ESTIMASI PEKERJAAN BOBOKAN DAN FINISH KEMBALI RUANG GENSET AS 29-30/P'-Q

PROYEK PERLUASAN TRANS STUDIO MAKASSAR

PT.SENTRA PRIMA MANDIRI

HARGA TOTAL
NO. LANTAI DESKRIPSI SAT. P L T QTY KETERANGAN
(Rp) (Rp)

A Item Approve : IOM 347/MEP/ENG-PRECONS/VII/2022


A1 Pekerjaan Bongkaran
1 LGM a. Bongkaran Dinding Existing as P'/29-30 & Q/29-30 m2 8.00 6.00 96.00 200,000.00 19,200,000 Bongkar bata (Dalam & Luar) 2x
a. Bongkaran Dinding Bata & Cladding Q/29-30 m2 8.00 3.20 76.80 450,000.00 34,560,000
2 LG
b. Bongkaran Dinding As P'/29-30 m2 4.16 4.60 19.14 450,000.00 8,611,200
3 LG a. Bongkaran Plat Lantai as P'-Q/29-30 m3 7.85 3.10 0.15 5.38 2,500,000.00 13,445,625 Bobok Plat dan balok anak

A2 Pekerjaan Pasang Baru


Pasangan Dinding Baru as P', Q/29-30 + Plester, Aci -
a. Pasangan Dinding Baru as Q/29-30 (bata ringan) m2 8.00 6.00 48.00 850,000.00 40,800,000
b. Plester Aci Dinding Baru as Q/29-30 m2 8.00 6.00 96.00 150,000.00 14,400,000 2 Sisi
c. Cat (sisi luar) Dinding Baru as Q/29-30 m2 8.00 6.00 48.00 150,000.00 7,200,000 1 Sisi
d. Pasangan Dinding Baru as P'/29-30 (bata ringan) m2 8.00 6.00 48.00 850,000.00 40,800,000
4 LGM
e. Plester Aci Dinding Baru as P'/29-30 m2 8.00 6.00 48.00 150,000.00 7,200,000 2 Sisi
f. Bongkar dinding AsP'/28-29 (dinding yang rusak) m2 16.00 450,000.00 7,200,000
g. Pasang dinding bata ringan As P/28-29 (eks. Dinding yang rusak) m2 16.00 850,000.00 13,600,000
h. Plester Aci As P'/28-29 (eks. Dinding yang rusak) m2 16.00 150,000.00 2,400,000
i. Rockwool 50mm Dencity 100 & Hanger UNP 100 (Lepas yang rusak, pasang baru) m2 176.14 275,000.00 48,438,500 Utk peredam suara

Pasangan Dinding Baru as P'/29-30 + Plester, Aci + Perapiha Opening Louvre


a. Pasangan Dinding Baru as P' (dinding ruang trafo)(bata ringan) m2 4.16 4.60 19.14 850,000.00 16,265,600
5 LG
b. Plester Aci Dinding Baru as P' (dinding ruang trafo) m2 4.16 4.60 38.27 150,000.00 5,740,800 2 Sisi
c. Finish perapihan keliling exhaust louvre grill As Q m' 3.20 3.20 16.00 250,000.00 4,000,000 louvre dari Vendor ME
6 a. Pengecoran Slooping as P'-Q/29-30 (material dan upah) m3 9.63 7,500,000.00 72,259,525 sirkulasi angin pembungannya gak langsung nabrak dinding secara horizontal
b. Pembesian Slooping (besi SBO, hanya upah) Kg 751.50 14,000.00 10,520,987 Ratio Slab 78 Kg/m3 (S1)
LGM
7 Chipping pondasi pompa (6 Titik) bagian selimut beton m3 2.55 0.40 0.10 0.61 10,000,000 6,120,000 Opsi Jika Bongkar
8 Epoxy Lantai 2 warna LGM m2 7.81 8.00 72.50 185,000 13,411,760
a. Bongkar dinding As 30-31/N m2 2.20 6.40 14.08 200,000.00 2,816,000
9 Untuk Jalur udara ke intakefan 5 (IF5)
LGM b. Perapihan dinding As 30-31/N m' 2.20 6.40 17.20 250,000.00 4,300,000
10 a. Bongkar dinding As 28/N-P m2 3.00 3.00 9.00 200,000.00 1,800,000 Untuk kebutuhan posisi Grill, (Grill dari Vendor ME)
b. Perapihan dinding As 28/N-P m' 3.00 3.00 12.00 250,000.00 3,000,000
11 LG BJLS Lt. LG m 6.87 - - - 2x

