1.3.06.04.01.0001 Penggalian Tanah Biasa untuk Konstruksi 1.2825 m3 118,350.00 151,783.88 159,373.07 164,154.26 159,373.07 167,341.72 178,497.84 183,279.03
Pengurugan Tanah Kembali untuk
1.3.06.04.01.0001 0.261 m3 79,350.00 20,710.35 21,745.87 22,398.24 21,745.87 22,833.16 24,355.37 25,007.75
Konstruksi
Jumlah : 252,681.98 265,316.07 273,275.56 265,316.07 278,581.88 297,154.00 305,113.48
PEKERJAAN PASANGAN
1.3.06.04.01.0001 Pengurugan Pasir (PADAT) 0.4275 m3 339,680.00 145,213.20 152,473.86 157,048.08 152,473.86 160,097.55 170,770.72 175,344.94
Pekerjaan Pemasangan Batu Kali Belah
1.3.06.04.01.0001 0.3 m3 1,085,485.00 325,645.50 341,927.78 352,185.61 341,927.78 359,024.16 382,959.11 393,216.94
15/20 cm (1 Pc : 4 Ps)
Pemasangan Batu Kali Belah Kosongan
1.3.06.04.01.0001 0.171 m3 395,586.50 67,645.29 71,027.56 73,158.38 71,027.56 74,578.93 79,550.86 81,681.69
tebal 15 cm
1.3.06.04.01.0001 Plesteran Halus 1 Pc : 4 Ps tebal 1.5 cm 1 m2 99,141.90 99,141.90 104,099.00 107,221.96 104,099.00 109,303.94 116,590.87 119,713.84
Pemasangan Dasar Saluran R.15 (1/2
1.3.06.04.01.0001 1 m 108,970.00 108,970.00 114,418.50 117,851.06 114,418.50 120,139.43 128,148.72 131,581.28
lingkaran)
1.3.06.04.01.0001 Pemasangan Lubang Drainase 2 Buah 59,800.00 119,600.00 125,580.00 129,347.40 125,580.00 131,859.00 140,649.60 144,417.00
Jumlah : 866,215.89 909,526.69 936,812.49 909,526.69 955,003.02 1,018,669.89 1,045,955.69
Nilai ASB : 1,118,897.87 1,174,842.76 1,210,088.04 1,174,842.76 1,233,584.90 1,315,823.89 1,351,069.17
1.3.06.05.02.0008 Saluran Batu kali 60/80 M
1.3.06.04.01.0001 Pengangkutan Tanah keluar Proyek 1.7675 m3 78,500.00 138,748.75 145,686.19 150,056.77 145,686.19 152,970.50 163,168.53 167,539.12
1.3.06.04.01.0001 Penggalian Tanah Biasa untuk Konstruksi 2.3275 m3 118,350.00 275,459.63 289,232.61 297,909.58 289,232.61 303,694.24 323,940.52 332,617.50
1.3.06.04.01.0001 Pengurugan Pasir (PADAT) 0.6125 m3 339,680.00 208,054.00 218,456.70 225,010.40 218,456.70 229,379.54 244,671.50 251,225.21
1.3.06.04.01.0001 Plesteran Halus 1 Pc : 4 Ps tebal 1.5 cm 1.4 m2 99,141.90 138,798.66 145,738.59 150,110.75 145,738.59 153,025.52 163,227.22 167,599.38
1.3.06.04.01.0001 Pemasangan Lubang Drainase 2 Buah 59,800.00 119,600.00 125,580.00 129,347.40 125,580.00 131,859.00 140,649.60 144,417.00
1.3.06.04.01.0001 Pengangkutan Tanah keluar Proyek 2.28 m3 78,500.00 178,980.00 187,929.00 193,566.87 187,929.00 197,325.45 210,480.48 216,118.35
1.3.06.04.01.0001 Penggalian Tanah Biasa untuk Konstruksi 3.08 m3 118,350.00 364,518.00 382,743.90 394,226.22 382,743.90 401,881.10 428,673.17 440,155.49
