEN :
NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
I PEKERJAAN PAVING BLOCK
1 Pemasangan Paving Block Warna, Uk.10x20 T = 6 Cm m³ 0,500 246.660,00 123.330,00
Jumlah 123.330,00
II PEKERJAAN TAMAN -
1 Penanaman Rumput Gajah Manila m² 0,500 30.000,00 15.000,00
2 Tanah Lembang m² 0,300 100.000,00 30.000,00
3 Tabebuya, T = 250 Cm, Diameter Btg 8 S/ D 10 Cm phn 2,000 250.000,00 500.000,00
4 Penanaman Pucuk Merah (Syzygium), Tinggi 2 Meter phn - 500.000,00 -
Penanaman Bromelia Merah Mini (Neoregelia Fireball), 20 X
5 phn 7,000 15.000,00 105.000,00
20 Cm
6 Penanaman Kucir phn 6,000 10.000,00 60.000,00
7 Penanaman Azalea Bunga Orange Holland , 20 X 20 Cm phn 5,000 15.000,00 75.000,00
8 Landep phn 5,000 5.000,00 25.000,00
9 Landep polybag 4,000 3.000,00 12.000,00
10 Lili Paris (Chlorophytum Sp), T = 30 Cm polybag 6,000 2.000,00 12.000,00
Jumlah 834.000,00
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
Taman Tipe A
NO PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PAVING BLOCK 123.330,00
II PEKERJAAN TAMAN 834.000,00
JUMLAH (Rp) 957.330,00
PPN 10% 95.733,00
JUMLAH TOTAL (Rp) 1.053.063,00
JUMLAH DIBULATKAN (Rp) 1.053.000,00
34
ANALISIS STANDAR BELANJA (ASB)
TAMAN TIPE B
1 KELOMPOK : Kontruksi
2 SUB KELOMPOK : Membangun TAMAN
3 SUB- SUB KELOMPOK : TAMAN TIPE B
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : MEMBANGUN TAMAN TIPE B
6 DESKRIPSI AKTIVITAS : TAMAN TIPE B
7 SATUAN AKTIVITAS : m²
8 KOMPONEN/RINCIAN KOMPONEN :
NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
I PEKERJAAN PAVING BLOCK
1 Pemasangan Paving Block Warna, Uk.10x20 T = 6 Cm m³ 0,500 246.660,00 123.330,00
Jumlah 123.330,00
II PEKERJAAN TAMAN -
1 Penanaman Rumput Gajah Manila m² 0,500 30.000,00 15.000,00
2 Tanah Lembang m² 0,300 100.000,00 30.000,00
3 Tabebuya, T = 250 Cm, Diameter Btg 8 S/ D 10 Cm phn - 250.000,00 -
Tabebuya, T = 300 Cm, Diameter Btg 10 S/ D 15 cm phn 2,000 750.000,00 1.500.000,00
4 Penanaman Pucuk Merah (Syzygium), Tinggi 2 Meter phn - 500.000,00 -
Penanaman Bromelia Merah Mini (Neoregelia Fireball), 20 X
5 phn 7,000 15.000,00 105.000,00
20 Cm
6 Penanaman Kucir phn 6,000 10.000,00 60.000,00
7 Penanaman Azalea Bunga Orange Holland , 20 X 20 Cm phn 5,000 15.000,00 75.000,00
8 Landep phn 5,000 5.000,00 25.000,00
9 Landep Polybag 4,000 3.000,00 12.000,00
10 Lili Paris (Chlorophytum Sp), T = 30 Cm Polybag 6,000 2.000,00 12.000,00
Jumlah 1.834.000,00
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
Taman Tipe B
NO PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PAVING BLOCK 123.330,00
II PEKERJAAN TAMAN 1.834.000,00
JUMLAH (Rp) 1.957.330,00
PPN 10% 195.733,00
JUMLAH TOTAL (Rp) 2.153.063,00
JUMLAH DIBULATKAN (Rp) 2.153.000,00
35
ANALISIS STANDAR BELANJA (ASB)
TAMAN TIPE C
1 KELOMPOK : Kontruksi
2 SUB KELOMPOK : Membangun TAMAN
3 SUB- SUB KELOMPOK : TAMAN TIPE C
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : MEMBANGUN TAMAN TIPE C
6 DESKRIPSI AKTIVITAS : TAMAN TIPE C
7 SATUAN AKTIVITAS : m²
8 KOMPONEN/RINCIAN KOMPONEN :
NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
I PEKERJAAN PAVING BLOCK
1 Pemasangan Paving Block Warna, Uk.10x20 T = 6 Cm m³ 0,500 246.660,00 123.330,00
Jumlah 123.330,00
II PEKERJAAN TAMAN -
1 Penanaman Rumput Gajah Manila m² 0,500 30.000,00 15.000,00
2 Tanah Lembang m² 0,300 100.000,00 30.000,00
3 Tabebuya, T = 250 Cm, Diameter Btg 8 S/ D 10 Cm phn - 250.000,00 -
Tabebuya, T = 300 Cm, Diameter Btg 10 S/ D 15 cm phn 2,000 750.000,00 1.500.000,00
4 Penanaman Pucuk Merah (Syzygium), Tinggi 2 Meter phn 1,000 500.000,00 500.000,00
Penanaman Bromelia Merah Mini (Neoregelia Fireball), 20 X
5 phn 7,000 15.000,00 105.000,00
20 Cm
6 Penanaman Kucir phn 6,000 10.000,00 60.000,00
7 Penanaman Azalea Bunga Orange Holland , 20 X 20 Cm phn 5,000 15.000,00 75.000,00
8 Landep phn 5,000 5.000,00 25.000,00
9 Landep Polybag 4,000 3.000,00 12.000,00
10 Lili Paris (Chlorophytum Sp), T = 30 Cm Polybag 6,000 2.000,00 12.000,00
Jumlah 2.334.000,00
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
TAMAN TIPE C
NO PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PAVING BLOCK 123.330,00
II PEKERJAAN TAMAN 2.334.000,00
JUMLAH (Rp) 2.457.330,00
PPN 10% 245.733,00
JUMLAH TOTAL (Rp) 2.703.063,00
JUMLAH DIBULATKAN (Rp) 2.703.000,00
36
ANALISIS STANDAR BELANJA (ASB)
TAMAN TIPE D
1 KELOMPOK : Kontruksi
2 SUB KELOMPOK : Membangun TAMAN
3 SUB- SUB KELOMPOK : Taman Tipe D
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : MEMBANGUN TAMAN TIPE D
6 DESKRIPSI AKTIVITAS : Taman Tipe D
7 SATUAN AKTIVITAS : m²
8 KOMPONEN/RINCIAN KOMPONEN :
NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
I PEKERJAAN RABAT BETON
1 Galian tanah biasa sedalam 1 meter m³ 0,070 119.924,00 8.394,68
Membuat 1 m3 lantai kerja beton mutu f'c = 7.4 Mpa slump (3-
2 m³ 0,140 1.016.351,00 142.289,14
6) cm, w/c = 0.87
3 Plesteran 1:5 m² 0,280 95.270,00 26.675,60
4 Acian m² 0,280 58.187,00 16.292,36
Pengecetan 1 m2 tembok baru (1 lapis plamuur, 1 lapis cat
5 m² 0,280 42.948,00 12.025,44
dasar, 2 lapis cat penutup)
Jumlah 205.677,22
II PEKERJAAN TAMAN -
1 Penanaman Rumput Gajah Manila m² 0,300 30.000,00 9.000,00
2 Tanah lembang phn 0,300 100.000,00 30.000,00
3 Pucuk Merah (Syzygium), Tinggi 2 Meter phn - 500.000,00 -
Penanaman Bromelia Merah Mini (Neoregelia Fireball), 20 X
4 phn 5,000 15.000,00 75.000,00
20 Cm
5 Penanaman Kucir phn 5,000 10.000,00 50.000,00
6 Penanaman Azalea Bunga Orange Holland , 20 X 20 Cm phn 3,000 15.000,00 45.000,00
7 Landep phn 5,000 5.000,00 25.000,00
8 Landep Polybag 5,000 3.000,00 15.000,00
Lili Paris (Chlorophytum Sp), T = 30 Cm Polybag 7,000 2.000,00 14.000,00
Penanaman Tabebuya, T = 300 Cm, Diameter Btg 10 S/ D 15
phn 2,000 750.000,00 1.500.000,00
cm
Jumlah 1.763.000,00
III PEKERJAAN AKSESORIS TAMAN -
1 Lampu Taman Motif Kina Besar Tipe 1 Unit 1,000 4.000.000,00 4.000.000,00
Jumlah 4.000.000,00
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
TAMAN TIPE D
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN RABAT BETON 205.677,22
II PEKERJAAN TAMAN 1.763.000,00
III PEKERJAAN AKSESORIS TAMAN 4.000.000,00
JUMLAH (Rp) 5.968.677,22
PPN 10% 596.867,72
JUMLAH TOTAL (Rp) 6.565.544,94
JUMLAH DIBULATKAN (Rp) 6.565.000,00
37
ANALISIS STANDAR BELANJA (ASB)
TAMAN TIPE E
1 KELOMPOK : Kontruksi
2 SUB KELOMPOK : Membangun TAMAN
3 SUB- SUB KELOMPOK : Taman Tipe E
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Kontruksi
6 DESKRIPSI AKTIVITAS : Taman Tipe E
7 SATUAN AKTIVITAS : m²
8 KOMPONEN/RINCIAN KOMPONEN :
NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
I PEKERJAAN RABAT BETON
1 Galian tanah biasa sedalam 1 meter m³ 0,070 119.924,00 8.394,68
Membuat 1 m3 lantai kerja beton mutu f'c = 7.4 Mpa slump (3-
2 m³ 0,140 1.016.351,00 142.289,14
6) cm, w/c = 0.87
3 Plesteran 1:5 m² 0,280 95.270,00 26.675,60
4 Acian m² 0,280 58.187,00 16.292,36
Pengecetan 1 m2 tembok baru (1 lapis plamuur, 1 lapis cat
5 m² 0,280 42.948,00 12.025,44
dasar, 2 lapis cat penutup)
Jumlah 205.677,22
II PEKERJAAN TAMAN -
1 Penanaman Rumput Gajah Manila m² 0,300 30.000,00 9.000,00
2 Tanah lembang phn 0,300 100.000,00 30.000,00
3 Pucuk Merah (Syzygium), Tinggi 2 Meter phn - 500.000,00 -
Penanaman Bromelia Merah Mini (Neoregelia Fireball), 20 X
4 phn 5,000 15.000,00 75.000,00
20 Cm
5 Penanaman Kucir phn 5,000 10.000,00 50.000,00
6 Penanaman Kucir merah phn 4,000 10.000,00 40.000,00
Penanaman Bromelia Merah Mini (Neoregelia Fireball), 20 X
7 phn 4,000 15.000,00 60.000,00
20 Cm
8 Landep phn 3,000 5.000,00 15.000,00
Landep Polybag 5,000 3.000,00 15.000,00
Lili Paris (Chlorophytum Sp), T = 30 Cm Polybag 2,000 2.000,00 4.000,00
Jumlah 298.000,00
III PEKERJAAN AKSESORIS TAMAN -
1 Lampu Taman Motif Kina Besar Tipe 1 Unit 1,000 8.000.000,00 8.000.000,00
Jumlah 8.000.000,00
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
TAMAN TIPE E
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN RABAT BETON 205.677,22
II PEKERJAAN TAMAN 298.000,00
III PEKERJAAN AKSESORIS TAMAN 8.000.000,00
JUMLAH (Rp) 8.503.677,22
PPN 10% 850.367,72
JUMLAH TOTAL (Rp) 9.354.044,94
JUMLAH DIBULATKAN (Rp) 9.354.000,00
38
ANALISIS STANDAR BELANJA (ASB)
TPU TIPE A
1 KELOMPOK : Kontruksi
2 SUB KELOMPOK : Membangun TPU
3 SUB- SUB KELOMPOK : Membangun TPU TIPE A
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Kontruksi
6 DESKRIPSI AKTIVITAS : Membangun TPU TIPE A
7 SATUAN AKTIVITAS : m²
8 KOMPONEN/RINCIAN KOMPONEN :
NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
I PEKERJAAN PAVING BLOCK
1 Pemasangan Paving Block Warna. Uk.10x20 T = 6 Cm m² 0,500 246.660,00 123.330,00
Jumlah 123.330,00
III PEKERJAAN TAMAN -
1 Penanaman Rumput Gajah Manila m² 0,500 30.000,00 15.000,00
2 Tanah lembang m² 0,300 100.000,00 30.000,00
3 Tabebuya, T = 250 Cm, Diameter Btg 8 S/ D 10 Cm phn 2,000 250.000,00 500.000,00
4 Penanaman Pucuk Merah (Syzygium), Tinggi 2 Meter phn - 500.000,00 -
Penanaman Bromelia Merah Mini (Neoregelia Fireball), 20 X
5 phn 7,000 15.000,00 105.000,00
20 Cm
6 Penanaman Kucir phn 6,000 10.000,00 60.000,00
7 Penanaman Azalea Bunga Orange Holland , 20 X 20 Cm phn 5,000 15.000,00 75.000,00
8 Landep phn 5,000 5.000,00 25.000,00
9 Landep Polybag 4,000 3.000,00 12.000,00
10 Lili Paris (Chlorophytum Sp), T = 30 Cm Polybag 6,000 2.000,00 12.000,00
Jumlah 834.000,00
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
TPU TIPE A
No PEKERJAAN JUMLAH
I PEKERJAAN PAVING BLOCK 123.330,00
II PEKERJAAN TAMAN 834.000,00
JUMLAH (Rp) 957.330,00
PPN 10% 95.733,00
JUMLAH TOTAL (Rp) 1.053.063,00
JUMLAH DIBULATKAN (Rp) 1.053.000,00
39
ANALISIS STANDAR BELANJA (ASB)
TPU TIPE B
1 KELOMPOK : Kontruksi
2 SUB KELOMPOK : Membangun TPU
3 SUB- SUB KELOMPOK : TPU TIPE B
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Kontruksi
6 DESKRIPSI AKTIVITAS : TPU TIPE B
7 SATUAN AKTIVITAS : m²
8 KOMPONEN/RINCIAN KOMPONEN :
NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
I PEKERJAAN PERSIAPAN
1 Pemasangan Paving Block Warna, Uk.10x20 T = 6 Cm m³ 0,500 246.660,00 123.330,00
Jumlah 123.330,00
II PEKERJAAN TAMAN -
1 Penanaman Rumput Gajah Manila m² 0,500 30.000,00 15.000,00
2 Tabebuya, T = 250 Cm, Diameter Btg 8 S/ D 10 Cm phn 1,000 250.000,00 250.000,00
3 Tabebuya, T = 300 Cm, Diameter Btg 10 S/ D 15 cm phn 1,000 750.000,00 750.000,00
4 Penanaman Pucuk Merah (Syzygium), Tinggi 2 Meter phn - 500.000,00 -
Penanaman Bromelia Merah Mini (Neoregelia Fireball), 20 X
5 phn 15,000 15.000,00 225.000,00
20 Cm
6 Penanaman Kucir phn 8,000 10.000,00 80.000,00
7 Penanaman Azalea Bunga Orange Holland , 20 X 20 Cm phn 5,000 15.000,00 75.000,00
8 Landep phn 9,000 5.000,00 45.000,00
9 Landep Polybag 10,000 3.000,00 30.000,00
10 Lili Paris (Chlorophytum Sp), T = 30 Cm Polybag 12,000 2.000,00 24.000,00
11 Tanah lembang m² 0,300 100.000,00 30.000,00
Jumlah 1.524.000,00
3 Pek. Dinding Penahan Tanah (DPT) -
1 Pek. Pasangan Batu kali 1 : 3 (Dinding Penahan Tanah) m³ 0,210 1.237.730,00 259.923,30
2 Plesteran 1 : 5 m² 0,350 95.270,00 33.344,50
3 Acian m² 0,350 58.187,00 20.365,45
Jumlah 313.633,25
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
TPU TIPE B
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 123.330,00
II PEKERJAAN TAMAN 1.524.000,00
III Pek. Dinding Penahan Tanah (DPT) 313.633,25
JUMLAH (Rp) 1.960.963,25
PPN 10% 196.096,33
JUMLAH TOTAL (Rp) 2.157.059,58
JUMLAH DIBULATKAN (Rp) 2.157.000,00
40
ANALISIS STANDAR BELANJA (ASB)
TPU TIPE C
1 KELOMPOK : Kontruksi
2 SUB KELOMPOK : Membangun TPU
3 SUB- SUB KELOMPOK : TPU TIPE C
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Kontruksi
6 DESKRIPSI AKTIVITAS : TPU TIPE C
7 SATUAN AKTIVITAS : m²
8 KOMPONEN/RINCIAN KOMPONEN :
NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
I PEKERJAAN PERSIAPAN
1 Pemasangan Paving Block Warna, Uk.10x20 T = 6 Cm m³ 0,500 246.660,00 123.330,00
Jumlah 123.330,00
II PEKERJAAN TAMAN -
1 Penanaman Rumput Gajah Manila m² 0,500 30.000,00 15.000,00
2 Tabebuya, T = 250 Cm, Diameter Btg 8 S/ D 10 Cm phn 1,000 250.000,00 250.000,00
3 Tabebuya, T = 300 Cm, Diameter Btg 10 S/ D 15 cm phn 1,000 750.000,00 750.000,00
4 Penanaman Pucuk Merah (Syzygium), Tinggi 2 Meter phn 1,000 500.000,00 500.000,00
Penanaman Bromelia Merah Mini (Neoregelia Fireball), 20 X
5 phn 15,000 15.000,00 225.000,00
20 Cm
6 Penanaman Kucir phn 8,000 10.000,00 80.000,00
7 Penanaman Azalea Bunga Orange Holland , 20 X 20 Cm phn 5,000 15.000,00 75.000,00
8 Landep phn 9,000 5.000,00 45.000,00
9 Landep Polybag 10,000 3.000,00 30.000,00
10 Lili Paris (Chlorophytum Sp), T = 30 Cm Polybag 12,000 2.000,00 24.000,00
11 Tanah lembang m² 0,500 100.000,00 50.000,00
Jumlah 2.044.000,00
3 Pek. Dinding Penahan Tanah (DPT) -
1 Pek. Pasangan Batu kali 1 : 3 (Dinding Penahan Tanah) m³ 0,210 1.237.730,00 259.923,30
2 Plesteran 1 : 5 m² 0,350 95.270,00 33.344,50
3 Acian m² 0,350 58.187,00 20.365,45
Jumlah 313.633,25
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
TPU TIPE C
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 123.330,00
II PEKERJAAN TAMAN 2.044.000,00
III Pek. Dinding Penahan Tanah (DPT) 313.633,25
JUMLAH (Rp) 2.480.963,25
PPN 10% 248.096,33
JUMLAH TOTAL (Rp) 2.729.059,58
JUMLAH DIBULATKAN (Rp) 2.729.000,00
41
ANALISIS STANDAR BELANJA (ASB)
GAPURA TIPE 1
1 KELOMPOK : Kontruksi
2 SUB KELOMPOK : Membangun Taman
3 SUB- SUB KELOMPOK : ASB GAPURA 1
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Kontruksi
6 DESKRIPSI AKTIVITAS : ASB GAPURA 1
7 SATUAN AKTIVITAS : Unit
8 KOMPONEN/RINCIAN KOMPONEN :
NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
I PEKERJAAN PERSIAPAN
1 Pembersihan lapangan dan perataan m2 4,000 25.719,00 102.876,00
2 Pengukuran dan pemasangan Bouwplank m' 8,000 81.786,00 654.288,00
Jumlah 757.164,00
II PEKERJAAN TANAH -
1 Galian tanah biasa sedalam 1 meter m3 2,000 119.924,00 239.848,00
2 Pengurugan kembali galian tanah m3 1,600 86.899,00 139.038,40
3 Pengurugan dengan pasir urug (untuk pondasi t.5 cm) m3 0,100 268.769,00 26.876,90
Jumlah 405.763,30
III PEKERJAAN BETON -
1 Beton mutu f'c = 14.5 MPa Pondasi Telapak 0,9x0,9 m3 0,860 1.269.586,00 1.091.843,96
2 Besi beton pondasi telapak 0,9x0,9 kg 3,000 17.596,00 52.788,00
3 Bekisting pondasi telapak 0,9x0,9 m2 5,200 228.448,00 1.187.929,60
4 Beton mutu f'c = 14.5 MPa kolom 60x60 m3 4,500 1.269.586,00 5.713.137,00
5 Besi beton kolom 60x60 kg 47,500 17.596,00 835.810,00
6 Bekisting kolom 60x60 m2 14,400 428.677,00 6.172.948,80
7 Beton mutu f'c = 14.5 MPa ringbalk 30/60 m3 1,100 1.269.586,00 1.396.544,60
8 Besi beton ringbalk 30/60 kg 17,300 17.596,00 304.410,80
9 Bekisting ringbalk 30/60 m2 9,000 439.027,00 3.951.243,00
10 Lantai kerja beton mutu f'c = 7.4 Mpa m3 0,500 1.016.351,00 508.175,50
Jumlah 21.214.831,26
IV PEKERJAAN ATAP -
1 Rangka Atap Sirap m2 12,000 288.093,00 3.457.116,00
2 Nok Sirap m' 6,000 157.741,00 946.446,00
3 Penutup Atap Sirap Kayu m2 12,000 241.029,00 2.892.348,00
4 Rangka plafond atap gapura m2 10,000 156.499,00 1.564.990,00
5 Plafond atap gapura m2 10,000 59.164,00 591.640,00
6 Lisplank m' 7,500 95.738,00 718.035,00
Jumlah 10.170.575,00
V PEKERJAAN PASANGAN -
1 Plesteran 1:3 m2 3,000 132.153,00 396.459,00
2 Acian m2 3,000 58.187,00 174.561,00
3 Pemasangan Batu Tempel m2 27,000 340.842,00 9.202.734,00
Jumlah 9.773.754,00
VI PEKERJAAN CAT DAN LABURAN -
1 Coating Batu Tempel m2 27,000 132.922,00 3.588.894,00
2 Cat Kayu Lisplank dengan politur m2 4,000 97.325,00 389.300,00
Jumlah 3.978.194,00
VII PEKERJAAN LAIN-LAIN -
1 Logo Kabupaten buah 1,000 2.800.000,00 2.800.000,00
Huruf Timbul Bahan Stainless, Tebal 15 cm (Huruf Selamat
2 buah 50,000 67.500,00 3.375.000,00
Datang dll)
3 Batu Grafir Motif Daun Kina m' 2,000 300.000,00 600.000,00
4 Finishing Batu Koral Sikat m2 4,800 340.842,00 1.636.041,60
Jumlah 8.411.041,60
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
GAPURA TIPE 1
NO URAIAN PEKERJAAN JUMLAH
I PEKERJAAN PERSIAPAN 757.164,00
II PEKERJAAN TANAH 405.763,30
III PEKERJAAN BETON 21.214.831,26
IV PEKERJAAN ATAP 10.170.575,00
V PEKERJAAN CAT DAN LABURAN 3.978.194,00
VI PEKERJAAN PASANGAN 9.773.754,00
VII PEKERJAAN LAIN-LAIN 8.411.041,60
JUMLAH (Rp) 54.711.323,16
PPN 10% 5.471.132,32
JUMLAH TOTAL (Rp) 60.182.455,48
JUMLAH DIBULATKAN (Rp) 60.182.000,00
42
ANALISIS STANDAR BELANJA (ASB)
GAPURA TIPE 2
1 KELOMPOK : Kontruksi
2 SUB KELOMPOK : Membangun Taman
3 SUB- SUB KELOMPOK : ASB GAPURA 2
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Kontruksi
6 DESKRIPSI AKTIVITAS : ASB GAPURA 2
7 SATUAN AKTIVITAS : Unit
8 KOMPONEN/RINCIAN KOMPONEN :
NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
I PEKERJAAN PERSIAPAN
1 Pembersihan lapangan dan perataan m2 2,000 25.719,00 51.438,00
2 Pengukuran dan pemasangan Bouwplank m' 4,000 81.786,00 327.144,00
Jumlah 378.582,00
II PEKERJAAN TANAH -
1 Penggalian tanah biasa sedalam 1 m (Pondasi Telapak 1x1m) m3 2,000 119.924,00 239.848,00
2 Pengurugan kembali galian tanah m3 1,600 86.899,00 139.038,40
3 Pengurugan dengan pasir urug (untuk pondasi t.5 cm) m3 0,100 268.769,00 26.876,90
Jumlah 405.763,30
III PEKERJAAN BETON -
1 Beton mutu f'c = 14.5 MPa Pondasi Telapak 0,9x0,9 m3 0,320 1.269.586,00 406.267,52
2 Besi beton pondasi telapak 0,9x0,9 kg 1,100 17.596,00 19.355,60
3 Bekisting pondasi telapak 0,9x0,9 m2 3,100 228.448,00 708.188,80
4 Beton mutu f'c = 14.5 MPa kolom 60x60 m3 0,650 1.269.586,00 825.230,90
5 Besi beton kolom 60x60 kg 7,600 17.596,00 133.729,60
6 Bekisting kolom 60x60 m2 8,400 428.677,00 3.600.886,80
7 Beton mutu f'c = 14.5 MPa ringbalk 30/60 m3 0,160 1.269.586,00 203.133,76
8 Besi beton ringbalk 30/60 kg 3,000 17.596,00 52.788,00
9 Bekisting ringbalk 30/60 m2 2,550 439.027,00 1.119.518,85
10 Lantai kerja beton mutu f'c = 7.4 Mpa m3 0,200 1.016.351,00 203.270,20
Jumlah 7.272.370,03
IV PEKERJAAN ATAP -
1 Rangka Atap Sirap m2 6,000 288.093,00 1.728.558,00
2 Nok Sirap m' 6,000 157.741,00 946.446,00
3 Penutup Atap Sirap Kayu m2 6,000 241.029,00 1.446.174,00
4 Rangka plafond atap gapura m2 4,000 156.499,00 625.996,00
5 Plafond atap gapura m2 4,000 59.164,00 236.656,00
6 Lisplank m' 3,500 95.738,00 335.083,00
Jumlah 5.318.913,00
V PEKERJAAN PASANGAN -
1 Plesteran 1:3 m2 2,500 132.153,00 330.382,50
2 Acian m2 2,500 58.187,00 145.467,50
3 Pemasangan Batu Tempel m2 10,000 340.842,00 3.408.420,00
Jumlah 3.884.270,00
VI PEKERJAAN CAT DAN LABURAN -
1 Coating Batu Tempel m2 10,000 132.922,00 1.329.220,00
2 Cat Kayu Lisplank dengan politur m2 2,000 140.820,00 281.640,00
Jumlah 1.610.860,00
PEKERJAAN LAIN-LAIN -
1 Logo Kabupaten buah 1,000 2.800.000,00 2.800.000,00
Huruf Timbul Bahan Stainless, Tebal 15 cm (Huruf Selamat
2 buah 50,000 67.500,00 3.375.000,00
Datang dll)
3 Batu Grafir Motif Daun Kina m' 2,000 300.000,00 600.000,00
4 Finishing Batu Koral Sikat m2 2,500 340.842,00 852.105,00
Jumlah 7.627.105,00
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
GAPURA TIPE 2
NO URAIAN PEKERJAAN JUMLAH
I PEKERJAAN PERSIAPAN 378.582,00
II PEKERJAAN TANAH 405.763,30
III PEKERJAAN BETON 7.272.370,03
IV PEKERJAAN ATAP 5.318.913,00
V PEKERJAAN CAT DAN LABURAN 1.610.860,00
VI PEKERJAAN PASANGAN 3.884.270,00
VII PEKERJAAN LAIN-LAIN 7.627.105,00
JUMLAH (Rp) 26.497.863,33
PPN 10% 2.649.786,33
JUMLAH TOTAL (Rp) 29.147.649,66
JUMLAH DIBULATKAN (Rp) 29.147.000,00
43
ANALISIS STANDAR BELANJA (ASB)
GAPURA TIPE 3
1 KELOMPOK : Kontruksi
2 SUB KELOMPOK : Membangun Taman
3 SUB- SUB KELOMPOK : ASB GAPURA 3
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Kontruksi
6 DESKRIPSI AKTIVITAS : ASB GAPURA 3
7 SATUAN AKTIVITAS : Unit
8 KOMPONEN/RINCIAN KOMPONEN :
NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
I PEKERJAAN PERSIAPAN
1 Pembersihan lapangan dan perataan m2 0,800 25.719,00 20.575,20
2 Pengukuran dan pemasangan Bouwplank m' 4,000 81.786,00 327.144,00
Jumlah 347.719,20
II PEKERJAAN TANAH -
1 Penggalian tanah biasa sedalam 1 m (Pondasi Telapak 1x1m) m3 2,000 25.719,00 51.438,00
2 Pengurugan kembali galian tanah m3 1,600 86.899,00 139.038,40
3 Pengurugan dengan pasir urug (untuk pondasi t.5 cm) m3 0,100 268.769,00 26.876,90
Jumlah 217.353,30
III PEKERJAAN BETON -
1 Beton mutu f'c = 14.5 MPa Pondasi Telapak 0,9x0,9 m3 0,320 1.269.586,00 406.267,52
2 Besi beton pondasi telapak 0,9x0,9 kg 1,000 17.596,00 17.596,00
3 Bekisting pondasi telapak 0,9x0,9 m2 3,100 228.448,00 708.188,80
4 Beton mutu f'c = 14.5 MPa kolom 60x60 m3 0,450 1.269.586,00 571.313,70
5 Besi beton kolom 60x60 kg 10,000 17.596,00 175.960,00
6 Bekisting kolom 60x60 m2 6,000 428.677,00 2.572.062,00
7 Beton mutu f'c = 14.5 MPa ringbalk 30/60 m3 0,070 1.269.586,00 88.871,02
8 Besi beton ringbalk 30/60 kg 1,000 17.596,00 17.596,00
9 Bekisting ringbalk 30/60 m2 1,000 439.027,00 439.027,00
10 Lantai kerja beton mutu f'c = 7.4 Mpa m3 0,050 1.016.351,00 50.817,55
Jumlah 5.047.699,59
IV PEKERJAAN ATAP -
1 Rangka Atap Sirap m2 2,500 288.093,00 720.232,50
2 Nok Sirap m' 2,500 157.741,00 394.352,50
3 Penutup Atap Sirap Kayu m2 2,500 241.029,00 602.572,50
4 Rangka plafond atap gapura m2 2,000 156.499,00 312.998,00
5 Plafond atap gapura m2 2,000 59.164,00 118.328,00
6 Lisplank m' 1,500 95.738,00 143.607,00
Jumlah 2.292.090,50
V PEKERJAAN PASANGAN -
1 Plesteran 1:3 m2 1,000 132.153,00 132.153,00
2 Acian m2 1,000 58.187,00 58.187,00
3 Pemasangan Batu Tempel m2 6,000 340.842,00 2.045.052,00
Jumlah 2.235.392,00
VI PEKERJAAN CAT DAN LABURAN -
1 Coating Batu Tempel m2 6,000 132.922,00 797.532,00
2 Cat Kayu Lisplank dengan politur m2 1,000 97.325,00 97.325,00
Jumlah 894.857,00
VII PEKERJAAN LAIN-LAIN -
1 Logo Kabupaten buah 1,000 2.800.000,00 2.800.000,00
Huruf Timbul Bahan Stainless, Tebal 15 cm (Huruf Selamat
2 buah 30,000 67.500,00 2.025.000,00
Datang dll)
3 Batu Grafir Motif Daun Kina m' 2,000 300.000,00 600.000,00
4 Finishing Batu Koral Sikat m2 2,500 340.842,00 852.105,00
Jumlah 6.277.105,00
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
GAPURA TIPE 3
NO URAIAN PEKERJAAN JUMLAH
I PEKERJAAN PERSIAPAN 347.719,20
II PEKERJAAN TANAH 217.353,30
III PEKERJAAN BETON 5.047.699,59
IV PEKERJAAN ATAP 2.292.090,50
V PEKERJAAN CAT DAN LABURAN 894.857,00
VI PEKERJAAN PASANGAN 2.235.392,00
VII PEKERJAAN LAIN-LAIN 6.277.105,00
JUMLAH (Rp) 17.312.216,59
PPN 10% 1.731.221,66
JUMLAH TOTAL (Rp) 19.043.438,25
JUMLAH DIBULATKAN (Rp) 19.043.000,00
44
ANALISIS STANDAR BELANJA (ASB)
MURAL TEMATIK
1 KELOMPOK : Kontruksi
2 SUB KELOMPOK : Membangun Taman
3 SUB- SUB KELOMPOK : ASB MURAL TEMATIK
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Kontruksi
6 DESKRIPSI AKTIVITAS : ASB MURAL TEMATIK
7 SATUAN AKTIVITAS : m²
8 KOMPONEN/RINCIAN KOMPONEN :
NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
1 Pengecatan Mural m2 1,000 300.381,00 300.381,00
2 Coating Mural m2 1,000 132.922,00 132.922,00
Jumlah 433.303,00
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
MURAL TEMATIK
No PEKERJAAN JUMLAH (Rp)
1 Pengecatan Mural 300.381,00
2 Coating Mural 132.922,00
JUMLAH (Rp) 433.303,00
PPN 10% 43.330,30
JUMLAH TOTAL (Rp) 476.633,30
JUMLAH DIBULATKAN (Rp) 476.000,00
45
ANALISIS STANDAR BELANJA (ASB)
PEMBANGUNAN RUANG KELAS BARU, RUANG GURU, RUANG KEPSEK, DAN LAINNYA
1 KELOMPOK : Konstruksi
2 SUB KELOMPOK : Pembangunan Fasilitas Pendidikan
3 SUB- SUB KELOMPOK : Pembangunan Ruang Guru, Ruang Kepsek, dan lainnya
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Pembangunan Ruang Guru, Ruang Kepsek, dan lainnya
6 DESKRIPSI AKTIVITAS : Membangun Ruang Guru, Ruang Kepsek, dan lainnya
7 SATUAN AKTIVITAS : m²
8 KOMPONEN/RINCIAN KOMPONEN :
NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
A PEKERJAAN PERSIAPAN
1 Papan Nama Proyek m² 1,000 251.059,00 251.059,00
2 Pek. Bouwplank dan Pengukuran ulang m' 37,000 81.786,00 3.026.082,00
Jumlah 3.277.141,00
B PEKERJAAN TANAH -
1 Pas. urugan sirtu padat m³ 3,150 215.949,00 680.239,35
2 Galian tanah, dalam s/d 1 m m³ 13,920 119.924,00 1.669.342,08
3 Pas. Urugan Tanah m³ 4,520 86.899,00 392.783,48
Jumlah 2.742.364,91
C PEKERJAAN PONDASI -
1 Urugan pasir bawah pondasi batu kali m³ 1,160 268.769,00 311.772,04
2 Aanstamping batu kali m³ 4,640 650.982,00 3.020.556,48
3 Pas. Pondasi batu kali 1 : 5 t = 75 cm m³ 9,790 1.144.638,00 11.206.006,02
4 Pas. Pondasi batu kali 1 : 5 t = 50 cm (teras) m³ 1,240 1.144.638,00 1.419.351,12
5 Pas. Pondasi rolag bata m³ 30,650 341.403,00 10.464.001,95
Jumlah 26.421.687,61
D PEKERJAAN STRUKTUR -
D1 PEKERJAAN STRUKTUR BETON -
1 Sloof Beton 15/20 Type K1 Beton K - 175 m³ 0,870 7.374.284,00 6.415.627,08
2 Kolom Struktur 15/25 Type K1 Beton K- 175 m³ 0,400 7.581.467,00 3.032.586,80
3 Kolom Praktis 12/12 Type Kp Beton K- 175 m³ 0,550 7.581.467,00 4.169.806,85
4 Balok Lintel 12/12 Mutu Beton K - 175 m³ 0,030 8.001.566,00 240.046,98
5 Ring Balok 12/20 Mutu Beton K - 175 m³ 0,700 8.001.566,00 5.601.096,20
6 Topi Beton, t = 8 cm m³ 0,620 7.384.259,00 4.578.240,58
Jumlah 24.037.404,49
D2 PEKERJAAN STRUKTUR ATAP -
1 Pekerjaan Rangka Atap Baja Ringan m² 89,500 288.093,00 25.784.323,50
2 Pas. Penutup atap genteng Metal Berpasir m² 89,500 137.026,00 12.263.827,00
3 Pas. Nok Atap Metal Berpasir m' 35,850 122.555,00 4.393.596,75
4 Pas. Talang Jurai Zincalume m' 6,450 235.546,00 1.519.271,70
5 Pas. Talang Patah Zincalume m' 2,200 235.546,00 518.201,20
6 Pas. Capit Gunting m' 3,100 96.428,00 298.926,80
7 Pas. Ampig GRC m² 0,960 57.280,00 54.988,80
8 Pas. Listplank GRC Serat kayu m' 36,950 96.428,00 3.563.014,60
Jumlah 48.396.150,35
E PEKERJAAN ARSITEKTUR -
E1 PEKERJAAN DINDING -
1 Pasangan Bata Merah 1 : 5 m² 73,180 166.609,00 12.192.446,62
2 Plesteran Bata baru Spesi 1 : 3 m² 146,360 98.730,00 14.450.122,80
3 Acian m² 146,360 58.187,00 8.516.249,32
4 Pek. Ban + Perapihan t = 8 cm m' 8,900 98.012,00 872.306,80
5 Pas. Batu andesit/tempel (coating) m² 10,950 340.842,00 3.732.219,90
Jumlah 39.763.345,44
E2 PEKERJAAN KUSEN DAN ALAT PENGGANTUNG -
1 Pek. Kusen Allumunium warna + Pintu Type P1 "Alexindo" unit 1,000 4.170.179,00 4.170.179,00
2 Pek. Kusen Allumunium warna + Jendela Type J1 "Alexindo" unit 5,000 1.477.224,00 7.386.120,00
Jumlah 11.556.299,00
F PEKERJAAN RANGKA DAN PENUTUP PLAFOND -
1 Pas. Rangka hollow 40x40x0,5 m² 77,600 166.799,00 12.943.602,40
2 Pas. Penutup Plafond Gypsum m² 56,850 59.164,00 3.363.473,40
3 Pas. Penutup Plafond GRC m² 20,750 57.280,00 1.188.560,00
4 Pas. List Profil Gypsum m' 31,150 45.572,00 1.419.567,80
5 Pas. List Profil Kayu m' 32,250 32.900,00 1.061.025,00
Jumlah 19.976.228,60
G PEKERJAAN LANTAI -
1 Pekerjaan Urugan pasir dibawah Lantai, t = 5 cm m³ 2,980 268.769,00 800.931,62
2 Pekerjaan Lantai Keramik 40 x 40 cm,warna m² 59,690 195.001,00 11.639.609,69
3 Pekerjaan Rabat Beton + Perapihan m² 21,000 100.912,00 2.119.152,00
4 Pasangan Gravel dia.20 cm m² 36,950 252.353,00 9.324.443,35
Jumlah 23.884.136,66
46
H PEKERJAAN PENGECATAN -
1 Pengecatan dinding tembok m² 146,360 33.978,00 4.973.020,08
2 Pengecatan Plafond m² 77,600 33.978,00 2.636.692,80
3 Pengecatan Kayu (Listplang GRC ) m² 7,390 59.114,00 436.852,46
Jumlah 8.046.565,34
I PEKERJAAN MEKANIKAL/ELEKTRIKAL -
I1 PEKERJAAN INSTALASI LISTRIK -
1 Pek. Instalasi Penerangan + Fiting Downlight ttk 7,000 384.132,00 2.688.924,00
2 Pek. Instalasi Saklar/Stop Kontak ttk 7,000 514.509,00 3.601.563,00
3 Pas. Lampu PL 11 Watt bh 7,000 852.748,00 5.969.236,00
4 Pas. Sakelar Tunggal bh 1,000 104.678,00 104.678,00
5 Pas. Sakelar Ganda bh 3,000 110.486,00 331.458,00
6 Pas. Stop Kontak 1 Phasa 16 A bh 3,000 113.390,00 340.170,00
7 Pemasangan/penyambungan Sumber Listrik ss 1,000 3.273.600,00 3.273.600,00
Jumlah 16.309.629,00
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
PEMBANGUNAN RUANG GURU, RUANG KEPSEK, DAN LAINNYA
No PEKERJAAN JUMLAH (Rp)
A PEKERJAAN PERSIAPAN 3.277.141,00
B PEKERJAAN TANAH 2.742.364,91
C PEKERJAAN PONDASI 26.421.687,61
D PEKERJAAN STRUKTUR
D1 PEKERJAAN STRUKTUR BETON 24.037.404,49
D2 PEKERJAAN STRUKTUR ATAP 48.396.150,35
E PEKERJAAN ARSITEKTUR -
E1 PEKERJAAN DINDING 39.763.345,44
E2 PEKERJAAN KUSEN DAN ALAT PENGGANTUNG 11.556.299,00
F PEKERJAAN RANGKA DAN PENUTUP PLAFOND 19.976.228,60
G PEKERJAAN LANTAI 23.884.136,66
H PEKERJAAN PENGECATAN 8.046.565,34
I PEKERJAAN MEKANIKAL/ELEKTRIKAL -
I1 PEKERJAAN INSTALASI LISTRIK 16.309.629,00
JUMLAH (Rp) 224.410.952,40
JUMLAH DIBULATKAN (Rp) 224.410.000,00
PPN 10% 22.441.000,00
JUMLAH TOTAL (Rp) 246.851.000,00
LUAS BANGUNAN (m²) 81,00
ASB /m² (Rp) 3.047.543,21
DIBULATKAN (Rp) 3.047.000,00
47
ANALISIS STANDAR BELANJA (ASB)
PEMBANGUNAN PERPUSTAKAAN
1 KELOMPOK : Konstruksi
2 SUB KELOMPOK : Pembangunan Fasilitas Pendidikan
3 SUB- SUB KELOMPOK : Pembangunan Perpustakaan
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Pembangunan Perpustakaan
6 DESKRIPSI AKTIVITAS : Membangun Perpustakaan
7 SATUAN AKTIVITAS : m²
8 KOMPONEN/RINCIAN KOMPONEN :
NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
A PEKERJAAN PERSIAPAN
1 Papan Nama Proyek ls 1,000 251.059,00 251.059,00
2 Pek. Bouwplank dan Pengukuran ulang m² 37,000 81.786,00 3.026.082,00
Jumlah 3.277.141,00
B PEKERJAAN TANAH -
1 Peninggian Lantai Bangunan m³ 3,150 86.899,00 273.731,85
2 Galian Tanah pondasi Batu Kali m³ 13,920 119.924,00 1.669.342,08
3 Urugan tanah kembali m³ 4,520 52.558,00 237.562,16
Jumlah 2.180.636,09
C PEKERJAAN PONDASI -
1 Urugan pasir bawah pondasi batu kali m³ 1,160 268.769,00 311.772,04
2 Pas. Aanstamping batu kali m³ 4,640 650.982,00 3.020.556,48
3 Pas. Pondasi batu kali 1 : 5 t = 75 cm m³ 9,790 1.144.638,00 11.206.006,02
4 Pas. Pondasi batu kali 1 : 5 t = 50 cm (teras) m³ 1,240 1.144.638,00 1.419.351,12
5 Pas. Pondasi rolag bata m² 30,650 341.403,00 10.464.001,95
Jumlah 26.421.687,61
D PEKERJAAN STRUKTUR -
D1 PEKERJAAN STRUKTUR BETON -
1 Sloof Beton 15/20 Type K1 Beton K - 175 m³ 0,870 7.374.284,00 6.415.627,08
2 Kolom Struktur 15/25 Type K1 Beton K- 175 m³ 0,400 7.581.467,00 3.032.586,80
3 Kolom Praktis 12/12 Type Kp Beton K- 175 m³ 0,550 7.581.467,00 4.169.806,85
4 Balok Lintel 12/12 Mutu Beton K - 175 m³ 0,030 8.001.566,00 240.046,98
5 Ring Balok 12/20 Mutu Beton K - 175 m³ 0,700 8.001.566,00 5.601.096,20
6 Topi Beton, t = 8 cm m³ 0,620 7.384.259,00 4.578.240,58
Jumlah 24.037.404,49
D2 PEKERJAAN ATAP -
1 Pekerjaan Rangka Atap Baja Ringan m² 89,500 288.093,00 25.784.323,50
2 Pas. Penutup atap genteng Metal Berpasir m² 89,500 137.026,00 12.263.827,00
3 Pas. Nok Atap Metal Berpasir m' 35,850 122.555,00 4.393.596,75
4 Pas. Talang Jurai Zincalume m' 6,450 235.546,00 1.519.271,70
5 Pas. Talang Patah Zincalume m' 2,200 235.546,00 518.201,20
6 Pas. Capit Gunting m' 3,100 96.428,00 298.926,80
7 Pas. Ampig GRC m² 0,960 57.280,00 54.988,80
8 Pas. Listplank GRC Serat kayu m' 36,950 96.428,00 3.563.014,60
Jumlah 48.396.150,35
E PEKERJAAN ARSITEKTUR -
E1 PEKERJAAN DINDING -
1 Pasangan Bata Merah 1 : 5 m² 73,180 166.609,00 12.192.446,62
2 Plesteran Bata baru Spesi 1 : 3 m² 146,360 98.730,00 14.450.122,80
3 Acian m² 146,360 58.187,00 8.516.249,32
4 Pek. Ban + Perapihan t = 8 cm m 8,900 98.012,00 872.306,80
5 Pas. Batu andesit/tempel (coating) m² 10,950 340.842,00 3.732.219,90
Jumlah 39.763.345,44
E2 PEKERJAAN KUSEN DAN ALAT PENGGANTUNG -
1 Pek. Kusen Allumunium warna + Pintu Type P1 "Alexindo" unit 1,000 4.170.179,00 4.170.179,00
2 Pek. Kusen Allumunium warna + Jendela Type J1 "Alexindo" unit 5,000 1.477.224,00 7.386.120,00
Jumlah 11.556.299,00
F PEKERJAAN PLAFON -
1 Pas. Rangka hollow m² 77,600 179.081,00 13.896.685,60
2 Pas. Penutup Plafond Gypsum m² 56,850 57.280,00 3.256.368,00
3 Pas. Penutup Plafond GRC m² 20,750 57.280,00 1.188.560,00
4 Pas. List Profil Gypsum m 31,150 52.466,00 1.634.315,90
5 Pas. List Profil Kayu m 32,250 32.900,00 1.061.025,00
Jumlah 21.036.954,50
G PEKERJAAN LANTAI -
1 Pekerjaan Urugan pasir dibawah Lantai, t = 5 cm m³ 2,980 268.769,00 800.931,62
2 Pekerjaan Lantai Keramik 40 x 40 cm,warna m² 59,690 195.001,00 11.639.609,69
3 Pekerjaan Rabat Beton + Perapihan m² 21,000 100.912,00 2.119.152,00
4 Pasangan Gravel dia.20 cm m² 36,950 252.353,00 9.324.443,35
Jumlah 23.884.136,66
48
H PEKERJAAN PENGECATAN -
1 Pengecatan dinding tembok unit 146,360 33.978,00 4.973.020,08
2 Pengecatan Plafond unit 77,600 33.978,00 2.636.692,80
3 Pengecatan Kayu (Listplang GRC ) unit 7,390 33.978,00 251.097,42
Jumlah 7.860.810,30
I PEKERJAAN MEKANIKAL/ELEKTRIKAL -
I1 PEKERJAAN INSTALASI LISTRIK -
1 Pek. Instalasi Penerangan + Fiting Downlight ttk 7,000 384.132,00 2.688.924,00
2 Pek. Instalasi Saklar/Stop Kontak ttk 7,000 113.390,00 793.730,00
3 Pas. Lampu PL 11 Watt bh 7,000 852.748,00 5.969.236,00
4 Pas. Sakelar Tunggal bh 1,000 104.678,00 104.678,00
5 Pas. Sakelar Ganda bh 3,000 110.486,00 331.458,00
6 Pas. Stop Kontak 1 Phasa 16 A bh 3,000 113.390,00 340.170,00
7 Pemasangan/penyambungan Sumber Listrik ls 1,000 3.273.600,00 3.273.600,00
Jumlah 13.501.796,00
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
PEMBANGUNAN PERPUSTAKAAN
No PEKERJAAN JUMLAH (Rp)
A PEKERJAAN PERSIAPAN 3.277.141,00
B PEKERJAAN TANAH 2.180.636,09
C PEKERJAAN PONDASI 26.421.687,61
D PEKERJAAN STRUKTUR -
D.1 PEKERJAAN STRUKTUR BETON 24.037.404,49
D.2 PEKERJAAN ATAP 48.396.150,35
E PEKERJAAN ARSITEKTUR -
E.1 PEKERJAAN DINDING 39.763.345,44
E.2 PEKERJAAN KUSEN DAN ALAT PENGGANTUNG 11.556.299,00
F PEKERJAAN PLAFON 21.036.954,50
G PEKERJAAN LANTAI 23.884.136,66
H PEKERJAAN PENGECATAN 7.860.810,30
I PEKERJAAN MEKANIKAL/ELEKTRIKAL -
I.1 PEKERJAAN INSTALASI LISTRIK 13.501.796,00
JUMLAH (Rp) 221.916.361,44
JUMLAH DIBULATKAN (Rp) 221.916.000,00
PPN 10% 22.191.600,00
JUMLAH TOTAL (Rp) 244.107.600,00
LUAS BANGUNAN (m²) 56,00
HARGA BANGUNAN/m² (Rp) 4.359.064,29
DIBULATKAN (Rp) 4.359.000,00
49
ANALISIS STANDAR BELANJA (ASB)
PEMBANGUNAN RUANG KELAS BERTINGKAT
1 KELOMPOK : Konstruksi
2 SUB KELOMPOK : Pembangunan Fasilitas Pendidikan
3 SUB- SUB KELOMPOK : Pembangunan Ruang Kelas SD Bertingkat
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Pembangunan Ruang Kelas SD Bertingkat
6 DESKRIPSI AKTIVITAS : Membangun Ruang Kelas SD Bertingkat
7 SATUAN AKTIVITAS : m²
8 KOMPONEN/RINCIAN KOMPONEN :
NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
PEKERJAAN LANTAI 1
A PEKERJAAN PERSIAPAN
1 Pengukuran kembali site & Pas. Bouwplank m 34,000 81.786,00 2.780.724,00
2 Papan Nama Proyek ls 1,000 251.059,00 251.059,00
4 Bongkaran ls 1,000 4.000.000,00 4.000.000,00
Jumlah 7.031.783,00
B PEKERJAAN TANAH DAN PONDASI -
1 Galian Tanah Pondasi m³ 8,400 119.924,00 1.007.361,60
2 Urugan Tanah kembali bekas galian m³ 8,400 52.558,00 441.487,20
3 Urugan pasir bawah Pondasi m³ 0,350 268.769,00 94.069,15
4 Pas. Pondasi Poer Beton bertulang , K - 225 m³ 1,400 5.535.109,00 7.749.152,60
Jumlah 9.292.070,55
C PEKERJAAN BETON -
C1 PEKERJAAN BETON LANTAI 1 -
1 Pas. Kolom K1 / KP dan Balok Lintel, K-225 m³ 1,620 7.581.467,00 12.281.976,54
2 Pas. Balok B1 Ukuran 25 / 35 cm, K-225 m³ 4,670 8.001.566,00 37.367.313,22
3 Pas. Balok B2 Ukuran 20 / 25 cm, K-225 m³ 1,130 8.001.566,00 9.041.769,58
Jumlah 58.691.059,34
C2 PEKERJAAN BETON LANTAI 2 -
1 Pas. Plat Lantai beton, t = 12 cm ( dia 10 - 12.5 ), K - 225 m³ 8,280 7.384.259,00 61.141.664,52
Pas. Kolom K2 / KP Ukuran 15/15cm m³ 0,570 7.581.467,00 4.321.436,19
2 Pas. RingBalk RB1 Ukuran 15/15cm m³ 0,670 8.001.566,00 5.361.049,22
3 Pas. Balok Lintel Ukuran 15/15cm m³ 0,170 8.001.566,00 1.360.266,22
Jumlah 72.184.416,15
D PEKERJAAN DINDING -
D1 PEKERJAAN DINDING LANTAI 1 -
1 Pas. Bata merah tebal 1/2 bata 1Pc : 5 Ps m² 16,280 166.609,00 2.712.394,52
2 Pas. Bata merah tebal 1/2 bata 1Pc : 5 Ps m² 9,000 166.609,00 1.499.481,00
3 Pek. Plesteran + Acian Dinding 1 Pc : 5 Ps m² 25,280 95.270,00 2.408.425,60
Jumlah 6.620.301,12
D2 PEKERJAAN DINDING LANTAI 2 -
1 Pas. Bata merah tebal 1/2 bata 1Pc : 5 Ps m² 107,070 166.609,00 17.838.825,63
3 Pek. Plesteran + Acian Dinding 1 Pc : 5 Ps m² 107,070 95.270,00 10.200.558,90
Jumlah 28.039.384,53
E PEKERJAAN PENGECATAN -
E1 PEKERJAAN PENGECATAN LANTAI 1 -
1 Pelaburan bidang tembok m² 25,280 33.978,00 858.963,84
2 Pelaburan balok m² 32,040 33.978,00 1.088.655,12
Jumlah 1.947.618,96
E2 PEKERJAAN PENGECATAN LANTAI 2 -
1 Pelaburan bidang tembok m² 107,070 33.978,00 3.638.024,46
2 Pelaburan balok m² 105,300 33.978,00 3.577.883,40
Jumlah 7.215.907,86
F PEKERJAAN LANTAI -
F1 PEKERJAAN LANTAI, LANTAI 1 -
1 Urugan pasir bawah Lantai t = 5cm m³ 3,250 268.769,00 873.499,25
2 Pas. Lantai Keramik Uk. 30/30 m² 4,480 189.964,00 851.038,72
Jumlah 1.724.537,97
F2 PEKERJAAN LANTAI, LANTAI 2 -
1 Urugan pasir bawah Lantai t = 5cm m³ 3,250 268.769,00 873.499,25
2 Pas. Lantai Keramik Uk. 30/30 m² 22,360 189.964,00 4.247.595,04
3 Pas. Lantai Keramik Uk. 30/30 m² 64,000 189.964,00 12.157.696,00
Jumlah 17.278.790,29
G PEKERJAAN KUSEN DAN JENDELA -
1 Pintu Type PJ1 unit 1,000 8.203.229,00 8.203.229,00
2 Jendela Type J1 unit 2,000 1.477.224,00 2.954.448,00
3 Bouvenlight Type BV1 unit 3,000 941.554,00 2.824.662,00
4 Bouvenlight Type BV2 unit 2,000 1.554.101,00 3.108.202,00
Jumlah 17.090.541,00
H PEKERJAAN ATAP -
1 Pas. Rangka Atap Baja Ringan m² 135,650 288.093,00 39.079.815,45
2 Pas. Atap Genteng Palentong m² 135,650 241.029,00 32.695.583,85
3 Pas. Bubung atap m 9,700 157.741,00 1.530.087,70
4 Pas. Lisplank GRC 8 mm / 20 cm m 30,900 96.428,00 2.979.625,20
Jumlah 76.285.112,20
I PEKERJAAN PLAFON -
50
1 Pas. Rangka langit-langit jarak 60/60 m² 105,300 167.628,00 17.651.228,40
2 Pas. Langit-langit GRC 4 mm m² 52,000 57.280,00 2.978.560,00
3 Pas. Langit-langit Gypsump 9 mm m² 64,000 59.164,00 3.786.496,00
Jumlah 24.416.284,40
J PEKERJAAN INSTALASI LISTRIK -
1 Instalasi titik penerangan NYM 2x2,5 mm ttk 5,000 437.032,00 2.185.160,00
2 Instalasi Stop Kontak NYM 2 x 2,5 ttk 3,000 514.509,00 1.543.527,00
3 TL 2 x 18 Watt, Recessed Mounting Alumunium Grille bh 4,000 357.293,00 1.429.172,00
4 Out Bow Light 13 Watt bh 1,000 165.140,00 165.140,00
5 Saklar Tunggal bh 1,000 104.678,00 104.678,00
6 Saklar Ganda bh 1,000 110.486,00 110.486,00
7 Stop Kontak Dinding bh 1,000 113.390,00 113.390,00
8 MCB + Box ls 1,000 240.000,00 240.000,00
Jumlah 5.891.553,00
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
PEMBANGUNAN RUANG KELAS BERTINGKAT
No PEKERJAAN JUMLAH (Rp)
A PEKERJAAN PERSIAPAN 7.031.783,00
B PEKERJAAN TANAH DAN PONDASI 9.292.070,55
C.1 PEKERJAAN BETON LANTAI 1 58.691.059,34
C.2 PEKERJAAN BETON LANTAI 2 72.184.416,15
D.1 PEKERJAAN DINDING LANTAI 1 6.620.301,12
D.2 PEKERJAAN DINDING LANTAI 2 28.039.384,53
E.1 PEKERJAAN PENGECATAN LANTAI 1 1.947.618,96
E.2 PEKERJAAN PENGECATAN LANTAI 2 7.215.907,86
F.1 PEKERJAAN LANTAI, LANTAI 1 1.724.537,97
F.2 PEKERJAAN LANTAI, LANTAI 2 17.278.790,29
G PEKERJAAN KUSEN DAN JENDELA 17.090.541,00
H PEKERJAAN ATAP 76.285.112,20
I PEKERJAAN PLAFON 24.416.284,40
J PEKERJAAN INSTALASI LISTRIK 5.891.553,00
JUMLAH (Rp) 333.709.360,37
JUMLAH DIBULATKAN (Rp) 333.709.000,00
PPN 10% 33.370.900,00
JUMLAH TOTAL (Rp) 367.079.900,00
LUAS BANGUNAN (m²) 65,77
HARGA BANGUNAN/m² (Rp) 5.581.266,53
DIBULATKAN (Rp) 5.581.000,00
51
ANALISIS STANDAR BELANJA (ASB)
PEMBANGUNAN SARANA AIR BERSIH DAN SANITASI
1 KELOMPOK : Konstruksi
2 SUB KELOMPOK : Pembangunan Fasilitas Pendidikan
3 SUB- SUB KELOMPOK : Pembangunan Sarana Air Bersih dan Sanitasi
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Pembangunan dan Pemasangan Sarana Air Bersih dan Sanitasi
6 DESKRIPSI AKTIVITAS : Membangun dan Memasang Sarana Air Bersih dan Sanitasi
7 SATUAN AKTIVITAS : m²
8 KOMPONEN/RINCIAN KOMPONEN
NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
A PEKERJAAN PERSIAPAN
1 Pek. Pemasangan Papan Nama Proyek bh 1,000 251.059,00 251.059,00
Jumlah 251.059,00
B PEKERJAAN TANAH -
1 Pek. Galian Tanah Pondasi m³ 4,490 119.924,00 538.458,76
2 Pek. Urugan Tanah Kembali pada Pondasi m³ 4,490 52.558,00 235.985,42
3 Pek. Urugan Pasir dibawah Pondasi m³ 0,350 268.769,00 94.069,15
4 Pas. Pondasi Batu Kali 1PC : 4PS m³ 2,160 1.182.760,00 2.554.761,60
Jumlah 3.423.274,93
C PEKERJAAN BETON -
1 Pas. Sloof Type SL Ukuran 15 /20, K - 175 m³ 0,350 7.374.284,00 2.580.999,40
2 Pas. Kolom KP dan Balok Lintel, K - 175 m³ 0,510 7.581.467,00 3.866.548,17
3 Pas. Ring Balk Ukuran 15 / 15 cm, K-175 m³ 0,260 8.001.566,00 2.080.407,16
4 Pas. Plat Beton Penutup Saluran t = 12 cm, K - 175 m³ 0,480 7.384.259,00 3.544.444,32
5 Pas. Rabat Beton ( Ramp Akses Masuk ) m³ 0,200 1.078.544,00 215.708,80
Jumlah 12.288.107,85
D PEKERJAAN DINDING -
1 Pas. Bata merah tebal 1/2 bata 1Pc : 5 Ps m² 15,540 166.609,00 2.589.103,86
2 Pas. Bata merah Trasraam tebal 1/2 bata 1Pc : 3 Ps m² 13,580 172.992,00 2.349.231,36
3 Pek. Plesteran + Acian Dinding 1 Pc : 5 Ps m² 31,080 95.270,00 2.960.991,60
4 Pek. Plesteran + Acian Dinding Trasraam 1 Pc : 3 Ps m² 12,000 98.730,00 1.184.760,00
5 Pas. Dinding Keramik UK. 20 x 25 m² 15,150 325.583,00 4.932.582,45
6 Pas. Dinding Keramik UK. 20 x 25 m² 3,390 325.583,00 1.103.726,37
Jumlah 15.120.395,64
E PEKERJAAN LANTAI -
1 Urugan pasir bawah Lantai t = 5cm m² 0,220 268.769,00 59.129,18
2 Pas. Lantai Keramik Uk. 30/30 m² 2,920 189.964,00 554.694,88
3 Pas. Ubin Pengarah Uk. 30/30 m² 14,000 189.964,00 2.659.496,00
4 Pas. Lantai Keramik Uk. 30/30 m² 4,320 250.339,00 1.081.464,48
Jumlah 4.354.784,54
F PEKERJAAN KUSEN, PINTU DAN JENDELA -
1 Pintu Type P1 Kusen Kayu 5/15 Kelas II unit 2,000 1.701.689,00 3.403.378,00
2 Bouvenlight Type BV1 Kusen Kayu 5/15 Kelas II unit 2,000 131.666,00 263.332,00
Jumlah 3.666.710,00
G PEKERJAAN PLAFOND -
1 Pas. Rangka langit-langit Jarak 60cm x 60cm m² 16,920 167.628,00 2.836.265,76
2 Pas. Langit-langit GRC 4 mm (Area Dalam) m² 4,320 57.280,00 247.449,60
3 Pas. Langit-langit GRC 4 mm (Area tritisan) m² 12,600 57.280,00 721.728,00
Jumlah 3.805.443,36
H PEKERJAAN ATAP -
1 Pas. Rangka Atap Baja Ringan m² 14,230 288.093,00 4.099.563,39
2 Pas. Atap Genteng Metal Pasir m² 12,320 137.026,00 1.688.160,32
3 Pas. Bubung Atap Sekelas Sakura Roof m 4,650 122.555,00 569.880,75
4 Pas. Lisplank GRC 8 mm / 20 cm m 14,300 96.428,00 1.378.920,40
5 Pas. Talang Seng BJLS 30 cm m 5,110 235.546,00 1.203.640,06
Jumlah 8.940.164,92
I PEKERJAAN SANITASI -
1 Pas. Closet Jongkok Sekelas Toto unit 1,000 1.259.581,00 1.259.581,00
2 Pas. Closet Duduk Sekelas Toto unit 1,000 4.853.888,00 4.853.888,00
3 Pas. Wastafel Sekelas Toto unit 1,000 2.717.432,00 2.717.432,00
4 Pas. Keran 1/2" Sekelas Onda unit 2,000 326.886,00 653.772,00
5 Pas. Floor Drain Sekelas Onda unit 2,000 277.964,00 555.928,00
Jumlah 10.040.601,00
J PEKERJAAN PENGECATAN -
1 Pelaburan bidang tembok Sekelas Sanlex m² 27,540 42.948,00 1.182.787,92
2 Pelaburan langit-langit Sekelas Sanlex m² 16,920 42.948,00 726.680,16
Jumlah 1.909.468,08
K PEKERJAAN MEKANIKAL ELEKTRIKAL -
K1 PEKERJAAN INSTALASI AIR BERSIH -
1 Pipa PVC dia 15 (1/2"), Sekelas Maspion m 10,000 24.351,00 243.510,00
2 Toren Air 500 liter unit 1,000 1.085.500,00 1.085.500,00
3 Menara Toren T = 3 meter + Alas Pondasi unit 1,000 3.170.198,00 3.170.198,00
4 Pek. Sumur Bor ls 1,000 7.389.631,00 7.389.631,00
Jumlah 11.888.839,00
52
K2 PEKERJAAN INSTALASI AIR KOTOR -
1 Pipa PVC AW (4") Sekelas Maspion m 10,000 120.248,00 1.202.480,00
2 Pipa PVC Klas AW (3") Sekelas Maspion m 10,000 91.728,00 917.280,00
Jumlah 2.119.760,00
K3 PEKERJAAN INSTALASI LISTRIK -
1 Instalasi titik penerangan NYM 2x2,5 mm ttk 3,000 437.032,00 1.311.096,00
2 Out Bow Light 13 Watt bh 3,000 40.204,00 120.612,00
3 Saklar Tunggal bh 1,000 104.678,00 104.678,00
4 Saklar Ganda bh 1,000 110.486,00 110.486,00
Jumlah 1.646.872,00
L PEKERJAAN SEPTICTANK -
1 Pek. Galian Tanah m³ 3,380 119.924,00 405.343,12
2 Pas. Pasir Urug T = 5 cm m³ 0,050 268.769,00 13.438,45
3 Pas. Bata merah Trasraam tebal 1/2 bata 1Pc : 3 Ps m² 12,140 172.992,00 2.100.122,88
4 Pas. Plat Beton Penutup m³ 0,300 1.016.351,00 304.905,30
5 Lantai Kerja m³ 0,150 1.016.351,00 152.452,65
6 Pek. Galian Tanah Rembesan Kapasitas 1 m3 m³ 1,000 119.924,00 119.924,00
7 Pas. Ijuk kg 5,000 64.433,00 322.165,00
8 Pas. Urugan Kerikil 3/5 cm m³ 0,050 215.949,00 10.797,45
Jumlah 3.429.148,85
M PEKERJAAN LAIN - LAIN -
1 Pek. Pembuatan Plakat bh 1,000 600.000,00 600.000,00
2 Pek. Hand Railing m 4,500 37.900,00 170.550,00
3 Pek. Tempat Sampah 3 Warna bh 1,000 985.000,00 985.000,00
4 Pek. Rambu Pengarah Jalur Keluar bh 1,000 150.000,00 150.000,00
5 Pek. Rambu Pengarah Jalur Evakuasi bh 1,000 150.000,00 150.000,00
6 Pek. Rambu Pengarah Titik Kumpul bh 1,000 265.000,00 265.000,00
Jumlah 2.320.550,00
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
PEMBANGUNAN SARANA AIR BERSIH DAN SANITASI
No PEKERJAAN JUMLAH (Rp)
A PEKERJAAN PERSIAPAN 251.059,00
B PEKERJAAN TANAH 3.423.274,93
C PEKERJAAN BETON 12.288.107,85
D PEKERJAAN DINDING 15.120.395,64
E PEKERJAAN LANTAI 4.354.784,54
F PEKERJAAN KUSEN, PINTU DAN JENDELA 3.666.710,00
G PEKERJAAN PLAFOND 3.805.443,36
H PEKERJAAN ATAP 8.940.164,92
I PEKERJAAN SANITASI 10.040.601,00
J PEKERJAAN PENGECATAN 1.909.468,08
K PEKERJAAN MEKANIKAL ELEKTRIKAL -
K.1 PEKERJAAN INSTALASI AIR BERSIH 11.888.839,00
K.2 PEKERJAAN INSTALASI AIR KOTOR 2.119.760,00
K.3 PEKERJAAN INSTALASI LISTRIK 1.646.872,00
L PEKERJAAN SEPTICTANK 3.429.148,85
M PEKERJAAN LAIN - LAIN 2.320.550,00
JUMLAH (Rp) 85.205.179,17
JUMLAH DIBULATKAN (Rp) 85.205.000,00
PPN 10% 8.520.500,00
JUMLAH TOTAL (Rp) 93.725.500,00
LUAS BANGUNAN (m²) 28,00
HARGA BANGUNAN/m² (Rp) 3.347.339,29
DIBULATKAN (Rp) 3.347.000,00
53
ANALISIS STANDAR BELANJA (ASB)
GEDUNG NEGARA TIDAK SEDERHANA
1 KELOMPOK : Konstruksi
2 SUB KELOMPOK : Pembangunan Gedung Negara
3 SUB- SUB KELOMPOK : Pembangunan Gedung Negara Tidak Sederhana
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Pembangunan Seluruh Komponen Gedung Negara Tidak Sederhana
6 DESKRIPSI AKTIVITAS : Membangun Seluruh Komponen Gedung Negara Tidak Sederhana
7 SATUAN AKTIVITAS : m2
8 KOMPONEN/RINCIAN KOMPONEN :
A PEKERJAAN STRUKTUR
A1 PEKERJAAN PONDASI
1 Pas. urugan tanah m³ 824,72 86.899,00 71.666.908,79
2 Galian tanah, dalam s/d 1 m m³ 58,72 119.924,00 7.042.225,10
3 Pas. Urugan Pasir m³ 11,81 268.769,00 3.175.425,10
4 Aanstamping batu kali m³ 96,90 650.982,00 63.080.155,80
5 Pas. pondasi batu kali 1:4 m³ 14,14 1.182.760,00 16.728.366,06
6 Pas. Lantai kerja beton tumbuk 1:3:5 m² 5,91 100.912,00 596.127,55
7 Bekisting sloof beton m² 66,00 238.798,00 15.760.668,00
8 Tulangan besi beton U-39 kg 1856,61 17.596,00 32.668.909,56
9 Tulangan besi beton U-39 kg 755,47 17.596,00 13.293.206,13
10 Tulangan besi beton U-24 kg 135,52 17.596,00 2.384.609,92
11 Beton K-225 m³ 39,46 1.320.118,00 52.086.575,81
12 Bekisting sloof beton m² 118,30 238.798,00 28.249.803,40
13 Tulangan besi beton U-39 kg 1832,21 17.596,00 32.239.531,97
14 Tulangan besi beton U-24 kg 826,06 17.596,00 14.535.281,38
15 Beton K-225 m³ 21,13 1.320.118,00 27.887.492,75
Jumlah 381.395.287,31
A2 PEKERJAAN BETON STRUKTUR
A2 1 LANTAI DASAR
Pekerjaan Kolom
1 Bekisting kolom beton m² 133,2 428.677,00 57.099.776,40
2 Tulangan besi beton U-40 kg 1121,76 17.596,00 19.738.488,96
3 Tulangan besi beton U-40 kg 153,56 17.596,00 2.702.041,76
4 Tulangan besi beton U-24 kg 591,85 17.596,00 10.414.192,60
5 Beton K-225 m³ 10,37 1.320.118,00 13.689.623,66
Jumlah 103.644.123,38
Pekerjaan Balok Bordes
1 Bekisting balok beton m² 3,9 439.027,00 1.712.205,30
2 Tulangan besi beton U-40 kg 11,9 17.596,00 209.392,40
3 Tulangan besi beton U-24 kg 18,48 17.596,00 325.174,08
4 Beton K-225 m³ 0,36 1.320.118,00 475.242,48
Jumlah 2.722.014,26
Pekerjaan Tangga
1 Bekisting tangga m² 24,16 406.683,00 9.825.461,28
2 Tulangan besi beton U-40 kg 202,67 17.596,00 3.566.181,32
3 Tulangan besi beton U-24 kg 186,14 17.596,00 3.275.319,44
4 Beton K-225 m³ 3,86 1.320.118,00 5.095.655,48
Jumlah 21.762.617,52
Pekerjaan Balok
1 Bekisting balok beton m² 198,49 439.027,00 87.142.469,23
2 Tulangan besi beton U-39 kg 259,56 17.596,00 4.567.217,76
3 Tulangan besi beton U-39 kg 2604,1 17.596,00 45.821.743,60
4 Tulangan besi beton U-39 kg 101,66 17.596,00 1.788.809,36
5 Tulangan besi beton U-24 kg 1050,53 17.596,00 18.485.125,88
6 Beton K-225 m³ 26,4 1.320.118,00 34.851.115,20
Jumlah 192.656.481,03
Pekerjaan Plat Lantai
1 Bekisting plat beton m² 14,1 491.697,00 6.932.927,70
2 Tulangan besi beton U-39 kg 9334,12 17.596,00 164.243.175,52
3 Beton K-225 m³ 62,96 1.320.118,00 83.114.629,28
Jumlah 254.290.732,50
A2 2 LANTAI ATAS
Pekerjaan Kolom
1 Bekisting kolom beton m² 131,6 428.677,00 56.413.893,20
2 Tulangan besi beton U-39 kg 942,28 17.596,00 16.580.358,88
3 Tulangan besi beton U-39 kg 144,83 17.596,00 2.548.428,68
4 Tulangan besi beton U-24 kg 678,96 17.596,00 11.946.980,16
5 Beton K-225 m³ 11,2 1.320.118,00 14.785.321,60
Jumlah 102.274.982,52
Page 54
Pekerjaan Ringbalk
1 Bekisting Ring balok beton m² 148,36 439.027,00 65.135.143,29
2 Tulangan besi beton U-39 kg 1101,19 17.596,00 19.376.539,24
3 Tulangan besi beton U-39 kg 257,52 17.596,00 4.531.321,92
4 Tulangan besi beton U-24 kg 665,28 17.596,00 11.706.266,88
5 Beton K-225 m³ 11,81 1.320.118,00 15.590.593,58
Jumlah 116.339.864,91
Pekerjaan Pelat Lantai
1 Bekisting pelat Lantai beton m² 344 491.697,00 169.143.768,00
2 Tulangan besi beton U-24 kg 4666,41 17.596,00 82.110.150,36
3 Beton K-225 m³ 51,85 1.320.118,00 68.448.118,30
Jumlah 319.702.036,66
B PEKERJAAN ARSITEKTUR
B1 PEKERJAAN LANTAI
B1 1 PEKERJAAN LANTAI, LANTAI DASAR
1 Pas. Urugan pasir m³ 43,88 268.769,00 11.793.583,72
2 Pas. Lantai kerja beton tumbuk 1:3:5 m² 21,94 100.912,00 2.214.009,28
3 Pas. Lantai ubin marmer 600x600 m² 17 615.004,00 10.455.068,00
4 Pas. Lantai ubin marmer 600x600 m² 470,71 615.004,00 289.488.532,84
5 Pas. Lantai ubin marmer 600x600 m² 26,61 615.004,00 16.365.256,44
Jumlah 330.316.450,28
B1 2 PEKERJAAN LANTAI, LANTAI ATAS
1 Pas. Lantai ubin marmer 600x600 m³ 18,45 615.004,00 11.346.823,80
2 Pas. Lantai ubin marmer 600x600 m³ 350,55 615.004,00 215.589.652,20
3 Pas. Lantai plint granit tile 100x600 m² 272,1 83.815,00 22.806.061,50
Jumlah 249.742.537,50
B2 PEKERJAAN DINDING
B2 1 PEKERJAAN DINDING; LANTAI DASAR
1 Pas. Dinding batu bata ringan m² 34,95 186.303,00 6.511.289,85
2 Pas. Dinding batu bata ringan m² 455,44 186.303,00 84.849.838,32
3 Pas. plester aci; ad. 1:4 m² 63,72 96.456,00 6.146.176,32
4 Pas. plester aci; ad. 1:4 m² 870,37 96.456,00 83.952.408,72
5 Pas. Dinding keramik 300x300 m² 16 250.339,00 4.005.424,00
6 Pas. Dinding granit tile 400x400 m² 50,1 364.051,00 18.238.955,10
7 Pas. Dinding partisi gypsumboard Rangka Kayu m² 66 605.858,00 39.986.628,00
Jumlah 243.690.720,31
B2 2 PEKERJAAN DINDING; LANTAI ATAS
1 Pas. Dinding batu bata, ad. 1:2 m² 49,84 180.054,00 8.973.891,36
2 Pas. Dinding batu bata, ad. 1:4 m² 666,12 169.068,00 112.619.576,16
3 Pas. plester aci; ad. 1:4 m² 61,37 96.456,00 5.919.504,72
4 Pas. plester aci; ad. 1:4 m² 1246,55 96.456,00 120.237.226,80
5 Pas. Dinding keramik 300x300 m² 29 250.339,00 7.259.831,00
6 Pas. Dinding granit tile 400x400 m² 56,7 365.051,00 20.698.391,70
7 Pas. Dinding partisi gypsumboard Rangka Kayu m² 62,9 605.858,00 38.108.468,20
Jumlah 313.816.889,94
B3 PEKERJAAN PLAFON
B3 1 PEKERJAAN PLAFON; LANTAI DASAR
1 Pas. Rangka Plafon Metal furing m² 342,9 156.499,00 53.663.507,10
2 Pas. Penutup plafon Gypsumboard t.9 mm m² 342,9 59.164,00 20.287.335,60
Jumlah 73.950.842,70
B3 2 PEKERJAAN PLAFON; LANTAI ATAS
1 Pas. Rangka Plafon Metal furing m² 489 156.499,00 76.528.011,00
2 Pas. Penutup plafon Gypsumboard t.9 mm m² 489 59.164,00 28.931.196,00
Jumlah 105.459.207,00
B4 PEKERJAAN ATAP
1 Rangka atap baja ringan m² 606,98 288.093,00 174.866.689,14
2 Penutup atap Genteng Keramik Glazur m² 606,98 260.916,00 158.370.793,68
3 Bubungan Genteng Keramik Glazur m 112 174.715,00 19.568.080,00
4 Pas. Lisplank Kayu 3/20 mm m 123,5 200.913,00 24.812.755,50
5 Pas. Talang seng plat m 46 235.546,00 10.835.116,00
Jumlah 388.453.434,32
B5 PEKERJAAN KUSEN
B5 1 PEKERJAAN KUSEN LANTAI DASAR
1 Kusen pintu P1 A unit 9 4.170.179,00 37.531.611,00
2 Kusen pintu P1 B unit 6 878.074,00 5.268.444,00
3 Kusen pintu P2 A unit 2 4.738.394,00 9.476.788,00
4 Kusen Pintu PJ1 unit 1 8.203.229,00 8.203.229,00
5 Kusen pintu Jendela J1 A unit 8 1.477.224,00 11.817.792,00
6 Kusen pintu jendela J2 A unit 10 3.768.081,00 37.680.810,00
7 Kusen pintu jendela J3 A unit 4 5.494.979,00 21.979.916,00
8 Kusen pintu jendela J4 A unit 2 3.510.280,00 7.020.560,00
9 Kusen pintu jendela J5 A unit 1 10.525.136,00 10.525.136,00
Jumlah 149.504.286,00
Page 55
B5 2 PEKERJAAN KUSEN LANTAI ATAS
1 Kusen pintu P1 A unit 9 4.170.179,00 37.531.611,00
2 Kusen pintu P1 B unit 4 878.074,00 3.512.296,00
3 Kusen pintu P2 A unit 1 4.738.394,00 4.738.394,00
4 Kusen pintu Jendela J1 A unit 6 1.477.224,00 8.863.344,00
5 Kusen pintu Jendela J1 C unit 2 1.996.046,00 3.992.092,00
6 Kusen pintu jendela J2 A unit 12 3.768.081,00 45.216.972,00
7 Kusen pintu jendela J3 A unit 2 5.494.979,00 10.989.958,00
8 Kusen pintu jendela J4 A unit 2 3.510.280,00 7.020.560,00
9 Kusen pintu jendela J5 A unit 2 10.525.136,00 21.050.272,00
Jumlah 142.915.499,00
C PEKERJAAN UTILITAS
C1 PEKERJAAN PLUMBING
C1 1 PEKERJAAN SANITARY LANTAI DASAR
1 Pas. Kloset duduk keramik unit 4 4.853.888,00 19.415.552,00
2 Pas. Urinoir keramik unit 2 4.273.382,00 8.546.764,00
3 Pas. Floor drain bh 7 277.964,00 1.945.748,00
4 Pas. Kran dinding bh 4 543.086,00 2.172.344,00
5 Pas. Meja Pantry uk. 600x 1500 mm bh 1 2.065.172,00 2.065.172,00
Jumlah 34.145.580,00
C1 2 PEKERJAAN SANITARY LANTAI DASAR
1 Pas. Kloset duduk keramik unit 2 4.853.888,00 9.707.776,00
2 Pas. Urinoir keramik unit 2 4.273.382,00 8.546.764,00
3 Pas. Floor drain bh 6 277.964,00 1.667.784,00
4 Pas. Kran dinding bh 10 543.086,00 5.430.860,00
Jumlah 25.353.184,00
C1 3 PEKERJAAN SUMUR DALAM
1 Pengeboran sumur m 36 386.939,00 13.929.804,00
2 Pipa PVC dia. 3" m 28 91.728,00 2.568.384,00
3 Pipa PVC dia. 2" m 8 48.759,00 390.072,00
4 Pipa PVC dia. 3/4" m 64 26.802,00 1.715.328,00
5 Klep diameter 3/4" bh 1 40.000,00 40.000,00
6 Stop kran dia. 1" bh 1 174.000,00 174.000,00
7 Mesin Jet Pump kap.250 watt bh 1 4.000.000,00 4.000.000,00
Jumlah 22.817.588,00
C1 4 TANGKI AIR
1 Pipa PVC dia. 1" m 12 30.233,00 362.796,00
2 Pipa PVC dia. 1" m 8 30.233,00 241.864,00
3 Pipa PVC dia. 3/4" m 4 26.802,00 107.208,00
4 Tangki air 500 liter bh 1 1.085.500,00 1.085.500,00
5 Dudukan tangki air bh 1 3.170.198,00 3.170.198,00
6 Stop kran dia. 1" bh 4 174.000,00 696.000,00
Jumlah 5.663.566,00
C1 5 PEKERJAAN RESERVOIR
1 Galian tanah, dalam s/d 1 m m³ 5,63 119.924,00 675.172,12
2 Pas. Urugan pasir m³ 0,12 268.769,00 32.252,28
3 Pas. Lantai kerja beton tumbuk 1:3:5 m² 3,75 100.912,00 378.420,00
4 Bekisting plat beton m² 21 491.697,00 10.325.637,00
5 Tulangan besi beton U-24 kg 315 17.596,00 5.542.740,00
6 Beton K-200 m³ 2,1 1.302.437,00 2.735.117,70
Jumlah 19.689.339,10
C1 6 INSTALASI AIR BERSIH LANTAI DASAR
1 Pipa PVC dia. 2" m 45 48.759,00 2.194.155,00
2 Pipa PVC dia. 1" m 37 30.233,00 1.118.621,00
3 Pipa PVC dia. 3/4" m 10 26.802,00 268.020,00
Jumlah 3.580.796,00
C1 7 INSTALASI AIR KOTOR & AIR BEKAS LANTAI DASAR
1 Pipa PVC dia. 3" m 6 91.728,00 550.368,00
2 Pipa PVC dia. 4" air mandi m 12 120.248,00 1.442.976,00
3 Pipa PVC dia. 3" m 48 91.728,00 4.402.944,00
4 Pipa PVC dia. 4" air hujan m 75 120.248,00 9.018.600,00
Jumlah 15.414.888,00
C1 8 INSTALASI AIR BERSIH LANTAI ATAS
2 Pipa PVC dia. 1" m 45 30.233,00 1.360.485,00
3 Pipa PVC dia. 3/4" m 28 26.802,00 750.456,00
Jumlah 2.110.941,00
C1 9 INSTALASI AIR KOTOR & AIR BEKAS LANTAI ATAS
1 Pipa PVC dia. 3" m 3 91.728,00 275.184,00
2 Pipa PVC dia. 4" m 45 120.248,00 5.411.160,00
3 Pipa PVC dia. 3" m 28 91.728,00 2.568.384,00
Jumlah 8.254.728,00
Page 56
C1 10 PEKERJAAN SEPTICTANK
1 Septictank pabrikan kap. 3,00 m3 bh 2 21.092.313,00 42.184.626,00
Jumlah 42.184.626,00
C2 PEKERJAAN ELEKTRIKAL
C2 1 PEKERJAAN ELEKTRIKAL LANTAI DASAR
1 Pas. Box panel unit 1 2.297.449,00 2.297.449,00
2 Pas. Instalasi Lampu ttk 43 384.132,00 16.517.676,00
3 Pas. instalasi stop kontak ttk 14 514.509,00 7.203.126,00
4 Pas. Saklar engkel ttk 43 104.678,00 4.501.154,00
5 Pas. Stop kontak ttk 14 113.390,00 1.587.460,00
6 Pas. Lampu TL 2 x 36 watt grille bh 13 454.859,00 5.913.167,00
7 Pas. Down light & PLC 13 W bh 24 165.140,00 3.963.360,00
Jumlah 41.983.392,00
C2 1 PEKERJAAN ELEKTRIKAL LANTAI ATAS
1 Pas. Box panel bh 1 2.297.449,00 2.297.449,00
2 Pas. Instalasi Lampu ttk 30 384.132,00 11.523.960,00
3 Pas. Instalasi stop kontak ttk 15 514.509,00 7.717.635,00
4 Pas. Saklar engkel ttk 30 104.678,00 3.140.340,00
5 Pas. Stop kontak ttk 75 113.390,00 8.504.250,00
6 Pas. Lampu TL 2 x 36 watt grille bh 18 454.859,00 8.187.462,00
7 Pas. Down light & PLC 13 W bh 27 165.140,00 4.458.780,00
Jumlah 45.829.876,00
D PEKERJAAN FINISHING
1 Cat dinding dalam acrylic emulsion KW.I m² 870,37 42.948,00 37.380.650,76
2 Cat dinding dalam acrylic emulsion KW.I m² 1246,55 42.948,00 53.536.829,40
3 Cat plafond acrylic emulsion KW.I m² 342,9 42.948,00 14.726.869,20
4 Cat plafond acrylic emulsion KW.I m² 489 42.948,00 21.001.572,00
5 Railing Tangga Besi Hollow m² 10 820.625,00 8.206.250,00