12 LGM Pondasi Genset (2 Unit) 2


73,740,222 - - - - - Tidak ada Bobok Plat
Bor + Epoxy (D13-200) Titik 85.00 185,000.00 15,725,000
Besi (besi SBO, hanya upah) kg 324.44 14,000.00 4,542,202
Beton (material dan upah) m3 6.00 2.46 0.20 5.90 7,500,000.00 44,280,000
Bekisting (Material dan upah) m2 6.00 2.46 0.20 4.37 650,000.00 2,839,200

Pekerjaan Tanggulan Beton (2 Unit) 2


Bor + Epoxy (D13-200) Titik 32.00 125,000.00 4,000,000
Besi (besi SBO, hanya upah) kg 8.13 14,000.00 113,820
Beton (material dan upah) m3 8.00 0.10 0.10 0.16 7,500,000.00 1,200,000
Bekisting (Material dan upah) m2 8.00 0.10 1.60 650,000.00 1,040,000
*)Note
-Dimensi Pondasi Weekly Tank Existing m3 2.55 0.40 0.10 Kondisi exsting ( 8 Titik)
-Dimensi Pondasi Genset Baru m3 (4,43 & 1,2) (2 & 2.46) 0.86 Referensi Pondasi genset - SZ001, (4,43*2) + (1,2*2.46) : 2 Unit
TOTAL A 471,830,218

1 a. Pasang dinding dan kaca m2 1.50 0.50 5.00 2,500,000.00 12,500,000 Penambahan kaca ukuran 1500x500 = 5 buah (fungsi kontrol Genset dari luar)
b. Pas. Bata Ringan m2 4.87 3.50 17.03 850,000.00 14,473,375
LGM
c. Plester Aci m2 4.87 6.00 58.38 150,000.00 8,757,000
d. Cat - Cat Acrylic Emulsi Fungus Resitant m2 4.87 6.00 58.38 250,000.00 14,595,000

Pintu di pindah + di finish (dari Kanan ke Kiri) karena genset kalau nyala sedotan kuat,
2 LGM Pindah pintu besi ke ruang baru + Finish titik 1.00 1.00 4,500,000.00 4,500,000
pintu ga bisa dibuka

3 LGM Bobok dinding dan pasang pintu baru ke koridoor Fungsinya Jika mesin menyala, untuk akses ke Koridor & maintenance
a. Bobok dinding Titik 1.00 1.00 350,000.00 350,000 Bobok Plat dan balok anak
b. Harga pengadaan dan pemasangan kusen pintu, engsel dan slot kunci pintu besi Titik 1.00 4,500,000.00 4,500,000 Eks. Pintu existing

4 LGM Pagar BRC H 1500 (as P-P'/18-20) Fungsinya sebagai Batas Pengaman Mesin Trafo
c. Pagar m' 13.71 13.71 750,000.00 10,281,000
b. Tiang pagar Titik 12.00 250,000.00 3,000,000
c. Pintu Titik 1.00 750,000.00 750,000

7 LG a. Bobok dinding instalasi ducting perpindahan di Ruang Travo lantai LG + finish m2 1.50 0.60 0.90 350,000.00 315,000 Alokasi Pemindahan Exhaust- ducting trafo ke genset
b. Finish perapihan keliling exhaust m' 1.50 0.60 4.80 450,000.00 2,160,000

C BERITA ACARA PENGECEKAN BERSAMA 76,181,375

9 LGM Pembuatan Partisi Temporer antara Ruangan Genset 4x1800kVA dengan m2 8.00 10.00 6.00 108.00 450,000 48,600,000
genset baru dengan material Baja ringan+ dinding multipleks meliputi
PQ 29-30 ( Bentuk Letter L) lengkap pintu
(Pekerjaan ini pasang dan bongkar)