1.3.06.04.01.0001 Pengurugan Pasir (PADAT) 0.33 m3 339,680.00 112,094.40 117,699.12 121,230.09 117,699.12 123,584.08 131,823.01 135,353.99
ANALISA SATUAN BIAYA (ASB)
1.3.06.04.01.0001 Plesteran Halus 1 Pc : 4 Ps tebal 1.5 cm 1.8 m2 99,141.90 178,455.42 187,378.19 192,999.54 187,378.19 196,747.10 209,863.57 215,484.92
1.3.06.04.01.0001 Pemasangan Lubang Drainase 2 Buah 59,800.00 119,600.00 125,580.00 129,347.40 125,580.00 131,859.00 140,649.60 144,417.00
1.3.06.04.01.0001 Penggalian Tanah Biasa untuk Konstruksi 1.1 m3 118,350.00 130,185.00 136,694.25 140,795.08 136,694.25 143,528.96 153,097.56 157,198.39
1.3.06.04.01.0001 Pengurugan Pasir (PADAT) 0.2 m3 339,680.00 67,936.00 71,332.80 73,472.78 71,332.80 74,899.44 79,892.74 82,032.72
Pekerjaan Pemasangan Batu Kali Belah
1.3.06.04.01.0001 0.6 m3 1,085,485.00 651,291.00 683,855.55 704,371.22 683,855.55 718,048.33 765,918.22 786,433.88
15/20 cm (1 Pc : 4 Ps)
1.3.06.04.01.0001 Pekerjaan Beton ( 1Pc : 2 Ps : 3 Kr) 0.1 m3 1,480,410.85 148,041.09 155,443.14 160,106.43 155,443.14 163,215.30 174,096.32 178,759.61
1.3.06.04.01.0001 Plesteran Halus 1 Pc : 4 Ps tebal 1.5 cm 1.8 m2 99,141.90 178,455.42 187,378.19 192,999.54 187,378.19 196,747.10 209,863.57 215,484.92
1.3.06.04.01.0001 Pasang Benangan 1 Pc: 2Ps 2 m 103,709.00 207,418.00 217,788.90 224,322.57 217,788.90 228,678.35 243,923.57 250,457.24
Pemasangan Dasar Saluran R.15 (1/2
1.3.06.04.01.0001 1 m 108,970.00 108,970.00 114,418.50 117,851.06 114,418.50 120,139.43 128,148.72 131,581.28
lingkaran)
1.3.06.04.01.0001 Pemasangan Lubang Drainase 2 Buah 59,800.00 119,600.00 125,580.00 129,347.40 125,580.00 131,859.00 140,649.60 144,417.00
Jumlah : 2,498,246.51 2,623,158.83 2,701,853.60 2,623,158.83 2,754,316.77 2,937,937.89 3,016,632.66
Nilai ASB : 2,498,246.51 2,623,158.83 2,701,853.60 2,623,158.83 2,754,316.77 2,937,937.89 3,016,632.66
Saluran Batu kali 60/80 + Tutup Pelat
1.3.06.05.02.0008 M
(1 sisi)
Pelat Beton K-350 Pre-Cast Tb.12 Cm
1.1.12.01.01.0001 2 Buah 500,000.00 1,000,000.00 1,050,000.00 1,081,500.00 1,050,000.00 1,102,500.00 1,176,000.00 1,207,500.00
(Fabrikan)
1.3.06.04.01.0001 Pengangkutan Tanah keluar Proyek 1.9 m3 78,500.00 149,150.00 156,607.50 161,305.73 156,607.50 164,437.88 175,400.40 180,098.63
1.3.06.04.01.0001 Penggalian Tanah Biasa untuk Konstruksi 2 m3 118,350.00 236,700.00 248,535.00 255,991.05 248,535.00 260,961.75 278,359.20 285,815.25
Pengurugan Tanah Kembali untuk
1.3.06.04.01.0001 0.1 m3 79,350.00 7,935.00 8,331.75 8,581.70 8,331.75 8,748.34 9,331.56 9,581.51
Konstruksi