Jumlah 134.852.171,36
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
GEDUNG NEGARA TIDAK SEDERHANA
Page 57
ANALISIS STANDAR BELANJA (ASB)
GEDUNG NEGARA SEDERHANA
1 KELOMPOK : Konstruksi
2 SUB KELOMPOK : Pembangunan Gedung Negara
3 SUB- SUB KELOMPOK : Pembangunan Gedung Negara Sederhana
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Pembangunan Seluruh Komponen Gedung Negara Sederhana
6 DESKRIPSI AKTIVITAS : Membangun Seluruh Komponen Gedung Negara Sederhana
7 SATUAN AKTIVITAS : m2
8 KOMPONEN/RINCIAN KOMPONEN :
NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
A PEKERJAAN STRUKTUR
A1 PEKERJAAN PONDASI
1 Galian tanah, dalam s/d 1 m m³ 99,68 119.924,00 11.954.024,32
2 Pas. Urugan Pasir m³ 6,23 268.769,00 1.674.430,87
3 Aanstamping batu kali m³ 22,59 650.982,00 14.705.683,38
4 Pas. pondasi batu kali 1:4 m³ 68,45 1.182.760,00 80.959.922,00
5 Urugan tanah kembali m³ 25,01 86.899,00 2.173.343,99
6 Buang tanah m³ 97,26 52.558,00 5.111.791,08
Jumlah 116.579.195,64
A2 PEKERJAAN BETON STRUKTUR
A2 1 PEKERJAAN SLOOF BETON
1 Bekisting sloof beton m² 71,20 238.798,00 17.002.417,60
2 Tulangan besi beton U-39 kg 730,11 17.596,00 12.847.015,56
3 Tulangan besi beton U-24 kg 382,47 17.596,00 6.729.942,12
4 Beton K-175 m³ 5,34 1.269.586,00 6.779.589,24
Jumlah 43.358.964,52
A2 2 PEKERJAAN KOLOM PRAKTIS
1 Bekisting kolom beton m² 78,32 428.677,00 33.573.982,64
2 Tulangan besi beton U-39 kg 856,29 17.596,00 15.067.278,84
3 Tulangan besi beton U-24 kg 494,38 17.596,00 8.699.110,48
4 Beton K-175 m³ 5,09 1.269.586,00 6.462.192,74
Jumlah 63.802.564,70
A2 3 PEKERJAAN RINGBALK
1 Bekisting balok beton m² 96,74 439.027,00 42.471.471,98
2 Tulangan besi beton U-39 kg 755,51 17.596,00 13.293.953,96
3 Tulangan besi beton U-24 kg 478,57 17.596,00 8.420.917,72
4 Beton K-175 m³ 7,21 1.269.586,00 9.153.715,06
Jumlah 73.340.058,72
A2 4 PEKERJAAN PLAT LANTAI
1 Bekisting plat beton m² 3,00 491.697,00 1.475.091,00
2 Tulangan besi beton U-24 kg 63,52 17.596,00 1.117.697,92
3 Beton K-175 m³ 0,34 1.269.586,00 431.659,24
Jumlah 3.024.448,16
B PEKERJAAN ARSITEKTUR
B1 PEKERJAAN LANTAI
1 Pas. Urugan pasir m³ 17,70 268.769,00 4.757.211,30
2 Pas. Lantai kerja beton tumbuk 1:3:5 m³ 7,56 1.016.351,00 7.683.613,56
3 Pas. Lantai keramik 300x300 m² 243,40 250.339,00 60.932.512,60
4 Pas. Rabat beton, finish acian m² 54,87 8.072,96 442.963,32
5 Pas. Dinding batu bata, ad. 1:4 m 66,56 169.068,00 11.253.166,08
Jumlah 85.069.466,86
B2 PEKERJAAN DINDING
1 Pas. Dinding batu bata, ad. 1:2 m² 21,50 180.054,00 3.871.161,00
2 Pas. Dinding batu bata, ad. 1:4 m² 484,21 169.068,00 81.864.416,28
3 Pas. Dinding partisi gypsum rangka kayu m² 28,50 605.858,00 17.266.953,00
4 Pas. Dinding batu bata, ad. 1:4 m³ 1,60 169.068,00 270.508,80
5 Pas. plester aci; ad. 1:4 m² 947,13 96.456,00 91.356.371,28
Jumlah 194.629.410,36
B3 PEKERJAAN PLAFON
1 Pas. Rangka Plafon Metal furing m² 334,46 156.499,00 52.342.655,54
2 Pas. Penutup plafon Gypsumboard t.9 mm m² 334,46 59.164,00 19.787.991,44
Jumlah 72.130.646,98
B4 PEKERJAAN ATAP
1 Rangka atap baja ringan m² 397,87 288.093,00 114.623.561,91
2 Penutup atap Genteng Keramik m² 397,87 252.291,00 100.379.020,17
3 Bubungan Genteng Keramik m 75,25 168.965,00 12.714.616,25
4 Pas. Lisplank Kayu 3/20 mm m 102,50 200.913,00 20.593.582,50
5 Pas. Talang seng plat m 42,00 235.546,00 9.892.932,00
Jumlah 258.203.712,83
Page 58
B5 PEKERJAAN KUSEN
1 Kusen pintu P1 unit 7,00 4.234.751,00 29.643.257,00
2 Kusen pintu P2 unit 4,00 4.086.861,00 16.347.444,00
3 Kusen pintu P3 unit 3,00 878.074,00 2.634.222,00
4 Kusen pintu PJ1 unit 1,00 7.883.529,00 7.883.529,00
5 Kusen pintu PJ2 unit 1,00 4.522.366,00 4.522.366,00
6 Kusen pintu jendela J-1 unit 2,00 5.648.389,00 11.296.778,00
7 Kusen pintu jendela J-2 unit 5,00 6.396.349,00 31.981.745,00
8 Kusen pintu jendela J-3 unit 1,00 3.431.994,00 3.431.994,00
9 Kusen Bovenlight BV 1 unit 8,00 941.554,00 7.532.432,00
# Kusen Bovenlight BV 2 unit 3,00 1.554.101,00 4.662.303,00
# Kusen Bovenlight BV 3 unit 3,00 2.361.286,00 7.083.858,00
# Bovenlight GR 1 unit 2,00 941.554,00 1.883.108,00
# Bovenlight GR 2 unit 2,00 1.554.101,00 3.108.202,00
# Bovenlight GR 3 unit 2,00 2.361.286,00 4.722.572,00
Jumlah 136.733.810,00
C PEKERJAAN UTILITAS
C1 PEKERJAAN PLUMBING
C1 1 PEKERJAAN SANITARY
1 Pas. Kloset duduk keramik unit 1,00 4.853.888,00 4.853.888,00
2 Pas. Kloset jongkok keramik unit 2,00 1.259.581,00 2.519.162,00
3 Pas. Floor drain bh 3,00 277.964,00 833.892,00
4 Pas. Kran dinding bh 3,00 543.086,00 1.629.258,00
5 Pas. Bak Air Fiberglass bh 1,00 1.221.816,00 1.221.816,00
Jumlah 11.058.016,00
C1 2 PEKERJAAN SUMUR DALAM
1 Pengeboran sumur m 24,00 386.939,00 9.286.536,00
2 Pipa PVC dia. 3" m 24,00 91.728,00 2.201.472,00
3 Pipa PVC dia. 2" m 6,00 48.759,00 292.554,00
4 Pipa PVC dia. 3/4" m 24,00 26.802,00 643.248,00
5 Klep diameter 3/4" bh 1,00 40.000,00 40.000,00
6 Stop kran dia. 1" bh 1,00 174.000,00 174.000,00
7 Mesin Jet Pump kap.250 watt bh 1,00 4.000.000,00 4.000.000,00
Jumlah 16.637.810,00
C1 3 TANGKI AIR
1 Pipa PVC dia. 1" m 12,00 30.233,00 362.796,00
2 Pipa PVC dia. 1" m 8,00 30.233,00 241.864,00
3 Pipa PVC dia. 3/4" m 4,00 26.802,00 107.208,00
4 Tangki air 500 liter bh 1,00 1.085.500,00 1.085.500,00
5 Dudukan tangki air bh 1,00 3.170.198,00 3.170.198,00
6 Stop kran dia. 1" bh 2,00 174.000,00 348.000,00
7 Stop kran dia. 1" bh 1,00 174.000,00 174.000,00
8 Stop kran dia. 1" bh 1,00 174.000,00 174.000,00
Jumlah 5.663.566,00
C1 4 INSTALASI AIR BERSIH
1 Pipa PVC dia. 2" m 40,00 48.759,00 1.950.360,00
2 Pipa PVC dia. 1" m 35,00 30.233,00 1.058.155,00
3 Pipa PVC dia. 3/4" m 8,00 26.802,00 214.416,00
Jumlah 3.222.931,00
C1 5 INSTALASI AIR KOTOR & AIR BEKAS
1 Pipa PVC dia. 4" m 40,00 120.248,00 4.809.920,00
2 Pipa PVC dia. 4" m 63,50 120.248,00 7.635.748,00
3 Pipa PVC dia. 2" m 9,00 48.759,00 438.831,00
Jumlah 12.884.499,00
C1 6 PEKERJAAN RESERVOIR
1 Galian tanah, dalam s/d 1 m m³ 5,63 119.924,00 675.172,12
2 Pas. Urugan pasir m³ 0,12 268.769,00 32.252,28
3 Pas. Lantai kerja beton tumbuk 1:3:5 m² 3,75 100.912,00 378.420,00
4 Bekisting plat beton m² 21,00 491.697,00 10.325.637,00
5 Tulangan besi beton U-24 kg 315,00 17.596,00 5.542.740,00
6 Beton K-200 m³ 2,10 1.302.437,00 2.735.117,70
Jumlah 19.689.339,10
C1 7 PEKERJAAN SEPTICTANK
1 Septictank Pas bata kap. 3,00 m3 + Rembesan bh 1,00 7.733.160,00 7.733.160,00
Jumlah 7.733.160,00
C2 PEKERJAAN ELEKTRIKAL
C2 1 PANEL
1 Pas. Box Panel unit 1,00 2.297.449,00 2.297.449,00
Jumlah 2.297.449,00
C2 2 INSTALASI
1 Pas. Instalasi lampu ttk 37,00 384.132,00 14.212.884,00
2 Pas. Instalasi stop kontak ttk 18,00 514.509,00 9.261.162,00
Jumlah 23.474.046,00
Page 59
C2 3 ARMATURE
1 Pas. Saklar engkel ttk 18,00 104.678,00 1.884.204,00
2 Pas. Saklar double ttk 19,00 110.486,00 2.099.234,00
3 Pas. Stop kontak ttk 18,00 113.390,00 2.041.020,00
4 Pas. Lampu TL 2 x 18 watt grille bh 8,00 357.293,00 2.858.344,00
5 Pas. Lampu TL 2 x 36 watt grille bh 8,00 454.859,00 3.638.872,00
6 Pas. Down light & PLC 13 W bh 21,00 165.140,00 3.467.940,00
Jumlah 15.989.614,00
D PEKERJAAN FINISHING
1 Cat dinding dalam acrylic emulsion KW.II m² 947,13 33.978,00 32.181.583,14
2 Pas. Dinding Keramik 300x300 m² 36,40 250.339,00 9.112.339,60
3 Pas. Dinding Keramik 300x300 m² 9,20 250.339,00 2.303.118,80
4 Cat plafond acrylic emulsion KW.II m² 335,46 33.978,00 11.398.259,88
5 Cat kayu synthetic m² 47,15 66.412,00 3.131.325,80
Jumlah 58.126.627,22
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
GEDUNG NEGARA SEDERHANA
Page 60
ANALISIS STANDAR BELANJA (ASB)
PAGAR DEPAN GEDUNG NEGARA
1 KELOMPOK : Konstruksi
2 SUB KELOMPOK : Pembangunan Pagar Gedung Negara
3 SUB- SUB KELOMPOK : Pembangunan Pagar Depan Gedung Negara
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Pembangunan dan Pemasangan Pagar Depan Gedung Negara
6 DESKRIPSI AKTIVITAS : Membangun dan Memasang Pagar Depan Gedung Negara
7 SATUAN AKTIVITAS : m'
8 KOMPONEN/RINCIAN KOMPONEN :
NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
A PAGAR DEPAN tinggi 1,50 m
I PEKERJAAN PONDASI BATU KALI
1 Galian tanah, dalam s/d 1 m m³ 9,240 119.924,00 1.108.097,76
2 Pas. Urugan Pasir m³ 0,420 268.769,00 112.882,98
3 Aanstamping batu kali m³ 1,260 650.982,00 820.237,32
4 Pas. pondasi batu kali 1:4 m³ 3,780 1.182.760,00 4.470.832,80
5 Urugan tanah kembali m³ 3,780 86.899,00 328.478,22
6 Buang tanah m³ 5,460 52.558,00 286.966,68
Jumlah 7.127.495,76
II PEKERJAAN SLOOF -
1 Bekisting sloof beton m² 4,800 238.798,00 1.146.230,40
2 Tulangan besi beton U-24 kg 68,100 17.596,00 1.198.287,60
3 Beton K-175 m³ 0,260 1.269.586,00 330.092,36
Jumlah 2.674.610,36
III PEKERJAAN KOLOM PRAKTIS -
1 Bekisting kolom beton m² 1,350 428.677,00 578.713,95
2 Tulangan besi beton U-24 kg 31,530 17.596,00 554.801,88
3 Beton K-175 m³ 0,100 1.269.586,00 126.958,60
Jumlah 1.260.474,43
IV PEKERJAAN DINDING -
1 Pagar Besi m² 16,350 831.435,00 13.593.962,25
2 Pintu Pagar Besi m² 1,500 831.435,00 1.247.152,50
Pilar; -
3 Pas. Dinding batu bata; ad 1:4 m² 15,600 169.068,00 2.637.460,80
4 Pas. Plester acian; ad. 1:4 m² 31,200 96.456,00 3.009.427,20
5 Cat dinding dalam acrylic emulsion KW.II m² 31,200 33.978,00 1.060.113,60
Jumlah 21.548.116,35
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
PAGAR DEPAN GEDUNG NEGARA
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PONDASI BATU KALI 7.127.495,76
II PEKERJAAN SLOOF 2.674.610,36
III PEKERJAAN KOLOM PRAKTIS 1.260.474,43
IV PEKERJAAN DINDING 21.548.116,35
JUMLAH (Rp) 32.610.696,90
JUMLAH DIBULATKAN (Rp) 32.610.000,00
PPN 10% 3.261.000,00
JUMLAH TOTAL (Rp) 35.871.000,00
PANJANG PAGAR (m) 12,00
HARGA PAGAR /m (Rp) 2.989.250,00
DIBULATKAN (Rp) 2.989.000,00
61
ANALISIS STANDAR BELANJA (ASB)
PAGAR SAMPING GEDUNG NEGARA
1 KELOMPOK : Konstruksi
2 SUB KELOMPOK : Pembangunan Pagar Gedung Negara
3 SUB- SUB KELOMPOK : Pembangunan Pagar Samping Gedung Negara
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Pembangunan dan Pemasangan Pagar Samping Gedung Negara
6 DESKRIPSI AKTIVITAS : Membangun dan Memasang Pagar Samping Gedung Negara
7 SATUAN AKTIVITAS : m'
8 KOMPONEN/RINCIAN KOMPONEN :
NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
B PAGAR SAMPING, tinggi 2,00 m
I PEKERJAAN PONDASI BATU KALI
1 Galian tanah, dalam s/d 1 m m³ 6,280 119.924,00 753.122,72
2 Pas. Urugan Pasir m³ 0,290 268.769,00 77.943,01
3 Aanstamping batu kali m³ 0,860 650.982,00 559.844,52
4 Pas. pondasi batu kali 1:4 m³ 2,570 1.182.760,00 3.039.693,20
5 Urugan tanah kembali m³ 2,570 86.899,00 223.330,43
6 Buang tanah m³ 3,710 52.558,00 194.990,18
Jumlah 4.848.924,06
II PEKERJAAN SLOOF -
1 Bekisting sloof beton m² 3,260 238.798,00 778.481,48
2 Tulangan besi beton U-24 kg 46,250 17.596,00 813.815,00
3 Beton K-175 m³ 0,240 1.269.586,00 304.700,64
Jumlah 1.896.997,12
III PEKERJAAN KOLOM PRAKTIS -
1 Bekisting kolom beton m² 3,000 428.677,00 1.286.031,00
2 Tulangan besi beton U-24 kg 62,880 17.596,00 1.106.436,48
3 Beton K-175 m³ 0,230 1.269.586,00 292.004,78
Jumlah 2.684.472,26
IV PEKERJAAN RINGBALK -
1 Bekisting balok beton m² 2,450 439.027,00 1.075.616,15
2 Tulangan besi beton U-24 kg 43,980 17.596,00 773.872,08
3 Beton K-175 m³ 0,180 1.269.586,00 228.525,48
Jumlah 2.078.013,71
V PEKERJAAN DINDING -
3 Pas. Dinding batu bata; ad 1:4 m² 16,300 169.068,00 2.755.808,40
4 Pas. Plester acian; ad. 1:5 m² 32,600 96.456,00 3.144.465,60
5 Cat dinding dalam acrylic emulsion KW.II m² 32,600 33.978,00 1.107.682,80
Jumlah 7.007.956,80
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
PAGAR SAMPING GEDUNG NEGARA
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PONDASI BATU KALI 4.848.924,06
II PEKERJAAN SLOOF 1.896.997,12
III PEKERJAAN KOLOM PRAKTIS 2.684.472,26
IV PEKERJAAN RINGBALK 2.078.013,71
V PEKERJAAN DINDING 7.007.956,80
JUMLAH (Rp) 18.516.363,95
JUMLAH DIBULATKAN (Rp) 18.516.000,00
PPN 10% 1.851.600,00
JUMLAH TOTAL (Rp) 20.367.600,00
PANJANG PAGAR (m) 8,00
HARGA PAGAR /m (Rp) 2.545.950,00
DIBULATKAN (Rp) 2.545.000,00
62
ANALISIS STANDAR BELANJA (ASB)
PAGAR BELAKANG GEDUNG NEGARA
1 KELOMPOK : Konstruksi
2 SUB KELOMPOK : Pembangunan Pagar Gedung Negara
3 SUB- SUB KELOMPOK : Pembangunan Pagar Belakang Gedung Negara
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Pembangunan dan Pemasangan Pagar Belakang Gedung Negara
6 DESKRIPSI AKTIVITAS : Membangun dan Memasang Pagar Belakang Gedung Negara
7 SATUAN AKTIVITAS : m'
8 KOMPONEN/RINCIAN KOMPONEN :
NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
A PAGAR BELAKANG, tinggi 3,00 m
I PEKERJAAN PONDASI BATU KALI
1 Galian tanah, dalam s/d 1 m m³ 3,850 119.924,00 461.707,40
2 Pas. Urugan Pasir m³ 0,180 268.769,00 48.378,42
3 Aanstamping batu kali m³ 0,530 650.982,00 345.020,46
4 Pas. pondasi batu kali 1:4 m³ 1,580 1.182.760,00 1.868.760,80
5 Urugan tanah kembali m³ 1,580 86.899,00 137.300,42
6 Buang tanah m³ 2,280 52.558,00 119.832,24
Jumlah 2.980.999,74
II PEKERJAAN SLOOF -
1 Bekisting sloof beton m² 2,000 238.798,00 477.596,00
2 Tulangan besi beton U-24 kg 28,450 17.596,00 500.606,20
3 Beton K-175 m³ 0,150 1.269.586,00 190.437,90
Jumlah 1.168.640,10
III PEKERJAAN KOLOM PRAKTIS -
1 Bekisting kolom beton m² 1,500 428.677,00 643.015,50
2 Tulangan besi beton U-24 kg 27,050 17.596,00 475.971,80
3 Beton K-175 m³ 0,110 1.269.586,00 139.654,46
Jumlah 1.258.641,76
IV PEKERJAAN RINGBALK -
1 Bekisting balok beton m² 1,500 439.027,00 658.540,50
2 Tulangan besi beton U-24 kg 27,050 17.596,00 475.971,80
3 Beton K-175 m³ 0,110 1.269.586,00 139.654,46
Jumlah 1.274.166,76
V PEKERJAAN DINDING -
3 Pas. Dinding batu bata; ad 1:4 m² 12,500 169.068,00 2.113.350,00
4 Pas. Plester acian; ad. 1:4 m² 25,000 96.456,00 2.411.400,00
5 Cat dinding dalam acrylic emulsion KW.II m² 25,000 33.978,00 849.450,00
Jumlah 5.374.200,00
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
PAGAR BELAKANG GEDUNG NEGARA
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PONDASI BATU KALI 2.980.999,74
II PEKERJAAN SLOOF 1.168.640,10
III PEKERJAAN KOLOM PRAKTIS 1.258.641,76
IV PEKERJAAN RINGBALK 1.274.166,76
V PEKERJAAN DINDING 5.374.200,00
JUMLAH (Rp) 12.056.648,36
JUMLAH DIBULATKAN (Rp) 12.056.000,00
PPN 10% 1.205.600,00
JUMLAH TOTAL (Rp) 13.261.600,00
PANJANG PAGAR (m) 5,00
HARGA PAGAR /m (Rp) 2.652.320,00
DIBULATKAN (Rp) 2.652.000,00
63
ANALISIS STANDAR BELANJA (ASB)
RUMAH NEGARA TIPE A
1 KELOMPOK : Konstruksi
2 SUB KELOMPOK : Pembangunan Gedung Rumah Negara
3 SUB- SUB KELOMPOK : Pembangunan Gedung Rumah Negara Tipe A
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Pembangunan Seluruh Komponen Rumah Negara Tipe A
6 DESKRIPSI AKTIVITAS : Membangun Seluruh Komponen Rumah Negara Tipe A
7 SATUAN AKTIVITAS : m²
8 KOMPONEN/RINCIAN KOMPONEN :
NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
A PEKERJAAN STRUKTUR
A1 PEKERJAAN PONDASI
A1.1 PEKERJAAN PONDASI BATU KALI
1 Galian tanah, dalam s/d 1 m m³ 143,220 119.924,00 17.175.515,28
2 Pas. Urugan Pasir m³ 6,510 268.769,00 1.749.686,19
3 Aanstamping batu kali m³ 19,530 650.982,00 12.713.678,46
4 Pas. pondasi batu kali 1:4 m³ 58,590 1.182.760,00 69.297.908,40
5 Urugan tanah kembali m³ 58,590 86.899,00 5.091.412,41
6 Buang tanah m³ 84,630 52.558,00 4.447.983,54
Jumlah 110.476.184,28
A1.2 PEKERJAAN PONDASI ROLLAG BATA -
1 Galian tanah, dalam s/d 1 m m³ 4,260 119.924,00 510.876,24
2 Pas. Urugan pasir m³ 0,530 268.769,00 142.447,57
3 Pas. Lantai kerja beton tumbuk 1:3:5 m² 10,650 100.912,00 1.074.712,80
4 Pas. Dinding batu bata; ad 1:4 m² 17,750 169.068,00 3.000.957,00
5 Pas. Plester acian; ad. 1:4 m² 35,500 96.456,00 3.424.188,00
6 Urugan tanah kembali m³ 1,420 86.899,00 123.396,58
7 Buang tanah m³ 2,840 52.558,00 149.264,72
Jumlah 8.425.842,91
A2 PEKERJAAN BETON STRUKTUR -
A2.1 PEKERJAAN SLOOF BETON -
2 Tulangan besi beton U-24 kg 840,210 17.596,00 14.784.335,16
3 Beton K-175 m³ 5,580 1.269.586,00 7.084.289,88
Jumlah 21.868.625,04
A2.2 PEKERJAAN KOLOM PRAKTIS -
1 Bekisting kolom beton m² 76,800 428.677,00 32.922.393,60
2 Tulangan besi beton U-24 kg 1.175,410 17.596,00 20.682.514,36
3 Beton K-175 m³ 5,760 1.269.586,00 7.312.815,36
Jumlah 60.917.723,32
A2.3 PEKERJAAN RINGBALK -
1 Bekisting balok beton m² 74,400 439.027,00 32.663.608,80
3 Tulangan besi beton U-24 kg 485,530 17.596,00 8.543.385,88
4 Beton K-175 m³ 3,230 1.269.586,00 4.100.762,78
Jumlah 45.307.757,46
A2.4 PEKERJAAN PLAT DAK -
1 Bekisting plat beton m² 36,570 491.697,00 17.981.359,29
2 Tulangan besi beton U-24 kg 307,510 17.596,00 5.410.945,96
3 Beton K-175 m³ 3,500 1.269.586,00 4.443.551,00
Jumlah 27.835.856,25
A2.5 PEKERJAAN KANOPI -
1 Bekisting plat beton m² 14,070 491.697,00 6.918.176,79
2 Tulangan besi beton U-24 kg 124,700 17.596,00 2.194.221,20
3 Beton K-175 m³ 1,200 1.269.586,00 1.523.503,20
Jumlah 10.635.901,19
A2.6 PEKERJAAN MEJA BETON -
1 Bekisting plat beton m² 2,870 491.697,00 1.411.170,39
2 Tulangan besi beton U-24 kg 25,670 17.596,00 451.689,32
3 Beton K-175 m³ 0,240 1.269.586,00 304.700,64
Jumlah 2.167.560,35
B PEKERJAAN ARSITEKTUR -
B1 PEKERJAAN LANTAI -
1 Pas. Urugan pasir m³ 17,140 268.769,00 4.606.700,66
2 Pas. Lantai kerja beton tumbuk 1:3:5 m² 306,750 100.912,00 30.954.756,00
3 Pas. Lantai keramik 300x300 m² 262,250 250.339,00 65.651.402,75
4 Pas. Lantai keramik 300x300 m² 87,540 250.339,00 21.914.676,06
5 Pas. Plint Granitetile 100x400 m 236,500 83.815,00 19.822.247,50
6 Pas. Lantai Keramik 300x300 m² 36,000 250.339,00 9.012.204,00
Jumlah 151.961.986,97
B2 PEKERJAAN DINDING -
1 Pas. Dinding batu bata, ad. 1:4 m² 792,760 169.068,00 134.030.347,68
2 Pas. plester; ad. 1:4 m² 1.585,520 96.456,00 152.932.917,12
3 Pas. acian m² 1.585,520 58.187,00 92.256.652,24
Jumlah 379.219.917,04
64
B3 PEKERJAAN PLAFON -
1 Pas. Rangka Plafon Metal furing m² 328,000 156.499,00 51.331.672,00
2 Pas. Penutup plafon Gypsumboard t.9 mm m² 349,940 59.164,00 20.703.850,16
3 Pas. List Profil Gypsum t. 5 cm m 249,300 45.572,00 11.361.099,60
Jumlah 83.396.621,76
B4 PEKERJAAN ATAP -
1 Rangka atap baja ringan m² 396,000 288.093,00 114.084.828,00
2 Penutup atap Genteng Keramik Glazur m² 396,000 260.916,00 103.322.736,00
3 Bubungan Genteng Keramik Glazur m 18,000 174.715,00 3.144.870,00
4 Pas. Lisplank Kayu 3/20 mm m 58,000 95.738,00 5.552.804,00
5 Pas. Fleshing seng plat m 22,000 127.017,00 2.794.374,00
6 Pas. Roof Drain bh 2,000 208.964,00 417.928,00
Jumlah 229.317.540,00
B5 PEKERJAAN KUSEN -
1 Kusen Pintu dan Jendela Kayu KW.I m³ 1,280 8.786.690,00 11.246.963,20
2 Pintu panel kayu KW.I; 82 x 206 cm; R. Tamu m² 2,930 937.040,00 2.745.527,20
3 Pintu panel kayu KW.I; 82 x 206 cm; K. Tidur m² 16,690 937.040,00 15.639.197,60
4 Pintu panel kayu KW.I; 72 x 206 cm; K. Mandi m² 5,850 937.040,00 5.481.684,00
5 Pintu kaca kayu KW.I; 50 x 206 cm m² 4,120 937.040,00 3.860.604,80
6 Jendela kaca kayu KW.I; 52 x 122 cm m² 12,690 937.040,00 11.891.037,60
7 Jendela kaca kayu KW.I; 52 x 182 cm m² 1,890 937.040,00 1.771.005,60
8 Pintu Besi 240 x 400 cm; Garasi m² 9,600 986.653,00 9.471.868,80
9 Pas. Kaca polos 5 mm m² 11,610 146.491,00 1.700.760,51
11 Pas. Engsel pintu bh 60,000 75.057,00 4.503.420,00
12 Pas. Engsel jendela bh 44,000 57.347,00 2.523.268,00
13 Pas. Kunci pintu ruangan bh 13,000 227.810,00 2.961.530,00
14 Pas. Kunci knob pintu kamar mandi ps 4,000 300.631,00 1.202.524,00
15 Pas. Slot tanam pintu doble ps 3,000 227.810,00 683.430,00
16 Pas. Kait angin jendela bh 22,000 63.691,00 1.401.202,00
17 Pas. Grendel Jendela bh 44,000 83.990,00 3.695.560,00
18 Pas. Rel pintu lipat 4 pintu unit 1,000 1.033.569,00 1.033.569,00
Jumlah 81.813.152,31
C PEKERJAAN UTILITAS -
C1 PEKERJAAN PLUMBING -
C1.1 PEKERJAAN SANITARY -
1 Pas. Washtafel keramik bh 2,000 1.452.432,00 2.904.864,00
2 Pas. Kloset Duduk Keramik bh 2,000 2.903.488,00 5.806.976,00
3 Pas. Kloset Jongkok Keramik bh 1,000 730.581,00 730.581,00
4 Pas. Bak Air Fiberglass bh 1,000 1.221.816,00 1.221.816,00
5 Pas. Shower spray bh 2,000 399.193,00 798.386,00
6 Pas. Shower set bh 2,000 2.612.943,00 5.225.886,00
7 Pas. Floor Drain bh 4,000 126.164,00 504.656,00
8 Pas. Tempat sabun keramik bh 3,000 241.068,00 723.204,00
9 Pas. Kitchenzink stainlees stell 1 lubang bh 1,000 481.994,00 481.994,00
10 Pas. Kran zink bh 1,000 543.086,00 543.086,00
11 Pas. Kran dinding bh 3,000 135.986,00 407.958,00
Jumlah 19.349.407,00
C1.2 PEKERJAAN SUMUR DALAM -
1 Pengeboran sumur m 36,000 386.939,00 13.929.804,00
2 Pipa PVC dia. 3" m 36,000 91.728,00 3.302.208,00
3 Pipa PVC dia. 2" m 10,000 48.759,00 487.590,00
4 Pipa PVC dia. 3/4" m 36,000 26.802,00 964.872,00
5 Klep diameter 3/4" bh 1,000 40.000,00 40.000,00
6 Stop kran dia. 1" bh 1,000 174.000,00 174.000,00
7 Mesin Jet Pump kap.250 watt bh 1,000 4.000.000,00 4.000.000,00
Jumlah 22.898.474,00
C1.3 TANGKI AIR -
1 Pipa PVC dia. 1" m 12,000 30.233,00 362.796,00
2 Pipa PVC dia. 1" m 8,000 30.233,00 241.864,00
3 Pipa PVC dia. 3/4" m 4,000 26.802,00 107.208,00
4 Tangki air 500 liter bh 1,000 1.085.500,00 1.085.500,00
5 Dudukan tangki air bh 1,000 3.170.198,00 3.170.198,00
6 Mesin pompa kap.150 watt bh 1,000 1.750.000,00 1.750.000,00
7 Stop kran dia. 1" bh 2,000 174.000,00 348.000,00
8 Stop kran dia. 1" bh 1,000 174.000,00 174.000,00
9 Stop kran dia. 1" bh 1,000 174.000,00 174.000,00
Jumlah 7.413.566,00
C1.4 PEKERJAAN RESERVOIR -
1 Galian tanah, dalam s/d 1 m m³ 5,630 119.924,00 675.172,12
2 Pas. Urugan pasir m³ 0,120 268.769,00 32.252,28
3 Pas. Lantai kerja beton tumbuk 1:3:5 m² 3,750 100.912,00 378.420,00
4 Bekisting plat beton m² 21,000 491.697,00 10.325.637,00
5 Tulangan besi beton U-24 kg 315,000 17.596,00 5.542.740,00
6 Beton K-200 m³ 2,100 1.302.437,00 2.735.117,70
Jumlah 19.689.339,10
65
C1.5 INSTALASI AIR BERSIH -
1 Pipa PVC dia. 1" m 36,000 30.233,00 1.088.388,00
2 Pipa PVC dia. 3/4" m 32,000 26.802,00 857.664,00
3 Pipa PVC dia. 1/2" m 36,000 24.351,00 876.636,00
Jumlah 2.822.688,00
C1.6 INSTALASI AIR KOTOR & AIR BEKAS -
1 Pipa PVC dia. 4" m 20,000 120.248,00 2.404.960,00
2 Pipa PVC dia. 3" m 28,000 91.728,00 2.568.384,00
3 Pipa PVC dia. 2" m 20,000 48.759,00 975.180,00
4 Pipa PVC dia. 1" m 16,000 30.233,00 483.728,00
Jumlah 6.432.252,00
C1.77 PEKERJAAN SEPTICTANK -
1 Septictank Pas bata kap. 6,00 m3 + Rembesan unit 1,000 5.155.440,00 5.155.440,00
Jumlah 5.155.440,00
C2 PEKERJAAN ELEKTRIKAL -
C2.1 PANEL -
1 Pas. Box Panel bh 2,000 1.052.402,00 2.104.804,00
Jumlah 2.104.804,00
C2.2 INSTALASI -
1 Pas. Instalasi lampu ttk 26,000 437.032,00 11.362.832,00
2 Pas. Instalasi exhausfan ttk 2,000 694.140,00 1.388.280,00
3 Pas. Instalasi antena TV ttk 5,000 142.427,00 712.135,00
2 Pas. Instalasi stop kontak ttk 15,000 514.509,00 7.717.635,00
Jumlah 21.180.882,00
C2.3 ARMATURE -
1 Pas. Down light & PLC 13 W bh 26,000 165.140,00 4.293.640,00
2 Pas. Saklar engkel bh 12,000 104.678,00 1.256.136,00
3 Pas. Saklar doble bh 6,000 110.486,00 662.916,00
4 Pas. Stop kontak bh 15,000 113.390,00 1.700.850,00
5 Pas. Outlet TV bh 5,000 142.427,00 712.135,00
6 Pas. Outlet exhausefan bh 2,000 142.427,00 284.854,00
Jumlah 8.910.531,00
D PEKERJAAN FINISHING -
1 Pas. Dinding Keramik 300x300 m² 93,060 250.339,00 23.296.547,34
2 Pas. Dinding Keramik 300x300 m² 17,500 250.339,00 4.380.932,50
3 Cat dinding luar KW.I m² 906,370 42.948,00 38.926.778,76
4 Cat dinding dalam acrylic emulsion KW.I m² 521,590 42.948,00 22.401.247,32
5 Cat plafond acrylic emulsion KW.I m² 328,000 42.948,00 14.086.944,00
6 Cat kayu synthetic m² 142,360 66.412,00 9.454.412,32
7 Cat besi synthetic m² 19,200 51.350,00 985.920,00
8 Pekerjaan Canopi -
9 Pas. Acian PC m² 36,570 58.187,00 2.127.898,59
10 Cat plafond acrylic emulsion KW.I m² 36,570 42.948,00 1.570.608,36
Jumlah 117.231.289,19
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
RUMAH NEGARA TIPE A
No PEKERJAAN JUMLAH (Rp)
A PEKERJAAN STRUKTUR
A.1 PEKERJAAN PONDASI 110.476.184,28
A.2 PEKERJAAN BETON STRUKTUR 177.159.266,52
B PEKERJAAN ARSITEKTUR -
B.1 PEKERJAAN LANTAI 151.961.986,97
B.2 PEKERJAAN DINDING 379.219.917,04
B.3 PEKERJAAN PLAFON 83.396.621,76
B.4 PEKERJAAN ATAP 229.317.540,00
B.5 PEKERJAAN KUSEN 81.813.152,31
C PEKERJAAN UTILITAS -
C.1 PEKERJAAN PLUMBING 83.761.166,10
C.2 PEKERJAAN ELEKTRIKAL 32.196.217,00
D PEKERJAAN FINISHING 117.231.289,19
JUMLAH (Rp) 1.446.533.341,17
JUMLAH DIBULATKAN (Rp) 1.446.533.000,00
PPN 10% 144.653.300,00
JUMLAH TOTAL (Rp) 1.591.186.300,00
LUAS BANGUNAN (m²) 250,00
HARGA BANGUNAN/m² (Rp) 6.364.745,20
DIBULATKAN (Rp) 6.364.000,00
66
ANALISIS STANDAR BELANJA (ASB)
RUMAH NEGARA TIPE B
1 KELOMPOK : Konstruksi
2 SUB KELOMPOK : Pembangunan Gedung Rumah Negara
3 SUB- SUB KELOMPOK : Pembangunan Gedung Rumah Negara Tipe B
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Pembangunan Seluruh Komponen Rumah Negara Tipe B
6 DESKRIPSI AKTIVITAS : Membangun Seluruh Komponen Rumah Negara Tipe B
7 SATUAN AKTIVITAS : m²
8 KOMPONEN/RINCIAN KOMPONEN :
NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
A PEKERJAAN STRUKTUR
A1 PEKERJAAN PONDASI
A1.1 PEKERJAAN PONDASI BATU KALI
1 Galian tanah, dalam s/d 1 m m³ 53,510 119.924,00 6.417.133,24
2 Pas. Urugan Pasir m³ 2,970 268.769,00 798.243,93
3 Aanstamping batu kali m³ 8,920 650.982,00 5.806.759,44
4 Pas. pondasi batu kali 1:4 m³ 23,780 1.182.760,00 28.126.032,80
5 Urugan tanah kembali m³ 17,840 86.899,00 1.550.278,16
6 Buang tanah m³ 35,680 52.558,00 1.875.269,44
Jumlah 44.573.717,01
A1.2 PEKERJAAN PONDASI ROLLAG BATA -
1 Galian tanah, dalam s/d 1 m m³ 0,540 119.924,00 64.758,96
2 Pas. Urugan pasir m³ 0,070 268.769,00 18.813,83
3 Pas. Lantai kerja beton tumbuk 1:3:5 m² 1,350 100.912,00 136.231,20
4 Pas. Dinding batu bata; ad 1:4 m² 2,250 169.068,00 380.403,00
5 Pas. Plester acian; ad. 1:4 m² 4,500 96.456,00 434.052,00
6 Urugan tanah kembali m³ 0,180 86.899,00 15.641,82
7 Buang tanah m³ 0,360 52.558,00 18.920,88
Jumlah 1.068.821,69
A2 PEKERJAAN BETON STRUKTUR -
A2.1 PEKERJAAN SLOOF BETON -
2 Tulangan besi beton U-24 kg 448,990 17.596,00 7.900.428,04
3 Beton K-175 m³ 2,970 1.269.586,00 3.770.670,42
Jumlah 11.671.098,46
A2.2 PEKERJAAN KOLOM PRAKTIS -
1 Bekisting kolom beton m² 25,740 428.677,00 11.034.145,98
2 Tulangan besi beton U-24 kg 369,500 17.596,00 6.501.722,00
3 Beton K-175 m³ 1,420 1.269.586,00 1.802.812,12
Jumlah 19.338.680,10
A2.3 PEKERJAAN RINGBALK -
1 Bekisting balok beton m² 29,730 439.027,00 13.052.272,71
3 Tulangan besi beton U-24 kg 290,700 17.596,00 5.115.157,20
4 Beton K-175 m³ 1,700 1.269.586,00 2.158.296,20
Jumlah 20.325.726,11
A2.4 PEKERJAAN KANOPI -
1 Bekisting plat beton m² 4,620 491.697,00 2.271.640,14
2 Tulangan besi beton U-24 kg 40,850 17.596,00 718.796,60
3 Beton K-175 m³ 0,390 1.269.586,00 495.138,54
Jumlah 3.485.575,28
A2.5 PEKERJAAN MEJA BETON -
1 Bekisting plat beton m² 1,330 491.697,00 653.957,01
2 Tulangan besi beton U-24 kg 12,050 17.596,00 212.031,80
3 Beton K-175 m³ 0,110 1.269.586,00 139.654,46
Jumlah 1.005.643,27
B PEKERJAAN ARSITEKTUR -
B1 PEKERJAAN LANTAI -
1 Pas. Urugan pasir m³ 8,470 268.769,00 2.276.473,43
2 Pas. Lantai kerja beton tumbuk 1:3:5 m² 131,910 100.912,00 13.311.301,92
3 Pas. Lantai keramik 300x300 m² 41,210 250.339,00 10.316.470,19
4 Pas. Lantai keramik 300x300 m² 104,570 250.339,00 26.177.949,23
5 Pas. Plint Granitetile 100x400 m 103,680 83.815,00 8.689.939,20
6 Pas. Rabat beton; finish acian m² 37,500 100.912,00 3.784.200,00
Jumlah 64.556.333,97
B2 PEKERJAAN DINDING -
1 Pas. Dinding batu bata, ad. 1:4 m² 471,850 169.068,00 79.774.735,80
2 Pas. plester; ad. 1:4 m² 943,690 96.456,00 91.024.562,64
3 Pas. acian m² 943,690 58.187,00 54.910.490,03
Jumlah 225.709.788,47
B3 PEKERJAAN PLAFON -
1 Pas. Rangka Plafon Metal furing m² 152,710 156.499,00 23.898.962,29
2 Pas. Penutup plafon Gypsumboard t.9 mm m² 154,960 59.164,00 9.168.053,44
3 Pas. List Profil Gypsum t. 5 cm m 122,130 45.572,00 5.565.708,36
Jumlah 38.632.724,09
67
B4 PEKERJAAN ATAP -
1 Rangka atap baja ringan m² 158,750 288.093,00 45.734.763,75
2 Penutup atap Genteng Keramik Glazur m² 158,750 260.916,00 41.420.415,00
3 Bubungan Genteng Keramik Glazur m 12,800 174.715,00 2.236.352,00
4 Pas. Lisplank Kayu 3/20 mm m 41,400 95.738,00 3.963.553,20
5 Pas. Fleshing seng plat m 46,000 127.017,00 5.842.782,00
6 Pas. Roof Drain bh 2,000 208.964,00 417.928,00
Jumlah 99.615.793,95
B5 PEKERJAAN KUSEN -
1 Kusen Pintu dan Jendela Kayu KW.I m³ 1,280 8.786.690,00 11.246.963,20
2 Pintu panel kayu KW.II; 82 x 206 cm; R. Tamu m² 2,930 717.117,00 2.101.152,81
3 Pintu doble teakwood 82 x 206 cm; K. Tidur m² 16,690 717.117,00 11.968.682,73
4 Pintu doble teakwood 72 x 206 cm; K. Mandi m² 5,850 717.117,00 4.195.134,45
5 Pintu kaca kayu KW.II; 50 x 206 cm m² 4,120 717.117,00 2.954.522,04
6 Jendela kaca kayu KW.II; 52 x 122 cm m² 12,690 717.117,00 9.100.214,73
7 Jendela kaca kayu KW.II; 52 x 182 cm m² 1,890 717.117,00 1.355.351,13
8 Pintu Besi 240 x 400 cm; Garasi m² 9,600 986.653,00 9.471.868,80
9 Pas. Kaca polos 5 mm m² 11,610 146.491,00 1.700.760,51
11 Pas. Engsel pintu bh 60,000 75.057,00 4.503.420,00
12 Pas. Engsel jendela bh 44,000 57.347,00 2.523.268,00
13 Pas. Kunci pintu ruangan bh 13,000 227.810,00 2.961.530,00
14 Pas. Kunci knob pintu kamar mandi ps 4,000 300.631,00 1.202.524,00
15 Pas. Slot tanam pintu doble ps 3,000 227.810,00 683.430,00
16 Pas. Kait angin jendela bh 22,000 63.691,00 1.401.202,00
17 Pas. Grendel Jendela bh 44,000 83.990,00 3.695.560,00
18 Pas. Rel pintu lipat 4 pintu unit 1,000 1.033.569,00 1.033.569,00
Jumlah 72.099.153,40
C PEKERJAAN UTILITAS -
C1 PEKERJAAN PLUMBING -
C1.1 PEKERJAAN SANITARY -
1 Pas. Washtafel keramik bh 1,000 1.452.432,00 1.452.432,00
2 Pas. Kloset Duduk Keramik bh 1,000 2.903.488,00 2.903.488,00
3 Pas. Kloset Jongkok Keramik bh 1,000 730.581,00 730.581,00
4 Pas. Bak Air Fiberglass bh 1,000 1.221.816,00 1.221.816,00
5 Pas. Shower spray bh 1,000 399.193,00 399.193,00
6 Pas. Shower set bh 1,000 2.612.943,00 2.612.943,00
7 Pas. Floor Drain bh 3,000 126.164,00 378.492,00
8 Pas. Tempat sabun keramik bh 2,000 241.068,00 482.136,00
9 Pas. Kitchenzink stainlees stell 1 lubang bh 1,000 481.994,00 481.994,00
10 Pas. Kran zink bh 1,000 543.086,00 543.086,00
11 Pas. Kran dinding bh 3,000 135.986,00 407.958,00
Jumlah 11.614.119,00
C1.2 PEKERJAAN SUMUR DALAM -
1 Pengeboran sumur m 24,000 386.939,00 9.286.536,00
2 Pipa PVC dia. 3" m 24,000 91.728,00 2.201.472,00
3 Pipa PVC dia. 2" m 6,000 48.759,00 292.554,00
4 Pipa PVC dia. 3/4" m 24,000 26.802,00 643.248,00
5 Klep diameter 3/4" bh 1,000 40.000,00 40.000,00
6 Stop kran dia. 1" bh 1,000 174.000,00 174.000,00
7 Mesin Jet Pump kap.250 watt bh 1,000 4.000.000,00 4.000.000,00
Jumlah 16.637.810,00
C1.3 TANGKI AIR -
1 Pipa PVC dia. 1" m 12,000 30.233,00 362.796,00
2 Pipa PVC dia. 1" m 8,000 30.233,00 241.864,00
3 Pipa PVC dia. 3/4" m 4,000 26.802,00 107.208,00
4 Tangki air 500 liter bh 1,000 1.085.500,00 1.085.500,00
5 Dudukan tangki air bh 1,000 3.170.198,00 3.170.198,00
6 Stop kran dia. 1" bh 2,000 174.000,00 348.000,00
7 Stop kran dia. 1" bh 1,000 174.000,00 174.000,00
8 Stop kran dia. 1" bh 1,000 174.000,00 174.000,00
Jumlah 5.663.566,00
C1.4 INSTALASI AIR BERSIH -
1 Pipa PVC dia. 1" m 28,000 30.233,00 846.524,00
2 Pipa PVC dia. 3/4" m 24,000 26.802,00 643.248,00
3 Pipa PVC dia. 1/2" m 28,000 24.351,00 681.828,00
Jumlah 2.171.600,00
C1.5 INSTALASI AIR KOTOR & AIR BEKAS -
1 Pipa PVC dia. 4" m 12,000 120.248,00 1.442.976,00
2 Pipa PVC dia. 3" m 20,000 91.728,00 1.834.560,00
3 Pipa PVC dia. 2" m 12,000 48.759,00 585.108,00
4 Pipa PVC dia. 1" m 8,000 30.233,00 241.864,00
Jumlah 4.104.508,00
C1.6 PEKERJAAN SEPTICTANK -
1 Septictank Pas bata kap. 3,00 m3 + Rembesan unit 1,000 2.577.720,00 2.577.720,00
Jumlah 2.577.720,00
68
C2 PEKERJAAN ELEKTRIKAL -
C2.1 PANEL -
1 Pas. Box Panel bh 2,000 1.052.402,00 2.104.804,00
Jumlah 2.104.804,00
C2.2 INSTALASI -
1 Pas. Instalasi lampu ttk 16,000 437.032,00 6.992.512,00
2 Pas. Instalasi exhausfan ttk 1,000 694.140,00 694.140,00
3 Pas. Instalasi stop kontak ttk 10,000 514.509,00 5.145.090,00
Jumlah 12.831.742,00
C2.3 ARMATURE -
1 Pas. Down light & PLC 13 W bh 16,000 165.140,00 2.642.240,00
2 Pas. Saklar engkel bh 6,000 104.678,00 628.068,00
3 Pas. Saklar doble bh 3,000 110.486,00 331.458,00
4 Pas. Stop kontak bh 10,000 113.390,00 1.133.900,00
5 Pas. Outlet exhausefan bh 1,000 142.427,00 142.427,00
Jumlah 4.878.093,00
D PEKERJAAN FINISHING -
1 Pas. Dinding Keramik 300x300 m² 43,500 250.339,00 10.889.746,50
2 Pas. Dinding Keramik 300x300 m² 20,000 250.339,00 5.006.780,00
3 Cat dinding luar KW.I m² 554,390 42.948,00 23.809.941,72
4 Cat dinding dalam acrylic emulsion KW.I m² 264,710 42.948,00 11.368.765,08
5 Cat plafond acrylic emulsion KW.I m² 135,270 42.948,00 5.809.575,96
6 Cat kayu synthetic m² 19,870 66.412,00 1.319.606,44
7 Cat besi synthetic m² 14,640 51.350,00 751.764,00
8 Pekerjaan Canopi -
9 Pas. Acian PC m² 15,790 58.187,00 918.772,73
10 Cat plafond acrylic emulsion KW.I m² 15,790 42.948,00 678.148,92
Jumlah 60.553.101,35
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
RUMAH NEGARA TIPE B
No PEKERJAAN JUMLAH (Rp)
A PEKERJAAN STRUKTUR
A.1 PEKERJAAN PONDASI 45.642.538,70
A.2 PEKERJAAN BETON STRUKTUR 55.826.723,22
B PEKERJAAN ARSITEKTUR -
B.1 PEKERJAAN LANTAI 64.556.333,97
B.2 PEKERJAAN DINDING 225.709.788,47
B.3 PEKERJAAN PLAFON 38.632.724,09
B.4 PEKERJAAN ATAP 99.615.793,95
B.5 PEKERJAAN KUSEN 72.099.153,40
C PEKERJAAN UTILITAS -
C.1 PEKERJAAN PLUMBING 42.769.323,00
C.2 PEKERJAAN ELEKTRIKAL 19.814.639,00
D PEKERJAAN FINISHING 60.553.101,35
JUMLAH (Rp) 725.220.119,15
JUMLAH DIBULATKAN (Rp) 725.220.000,00
PPN 10% 72.522.000,00
JUMLAH TOTAL (Rp) 797.742.000,00
LUAS BANGUNAN (m²) 120,00
HARGA BANGUNAN/m² (Rp) 6.647.850,00
DIBULATKAN (Rp) 6.647.000,00
69
ANALISIS STANDAR BELANJA (ASB)
RUMAH NEGARA TIPE C
1 KELOMPOK : Konstruksi
2 SUB KELOMPOK : Pembangunan Gedung Rumah Negara
3 SUB- SUB KELOMPOK : Pembangunan Gedung Rumah Negara Tipe C
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Pembangunan Gedung Rumah Negara Tipe C
6 DESKRIPSI AKTIVITAS : Pembangunan Gedung Rumah Negara Tipe C
7 SATUAN AKTIVITAS : m²
8 KOMPONEN/RINCIAN KOMPONEN :
NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
A PEKERJAAN STRUKTUR
A1 PEKERJAAN PONDASI
A1.1 PEKERJAAN PONDASI BATU KALI
1 Galian tanah, dalam s/d 1 m m³ 33,020 119.924,00 3.959.890,48
2 Pas. Urugan Pasir m³ 3,890 268.769,00 1.045.511,41
3 Aanstamping batu kali m³ 5,830 650.982,00 3.795.225,06
4 Pas. pondasi batu kali 1:4 m³ 16,510 1.182.760,00 19.527.367,60
Jumlah 28.327.994,55
A2 PEKERJAAN BETON STRUKTUR -
A2.1 PEKERJAAN SLOOF BETON -
1 Bekisting sloof beton m² 25,900 238.798,00 6.184.868,20
2 Tulangan besi beton U-24 kg 321,070 17.596,00 5.649.547,72
3 Beton K-175 m³ 1,940 1.269.586,00 2.462.996,84
Jumlah 14.297.412,76
A2.2 PEKERJAAN KOLOM PRAKTIS -
1 Bekisting kolom beton m² 39,900 428.677,00 17.104.212,30
2 Tulangan besi beton U-24 kg 242,600 17.596,00 4.268.789,60
3 Beton K-175 m³ 1,500 1.269.586,00 1.904.379,00
Jumlah 23.277.380,90
A2.3 PEKERJAAN RINGBALK -
1 Bekisting balok beton m² 5,320 439.027,00 2.335.623,64
3 Tulangan besi beton U-24 kg 33,270 17.596,00 585.418,92
4 Beton K-175 m³ 0,320 1.269.586,00 406.267,52
Jumlah 3.327.310,08
B PEKERJAAN ARSITEKTUR -
B1 PEKERJAAN LANTAI -
1 Pas. Urugan pasir m³ 7,610 268.769,00 2.045.332,09
2 Pas. Lantai kerja beton tumbuk 1:3:5 m² 76,060 100.912,00 7.675.366,72
3 Pas. Lantai keramik 300x300 m² 76,060 250.339,00 19.040.784,34
4 Pas. Rabat beton; finish acian m² 9,150 100.912,00 923.344,80
Jumlah 29.684.827,95
B2 PEKERJAAN DINDING -
1 Pas. Dinding batu bata, ad. 1:4 m² 169,990 169.068,00 28.739.869,32
2 Pas. plester; ad. 1:4 m² 10,320 96.456,00 995.425,92
3 Pas. acian m² 326,220 58.187,00 18.981.763,14
Jumlah 48.717.058,38
B3 PEKERJAAN PLAFON -
1 Pas. Rangka Plafond Kayu m² 65,950 303.234,00 19.998.282,30
2 Pas. Penutup plafon Gypsumboard t.9 mm m² 65,950 59.164,00 3.901.865,80
Jumlah 23.900.148,10
B4 PEKERJAAN ATAP -
1 Pas. Kuda kuda Kayu m³ 1,430 7.212.340,00 10.313.646,20
2 Rangka Atap kayu m² 70,000 318.517,00 22.296.190,00
3 Penutup atap Genteng Keramik m 70,000 252.291,00 17.660.370,00
4 Bubungan Genteng Keramik m 9,500 168.965,00 1.605.167,50
5 Pas. Lisplank Kayu 3/20 mm m 24,500 200.913,00 4.922.368,50
6 Pas. Fleshing seng plat m 36,000 127.017,00 4.572.612,00
Jumlah 61.370.354,20
B5 PEKERJAAN KUSEN -
1 Kusen Pintu dan Jendela Kayu KW.I m³ 0,580 8.786.690,00 5.096.280,20
2 Pintu panel kayu KW.III; 82 x 206 cm; R. Tamu m² 1,460 717.117,00 1.046.990,82
3 Pintu doble triplex 82 x 206 cm; K. Tidur m² 5,010 717.117,00 3.592.756,17
4 Pintu doble triplex 72 x 206 cm; K. Mandi m² 2,930 717.117,00 2.101.152,81
5 Jendela kaca kayu KW.III; 52 x 122 cm m² 0,630 717.117,00 451.783,71
6 Jendela kaca kayu KW.III; 52 x 182 cm m² 5,680 717.117,00 4.073.224,56
7 Pas. Kaca polos 3 mm m² 2,890 146.491,00 423.358,99
8 Cat kayu synthetic m² 2,890 986.653,00 2.851.427,17
9 Cat besi synthetic m² 24,000 342.566,00 8.221.584,00
11 Pas. Engsel pintu bh 24,000 75.057,00 1.801.368,00
12 Pas. Engsel jendela bh 14,000 57.347,00 802.858,00
13 Pas. Kunci pintu ruangan bh 6,000 227.810,00 1.366.860,00
14 Pas. Kunci knob pintu kamar mandi bh 2,000 300.631,00 601.262,00
15 Pas. Kait angin jendela bh 7,000 227.810,00 1.594.670,00
16 Pas.Kait angin jendela bh 14,000 63.691,00 891.674,00
Jumlah 34.917.250,43
70
C PEKERJAAN UTILITAS -
C1 PEKERJAAN PLUMBING -
C1.1 PEKERJAAN SANITARY -
1 Pas. Kloset Jongkok Keramik bh 1,000 730.581,00 730.581,00
2 Pas. Bak Air Fiberglass bh 1,000 1.221.816,00 1.221.816,00
3 Pas. Floor Drain bh 2,000 126.164,00 252.328,00
4 Pas. Kran dinding bh 1,000 135.986,00 135.986,00
Jumlah 2.340.711,00
C1.2 PEKERJAAN SUMUR DALAM -
1 Pipa PVC dia. 3" m 24,000 91.728,00 2.201.472,00
2 Pipa PVC dia. 2" m 6,000 48.759,00 292.554,00
3 Pipa PVC dia. 3/4" m 24,000 26.802,00 643.248,00
4 Klep diameter 3/4" bh 1,000 40.000,00 40.000,00
5 Stop kran dia. 1" bh 1,000 174.000,00 174.000,00
6 Mesin Jet Pump kap.250 watt bh 1,000 4.000.000,00 4.000.000,00
Jumlah 7.351.274,00
C1.3 INSTALASI AIR BERSIH -
1 Pipa PVC dia. 1" m 15,400 30.233,00 465.588,20
2 Pipa PVC dia. 3/4" m 13,200 26.802,00 353.786,40
3 Pipa PVC dia. 1/2" m 15,400 24.351,00 375.005,40
Jumlah 1.194.380,00
C1.4 INSTALASI AIR KOTOR & AIR BEKAS -
1 Pipa PVC dia. 4" m 6,600 120.248,00 793.636,80
2 Pipa PVC dia. 3" m 11,000 91.728,00 1.009.008,00
3 Pipa PVC dia. 2" m 6,600 48.759,00 321.809,40
4 Pipa PVC dia. 1" m 4,400 30.233,00 133.025,20
Jumlah 2.257.479,40
C1.5 PEKERJAAN SEPTICTANK -
1 Septictank Pas bata kap. 3,00 m3 + Rembesan unit 1,000 2.577.720,00 2.577.720,00
Jumlah 2.577.720,00
C2 PEKERJAAN ELEKTRIKAL -
C2.1 PANEL -
1 Pas. Box Panel bh 2,000 1.052.402,00 2.104.804,00
Jumlah 2.104.804,00
C2.2 INSTALASI -
1 Pas. Instalasi lampu ttk 8,000 437.032,00 3.496.256,00
2 Pas. Instalasi stop kontak ttk 4,000 514.509,00 2.058.036,00
Jumlah 5.554.292,00
C2.3 ARMATURE -
1 Pas. Saklar engkel bh 4,000 104.678,00 418.712,00
2 Pas. Saklar doble bh 2,000 110.486,00 220.972,00
3 Pas. Stop kontak bh 4,000 113.390,00 453.560,00
4 Pas. Fitting plafond + Lampu SL bh 8,000 97.773,00 782.184,00
Jumlah 1.875.428,00
D PEKERJAAN FINISHING -
1 Cat dinding luar KW.I m² 183,160 42.948,00 7.866.355,68
2 Cat dinding dalam acrylic emulsion KW.I m² 153,380 42.948,00 6.587.364,24
3 Cat plafond acrylic emulsion KW.I m² 65,950 42.948,00 2.832.420,60
4 Cat kayu synthetic m² 18,000 66.412,00 1.195.416,00
5 Pas. Acian PC m² 5,320 58.187,00 309.554,84
6 Cat plafond acrylic emulsion KW.I m² 5,320 42.948,00 228.483,36
Jumlah 19.019.594,72
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
RUMAH NEGARA TIPE C
No PEKERJAAN JUMLAH (Rp)
A PEKERJAAN STRUKTUR
A.1 PEKERJAAN PONDASI 28.327.994,55
A.2 PEKERJAAN BETON STRUKTUR 40.902.103,74
B PEKERJAAN ARSITEKTUR -
B.1 PEKERJAAN LANTAI 29.684.827,95
B.2 PEKERJAAN DINDING 48.717.058,38
B.3 PEKERJAAN PLAFON 23.900.148,10
B.4 PEKERJAAN ATAP 61.370.354,20
B.5 PEKERJAAN KUSEN 34.917.250,43
C PEKERJAAN UTILITAS -
C.1 PEKERJAAN PLUMBING 15.721.564,40
C.2 PEKERJAAN ELEKTRIKAL 9.534.524,00
D PEKERJAAN FINISHING 19.019.594,72
JUMLAH (Rp) 312.095.420,47
JUMLAH DIBULATKAN (Rp) 312.095.000,00
PPN 10% 31.209.500,00
JUMLAH TOTAL (Rp) 343.304.500,00
LUAS BANGUNAN (m²) 70,00
HARGA BANGUNAN/m² (Rp) 4.904.350,00
DIBULATKAN (Rp) 4.904.000,00
71
ANALISIS STANDAR BELANJA (ASB)
PAGAR DEPAN RUMAH NEGARA
1 KELOMPOK : Konstruksi
2 SUB KELOMPOK : Pembangunan Pagar Gedung Negara
3 SUB- SUB KELOMPOK : Pembangunan Pagar Depan Rumah Negara
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Pembangunan dan Pemasangan Pagar Depan Rumah Negara
6 DESKRIPSI AKTIVITAS : Membangun dan Memasang Pagar Depan Rumah Negara
7 SATUAN AKTIVITAS : m'
8 KOMPONEN/RINCIAN KOMPONEN :
NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
A PAGAR DEPAN tinggi 1,50 m
I PEKERJAAN PONDASI BATU KALI
1 Galian tanah, dalam s/d 1 m m³ 2,100 119.924,00 251.840,40
2 Pas. Urugan Pasir m³ 0,150 268.769,00 40.315,35
3 Aanstamping batu kali m³ 0,450 650.982,00 292.941,90
4 Pas. pondasi batu kali 1:4 m³ 1,080 1.182.760,00 1.277.380,80
5 Urugan tanah kembali m³ 0,420 86.899,00 36.497,58
6 Buang tanah m³ 1,680 52.558,00 88.297,44
Jumlah 1.987.273,47
II PEKERJAAN SLOOF -
1 Bekisting sloof beton m² 1,800 238.798,00 429.836,40
2 Tulangan besi beton U-24 kg 30,810 17.596,00 542.132,76
3 Beton K-175 m³ 0,090 1.269.586,00 114.262,74
Jumlah 1.086.231,90
III PEKERJAAN KOLOM PRAKTIS -
1 Bekisting kolom beton m² 0,600 428.677,00 257.206,20
2 Tulangan besi beton U-24 kg 7,500 17.596,00 131.970,00
3 Beton K-175 m³ 1,500 1.269.586,00 1.904.379,00
Jumlah 2.293.555,20
IV PEKERJAAN DINDING -
Pilar; -
3 Pas. Dinding batu bata; ad 1:4 m² 8,700 169.068,00 1.470.891,60
4 Pas. Plester acian; ad. 1:4 m² 17,400 96.456,00 1.678.334,40
5 Cat dinding dalam acrylic emulsion KW.II m² 17,400 33.978,00 591.217,20
Jumlah 3.740.443,20
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
PAGAR DEPAN RUMAH NEGARA
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PONDASI BATU KALI 1.987.273,47
II PEKERJAAN SLOOF 1.086.231,90
III PEKERJAAN KOLOM PRAKTIS 2.293.555,20
IV PEKERJAAN DINDING 3.740.443,20
JUMLAH (Rp) 9.107.503,77
JUMLAH DIBULATKAN (Rp) 9.107.000,00
PPN 10% 910.700,00
JUMLAH TOTAL (Rp) 10.017.700,00
PANJANG PAGAR (m) 6,00
HARGA PAGAR /m (Rp) 1.669.616,67
DIBULATKAN (Rp) 1.669.000,00
72
ANALISIS STANDAR BELANJA (ASB)
PAGAR SAMPING RUMAH NEGARA
1 KELOMPOK : Konstruksi
2 SUB KELOMPOK : Pembangunan Pagar Gedung Negara
3 SUB- SUB KELOMPOK : Pembangunan Pagar Samping Rumah Negara
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Pembangunan dan Pemasangan Pagar Samping Rumah Negara
6 DESKRIPSI AKTIVITAS : Membangun dan Memasang Pagar Samping Rumah Negara
7 SATUAN AKTIVITAS : m'
8 KOMPONEN/RINCIAN KOMPONEN :
NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
B PAGAR SAMPING, tinggi 2,00 m
I PEKERJAAN PONDASI BATU KALI
1 Galian tanah, dalam s/d 1 m m³ 2,100 119.924,00 251.840,40
2 Pas. Urugan Pasir m³ 0,150 268.769,00 40.315,35
3 Aanstamping batu kali m³ 0,450 650.982,00 292.941,90
4 Pas. pondasi batu kali 1:4 m³ 1,080 1.182.760,00 1.277.380,80
5 Urugan tanah kembali m³ 0,420 86.899,00 36.497,58
6 Buang tanah m³ 1,680 52.558,00 88.297,44
Jumlah 1.987.273,47
II PEKERJAAN SLOOF -
1 Bekisting sloof beton m² 1,800 238.798,00 429.836,40
2 Tulangan besi beton U-24 kg 30,810 17.596,00 542.132,76
3 Beton K-175 m³ 0,090 1.269.586,00 114.262,74
Jumlah 1.086.231,90
III PEKERJAAN KOLOM PRAKTIS -
1 Bekisting kolom beton m² 1,200 439.027,00 526.832,40
2 Tulangan besi beton U-24 kg 29,120 17.596,00 512.395,52
3 Beton K-175 m³ 0,060 1.269.586,00 76.175,16
Jumlah 1.115.403,08
IV PEKERJAAN DINDING -
1 Pas. Dinding batu bata; ad 1:4 m² 12,000 169.068,00 2.028.816,00
2 Pas. Plester acian; ad. 1:5 kg 12,000 96.456,00 1.157.472,00
3 Cat dinding dalam acrylic emulsion KW.II m³ 12,000 33.978,00 407.736,00
Jumlah 3.594.024,00
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
PAGAR SAMPING RUMAH NEGARA
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PONDASI BATU KALI 1.987.273,47
II PEKERJAAN SLOOF 1.086.231,90
III PEKERJAAN KOLOM PRAKTIS 1.115.403,08
IV PEKERJAAN DINDING 3.594.024,00
JUMLAH (Rp) 7.782.932,45
JUMLAH DIBULATKAN (Rp) 7.782.000,00
PPN 10% 778.200,00
JUMLAH TOTAL (Rp) 8.560.200,00
PANJANG PAGAR (m) 6,00
HARGA PAGAR /m (Rp) 1.426.700,00
DIBULATKAN (Rp) 1.426.000,00
73
ANALISIS STANDAR BELANJA (ASB)
PAGAR BELAKANG RUMAH NEGARA
1 KELOMPOK : Konstruksi
2 SUB KELOMPOK : Pembangunan Pagar Gedung Negara
3 SUB- SUB KELOMPOK : Pembangunan Pagar Belakang Rumah Negara
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Pembangunan dan Pemasangan Pagar Belakang Rumah Negara
6 DESKRIPSI AKTIVITAS : Membangun dan Memasang Pagar Belakang Rumah Negara
7 SATUAN AKTIVITAS : m'
8 KOMPONEN/RINCIAN KOMPONEN :
NO URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
C PAGAR BELAKANG, tinggi 3,00 m
I PEKERJAAN PONDASI BATU KALI
1 Galian tanah, dalam s/d 1 m m³ 2,100 119.924,00 251.840,40
2 Pas. Urugan Pasir m³ 0,150 268.769,00 40.315,35
3 Aanstamping batu kali m³ 0,450 650.982,00 292.941,90
4 Pas. pondasi batu kali 1:4 m³ 1,080 1.182.760,00 1.277.380,80
5 Urugan tanah kembali m³ 0,420 86.899,00 36.497,58
6 Buang tanah m³ 1,680 52.558,00 88.297,44
Jumlah 1.987.273,47
II PEKERJAAN SLOOF -
1 Bekisting sloof beton m² 1,800 238.798,00 429.836,40
2 Tulangan besi beton U-24 kg 30,810 17.596,00 542.132,76
3 Beton K-175 m³ 0,090 1.269.586,00 114.262,74
Jumlah 1.086.231,90
III PEKERJAAN KOLOM PRAKTIS -
1 Bekisting kolom beton m² 1,200 428.677,00 514.412,40
2 Tulangan besi beton U-24 kg 29,120 17.596,00 512.395,52
3 Beton K-175 m³ 0,060 1.269.586,00 76.175,16
Jumlah 1.102.983,08
IV PEKERJAAN DINDING -
3 Pas. Dinding batu bata; ad 1:4 m² 15,000 169.068,00 2.536.020,00
4 Pas. Plester acian; ad. 1:4 m² 15,000 96.456,00 1.446.840,00
5 Cat dinding dalam acrylic emulsion KW.II m² 15,000 33.978,00 509.670,00
Jumlah 4.492.530,00
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
PAGAR BELAKANG RUMAH NEGARA
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PONDASI BATU KALI 1.987.273,47
II PEKERJAAN SLOOF 1.086.231,90
III PEKERJAAN KOLOM PRAKTIS 1.102.983,08
IV PEKERJAAN DINDING 4.492.530,00
JUMLAH (Rp) 8.669.018,45
JUMLAH DIBULATKAN (Rp) 8.669.000,00
PPN 10% 866.900,00
JUMLAH TOTAL (Rp) 9.535.900,00
PANJANG PAGAR (m) 6,00
HARGA PAGAR /m (Rp) 1.589.316,67
DIBULATKAN (Rp) 1.589.000,00
74
ANALISIS STANDAR BELANJA (ASB)
PEMBANGUNAN JALAN RIGID PAVEMENT K.350 T=25Cm
1 KELOMPOK : KONSTRUKSI
2 SUB KELOMPOK : BIDANG JALAN
3 SUB- SUB KELOMPOK : PEMBANGUNAN JALAN
4 ZONA WILAYAH SSH : SELURUH WILAYAH KABUPATEN
5 AKTIVITAS : PEMBANGUNAN JALAN RIGID PAVEMENT K.350 T=25Cm
6 DESKRIPSI AKTIVITAS : PEMBANGUNAN JALAN RIGID PAVEMENT K.350 T=25Cm
7 Volume = 100 x 6 M'
7 SATUAN AKTIVITAS : m²
8 KOMPONEN/RINCIAN KOMPONEN :
NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
I DIVISI 1. UMUM
1 Mobilisasi 0,500 3.316.376,00 1.658.188,00
2 Manajemen dan Keselamatan Lalu Lintas LS 0,500 780.000,00 390.000,00
3 Penyiapan Badan Jalan -
Jumlah 2.048.188,00
II DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK -
4 Galian Biasa M3 180,000 133.547,00 24.038.460,00
Jumlah 24.038.460,00
III DIVISI 5. PERKERASAN BERBUTIR -
5 Lapis Pondasi Agregat Kelas A M3 60,000 603.416,00 36.204.960,00
6 Lapis Pondasi Agregat Kelas B M3 120,000 581.705,00 69.804.600,00
7 Lapis Pondasi Agregat Kelas S ( Timbunan Bahu Jalan ) M3 35,000 552.757,00 19.346.495,00
Perkerasan Beton Semen (dengan Sambungan Tie Bar) FC 30
8 M3 150,000 2.290.383,00 343.557.450,00
(K - 350)
Jumlah 468.913.505,00
IV Pengeboran, Termasuk SPT dan Laporan -
9 Peralatan Pengeboran lengkap Unit 1,000 7.500.000,00 7.500.000,00
10 Mobilisasi dan Demobilisasi Peralatan Pengeboran lengkap Ls 1,000 1.000.000,00 1.000.000,00
11 Pelaksanaan Pekerjaan Pengeboran dilapangan M 1,000 45.000,00 45.000,00
12 Pengambilan SPT interval 2 meter Sampel 0,500 75.000,00 37.500,00
13 Pengambilan benda uji tanah interval 2 meter Sampel 0,500 75.000,00 37.500,00
14 Pengujian Laboratorium untuk benda uji lengkap Sampel 0,500 200.000,00 100.000,00
15 Laporan hasil pengeboran dan pengujian Ls 1,000 500.000,00 500.000,00
16 Alat Bantu Ls 1,000 -
17 Tenaga Ahli Pengeboran M 1,000 801.666,67 801.666,67
18 Tenaga Pendukung OH 4,000 403.000,00 1.612.000,00
19 Mobilisasi dan Demobilisasi Tenaga OH 1,000 1.000.000,00 1.000.000,00
Jumlah 12.633.666,67
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
PEMBANGUNAN JALAN RIGID PAVEMENT K.350 T=25Cm ( Dengan Tiebar )
` PEKERJAAN JUMLAH (Rp)
I DIVISI 1. UMUM 2.048.188,00
II DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK 24.038.460,00
III DIVISI 5. PERKERASAN BERBUTIR 468.913.505,00
IV Pengeboran, Termasuk SPT dan Laporan 12.633.666,67
JUMLAH (Rp) 507.633.819,67
PPN 10% 50.763.381,97
JUMLAH TOTAL (Rp) 558.397.201,63
Luas 600,00
ASB/m² 930.662,00
JUMLAH DIBULATKAN (Rp) 930.662,00
75
ANALISIS STANDAR BELANJA (ASB)
PEMBANGUNAN TPT JALAN
1 KELOMPOK : KONSTRUKSI
2 SUB KELOMPOK : BIDANG JALAN
3 SUB- SUB KELOMPOK : PEMBANGUNAN TPT JALAN
4 ZONA WILAYAH SSH : SELURUH WILAYAH
5 AKTIVITAS : PEMBANGUNAN TPT JALAN
6 DESKRIPSI AKTIVITAS : PEKERJAAN BANGUNAN PELENGKAP TPT JALAN
Volume : Panjang = 100 m' x ( Tinggi =1,80 m' )
7 SATUAN AKTIVITAS : m²
8 KOMPONEN/RINCIAN KOMPONEN :
NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
I DIVISI 1. UMUM
1 Mobilisasi LS 0,500 3.316.376,00 1.658.188,00
2 Manajemen dan Keselamatan Lalu Lintas LS 1,000 780.000,00 780.000,00
Jumlah 2.438.188,00
II DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK -
3 Galian Biasa M3 42,000 133.547,00 5.608.974,00
4 Timbunan Biasa dari Sumber Galian M3 18,000 575.951,00 10.367.118,00
Jumlah 15.976.092,00
III DIVISI 7. STRUKTUR -
5 Pasangan Batu m3 99,000 952.941,00 94.341.159,00
Jumlah 94.341.159,00
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
PEKERJAAN PEMBANGUNAN TPT JALAN
No PEKERJAAN JUMLAH (Rp)
I DIVISI 1. UMUM 2.438.188,00
III DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK 15.976.092,00
III DIVISI 7. STRUKTUR 94.341.159,00
JUMLAH (Rp) 112.755.439,00
PPN 10% 11.275.543,90
JUMLAH TOTAL (Rp) 124.030.982,90
Luas 100,00
ASB/m² 1.240.309,83
JUMLAH DIBULATKAN (Rp) 1.240.309,00
76
ANALISIS STANDAR BELANJA (ASB)
PEMBANGUNAN TPT FRAME
1 KELOMPOK : KONSTRUKSI
2 SUB KELOMPOK : BIDANG JALAN
3 SUB- SUB KELOMPOK : PEMBANGUNAN TPT JALAN
4 ZONA WILAYAH SSH : SELURUH WILAYAH
5 AKTIVITAS : PEMBANGUNAN TPT Frame
6 DESKRIPSI AKTIVITAS : PEMBANGUNAN TPT Frame
V : Panjang = 20 m' x ( Tinggi = 5 m' )
7 SATUAN AKTIVITAS : m²
8 KOMPONEN/RINCIAN KOMPONEN
NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
(1) (2) (3) (4) (5) (6)
I DIVISI 1. UMUM
1 Mobilisasi LS 1,000 3.316.376,00 3.316.376,00
2 Manajemen dan Keselamatan Lalu Lintas LS 1,000 780.000,00 780.000,00
Jumlah 4.096.376,00
II DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK -
3 Galian Struktur dengan kedalaman 0-2 meter m3 41,000 88.666,00 3.635.306,00
4 Timbunan Biasa dari Sumber Galian m3 35,000 575.951,00 20.158.285,00
Jumlah 23.793.591,00
III DIVISI 7. STRUKTUR -
5 Pasangan Batu m3 123,500 952.941,00 117.688.213,50
6 Beton struktur, fc’20 MPa (K250) m3 18,000 1.309.131,00 23.564.358,00
7 Baja Tulangan Polos-BjTP 280 kg 1.414,600 19.732,00 27.912.887,20
8 Tiang Bor Beton, diameter 800 mm m3 10,000 1.944.941,00 19.449.410,00
Jumlah 188.614.868,70
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
PEMBANGUNAN TPT RAME
No PEKERJAAN JUMLAH (Rp)
I DIVISI 1. UMUM 4.096.376,00
III DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK 23.793.591,00
III DIVISI 7. STRUKTUR 188.614.868,70
JUMLAH (Rp) 216.504.835,70
PPN 10% 21.650.483,57
JUMLAH TOTAL (Rp) 238.155.319,27
Luas 100,00
ASB/m² 2.381.553,19
JUMLAH DIBULATKAN (Rp) 2.381.553,00
77
ANALISIS STANDAR BELANJA (ASB)
PENINGKATAN TROTOAR DIATAS BAHU JALAN
1 KELOMPOK : KONSTRUKSI
2 SUB KELOMPOK : BIDANG JALAN
3 SUB- SUB KELOMPOK : PENINGKATAN TROTOAR DIATAS BAHU JALAN
4 ZONA WILAYAH SSH : SELURUH WILAYAH KABUPATEN
5 AKTIVITAS : PENINGKATAN TROTOAR DIATAS BAHU JALAN
6 DESKRIPSI AKTIVITAS : V = 388,5 (P=129,5 m x L=3m' )
7 SATUAN AKTIVITAS : m²
8 KOMPONEN/RINCIAN KOMPONEN :
NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
(1) (2) (3) (4) (5) (6)
I DIVISI 1. UMUM
1 Mobilisasi LS 1,000 3.316.376,00 3.316.376,00
2 Manajemen dan Keselamatan Lalu Lintas LS 1,000 780.000,00 780.000,00
Jumlah 4.096.376,00
II DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK -
3 Galian Struktur dengan kedalaman 0-2 meter M3 - 88.666,00 -
4 Timbunan Biasa dari Sumber Galian M3 15,550 575.951,00 8.956.038,05
Jumlah 8.956.038,05
DIVISI 4. PELEBARAN PERKERASAN DAN BAHU
III -
JALAN
5 Pekerjaan Beton Pola m2 388,500 245.599,00 95.415.211,50
6 Guiding Block (difabel stone) M3 38,850 323.430,00 12.565.255,50
Jumlah 107.980.467,00
IV DIVISI 7. STRUKTUR -
7 Beton K-250 (Ready Mix) m3 33,670 1.309.131,00 44.078.440,77
8 Baja Tulangan U 24 Polos Kg 1.190,850 17.596,00 20.954.196,60
9 Pipa Penyalur PVC 6" m1 4,320 275.994,00 1.192.294,08
10 Manhole Bh - -
Jumlah 66.224.931,45
DIVISI 8. PENGEMBALIAN KONDISI DAN
V -
PEKERJAAN MINOR
11 Marka Jalan Bukan Termoplastik m2 38,850 54.236,00 2.107.068,60
Kerb Pracetak Jenis 4 (Penghalang Berparit / Barrier Gutter) t
12 m1 129,500 62.735,00 8.124.182,50
= 20 cm
Jumlah 10.231.251,10
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
PENINGKATAN TROTOAR DIATAS BAHU JALAN
No PEKERJAAN JUMLAH (Rp)
I DIVISI 1. UMUM 4.096.376,00
II DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK 8.956.038,05
III DIVISI 4. PELEBARAN PERKERASAN DAN BAHU JALAN 107.980.467,00
IV DIVISI 7. STRUKTUR 66.224.931,45
V DIVISI 8. PENGEMBALIAN KONDISI DAN PEKERJAAN MINOR 10.231.251,10
JUMLAH (Rp) 197.489.063,60
PPN 10% 19.748.906,36
JUMLAH TOTAL (Rp) 217.237.969,96
Luas 388,50
ASB/m² 559.171,09
JUMLAH DIBULATKAN (Rp) 559.171,00
78
ANALISIS STANDAR BELANJA (ASB)
PELEBARAN JALAN
1 KELOMPOK : KONSTRUKSI
2 SUB KELOMPOK : BIDANG JALAN
3 SUB- SUB KELOMPOK : PENINGKATAN TROTOAR DIATAS BAHU JALAN
4 ZONA WILAYAH SSH : REHABILITASI JALAN
5 AKTIVITAS : PELEBARAN JALAN
6 DESKRIPSI AKTIVITAS : PELEBARAN JALAN ( BETON K-250 ) V= 100 X 1,5 M' ( Kiri + Kanan )
7 SATUAN AKTIVITAS : m²
8 KOMPONEN/RINCIAN KOMPONEN :
NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
I DIVISI 1. UMUM
1 Mobilisasi LS 1,000 3.316.376,00 3.316.376,00
2 Manajemen dan Keselamatan Lalu Lintas LS 1,000 780.000,00 780.000,00
Jumlah 4.096.376,00
II DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK -
3 Galian Struktur dengan kedalaman 0-2 meter M3 90,000 88.666,00 7.979.940,00
Jumlah 7.979.940,00
III DIVISI 5. PERKERASAN BERBUTIR -
3 Lapis Pondasi Agregat Kelas A M3 15,000 603.416,00 9.051.240,00
4 Lapis Pondasi Agregat Kelas B M3 15,000 581.705,00 8.725.575,00
5 Perkerasan Beton Semen FC 20 (K - 250) M3 60,000 1.309.131,00 78.547.860,00
Jumlah 96.324.675,00
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
PELEBARAN JALAN ( BETON K-250 ) V= 100 X 1,5 M' ( Kiri + Kanan )
No PEKERJAAN JUMLAH (Rp)
I DIVISI 1. UMUM 4.096.376,00
II DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK 7.979.940,00
III DIVISI 5. PERKERASAN BERBUTIR 96.324.675,00
JUMLAH (Rp) 108.400.991,00
PPN 10% 10.840.099,10
JUMLAH TOTAL (Rp) 119.241.090,10
Luas 300,00
ASB/m² 397.470,30
JUMLAH DIBULATKAN (Rp) 397.470,00
79
ANALISIS STANDAR BELANJA (ASB)
PEMBANGUNAN JEMBATAN
1 KELOMPOK : KONSTRUKSI
2 SUB KELOMPOK : BIDANG JALAN
3 SUB- SUB KELOMPOK : PEMBANGUNAN JEMBATAN
4 ZONA WILAYAH SSH : SELURUH WILAYAH KABUPATEN
5 AKTIVITAS : PEMBANGUNAN JEMBATAN
6 DESKRIPSI AKTIVITAS : PEMBANGUNAN JEMBATAN V = 4X4,5 M'
7 SATUAN AKTIVITAS : m²
8 KOMPONEN/RINCIAN KOMPONEN :
NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
(1) (2) (3) (4) (5) (6)
I DIVISI 1. UMUM
1 Mobilisasi LS 0,500 3.316.376,00 1.658.188,00
2 Manajemen dan Keselamatan Lalu Lintas LS 1,000 780.000,00 780.000,00
3 Overdam / Kisdam LS 1,000 38.571,00 38.571,00
Jumlah 2.476.759,00
II DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK -
4 Galian Biasa M2 180,000 133.547,00 24.038.460,00
5 Timbunan Biasa dari Sumber Galian M3 3,850 575.951,00 2.217.411,35
Jumlah 26.255.871,35
III DIVISI 7. STRUKTUR -
6 Beton struktur, fc’30 MPa M3 - 1.342.896,00 -
7 Beton struktur, fc’20 MPa (K250) M3 14,150 1.309.131,00 18.524.203,65
8 Beton Siklop, fc’15 Mpa M3 - 3.220.490,00 -
9 Baja Tulangan Polos-BjTP 280 Kg 1.491,920 21.638,00 32.282.164,96
10 Anyaman Kawat Yang Dilas (Welded Wire Mesh) Kg 316,040 45.147,00 14.268.257,88
11 Penyediaan Baja Struktur Grade 250 (Kuat Leleh 250 MPa) Kg - - -
12 Pemasangan Baja Struktur Kg - - -
13 Pasangan Batu M3 98,070 1.117.843,00 109.626.863,01
14 Bronjong dengan kawat yang dilapisi Galvanis M3 - - -
15 Expansion Joint Baja Bersudut M1 8,000 352.543,00 2.820.344,00
Landasan Elastomerik Karet Sintetis Berlapis Baja Ukuran …..