10 LGM Pembuatan Partisi Temporer antara Ruangan Genset 4x1800kVA dengan m2 4.00 3.00 3.00 42.00 350,000 14,700,000
bobokan intake fan baru dengan material Baja ringan+ dinding multipleks
Area AS 28N
(Pekerjaan ini pasang dan bongkar)
11 LGM 'Pembuatan Partisi Temporer antara Ruangan Genset baru dengan sisi luar m2 8.00 6.00 48.00 250,000 12,000,000
(jalan) dengan material baja ringan dinding clading seng bekas bongkaran
Area AS 29-30Q '(Pekerjaan ini pasang dan bongkar)

12 LGM - LG Pasang dinding Sekat dalam (bata ringan) m2 3.10 10.50 32.55 850,000.00 27,667,500

13 LGM 'Bobok partisi dinding R. Operator PKG Existing (Include perbaikan bekas bobokan dinding) m2 4.70 7.00 32.90 350,000.00 11,515,000

14 LGM Pondasi dudukan daily tank (4 buah tingg 10cm) 4


Bor + Epoxy (D13-200) Titik 32.00 125,000.00 4,000,000
Besi (besi SBO, hanya upah) kg 10.00 14,000.00 140,029
Beton (material dan upah) m3 0.0160 7,500,000.00 120,000
Bekisting (Material dan upah) m2 0.32 550,000.00 176,000

15 LGM Bobok louvre grill intek m2 3.00 3.00 9.00 350,000.00 3,150,000

16 PEK. PAGAR DAN ATAP WEEKLY TANK DAN R. PUMP


Pondasi Pompa
Besi (besi SBO, hanya upah) kg 8.54 14,000.00 119,608
Beton (material dan upah) m3 0.25 7,500,000.00 1,882,500
Bekisting (Material dan upah) m2 4.23 550,000.00 2,326,500
Chemset Titik 82.00 185,000.00 15,170,000
Gutter m' 7.70 550,000.00 4,235,000
Perbaikan lantai Epoxy m2 4.60 450,000.00 2,070,000

Dinding Bata Fin. Plester Aci Cat + Finish kolom dan balok
Pas. Bata Ringan m2 60.00 550,000.00 33,000,000
Plester Aci m2 190.80 150,000.00 28,620,000
Cat m2 190.80 250,000.00 47,700,000

BRC Weekly Tank


Pagar BRC Buah 10.00 1,250,000.00 12,500,000
Pagar BRC Buah 2.00 1,250,000.00 2,500,000
Pagar BRC Buah 1.00 1,250,000.00 1,250,000
Tiang BRC Batang 24.00 550,000.00 13,200,000
Pintu pagar BRC Buah 2.00 1,250,000.00 2,500,000

TOTAL B 289,142,138

GRAND TOTAL A + B 837,153,731


Note : DP 20% PT. SENTRA PRIMA MANDIRI
DP dibyarKan ketika sdh ttd kontrak
Pembayaran pling lama 21 hari stelah invoice terbit
Pembayaran progres bulanan

Ir. Abdi Gofrelin Purba


Direktur
harga per m 96,667
keuntungan 10% 9,667
Total 106,333
0.595238
8.4

Pek. Pagar Pagar BRC (m)


Bahan : - Pagar BRC lmbr 0.4375
- Accessories ls 1

Upah : - Pekerja Oh 0.1


- Tukang batu Oh 0.033333
- Kepala tukang Oh 0.0032
- Mandor Oh 0.005067

keuntungan 10%
Harga total

Tiang BRC (bh)


- Tiang BRC btg 1

- Pekerja Oh 0.1
- Tukang batu Oh 0.033333
- Kepala tukang Oh 0.0032
- Mandor Oh 0.005067

keuntungan 10%
Harga total

Pintu BRC (BH)


- Pagar BRC lmbr 0.4375
- Tiang BRC btg 2
- Accessories ls 1

- Pekerja Oh 0.1
- Tukang batu Oh 0.033333
- Kepala tukang Oh 0.0032
- Mandor Oh 0.005067

keuntungan 10%
Harga total
Dinding/Jendela kaca
Jendela Alumunium 1
Ongkit 1

upah pemasangan
Pekerja Oh 1
Tukang batu Oh 0.333333
Kepala tukang Oh 0.032
Mandor Oh 0.050667

keuntungan 10%
Harga total

Pemindahan pintu

upah pemindahan
Pekerja Oh 0.666667
Tukang batu Oh 0.222222
Kepala tukang Oh 0.021333
Mandor Oh 0.033778

keuntungan 10%
Harga total
Pagar BRC (BH)
375,000 164,063 2.285714 1 375,000 375,000
10,000 10,000 2.285714 10,000 22,857