1.3.06.04.01.0001 Pengurugan Pasir (PADAT) 0.4 m3 339,680.00 135,872.00 142,665.60 146,945.57 142,665.60 149,798.88 159,785.47 164,065.44
Pekerjaan Pemasangan Batu Kali Belah
1.3.06.04.01.0001 0.9 m3 1,085,485.00 976,936.50 1,025,783.33 1,056,556.82 1,025,783.33 1,077,072.49 1,148,877.32 1,179,650.82
15/20 cm (1 Pc : 4 Ps)
1.3.06.04.01.0001 Pekerjaan Beton ( 1Pc : 2 Ps : 3 Kr) 0.1 m3 1,480,410.85 148,041.09 155,443.14 160,106.43 155,443.14 163,215.30 174,096.32 178,759.61
1.3.06.04.01.0001 Plesteran Halus 1 Pc : 4 Ps tebal 1.5 cm 2.2 m2 99,141.90 218,112.18 229,017.79 235,888.32 229,017.79 240,468.68 256,499.92 263,370.46
1.3.06.04.01.0001 Pasang Benangan 1 Pc: 2Ps 2 m 103,709.00 207,418.00 217,788.90 224,322.57 217,788.90 228,678.35 243,923.57 250,457.24
Pemasangan Dasar Saluran R.15 (1/2
1.3.06.04.01.0001 1 m 108,970.00 108,970.00 114,418.50 117,851.06 114,418.50 120,139.43 128,148.72 131,581.28
lingkaran)
1.3.06.04.01.0001 Pemasangan Lubang Drainase 2 Buah 59,800.00 119,600.00 125,580.00 129,347.40 125,580.00 131,859.00 140,649.60 144,417.00
1.3.06.04.01.0001 Penggalian Tanah Biasa untuk Konstruksi 3.1 m3 118,350.00 366,885.00 385,229.25 396,786.13 385,229.25 404,490.71 431,456.76 443,013.64
Pengurugan Tanah Kembali untuk
1.3.06.04.01.0001 0.3 m3 79,350.00 23,805.00 24,995.25 25,745.11 24,995.25 26,245.01 27,994.68 28,744.54
Konstruksi
1.3.06.04.01.0001 Pengurugan Pasir (PADAT) 0.6 m3 339,680.00 203,808.00 213,998.40 220,418.35 213,998.40 224,698.32 239,678.21 246,098.16
Pekerjaan Pemasangan Batu Kali Belah
1.3.06.04.01.0001 1.3 m3 1,085,485.00 1,411,130.50 1,481,687.03 1,526,137.64 1,481,687.03 1,555,771.38 1,659,489.47 1,703,940.08
15/20 cm (1 Pc : 4 Ps)
1.3.06.04.01.0001 Pekerjaan Beton ( 1Pc : 2 Ps : 3 Kr) 0.1 m3 1,480,410.85 148,041.09 155,443.14 160,106.43 155,443.14 163,215.30 174,096.32 178,759.61
1.3.06.04.01.0001 Plesteran Halus 1 Pc : 4 Ps tebal 1.5 cm 2.6 m2 99,141.90 257,768.94 270,657.39 278,777.11 270,657.39 284,190.26 303,136.27 311,256.00
1.3.06.04.01.0001 Pasang Benangan 1 Pc: 2Ps 2 m 103,709.00 207,418.00 217,788.90 224,322.57 217,788.90 228,678.35 243,923.57 250,457.24
Pemasangan Dasar Saluran R.15 (1/2
1.3.06.04.01.0001 1 m 108,970.00 108,970.00 114,418.50 117,851.06 114,418.50 120,139.43 128,148.72 131,581.28
lingkaran)
1.3.06.04.01.0001 Pemasangan Lubang Drainase 2 Buah 59,800.00 119,600.00 125,580.00 129,347.40 125,580.00 131,859.00 140,649.60 144,417.00
1.3.06.04.01.0001 Pengangkutan Tanah keluar Proyek 4 m3 78,500.00 314,000.00 329,700.00 339,591.00 329,700.00 346,185.00 369,264.00 379,155.00