16 Buah - 1.048.336,00 -
Mm x ….. Mm x…….. Mm
17 Sandaran (Railing) M1 12,000 144.719,00 1.736.628,00
18 Papan Nama Jembatan Buah 2,000 937.020,00 1.874.040,00
19 Pembongkaran Pasangan Batu M3 9,450 245.062,00 2.315.835,90
20 Pembongkaran Beton M3 2,940 579.287,00 1.703.103,78
21 Pipa Penyalur PVC M1 3,000 275.994,00 827.982,00
Jumlah 185.979.423,18
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
PEMBANGUNAN JEMBATAN V = 4X4,5 M'
` PEKERJAAN JUMLAH (Rp)
I DIVISI 1. UMUM 2.476.759,00
II DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK 26.255.871,35
III DIVISI 7. STRUKTUR 185.979.423,18
JUMLAH (Rp) 214.712.053,53
PPN 10% 21.471.205,35
JUMLAH TOTAL (Rp) 236.183.258,88
Luas 18,00
ASB/m² 13.121.292,16
JUMLAH DIBULATKAN (Rp) 13.121.292,00
80
ANALISIS STANDAR BELANJA (ASB)
PENINGKATAN JALAN RIGID PAVEMENT K.350 T=25 Cm
1 KELOMPOK : KONSTRUKSI
2 SUB KELOMPOK : BIDANG JALAN
3 SUB- SUB KELOMPOK : REHABILITASI JALAN
4 ZONA WILAYAH SSH : SELURUH WILAYAH KABUPATEN
5 AKTIVITAS : PENINGKATAN JALAN RIGID PAVEMENT K.350 T=25 Cm
6 DESKRIPSI AKTIVITAS : PENINGKATAN JALAN RIGID PAVEMENT K.350 T=25 Cm ( Dengan Tiebar )
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
PENINGKATAN JALAN RIGID PAVEMENT K.350 T=25 Cm ( Dengan Tiebar )
` PEKERJAAN JUMLAH (Rp)
I DIVISI 1. UMUM 4.876.376,00
II DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK 716.704,00
III DIVISI 5. PERKERASAN BERBUTIR 339.302.655,00
JUMLAH (Rp) 344.895.735,00
PPN 10% 34.489.573,50
JUMLAH TOTAL (Rp) 379.385.308,50
Luas 500,00
ASB/m² 758.770,62
JUMLAH DIBULATKAN (Rp) 758.770,00
81
ANALISIS STANDAR BELANJA (ASB)
PENINGKATAN JALAN RIGID PAVEMENT K.500 T=25 Cm
1 KELOMPOK : KONSTRUKI
2 SUB KELOMPOK : BIDANG JALAN
3 SUB- SUB KELOMPOK : REHABILITASI JALAN
4 ZONA WILAYAH SSH : SELURUH WILAYAH KABUPATEN
5 AKTIVITAS : PENINGKATAN JALAN RIGID PAVEMENT K.500 T=25 Cm
6 DESKRIPSI AKTIVITAS : PENINGKATAN JALAN RIGID PAVEMENT K.500 T=25 Cm (Dengan Tiebar )
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
PENINGKATAN JALAN RIGID PAVEMENT K.500 T=25 Cm (Dengan Tiebar )
` PEKERJAAN JUMLAH (Rp)
I DIVISI 1. UMUM 4.876.376,00
II DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK 716.704,00
III DIVISI 5. PERKERASAN BERBUTIR 354.290.780,00
JUMLAH (Rp) 359.883.860,00
PPN 10% 35.988.386,00
JUMLAH TOTAL (Rp) 395.872.246,00
Luas 500,00
ASB/m² 791.744,49
JUMLAH DIBULATKAN (Rp) 791.744,00
82
ANALISIS STANDAR BELANJA (ASB)
PENINGKATAN JALAN RIGID PAVEMENT K.350 T=20 Cm
1 KELOMPOK : KONSTRUKSI
2 SUB KELOMPOK : BIDANG JALAN
3 SUB- SUB KELOMPOK : REHABILITASI JALAN
4 ZONA WILAYAH SSH : SELURUH WILAYAH KABUPATEN
5 AKTIVITAS : PENINGKATAN JALAN RIGID PAVEMENT K.350 T=20 Cm
6 DESKRIPSI AKTIVITAS : PENINGKATAN JALAN RIGID PAVEMENT K.350 T=20 Cm (Dengan Tiebar )
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
PENINGKATAN JALAN RIGID PAVEMENT K.350 T=20 Cm (Dengan Tiebar )
` PEKERJAAN JUMLAH (Rp)
I DIVISI 1. UMUM 4.096.376,00
II DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK 716.704,00
III DIVISI 5. PERKERASAN BERBUTIR 282.043.080,00
JUMLAH (Rp) 286.856.160,00
PPN 10% 28.685.616,00
JUMLAH TOTAL (Rp) 315.541.776,00
Luas 500,00
ASB/m² 631.083,55
JUMLAH DIBULATKAN (Rp) 631.083,00
83
ANALISIS STANDAR BELANJA (ASB)
REHABILITASI JALAN LASTON AC-WC T= 4 CM
1 KELOMPOK : KONSTRUKSI
2 SUB KELOMPOK : BIDANG JALAN
3 SUB- SUB KELOMPOK : REHABILITASI JALAN
4 ZONA WILAYAH SSH : SELURUH WILAYAH KABUPATEN
5 AKTIVITAS : REHABILITASI JALAN LASTON AC-WC T= 4 CM
6 DESKRIPSI AKTIVITAS : REHABILITASI JALAN LASTON T=4 CM
Volume : 500 m2
7 SATUAN AKTIVITAS : m²
8 KOMPONEN/RINCIAN KOMPONEN :
NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
I DIVISI 1. UMUM
1 Mobilisasi LS 1,000 3.316.376,00 3.316.376,00
2 Manajemen dan Keselamatan Lalu Lintas LS 1,000 780.000,00 780.000,00
3 Penyiapan Badan Jalan -
Jumlah 4.096.376,00
II DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK -
4 Galian Biasa M3 10,000 133.547,00 1.335.470,00
Jumlah 1.335.470,00
III DIVISI 5. PERKERASAN BERBUTIR -
5 Lapis Pondasi Agregat Kelas A M3 30,000 603.416,00 18.102.480,00
6 Lapis Pondasi Agregat Kelas B M3 50,000 581.705,00 29.085.250,00
Jumlah 47.187.730,00
IV DIVISI 6. PERKERASAN ASPAL -
7 Lapis Resap Pengikat - Aspal Cair/Emulsi Liter 400,000 17.034,00 6.813.600,00
8 Lapis Perekat - Aspal Cair/Emulsi Liter 400,000 16.196,00 6.478.400,00
9 Laston Lapis Aus (AC-WC) Ton 45,000 1.282.079,00 57.693.555,00
Jumlah 70.985.555,00
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
REHABILITASI JALAN LASTON T=4 CM
` PEKERJAAN JUMLAH (Rp)
I DIVISI 1. UMUM 4.096.376,00
II DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK 1.335.470,00
III DIVISI 5. PERKERASAN BERBUTIR 47.187.730,00
IV DIVISI 6. PERKERASAN ASPAL 70.985.555,00
JUMLAH (Rp) 123.605.131,00
PPN 10% 12.360.513,10
JUMLAH TOTAL (Rp) 135.965.644,10
Luas 500,00
ASB/m² 271.931,29
JUMLAH DIBULATKAN (Rp) 271.931,00
84
ANALISIS STANDAR BELANJA (ASB)
STABILISASI DAN PENGUATAN TEBING POLIMER
1 KELOMPOK : KONSTRUKSI
2 SUB KELOMPOK : BIDANG JALAN
3 SUB- SUB KELOMPOK : REHABILITASI JALAN
4 ZONA WILAYAH SSH : SELURUH WILAYAH KABUPATEN
5 AKTIVITAS : Stabilisasi dan Penguatan Tebing Polimer
6 DESKRIPSI AKTIVITAS : Stabilisasi dan Penguatan Tebing Polimer
7 SATUAN AKTIVITAS : m²
8 KOMPONEN/RINCIAN KOMPONEN
NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
I DIVISI 1. UMUM
1 Mobilisasi LS - 3.316.376,00 -
2 Galian Biasa m3 0,300 133.547,00 40.064,10
Pipa Berlubang Banyak (Perforated Pipe) untuk Pekerjaan
3 m1 1,000 61.962,00 61.962,00
Drainase Bawah Permukaan, diameter 2 inch
4 Pembersihan dan Pengupasan Lahan m2 1,000 12.612,00 12.612,00
5 Penyemprotan Polymer m2 1,000 15.430,00 15.430,00
6 Stabilisasi dengan Tanaman (Vertiper) m2 1,000 39.220,00 39.220,00
Jumlah 169.288,10
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
STABILISASI DAN PENGUATAN TEBING POLIMER
` PEKERJAAN JUMLAH (Rp)
I DIVISI 1. UMUM 169.288,10
JUMLAH (Rp) 169.288,10
PPN 10% 16.928,81
JUMLAH TOTAL (Rp) 186.216,91
Luas 1,00
ASB/m² 186.216,91
JUMLAH DIBULATKAN (Rp) 186.216,00
85
ANALISIS STANDAR BELANJA (ASB)
REHABILITASI JEMBATAN
1 KELOMPOK : KONSTRUKSI
2 SUB KELOMPOK : BIDANG JALAN
3 SUB- SUB KELOMPOK : REHABILITASI JEMBATAN
4 ZONA WILAYAH SSH : SELURUH WILAYAH KABUPATEN
5 AKTIVITAS : REHABILITASI JEMBATAN
6 DESKRIPSI AKTIVITAS : REHABILITASI JEMBATAN
P=5mL=5m
7 SATUAN AKTIVITAS : m²
8 KOMPONEN/RINCIAN KOMPONEN :
NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
I DIVISI 1. UMUM
1 Mobilisasi LS - 3.316.376,00 -
2 Manajemen dan Keselamatan Lalu Lintas LS - 780.000,00 -
3 Overdam / Kisdam LS - - -
Jumlah -
II DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK -
4 Galian Biasa m3 52,300 133.547,00 6.984.508,10
5 Timbunan Biasa dari Sumber Galian M3 20,000 575.951,00 11.519.020,00
Jumlah 18.503.528,10
III DIVISI 7. STRUKTUR -
6 Beton struktur, fc’30 MPa M3 1.342.896,00 -
7 Beton struktur, fc’20 MPa (K250) M3 44,440 1.309.131,00 58.177.781,64
8 Beton Siklop, fc’15 Mpa M3 - 3.220.490,00 -
9 Baja Tulangan Polos-BjTP 280 Kg 1.220,000 21.638,00 26.398.360,00
10 Anyaman Kawat Yang Dilas (Welded Wire Mesh) Kg 45.147,00 -
11 Penyediaan Baja Struktur Grade 250 (Kuat Leleh 250 MPa) Kg - -
12 Pemasangan Baja Struktur Kg - -
13 Pasangan Batu M3 - 952.941,00 -
14 Bronjong dengan kawat yang dilapisi Galvanis M3 - -
15 Expansion Joint Baja Bersudut M1 352.543,00 -
Landasan Elastomerik Karet Sintetis Berlapis Baja Ukuran …..
16 Buah 8,000 1.048.336,00 8.386.688,00
Mm x ….. Mm x…….. Mm
17 Sandaran (Railing) M1 10,000 144.719,00 1.447.190,00
18 Papan Nama Jembatan Buah 2,000 937.020,00 1.874.040,00
19 Pembongkaran Pasangan Batu M3 25,000 245.062,00 6.126.550,00
20 Pembongkaran Beton M3 579.287,00 -
21 Pipa Penyalur PVC M1 275.994,00 -
Jumlah 102.410.609,64
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
REHABILITASI JEMBATAN
NO PEKERJAAN JUMLAH (Rp)
I DIVISI 1. UMUM -
II DIVISI 3. PEKERJAAN TANAH DAN GEOSINTETIK 18.503.528,10
III DIVISI 7. STRUKTUR 102.410.609,64
JUMLAH (Rp) 120.914.137,74
PPN 10% 12.091.413,77
JUMLAH TOTAL (Rp) 133.005.551,51
Luas 25,00
ASB/m² 5.320.222,06
JUMLAH DIBULATKAN (Rp) 5.320.222,00
86
ANALISIS STANDAR BELANJA (ASB)
PENGADAAN DAN PEMASANGAN PAPAN PENGENAL RUAS JALAN
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : Pengadaan dan Pemasangan Papan Pengenal Ruas Jalan
3 SUB- SUB KELOMPOK : Pengadaan dan Pemasangan Papan Pengenal Ruas Jalan
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten
5 AKTIVITAS : Pengadaan dan Pemasangan Papan Pengenal Ruas Jalan
6 DESKRIPSI AKTIVITAS : Pengadaan dan Pemasangan Papan Pengenal Ruas Jalan
7 SATUAN AKTIVITAS : Unit
8 KOMPONEN/RINCIAN KOMPONEN :
NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
A TENAGA
1 Pekerja Jam 3,000 19.000,00 57.000,00
2 Tukang Jam 3,000 22.500,00 67.500,00
Jumlah 124.500,00
B BAHAN -
1 Bahan Tanah Timbunan m3 0,125 57.353,00 7.169,13
2 Beton Fc' 10 Mpa K125 m3 0,150 1.198.734,00 179.810,10
3 Papan Pengenal Ruas Jalan unit 1,000 2.400.000,00 2.400.000,00
Jumlah 2.586.979,23
C PERALATAN -
4 Sewa Mobil Pick Up Hari 1,000 350.000,00 350.000,00
Jumlah 350.000,00
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
PENGADAAN DAN PEMASANGAN PAPAN PENGENAL RUAS JALAN
No PEKERJAAN JUMLAH
A TENAGA 124.500,00
B BAHAN 2.586.979,23
C PERALATAN 350.000,00
JUMLAH (Rp) 3.061.479,23
PPN 10% 306.147,92
JUMLAH TOTAL (Rp) 3.367.627,15
JUMLAH DIBULATKAN (Rp) 3.367.000,00
87
ANALISIS STANDAR BELANJA (ASB)
REHABILITASI BENDUNG
1 KELOMPOK : KONSTRUKSI
2 SUB KELOMPOK : Bidang Irigasi
3 SUB- SUB KELOMPOK : Rehabilitasi bendung Irigasi
4 ZONA WILAYAH SSH : Semua Wilayah
5 AKTIVITAS : Rehabilitasi bendung Irigasi
6 DESKRIPSI AKTIVITAS : Rehabilitasi bendung Irigasi
7 SATUAN AKTIVITAS : Volume : 1 Pasangan Tegak Hulu P=40 m'
m' 2,000 Lantai dan mercu bendung L=5 m'
3,000 Perbaikan / Pemb. Saluran/Kirmir P=30 M'
4,000 Sayap hilir P = 5 M'
8 KOMPONEN/RINCIAN KOMPONEN
NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
A PEKERJAAN PERSIAPAN
1 Dokumentasi Set 2,000 137.856,00 275.712,00
2 Pengalihan Aliran / Kistdam m 30,000 38.571,00 1.157.130,00
3 Mutual Chek dan Survey paket 1,000 1.416.340,00 1.416.340,00
4 Papan Nama Proyek bh 1,000 251.059,00 251.059,00
Jumlah 3.100.241,00
B PEKERJAAN POKOK -
1 Pembersihan dan Striping/Kosrekan 1m2 m² 28,800 10.427,00 300.297,60
2 1 m³ Galian Tanah Biasa Sedalam ≤ 1 m' m³ 40,860 119.924,00 4.900.094,64
3 Timbunan Tanah atau Urugan Tanah Kembali ( 1 m³ ) m³ 13,520 57.353,00 775.412,56
Mortar tipe N ( untuk mutu PP setara dengan campuran
4 m³ 104,739 1.419.273,00 148.652.950,89
1PC:4PP)
Plesteran t= 1,5 cm, mortar tipe S (setara campuran 1 PC : 3
5 m² 48,000 107.343,00 5.152.464,00
PP)
6 Siaran mortar tipe M (setara campuran 1 PC : 2 PP ) m² 145,600 115.044,00 16.750.406,40
Jumlah 176.531.626,09
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
REHABILITASI BENDUNG
No PEKERJAAN
A PEKERJAAN PERSIAPAN 3.100.241,00
B PEKERJAAN POKOK 176.531.626,09
JUMLAH (Rp) 179.631.867,09
PPN 10% 17.963.186,71
JUMLAH TOTAL (Rp) 197.595.053,80
JUMLAH DIBULATKAN (Rp) 197.595.000,00
PANJANG SALURAN (M) 30,00
HARGA PER M 6.586.500,00
88
ANALISIS STANDAR BELANJA (ASB)
REHABILITASI JARINGAN IRIGASI
1 KELOMPOK : KONSTRUKSI
2 SUB KELOMPOK : Bidang Irigasi
3 SUB- SUB KELOMPOK : Rehabilitasi Jaringan Irigasi
4 ZONA WILAYAH SSH : Semua Wilayah
5 AKTIVITAS : Rehabilitasi Jaringan Irigasi
6 DESKRIPSI AKTIVITAS : Rehabilitasi Jaringan Irigasi
7 SATUAN AKTIVITAS : m³
8 KOMPONEN/RINCIAN KOMPONEN
NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
A PEKERJAAN PERSIAPAN
1 Dokumentasi Set 1,000 137.856,00 137.856,00
2 Mutual Chek dan Survey Paket 1,000 1.416.340,00 1.416.340,00
3 Papan Nama Proyek bh 1,000 251.059,00 251.059,00
Jumlah 1.805.255,00
B PEKERJAAN POKOK -
1 1 m³ Galian Tanah Biasa Sedalam ≤ 1 m' m³ 50,400 119.924,00 6.044.169,60
2 Timbunan Tanah atau Urugan Tanah Kembali ( 1 m³ ) m³ 9,800 57.353,00 562.059,40
Mortar tipe N ( untuk mutu PP setara dengan campuran
3 m³ 99,400 1.419.273,00 141.075.736,20
1PC:4PP)
Plesteran t= 1,5 cm, mortar tipe S (setara campuran 1 PC : 3
4 m² 70,000 107.343,00 7.514.010,00
PP)
5 Siaran mortar tipe M (setara campuran 1 PC : 2 PP ) m² 84,000 115.044,00 9.663.696,00
Jumlah 164.859.671,20
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
REHABILITASI JARINGAN IRIGASI
No PEKERJAAN JUMLAH
A PEKERJAAN PERSIAPAN 1.805.255,00
B PEKERJAAN POKOK 164.859.671,20
JUMLAH (Rp) 166.664.926,20
PPN 10% 16.666.492,62
JUMLAH TOTAL (Rp) 183.331.418,82
JUMLAH DIBULATKAN (Rp) 183.331.000,00
VOLUME SALURAN (M3) 49,00
HARGA PER M3 3.741.449,00
89
ANALISIS STANDAR BELANJA (ASB)
REHABILITASI SALURAN DRAINASE
1 KELOMPOK : KONSTRUKSI
2 SUB KELOMPOK : Bidang Drainase
3 SUB- SUB KELOMPOK : Rehabilitasi Saluran Drainase
4 ZONA WILAYAH SSH : Semua Wilayah
5 AKTIVITAS : Rehabilitasi Saluran Drainase
6 DESKRIPSI AKTIVITAS : Rehabilitasi Saluran Drainase
7 SATUAN AKTIVITAS : m
8 KOMPONEN/RINCIAN KOMPONEN
NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
1 Mobilisasi Trip 0,050 728.553,00 36.427,65
2 Manajemen dan Keselamatan Lalu Lintas LS 0,030 2.427.995,00 72.839,85
3 Galian Untuk selokan Drainase Dan Saluran m³ 31,000 36.827,00 1.141.637,00
4 Pasangan Batu Dengan Mortar m³ 31,000 908.220,00 28.154.820,00
5 Timbunan Biasa dari Sumber Galian m³ 5,000 325.436,00 1.627.180,00
JUMLAH (Rp) 31.032.904,50
PPN 10% 3.103.290,45
JUMLAH TOTAL (Rp) 34.136.194,95
JUMLAH DIBULATKAN (Rp) 34.136.000,00
PANJANG SALURAN (M) 100,00
HARGA PER M 341.360,00
90
ANALISIS STANDAR BELANJA (ASB)
PEMBANGUNAN EMBUNG
1 KELOMPOK : KONSTRUKSI
2 SUB KELOMPOK : Bidang Drainase
3 SUB- SUB KELOMPOK : Pembangunan Embung
4 ZONA WILAYAH SSH : Semua Wilayah
5 AKTIVITAS : Pembangunan Embung
DESKRIPSI AKTIVITAS : Pembangunan Embung
6 SATUAN AKTIVITAS : m²
7 KOMPONEN/RINCIAN KOMPONEN
NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
A PEKERJAAN PERSIAPAN
1 Dokumentasi Set 1,000 137.856,00 137.856,00
3 Mutual Chek dan Survey paket 1,000 1.416.340,00 1.416.340,00
4 Papan Nama Proyek bh 1,000 251.059,00 251.059,00
Jumlah 1.805.255,00
B PEKERJAAN POKOK -
1 Pembersihan dan Striping/Kosrekan m² 100,000 10.427,00 1.042.700,00
2 1 m³ Galian Tanah Biasa Sedalam ≤ 1 m' m³ 368,000 119.924,00 44.132.032,00
3 1 m³ Galian Tanah Biasa > 1 m' s.d 2 m' m³ 30.000,000 117.314,00 3.519.420.000,00
4 Timbunan Tanah atau Urugan Tanah Kembali ( 1 m³ ) m³ 150,220 57.353,00 8.615.567,66
Mortar tipe N ( untuk mutu PP setara dengan campuran
5 m² 1.023,500 1.419.273,00 1.452.625.915,50
1PC:4PP)
Plesteran t= 1,5 cm, mortar tipe S (setara campuran 1 PC : 3
6 m² 115,000 107.343,00 12.344.445,00
PP)
7 Siaran mortar tipe M (setara campuran 1 PC : 2 PP ) m² 671,600 115.044,00 77.263.550,40
8 Pasangan pipa suling-suling m 115,000 41.686,00 4.793.890,00
Jumlah 5.120.238.100,56
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
PEMBANGUNAN EMBUNG
No PEKERJAAN JUMLAH
A PEKERJAAN PERSIAPAN 1.805.255,00
B PEKERJAAN POKOK 5.120.238.100,56
JUMLAH (Rp) 5.122.043.355,56
PPN 10% 512.204.335,56
JUMLAH TOTAL (Rp) 5.634.247.691,12
JUMLAH DIBULATKAN (Rp) 5.634.247.000,00
LUAS SALURAN (M2) 10.000,00
HARGA PER M2 563.425,00
91
ANALISIS STANDAR BELANJA (ASB)
PEMBANGUNAN KOLAM RETENSI DAN REHABILITASI STATION POMPA BANJIR
1 KELOMPOK : KONSTRUKSI
2 SUB KELOMPOK : Bidang Drainase
3 SUB- SUB KELOMPOK : Pembangunan Kolam Retensi
4 ZONA WILAYAH SSH : Semua Wilayah
5 AKTIVITAS : Pembangunan Kolam Retensi
6 DESKRIPSI AKTIVITAS : Pembangunan Kolam Retensi
7 SATUAN AKTIVITAS : m²
8 KOMPONEN/RINCIAN KOMPONEN
NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
A PEKERJAAN PERSIAPAN
1 Dokumentasi Set 1,000 137.856,00 137.856,00
3 Mutual Chek dan Survey Paket 1,000 1.416.340,00 1.416.340,00
4 Papan Nama Proyek bh 1,000 251.059,00 251.059,00
Jumlah 1.805.255,00
B PEKERJAAN POKOK -
1 Pembersihan dan Striping/Kosrekan 1m2 m² 100,000 10.427,00 1.042.700,00
2 1 m³ Galian Tanah Biasa Sedalam ≤ 1 m' m³ 147,200 119.924,00 17.652.812,80
3 1 m³ Galian Tanah Biasa > 1 m' s.d 2 m' m³ 5.600,000 117.314,00 656.958.400,00
4 Timbunan Tanah atau Urugan Tanah Kembali m³ 150,220 57.353,00 8.615.567,66
Mortar tipe N ( untuk mutu PP setara dengan campuran
5 m² 561,200 1.419.273,00 796.496.007,60
1PC:4PP)
Plesteran t= 1,5 cm, mortar tipe S (setara campuran 1 PC : 3
6 m² 115,000 107.343,00 12.344.445,00
PP)
7 Siaran mortar tipe M (setara campuran 1 PC : 2 PP ) m² 671,600 115.044,00 77.263.550,40
8 Pasangan pipa suling-suling m 115,000 41.686,00 4.793.890,00
9 Perbaikan Pintu Air ( 2 Drat reel pintu ) bh 1,000 6.963.583,00 6.963.583,00
Jumlah 1.582.130.956,46
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
PEMBANGUNAN KOLAM RETENSI
No PEKERJAAN JUMLAH
A PEKERJAAN PERSIAPAN 1.805.255,00
B PEKERJAAN POKOK 1.582.130.956,46
JUMLAH (Rp) 1.583.936.211,46
PPN 10% 158.393.621,15
JUMLAH TOTAL (Rp) 1.742.329.832,61
JUMLAH DIBULATKAN (Rp) 1.742.329.000,00
LUAS SALURAN (M2) 2.800,00
HARGA PER M2 622.260,00
REHABILITASU STATION POMPA BANJIR 622.260,00
92
ANALISIS STANDAR BELANJA (ASB)
PEMBANGUNAN PERKUATAN TEBING
1 KELOMPOK : KONSTRUKSI
2 SUB KELOMPOK : Bidang Drainase
3 SUB- SUB KELOMPOK : Pembangunan Perkuatan Tebing
4 ZONA WILAYAH SSH : Semua Wilayah
5 AKTIVITAS : Pembangunan Perkuatan Tebing
DESKRIPSI AKTIVITAS : Pembangunan Perkuatan Tebing
6 SATUAN AKTIVITAS : m³
7 KOMPONEN/RINCIAN KOMPONEN
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
PEMBANGUNAN PERKUATAN TEBING
No PEKERJAAN JUMLAH
A PEKERJAAN PERSIAPAN 328.768,80
B PEKERJAAN POKOK 1.654.247,85
JUMLAH (Rp) 1.983.016,65
PPN 10% 198.301,67
JUMLAH TOTAL (Rp) 2.181.318,32
JUMLAH DIBULATKAN (Rp) 2.181.000,00
93
ANALISIS STANDAR BELANJA (ASB)
REHABILITASI SALURAN DRAINASE GORONG-GORONG
1 KELOMPOK : KONSTRUKSI
2 SUB KELOMPOK : Bidang Drainase
3 SUB- SUB KELOMPOK : Rehabilitasi Saluran Drainase Gorong-Gorong
4 ZONA WILAYAH SSH : Semua Wilayah
5 AKTIVITAS : Rehabilitasi Saluran Drainase Gorong-Gorong
DESKRIPSI AKTIVITAS : Rehabiltasi Saluran Drainase gorong-gorong
6 SATUAN AKTIVITAS : m
7 KOMPONEN/RINCIAN KOMPONEN
NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN SUB-TOTAL
1 Mobilisasi Trip 0,050 728.553,00 36.427,65
2 Manajemen dan Keselamatan Lalu Lintas Lot 0,023 2.427.995,00 55.843,89
3 Galian untuk Selokan Drainase dan Saluran Air Pakai Buruh m³ 0,400 95.833,00 38.333,20
4 Beton K250 (fc’ 20) untuk struktur drainase beton minor m³ 0,480 2.024.315,00 971.671,20
5 Baja Tulangan untuk struktur drainase beton minor m³ 94,530 21.187,00 2.002.807,11
6 Galian Perkerasan Beton m³ 0,200 200.733,00 40.146,60
7 Timbunan Pilihan dari sumber galian m³ 0,480 325.436,00 156.209,28
JUMLAH 3.301.438,93
PPN 10% 330.143,89
JUMLAH TOTAL 3.631.582,82
JUMLAH DIBULATKAN (Rp) 3.631.000,00
DESKRIPSI AKTIVITAS : Membongkar Armature dan Memasang Armature LED 100-140 Watt
6 SATUAN AKTIVITAS : TC
7 KOMPONEN/RINCIAN KOMPONEN
NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
I PEKERJAAN ELEKTRIKAL
1 Pekerjaan Pembongkaran Armature Bh 1,000 90.723,00 90.723,00
2 Pekerjaan Pemasangan Armatur LED 100-140 watt Unit 1,000 4.302.647,00 4.302.647,00
Jumlah 4.393.370,00
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
PENINGKATAN PJU LED 100-140 Watt
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN ELEKTRIKAL 4.393.370,00
JUMLAH (Rp) 4.393.370,00
PPN 10% 439.337,00
JUMLAH TOTAL (Rp) 4.832.707,00
JUMLAH DIBULATKAN (Rp) 4.832.000,00
94
ANALISIS STANDAR BELANJA (ASB)
PENGGANTIAN BOX APP
1 KELOMPOK : Konstruksi
2 SUB KELOMPOK : Penggantian Box APP
3 SUB- SUB KELOMPOK : Penggantian Box APP
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Penggantian Box APP
DESKRIPSI AKTIVITAS : Mengganti Box APP
6 SATUAN AKTIVITAS : Set
7 KOMPONEN/RINCIAN KOMPONEN
NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
I PEKERJAAN ELEKTRIKAL
1 Pekerjaan Penggantian Box APP Gendong Set 1,000 3.852.222,00 3.852.222,00
JUMLAH (Rp) 3.852.222,00
PPN 10% 385.222,20
JUMLAH TOTAL (Rp) 4.237.444,20
JUMLAH DIBULATKAN (Rp) 4.237.000,00
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
PENGGANTIAN KOMPONEN BOX APP
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN ELEKTRIKAL 1.169.429,00
JUMLAH (Rp) 1.169.429,00
PPN 10% 116.942,90
JUMLAH TOTAL (Rp) 1.286.371,90
JUMLAH DIBULATKAN (Rp) 1.286.000,00
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
PEMASANGAN JARINGAN KABEL BAWAH TANAH PJU
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN TANAH 35.977,20
II PEKERJAAN ELEKTRIKAL 216.031,20
JUMLAH (Rp) 252.008,40
PPN 10% 25.200,84
JUMLAH TOTAL (Rp) 277.209,24
JUMLAH DIBULATKAN (Rp) 277.000,00
95
ANALISIS STANDAR BELANJA (ASB)
PEMBANGUNAN TIANG BULAT 7 M, ARMATURE PJU SODIUM 150 WATT, JARINGAN KABEL UDARA, BOX APP DAN BPUJL
1 KELOMPOK : Konstruksi
2 SUB KELOMPOK : Pembangunan PJU
3 SUB- SUB KELOMPOK : Pembangunan PJU
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
Pembangunan Tiang Bulat 7 Mtr, Armature PJU Sodium 150 Watt, Jaringan Kabel
5 AKTIVITAS :
Udara, Box APP dan BPUJL
Membangun Unit PJU lengkap pondasi, Tiang bulat 7 Mtr, Armature PJU Sodium 150
6 DESKRIPSI AKTIVITAS :
Watt, Jaringan Kabel Udara, Box APP dan BPUJL
7 SATUAN AKTIVITAS : TC
8 KOMPONEN/RINCIAN KOMPONEN
NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
I PEKERJAAN TANAH
1 Penggalian 1 m3 tanah biasa sedalam 1 m m³ 0,192 119.924,00 23.025,41
Jumlah 23.025,41
II PEKERJAAN BETON -
Membuat 1 m3 beton mutu f'c = 14.5 MPa slump (120 ± 20)
1 m³ 0,240 1.219.480,00 292.675,20
mm
2 Pembesian 10 Kg dengan besi polos atau besi ulir Kg 13,750 20.011,00 275.151,25
Jumlah 567.826,45
III PEKERJAAN PELESTERAN -
1 Pemasangan 1 m2 acian m2 0,480 58.187,00 27.929,76
Jumlah 27.929,76
IV PEKERJAAN ELEKTRIKAL -
1 Pekerjaan Pemasangan Tiang Bulat 7 m Unit 1,000 4.199.462,00 4.199.462,00
Pekerjaan Pemasangan Armatur Lengkap Sodium 150 Watt
2 Unit 1,000 2.874.347,00 2.874.347,00
Tipe Cobra
3 Pekerjaan Pemasangan Aksesoris jaringan Set 2,000 89.473,00 178.946,00
4 Pekerjaan Pemasangan Tap Connector Set 1,000 62.893,00 62.893,00
5 Pekerjaan Pemasangan Kabel TIC 2 x 10 mm m 50,000 32.401,00 1.620.050,00
6 Pekerjaan Pemasangan Kabel NYM 2 x 1,5 mm m 4,000 44.281,00 177.124,00
7 Pekerjaan Pemasangan Box APP Gendong daya 1300 VA Set 1,000 6.461.405,00 6.461.405,00
8 Pekerjaan Pemasangan Grounding Set 1,000 155.929,00 155.929,00
Jumlah 15.730.156,00
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
PEMBANGUNAN TIANG BULAT 7 M, ARMATURE PJU SODIUM 150 WATT, JARINGAN KABEL UDARA, BOX APP DAN BPUJL
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN TANAH 23.025,41
II PEKERJAAN BETON 567.826,45
III PEKERJAAN PELESTERAN 27.929,76
IV PEKERJAAN ELEKTRIKAL 15.730.156,00
JUMLAH (Rp) 16.348.937,62
PPN 10% 1.634.893,76
JUMLAH TOTAL (Rp) 17.983.831,38
JUMLAH DIBULATKAN (Rp) 17.983.000,00
96
ANALISIS STANDAR BELANJA (ASB)
PEMBANGUNAN TIANG BULAT 7 M, ARMATURE LED 60-90 WATT, JARINGAN KABEL UDARA, BOX APP DAN BPUJL
1 KELOMPOK : Konstruksi
2 SUB KELOMPOK : Pembangunan PJU
3 SUB- SUB KELOMPOK : Pembangunan PJU
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
Pembangunan Tiang bulat 7 Mtr, Armature LED 60-90 Watt, Jaringan Kabel Udara,
5 AKTIVITAS :
Box APP dan BPUJL
Membangun Unit PJU lengkap pondasi, Tiang bulat 7 Mtr, Armature LED 60-90 Watt,
6 DESKRIPSI AKTIVITAS :
Jaringan Kabel Udara, Box APP dan BPUJL
7 SATUAN AKTIVITAS : TC
8 KOMPONEN/RINCIAN KOMPONEN
NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
I PEKERJAAN TANAH
1 Penggalian 1 m3 tanah biasa sedalam 1 m m³ 0,192 119.924,00 23.025,41
Jumlah 23.025,41
II PEKERJAAN BETON -
Membuat 1 m3 beton mutu f'c = 14.5 MPa slump (120 ± 20)
1 m³ 0,240 1.269.586,00 304.700,64
mm
2 Pembesian 10 Kg dengan besi polos atau besi ulir Kg 1,375 20.011,00 27.519,13
Jumlah 332.219,77
III PEKERJAAN PELESTERAN -
1 Pemasangan 1 m2 acian m2 0,480 58.187,00 27.929,76
Jumlah 27.929,76
IV PEKERJAAN ELEKTRIKAL -
1 Pekerjaan Pemasangan Tiang Bulat 7 m Unit 1,000 4.199.462,00 4.199.462,00
2 Pekerjaan Pemasangan Armatur LED 60-90 watt Unit 1,000 3.152.647,00 3.152.647,00
3 Pekerjaan Pemasangan Aksesoris jaringan Set 2,000 89.473,00 178.946,00
4 Pekerjaan Pemasangan Tap Connector Set 1,000 62.893,00 62.893,00
5 Pekerjaan Pemasangan Kabel TIC 2 x 10 mm m 50,000 32.401,00 1.620.050,00
6 Pekerjaan Pemasangan Kabel NYM 2 x 1,5 mm m 4,000 44.281,00 177.124,00
7 Pekerjaan Pemasangan Box APP Gendong daya 1300 VA Set 1,000 6.461.405,00 6.461.405,00
8 Pekerjaan Pemasangan Grounding Set 1,000 155.929,00 155.929,00
Jumlah 16.008.456,00
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
PEMBANGUNAN TIANG BULAT 7 M, ARMATURE LED 60-90 WATT, JARINGAN KABEL UDARA, BOX APP DAN BPUJL
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN TANAH 23.025,41
II PEKERJAAN BETON 332.219,77
III PEKERJAAN PELESTERAN 27.929,76
IV PEKERJAAN ELEKTRIKAL 16.008.456,00
JUMLAH (Rp) 16.391.630,94
PPN 10% 1.639.163,09
JUMLAH TOTAL (Rp) 18.030.794,03
JUMLAH DIBULATKAN (Rp) 18.030.000,00
97
ANALISIS STANDAR BELANJA (ASB)
PEMBANGUNAN TIANG BULAT 7 M, PJU TENAGA SURYA ALL IN ONE 40 WATT
1 KELOMPOK : Konstruksi
2 SUB KELOMPOK : Pembangunan PJU
3 SUB- SUB KELOMPOK : Pembangunan PJU
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Pembangunan Tiang bulat 7 Mtr, PJU Tenaga Surya All in one 40 watt
DESKRIPSI AKTIVITAS : Membangun Unit PJU lengkap pondasi, Tiang bulat 7 Mtr, PJU Tenaga Surya All in
6 SATUAN AKTIVITAS : TC
7 KOMPONEN/RINCIAN KOMPONEN
NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
I PEKERJAAN TANAH
1 Penggalian 1 m3 tanah biasa sedalam 2 m m³ 0,192 147.037,00 28.231,10
Jumlah 28.231,10
II PEKERJAAN BETON -
1 Membuat 1 m3 beton mutu f'c = 16.9 MPa m³ 0,240 1.255.198,00 301.247,52
2 Pemasangan 10 Kg kabel prategang (prestressed) polos/strands Kg 13,750 20.011,00 275.151,25
Jumlah 576.398,77
III PEKERJAAN PLESTERAN -
1 Pemasangan 1 m2 plesteran dengan mortar siap pakai (MSP) m2 0,480 129.026,00 61.932,48
Jumlah 61.932,48
IV PEKERJAAN ELEKTRIKAL -
1 Pekerjaan Pemasangan Tiang Bulat 7 m PJU Tenaga Surya Unit 1,000 5.758.391,00 5.758.391,00
2 Pekerjaan Pemasangan Armatur PJU TS All In One 40 Watt Unit 1,000 14.577.897,00 14.577.897,00
Jumlah 20.336.288,00
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
PEMBANGUNAN TIANG BULAT 7 M, PJU TENAGA SURYA ALL IN ONE 40 WATT
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN TANAH 28.231,10
II PEKERJAAN BETON 576.398,77
III PEKERJAAN PLESTERAN 61.932,48
IV PEKERJAAN ELEKTRIKAL 20.336.288,00
JUMLAH (Rp) 21.002.850,35
PPN 10% 2.100.285,04
JUMLAH TOTAL (Rp) 23.103.135,39
JUMLAH DIBULATKAN (Rp) 23.103.000,00
98
ANALISIS STANDAR BELANJA (ASB)
PEMBANGUNAN TIANG BULAT 3,5 M, ARMATURE LED 12 WATT, JARINGAN KABEL UDARA, BOX APP DAN BPUJL
1 KELOMPOK : Konstruksi
2 SUB KELOMPOK : Pembangunan PJU
3 SUB- SUB KELOMPOK : Pembangunan PJU Lingkungan
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
Pembangunan Tiang Bulat 3.5 Mtr, Armature LED 12 Watt, Jaringan Kabel Bawah
5 AKTIVITAS :
Tanah, Box APP dan BPUJL
Membangun Unit PJU lengkap pondasi, Tiang Bulat 3.5 Mtr, Armature LED 12 Watt,
6 DESKRIPSI AKTIVITAS :
Jaringan Kabel Bawah Tanah, Box APP dan BPUJL
7 SATUAN AKTIVITAS : TC
8 KOMPONEN/RINCIAN KOMPONEN
NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
I PEKERJAAN TANAH
1 Penggalian 1 m3 tanah biasa sedalam 1 m m³ 1,290 119.924,00 154.701,96
Jumlah 154.701,96
II PEKERJAAN BETON -
Membuat 1 m3 beton mutu f'c = 14.5 MPa slump (120 ± 20)
1 m³ 0,575 1.219.480,00 701.201,00
mm
2 Pembesian 10 Kg dengan besi polos atau besi ulir Kg 4,448 20.011,00 89.008,93
Jumlah 790.209,93
III PEKERJAAN ELEKTRIKAL -
1 Pekerjaan Pemasangan Tiang Bulat Parabola Cabang 1 h=3,5 m Unit 1,000 2.400.548,00 2.400.548,00
2 Pekerjaan Pemasangan Armature LED 12 Watt Unit 1,000 1.558.761,00 1.558.761,00
3 Pekerjaan Pemasangan Aksesoris jaringan Set 2,000 89.473,00 178.946,00
4 Pekerjaan Pemasangan Kabel NYGBY 3 x 2,5 mm Set 20,000 95.637,00 1.912.740,00
5 Pekerjaan Pemasangan Kabel TIC 2 x 10 mm m 20,000 32.401,00 648.020,00
6 Pekerjaan Pemasangan Kabel NYM 2 x 1,5 mm m 7,000 44.281,00 309.967,00
7 Pekerjaan Pemasangan Box APP KWH Meter daya 1300 VA Set 1,000 6.335.572,00 6.335.572,00
8 Pekerjaan Pemasangan MCB di Tiang Bh 1,000 118.983,00 118.983,00
9 Pekerjaan Pemasangan Grounding Set 1,000 155.929,00 155.929,00
Jumlah 13.619.466,00
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
PEMBANGUNAN TIANG BULAT 3,5 M, ARMATURE LED 12 WATT, JARINGAN KABEL UDARA, BOX APP DAN BPUJL
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN TANAH 154.701,96
II PEKERJAAN BETON 790.209,93
III PEKERJAAN ELEKTRIKAL 13.619.466,00
JUMLAH (Rp) 14.564.377,89
PPN 10% 1.456.437,79
JUMLAH TOTAL (Rp) 16.020.815,68
JUMLAH DIBULATKAN (Rp) 16.020.000,00
99
ANALISIS STANDAR BELANJA (ASB)
PEMBANGUNAN TIANG OKTAGONAL 9 M, ARMATURE PJU SODIUM 250 WATT TIPE COBRA, JARINGAN KABEL UDARA, BOX APP
DAN BPUJL
1 KELOMPOK : Konstruksi
2 SUB KELOMPOK : Pembangunan PJU
3 SUB- SUB KELOMPOK : Pembangunan PJU
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
Pembangunan Tiang Oktagonal 9 Mtr, Armature PJU Sodium 250 Watt tipe Cobra,
5 AKTIVITAS :
Jaringan Kabel Udara, Box APP dan BPUJL
Membangun Unit PJU lengkap pondasi, Tiang Oktagonal 9 Mtr, Armature PJU
6 DESKRIPSI AKTIVITAS :
Sodium 250 Watt tipe Cobra, Jaringan Kabel Udara, Box APP dan BPUJL
7 SATUAN AKTIVITAS : TC
8 KOMPONEN/RINCIAN KOMPONEN
NO. URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN SUB-TOTAL
I PEKERJAAN TANAH
1 Penggalian 1 m3 tanah biasa sedalam 1 m m³ 0,240 119.924,00 28.781,76
Jumlah 28.781,76
II PEKERJAAN BETON -
Membuat 1 m3 beton mutu f'c = 14.5 MPa slump (120 ± 20)
1 m³ 0,288 1.219.480,00 351.210,24
mm
2 Pembesian 10 Kg dengan besi polos atau besi ulir Kg 1,676 20.011,00 33.530,43
Jumlah 384.740,67
III PEKERJAAN PELESTERAN -
1 Pemasangan 1 m2 acian m2 0,480 58.187,00 27.929,76
Jumlah 27.929,76
IV PEKERJAAN ELEKTRIKAL -
1 Pekerjaan Pemasangan Tiang Oktagonal 9 m Unit 1,000 6.656.724,00 6.656.724,00
Pekerjaan Pemasangan Armatur Lengkap Sodium 250 Watt
2 Unit 1,000 2.950.247,00 2.950.247,00
Tipe Cobra
3 Pekerjaan Pemasangan Aksesoris jaringan Set 2,000 89.473,00 178.946,00
4 Pekerjaan Pemasangan Tap Connector Set 1,000 62.893,00 62.893,00
5 Pekerjaan Pemasangan Kabel TIC 2 x 10 mm m 50,000 32.401,00 1.620.050,00
6 Pekerjaan Pemasangan Kabel NYM 2 x 1,5 mm m 4,000 44.281,00 177.124,00
7 Pekerjaan Pemasangan Box APP Gendong daya 1300 VA Set 1,000 6.461.405,00 6.461.405,00
8 Pekerjaan Pemasangan Grounding Set 1,000 155.929,00 155.929,00
Jumlah 18.263.318,00
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
PEMBANGUNAN TIANG OKTAGONAL 9 M, ARMATURE PJU SODIUM 250 WATT TIPE COBRA, JARINGAN KABEL UDARA, BOX APP
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN TANAH 28.781,76
II PEKERJAAN BETON 384.740,67
III PEKERJAAN PELESTERAN 27.929,76
IV PEKERJAAN ELEKTRIKAL 18.263.318,00
JUMLAH (Rp) 18.704.770,19
PPN 10% 1.870.477,02
JUMLAH TOTAL (Rp) 20.575.247,21
JUMLAH DIBULATKAN (Rp) 20.575.000,00
100
ANALISIS STANDAR BELANJA (ASB)
PEMBANGUNAN TIANG OKTAGONAL 9 M, ARMATURE LED 100-140 WATT, JARINGAN KABEL UDARA, BOX APP DAN BPUJL
1 KELOMPOK : Konstruksi
2 SUB KELOMPOK : Pembangunan PJU
3 SUB- SUB KELOMPOK : Pembangunan PJU
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
Pembangunan Tiang Oktagonal 9 Mtr, Armature LED 100-140 Watt , Jaringan Kabel
5 AKTIVITAS :
Udara, Box APP dan BPUJL
Membangun Unit PJU lengkap pondasi, Tiang Oktagonal 9 Mtr, Armature LED 100-
DESKRIPSI AKTIVITAS :
140 Watt , Jaringan Kabel Udara, Box APP dan BPUJL
6 SATUAN AKTIVITAS : TC
7 KOMPONEN/RINCIAN KOMPONEN
NO. URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH
I PEKERJAAN TANAH
1 Penggalian 1 m3 tanah biasa sedalam 1 m m³ 0,240 119.924,00 28.781,76
Jumlah 28.781,76
II PEKERJAAN BETON -
Membuat 1 m3 beton mutu f'c = 14.5 MPa slump (120 ± 20)
1 m³ 0,288 1.219.480,00 351.210,24
mm
2 Pembesian 10 Kg dengan besi polos atau besi ulir Kg 16,756 20.011,00 335.304,32
Jumlah 686.514,56
III PEKERJAAN PELESTERAN -
1 Pemasangan 1 m2 acian m2 0,480 58.187,00 27.929,76
Jumlah 27.929,76
IV PEKERJAAN ELEKTRIKAL -
1 Pekerjaan Pemasangan Tiang Oktagonal 9 m Unit 1,000 6.656.724,00 6.656.724,00
2 Pekerjaan Pemasangan Armatur LED 100-140 watt Unit 1,000 4.302.647,00 4.302.647,00
3 Pekerjaan Pemasangan Aksesoris jaringan Set 2,000 89.473,00 178.946,00
4 Pekerjaan Pemasangan Tap Connector Set 1,000 62.893,00 62.893,00
5 Pekerjaan Pemasangan Kabel TIC 2 x 10 mm m 50,000 32.401,00 1.620.050,00
6 Pekerjaan Pemasangan Kabel NYM 2 x 1,5 mm m 4,000 44.281,00 177.124,00
7 Pekerjaan Pemasangan Box APP Gendong daya 1300 VA Set 1,000 6.461.405,00 6.461.405,00
8 Pekerjaan Pemasangan Grounding Set 1,000 155.929,00 155.929,00
Jumlah 19.615.718,00
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
PEMBANGUNAN TIANG OKTAGONAL 9 M, ARMATURE LED 100-140 WATT, JARINGAN KABEL UDARA, BOX APP DAN BPUJL
101
ANALISIS STANDAR BELANJA (ASB)
PEMBANGUNAN TIANG 11 M STANG GANDA, ARMATURE PJU SODIUM 250 WATT TIPE KEONG, JARINGAN KABEL BAWAH TANAH,
BOX APP DAN BPUJL
1 KELOMPOK : Konstruksi
2 SUB KELOMPOK : Pembangunan PJU
3 SUB- SUB KELOMPOK : Pembangunan PJU
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
Pembangunan Tiang 11 Mtr Stang Ganda, Armature PJU Sodium 250 Watt Tipe
5 AKTIVITAS :
Keong, Jaringan Kabel Bawah Tanah, Box APP dan BPUJL
Membangun Unit PJU lengkap pondasi, Tiang Oktagonal 11 Mtr Stang Ganda,
6 DESKRIPSI AKTIVITAS : Armature PJU Sodium 250 Watt tipe keong, Jaringan Kabel Bawah Tanah, Box APP
dan BPUJL
7 SATUAN AKTIVITAS : TC
8 KOMPONEN/RINCIAN KOMPONEN
NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
I PEKERJAAN TANAH
1 Penggalian 1 m3 tanah biasa sedalam 1 m m³ 3,450 119.924,00 413.737,80
Jumlah 413.737,80
II PEKERJAAN BETON -
Membuat 1 m3 beton mutu f'c = 14.5 MPa slump (120 ± 20)
1 m³ 0,575 1.269.586,00 730.011,95
mm
2 Pembesian 10 Kg dengan besi polos atau besi ulir Kg 19,760 20.011,00 395.417,36
Jumlah 1.125.429,31
III PEKERJAAN PELESTERAN -
1 Pemasangan 1 m2 acian m2 0,600 58.187,00 34.912,20
Jumlah 34.912,20
IV PEKERJAAN ELEKTRIKAL -
1 Pekerjaan Pemasangan Tiang Oktagonal 11 m Stang Ganda Unit 1,000 8.169.952,00 8.169.952,00
Pekerjaan Pemasangan Armatur Lengkap Sodium 250 Watt
2 Unit 2,000 5.989.122,00 11.978.244,00
Tipe Keong
3 Pekerjaan Pemasangan Jaringan Kabel Bawah Tanah PJU m 33,000 196.392,00 6.480.936,00
4 Pekerjaan Pemasangan Kabel NYM 2 x 1,5 mm m 30,000 44.281,00 1.328.430,00
5 Pekerjaan Pemasangan MCB di Tiang Bh 2,000 118.983,00 237.966,00
6 Pekerjaan Pemasangan Box APP Duduk daya 1300 VA Set 1,000 10.174.975,00 10.174.975,00
Jumlah 38.370.503,00
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
PEMBANGUNAN TIANG 11 M STANG GANDA, ARMATURE PJU SODIUM 250 WATT TIPE KEONG, JARINGAN KABEL BAWAH TANAH,
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN TANAH 413.737,80
II PEKERJAAN BETON 1.125.429,31
III PEKERJAAN PELESTERAN 34.912,20
IV PEKERJAAN ELEKTRIKAL 38.370.503,00
JUMLAH (Rp) 39.944.582,31
PPN 10% 3.994.458,23
JUMLAH TOTAL (Rp) 43.939.040,54
JUMLAH DIBULATKAN (Rp) 43.939.000,00
102
ANALISIS STANDAR BELANJA (ASB)
PEMBANGUNAN TIANG OKTAGONAL 9 M, ARMATURE LED SMART 120 WATT, JARINGAN KABEL UDARA, BOX APP DAN BPUJL
1 KELOMPOK : Konstruksi
2 SUB KELOMPOK : Pembangunan PJU
3 SUB- SUB KELOMPOK : Pembangunan PJU
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
Pembangunan Tiang Oktagonal 9 Mtr, Armature LED Smart 120 Watt , Jaringan
5 AKTIVITAS :
Kabel Udara, Box APP dan BPUJL
Membangun Unit PJU lengkap pondasi, Tiang Oktagonal 9 Mtr, Armature LED Smart
6 DESKRIPSI AKTIVITAS :
120 Watt , Jaringan Kabel Udara, Box APP dan BPUJL
7 SATUAN AKTIVITAS : TC
8 KOMPONEN/RINCIAN KOMPONEN
NO. URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN SUB-TOTAL
I PEKERJAAN TANAH
1 Penggalian 1 m3 tanah biasa sedalam 1 m m³ 0,240 119.924,00 28.781,76
Jumlah 28.781,76
II PEKERJAAN BETON -
Membuat 1 m3 beton mutu f'c = 14.5 MPa slump (120 ± 20)
1 m³ 0,288 1.219.480,00 351.210,24
mm
2 Pembesian 10 Kg dengan besi polos atau besi ulir Kg 16,756 20.011,00 335.304,32
Jumlah 686.514,56
III PEKERJAAN PELESTERAN -
1 Pemasangan 1 m2 acian m2 0,480 58.187,00 27.929,76
Jumlah 27.929,76
IV PEKERJAAN ELEKTRIKAL -
1 Pekerjaan Pemasangan Tiang Oktagonal 9 m Unit 1,000 6.656.724,00 6.656.724,00
2 Pekerjaan Pemasangan Armatur LED Smart 120 watt Unit 1,000 8.983.147,00 8.983.147,00
3 Pekerjaan Pemasangan Aksesoris jaringan Set 2,000 89.473,00 178.946,00
4 Pekerjaan Pemasangan Tap Connector Set 1,000 62.893,00 62.893,00
5 Pekerjaan Pemasangan Kabel TIC 2 x 10 mm m 50,000 32.401,00 1.620.050,00
6 Pekerjaan Pemasangan Kabel NYM 2 x 1,5 mm m 4,000 44.281,00 177.124,00
7 Pekerjaan Pemasangan Box APP Gendong daya 1300 VA Set 1,000 6.461.405,00 6.461.405,00
8 Pekerjaan Pemasangan Grounding Set 1,000 155.929,00 155.929,00
Jumlah 24.296.218,00
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
PEMBANGUNAN TIANG OKTAGONAL 9 M, ARMATURE LED SMART 120 WATT, JARINGAN KABEL UDARA, BOX APP DAN BPUJL
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN TANAH 28.781,76
II PEKERJAAN BETON 686.514,56
III PEKERJAAN PELESTERAN 27.929,76
IV PEKERJAAN ELEKTRIKAL 24.296.218,00
JUMLAH (Rp) 25.039.444,08
PPN 10% 2.503.944,41
JUMLAH TOTAL (Rp) 27.543.388,48
JUMLAH DIBULATKAN (Rp) 27.543.000,00
103
ANALISIS STANDAR BELANJA (ASB)
SUMUR RESAPAN
1 KELOMPOK : Konstruksi
2 SUB KELOMPOK : Pembangunan Sumur
3 SUB- SUB KELOMPOK : Pembangunan Sumur Resapan
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Pembangunan Sumur Resapan
6 DESKRIPSI AKTIVITAS : Membangun Sumur Resapan
7 SATUAN AKTIVITAS : Unit
8 KOMPONEN/RINCIAN KOMPONEN :
NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
I PEKERJAAN PERSIAPAN
1 Pek. Pembersihan Lapangan dan perataan m¹ 63,000 25.719,00 1.620.297,00
Jumlah 1.620.297,00
II PEKERJAAN SUMUR RESAPAN -
1 Pas. Aanstamping m³ 2,000 650.982,00 1.301.964,00
2 Galian tanah m³ 10,500 119.924,00 1.259.202,00
3 Pas. bata 1 bata 1 : 3 m² 3,600 356.167,00 1.282.201,20
4 Adukan beton 1 Pc : 2 Ps : 3 Kr. m³ 0,150 1.288.543,00 193.281,45
5 Tulangan beton besi U-24 Kg 7,500 17.596,00 131.970,00
6 Bekisting Papan m² 0,330 491.697,00 162.260,01
Jumlah 4.330.878,66
III PEKERJAAN PLUMBING -
1 Pek. Pengadaan Dan Pemasangan Pipa PVC Dia 3" m1 4,000 68.868,00 275.472,00
2 Pek. Pengadaan Dan Pemasangan Pipa PVC Dia 4" m1 1,000 82.014,00 82.014,00
Jumlah 357.486,00
IV PEKERJAAN PENAMPUNGAN AIR -
1 Pek. Pasang Bak Kontrol precast unit 1,000 400.000,00 400.000,00
2 Tower Air Dari Siku 50.50.5 + Pondasi Tinggi 1,5 - unit 1,000 2.000.000,00 2.000.000,00
3 Tangki Air Torn Penampungan Air 500 L Unit 1,000 1.085.500,00 1.085.500,00
Jumlah 3.485.500,00
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
SUMUR RESAPAN
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 1.620.297,00
II PEKERJAAN SUMUR RESAPAN 4.330.878,66
III PEKERJAAN PLUMBING 357.486,00
IV PEKERJAAN PENAMPUNGAN AIR 3.485.500,00
JUMLAH (Rp) 9.794.161,66
PPN 10% 979.416,17
JUMLAH TOTAL (Rp) 10.773.577,83
JUMLAH DIBULATKAN (Rp) 10.773.000,00
104
ANALISIS STANDAR BELANJA (ASB)
INSTALASI PEMANEN AIR HUJAN (IPAH) AM
1 KELOMPOK : Konstruksi
2 SUB KELOMPOK : Membangun Instalasi Pemanen Air Hujan (IPAH) AM
3 SUB- SUB KELOMPOK : Instalasi Pemanen Air Hujan (IPAH ) AM
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Instalasi Pemanen Air Hujan (IPAH ) AM
6 DESKRIPSI AKTIVITAS : Instalasi Pemanen Air Hujan (IPAH ) AM
7 SATUAN AKTIVITAS : Unit
8 KOMPONEN/RINCIAN KOMPONEN :
NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
I PEKERJAAN PERSIAPAN
1 Biaya Mobilisasi Barang/Tenaga LS - - -
2 Pembuatan Papan Nama IPAH Buah - - -
Jumlah -
II PEKERJAAN SUMUR RESAPAN -
1 Galian tanah biasa sedalam 3 meter m3 6,300 174.566,00 1.099.765,80
2 Pasangan dinding bata merah 1 PC : 3 PP tebal 1/2 bata m2 3,130 172.992,00 541.464,96
3 Adukan beton 1 Pc : 2 Ps : 3 Kr. m3 0,100 1.288.543,00 128.854,30
4 Tulangan beton besi U-24 Kg 5,000 17.596,00 87.980,00
5 Bekisting Papan m2 0,215 491.697,00 105.714,86
6 Pekerjaan Aanstamping m3 2,000 650.982,00 1.301.964,00
Jumlah 3.265.743,92
III PEKERJAAN INSTALASI PIPA -
1 Pek. Pengadaan Dan Pemasangan Pipa PVC Dia 3" m' 16,000 91.728,00 1.467.648,00
2 Pek. Pengadaan Dan Pemasangan Pipa PVC Dia 8" m' 5,000 592.602,00 2.963.010,00
Pek. Pengadaan Dan Pemasangan Talang Air PVC Setengah
3 m' 5,000 123.630,00 618.150,00
Lingkaran
4 Catridge Filter 20" (Air RO) pcs 1,000 19.000.000,00 19.000.000,00
Jumlah 24.048.808,00
PEKERJAAN PEMASANGAN TANGKI AIR SEBAGAI
IV -
BAK KONTROL
1 Pemasangan tangki air 1000 ltr sebagai bak kontrol Set 1,000 1.595.500,00 1.595.500,00
Jumlah 1.595.500,00
PEKERJAAN PEMASANGAN TANGKI AIR
V -
PENAMPUNGAN AIR HUJAN
1 Pemasangan Tangki Air Penampungan Air Hujan 1000 ltr Set 2,000 1.595.500,00 3.191.000,00
Jumlah 3.191.000,00
PEKERJAAN PEMASANGAN TANGKI AIR
VI -
PENAMPUNGAN AIR BERSIH
1 Pemasangan Tangki Air Penampungan Air Bersih 1000 ltr ls 1,000 1.595.500,00 1.595.500,00
Jumlah 1.595.500,00
VII PEMASANGAN STRELISASI AIR HUJAN -
1 Pemasangan Sterilisasi Air Bersih Set 1,000 1.595.500,00 1.595.500,00
Jumlah 1.595.500,00
PEKERJAAN PEMASANGAN PENAMPUNGAN AIR
VIII -
HUJAN
1 Pek. Pasang Tower Air (tinggi 1.5-2 m) unit 1,000 2.000.000,00 2.000.000,00
Jumlah 2.000.000,00
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
INSTALASI PEMANEN AIR HUJAN (IPAH) AM
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN -
II PEKERJAAN SUMUR RESAPAN 3.265.743,92
III PEKERJAAN INSTALASI PIPA 24.048.808,00
IV PEKERJAAN PEMASANGAN TANGKI AIR SEBAGAI BAK KONTROL 1.595.500,00
V PEKERJAAN PEMASANGAN TANGKI AIR PENAMPUNGAN AIR HUJAN 3.191.000,00
VI PEKERJAAN PEMASANGAN TANGKI AIR PENAMPUNGAN AIR BERSIH 1.595.500,00
VII PEMASANGAN STRELISASI AIR HUJAN 1.595.500,00
VIII PEKERJAAN PEMASANGAN PENAMPUNGAN AIR HUJAN 2.000.000,00
JUMLAH (Rp) 37.292.051,92
PPN 10% 3.729.205,19
JUMLAH TOTAL (Rp) 41.021.257,11
JUMLAH DIBULATKAN (Rp) 41.021.000,00
105
ANALISIS STANDAR BELANJA (ASB)
INSTALASI PEMANEN AIR HUJAN (IPAH) AB
1 KELOMPOK : Konstruksi
2 SUB KELOMPOK : Membangun Instalasi Pemanen Air Hujan (IPAH) AB
3 SUB- SUB KELOMPOK : Instalasi Pemanen Air Hujan (IPAH ) AB
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Instalasi Pemanen Air Hujan (IPAH ) AB
6 DESKRIPSI AKTIVITAS : Instalasi Pemanen Air Hujan (IPAH ) AB
7 SATUAN AKTIVITAS : Unit
8 KOMPONEN/RINCIAN KOMPONEN :
NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
I PEKERJAAN PERSIAPAN
1 Biaya Mobilisasi Barang/Tenaga LS - - -
2 Pembuatan Papan Nama IPAH Buah - - -
Jumlah -
II PEKERJAAN SUMUR RESAPAN -
1 1 m³ Galian tanah biasa sedalam 3 meter m3 6,300 174.566,00 1.099.765,80
1M2 PAS. BATA MERAH TRASRAAM TEBAL 1/2 BATA
2 m2 3,130 172.992,00 541.464,96
1 PC : 3 PS
3 Adukan beton 1 Pc : 2 Ps : 3 Kr. m3 0,100 1.288.543,00 128.854,30
4 Tulangan beton besi U-24 Kg 5,000 17.596,00 87.980,00
5 Bekisting Papan m2 0,215 491.697,00 105.714,86
6 Pekerjaan Aanstamping m3 2,000 650.982,00 1.301.964,00
Jumlah 3.265.743,92
III PEKERJAAN INSTALASI PIPA -
1 Pek. Pengadaan Dan Pemasangan Pipa PVC Dia 3" m' 16,000 91.728,00 1.467.648,00
2 Pek. Pengadaan Dan Pemasangan Pipa PVC Dia 8" m' 5,000 592.602,00 2.963.010,00
Pek. Pengadaan Dan Pemasangan Talang Air PVC Setengah
3 m' 5,000 123.630,00 618.150,00
Lingkaran
Jumlah 5.048.808,00
PEKERJAAN PEMASANGAN TANGKI AIR SEBAGAI
IV -
BAK KONTROL
1 Pemasangan Tangki Air 1000 ltr Sebagai Bak Kontrol Set 2,000 1.595.500,00 3.191.000,00
Jumlah 3.191.000,00
PEKERJAAN PEMASANGAN TANGKI AIR
V -
PENAMPUNGAN AIR HUJAN
1 Pemasangan Tangki Air 1000 ltr Penampungan Air Bersih Set 2,000 1.595.500,00 3.191.000,00
Jumlah 3.191.000,00
PEKERJAAN PEMASANGAN TANGKI AIR
VI -
PENAMPUNGAN AIR BERSIH
1 Pemasangan Tangki Air 1000 ltr Penampungan Air Bersih Set 2,000 1.595.500,00 3.191.000,00
Jumlah 3.191.000,00
VII PEMASANGAN STRELISASI AIR HUJAN -
1 Pemasangan Sterilisasi Air Bersih Set 2,000 1.595.500,00 3.191.000,00
Jumlah 3.191.000,00
PEKERJAAN PEMASANGAN PENAMPUNGAN AIR
VIII -
HUJAN
1 Pek. Pasang Tower Air (tinggi 1.5-2 m) unit 1,000 2.000.000,00 2.000.000,00
Jumlah 2.000.000,00
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
INSTALASI PEMANEN AIR HUJAN (IPAH) AB
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN -
II PEKERJAAN SUMUR RESAPAN 3.265.743,92
III PEKERJAAN INSTALASI PIPA 5.048.808,00
IV PEKERJAAN PEMASANGAN TANGKI AIR SEBAGAI BAK KONTROL 3.191.000,00
V PEKERJAAN PEMASANGAN TANGKI AIR PENAMPUNGAN AIR HUJAN 3.191.000,00
VI PEKERJAAN PEMASANGAN TANGKI AIR PENAMPUNGAN AIR BERSIH 3.191.000,00
VII PEMASANGAN STRELISASI AIR HUJAN 3.191.000,00
VIII PEKERJAAN PEMASANGAN PENAMPUNGAN AIR HUJAN 2.000.000,00
JUMLAH (Rp) 23.078.551,92
PPN 10% 2.307.855,19
JUMLAH TOTAL (Rp) 25.386.407,11
JUMLAH DIBULATKAN (Rp) 25.386.000,00
106
ANALISIS STANDAR BELANJA (ASB)
POJOK EDUKASI BERSIH SAMPAH (POKASIH)
1 KELOMPOK : Konstruksi
2 SUB KELOMPOK : Membangun Pojok Edukasi Bersih Sampah (POKASIH)
3 SUB- SUB KELOMPOK : Pojok Edukasi Bersih Sampah
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten
5 AKTIVITAS : Konstruksi
6 DESKRIPSI AKTIVITAS : Pojok Edukasi Bersih Sampah
7 SATUAN AKTIVITAS : Unit
8 KOMPONEN/RINCIAN KOMPONEN :
NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA
I Pek. Persiapan
1 Pek. Pembersihan Lahan ls - - -
2 Pek. Mobilisasi & Demobilisasi ls - - -
3 Pek. Kesehatan & Keselamatan Kerja ls - - -
4 Pek. Pas. Bouwplank m' 24,000 81.786,00 1.962.864,00
Jumlah 1.962.864,00
II Pek. Perkerasan Lantai Paving Block -
1 Pek. Urugan Tanah Tebal 10cm (pematangan lahan) m³ 1,000 86.899,00 86.899,00
2 Pek. Pasangan Paving Block T=8cm m² 10,000 314.395,00 3.143.950,00
3 Pek. Pasangan bata batas lahan m' 3,600 165.491,00 595.767,60
4 Pek. Plesteran + Acian Pembatas m² 1,800 94.277,00 169.698,60
Jumlah 3.996.315,20
III Pek. Lantai Beton area kontainer sampah -
1 Besi Wiremesh M-8 m² 18,000 13.353,00 240.354,00
2 Pengecoran Beton Mutu K-225 T=10cm m³ 1,800 1.288.543,00 2.319.377,40
3 Stoper Parkir pipa baja diameter 2" kg 20,360 46.100,00 938.596,00
Jumlah 3.498.327,40
IV Pek. Tempat Duduk, Panel Informasi & Kanopi -
1 Pek. Urugan Pasir m³ 0,019 268.769,00 5.120,05
2 Pek. Pondasi Beton t=8cm (tanpa tulangan) m³ 0,027 1.288.543,00 34.326,79
3 Pek. Base Plate t=9mm + mur baut angkur Ls 1,000 350.000,00 350.000,00
4 Pek. Pipa Baja BSP Ø3" (tempat duduk) kg 60,984 39.711,00 2.421.735,62
5 Pek. Rangka Hollow 40x40 m² 2,400 265.146,00 636.350,40
6 Pek. Panel GRC m² 3,060 57.280,00 175.276,80
7 Pek. Pengecatan Panel GRC dgn Cat Eksterior m² 3,060 33.978,00 103.972,68
8 Pek. Rangka Kanopi Hollow 40x40 m² 3,200 179.081,00 573.059,20
9 Pek. Penutup Atap Kanopi Solar Tuff m² 3,200 98.151,00 314.083,20
Jumlah 4.613.924,74
V Pek. Blumbak -
1 Pek. Blumbak tanaman m² - - -
2 Pek. Galian Tanah m² 1,210 119.924,00 145.108,04
3 Pek. Dinding 1/2 bata add. 1 : 5 m² 16,940 166.609,00 2.822.356,46
4 Pek. Plesteran Dinding bata add. 1 : 5 m² 33,880 95.270,00 3.227.747,60
5 Pek. Acian m² 33,880 58.187,00 1.971.375,56
6 Pek. Pengecatan blumbak m² 33,880 33.978,00 1.151.174,64
7 Pek. Tanah subur m² 0,652 -
8 Pas. Pohon Ketapang Kencana bh 3,000 75.000,00 225.000,00
9 Pas. Pucuk Merah bh 8,000 500.000,00 4.000.000,00
Jumlah 13.542.762,30
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
POJOK EDUKASI BERSIH SAMPAH (POKASIH)
No PEKERJAAN JUMLAH (Rp)
I Pek. Persiapan 1.962.864,00
II Pek. Perkerasan Lantai Paving Block 3.996.315,20
III Pek. Lantai Beton area kontainer sampah 3.498.327,40
IV Pek. Tempat Duduk, Panel Informasi & Kanopi 4.613.924,74
V Pek. Blumbak 13.542.762,30
JUMLAH (Rp) 27.614.193,64
PPN 10% 2.761.419,36
JUMLAH TOTAL (Rp) 30.375.613,00
JUMLAH DIBULATKAN (Rp) 30.376.000,00
107
ANALISIS STANDAR BELANJA (ASB)
TPS3R
1 KELOMPOK : Konstruksi
2 SUB KELOMPOK : Membangun TPS3R
3 SUB- SUB KELOMPOK : TPS3R
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Kontruksi
6 DESKRIPSI AKTIVITAS : TPS3R
7 SATUAN AKTIVITAS : m'
8 KOMPONEN/RINCIAN KOMPONEN :
No URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH
I PEKERJAAN PERSIAPAN
1 Pengukuran dan Pemasangan Bowplank m' 60,000 81.786,00 4.907.160,00
2 Pembersihan 1 m2 lapangan dan perataan m² 340,000 25.719,00 8.744.460,00
Jumlah 13.651.620,00
II PEKERJAAN TANAH -
1 Pek. Galian tanah pondasi setempat / telapak m³ 12,000 119.924,00 1.439.088,00
2 Pek. Galian tanah pondasi lajur / batu kali m³ 21,000 119.924,00 2.518.404,00
3 Pek. Urugan tanah bekas galian m³ 8,000 86.899,00 695.192,00
4 Pek. Urugan pasir pondasi setempat t. 5 cm m³ 1,000 268.769,00 268.769,00
5 Pek. Urugan pasir pondasi lajur t. 5 cm m³ 2,000 268.769,00 537.538,00
Jumlah 5.458.991,00
III PEKERJAAN PONDASI -
1 Pek. Batu kosong (Anstamping) m³ 4,000 650.982,00 2.603.928,00
2 Pek. Pondasi lajur batu belah 1 : 4 m³ 16,000 1.182.760,00 18.924.160,00
Jumlah 21.528.088,00
IV PEKERJAAN PASANGAN -
Pek. Dinding bata ringan tebal 10cm m² 272,000 186.303,00 50.674.416,00
Pek. Plesteran dinding ad. 1 Pc : 4 Psr m² 544,000 96.456,00 52.472.064,00
Pek. Acian m² 544,000 58.187,00 31.653.728,00
Jumlah 134.800.208,00
V PEKERJAAN STRUKTUR -
BETON -
Pek. Lantai beton pondasi plat t = 5 cm m³ 1,000 1.078.544,00 1.078.544,00
Pek. Rabat beton saluran t = 5 cm m³ - - -
Pek. Pondasi plat 100x100x30 cm m³ 4,000 1.288.543,00 5.154.172,00
- Besi Tulangan U - 24 Ø 12 mm lt 49,000 17.596,00 862.204,00
- Besi Tulangan Sengkang Ø 8 mm lt 6,000 17.596,00 105.576,00
- Pekerjaan papan bekisting m² 22,000 228.448,00 5.025.856,00
Pek. Sloof 15x20 cm m³ 3,000 1.288.543,00 3.865.629,00
- Besi Tulangan U - 24 Ø 12 mm lt 29,000 17.596,00 510.284,00
- Besi Tulangan Sengkang Ø 8 mm lt 25,000 17.596,00 439.900,00
- Pekerjaan papan bekisting m² 34,000 228.448,00 7.767.232,00
Pek. Kolom 30x20 cm (Pedestal) m³ - 1.288.543,00 -
- Besi Tulangan U - 24 Ø 12 mm lt 4,000 17.596,00 70.384,00
- Besi Tulangan Sengkang Ø 8 mm lt 3,000 17.596,00 52.788,00
- Pekerjaan papan bekisting m² 4,000 428.677,00 1.714.708,00
Pek. Kolom 15x15 cm (Praktis) m³ 1,000 1.288.543,00 1.288.543,00
- Besi Tulangan U - 24 Ø 10 mm lt 29,000 17.596,00 510.284,00
- Besi Tulangan Sengkang Ø 8 mm lt 19,000 17.596,00 334.324,00
- Pekerjaan papan bekisting m² 21,000 428.677,00 9.002.217,00
Pek. Ring Balk 15x15 cm m³ 1,000 1.288.543,00 1.288.543,00
- Besi Tulangan U - 24 Ø 10 mm lt 22,000 17.596,00 387.112,00
- Besi Tulangan Sengkang Ø 8 mm lt 14,000 17.596,00 246.344,00
- Pekerjaan papan bekisting m² 17,000 439.027,00 7.463.459,00
Pek. Plat Lantai Beton tebal 10cm m³ 20,000 1.288.543,00 25.770.860,00
- Besi Wiremash Ø 6 mm m² 200,000 13.353,00 2.670.600,00
Pek. Cor Jalur Masuk tebal 20 cm m³ 6,000 1.288.543,00 7.731.258,00
- Besi Wiremash Ø 6 mm m² 28,000 13.353,00 373.884,00
- Pekerjaan papan bekisting m² 6,000 491.697,00 2.950.182,00
BAJA -
Pek. Rangka Baja I/WF -
- Kolom Baja WF 150x75x5x7 kg 560,000 39.711,00 22.238.160,00
- Balok Baja WF 100x50x5x7 kg 653,000 39.711,00 25.931.283,00
- Kuda-kuda Baja WF 150x75x5x7 kg 882,000 39.711,00 35.025.102,00
- Voute Baja WF 150x75x5x7 kg 119,000 39.711,00 4.725.609,00
- Plat baja = 10 mm (Pelat pengaku dan simpul) kg 149,000 39.711,00 5.916.939,00
- Baut 16 mm HTB + mur bh 358,000 26.686,00 9.553.588,00
- Angkur Pondasi Base Plate Dia. 16 kg 32,000 77.286,00 2.473.152,00
Pek. Gording / Purlin C -
- Gording baja C 100.50.20.2,3 kg 1.025,000 39.711,00 40.703.775,00
- Besi siku 50.50.3 (dudukan gordeng) kg 18,000 39.711,00 714.798,00
Pek. Atap -
- Brasing dia. 10 mm lt 9,000 18.902,00 170.118,00
- Tracstang dia 10 mm lt 9,000 18.902,00 170.118,00
- Mur trekstang 10 mm bh 90,000 - -
Pek Dinding Wiremesh m6 -
108
- Wiremesh m6 m² 25,000 265.146,00 6.628.650,00
- Rangka Hollow 40x40x2 kg 205,000 - -
Pek. Dinding Zincalum 0.4mm (Ampig) -
- Zincalum 0.4mm (Ampig) m² 27,000 344.064,00 9.289.728,00
- Rangka C 100.50.20.2,3 kg 156,000 - -
Jumlah 250.205.907,00
VI PEKERJAAN KUSEN & PENGGANTUNG -
Pas. Pintu Besi + Asesoris m² 11,000 986.653,00 10.853.183,00
Rel Pintu Besi Lengkap Kapasitas Max Berat Pintu 300 Kg m' 4,000 1.033.569,00 4.134.276,00
Pek. Kusen pintu dan jendela Aluminium 4" m' 51,000 162.222,00 8.273.322,00
Pek. Daun pintu taekwood m² 6,000 1.034.511,00 6.207.066,00
Pek. Daun jendela Aluminium m² 1,000 831.749,00 831.749,00
Pas. Kaca polos t. 5 mm m² 3,000 146.491,00 439.473,00
Pas. Kunci tanam bh 1,000 347.766,00 347.766,00
Pas. Lever handle bh 5,000 282.306,00 1.411.530,00
Pas. Engsel pintu 4" bh 18,000 75.057,00 1.351.026,00
Pas. Engsel jendela 3" bh 2,000 57.347,00 114.694,00
Pas. Kait angin jendela bh 1,000 63.691,00 63.691,00
Pas. Slot bh 2,000 83.243,00 166.486,00
Jumlah 34.194.262,00
VII PEKERJAAN PENUTUP LANTAI -
Pek. Keramik lantai 30 x 30 cm m² 27,000 189.964,00 5.129.028,00
Pek. Keramik lantai 20 x 20 cm m² 3,000 244.301,00 732.903,00
Pek. Dinding Keramik 20 x 40 cm m² 12,000 277.283,00 3.327.396,00
Jumlah 9.189.327,00
VIII PEKERJAAN SANITAIR -
Pas. Floor drain Stainless Lokal bh 1,000 126.164,00 126.164,00
Pas. Kloset Jongkok bh 1,000 730.581,00 730.581,00
Pas. Wastafel bh 2,000 1.452.432,00 2.904.864,00
Pas. Kran dinding 1/2" lokal bh 2,000 135.986,00 271.972,00
Pek. Instalasi air bersih Pipa PVC AW dia. 3/4" m' 27,000 165.699,00 4.473.873,00
Pek. Instalasi air bersih Pipa PVC AW dia. 1/2" m' 4,000 24.351,00 97.404,00
Pek. Instalasi air hujan Pipa PVC AW dia. 3" m' 14,000 120.248,00 1.683.472,00
Pek. Instalasi air bekas Pipa PVC AW dia. 4" m' 8,000 120.248,00 961.984,00
Peng. tangki air/Toren kapasitas 1050 L Unit 1,000 1.595.500,00 1.595.500,00
Pek. Kolam Lindi -
- Galian tanah m³ 2,000 119.924,00 239.848,00
- Pek. dinding bata merah tebal 1/2 bata, campuran spesi 1 PC :
m² 6,000 166.609,00 999.654,00
5 PP
- Pek. plesteran 1 PC : 2 PP, tebal 15 mm m² 6,000 101.950,00 611.700,00
- Pek. Beton K 175 -
Pek. Beton m³ - 1.269.586,00 -
Pek. Wiremash dia. 8 m² 1,000 13.353,00 13.353,00
- Pek. Pipa PVC AW dia. 3" m' 3,000 91.728,00 275.184,00
Pek. Septictank dan Sumur Resapan -
- Pek. Galian Tanah m³ 6,000 119.924,00 719.544,00