100,000 10,000 0.228571 100,000 22,857


150,000 5,000 0.07619 150,000 11,429
175,000 560 0.007314 175,000 1,280
200,000 1,013 0.011581 200,000 2,316

190,636 435,739
keuntungan 10% 19,064 keuntungan 10% 43,574
Harga total 209,699 Harga total 479,313

75,000 75,000

100,000 10,000
150,000 5,000
175,000 560
200,000 1,013

91,573
keuntungan 10% 9,157
Harga total 100,731

375,000 164,063
75,000 150,000
10,000 10,000

100,000 10,000
150,000 5,000
175,000 560
200,000 1,013

340,636
keuntungan 10% 34,064
Harga total 374,699
972,000 972,000
400,000 400,000

100,000 100,000
150,000 50,000
175,000 5,600
200,000 10,133

1,537,733
keuntungan 10% 153,773
Harga total 1,691,507

100,000 66,667
150,000 33,333
175,000 3,733
200,000 6,756

110,489
keuntungan 10% 11,049
Harga total 121,538
ESTIMASI PEKERJAAN BOBOKAN DAN FINISH KEMBALI RUANG GENSET AS 29-30/P'-Q
PROYEK PERLUASAN TRANS STUDIO MAKASSAR

ESTIMASI
HARGA TOTAL
NO. LANTAI DESKRIPSI SAT. P L T QTY KETERANGAN REFERENSI HARGA
(Rp) (Rp)

A Item Approve : IOM 347/MEP/ENG-PRECONS/VII/2022


A1 Pekerjaan Bongkaran
1 LGM a. Bongkaran Dinding Existing as P'/29-30 & Q/29-30 m2 8.00 6.00 96.00 50,000 4,800,000 Bongkar bata (Dalam & Luar) 2x Harga kontrak Yusfi

a. Bongkaran Dinding Bata & Cladding Q/29-30 m2 8.00 3.20 76.80 200,000 15,360,000 Dinding + Cladding
2 LG
b. Bongkaran Dinding As P'/29-30 m2 4.16 4.60 19.14 50,000 956,800 Harga kontrak Edo

3 LG a. Bongkaran Plat Lantai as P'-Q/29-30 m3 7.85 3.10 0.15 5.38 700,000 3,764,775 Bobok Plat dan balok anak Harga kontrak Edo

A2 Pekerjaan Pasang Baru


Pasangan Dinding Baru as P', Q/29-30 + Plester, Aci -
a. Pasangan Dinding Baru as Q/29-30 m2 8.00 6.00 48.00 165,000 7,920,000 Harga kontrak Pasopati
b. Plester Aci Dinding Baru as Q/29-30 m2 8.00 6.00 96.00 80,000 7,680,000 2 Sisi Harga kontrak Pasopati
4 LGM c. Cat (sisi luar) Dinding Baru as Q/29-30 m2 8.00 6.00 48.00 26,000 1,248,000 1 Sisi Harga kontrak Dakina
d. Pasangan Dinding Baru as P'/29-30 m2 8.00 6.00 48.00 165,000 7,920,000 Harga kontrak Pasopati
e. Plester Aci Dinding Baru as P'/29-30 m2 8.00 6.00 48.00 80,000 3,840,000 2 Sisi Harga kontrak Pasopati
f. Rockwool 50mm Dencity 100 & Hanger UNP 100 m2 317.01 Utk peredam suara Masuk Scope Vendor ME

Pasangan Dinding Baru as P'/29-30 + Plester, Aci + Perapiha Opening Louvre


a. Pasangan Dinding Baru as P' (dinding ruang trafo) m2 4.16 4.60 19.14 165,000 3,157,440 Harga kontrak Pasopati
5 LG
b. Plester Aci Dinding Baru as P' (dinding ruang trafo) m2 4.16 4.60 38.27 80,000 3,061,760 2 Sisi Harga kontrak Pasopati
c. Finish perapihan keliling exhaust louvre grill As Q m' 3.20 3.20 16.00 56,020 896,320 louvre dari Vendor ME Estimasi
6 a. Pengecoran Slooping as P'-Q/29-30 m3 9.63 1,150,000 11,079,794 sirkulasi angin pembungannya gak langsung nabrak dinding secara horizontal Harga Kontrak PT Ravirianmas
b. Pembesian Slooping Kg 751.50 16,250 12,211,860 Ratio Slab 78 Kg/m3 (S1) Harga Kontrak PT Ravirianmas