1.3.06.04.01.0001 Penggalian Tanah Biasa untuk Konstruksi 4.3 m3 118,350.00 508,905.00 534,350.25 550,380.76 534,350.25 561,067.76 598,472.28 614,502.79
1.3.06.04.01.0001 Pengurugan Pasir (PADAT) 0.7 m3 339,680.00 237,776.00 249,664.80 257,154.74 249,664.80 262,148.04 279,624.58 287,114.52
1.3.06.04.01.0001 Pekerjaan Beton ( 1Pc : 2 Ps : 3 Kr) 0.1 m3 1,480,410.85 148,041.09 155,443.14 160,106.43 155,443.14 163,215.30 174,096.32 178,759.61
1.3.06.04.01.0001 Plesteran Halus 1 Pc : 4 Ps tebal 1.5 cm 3.2 m2 99,141.90 317,254.08 333,116.78 343,110.29 333,116.78 349,772.62 373,090.80 383,084.30
1.3.06.04.01.0001 Pasang Benangan 1 Pc: 2Ps 2 m 103,709.00 207,418.00 217,788.90 224,322.57 217,788.90 228,678.35 243,923.57 250,457.24
1.3.06.04.01.0001 Pemasangan Lubang Drainase 2 Buah 59,800.00 119,600.00 125,580.00 129,347.40 125,580.00 131,859.00 140,649.60 144,417.00
1.3.06.04.01.0001 Pengangkutan Tanah keluar Proyek 2.2 m3 78,500.00 172,700.00 181,335.00 186,775.05 181,335.00 190,401.75 203,095.20 208,535.25
ANALISA SATUAN BIAYA (ASB)
1.3.06.04.01.0001 Penggalian Tanah Biasa untuk Konstruksi 2.2 m3 118,350.00 260,370.00 273,388.50 281,590.16 273,388.50 287,057.93 306,195.12 314,396.78
1.3.06.04.01.0001 Pengurugan Pasir (PADAT) 0.4 m3 339,680.00 135,872.00 142,665.60 146,945.57 142,665.60 149,798.88 159,785.47 164,065.44
1.3.06.04.01.0001 Pekerjaan Beton ( 1Pc : 2 Ps : 3 Kr) 0.2 m3 1,480,410.85 296,082.17 310,886.28 320,212.87 310,886.28 326,430.59 348,192.63 357,519.22
1.3.06.04.01.0001 Plesteran Halus 1 Pc : 4 Ps tebal 1.5 cm 3.6 m2 99,141.90 356,910.84 374,756.38 385,999.07 374,756.38 393,494.20 419,727.15 430,969.84
1.3.06.04.01.0001 Pasang Benangan 1 Pc: 2Ps 4 m 103,709.00 414,836.00 435,577.80 448,645.13 435,577.80 457,356.69 487,847.14 500,914.47
1.3.06.04.01.0001 Pemasangan Lubang Drainase 4 Buah 59,800.00 239,200.00 251,160.00 258,694.80 251,160.00 263,718.00 281,299.20 288,834.00
1.3.06.04.01.0001 Penggalian Tanah Biasa untuk Konstruksi 4 m3 118,350.00 473,400.00 497,070.00 511,982.10 497,070.00 521,923.50 556,718.40 571,630.50
Pengurugan Tanah Kembali untuk
1.3.06.04.01.0001 0.2 m3 79,350.00 15,870.00 16,663.50 17,163.41 16,663.50 17,496.68 18,663.12 19,163.03
Konstruksi
1.3.06.04.01.0001 Pengurugan Pasir (PADAT) 0.8 m3 339,680.00 271,744.00 285,331.20 293,891.14 285,331.20 299,597.76 319,570.94 328,130.88
Pekerjaan Pemasangan Batu Kali Belah
1.3.06.04.01.0001 1.8 m3 1,085,485.00 1,953,873.00 2,051,566.65 2,113,113.65 2,051,566.65 2,154,144.98 2,297,754.65 2,359,301.65
15/20 cm (1 Pc : 4 Ps)
1.3.06.04.01.0001 Pekerjaan Beton ( 1Pc : 2 Ps : 3 Kr) 0.2 m3 1,480,410.85 296,082.17 310,886.28 320,212.87 310,886.28 326,430.59 348,192.63 357,519.22