- Pek. dinding bata merah tebal 1/2 bata, campuran spesi 1 PC :
m² 6,000 166.609,00 999.654,00
5 PP
- Pek. plesteran 1 PC : 2 PP, tebal 15 mm m² 6,000 101.950,00 611.700,00
- Pek. Pipa PVC AW dia. 1" m' 1,000 30.233,00 30.233,00
- Pek. Pipa PVC AW dia. 3" m' 2,000 91.728,00 183.456,00
- Pek. Beton K 175 -
Pek. Beton m³ 2,000 1.269.586,00 2.539.172,00
Pek. Wiremash dia 8 m² 18,000 13.353,00 240.354,00
- Pek. Bio Filter m³ 1,000 - -
- Pek. Ijuk kg 10,000 10.000,00 100.000,00
- Peng. Batu Zeolit kg 10,000 - -
- Peng. Pasir Pasang m³ - 250.000,00 -
Tower Toren Kapasitas 1000 L ls 1,000 - -
Jumlah 20.409.666,00
IX PEKERJAAN PENGECATAN -
Pek. Cat dinding dalam m² 385,000 33.978,00 13.081.530,00
Pek. Cat dinding luar m² 182,000 42.948,00 7.816.536,00
Pek. Meni Wiremash dinding m² 19,000 51.350,00 975.650,00
Pek. Cat Plafond m² 30,000 33.978,00 1.019.340,00
Pek. Meni Besi profil m² 98,000 51.350,00 5.032.300,00
Jumlah 27.925.356,00
X PEKERJAAN ATAP & PLAFOND -
Pek. Penutup atap zincalum 0,4 mm m² 288,000 178.170,00 51.312.960,00
Pek. Nok Zincalum m' 22,000 120.819,00 2.658.018,00
Pek. Listplank m' 70,000 86.790,00 6.075.300,00
Pek. Plafond gypsum t. 9 mm + Hollow m² 30,000 215.663,00 6.469.890,00
List plafond gypsum tg. 11 cm m' - 54.174,00 -
Jumlah 66.516.168,00
109
XI PEKERJAAN LISTRIK -
Instalasi titik lampu (NYM 3x2,5 mm + pipa conduit 20 mm) ttk 11,000 449.606,00 4.945.666,00
Instalasi stop kontak (NYM 3x2,5 mm + pipa conduit 20 mm) ttk 8,000 514.509,00 4.116.072,00
Pas. Lampu TL 16 watt philips ecofit - LED bh 4,000 310.833,00 1.243.332,00
Pas. Lampu SL 12 watt Philips ecofit - LED bh 7,000 97.773,00 684.411,00
Pas. Saklar seri bh 2,000 110.486,00 220.972,00
Pas. Saklar engkel bh 3,000 104.678,00 314.034,00
Pas. Stop kontak CP double bh 8,000 113.390,00 907.120,00
Penyambungan Daya Listrik 900 VA ls 1,000 2.101.400,00 2.101.400,00
Jumlah 14.533.007,00
XII PEKERJAAN LANDSCAPE -
Pek. Paving Block Natural m² 17,000 314.395,00 5.344.715,00
Pek. Fasad -
- Pek. Pasangan Bata Merah m² - - -
- Pek. Plesteran Dinding 1 Pc : 4 Ps m² - - -
- Pek. Batu Alam m² - - -
- Pas. Lettersign ( TPS 3 R KSM PABER DESA
ls - - -
CIKEMBANG )
Jumlah 5.344.715,00
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
TPS3R
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 13.651.620,00
II PEKERJAAN TANAH 5.458.991,00
III PEKERJAAN PONDASI 21.528.088,00
IV PEKERJAAN PASANGAN 134.800.208,00
V PEKERJAAN STRUKTUR 250.205.907,00
VI PEKERJAAN KUSEN & PENGGANTUNG 34.194.262,00
VII PEKERJAAN PENUTUP LANTAI 9.189.327,00
VIII PEKERJAAN SANITAIR 20.409.666,00
IX PEKERJAAN PENGECATAN 27.925.356,00
X PEKERJAAN ATAP & PLAFOND 66.516.168,00
XI PEKERJAAN LISTRIK 14.533.007,00
XII PEKERJAAN LANDSCAPE 5.344.715,00
JUMLAH (Rp) 603.757.315,00
PPN 10% 60.375.731,50
JUMLAH TOTAL (Rp) 664.133.046,50
JUMLAH DIBULATKAN (Rp) 664.133.000,00
Luas Bangunan 200,00
JUMLAH TOTAL (Rp) 3.320.665,00
JUMLAH DIBULATKAN (Rp) 3.320.000,00
110
ANALISIS STANDAR BELANJA (ASB)
BRONCAPTERING
1 KELOMPOK : Pembangunan Broncaptering
2 SUB KELOMPOK : Program Lingkungan Sehat Perumahan
3 SUB- SUB KELOMPOK : Penyediaan sarana air bersih dan sanitasi dasar terutama bagi masyarakat miskin
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
BRONCAPTERING
No PEKERJAAN JUMLAH (Rp)
I PEKEERJAAN TANAH 2.736.161,28
II PEKERJAAN PASANGAN 18.298.710,48
III PEKERJAAN PIPA 1.512.964,50
IV PEKERJAAN BESI 2.120.000,00
JUMLAH (Rp) 24.667.836,26
PPN 10% 2.466.783,63
JUMLAH TOTAL (Rp) 27.134.619,89
JUMLAH DIBULATKAN (Rp) 27.134.000,00
111
ANALISIS STANDAR BELANJA (ASB)
JARINGAN KOSNTRUKSI PERPIPAAN AIR BERSIH
1 KELOMPOK : Pengembangan Perpipaan Sambungan Rumah (SR)
2 SUB KELOMPOK : Program Lingkungan Sehat Perumahan
3 SUB- SUB KELOMPOK : Penyediaan sarana air bersih dan sanitasi dasar terutama bagi masyarakat miskin
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
PEMBANGUNAN JARINGAN KONSTRUKSI PERPIPAAN AIR BERSIH
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 6.910.274,00
II PEMASANGAN PIPA DAN ACCSESORIES 102.209.804,01
III PEKERJAAN KONSTRUKSI -
IV PEKERJAAN SAMBUNGAN RUMAH PERDESAAN 8.330.010,00
JUMLAH (Rp) 117.450.088,01
PPN 10% 11.745.008,80
JUMLAH TOTAL (Rp) 129.195.096,81
JUMLAH DIBULATKAN (Rp) 129.195.000,00
PANJANG JARINGAN (M) 1.038,00
ASB JARINGAN TERMASUK BRONCAPTERING, RESERVOIR, SR / M¹ (Rp) 124.465,32
ASB JARINGAN TERMASUK BRONCAPTERING, RESERVOIR INCLUDE PPN , SR / M¹ (Rp) 124.465,00
ASB JARINGAN PIPA / M¹ (Rp) 98.468,02
ASB JARINGAN PIPA INCLUDE PPN / M¹ (Rp) 124.465,00
112
ANALISIS STANDAR BELANJA (ASB)
SAMBUNGAN RUMAH PERDESAAN
1 KELOMPOK : Pengembangan Perpipaan Sambungan Rumah (SR) Perdesaan
2 SUB KELOMPOK : Program Lingkungan Sehat Perumahan
3 SUB- SUB KELOMPOK : Penyediaan sarana air bersih dan sanitasi dasar terutama bagi masyarakat miskin
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
SAMBUNGAN RUMAH PERDESAAN
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN -
II PEMASANGAN PIPA DAN ACCSESORIES 367.796,00
III PEKERJAAN KONSTRUKSI 190.308,24
IV PEKERJAAN SAMBUNGAN RUMAH PERDESAAN 833.001,00
JUMLAH (Rp) 1.391.105,24
PPN 10% 139.110,52
JUMLAH TOTAL (Rp) 1.530.215,76
JUMLAH DIBULATKAN (Rp) 1.530.000,00
113
ANALISIS STANDAR BELANJA (ASB)
SAMBUNGAN RUMAH PERKOTAAN
1 KELOMPOK : Pengembangan Perpipaan Sambungan Rumah (SR) Perkotaan
2 SUB KELOMPOK : Program Lingkungan Sehat Perumahan
3 SUB- SUB KELOMPOK : Penyediaan sarana air bersih dan sanitasi dasar terutama bagi masyarakat miskin
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
SAMBUNGAN RUMAH PERKOTAAN
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN -
II PEMASANGAN PIPA DAN ACCSESORIES 367.796,00
III PEKERJAAN KONSTRUKSI 190.308,24
IV PEKERJAAN SAMBUNGAN RUMAH PERKOTAAN 948.001,00
JUMLAH (Rp) 1.506.105,24
PPN 10% 150.610,52
JUMLAH TOTAL (Rp) 1.656.715,76
JUMLAH DIBULATKAN (Rp) 1.656.000,00
114
ANALISIS STANDAR BELANJA (ASB)
SAMBUNGAN RUMAH HIBAH AIR MINUM PERDESAAN
1 KELOMPOK : Pengembangan Perpipaan Sambungan Rumah (SR) HAMP
2 SUB KELOMPOK : Program Lingkungan Sehat Perumahan
3 SUB- SUB KELOMPOK : Penyediaan sarana air bersih dan sanitasi dasar terutama bagi masyarakat miskin
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
SAMBUNGAN RUMAH HIBAH AIR MINUM PERDESAAN
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN -
II PEMASANGAN PIPA DAN ACCSESORIES 367.796,00
III PEKERJAAN KONSTRUKSI 190.308,24
IV PEKERJAAN SAMBUNGAN RUMAH HIBAH AIR MINUM PERDESAAN 1.318.165,00
JUMLAH (Rp) 1.876.269,24
PPN 10% 187.626,92
JUMLAH TOTAL (Rp) 2.063.896,16
JUMLAH DIBULATKAN (Rp) 2.063.000,00
115
ANALISIS STANDAR BELANJA (ASB)
RESERVOIR KAPASITAS 2 m ³
1 KELOMPOK : Pembangunan Reservoir Kapasitas 2 m³
2 SUB KELOMPOK : Program Lingkungan Sehat Perumahan
3 SUB- SUB KELOMPOK : Penyediaan sarana air bersih dan sanitasi dasar terutama bagi masyarakat miskin
116
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
RESERVOIR KAPASITAS 2 m ³
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN TANAH 1.286.412,45
II PEKEERJAAN BETON 28.901.296,67
III PEKERJAAN BESI 842.027,00
IV PEKERJAAN PIPA DAN ASESORI 4.949.339,50
V PEKERJAAN CAT 547.672,90
VI PEKERJAAN PAGAR BRC 12.411.924,55
JUMLAH (Rp) 48.938.673,06
PPN 10% 4.893.867,31
JUMLAH TOTAL (Rp) 53.832.540,37
JUMLAH DIBULATKAN (Rp) 53.832.000,00
117
ANALISIS STANDAR BELANJA (ASB)
RESERVOIR KAPASITAS 5 m ³
1 KELOMPOK : Pembangunan Reservoir Kapasitas 5 m³
2 SUB KELOMPOK : Program Lingkungan Sehat Perumahan
3 SUB- SUB KELOMPOK : Penyediaan sarana air bersih dan sanitasi dasar terutama bagi masyarakat miskin
118
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
RESERVOIR KAPASITAS 5 m ³
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN TANAH 1.808.032,20
II PEKEERJAAN BETON 46.472.850,35
III PEKERJAAN BESI 842.027,00
IV PEKERJAAN PIPA DAN ASESORI 6.718.012,00
V PEKERJAAN CAT 867.206,02
VI PEKERJAAN PAGAR BRC 11.059.951,46
JUMLAH (Rp) 67.768.079,03
PPN 10% 6.776.807,90
JUMLAH TOTAL (Rp) 74.544.886,93
JUMLAH DIBULATKAN (Rp) 74.544.000,00
119
ANALISIS STANDAR BELANJA (ASB)
RESERVOIR KAPASITAS 10 m ³
1 KELOMPOK : Pembangunan Reservoir Kapasitas 10 m³
2 SUB KELOMPOK : Program Lingkungan Sehat Perumahan
3 SUB- SUB KELOMPOK : Penyediaan sarana air bersih dan sanitasi dasar terutama bagi masyarakat miskin
120
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
RESERVOIR KAPASITAS 10 m ³
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN TANAH 2.329.651,95
II PEKEERJAAN BETON 66.407.553,02
III PEKERJAAN BESI 1.387.761,00
IV PEKERJAAN PIPA DAN ASESORI 7.439.816,00
V PEKERJAAN CAT 1.276.929,94
VI PEKERJAAN PAGAR BRC 15.744.770,19
JUMLAH (Rp) 94.586.482,09
PPN 10% 9.458.648,21
JUMLAH TOTAL (Rp) 104.045.130,30
JUMLAH DIBULATKAN (Rp) 104.045.000,00
121
ANALISIS STANDAR BELANJA (ASB)
RESERVOIR KAPASITAS 20 m ³
1 KELOMPOK : Pembangunan Reservoir Kapasitas 20 m³
2 SUB KELOMPOK : Program Lingkungan Sehat Perumahan
3 SUB- SUB KELOMPOK : Penyediaan sarana air bersih dan sanitasi dasar terutama bagi masyarakat miskin
122
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
RESERVOIR KAPASITAS 20 m ³
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN TANAH 3.261.268,14
II PEKEERJAAN BETON 99.290.867,73
III PEKERJAAN BESI 1.387.761,00
IV PEKERJAAN PIPA DAN ASESORI 6.957.915,00
V PEKERJAAN CAT 1.947.777,70
VI PEKERJAAN PAGAR BRC 27.026.134,07
JUMLAH (Rp) 139.871.723,63
PPN 10% 13.987.172,36
JUMLAH TOTAL (Rp) 153.858.896,00
JUMLAH DIBULATKAN (Rp) 153.858.000,00
123
ANALISIS STANDAR BELANJA (ASB)
MENARA BESI AIR 3M + TANGKI AIR KAP.2000 Lt
1 KELOMPOK : Pembangunan Menara Besi 3m + Tangki Air Kapasitas 2000 ltr
2 SUB KELOMPOK : Program Lingkungan Sehat Perumahan
3 SUB- SUB KELOMPOK : Penyediaan sarana air bersih dan sanitasi dasar terutama bagi masyarakat miskin
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
MENARA BESI 3M + TANGKI AIR KAPASITAS 2000 LTR
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 3.814.398,00
II PEMBUATAN MENARA AIR TINGGI 3 m, KAPASITAS 2.000 LITER 15.144.683,48
III PEKERJAAN DINDING DAN LANTAI 652.192,25
IV PEKERJAAN PIPA, TANGKI DAN ACCESSORIES 3.500.000,00
JUMLAH (Rp) 23.111.273,73
PPN 10% 2.311.127,37
JUMLAH TOTAL (Rp) 25.422.401,10
JUMLAH DIBULATKAN (Rp) 25.422.000,00
124
ANALISIS STANDAR BELANJA (ASB)
MENARA BESI AIR 3M + TANGKI AIR KAP.2 X 2000 Lt
1 KELOMPOK : Pembangunan Menara Besi 3m + Tangki Air Kapasitas 2X 2000 ltr
2 SUB KELOMPOK : Program Lingkungan Sehat Perumahan
3 SUB- SUB KELOMPOK : Penyediaan sarana air bersih dan sanitasi dasar terutama bagi masyarakat miskin
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
MENARA BESI 3m + TANGKI AIR Kapasitas 2 X 2000 ltr
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 3.814.398,00
II PEMBUATAN MENARA AIR TINGGI 3 m, KAPASITAS 2.000 LITER 22.312.968,30
III PEKERJAAN DINDING DAN LANTAI 1.327.403,05
IV PEKERJAAN PIPA, TANGKI DAN ACCESSORIES 7.000.000,00
JUMLAH (Rp) 34.454.769,35
PPN 10% 3.445.476,94
JUMLAH TOTAL (Rp) 37.900.246,29
JUMLAH DIBULATKAN (Rp) 37.900.000,00
125
ANALISIS STANDAR BELANJA (ASB)
MENARA BESI AIR 4M + TANGKI AIR KAP.2000 Lt
1 KELOMPOK : Pembangunan Menara Besi 4m + Tangki Air Kapasitas 2000 ltr
2 SUB KELOMPOK : Program Lingkungan Sehat Perumahan
3 SUB- SUB KELOMPOK : Penyediaan sarana air bersih dan sanitasi dasar terutama bagi masyarakat miskin
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
MENARA BESI 4m + TANGKI AIR Kapasitas 2000 ltr
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 3.814.398,00
PEMBUATAN MENARA AIR TINGGI 4 m, KAPASITAS
II 16.914.746,00
2.000 LITER
III PEKERJAAN DINDING DAN LANTAI 650.657,68
IV PEKERJAAN PIPA, TANGKI DAN ACCESSORIES 3.500.000,00
JUMLAH (Rp) 24.879.801,68
PPN 10% 2.487.980,17
JUMLAH TOTAL (Rp) 27.367.781,85
JUMLAH DIBULATKAN (Rp) 27.367.000,00
126
ANALISIS STANDAR BELANJA (ASB)
MENARA BESI AIR 4M + TANGKI AIR KAP.2 x 2000 Lt
1 KELOMPOK : Pembangunan Menara Besi 4m + Tangki Air Kapasitas 2 x 2000 ltr
2 SUB KELOMPOK : Program Lingkungan Sehat Perumahan
3 SUB- SUB KELOMPOK : Penyediaan sarana air bersih dan sanitasi dasar terutama bagi masyarakat miskin
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
MENARA BESI 4m + TANGKI AIR Kapasitas 2 x 2000 ltr
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 3.814.398,00
II PEMBUATAN MENARA AIR TINGGI 4 m, KAPASITAS 2X 2.000 LITER 25.094.379,99
III PEKERJAAN DINDING DAN LANTAI 1.227.656,00
IV PEKERJAAN PIPA, TANGKI DAN ACCESSORIES 7.000.000,00
JUMLAH (Rp) 37.136.433,99
PPN 10% 3.713.643,40
JUMLAH TOTAL (Rp) 40.850.077,39
JUMLAH DIBULATKAN (Rp) 40.850.000,00
127
ANALISIS STANDAR BELANJA (ASB)
MENARA BESI AIR 6M + TANGKI AIR KAP.5000 Lt
1 KELOMPOK : Pembangunan Menara Besi 6m + Tangki Air Kapasitas 5000 ltr
2 SUB KELOMPOK : Program Lingkungan Sehat Perumahan
3 SUB- SUB KELOMPOK : Penyediaan sarana air bersih dan sanitasi dasar terutama bagi masyarakat miskin
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
MENARA BESI 6m + TANGKI AIR Kapasitas 5000 ltr
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 3.814.398,00
II PEMBUATAN MENARA AIR TINGGI 6 m, KAPASITAS 5.000 LITER 30.657.718,84
III PEKERJAAN DINDING DAN LANTAI 1.611.298,50
IV PEKERJAAN PIPA, TANGKI DAN ACCESSORIES 7.500.000,00
JUMLAH (Rp) 43.583.415,34
PPN 10% 4.358.341,53
JUMLAH TOTAL (Rp) 47.941.756,87
JUMLAH DIBULATKAN (Rp) 47.941.000,00
128
ANALISIS STANDAR BELANJA (ASB)
MENARA BESI AIR 6M + TANGKI AIR KAP.2 x 5000 Lt
1 KELOMPOK : Pembangunan Menara Besi 6m + Tangki Air Kapasitas 2 x 5000 ltr
2 SUB KELOMPOK : Program Lingkungan Sehat Perumahan
3 SUB- SUB KELOMPOK : Penyediaan sarana air bersih dan sanitasi dasar terutama bagi masyarakat miskin
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
MENARA BESI 6m + TANGKI AIR Kapasitas 2 x 5000 ltr
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 3.814.398,00
II PEMBUATAN MENARA AIR TINGGI 6 m, KAPASITAS 2X 5.000 LITER 44.481.129,40
III PEKERJAAN DINDING DAN LANTAI 1.933.558,20
IV PEKERJAAN PIPA, TANGKI DAN ACCESSORIES 15.000.000,00
JUMLAH (Rp) 65.229.085,60
PPN 10% 6.522.908,56
JUMLAH TOTAL (Rp) 71.751.994,16
JUMLAH DIBULATKAN (Rp) 71.751.000,00
129
ANALISIS STANDAR BELANJA (ASB)
MENARA BAJA WF TINGGI 6M + TANGKI AIR KAP.5000 Lt
1 KELOMPOK : Pembangunan Menara Baja IWF 6m + Tangki Air Kapasitas 5000 ltr
2 SUB KELOMPOK : Program Lingkungan Sehat Perumahan
3 SUB- SUB KELOMPOK : Penyediaan sarana air bersih dan sanitasi dasar terutama bagi masyarakat miskin
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
MENARA BAJA IWF 6m + TANGKI AIR Kapasitas 5000 ltr
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 3.814.398,00
II PEMBUATAN MENARA AIR TINGGI 6 m, KAPASITAS 5.000 LITER 85.253.443,57
III PEKERJAAN DINDING DAN LANTAI 1.381.113,00
IV PEKERJAAN PIPA, TANGKI DAN ACCESSORIES 7.500.000,00
JUMLAH (Rp) 97.948.954,57
PPN 10% 9.794.895,46
JUMLAH TOTAL (Rp) 107.743.850,03
JUMLAH DIBULATKAN (Rp) 107.743.000,00
130
ANALISIS STANDAR BELANJA (ASB)
MENARA BAJA WF TINGGI 6M + TANGKI AIR KAP.2 x 5000 Lt
1 KELOMPOK : Pembangunan Menara Baja IWF 6m + Tangki Air Kapasitas 2 X 5000 ltr
2 SUB KELOMPOK : Program Lingkungan Sehat Perumahan
3 SUB- SUB KELOMPOK : Penyediaan sarana air bersih dan sanitasi dasar terutama bagi masyarakat miskin
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
MENARA BAJA IWF 6m + TANGKI AIR Kapasitas 2 X 5000 ltr
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 3.814.398,00
II PEMBUATAN MENARA AIR TINGGI 6 m, KAPASITAS 2 X 5.000 LITER 118.039.336,35
III PEKERJAAN DINDING DAN LANTAI 1.534.570,00
IV PEKERJAAN PIPA, TANGKI DAN ACCESSORIES 15.000.000,00
JUMLAH (Rp) 138.388.304,35
PPN 10% 13.838.830,44
JUMLAH TOTAL (Rp) 152.227.134,79
JUMLAH DIBULATKAN (Rp) 152.227.000,00
131
ANALISIS STANDAR BELANJA (ASB)
SUMUR DANGKAL 60M
1 KELOMPOK : Pembangunan Sumur Dangkal 60 m
2 SUB KELOMPOK : Program Lingkungan Sehat Perumahan
3 SUB- SUB KELOMPOK : Penyediaan sarana air bersih dan sanitasi dasar terutama bagi masyarakat miskin
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
SUMUR DANGKAL 60 M
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 3.814.398,00
II PEMBUATAN MENARA AIR TINGGI 6 m, KAPASITAS 2 X 5.000 LITER 36.859.779,00
III PEKERJAAN DINDING DAN LANTAI 4.900.000,00
IV PEKERJAAN PIPA, TANGKI DAN ACCESSORIES 5.000.000,00
JUMLAH (Rp) 50.574.177,00
PPN 10% 5.057.417,70
JUMLAH TOTAL (Rp) 55.631.594,70
JUMLAH DIBULATKAN (Rp) 55.631.000,00
132
ANALISIS STANDAR BELANJA (ASB)
SUMUR DANGKAL 60M + MENARA AIR 4 M
1 KELOMPOK : Pembangunan Sumur Dangkal 60 m + Menara Air 4 m
2 SUB KELOMPOK : Program Lingkungan Sehat Perumahan
3 SUB- SUB KELOMPOK : Penyediaan sarana air bersih dan sanitasi dasar terutama bagi masyarakat miskin
133
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
SUMUR DANGKAL 60 M + Menara Air 4m
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 3.814.398,00
II PEKERJAAN KONSTRUKSI SUMUR 36.859.779,00
III PENGADAAAN DAN PEMASANGAN POMPA 4.900.000,00
IV PEKERJAAN INSTALASI LISTRIK 5.000.000,00
V PEMBUATAN MENARA AIR TINGGI 4 m, KAPASITAS 2.000 LITER 16.914.746,00
VI PEKERJAAN DINDING DAN LANTAI 650.657,68
VII PEKERJAAN PIPA, TANGKI DAN ACCESSORIES 3.500.000,00
JUMLAH (Rp) 71.639.580,68
PPN 10% 7.163.958,07
JUMLAH TOTAL (Rp) 78.803.538,75
JUMLAH DIBULATKAN (Rp) 78.803.000,00
134
ANALISIS STANDAR BELANJA (ASB)
SUMUR DANGKAL 60M + JARINGAN PIPA
1 KELOMPOK : Pembangunan Sumur Dangkal 60 m + Jaringan Pipa
2 SUB KELOMPOK : Program Lingkungan Sehat Perumahan
3 SUB- SUB KELOMPOK : Penyediaan sarana air bersih dan sanitasi dasar terutama bagi masyarakat miskin
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
SUMUR DANGKAL 60 M + Jaringan Pipa
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 3.814.398,00
II PEKERJAAN KONSTRUKSI SUMUR 36.859.779,00
III PENGADAAAN DAN PEMASANGAN POMPA 4.900.000,00
IV PEKERJAAN INSTALASI LISTRIK 5.000.000,00
V PENGADAAN DAN PEMASANGAN PIPA JARINGAN 54.387.601,21
JUMLAH (Rp) 104.961.778,21
PPN 10% 10.496.177,82
JUMLAH TOTAL (Rp) 115.457.956,03
JUMLAH DIBULATKAN (Rp) 115.457.000,00
135
ANALISIS STANDAR BELANJA (ASB)
SUMUR DANGKAL 60M + MENARA AIR 4 M + JARINGAN PIPA+ TANGKI AIR KAP.2000 + SR
Pembangunan Sumur Dangkal 60 m + Menara 4m + Jaringan Pipa + Tangki Air 2000
1 KELOMPOK :
ltr+ SR
2 SUB KELOMPOK : Program Lingkungan Sehat Perumahan
3 SUB- SUB KELOMPOK : Penyediaan sarana air bersih dan sanitasi dasar terutama bagi masyarakat miskin
136
VII PEKERJAAN PIPA, TANGKI DAN ACCESSORIES -
Pekerjaan Tangki Dan Accessories -
1 Tangki PE Kapasitas 2.000 Ltr bh 1,000 3.500.000,00 3.500.000,00
- Pipa Inlet : -
- Pipa PVC Dia.1 1/2" m¹ 6,000 37.586,00 225.516,00
- Knee PVC Dia.1 1/2" bh 2,000 66.790,00 133.580,00
- Tee PVC Dia.1 1/2" bh 1,000 24.000,00 24.000,00
- Socket Drat Luar Dia.1 1/2" bh 2,000 13.000,00 26.000,00
- Stop Valve Dia.1 1/2" bh 1,000 387.836,00 387.836,00
- Pipa Outlet : -
- Pipa PVC Dia. 11/2" m¹ 4,000 37.586,00 150.344,00
- Bend All Socket PVC 90° Dia. 1 1/2" bh 2,000 66.790,00 133.580,00
- Tee All Socket dia. 11/2" x 1" bh 2,000 24.000,00 48.000,00
- Socket Drat Luar PVC Dia. 11/2" bh 2,000 13.000,00 26.000,00
- Stop Valve Dia. 11/2" bh 1,000 387.836,00 387.836,00
2 Pemasangan Pipa, Tangki dan Accessories -
- Pipa Inlet -
- Tangki PE Kapasitas 2.000 Ltr bh 0,200 3.500.000,00 700.000,00
Jumlah 5.742.692,00
VIII PENGADAAN DAN PEMASANGAN PIPA JARINGAN -
1 Pengadaan Pipa -
Pengadaan Pipa PVC - AW -
Pipa PVC Dia. 63 mm ( 1 2/2 " ) m¹ 90,000 37.586,00 3.382.740,00
Pipa PVC Dia. 32 mm ( 1 " ) m¹ 540,000 30.233,00 16.325.820,00
2 Pemasangan Pipa PVC -
Galian Tanah Biasa -
Pipa PVC Dia. 63 mm ( 11/2 " ) m³ 6,000 119.924,00 719.544,00
Pipa PVC Dia. 32 mm ( 1 " ) m³ 48,000 119.924,00 5.756.352,00
Galian Tanah Keras -
Pipa PVC Dia. 63 mm ( 11/2 " ) m³ 4,800 159.621,00 766.180,80
Pipa PVC Dia. 32 mm ( 1 " ) m³ 1,680 159.621,00 268.163,28
Perbaikan Bekas Galian Pipa, Rabat Beton 1:3:5 -
Perbaikan Bekas Galian Pipa, Rabat Beton 1:3:5 m³ 0,650 1.016.351,00 660.628,15
Jumlah 27.879.428,23
IX PEKERJAAN SAMBUNGAN RUMAH -
1 Pengadaan Dan Pemasangan Sambungan Rumah unit 25,000 833.001,00 20.825.025,00
Jumlah 20.825.025,00
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
SUMUR DANGKAL 60 M + MENARA 4M + JARINGAN PIPA + TANGKI AIR 2000 ltr + SR
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 3.814.398,00
II PEKERJAAN KONSTRUKSI SUMUR 36.859.779,00
III PENGADAAAN DAN PEMASANGAN POMPA 4.900.000,00
IV PEKERJAAN INSTALASI LISTRIK 5.000.000,00
V PEMBUATAN MENARA AIR TINGGI 4 m, KAPASITAS 2.000 LITER 16.914.746,00
VI PEKERJAAN DINDING DAN LANTAI 805.649,25
VII PEKERJAAN PIPA, TANGKI DAN ACCESSORIES 5.742.692,00
VIII PENGADAAN DAN PEMASANGAN PIPA JARINGAN 27.879.428,23
IX PEKERJAAN SAMBUNGAN RUMAH 20.825.025,00
JUMLAH (Rp) 122.741.717,48
PPN 10% 12.274.171,75
JUMLAH TOTAL (Rp) 135.015.889,23
JUMLAH DIBULATKAN (Rp) 135.015.000,00
137
ANALISIS STANDAR BELANJA (ASB)
SUMUR DANGKAL 60M x 2 UNIT + MENARA AIR 4 M + JARINGAN PIPA+ TANGKI AIR KAP.2000
Pembangunan Sumur Dangkal 60 m x 2 Unit + Menara 4m + Jaringan Pipa + Tangki
1 KELOMPOK :
Air 2000 ltr+ SR
2 SUB KELOMPOK : Program Lingkungan Sehat Perumahan
3 SUB- SUB KELOMPOK : Penyediaan sarana air bersih dan sanitasi dasar terutama bagi masyarakat miskin
138
VII A PEKERJAAN PIPA, TANGKI DAN ACCESSORIES -
Pekerjaan Tangki Dan Accessories -
1 Tangki PE Kapasitas 2.000 Ltr bh 1,000 3.500.000,00 3.500.000,00
- Pipa Inlet : -
- Pipa PVC Dia.1 1/2" m¹ 6,000 37.586,00 225.516,00
- Knee PVC Dia.1 1/2" bh 2,000 66.790,00 133.580,00
- Tee PVC Dia.1 1/2" bh 1,000 24.000,00 24.000,00
- Socket Drat Luar Dia.1 1/2" bh 2,000 13.000,00 26.000,00
- Stop Valve Dia.1 1/2" bh 1,000 387.836,00 387.836,00
- Pipa Outlet : -
- Pipa PVC Dia. 11/2" m¹ 4,000 37.586,00 150.344,00
- Bend All Socket PVC 90° Dia. 1 1/2" bh 2,000 66.790,00 133.580,00
- Tee All Socket dia. 11/2" x 1" bh 2,000 24.000,00 48.000,00
- Socket Drat Luar PVC Dia. 11/2" bh 2,000 13.000,00 26.000,00
- Stop Valve Dia. 11/2" bh 1,000 387.836,00 387.836,00
2 Pemasangan Pipa, Tangki dan Accessories -
- Pipa Inlet -
- Tangki PE Kapasitas 2.000 Ltr bh 0,200 3.500.000,00 700.000,00
Jumlah 5.742.692,00
VIII A PENGADAAN DAN PEMASANGAN PIPA JARINGAN -
1 Pengadaan Pipa -
Pengadaan Pipa PVC - AW -
Pipa PVC Dia. 63 mm (1 1/2 " ) m¹ 100,000 37.586,00 3.758.600,00
Pipa PVC Dia. 32 mm ( 1 " ) m¹ 300,000 30.233,00 9.069.900,00
2 Pemasangan Pipa PVC -
Galian Tanah Biasa -
Pipa PVC Dia. 63 mm ( 11/2 " ) m³ 6,000 119.924,00 719.544,00
Pipa PVC Dia. 32 mm ( 1 " ) m³ 18,000 119.924,00 2.158.632,00
Galian Tanah Keras -
Pipa PVC Dia. 63 mm ( 11/2 " ) m³ 6,000 159.621,00 957.726,00
Pipa PVC Dia. 32 mm ( 1 " ) m³ 18,000 159.621,00 2.873.178,00
Perbaikan Bekas Galian Pipa, Rabat Beton 1:3:5 -
Perbaikan Bekas Galian Pipa, Rabat Beton 1:3:5 m³ 1,000 1.016.351,00 1.016.351,00
Jumlah 20.553.931,00
II B PEKERJAAN KONSTRUKSI SUMUR -
A Pekerjaan Pengeboran -
Pembuatan Lubang Bor Sumur Dangkal Lubang Dia. 6"
1 m¹ 60,000 386.939,00 23.216.340,00
Kedalaman 0 m - 60 m
B Pengadaan dan Pemasangan Material -
1 Pipa Selubung (Casing) PVC Dia. 4" m¹ 50,000 120.248,00 6.012.400,00
2 Pipa Screen Dia. 4" m¹ 10,000 120.248,00 1.202.480,00
3 Pipa Tekan PVC Dia. 1" m¹ 54,000 30.233,00 1.632.582,00
4 Kawat Seling 8mm - m' 60,000 30.000,00 1.800.000,00
Penutup Sumur uk.60.60.50 cm (Pabrikasi bahan beton pra
5 Unit 1,000 2.100.000,00 2.100.000,00
cetak, tutup dari besi cor berlogo)
6 Batu Pecah - Koral 1/2 m³ 1,200 550.000,00 660.000,00
7 Cement Grouting Kedalaman 60 Meter m³ 0,750 314.636,00 235.977,00
Jumlah 36.859.779,00
III B PENGADAAAN DAN PEMASANGAN POMPA -
Pengadaan dan Pemasangan Sumersibel 1 HP Lengkap dengan
1 bh 1,000 4.900.000,00 4.900.000,00
WLC dan Kabel MMYM + Panel
Jumlah 4.900.000,00
IV B PEKERJAAN INSTALASI LISTRIK -
Biaya Pesang Baru listrik ke PLN 2200 + SLO + Box Panel
1 SS 1,000 5.000.000,00 5.000.000,00
KVA 1 phase
Jumlah 5.000.000,00
PEMBUATAN MENARA AIR TINGGI 4 m,
VB -
KAPASITAS 2.000 LITER
A PEKERJAAN TANAH -
1 Galian Tanah Biasa m³ 2,560 119.924,00 307.005,44
2 Urugan Pasir m³ 0,140 268.769,00 37.627,66
3 Urugan Tanah Kembali m³ 2,060 86.899,00 179.011,94
4 Buangan Tanah Sisa Galian m³ 0,360 52.558,00 18.920,88
B PEKERJAAN BETON DAN PASANGAN -
PEKERJAAN STRUKTUR -
Pek PoerPlat 60 x 60 x 20 -
1 Pek. Beton campuran 1 sp : 2 ps : 3 kr m³ 0,290 1.320.118,00 382.834,22
2 Pek. tulangan besi Ø 10, sk Ø 8-150 kg 27,940 17.596,00 491.632,24
3 Pek Bekisting m² 0,070 228.448,00 15.991,36
Pek kolom 30x30 -
1 Pek. Beton campuran 1 sp : 2 ps : 3 kr m³ 0,220 1.320.118,00 290.425,96
2 Pek. tulangan besi Ø 10, sk Ø 8-150 kg 12,960 17.596,00 228.044,16
3 Pek Bekisting m² 2,190 228.448,00 500.301,12
4 Pek. Beton tumbuk Campuran 1 : 3 : 5 m³ 0,420 1.016.351,00 426.867,42
139
C PEKERJAAN BESI -
1 Rangka besi siku, pelat simpul angkur baut kg 230,150 41.264,00 9.496.909,60
2 - Plat bordes 3 mm kg 90,000 36.405,00 3.276.450,00
3 - Pengecatan Besi yang Tampak m² 19,300 51.680,00 997.424,00
- Pembuatan Anak Tangga Dengan Besi DN. 31,25 mm (1
4 m' 7,000 37.900,00 265.300,00
1/4")
Jumlah 16.914.746,00
VI B PEKERJAAN DINDING DAN LANTAI -
1 Pekerjaan Plesteran m² 5,250 95.270,00 500.167,50
2 Pekerjaan Acian m² 5,250 58.187,00 305.481,75
Jumlah 805.649,25
VII B PEKERJAAN PIPA, TANGKI DAN ACCESSORIES -
Pekerjaan Tangki Dan Accessories -
1 Tangki PE Kapasitas 2.000 Ltr bh 1,000 3.500.000,00 3.500.000,00
- Pipa Inlet : -
- Pipa PVC Dia.1 1/2" m¹ 6,000 37.586,00 225.516,00
- Knee PVC Dia.1 1/2" bh 2,000 66.790,00 133.580,00
- Tee PVC Dia.1 1/2" bh 1,000 24.000,00 24.000,00
- Socket Drat Luar Dia.1 1/2" bh 2,000 13.000,00 26.000,00
- Stop Valve Dia.1 1/2" bh 1,000 387.836,00 387.836,00
- Pipa Outlet : -
- Pipa PVC Dia. 11/2" m¹ 4,000 37.586,00 150.344,00
- Bend All Socket PVC 90° Dia. 1 1/2" bh 2,000 66.790,00 133.580,00
- Tee All Socket dia. 11/2" x 1" bh 2,000 24.000,00 48.000,00
- Socket Drat Luar PVC Dia. 11/2" bh 2,000 13.000,00 26.000,00
- Stop Valve Dia. 11/2" bh 1,000 387.836,00 387.836,00
2 Pemasangan Pipa, Tangki dan Accessories -
- Pipa Inlet -
- Tangki PE Kapasitas 2.000 Ltr bh 0,200 3.500.000,00 700.000,00
Jumlah 5.742.692,00
VIII B PENGADAAN DAN PEMASANGAN PIPA JARINGAN -
1 Pengadaan Pipa -
Pengadaan Pipa PVC - AW -
Pipa PVC Dia. 63 mm ( 1 2/2 " ) m¹ 100,000 37.586,00 3.758.600,00
Pipa PVC Dia. 32 mm ( 1 " ) m¹ 300,000 30.233,00 9.069.900,00
2 Pemasangan Pipa PVC -
Galian Tanah Biasa -
Pipa PVC Dia. 63 mm ( 11/2 " ) m³ 6,000 119.924,00 719.544,00
Pipa PVC Dia. 32 mm ( 1 " ) m³ 18,000 119.924,00 2.158.632,00
Galian Tanah Keras -
Pipa PVC Dia. 63 mm ( 11/2 " ) m³ 6,000 159.621,00 957.726,00
Pipa PVC Dia. 32 mm ( 1 " ) m³ 18,000 159.621,00 2.873.178,00
Perbaikan Bekas Galian Pipa, Rabat Beton 1:3:5 -
Perbaikan Bekas Galian Pipa, Rabat Beton 1:3:5 m³ 1,000 1.016.351,00 1.016.351,00
Jumlah 20.553.931,00
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
SUMUR DANGKAL 60 M x 2 Unit + MENARA 4M + JARINGAN PIPA + TANGKI AIR 2000 ltr + SR
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 3.814.398,00
II A PEKERJAAN KONSTRUKSI SUMUR 36.859.779,00
III A PENGADAAAN DAN PEMASANGAN POMPA 4.900.000,00
IV A PEKERJAAN INSTALASI LISTRIK 5.000.000,00
VA PEMBUATAN MENARA AIR TINGGI 4 m, KAPASITAS 2.000 LITER 16.914.746,00
VI A PEKERJAAN DINDING DAN LANTAI 805.649,25
VII A PEKERJAAN PIPA, TANGKI DAN ACCESSORIES 5.742.692,00
VIII A PENGADAAN DAN PEMASANGAN PIPA JARINGAN 20.553.931,00
-
II B PEKERJAAN KONSTRUKSI SUMUR 36.859.779,00
III B PENGADAAAN DAN PEMASANGAN POMPA 4.900.000,00
IV B PEKERJAAN INSTALASI LISTRIK 5.000.000,00
VB PEMBUATAN MENARA AIR TINGGI 4 m, KAPASITAS 2.000 LITER 16.914.746,00
VI B PEKERJAAN DINDING DAN LANTAI 805.649,25
VII B PEKERJAAN PIPA, TANGKI DAN ACCESSORIES 5.742.692,00
VIII B PENGADAAN DAN PEMASANGAN PIPA JARINGAN 20.553.931,00
JUMLAH (Rp) 185.367.992,50
PPN 10% 18.536.799,25
JUMLAH TOTAL (Rp) 203.904.791,75
JUMLAH DIBULATKAN (Rp) 203.904.000,00
140
ANALISIS STANDAR BELANJA (ASB)
SUMUR DANGKAL 70M
1 KELOMPOK : Pembangunan Sumur Dangkal 70 m
2 SUB KELOMPOK : Program Lingkungan Sehat Perumahan
3 SUB- SUB KELOMPOK : Penyediaan sarana air bersih dan sanitasi dasar terutama bagi masyarakat miskin
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
SUMUR DANGKAL 70 M
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 3.814.398,00
II PEKERJAAN KONSTRUKSI SUMUR 42.790.908,60
III PENGADAAAN DAN PEMASANGAN POMPA 14.750.000,00
IV PEKERJAAN INSTALASI LISTRIK 6.000.000,00
JUMLAH (Rp) 67.355.306,60
PPN 10% 6.735.530,66
JUMLAH TOTAL (Rp) 74.090.837,26
JUMLAH DIBULATKAN (Rp) 74.090.000,00
141
ANALISIS STANDAR BELANJA (ASB)
SUMUR DANGKAL 70M + MENARA AIR 4 M
1 KELOMPOK : Pembangunan Sumur Dangkal 70 m + Menara 4m
2 SUB KELOMPOK : Program Lingkungan Sehat Perumahan
3 SUB- SUB KELOMPOK : Penyediaan sarana air bersih dan sanitasi dasar terutama bagi masyarakat miskin
142
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
SUMUR DANGKAL 70 M + MENARA 4M
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 3.814.398,00
II PEKERJAAN KONSTRUKSI SUMUR 42.790.908,60
III PENGADAAAN DAN PEMASANGAN POMPA 14.750.000,00
IV PEKERJAAN INSTALASI LISTRIK 6.000.000,00
V PEMBUATAN MENARA AIR TINGGI 4 m, KAPASITAS 2.000 LITER 16.914.746,00
VI PEKERJAAN DINDING DAN LANTAI 650.657,68
JUMLAH (Rp) 84.920.710,28
PPN 10% 8.492.071,03
JUMLAH TOTAL (Rp) 93.412.781,31
JUMLAH DIBULATKAN (Rp) 93.412.000,00
143
ANALISIS STANDAR BELANJA (ASB)
SUMUR DANGKAL 70M + JARINGAN PIPA
1 KELOMPOK : Pembangunan Sumur Dangkal 70 m + Jaringan Pipa
2 SUB KELOMPOK : Program Lingkungan Sehat Perumahan
3 SUB- SUB KELOMPOK : Penyediaan sarana air bersih dan sanitasi dasar terutama bagi masyarakat miskin
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
SUMUR DANGKAL 70 M + JARINGAN PIPA
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 3.814.398,00
II PEKERJAAN KONSTRUKSI SUMUR 42.790.908,60
III PENGADAAAN DAN PEMASANGAN POMPA 14.750.000,00
IV PEKERJAAN INSTALASI LISTRIK 6.000.000,00
V PENGADAAN DAN PEMASANGAN PIPA JARINGAN 46.767.674,64
JUMLAH (Rp) 114.122.981,24
PPN 10% 11.412.298,12
JUMLAH TOTAL (Rp) 125.535.279,36
JUMLAH DIBULATKAN (Rp) 125.535.000,00
144
ANALISIS STANDAR BELANJA (ASB)
SUMUR DANGKAL 70M + MENARA AIR 4 M + JARINGAN PIPA+ TANGKI AIR KAP.2000 + SR
Pembangunan Sumur Dangkal 70 m + Jaringan Pipa + Tangki Air Kapasitas 2000 ltr +
1 KELOMPOK :
SR
2 SUB KELOMPOK : Program Lingkungan Sehat Perumahan
3 SUB- SUB KELOMPOK : Penyediaan sarana air bersih dan sanitasi dasar terutama bagi masyarakat miskin
145
VII PEKERJAAN PIPA, TANGKI DAN ACCESSORIES -
Pekerjaan Tangki Dan Accessories titik -
1 Tangki PE Kapasitas 2.000 Ltr bh 1,000 3.500.000,00 3.500.000,00
- Pipa Inlet : -
- Pipa PVC Dia.1 1/2" m¹ 6,000 37.586,00 225.516,00
- Knee PVC Dia.1 1/2" bh 2,000 66.790,00 133.580,00
- Tee PVC Dia.1 1/2" bh 1,000 24.000,00 24.000,00
- Socket Drat Luar Dia.1 1/2" bh 2,000 13.000,00 26.000,00
- Stop Valve Dia.1 1/2" bh 1,000 387.836,00 387.836,00
- Pipa Outlet : -
- Pipa PVC Dia. 11/2" m¹ 4,000 37.586,00 150.344,00
- Bend All Socket PVC 90° Dia. 1 1/2" bh 2,000 66.790,00 133.580,00
- Tee All Socket dia. 11/2" x 1" bh 2,000 24.000,00 48.000,00
- Socket Drat Luar PVC Dia. 11/2" bh 2,000 13.000,00 26.000,00
- Stop Valve Dia. 11/2" bh 1,000 387.836,00 387.836,00
2 Pemasangan Pipa, Tangki dan Accessories -
- Pipa Inlet -
- Tangki PE Kapasitas 2.000 Ltr bh 0,200 3.500.000,00 700.000,00
Jumlah 5.742.692,00
VIII PENGADAAN DAN PEMASANGAN PIPA JARINGAN -
1 Pengadaan Pipa -
Pengadaan Pipa PVC - AW -
Pipa PVC Dia. 63 mm ( 1 2/2 " ) m¹ 80,000 37.586,00 3.006.880,00
Pipa PVC Dia. 32 mm ( 1 " ) m¹ 400,000 30.233,00 12.093.200,00
2 Pemasangan Pipa PVC -
Galian Tanah Biasa -
Pipa PVC Dia. 63 mm ( 11/2 " ) m³ 7,200 119.924,00 863.452,80
Pipa PVC Dia. 32 mm ( 1 " ) m³ 19,200 119.924,00 2.302.540,80
Galian Tanah Keras -
Pipa PVC Dia. 63 mm ( 11/2 " ) m³ 2,400 159.621,00 383.090,40
Pipa PVC Dia. 32 mm ( 1 " ) m³ 2,880 159.621,00 459.708,48
Perbaikan Bekas Galian Pipa, Rabat Beton 1:3:5 -
Perbaikan Bekas Galian Pipa, Rabat Beton 1:3:5 m³ 1,123 1.016.351,00 1.141.362,17
Jumlah 20.250.234,65
IX PEKERJAAN SAMBUNGAN RUMAH -
1 Pengadaan Dan Pemasangan Sambungan Rumah unit 35,000 833.001,00 29.155.035,00
Jumlah 29.155.035,00
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
SUMUR DANGKAL 70 M + JARINGAN PIPA + Tangki Air Kapasitas 2000 ltr + SR
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 3.814.398,00
II PEKERJAAN KONSTRUKSI SUMUR 42.790.908,60
III PENGADAAAN DAN PEMASANGAN POMPA 14.750.000,00
IV PEKERJAAN INSTALASI LISTRIK 6.000.000,00
V PEMBUATAN MENARA AIR TINGGI 4 m, KAPASITAS 2.000 LITER 16.914.746,00
] PEKERJAAN DINDING DAN LANTAI 650.657,68
VII PEKERJAAN PIPA, TANGKI DAN ACCESSORIES 5.742.692,00
VIII PENGADAAN DAN PEMASANGAN PIPA JARINGAN 20.250.234,65
IX PEKERJAAN SAMBUNGAN RUMAH 29.155.035,00
JUMLAH (Rp) 140.068.671,93
PPN 10% 14.006.867,19
JUMLAH TOTAL (Rp) 154.075.539,13
JUMLAH DIBULATKAN (Rp) 154.075.000,00
146
ANALISIS STANDAR BELANJA (ASB)
SUMUR DANGKAL 70M x 2 UNIT + MENARA AIR 4 M + JARINGAN PIPA+ TANGKI AIR KAP.2000
Pembangunan Sumur Dangkal 70 m x 2 Unit + Jaringan Pipa + Tangki Air Kapasitas
1 KELOMPOK :
2000 ltr + SR
2 SUB KELOMPOK : Program Lingkungan Sehat Perumahan
3 SUB- SUB KELOMPOK : Penyediaan sarana air bersih dan sanitasi dasar terutama bagi masyarakat miskin
147
VII A PEKERJAAN PIPA, TANGKI DAN ACCESSORIES -
Pekerjaan Tangki Dan Accessories -
1 Tangki PE Kapasitas 2.000 Ltr bh 1,000 3.500.000,00 3.500.000,00
- Pipa Inlet : -
- Pipa PVC Dia.1 1/2" m¹ 6,000 37.586,00 225.516,00
- Knee PVC Dia.1 1/2" bh 2,000 66.790,00 133.580,00
- Tee PVC Dia.1 1/2" bh 1,000 24.000,00 24.000,00
- Socket Drat Luar Dia.1 1/2" bh 2,000 13.000,00 26.000,00
- Stop Valve Dia.1 1/2" bh 1,000 387.836,00 387.836,00
- Pipa Outlet : -
- Pipa PVC Dia. 11/2" m¹ 4,000 37.586,00 150.344,00
- Bend All Socket PVC 90° Dia. 1 1/2" bh 2,000 66.790,00 133.580,00
- Tee All Socket dia. 11/2" x 1" bh 2,000 24.000,00 48.000,00
- Socket Drat Luar PVC Dia. 11/2" bh 2,000 13.000,00 26.000,00
- Stop Valve Dia. 11/2" bh 1,000 387.836,00 387.836,00
2 Pemasangan Pipa, Tangki dan Accessories -
- Pipa Inlet -
- Tangki PE Kapasitas 2.000 Ltr bh 0,200 3.500.000,00 700.000,00
Jumlah 5.742.692,00
VIII A PENGADAAN DAN PEMASANGAN PIPA JARINGAN -
1 Pengadaan Pipa -
Pengadaan Pipa PVC - AW -
Pipa PVC Dia. 63 mm ( 1 2/2 " ) m¹ 10,000 37.586,00 375.860,00
Pipa PVC Dia. 32 mm ( 1 " ) m¹ 20,000 30.233,00 604.660,00
2 Pemasangan Pipa PVC -
Galian Tanah Biasa -
Pipa PVC Dia. 63 mm ( 11/2 " ) m³ 0,600 119.924,00 71.954,40
Pipa PVC Dia. 32 mm ( 1 " ) m³ 1,200 119.924,00 143.908,80
Galian Tanah Keras -
Pipa PVC Dia. 63 mm ( 11/2 " ) m³ 0,600 159.621,00 95.772,60
Pipa PVC Dia. 32 mm ( 1 " ) m³ 0,120 159.621,00 19.154,52
Perbaikan Bekas Galian Pipa, Rabat Beton 1:3:5 -
Perbaikan Bekas Galian Pipa, Rabat Beton 1:3:5 m³ 0,211 1.016.351,00 214.450,06
Jumlah 1.525.760,38
II B PEKERJAAN KONSTRUKSI SUMUR -
A Pekerjaan Pengeboran -
Pembuatan Lubang Bor Sumur Dangkal Lubang Dia. 6"
1 m¹ 70,000 386.939,00 27.085.730,00
Kedalaman 0 m - 60 m
B Pengadaan dan Pemasangan Material -
1 Pipa Selubung (Casing) PVC Dia. 4" m¹ 60,000 120.248,00 7.214.880,00
2 Pipa Screen Dia. 4" m¹ 10,000 120.248,00 1.202.480,00
3 Pipa Tekan PVC Dia. 1" m¹ 66,000 30.233,00 1.995.378,00
4 Kawat Seling 8mm - m' 70,000 30.000,00 2.100.000,00
Penutup Sumur uk.60.60.50 cm (Pabrikasi bahan beton pra
5 Unit 1,000 2.100.000,00 2.100.000,00
cetak, tutup dari besi cor berlogo)
6 Batu Pecah - Koral 1/2 m³ 1,500 550.000,00 825.000,00
7 Cement Grouting Kedalaman 60 Meter m³ 0,850 314.636,00 267.440,60
Jumlah 42.790.908,60
III B PENGADAAAN DAN PEMASANGAN POMPA -
Pengadaan dan Pemasangan Sumersibel 1 HP Lengkap dengan
1 bh 1,000 14.750.000,00 14.750.000,00
WLC dan Kabel MMYM + Panel
Jumlah 14.750.000,00
IV B PEKERJAAN INSTALASI LISTRIK -
Biaya Pesang Baru listrik ke PLN 2200 + SLO + Box Panel
1 SS 1,000 6.000.000,00 6.000.000,00
KVA 1 phase
Jumlah 6.000.000,00
PEMBUATAN MENARA AIR TINGGI 4 m,
VB -
KAPASITAS 2.000 LITER
A PEKERJAAN TANAH -
1 Galian Tanah Biasa m³ 2,560 119.924,00 307.005,44
2 Urugan Pasir m³ 0,140 268.769,00 37.627,66
3 Urugan Tanah Kembali m³ 2,060 86.899,00 179.011,94
4 Buangan Tanah Sisa Galian m³ 0,360 52.558,00 18.920,88
B PEKERJAAN BETON DAN PASANGAN -
PEKERJAAN STRUKTUR -
Pek PoerPlat 60 x 60 x 20 -
1 Pek. Beton campuran 1 sp : 2 ps : 3 kr m³ 0,290 1.320.118,00 382.834,22
2 Pek. tulangan besi Ø 10, sk Ø 8-150 kg 27,940 17.596,00 491.632,24
3 Pek Bekisting m² 0,070 228.448,00 15.991,36
Pek kolom 30x30 -
1 Pek. Beton campuran 1 sp : 2 ps : 3 kr m³ 0,220 1.320.118,00 290.425,96
2 Pek. tulangan besi Ø 10, sk Ø 8-150 kg 12,960 17.596,00 228.044,16
3 Pek Bekisting m² 2,190 228.448,00 500.301,12
4 Pek. Beton tumbuk Campuran 1 : 3 : 5 m³ 0,420 1.016.351,00 426.867,42
148
C PEKERJAAN BESI -
1 Rangka besi siku, pelat simpul angkur baut kg 230,150 41.264,00 9.496.909,60
2 - Plat bordes 3 mm kg 90,000 36.405,00 3.276.450,00
3 - Pengecatan Besi yang Tampak m² 19,300 51.680,00 997.424,00
- Pembuatan Anak Tangga Dengan Besi DN. 31,25 mm (1
4 m' 7,000 37.900,00 265.300,00
1/4")
Jumlah 16.914.746,00
VI B PEKERJAAN DINDING DAN LANTAI -
1 Pekerjaan Plesteran m² 4,240 95.270,00 403.944,80
2 Pekerjaan Acian m² 4,240 58.187,00 246.712,88
Jumlah 650.657,68
VII B PEKERJAAN PIPA, TANGKI DAN ACCESSORIES -
Pekerjaan Tangki Dan Accessories titik -
1 Tangki PE Kapasitas 2.000 Ltr bh 1,000 3.500.000,00 3.500.000,00
- Pipa Inlet : -
- Pipa PVC Dia.1 1/2" m¹ 6,000 37.586,00 225.516,00
- Knee PVC Dia.1 1/2" bh 2,000 66.790,00 133.580,00
- Tee PVC Dia.1 1/2" bh 1,000 24.000,00 24.000,00
- Socket Drat Luar Dia.1 1/2" bh 2,000 13.000,00 26.000,00
- Stop Valve Dia.1 1/2" bh 1,000 387.836,00 387.836,00
- Pipa Outlet : -
- Pipa PVC Dia. 11/2" m¹ 4,000 37.586,00 150.344,00
- Bend All Socket PVC 90° Dia. 1 1/2" bh 2,000 66.790,00 133.580,00
- Tee All Socket dia. 11/2" x 1" bh 2,000 24.000,00 48.000,00
- Socket Drat Luar PVC Dia. 11/2" bh 2,000 13.000,00 26.000,00
- Stop Valve Dia. 11/2" bh 1,000 387.836,00 387.836,00
2 Pemasangan Pipa, Tangki dan Accessories -
- Pipa Inlet -
- Tangki PE Kapasitas 2.000 Ltr bh 0,200 3.500.000,00 700.000,00
Jumlah 5.742.692,00
VIII B PENGADAAN DAN PEMASANGAN PIPA JARINGAN -
1 Pengadaan Pipa -
Pengadaan Pipa PVC - AW -
Pipa PVC Dia. 63 mm ( 1 2/2 " ) m¹ 10,000 37.586,00 375.860,00
Pipa PVC Dia. 32 mm ( 1 " ) m¹ 20,000 30.233,00 604.660,00
2 Pemasangan Pipa PVC -
Galian Tanah Biasa -
Pipa PVC Dia. 63 mm ( 11/2 " ) m³ 0,600 119.924,00 71.954,40
Pipa PVC Dia. 32 mm ( 1 " ) m³ 1,200 119.924,00 143.908,80
Galian Tanah Keras -
Pipa PVC Dia. 63 mm ( 11/2 " ) m³ 0,600 159.621,00 95.772,60
Pipa PVC Dia. 32 mm ( 1 " ) m³ 0,120 159.621,00 19.154,52
Perbaikan Bekas Galian Pipa, Rabat Beton 1:3:5 -
Perbaikan Bekas Galian Pipa, Rabat Beton 1:3:5 m³ 0,211 1.016.351,00 214.450,06
Jumlah 1.525.760,38
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
SUMUR DANGKAL 70 M x 2 Unit + JARINGAN PIPA + Tangki Air Kapasitas 2000 ltr + SR
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 3.814.398,00
II A PEKERJAAN KONSTRUKSI SUMUR 42.790.908,60
III A PENGADAAAN DAN PEMASANGAN POMPA 14.750.000,00
IV A PEKERJAAN INSTALASI LISTRIK 6.000.000,00
VA PEMBUATAN MENARA AIR TINGGI 4 m, KAPASITAS 2.000 LITER 16.914.746,00
VI A PEKERJAAN DINDING DAN LANTAI 650.657,68
VII A PEKERJAAN PIPA, TANGKI DAN ACCESSORIES 5.742.692,00
VIII A PENGADAAN DAN PEMASANGAN PIPA JARINGAN 1.525.760,38
-
II B PEKERJAAN KONSTRUKSI SUMUR 42.790.908,60
III B PENGADAAAN DAN PEMASANGAN POMPA 14.750.000,00
IV B PEKERJAAN INSTALASI LISTRIK 6.000.000,00
VB PEMBUATAN MENARA AIR TINGGI 4 m, KAPASITAS 2.000 LITER 16.914.746,00
VI B PEKERJAAN DINDING DAN LANTAI 650.657,68
VII B PEKERJAAN PIPA, TANGKI DAN ACCESSORIES 5.742.692,00
VIII B PENGADAAN DAN PEMASANGAN PIPA JARINGAN 1.525.760,38
JUMLAH (Rp) 180.563.927,32
PPN 10% 18.056.392,73
JUMLAH TOTAL (Rp) 198.620.320,05
JUMLAH DIBULATKAN (Rp) 198.620.000,00
149
ANALISIS STANDAR BELANJA (ASB)
SUMUR DANGKAL 80M
1 KELOMPOK : Pembangunan Sumur Dangkal 80 m
2 SUB KELOMPOK : Program Lingkungan Sehat Perumahan
3 SUB- SUB KELOMPOK : Penyediaan sarana air bersih dan sanitasi dasar terutama bagi masyarakat miskin
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
SUMUR DANGKAL 80 M
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 3.814.398,00
II PEKERJAAN KONSTRUKSI SUMUR 48.512.304,00
III PENGADAAAN DAN PEMASANGAN POMPA 17.400.000,00
IV PEKERJAAN INSTALASI LISTRIK 7.500.000,00
JUMLAH (Rp) 77.226.702,00
PPN 10% 7.722.670,20
JUMLAH TOTAL (Rp) 84.949.372,20
JUMLAH DIBULATKAN (Rp) 84.949.000,00
150
ANALISIS STANDAR BELANJA (ASB)
SUMUR DANGKAL 80M + MENARA AIR 4 M
1 KELOMPOK : Pembangunan Sumur Dangkal 80 m + Menara Air 4 m
2 SUB KELOMPOK : Program Lingkungan Sehat Perumahan
3 SUB- SUB KELOMPOK : Penyediaan sarana air bersih dan sanitasi dasar terutama bagi masyarakat miskin
151
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
SUMUR DANGKAL 80 M + MENARA AIR 4m
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 3.814.398,00
II PEKERJAAN KONSTRUKSI SUMUR 48.512.304,00
III PENGADAAAN DAN PEMASANGAN POMPA 17.400.000,00
IV PEKERJAAN INSTALASI LISTRIK 7.500.000,00
V PEMBUATAN MENARA AIR TINGGI 4 m, KAPASITAS 2.000 LITER 16.914.746,00
VI PEKERJAAN DINDING DAN LANTAI 650.657,68
JUMLAH (Rp) 94.792.105,68
PPN 10% 9.479.210,57
JUMLAH TOTAL (Rp) 104.271.316,25
JUMLAH DIBULATKAN (Rp) 104.271.000,00
152
ANALISIS STANDAR BELANJA (ASB)
SUMUR DANGKAL 80M + JARINGAN PIPA
1 KELOMPOK : Pembangunan Sumur Dangkal 80 m + Jaringan Pipa
2 SUB KELOMPOK : Program Lingkungan Sehat Perumahan
3 SUB- SUB KELOMPOK : Penyediaan sarana air bersih dan sanitasi dasar terutama bagi masyarakat miskin
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
SUMUR DANGKAL 80 M + JARINGAN PIPA
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 3.814.398,00
II PEKERJAAN KONSTRUKSI SUMUR 48.512.304,00
III PEKERJAAN KONSTRUKSI SUMUR 17.400.000,00
IV PEKERJAAN INSTALASI LISTRIK 7.500.000,00
V PENGADAAN DAN PEMASANGAN PIPA JARINGAN 50.496.775,47
JUMLAH (Rp) 127.723.477,47
PPN 10% 12.772.347,75
JUMLAH TOTAL (Rp) 140.495.825,22
JUMLAH DIBULATKAN (Rp) 140.495.000,00
153
ANALISIS STANDAR BELANJA (ASB)
SUMUR DANGKAL 80M + MENARA AIR 4 M + JARINGAN PIPA+ TANGKI AIR KAP.2000 + SR
Pembangunan Sumur Dangkal 80 m + Jaringan Pipa + Tangki Air Kapasitas 2000 ltr +
1 KELOMPOK :
SR
2 SUB KELOMPOK : Program Lingkungan Sehat Perumahan
3 SUB- SUB KELOMPOK : Penyediaan sarana air bersih dan sanitasi dasar terutama bagi masyarakat miskin
154
VII PEKERJAAN PIPA, TANGKI DAN ACCESSORIES -
Pekerjaan Tangki Dan Accessories titik - -
1 Tangki PE Kapasitas 2.000 Ltr bh 1,000 3.500.000,00 3.500.000,00
- Pipa Inlet : -
- Pipa PVC Dia.1 1/2" m¹ 6,000 37.586,00 225.516,00
- Knee PVC Dia.1 1/2" bh 2,000 66.790,00 133.580,00
- Tee PVC Dia.1 1/2" bh 1,000 24.000,00 24.000,00
- Socket Drat Luar Dia.1 1/2" bh 2,000 13.000,00 26.000,00
- Stop Valve Dia.1 1/2" bh 1,000 387.836,00 387.836,00
- Pipa Outlet : -
- Pipa PVC Dia. 11/2" m¹ 4,000 37.586,00 150.344,00
- Bend All Socket PVC 90° Dia. 1 1/2" bh 2,000 66.790,00 133.580,00
- Tee All Socket dia. 11/2" x 1" bh 2,000 24.000,00 48.000,00
- Socket Drat Luar PVC Dia. 11/2" bh 2,000 13.000,00 26.000,00
- Stop Valve Dia. 11/2" bh 1,000 387.836,00 387.836,00
2 Pemasangan Pipa, Tangki dan Accessories -
- Pipa Inlet -
- Tangki PE Kapasitas 2.000 Ltr bh 0,200 3.500.000,00 700.000,00
Jumlah 5.742.692,00
VIII PENGADAAN DAN PEMASANGAN PIPA JARINGAN -
1 Pengadaan Pipa -
Pengadaan Pipa PVC - AW -
Pipa PVC Dia. 63 mm ( 1 2/2 " ) m¹ 100,000 37.586,00 3.758.600,00
Pipa PVC Dia. 32 mm ( 1 " ) m¹ 600,000 30.233,00 18.139.800,00
2 Pemasangan Pipa PVC -
Galian Tanah Biasa -
Pipa PVC Dia. 63 mm ( 11/2 " ) m³ 6,000 119.924,00 719.544,00
Pipa PVC Dia. 32 mm ( 1 " ) m³ 48,000 119.924,00 5.756.352,00
Galian Tanah Keras -
Pipa PVC Dia. 63 mm ( 11/2 " ) m³ 6,000 159.621,00 957.726,00
Pipa PVC Dia. 32 mm ( 1 " ) m³ 2,400 159.621,00 383.090,40
Perbaikan Bekas Galian Pipa, Rabat Beton 1:3:5 -
Perbaikan Bekas Galian Pipa, Rabat Beton 1:3:5 m³ 3,967 1.016.351,00 4.031.864,42
Jumlah 33.746.976,82
IX PEKERJAAN SAMBUNGAN RUMAH -
1 Pengadaan Dan Pemasangan Sambungan Rumah unit 35,000 833.001,00 29.155.035,00
Jumlah 29.155.035,00
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
SUMUR DANGKAL 80 M + JARINGAN PIPA + Tangki Air Kapasitas 2000 ltr + SR
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 3.814.398,00
II PEKERJAAN KONSTRUKSI SUMUR 48.512.304,00
III PENGADAAAN DAN PEMASANGAN POMPA 17.400.000,00
IV PEKERJAAN INSTALASI LISTRIK 7.500.000,00
V PEMBUATAN MENARA AIR TINGGI 4 m, KAPASITAS 2.000 LITER 16.914.746,00
VI PEKERJAAN DINDING DAN LANTAI 650.657,68
VII PEKERJAAN PIPA, TANGKI DAN ACCESSORIES 5.742.692,00
VIII PENGADAAN DAN PEMASANGAN PIPA JARINGAN 33.746.976,82
IX PEKERJAAN SAMBUNGAN RUMAH 29.155.035,00
JUMLAH (Rp) 163.436.809,50
PPN 10% 16.343.680,95
JUMLAH TOTAL (Rp) 179.780.490,45
JUMLAH DIBULATKAN (Rp) 179.780.000,00
155
ANALISIS STANDAR BELANJA (ASB)
SUMUR DANGKAL 80M + MENARA AIR 4 M + JARINGAN PIPA+ TANGKI AIR KAP.2000 + SR DAK
Pembangunan Sumur Dangkal 80 m + Jaringan Pipa + Tangki Air Kapasitas 2000 ltr +
1 KELOMPOK :
SR DAK
2 SUB KELOMPOK : Program Lingkungan Sehat Perumahan
3 SUB- SUB KELOMPOK : Penyediaan sarana air bersih dan sanitasi dasar terutama bagi masyarakat miskin
156
VII PEKERJAAN PIPA, TANGKI DAN ACCESSORIES -
Pekerjaan Tangki Dan Accessories titik - -
1 Tangki PE Kapasitas 2.000 Ltr bh 1,000 3.500.000,00 3.500.000,00
- Pipa Inlet : -
- Pipa PVC Dia.1 1/2" m¹ 6,000 37.586,00 225.516,00
- Knee PVC Dia.1 1/2" bh 2,000 66.790,00 133.580,00
- Tee PVC Dia.1 1/2" bh 1,000 24.000,00 24.000,00
- Socket Drat Luar Dia.1 1/2" bh 2,000 13.000,00 26.000,00
- Stop Valve Dia.1 1/2" bh 1,000 387.836,00 387.836,00
- Pipa Outlet : -
- Pipa PVC Dia. 11/2" m¹ 4,000 37.586,00 150.344,00
- Bend All Socket PVC 90° Dia. 1 1/2" bh 2,000 66.790,00 133.580,00
- Tee All Socket dia. 11/2" x 1" bh 2,000 24.000,00 48.000,00
- Socket Drat Luar PVC Dia. 11/2" bh 2,000 13.000,00 26.000,00
- Stop Valve Dia. 11/2" bh 1,000 387.836,00 387.836,00
2 Pemasangan Pipa, Tangki dan Accessories -
- Pipa Inlet -
- Tangki PE Kapasitas 2.000 Ltr bh 0,200 3.500.000,00 700.000,00
Jumlah 5.742.692,00
VIII PENGADAAN DAN PEMASANGAN PIPA JARINGAN -
1 Pengadaan Pipa -
Pengadaan Pipa PVC - AW -
Pipa PVC Dia. 63 mm ( 1 2/2 " ) m¹ 100,000 37.586,00 3.758.600,00
Pipa PVC Dia. 32 mm ( 1 " ) m¹ 800,000 30.233,00 24.186.400,00
2 Pemasangan Pipa PVC -
Galian Tanah Biasa -
Pipa PVC Dia. 63 mm ( 11/2 " ) m³ 6,000 119.924,00 719.544,00
Pipa PVC Dia. 32 mm ( 1 " ) m³ 32,000 119.924,00 3.837.568,00
Galian Tanah Keras -
Pipa PVC Dia. 63 mm ( 11/2 " ) m³ 6,000 159.621,00 957.726,00
Pipa PVC Dia. 32 mm ( 1 " ) m³ 32,000 159.621,00 5.107.872,00
Perbaikan Bekas Galian Pipa, Rabat Beton 1:3:5 -
Perbaikan Bekas Galian Pipa, Rabat Beton 1:3:5 m³ 1,000 1.016.351,00 1.016.351,00
Jumlah 39.584.061,00
IX PEKERJAAN SAMBUNGAN RUMAH -
1 Pengadaan Dan Pemasangan Sambungan Rumah unit 50,000 833.001,00 41.650.050,00
Jumlah 41.650.050,00
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
SUMUR DANGKAL 80 M + JARINGAN PIPA + Tangki Air Kapasitas 2000 ltr + SR DAK
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 3.814.398,00
II PEKERJAAN KONSTRUKSI SUMUR 48.512.304,00
III PENGADAAAN DAN PEMASANGAN POMPA 17.400.000,00
IV PEKERJAAN INSTALASI LISTRIK 7.500.000,00
V PEMBUATAN MENARA AIR TINGGI 4 m, KAPASITAS 2.000 LITER 16.914.746,00
VI PEKERJAAN DINDING DAN LANTAI 650.657,68
VII PEKERJAAN PIPA, TANGKI DAN ACCESSORIES 5.742.692,00
VIII PENGADAAN DAN PEMASANGAN PIPA JARINGAN 39.584.061,00
IX PEKERJAAN SAMBUNGAN RUMAH 41.650.050,00
JUMLAH (Rp) 181.768.908,68
PPN 10% 18.176.890,87
JUMLAH TOTAL (Rp) 199.945.799,55
JUMLAH DIBULATKAN (Rp) 199.945.000,00
157
ANALISIS STANDAR BELANJA (ASB)
SUMUR DALAM 100 M
1 KELOMPOK : Pembangunan Sumur Dalam 100 m
2 SUB KELOMPOK : Program Lingkungan Sehat Perumahan
3 SUB- SUB KELOMPOK : Penyediaan sarana air bersih dan sanitasi dasar terutama bagi masyarakat miskin
158
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
SUMUR DALAM 100 M
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 3.814.398,00
II PEKERJAAN KONSTRUKSI SUMUR 119.514.476,00
III PENGADAAAN DAN PEMASANGAN POMPA 34.250.000,00
IV PEKERJAAN INSTALASI LISTRIK 14.850.000,00
9.379.375,29
JUMLAH (Rp) 181.808.249,29
PPN 10% 18.180.824,93
JUMLAH TOTAL (Rp) 199.989.074,22
JUMLAH DIBULATKAN (Rp) 199.989.000,00
159
ANALISIS STANDAR BELANJA (ASB)
SUMUR DALAM 100 M + MENARA AIR 6 M TANGKI AIR KAP.5000 Lt
1 KELOMPOK : Pembangunan Sumur Dalam 100 m + Menara Kapasitas 5000 ltr
2 SUB KELOMPOK : Program Lingkungan Sehat Perumahan
3 SUB- SUB KELOMPOK : Penyediaan sarana air bersih dan sanitasi dasar terutama bagi masyarakat miskin
160
VI PEKERJAAN DINDING DAN LANTAI -
1 Pekerjaan Plesteran m² 10,500 95.270,00 1.000.335,00
2 Pekerjaan Acian m² 10,500 58.187,00 610.963,50
Jumlah 1.611.298,50
-
VII PEKERJAAN PIPA, TANGKI DAN ACCESSORIES -
1 Tangki PE Kapasitas 5.000 Ltr bh 1,000 7.500.000,00 7.500.000,00
Jumlah 7.500.000,00
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
SUMUR DALAM 100 M + MENARA KAPASITAS 5000 Liter
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 3.814.398,00
II PEKERJAAN KONSTRUKSI SUMUR 119.514.476,00
III PENGADAAAN DAN PEMASANGAN POMPA 34.250.000,00
IV PEKERJAAN INSTALASI LISTRIK 14.850.000,00
V PEMBUATAN MENARA AIR TINGGI 6 m, KAPASITAS 5.000 LITER 30.657.718,84
VI PEKERJAAN DINDING DAN LANTAI 1.611.298,50
VII PEKERJAAN PIPA, TANGKI DAN ACCESSORIES 7.500.000,00
JUMLAH (Rp) 212.197.891,34
PPN 10% 21.219.789,13
JUMLAH TOTAL (Rp) 233.417.680,47
JUMLAH DIBULATKAN (Rp) 233.417.000,00
161
ANALISIS STANDAR BELANJA (ASB)
SUMUR DALAM 100 M + JARINGAN
1 KELOMPOK : Pembangunan Sumur Dalam 100 m + Jaringan Pipa
2 SUB KELOMPOK : Program Lingkungan Sehat Perumahan
3 SUB- SUB KELOMPOK : Penyediaan sarana air bersih dan sanitasi dasar terutama bagi masyarakat miskin
162
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
SUMUR DALAM 100 M + JARINGAN PIPA
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 3.814.398,00
II PEKERJAAN KONSTRUKSI SUMUR 119.514.476,00
III PENGADAAAN DAN PEMASANGAN POMPA 34.250.000,00
IV PEKERJAAN INSTALASI LISTRIK 14.850.000,00
V PENGADAAN DAN PEMASANGAN PIPA JARINGAN 65.345.308,60
JUMLAH (Rp) 237.774.182,60
PPN 10% 23.777.418,26
JUMLAH TOTAL (Rp) 261.551.600,86
JUMLAH DIBULATKAN (Rp) 261.551.000,00
163
ANALISIS STANDAR BELANJA (ASB)
SUMUR DALAM 150 M
1 KELOMPOK : Pembangunan Sumur Dalam 150 m
2 SUB KELOMPOK : Program Lingkungan Sehat Perumahan
3 SUB- SUB KELOMPOK : Penyediaan sarana air bersih dan sanitasi dasar terutama bagi masyarakat miskin
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
SUMUR DALAM 150 M
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 3.814.398,00
II PEKERJAAN KONSTRUKSI SUMUR 193.610.230,20
III PENGADAAAN DAN PEMASANGAN POMPA 56.745.000,00
IV PEKERJAAN INSTALASI LISTRIK 23.804.000,00
JUMLAH (Rp) 277.973.628,20
PPN 10% 27.797.362,82
JUMLAH TOTAL (Rp) 305.770.991,02
JUMLAH DIBULATKAN (Rp) 305.770.000,00
164
ANALISIS STANDAR BELANJA (ASB)
SUMUR DALAM 150M + MENARA+JARINGAN PIPA+SR
1 KELOMPOK : Pembangunan Sumur Dalam 150 m + Menara 6 m Kapasitas 5000 Ltr+ Jaringan Pipa
2 SUB KELOMPOK : Program Lingkungan Sehat Perumahan
3 SUB- SUB KELOMPOK : Penyediaan sarana air bersih dan sanitasi dasar terutama bagi masyarakat miskin
165
C PEKERJAAN BESI -
Rangka besi IWF, pelat simpul angkur baut -
1 Besi WF 200.100.5,5.8 kg 923,400 39.711,00 36.669.137,40
2 Besi WF 148.100.6.9 kg 611,300 39.711,00 24.275.334,30
3 Besi UNP 100.50.5 kg 421,150 36.405,00 15.331.965,75
4 Railing Pipa GI DN. 1,5" (37,5 mm) m' 48,000 43.300,00 2.078.400,00
5 Base Plate 400 mm x 400 mm x 16 mm kg 121,600 36.405,00 4.426.848,00
6 Simpul Besi Plate 8 mm m¹ 108,000 18.902,00 2.041.416,00
7 Pasang baut Ø 16 bh 32,000 26.686,00 853.952,00
8 Pembuatan Anak Tangga Dengan Besi DN. 1,5" (37,5 mm) m' 9,000 43.300,00 389.700,00
9 - Plat bordes 3 mm kg 240,000 36.405,00 8.737.200,00
10 Pengecatan Besi yang Tampak m² 135,000 51.680,00 6.976.800,00
Jumlah 118.039.336,35
VI PEKERJAAN DINDING DAN LANTAI -
1 Pekerjaan Plesteran m² 12,600 95.270,00 1.200.402,00
2 Pekerjaan Acian m² 12,600 58.187,00 733.156,20
Jumlah 1.933.558,20
VII PEKERJAAN PIPA, TANGKI DAN ACCESSORIES -
1 Tangki PE Kapasitas 5.000 Ltr bh 2,000 7.500.000,00 15.000.000,00
- Pipa Inlet : -
- Pipa PVC Dia.1 1/2" m¹ 8,000 37.586,00 300.688,00
- Knee PVC Dia.1 1/2" bh 2,000 66.790,00 133.580,00
- Tee PVC Dia.1 1/2" bh 1,000 24.000,00 24.000,00
- Socket Drat Luar Dia.1 1/2" bh 2,000 13.000,00 26.000,00
- Stop Valve Dia.1 1/2" bh 1,000 387.836,00 387.836,00
- Pipa Outlet : -
- Pipa PVC Dia. 11/2" m¹ 6,000 37.586,00 225.516,00
- Bend All Socket PVC 90° Dia. 1 1/2" bh 2,000 66.790,00 133.580,00
- Tee All Socket dia. 11/2" x 1" bh 2,000 24.000,00 48.000,00
- Socket Drat Luar PVC Dia. 11/2" bh 2,000 13.000,00 26.000,00
- Stop Valve Dia. 11/2" bh 1,000 387.836,00 387.836,00
2 Pipa Penguras Dan Over flow -
- Pipa PVC Dia. 11/2" m¹ 6,000 37.586,00 225.516,00
- Bend All Socket PVC 90° Dia. 1 1/2" bh 2,000 66.790,00 133.580,00
- Tee All Socket dia. 11/2" x 1" bh 2,000 24.000,00 48.000,00
- Socket Drat Luar PVC Dia. 11/2" bh 2,000 13.000,00 26.000,00
- Stop Valve Dia. 11/2" bh 1,000 387.836,00 387.836,00
3 Pemasangan Tangki dan Accessories -
- Tangki PE Kapasitas 5.000 Ltr bh 0,200 7.500.000,00 1.500.000,00
Jumlah 19.013.968,00
VIII PENGADAAN DAN PEMASANGAN PIPA JARINGAN -
1 Pengadaan Pipa -
Pemasangan Pipa PVC - AW -
Pipa PVC Dia. 63 mm ( 2 " ) m¹ 800,000 48.759,00 39.007.200,00
Pipa PVC Dia. 32 mm ( 1 " ) m¹ 1.500,000 30.233,00 45.349.500,00
2 Galian Pemasangan Pipa PVC -
Galian Tanah Biasa -
Pipa PVC Dia. 63 mm ( 11/2 " ) m³ 48,000 119.924,00 5.756.352,00