LGM
7 Chipping pondasi pompa (6 Titik) bagian selimut beton m3 2.55 0.40 0.10 0.61 700,000 428,400 Opsi Jika Bongkar Harga kontrak Edo

8 Epoxy Lantai 2 warna LGM m2 7.81 8.00 72.50 125,000 9,062,000

a. Bongkar dinding As 30-31/N-P m2 2.20 4.20 9.24 35,000 323,400 Harga kontrak Yusfi
9 Untuk Jalur udara ke intakefan 5 (IF5)
LGM b. Perapihan dinding As 30-31/N-P m' 2.20 4.20 12.80 56,020 717,056 Estimasi
10 a. Bongkar dinding As 28/N-P m2 7.00 4.50 31.50 35,000 1,102,500 Untuk kebutuhan posisi Grill, (Grill dari Vendor ME) Harga kontrak Yusfi
b. Perapihan dinding As 30-31/N-P m' 7.00 4.50 23.00 16,250 373,750 Estimasi
11 LG BJLS Lt. LG m 6.87 - - 709,326 4,875,198 2x Estimasi

12 LGM Pondasi Genset (2 Unit) 2


91,875,102 Bobok lantai dan buang m3 5.63 2.46 0.86 23.82 700,000 16,675,159 Bobok Plat dan balok anak Harga kontrak Edo
20 - Anchor. L-M20X315 Anchor Titik 40.00 313,000 12,520,000 Harga SI PT Pramesta
Besi kg 2,034.04 16,250 33,053,080 Harga Kontrak PT Ravirianmas
Beton m3 5.63 2.46 0.86 23.82 1,150,000 27,394,904 Harga Kontrak PT Ravirianmas
Bekisting m2 5.63 2.46 0.86 18.15 123,000 2,231,958 Harga Kontrak PT Ravirianmas

*)Note
-Dimensi Pondasi Weekly Tank Existing m3 2.55 0.40 0.10 Kondisi exsting ( 8 Titik)
-Dimensi Pondasi Genset Baru m3 (4,43 & 1,2) (2 & 2.46) 0.86 Referensi Pondasi genset - SZ001, (4,43*2) + (1,2*2.46) : 2 Unit
TOTAL A 192,654,154

B Item Belum Approve

1 LG Bobok Plat Ruang Genset 1900 x 1900 m3 4.70 2.00 0.25 2.35 700,000 1,645,000 Bobok Plat dan balok anak (Untuk Daily Tank & Ducting) Harga kontrak Edo

2 LG Dog house UK 2000 x 2000 titik 1.00 1.00 2,716,334 2,716,334 Untuk Ducting Harga Satuan PT Ravirianmas

3 a. Pasang dinding dan kaca m2 1.50 0.50 3.75 338,385 1,268,945 Penambahan kaca ukuran 1500x500 = 5 buah (fungsi kontrol Genset dari luar) Harga Satuan Dwi Kreasi
b. Pas. Bata Ringan m2 4.87 3.50 17.03 165,000 2,809,538
LGM Harga kontrak Pasopati
c. Plester Aci m2 4.87 6.00 58.38 80,000 4,670,400
d. Cat - Cat Acrylic Emulsi Fungus Resitant m2 4.87 6.00 58.38 15,500 904,890 Harga kontrak Dakina

Pintu di pindah + di finish (dari Kanan ke Kiri) karena genset kalau nyala sedotan kuat,
4 LGM Pindah pintu besi ke ruang baru + Finish titik 1.00 1.00 1,300,000 1,300,000 Harga Satuan PT Marksindo
pintu ga bisa dibuka

5 LGM Bobok dinding dan pasang pintu baru ke koridoor Fungsinya Jika mesin menyala, untuk akses ke Koridor & maintenance
a. Bobok dinding Titik 1.00 1.00 700,000 700,000 Bobok Plat dan balok anak Harga kontrak Edo
b. Harga pengadaan pintu besi Titik 1.00 3,480,000 3,480,000 2150 X 900 X 50 mm SD-2 Pengadaan marksindo
c. Harga pemasangan Titik 1.00 1,000,000 1,000,000 2150 X 900 X 50 mm SD-2 Pemasangan marksindo