1.3.06.04.01.0001 Plesteran Halus 1 Pc : 4 Ps tebal 1.5 cm 4.4 m2 99,141.90 436,224.36 458,035.58 471,776.65 458,035.58 480,937.36 512,999.85 526,740.91
1.3.06.04.01.0001 Pasang Benangan 1 Pc: 2Ps 4 m 103,709.00 414,836.00 435,577.80 448,645.13 435,577.80 457,356.69 487,847.14 500,914.47
Pemasangan Dasar Saluran R.15 (1/2
1.3.06.04.01.0001 2 m 108,970.00 217,940.00 228,837.00 235,702.11 228,837.00 240,278.85 256,297.44 263,162.55
lingkaran)
1.3.06.04.01.0001 Pemasangan Lubang Drainase 4 Buah 59,800.00 239,200.00 251,160.00 258,694.80 251,160.00 263,718.00 281,299.20 288,834.00
Jumlah : 6,617,469.53 6,948,343.01 7,156,793.30 6,948,343.01 7,295,760.16 7,782,144.17 7,990,594.46
Nilai ASB : 6,617,469.53 6,948,343.01 7,156,793.30 6,948,343.01 7,295,760.16 7,782,144.17 7,990,594.46
Saluran Batu kali 80/100 + Tutup
1.3.06.05.02.0008 M
Pelat (2 sisi)
Pelat Beton K-350 Pre-Cast Tb.12 Cm
1.1.12.01.01.0001 4 Buah 500,000.00 2,000,000.00 2,100,000.00 2,163,000.00 2,100,000.00 2,205,000.00 2,352,000.00 2,415,000.00
(Fabrikan)
1.3.06.04.01.0001 Pengangkutan Tanah keluar Proyek 5.6 m3 78,500.00 439,600.00 461,580.00 475,427.40 461,580.00 484,659.00 516,969.60 530,817.00
1.3.06.04.01.0001 Penggalian Tanah Biasa untuk Konstruksi 6.2 m3 118,350.00 733,770.00 770,458.50 793,572.26 770,458.50 808,981.43 862,913.52 886,027.28
Pengurugan Tanah Kembali untuk
1.3.06.04.01.0001 0.6 m3 79,350.00 47,610.00 49,990.50 51,490.22 49,990.50 52,490.03 55,989.36 57,489.08
Konstruksi
1.3.06.04.01.0001 Pengurugan Pasir (PADAT) 1.2 m3 339,680.00 407,616.00 427,996.80 440,836.70 427,996.80 449,396.64 479,356.42 492,196.32
Pekerjaan Pemasangan Batu Kali Belah
1.3.06.04.01.0001 2.6 m3 1,085,485.00 2,822,261.00 2,963,374.05 3,052,275.27 2,963,374.05 3,111,542.75 3,318,978.94 3,407,880.16
15/20 cm (1 Pc : 4 Ps)
1.3.06.04.01.0001 Pekerjaan Beton ( 1Pc : 2 Ps : 3 Kr) 0.2 m3 1,480,410.85 296,082.17 310,886.28 320,212.87 310,886.28 326,430.59 348,192.63 357,519.22
ANALISA SATUAN BIAYA (ASB)
1.3.06.04.01.0001 Plesteran Halus 1 Pc : 4 Ps tebal 1.5 cm 5.2 m2 99,141.90 515,537.88 541,314.77 557,554.22 541,314.77 568,380.51 606,272.55 622,511.99
1.3.06.04.01.0001 Pasang Benangan 1 Pc: 2Ps 4 m 103,709.00 414,836.00 435,577.80 448,645.13 435,577.80 457,356.69 487,847.14 500,914.47
Pemasangan Dasar Saluran R.15 (1/2
1.3.06.04.01.0001 2 m 108,970.00 217,940.00 228,837.00 235,702.11 228,837.00 240,278.85 256,297.44 263,162.55
lingkaran)
1.3.06.04.01.0001 Pemasangan Lubang Drainase 4 Buah 59,800.00 239,200.00 251,160.00 258,694.80 251,160.00 263,718.00 281,299.20 288,834.00