Pipa PVC Dia. 32 mm ( 1 " ) m³ 60,000 119.924,00 7.195.440,00
Galian Tanah Keras -
Pipa PVC Dia. 63 mm ( 11/2 " ) m³ 48,000 159.621,00 7.661.808,00
Pipa PVC Dia. 32 mm ( 1 " ) m³ 60,000 159.621,00 9.577.260,00
3 Perbaikan Bekas Galian Pipa, Rabat Beton 1:3:5 -
Perbaikan Bekas Galian Pipa, Rabat Beton 1:3:5 m³ 5,200 1.016.351,00 5.285.025,20
Jumlah 119.832.585,20
IX PEKERJAAN SAMBUNGAN RUMAH -
Pengadaan Dan Pemasangan Sambungan Rumah unit 180,000 833.001,00 149.940.180,00
Jumlah 149.940.180,00
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
SUMUR DALAM 150 M + MENARA 6 M KAP. 2X 5000 Ltr + JARINGAN PIPA + SR
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 3.814.398,00
II PEKERJAAN KONSTRUKSI SUMUR DALAM 193.610.230,20
III PENGADAAAN DAN PEMASANGAN POMPA 56.745.000,00
IV PEKERJAAN INSTALASI LISTRIK 23.804.000,00
V PEMBUATAN MENARA AIR TINGGI 6 m, KAPASITAS 2X 5.000 LITER 118.039.336,35
VI PEKERJAAN DINDING DAN LANTAI 1.933.558,20
VII PEKERJAAN PIPA, TANGKI DAN ACCESSORIES 19.013.968,00
VIII PENGADAAN DAN PEMASANGAN PIPA JARINGAN 119.832.585,20
IX PEKERJAAN SAMBUNGAN RUMAH 149.940.180,00
JUMLAH (Rp) 686.733.255,95
PPN 10% 68.673.325,60
JUMLAH TOTAL (Rp) 755.406.581,55
JUMLAH DIBULATKAN (Rp) 755.406.000,00
166
ANALISIS STANDAR BELANJA (ASB)
SUMUR DALAM 150M + RESEVOAR 20 M3+PEMAGARAN+JARINGAN PIPA+SR
1 KELOMPOK : KONSTRUKSI
2 SUB KELOMPOK : Program Lingkungan Sehat Perumahan
3 SUB- SUB KELOMPOK : Penyediaan sarana air bersih dan sanitasi dasar terutama bagi masyarakat miskin
167
VIII PEKERJAAN PIPA DAN ASESORI -
A Pipa Inlet -
1 Wall Pipe GIP All Flange L = 60 cm Dia. 63 mm (2") unit 1,000 368.421,00 368.421,00
2 Flange Socket Dia. 63 mm (2") bh 1,000 197.000,00 197.000,00
3 Bend 90 CI All Flange Dia. 63 mm (2") bh 2,000 152.000,00 304.000,00
4 Pipa GIP Dia. 63 mm (2") m¹ 1,500 135.901,00 203.851,50
5 Loose Flange Dia. 63 mm (2") bh 1,000 107.400,00 107.400,00
B Pipa Outlet -
1 Wall Pipe GIP All Flange L = 60 cm Dia. 63 mm (2") unit 1,000 368.421,00 368.421,00
2 Flange Socket Dia. 2" bh 1,000 197.000,00 197.000,00
3 Bend 90 CI All Flange Dia. 2" bh 2,000 152.000,00 304.000,00
4 Pipa GIP Dia. 2" m¹ 1,500 135.901,00 203.851,50
5 Loose Flange Dia. 2" bh 1,000 107.400,00 107.400,00
6 Gate Valve Dia. 2" bh 1,000 588.000,00 588.000,00
C Pipa Penguras Dan Over flow -
1 Wall Pipe GIP All Flange L = 60 cm Dia. 63 mm (2") unit 2,000 368.421,00 736.842,00
2 Pipa PVC Dia. 63 mm (2") m¹ 2,000 48.759,00 97.518,00
3 Flange Socket Dia. 63 mm (2") bh 4,000 197.000,00 788.000,00
4 Bend 90 CI All Flange Dia. 63 mm (2") bh 3,000 152.000,00 456.000,00
5 Pipa GIP Dia. 63 mm (2") m¹ 2,000 135.901,00 271.802,00
6 Loose Flange Dia. 63 mm (2") bh 2,000 107.400,00 214.800,00
D Pipa Vent -
1 Pekerjaan Pipa Vent Dia. 2" (Sesuai Gambar) unit 2,000 721.804,00 1.443.608,00
Jumlah 6.957.915,00
IX PEKERJAAN CAT -
1 Pengecatan Dinding Tembok Baru m² 45,352 42.948,00 1.947.777,70
Jumlah 1.947.777,70
X PEKERJAAN PAGAR BRC -
1 Galian Tanah Biasa m³ 1,785 119.924,00 214.064,34
2 Urugan Pasir m³ 1,971 268.769,00 529.743,70
3 Pasangan Batu Kali 1 : 4 m³ 1,428 1.117.843,00 1.595.720,88
4 Beton Tumbuk 1 : 3 : 5 (t = 10 cm) m³ 1,648 1.078.544,00 1.777.440,51
5 Pondasi Tiang Pagar, Adukan Beton 1 : 1,5 : 2,5 m³ 0,160 5.535.109,00 885.617,44
6 Pasangan Grevel 20 cm m¹ 25,400 252.353,00 6.409.766,20
7 Plesteran 1 : 4, t = 15 mm + Acian m² 16,480 96.456,00 1.589.594,88
8 Acian m² 16,480 58.187,00 958.921,76
Pengadaan & Pemasangan Pagar BRC t=120 cm + tiang +
9 m¹ 25,400 409.350,00 10.397.490,00
Pintu
10 Pengecatan Pagar dengan cat minyak m² 48,260 53.359,00 2.575.105,34
Jumlah 26.933.465,05
XI PENGADAAN DAN PEMASANGAN PIPA JARINGAN -
1 Pengadaan Pipa -
Pemasangan Pipa PVC - AW 48.759,00 -
Pipa PVC Dia. 63 mm ( 2 " ) m¹ 600,000 48.759,00 29.255.400,00
Pipa PVC Dia. 32 mm ( 1 " ) m¹ 1.200,000 30.233,00 36.279.600,00
2 Galian Pemasangan Pipa PVC -
Galian Tanah Biasa -
Pipa PVC Dia. 63 mm ( 2 " ) m³ 24,000 119.924,00 2.878.176,00
Pipa PVC Dia. 32 mm ( 1 " ) m³ 72,000 119.924,00 8.634.528,00
Galian Tanah Keras -
Pipa PVC Dia. 63 mm ( 11/2 " ) m³ 48,000 159.621,00 7.661.808,00
Pipa PVC Dia. 32 mm ( 1 " ) m³ 72,000 159.621,00 11.492.712,00
3 Perbaikan Bekas Galian Pipa, Rabat Beton 1:3:5 -
Perbaikan Bekas Galian Pipa, Rabat Beton 1:3:5 m³ 6,355 1.016.351,00 6.458.910,61
Jumlah 102.661.134,61
PEKERJAAN CROSSING JALAN ASPAL PIPA 2" ( 63
XII -
mm) - L= 6M
Pekerjaan Crossing Jalan Aspal Pipa 63 mm (2") - L = 6 m unit 4,000 1.561.591,00 6.246.364,00
Jumlah 6.246.364,00
XIII PEKERJAAN SAMBUNGAN RUMAH -
Pengadaan Dan Pemasangan Sambungan Rumah unit 175,000 833.001,00 145.775.175,00
Jumlah 145.775.175,00
168
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
SUMUR DALAM 150 M + RESERVOIR 20 M³ + JARINGAN PIPA
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 3.814.398,00
II PEKERJAAN KONSTRUKSI SUMUR 193.610.230,20
III PENGADAAAN DAN PEMASANGAN POMPA 56.745.000,00
IV PEKERJAAN INSTALASI LISTRIK 23.804.000,00
V PEKERJAAN TANAH 3.261.337,87
VI PEKEERJAAN BETON 99.290.867,73
VII PEKERJAAN BESI 1.387.761,00
VIII PEKERJAAN PIPA DAN ASESORI 6.957.915,00
IX PEKERJAAN CAT 1.947.777,70
X PEKERJAAN PAGAR BRC 26.933.465,05
XI PENGADAAN DAN PEMASANGAN PIPA JARINGAN 102.661.134,61
XII PEKERJAAN CROSSING JALAN ASPAL PIPA 2" ( 63 mm) - L= 6M 6.246.364,00
XIII PEKERJAAN SAMBUNGAN RUMAH 145.775.175,00
JUMLAH (Rp) 672.435.426,15
PPN 10% 67.243.542,61
JUMLAH TOTAL (Rp) 739.678.968,76
JUMLAH DIBULATKAN (Rp) 739.678.000,00
169
ANALISIS STANDAR BELANJA (ASB)
SUMUR DANGKAL 100M + MENARA+JARINGAN PIPA+SR
1 KELOMPOK : KONSTRUKSI
2 SUB KELOMPOK : Program Lingkungan Sehat Perumahan
3 SUB- SUB KELOMPOK : Penyediaan sarana air bersih dan sanitasi dasar terutama bagi masyarakat miskin
170
C PEKERJAAN BESI -
Rangka besi IWF, pelat simpul angkur baut -
1 Besi WF 200.100.5,5.8 kg 748,000 39.711,00 29.703.828,00
2 Besi WF 148.100.6.9 kg 512,300 39.711,00 20.343.945,30
3 Besi UNP 100.50.5 kg 265,460 36.405,00 9.664.071,30
4 Railing Pipa GI DN. 1,5" (37,5 mm) m' 24,000 43.300,00 1.039.200,00
5 Base Plate 400 mm x 400 mm x 16 mm kg 40,530 36.405,00 1.475.494,65
6 Simpul Besi Plate 8 mm m¹ 35,000 18.902,00 661.570,00
7 Pasang baut Ø 16 bh 16,000 26.686,00 426.976,00
8 Pembuatan Anak Tangga Dengan Besi DN. 1,5" (37,5 mm) m' 9,000 43.300,00 389.700,00
9 - Plat bordes 3 mm kg 120,000 36.405,00 4.368.600,00
10 Pengecatan Besi yang Tampak m² 110,000 51.680,00 5.684.800,00
Jumlah 85.253.443,57
VI PEKERJAAN DINDING DAN LANTAI -
1 Pekerjaan Plesteran m² 9,000 95.270,00 857.430,00
2 Pekerjaan Acian m² 9,000 58.187,00 523.683,00
Jumlah 1.381.113,00
VII PEKERJAAN PIPA, TANGKI DAN ACCESSORIES -
1 Tangki PE Kapasitas 5.000 Ltr bh 1,000 7.500.000,00 7.500.000,00
- Pipa Inlet : -
- Pipa PVC Dia.1 1/2" m¹ 8,000 37.586,00 300.688,00
- Knee PVC Dia.1 1/2" bh 2,000 66.790,00 133.580,00
- Tee PVC Dia.1 1/2" bh 1,000 24.000,00 24.000,00
- Socket Drat Luar Dia.1 1/2" bh 2,000 13.000,00 26.000,00
- Stop Valve Dia.1 1/2" bh 1,000 387.836,00 387.836,00
- Pipa Outlet : -
- Pipa PVC Dia. 11/2" m¹ 6,000 37.586,00 225.516,00
- Bend All Socket PVC 90° Dia. 1 1/2" bh 2,000 66.790,00 133.580,00
- Tee All Socket dia. 11/2" x 1" bh 2,000 24.000,00 48.000,00
- Socket Drat Luar PVC Dia. 11/2" bh 2,000 13.000,00 26.000,00
- Stop Valve Dia. 11/2" bh 1,000 387.836,00 387.836,00
2 Pipa Penguras Dan Over flow -
- Pipa PVC Dia. 11/2" m¹ 6,000 37.586,00 225.516,00
- Bend All Socket PVC 90° Dia. 1 1/2" bh 2,000 66.790,00 133.580,00
- Tee All Socket dia. 11/2" x 1" bh 2,000 24.000,00 48.000,00
- Socket Drat Luar PVC Dia. 11/2" bh 2,000 13.000,00 26.000,00
- Stop Valve Dia. 11/2" bh 1,000 387.836,00 387.836,00
3 Pemasangan Tangki dan Accessories -
- Tangki PE Kapasitas 5.000 Ltr bh 0,200 7.500.000,00 1.500.000,00
Jumlah 11.513.968,00
VIII PENGADAAN DAN PEMASANGAN PIPA JARINGAN -
1 Pengadaan Pipa -
Pemasangan Pipa PVC - AW -
Pipa PVC Dia. 63 mm ( 2 " ) m¹ 900,000 48.759,00 43.883.100,00
Pipa PVC Dia. 32 mm ( 1 " ) m¹ 1.200,000 30.233,00 36.279.600,00
2 Galian Pemasangan Pipa PVC -
Galian Tanah Biasa -
Pipa PVC Dia. 63 mm ( 11/2 " ) m³ 54,000 119.924,00 6.475.896,00
Pipa PVC Dia. 32 mm ( 1 " ) m³ 48,000 119.924,00 5.756.352,00
Galian Tanah Keras -
Pipa PVC Dia. 63 mm ( 11/2 " ) m³ 54,000 159.621,00 8.619.534,00
Pipa PVC Dia. 32 mm ( 1 " ) m³ 48,000 159.621,00 7.661.808,00
3 Perbaikan Bekas Galian Pipa, Rabat Beton 1:3:5 -
Perbaikan Bekas Galian Pipa, Rabat Beton 1:3:5 m³ 4,000 1.016.351,00 4.065.404,00
Jumlah 112.741.694,00
IX PEKERJAAN SAMBUNGAN RUMAH -
Pengadaan Dan Pemasangan Sambungan Rumah unit 200,000 833.001,00 166.600.200,00
Jumlah 166.600.200,00
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
SUMUR DANGKAL 100 M + MENARA 6 M KAP. 5000 Ltr + JARINGAN PIPA + SR
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 3.814.398,00
II PEKERJAAN KONSTRUKSI SUMUR DANGKAL 100 m 119.514.476,00
III PENGADAAAN DAN PEMASANGAN POMPA 34.250.000,00
IV PEKERJAAN INSTALASI LISTRIK 14.850.000,00
V PEMBUATAN MENARA AIR TINGGI 6 m, KAPASITAS 5.000 LITER 85.253.443,57
VI PEKERJAAN DINDING DAN LANTAI 1.381.113,00
VII PEKERJAAN PIPA, TANGKI DAN ACCESSORIES 11.513.968,00
VIII PENGADAAN DAN PEMASANGAN PIPA JARINGAN 112.741.694,00
IX PEKERJAAN SAMBUNGAN RUMAH 166.600.200,00
JUMLAH (Rp) 549.919.292,57
PPN 10% 54.991.929,26
JUMLAH TOTAL (Rp) 604.911.221,83
JUMLAH DIBULATKAN (Rp) 604.911.000,00
171
ANALISIS STANDAR BELANJA (ASB)
SUMUR DANGKAL 100M + RESERVOIR 20 M3+JARINGAN PIPA+SR
1 KELOMPOK : KONSTRUKSI
2 SUB KELOMPOK : Program Lingkungan Sehat Perumahan
3 SUB- SUB KELOMPOK : Penyediaan sarana air bersih dan sanitasi dasar terutama bagi masyarakat miskin
172
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
SUMUR DANGKAL 100 M + RESERVOIR 20 M3 + JARINGAN PIPA + SR
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 3.814.398,00
II PEKERJAAN KONSTRUKSI SUMUR DANGKAL 100 m 119.514.476,00
III PENGADAAAN DAN PEMASANGAN POMPA 34.250.000,00
IV PEKERJAAN INSTALASI LISTRIK 14.850.000,00
V PEMBUATAN RESERVOIR KAPASITAS 20 M³ 153.858.000,00
VI PENGADAAN DAN PEMASANGAN PIPA JARINGAN 112.741.694,00
VII PEKERJAAN SAMBUNGAN RUMAH 166.600.200,00
JUMLAH (Rp) 605.628.768,00
PPN 10% 60.562.876,80
JUMLAH TOTAL (Rp) 666.191.644,80
JUMLAH DIBULATKAN (Rp) 666.191.000,00
173
ANALISIS STANDAR BELANJA (ASB)
PEMBUATAN BANK SAMPAH TEMATIK
1 KELOMPOK : KONSTRUKSI
2 SUB KELOMPOK : PEMBUATAN BANK SAMPAH TEMATIK
3 SUB- SUB KELOMPOK : BANK SAMPAH TEMATIK
4 ZONA WILAYAH SSH : SELURUH WILAYAH KABUPATEN BNAN
5 AKTIVITAS : PEMBUATAN BANK SAMPAH TEMATIK
6 DESKRIPSI AKTIVITAS : PEMBUATAN BANK SAMPAH TEMATIK
7 KOMPONEN/RINCIAN KOMPONEN : unit
8 SATUAN AKTIVITAS :
NO. URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH
I PEKERJAAN PERSIAPAN
Pengukuran dan Pemasangan Bouwplank m¹ 20,00 81.786,00 1.635.720,00
Jumlah 1.635.720,00
II PEKERJAAN KONSTRUKSI -
Galian tanah biasa sedalam 1 meter m³ 0,43 119.924,00 51.807,17
Urugan pasir padat m³ 0,04 215.949,00 7.774,16
Pekerjaan Beton K 225 - f'c 19,3 Mpa m³ 0,19 1.320.118,00 253.462,66
Pekerjaan Bekisting Sloof m² 0,60 238.798,00 143.278,80
Pemasangan Baja Profil kg 9,29 39.711,00 368.721,40
Jumlah 825.044,19
Pek. Lantai -
Pekerjaan Beton K 225 - f'c 19,3 Mpa m³ 2,50 1.320.118,00 3.300.295,00
Acian m² 25,00 58.187,00 1.454.675,00
Jumlah 4.754.970,00
Pek. Dinding Bata T=80cm -
Pasangan dinding bata merah 1 PC : 3 PP tebal 1 bata m² 8,06 356.167,00 2.870.706,02
Pasangan dinding bata merah 1 PC : 5 PP tebal 1/2 bata m² 15,20 166.609,00 2.532.456,80
Plesteran 1 Pc : 5 Ps tebal 20 mm m² 36,00 127.540,00 4.591.440,00
Acian m² 36,00 58.187,00 2.094.732,00
Jumlah 12.089.334,82
Pek. Pintu Besi & Accessories -
Pemasangan Baja Profil kg 18,21 39.711,00 723.216,73
Pemasangan Baja Profil kg 1,88 39.711,00 74.618,56
Ram Kawat Galvanis 25x25mm M2 0,91 108.000,00 98.280,00
Plat Besi M 0,45 155.000,00 69.750,00
Engsel Pintu (Besar) (Besar) Psg 1,00 46.000,00 46.000,00
Grendel Pintu Biasa (Selot) - (Selot) Buah 1,00 15.000,00 15.000,00
Handle Pintu Set 2,00 255.000,00 510.000,00
Jumlah 1.536.865,29
Pek. Rangka Hollow & Perkuatan -
Pemasangan Baja Profil kg 160,30 39.711,00 6.365.554,17
Pemasangan Baja Profil kg 243,39 39.711,00 9.665.435,02
Ram Kawat Galvanis 25x25mm M2 37,29 108.000,00 4.027.320,00
Jumlah 20.058.309,19
Pek. Pengecatan -
Pengecatan tembok baru dg cat KW 2 m² 36,00 33.978,00 1.223.208,00
Pengecatan permukaan baja 1 m² dgn meni besi m² 35,78 51.350,00 1.837.200,30
Jumlah 3.060.408,30
Pek. Penutup Atap -
Pekerjaan Dinding Zincallum rangka baja C m² 41,55 344.064,00 14.297.235,46
Pasang talang 1/2 lingkaran D-15 cm, seng BJLS 30 lebar 45
m¹ 5,26 123.630,00 650.293,80
cm
Jumlah 14.947.529,26
III PEKERJAAN MEKANIKAL & ELEKTRIKAL -
Pek. Plumbing & Sanitasi -
Memasang pipa PVC tipe D dia 1 1/2 " m¹ 10,00 30.723,00 307.230,00
Memasang pipa PVC tipe AW dia 1" m¹ 2,00 30.233,00 60.466,00
Memasang pipa PVC tipe AW dia 3" m¹ 15,00 91.728,00 1.375.920,00
Gate Valve, 1" Buah 1,00 162.000,00 162.000,00
Memasang 1 floor drain sederhana bh 1,00 126.164,00 126.164,00
Memasang 1 buah kran dia 3/4" atau 1/2" sederhana bh 4,00 135.986,00 543.944,00
Tanki Air 1050 Liter - Buah 1,00 1.590.000,00 1.590.000,00
Saringan Air - Buah 1,00 12.000,00 12.000,00
Pek. Elektrikal -
Pekerjaan Pemasangan MCB di Tiang Unit 1,00 118.983,00 118.983,00
Pasang 1 buah lampu TL 1x18 Balk bh 4,00 169.130,00 676.520,00
Pasang 1 buah lampu pijar bh 3,00 40.204,00 120.612,00
Pasang 1 buah lampu down light PLC 18 watt bh 4,00 165.140,00 660.560,00
Pasang 1 buah saklar tunggal bh 1,00 104.678,00 104.678,00
Jumlah 5.859.077,00
174
IV PEMBUATAN MEDIA BUDIDAYA LALAT BSF & -
Pembuatan Kandang Kawin Lalat BSF -
Pemasangan Baja Profil kg 5,31 39.711,00 210.746,28
Insectnet / Inseknet / Shadingnet (40-50 mesh), warna hijau
dengan ukuran lebar 0.8 meter dengan ukuran lubangnya 40-50 Roll 1,00 729.500,00 729.500,00
mesh
-
Pembuatan Kandang Gelap Pra Pupa -
-
Pemasangan Baja Profil KG 26,72 39.711,00 1.060.982,61
terpal M 6,00 35.000,00 210.000,00
Container Plastik Kecil Buah 1,00 105.000,00 105.000,00
Kolam terpal ikan hias ukuran 1x2x0,5 m, kolam ikan bahan
Unit 3,00 2.200.000,00 6.600.000,00
terpal dengan rangka baja ringan ukuran 1x2x0,5 m
-
Jumlah 8.916.228,89
REKAPITULASI
ANALISIS STANDAR BELANJA (ASB)
BANK SAMPAH TEMATIK
No PEKERJAAN JUMLAH (Rp)
I PEKERJAAN PERSIAPAN 1.635.720,00
II PEKERJAAN KONSTRUKSI 57.272.461,04
III PEKERJAAN MEKANIKAL & ELEKTRIKAL 5.859.077,00
IV PEMBUATAN MEDIA BUDIDAYA LALAT BSF & LELE 8.916.228,89
JUMLAH (Rp) 73.683.486,93
PPN 10% 7.368.348,69
JUMLAH TOTAL (Rp) 81.051.835,62
JUMLAH DIBULATKAN (Rp) 81.051.000,00
175
ANALISIS STANDAR BELANJA (ASB)
INSTALASI PENGOLAHAN LUMPUR TINJA (IPLT)
1 KELOMPOK : KONSTRUKSI
2 SUB KELOMPOK : INSTALASI PENGOLAHAN LUMPUR TINJA (IPLT)
3 SUB- SUB KELOMPOK : BANK SAMPAH TEMATIK
4 ZONA WILAYAH SSH : INSTALASI PENGOLAHAN LUMPUR TINJA (IPLT)
5 AKTIVITAS : INSTALASI PENGOLAHAN LUMPUR TINJA (IPLT)
6 DESKRIPSI AKTIVITAS : INSTALASI PENGOLAHAN LUMPUR TINJA (IPLT)
7 KOMPONEN/RINCIAN KOMPONEN : m²
8 SATUAN AKTIVITAS :
NO. URAIAN PEKERJAAN SAT. VOLUME HARGA SATUAN JUMLAH
I PEKERJAAN PERSIAPAN
Pembersihan dan perataan lahan m2 368,00 25.719,00 9.464.592,00
Pembuatan Pagar sementara seng gelombang m2 110,00 423.822,00 46.620.420,00
Pembuatan direksi kit lantai plesteran m2 12,00 1.583.084,00 18.997.008,00
Mobilisasi & demolisasi untuk pekerjaan Ls 1,00 20.000.000,00 20.000.000,00
Pekerjaan Soil test LS 1,00 16.500.000,00 16.500.000,00
Jumlah 111.582.020,00
II BANGUNAN SUMPWELL & GREASE TRAP
A PEKERJAAN PENDAHULUAN
1 Pengukuran dan pasang patok bouwplank m1 33,85 81.786,00 2.768.456,10
Jumlah 2.768.456,10
B PEKERJAAN TANAH
1 Galian tanah pondasi dan saluran m3 53,89 119.924,00 6.462.704,36
2 Urugan tanah kembali Urugan m3 15,97 86.899,00 1.387.994,28
3 Pembuangan tanah M3 37,92 52.558,00 1.992.867,97
4 Urugan pasir bawah lantai t = 5 cm M3 0,51 268.769,00 137.475,34
Jumlah 9.981.041,95
C PEKERJAAN BETON -
1 Beton lantai kerja campuran 7,4 Mpa, K-100 M3 1,19 1.078.544,00 1.281.310,27
2 Beton Plat lantai t= 15 cm (K300)
a. Beton K-300 M3 1,78 1.374.406,00 2.449.191,49
b. Besi Tulangan U-40 Kg 500,26 20.011,00 10.010.622,82
c. Bekisting M2 2,81 491.697,00 1.380.685,18
3 Beton Plat Dinding t = 15 cm (K300)
a. Beton K-300 M3 2,04 1.374.406,00 2.806.365,25
b. Besi Tulangan U-40 Kg 245,11 20.011,00 4.904.829,51
c. Bekisting M2 68,39 467.087,00 31.942.912,21
4 Beton Balok Koagulan, (15/20) (K300)
a. Beton K-300 M3 0,54 1.374.406,00 742.179,24
b. Besi Tulangan U-40 Kg 500,26 20.011,00 10.010.622,82
c. Bekisting M2 9,90 439.027,00 4.346.367,30
4 Beton Kolom (20/20) Koagulan (K300)
a. Beton K-300 M3 0,48 1.374.406,00 665.212,50
b. Besi Tulangan U-40 Kg 87,12 20.011,00 1.743.358,32
c. Bekisting M2 5,40 428.677,00 2.314.855,80
5 Beton Saluran Pembawa 40/50 (K300)
a. Beton K-300 M3 4,62 1.374.406,00 6.349.755,72
b. Besi Tulangan U-40 Kg 254,61 20.011,00 5.095.067,41
c. Bekisting M2 36,96 491.697,00 18.173.121,12
Jumlah 104.216.456,96
D PEKERJAAN PASANGAN & PLESTERAN
1 Plesteran 1 : 4 M2 23,40 96.456,00 2.257.070,40
2 Acian dinding M2 25,74 58.187,00 1.497.733,38
3 Acian Lantai M2 10,80 58.187,00 628.419,60
4 Pas. Bar screen ls 1,00 7.500.000,00 7.500.000,00
Jumlah 11.883.223,38
E PEKERJAAN PENGECATAN
1 Cat dinding luar WTP m2 25,74 42.948,00 1.105.481,52
Jumlah 1.105.481,52
F PEKERJAAN BESI BAJA
1 Grill Saluran Sedimentasi Unit 1,00 553.932,00 553.932,00
2 Bar screen Unit 1,00 7.500.000,00 7.500.000,00
Jumlah 8.053.932,00
III BANGUNAN THICKENER 1
A PEKERJAAN PERSIAPAN
1 Pengukuran dan pasang patok bouwplank m1 18,84 81.786,00 1.540.848,24
Jumlah 1.540.848,24
B PEKERJAAN TANAH
1 Galian tanah pondasi dan saluran m3 31,79 119.924,00 3.812.683,77
2 Urugan tanah kembali m3 11,45 86.899,00 994.585,12
3 Pembuangan tanah M3 20,35 52.558,00 1.069.408,14
4 Urugan pasir bawah lantai t = 5 cm M3 0,45 268.769,00 121.526,59
Jumlah 5.998.203,62
176
C PEKERJAAN BETON
1 Beton lantai kerja campuran 1 : 3 : 5 M3 0,45 1.078.544,00 487.674,46
2 Beton Plat lantai t= 15 cm (K300)
a. Beton K-300 M3 1,49 1.374.406,00 2.050.789,68
b. Besi Tulangan U-40 Kg 124,03 20.011,00 2.482.008,16
c. Bekisting M2 2,64 491.697,00 1.296.900,01
3 Beton Plat Dinding t = 15 cm (K300)
a. Beton K-300 M3 9,35 1.374.406,00 12.854.235,20
b. Besi Tulangan U-40 Kg 689,69 20.011,00 13.801.481,04
c. Bekisting M2 60,29 467.087,00 28.159.741,06
4 Bak konyrol 50/50, (K300)
a. Beton K-300 M3 0,45 1.374.406,00 618.482,70
b. Besi Tulangan U-40 Kg 12,40 20.011,00 248.136,40
c. Bekisting M2 0,44 491.697,00 216.346,68
5 Beton Saluran Pembawa 40/50 (K300)
a. Beton K-300 M3 0,91 1.374.406,00 1.251.534,10
b. Besi Tulangan U-40 Kg 22,58 20.011,00 451.906,01
c. Bekisting M2 1,51 491.697,00 741.085,72
Jumlah 64.660.321,21
D PEKERJAAN PASANGAN & PLESTERAN
1 Plesteran 1 : 4 + Acian M2 2,25 96.456,00 217.026,00
2 Acian dinding M2 2,48 58.187,00 144.012,83
3 Acian Lantai saluaran M2 9,11 58.187,00 529.850,82
Jumlah 890.889,65
E PEKERJAAN PENGECATAN
1 Cat dinding luar WTP m2 2,48 42.948,00 106.296,30
Jumlah 106.296,30
F PEKERJAAN BESI BAJA
1 Grill Saluran Sedimentasi Unit 1,00 553.932,00 553.932,00
2 Pekerjaan tangga besi m1 10,40 296.293,00 3.081.447,20
Jumlah 3.635.379,20
PENGADAAN & PEMASANGAN PIPA &
G
AKSESSORIES
I PENGADAAN PIPA & AKSESSORIES
1 Pipa Outlet PVC dia.200 mm ( menuju sdb) m1 6,00 592.602,00 3.555.612,00
2 Pipa Outlet PVCdia.200 mm ( menujuI PAL) m1 28,00 592.602,00 16.592.856,00
3 Pipa Intlet dia.200 mm ( dari greastrap) m1 6,00 592.602,00 3.555.612,00
4 Bend 90 ' PVC diameter 200 mm Unit 19,00 592.602,00 11.259.438,00
6 Tee PVC diameter 200 mm Unit 1,00 188.721,00 188.721,00
7 Gate Valve diameter 200 mm Unit 2,00 14.000.000,00 28.000.000,00
8 Wall Pipe 200 mm Unit 3,00 6.852.600,00 20.557.800,00
177
D PEKERJAAN BETON
1 Beton lantai kerja campuran K-100 M3 0,45 1.078.544,00 487.674,46
2 Beton Plat lantai t= 15 cm (K300)
a. Beton K-300 M3 2,33 1.374.406,00 3.204.358,87
b. Besi Tulangan U-40 Kg 124,80 20.011,00 2.497.372,80
c. Bekisting M2 3,30 491.697,00 1.621.125,01
3 Beton Plat Dinding t = 15 cm (K300) -
a. Beton K-300 M3 13,56 1.374.406,00 18.643.542,51
b. Besi Tulangan U-40 Kg 15,06 20.011,00 301.304,19
c. Bekisting M2 90,43 467.087,00 42.239.611,58
4 Bak kontrol 50/50, (K300)
a. Beton K-300 M3 0,45 1.374.406,00 618.482,70
b. Besi Tulangan U-40 Kg 12,40 20.011,00 248.136,40
c. Bekisting M2 0,44 491.697,00 216.346,68
5 Beton Saluran Pembawa 40/50 (K300)
a. Beton K-300 M3 0,96 1.374.406,00 1.314.110,81
b. Besi Tulangan U-40 Kg 23,71 20.011,00 474.501,31
c. Bekisting M2 1,58 491.697,00 778.140,00
Jumlah 72.644.707,32
E PEKERJAAN PASANGAN & PLESTERAN
1 Plesteran 1 : 4 + Acian M2 2,25 96.456,00 217.026,00
2 Acian dinding M2 2,48 58.187,00 144.012,83
3 Acian Lantai saluaran M2 9,11 58.187,00 529.850,82
Jumlah 890.889,65
F PEKERJAAN PENGECATAN
1 Cat dinding luar WTP m2 2,48 42.948,00 106.296,30
Jumlah 106.296,30
G PEKERJAAN BESI BAJA
1 Grill Saluran Sedimentasi Unit 1,00 553.932,00 553.932,00
2 Pekerjaan tangga besi m1 10,40 296.293,00 3.081.447,20
Jumlah 3.635.379,20
PENGADAAN & PEMASANGAN PIPA &
H
AKSESSORIES
PENGADAAN PIPA & AKSESSORIES
1 Pipa Outlet PVC dia.200 mm ( menuju sdb) m1 6,00 592.602,00 3.555.612,00
2 Pipa Outlet PVCdia.200 mm ( menuju IPAL) m1 23,00 592.602,00 13.629.846,00
3 Pipa Intlet dia.200 mm ( dari greastrap) m1 48,00 592.602,00 28.444.896,00
4 Bend 90 ' PVC diameter 200 mm Unit 19,00 592.602,00 11.259.438,00
5 Tee y PVC diameter 200 mm Unit 2,00 188.721,00 377.442,00
6 Tee PVC diameter 200 mm Unit 1,00 188.721,00 188.721,00
7 Gate Valve diameter 200 mm Unit 2,00 14.000.000,00 28.000.000,00
8 Wall Pipe Unit 3,00 6.852.600,00 20.557.800,00
Jumlah 106.013.755,00
I PEMASANGAN PIPA & AKSESSORIES
1 Pipa Outlet PVC dia.200 mm ( menuju sdb) m1 6,00 592.602,00 3.555.612,00
2 Pipa Outlet PVCdia.200 mm ( menuju iplt) m1 30,00 592.602,00 17.778.060,00
3 Pipa Intlet dia.200 mm ( dari greastrap) m1 58,00 592.602,00 34.370.916,00
4 Tee y PVC diameter 200 mm Unit 2,00 188.721,00 377.442,00
5 Tee PVC diameter 200 mm Unit 1,00 188.721,00 188.721,00
6 Gate Valve diameter 200 mm Unit 4,00 14.000.000,00 56.000.000,00
7 Wall Pipe Unit 5,00 6.852.600,00 34.263.000,00
Jumlah 146.533.751,00
J PENGADAAN & PEMASANGAN Scrapper
1 Scrapper Plus motor ls 1,00 150.000.000,00 150.000.000,00
Jumlah 150.000.000,00
V BANGUNAN SLUDGE DRYING BED (SDB) 1-2
A PEKERJAAN PERSIAPAN
Pemasangan bowplank rencana bangunan M' 33,00 81.786,00 2.698.938,00
Jumlah 2.698.938,00
B PEKERJAAN TANAH
1 Galian tanah bangunan M3 66,83 119.924,00 8.013.921,30
2 Urugan tanah kembali M3 60,14 86.899,00 5.226.323,11
3 Urugan Pasir bawah lantai t = 20 cm M3 1,66 268.769,00 445.597,50
Jumlah 13.685.841,91
178
C PEKERJAAN BETON
1 Pas. Pondasi Batukali
a. Pondasi Batu Belah 1:4 M3 9,61 1.182.760,00 11.365.436,53
b. Aanstamping M3 3,32 650.982,00 2.161.051,93
c. Urugan Pasir = 5 cm M3 0,88 268.769,00 235.925,43
d. Sloof 20/30, K-300
- Beton K-300 M3 1,68 1.374.406,00 2.303.229,57
- Besi Tulangan U-40 Kg 304,30 20.011,00 6.089.427,34
- Bekisting M2 23,41 238.798,00 5.589.783,58
2 Beton K-300 Lantai SDB t = 20 cm
a. Beton K-300 M3 8,72 1.374.406,00 11.977.948,29
b. Besi Tulangan U-40 Kg 3.846,77 20.011,00 76.977.781,17
c. Bekisting M2 25,30 491.697,00 12.439.934,10
3 Beton K-300 Dinding SDB t= 20 cm
a. Beton K-300 M3 9,14 1.374.406,00 12.557.397,86
b. Besi Tulangan U-40 Kg 2.356,22 20.011,00 47.150.398,46
c. Bekisting M2 97,64 467.087,00 45.604.506,33
4 Beton K-300 Saluran Pembawa 30/30
a. Beton K-300 M3 1,64 1.374.406,00 2.258.698,82
b. Besi Tulangan U-40 Kg 227,88 20.011,00 4.560.202,73
c. Bekisting M2 2,99 491.697,00 1.469.190,64
5 Beton lantai kerja campuran K-100 M3 2,08 1.078.544,00 2.237.978,80
Jumlah 244.978.891,59
D PEKERJAAN PASANGAN & ACIAN BETON
1 Acian Dak Lantai M2 41,50 58.187,00 2.414.760,50
2 Acian Saluran pembawa M2 7,47 58.187,00 434.656,89
3 Acian Dinding M2 66,50 58.187,00 3.869.435,50
4 Pas. Saluran bata sekitar sdb Uk.60x60 cm 1:4 M' 33,00 169.068,00 5.579.244,00
Jumlah 12.298.096,89
E PEKERJAAN PENGECATAN
1 Cat dinding M2 66,50 42.948,00 2.856.042,00
2 Cat beton saluran M2 7,20 42.948,00 309.225,60
Jumlah 3.165.267,60
F PEKERJAAN ATAP BAJA SDB 1 - 2
1 Rangka CNP 100 ,P=6m, Uk.100(95) X 50(43) X 20(10) Mm kg 377,38 36.405,00 13.738.518,90
2 Besi Tiang WF 150.75.5.7 kg 352,80 39.711,00 14.010.040,80
3 Gording Kanal C 150.50.20.3,2 kg 243,61 39.711,00 9.673.980,83
4 Pemasangan Rangka Kuda-kuda Baja IWF / kg kg 44,06 39.711,00 1.749.825,50
5 Besi Beton Regel dia. 13 ulir kg 44,93 20.011,00 899.054,21
6 Plat tumpuan dan sambungan T= 10 MM kg 94,48 14.100,00 1.332.145,44
7 Talang datar tengah PVC 4" m1 15,00 120.248,00 1.803.720,00
8 Talang tegak pvc 4 " m1 16,80 120.248,00 2.020.166,40
9 Ikatan angin besi Ø 16 mm kg 52,46 20.011,00 1.049.697,02
10 Track stank Ø 12 mm kg 34,53 20.011,00 690.939,81
11 Baut Mur bh 144,00 28.411,00 4.091.184,00
12 Baut angkur dia 19 mm-50 bh 36,00 28.411,00 1.022.796,00
13 Penutup atap zincalum 0,4 mm m2 91,30 178.170,00 16.266.921,00
14 Wuwungan zincalum m1 12,00 122.555,00 1.470.660,00
Jumlah 69.819.649,90
PENGADAAN & PEMASANGAN BAJA & FASILITAS
G
TREATMENT
1 Pekerjaan Gutter Sedimentasi SS 304 Unit 7,00 3.441.147,00 24.088.029,00
2 Pengadaan Plat Pengarah Aliran SS 304 Kg 102,02 14.100,00 1.438.538,40
3 Pengurugan Media Treatment :
a. Find sand dia. 0.1 t = 15 cm m3 5,60 268.769,00 1.505.778,32
b. Coarse Sand dia. 0.3 T= 10 cm m3 3,74 268.769,00 1.003.852,22
c. Find Gravel dia. 2 cm T = 10 cm M3 3,74 215.949,00 806.569,52
d. Coarse Gravel dia. 3 cm T = 15 cm M3 5,60 215.949,00 1.209.854,27
e. Gravel dia. 5 cm T = 30 cm M3 11,21 215.949,00 2.419.708,55
4 Pipa berpori dia. 150 mm m1 8,30 275.994,00 2.290.750,20
Jumlah 34.763.080,47
H PEKERJAAN BESI DAN LAMPU PENERANGAN
1 Pintu Air Unit 3,00 2.750.000,00 8.250.000,00
2 Penerangan :
- Lampu TL 1 x 20 Watt + Instalasi Kabel Ttk 4,00 310.833,00 1.243.332,00
- Stop Kontak + Instalasi kabel Ttk 2,00 514.509,00 1.029.018,00
-Instalasi lampu Ttk 4,00 449.606,00 1.798.424,00
Jumlah 12.320.774,00
VI BANGUNAN SLUDGE DRYING BED (SDB) 3
A PEKERJAAN PERSIAPAN
1 Pemasangan bowplank rencana bangunan M' 29,00 81.786,00 2.371.794,00
Jumlah 2.371.794,00
B PEKERJAAN TANAH
1 Galian tanah bangunan m3 53,89 119.924,00 6.462.704,36
2 Urugan tanah kembali m3 15,97 86.899,00 1.387.994,28
3 Urugan Pasir bawah lantai t = 20 cm m3 8,66 268.769,00 2.326.555,85
Jumlah 10.177.254,48
179
C PEKERJAAN BETON
1 Pas. Pondasi Batukali
a. Pondasi Batu kali m3 9,74 1.182.760,00 11.523.527,19
b. Aanstamping m3 3,37 650.982,00 2.191.111,67
c. Urugan Pasir = 5 cm m3 0,89 268.769,00 239.207,10
d. Sloof 20/30, K-300
- Beton K-300 m3 1,70 1.374.406,00 2.335.266,98
- Besi Tulangan U-40 m3 308,54 20.011,00 6.174.129,90
- Bekisting m3 23,73 238.798,00 5.667.536,21
2 Beton K-300 Lantai SDB t = 20 cm
a. Beton K-300 m3 9,95 1.374.406,00 13.674.954,87
b. Besi Tulangan U-40 Kg 1.485,31 20.011,00 29.722.582,03
c. Bekisting m3 9,92 491.697,00 4.879.699,37
3 Beton K-300 Dinding SDB t= 20 cm
a. Beton K-300 m3 8,31 1.374.406,00 11.416.860,78
b. Besi Tulangan U-40 Kg 1.047,16 20.011,00 20.954.622,71
c. Bekisting m2 85,07 467.087,00 39.733.970,08
4 Beton K-300 Saluran Pembawa 30/30
a. Beton K-300 m3 1,64 1.374.406,00 2.254.163,28
b. Besi Tulangan U-40 Kg 168,39 20.011,00 3.369.692,31
c. Bekisting m3 15,12 491.697,00 7.434.852,00
5 Beton lantai kerja campuran K-100 t = 5 cm m3 5,10 1.078.544,00 5.505.427,85
Jumlah 167.077.604,33
D PEKERJAAN PASANGAN & ACIAN BETON
1 Acian Dak Lantai m2 102,09 58.187,00 5.940.310,83
2 Acian Saluran pembawa m2 8,01 58.187,00 466.077,87
3 Acian Dinding m2 67,25 58.187,00 3.913.075,75
4 Pas. Saluran bata sekitar sdb Uk.60x60 cm m2 30,90 169.068,00 5.224.201,20
Jumlah 15.543.665,65
E PEKERJAAN ATAP BAJA SDB 3
1 Rangka C.75.45.2,3 kg 401,15 36.405,00 14.603.805,50
2 Besi Tiang WF 150.75.5.7 kg 509,60 39.711,00 20.236.725,60
3 Gording Kanal C 150.50.20.3,2 kg 580,18 39.711,00 23.039.655,06
4 Besi L 50.50.5 Regel kg 63,65 - -
5 Besi Beton Regel dia. 13 ulir kg 64,90 20.011,00 1.298.633,86
6 Plat tumpuan dan sambungan T= 10 MM kg 136,47 14.100,00 `
7 Talang datar tengah m1 27,50 120.248,00 3.306.820,00
8 Talang tegak pvc 4 " m1 25,20 120.248,00 3.030.249,60
9 Ikatan angin besi Ø 16 mm kg 55,30 20.011,00 1.106.608,30
10 Track stank Ø 12 mm kg 36,40 20.011,00 728.400,40
11 Baut Mur bh 208,00 28.411,00 5.909.488,00
12 Baut angkur dia 19 mm-50 bh 52,00 28.411,00 1.477.372,00
13 Penutup atap zincalum 0,4 mm m2 119,60 178.170,00 21.309.132,00
14 Wuwungan zincalum m1 19,00 122.555,00 2.328.545,00
Jumlah 98.375.435,31
PENGADAAN & PEMASANGAN BAJA & FASILITAS
F
TREATMENT
1 Pekerjaan Gutter Sedimentasi SS 304 Unit 7,00 3.441.147,00 24.088.029,00
2 Pengadaan Plat Pengarah Aliran SS 304 Kg 112,23 14.100,00 1.582.392,24
3 Pengurugan Media Treatment :
a. Find sand dia. 0.1 t = 15 cm m3 15,31 268.769,00 4.115.794,08
b. Coarse Sand dia. 0.3 T= 10 cm m3 10,21 268.769,00 2.743.862,72
c. Find Gravel dia. 2 cm T = 10 cm m3 10,21 268.769,00 2.743.862,72
d. Coarse Gravel dia. 3 cm T = 15 cm m3 15,31 268.769,00 4.115.794,08
e. Gravel dia. 5 cm T = 30 cm m3 30,63 268.769,00 8.231.588,16
4 Pipa berpori dia. 150 mm m1 8,90 275.994,00 2.456.346,60
Jumlah 50.077.669,61
G PEKERJAAN BESI DAN LAMPU PENERANGAN
1 Pintu Air Unit 1,00 2.750.000,00 2.750.000,00
2 Penerangan : -
- Lampu TL 1 x 20 Watt + Instalasi Kabel Ttk 4,00 310.833,00 1.243.332,00
- Stop Kontak + Instalasi kabel Ttk 2,00 514.509,00 1.029.018,00
-Instalasi lampu Ttk 4,00 449.606,00 1.798.424,00
Jumlah 6.820.774,00
VII BANGUNAN RUMAH POMPA & PANEL
A PEKERJAAN PERSIAPAN
1 Pemasangan bowplank rencana bangunan M1 14,00 81.786,00 1.145.004,00
Jumlah 1.145.004,00
B PEKERJAAN TANAH
1 Galian Tanah M3 8,64 119.924,00 1.036.143,36
2 Urugan Tanah Kembali M3 6,05 86.899,00 525.565,15
3 Urugan Pasir pasir bawah lantai M3 0,80 268.769,00 215.015,20
4 Urugan Pasir bawah pondasi M3 0,48 268.769,00 129.009,12
Jumlah 1.905.732,83
180
C PEKERJAAN BETON
1 Beton lantai kerja K 100 M3 0,45 1.078.544,00 485.344,80
2 Beton Sloof 15/20, K250 M1 12,00 135.210,00 1.622.520,00
3 Beton Kolom 15/15, K250 M1 12,40 105.645,00 1.309.998,00
4 Beton Balok Ring 15/20, K250 M1 18,00 135.210,00 2.433.780,00
5 Beton pondasi Pompa t=20 cm K-250 M3 0,43 5.535.109,00 2.391.167,09
6 Balok topi atas jendela beton K250 M3 0,56 5.535.109,00 3.071.985,50
Jumlah 11.314.795,38
D PEKERJAAN PASANGAN DAN PLESTERAN
1 Aanstamping M3 1,68 650.982,00 1.093.649,76
2 Batu kali 1:4 M3 4,20 1.182.760,00 4.967.592,00
3 Pasangan dinding batu bata 1:4 M2 30,70 169.068,00 5.190.387,60
4 Plesteran dan Acian M2 61,40 96.456,00 5.922.398,40
5 Pasangna Plafond Gypsum Rangka Hollow M2 21,16 211.316,00 4.471.446,56
6 Acian Beton M2 15,65 58.187,00 910.626,55
Jumlah 22.556.100,87
E PEKERJAAN LANTAI
1 Pasangan Keramik Lantai 40x40 M2 19,53 293.205,00 5.726.293,65
2 Rabat beton keliling t= 6 cm M3 1,22 1.078.544,00 1.310.430,96
Jumlah 7.036.724,61
F KUSEN PINTU DAN JENDELA
1 Pintu alumunium m2 1,40 831.749,00 1.164.448,60
2 Jendela Allumunium m2 2,45 831.749,00 2.037.785,05
3 Exhaust fan bh 3,00 520.000,00 1.560.000,00
4 Bouvenlight kayu (rooster) bh 131,00 10.200,00 1.336.200,00
Jumlah 6.098.433,65
G PEKERJAAN ATAP
1 Pekerjaan Atap rangka Baja Ringan M2 15,00 288.093,00 4.321.395,00
2 Atap Genteng M2 15,00 241.029,00 3.615.435,00
3 Lisplank 3/30 cm M1 18,40 95.738,00 1.761.579,20
4 Bubungan atap pelentong M1 10,80 157.741,00 1.703.602,80
Jumlah 11.402.012,00
H PEKERJAAN PENGECATAN
1 Cat dinding M2 61,40 42.948,00 2.637.007,20
2 Cat Expose plafond M2 21,16 42.948,00 908.779,68
3 Cat topi lisplank M2 11,10 42.948,00 476.722,80
Jumlah 4.022.509,68
I PEKERJAAN SANITAIR
1 Bak kontrol 60 x 60 x 65 cm sebanyak 4 buah
- Pek pas bata 1:4 m2 4,68 169.068,00 791.238,24
- Pek Plesteran m2 4,77 96.456,00 460.095,12
- Pek Acian m2 4,77 58.187,00 277.551,99
- Pek Galian tanah m3 0,23 119.924,00 28.062,22
- Pek beton tutup bak kontrol K 250 m3 0,10 1.336.744,00 133.674,40
- Besi tulangan D=10 mm kg 7,44 20.011,00 148.881,84
2 Talang tegak pvc 4 " m' 30,00 120.248,00 3.607.440,00
3 Saluran air sepanjang 30 m
- Pek pas bata 1:4 m2 30,00 169.068,00 5.072.040,00
- Pek Plesteran m2 37,36 96.456,00 3.603.596,16
- Pek Acian m2 37,36 58.187,00 2.173.866,32
- Pek Galian tanah m3 10,50 119.924,00 1.259.202,00
- Pek beton dasar saluran K 250 m3 1,80 1.336.744,00 2.406.139,20
Jumlah 19.961.787,49
J PPEKERJAAN INSTALASI LISTRIK
1 Lampu TL 2X40 W RMI bh 2,00 310.833,00 621.666,00
2 Lampu SL 11 W bh 4,00 97.773,00 391.092,00
3 Stop Kontak bh 2,00 113.390,00 226.780,00
4 Instalasi lampu dan stop kontak ttk 6,00 449.606,00 2.697.636,00
5 Saklar Doubel ttk 2,00 110.486,00 220.972,00
6 Panel 2200 V bh 1,00 2.321.024,00 2.321.024,00
Jumlah 6.479.170,00
PEKERJAAN PENGADAAN DAN PEMASANGAN
K
POMPA
1 Pompa Air 3 Inch 6,5 Pk Bahan Bakar Solar bh 4,00 4.000.000,00 16.000.000,00
2 Pemasangan ls 1,00 1.600.000,00 1.600.000,00
Jumlah 17.600.000,00
VIII BANGUNAN & SARANA PENUNJANG
A PONDASI KELILING
1 Pondasi DPT Batu Kali 1 m3 52,03 1.182.760,00 61.540.481,25
2 Pondasi DPT Batu Kali 2 m3 91,08 1.182.760,00 107.725.780,80
3 Pondasi Penahan Tanah Cor beton, K300 m3 93,90 1.374.406,00 129.060.503,02
4 Pembuatan Tangga Besi
- Pengecoran Lantai dan trap tangga beton K 300 m3 1,10 1.374.406,00 1.515.694,94
- Pemasangan railing tangga pipa galv. 1.25'', berikut cat unit 9,19 296.293,00 2.722.932,67
Jumlah 302.565.392,67
181
182
LAMPIRAN III PRATURAN BUPATI BANDUNG
NOMOR : 70 TAHUN 2021
TENTANG : HARGA SATUAN POKOK KEGIATAN
DAN ANALISIS STANDAR BELANJA
NON KONSTRUKSI
9.1.2.11.02.01.001.00068 Snack 5,00 Panitia 1,00 Box 1,00 N/A Fix 20.000,00 100.000,00
9.1.2.11.02.01.001.00068 Snack 1,00 Narasumber 1,00 Box 1,00 N/A Fix 20.000,00 20.000,00
140.000,00
JUMLAH 5.103.000,00
Total Variabel Cost 173.000,00
Total Fix Cost 4.930.000,00
Total Cost 5.103.000,00
HSAK 271.600,00
1
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : Sosialisasi
3 SUB- SUB KELOMPOK : Sosialisasi Di Lingkungan Luar Kantor Pemda
4 ZONA WILAYAH SSH : Seluruh Wilayah di Kabupaten Bandung
5 AKTIVITAS : Sosialisasi Tipe X.2
DESKRIPSI AKTIVITAS : Sosialisasi di Luar Kantor Pemda selama satu hari, sewa gedung, Narasumber Praktisi, Peserta Non PNS
6 SATUAN AKTIVITAS : 50 Peserta
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Peserta Derivatif 1 Kelas Range 50 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
Pejabat Eselon III ke bawah/yang
disetarakan (Non ASN Pemda)
9.1.2.24.01.01.001.00201 1,00 Orang 6,00 Jam 1,00 N/A Fix 900.000,00 5.400.000,00
Honorarium Narasumber/Praktisi
(pembahas)
Biaya Kediklatan, Uang Saku
9.1.2.23.01.01.001.01244 1,00 Orang 1,00 Hari 1,00 N/A Var 150.000,00 150.000,00
Peserta Diklat
5.550.000,00
7.2 Bahan Material
9.1.2.06.02.01.001.00053 Fotocopy - A.4 1,00 Peserta 10,00 Lembar 1,00 N/A Var 300,00 3.000,00
Biaya Penjilidan - Lakban, 1
1.1.7.01.03.01.014.00867 1,00 Dokumen 5,00 Eksemplar 1,00 N/A Fix 4.000,00 20.000,00
warna, tebal
Cetak Spanduk, Bahan Flexy
1.1.7.01.03.03.007.01470 1,00 Buah 5,00 Meter 1,00 N/A Fix 18.000,00 90.000,00
China
113.000,00
7.3 Peralatan/sewa
Beban sewa gedung/
9.1.2.07.02.01.001.00137 kantor/tempat Sewa 1,00 Unit 1,00 Ruang 1,00 N/A Fix 2.000.000,00 2.000.000,00
Gedung/Aula
2.000.000,00
7.4 Belanja Makan Minum
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 1,00 Peserta 1,00 Box 1,00 N/A Var 45.000,00 45.000,00
dan Minuman
9.1.2.11.02.01.001.00068 Snack 1,00 Peserta 1,00 Box 1,00 N/A Var 20.000,00 20.000,00
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 5,00 Panitia 1,00 Box 1,00 N/A Fix 45.000,00 225.000,00
dan Minuman
9.1.2.11.02.01.001.00068 Snack 5,00 Panitia 1,00 Box 1,00 N/A Fix 20.000,00 100.000,00
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 1,00 Narasumber 1,00 Box 1,00 N/A Fix 45.000,00 45.000,00
dan Minuman
9.1.2.11.02.01.001.00068 Snack 1,00 Narasumber 1,00 Box 1,00 N/A Fix 20.000,00 20.000,00
455.000,00
JUMLAH 8.118.000,00
Total Variabel Cost 218.000,00
Total Fix Cost 7.900.000,00
Total Cost 8.118.000,00
HSAK 376.000,00
2
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : Sosialisasi
3 SUB- SUB KELOMPOK : Sosialisasi Di Lingkungan Luar Kantor Pemda
4 ZONA WILAYAH SSH : Seluruh Wilayah di Kabupaten Bandung
5 AKTIVITAS : Sosialisasi Tipe X.4
DESKRIPSI AKTIVITAS : Sosialisasi di Luar Kantor Pemda selama satu hari , sewa gedung, Narasumber internal, Peserta Non PNS
6 SATUAN AKTIVITAS : 50 Peserta
7 KOMPONEN/RINCIAN KOMPONEN :
Cost Driver
Peserta Derivatif 1 Kelas Range 50 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
Biaya Kediklatan, Uang Saku
9.1.2.23.01.01.001.01244 1,00 Orang 1,00 Hari 1,00 N/A Var 150.000,00 150.000,00
Peserta Diklat
150.000,00
7.2 Bahan Material
9.1.2.06.02.01.001.00053 Fotocopy - A.4 1,00 Peserta 10,00 Lembar 1,00 N/A Var 300,00 3.000,00
Biaya Penjilidan - Lakban, 1
1.1.7.01.03.01.014.00867 1,00 Dokumen 5,00 Eksemplar 1,00 N/A Fix 4.000,00 20.000,00
warna, tebal
Cetak Spanduk, Bahan Flexy
1.1.7.01.03.03.007.01470 1,00 Buah 5,00 Meter 1,00 N/A Fix 18.000,00 90.000,00
China
113.000,00
7.3 Peralatan/sewa
Beban sewa gedung/
9.1.2.07.02.01.001.00137 kantor/tempat Sewa 1,00 Hari 1,00 Ruang 1,00 N/A Fix 2.000.000,00 2.000.000,00
Gedung/Aula
2.000.000,00
7.4 Belanja Makan Minum
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 1,00 Peserta 1,00 Box 1,00 N/A Var 45.000,00 45.000,00
dan Minuman
9.1.2.11.02.01.001.00068 Snack 1,00 Peserta 1,00 Box 1,00 N/A Var 20.000,00 20.000,00
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 5,00 Panitian 1,00 Box 1,00 N/A Fix 45.000,00 225.000,00
dan Minuman
9.1.2.11.02.01.001.00068 Snack 5,00 Panitian 1,00 Box 1,00 N/A Fix 20.000,00 100.000,00
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 1,00 Narasumber 1,00 Box 1,00 N/A Fix 45.000,00 45.000,00
dan Minuman
9.1.2.11.02.01.001.00068 Snack 1,00 Narasumber 1,00 Box 1,00 N/A Fix 20.000,00 20.000,00
455.000,00
JUMLAH 2.718.000,00
Total Variabel Cost 218.000,00
Total Fix Cost 2.500.000,00
Total Cost 2.718.000,00
HSAK 268.000,00
3
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : Sosialisasi
3 SUB- SUB KELOMPOK : Sosialisasi Di Lingkungan Luar Kantor Pemda
4 ZONA WILAYAH SSH : Seluruh Wilayah di Kabupaten Bandung
5 AKTIVITAS : Sosialisasi Tipe X.6
DESKRIPSI AKTIVITAS : Sosialisasi di Hotel (fullday), Narasumber Luar Pemda Peserta Non PNS
6 SATUAN AKTIVITAS : 50 Peserta
7 KOMPONEN/RINCIAN KOMPONEN :
Cost Driver
Peserta Derivatif 1 Kelas Range 50 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
Honorarium Narasumber/
9.1.2.25.03.01.001.00054 Pembahas Pejabat Eselon II /yang 1,00 Orang 6,00 Jam 1,00 N/A Fix 1.000.000,00 6.000.000,00
disetarakan
Biaya Kediklatan, Uang Saku
9.1.2.23.01.01.001.01244 1,00 Peserta 1,00 Hari 1,00 N/A Var 150.000,00 150.000,00
Peserta Diklat
6.150.000,00
7.2 Bahan Material
9.1.2.06.02.01.001.00053 Fotocopy - A.4 1,00 Peserta 10,00 Lembar 1,00 N/A Var 300,00 3.000,00
Biaya Penjilidan - Lakban, 1
1.1.7.01.03.01.014.00867 1,00 Dokumen 5,00 Eksemplar 1,00 N/A Fix 4.000,00 20.000,00
warna, tebal
Cetak Spanduk, Bahan Flexy
1.1.7.01.03.03.007.01470 1,00 Buah 5,00 Meter 1,00 N/A Fix 18.000,00 90.000,00
China
113.000,00
7.3 Peralatan/sewa
Biaya Kegiatan Rapat Atau
Pertemuan Di Luar Kantor Eselon
9.1.2.15.02.01.001.07717 1,00 Peserta 1,00 Paket 1,00 N/A Var 300.000,00 300.000,00
IV, Staff dan Non PNS - Fullday
Jawa Barat
Biaya Kegiatan Rapat Atau
Pertemuan Di Luar Kantor Eselon
9.1.2.15.02.01.001.07717 5,00 Orang 1,00 Paket 1,00 N/A Fix 300.000,00 1.500.000,00
IV, Staff dan Non PNS - Fullday
Jawa Barat
Biaya Kegiatan Rapat Atau
Pertemuan Di Luar Kantor Eselon
9.1.2.15.02.01.001.07717 1,00 Orang 1,00 Paket 1,00 N/A Fix 300.000,00 300.000,00
IV, Staff dan Non PNS - Fullday
Jawa Barat
2.100.000,00
JUMLAH 8.363.000,00
Total Variabel Cost 453.000,00
Total Fix Cost 7.910.000,00
Total Cost 8.363.000,00
HSAK 611.200,00
4
1 KELOMPOK : Non Konstruktsi
2 SUB KELOMPOK : Sosialisasi
3 SUB- SUB KELOMPOK : Sosialisasi Di Lingkungan Kantor Pemda
4 ZONA WILAYAH SSH : Seluruh Wilayah di Kabupaten Bandung
5 AKTIVITAS : Sosialisasi Tipe Y.1
DESKRIPSI AKTIVITAS : Sosialisasi di Kantor Pemda selama setengah hari, Narasumber Praktisi, Peserta PNS
6 SATUAN AKTIVITAS : 50 Peserta
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Peserta Derivatif 1 Kelas Range 50 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
Pejabat Eselon III ke bawah/yang
disetarakan (Non ASN Pemda)
9.1.2.24.01.01.001.00201 1,00 Orang 3,00 Jam 1,00 N/A Fix 900.000,00 2.700.000,00
Honorarium Narasumber/Praktisi
(pembahas)
2.700.000,00
7.2 Bahan Material
9.1.2.06.02.01.001.00053 Fotocopy - A.4 1,00 Peserta 10,00 Lembar 1,00 N/A Var 300,00 3.000,00
Biaya Penjilidan - Lakban, 1
1.1.7.01.03.01.014.00867 1,00 Dokumen 5,00 Eksemplar 1,00 N/A Fix 4.000,00 20.000,00
warna, tebal
Cetak Spanduk, Bahan Flexy
1.1.7.01.03.03.007.01470 1,00 Buah 5,00 Meter 1,00 N/A Fix 18.000,00 90.000,00
China
113.000,00
7.3 Peralatan/sewa
9.1.2.11.02.01.001.00068 Snack 1,00 Peserta 1,00 Box 1,00 N/A Var 20.000,00 20.000,00
9.1.2.11.02.01.001.00068 Snack 5,00 Panitia 1,00 Box 1,00 N/A Fix 20.000,00 100.000,00
9.1.2.11.02.01.001.00068 Snack 1,00 Narasumber 1,00 Box 1,00 N/A Fix 20.000,00 20.000,00
140.000,00
JUMLAH 2.953.000,00
Total Variabel Cost 23.000,00
Total Fix Cost 2.930.000,00
Total Cost 2.953.000,00
HSAK 81.600,00
5.400.000,00
7.2 Bahan Material
9.1.2.06.02.01.001.00053 Fotocopy - A.4 1,00 Peserta 10,00 Lembar 1,00 N/A Var 300,00 3.000,00
Biaya Penjilidan - Lakban, 1
1.1.7.01.03.01.014.00867 1,00 Dokumen 5,00 Eksemplar 1,00 N/A Fix 4.000,00 20.000,00
warna, tebal
Cetak Spanduk, Bahan Flexy
1.1.7.01.03.03.007.01470 1,00 Buah 5,00 Meter 1,00 N/A Fix 18.000,00 90.000,00
China
113.000,00
7.3 Peralatan/sewa
- - -
-
7.4 Peralatan/sewa
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 1,00 Peserta 1,00 Box 1,00 N/A Var 45.000,00 45.000,00
dan Minuman
9.1.2.11.02.01.001.00068 Snack 1,00 Peserta 1,00 Box 1,00 N/A Var 20.000,00 20.000,00
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 5,00 Panita 1,00 Box 1,00 N/A Fix 45.000,00 225.000,00
dan Minuman
9.1.2.11.02.01.001.00068 Snack 5,00 Panita 1,00 Box 1,00 N/A Fix 20.000,00 100.000,00
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 1,00 Narasumber 1,00 Box 1,00 N/A Fix 45.000,00 45.000,00
dan Minuman
9.1.2.11.02.01.001.00068 Snack 1,00 Narasumber 1,00 Box 1,00 N/A Fix 20.000,00 20.000,00
455.000,00
JUMLAH 5.968.000,00
Total Variabel Cost 68.000,00
Total Fix Cost 5.900.000,00
Total Cost 5.968.000,00
HSAK 186.000,00
5
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : Sosialisasi
3 SUB- SUB KELOMPOK : Sosialisasi Di Lingkungan Luar Kantor Pemda
4 ZONA WILAYAH SSH : Seluruh Wilayah di Kabupaten Bandung
5 AKTIVITAS : Sosialisasi Tipe Y.3
DESKRIPSI AKTIVITAS : Sosialisasi di Luar Kantor Pemda selama satu hari, sewa gedung, Narasumber Praktisi, Peserta PNS
6 SATUAN AKTIVITAS : 50 Peserta
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Peserta Derivatif 1 Kelas Range 50 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
Pejabat Eselon III ke bawah/yang
disetarakan (Non ASN Pemda)
9.1.2.24.01.01.001.00201 1,00 Orang 6,00 Jam 1,00 N/A Fix 900.000,00 5.400.000,00
Honorarium Narasumber/Praktisi
(pembahas)
5.400.000,00
7.2 Bahan Material
9.1.2.06.02.01.001.00053 Fotocopy - A.4 1,00 Peserta 10,00 Lembar 1,00 N/A Var 300,00 3.000,00
Biaya Penjilidan - Lakban, 1
1.1.7.01.03.01.014.00867 1,00 Dokumen 5,00 Eksemplar 1,00 N/A Fix 4.000,00 20.000,00
warna, tebal
Cetak Spanduk, Bahan Flexy
1.1.7.01.03.03.007.01470 1,00 Buah 5,00 Meter 1,00 N/A Fix 18.000,00 90.000,00
China
113.000,00
7.3 Peralatan/sewa
Beban sewa gedung/
9.1.2.07.02.01.001.00137 kantor/tempat Sewa 1,00 Unit 1,00 Hari 1,00 N/A Fix 2.000.000,00 2.000.000,00
Gedung/Aula
2.000.000,00
7.4 Belanja Makan Minum
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 1,00 Peserta 1,00 Box 1,00 N/A Var 45.000,00 45.000,00
dan Minuman
9.1.2.11.02.01.001.00068 Snack 1,00 Peserta 1,00 Box 1,00 N/A Var 20.000,00 20.000,00
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 5,00 Orang 1,00 Box 1,00 N/A Fix 45.000,00 225.000,00
dan Minuman
9.1.2.11.02.01.001.00068 Snack 5,00 Orang 1,00 Box 1,00 N/A Fix 20.000,00 100.000,00
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 1,00 Orang 1,00 Box 1,00 N/A Fix 45.000,00 45.000,00
dan Minuman
9.1.2.11.02.01.001.00068 Snack 1,00 Orang 1,00 Box 1,00 N/A Fix 20.000,00 20.000,00
455.000,00
JUMLAH 7.968.000,00
Total Variabel Cost 68.000,00
Total Fix Cost 7.900.000,00
Total Cost 7.968.000,00
HSAK 226.000,00
6
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : Sosialisasi
3 SUB- SUB KELOMPOK : Sosialisasi Di Lingkungan Luar Kantor Pemda
4 ZONA WILAYAH SSH : Semua Wilayah Kabupaten Bandung
5 AKTIVITAS : Sosialisasi Tipe Y.5
DESKRIPSI AKTIVITAS : Sosialisasi di Hotel (fullday) Narasumber Luar Pemda, Peserta PNS
6 SATUAN AKTIVITAS : 50 peserta
7 KOMPONEN/RINCIAN KOMPONEN :
Cost Driver
Peserta Derivatif 1 Kelas Range 50 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
Honorarium Narasumber/
9.1.2.25.03.01.001.00054 Pembahas Pejabat Eselon II /yang 1,00 Orang 6,00 Jam 1,00 N/A Fix 1.000.000,00 6.000.000,00
disetarakan
6.000.000,00
7.2 Bahan Material
9.1.2.06.02.01.001.00053 Fotocopy - A.4 1,00 Peserta 10,00 Lembar 1,00 N/A Var 300,00 3.000,00
Biaya Penjilidan - Lakban, 1
1.1.7.01.03.01.014.00867 1,00 Dokumen 5,00 Eksemplar 1,00 N/A Fix 4.000,00 20.000,00
warna, tebal
Cetak Spanduk, Bahan Flexy
1.1.7.01.03.03.007.01470 1,00 Buah 5,00 Meter 1,00 N/A Fix 18.000,00 90.000,00
China
113.000,00
7.3 Peralatan/sewa
Biaya Kegiatan Rapat Atau
Pertemuan Di Luar Kantor Eselon
9.1.2.15.02.01.001.07717 1,00 Peserta 1,00 Paket 1,00 N/A Var 300.000,00 300.000,00
IV, Staff dan Non PNS - Fullday
Jawa Barat
Biaya Kegiatan Rapat Atau
Pertemuan Di Luar Kantor Eselon
9.1.2.15.02.01.001.07717 5,00 Orang 1,00 Paket 1,00 N/A Fix 300.000,00 1.500.000,00
IV, Staff dan Non PNS - Fullday
Jawa Barat
Biaya Kegiatan Rapat Atau
Pertemuan Di Luar Kantor Eselon
9.1.2.15.02.01.001.07717 1,00 Orang 1,00 Paket 1,00 N/A Fix 300.000,00 300.000,00
IV, Staff dan Non PNS - Fullday
Jawa Barat
2.100.000,00
JUMLAH 8.213.000,00
Total Variabel Cost 303.000,00
Total Fix Cost 7.910.000,00
Total Cost 8.213.000,00
HSAK 461.200,00
7
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : Sosialisasi
3 SUB- SUB KELOMPOK : Sosialisasi Di Lingkungan Kantor Pemda
4 ZONA WILAYAH SSH : Seluruh Wilayah di Kabupaten Bandung
5 AKTIVITAS : Sosialisasi Tipe Y.7
DESKRIPSI AKTIVITAS : Sosialisasi di Kantor Pemda selama setengah hari, Narasumber internal, Peserta PNS
6 SATUAN AKTIVITAS : 50 Peserta
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Peserta Derivatif 1 Kelas Range 50 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
- - -
-
7.2 Bahan Material
9.1.2.06.02.01.001.00053 Fotocopy - A.4 1,00 Peserta 10,00 Lembar 1,00 N/A Var 300,00 3.000,00
Biaya Penjilidan - Lakban, 1
1.1.7.01.03.01.014.00867 1,00 Dokumen 5,00 Eksemplar 1,00 N/A Fix 4.000,00 20.000,00
warna, tebal
Cetak Spanduk, Bahan Flexy
1.1.7.01.03.03.007.01470 1,00 Buah 5,00 Meter 1,00 N/A Fix 18.000,00 90.000,00
China
113.000,00
7.3 Peralatan/sewa
- - -
-
7.4 Belanja Makan Minum
9.1.2.11.02.01.001.00068 Snack 1,00 Peserta 1,00 Box 1,00 N/A Var 20.000,00 20.000,00
9.1.2.11.02.01.001.00068 Snack 5,00 Panitia 1,00 Box 1,00 N/A Fix 20.000,00 100.000,00
9.1.2.11.02.01.001.00068 Snack 1,00 Narasumber 1,00 Box 1,00 N/A Fix 20.000,00 20.000,00
140.000,00
JUMLAH 253.000,00
Total Variabel Cost 23.000,00
Total Fix Cost 230.000,00
Total Cost 253.000,00
HSAK 27.600,00
8
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : Sosialisasi
3 SUB- SUB KELOMPOK : Sosialisasi Di Lingkungan Kantor Pemda
4 ZONA WILAYAH SSH : Seluruh Wilayah di Kabupaten Bandung
5 AKTIVITAS : Sosialisasi Tipe X.8
DESKRIPSI AKTIVITAS : Sosialisasi di Lingkungan Kantor Pemda selama satu hari, Narasumber Praktisi, Peserta Non PNS
6 SATUAN AKTIVITAS : 50 Peserta
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Peserta Derivatif 1 Kelas Range 50 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
Pejabat Eselon III ke bawah/yang
disetarakan (Non ASN Pemda)
9.1.2.24.01.01.001.00201 1,00 Orang 6,00 Jam 1,00 N/A Fix 900.000,00 5.400.000,00
Honorarium Narasumber/Praktisi
(pembahas)
455.000,00
JUMLAH 6.118.000,00
Total Variabel Cost 218.000,00
Total Fix Cost 5.900.000,00
Total Cost 6.118.000,00
HSAK 336.000,00
455.000,00
JUMLAH 3.418.000,00
Total Variabel Cost 218.000,00
Total Fix Cost 3.200.000,00
Total Cost 3.418.000,00
HSAK 282.000,00
9
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : Perogram Obat dan Perbekalan Kesehatan
3 SUB- SUB KELOMPOK : Pengadaan Obat dan Perbekalan Kesehatan
4 ZONA WILAYAH SSH : Semua Wilayah (satuannya RW)
5 AKTIVITAS : Pengukuran dan Pemeriksaan Faktor Risiko Penyakit Tidak Menular Penduduk Usia 15 - 59 tahun
Pengukuran dan Pemeriksaan Faktor Risiko Penyakit Tidak Menular Penduduk Usia 15 - 59 tahun dengan menggunakan stik Gula darah/stik cholestrol dengan darah
DESKRIPSI AKTIVITAS :
perifer Pasien
6 SATUAN AKTIVITAS : Peserta
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Peserta Derivatif 1 Kelas Range 1 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
- - -
-
7.2 Bahan Material
Stik Gula Darah, Harga Untuk Per
1.3.2.07.02.05.025.19661 1,00 Orang 1,00 pcs 1,00 Kegiatan var 6.000,00 6.000,00
Pcs Stik
Stik Kolesterol, Harga Untuk Per
1.3.2.07.02.05.025.19662 1,00 Orang 1,00 pcs 1,00 Kegiatan var 30.000,00 30.000,00
Pcs Stik
1.3.2.07.02.05.025.17319 Alcohol Swab, 1,00 Orang 0,01 box 1,00 Kegiatan var 16.335,00 163,35
1.3.2.07.02.05.025.17633 Blood Lancet Disposible, 200/Box 1,00 Orang 0,01 box 1,00 Kegiatan var 72.930,00 364,65
36.528,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 36.528,00
Total Variabel Cost 36.528,00
Total Fix Cost -
Total Cost 36.528,00
HSAK 36.528,00
10
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : Dinas Pertanian
3 SUB- SUB KELOMPOK : Penjaminan Kemurnian dan Kelestarian SDG Hewan/Tanaman
4 ZONA WILAYAH SSH : Semua Wilayah
5 AKTIVITAS : Pengembangan Budidaya jeruk siam madu
Pengadaan sarana pengembangan budidaya jeruk siam madu diperuntukan bagi kelompok tani yang terdaftar di Simluhtan yang mengusahakan komoditi hortikultura
DESKRIPSI AKTIVITAS :
dengan satuan luas garapan lahan sebesar 1 Ha. Setiap kelompok mendapatkan fasilitasi bibit jeruk siam madu sebanyak 200 pohon, dan 2.500 kg pupuk organik padat.
1.1.7.01.01.11.001.00349 Itik Petelur Betina Dewasa 1,00 Paket 180,00 ekor 1,00 N/A Var 158.400,00 28.512.000,00
31.372.000,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 31.372.000,00
Total Variabel Cost 31.372.000,00
Total Fix Cost -
Total Cost 31.372.000,00
HSAK 31.372.000,00
1.1.7.01.01.02.002.00104 Pupuk hayati cair 1,00 Paket 62,50 liter 1,00 N/A Var 66.500,00 4.156.250,00
10.775.000,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 10.775.000,00
Total Variabel Cost 10.775.000,00
Total Fix Cost -
Total Cost 10.775.000,00
HSAK 10.775.000,00
11
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : Dinas Pertanian
3 SUB- SUB KELOMPOK : Pengawasan Penggunaan Sarana Pendukung Pertanian sesuai dengan Komoditas, Teknologi dan Spesifik Lokasi
4 ZONA WILAYAH SSH : Semua Wilayah
5 AKTIVITAS : Pengembangan Budidaya Jagung hibrida
Pengembangan Budidaya Jagung Hibrida diberikan kepada kelompok tani pertanian tanaman pangan yang terdaftar di Simluhtan dengan satuan garapan lahan seluas 20
DESKRIPSI AKTIVITAS :
Ha atau kelipatannya. Setiap Paket terdiri dari 300 kg benih jagung
6 SATUAN AKTIVITAS : Kelompok
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Kelompok Derivatif 1 Kelas Range 1 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
- - -
-
7.2 Bahan Material
1.1.7.01.01.08.001.00707 Benih Jagung hibrida, label biru 1,00 Paket 330,00 kg 1,00 N/A Var 43.850,00 14.470.500,00
14.470.500,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 14.470.500,00
Total Variabel Cost 14.470.500,00
Total Fix Cost -
Total Cost 14.470.500,00
HSAK 14.470.500,00
12
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : Dinas Pertanian
3 SUB- SUB KELOMPOK : Pelestarian dan Pemanfaatan Wilayah Sumber Bibit Ternak dan Rumpun Galur Ternak
4 ZONA WILAYAH SSH : Semua Wilayah
5 AKTIVITAS : Penunjang peningkatan produksi sapi perah (Karpet kandang, Milkcan)
Penunjang peningkatan produksi sapi perah diperuntukan bagi kelompok tani ternak yang terdaftar di Simluhtan. Setiap Paketnya Terdiri dari 5 buah Milkcan dan 10
DESKRIPSI AKTIVITAS :
lembar Karpet Kandang.
6 SATUAN AKTIVITAS : Kelompok
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Kelompok Derivatif 1 Kelas Range 1 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
- - -
-
7.2 Bahan Material
Milkcan 20 liter, Kapasitas 20
1.3.2.04.01.06.044.00048 1,00 Paket 5,00 buah 1,00 N/A Var 2.200.000,00 11.000.000,00
Liter
1.3.2.04.01.06.044.00033 Karpet Kandang, 1,00 Paket 10,00 lembar 1,00 N/A Var 935.000,00 9.350.000,00
20.350.000,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 20.350.000,00
Total Variabel Cost 20.350.000,00
Total Fix Cost -
Total Cost 20.350.000,00
HSAK 20.350.000,00
2.106.500,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 2.106.500,00
Total Variabel Cost 2.106.500,00
Total Fix Cost -
Total Cost 2.106.500,00
HSAK 2.106.500,00
13
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : Dinas Pertanian
3 SUB- SUB KELOMPOK : Pengendalian Organisme Pengganggu Tumbuhan (OPT) Tanaman Pangan, Hortikultura, dan Perkebunan
4 ZONA WILAYAH SSH : Semua Wilayah
5 AKTIVITAS : Fasilitasi Pengendalian OPT Kopi
Fasilitasi Pengendalian OPT Kopi berupa 2 Perakngkap PBKO dan 6 sachet Senyawa Antraktan OPT Kopi diperuntukan bagi kelompok tani perkebunan kopi yang telah
DESKRIPSI AKTIVITAS :
terdaftar di SIMLUHTAN.