6 LGM Pagar BRC H 1500 (as P-P'/18-20) Fungsinya sebagai Batas Pengaman Mesin Trafo
c. Pagar m' 13.71 13.71 700,000 9,595,600 Estimasi
b. Tiang pagar Titik 12.00 180,000 2,160,000 Estimasi
c. Pintu Titik 1.00 380,000 380,000 Estimasi

7 LG a. Bobok dinding instalasi ducting perpindahan di Ruang Travo lantai LG + finish m2 1.50 0.60 0.90 50,000 45,000 Alokasi Pemindahan Exhaust- ducting trafo ke genset
b. Finish perapihan keliling exhaust m' 1.50 0.60 4.80 56,020 268,896 Estimasi

8 LG UNP m' 125.00 145,167 18,145,253 Sekunder Muffler, Exhaust Attenuaor, Primer Muffler Estimasi

TOTAL B 51,089,855

GRAND TOTAL A + B 243,744,009


UPGRADE TRANS STUDIO MALL MAKASSAR
BILL OF QUANTITY
SECTION A. PEK.
SECTION A.1 7 A.2 PEK. PAGAR DAN ATAP WEEKLY TANK
HARGA JUMLAH Ket
NO URAIAN PEKERJAAN SAT VOLUME
Rp. Rp.

A PEK. PAGAR DAN ATAP WEEKLY TANK DAN R. PUMP


1 Pondasi Pompa Estimasi
- Besi kg 8.54 -
- Beton m3 0.25 -
- Bekisting m2 4.23 -
- Chemset Titik 82.00 -
- Gutter m' 7.70 -
- Perbaikan lantai Epoxy m2 4.60 -

2 Dinding Bata Fin. Plester Aci Cat + Finish kolom dan balok
- Pas. Bata Ringan Incld kolom praktis dan ring balok m2 60.00 -
- Plester Aci m2 190.80 -
- Cat m2 190.80 -

3 BRC Weekly Tank


- Pagar BRC Uk 1850 x 1.200 Buah 10.00 - Conditional
- Pagar BRC Uk 1775 x 1.200 Buah 2.00 - Conditional
- Pagar BRC Uk 2000 x 1.200 Buah 1.00 - Conditional
- Tiang BRC T. 1.200 Batang 24.00 -
- Pintu pagar BRC Uk 900 x 2550 Buah 2.00 - Conditional

4 Atap Weekly Tank


- Atap metal termasuk tiang m2 56.00 -
- Talang air metal m' 8.00 -
- Pipa PVC tipe D diameter 2" m' 11.20 -
- Rooft drain diameter 3" Buah 2.00 -
- Fleshing atap m' 8.00 -

SUB TOTAL - -

NOTE :
Before 0068 STR FC TSM-MKS D&P VI 2021 (Detail Weekly Tank) 25 juni 21
After 182_IOM_ARS_ENG-PRECONS_X_2021_TSM (Gambar Update For Construction Detail Weekly Tank)
5
Pasangan Dinding Baru as P', Q/29-30 +
Plester, Aci (Atas bagian dalam) Lt. LG

3
Bongkaran Plat
Lantai as P'-Q/29-30
Lt. LG (Foto dari atas
dan bawah)

2
Bongkaran Dinding Existing as P',
Q/29-30 (Atas) Lt. LG
-Bongkaran Dinding Bata As Q
-Bongkaran Cladding As Q
-Finish perapihan keliling exhaust
louvre grill As Q
-Bongkaran Dinding Gysum As P'

6
Pengecoran Slooping as P'-
Q/29-30 1
Bongkaran Dinding
Existing as P', Q/29-30
(Bawah) Lt. LGM

4
Pekerjaan Pasang Baru
Pasangan Dinding Baru as P', Q/29-
30 + Plester, Aci (Bawah) Lt. LGM
-Pasangan Dinding Baru as Q + Pondasi mesin genset 2
Plester Aci + Cat (sisi luar) buah (Menunggu approval)
-Pasangan Dinding Baru as P' +
Plester Aci
-ROCKWOOL 50mm DENCITY 100 &
HANGER UNP 100