1.3.06.04.01.0001 Pengangkutan Tanah keluar Proyek 8 m3 78,500.00 628,000.00 659,400.00 679,182.00 659,400.00 692,370.00 738,528.00 758,310.00
1.3.06.04.01.0001 Penggalian Tanah Biasa untuk Konstruksi 8.6 m3 118,350.00 1,017,810.00 1,068,700.50 1,100,761.52 1,068,700.50 1,122,135.53 1,196,944.56 1,229,005.58
1.3.06.04.01.0001 Pengurugan Pasir (PADAT) 1.4 m3 339,680.00 475,552.00 499,329.60 514,309.49 499,329.60 524,296.08 559,249.15 574,229.04
1.3.06.04.01.0001 Pekerjaan Beton ( 1Pc : 2 Ps : 3 Kr) 0.2 m3 1,480,410.85 296,082.17 310,886.28 320,212.87 310,886.28 326,430.59 348,192.63 357,519.22
1.3.06.04.01.0001 Plesteran Halus 1 Pc : 4 Ps tebal 1.5 cm 6.4 m2 99,141.90 634,508.16 666,233.57 686,220.58 666,233.57 699,545.25 746,181.60 766,168.60
1.3.06.04.01.0001 Pasang Benangan 1 Pc: 2Ps 4 m 103,709.00 414,836.00 435,577.80 448,645.13 435,577.80 457,356.69 487,847.14 500,914.47
1.3.06.04.01.0001 Pemasangan Lubang Drainase 4 Buah 59,800.00 239,200.00 251,160.00 258,694.80 251,160.00 263,718.00 281,299.20 288,834.00
1.3.06.04.01.0001 Pengangkutan Tanah keluar Proyek 1.1 m3 78,500.00 86,350.00 90,667.50 93,387.53 90,667.50 95,200.88 101,547.60 104,267.63
1.3.06.04.01.0001 Penggalian Tanah Biasa untuk Konstruksi 1.1 m3 118,350.00 130,185.00 136,694.25 140,795.08 136,694.25 143,528.96 153,097.56 157,198.39
Pengurugan Tanah Kembali untuk
1.3.06.04.01.0001 0 m3 79,350.00 0.00 - - - - - -
Konstruksi
Jumlah : 216,535.00 227,361.75 234,182.60 227,361.75 238,729.84 254,645.16 261,466.01
PEKERJAAN PASANGAN
Pelat Beton K-350 Pre-Cast Tb.10 Cm
1.1.12.01.01.0001 1.66667 Buah 400,000.00 666,666.67 700,000.00 721,000.00 700,000.00 735,000.00 784,000.00 805,000.00
(Fabrikan)
1.3.06.04.01.0001 Pengurugan Pasir (PADAT) 0.2 m3 339,680.00 67,936.00 71,332.80 73,472.78 71,332.80 74,899.44 79,892.74 82,032.72
Pekerjaan Pemasangan Batu Kali Belah
1.3.06.04.01.0001 0.6 m3 1,085,485.00 651,291.00 683,855.55 704,371.22 683,855.55 718,048.33 765,918.22 786,433.88
15/20 cm (1 Pc : 4 Ps)
1.3.06.04.01.0001 Pekerjaan Beton ( 1Pc : 2 Ps : 3 Kr) 0.1 m3 1,480,410.85 148,041.09 155,443.14 160,106.43 155,443.14 163,215.30 174,096.32 178,759.61
ANALISA SATUAN BIAYA (ASB)
1.3.06.04.01.0001 Pasang Benangan 1 Pc: 2Ps 2 m 103,709.00 207,418.00 217,788.90 224,322.57 217,788.90 228,678.35 243,923.57 250,457.24
Pemasangan Dasar Saluran R.15 (1/2
1.3.06.04.01.0001 1 m 108,970.00 108,970.00 114,418.50 117,851.06 114,418.50 120,139.43 128,148.72 131,581.28
lingkaran)
1.3.06.04.01.0001 Pemasangan Lubang Drainase 2 Buah 59,800.00 119,600.00 125,580.00 129,347.40 125,580.00 131,859.00 140,649.60 144,417.00