6 SATUAN AKTIVITAS : set
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
set Derivatif 1 Kelas Range 1 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
- - -
-
7.2 Bahan Material
1.1.7.01.02.07.002.00020 Perangkap OPT Kopi 1,00 Set 2,00 buah 1,00 N/A Var 32.500,00 65.000,00
1.1.7.01.01.02.001.00118 Senyawa Antraktan OPT Kopi 1,00 Set 6,00 sachet 1,00 N/A Var 7.500,00 45.000,00
110.000,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 110.000,00
Total Variabel Cost 110.000,00
Total Fix Cost -
Total Cost 110.000,00
HSAK 110.000,00
9.1.2.02.06.01.001.02732 garam beryodium, Halus 250gr 1,00 Paket 1,00 buah 1,00 N/A Fix 5.000,00 5.000,00
9.1.2.01.09.01.001.05876 Daging Ayam Fillet 1,00 Paket 5,00 kg 1,00 N/A Fix 52.200,00 261.000,00
9.1.2.01.09.01.001.05857 Bumbu Dapur 1,00 Paket 1,00 kg 1,00 N/A Fix 25.300,00 25.300,00
1.279.800,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 1.279.800,00
Total Variabel Cost -
Total Fix Cost 1.279.800,00
Total Cost 1.279.800,00
HSAK 1.279.800,00
14
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : Dinas Pertanian
3 SUB- SUB KELOMPOK : Pelestarian dan Pemanfaatan Wilayah Sumber Bibit Ternak dan Rumpun Galur Ternak
4 ZONA WILAYAH SSH : Semua Wilayah
5 AKTIVITAS : Sarana Pengolahan Kompos
DESKRIPSI AKTIVITAS : Sarana Pengolahan Kompos diperuntukan bagi kelompok tani yang sudah terdaftar di Simluhtan
6 SATUAN AKTIVITAS : Kelompok
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Kelompok Derivatif 1 Kelas Range 1 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
- - -
-
7.2 Bahan Material
1.3.2.02.02.01.002.00011 Roda Dorong 1,00 Paket 3,00 unit 1,00 N/A Fix 2.060.000,00 6.180.000,00
1.1.7.01.05.01.004.02508 Timbangan Duduk Digital 150 Kg 1,00 Paket 1,00 unit 1,00 N/A Fix 4.075.000,00 4.075.000,00
Cangkul Material : besi Dimensi
1.3.2.04.01.01.003.00031 produk : 16 x 20 x 74 cm Berat : 3 1,00 Paket 3,00 buah 1,00 N/A Fix 80.000,00 240.000,00
Kg
9.1.2.01.05.01.001.01377 Gacok 4 Gigi Sedang 1,00 Paket 3,00 buah 1,00 N/A Fix 75.000,00 225.000,00
Terpal Plastik Untuk Truk
1.1.7.01.01.01.022.08087 1,00 Paket 36,00 meter 1,00 N/A Fix 15.900,00 572.400,00
Sampah -
1.1.7.01.05.01.004.02407 Mesin Jahit Karung 1,00 Paket 1,00 unit 1,00 N/A Fix 1.500.000,00 1.500.000,00
1.1.7.01.03.09.007.00035 Sepatu Boot Ukuran 38 - 42 1,00 Paket 10,00 buah 1,00 N/A Fix 145.000,00 1.450.000,00
Pakaian Kerja Lapangan, Pakaian
9.1.2.01.09.01.001.06065 Kerja Lapangan, bahan drill, 1,00 Paket 5,00 stel 1,00 N/A Fix 350.000,00 1.750.000,00
untuk KSB
1.1.7.01.01.02.005.02054 Starter EM-4, 500 ml 1,00 Paket 20,00 botol 1,00 N/A Fix 50.000,00 1.000.000,00
16.992.400,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 16.992.400,00
Total Variabel Cost -
Total Fix Cost 16.992.400,00
Total Cost 16.992.400,00
HSAK 16.992.400,00
1.1.7.01.05.01.004.02409 Mesin Meat Grinder, 1,00 Paket 1,00 buah 1,00 N/A Fix 5.730.000,00 5.730.000,00
1.3.2.05.02.06.077.02568 Blender Plus Chopper 1,00 Paket 1,00 buah 1,00 N/A Fix 3.250.000,00 3.250.000,00
9.1.2.01.09.01.001.06229 Wajan, 1,00 Paket 2,00 pcs 1,00 N/A Fix 300.000,00 600.000,00
1.3.2.05.02.06.077.02763 Panci Serbaguna, Tutup kaca 1,00 Paket 2,00 buah 1,00 N/A Fix 742.300,00 1.484.600,00
1.1.7.01.05.01.004.02387 Kompor Gas 2 Tungku, 1,00 Paket 1,00 unit 1,00 N/A Fix 540.000,00 540.000,00
9.1.2.01.09.01.001.06180 Tabung Gas dan Selang Regulator, 1,00 Paket 1,00 set 1,00 N/A Fix 350.000,00 350.000,00
9.1.2.01.09.01.001.06161 Serokan Penggorengan, 1,00 Paket 1,00 pcs 1,00 N/A Fix 332.250,00 332.250,00
1.3.2.05.02.06.077.02795 Pisau Dapur 1,00 Paket 2,00 pcs 1,00 N/A Fix 101.500,00 203.000,00
9.1.2.01.09.01.001.06178 Susuk stenless steel, 1,00 Paket 1,00 pcs 1,00 N/A Fix 330.800,00 330.800,00
21.580.650,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 21.580.650,00
Total Variabel Cost -
Total Fix Cost 21.580.650,00
Total Cost 21.580.650,00
HSAK 21.580.650,00
15
1 KELOMPOK : Non Konstruktif
2 SUB KELOMPOK : Dinas Pemadam kebakaran dan Penyelamatan
3 SUB- SUB KELOMPOK : Pemberdayaan Masyarakat
4 ZONA WILAYAH SSH : Semua Wilayah
5 AKTIVITAS : Pelatihan dan Sosialisasi masyarakat
DESKRIPSI AKTIVITAS : Kegiatan Penyuluhan dalam Pencegahan Kebakaran Melalui Sosialisasi dan Edukasi Masyarakat
6 SATUAN AKTIVITAS : Peserta 60
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Peserta Derivatif 1 Kelas Range 60 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
9.1.2.24.01.01.001.00156 Honorarium Narasumber Praktisi 1,00 orang 1,00 kegiatan 1,00 Hari Fix 1.000.000,00 1.000.000,00
Biaya Kediklatan, Uang Saku
9.1.2.23.01.01.001.01244 1,00 orang 1,00 hari 1,00 n/a Var 150.000,00 150.000,00
Peserta Diklat
1.150.000,00
7.2 Bahan Material
1.1.7.01.01.04.006.01008 Pertalite - 40,00 liter 1,00 paket 1,00 Hari Fix 8.100,00 324.000,00
1.1.7.01.01.04.001.00052 Bio Solar 60,00 liter 1,00 paket 1,00 Hari Fix 9.400,00 564.000,00
1.1.7.01.01.09.002.00312 6 KG Powder 12,00 tabung 1,00 paket 1,00 Hari Fix 272.250,00 3.267.000,00
1.3.2.07.02.05.025.18829 Masker N 95, 1,00 pcs 1,00 orang 1,00 n/a Fix 7.814,00 7.814,00
1.3.2.05.02.06.077.02839 Sarung Tangan Kain 1,00 pcs 1,00 orang 1,00 n/a Fix 10.000,00 10.000,00
Map - Pemda Cetak Berwarna Full
9.1.2.06.03.01.001.05090 1,00 pcs 1,00 orang 1,00 n/a Var 12.000,00 12.000,00
Colour
1.1.7.01.03.01.014.00972 Jilid Dokumen 1,00 mdl 1,00 orang 1,00 n/a Var 100.000,00 100.000,00
4.284.814,00
7.3 Peralatan/sewa
- - -
-
7.4 Peralatan/sewa
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 1,00 orang 1,00 dus 1,00 n/a Var 45.000,00 45.000,00
dan Minuman
9.1.2.11.02.01.001.00068 Snack 1,00 orang 2,00 dus 1,00 n/a Var 20.000,00 40.000,00
85.000,00
JUMLAH 5.519.814,00
Total Variabel Cost 347.000,00
Total Fix Cost 5.172.814,00
Total Cost 5.519.814,00
HSAK 433.213,57
DESKRIPSI AKTIVITAS : Kegiatan Pembentukan Relawan Pemadam Kebakaran dilaksanakan oleh OPD di Lingkungan luar kantor dengan peserta Masyarakat selama 3 (tiga) hari
1.1.7.01.01.04.001.00052 Bio Solar 80,00 liter 1,00 paket 1,00 Hari Fix 9.400,00 752.000,00
1.1.7.01.01.09.002.00312 6 KG Powder 15,00 tabung 1,00 paket 1,00 Hari Fix 272.250,00 4.083.750,00
1.1.7.01.01.09.002.00309 3 KG Foam 10,00 tabung 1,00 paket 1,00 Hari Fix 136.125,00 1.361.250,00
Tabung APAR 2 - 3 kg powder
(kadar chemical < 50 %, atau
1.3.2.05.02.07.017.03079 5,00 tabung 1,00 paket 1,00 Hari Fix 385.000,00 1.925.000,00
tidak mencantumkan Nominal
Fire Rating/Daya padam)
Pakaian Lapangan (seragam
1,00 orang 1,00 paket 1,00 Buah Var 400.000,00 400.000,00
Redkar)
1.1.7.01.03.01.014.00972 Jilid Dokumen 1,00 mdl 1,00 Orang 1,00 n/a Var 100.000,00 100.000,00
1.1.7.01.03.01.001.01084 Ballpoint - 0,5 Mm 1,00 orang 1,00 buah 1,00 n/a Var 4.000,00 4.000,00
Block Note - Garis A6 105 X 148
1.1.7.01.03.01.005.00257 1,00 orang 1,00 buah 1,00 n/a Var 33.000,00 33.000,00
mm (50 lbr)
Map - Pemda Cetak Berwarna Full
9.1.2.06.03.01.001.05090 1,00 orang 1,00 buah 1,00 n/a Var 12.000,00 12.000,00
Colour
1.3.2.05.02.07.017.02895 Ransel khusus Pemadam , 1,00 orang 1,00 paket 1,00 Buah Var 315.000,00 315.000,00
9.1.2.06.03.01.001.04826 Cetak Sertifikat 1,00 orang 1,00 paket 1,00 n/a Var 10.000,00 10.000,00
1.1.7.01.03.03.007.01533 Spanduk 1,00 buah 1,00 keg 1,00 n/a Fix 330.000,00 330.000,00
9.731.000,00
7.3 Peralatan/sewa
9.1.2.07.02.01.001.00143 Kamar Standar 1,00 kamar 1,00 paket 3,00 hari Var 340.000,00 1.020.000,00
1.020.000,00
JUMLAH 22.751.000,00
Total Variabel Cost 2.344.000,00
Total Fix Cost 20.407.000,00
Total Cost 22.751.000,00
HSAK 3.364.350,00
16
1 KELOMPOK : Non Kontruksi
2 SUB KELOMPOK : Non Konstruksi Disdik
3 SUB- SUB KELOMPOK : Pengadaan Mebeluer Sekolah
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Pengadaan Meubelair Sekolah
DESKRIPSI AKTIVITAS : Penyediaan sarana meubelair Untuk Sekolah
6 SATUAN AKTIVITAS : Sekolah / Lembaga
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Lembaga Derivatif 1 Kelas Range 1 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
- - -
-
7.2 Bahan Material
1.3.2.05.03.01.009.00032 Meubelair, Meja Kerja utk Kasie 1,00 paket 1,00 Buah var 2.500.000,00 2.500.000,00
1.3.2.05.03.07.006.00034 Lemari, Arsip Datascript 1,00 paket 1,00 Buah var 2.275.000,00 2.275.000,00
16.507.650,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 16.507.650,00
Total Variabel Cost 16.507.650,00
Total Fix Cost -
Total Cost 16.507.650,00
HSAK 16.507.650,00
17
1 KELOMPOK : Non Kontruksi
2 SUB KELOMPOK : Non Konstruksi Disdik
3 SUB- SUB KELOMPOK : Pengadaaan Alat Praktik dan Peraga Siswa PAUD
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Pengadaan Alat Peraga olahraga PAUD
DESKRIPSI AKTIVITAS : Penyediaan alat olahraga di lembaga PAUD
6 SATUAN AKTIVITAS : Sekolah / Lembaga
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Lembaga Derivatif 1 Kelas Range 1 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
- - -
-
7.2 Bahan Material
1.3.2.19.01.02.018.01256 Trampolin, alat olahraga PAUD 1,00 paket 2,00 Buah var 1.500.000,00 3.000.000,00
1.3.2.19.01.02.018.01248 Bola, alat olahraga PAUD 1,00 paket 4,00 Buah var 65.000,00 260.000,00
Bola keranjang, alat olahraga
1.3.2.19.01.02.018.01247 1,00 paket 10,00 set var 130.000,00 1.300.000,00
PAUD
1.3.2.19.01.02.018.01249 Cones, alat olahraga PAUD 1,00 paket 12,00 Buah var 62.000,00 744.000,00
1.3.2.19.01.02.018.01253 Raket Mini, alat olahraga PAUD 1,00 paket 4,00 Buah var 46.900,00 187.600,00
Shutlecock sintetis, alat olahraga
1.3.2.19.01.02.018.01255 1,00 paket 7,00 slop var 75.000,00 525.000,00
PAUD
1.3.2.19.01.02.018.01250 Holahop, alat olahraga PAUD 1,00 paket 8,00 Buah var 45.000,00 360.000,00
6.376.600,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 6.376.600,00
Total Variabel Cost 6.376.600,00
Total Fix Cost -
Total Cost 6.376.600,00
HSAK 6.376.600,00
1.3.2.19.01.02.018.01245 Alat Mewarnai, 1,00 paket 40,00 set var 179.900,00 7.196.000,00
7.386.000,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 7.386.000,00
Total Variabel Cost 7.386.000,00
Total Fix Cost -
Total Cost 7.386.000,00
HSAK 7.386.000,00
18
1 KELOMPOK : Non Kontruksi
2 SUB KELOMPOK : Non Konstruksi Disdik
3 SUB- SUB KELOMPOK : Pengadaan Perlengkapan PAUD
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Pengadaan Komputer dan printer untuk lembaga PAUD
DESKRIPSI AKTIVITAS : Pengadaan Komputer dan printer untuk lembaga PAUD
6 SATUAN AKTIVITAS : Sekolah / Lembaga
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Lembaga Derivatif 1 Kelas Range 1 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
- - -
-
7.2 Bahan Material
Laptop - Hybrid / Intel Core i3-
1.3.2.10.01.02.002.00150 7020U / 4GB DDR4 / 1TB 5400 1,00 paket 1,00 Buah var 6.276.768,00 6.276.768,00
rpm SATA / Ubuntu Linux 16.04
Printer - Deskjet Ink advantge
1.3.2.10.02.03.003.00261 1,00 paket 1,00 buah var 1.150.000,00 1.150.000,00
1115
7.426.768,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 7.426.768,00
Total Variabel Cost 7.426.768,00
Total Fix Cost -
Total Cost 7.426.768,00
HSAK 7.426.768,00
110.660.000,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 110.660.000,00
Total Variabel Cost 110.660.000,00
Total Fix Cost -
Total Cost 110.660.000,00
HSAK 110.660.000,00
19
1 KELOMPOK : Non Kontruksi
2 SUB KELOMPOK : Non Konstruksi Disdik
3 SUB- SUB KELOMPOK : Pengadaan Alat praktek dan Peraga siswa (bankeu prov)
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Pengadaan Media Bahan Ajar Digital Interaktif dalam rangka proses penguatan belajar mengajar jenjang PAUD
Pengadaan peralatan untuk sekolah negeri (belanja modal peralatan pendidikan ) dan belanja hibah barang untuk lembaga nirlaba berdasarkan peraturan perundang
DESKRIPSI AKTIVITAS :
undangan yang bersumber dari Bantuan Keuangan provinsi
6 SATUAN AKTIVITAS : Sekolah / Lembaga
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Lembaga Derivatif 1 Kelas Range 1 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
- - -
-
7.2 Bahan Material
20
1 KELOMPOK : Non Kontruksi
2 SUB KELOMPOK : Non Konstruksi Disdik
3 SUB- SUB KELOMPOK : Pengadaan Alat praktek dan Peraga siswa
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Pengadaan Media Inovasi Kreatifitas Guru dan Siswa Jenjang SMP
Pengadaan peralatan untuk sekolah negeri (belanja modal peralatan pendidikan ) dan belanja hibah barang untuk lembaga nirlaba berdasarkan peraturan perundang
DESKRIPSI AKTIVITAS :
undangan yang bersumber dari Bantuan Keuangan provinsi
6 SATUAN AKTIVITAS : Sekolah / Lembaga
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Lembaga Derivatif 1 Kelas Range 1 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
- - -
-
7.2 Bahan Material
Interactive Flat Panel 75",
ViewBoard 75" 4K Interactive
1.3.2.05.01.05.050.00018 1,00 Unit 1,00 var 182.500.000,00 182.500.000,00
Display / Commercial Touch
Display
21
1 KELOMPOK : Non Kontruksi
2 SUB KELOMPOK : Non Konstruksi Disdik
3 SUB- SUB KELOMPOK : Pengadaan Alat praktek dan Peraga siswa
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Pengadaan Media Interaktif Pembelajaran Berbasis Digital
Pengadaan peralatan untuk sekolah negeri (belanja modal peralatan pendidikan ) dan belanja hibah barang untuk lembaga nirlaba berdasarkan peraturan perundang
DESKRIPSI AKTIVITAS :
undangan yang bersumber dari Bantuan Keuangan provinsi
6 SATUAN AKTIVITAS : Sekolah / Lembaga
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Lembaga Derivatif 1 Kelas Range 1 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
- - -
-
7.2 Bahan Material
Interactive Flat Panel 75",
ViewBoard 75" 4K Interactive
1.3.2.05.01.05.050.00018 1,00 Unit 1,00 var 182.500.000,00 182.500.000,00
Display / Commercial Touch
Display
22
1 KELOMPOK : Non Kontruksi
2 SUB KELOMPOK : Non Konstruksi Disdik
3 SUB- SUB KELOMPOK : Pengadaan MEUBELAIR paud
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Meubelair Indoor untuk Anak Usia Dini Yang Aktif Bermain dan Belajar
Pengadaan peralatan untuk sekolah negeri (belanja modal mebel) dan belanja hibah barang untuk lembaga nirlaba berdasarkan peraturan perundang undangan yang
DESKRIPSI AKTIVITAS :
bersumber dari Bantuan Keuangan provinsi
6 SATUAN AKTIVITAS : Sekolah / Lembaga
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Lembaga Derivatif 1 Kelas Range 1 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
- - -
-
7.2 Bahan Material
23
1 KELOMPOK : Non Kontruksi
2 SUB KELOMPOK : Non Konstruksi Disdik
3 SUB- SUB KELOMPOK : Pengadaan meubelair SMP
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Furniture Kelas Elegant Design untuk Peningkatan Keaktifan Belajar Siswa SMP
Pengadaan peralatan untuk sekolah negeri (belanja modal mebel) dan belanja hibah barang untuk lembaga nirlaba berdasarkan peraturan perundang undangan yang
DESKRIPSI AKTIVITAS :
bersumber dari Bantuan Keuangan provinsi
6 SATUAN AKTIVITAS : Sekolah / Lembaga
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Lembaga Derivatif 1 Kelas Range 1 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
- - -
-
7.2 Bahan Material
64.085.720,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 64.085.720,00
Total Variabel Cost 64.085.720,00
Total Fix Cost -
Total Cost 64.085.720,00
HSAK 64.085.720,00
24
1 KELOMPOK : Non Kontruksi
2 SUB KELOMPOK : Non Konstruksi Disdik
3 SUB- SUB KELOMPOK : Pengadan alat praktek dan peraga siswa SD
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Pengadaan Peralatan Media Pendidikan
Pengadaan peralatan untuk sekolah negeri (belanja modal peralatan pendidikan ) dan belanja hibah barang untuk lembaga nirlaba berdasarkan peraturan perundang
DESKRIPSI AKTIVITAS :
undangan yang bersumber dari DAK FISIK
6 SATUAN AKTIVITAS : Sekolah / Lembaga
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Lembaga Derivatif 1 Kelas Range 1 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
- - -
-
7.2 Bahan Material
1.3.2.08.01.41.192.00010 Laptop, i3-1005G1, 4GB, 1TB 3,00 Unit 1,00 var 6.718.950,00 20.156.850,00
Wifi 4G Router, wifi 300 Mbps, 4
1.3.2.10.02.04.002.00025 1,00 Unit 1,00 var 1.040.000,00 1.040.000,00
LAN, on/off switch
1.1.7.01.03.08.001.00186 Kabel Konektor USB 3,00 Unit 1,00 var 100.000,00 300.000,00
44.934.800,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 44.934.800,00
Total Variabel Cost 44.934.800,00
Total Fix Cost -
Total Cost 44.934.800,00
HSAK 44.934.800,00
1.1.7.01.03.08.001.00186 Kabel Konektor USB 3,00 unit 1,00 var 100.000,00 300.000,00
25
1 KELOMPOK : Non Kontruksi
2 SUB KELOMPOK : Non Konstruksi Disdik
3 SUB- SUB KELOMPOK : Pengadaan perlengkapan pendidikan non formal/kesetaraan
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Pengadaan Peralatan praktek lembaga kursus
DESKRIPSI AKTIVITAS : Pengadaan peralatan belanja hibah barang untuk lembaga nirlaba berdasarkan peraturan perundang undangan
6 SATUAN AKTIVITAS : Sekolah / Lembaga
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Lembaga Derivatif 1 Kelas Range 1 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
- - -
-
7.2 Bahan Material
Printer - Color Laser jet pro
1.3.2.10.02.03.003.00260 1,00 unit 1,00 var 5.250.000,00 5.250.000,00
M177fw MFP
Lemari Arsip, Lemari Besi Dua
1.3.2.05.01.04.001.00043 1,00 unit 1,00 var 4.848.000,00 4.848.000,00
Pintu
1.3.2.07.01.08.125.00079 proyektor - PTLB280 1,00 unit 1,00 var 10.510.000,00 10.510.000,00
Kursi, Kursi Kerja Direktur
1.3.2.05.03.03.008.00196 1,00 unit 1,00 var 2.095.000,00 2.095.000,00
Fantoni Crezzo
25.230.980,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 25.230.980,00
Total Variabel Cost 25.230.980,00
Total Fix Cost -
Total Cost 25.230.980,00
HSAK 25.230.980,00
26
1 KELOMPOK : Non Kontruksi
2 SUB KELOMPOK : Non Konstruksi Disdik
3 SUB- SUB KELOMPOK : Pengadan alat praktek dan peraga siswa
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Pengadaan peralatan teknologi, informasi dan komunikasi (TIK) untuk PKBM
Pengadaan peralatan untuk PKBM negeri (belanja modal peralatan pendidikan ) dan PKBM swasta ( belanja hibah barang untuk lembaga nirlaba berdasarkan peraturan
DESKRIPSI AKTIVITAS :
perundang undangan) yang bersumber dari DAK FISIK
6 SATUAN AKTIVITAS : Sekolah / Lembga
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Lembaga Derivatif 1 Kelas Range 1 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
- - -
-
7.2 Bahan Material
1.3.2.08.01.41.192.00010 Laptop, i3-1005G1, 4GB, 1TB 29,00 unit 1,00 var 6.718.950,00 194.849.550,00
1.1.7.01.03.08.001.00186 Kabel Konektor USB 1,00 unit 1,00 var 100.000,00 100.000,00
208.185.850,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 208.185.850,00
Total Variabel Cost 208.185.850,00
Total Fix Cost -
Total Cost 208.185.850,00
HSAK 208.185.850,00
9.1.2.24.01.01.001.00194 Narasumber Pakar, 2,00 jam 2,00 orang fix 1.700.000,00 6.800.000,00
Biaya Kediklatan, Uang Saku
9.1.2.23.01.01.001.01244 1,00 orang 1,00 hari var 150.000,00 150.000,00
Peserta Diklat
8.950.000,00
7.2 Bahan Material
1.1.7.01.03.01.014.00914 Cetak Buku Perkoperasian 1,00 orang 1,00 buah var 25.000,00 25.000,00
9.1.2.06.02.01.001.00058 Fotocopy - F.4 1,00 orang 90,00 lbr var 300,00 27.000,00
9.1.2.06.02.01.001.00058 Fotocopy - F.4 50,00 lbr 3,00 kali fix 300,00 45.000,00
Biaya Penjilidan - Ring plastik, 1
1.1.7.01.03.01.014.00878 3,00 set 1,00 kali fix 35.000,00 105.000,00
warna, tebal >5cm
Cetak Spanduk, Bahan Flexy
1.1.7.01.03.03.007.01470 1,00 buah 5,00 meter fix 18.000,00 90.000,00
China
292.000,00
7.3 Peralatan/sewa
9.1.2.07.02.01.001.00146 Lembaga pemerintah 1,00 kali 1,00 hari fix 1.000.000,00 1.000.000,00
1.000.000,00
7.4 Belanja Makan Minum
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 1,00 Narasumber 1,00 kali var 45.000,00 45.000,00
dan Minuman
9.1.2.11.02.01.001.00068 Snack 1,00 Narasumber 2,00 kali var 20.000,00 40.000,00
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 3,00 Panitia 1,00 kali fix 45.000,00 135.000,00
dan Minuman
9.1.2.11.02.01.001.00068 Snack 3,00 Panitia 2,00 kali fix 20.000,00 120.000,00
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 5,00 Peserta 1,00 kali fix 45.000,00 225.000,00
dan Minuman
9.1.2.11.02.01.001.00068 Snack 5,00 Peserta 2,00 kali fix 20.000,00 200.000,00
765.000,00
JUMLAH 11.007.000,00
Total Variabel Cost 287.000,00
Total Fix Cost 10.720.000,00
Total Cost 11.007.000,00
HSAK 555.000,00
27
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : Dinas Koperasi dan Usaha Kecil dan Menengah
3 SUB- SUB KELOMPOK : Pemberdayaan melalui Kemitraan Usaha Mikro
4 ZONA WILAYAH SSH : Seluruh Wilayah di Kabupaten Bandung
5 AKTIVITAS : Kemitraan Usaha bagi UMKM
Kegiatan Kemitraan Usaha bagi UMKM dilaksanakan di Hotel Bintang 4 dan 5 (Fullday), Narasumber Luar Pemda, Peserta Non PNS, dalam waktu pelaksanaan 3 hari
DESKRIPSI AKTIVITAS :
kerja
6 SATUAN AKTIVITAS : Peserta
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Peserta Derivatif 1 Kelas Range 20 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
9.1.2.24.01.01.001.00196 Narasumber Praktisi, 9,00 orang 2,00 jam fix 900.000,00 16.200.000,00
Biaya Kediklatan, Uang Saku
9.1.2.23.01.01.001.01244 1,00 orang 3,00 hari var 150.000,00 450.000,00
Peserta Diklat
16.650.000,00
7.2 Bahan Material
9.1.2.06.02.01.001.00058 Fotocopy - F.4 1,00 orang 90,00 lbr var 300,00 27.000,00
27.000,00
7.3 Peralatan/sewa
Biaya Kegiatan Rapat Atau
Pertemuan Di Luar Kantor Eselon
9.1.2.15.02.01.001.07717 1,00 orang 3,00 hari var 300.000,00 900.000,00
IV, Staff dan Non PNS - Fullday
Jawa Barat
Biaya Kegiatan Rapat Atau
Pertemuan Di Luar Kantor Eselon
9.1.2.15.02.01.001.07717 9,00 orang 3,00 hari fix 300.000,00 8.100.000,00
IV, Staff dan Non PNS - Fullday
Jawa Barat
Biaya Kegiatan Rapat Atau
Pertemuan Di Luar Kantor Eselon
9.1.2.15.02.01.001.07717 5,00 orang 3,00 hari fix 300.000,00 4.500.000,00
IV, Staff dan Non PNS - Fullday
Jawa Barat
13.500.000,00
JUMLAH 30.177.000,00
Total Variabel Cost 1.377.000,00
Total Fix Cost 28.800.000,00
Total Cost 30.177.000,00
HSAK 2.817.000,00
DESKRIPSI AKTIVITAS : Kegiatan Pelatihan Kewirausahaan bagi UMKM dilaksanakan di Luar Kantor (Fullday), Narasumber Luar Pemda, Peserta Non PNS, dalam waktu pelaksanaan 2 hari kerja
9.1.2.24.01.01.001.00196 Narasumber Praktisi, 4,00 jam 2,00 hari fix 900.000,00 7.200.000,00
Biaya Kediklatan, Uang Saku
9.1.2.23.01.01.001.01244 1,00 orang 2,00 hari var 150.000,00 300.000,00
Peserta Diklat
11.100.000,00
7.2 Bahan Material
9.1.2.06.02.01.001.00058 Fotocopy - F.4 1,00 orang 180,00 lbr var 300,00 54.000,00
9.1.2.06.02.01.001.00058 Fotocopy - F.4 50,00 lbr 3,00 kali fix 300,00 45.000,00
Biaya Penjilidan - Ring plastik, 1
1.1.7.01.03.01.014.00878 3,00 set 1,00 set fix 35.000,00 105.000,00
warna, tebal >5cm
9.1.2.06.03.01.001.04826 Cetak Sertifikat 1,00 lbr 1,00 orang var 10.000,00 10.000,00
214.000,00
7.3 Peralatan/sewa
9.1.2.07.02.01.001.00146 Lembaga pemerintah 1,00 ruang 2,00 hari fix 1.000.000,00 2.000.000,00
2.000.000,00
7.4 Belanja Makan Minum
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 1,00 orang 2,00 kali var 45.000,00 90.000,00
dan Minuman
9.1.2.11.02.01.001.00068 Snack 1,00 orang 4,00 kali var 20.000,00 80.000,00
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 3,00 orang 2,00 kali fix 45.000,00 270.000,00
dan Minuman
9.1.2.11.02.01.001.00068 Snack 3,00 orang 4,00 kali fix 20.000,00 240.000,00
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 5,00 orang 2,00 kali fix 45.000,00 450.000,00
dan Minuman
9.1.2.11.02.01.001.00068 Snack 5,00 orang 4,00 kali fix 20.000,00 400.000,00
1.530.000,00
JUMLAH 14.844.000,00
Total Variabel Cost 534.000,00
Total Fix Cost 14.310.000,00
Total Cost 14.844.000,00
HSAK 942.857,14
28
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : Dinas Koperasi dan Usaha Kecil dan Menengah
3 SUB- SUB KELOMPOK : Fasilitasi Usaha mikro Menjadi Usaha kecil dalam Pengembangan Produksi dan Pengolahan, Pemasaran, SDM, serta Desain dan Teknologi
4 ZONA WILAYAH SSH : Seluruh Wilayah di Kabupaten Bandung
5 AKTIVITAS : Pendampingan Usaha bagi UMKM
Kegiatan Pendampingan Usaha bagi UMKM dilaksanakan di Hotel Bintang 4 dan 5 (Fullday), Narasumber Luar Pemda, Peserta Non PNS, dalam waktu pelaksanaan 3 hari
DESKRIPSI AKTIVITAS :
kerja
6 SATUAN AKTIVITAS : Peserta
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Peserta Derivatif 1 Kelas Range 25 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
9.1.2.24.01.01.001.00196 Narasumber Praktisi, 9,00 orang 2,00 jam fix 900.000,00 16.200.000,00
Tenaga Pendamping UMKM
9.1.2.24.01.01.001.00224 1,00 orang 6,00 bulan fix 2.600.000,00 15.600.000,00
Pendamping UMKM
31.800.000,00
7.2 Bahan Material
9.1.2.06.02.01.001.00058 Fotocopy - F.4 50,00 lbr 3,00 kali fix 300,00 45.000,00
Biaya Penjilidan - Ring plastik, 1
1.1.7.01.03.01.014.00878 1,00 set 3,00 kali fix 35.000,00 105.000,00
warna, tebal >5cm
150.000,00
7.3 Peralatan/sewa
Biaya Kegiatan Rapat Atau
Pertemuan Di Luar Kantor Eselon
9.1.2.15.02.01.001.07717 1,00 orang 3,00 hari fix 300.000,00 900.000,00
IV, Staff dan Non PNS - Fullday
Jawa Barat
Biaya Kegiatan Rapat Atau
Pertemuan Di Luar Kantor Eselon
9.1.2.15.02.01.001.07717 9,00 orang 3,00 hari fix 300.000,00 8.100.000,00
IV, Staff dan Non PNS - Fullday
Jawa Barat
Biaya Kegiatan Rapat Atau
Pertemuan Di Luar Kantor Eselon
9.1.2.15.02.01.001.07717 5,00 orang 3,00 hari fix 300.000,00 4.500.000,00
IV, Staff dan Non PNS - Fullday
Jawa Barat
13.500.000,00
JUMLAH 45.450.000,00
Total Variabel Cost -
Total Fix Cost 45.450.000,00
Total Cost 45.450.000,00
HSAK 1.818.000,00
DESKRIPSI AKTIVITAS : Kegiatan Inkubasi Bisnis bagi UMKM dilaksanakan di Hotel Bintang 4 dan 5 (Fullday), Narasumber Luar Pemda, Peserta Non PNS, dalam waktu pelaksanaan 5 hari kerja
9.1.2.24.01.01.001.00196 Narasumber Praktisi, 6,00 orang 2,00 jam fix 900.000,00 10.800.000,00
Tenaga Pendamping UMKM
9.1.2.24.01.01.001.00224 1,00 orang 6,00 bulan fix 2.600.000,00 15.600.000,00
Pendamping UMKM
Biaya Kediklatan, Uang Saku
9.1.2.23.01.01.001.01244 1,00 orang 3,00 hari var 150.000,00 450.000,00
Peserta Diklat
43.050.000,00
7.2 Bahan Material
9.1.2.06.02.01.001.00058 Fotocopy - F.4 1,00 orang 90,00 lbr var 300,00 27.000,00
27.000,00
7.3 Peralatan/sewa
Biaya Kegiatan Rapat Atau
Pertemuan Di Luar Kantor Eselon
9.1.2.15.02.01.001.07717 1,00 orang 3,00 hari var 300.000,00 900.000,00
IV, Staff dan Non PNS - Fullday
Jawa Barat
Biaya Kegiatan Rapat Atau
Pertemuan Di Luar Kantor Eselon
9.1.2.15.02.01.001.07717 1,00 orang 2,00 hari fix 300.000,00 600.000,00
IV, Staff dan Non PNS - Fullday
Jawa Barat
Biaya Kegiatan Rapat Atau
Pertemuan Di Luar Kantor Eselon
9.1.2.15.02.01.001.07717 6,00 orang 2,00 hari fix 300.000,00 3.600.000,00
IV, Staff dan Non PNS - Fullday
Jawa Barat
Biaya Kegiatan Rapat Atau
Pertemuan Di Luar Kantor Eselon
9.1.2.15.02.01.001.07717 9,00 orang 3,00 hari fix 300.000,00 8.100.000,00
IV, Staff dan Non PNS - Fullday
Jawa Barat
Biaya Kegiatan Rapat Atau
Pertemuan Di Luar Kantor Eselon
9.1.2.15.02.01.001.07717 5,00 orang 5,00 hari fix 300.000,00 7.500.000,00
IV, Staff dan Non PNS - Fullday
Jawa Barat
20.700.000,00
JUMLAH 63.777.000,00
Total Variabel Cost 1.377.000,00
Total Fix Cost 62.400.000,00
Total Cost 63.777.000,00
HSAK 3.457.000,00
29
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : Dinas Koperasi dan Usaha Kecil dan Menengah
3 SUB- SUB KELOMPOK : Fasilitasi Usaha mikro Menjadi Usaha kecil dalam Pengembangan Produksi dan Pengolahan, Pemasaran, SDM, serta Desain dan Teknologi
4 ZONA WILAYAH SSH : Seluruh Wilayah di Kabupaten Bandung
5 AKTIVITAS : Penyelenggaraan Gelar Produk UMKM
Kegiatan Gelar Produk UMKM dalam dalam rangka memperkenalkan dan mengangkatkan hasil produk masyarakat yang dilaksanakan oleh OPD bertempat di luar kantor
DESKRIPSI AKTIVITAS :
dengan memanfaatkan sumber daya yang dimiliki sendiri dalam, waktu pelaksanaan 2 hari kerja
6 SATUAN AKTIVITAS : Peserta
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Peserta Derivatif 1 Kelas Range 1 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
Biaya Kediklatan, Uang Saku
9.1.2.23.01.01.001.01244 20,00 orang 2,00 hari fix 150.000,00 6.000.000,00
Peserta Diklat
6.000.000,00
7.2 Bahan Material
1.1.7.01.03.03.006.00289 Cetak Film Ukuran 3 R 10,00 lbr 1,00 keg fix 8.000,00 80.000,00
80.000,00
7.3 Peralatan/sewa
9.1.2.10.05.01.001.00050 Stand Pameran 10,00 set 2,00 hari fix 500.000,00 10.000.000,00
10.000.000,00
7.4 Belanja Makan Minum
9.1.2.11.02.01.001.00068 Snack 20,00 orang 1,00 hari fix 20.000,00 400.000,00
9.1.2.24.01.01.001.00196 Narasumber Praktisi, 2,00 Orang 2,00 Jam 2,00 n/a Fix 900.000,00 7.200.000,00
Biaya Kediklatan, Uang Saku
9.1.2.23.01.01.001.01244 1,00 orang 1,00 Hari 2,00 n/a Var 150.000,00 300.000,00
Peserta Diklat
11.500.000,00
7.2 Bahan Material
9.1.2.06.02.01.001.00058 Fotocopy - F.4 1,00 Peserta 10,00 Lembar 1,00 n/a Var 300,00 3.000,00
Biaya Penjilidan - Ring Kawat, 1
1.1.7.01.03.01.014.00873 1,00 Dokumen 5,00 Buku 1,00 n/a Fix 12.300,00 61.500,00
warna, tebal <5cm
Cetak Spanduk, Bahan Flexy
1.1.7.01.03.03.007.01470 1,00 buah 5,00 Meter 1,00 n/a Fix 18.000,00 90.000,00
China
154.500,00
7.3 Peralatan/sewa
Sewa Ruang
Gedung/Rumah/Kantor
9.1.2.07.02.01.001.00179 1,00 Ruang 1,00 hari 2,00 n/a Fix 5.000.000,00 10.000.000,00
(Rapat/Pertemuan) Luar Lembaga
Pemerintah, Aula
10.000.000,00
Belanja Makan Dan
7.4
Minum
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 1,00 orang 1,00 Kali 2,00 n/a Var 45.000,00 90.000,00
dan Minuman
9.1.2.11.02.01.001.00068 Snack 1,00 orang 2,00 Kali 2,00 n/a Var 20.000,00 80.000,00
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 5,00 orang 1,00 Kali 2,00 n/a Fix 45.000,00 450.000,00
dan Minuman
9.1.2.11.02.01.001.00068 Snack 5,00 orang 2,00 Kali 2,00 n/a Fix 20.000,00 400.000,00
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 3,00 orang 1,00 Kali 2,00 n/a Fix 45.000,00 270.000,00
dan Minuman
9.1.2.11.02.01.001.00068 Snack 3,00 orang 2,00 Kali 2,00 n/a Fix 20.000,00 240.000,00
1.530.000,00
JUMLAH 23.184.500,00
Total Variabel Cost 473.000,00
Total Fix Cost 22.711.500,00
Total Cost 23.184.500,00
HSAK 927.230,00
30
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : Dinas Pariwisata dan Kebudayaan
3 SUB- SUB KELOMPOK : Pelatihan dasar SDM Kepariwisataan bagi masyarakat, Guru dan Pelajar
4 ZONA WILAYAH SSH : Semua Wilayah Kabupaten Bandung
5 AKTIVITAS : Pelatihan Tatakelola Destinasi Pariwisata
DESKRIPSI AKTIVITAS : Pelatihan di Luar Kantor Pemda selama dua hari, sewa gedung, Narasumber Praktisi, Peserta Non PNS
6 SATUAN AKTIVITAS : Peserta
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Peserta Derivatif 1 Kelas Range 50 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
Pejabat Eselon II/yang
disetarakan (Non ASN Pemda)
9.1.2.24.01.01.001.00200 1,00 orang 2,00 jam 2,00 n/a Fix 1.000.000,00 4.000.000,00
Honorarium Narasumber/Praktisi
(pembahas)
9.1.2.24.01.01.001.00196 Narasumber Praktisi, 2,00 Orang 2,00 Jam 2,00 n/a Fix 900.000,00 7.200.000,00
Biaya Kediklatan, Uang Saku
9.1.2.23.01.01.001.01244 1,00 orang 1,00 Hari 2,00 n/a Var 150.000,00 300.000,00
Peserta Diklat
11.500.000,00
7.2 Bahan Material
9.1.2.06.02.01.001.00058 Fotocopy - F.4 1,00 Peserta 10,00 Lembar 1,00 n/a Var 300,00 3.000,00
Biaya Penjilidan - Ring Kawat, 1
1.1.7.01.03.01.014.00873 1,00 Dokumen 5,00 Buku 1,00 n/a Fix 12.300,00 61.500,00
warna, tebal <5cm
Cetak Spanduk, Bahan Flexy
1.1.7.01.03.03.007.01470 1,00 buah 5,00 Meter 1,00 n/a Fix 18.000,00 90.000,00
China
154.500,00
7.3 Peralatan/sewa
Sewa Ruang
Gedung/Rumah/Kantor
9.1.2.07.02.01.001.00179 1,00 Ruang 1,00 hari 2,00 n/a Fix 5.000.000,00 10.000.000,00
(Rapat/Pertemuan) Luar Lembaga
Pemerintah, Aula
10.000.000,00
Belanja Makan Dam
7.4
Minum
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 1,00 orang 1,00 Kali 2,00 n/a Var 45.000,00 90.000,00
dan Minuman
9.1.2.11.02.01.001.00068 Snack 1,00 orang 2,00 Kali 2,00 n/a Var 20.000,00 80.000,00
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 5,00 orang 1,00 Kali 2,00 n/a Fix 45.000,00 450.000,00
dan Minuman
9.1.2.11.02.01.001.00068 Snack 5,00 orang 2,00 Kali 2,00 n/a Fix 20.000,00 400.000,00
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 3,00 orang 1,00 Kali 2,00 n/a Fix 45.000,00 270.000,00
dan Minuman
9.1.2.11.02.01.001.00068 Snack 3,00 orang 2,00 Kali 2,00 n/a Fix 20.000,00 240.000,00
1.530.000,00
JUMLAH 23.184.500,00
Total Variabel Cost 473.000,00
Total Fix Cost 22.711.500,00
Total Cost 23.184.500,00
HSAK 927.230,00
31
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : Dinas Pariwisata dan Kebudayaan
3 SUB- SUB KELOMPOK : Standarisasi dan sertifikasi sumber daya manusia kesenian tradisional sesuai dengan kebutuhan dan tuntutan
4 ZONA WILAYAH SSH : Semua Wilayah Kabupaten Bandung
5 AKTIVITAS : Pelatihan Sumber Daya Manusia Kesenian Tradisional sesuai dengan kebutuhan dan Tuntutan
DESKRIPSI AKTIVITAS : Pelatihan di Luar Kantor Pemda selama dua hari, sewa gedung, Narasumber Praktisi, Peserta Non PNS
6 SATUAN AKTIVITAS : Peserta
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Peserta Derivatif 1 Kelas Range 50 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
Pejabat Eselon II/yang
disetarakan (Non ASN Pemda)
9.1.2.24.01.01.001.00200 1,00 orang 2,00 jam 2,00 n/a Fix 1.000.000,00 4.000.000,00
Honorarium Narasumber/Praktisi
(pembahas)
9.1.2.24.01.01.001.00196 Narasumber Praktisi, 2,00 Orang 2,00 Jam 2,00 n/a Fix 900.000,00 7.200.000,00
Biaya Kediklatan, Uang Saku
9.1.2.23.01.01.001.01244 1,00 orang 1,00 Hari 2,00 n/a Var 150.000,00 300.000,00
Peserta Diklat
11.500.000,00
7.2 Bahan Material
9.1.2.06.02.01.001.00058 Fotocopy - F.4 1,00 Peserta 10,00 Lembar 1,00 n/a Var 300,00 3.000,00
Biaya Penjilidan - Ring Kawat, 1
1.1.7.01.03.01.014.00873 1,00 Dokumen 5,00 Buku 1,00 n/a Fix 12.300,00 61.500,00
warna, tebal <5cm
Cetak Spanduk, Bahan Flexy
1.1.7.01.03.03.007.01470 1,00 buah 5,00 Meter 1,00 n/a Fix 18.000,00 90.000,00
China
Cetakan sertifikat peserta,
1.1.7.01.03.01.014.00932 1,00 Orang 1,00 Lembar 1,00 n/a Var 17.000,00 17.000,00
Sertifikat untuk peserta
171.500,00
7.3 Peralatan/sewa
Sewa Ruang
Gedung/Rumah/Kantor
9.1.2.07.02.01.001.00179 1,00 Ruang 1,00 hari 2,00 n/a Fix 5.000.000,00 10.000.000,00
(Rapat/Pertemuan) Luar Lembaga
Pemerintah, Aula
10.000.000,00
Belanja Makan Dan
7.4
Minum
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 1,00 orang 1,00 Kali 2,00 n/a Var 45.000,00 90.000,00
dan Minuman
9.1.2.11.02.01.001.00068 Snack 1,00 orang 2,00 Kali 2,00 n/a Var 20.000,00 80.000,00
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 5,00 orang 1,00 Kali 2,00 n/a Fix 45.000,00 450.000,00
dan Minuman
9.1.2.11.02.01.001.00068 Snack 5,00 orang 2,00 Kali 2,00 n/a Fix 20.000,00 400.000,00
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 3,00 orang 1,00 Kali 2,00 n/a Fix 45.000,00 270.000,00
dan Minuman
9.1.2.11.02.01.001.00068 Snack 3,00 orang 2,00 Kali 2,00 n/a Fix 20.000,00 240.000,00
1.530.000,00
JUMLAH 23.201.500,00
Total Variabel Cost 490.000,00
Total Fix Cost 22.711.500,00
Total Cost 23.201.500,00
HSAK 944.230,00
32
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : Dinas Pariwisata dan Kebudayaan
3 SUB- SUB KELOMPOK : Pemberian Penghargaan Kepada Pihak yang berprestasi atau berkontribusi Luar biasa sesuai dengan prestasi dan kontribusinya dalam pemajuan kebudayaan
Var /
NO KODE SIPD URAIAN PEKERJAAN Cost Driver 2 N/A Koef Derivatif 2 n/a Range SATUAN HARGA
Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
9.1.2.26.03.01.001.00545 Jasa Team Kesenian Tradisional 1,00 Hari 3,00 grup 1,00 n/a Fix 10.000.000,00 30.000.000,00
9.1.2.26.03.01.001.00581 Pembawa Acara Pagelaran 1,00 Hari 1,00 orang 1,00 n/a Fix 1.000.000,00 1.000.000,00
31.000.000,00
7.2 Bahan Material
1.1.7.01.03.03.007.01533 Spanduk 1,00 Hari 2,00 Buah 1,00 n/a Fix 330.000,00 660.000,00
9.1.2.06.03.01.001.04956 Foto, Foto Ukuran 3R 20,00 lembar 1,00 Kegiatan 1,00 n/a 2.500,00 50.000,00
1.3.2.05.02.06.065.00075 Riging (10 m x 12 m) 1,00 hari 40,00 meter2 1,00 n/a Fix 189.750,00 7.590.000,00
1.3.2.05.02.06.065.00068 Dekorasi Kain Rumbe 1,00 hari 20,00 meter 1,00 n/a Fix 50.000,00 1.000.000,00
1.3.2.05.02.06.065.00067 Cover Dinding 1,00 hari 10,00 meter 1,00 n/a Fix 30.000,00 300.000,00
9.600.000,00
7.3 Peralatan/sewa
9.1.2.10.01.01.001.00061 Beban sewa meja kursi Kursi Lipat 1,00 hari 50,00 Unit 1,00 n/a Fix 7.500,00 375.000,00
9.1.2.10.05.01.001.00056 Tenda Standar 1,00 hari 50,00 meter2 1,00 n/a Fix 37.969,00 1.898.450,00
Soundsystem dan Operator - 5.000
9.1.2.10.07.01.001.00065 1,00 hari 1,00 Unit 1,00 n/a Fix 5.000.000,00 5.000.000,00
Watt
9.1.2.10.04.01.001.00017 Generator 100 Kva 1,00 hari 1,00 Unit 1,00 n/a Fix 5.625.000,00 5.625.000,00
Jasa Peliputan Media
9.1.2.24.03.01.001.00563 4,00 Orang 1,00 Kegiatan 1,00 n/a Fix 250.000,00 1.000.000,00
(Cetak/Elektronik),
9.1.2.24.03.01.001.00567 Jasa Pengamanan Pagelaran 1,00 hari 15,00 Orang 1,00 n/a Fix 150.000,00 2.250.000,00
9.1.2.26.03.01.001.00544 Jasa Kebersihan Pagelaran 1,00 hari 15,00 Orang 1,00 n/a Fix 100.000,00 1.500.000,00
17.648.450,00
7.4 Belanja Makan Dan Minum
9.1.2.11.02.01.001.00068 Snack 1,00 Hari 50,00 Orang 1,00 Dus Fix 20.000,00 1.000.000,00
Makan/Nasi Dus Biaya Makanan dan
9.1.2.23.04.01.001.00021 1,00 Hari 10,00 Orang 1,00 Dus Fix 45.000,00 450.000,00
Minuman
9.1.2.11.02.01.001.00068 Snack 1,00 Hari 10,00 Orang 1,00 Dus Fix 20.000,00 200.000,00
3.900.000,00
JUMLAH 62.148.450,00
Total Variabel Cost -
Total Fix Cost 62.098.450,00
Total Cost 62.098.450,00
HSAK 62.098.450,00
Var /
NO KODE SIPD URAIAN PEKERJAAN Cost Driver 2 N/A Koef Derivatif 2 n/a Range SATUAN HARGA
Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
9.1.2.24.01.01.001.00196 Narasumber Praktisi, 2,00 orang 3,00 jam 1,00 Fix 900.000,00 5.400.000,00
Biaya Kediklatan, Uang Saku Peserta
9.1.2.23.01.01.001.01244 1,00 orang 1,00 hari 1,00 Var 150.000,00 150.000,00
Diklat
5.550.000,00
7.2 Bahan Material
1.3.2.16.01.03.001.00005 Tas Daur Ulang 1,00 orang 1,00 hari 1,00 Var 49.600,00 49.600,00
Block Note - Garis A5 148 X 210 mm
1.1.7.01.03.01.005.00256 1,00 orang 1,00 hari 1,00 Var 4.000,00 4.000,00
(50 lbr)
1.1.7.01.03.01.001.01084 Ballpoint - 0,5 Mm 1,00 orang 1,00 hari 1,00 Var 4.000,00 4.000,00
9.1.2.06.02.01.001.00058 Fotocopy - F.4 1,00 Orang 25,00 Lembar 1,00 Var 300,00 7.500,00
1.1.7.01.03.01.016.01110 Gunting Kertas Kecil 1,00 Orang 1,00 Buah 1,00 Var 7.500,00 7.500,00
1.1.7.01.03.01.010.00332 Lem Power Glue General 1,00 Orang 1,00 Buah 1,00 Var 5.000,00 5.000,00
1.1.7.01.03.01.010.00330 Lem Kertas Sedang 1,00 Orang 1,00 Buah 1,00 Var 17.500,00 17.500,00
9.1.2.01.09.01.001.05975 Kawat Hias 1,00 Orang 3,00 Meter 1,00 Var 600,00 1.800,00
9.1.2.01.09.01.001.06082 Peniti, 1,00 Orang 1,00 Lusin 1,00 Var 15.000,00 15.000,00
Alat Rajut Bahan Baku Bimtek
9.1.2.01.09.01.001.05793 1,00 Orang 1,00 Buah 1,00 Var 5.000,00 5.000,00
Persampahan
1.1.7.01.03.03.007.01470 Cetak Spanduk, Bahan Flexy China 1,00 Buah 6,00 meter 1,00 Fix 18.000,00 108.000,00
224.900,00
7.3 Peralatan/sewa
- - -
-
9.1.2.11.02.01.001.00068 Snack 1,00 orang 1,00 hari 1,00 Var 20.000,00 20.000,00
260.000,00
JUMLAH 6.034.900,00
Total Variabel Cost 331.900,00
Total Fix Cost 5.703.000,00
Total Cost 6.034.900,00
HSAK 445.960,00
33
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : Dinas Lingkungan Hidup
3 SUB- SUB KELOMPOK : Koordinasi, Sinkronisasi dan Pelaksanaan Pengendalian Emisi Gas Rumah Kaca, Mitigasi dan Adaptasi Perubahan Iklim
4 ZONA WILAYAH SSH : Semua Wilayah
5 AKTIVITAS : Bimbingan Teknis Konservasi Sumber Daya Air (KSDA)
Bimbingan Teknis Konservasi Sumber Daya Air (KSDA) dengan pembuatan Lubang Biopori/Lubang Cerdas Organik dengan sasaran kegiatan pada masyarakat
DESKRIPSI AKTIVITAS :
(musrenbang)
6 SATUAN AKTIVITAS : Peserta
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Peserta Derivatif 1 Kelas Range 40 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
9.1.2.24.01.01.001.00196 Narasumber Praktisi, 1,00 orang 2,00 Jam 1,00 Fix 900.000,00 1.800.000,00
1.800.000,00
7.2 Bahan Material
Bor Biopori ( Bahan Pipa Besi
Untuk Handel Dilapisi Karet
9.1.2.01.05.01.001.01356 Dengan Uk. 5/8" Panjang Total 1,00 buah 0,50 1,00 Var 300.000,00 150.000,00
120 Cm Panjang Mata Bor 20 Cm
Panjang Handle 50 Cm)
Tutup Lubang Biopori Fiber 10
9.1.2.01.05.01.001.01594 2,00 buah 1,00 1,00 Var 11.903,00 23.806,00
Cm
Block Note - Polos A6 105 X 148
1.1.7.01.03.01.005.00259 1,00 orang 1,00 Hari 1,00 Var 10.500,00 10.500,00
mm (50 lbr)
1.1.7.01.03.01.001.01089 Ballpoint - Boxy 0,5 1,00 orang 1,00 Hari 1,00 Var 10.000,00 10.000,00
9.1.2.06.02.01.001.00058 Fotocopy - F.4 1,00 orang 15,00 Lembar 1,00 Var 300,00 4.500,00
Cetak Spanduk, Bahan Flexy
1.1.7.01.03.03.007.01470 2,00 Buah 6,00 1,00 Fix 18.000,00 216.000,00
China
1.3.2.05.02.06.077.02931 Termos air 2,00 buah 1,00 Hari 1,00 Var 75.000,00 150.000,00
9.1.2.06.02.01.001.00058 Fotocopy - F.4 200,00 Lembar 1,00 1,00 Fix 300,00 60.000,00
624.806,00
7.3 Peralatan/sewa
- - -
-
Belanja Makan Dan
7.4
Minum
9.1.2.11.02.01.001.00068 Snack 1,00 orang 1,00 Hari 1,00 Var 20.000,00 20.000,00
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 1,00 orang 1,00 Hari 1,00 Var 45.000,00 45.000,00
dan Minuman
9.1.2.11.02.01.001.00068 Snack 6,00 orang hari 1,00 1,00 Fix 20.000,00 120.000,00
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 6,00 orang hari 1,00 1,00 Fix 45.000,00 270.000,00
dan Minuman
455.000,00
JUMLAH 2.879.806,00
Total Variabel Cost 413.806,00
Total Fix Cost 2.466.000,00
Total Cost 2.879.806,00
HSAK 475.456,00
HSAK Pembulatan 475.400,00
34
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : Dinas Lingkungan Hidup
3 SUB- SUB KELOMPOK : Pengisolasian Pencemaran dan/atau Kerusakan Lingkungan Hidup
4 ZONA WILAYAH SSH : Semua Wilayah
5 AKTIVITAS : Bimbingan Teknis Pengolahan Limbah Peternakan ( Rumah Budidaya Cacing)
DESKRIPSI AKTIVITAS : Kegiatan Bimbingan Teknis pengelolaan limbah peternakan sapi pada kelompok peternak
6 SATUAN AKTIVITAS : Kelompok
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Kelompok Derivatif 1 Kelas Range 2 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
9.1.2.24.01.01.001.00194 Narasumber Pakar, 2,00 orang 4,00 jam 1,00 Fix 1.700.000,00 13.600.000,00
Biaya Kediklatan, Uang Saku
9.1.2.23.01.01.001.01244 25,00 orang 2,00 hari 1,00 Var 150.000,00 7.500.000,00
Peserta Diklat
21.100.000,00
7.2 Bahan Material
1.1.7.01.03.01.001.01084 Ballpoint - 0,5 Mm 25,00 orang 1,00 Buah 1,00 Var 4.000,00 100.000,00
Block Note - Garis A5 148 X 210
1.1.7.01.03.01.005.00256 25,00 orang 1,00 Buku 1,00 Var 4.000,00 100.000,00
mm (50 lbr)
1.1.7.01.03.01.016.01197 Ziper Bag - (Clear Case) Folio 25,00 orang 1,00 buah 1,00 Var 10.500,00 262.500,00
Cetak Spanduk, Bahan Flexy
1.1.7.01.03.03.007.01470 6,00 meter 1,00 Kegiatan 1,00 Fix 18.000,00 108.000,00
China
1.3.2.08.03.04.034.00017 Bambu Gombong 45,00 Batang 1,00 Unit 1,00 Var 70.000,00 3.150.000,00
1.1.7.01.01.12.001.00350 Bambu Tali 43,00 Batang 1,00 Unit 1,00 Var 34.600,00 1.487.800,00
1.1.7.01.01.01.022.07860 Reng Bambu 20,00 Ikat 1,00 Unit 1,00 Var 35.000,00 700.000,00
9.1.2.01.09.01.001.06183 Tali Kur, Bahan Baku Pelatihan 8,00 Buah 1,00 Unit 1,00 Var 1.500,00 12.000,00
9.1.2.01.09.01.001.05973 Karung Kaps. 50Kg Plastik 43,00 Lembar 1,00 Unit 1,00 Var 22.250,00 956.750,00
1.1.7.01.01.12.001.00359 Cacing Lumbricus Rubellus 17,00 Kg 1,00 Unit 1,00 Var 50.000,00 850.000,00
1.1.7.01.01.12.001.00363 Esenia Poetida (Tiger) 17,00 Kg 1,00 Unit 1,00 Var 50.000,00 850.000,00
1.3.2.05.02.06.077.02612 Ember Sedang + Tutup Plastik 1,00 Buah 1,00 Unit 1,00 Var 70.000,00 70.000,00
9.1.2.01.09.01.001.06139 Sekop 1,6-2MM, 1,00 Buah 1,00 Unit 1,00 Var 40.500,00 40.500,00
Cangkul Material : besi Dimensi
1.3.2.04.01.01.003.00031 produk : 16 x 20 x 74 cm Berat : 3 1,00 Buah 1,00 Unit 1,00 Var 80.000,00 80.000,00
Kg
1.1.7.01.05.01.004.02338 Ayakan Besar, Bambu 1,00 Buah 1,00 Unit 1,00 Var 134.000,00 134.000,00
1.1.7.01.04.01.008.00193 Sarung tangan karet isi 50 buah 1,00 Box 1,00 Unit 1,00 Var 50.000,00 50.000,00
9.1.2.06.02.01.001.00058 Fotocopy - F.4 407,00 Lembar 1,00 Kegiatan 1,00 Fix 300,00 122.100,00
10.928.765,50
7.3 Peralatan/sewa
- - -
-
Belanja Makan Dan
7.4
Minum
9.1.2.11.02.01.001.00068 Snack 25,00 orang 2,00 hari 1,00 Var 20.000,00 1.000.000,00
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 25,00 orang 2,00 hari 1,00 Var 45.000,00 2.250.000,00
dan Minuman
3.250.000,00
JUMLAH 35.278.765,50
Total Variabel Cost 21.448.665,50
Total Fix Cost 13.830.100,00
Total Cost 35.278.765,50
HSAK 28.363.715,50
35
1 KELOMPOK : Dinas Lingkungan Hidup
2 SUB KELOMPOK : Koordinasi, Sinkronisasi dan Pelaksanaan Rehabilitasi
3 SUB- SUB KELOMPOK : Semua Wilayah
4 ZONA WILAYAH SSH : Dukungan Bantuan Pohon Multy Purpose Tree Species (MPTS) Kayu-kayuan
5 AKTIVITAS : Sosialisasi dan Penanaman Pohon Multy Purpose Tree Species (MPTS) Kayu-kayuan
DESKRIPSI AKTIVITAS : Kegiatan Dukungan Bantuan Pohon Multy Purpose Tree (MPTS) Kayu-kayuan di zona MPTS yang ditentukan dengan sasaran kegiatan pada masyarakat (musrenbang)
-
7.2 Bahan Material
1.3.2.05.02.06.077.02931 Termos air 2,00 buah 1,00 Hari 1,00 Var 75.000,00 150.000,00
Cetak Spanduk, Bahan Flexy
1.1.7.01.03.03.007.01470 1,00 buah 6,00 meter 1,00 Fix 18.000,00 108.000,00
China
258.000,00
7.3 Peralatan/sewa
- - -
-
Belanja Makan Dan
7.4
Minum
9.1.2.11.02.01.001.00068 Snack 1,00 orang 1,00 hari 1,00 Var 20.000,00 20.000,00
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 1,00 orang 1,00 hari 1,00 Var 45.000,00 45.000,00
dan Minuman
65.000,00
JUMLAH 323.000,00
Total Variabel Cost 215.000,00
Total Fix Cost 108.000,00
Total Cost 323.000,00
HSAK 217.160,00
36
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : Dinas Lingkungan Hidup
3 SUB- SUB KELOMPOK : Pengawasan Usaha dan/atau Kegiatan yang Izin Lingkungan Hidup, Izin PPLH yang Diterbitkan oleh Pemerintah Daerah Kabupaten/Kota
4 ZONA WILAYAH SSH : Semua Wilayah
5 AKTIVITAS : Sosialiasasi Pengendalian Pencemaran Lingkungan
DESKRIPSI AKTIVITAS : Kegiatan Sosialiasasi Pengendalian Pencemaran Lingkungan dengan sasaran kegiatan masyarakat (musrenbang)
6 SATUAN AKTIVITAS : Peserta
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Peserta Derivatif 1 Kelas Range 40 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
9.1.2.24.01.01.001.00196 Narasumber Praktisi, 2,00 orang 2,00 jam 1,00 Fix 900.000,00 3.600.000,00
Biaya Kediklatan, Uang Saku
9.1.2.23.01.01.001.01244 1,00 orang 1,00 hari 1,00 Var 150.000,00 150.000,00
Peserta Diklat
3.750.000,00
7.2 Bahan Material
Block Note - Polos A6 105 X 148
1.1.7.01.03.01.005.00259 1,00 orang 1,00 Hari 1,00 Var 10.500,00 10.500,00
mm (50 lbr)
1.1.7.01.03.01.001.01085 Ballpoint - 3 Warna 1,00 orang 1,00 Hari 1,00 Var 8.900,00 8.900,00
9.1.2.06.02.01.001.00058 Fotocopy - F.4 15,00 orang 1,00 Lembar 1,00 Var 300,00 4.500,00
Cetak Spanduk, Bahan Flexy
1.1.7.01.03.03.007.01470 2,00 Buah 6,00 Meter 1,00 Fix 18.000,00 216.000,00
China
9.1.2.06.02.01.001.00058 Fotocopy - F.4 400,00 lembar 1,00 1,00 Fix 300,00 120.000,00
359.900,00
7.3 Peralatan/sewa
- - -
-
Belanja Makan Dan
7.4
Minum
9.1.2.11.02.01.001.00068 Snack 1,00 orang 1,00 hari 1,00 Var 20.000,00 20.000,00
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 1,00 orang 1,00 hari 1,00 Var 45.000,00 45.000,00
dan Minuman
9.1.2.11.02.01.001.00068 Snack 4,00 orang 1,00 hari 1,00 Fix 20.000,00 80.000,00
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 4,00 orang 1,00 hari 1,00 Fix 45.000,00 180.000,00
dan Minuman
325.000,00
JUMLAH 4.434.900,00
Total Variabel Cost 238.900,00
Total Fix Cost 4.196.000,00
Total Cost 4.434.900,00
HSAK 343.800,00
1.1.7.01.01.11.002.00390 Benih ikan lele, 5-7 cm 250,00 Ekor 1,00 1,00 Var 700,00 175.000,00
1.1.7.01.01.02.005.01961 Media bioflok, 1,00 Paket 1,00 1,00 Var 5.000.000,00 5.000.000,00
1.1.7.01.01.11.001.00326 Ayam dewasa, usia lebih 1 bulan 30,00 Ekor 1,00 1,00 Var 50.000,00 1.500.000,00
9.1.2.01.09.01.001.05844 Bibit Magot (BSF) 10,00 Kg 1,00 1,00 Var 75.000,00 750.000,00
Roda Sampah Dari Plat Besi
9.1.2.01.05.01.001.01503 2,00 Unit 1,00 1,00 Var 3.600.000,00 7.200.000,00
Kapasitas 0,84 m3
Timbangan gantung, manual,
1.1.7.01.05.01.004.02509 1,00 Buah 1,00 1,00 Var 900.000,00 900.000,00
kapasitas 100-110 kg
1.1.7.01.01.01.022.07216 Green House 15,00 M2 1,00 1,00 Var 495.000,00 7.425.000,00
Bor Biopori ( Bahan Pipa Besi
Untuk Handel Dilapisi Karet
9.1.2.01.05.01.001.01356 Dengan Uk. 5/8" Panjang Total 5,00 Unit 1,00 1,00 Var 300.000,00 1.500.000,00
120 Cm Panjang Mata Bor 20 Cm
Panjang Handle 50 Cm)
9.1.2.01.05.01.001.01408 Karung Plastik 50,00 Buah 1,00 1,00 Var 12.000,00 600.000,00
32.979.500,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 32.979.500,00
Total Variabel Cost 32.979.500,00
Total Fix Cost -
Total Cost 32.979.500,00
HSAK 32.979.500,00
37
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : Dinas Lingkungan Hidup
3 SUB- SUB KELOMPOK : Koordinasi, Sinkronisasi dan Pelaksanaan Rehabilitasi
4 ZONA WILAYAH SSH : Semua Wilayah
5 AKTIVITAS : Pembuatan Persemaian
DESKRIPSI AKTIVITAS : Kegiatan pembuatan Persemaian untuk mendukung Gerakan Penanaman dengan sasaran kegiatan masyarakat (musrenbang)
6 SATUAN AKTIVITAS : Unit
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
unit Derivatif 1 Kelas Range 1 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
- - -
-
7.2 Bahan Material
Bibit Pohon sesuai dengan kondisi
geografis dan tanah (Mahoni,
1.1.7.01.01.08.002.00446 600,00 Buah 1,00 1,00 Var 7.000,00 4.200.000,00
Gamelina,Suren,Albaziah, dst),
ketinggian min 60 cm
1.3.2.04.01.02.009.00039 Polybag Plastik hitam 35,00 kg 1,00 1,00 Var 60.500,00 2.117.500,00
1.1.7.01.01.12.001.00350 Bambu Tali 100,00 batang 1,00 1,00 Var 34.600,00 3.460.000,00
1.1.7.02.02.06.001.00579 PVC Kelas AW 3/4", D. 26 mm 60,00 batang 4,00 1,00 Var 9.500,00 2.280.000,00
accesoreis PVC 2,00 lump 1,00 1,00 Var 3.325,00 6.650,00
1.1.7.01.02.07.002.00037 Selang air, plastik ukuran 3/4 1,50 Rol 1,00 1,00 Var 1.200.000,00 1.800.000,00
1.1.7.01.01.01.022.07727 Plastik Cor (Pet Murni) 20,00 meter 1,00 1,00 Var 25.000,00 500.000,00
1.1.7.01.01.02.005.02019 Pupuk, Kandang dari domba 580,00 kg 1,00 1,00 Var 600,00 348.000,00
1.1.7.01.02.07.002.00038 Tanah Top Soil 10,00 m3 1,00 1,00 Var 300.000,00 3.000.000,00
1.1.7.01.03.08.001.00184 Kabel Gulung 2x1,5 mm 1,00 m3 1,00 1,00 Var 333.500,00 333.500,00
1.1.7.01.01.12.001.00383 Sprinkler Taman Semprot Embun 6,00 buah 1,00 1,00 Var 51.000,00 306.000,00
Tangki Air Silinder (Kap = 800
Liter) Kap = 800 Liter, Dia =
1.1.7.02.02.06.001.00664 830mm, Tinggi = 1700mm, 1,00 buah 1,00 1,00 Var 2.100.000,00 2.100.000,00
Manhole 400mm, Fitting (Drain
3/4", I/O = 3/4")
Pompa Submersible (375 watt)
1.1.7.02.02.06.001.00535 375 watt , Hisap m; Dorong 43 m , 1,00 unit 1,00 1,00 Var 2.538.000,00 2.538.000,00
Debit Air : 2,4 m3/Jam
1.1.7.01.01.01.022.07470 Mesin Pompa tekan kap. 150 watt 1,00 Unit 1,00 1,00 Var 1.750.000,00 1.750.000,00
1.3.2.04.01.08.040.00007 Menara tangki air 1,00 unit 1,00 1,00 Var 4.000.000,00 4.000.000,00
Upah Kerja Harian Buruh/Tenaga
9.1.2.24.03.01.001.00699 180,00 HOK 1,00 1,00 Var 75.000,00 13.500.000,00
Kebun Demplot
49.974.150,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 49.974.150,00
Total Variabel Cost 49.974.150,00
Total Fix Cost -
Total Cost 49.974.150,00
HSAK 49.974.150,00
38
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : DINAS KETENAGAKERJAAN
3 SUB- SUB KELOMPOK : Perluasan Kesempatan Kerja
4 ZONA WILAYAH SSH : Semua Wilayah
5 AKTIVITAS : PENGOLAHAN HASIL PERTANIAN
DESKRIPSI AKTIVITAS : Kegiatan Bimbingan Teknis Ketenagakerjaan yang dilaksanakan oleh OPD bertempat di luar kantor, waktu pelaksanaan 8 (delapan) hari dengan jumlah 20 peserta
Var /
NO KODE SIPD URAIAN PEKERJAAN Cost Driver 2 N/A Koef Derivatif 2 n/a Range SATUAN HARGA
Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
9.1.2.24.01.01.001.00196 Narasumber Praktisi, 1,00 Orang 4,00 Jam 1,00 Hari Fix 900.000,00 3.600.000,00
Biaya Kediklatan, honorarium
9.1.2.23.01.01.001.01238 1,00 Orang 1,00 Hari 8,00 Hari Fix 100.000,00 800.000,00
Pengamat Kelas
Operasional Tenaga Rekrutmen
9.1.2.25.04.01.001.00848 2,00 Orang 3,00 Jam 1,00 Hari Fix 250.000,00 1.500.000,00
Peserta Pelatihan Ketenegakerjaan
Instruktur Teknis (Muda) Tenaga
Pengajar yang memiliki keterampilan
9.1.2.24.01.01.001.00188 2,00 Orang 8,00 Jam 5,00 Hari Fix 80.000,00 6.400.000,00
teknis level muda (Non PNS/Non ASN
Pemkab)
Instruktur Teknis (Madya) Tenaga
Pengajar yang memiliki keterampilan
9.1.2.24.01.01.001.00187 1,00 Orang 8,00 Jam 2,00 Hari Fix 100.000,00 1.600.000,00
teknis level madya (Non PNS/Non
ASN Pemkab)
Biaya Kediklatan, Uang Saku Peserta
9.1.2.23.01.01.001.01244 1,00 Peserta 8,00 Hari 1,00 N/A var 150.000,00 1.200.000,00
Diklat
15.250.000,00
7.2 Bahan Material
Bakerine Plus, Bahan Pelatihan Tata
9.1.2.01.09.01.001.05829 1,00 Peserta 0,10 kg 1,00 N/A var 76.300,00 7.630,00
Boga,
9.1.2.02.06.01.001.02612 Bawang Bombay 1,00 Peserta 0,25 kg 1,00 N/A var 35.000,00 8.750,00
9.1.2.02.06.01.001.02613 Bawang Daun 1,00 Peserta 0,20 kg 1,00 N/A var 25.000,00 5.000,00
9.1.2.02.06.01.001.02615 Bawang Merah 1,00 Peserta 0,50 kg 1,00 N/A var 38.000,00 19.000,00
9.1.2.02.06.01.001.02616 Bawang Putih 1,00 Peserta 0,25 kg 1,00 N/A var 38.500,00 9.625,00
9.1.2.02.06.01.001.02629 Bihun 1,00 Peserta 0,50 bungkus 1,00 N/A var 33.000,00 16.500,00
9.1.2.01.09.01.001.05856 Bumbu Bakso 1,00 Peserta 0,20 kg 1,00 N/A var 3.500,00 700,00
9.1.2.01.09.01.001.05857 Bumbu Dapur 1,00 Peserta 0,20 kg 1,00 N/A var 25.300,00 5.060,00
9.1.2.01.09.01.001.05858 Bumbu Spagethi 1,00 Peserta 0,60 Kantong 1,00 N/A var 40.200,00 24.120,00
9.1.2.02.06.01.001.02657 Cabe Merah 1,00 Peserta 0,25 kg 1,00 N/A var 78.900,00 19.725,00
9.1.2.01.09.01.001.05859 Cabe Paprika 1,00 Peserta 0,25 kg 1,00 N/A var 55.300,00 13.825,00
9.1.2.01.09.01.001.05860 Cabe Rawit Merah 1,00 Peserta 0,25 kg 1,00 N/A var 43.100,00 10.775,00
9.1.2.01.09.01.001.05867 Coklat Blok, 1,00 Peserta 0,20 kg 1,00 N/A var 48.000,00 9.600,00
9.1.2.01.09.01.001.05876 Daging Ayam Fillet 1,00 Peserta 0,60 kg 1,00 N/A var 52.200,00 31.320,00
Daging Iga, Sapi muda, segar, bersih,
9.1.2.02.06.01.001.02676 1,00 Peserta 0,60 kg 1,00 N/A var 120.000,00 72.000,00
sedikit lemak
9.1.2.01.09.01.001.05877 Daun Jeruk, 1,00 Peserta 0,20 Ons 1,00 N/A var 7.500,00 1.500,00
9.1.2.01.09.01.001.05880 Dendeng/Krewetan 1,00 Peserta 0,25 kg 1,00 N/A var 100.500,00 25.125,00
9.1.2.01.09.01.001.06189 Tauge, 1,00 Peserta 0,10 kg 1,00 N/A var 6.500,00 650,00
9.1.2.01.09.01.001.05895 Garam, Bahan Pelatihan Tata Boga, 1,00 Peserta 0,10 Pak 1,00 N/A var 56.300,00 5.630,00
9.1.2.02.06.01.001.02737 Gula Merah 1,00 Peserta 0,40 kg 1,00 N/A var 29.700,00 11.880,00
9.1.2.02.06.01.001.02739 Gula Pasir 1,00 Peserta 0,50 kg 1,00 N/A var 21.500,00 10.750,00
9.1.2.01.09.01.001.05927 Ikan Tuna 150 gr, 1,00 Peserta 0,60 kotak 1,00 N/A var 80.500,00 48.300,00
9.1.2.01.09.01.001.05936 Jeruk Sayur (Purut), 1,00 Peserta 0,05 kg 1,00 N/A var 7.000,00 350,00
9.1.2.01.09.01.001.05939 Kacang Tanah, 1,00 Peserta 0,30 kg 1,00 N/A var 28.000,00 8.400,00
9.1.2.02.06.01.001.02817 Kecap 275 ml 1,00 Peserta 0,20 Botol 1,00 N/A var 24.000,00 4.800,00
9.1.2.01.09.01.001.05982 Keju, 1,00 Peserta 0,70 kg 1,00 N/A var 102.000,00 71.400,00
9.1.2.01.09.01.001.06002 Kulit Pangsit, 1,00 Peserta 0,20 kg 1,00 N/A var 22.750,00 4.550,00
9.1.2.01.09.01.001.06006 Lada, 1,00 Peserta 0,50 Renceng 1,00 N/A var 13.000,00 6.500,00
9.1.2.01.09.01.001.06016 Lemak Sapi, 1,00 Peserta 0,25 kg 1,00 N/A var 52.500,00 13.125,00
9.1.2.01.09.01.001.06028 Mayonaise, 1,00 Peserta 0,60 bungkus 1,00 N/A var 23.750,00 14.250,00
9.1.2.01.09.01.001.06029 Meisis Berwarna, 1,00 Peserta 0,20 kg 1,00 N/A var 18.000,00 3.600,00
9.1.2.01.09.01.001.06030 Meisis Coklat, 1,00 Peserta 0,20 kg 1,00 N/A var 18.000,00 3.600,00
9.1.2.01.09.01.001.06033 Mentega BB, 1,00 Peserta 0,30 kg 1,00 N/A var 22.200,00 6.660,00
9.1.2.01.09.01.001.06034 Mentega Putih, 1,00 Peserta 0,50 kg 1,00 N/A var 22.000,00 11.000,00
9.1.2.01.09.01.001.06036 Mie Ayam, 1,00 Peserta 0,30 kg 1,00 N/A var 8.800,00 2.640,00
9.1.2.01.09.01.001.06037 Mie Telur, 1,00 Peserta 0,30 Bal 1,00 N/A var 3.250,00 975,00
9.1.2.01.09.01.001.06039 Minyak Goreng, 1,00 Peserta 0,60 Liter 1,00 N/A var 14.200,00 8.520,00
9.1.2.01.09.01.001.06080 Pengenyal, 1,00 Peserta 0,20 Sachet 1,00 N/A var 4.700,00 940,00
9.1.2.01.09.01.001.06087 Pisang Raja Cere, 1,00 Peserta 0,50 kg 1,00 N/A var 12.000,00 6.000,00
9.1.2.01.09.01.001.06084 Penyedap Rasa 1,00 Peserta 0,10 kg 1,00 N/A var 50.300,00 5.030,00
9.1.2.01.09.01.001.06123 Saledri, 1,00 Peserta 0,25 kg 1,00 N/A var 25.200,00 6.300,00
9.1.2.01.09.01.001.06127 Saos, 1,00 Peserta 0,30 Botol 1,00 N/A var 10.800,00 3.240,00
9.1.2.01.09.01.001.06126 Saos tomat uk 335 ml, 1,00 Peserta 0,50 Botol 1,00 N/A var 10.800,00 5.400,00
9.1.2.01.09.01.001.06143 Selai Coklat, 1,00 Peserta 2,00 gram 1,00 N/A var 12.000,00 24.000,00
9.1.2.01.09.01.001.06166 Sosin, 1,00 Peserta 0,30 kg 1,00 N/A var 8.200,00 2.460,00
9.1.2.01.09.01.001.06174 Susu Bubuk, 1,00 Peserta 0,30 kg 1,00 N/A var 22.500,00 6.750,00
9.1.2.01.09.01.001.06189 Tauge, 1,00 Peserta 0,30 kg 1,00 N/A var 6.500,00 1.950,00
9.1.2.01.09.01.001.06193 Telur Ayam, 1,00 Peserta 0,60 kg 1,00 N/A var 28.800,00 17.280,00
9.1.2.02.06.01.001.03076 Tepung Tapioka 1,00 Peserta 0,60 kg 1,00 N/A var 13.000,00 7.800,00
9.1.2.02.06.01.001.03079 Tepung Terigu 1,00 Peserta 0,50 kg 1,00 N/A var 14.000,00 7.000,00
9.1.2.01.09.01.001.06213 Tomat, Bahan Pelatihan Tata Boga, 1,00 Peserta 0,50 kg 1,00 N/A var 8.500,00 4.250,00
9.1.2.01.09.01.001.06222 Tulang Lutut, 1,00 Peserta 0,25 Kaki 1,00 N/A var 35.000,00 8.750,00
Urat Sapi, Bahan Pelatihan Tata
9.1.2.01.09.01.001.06224 1,00 Peserta 0,25 kg 1,00 N/A var 60.750,00 15.187,50
Boga,
9.1.2.01.09.01.001.06226 Vetsin, 1,00 Peserta 0,10 Pak 1,00 N/A var 99.900,00 9.990,00
9.1.2.01.09.01.001.05831 Baki Plastik/melamin, Bahan Plastik 1,00 Peserta 0,60 pcs 1,00 N/A var 56.000,00 33.600,00
9.1.2.01.09.01.001.06093 Plastik Kemasan Tebal 10 Ln (1 kg), 1,00 Peserta 0,10 kg 1,00 N/A var 44.250,00 4.425,00
9.1.2.01.09.01.001.06094 Plastik Kotak Kemasan, 1,00 Peserta 1,20 pcs 1,00 N/A var 3.700,00 4.440,00
1.3.2.05.02.06.077.02827 Roler Kayu 1,00 Peserta 0,20 pcs 1,00 N/A var 25.000,00 5.000,00
39
9.1.2.01.09.01.001.06128 Saringan Mie Ayam, 1,00 Peserta 0,20 pcs 1,00 N/A var 52.800,00 10.560,00
9.1.2.01.09.01.001.06129 Saringan Mie Kocok, 1,00 Peserta 0,20 pcs 1,00 N/A var 32.550,00 6.510,00
9.1.2.01.09.01.001.06130 Saringan Minyak Kelapa, 1,00 Peserta 0,20 pcs 1,00 N/A var 42.500,00 8.500,00
9.1.2.01.09.01.001.06149 Sendok Kayu, 1,00 Peserta 0,20 pcs 1,00 N/A var 11.000,00 2.200,00
9.1.2.01.09.01.001.06151 Sendok, Sendok Makan 1,00 Peserta 0,30 lusin 1,00 N/A var 77.000,00 23.100,00
9.1.2.01.09.01.001.06150 Sendok Sayur, 1,00 Peserta 0,30 pcs 1,00 N/A var 24.000,00 7.200,00
9.1.2.01.09.01.001.06168 Spatula, 1,00 Peserta 0,20 pcs 1,00 N/A var 36.500,00 7.300,00
9.1.2.01.09.01.001.06169 Spon Pencuci Piring, 1,00 Peserta 0,50 buah 1,00 N/A var 12.500,00 6.250,00
9.1.2.01.09.01.001.06172 Sumpit Mie Ayam, 1,00 Peserta 0,20 Pax 1,00 N/A var 26.000,00 5.200,00
9.1.2.01.09.01.001.06181 Talenan, 1,00 Peserta 0,50 pcs 1,00 N/A var 20.000,00 10.000,00
Ulekan Kayu, Bahan Pelatihan Tata
9.1.2.01.09.01.001.06223 1,00 Peserta 0,10 set 1,00 N/A var 45.000,00 4.500,00
Boga,
9.1.2.01.09.01.001.05848 Blender, Bahan Kaca 1,00 Peserta 0,10 buah 1,00 N/A var 1.200.000,00 120.000,00
Buleng / Panci Bakso, Bahan
9.1.2.01.09.01.001.05855 1,00 Peserta 0,10 pcs 1,00 N/A var 546.000,00 54.600,00
Aluminium
Grobak Bakso / Mie, Bahan
9.1.2.01.09.01.001.05908 1,00 Peserta 0,10 unit 1,00 N/A var 3.294.000,00 329.400,00
aluminium, roda 3, ukuran 0,9 x 2 m
Impuls Sealer Plastik, Kap 30,300
9.1.2.01.09.01.001.05928 1,00 Peserta 0,50 pcs 1,00 N/A var 194.000,00 97.000,00
watt, 220 V, 50/60 Hz
Kompor Semawar, Bahan Pelatihan
9.1.2.01.09.01.001.05993 1,00 Peserta 0,10 unit 1,00 N/A var 367.000,00 36.700,00
Tata Boga,
9.1.2.01.09.01.001.06031 Meja Dudukan Kompor, 1,00 Peserta 0,10 unit 1,00 N/A var 615.000,00 61.500,00
9.1.2.01.09.01.001.06050 Mixer, 1,00 Peserta 0,30 set 1,00 N/A var 485.000,00 145.500,00
9.1.2.01.09.01.001.06061 Oven, 1,00 Peserta 0,10 pcs 1,00 N/A var 680.000,00 68.000,00
9.1.2.01.09.01.001.06071 Panci Alumunium, 1,00 Peserta 0,20 pcs 1,00 N/A var 240.000,00 48.000,00
9.1.2.01.09.01.001.06113 Regulator, 1,00 Peserta 0,10 set 1,00 N/A var 200.000,00 20.000,00
9.1.2.01.09.01.001.06161 Serokan Penggorengan, 1,00 Peserta 0,10 pcs 1,00 N/A var 332.250,00 33.225,00
9.1.2.01.09.01.001.06178 Susuk stenless steel, 1,00 Peserta 0,10 pcs 1,00 N/A var 330.800,00 33.080,00
9.1.2.01.09.01.001.06180 Tabung Gas dan Selang Regulator, 1,00 Peserta 0,10 set 1,00 N/A var 350.000,00 35.000,00
9.1.2.01.09.01.001.06206 Timbangan Duduk 20 Kg 1,00 Peserta 0,10 unit 1,00 N/A var 165.000,00 16.500,00
9.1.2.01.09.01.001.06229 Wajan, 1,00 Peserta 0,10 pcs 1,00 N/A var 300.000,00 30.000,00
9.1.2.01.09.01.001.06083 Pensil 2B 1,00 Peserta 1,00 buah 1,00 N/A var 5.000,00 5.000,00
Block Note - Garis A6 105 X 148 mm
1.1.7.01.03.01.005.00257 1,00 Peserta 1,00 buku 1,00 N/A var 33.000,00 33.000,00
(50 lbr)
1.1.7.01.03.01.016.01133 Name Tag - Plastik 1,00 Peserta 1,00 buah 1,00 N/A var 7.300,00 7.300,00
1.1.7.01.03.01.006.00360 Map Plastik Kancing 1,00 Peserta 1,00 buah 1,00 N/A var 12.000,00 12.000,00
1.1.7.01.03.01.001.01096 Ballpoint - Pen Stand 1,00 Peserta 1,00 pcs 1,00 N/A var 10.000,00 10.000,00
1.1.7.01.03.03.007.01321 Cetak Buku Modul 1,00 Peserta 3,00 modul 1,00 N/A var 25.000,00 75.000,00
9.1.2.06.03.01.001.04826 Cetak Sertifikat 1,00 Peserta 1,00 lembar 1,00 N/A var 10.000,00 10.000,00
1.1.7.01.03.03.007.01470 Cetak Spanduk, Bahan Flexy China 5,00 meter 1,00 Keg 1,00 N/A Fix 18.000,00 90.000,00
2.468.039,50
7.3 Peralatan/sewa
2.000.000,00
40
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : DINAS KETENAGAKERJAAN
3 SUB- SUB KELOMPOK : Perluasan Kesempatan Kerja
4 ZONA WILAYAH SSH : Semua Wilayah
5 AKTIVITAS : KONVEKSI
DESKRIPSI AKTIVITAS : Kegiatan Bimbingan Teknis Ketenagakerjaan yang dilaksanakan oleh OPD bertempat di luar kantor, waktu pelaksanaan 8 (delapan) hari dengan jumlah 20 peserta
9.1.2.01.09.01.001.05838 Benang Obras 1,00 Peserta 0,50 Gulung 1,00 N/A var 33.000,00 16.500,00
9.1.2.01.09.01.001.05839 Benang Sulam 1,00 Peserta 0,50 Ikat 1,00 N/A var 1.800,00 900,00
9.1.2.01.09.01.001.05847 Bisban 1,00 Peserta 0,10 buah 1,00 N/A var 18.000,00 1.800,00
9.1.2.01.09.01.001.05911 Gunting Kain, Camel 1,00 Peserta 0,50 buah 1,00 N/A var 100.000,00 50.000,00
1.1.7.01.01.12.001.00365 Jarum Jelujur 1,00 Peserta 0,50 buah 1,00 N/A var 4.100,00 2.050,00
9.1.2.01.09.01.001.05933 Jarum Mesin Jahit 1,00 Peserta 0,20 pak 1,00 N/A var 50.000,00 10.000,00
9.1.2.01.09.01.001.05934 Jarum Pentul 1,00 Peserta 0,10 pak 1,00 N/A var 15.000,00 1.500,00
9.1.2.01.09.01.001.05941 Kain Katun 1,00 Peserta 10,00 meter 1,00 N/A var 36.000,00 360.000,00
9.1.2.01.09.01.001.05949 Kancing Cetet 1,00 Peserta 0,60 lusin 1,00 N/A var 25.000,00 15.000,00