8
Epoxy Lantai 2 warna LGM

7
Chipping pondasi pompa (6 Titik)
bagian atas
Area Ruang Atas Genset Area Luar Genset

Bobok lantai. Bobok dinding bata dan cladding Pasang bata (saat ini yang terpasang gypsum) Penambahan 2 grill genset
Bobok dinding luar

Area Genset Gambar Rencana Sloping

Gambar rencana sloping

Bobok Dinding luar + pasang kembali. Item : Pekerjaan sloping dan bongkar pondasi pompa
- Pas. Bata ringan finish plester aci dinding
- Pas. Rockwoll 50mm DENCITY 100 & HANGER UNP 100
Area Genset

Pekerjaan dinding lama Pas. Bata dinding baru untuk batas radiator Bobok Plat atas dan balok anak
- Bongkar pondasi pompa - Pas. Rockwoll 50mm dll
- Pekerjaan pondasi genset
- Epoxy 2 warna

UPDATE DENAH SAAT INI

Tambahan bobokan dinding kebutuhan ruang genset


Area Ruang Trafo (Bobok dinding) Area Luar Genset

Bobok dinding area ruang trafo

Area Genset (Penambahan sekat dinding baru)

A Penambahan kaca ukuran 1500x2000 = 5 buah (fungsi kontrol Genset dari luar)
B Pintu di pindah + di finish (dari Kanan ke Kiri) karena genset kalau nyala sedotan kuat, pintu ga bisa dibuka
C Penambahan pintu akses keluar ke koridor

Area Genset (Bobokan Lantai)

Bobok Lantai ukuran 1900 x 1900


di atasnya di pasang dog house ukuran 2000 x 2000

Area Travo Lantai LG Mezzanine

Pagar Brc H 1500 Untuk Penutup/Sekat Area Trafo


2
Dog house UK 2000 x
2000 (Gambar ada di
lembar ke 2)

1
Bobok Plat Ruang Genset
1900 x 1900

3
Pasang dinding dan kaca

5
Bobok dinding dan
pasang pintu baru ke
4 koridoor (Foto atas arah
Pindah pintu besi ke luar koridor. foto bawah
ruang baru + Finish arah ruang genset)

A Penambahan kaca ukuran 1500x500 = 5 buah (fungsi kontrol Genset dari luar)
B Pintu di pindah + di finish (dari Kanan ke Kiri) karena genset kalau nyala sedotan kuat, pintu ga bisa dibuka
C Penambahan pintu akses keluar ke koridor (Fungsinya Jika mesin menyala, untuk akses ke Koridor & maintenance)

6
Pagar BRC H 1500
7
Alokasi ducting trafo ke genset

1
Dog house UK 2000 x
2000

A. 12
Dudukan pondasi 2 buah
Pemasangan 1 m Openingan

Harga Jumlah
Satuan Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)

A TENAGA
Pekerja L.01 OH 0.08 100,000 8,000
Tukang Batu L.02 OH 0.4 105,000 42,000
Mandor L.04 OH 0.004 180,000 720
JUMLAH
B BAHAN TENAGA
Semen Portland kg KERJA
0.500 1,500 750
Pasir Beton m3 0.013 350,000 4,550
C PERALATAN

JUMLAH
HARGA
D Jumlah (A+B+C) ALAT 56,020.00

Pemasangan 1 m Seng BJLS 28 Lebar 90 cm

Harga Jumlah
Satuan Harga
No Uraian Kode Satuan Koefisien
(Rp) (Rp)

A TENAGA
Pekerja L.01 OH 0.2 100,000 20,000
Tukang L.02 OH 0.2 105,000 21,000
Kepala tukang L.03 OH 0.02 120,000 2,400
Mandor L.04 OH 0.001 180,000 180
JUMLAH
B BAHAN TENAGA
KERJA
Seng Plat m3 1.050 55,000 57,750
Paku 1 cm - 2,5 cm kg 0.013 25,000 325

C PERALATAN

JUMLAH
HARGA
D Jumlah (A+B+C) ALAT 101,655.00
E R2000 6.98 709,326.00

1/2 keliling R2000 =𝜋 x r x 2 x (1/2) 6.28