1.3.06.04.01.0001 Penggalian Tanah Biasa untuk Konstruksi 8.6 m3 118,350.00 1,017,810.00 1,068,700.50 1,100,761.52 1,068,700.50 1,122,135.53 1,196,944.56 1,229,005.58
Pengurugan Tanah Kembali untuk
1.3.06.04.01.0001 0.6 m3 79,350.00 47,610.00 49,990.50 51,490.22 49,990.50 52,490.03 55,989.36 57,489.08
Konstruksi
1.3.06.04.01.0001 Pengurugan Pasir (PADAT) 1.4 m3 339,680.00 475,552.00 499,329.60 514,309.49 499,329.60 524,296.08 559,249.15 574,229.04
Pekerjaan Pemasangan Batu Kali Belah
1.3.06.04.01.0001 3.6 m3 1,085,485.00 3,907,746.00 4,103,133.30 4,226,227.30 4,103,133.30 4,308,289.97 4,595,509.30 4,718,603.30
15/20 cm (1 Pc : 4 Ps)
1.3.06.04.01.0001 Pekerjaan Beton ( 1Pc : 2 Ps : 3 Kr) 0.2 m3 1,480,410.85 296,082.17 310,886.28 320,212.87 310,886.28 326,430.59 348,192.63 357,519.22
1.3.06.04.01.0001 Plesteran Halus 1 Pc : 4 Ps tebal 1.5 cm 6.4 m2 99,141.90 634,508.16 666,233.57 686,220.58 666,233.57 699,545.25 746,181.60 766,168.60
1.3.06.04.01.0001 Pasang Benangan 1 Pc: 2Ps 4 m 103,709.00 414,836.00 435,577.80 448,645.13 435,577.80 457,356.69 487,847.14 500,914.47
Pemasangan Dasar Saluran R.15 (1/2
1.3.06.04.01.0001 2 m 108,970.00 217,940.00 228,837.00 235,702.11 228,837.00 240,278.85 256,297.44 263,162.55
lingkaran)
1.3.06.04.01.0001 Pemasangan Lubang Drainase 4 Buah 59,800.00 239,200.00 251,160.00 258,694.80 251,160.00 263,718.00 281,299.20 288,834.00
1.3.06.04.01.0001 Pengangkutan Tanah keluar Proyek 4 m3 78,500.00 314,000.00 329,700.00 339,591.00 329,700.00 346,185.00 369,264.00 379,155.00
1.3.06.04.01.0001 Penggalian Tanah Biasa untuk Konstruksi 4.3 m3 118,350.00 508,905.00 534,350.25 550,380.76 534,350.25 561,067.76 598,472.28 614,502.79
Pengurugan Tanah Kembali untuk
1.3.06.04.01.0001 0.3 m3 79,350.00 23,805.00 24,995.25 25,745.11 24,995.25 26,245.01 27,994.68 28,744.54
Konstruksi
1.3.06.04.01.0001 Pengurugan Pasir (PADAT) 0.7 m3 339,680.00 237,776.00 249,664.80 257,154.74 249,664.80 262,148.04 279,624.58 287,114.52
Pekerjaan Pemasangan Batu Kali Belah
1.3.06.04.01.0001 1.8 m3 1,085,485.00 1,953,873.00 2,051,566.65 2,113,113.65 2,051,566.65 2,154,144.98 2,297,754.65 2,359,301.65
15/20 cm (1 Pc : 4 Ps)
1.3.06.04.01.0001 Pekerjaan Beton ( 1Pc : 2 Ps : 3 Kr) 0.1 m3 1,480,410.85 148,041.09 155,443.14 160,106.43 155,443.14 163,215.30 174,096.32 178,759.61
1.3.06.04.01.0001 Plesteran Halus 1 Pc : 4 Ps tebal 1.5 cm 3.2 m2 99,141.90 317,254.08 333,116.78 343,110.29 333,116.78 349,772.62 373,090.80 383,084.30
1.3.06.04.01.0001 Pasang Benangan 1 Pc: 2Ps 2 m 103,709.00 207,418.00 217,788.90 224,322.57 217,788.90 228,678.35 243,923.57 250,457.24