9.1.2.01.09.01.001.05950 Kancing Kain Besar 1,00 Peserta 0,40 lusin 1,00 N/A var 25.000,00 10.000,00
9.1.2.01.09.01.001.05951 Kancing Kain Kecil 1,00 Peserta 0,40 lusin 1,00 N/A var 23.000,00 9.200,00
9.1.2.01.09.01.001.05953 Kancing kemeja 1,00 Peserta 0,10 pak 1,00 N/A var 35.000,00 3.500,00
Kapur Jahit Korea Berbagai
9.1.2.01.09.01.001.05962 1,00 Peserta 0,10 pak 1,00 N/A var 100.000,00 10.000,00
Warna
9.1.2.01.09.01.001.05963 Kapur Kain 1,00 Peserta 0,10 pak 1,00 N/A var 25.000,00 2.500,00
9.1.2.01.09.01.001.05985 Kertas Karton Jahit 1,00 Peserta 0,20 lembar 1,00 N/A var 2.200,00 440,00
9.1.2.01.09.01.001.05987 Kertas Pola, 1,00 Peserta 0,40 lembar 1,00 N/A var 1.500,00 600,00
9.1.2.01.09.01.001.06013 Lem kertas Besar, 1,00 Peserta 0,20 pcs 1,00 N/A var 25.000,00 5.000,00
1.3.2.07.02.05.025.18829 Masker N 95, 1,00 Peserta 8,00 lembar 1,00 N/A var 7.814,00 62.512,00
9.1.2.01.09.01.001.06032 Meniquen, 1,00 Peserta 0,20 buah 1,00 N/A var 35.000,00 7.000,00
9.1.2.01.09.01.001.06035 Meteran Kain, 1,00 Peserta 0,30 buah 1,00 N/A var 5.000,00 1.500,00
9.1.2.01.09.01.001.06045 Minyak Mesin, 1,00 Peserta 0,10 liter 1,00 N/A var 30.000,00 3.000,00
9.1.2.01.09.01.001.06048 Mistar Kayu 1 M, 1,00 Peserta 0,10 buah 1,00 N/A var 11.000,00 1.100,00
9.1.2.01.09.01.001.06067 Palet, 1,00 Peserta 1,00 buah 1,00 N/A var 2.000,00 2.000,00
9.1.2.01.09.01.001.06069 Pamidangan, 1,00 Peserta 0,20 buah 1,00 N/A var 33.000,00 6.600,00
9.1.2.01.09.01.001.06078 Pencil Warna, 1,00 Peserta 0,50 set 1,00 N/A var 110.000,00 55.000,00
9.1.2.01.09.01.001.06079 Pendedel, 1,00 Peserta 0,40 buah 1,00 N/A var 25.000,00 10.000,00
9.1.2.01.09.01.001.06081 Penggaris Pola, 1,00 Peserta 0,20 set 1,00 N/A var 15.000,00 3.000,00
9.1.2.01.09.01.001.06082 Peniti, 1,00 Peserta 0,20 lusin 1,00 N/A var 15.000,00 3.000,00
9.1.2.01.09.01.001.06088 Pita, 1,00 Peserta 0,10 Roll 1,00 N/A var 26.000,00 2.600,00
9.1.2.01.09.01.001.06104 Raderivatif, 1,00 Peserta 0,10 buah 1,00 N/A var 5.000,00 500,00
9.1.2.01.09.01.001.06115 Resleting, 1,00 Peserta 0,25 buah 1,00 N/A var 20.000,00 5.000,00
9.1.2.01.09.01.001.06164 Skoci, 1,00 Peserta 0,50 buah 1,00 N/A var 15.000,00 7.500,00
1.1.7.01.05.01.004.02334 Alat Lobang kancing 1,00 Peserta 0,05 unit 1,00 N/A var 935.000,00 46.750,00
1.3.2.05.01.04.022.00006 Box/kontainer 1,00 Peserta 0,10 buah 1,00 N/A var 300.000,00 30.000,00
1.1.7.01.05.01.004.02402 Mesin Cutting Kain 1,00 Peserta 0,10 buah 1,00 N/A var 2.750.000,00 275.000,00
1.1.7.01.05.01.004.02408 Mesin Jahit Listrik 1,00 Peserta 0,20 buah 1,00 N/A var 3.386.000,00 677.200,00
1.1.7.01.05.01.004.02410 Mesin Obras 5 Benang 1,00 Peserta 0,10 buah 1,00 N/A var 6.600.000,00 660.000,00
9.1.2.01.09.01.001.06055 Obeng( 1 set), 1,00 Peserta 0,10 set 1,00 N/A var 205.000,00 20.500,00
41
9.1.2.01.09.01.001.06083 Pensil 2B 1,00 Peserta 1,00 buah 1,00 N/A var 5.000,00 5.000,00
Block Note - Garis A6 105 X 148
1.1.7.01.03.01.005.00257 1,00 Peserta 1,00 buku 1,00 N/A var 33.000,00 33.000,00
mm (50 lbr)
1.1.7.01.03.01.016.01133 Name Tag - Plastik 1,00 Peserta 1,00 buah 1,00 N/A var 7.300,00 7.300,00
1.1.7.01.03.01.006.00360 Map Plastik Kancing 1,00 Peserta 1,00 buah 1,00 N/A var 12.000,00 12.000,00
1.1.7.01.03.01.001.01096 Ballpoint - Pen Stand 1,00 Peserta 1,00 pcs 1,00 N/A var 10.000,00 10.000,00
1.1.7.01.03.03.007.01321 Cetak Buku Modul 1,00 Peserta 3,00 modul 1,00 N/A var 25.000,00 75.000,00
9.1.2.06.03.01.001.04826 Cetak Sertifikat 1,00 Peserta 1,00 lembar 1,00 N/A var 10.000,00 10.000,00
Cetak Spanduk, Bahan Flexy
1.1.7.01.03.03.007.01470 5,00 meter 1,00 Keg 1,00 N/A Fix 18.000,00 90.000,00
China
2.633.552,00
7.3 Peralatan/sewa
Beban sewa gedung/
9.1.2.07.02.01.001.00137 kantor/tempat Sewa 1,00 Gedung 1,00 Keg 1,00 N/A Fix 2.000.000,00 2.000.000,00
Gedung/Aula
2.000.000,00
Belanja Makan Dan
7.4
Minum
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 1,00 Peserta 1,00 OH 8,00 Hari var 45.000,00 360.000,00
dan Minuman
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 3,00 Orang 1,00 OH 8,00 Hari Fix 45.000,00 1.080.000,00
dan Minuman
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 2,00 Orang 1,00 OH 8,00 Hari Fix 45.000,00 720.000,00
dan Minuman
9.1.2.11.02.01.001.00068 Snack 30,00 Peserta 1,00 OH 1,00 N/A Fix 20.000,00 600.000,00
9.1.2.11.02.01.001.00068 Snack 1,00 Peserta 1,00 OH 8,00 Hari var 20.000,00 160.000,00
9.1.2.11.02.01.001.00068 Snack 3,00 Orang 1,00 OH 8,00 Hari Fix 20.000,00 480.000,00
9.1.2.11.02.01.001.00068 Snack 2,00 Orang 1,00 OH 8,00 Hari Fix 20.000,00 320.000,00
3.720.000,00
JUMLAH 23.603.552,00
Total Variabel Cost 4.413.552,00
Total Fix Cost 19.190.000,00
Total Cost 23.603.552,00
HSAK 5.373.052,00
42
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : DINAS KETENAGAKERJAAN
3 SUB- SUB KELOMPOK : Perluasan Kesempatan Kerja
4 ZONA WILAYAH SSH : Semua Wilayah
5 AKTIVITAS : PENGOLAHAN SAMPAH PLASTIK
DESKRIPSI AKTIVITAS : Kegiatan Bimbingan Teknis Ketenagakerjaan yang dilaksanakan oleh OPD bertempat di luar kantor, waktu pelaksanaan 8 (delapan) hari dengan jumlah 20 peserta
6 SATUAN AKTIVITAS : Peserta
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Peserta Derivatif 1 Kelas Range 20 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
9.1.2.24.01.01.001.00196 Narasumber Praktisi, 1,00 Orang 4,00 Jam 1,00 Hari Fix 900.000,00 3.600.000,00
Biaya Kediklatan, honorarium
9.1.2.23.01.01.001.01238 1,00 Orang 1,00 Hari 8,00 Hari Fix 100.000,00 800.000,00
Pengamat Kelas
Operasional Tenaga Rekrutmen
9.1.2.25.04.01.001.00848 2,00 Orang 3,00 Jam 1,00 Hari Fix 250.000,00 1.500.000,00
Peserta Pelatihan Ketenegakerjaan
Instruktur Teknis (Muda) Tenaga
Pengajar yang memiliki
9.1.2.24.01.01.001.00188 2,00 Orang 8,00 Jam 5,00 Hari Fix 80.000,00 6.400.000,00
keterampilan teknis level muda
(Non PNS/Non ASN Pemkab)
Instruktur Teknis (Madya) Tenaga
Pengajar yang memiliki
9.1.2.24.01.01.001.00187 1,00 Orang 8,00 Jam 2,00 Hari Fix 100.000,00 1.600.000,00
keterampilan teknis level madya
(Non PNS/Non ASN Pemkab)
Biaya Kediklatan, Uang Saku
9.1.2.23.01.01.001.01244 1,00 Peserta 8,00 Hari 1,00 N/A var 150.000,00 1.200.000,00
Peserta Diklat
Tes Kesehatan Bimtek
Ketenagakerjaan, Tes Kesehatan,
9.1.2.03.12.01.001.00620 1,00 Peserta 1,00 Orang 1,00 N/A var 150.000,00 150.000,00
Rapid Test Virus Corona (Covid-
19)
15.250.000,00
7.2 Bahan Material
9.1.2.01.09.01.001.05973 Karung Kaps. 50Kg Plastik 1,00 Peserta 1,00 lembar 1,00 N/A var 22.250,00 22.250,00
9.1.2.01.09.01.001.06018 Limbah plastik, 1,00 Peserta 5,00 kg 1,00 N/A var 7.800,00 39.000,00
1.3.2.07.02.05.025.18829 Masker N 95, 1,00 Peserta 8,00 lembar 1,00 N/A var 7.814,00 62.512,00
9.1.2.01.09.01.001.06074 Pasir Silika, 1,00 Peserta 0,50 kg 1,00 N/A var 12.500,00 6.250,00
1.1.7.01.01.04.006.01008 Pertalite - 1,00 Peserta 2,50 liter 1,00 N/A var 8.100,00 20.250,00
9.1.2.01.09.01.001.06131 Sarung Tangan Kain, 1,00 Peserta 1,00 pasang 1,00 N/A var 9.999,00 9.999,00
9.1.2.01.09.01.001.06152 Sepatu Boot, 1,00 Peserta 1,00 pasang 1,00 N/A var 45.000,00 45.000,00
9.1.2.01.09.01.001.06207 Timbangan Gantung 1,00 Peserta 0,05 buah 1,00 N/A var 55.000,00 2.750,00
Timbangan Gantung Manual
9.1.2.01.09.01.001.06208 1,00 Peserta 0,10 buah 1,00 N/A var 22.700,00 2.270,00
Pocket
9.1.2.01.09.01.001.05906 Golok Ukuran Besar, 1,00 Peserta 0,10 buah 1,00 N/A var 190.000,00 19.000,00
1.1.7.01.05.01.004.02401 Mesin Cetakan 1,00 Peserta 0,05 unit 1,00 N/A var 3.300.000,00 165.000,00
1.1.7.01.05.01.004.02413 Mesin Pelebur 1,00 Peserta 0,05 unit 1,00 N/A var 25.300.000,00 1.265.000,00
1.1.7.01.05.01.004.02415 Mesin Pencacah Plastik 1,00 Peserta 0,05 unit 1,00 N/A var 13.750.000,00 687.500,00
9.1.2.01.09.01.001.06199 Terpal 4x5 m 1,00 Peserta 0,20 Roll 1,00 N/A var 101.000,00 20.200,00
9.1.2.01.09.01.001.06083 Pensil 2B 1,00 Peserta 1,00 buah 1,00 N/A var 5.000,00 5.000,00
Block Note - Garis A6 105 X 148
1.1.7.01.03.01.005.00257 1,00 Peserta 1,00 buku 1,00 N/A var 33.000,00 33.000,00
mm (50 lbr)
1.1.7.01.03.01.016.01133 Name Tag - Plastik 1,00 Peserta 1,00 buah 1,00 N/A var 7.300,00 7.300,00
1.1.7.01.03.01.006.00360 Map Plastik Kancing 1,00 Peserta 1,00 buah 1,00 N/A var 12.000,00 12.000,00
1.1.7.01.03.01.001.01096 Ballpoint - Pen Stand 1,00 Peserta 1,00 pcs 1,00 N/A var 10.000,00 10.000,00
1.1.7.01.03.03.007.01321 Cetak Buku Modul 1,00 Peserta 3,00 modul 1,00 N/A var 25.000,00 75.000,00
9.1.2.06.03.01.001.04826 Cetak Sertifikat 1,00 Peserta 1,00 lembar 1,00 N/A var 10.000,00 10.000,00
Cetak Spanduk, Bahan Flexy
1.1.7.01.03.03.007.01470 5,00 meter 1,00 Keg 1,00 N/A Fix 18.000,00 90.000,00
China
2.618.281,00
7.3 Peralatan/sewa
Beban sewa gedung/
9.1.2.07.02.01.001.00137 kantor/tempat Sewa 1,00 Gedung 1,00 Keg 1,00 N/A Fix 2.000.000,00 2.000.000,00
Gedung/Aula
2.000.000,00
Belanja Makan Dan
7.4
Minum
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 1,00 Peserta 1,00 OH 8,00 Hari var 45.000,00 360.000,00
dan Minuman
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 3,00 Orang 1,00 OH 8,00 Hari Fix 45.000,00 1.080.000,00
dan Minuman
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 2,00 Orang 1,00 OH 8,00 Hari Fix 45.000,00 720.000,00
dan Minuman
9.1.2.11.02.01.001.00068 Snack 30,00 Peserta 1,00 OH 1,00 N/A Fix 20.000,00 600.000,00
9.1.2.11.02.01.001.00068 Snack 1,00 Peserta 1,00 OH 8,00 Hari var 20.000,00 160.000,00
9.1.2.11.02.01.001.00068 Snack 3,00 Orang 1,00 OH 8,00 Hari Fix 20.000,00 480.000,00
9.1.2.11.02.01.001.00068 Snack 2,00 Orang 1,00 OH 8,00 Hari Fix 20.000,00 320.000,00
3.720.000,00
JUMLAH 23.588.281,00
Total Variabel Cost 4.398.281,00
Total Fix Cost 19.190.000,00
Total Cost 23.588.281,00
HSAK 5.357.781,00
43
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : DINAS KETENAGAKERJAAN
3 SUB- SUB KELOMPOK : Perluasan Kesempatan Kerja
4 ZONA WILAYAH SSH : Semua Wilayah
5 AKTIVITAS : PENGOLAHAN KOPI
DESKRIPSI AKTIVITAS : Kegiatan Bimbingan Teknis Ketenagakerjaan yang dilaksanakan oleh OPD bertempat di luar kantor, waktu pelaksanaan 8 (delapan) hari dengan jumlah 20 peserta
1.3.2.07.02.05.025.18829 Masker N 95, 1,00 Peserta 8,00 lembar 1,00 N/A var 7.814,00 62.512,00
9.1.2.01.09.01.001.06131 Sarung Tangan Kain, 1,00 Peserta 1,00 pasang 1,00 N/A var 9.999,00 9.999,00
Ember Sedang + Tutup Plastik,
9.1.2.01.09.01.001.05889 1,00 Peserta 0,10 buah 1,00 N/A var 72.000,00 7.200,00
Bahan Plastik
Gayung Plastik Kualitas Sedang,
9.1.2.01.09.01.001.05899 1,00 Peserta 0,10 buah 1,00 N/A var 10.000,00 1.000,00
Bahan Plastik
9.1.2.01.09.01.001.05937 Jolang Besar, 1,00 Peserta 0,10 buah 1,00 N/A var 62.000,00 6.200,00
Kompor, Peralatan untuk
9.1.2.01.09.01.001.05994 pelatihan, Kompor Gas Bahan 1,00 Peserta 0,05 buah 1,00 N/A var 500.500,00 25.025,00
Pelatihan Tata Boga,
1.1.7.01.05.01.004.02400 Mesin Bubuk Kopi (Grinderivatif) 1,00 Peserta 0,05 unit 1,00 N/A var 8.250.000,00 412.500,00
Mesin Pengupas Kulit Kopi
1.1.7.01.05.01.004.02420 1,00 Peserta 0,05 unit 1,00 N/A var 15.700.000,00 785.000,00
(Pulper)
1.1.7.01.05.01.004.02428 Mesin Roasting 1,00 Peserta 0,05 unit 1,00 N/A var 30.000.000,00 1.500.000,00
9.1.2.01.09.01.001.06113 Regulator, 1,00 Peserta 0,05 set 1,00 N/A var 200.000,00 10.000,00
9.1.2.01.09.01.001.06180 Tabung Gas dan Selang Regulator, 1,00 Peserta 0,05 set 1,00 N/A var 350.000,00 17.500,00
9.1.2.01.09.01.001.06199 Terpal 4x5 m 1,00 Peserta 0,10 Roll 1,00 N/A var 101.000,00 10.100,00
9.1.2.01.09.01.001.06211 Timbangan Seca Digital, 1,00 Peserta 0,05 buah 1,00 N/A var 3.000.000,00 150.000,00
9.1.2.01.09.01.001.06083 Pensil 2B 1,00 Peserta 1,00 buah 1,00 N/A var 5.000,00 5.000,00
Block Note - Garis A6 105 X 148
1.1.7.01.03.01.005.00257 1,00 Peserta 1,00 buku 1,00 N/A var 33.000,00 33.000,00
mm (50 lbr)
1.1.7.01.03.01.016.01133 Name Tag - Plastik 1,00 Peserta 1,00 buah 1,00 N/A var 7.300,00 7.300,00
1.1.7.01.03.01.006.00360 Map Plastik Kancing 1,00 Peserta 1,00 buah 1,00 N/A var 12.000,00 12.000,00
1.1.7.01.03.01.001.01096 Ballpoint - Pen Stand 1,00 Peserta 1,00 pcs 1,00 N/A var 10.000,00 10.000,00
1.1.7.01.03.03.007.01321 Cetak Buku Modul 1,00 Peserta 3,00 modul 1,00 N/A var 25.000,00 75.000,00
9.1.2.06.03.01.001.04826 Cetak Sertifikat 1,00 Peserta 1,00 lembar 1,00 N/A var 10.000,00 10.000,00
Cetak Spanduk, Bahan Flexy
1.1.7.01.03.03.007.01470 5,00 meter 1,00 Keg 1,00 N/A Fix 18.000,00 90.000,00
China
3.309.536,00
7.3 Peralatan/sewa
Beban sewa gedung/
9.1.2.07.02.01.001.00137 kantor/tempat Sewa 1,00 Gedung 1,00 Keg 1,00 N/A Fix 2.000.000,00 2.000.000,00
Gedung/Aula
2.000.000,00
Belanja Makan Dan
7.4
Minum
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 1,00 Peserta 1,00 OH 8,00 Hari var 45.000,00 360.000,00
dan Minuman
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 3,00 Orang 1,00 OH 8,00 Hari Fix 45.000,00 1.080.000,00
dan Minuman
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 2,00 Orang 1,00 OH 8,00 Hari Fix 45.000,00 720.000,00
dan Minuman
9.1.2.11.02.01.001.00068 Snack 30,00 Peserta 1,00 OH 1,00 N/A Fix 20.000,00 600.000,00
9.1.2.11.02.01.001.00068 Snack 1,00 Peserta 1,00 OH 8,00 Hari var 20.000,00 160.000,00
9.1.2.11.02.01.001.00068 Snack 3,00 Orang 1,00 OH 8,00 Hari Fix 20.000,00 480.000,00
9.1.2.11.02.01.001.00068 Snack 2,00 Orang 1,00 OH 8,00 Hari Fix 20.000,00 320.000,00
3.720.000,00
JUMLAH 24.279.536,00
Total Variabel Cost 5.089.536,00
Total Fix Cost 19.190.000,00
Total Cost 24.279.536,00
HSAK 6.049.036,00
44
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : DINAS KETENAGAKERJAAN
3 SUB- SUB KELOMPOK : Perluasan Kesempatan Kerja
4 ZONA WILAYAH SSH : Semua Wilayah
5 AKTIVITAS : BARISTA
DESKRIPSI AKTIVITAS : Kegiatan Bimbingan Teknis Ketenagakerjaan yang dilaksanakan oleh OPD bertempat di luar kantor, waktu pelaksanaan 8 (delapan) hari dengan jumlah 20 peserta
9.1.2.01.09.01.001.05902 Gelas Tabung (server) 1,00 Peserta 0,05 buah 1,00 N/A var 98.800,00 4.940,00
9.1.2.02.06.01.001.02846 Kopi Roasting, 1,00 Peserta 1,00 kg 1,00 N/A var 188.000,00 188.000,00
1.3.2.07.02.05.025.18829 Masker N 95, 1,00 Peserta 8,00 lembar 1,00 N/A var 7.814,00 62.512,00
9.1.2.01.09.01.001.05787 Aero Press, 1,00 Peserta 0,10 buah 1,00 N/A var 805.400,00 80.540,00
9.1.2.01.09.01.001.05891 Espresso Tamping Corner 1,00 Peserta 0,05 unit 1,00 N/A var 192.100,00 9.605,00
9.1.2.01.09.01.001.05901 Gelas Saji Kopi 1,00 Peserta 0,10 lusin 1,00 N/A var 288.500,00 28.850,00
9.1.2.01.09.01.001.05921 Hand Press, 1,00 Peserta 0,10 set 1,00 N/A var 1.085.000,00 108.500,00
Machine Espresso La Nouva Era
1.1.7.01.05.01.004.02390 1,00 Peserta 0,05 unit 1,00 N/A var 30.261.000,00 1.513.050,00
Cuardona Barista Kit
1.1.7.01.05.01.004.02400 Mesin Bubuk Kopi (Grinderivatif) 1,00 Peserta 0,05 unit 1,00 N/A var 8.250.000,00 412.500,00
Nathome Mini Portable Espresso
1.1.7.01.05.01.004.02434 1,00 Peserta 0,05 unit 1,00 N/A var 1.320.000,00 66.000,00
Maker barista kopi
9.1.2.01.09.01.001.06113 Regulator, 1,00 Peserta 0,05 set 1,00 N/A var 200.000,00 10.000,00
9.1.2.01.09.01.001.06180 Tabung Gas dan Selang Regulator, 1,00 Peserta 0,05 set 1,00 N/A var 350.000,00 17.500,00
9.1.2.01.09.01.001.06192 Teko Kopi, 1,00 Peserta 0,05 buah 1,00 N/A var 285.000,00 14.250,00
9.1.2.01.09.01.001.06211 Timbangan Seca Digital, 1,00 Peserta 0,05 buah 1,00 N/A var 3.000.000,00 150.000,00
9.1.2.01.09.01.001.06225 V60 + Saring, 1,00 Peserta 0,05 set 1,00 N/A var 1.561.450,00 78.072,50
9.1.2.01.09.01.001.06083 Pensil 2B 1,00 Peserta 1,00 buah 1,00 N/A var 5.000,00 5.000,00
Block Note - Garis A6 105 X 148
1.1.7.01.03.01.005.00257 1,00 Peserta 1,00 buku 1,00 N/A var 33.000,00 33.000,00
mm (50 lbr)
1.1.7.01.03.01.016.01133 Name Tag - Plastik 1,00 Peserta 1,00 buah 1,00 N/A var 7.300,00 7.300,00
1.1.7.01.03.01.006.00360 Map Plastik Kancing 1,00 Peserta 1,00 buah 1,00 N/A var 12.000,00 12.000,00
1.1.7.01.03.01.001.01096 Ballpoint - Pen Stand 1,00 Peserta 1,00 pcs 1,00 N/A var 10.000,00 10.000,00
1.1.7.01.03.03.007.01321 Cetak Buku Modul 1,00 Peserta 3,00 modul 1,00 N/A var 25.000,00 75.000,00
9.1.2.06.03.01.001.04826 Cetak Sertifikat 1,00 Peserta 1,00 lembar 1,00 N/A var 10.000,00 10.000,00
Cetak Spanduk, Bahan Flexy
1.1.7.01.03.03.007.01470 5,00 meter 1,00 Keg 1,00 N/A Fix 18.000,00 90.000,00
China
3.184.059,50
7.3 Peralatan/sewa
Beban sewa gedung/
9.1.2.07.02.01.001.00137 1,00 Gedung 1,00 Keg 1,00 N/A Fix 2.000.000,00 2.000.000,00
kantor/tempat Sewa Gedung/Aula
2.000.000,00
7.4 Belanja Makan Dan Minum
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 1,00 Peserta 1,00 OH 8,00 Hari var 45.000,00 360.000,00
dan Minuman
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 3,00 Orang 1,00 OH 8,00 Hari Fix 45.000,00 1.080.000,00
dan Minuman
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 2,00 Orang 1,00 OH 8,00 Hari Fix 45.000,00 720.000,00
dan Minuman
9.1.2.11.02.01.001.00068 Snack 30,00 Peserta 1,00 OH 1,00 N/A Fix 20.000,00 600.000,00
9.1.2.11.02.01.001.00068 Snack 1,00 Peserta 1,00 OH 8,00 Hari var 20.000,00 160.000,00
9.1.2.11.02.01.001.00068 Snack 3,00 Orang 1,00 OH 8,00 Hari Fix 20.000,00 480.000,00
9.1.2.11.02.01.001.00068 Snack 2,00 Orang 1,00 OH 8,00 Hari Fix 20.000,00 320.000,00
3.720.000,00
JUMLAH 24.154.059,50
Total Variabel Cost 4.964.059,50
Total Fix Cost 19.190.000,00
Total Cost 24.154.059,50
HSAK 5.923.559,50
45
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : DINAS KETENAGAKERJAAN
3 SUB- SUB KELOMPOK : Perluasan Kesempatan Kerja
4 ZONA WILAYAH SSH : Semua Wilayah
5 AKTIVITAS : SOUND SYSTEM
DESKRIPSI AKTIVITAS : Kegiatan Bimbingan Teknis Ketenagakerjaan yang dilaksanakan oleh OPD bertempat di luar kantor, waktu pelaksanaan 8 (delapan) hari dengan jumlah 20 peserta
1.1.7.01.03.08.001.00196 Kabel Power, 1,00 Peserta 0,50 pc 1,00 N/A var 30.800,00 15.400,00
1.1.7.01.03.08.001.00197 Kabel RCA, 1,00 Peserta 0,10 roll 1,00 N/A var 350.000,00 35.000,00
Kabel Speaker AP-2120CS
1.1.7.01.03.08.001.00200 1,00 Peserta 0,10 roll 1,00 N/A var 628.000,00 62.800,00
(Panjang 35 Meter)
1.3.2.07.02.05.025.18829 Masker N 95, 1,00 Peserta 8,00 lembar 1,00 N/A var 7.814,00 62.512,00
1.1.7.01.03.08.001.00188 Kabel Mic, 1,00 Peserta 0,10 set 1,00 N/A var 749.000,00 74.900,00
Mic Senheiser Ew 122G2,
Spesifikasi Mic Senheiser Ew
122G2 mic model clip yang
dirancang untuk profesional
1.3.5.02.01.01.003.01072 vokalis. suara mudah didapat, 1,00 Peserta 0,10 unit 1,00 N/A var 4.400.000,00 440.000,00
jangkauan 25 meter. performa
optimal. cocok untuk penyanyi
life, hiburan, dan lainnya mic
tidak perlu dip
1.3.2.05.02.06.008.00109 Sound system, Amplifier Rx-V6381 1,00 Peserta 0,05 set 1,00 N/A var 9.300.000,00 465.000,00
Sound system, Monitor Speaker
1.3.2.05.02.06.008.00110 1,00 Peserta 0,05 unit 1,00 N/A var 5.940.000,00 297.000,00
System
Sound system, Samsung Giga
1.3.2.05.02.06.008.00111 1,00 Peserta 0,05 unit 1,00 N/A var 18.603.585,00 930.179,25
Sound Js8000
1.3.2.05.02.06.008.00112 Soundcard, 1,00 Peserta 0,10 buah 1,00 N/A var 350.000,00 35.000,00
Sparepart Mixer Lager Roll
1.1.7.01.02.02.004.02775 1,00 Peserta 0,05 set 1,00 N/A var 5.000.000,00 250.000,00
Komeyor
1.3.2.05.02.06.008.00113 Speaker, Aktif Huper Type 8Ha 150 1,00 Peserta 0,05 unit 1,00 N/A var 9.250.000,00 462.500,00
9.1.2.01.09.01.001.06083 Pensil 2B 1,00 Peserta 1,00 buah 1,00 N/A var 5.000,00 5.000,00
Block Note - Garis A6 105 X 148
1.1.7.01.03.01.005.00257 1,00 Peserta 1,00 buku 1,00 N/A var 33.000,00 33.000,00
mm (50 lbr)
1.1.7.01.03.01.016.01133 Name Tag - Plastik 1,00 Peserta 1,00 buah 1,00 N/A var 7.300,00 7.300,00
1.1.7.01.03.01.006.00360 Map Plastik Kancing 1,00 Peserta 1,00 buah 1,00 N/A var 12.000,00 12.000,00
1.1.7.01.03.01.001.01096 Ballpoint - Pen Stand 1,00 Peserta 1,00 pcs 1,00 N/A var 10.000,00 10.000,00
1.1.7.01.03.03.007.01321 Cetak Buku Modul 1,00 Peserta 3,00 modul 1,00 N/A var 25.000,00 75.000,00
9.1.2.06.03.01.001.04826 Cetak Sertifikat 1,00 Peserta 1,00 lembar 1,00 N/A var 10.000,00 10.000,00
Cetak Spanduk, Bahan Flexy
1.1.7.01.03.03.007.01470 5,00 meter 1,00 Keg 1,00 N/A Fix 18.000,00 90.000,00
China
3.411.091,25
7.3 Peralatan/sewa
Beban sewa gedung/
9.1.2.07.02.01.001.00137 1,00 Gedung 1,00 eg 1,00 N/A Fix 2.000.000,00 2.000.000,00
kantor/tempat Sewa Gedung/Aula
2.000.000,00
7.4 Belanja Makan Dan Minum
46
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : DINAS KETENAGAKERJAAN
3 SUB- SUB KELOMPOK : Perluasan Kesempatan Kerja
4 ZONA WILAYAH SSH : Semua Wilayah
5 AKTIVITAS : DIGITAL PRINTING
DESKRIPSI AKTIVITAS : Kegiatan Bimbingan Teknis Ketenagakerjaan yang dilaksanakan oleh OPD bertempat di luar kantor, waktu pelaksanaan 8 (delapan) hari dengan jumlah 20 peserta
6 SATUAN AKTIVITAS : Peserta
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Peserta Derivatif 1 Kelas Range 20 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
9.1.2.24.01.01.001.00196 Narasumber Praktisi, 1,00 Orang 4,00 Jam 1,00 Hari Fix 900.000,00 3.600.000,00
Biaya Kediklatan, honorarium
9.1.2.23.01.01.001.01238 1,00 Orang 1,00 Hari 8,00 Hari Fix 100.000,00 800.000,00
Pengamat Kelas
Operasional Tenaga Rekrutmen
9.1.2.25.04.01.001.00848 2,00 Orang 3,00 Jam 1,00 Hari Fix 250.000,00 1.500.000,00
Peserta Pelatihan Ketenegakerjaan
Instruktur Teknis (Muda) Tenaga
Pengajar yang memiliki
9.1.2.24.01.01.001.00188 2,00 Orang 8,00 Jam 5,00 Hari Fix 80.000,00 6.400.000,00
keterampilan teknis level muda
(Non PNS/Non ASN Pemkab)
Instruktur Teknis (Madya) Tenaga
Pengajar yang memiliki
9.1.2.24.01.01.001.00187 1,00 Orang 8,00 Jam 2,00 Hari Fix 100.000,00 1.600.000,00
keterampilan teknis level madya
(Non PNS/Non ASN Pemkab)
Biaya Kediklatan, Uang Saku
9.1.2.23.01.01.001.01244 1,00 Peserta 8,00 Hari 1,00 N/A var 150.000,00 1.200.000,00
Peserta Diklat
Tes Kesehatan Bimtek
Ketenagakerjaan, Tes Kesehatan,
9.1.2.03.12.01.001.00620 1,00 Peserta 1,00 Orang 1,00 N/A var 150.000,00 150.000,00
Rapid Test Virus Corona (Covid-
19)
15.250.000,00
7.2 Bahan Material
9.1.2.01.09.01.001.05940 Kain Kaos 1,00 Peserta 1,00 Kg 1,00 N/A var 101.200,00 101.200,00
Kertas Sticker Polyflex Solid
1.1.7.01.03.03.007.01507 Standard (PVC / ukuran 0,5 x 1 1,00 Peserta 2,00 Meter 1,00 N/A var 87.500,00 175.000,00
m)
1.3.2.07.02.05.025.18829 Masker N 95, 1,00 Peserta 8,00 lembar 1,00 N/A var 7.814,00 62.512,00
Mug Kramik polos, bahan dari
1.3.2.05.02.05.026.00046 1,00 Peserta 3,00 Buah 1,00 N/A var 17.000,00 51.000,00
keramik
Tinta Polyflex Pu Eco Solvent
1.1.7.01.03.06.004.01113 1,00 Peserta 0,50 Botol 1,00 N/A var 150.000,00 75.000,00
ukuran 100 ML
Mesin Cutting Sticker LED 720
Alat Pemotong Vinyl Polyflex,
1.3.2.01.01.11.007.00001 sudah dilengkapi LAMPU LED, 1,00 Peserta 0,05 Unit 1,00 N/A var 6.504.000,00 325.200,00
terdapat 4 Roller pada HEAD
dengan tatakan METAL
Mesin Heat Press 6 In 1,
Konsumsi Daya Listrik : 1300 W,
Tegangan : 220 v / 50~60 Hz, Plat
1.3.2.01.01.11.007.00002 Material : Teflon Spray (Anti 1,00 Peserta 0,05 Set 1,00 N/A var 10.119.000,00 505.950,00
Lengket), Moulding : 6 in 1,
Dimensi Ukuran : 400 x 380 x 460
Kg
PC - PC Intel core i7-7700 RAM 8
1.3.2.10.01.02.001.00246 GB1 TB HDDNvidia Geforce GT 1,00 Peserta 0,05 Unit 1,00 N/A var 14.900.000,00 745.000,00
940 MX 2 GBMonitor 19,6 Inch
1.3.2.10.02.03.003.00270 Printer - Inkjet L310 1,00 Peserta 0,05 Unit 1,00 N/A var 2.426.300,00 121.315,00
9.1.2.01.09.01.001.06083 Pensil 2B 1,00 Peserta 1,00 buah 1,00 N/A var 5.000,00 5.000,00
Block Note - Garis A6 105 X 148
1.1.7.01.03.01.005.00257 1,00 Peserta 1,00 buku 1,00 N/A var 33.000,00 33.000,00
mm (50 lbr)
1.1.7.01.03.01.016.01133 Name Tag - Plastik 1,00 Peserta 1,00 buah 1,00 N/A var 7.300,00 7.300,00
1.1.7.01.03.01.006.00360 Map Plastik Kancing 1,00 Peserta 1,00 buah 1,00 N/A var 12.000,00 12.000,00
1.1.7.01.03.01.001.01096 Ballpoint - Pen Stand 1,00 Peserta 1,00 pcs 1,00 N/A var 10.000,00 10.000,00
1.1.7.01.03.03.007.01321 Cetak Buku Modul 1,00 Peserta 3,00 modul 1,00 N/A var 25.000,00 75.000,00
9.1.2.06.03.01.001.04826 Cetak Sertifikat 1,00 Peserta 1,00 lembar 1,00 N/A var 10.000,00 10.000,00
Cetak Spanduk, Bahan Flexy
1.1.7.01.03.03.007.01470 5,00 meter 1,00 Keg 1,00 N/A Fix 18.000,00 90.000,00
China
2.404.477,00
7.3 Peralatan/sewa
Beban sewa gedung/
9.1.2.07.02.01.001.00137 1,00 Gedung 1,00 Keg 1,00 N/A Fix 2.000.000,00 2.000.000,00
kantor/tempat Sewa Gedung/Aula
2.000.000,00
7.4 Belanja Makan Dan Minum
9.1.2.11.02.01.001.00068 Snack 30,00 Peserta 1,00 OH 1,00 N/A Fix 20.000,00 600.000,00
9.1.2.11.02.01.001.00068 Snack 1,00 Peserta 1,00 OH 8,00 Hari var 20.000,00 160.000,00
9.1.2.11.02.01.001.00068 Snack 3,00 Orang 1,00 OH 8,00 Hari Fix 20.000,00 480.000,00
9.1.2.11.02.01.001.00068 Snack 2,00 Orang 1,00 OH 8,00 Hari Fix 20.000,00 320.000,00
3.720.000,00
JUMLAH 23.374.477,00
Total Variabel Cost 4.184.477,00
Total Fix Cost 19.190.000,00
Total Cost 23.374.477,00
HSAK 5.143.977,00
47
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : DINAS KETENAGAKERJAAN
3 SUB- SUB KELOMPOK : Penyuluhan dan Bimbingan Jabatan bagi Pencari Kerja
4 ZONA WILAYAH SSH : Semua Wilayah
5 AKTIVITAS : BIMBINGAN JABATAN
Kegiatan Bimbingan Jabatan yang dilaksanakan oleh OPD bertempat di luar kantor, Petugas Psikotes, Narasumber Luar Pemda, Peserta Non PNS, waktu pelaksanaan 1
DESKRIPSI AKTIVITAS :
(satu) hari dengan jumlah 40 peserta
6 SATUAN AKTIVITAS : Peserta
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Peserta Derivatif 1 Kelas Range 40 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
9.1.2.24.01.01.001.00196 Narasumber Praktisi, 1,00 Orang 2,00 Jam 1,00 Hari Fix 900.000,00 1.800.000,00
Honorarium Tenaga
9.1.2.24.01.01.001.00178 Ahli/Narasumber/Instruktur 1,00 Orang 1,00 Kali 1,00 Peserta var 100.000,00 100.000,00
Petugas Psikotes (Muda)
9.1.2.24.01.01.001.00149 Honor Pendamping Narasumber, - 1,00 Orang 1,00 Kegiatan 1,00 N/A Fix 150.000,00 150.000,00
Tes Kesehatan Bimtek
Ketenagakerjaan, Tes Kesehatan,
9.1.2.03.12.01.001.00620 1,00 Peserta 1,00 Orang 1,00 N/A var 150.000,00 150.000,00
Rapid Test Virus Corona (Covid-
19)
2.200.000,00
7.2 Bahan Material
1.3.2.07.02.05.025.18829 Masker N 95, 1,00 Peserta 1,00 buah 1,00 N/A var 7.814,00 7.814,00
9.1.2.06.02.01.001.00058 Fotocopy - F.4 1,00 keg 500,00 lembar 1,00 N/A Fix 300,00 150.000,00
Biaya Penjilidan - softhard cover 1
1.1.7.01.03.01.014.00885 2,00 buku 1,00 Keg 1,00 N/A Fix 25.000,00 50.000,00
warna
9.1.2.06.03.01.001.04819 Cetak Map Sertifikat 1,00 Peserta 1,00 lembar 1,00 N/A var 11.500,00 11.500,00
9.1.2.06.03.01.001.04826 Cetak Sertifikat 1,00 Peserta 1,00 lembar 1,00 N/A var 10.000,00 10.000,00
Cetak Spanduk, Bahan Flexy
1.1.7.01.03.03.007.01470 5,00 meter 1,00 Keg 1,00 N/A Fix 18.000,00 90.000,00
China
319.314,00
7.3 Peralatan/sewa
- - -
-
Belanja Makan Dan
7.4
Minum
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 1,00 Peserta 1,00 dus 1,00 Hari var 45.000,00 45.000,00
dan Minuman
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 3,00 Orang 1,00 dus 1,00 Hari Fix 45.000,00 135.000,00
dan Minuman
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 2,00 Orang 1,00 dus 1,00 Hari Fix 45.000,00 90.000,00
dan Minuman
9.1.2.11.02.01.001.00068 Snack 1,00 Peserta 1,00 dus 1,00 Hari var 20.000,00 20.000,00
9.1.2.11.02.01.001.00068 Snack 3,00 Orang 1,00 dus 1,00 Hari Fix 20.000,00 60.000,00
9.1.2.11.02.01.001.00068 Snack 2,00 Orang 1,00 dus 1,00 Hari Fix 20.000,00 40.000,00
390.000,00
JUMLAH 2.909.314,00
Total Variabel Cost 344.314,00
Total Fix Cost 2.565.000,00
Total Cost 2.909.314,00
HSAK 408.439,00
48
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : DINAS KETENAGAKERJAAN
3 SUB- SUB KELOMPOK : Penyuluhan dan Bimbingan Jabatan bagi Pencari Kerja
4 ZONA WILAYAH SSH : Semua Wilayah
5 AKTIVITAS : PENYULUHAN BIMBINGAN JABATAN
Kegiatan Penyuluhan Bimbingan Jabatan yang dilaksanakan oleh OPD bertempat di luar kantor, Narasumber Luar Pemda, Peserta Non PNS, waktu pelaksanaan 1 (satu)
DESKRIPSI AKTIVITAS :
hari dengan jumlah 40 peserta
6 SATUAN AKTIVITAS : Peserta
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Peserta Derivatif 1 Kelas Range 40 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
9.1.2.24.01.01.001.00196 Narasumber Praktisi, 1,00 Orang 4,00 Jam 1,00 Hari Fix 900.000,00 3.600.000,00
9.1.2.24.01.01.001.00149 Honor Pendamping Narasumber, - 2,00 Orang 1,00 Kegiatan 1,00 N/A Fix 150.000,00 300.000,00
Tes Kesehatan Bimtek
Ketenagakerjaan, Tes Kesehatan,
9.1.2.03.12.01.001.00620 1,00 Peserta 1,00 Orang 1,00 N/A var 150.000,00 150.000,00
Rapid Test Virus Corona (Covid-
19)
4.050.000,00
7.2 Bahan Material
1.3.2.07.02.05.025.18829 Masker N 95, 1,00 Peserta 1,00 buah 1,00 N/A var 7.814,00 7.814,00
9.1.2.06.02.01.001.00058 Fotocopy - F.4 1,00 keg 500,00 lembar 1,00 N/A Fix 300,00 150.000,00
Biaya Penjilidan - softhard cover 1
1.1.7.01.03.01.014.00885 2,00 buku 1,00 Keg 1,00 N/A Fix 25.000,00 50.000,00
warna
1.1.7.01.03.03.007.01321 Cetak Buku Modul 1,00 Peserta 2,00 modul 1,00 N/A var 25.000,00 50.000,00
Cetak Spanduk, Bahan Flexy
1.1.7.01.03.03.007.01470 5,00 meter 1,00 Keg 1,00 N/A Fix 18.000,00 90.000,00
China
347.814,00
7.3 Peralatan/sewa
- - -
-
Belanja Makan Dan
7.4
Minum
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 1,00 Peserta 1,00 dus 1,00 Hari var 45.000,00 45.000,00
dan Minuman
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 3,00 Orang 1,00 dus 1,00 Hari Fix 45.000,00 135.000,00
dan Minuman
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 2,00 Orang 1,00 dus 1,00 Hari Fix 45.000,00 90.000,00
dan Minuman
9.1.2.11.02.01.001.00068 Snack 1,00 Peserta 1,00 dus 1,00 Hari var 20.000,00 20.000,00
9.1.2.11.02.01.001.00068 Snack 3,00 Orang 1,00 dus 1,00 Hari Fix 20.000,00 60.000,00
9.1.2.11.02.01.001.00068 Snack 2,00 Orang 1,00 dus 1,00 Hari Fix 20.000,00 40.000,00
390.000,00
JUMLAH 4.787.814,00
Total Variabel Cost 272.814,00
Total Fix Cost 4.515.000,00
Total Cost 4.787.814,00
HSAK 385.689,00
49
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : DINAS KETENAGAKERJAAN
3 SUB- SUB KELOMPOK : Penyuluhan dan Bimbingan Jabatan bagi Pencari Kerja
4 ZONA WILAYAH SSH : Semua Wilayah
5 AKTIVITAS : TEMU KONSULTASI PENGELOLA BKK
Kegiatan Temu Konsultasi Pengelola BKK yang dilaksanakan oleh OPD bertempat di luar kantor, Narasumber Luar Pemda, Peserta Non PNS Pengurus BKK SMK, waktu
DESKRIPSI AKTIVITAS :
pelaksanaan 1 (satu) hari dengan jumlah 40 peserta
6 SATUAN AKTIVITAS : Peserta
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Peserta Derivatif 1 Kelas Range 20 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
9.1.2.24.01.01.001.00196 Narasumber Praktisi, 2,00 Orang 2,00 Jam 1,00 Hari Fix 900.000,00 3.600.000,00
Biaya Kediklatan, Uang Saku
9.1.2.23.01.01.001.01244 1,00 Peserta 1,00 Hari 1,00 N/A Var 150.000,00 150.000,00
Peserta Diklat
Tes Kesehatan Bimtek
Ketenagakerjaan, Tes Kesehatan,
9.1.2.03.12.01.001.00620 1,00 Peserta 1,00 Kali 1,00 N/A Var 150.000,00 150.000,00
Rapid Test Virus Corona (Covid-
19)
3.900.000,00
7.2 Bahan Material
1.3.2.07.02.05.025.18829 Masker N 95, 1,00 Peserta 1,00 buah 1,00 N/A Var 7.814,00 7.814,00
9.1.2.06.02.01.001.00058 Fotocopy - F.4 1,00 keg 500,00 lembar 1,00 N/A Fix 300,00 150.000,00
Biaya Penjilidan - softhard cover 1
1.1.7.01.03.01.014.00885 2,00 buku 1,00 Keg 1,00 N/A Fix 25.000,00 50.000,00
warna
9.1.2.06.03.01.001.04826 Cetak Sertifikat 1,00 Peserta 1,00 lembar 1,00 N/A Var 10.000,00 10.000,00
9.1.2.06.03.01.001.04819 Cetak Map Sertifikat 1,00 Peserta 1,00 lembar 1,00 N/A Var 11.500,00 11.500,00
Cetak Spanduk, Bahan Flexy
1.1.7.01.03.03.007.01470 5,00 meter 1,00 Keg 1,00 N/A Fix 18.000,00 90.000,00
China
319.314,00
7.3 Peralatan/sewa
Beban sewa gedung/
9.1.2.07.02.01.001.00137 kantor/tempat Sewa 1,00 Ruang 1,00 Hari 1,00 N/A Fix 2.000.000,00 2.000.000,00
Gedung/Aula
2.000.000,00
Belanja Makan Dan
7.4
Minum
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 1,00 Peserta 1,00 dus 1,00 Hari Var 45.000,00 45.000,00
dan Minuman
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 3,00 Orang 1,00 dus 1,00 Hari Fix 45.000,00 135.000,00
dan Minuman
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 2,00 Orang 1,00 dus 1,00 Hari Fix 45.000,00 90.000,00
dan Minuman
9.1.2.11.02.01.001.00068 Snack 1,00 Peserta 1,00 dus 1,00 Hari Var 20.000,00 20.000,00
9.1.2.11.02.01.001.00068 Snack 3,00 Orang 1,00 dus 1,00 Hari Fix 20.000,00 60.000,00
9.1.2.11.02.01.001.00068 Snack 2,00 Orang 1,00 dus 1,00 Hari Fix 20.000,00 40.000,00
390.000,00
JUMLAH 6.609.314,00
Total Variabel Cost 394.314,00
Total Fix Cost 6.215.000,00
Total Cost 6.609.314,00
HSAK 705.064,00
50
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : Dinas Ketenagakerjaan
3 SUB- SUB KELOMPOK : Proses Pelaksanaan Pendidikan dan Pelatihan Keterampilan Bagi Pencari Kerja Berdasarkan Klaster Kompetensi
4 ZONA WILAYAH SSH : Seluruh Wilayah
5 AKTIVITAS : Pelatihan Montir Sepeda Motor Unit Pelatihan Keliling
DESKRIPSI AKTIVITAS : Kegiatan Pelatihan Mobile Training Unit yang dilaksanakan oleh OPD bertempat diluar Kantor, waktu pelaksanaan 30 hari dengan jumlah 20 Peserta.
1.1.7.01.05.01.004.02380 Kanvas Kopling 1,00 Orang 0,50 Buah 1,00 N/A Var 132.000,00 66.000,00
1.1.7.01.05.01.004.02381 Koil 1,00 Orang 0,50 Buah 1,00 N/A Var 224.400,00 112.200,00
9.1.2.01.09.01.001.06058 Oli Mesin Motor 1,00 Orang 1,00 botol 1,00 N/A Var 39.600,00 39.600,00
9.1.2.01.09.01.001.06059 Oli Samping 1,00 Orang 1,00 botol 1,00 N/A Var 48.950,00 48.950,00
9.1.2.01.09.01.001.06063 Packing 1,00 Orang 0,50 Buah 1,00 N/A Var 92.400,00 46.200,00
1.1.7.01.01.04.006.01008 Pertalite - 1,00 Orang 1,00 Liter 1,00 N/A Var 8.100,00 8.100,00
9.1.2.01.05.01.001.01509 Sabun Cuci Tangan 1,00 Orang 0,20 Gln 1,00 N/A Var 136.000,00 27.200,00
1.1.7.01.01.01.022.07394 Majun Katun 1,00 Orang 1,00 Kg 1,00 N/A Var 15.000,00 15.000,00
Block Note - Polos A6 105 X 148
1.1.7.01.03.01.005.00259 1,00 Orang 1,00 Buah 1,00 N/A Var 10.500,00 10.500,00
mm (50 lbr)
9.1.2.01.09.01.001.06083 Pensil 2B 1,00 Orang 1,00 Buah 1,00 N/A Var 5.000,00 5.000,00
1.1.7.01.03.13.001.00017 Serutan Pensil 1,00 Orang 1,00 Buah 1,00 N/A Var 7.500,00 7.500,00
1.1.7.01.03.01.001.01096 Ballpoint - Pen Stand 1,00 Orang 1,00 Buah 1,00 N/A Var 10.000,00 10.000,00
1.1.7.01.03.01.004.00144 Penghapus Pulpen Pensil 1,00 Orang 1,00 Buah 1,00 N/A Var 5.000,00 5.000,00
1.1.7.01.03.01.016.01133 Name Tag - Plastik 1,00 Orang 1,00 Buah 1,00 N/A Var 7.300,00 7.300,00
1.1.7.01.03.01.006.00360 Map Plastik Kancing 1,00 Orang 1,00 Buah 1,00 N/A Var 12.000,00 12.000,00
1.1.7.01.01.01.022.08160 Wearpack Bengkel 1,00 Orang 1,00 Stel 1,00 N/A Var 150.000,00 150.000,00
9.1.2.06.03.01.001.04826 Cetak Sertifikat 1,00 Orang 1,00 Lembar 1,00 N/A Var 10.000,00 10.000,00
Cetak Spanduk, Spanduk
1.1.7.01.03.03.007.01471 4,00 Meter 1,00 Keg 1,00 N/A Fix 33.450,00 133.800,00
Premium
9.1.2.06.02.01.001.00058 Fotocopy - F.4 1,00 Orang 200,00 Lembar 1,00 N/A Var 300,00 60.000,00
9.1.2.06.02.01.001.00058 Fotocopy - F.4 1,00 Buah 100,00 Lembar 1,00 N/A Fix 300,00 30.000,00
Biaya Penjilidan - soft cover 2
1.1.7.01.03.01.014.00884 1,00 Laporan 1,00 N/A 1,00 N/A Fix 35.000,00 35.000,00
warna, tebal >5cm
995.350,00
7.3 Peralatan/sewa
Sewa Ruang/ Kelas/ Aula/
9.1.2.07.02.01.001.00181 Pemerintah Kelas/Aula/Meeting 1,00 Ruangan 1,00 Keg 1,00 N/A Fix 2.500.000,00 2.500.000,00
Room
2.500.000,00
Belanja Makan Dan
7.4
Minum
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 1,00 Orang 1,00 Kali 30,00 Hari Var 45.000,00 1.350.000,00
dan Minuman
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 1,00 Orang 1,00 Kali 30,00 Hari Fix 45.000,00 1.350.000,00
dan Minuman
2.700.000,00
JUMLAH 27.395.350,00
Total Variabel Cost 3.646.550,00
Total Fix Cost 23.748.800,00
Total Cost 27.395.350,00
HSAK 4.833.990,00
51
2 SUB KELOMPOK : Dinas Ketenagakerjaan
3 SUB- SUB KELOMPOK : Proses Pelaksanaan Pendidikan dan Pelatihan Keterampilan Bagi Pencari Kerja Berdasarkan Klaster Kompetensi
4 ZONA WILAYAH SSH : Seluruh Wilayah
5 AKTIVITAS : Pelatihan Las Listrik Unit Pelatihan Keliling
DESKRIPSI AKTIVITAS : Kegiatan Pelatihan Mobile Training Unit yang dilaksanakan oleh OPD bertempat diluar Kantor, waktu pelaksanaan 30 hari dengan jumlah 20 Peserta.
1.1.7.01.01.01.022.06950 Besi Holo (4 x 4 x 600) 1,00 Orang 1,00 Batang 1,00 N/A Var 132.000,00 132.000,00
1.1.7.01.01.01.022.06951 Besi Kotak/Nako (1/1 x 400) 1,00 Orang 1,00 Batang 1,00 N/A Var 40.700,00 40.700,00
1.1.7.02.02.07.001.00001 Besi Pipa (0,6 x 5 Ø 3") 1,00 Orang 6,00 Buah 1,00 N/A Var 6.600,00 39.600,00
1.1.7.01.01.01.022.06953 Besi Plat (0,6 x 10 x 10) 1,00 Orang 6,00 Buah 1,00 N/A Var 7.700,00 46.200,00
1.1.7.01.01.01.022.06954 Besi Plat (0,6 x 10 x 15) 1,00 Orang 6,00 Buah 1,00 N/A Var 8.800,00 52.800,00
1.1.7.01.01.01.022.06955 Besi Plat (0,6 x 10 x 5) 1,00 Orang 6,00 Buah 1,00 N/A Var 6.600,00 39.600,00
1.1.7.01.01.01.022.06960 Besi Strip (0,2 x 2,5 x 400) 1,00 Orang 1,50 Batang 1,00 N/A Var 30.250,00 45.375,00
1.1.7.01.01.01.006.00006 Cat Besi (Avian) 1,00 Orang 0,40 Liter 1,00 N/A Var 77.000,00 30.800,00
1.1.7.01.01.01.006.00026 Cat Meni 1,00 Orang 0,40 Liter 1,00 N/A Var 62.700,00 25.080,00
9.1.2.01.09.01.001.05879 Dempul (Isamu) 1,00 Orang 0,20 Kg 1,00 N/A Var 70.400,00 14.080,00
9.1.2.02.07.01.001.00084 Elektroda (Nikko 2,6) 1,00 Orang 1,50 Dus 1,00 N/A Var 167.200,00 250.800,00
9.1.2.01.09.01.001.06000 KUAS, Ukuran 2 Inchi 1,00 Orang 0,50 Buah 1,00 N/A Var 5.600,00 2.800,00
9.1.2.01.09.01.001.06007 Lap Katun (Biru) 1,00 Orang 1,00 Lembar 1,00 N/A Var 5.500,00 5.500,00
1.1.7.01.05.01.004.02391 Mata Circle Duduk (19") 1,00 Orang 0,25 Buah 1,00 N/A Var 77.000,00 19.250,00
1.1.7.01.05.01.004.02392 Mata Circle Tangan (4") 1,00 Orang 0,25 Buah 1,00 N/A Var 8.800,00 2.200,00
Mata Gergaji Tangan (12"
1.1.7.01.05.01.004.02393 1,00 Orang 0,25 Batang 1,00 N/A Var 17.600,00 4.400,00
Stanplex)
1.1.7.01.05.01.004.02394 Mata Gerinda Duduk (6") 1,00 Orang 0,25 Buah 1,00 N/A Var 41.800,00 10.450,00
Mata Gerinda Tangan (Nippon 10 x
1.1.7.01.05.01.004.02395 1,00 Orang 0,25 Buah 1,00 N/A Var 17.600,00 4.400,00
12 x 16)
9.1.2.01.09.01.001.06038 Minyak Cat (Impala) 1,00 Orang 0,25 Galon 1,00 N/A Var 104.500,00 26.125,00
9.1.2.01.09.01.001.06056 Oli Mesin Diesel (B.40) 1,00 Orang 0,10 Galon 1,00 N/A Var 209.000,00 20.900,00
9.1.2.01.05.01.001.01509 Sabun Cuci Tangan 1,00 Orang 0,40 Pasang 1,00 N/A Var 136.000,00 54.400,00
1.3.2.05.02.06.077.02873 Sikat Kawat Baja (Standard) 1,00 Orang 0,50 Liter 1,00 N/A Var 14.000,00 7.000,00
Block Note - Polos A6 105 X 148
1.1.7.01.03.01.005.00259 1,00 Orang 1,00 Buah 1,00 N/A Var 10.500,00 10.500,00
mm (50 lbr)
9.1.2.01.09.01.001.06083 Pensil 2B 1,00 Orang 1,00 Buah 1,00 N/A Var 5.000,00 5.000,00
1.1.7.01.03.13.001.00017 Serutan Pensil 1,00 Orang 1,00 Buah 1,00 N/A Var 7.500,00 7.500,00
1.1.7.01.03.01.001.01096 Ballpoint - Pen Stand 1,00 Orang 1,00 Buah 1,00 N/A Var 10.000,00 10.000,00
1.1.7.01.03.01.004.00144 Penghapus Pulpen Pensil 1,00 Orang 1,00 Buah 1,00 N/A Var 5.000,00 5.000,00
1.1.7.01.03.01.016.01133 Name Tag - Plastik 1,00 Orang 1,00 Buah 1,00 N/A Var 7.300,00 7.300,00
1.1.7.01.03.01.006.00360 Map Plastik Kancing 1,00 Orang 1,00 Buah 1,00 N/A Var 12.000,00 12.000,00
1.1.7.01.01.01.022.08160 Wearpack Bengkel 1,00 Orang 1,00 Stel 1,00 N/A Var 150.000,00 150.000,00
9.1.2.06.03.01.001.04826 Cetak Sertifikat 1,00 Orang 1,00 Lembar 1,00 N/A Var 10.000,00 10.000,00
1.1.7.01.03.03.007.01471 Cetak Spanduk, Spanduk Premium 4,00 Meter 1,00 Keg 1,00 N/A Fix 33.450,00 133.800,00
9.1.2.06.02.01.001.00058 Fotocopy - F.4 1,00 Orang 200,00 Lembar 1,00 N/A Var 300,00 60.000,00
9.1.2.06.02.01.001.00058 Fotocopy - F.4 1,00 Buah 100,00 Lembar 1,00 N/A Fix 300,00 30.000,00
Biaya Penjilidan - soft cover 2
1.1.7.01.03.01.014.00884 1,00 Laporan 1,00 N/A 1,00 N/A Fix 35.000,00 35.000,00
warna, tebal >5cm
1.353.060,00
7.3 Peralatan/sewa
Sewa Ruang/ Kelas/ Aula/
9.1.2.07.02.01.001.00181 Pemerintah Kelas/Aula/Meeting 1,00 Ruangan 1,00 Keg 1,00 N/A Fix 2.500.000,00 2.500.000,00
Room
2.500.000,00
7.4 Belanja Makan Dan Minum
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 1,00 Orang 1,00 Kali 30,00 Hari Var 45.000,00 1.350.000,00
dan Minuman
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 1,00 Orang 1,00 Kali 30,00 Hari Fix 45.000,00 1.350.000,00
dan Minuman
2.700.000,00
JUMLAH 27.753.060,00
Total Variabel Cost 4.004.260,00
Total Fix Cost 23.748.800,00
Total Cost 27.753.060,00
HSAK 5.191.700,00
52
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : Dinas Ketenagakerjaan
3 SUB- SUB KELOMPOK : Proses Pelaksanaan Pendidikan dan Pelatihan Keterampilan Bagi Pencari Kerja Berdasarkan Klaster Kompetensi
4 ZONA WILAYAH SSH : Seluruh Wilayah
5 AKTIVITAS : Pelatihan Menjahit Unit Pelatihan Keliling
DESKRIPSI AKTIVITAS : Kegiatan Pelatihan Mobile Training Unit yang dilaksanakan oleh OPD bertempat diluar Kantor, waktu pelaksanaan 20 hari dengan jumlah 20 Peserta.
9.1.2.01.09.01.001.05838 Benang Obras 1,00 Orang 0,50 set 1,00 N/A Var 33.000,00 16.500,00
1.1.7.01.01.12.001.00365 Jarum Jelujur 1,00 Orang 3,00 Buah 1,00 N/A Var 4.100,00 12.300,00
9.1.2.01.09.01.001.05933 Jarum Mesin Jahit 1,00 Orang 0,30 Pack 1,00 N/A Var 50.000,00 15.000,00
9.1.2.01.09.01.001.05934 Jarum Pentul 1,00 Orang 1,00 Pak 1,00 N/A Var 15.000,00 15.000,00
9.1.2.01.09.01.001.05942 Kain Katun (celana), Baloteli 1,00 Orang 2,00 meter 1,00 N/A Var 36.000,00 72.000,00
9.1.2.01.09.01.001.05943 Kain Katun (kemeja), Baloteli 1,00 Orang 2,00 meter 1,00 N/A Var 36.000,00 72.000,00
Kain Keras Dalam/ Supertik,
9.1.2.01.09.01.001.05944 1,00 Orang 4,00 roll 1,00 N/A Var 21.000,00 84.000,00
Supertik
9.1.2.02.07.01.001.00087 Kain Rib 1,00 Orang 0,30 roll 1,00 N/A Var 60.000,00 18.000,00
9.1.2.01.09.01.001.05952 Kancing Kait, Taobao 1,00 Orang 0,25 Dus 1,00 N/A Var 35.000,00 8.750,00
9.1.2.01.09.01.001.05953 Kancing kemeja 1,00 Orang 0,40 pak 1,00 N/A Var 35.000,00 14.000,00
9.1.2.01.09.01.001.05963 Kapur Kain 1,00 Orang 0,50 pak 1,00 N/A Var 25.000,00 12.500,00
bahan pelatihan Tata busana
9.1.2.01.09.01.001.05816 1,00 Orang 1,00 pak 1,00 N/A Var 12.000,00 12.000,00
Karbon jahit, kecakapan hidup
9.1.2.06.03.01.001.04980 Karton Manila 1,00 Orang 5,00 lembar 1,00 N/A Var 3.500,00 17.500,00
Kertas Pola Warna Coklat,
9.1.2.01.09.01.001.05986 1,00 Orang 10,00 lembar 1,00 N/A Var 2.500,00 25.000,00
Universally
9.1.2.01.09.01.001.06013 Lem kertas Besar, 1,00 Orang 0,40 pak 1,00 N/A Var 25.000,00 10.000,00
9.1.2.01.09.01.001.06057 Oli Mesin Jahit, Singer 1,00 Orang 0,50 liter 1,00 N/A Var 25.000,00 12.500,00
9.1.2.01.09.01.001.06068 Palet, Bobbins 1,00 Orang 1,00 Buah 1,00 N/A Var 5.000,00 5.000,00
9.1.2.01.09.01.001.06079 Pendedel, 1,00 Orang 0,30 lusin 1,00 N/A Var 25.000,00 7.500,00
1.1.7.01.03.01.001.01100 Pensil Merah biru 1,00 Orang 1,00 pak 1,00 N/A Var 5.000,00 5.000,00
1.3.2.07.02.05.025.19309 Rader, 1,00 Orang 1,00 lusin 1,00 N/A Var 5.000,00 5.000,00
9.1.2.01.09.01.001.06115 Resleting, 1,00 Orang 1,00 lusin 1,00 N/A Var 20.000,00 20.000,00
Block Note - Polos A6 105 X 148
1.1.7.01.03.01.005.00259 1,00 Orang 1,00 Buah 1,00 N/A Var 10.500,00 10.500,00
mm (50 lbr)
9.1.2.01.09.01.001.06083 Pensil 2B 1,00 Orang 1,00 Buah 1,00 N/A Var 5.000,00 5.000,00
1.1.7.01.03.13.001.00017 Serutan Pensil 1,00 Orang 1,00 Buah 1,00 N/A Var 7.500,00 7.500,00
1.1.7.01.03.01.001.01096 Ballpoint - Pen Stand 1,00 Orang 1,00 Buah 1,00 N/A Var 10.000,00 10.000,00
1.1.7.01.03.01.004.00144 Penghapus Pulpen Pensil 1,00 Orang 1,00 Buah 1,00 N/A Var 5.000,00 5.000,00
1.1.7.01.03.01.016.01133 Name Tag - Plastik 1,00 Orang 1,00 Buah 1,00 N/A Var 7.300,00 7.300,00
1.1.7.01.03.01.006.00360 Map Plastik Kancing 1,00 Orang 1,00 Buah 1,00 N/A Var 12.000,00 12.000,00
9.1.2.06.03.01.001.04826 Cetak Sertifikat 1,00 Orang 1,00 Lembar 1,00 N/A Var 10.000,00 10.000,00
Cetak Spanduk, Spanduk
1.1.7.01.03.03.007.01471 4,00 Meter 1,00 Keg 1,00 N/A Fix 33.450,00 133.800,00
Premium
9.1.2.06.02.01.001.00058 Fotocopy - F.4 1,00 Orang 200,00 Lembar 1,00 N/A Var 300,00 60.000,00
9.1.2.06.02.01.001.00058 Fotocopy - F.4 1,00 Buah 100,00 Lembar 1,00 N/A Fix 300,00 30.000,00
Biaya Penjilidan - soft cover 2
1.1.7.01.03.01.014.00884 1,00 Laporan 1,00 N/A 1,00 N/A Fix 35.000,00 35.000,00
warna, tebal >5cm
898.150,00
7.3 Peralatan/sewa
Sewa Ruang/ Kelas/ Aula/
9.1.2.07.02.01.001.00181 Pemerintah Kelas/Aula/Meeting 1,00 Ruangan 1,00 Keg 1,00 N/A Fix 2.500.000,00 2.500.000,00
Room
2.500.000,00
7.4 Belanja Makan Dan Minum
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 1,00 Orang 1,00 Kali 20,00 Hari Var 45.000,00 900.000,00
dan Minuman
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 1,00 Orang 1,00 Kali 20,00 Hari Fix 45.000,00 900.000,00
dan Minuman
1.800.000,00
JUMLAH 19.498.150,00
Total Variabel Cost 2.599.350,00
Total Fix Cost 16.898.800,00
Total Cost 19.498.150,00
HSAK 3.444.290,00
53
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : Dinas Ketenagakerjaan
3 SUB- SUB KELOMPOK : Proses Pelaksanaan Pendidikan dan Pelatihan Keterampilan Bagi Pencari Kerja Berdasarkan Klaster Kompetensi
4 ZONA WILAYAH SSH : Seluruh Wilayah
5 AKTIVITAS : Pelatihan Service HP Unit Pelatihan Keliling
DESKRIPSI AKTIVITAS : Kegiatan Pelatihan Mobile Training Unit yang dilaksanakan oleh OPD bertempat diluar Kantor, waktu pelaksanaan 20 hari dengan jumlah 20 Peserta.
1.3.2.08.01.04.011.00006 BGA Tools 1,00 Orang 1,50 Buah 1,00 N/A Var 112.200,00 168.300,00
1.1.7.01.03.06.011.00066 DVD-R 1,00 Orang 1,50 Buah 1,00 N/A Var 4.000,00 6.000,00
9.1.2.02.07.01.001.00085 Fluks BGA 1,00 Orang 2,50 Buah 1,00 N/A Var 13.750,00 34.375,00
1.3.2.10.02.05.001.00043 HP 2nd / Bahan Praktek 1,00 Orang 1,50 Buah 1,00 N/A Var 66.000,00 99.000,00
1.1.7.01.01.01.022.07328 Koas 1,00 Orang 1,00 Buah 1,00 N/A Var 13.200,00 13.200,00
1.1.7.01.03.01.010.00332 Lem Power Glue General 1,00 Orang 1,00 Buah 1,00 N/A Var 5.000,00 5.000,00
1.1.7.01.03.08.012.00353 multi kabel 1,00 Orang 1,00 roll 1,00 N/A Var 60.000,00 60.000,00
9.1.2.02.07.01.001.00090 Pasta BGA 1,00 Orang 2,00 Buah 1,00 N/A Var 10.900,00 21.800,00
1.1.7.01.03.08.012.00336 Isolasi Listrik 1,00 Orang 1,00 Buah 1,00 N/A Var 44.000,00 44.000,00
1.1.7.01.01.01.022.08115 Timah - 1,00 Orang 2,00 Golong 1,00 N/A Var 61.500,00 123.000,00
Block Note - Polos A6 105 X 148
1.1.7.01.03.01.005.00259 1,00 Orang 1,00 Buah 1,00 N/A Var 10.500,00 10.500,00
mm (50 lbr)
9.1.2.01.09.01.001.06083 Pensil 2B 1,00 Orang 1,00 Buah 1,00 N/A Var 5.000,00 5.000,00
1.1.7.01.03.13.001.00017 Serutan Pensil 1,00 Orang 1,00 Buah 1,00 N/A Var 7.500,00 7.500,00
1.1.7.01.03.01.001.01096 Ballpoint - Pen Stand 1,00 Orang 1,00 Buah 1,00 N/A Var 10.000,00 10.000,00
1.1.7.01.03.01.004.00144 Penghapus Pulpen Pensil 1,00 Orang 1,00 Buah 1,00 N/A Var 5.000,00 5.000,00
1.1.7.01.03.01.016.01133 Name Tag - Plastik 1,00 Orang 1,00 Buah 1,00 N/A Var 7.300,00 7.300,00
1.1.7.01.03.01.006.00360 Map Plastik Kancing 1,00 Orang 1,00 Buah 1,00 N/A Var 12.000,00 12.000,00
9.1.2.06.03.01.001.04826 Cetak Sertifikat 1,00 Orang 1,00 Lembar 1,00 N/A Var 10.000,00 10.000,00
Cetak Spanduk, Spanduk
1.1.7.01.03.03.007.01471 4,00 Meter 1,00 Keg 1,00 N/A Fix 33.450,00 133.800,00
Premium
9.1.2.06.02.01.001.00058 Fotocopy - F.4 1,00 Orang 200,00 Lembar 1,00 N/A Var 300,00 60.000,00
9.1.2.06.02.01.001.00058 Fotocopy - F.4 1,00 Buah 100,00 Lembar 1,00 N/A Fix 300,00 30.000,00
Biaya Penjilidan - soft cover 2
1.1.7.01.03.01.014.00884 1,00 Laporan 1,00 N/A 1,00 N/A Fix 35.000,00 35.000,00
warna, tebal >5cm
1.004.725,00
7.3 Peralatan/sewa
Sewa Ruang/ Kelas/ Aula/
9.1.2.07.02.01.001.00181 Pemerintah Kelas/Aula/Meeting 1,00 Ruangan 1,00 Keg 1,00 N/A Fix 2.500.000,00 2.500.000,00
Room
2.500.000,00
Belanja Makan Dan
7.4
Minum
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 1,00 Orang 1,00 Kali 20,00 Hari Var 45.000,00 900.000,00
dan Minuman
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 1,00 Orang 1,00 Kali 20,00 Hari Fix 45.000,00 900.000,00
dan Minuman
1.800.000,00
JUMLAH 19.604.725,00
Total Variabel Cost 2.705.925,00
Total Fix Cost 16.898.800,00
Total Cost 19.604.725,00
HSAK 3.550.865,00
54
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : Dinas Ketenagakerjaan
3 SUB- SUB KELOMPOK : Proses Pelaksanaan Pendidikan dan Pelatihan Keterampilan Bagi Pencari Kerja Berdasarkan Klaster Kompetensi
4 ZONA WILAYAH SSH : Seluruh Wilayah
5 AKTIVITAS : Pelatihan Tata Boga Unit Pelatihan Keliling
DESKRIPSI AKTIVITAS : Kegiatan Pelatihan Mobile Training Unit yang dilaksanakan oleh OPD bertempat diluar Kantor, waktu pelaksanaan 20 hari dengan jumlah 20 Peserta.
1.800.000,00
JUMLAH 19.512.650,00
Total Variabel Cost 2.613.850,00
Total Fix Cost 16.898.800,00
Total Cost 19.512.650,00
HSAK 3.458.790,00
55
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : Dinas Ketenagakerjaan
3 SUB- SUB KELOMPOK : Proses Pelaksanaan Pendidikan dan Pelatihan Keterampilan Bagi Pencari Kerja Berdasarkan Klaster Kompetensi
4 ZONA WILAYAH SSH : Seluruh Wilayah
5 AKTIVITAS : Pelatihan Tata Rias Unit Pelatihan Keliling
DESKRIPSI AKTIVITAS : Kegiatan Pelatihan Mobile Training Unit yang dilaksanakan oleh OPD bertempat diluar Kantor, waktu pelaksanaan 20 hari dengan jumlah 20 Peserta.
9.1.2.01.09.01.001.05870 Conditioner 1,00 Orang 0,50 botol 1,00 N/A Var 45.000,00 22.500,00
9.1.2.01.09.01.001.05872 Countur Coklat 1,00 Orang 0,50 Buah 1,00 N/A Var 16.500,00 8.250,00
9.1.2.01.09.01.001.05873 Countur Putih 1,00 Orang 0,50 Buah 1,00 N/A Var 16.500,00 8.250,00
Bahan Pelatihan Tata Rias
9.1.2.01.09.01.001.05823 Pengantin Eye liner, kecakapan 1,00 Orang 0,50 Buah 1,00 N/A Var 29.000,00 14.500,00
hidup
Bahan Pelatihan Tata Rias
9.1.2.01.09.01.001.05824 Pengantin Eye shadow, kecakapan 1,00 Orang 0,50 Buah 1,00 N/A Var 25.000,00 12.500,00
hidup
Bahan Pelatihan Tata Rias
9.1.2.01.09.01.001.05825 Pengantin Foundation, kecakapan 1,00 Orang 0,50 botol 1,00 N/A Var 35.000,00 17.500,00
hidup
Bahan Pelatihan Tata Kecantikan
9.1.2.01.09.01.001.05819 Rambut Hair Spray Non Aerosol 1,00 Orang 0,25 botol 1,00 N/A Var 35.000,00 8.750,00
200 ml, kecakapan hidup
9.1.2.01.09.01.001.05920 Hand Body Lotion 1,00 Orang 0,50 botol 1,00 N/A Var 57.750,00 28.875,00
1.3.2.05.02.06.077.02655 Handuk 1,00 Orang 1,00 Buah 1,00 N/A Var 63.500,00 63.500,00
1.3.2.05.02.06.077.02664 Jepit Hitam 1,00 Orang 0,25 lusin 1,00 N/A Var 32.500,00 8.125,00
1.3.2.05.02.06.077.02665 Jepit Parting 1,00 Orang 0,25 lusin 1,00 N/A Var 22.000,00 5.500,00
1.3.2.05.02.06.077.02666 Jepit Styling 1,00 Orang 0,25 lusin 1,00 N/A Var 42.900,00 10.725,00
9.1.2.01.05.01.001.01390 Kain lap karet 1,00 Orang 0,25 Buah 1,00 N/A Var 14.500,00 3.625,00
9.1.2.01.09.01.001.05995 Konde, Lemon Blue 1,00 Orang 0,50 Buah 1,00 N/A Var 85.000,00 42.500,00
9.1.2.01.09.01.001.05999 Krim Creambath 1,00 Orang 0,50 botol 1,00 N/A Var 70.000,00 35.000,00
9.1.2.01.09.01.001.06019 Lipstick 1,00 Orang 0,50 Buah 1,00 N/A Var 107.250,00 53.625,00
1.3.2.05.02.06.077.02725 Mangkok Cat 1,00 Orang 0,25 Buah 1,00 N/A Var 17.000,00 4.250,00
1.3.2.05.02.06.077.02726 Mangkok Creambath 1,00 Orang 0,25 Buah 1,00 N/A Var 8.900,00 2.225,00
Bahan Pelatihan Tata Rias
9.1.2.01.09.01.001.05826 Pengantin Maskara, kecakapan 1,00 Orang 0,50 Buah 1,00 N/A Var 65.000,00 32.500,00
hidup
9.1.2.01.09.01.001.06026 Masker Wajah 1,00 Orang 0,50 Buah 1,00 N/A Var 41.250,00 20.625,00
9.1.2.01.09.01.001.06044 Minyak Massage 1,00 Orang 0,50 botol 1,00 N/A Var 61.600,00 30.800,00
bahan pelatihan Tata Rias
9.1.2.01.09.01.001.05827 Pengantin Pinsil alis, kecakapan 1,00 Orang 0,50 Buah 1,00 N/A Var 52.500,00 26.250,00
hidup
Whisker, Bahan Pelatihan
9.1.2.01.09.01.001.06232 1,00 Orang 0,25 Buah 1,00 N/A Var 25.000,00 6.250,00
berbahan herbal sabun natural
9.1.2.01.09.01.001.06162 Shampo Botol 1,00 Orang 0,50 botol 1,00 N/A Var 22.000,00 11.000,00
1.3.2.05.02.06.077.02874 Sisir Cat 1,00 Orang 0,50 Buah 1,00 N/A Var 12.000,00 6.000,00
1.3.2.05.02.06.077.02875 Sisir Parting 1,00 Orang 0,50 Buah 1,00 N/A Var 16.500,00 8.250,00
1.3.2.05.02.06.077.02876 Sisir Rambut 1,00 Orang 0,50 Buah 1,00 N/A Var 86.000,00 43.000,00
9.1.2.01.09.01.001.06170 Sponge Bedak 1,00 Orang 0,50 Buah 1,00 N/A Var 8.250,00 4.125,00
9.1.2.01.09.01.001.06171 Spray Styling, Tresemme 1,00 Orang 0,50 Buah 1,00 N/A Var 144.900,00 72.450,00
1.1.7.01.05.01.004.02514 Tusuk Konde 1,00 Orang 0,25 lusin 1,00 N/A Var 24.750,00 6.187,50
9.1.2.01.09.01.001.06231 Wash Lap, Okiyo 1,00 Orang 0,50 Buah 1,00 N/A Var 10.000,00 5.000,00
Block Note - Polos A6 105 X 148
1.1.7.01.03.01.005.00259 1,00 Orang 1,00 Buah 1,00 N/A Var 10.500,00 10.500,00
mm (50 lbr)
56
9.1.2.01.09.01.001.06083 Pensil 2B 1,00 Orang 1,00 Buah 1,00 N/A Var 5.000,00 5.000,00
1.1.7.01.03.13.001.00017 Serutan Pensil 1,00 Orang 1,00 Buah 1,00 N/A Var 7.500,00 7.500,00
1.1.7.01.03.01.001.01096 Ballpoint - Pen Stand 1,00 Orang 1,00 Buah 1,00 N/A Var 10.000,00 10.000,00
1.1.7.01.03.01.004.00144 Penghapus Pulpen Pensil 1,00 Orang 1,00 Buah 1,00 N/A Var 5.000,00 5.000,00
1.1.7.01.03.01.016.01133 Name Tag - Plastik 1,00 Orang 1,00 Buah 1,00 N/A Var 7.300,00 7.300,00
1.1.7.01.03.01.006.00360 Map Plastik Kancing 1,00 Orang 1,00 Buah 1,00 N/A Var 12.000,00 12.000,00
9.1.2.06.03.01.001.04826 Cetak Sertifikat 1,00 Orang 1,00 Lembar 1,00 N/A Var 10.000,00 10.000,00
Cetak Spanduk, Spanduk
1.1.7.01.03.03.007.01471 4,00 Meter 1,00 Keg 1,00 N/A Fix 33.450,00 133.800,00
Premium
9.1.2.06.02.01.001.00058 Fotocopy - F.4 1,00 Orang 200,00 Lembar 1,00 N/A Var 300,00 60.000,00
9.1.2.06.02.01.001.00058 Fotocopy - F.4 1,00 Buah 100,00 Lembar 1,00 N/A Fix 300,00 30.000,00
Biaya Penjilidan - soft cover 2
1.1.7.01.03.01.014.00884 1,00 Laporan 1,00 N/A 1,00 N/A Fix 35.000,00 35.000,00
warna, tebal >5cm
1.135.487,50
7.3 Peralatan/sewa
Sewa Ruang/ Kelas/ Aula/
9.1.2.07.02.01.001.00181 Pemerintah Kelas/Aula/Meeting 1,00 Ruangan 1,00 Keg 1,00 N/A Fix 2.500.000,00 2.500.000,00
Room
2.500.000,00
Belanja Makan Dan
7.4
Minum
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 1,00 Orang 1,00 Kali 20,00 Hari Var 45.000,00 900.000,00
dan Minuman
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 1,00 Orang 1,00 Kali 20,00 Hari Fix 45.000,00 900.000,00
dan Minuman
1.800.000,00
JUMLAH 19.735.487,50
Total Variabel Cost 2.836.687,50
Total Fix Cost 16.898.800,00
Total Cost 19.735.487,50
HSAK 3.681.627,50
57
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : Dinas Ketenagakerjaan
3 SUB- SUB KELOMPOK : Proses Pelaksanaan Pendidikan dan Pelatihan Keterampilan Bagi Pencari Kerja Berdasarkan Klaster Kompetensi
4 ZONA WILAYAH SSH : Seluruh Wilayah
5 AKTIVITAS : Pelatihan Sablon Unit Pelatihan Keliling
DESKRIPSI AKTIVITAS : Kegiatan Pelatihan Mobile Training Unit yang dilaksanakan oleh OPD bertempat diluar Kantor, waktu pelaksanaan 20 hari dengan jumlah 20 Peserta.
9.1.2.01.09.01.001.05841 Bibit Biru 1,00 Orang 0,40 Botol 1,00 N/A Var 50.600,00 20.240,00
9.1.2.01.09.01.001.05842 Bibit Hitam 1,00 Orang 0,40 Botol 1,00 N/A Var 38.500,00 15.400,00
9.1.2.01.09.01.001.05843 Bibit Kuning 1,00 Orang 0,40 Botol 1,00 N/A Var 46.200,00 18.480,00
9.1.2.01.09.01.001.05845 Bibit Merah 1,00 Orang 0,40 Botol 1,00 N/A Var 49.500,00 19.800,00
9.1.2.01.09.01.001.05846 Binderivatif 1,00 Orang 0,40 Kg 1,00 N/A Var 27.500,00 11.000,00
1.1.7.01.05.01.004.02348 Bingkai Screen 1,00 Orang 0,50 Buah 1,00 N/A Var 33.000,00 16.500,00
9.1.2.01.09.01.001.05875 CVC Warna 1,00 Orang 1,00 Botol 1,00 N/A Var 55.000,00 55.000,00
9.1.2.01.09.01.001.05903 GL Busa 1,00 Orang 0,40 Botol 1,00 N/A Var 99.000,00 39.600,00
9.1.2.01.09.01.001.05904 GL Putih 1,00 Orang 0,40 Botol 1,00 N/A Var 44.000,00 17.600,00
9.1.2.01.09.01.001.05905 GL TW 1,00 Orang 0,40 Botol 1,00 N/A Var 412.500,00 165.000,00
1.3.2.05.02.06.077.02641 Glass Plastik 1,00 Orang 0,25 set 1,00 N/A Var 37.400,00 9.350,00
9.1.2.01.09.01.001.05940 Kain Kaos 1,00 Orang 0,50 Kg 1,00 N/A Var 101.200,00 50.600,00
9.1.2.01.09.01.001.05961 Kaporit 1,00 Orang 0,40 Kg 1,00 N/A Var 37.950,00 15.180,00
Kertas Sticker, Bahan Baku
9.1.2.01.09.01.001.05989 1,00 Orang 0,40 Pak 1,00 N/A Var 39.900,00 15.960,00
Pelatihan
9.1.2.01.09.01.001.05991 Kodaktris 1,00 Orang 0,40 Meter 1,00 N/A Var 37.950,00 15.180,00
1.1.7.01.03.01.010.00308 Lakban Bening Besar 1,00 Orang 0,25 buah 1,00 N/A Var 11.000,00 2.750,00
9.1.2.01.09.01.001.06011 Lem Fox ( warna putih ) 1,00 Orang 0,25 Kg 1,00 N/A Var 36.300,00 9.075,00
9.1.2.01.09.01.001.06042 Minyak M 3 1,00 Orang 0,40 Liter 1,00 N/A Var 49.500,00 19.800,00
9.1.2.01.09.01.001.06043 Minyak M 4 1,00 Orang 0,40 Liter 1,00 N/A Var 44.000,00 17.600,00
Plastik Bening Roll Ukuran 137
1.1.7.01.03.01.016.01160 1,00 Orang 0,50 Rol 1,00 N/A Var 21.000,00 10.500,00
Cm -
1.3.2.06.01.03.003.00051 Sablon Screen 120T 40x60 cm 1,00 Orang 0,40 buah 1,00 N/A Var 80.000,00 32.000,00
1.3.2.06.01.03.003.00052 Sablon Screen 150T 15x20 cm 1,00 Orang 0,40 buah 1,00 N/A Var 70.000,00 28.000,00
1.3.2.06.01.03.003.00053 Sablon Screen 165T 30x40 cm 1,00 Orang 0,40 buah 1,00 N/A Var 112.000,00 44.800,00
9.1.2.01.09.01.001.06165 Soda Api 1,00 Orang 0,25 Kg 1,00 N/A Var 44.000,00 11.000,00
Isolasi kabel/Nitto, Nitto 3/4 Inch
1.3.2.06.03.01.004.00005 1,00 Orang 0,25 buah 1,00 N/A Var 8.800,00 2.200,00
25 Meter
9.1.2.01.09.01.001.06173 Super X 1,00 Orang 0,40 Botol 1,00 N/A Var 44.000,00 17.600,00
Block Note - Polos A6 105 X 148
1.1.7.01.03.01.005.00259 1,00 Orang 1,00 Buah 1,00 N/A Var 10.500,00 10.500,00
mm (50 lbr)
9.1.2.01.09.01.001.06083 Pensil 2B 1,00 Orang 1,00 Buah 1,00 N/A Var 5.000,00 5.000,00
1.1.7.01.03.13.001.00017 Serutan Pensil 1,00 Orang 1,00 Buah 1,00 N/A Var 7.500,00 7.500,00
1.1.7.01.03.01.001.01096 Ballpoint - Pen Stand 1,00 Orang 1,00 Buah 1,00 N/A Var 10.000,00 10.000,00
1.1.7.01.03.01.004.00144 Penghapus Pulpen Pensil 1,00 Orang 1,00 Buah 1,00 N/A Var 5.000,00 5.000,00
1.1.7.01.03.01.016.01133 Name Tag - Plastik 1,00 Orang 1,00 Buah 1,00 N/A Var 7.300,00 7.300,00
1.1.7.01.03.01.006.00360 Map Plastik Kancing 1,00 Orang 1,00 Buah 1,00 N/A Var 12.000,00 12.000,00
9.1.2.06.03.01.001.04826 Cetak Sertifikat 1,00 Orang 1,00 Lembar 1,00 N/A Var 10.000,00 10.000,00
1.1.7.01.03.03.007.01471 Cetak Spanduk, Spanduk Premium 4,00 Meter 1,00 Keg 1,00 N/A Fix 33.450,00 133.800,00
9.1.2.06.02.01.001.00058 Fotocopy - F.4 1,00 Orang 200,00 Lembar 1,00 N/A Var 300,00 60.000,00
9.1.2.06.02.01.001.00058 Fotocopy - F.4 1,00 Buah 100,00 Lembar 1,00 N/A Fix 300,00 30.000,00
Biaya Penjilidan - soft cover 2
1.1.7.01.03.01.014.00884 1,00 Laporan 1,00 N/A 1,00 N/A Fix 35.000,00 35.000,00
warna, tebal >5cm
1.012.915,00
7.3 Peralatan/sewa
Sewa Ruang/ Kelas/ Aula/
9.1.2.07.02.01.001.00181 Pemerintah Kelas/Aula/Meeting 1,00 Ruangan 1,00 Keg 1,00 N/A Fix 2.500.000,00 2.500.000,00
Room
2.500.000,00
7.4 Belanja Makan Dan Minum
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 1,00 Orang 1,00 Kali 20,00 Hari Var 45.000,00 900.000,00
dan Minuman
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 1,00 Orang 1,00 Kali 20,00 Hari Fix 45.000,00 900.000,00
dan Minuman
1.800.000,00
JUMLAH 19.612.915,00
Total Variabel Cost 2.714.115,00
Total Fix Cost 16.898.800,00
Total Cost 19.612.915,00
HSAK 3.559.055,00
58
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : Dinas Ketenagakerjaan
3 SUB- SUB KELOMPOK : Proses Pelaksanaan Pendidikan dan Pelatihan Keterampilan Bagi Pencari Kerja Berdasarkan Klaster Kompetensi
4 ZONA WILAYAH SSH : Seluruh Wilayah
5 AKTIVITAS : Pelatihan Service Komputer Unit Pelatihan Keliling
DESKRIPSI AKTIVITAS : Kegiatan Pelatihan Mobile Training Unit yang dilaksanakan oleh OPD bertempat diluar Kantor, waktu pelaksanaan 20 hari dengan jumlah 20 Peserta.
9.1.2.02.07.01.001.00082 Card Detec 1,00 Orang 0,50 Buah 1,00 N/A Var 243.100,00 121.550,00
9.1.2.02.07.01.001.00083 C-ON-K 1,00 Orang 0,50 botol 1,00 N/A Var 104.500,00 52.250,00
9.1.2.01.09.01.001.05798 Arpus 1,00 Orang 1,00 botol 1,00 N/A Var 69.300,00 69.300,00
1.1.7.01.01.05.007.00335 Tiner 1,00 Orang 0,40 botol 1,00 N/A Var 50.000,00 20.000,00
9.1.2.01.09.01.001.05871 Contact cleaner 1,00 Orang 0,20 botol 1,00 N/A Var 83.600,00 16.720,00
9.1.2.02.07.01.001.00081 Batrai Cmos 1,00 Orang 1,00 Buah 1,00 N/A Var 7.700,00 7.700,00
1.3.2.05.02.06.077.02808 PSU ATX 450 watt 1,00 Orang 0,40 Buah 1,00 N/A Var 645.000,00 258.000,00
9.1.2.02.07.01.001.00086 Kabel Jaringan (UTP) 1,00 Orang 0,05 roll 1,00 N/A Var 590.700,00 29.535,00
1.1.7.01.01.01.022.07336 Kuas 4 Inchi 1,00 Orang 1,00 Buah 1,00 N/A Var 17.500,00 17.500,00
9.1.2.02.07.01.001.00099 RJ 45 1,00 Orang 0,10 box 1,00 N/A Var 204.750,00 20.475,00
1.1.7.01.01.01.022.08115 Timah - 1,00 Orang 1,00 Gul 1,00 N/A Var 61.500,00 61.500,00
1.1.7.01.01.05.007.00197 Lem Superglue, 3 gram 1,00 Orang 0,50 Buah 1,00 N/A Var 5.000,00 2.500,00
1.1.7.01.03.06.011.00065 CD-RW Plus 700 MB 1,00 Orang 1,00 Buah 1,00 N/A Var 15.000,00 15.000,00
1.1.7.01.03.08.012.00334 DVDRW 1,00 Orang 0,10 Buah 1,00 N/A Var 253.000,00 25.300,00
1.1.7.01.03.08.012.00353 multi kabel 1,00 Orang 0,20 roll 1,00 N/A Var 60.000,00 12.000,00
Block Note - Polos A6 105 X 148
1.1.7.01.03.01.005.00259 1,00 Orang 1,00 Buah 1,00 N/A Var 10.500,00 10.500,00
mm (50 lbr)
9.1.2.01.09.01.001.06083 Pensil 2B 1,00 Orang 1,00 Buah 1,00 N/A Var 5.000,00 5.000,00
1.1.7.01.03.13.001.00017 Serutan Pensil 1,00 Orang 1,00 Buah 1,00 N/A Var 7.500,00 7.500,00
1.1.7.01.03.01.001.01096 Ballpoint - Pen Stand 1,00 Orang 1,00 Buah 1,00 N/A Var 10.000,00 10.000,00
1.1.7.01.03.01.004.00144 Penghapus Pulpen Pensil 1,00 Orang 1,00 Buah 1,00 N/A Var 5.000,00 5.000,00
1.1.7.01.03.01.016.01133 Name Tag - Plastik 1,00 Orang 1,00 Buah 1,00 N/A Var 7.300,00 7.300,00
1.1.7.01.03.01.006.00360 Map Plastik Kancing 1,00 Orang 1,00 Buah 1,00 N/A Var 12.000,00 12.000,00
9.1.2.06.03.01.001.04826 Cetak Sertifikat 1,00 Orang 1,00 Lembar 1,00 N/A Var 10.000,00 10.000,00
Cetak Spanduk, Spanduk
1.1.7.01.03.03.007.01471 4,00 Meter 1,00 Keg 1,00 N/A Fix 33.450,00 133.800,00
Premium
9.1.2.06.02.01.001.00058 Fotocopy - F.4 1,00 Orang 200,00 Lembar 1,00 N/A Var 300,00 60.000,00
9.1.2.06.02.01.001.00058 Fotocopy - F.4 1,00 Buah 100,00 Lembar 1,00 N/A Fix 300,00 30.000,00
Biaya Penjilidan - soft cover 2
1.1.7.01.03.01.014.00884 1,00 Laporan 1,00 N/A 1,00 N/A Fix 35.000,00 35.000,00
warna, tebal >5cm
1.155.930,00
7.3 Peralatan/sewa
Sewa Ruang/ Kelas/ Aula/
9.1.2.07.02.01.001.00181 Pemerintah Kelas/Aula/Meeting 1,00 Ruangan 1,00 Keg 1,00 N/A Fix 2.500.000,00 2.500.000,00
Room
2.500.000,00
Belanja Makan Dan
7.4
Minum
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 1,00 Orang 1,00 Kali 20,00 Hari Var 45.000,00 900.000,00
dan Minuman
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 1,00 Orang 1,00 Kali 20,00 Hari Fix 45.000,00 900.000,00
dan Minuman
1.800.000,00
JUMLAH 19.755.930,00
Total Variabel Cost 2.857.130,00
Total Fix Cost 16.898.800,00
Total Cost 19.755.930,00
HSAK 3.702.070,00
59
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : Dinas Ketenagakerjaan
3 SUB- SUB KELOMPOK : Proses Pelaksanaan Pendidikan dan Pelatihan Keterampilan Bagi Pencari Kerja Berdasarkan Klaster Kompetensi
4 ZONA WILAYAH SSH : Seluruh Wilayah
5 AKTIVITAS : Pelatihan Mebeuler Unit Pelatihan Keliling
DESKRIPSI AKTIVITAS : Kegiatan Pelatihan Mobile Training Unit yang dilaksanakan oleh OPD bertempat diluar Kantor, waktu pelaksanaan 30 hari dengan jumlah 20 Peserta.