Pemasangan Dasar Saluran R.15 (1/2
1.3.06.04.01.0001 1 m 108,970.00 108,970.00 114,418.50 117,851.06 114,418.50 120,139.43 128,148.72 131,581.28
lingkaran)
1.3.06.04.01.0001 Pemasangan Lubang Drainase 2 Buah 59,800.00 119,600.00 125,580.00 129,347.40 125,580.00 131,859.00 140,649.60 144,417.00
1.3.06.04.01.0001 Pengangkutan Tanah keluar Proyek 4 m3 78,500.00 314,000.00 329,700.00 339,591.00 329,700.00 346,185.00 369,264.00 379,155.00
1.3.06.04.01.0001 Penggalian Tanah Biasa untuk Konstruksi 4.3 m3 118,350.00 508,905.00 534,350.25 550,380.76 534,350.25 561,067.76 598,472.28 614,502.79
Pengurugan Tanah Kembali untuk
1.3.06.04.01.0001 0.3 m3 79,350.00 23,805.00 24,995.25 25,745.11 24,995.25 26,245.01 27,994.68 28,744.54
Konstruksi
ANALISA SATUAN BIAYA (ASB)
1.3.06.04.01.0001 Pemasangan Lubang Drainase 2 Buah 59,800.00 119,600.00 125,580.00 129,347.40 125,580.00 131,859.00 140,649.60 144,417.00
1.1.12.01.01.0001 Pembuatan direksi kit 0.1600 m2 6,893,164.62 1,102,906.34 1,158,051.66 1,192,793.21 1,158,051.66 1,215,954.24 1,297,017.85 1,331,759.40
1.1.12.01.01.0001 Pembuatan papan nama proyek 0.0100 Buah 568,082.00 5,680.82 5,964.86 6,143.81 5,964.86 6,263.10 6,680.64 6,859.59
1.3.06.04.01.0001 Pemasangan bowplank 0.2500 m' 128,280.90 32,070.23 33,673.74 34,683.95 33,673.74 35,357.42 37,714.58 38,724.80
1.3.06.04.01.0001 Pembersihan dan striping/kosrekan 0.0190 m2 7,935.00 150.77 158.30 163.05 158.30 166.22 177.30 182.05
1.3.06.04.01.0001 Pengukuran (uitset) 0.5000 m' 128,280.90 64,140.45 67,347.47 69,367.90 67,347.47 70,714.85 75,429.17 77,449.59
8.1.02.02.04.0023 Pengeringan (Pompa) 0.4200 jam 138,000.00 57,960.00 60,858.00 62,683.74 60,858.00 63,900.90 68,160.96 69,986.70
PEKERJAAN STRUKTUR
Pekerjaan Saluran
1.3.06.05.02.0008 Penggalian Tanah 1.3600 m3 69,025.00 93,874.00 98,567.70 101,524.73 98,567.70 103,496.09 110,395.82 113,352.86
1.3.06.04.01.0001 Pas. batu belah 1:4 1.0413 m3 1,085,485.00 1,130,348.10 1,186,865.50 1,222,471.46 1,186,865.50 1,246,208.77 1,329,289.36 1,364,895.32
1.3.06.04.01.0001 Pekerjaan Plesteran 1:3 2.8000 m2 101,904.88 285,333.66 299,600.35 308,588.36 299,600.35 314,580.36 335,552.39 344,540.40
1.3.06.04.01.0001 Pekerjaan Acian 2.8000 m2 41,457.50 116,081.00 121,885.05 125,541.60 121,885.05 127,979.30 136,511.26 140,167.81
1.3.06.04.01.0001 Urugan tanah 0.5000 m3 79,350.00 39,675.00 41,658.75 42,908.51 41,658.75 43,741.69 46,657.80 47,907.56
1.3.06.04.01.0001 Pemadatan tanah 0.5000 m3 75,900.00 37,950.00 39,847.50 41,042.93 39,847.50 41,839.88 44,629.20 45,824.63