6 SATUAN AKTIVITAS : Peserta
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Peserta Derivatif 1 Kelas Range 20 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
Operasional Tenaga Rekrutmen
9.1.2.25.04.01.001.00848 2,00 Orang 1,00 Keg 1,00 N/A Fix 250.000,00 500.000,00
Peserta Pelatihan Ketenegakerjaan
Instruktur Teknis (Muda) Tenaga
Pengajar yang memiliki
9.1.2.24.01.01.001.00188 1,00 Orang 8,00 Jam 30,00 Hari Fix 80.000,00 19.200.000,00
keterampilan teknis level muda
(Non PNS/Non ASN Pemkab)
beban kursus-kursus
9.1.2.23.01.01.001.01209 singkat/pelatihan Uang Saku 1,00 Orang 1,00 Hari 30,00 Hari Var 50.000,00 1.500.000,00
peserta Diklat Ketenagakerjaan
21.200.000,00
7.2 Bahan Material
9.1.2.01.09.01.001.05980 Kayu Suren ( uk. 6 x 15 x 200 cm ) 1,00 Orang 1,00 Batang 1,00 N/A Var 84.700,00 84.700,00
9.1.2.01.09.01.001.05979 Kayu Suren ( uk. 4 x 4 x 200 cm ) 1,00 Orang 1,00 Batang 1,00 N/A Var 30.250,00 30.250,00
9.1.2.01.09.01.001.05978 Kayu Suren ( uk. 3 x 30 x 200 cm ) 1,00 Orang 1,00 Batang 1,00 N/A Var 118.800,00 118.800,00
9.1.2.01.09.01.001.05981 Kayu Suren ( uk. 6 x 6 x 200 cm ) 1,00 Orang 0,50 Batang 1,00 N/A Var 90.750,00 45.375,00
1.3.2.05.02.06.077.02614 Engsel Sendok ( nilon ) 1,00 Orang 0,50 pasang 1,00 N/A Var 21.000,00 10.500,00
9.1.2.01.09.01.001.06114 Rel laci ( uk. 40 cm ) 1,00 Orang 0,50 pasang 1,00 N/A Var 27.500,00 13.750,00
1.3.2.05.02.06.077.02654 Handle / Tarikan ( plastik ) 1,00 Orang 0,50 Buah 1,00 N/A Var 95.000,00 47.500,00
9.1.2.01.09.01.001.06228 Vynil ( bahan kayu ) 1,00 Orang 0,20 Kg 1,00 N/A Var 90.750,00 18.150,00
1.1.7.01.01.01.022.07536 Paku 1,00 Orang 0,80 Kg 1,00 N/A Var 17.500,00 14.000,00
9.1.2.01.09.01.001.06142 Sekrup kayu ( uk. 3 cm ) 1,00 Orang 0,20 Dus 1,00 N/A Var 62.700,00 12.540,00
9.1.2.01.09.01.001.06141 Sekrup kayu ( uk. 2,5 cm ) 1,00 Orang 0,20 Dus 1,00 N/A Var 62.700,00 12.540,00
1.1.7.01.05.01.004.02433 Multiple blok ( uk. 18 mm ) 1,00 Orang 0,20 lembar 1,00 N/A Var 458.700,00 91.740,00
1.1.7.01.05.01.004.02432 Multiple blok ( uk. 15 mm ) 1,00 Orang 0,20 lembar 1,00 N/A Var 222.200,00 44.440,00
1.3.2.05.02.06.077.02740 Melamine ( uk. 3 mm ) 1,00 Orang 0,20 lembar 1,00 N/A Var 152.900,00 30.580,00
9.1.2.01.09.01.001.06191 Teak wood ( uk. 3 mm ) 1,00 Orang 0,20 lembar 1,00 N/A Var 201.300,00 40.260,00
9.1.2.01.09.01.001.06233 Wood filler ( uk. 1 28 ) 1,00 Orang 0,30 Kg 1,00 N/A Var 77.000,00 23.100,00
9.1.2.01.09.01.001.06234 Wood stain ( uk. 1 28 ) 1,00 Orang 0,30 Kg 1,00 N/A Var 104.500,00 31.350,00
9.1.2.01.09.01.001.06203 Thiner ( laba-laba ) 1,00 Orang 0,20 Buah 1,00 N/A Var 111.100,00 22.220,00
9.1.2.01.09.01.001.05796 Ampelas ( no. 0 - 2 ) 1,00 Orang 0,50 meter 1,00 N/A Var 209.000,00 104.500,00
9.1.2.01.09.01.001.06010 Lem Fox ( warna kuning ) 1,00 Orang 0,30 galon 1,00 N/A Var 222.200,00 66.660,00
9.1.2.01.09.01.001.06011 Lem Fox ( warna putih ) 1,00 Orang 0,30 Kg 1,00 N/A Var 36.300,00 10.890,00
1.1.7.01.01.01.022.07284 Kacamata Las 1,00 Orang 0,30 Buah 1,00 N/A Var 50.000,00 15.000,00
Block Note - Polos A6 105 X 148
1.1.7.01.03.01.005.00259 1,00 Orang 1,00 Buah 1,00 N/A Var 10.500,00 10.500,00
mm (50 lbr)
9.1.2.01.09.01.001.06083 Pensil 2B 1,00 Orang 1,00 Buah 1,00 N/A Var 5.000,00 5.000,00
1.1.7.01.03.13.001.00017 Serutan Pensil 1,00 Orang 1,00 Buah 1,00 N/A Var 7.500,00 7.500,00
1.1.7.01.03.01.001.01096 Ballpoint - Pen Stand 1,00 Orang 1,00 Buah 1,00 N/A Var 10.000,00 10.000,00
1.1.7.01.03.01.004.00144 Penghapus Pulpen Pensil 1,00 Orang 1,00 Buah 1,00 N/A Var 5.000,00 5.000,00
1.1.7.01.03.01.016.01133 Name Tag - Plastik 1,00 Orang 1,00 Buah 1,00 N/A Var 7.300,00 7.300,00
1.1.7.01.03.01.006.00360 Map Plastik Kancing 1,00 Orang 1,00 Buah 1,00 N/A Var 12.000,00 12.000,00
9.1.2.06.03.01.001.04826 Cetak Sertifikat 1,00 Orang 1,00 Lembar 1,00 N/A Var 10.000,00 10.000,00
Cetak Spanduk, Spanduk
1.1.7.01.03.03.007.01471 4,00 Meter 1,00 Keg 1,00 N/A Fix 33.450,00 133.800,00
Premium
9.1.2.06.02.01.001.00058 Fotocopy - F.4 1,00 Orang 200,00 Lembar 1,00 N/A Var 300,00 60.000,00
9.1.2.06.02.01.001.00058 Fotocopy - F.4 1,00 Buah 100,00 Lembar 1,00 N/A Fix 300,00 30.000,00
Biaya Penjilidan - soft cover 2
1.1.7.01.03.01.014.00884 1,00 Laporan 1,00 N/A 1,00 N/A Fix 35.000,00 35.000,00
warna, tebal >5cm
1.214.945,00
7.3 Peralatan/sewa
Sewa Ruang/ Kelas/ Aula/
9.1.2.07.02.01.001.00181 Pemerintah Kelas/Aula/Meeting 1,00 Ruangan 1,00 Keg 1,00 N/A Fix 2.500.000,00 2.500.000,00
Room
2.500.000,00
Belanja Makan Dan
7.4
Minum
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 1,00 Orang 1,00 Kali 30,00 Hari Var 45.000,00 1.350.000,00
dan Minuman
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 1,00 Orang 1,00 Kali 30,00 Hari Fix 45.000,00 1.350.000,00
dan Minuman
2.700.000,00
JUMLAH 27.614.945,00
Total Variabel Cost 3.866.145,00
Total Fix Cost 23.748.800,00
Total Cost 27.614.945,00
HSAK 5.053.585,00
60
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : Dinas Ketenagakerjaan
3 SUB- SUB KELOMPOK : Proses Pelaksanaan Pendidikan dan Pelatihan Keterampilan Bagi Pencari Kerja Berdasarkan Klaster Kompetensi
4 ZONA WILAYAH SSH : Seluruh Wilayah
5 AKTIVITAS : Pelatihan Daur Ulang Sampah Unit Pelatihan Keliling
DESKRIPSI AKTIVITAS : Kegiatan Pelatihan Mobile Training Unit yang dilaksanakan oleh OPD bertempat diluar Kantor, waktu pelaksanaan 20 hari dengan jumlah 20 Peserta.
9.1.2.01.09.01.001.06115 Resleting, 1,00 Orang 1,50 buah 1,00 N/A Var 20.000,00 30.000,00
Sedotan Plastik, Berkualitas,
1.3.2.07.02.05.025.19485 1,00 Orang 3,00 Pak 1,00 N/A Var 12.150,00 36.450,00
Ukuran Sedang
9.1.2.01.09.01.001.05954 Kantong Keresek Sedang, 1,00 Orang 1,50 Pak 1,00 N/A Var 16.500,00 24.750,00
1.1.7.01.01.01.022.07265 Isolasi Tape 1,00 Orang 1,50 Roll 1,00 N/A Var 10.000,00 15.000,00
1.1.7.01.03.01.010.00321 Lem Aibon 70 Gr 1,00 Orang 1,50 buah 1,00 N/A Var 11.500,00 17.250,00
1.1.7.01.01.01.022.08075 Tembakan Lem Bakar - 1,00 Orang 1,00 Buah 1,00 N/A Var 61.000,00 61.000,00
9.1.2.01.09.01.001.06088 Pita, 1,00 Orang 2,00 Roll 1,00 N/A Var 26.000,00 52.000,00
TRIPLEX 4MM, Triplek Bahan
9.1.2.01.09.01.001.06221 1,00 Orang 0,50 Lbr 1,00 N/A Var 57.000,00 28.500,00
Maranti
9.1.2.01.09.01.001.05991 Kodaktris 1,00 Orang 1,50 Meter 1,00 N/A Var 37.950,00 56.925,00
Gunting, Peralatan untuk
9.1.2.01.09.01.001.05913 1,00 Orang 1,00 Buah 1,00 N/A Var 17.500,00 17.500,00
pelatihan
bahan pelatihan Tata busana
9.1.2.01.09.01.001.05815 1,00 Orang 1,00 Bungkus 1,00 N/A Var 4.000,00 4.000,00
Jarum Tangan, kecakapan hidup
Double tape, Bahan Baku
9.1.2.01.09.01.001.05883 1,00 Orang 1,00 Buah 1,00 N/A Var 4.000,00 4.000,00
Pelatihan, ukuran 1 cm
9.1.2.01.09.01.001.05975 Kawat Hias 1,00 Orang 5,00 Meter 1,00 N/A Var 600,00 3.000,00
Plastik Mika, Bahan Baku
9.1.2.01.09.01.001.06095 1,00 Orang 5,00 Meter 1,00 N/A Var 25.000,00 125.000,00
Pelatihan
9.1.2.01.09.01.001.06000 KUAS, Ukuran 2 Inchi 1,00 Orang 0,50 Bh 1,00 N/A Var 5.600,00 2.800,00
9.1.2.01.09.01.001.06018 Limbah plastik, 1,00 Orang 5,00 Kg 1,00 N/A Var 7.800,00 39.000,00
Block Note - Polos A6 105 X 148
1.1.7.01.03.01.005.00259 1,00 Orang 1,00 Buah 1,00 N/A Var 10.500,00 10.500,00
mm (50 lbr)
9.1.2.01.09.01.001.06083 Pensil 2B 1,00 Orang 1,00 Buah 1,00 N/A Var 5.000,00 5.000,00
1.1.7.01.03.13.001.00017 Serutan Pensil 1,00 Orang 1,00 Buah 1,00 N/A Var 7.500,00 7.500,00
1.1.7.01.03.01.001.01096 Ballpoint - Pen Stand 1,00 Orang 1,00 Buah 1,00 N/A Var 10.000,00 10.000,00
1.1.7.01.03.01.004.00144 Penghapus Pulpen Pensil 1,00 Orang 1,00 Buah 1,00 N/A Var 5.000,00 5.000,00
1.1.7.01.03.01.016.01133 Name Tag - Plastik 1,00 Orang 1,00 Buah 1,00 N/A Var 7.300,00 7.300,00
1.1.7.01.03.01.006.00360 Map Plastik Kancing 1,00 Orang 1,00 Buah 1,00 N/A Var 12.000,00 12.000,00
9.1.2.06.03.01.001.04826 Cetak Sertifikat 1,00 Orang 1,00 Lembar 1,00 N/A Var 10.000,00 10.000,00
Cetak Spanduk, Spanduk
1.1.7.01.03.03.007.01471 4,00 Meter 1,00 Keg 1,00 N/A Fix 33.450,00 133.800,00
Premium
9.1.2.06.02.01.001.00058 Fotocopy - F.4 1,00 Orang 200,00 Lembar 1,00 N/A Var 300,00 60.000,00
9.1.2.06.02.01.001.00058 Fotocopy - F.4 1,00 Buah 100,00 Lembar 1,00 N/A Fix 300,00 30.000,00
Biaya Penjilidan - soft cover 2
1.1.7.01.03.01.014.00884 1,00 Laporan 1,00 N/A 1,00 N/A Fix 35.000,00 35.000,00
warna, tebal >5cm
882.675,00
7.3 Peralatan/sewa
Sewa Ruang/ Kelas/ Aula/
9.1.2.07.02.01.001.00181 Pemerintah Kelas/Aula/Meeting 1,00 Ruangan 1,00 Keg 1,00 N/A Fix 2.500.000,00 2.500.000,00
Room
2.500.000,00
Belanja Makan Dan
7.4
Minum
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 1,00 Orang 1,00 Kali 20,00 Hari Var 45.000,00 900.000,00
dan Minuman
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 1,00 Orang 1,00 Kali 20,00 Hari Fix 45.000,00 900.000,00
dan Minuman
1.800.000,00
JUMLAH 19.482.675,00
Total Variabel Cost 2.583.875,00
Total Fix Cost 16.898.800,00
Total Cost 19.482.675,00
HSAK 3.428.815,00
61
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : Dinas Ketenagakerjaan
3 SUB- SUB KELOMPOK : Proses Pelaksanaan Pendidikan dan Pelatihan Keterampilan Bagi Pencari Kerja Berdasarkan Klaster Kompetensi
4 ZONA WILAYAH SSH : Seluruh Wilayah
5 AKTIVITAS : Pelatihan Design Grafis Unit Pelatihan Keliling
DESKRIPSI AKTIVITAS : Kegiatan Pelatihan Mobile Training Unit yang dilaksanakan oleh OPD bertempat diluar Kantor, waktu pelaksanaan 20 hari dengan jumlah 20 Peserta.
1.1.7.01.03.02.002.00319 Kertas Foto A4 1,00 Orang 0,50 pak 1,00 N/A Var 52.000,00 26.000,00
1.1.7.01.01.05.007.00179 Kertas HVS, A4; 80 Gsm 1,00 Orang 0,50 Rim 1,00 N/A Var 50.000,00 25.000,00
Kertas Sticker, Bahan Baku
9.1.2.01.09.01.001.05989 1,00 Orang 0,50 Pak 1,00 N/A Var 39.900,00 19.950,00
Pelatihan
9.1.2.02.07.01.001.00093 Polyflex Flock 1,00 Orang 0,50 Meter 1,00 N/A Var 135.000,00 67.500,00
9.1.2.02.07.01.001.00094 Polyflex Fosfor 1,00 Orang 0,50 Meter 1,00 N/A Var 160.000,00 80.000,00
9.1.2.02.07.01.001.00095 Polyflex PU, Printable 1,00 Orang 0,50 Meter 1,00 N/A Var 120.000,00 60.000,00
9.1.2.02.07.01.001.00096 Polyflex PU, Warna 1,00 Orang 0,50 Meter 1,00 N/A Var 100.000,00 50.000,00
bahan pelatihan komputer Tinta
9.1.2.01.09.01.001.05804 Printer Warna Dan Hitam, 1,00 Orang 0,50 Botol 1,00 N/A Var 330.000,00 165.000,00
kecakapan hidup
Block Note - Polos A6 105 X 148
1.1.7.01.03.01.005.00259 1,00 Orang 1,00 Buah 1,00 N/A Var 10.500,00 10.500,00
mm (50 lbr)
9.1.2.01.09.01.001.06083 Pensil 2B 1,00 Orang 1,00 Buah 1,00 N/A Var 5.000,00 5.000,00
1.1.7.01.03.13.001.00017 Serutan Pensil 1,00 Orang 1,00 Buah 1,00 N/A Var 7.500,00 7.500,00
1.1.7.01.03.01.001.01096 Ballpoint - Pen Stand 1,00 Orang 1,00 Buah 1,00 N/A Var 10.000,00 10.000,00
1.1.7.01.03.01.004.00144 Penghapus Pulpen Pensil 1,00 Orang 1,00 Buah 1,00 N/A Var 5.000,00 5.000,00
1.1.7.01.03.01.016.01133 Name Tag - Plastik 1,00 Orang 1,00 Buah 1,00 N/A Var 7.300,00 7.300,00
1.1.7.01.03.01.006.00360 Map Plastik Kancing 1,00 Orang 1,00 Buah 1,00 N/A Var 12.000,00 12.000,00
9.1.2.06.03.01.001.04826 Cetak Sertifikat 1,00 Orang 1,00 Lembar 1,00 N/A Var 10.000,00 10.000,00
Cetak Spanduk, Spanduk
1.1.7.01.03.03.007.01471 4,00 Meter 1,00 Keg 1,00 N/A Fix 33.450,00 133.800,00
Premium
9.1.2.06.02.01.001.00058 Fotocopy - F.4 1,00 Orang 200,00 Lembar 1,00 N/A Var 300,00 60.000,00
9.1.2.06.02.01.001.00058 Fotocopy - F.4 1,00 Buah 100,00 Lembar 1,00 N/A Fix 300,00 30.000,00
Biaya Penjilidan - soft cover 2
1.1.7.01.03.01.014.00884 1,00 Laporan 1,00 N/A 1,00 N/A Fix 35.000,00 35.000,00
warna, tebal >5cm
1.024.550,00
7.3 Peralatan/sewa
Sewa Ruang/ Kelas/ Aula/
9.1.2.07.02.01.001.00181 Pemerintah Kelas/Aula/Meeting 1,00 Ruangan 1,00 Keg 1,00 N/A Fix 2.500.000,00 2.500.000,00
Room
2.500.000,00
Belanja Makan Dan
7.4
Minum
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 1,00 Orang 1,00 Kali 20,00 Hari Var 45.000,00 900.000,00
dan Minuman
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 1,00 Orang 1,00 Kali 20,00 Hari Fix 45.000,00 900.000,00
dan Minuman
1.800.000,00
JUMLAH 19.624.550,00
Total Variabel Cost 2.725.750,00
Total Fix Cost 16.898.800,00
Total Cost 19.624.550,00
HSAK 3.570.690,00
62
1 KELOMPOK : DINAS KETENAGAKERJAAN
2 SUB KELOMPOK : Non Konstruksi
3 SUB- SUB KELOMPOK : Koordinasi Lintas Lembaga dan Kerja Sama dengan Sektor Swasta untuk Penyediaan Instruktur serta Sarana dan Prasarana Lembaga Pelatihan Kerja
4 ZONA WILAYAH SSH : Seluruh Wilayah
5 AKTIVITAS : Bahasa Jepang
Kegiatan pelatihan bagi pencari kerja, dilaksanakan oleh OPD bertempat diluar kantor kerjasama dengan Lembaga Pelatihan Kerja Swasta dengan waktu pelaksanaan 40
DESKRIPSI AKTIVITAS :
hari kerja atau 400 JPL dengan jumlah Peserta 20 orang
6 SATUAN AKTIVITAS : Peserta
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Peserta Derivatif 1 Kelas Range 20 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
Instruktur Teknis (Madya) Tenaga
Pengajar yang memiliki
9.1.2.24.01.01.001.00187 400,00 OJ 1,00 Keg 1,00 N/A Fix 100.000,00 40.000.000,00
keterampilan teknis level madya
(Non PNS/Non ASN Pemkab)
Biaya Kediklatan, honorarium
9.1.2.23.01.01.001.01238 40,00 OH 1,00 Keg 1,00 N/A Fix 100.000,00 4.000.000,00
Pengamat Kelas
44.000.000,00
7.2 Bahan Material
1.1.7.01.03.01.005.00260 Buku Agenda Kerja 1,00 Peserta 1,00 buku 1,00 N/A var 25.000,00 25.000,00
1.1.7.01.03.01.001.01096 Ballpoint - Pen Stand 1,00 Peserta 1,00 buah 1,00 N/A var 10.000,00 10.000,00
1.1.7.01.03.01.007.00081 Penggaris Plastik 30 Cm 1,00 Peserta 1,00 buah 1,00 N/A var 2.000,00 2.000,00
9.1.2.01.09.01.001.06083 Pensil 2B 1,00 Peserta 1,00 buah 1,00 N/A var 5.000,00 5.000,00
1.1.7.01.03.13.001.00017 Serutan Pensil 1,00 Peserta 1,00 buah 1,00 N/A var 7.500,00 7.500,00
1.1.7.01.03.01.004.00144 Penghapus Pulpen Pensil 1,00 Peserta 1,00 pcs 1,00 N/A var 5.000,00 5.000,00
1.1.7.01.03.01.016.01133 Name Tag - Plastik 1,00 Peserta 1,00 buah 1,00 N/A var 7.300,00 7.300,00
Cetak Spanduk, Bahan Flexy
1.1.7.01.03.03.007.01470 5,00 Meter 1,00 keg 1,00 N/A fix 18.000,00 90.000,00
China
9.1.2.06.02.01.001.00058 Fotocopy - F.4 1,00 Peserta 350,00 lembar 1,00 N/A var 300,00 105.000,00
1.1.7.01.03.03.007.01321 Cetak Buku Modul 1,00 Peserta 2,00 Modul 1,00 N/A var 25.000,00 50.000,00
9.1.2.06.03.01.001.04826 Cetak Sertifikat 1,00 Peserta 1,00 lembar 1,00 N/A var 10.000,00 10.000,00
1.1.7.01.03.01.006.00360 Map Plastik Kancing 1,00 Peserta 1,00 buah 1,00 N/A var 12.000,00 12.000,00
328.800,00
7.3 Peralatan/sewa
Sewa Ruangan kelas dan
9.1.2.07.02.01.001.00183 1,00 Ruang 40,00 hari 1,00 N/A fix 200.000,00 8.000.000,00
Peralatan Bahasa
9.1.2.07.02.01.001.00154 Sewa Asrama Ketenagakerjaan 1,00 Peserta 1,00 Rung 40,00 Hari Var 75.000,00 3.000.000,00
11.000.000,00
Belanja Makan Dan
7.4
Minum
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 1,00 Orang 3,00 Dus 40,00 Hari fix 45.000,00 5.400.000,00
dan Minuman
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 10,00 Orang 1,00 Dus 1,00 N/A fix 45.000,00 450.000,00
dan Minuman
9.1.2.11.02.01.001.00068 Snack 10,00 Orang 1,00 kali 1,00 N/A fix 20.000,00 200.000,00
6.050.000,00
JUMLAH 61.378.800,00
Total Variabel Cost 3.238.800,00
Total Fix Cost 58.140.000,00
Total Cost 61.378.800,00
HSAK 6.145.800,00
63
1 KELOMPOK : DINAS KETENAGAKERJAAN
2 SUB KELOMPOK : Non Konstruksi
3 SUB- SUB KELOMPOK : Koordinasi Lintas Lembaga dan Kerja Sama dengan Sektor Swasta untuk Penyediaan Instruktur serta Sarana dan Prasarana Lembaga Pelatihan Kerja
4 ZONA WILAYAH SSH : Seluruh Wilayah
5 AKTIVITAS : Bahasa Korea
Kegiatan pelatihan bagi pencari kerja, dilaksanakan oleh OPD bertempat diluar kantor kerjasama dengan Lembaga Pelatihan Kerja Swasta dengan waktu pelaksanaan 40
DESKRIPSI AKTIVITAS :
hari kerja atau 400 JPL dengan jumlah Peserta 20 orang
6 SATUAN AKTIVITAS : Peserta
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Peserta Derivatif 1 Kelas Range 20 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
Instruktur Teknis (Madya) Tenaga
Pengajar yang memiliki
9.1.2.24.01.01.001.00187 400,00 OJ 1,00 Keg 1,00 N/A Fix 100.000,00 40.000.000,00
keterampilan teknis level madya
(Non PNS/Non ASN Pemkab)
Biaya Kediklatan, honorarium
9.1.2.23.01.01.001.01238 40,00 OH 1,00 Keg 1,00 N/A Fix 100.000,00 4.000.000,00
Pengamat Kelas
44.000.000,00
7.2 Bahan Material
1.1.7.01.03.01.005.00260 Buku Agenda Kerja 1,00 Peserta 1,00 buku 1,00 N/A var 25.000,00 25.000,00
1.1.7.01.03.01.001.01096 Ballpoint - Pen Stand 1,00 Peserta 1,00 buah 1,00 N/A var 10.000,00 10.000,00
1.1.7.01.03.01.007.00081 Penggaris Plastik 30 Cm 1,00 Peserta 1,00 buah 1,00 N/A var 2.000,00 2.000,00
9.1.2.01.09.01.001.06083 Pensil 2B 1,00 Peserta 1,00 buah 1,00 N/A var 5.000,00 5.000,00
1.1.7.01.03.13.001.00017 Serutan Pensil 1,00 Peserta 1,00 buah 1,00 N/A var 7.500,00 7.500,00
1.1.7.01.03.01.004.00144 Penghapus Pulpen Pensil 1,00 Peserta 1,00 pcs 1,00 N/A var 5.000,00 5.000,00
1.1.7.01.03.01.016.01133 Name Tag - Plastik 1,00 Peserta 1,00 buah 1,00 N/A var 7.300,00 7.300,00
Cetak Spanduk, Bahan Flexy
1.1.7.01.03.03.007.01470 5,00 Meter 1,00 keg 1,00 N/A fix 18.000,00 90.000,00
China
9.1.2.06.02.01.001.00058 Fotocopy - F.4 1,00 Peserta 350,00 lembar 1,00 N/A var 300,00 105.000,00
1.1.7.01.03.03.007.01321 Cetak Buku Modul 1,00 Peserta 2,00 Modul 1,00 N/A var 25.000,00 50.000,00
9.1.2.06.03.01.001.04826 Cetak Sertifikat 1,00 Peserta 1,00 lembar 1,00 N/A var 10.000,00 10.000,00
1.1.7.01.03.01.006.00360 Map Plastik Kancing 1,00 Peserta 1,00 buah 1,00 N/A var 12.000,00 12.000,00
328.800,00
7.3 Peralatan/sewa
Sewa Ruangan kelas dan Peralatan
9.1.2.07.02.01.001.00183 1,00 Ruang 40,00 hari 1,00 N/A fix 200.000,00 8.000.000,00
Bahasa
9.1.2.07.02.01.001.00154 Sewa Asrama Ketenagakerjaan 1,00 Peserta 1,00 Rung 40,00 Hari Var 75.000,00 3.000.000,00
11.000.000,00
7.4 Belanja Makan Dan Minum
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 1,00 Orang 3,00 Dus 40,00 Hari fix 45.000,00 5.400.000,00
dan Minuman
9.1.2.11.02.01.001.00068 Snack 10,00 Orang 1,00 kali 1,00 N/A fix 20.000,00 200.000,00
Makan/Nasi Dus Biaya Makanan
9.1.2.23.04.01.001.00021 10,00 Orang 1,00 Dus 1,00 N/A fix 45.000,00 450.000,00
dan Minuman
6.050.000,00
JUMLAH 61.378.800,00
Total Variabel Cost 3.238.800,00
Total Fix Cost 58.140.000,00
Total Cost 61.378.800,00
HSAK 6.145.800,00
DESKRIPSI AKTIVITAS : Kegiatan Pelatihan Kewirausahaan muda dilaksanakan di Luar Kantor (Fullday), Narasumber Luar Pemda, Peserta Non PNS, dalam waktu pelaksanaan 1 hari kerja
64
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : Dinas Ketahanan Pangan dan Perikanan
3 SUB- SUB KELOMPOK : Pengembangan Kelembagaan Usaha Pangan Masyarakat dan Toko Tani Indonesia
4 ZONA WILAYAH SSH : Pengambangan Usaha Pangan Masyarakat (PUPM) melalui Toko Tani Indonesia (TTI)
5 AKTIVITAS : Pengambangan Usaha Pangan Masyarakat (PUPM) melalui Toko Tani Indonesia (TTI)
DESKRIPSI AKTIVITAS : Pengembangan Kelembagaan Usaha Pangan Masyarakat dan Toko Tani Indonesia
6 SATUAN AKTIVITAS : Kelompok
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Kelompok Derivatif 1 Kelas Range 1 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
- - -
-
7.2 Bahan Material
9.1.2.02.06.01.001.03064 Telur ayam negeri 1,00 Kelompok 40,00 kg 1,00 N/A Var 28.600,00 1.144.000,00
9.1.2.02.06.01.001.02738 Gula Merah, Toros Kawung merah 1,00 Kelompok 30,00 kg 1,00 N/A Var 24.000,00 720.000,00
9.1.2.02.06.01.001.02623 Beras Premium 1,00 Kelompok 2.000,00 kg 1,00 N/A Var 14.000,00 28.000.000,00
Tepung terigu, Kering, bersih,
9.1.2.02.06.01.001.03081 tidak apek, halus, kualitas 1,00 Kelompok 25,00 kg 1,00 N/A Var 12.000,00 300.000,00
premium
32.288.800,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 32.288.800,00
Total Variabel Cost 32.288.800,00
Total Fix Cost -
Total Cost 32.288.800,00
HSAK 32.288.800,00
65
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : Dinas Ketahanan Pangan dan Perikanan
3 SUB- SUB KELOMPOK : Pemberdayaan Masyarakat dalam Penganekaragaman Konsumsi Pangan Berbasis Sumber Daya Lokal
4 ZONA WILAYAH SSH : Pekarangan Pangan Lestari (P2L) Konvensional
5 AKTIVITAS : Pekarangan Pangan Lestari (P2L) Konvensional
DESKRIPSI AKTIVITAS : Pemberdayaan Masyarakat dalam Penganekaragaman Konsumsi Pangan Berbasis Sumber Daya Lokal
6 SATUAN AKTIVITAS : Kelompok
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Kelompok Derivatif 1 Kelas Range 1 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
- - -
-
7.2 Bahan Material
1.1.7.01.01.01.008.00470 Baja Ringan 1,00 Kelompok 18,00 Batang 1,00 N/A Var 85.500,00 1.539.000,00
Springklip Stenles,
1.1.7.01.01.01.022.07994 Perekat/Pengikat Siku-siku 1,00 Kelompok 34,00 Meter 1,00 N/A Var 50.000,00 1.700.000,00
rangka kebun bibit
Plastik UV, tebal 200 mic, UV 12
1.1.7.01.01.01.022.07731 1,00 Kelompok 36,00 M2 1,00 N/A Var 90.000,00 3.240.000,00
%
Coran Tiang Utama, Ketebalan 0,5
1.1.7.01.01.01.022.07091 1,00 Kelompok 6,00 Buah 1,00 N/A Var 90.000,00 540.000,00
M
Coran Tiang Meja, Ketebalan 0,5
1.1.7.01.01.01.022.07090 M penyimpan penyemaian di 1,00 Kelompok 30,00 Buah 1,00 N/A Var 25.000,00 750.000,00
dalam kebun bibit
1.1.7.01.01.01.022.07902 Screen 1,00 Kelompok 65,00 M2 1,00 N/A Var 60.000,00 3.900.000,00
pintu, rangka baja ringan pintu
1.1.7.01.01.01.022.07711 1,00 Kelompok 1,00 Set 1,00 N/A Var 605.000,00 605.000,00
masuk kebun bibit
1.1.7.01.01.01.022.06958 Besi Siku Rak 1,00 Kelompok 19,00 Batang 1,00 N/A Var 80.000,00 1.520.000,00
1.1.7.01.01.01.022.08161 Wermes - Ukuran 5 Cm Galvanis 1,00 Kelompok 15,00 M2 1,00 N/A Var 117.000,00 1.755.000,00
1.1.7.01.01.01.006.00019 Cat Galvanis 1,00 Kelompok 2,00 Kg 1,00 N/A Var 101.200,00 202.400,00
Seed Tray, wadah penyemaian,
1.1.7.01.01.02.005.02035 1,00 Kelompok 30,00 Buah 1,00 N/A Var 46.200,00 1.386.000,00
kapasitas 128 Lubang
Polybag 30, Polybag tebal 100 mic
1.1.7.01.01.02.005.01996 warna hitam ukuran 30 cm x 30 1,00 Kelompok 50,00 Kg 1,00 N/A Var 40.000,00 2.000.000,00
cm (per 50 Pcs)
Mulsa, Mulsa plastik hitam perak
9.1.2.01.09.01.001.06053 CBA (L : 2 x 60 cm, P : 600 m, T : 1,00 Kelompok 1,00 Roll 1,00 N/A Var 1.100.000,00 1.100.000,00
37 micron)
1.1.7.01.01.02.005.02037 Selang Elastis, 1,00 Kelompok 50,00 Meter 1,00 N/A Var 20.000,00 1.000.000,00
1.1.7.01.01.01.022.07139 Drum Air - kapasitas 120 liter 1,00 Kelompok 1,00 Bh 1,00 N/A Var 200.000,00 200.000,00
9.1.2.01.09.01.001.05890 Emrat Plastik , Kapasitas 5 Liter 1,00 Kelompok 3,00 Buah 1,00 N/A Var 87.500,00 262.500,00
Cangkul Kecil, Dimensi panjang
1.3.2.04.01.01.003.00030 keseluruhan 41 cm / Lebar kepala 1,00 Kelompok 2,00 Buah 1,00 N/A Var 40.000,00 80.000,00
cangkul 12 cm
Garuk Kebun/ Taman, Besi
1.1.7.01.01.01.022.07191 Garukan Taman 4 Gigi/ Garpu 1,00 Kelompok 2,00 Buah 1,00 N/A Var 225.000,00 450.000,00
alat kebun
9.1.2.01.09.01.001.06139 Sekop 1,6-2MM, 1,00 Kelompok 2,00 Buah 1,00 N/A Var 40.500,00 81.000,00
Cangkul Besar, PACUL JUMBO
1.3.2.04.01.01.003.00029 CANGKUL 2,15KG 35x 23CM 1,00 Kelompok 1,00 Buah 1,00 N/A Var 153.000,00 153.000,00
SUPER Alat pembersih gulma
Fresh Handling Product
9.1.2.01.09.01.001.05894 (Pengemasan), Plastik bening, 1,00 Kelompok 50,00 Pack 1,00 N/A Var 20.000,00 1.000.000,00
kapasitas 2 kg
9.1.2.01.09.01.001.06014 Lem Tikus 1,00 Kelompok 3,00 Buah 1,00 N/A Var 21.000,00 63.000,00
1.1.7.01.01.02.001.00100 Pupuk NPK (BASF, nitrophoska) 1,00 Kelompok 70,00 Kg 1,00 N/A Var 35.000,00 2.450.000,00
Benih Pakcoy per 10 gr,
1.1.7.01.01.08.001.00736 1,00 Kelompok 10,00 Pc 1,00 N/A Var 47.800,00 478.000,00
Bersertifikat
1.1.7.01.01.08.001.00706 Benih Caisim, 25 gr 1,00 Kelompok 10,00 Pc 1,00 N/A Var 40.000,00 400.000,00
1.1.7.01.01.08.001.00742 Benih Selada bokor, 10 gr 1,00 Kelompok 10,00 Pc 1,00 N/A Var 47.000,00 470.000,00
1.1.7.01.01.08.001.00742 Benih Selada bokor, 10 gr 1,00 Kelompok 10,00 Pc 1,00 N/A Var 47.000,00 470.000,00
1.1.7.01.01.08.001.00715 Benih Kangkung, 1000 gr 1,00 Kelompok 10,00 Pc 1,00 N/A Var 80.000,00 800.000,00
1.1.7.01.01.08.001.00745 Benih Seledri (Biji), Bersertifikat 1,00 Kelompok 10,00 sachet 1,00 N/A Var 59.250,00 592.500,00
Benih Bayam Hijau, 500 gr
1.1.7.01.01.08.001.00684 1,00 Kelompok 10,00 Pc 1,00 N/A Var 85.000,00 850.000,00
bersertifikat
1.1.7.01.01.08.003.03796 Benih Bawang Daun 1,00 Kelompok 10,00 Pc 1,00 N/A Var 30.000,00 300.000,00
1.1.7.01.01.08.001.00759 Benih Tomat, 1,00 Kelompok 10,00 Bungkus 1,00 N/A Var 90.000,00 900.000,00
Benih Terong Ungu, Terong
1.1.7.01.01.08.001.00752 1,00 Kelompok 10,00 Pc 1,00 N/A Var 100.000,00 1.000.000,00
Hibrida Bersertifikat
Bibit Tanaman Toga, Bibit
1.1.7.01.01.08.003.03804 1,00 Kelompok 100,00 Buah 1,00 N/A Var 20.000,00 2.000.000,00
tanaman toga dalam Polybag
34.237.400,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 34.237.400,00
Total Variabel Cost 34.237.400,00
Total Fix Cost -
Total Cost 34.237.400,00
HSAK 34.237.400,00
66
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : Dinas Ketahanan Pangan dan Perikanan
3 SUB- SUB KELOMPOK : Pemberdayaan Masyarakat dalam Penganekaragaman Konsumsi Pangan Berbasis Sumber Daya Lokal
4 ZONA WILAYAH SSH : Pengembangan Industri pangan lokal (PIPL)
5 AKTIVITAS : Pengembangan Industri pangan lokal (PIPL)
DESKRIPSI AKTIVITAS : Pemberdayaan Masyarakat dalam Penganekaragaman Konsumsi Pangan Berbasis Sumber Daya Lokal
6 SATUAN AKTIVITAS : Kelompok
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Kelompok Derivatif 1 Kelas Range 1 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
- - -
-
7.2 Bahan Material
1.1.7.01.05.01.004.02417 Mesin Penepung, 1,00 Kelompok 1,00 Unit 1,00 N/A Var 15.000.000,00 15.000.000,00
Mesin Perajang Singkong, ,
1.1.7.01.05.01.004.02423 Kapasitas 100-200Kg/Jam, 200 1,00 Kelompok 1,00 Unit 1,00 N/A Var 6.600.000,00 6.600.000,00
Watt
1.1.7.01.05.01.004.02411 Mesin Parud, 1,00 Kelompok 1,00 Unit 1,00 N/A Var 6.750.000,00 6.750.000,00
Spinner, Kapasitas 5 Kg, bahan
1.1.7.01.05.01.004.02496 1,00 Kelompok 1,00 Unit 1,00 N/A Var 5.000.000,00 5.000.000,00
stainless steel
33.350.000,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 33.350.000,00
Total Variabel Cost 33.350.000,00
Total Fix Cost -
Total Cost 33.350.000,00
HSAK 33.350.000,00
1.1.7.01.07.02.002.00128 Pakan ikan protein min 28 %, 1,00 Kg 500,00 Kg 1,00 N/A Var 16.000,00 8.000.000,00
19.000.000,00
Belanja Makan Dan
7.4
Minum
- - -
-
JUMLAH 19.000.000,00
Total Variabel Cost 19.000.000,00
Total Fix Cost -
Total Cost 19.000.000,00
HSAK 19.000.000,00
1.1.7.01.07.02.002.00126 Pakan ikan hias 1,00 unit 20,00 kg 1,00 N/A Var 30.000,00 600.000,00
Akuarium uk. 100x40x40 cm,
1.1.7.01.05.01.004.02332 bahan kaca dengan ketebalan 5 1,00 unit 6,00 unit 1,00 N/A Var 550.000,00 3.300.000,00
mm, ukuran uk. 100x40x40 cm
Rak Besi Untuk Aquarium, P 104
1.1.7.01.05.01.004.02469 1,00 unit 3,00 unit 1,00 N/A Var 3.500.000,00 10.500.000,00
Cm X T 65 Cm X L 44 Cm
Pompa High Blower, pompa udara
1.1.7.01.05.01.004.02460 1,00 unit 1,00 unit 1,00 N/A Var 2.200.000,00 2.200.000,00
untuk kolam ikan, Power: 50 watt
Selang aerator, selang udara
1.1.7.01.05.01.004.02480 1,00 roll 1,00 roll 1,00 N/A Var 165.000,00 165.000,00
bahan plastik panjang 100 m
Batu aerasi, batu gelembung udara
1.1.7.01.05.01.004.02343 1,00 buah 6,00 buah 1,00 N/A Var 50.000,00 300.000,00
Diameter 30 mm, Tinggi 80 mm
17.545.000,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 17.545.000,00
Total Variabel Cost 17.545.000,00
Total Fix Cost -
Total Cost 17.545.000,00
HSAK 17.545.000,00
67
1 KELOMPOK : ANALISIS STANDAR BELANJA (ASB)
2 SUB KELOMPOK : Non Konstruksi
3 SUB- SUB KELOMPOK : Dinas Ketahanan Pangan dan Perikanan
4 ZONA WILAYAH SSH : Pengembangan Kapasitas Pembudi Daya Ikan Kecil
5 AKTIVITAS : Pengembangan Budidaya Ikan Mas
DESKRIPSI AKTIVITAS : Pengembangan Kapasitas Pembudi Daya Ikan Kecil
6 SATUAN AKTIVITAS : Kelompok
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Kelompok Derivatif 1 Kelas Range 1 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
- - -
-
7.2 Bahan Material
1.1.7.01.01.11.002.00392 Benih ikan mas (beloan), 5-8 cm 1,00 Kg 200,00 Kg 1,00 N/A Var 80.000,00 16.000.000,00
1.1.7.01.07.02.002.00128 Pakan ikan protein min 28 %, 1,00 Kg 500,00 Kg 1,00 N/A Var 16.000,00 8.000.000,00
24.000.000,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 24.000.000,00
Total Variabel Cost 24.000.000,00
Total Fix Cost -
Total Cost 24.000.000,00
HSAK 24.000.000,00
1.1.7.01.07.02.002.00130 Pakan ikan protein min 35 %, 1,00 Kg 450,00 Kg 1,00 N/A Var 20.000,00 9.000.000,00
12.600.000,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 12.600.000,00
Total Variabel Cost 12.600.000,00
Total Fix Cost -
Total Cost 12.600.000,00
HSAK 12.600.000,00
68
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : Dinas Ketahanan Pangan dan Perikanan
3 SUB- SUB KELOMPOK : Pemberian Fasilitas bagi Pelaku Usaha Perikanan Skala Mikro dan Kecil dalam 1 (Satu) Daerah Kabupaten/Kota
4 ZONA WILAYAH SSH : Sarana dan Prasarana Pengolahan Ikan abon, nugget, bakso, siomay, otak-otak ikan
5 AKTIVITAS : Sarana dan Prasarana Pengolahan Ikan abon, nugget, bakso, siomay, otak-otak ikan
DESKRIPSI AKTIVITAS : Pemberian Fasilitas bagi Pelaku Usaha Perikanan Skala Mikro dan Kecil dalam 1 (Satu) Daerah Kabupaten/Kota
6 SATUAN AKTIVITAS : Kelompok
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Kelompok Derivatif 1 Kelas Range 1 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
- - -
-
7.2 Bahan Material
Spinner, Kapasitas 3 Kg, bahan
1.1.7.01.05.01.004.02495 1,00 buah 1,00 buah 1,00 N/A Var 3.500.000,00 3.500.000,00
stainless steel
1.3.2.05.02.06.077.02687 Kompor Gas 2 Tungku 1,00 buah 1,00 buah 1,00 N/A Var 796.000,00 796.000,00
9.1.2.01.09.01.001.06180 Tabung Gas dan Selang Regulator, 1,00 buah 1,00 buah 1,00 N/A Var 350.000,00 350.000,00
Food Procesor, Kap. 1,5 Liter,
1.1.7.01.05.01.004.02361 Daya 650 watt, lapisan berbahan 1,00 buah 1,00 buah 1,00 N/A Var 1.700.000,00 1.700.000,00
stainless
Mesin Press Plastik Kedap Udara
1.1.7.01.05.01.004.02427 1,00 buah 1,00 buah 1,00 N/A Var 2.119.500,00 2.119.500,00
Basah Vacum Press Sealer
Penutup Sambungan/Joint Sealer
1.1.7.01.01.01.022.07679 1,00 buah 1,00 buah 1,00 N/A Var 700.000,00 700.000,00
Tebal 20 Mm
Timbangan Kue Digital, Peralatan
untuk pelatihan, Timbangan
9.1.2.01.09.01.001.06209 1,00 buah 1,00 buah 1,00 N/A Var 195.000,00 195.000,00
Digital LCD Display Akurasi 0,1g,
Bahan Pelatihan Tata Boga,
9.360.500,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 9.360.500,00
Total Variabel Cost 9.360.500,00
Total Fix Cost -
Total Cost 9.360.500,00
HSAK 9.360.500,00
65.000,00
JUMLAH 2.438.000,00
Total Variabel Cost 215.000,00
Total Fix Cost 2.223.000,00
Total Cost 2.438.000,00
HSAK 326.150,00
69
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : Bimbingan Sosial
3 SUB- SUB KELOMPOK : Pemberian Bantuan bagi Fakir Miskin
4 ZONA WILAYAH SSH : Seluruh Wialayah Kabupaten Bandung
5 AKTIVITAS : Pemberian Bantuan Ternak Domba bagi KUBE KFM
DESKRIPSI AKTIVITAS : Pemberian bantuan hanya diberikan 1 (satu) kali dengan CPCL yang berbeda setiap tahunnya
6 SATUAN AKTIVITAS : Peserta
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Peserta Derivatif 1 Kelas Range 1 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
- - -
-
7.2 Bahan Material
Domba Jantan, Berat badan
minumal 35 kg, tinggi minimal 70
cm,usia minimal 14 bulan, sehat
1.1.7.01.01.11.001.00338 dan tidak cacat , siap kawin dan 1,00 kelompok 3,00 Ekor Var 3.500.000,00 10.500.000,00
telingga relative kecil dan kokoh,
bentuk telingga rumpung sampai
ngadaun iris
9.1.2.01.09.01.001.05967 Karung Beras, Kapasitas 10 kg 1,00 Kelompok 1,00 Buah Var 6.000,00 6.000,00
15.000.000,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 15.000.000,00
Total Variabel Cost 15.000.000,00
Total Fix Cost -
Total Cost 15.000.000,00
HSAK 15.000.000,00
70
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : Bimbingan Sosial
3 SUB- SUB KELOMPOK : Pemberian Bantuan Bagi Fakir Miskin
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Pemberian Bantuan Konveksi bagi KUBE KFM
DESKRIPSI AKTIVITAS : Pemberian bantuan hanya diberikan 1 (satu) kali dengan CPCL yang berbeda setiap tahunnya
6 SATUAN AKTIVITAS : Peserta
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver 1 Peserta Derivatif 1 Kelas Range 1 HARGA JUMLAH
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
- - -
-
7.2 Bahan Material
1.1.7.01.05.01.004.02408 Mesin Jahit Listrik 1,00 Kelompok 5,00 Buah Var 3.386.000,00 16.930.000,00
16.930.000,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 16.930.000,00
Total Variabel Cost 16.930.000,00
Total Fix Cost -
Total Cost 16.930.000,00
HSAK 16.930.000,00
71
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : Bimbingan Sosial
3 SUB- SUB KELOMPOK : Pemberian Bantuan Bagi Fakir Miskin
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Pemberian Bantuan Olah Pangan bagi KUBE WRSE
DESKRIPSI AKTIVITAS : Pemberian bantuan hanya diberikan 1 (satu) kali dengan CPCL yang berbeda setiap tahunnya
6 SATUAN AKTIVITAS : Peserta
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Peserta Derivatif 1 Kelas Range 1 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
- - -
-
7.2 Bahan Material
Oven Tangkring, Peralatan untuk
9.1.2.01.09.01.001.06060 pelatihan, Oven Stainless Ukuran 1,00 Kelompok 3,00 Buah Var 500.000,00 1.500.000,00
40
Mixer Duduk, Peralatan untuk
9.1.2.01.09.01.001.06049 pelatihan, 170 Watt 5 Fungsi 1,00 Kelompok 2,00 Buah Var 600.500,00 1.201.000,00
Kecepatan
1.3.2.05.02.06.077.02570 Blender, Blender 1,00 Kelompok 2,00 Buah Var 809.900,00 1.619.800,00
1.3.2.05.02.06.077.02687 Kompor Gas 2 Tungku 1,00 Kelompok 2,00 Buah Var 796.000,00 1.592.000,00
Tabung gas dan selang regulator,
1.3.2.05.02.06.077.02883 1,00 Kelompok 2,00 Buah Var 900.200,00 1.800.400,00
Standar SNI
Timbangan Kue Digital, Peralatan
untuk pelatihan, Timbangan
9.1.2.01.09.01.001.06209 1,00 Kelompok 3,00 Buah Var 195.000,00 585.000,00
Digital LCD Display Akurasi 0,1g,
Bahan Pelatihan Tata Boga,
Loyang Kue, Bahan
9.1.2.01.09.01.001.06022 alumaniumuk. 24x24x 3 cm, 1,00 Kelompok 31,00 Buah Var 30.000,00 930.000,00
Loyang persegi
9.1.2.02.06.01.001.03079 Tepung Terigu 1,00 Kelompok 100,00 Kg Var 14.000,00 1.400.000,00
Minyak Goreng, Pouch 2 liter, SNI,
9.1.2.02.06.01.001.02924 1,00 Kelompok 30,00 Pouch Var 32.000,00 960.000,00
bening bersih, Premium
bahan pelatihan Tata boga Pastry
9.1.2.01.09.01.001.05811 1,00 Kelompok 50,00 Kg Var 23.800,00 1.190.000,00
Gula Pasir, kecakapan hidup
15.664.800,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 15.664.800,00
Total Variabel Cost 15.664.800,00
Total Fix Cost -
Total Cost 15.664.800,00
HSAK 15.664.800,00
9.1.2.01.09.01.001.05967 Karung Beras, Kapasitas 10 kg 1,00 Kelompok 1,00 Buah Var 6.000,00 6.000,00
15.000.000,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 15.000.000,00
Total Variabel Cost 15.000.000,00
Total Fix Cost -
Total Cost 15.000.000,00
HSAK 15.000.000,00
72
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : Bimbingan Sosial
3 SUB- SUB KELOMPOK : Pemberian Bantuan Bagi Fakir Miskin
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Pemberian Bantuan Bagi KUBE Konveksi
DESKRIPSI AKTIVITAS : Pemberian bantuan hanya diberikan 1 (satu) kali dengan CPCL yang berbeda setiap tahunnya
6 SATUAN AKTIVITAS : Peserta
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Peserta Derivatif 1 Kelas Range 1 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
- - -
-
7.2 Bahan Material
1.1.7.01.05.01.004.02408 Mesin Jahit Listrik 1,00 Kelompok 5,00 Buah Var 3.386.000,00 16.930.000,00
16.930.000,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 16.930.000,00
Total Variabel Cost 16.930.000,00
Total Fix Cost -
Total Cost 16.930.000,00
HSAK 16.930.000,00
6.000.000,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 6.000.000,00
Total Variabel Cost 6.000.000,00
Total Fix Cost -
Total Cost 6.000.000,00
HSAK 6.000.000,00
73
1 KELOMPOK : Non Konstruksi
2 SUB KELOMPOK : Bimbingan Sosial
3 SUB- SUB KELOMPOK : Pengadaan Barang Bantuan bagi Orang Tua Penyandang Disabilitas
4 ZONA WILAYAH SSH : Seluruh Wilayah Kabupaten Bandung
5 AKTIVITAS : Pemberian Bantuan UEP Warungan bagi Orang Tua Penyandang Disabilitas
DESKRIPSI AKTIVITAS : Pemberian bantuan hanya diberikan 1 (satu) kali dengan CPCL yang berbeda setiap tahunnya
6 SATUAN AKTIVITAS : Peserta
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Peserta Derivatif 1 Kelas Range 1 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
- - -
-
7.2 Bahan Material
9.1.2.02.06.01.001.02623 Beras Premium 1,00 Orang 50,00 Buah Var 14.000,00 700.000,00
9.1.2.02.06.01.001.02914 Mie Instan 1,00 Orang 4,00 Dus Var 130.000,00 520.000,00
1.1.7.01.03.13.001.00019 Sikat Gigi 1,00 Orang 4,00 Pak Var 28.125,00 112.500,00
3.326.500,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 3.326.500,00
Total Variabel Cost 3.326.500,00
Total Fix Cost -
Total Cost 3.326.500,00
HSAK 3.326.500,00
1.3.2.05.02.06.077.02560 Baskom Plastik (sedang) 1,00 Orang 2,00 Buah Var 40.000,00 80.000,00
9.1.2.01.05.01.001.01539 Sarung Tangan Plastik 1,00 Orang 2,00 Box Var 20.000,00 40.000,00
3.989.200,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 3.989.200,00
Total Variabel Cost 3.989.200,00
Total Fix Cost -
Total Cost 3.989.200,00
HSAK 3.989.200,00
74
1 KELOMPOK : DINAS SOSIAL
2 SUB KELOMPOK : Non Konstruksi
3 SUB- SUB KELOMPOK : Bimbingan Sosial
4 ZONA WILAYAH SSH : Pemberian bantuan bagi penyandang cacat produktif
5 AKTIVITAS : Pemberian bantuan UEP Ternak Domba
DESKRIPSI AKTIVITAS : Pemberian bantuan hanya diberikan 1 (satu) kali dengan CPCL yang berbeda setiap tahunnya
6 SATUAN AKTIVITAS : Peserta
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Peserta Derivatif 1 Kelas Range 1 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
- - -
-
7.2 Bahan Material
Domba Jantan, Berat badan
minumal 35 kg, tinggi minimal 70
cm,usia minimal 14 bulan, sehat
1.1.7.01.01.11.001.00338 dan tidak cacat , siap kawin dan 1,00 Orang 1,00 Ekor Var 3.500.000,00 3.500.000,00
telingga relative kecil dan kokoh,
bentuk telingga rumpung sampai
ngadaun iris
6.000.000,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 6.000.000,00
Total Variabel Cost 6.000.000,00
Total Fix Cost -
Total Cost 6.000.000,00
HSAK 6.000.000,00
9.1.2.02.06.01.001.02914 Mie Instan 1,00 Orang 2,00 Dus Var 130.000,00 260.000,00
1.1.7.01.03.13.001.00019 Sikat Gigi 1,00 Orang 4,00 Pak Var 28.125,00 112.500,00
9.1.2.01.09.01.001.06162 Shampo Botol 1,00 Orang 2,00 Botol Var 22.000,00 44.000,00
3.040.200,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 3.040.200,00
Total Variabel Cost 3.040.200,00
Total Fix Cost -
Total Cost 3.040.200,00
HSAK 3.040.200,00
75
1 KELOMPOK : DINAS SOSIAL
2 SUB KELOMPOK : Non Kontruksi
3 SUB- SUB KELOMPOK : Pembinaan Anak Terlantar
4 ZONA WILAYAH SSH : Pemberian Bantuan Bagi Orang Tua ABH
5 AKTIVITAS : Pemberian Bantuan Bagi UEP Usaha Olah Pangan Kue
DESKRIPSI AKTIVITAS : Pemberian bantuan hanya diberikan 1 (satu) kali dengan CPCL yang berbeda setiap tahunnya
6 SATUAN AKTIVITAS : Peserta
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Peserta Derivatif 1 Kelas Range 1 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
- - -
-
7.2 Bahan Material
1.3.2.05.02.06.077.02687 Kompor Gas 2 Tungku 1,00 Orang 1,00 Buah Var 796.000,00 796.000,00
Tabung gas dan selang regulator,
1.3.2.05.02.06.077.02883 1,00 Orang 1,00 set Var 900.200,00 900.200,00
Standar SNI
Oven, Bahan plat alumanium anti
karat, rak 3 susun,
9.1.2.01.09.01.001.06062 1,00 Orang 1,00 Buah Var 320.000,00 320.000,00
terdapatputaranhawadiatas,
dimensi 37x35x32 cm.
Loyang Kue, Bahan
9.1.2.01.09.01.001.06022 alumaniumuk. 24x24x 3 cm, 1,00 Orang 9,00 Buah Var 30.000,00 270.000,00
Loyang persegi
Loyang Bolu, Bahan alumanium,
9.1.2.01.09.01.001.06021 Diameter 16 cm. tinggi 7 cm 1,00 Orang 2,00 Buah Var 35.000,00 70.000,00
Loyang bulat tanpa sambungan
3.851.600,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 3.851.600,00
Total Variabel Cost 3.851.600,00
Total Fix Cost -
Total Cost 3.851.600,00
HSAK 3.851.600,00
6.000.000,00
7.3 Peralatan/sewa
0 - -
-
JUMLAH 6.000.000,00
Total Variabel Cost 6.000.000,00
Total Fix Cost -
Total Cost 6.000.000,00
HSAK 6.000.000,00
76
1 KELOMPOK : DINAS SOSIAL
2 SUB KELOMPOK : Non Konstruksi
3 SUB- SUB KELOMPOK : Pembinaan Anak Terlantar
4 ZONA WILAYAH SSH : Pemberian Bantuan Bagi Anak Terlantar
5 AKTIVITAS : Pengadaan bahan baku bagi UEP Warungan
DESKRIPSI AKTIVITAS : Pemberian bantuan hanya diberikan 1 (satu) kali dengan CPCL yang berbeda setiap tahunnya
6 SATUAN AKTIVITAS : Peserta
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Peserta Derivatif 1 Kelas Range 1 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
- - -
-
7.2 Bahan Material
9.1.2.02.06.01.001.02623 Beras Premium 1,00 Orang 26,00 Kg Var 14.000,00 364.000,00
9.1.2.02.06.01.001.02914 Mie Instan 1,00 Orang 5,00 Dus Var 130.000,00 650.000,00
1.1.7.01.03.13.001.00019 Sikat Gigi 1,00 Orang 4,00 Pak Var 28.125,00 112.500,00
2.980.000,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 2.980.000,00
Total Variabel Cost 2.980.000,00
Total Fix Cost -
Total Cost 2.980.000,00
HSAK 2.980.000,00
9.1.2.01.09.01.001.05862 Celemek, Bahan Kain 1,00 Orang 3,00 Buah Var 24.000,00 72.000,00
Mesin Gilingan Mie, Pangsit, Kue
1.1.7.01.05.01.004.02403 Pastel, Pisang Molen, Pasta, 1,00 Orang 1,00 Buah Var 200.000,00 200.000,00
Cheese Stick
9.1.2.02.06.01.001.03079 Tepung Terigu 1,00 Orang 25,00 Kg Var 14.000,00 350.000,00
9.1.2.01.09.01.001.05850 Botol Aplikator, 1,00 Orang 4,00 Buah Var 5.930,00 23.720,00
4.094.320,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 4.094.320,00
Total Variabel Cost 4.094.320,00
Total Fix Cost -
Total Cost 4.094.320,00
HSAK 4.094.320,00
77
1 KELOMPOK : DINAS SOSIAL
2 SUB KELOMPOK : Non Konstruksi
3 SUB- SUB KELOMPOK : Pembinaan Anak Terlantar
4 ZONA WILAYAH SSH : Pemberian Bantuan Bagi Anak Terlantar
5 AKTIVITAS : Pemberian bantuan UEP Ternak Domba
DESKRIPSI AKTIVITAS : Pemberian bantuan hanya diberikan 1 (satu) kali dengan CPCL yang berbeda setiap tahunnya
6 SATUAN AKTIVITAS : Peserta
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Peserta Derivatif 1 Kelas Range 1 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
- - -
-
7.2 Bahan Material
Domba Jantan, Berat badan
minumal 35 kg, tinggi minimal 70
cm,usia minimal 14 bulan, sehat
1.1.7.01.01.11.001.00338 dan tidak cacat , siap kawin dan 1,00 Orang 1,00 Ekor Var 3.500.000,00 3.500.000,00
telingga relative kecil dan kokoh,
bentuk telingga rumpung sampai
ngadaun iris
Domba lokal Betina umur 12 - 24
1.1.7.01.01.11.001.00339 1,00 Orang 1,00 Ekor Var 3.300.000,00 3.300.000,00
bulan , umur 12 - 24 bulan
Multivitamin, Kombinasi lengkap
vitamin A, D, E, K, B dan C,
Kombinasi lengkap vitamin A, D,
1.1.7.01.04.01.001.15443 1,00 Orang 1,00 Botl Var 100.000,00 100.000,00
E, K, B dan C injeksi untuk
meningkatkan produktivitas
hewan isi 50 ml
6.900.000,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 6.900.000,00
Total Variabel Cost 6.900.000,00
Total Fix Cost -
Total Cost 6.900.000,00
HSAK 6.900.000,00
3.386.000,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 3.386.000,00
Total Variabel Cost 3.386.000,00
Total Fix Cost -
Total Cost 3.386.000,00
HSAK 3.386.000,00
78
1 KELOMPOK : DINAS SOSIAL
2 SUB KELOMPOK : Non Konstruksi
3 SUB- SUB KELOMPOK : Pembinaan Anak Terlantar
4 ZONA WILAYAH SSH : Pemberian Bantuan Bagi Orang Tua Balita Terlantar
5 AKTIVITAS : Pemberian Bantuan Bagi Orang Tua Balita Terlantar Usaha Warungan
DESKRIPSI AKTIVITAS : Pemberian bantuan hanya diberikan 1 (satu) kali dengan CPCL yang berbeda setiap tahunnya
6 SATUAN AKTIVITAS : Peserta
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Peserta Derivatif 1 Kelas Range 1 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
- - -
-
7.2 Bahan Material
9.1.2.02.06.01.001.02623 Beras Premium 1,00 Orang 25,00 Kg Var 14.000,00 350.000,00
9.1.2.02.06.01.001.02914 Mie Instan 1,00 Orang 5,00 Buah Var 130.000,00 650.000,00
1.1.7.01.01.05.007.00294 Sikat Gigi, 1,00 Orang 15,00 Buah Var 10.000,00 150.000,00
9.1.2.01.05.01.001.01551 Shampoo Shampoo Mandi 170 ml 1,00 Orang 5,00 Botol Var 39.500,00 197.500,00
3.040.200,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 3.040.200,00
Total Variabel Cost 3.040.200,00
Total Fix Cost -
Total Cost 3.040.200,00
HSAK 3.040.200,00
Susuk Pengorengan,
9.1.2.01.09.01.001.06177 Bahanalumaniumpanjang 32 cm, 1,00 Orang 1,00 Pcs Var 46.100,00 46.100,00
lebar 9,5 cm, pegangan plastic
Serok pengorengan, Bahan
9.1.2.01.09.01.001.06160 satanless, Diameter 20 cm 1,00 Orang 2,00 Buah Var 53.450,00 106.900,00
panjang 35 cm, gagang plastik
9.1.2.02.06.01.001.02739 Gula Pasir 1,00 Orang 8,00 Kg Var 21.500,00 172.000,00
9.1.2.01.05.01.001.01539 Sarung Tangan Plastik 1,00 Orang 2,00 Dus Var 20.000,00 40.000,00
3.635.000,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 3.635.000,00
Total Variabel Cost 3.635.000,00
Total Fix Cost -
Total Cost 3.635.000,00
HSAK 3.635.000,00
79
1 KELOMPOK : DINAS SOSIAL
2 SUB KELOMPOK : Non Kontruksi
3 SUB- SUB KELOMPOK : Pembinaan Anak Terlantar
4 ZONA WILAYAH SSH : Pemberian Bantuan Bagi Orang Tua Balita Terlantar
5 AKTIVITAS : Pemberian Bantuan Usaha Olah Pangan Kue Bagi Orang Tua Balita Terlantar
DESKRIPSI AKTIVITAS : Pemberian bantuan hanya diberikan 1 (satu) kali dengan CPCL yang berbeda setiap tahunnya
6 SATUAN AKTIVITAS : Peserta
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Peserta Derivatif 1 Kelas Range 1 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
- - -
-
7.2 Bahan Material
Kompor Gas 2 tungku, 2 tungku,
lubang api standar, bodi hitam,
9.1.2.01.09.01.001.05992 1,00 Orang 1,00 Unit Var 343.000,00 343.000,00
Dimensi 40 x 72 x 12 cm, Garansi
Pabrik, Model RI 522S.
Tabung Gas dan Isi, Gas Melon 3
9.1.2.01.09.01.001.06179 1,00 Orang 1,00 Unit Var 192.000,00 192.000,00
kg, Isi , Pertamina
Oven, Bahan plat alumanium anti
karat, rak 3 susun,
9.1.2.01.09.01.001.06062 1,00 Orang 1,00 Buah Var 320.000,00 320.000,00
terdapatputaranhawadiatas,
dimensi 37x35x32 cm.
9.1.2.01.09.01.001.06050 Mixer, 1,00 Orang 1,00 Set Var 485.000,00 485.000,00
Loyang Kue, Bahan
9.1.2.01.09.01.001.06022 alumaniumuk. 24x24x 3 cm, 1,00 Orang 6,00 Buah Var 30.000,00 180.000,00
Loyang persegi
Baskom Plastik (sedang), Bahan
9.1.2.01.09.01.001.05834 1,00 Orang 4,00 Buah Var 10.000,00 40.000,00
Plastik
9.1.2.01.09.01.001.05862 Celemek, Bahan Kain 1,00 Orang 2,00 buah Var 24.000,00 48.000,00
Mesin Gilingan Mie, Pangsit, Kue
1.1.7.01.05.01.004.02403 Pastel, Pisang Molen, Pasta, 1,00 Orang 1,00 Buah Var 200.000,00 200.000,00
Cheese Stick
9.1.2.02.06.01.001.03079 Tepung Terigu 1,00 Orang 25,00 Kg Var 14.000,00 350.000,00
9.1.2.01.09.01.001.05983 Kentang, Bahan Baku Pelatihan 1,00 Orang 1,00 Kg Var 16.300,00 16.300,00
80
1 KELOMPOK : DINAS SOSIAL
2 SUB KELOMPOK : Non Konstruksi
3 SUB- SUB KELOMPOK : Pemberian Jaminan Sosial
4 ZONA WILAYAH SSH : Bimbingan Sosial Keterampilan bagi Lanjut Usia Potensial
5 AKTIVITAS : Pengadaan bahan baku Warungan bagi LUP
DESKRIPSI AKTIVITAS : Pemberian bantuan hanya diberikan 1 (satu) kali dengan CPCL yang berbeda setiap tahunnya
6 SATUAN AKTIVITAS : Peserta
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Peserta Derivatif 1 Kelas Range 1 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
- - -
-
7.2 Bahan Material
9.1.2.02.06.01.001.02623 Beras Premium 1,00 Orang 25,00 Kg Var 14.000,00 350.000,00
9.1.2.02.06.01.001.02914 Mie Instan 1,00 Orang 4,00 Buah Var 130.000,00 520.000,00
1.1.7.01.01.05.007.00294 Sikat Gigi, 1,00 Orang 11,00 Buah Var 10.000,00 110.000,00
9.1.2.01.05.01.001.01551 Shampoo Shampoo Mandi 170 ml 1,00 Orang 5,00 Botol Var 39.500,00 197.500,00
2.978.000,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 2.978.000,00
Total Variabel Cost 2.978.000,00
Total Fix Cost -
Total Cost 2.978.000,00
HSAK 2.978.000,00
9.1.2.01.09.01.001.05862 Celemek, Bahan Kain 1,00 Orang 1,00 Buah Var 24.000,00 24.000,00
81
1 KELOMPOK : DINAS SOSIAL
2 SUB KELOMPOK : Non Kontruksi
3 SUB- SUB KELOMPOK : Pemberian Jaminan Sosial
4 ZONA WILAYAH SSH : Bimbingan Sosial Keterampilan bagi Lanjut Usia Potensial
5 AKTIVITAS : Pengadaan bahan baku Olah Pangan Kue bagi LUP
DESKRIPSI AKTIVITAS : Pemberian bantuan hanya diberikan 1 (satu) kali dengan CPCL yang berbeda setiap tahunnya
6 SATUAN AKTIVITAS : Peserta
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Peserta Derivatif 1 Kelas Range 1 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
- - -
-
7.2 Bahan Material
Kompor Gas 2 tungku, 2 tungku,
lubang api standar, bodi hitam,
9.1.2.01.09.01.001.05992 1,00 Orang 1,00 Unit Var 343.000,00 343.000,00
Dimensi 40 x 72 x 12 cm, Garansi
Pabrik, Model RI 522S.
Tabung Gas dan Isi, Gas Melon 3
9.1.2.01.09.01.001.06179 1,00 Orang 1,00 Buah Var 192.000,00 192.000,00
kg, Isi , Pertamina
Oven, Bahan plat alumanium anti
karat, rak 3 susun,
9.1.2.01.09.01.001.06062 1,00 Orang 1,00 Buah Var 320.000,00 320.000,00
terdapatputaranhawadiatas,
dimensi 37x35x32 cm.
Loyang Kue, Bahan
9.1.2.01.09.01.001.06022 alumaniumuk. 24x24x 3 cm, 1,00 Orang 10,00 Buah Var 30.000,00 300.000,00
Loyang persegi
Loyang Bolu, Bahan alumanium,
9.1.2.01.09.01.001.06021 Diameter 16 cm. tinggi 7 cm 1,00 Orang 3,00 Buah Var 35.000,00 105.000,00
Loyang bulat tanpa sambungan
1.3.2.05.02.06.077.02560 Baskom Plastik (sedang) 1,00 Orang 5,00 Buah Var 40.000,00 200.000,00
9.1.2.01.09.01.001.05862 Celemek, Bahan Kain 1,00 Orang 2,00 Buah Var 24.000,00 48.000,00
Mesin Gilingan Mie, Pangsit, Kue
1.1.7.01.05.01.004.02403 Pastel, Pisang Molen, Pasta, 1,00 Orang 1,00 Buah Var 200.000,00 200.000,00
Cheese Stick
9.1.2.02.06.01.001.03079 Tepung Terigu 1,00 Orang 25,00 Kg Var 14.000,00 350.000,00
3.389.400,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 3.389.400,00
Total Variabel Cost 3.389.400,00
Total Fix Cost -
Total Cost 3.389.400,00
HSAK 3.389.400,00
82
1 KELOMPOK : DINAS SOSIAL
2 SUB KELOMPOK : Non Konstruksi
3 SUB- SUB KELOMPOK : Pemberian Jaminan Sosial
4 ZONA WILAYAH SSH : Pemberian Jaminan Sosial Lanjut Usia Terlantar
5 AKTIVITAS : Pemberian Bantuan Jaminan Hidup Bagi Lansia tanpa Bimsos
DESKRIPSI AKTIVITAS : Pemberian bantuan hanya diberikan 1 (satu) kali dengan CPCL yang berbeda setiap tahunnya
6 SATUAN AKTIVITAS : Peserta
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Peserta Derivatif 1 Kelas Range 1 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
- - -
-
7.2 Bahan Material
9.1.2.01.09.01.001.05974 Kasur 1,00 Orang 1,00 Buah Var 900.000,00 900.000,00
9.1.2.01.09.01.001.06124 Samping Kebat/ Samping Sarung 1,00 Orang 1,00 Buah Var 85.000,00 85.000,00
9.1.2.01.09.01.001.05926 Handuk Mandi 1,00 Orang 1,00 Buah Var 75.000,00 75.000,00
9.1.2.01.09.01.001.06064 Pakaian Atasan Pria /Wanita 1,00 Orang 6,00 Buah Var 100.000,00 600.000,00
9.1.2.01.09.01.001.06148 Sendal Jepit 1,00 Orang 2,00 Pcs Var 23.000,00 46.000,00
9.1.2.01.09.01.001.06146 Selimut Flanel 1,00 Orang 1,00 Buah Var 90.000,00 90.000,00
9.1.2.01.09.01.001.06159 Seprey Katun No 3 1,00 Orang 1,00 Buah Var 150.000,00 150.000,00
9.1.2.01.09.01.001.05833 Bantal Busa 1,00 Orang 1,00 Buah Var 85.000,00 85.000,00
9.1.2.01.09.01.001.06196 Termos Air panas 1,00 Orang 1,00 Buah Var 80.000,00 80.000,00
1.1.7.01.03.13.001.00008 Pasta Gigi 1,00 Orang 4,00 Buah Var 28.750,00 115.000,00
1.1.7.01.01.05.007.00294 Sikat Gigi, 1,00 Orang 5,00 Buah Var 10.000,00 50.000,00
Sabun Mandi Sabun mandi
9.1.2.01.05.01.001.01513 1,00 Orang 7,00 Buah Var 5.500,00 38.500,00
batangan 110 gr
9.1.2.01.05.01.001.01551 Shampoo Shampoo Mandi 170 ml 1,00 Orang 3,00 Botol Var 39.500,00 118.500,00
2.500.000,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 2.500.000,00
Total Variabel Cost 2.500.000,00
Total Fix Cost -
Total Cost 2.500.000,00
HSAK 2.500.000,00
83
1 KELOMPOK : DINAS SOSIAL
2 SUB KELOMPOK : Non Konstruksi
3 SUB- SUB KELOMPOK : Penanganan bagi Eks. Gelandangan dan Pengemis (Gepeng)
4 ZONA WILAYAH SSH : Pemberian Bantuan Bagi Eks. Gelandangan dan Pengemis (Gepeng)
5 AKTIVITAS : Pemberian Bantuan Stimulan UEP Olah pangan Kue bagi Eks. Gelandangan dan Pengemis (Gepeng)
DESKRIPSI AKTIVITAS : Pemberian bantuan hanya diberikan 1 (satu) kali dengan CPCL yang berbeda setiap tahunnya
6 SATUAN AKTIVITAS : Peserta
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Peserta Derivatif 1 Kelas Range 1 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
- - -
-
7.2 Bahan Material
Kompor Gas 2 tungku, 2 tungku,
lubang api standar, bodi hitam,
9.1.2.01.09.01.001.05992 1,00 Orang 1,00 Unit Var 343.000,00 343.000,00
Dimensi 40 x 72 x 12 cm, Garansi
Pabrik, Model RI 522S.
Tabung Gas dan Isi, Gas Melon 3
9.1.2.01.09.01.001.06179 1,00 Orang 1,00 Buah Var 192.000,00 192.000,00
kg, Isi , Pertamina
Oven, Bahan plat alumanium anti
karat, rak 3 susun,
9.1.2.01.09.01.001.06062 1,00 Orang 1,00 Buah Var 320.000,00 320.000,00
terdapatputaranhawadiatas,
dimensi 37x35x32 cm.
Loyang Kue, Bahan
9.1.2.01.09.01.001.06022 alumaniumuk. 24x24x 3 cm, 1,00 Orang 10,00 Buah Var 30.000,00 300.000,00
Loyang persegi
Loyang Bolu, Bahan alumanium,
9.1.2.01.09.01.001.06021 Diameter 16 cm. tinggi 7 cm 1,00 Orang 3,00 Buah Var 35.000,00 105.000,00
Loyang bulat tanpa sambungan
1.3.2.05.02.06.077.02560 Baskom Plastik (sedang) 1,00 Orang 6,00 Buah Var 40.000,00 240.000,00
9.1.2.01.09.01.001.05862 Celemek, Bahan Kain 1,00 Orang 4,00 Buah Var 24.000,00 96.000,00
Mesin Gilingan Mie, Pangsit, Kue
1.1.7.01.05.01.004.02403 Pastel, Pisang Molen, Pasta, 1,00 Orang 1,00 Buah Var 200.000,00 200.000,00
Cheese Stick
9.1.2.02.06.01.001.03079 Tepung Terigu 1,00 Orang 25,00 Kg Var 14.000,00 350.000,00
3.422.400,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 3.422.400,00
Total Variabel Cost 3.422.400,00
Total Fix Cost -
Total Cost 3.422.400,00
HSAK 3.422.400,00
84
1 KELOMPOK : DINAS SOSIAL
2 SUB KELOMPOK : Non Konstruksi
3 SUB- SUB KELOMPOK : Penanganan bagi Eks. Narkoba
4 ZONA WILAYAH SSH : Pemberian Bantuan Bagi Eks Narkoba
5 AKTIVITAS : Pemberian Bantuan Stimulan UEP Ternak Domba Bagi Eks. Narkoba
DESKRIPSI AKTIVITAS : Pemberian bantuan hanya diberikan 1 (satu) kali dengan CPCL yang berbeda setiap tahunnya
6 SATUAN AKTIVITAS : Peserta
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Peserta Derivatif 1 Kelas Range 1 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
- - -
-
7.2 Bahan Material
Domba Jantan, Berat badan
minumal 35 kg, tinggi minimal 70
cm,usia minimal 14 bulan, sehat
1.1.7.01.01.11.001.00338 dan tidak cacat , siap kawin dan 1,00 Orang 1,00 Ekor Var 3.500.000,00 3.500.000,00
telingga relative kecil dan kokoh,
bentuk telingga rumpung sampai
ngadaun iris
Domba lokal Betina umur 12 - 24
1.1.7.01.01.11.001.00339 1,00 Orang 1,00 Ekor Var 3.300.000,00 3.300.000,00
bulan , umur 12 - 24 bulan
Multivitamin, Kombinasi lengkap
vitamin A, D, E, K, B dan C,
Kombinasi lengkap vitamin A, D,
1.1.7.01.04.01.001.15443 1,00 Orang 1,00 Botl Var 100.000,00 100.000,00
E, K, B dan C injeksi untuk
meningkatkan produktivitas
hewan isi 50 ml
6.900.000,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 6.900.000,00
Total Variabel Cost 6.900.000,00
Total Fix Cost -
Total Cost 6.900.000,00
HSAK 6.900.000,00
1.1.7.01.01.05.007.00294 Sikat Gigi, 1,00 Orang 10,00 Buah Var 10.000,00 100.000,00
9.1.2.01.05.01.001.01551 Shampoo Shampoo Mandi 170 ml 1,00 Orang 2,00 Botol Var 39.500,00 79.000,00
2.957.200,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 2.957.200,00
Total Variabel Cost 2.957.200,00
Total Fix Cost -
Total Cost 2.957.200,00
HSAK 2.957.200,00
85
1 KELOMPOK : DINAS SOSIAL
2 SUB KELOMPOK : Non Konstruksi
3 SUB- SUB KELOMPOK : Penanganan bagi Eks. Warga Binaan Pemasyarakatan (BWBP)
4 ZONA WILAYAH SSH : Pemberian Bantuan Bagi Eks. Warga Binaan Pemasyarakatan (BWBP)
5 AKTIVITAS : Pemberian Bantuan Stimulan UEP Ternak Domba Bagi Eks. Warga Binaan Pemasyarakatan
DESKRIPSI AKTIVITAS : Pemberian bantuan hanya diberikan 1 (satu) kali dengan CPCL yang berbeda setiap tahunnya
6 SATUAN AKTIVITAS : Peserta
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Peserta Derivatif 1 Kelas Range 1 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
- - -
-
7.2 Bahan Material
Domba Jantan, Berat badan
minumal 35 kg, tinggi minimal 70
cm,usia minimal 14 bulan, sehat
1.1.7.01.01.11.001.00338 dan tidak cacat , siap kawin dan 1,00 Orang 1,00 Ekor Var 3.500.000,00 3.500.000,00
telingga relative kecil dan kokoh,
bentuk telingga rumpung sampai
ngadaun iris
Domba lokal Betina umur 12 - 24
1.1.7.01.01.11.001.00339 1,00 Orang 1,00 Ekor Var 3.300.000,00 3.300.000,00
bulan , umur 12 - 24 bulan
Multivitamin, Kombinasi lengkap
vitamin A, D, E, K, B dan C,
Kombinasi lengkap vitamin A, D,
1.1.7.01.04.01.001.15443 1,00 Orang 1,00 Botl Var 100.000,00 100.000,00
E, K, B dan C injeksi untuk
meningkatkan produktivitas
hewan isi 50 ml
6.900.000,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 6.900.000,00
Total Variabel Cost 6.900.000,00
Total Fix Cost -
Total Cost 6.900.000,00
HSAK 6.900.000,00
9.1.2.02.06.01.001.02914 Mie Instan 1,00 Orang 2,00 Buah Var 130.000,00 260.000,00
1.1.7.01.01.05.007.00294 Sikat Gigi, 1,00 Orang 20,00 Buah Var 10.000,00 200.000,00
9.1.2.01.05.01.001.01551 Shampoo Shampoo Mandi 170 ml 1,00 Orang 5,00 Botol Var 39.500,00 197.500,00
2.979.200,00
7.3 Peralatan/sewa
- - -
-
JUMLAH 2.979.200,00
Total Variabel Cost 2.979.200,00
Total Fix Cost -
Total Cost 2.979.200,00
HSAK 2.979.200,00
86
1 KELOMPOK : Non Konstruktif
2 SUB KELOMPOK : Bimbingan Teknis BPBD
3 SUB- SUB KELOMPOK : Pelatihan Pencegahan dan Mitigasi Bencana Kabupaten/Kota Di Lingkungan Luar Kantor Pemda
4 ZONA WILAYAH SSH : Semua Wilayah
5 AKTIVITAS : Bimtek Rumah Siap Bangun Pasca Bencana
DESKRIPSI AKTIVITAS : Rapat/Sosialisasi/Lokakarya/Seminar di Lingkungan Pemda Bintang 4 dan 5 dengan Akomodasi Dengan Narasumber Luar Pemda Peserta Non PNS selama dua Hari (fullboard) (3 ha
1.1.7.01.03.09.007.00024 Kaos Lengan Panjang 6,00 orang 1,00 stel Fix 221.375,00 1.328.250,00
Paket Bangunan Instan dengan
1.3.1.01.03.09.009.00006 Risha/Ruspin/dll, Struktur 1,00 unit 1,00 keg Fix 50.000.000,00 50.000.000,00
bangunan, dinding, dan atap
1.3.2.05.02.06.077.02865 Sepatu Boot 6,00 orang 1,00 pasang Fix 85.000,00 510.000,00
9.1.2.06.02.01.001.00053 Fotocopy - A.4 1,00 Lembar 1,00 orang 1,00 n/a Var 300,00 300,00
Cetakan sertifikat peserta,
1.1.7.01.03.01.014.00932 1,00 orang 1,00 buah Var 17.000,00 17.000,00
Sertifikat untuk peserta
1.1.7.01.03.01.016.01132 Name Tag - Multi K 1,00 orang 1,00 buah Var 7.500,00 7.500,00
1.1.7.01.03.09.007.00024 Kaos Lengan Panjang 1,00 orang 1,00 buah Var 221.375,00 221.375,00
1.3.2.05.02.06.077.02865 Sepatu Boot 1,00 orang 1,00 pasang Var 85.000,00 85.000,00
Sarung tangan bintik ( warna
1.3.2.01.03.12.015.00068 1,00 orang 1,00 buah Var 6.050,00 6.050,00
putih bintik kuning )
52.699.475,00
7.3 Peralatan/sewa
Sewa Bangunan Gedung Kantor,
9.1.2.07.03.01.001.00006 Paket Fullboard meeting, paket 1,00 Peserta 2,00 paket 1,00 n/a Var 920.000,00 1.840.000,00
meeting 2 hari 1 malam
18.400.000,00
JUMLAH 84.829.475,00
Total Variabel Cost 2.627.225,00
Total Fix Cost 82.202.250,00
Total Cost 84.829.475,00
HSAK 4.682.281,25
87
1 KELOMPOK : Non Konstruktif
2 SUB KELOMPOK : Bimbingan Teknis BPBD
3 SUB- SUB KELOMPOK : Pelatihan Pencegahan dan Mitigasi Bencana Kabupaten/Kota Di Lingkungan Luar Kantor Pemda
4 ZONA WILAYAH SSH : Semua Wilayah
5 AKTIVITAS : Bimtek Psikososial Trauma Healing
Rapat/Sosialisasi/Lokakarya/Seminar di Lingkungan Luar Kantor Pemda Bintang 4 dan 5 dengan Akomodasi Dengan Narasumber Luar Pemda Peserta Non PNS selama
DESKRIPSI AKTIVITAS :
dua Hari (fullboard)
6 SATUAN AKTIVITAS : 40 Peserta
7 KOMPONEN/RINCIAN KOMPONEN
:
Cost Driver
Peserta Derivatif 1 Kelas Range 40 HARGA JUMLAH
1
Cost Driver Var /
NO KODE SIPD URAIAN PEKERJAAN N/A Koef Derivatif 2 n/a Range SATUAN HARGA
2 Fix
Koef Satuan Satuan Koef Satuan (Rp.) (Rp.)
1 2 3 4 5 6 7 8 9 10 13 14
7.1 Upah/Honor
Honorarium Narasumber/
9.1.2.25.03.01.001.00054 Pembahas Pejabat Eselon II /yang 1,00 orang jam 2,00 jam n/a Fix 1.000.000,00 2.000.000,00
disetarakan
Pejabat Eselon III ke bawah/yang
disetarakan (Non ASN Pemda)
9.1.2.24.01.01.001.00201 5,00 orang 2,00 jam n/a Fix 900.000,00 9.000.000,00
Honorarium Narasumber/Praktisi
(pembahas)
Biaya Kediklatan, Uang Saku
9.1.2.23.01.01.001.01244 1,00 orang 2,00 hari Var 150.000,00 300.000,00
Peserta Diklat
11.300.000,00
7.2 Bahan Material
9.1.2.06.02.01.001.00053 Fotocopy - A.4 500,00 lembar 1,00 keg 1,00 Fix 300,00 150.000,00
Biaya Penjilidan - Ring Kawat, 1
1.1.7.01.03.01.014.00873 1,00 Dokumen 5,00 Eksemplar 1,00 n/a Fix 12.300,00 61.500,00
warna, tebal <5cm
9.1.2.06.03.01.001.04956 Foto, Foto Ukuran 3R 10,00 Lembar 1,00 Kegiatan Fix 2.500,00 25.000,00
Spanduk Banner Selamat Datang,
1.1.7.01.03.03.007.01537 2,00 Buah 1,00 buah 1,00 n/a Fix 125.000,00 250.000,00
5x1m
9.1.2.06.03.01.001.05096 Name Tag 5,00 Panitia 1,00 buah 1,00 Fix 35.000,00 175.000,00
9.1.2.06.02.01.001.00053 Fotocopy - A.4 25,00 Lembar 1,00 orang 1,00 n/a Var 300,00 7.500,00
Cetakan sertifikat peserta,
1.1.7.01.03.01.014.00932 1,00 orang 1,00 buah Var 17.000,00 17.000,00
Sertifikat untuk peserta
9.1.2.06.03.01.001.05096 Name Tag 1,00 Peserta 1,00 buah Var 35.000,00 35.000,00
1.1.7.01.03.09.007.00024 Kaos Lengan Panjang 1,00 orang 1,00 Buah Var 221.375,00 221.375,00
942.375,00
7.3 Peralatan/sewa
Sewa Bangunan Gedung Kantor,
9.1.2.07.03.01.001.00006 Paket Fullboard meeting, paket 1,00 Peserta 1,00 paket 1,00 n/a Var 920.000,00 920.000,00
meeting 2 hari 1 malam
88
89