Anda di halaman 1dari 36

KONTRAKTOR : PT.

KALINGGA KENCANA TANGGAL : 28 APRIL 2023

PEKERJAAN : STUDIO TVRI REV. 0

AREA : PALANGKARAYA

PALANGKARAYA
Harga
No Uraian Pekerjaan Sat Volume Jumlah Harga
Satuan

A PEKERJAAN PERSIAPAN 141,955,935.49


1 Mobilisasi & Demobilisasi Pekerja ls 1.0 25,235,000 25,235,000
Mobilisasi & Demobilisasi + TU + EL + FA + CCTV ls 1.0 30,000,000 30,000,000
2 Pembersihan lapangan dan peralatan m2 320.9 39,655 12,724,496
3 Biaya Air kerja bln 3.0 1,369,900 4,109,700
4 Biaya Listrik kerja bln 3.0 2,090,900 6,272,700
5 Pekerjaan Pembuatan Papan Nama Proyek Uk 120x240m unt 1.0 540,750 540,750
6 Pengukuran & Pemasangan bowplank m 45.6 46,865 2,137,044
Pembuatan gudang semen dan alat-alat, Bedeng Pekerja,
7 m2 42.0 324,450 13,626,900
Toilet uk. 5,00 x 6,00 m
8 Peralatan Keamanan Kerja & K3 unit 1.0 4,181,800 4,181,800
Pekerjaan Bongkaran , Buangan Puing, Termasuk
9 diantaranya Pembongkaran Perangkat Studio Aktif dan m2 153.5 129,059 19,811,847
Tidak Aktif Atau Reposisi Perangkat Aktif
Pek Dinding Sementara untuk Pengamanan Pekerjaan,
10 m2 38.4 133,385 5,121,984
dengan Multiplek+rangka, sesuai gambar dan spesifikasi

11 Pek Pembuatan Pagar Sementara,Tinggi 2 m m2 162.8 111,755 18,193,714

1 BANGUNAN TYPICAL 1
1.B PEKERJAAN STRUKTUR
1.B.1 PEKERJAAN TANAH 44,058,763
Pekerjaan galian tanah m3 14.1 54,075 762,863
Pekerjaan Urugan tanah untuk mencapai elevasi yg
m3 54.3 126,175 6,847,517
ditentukan tanah baru tinggi 50 cm
Pekerjaan pemadatan tanah per 20 cm m2 108.5 68,495 7,434,447
Pekerjaan Lean Concrete tebal 5 cm m2 108.5 27,038 2,934,650

Pekerjaan pasir kerikil tebal 65 cm m3 75.1 284,795 21,399,496

Pekerjaan pasir Limestone tebal 20 cm m3 21.7 215,579 4,679,789

1.B.2 STRUKTUR BETON 84,525,327


Pekerjaan Pile Cap
Pekerjaan Beton Fc'25 m3 9.4 973,350 9,154,357
Pekerjaan Besi kg 2294.8 14,060 32,263,784
Pekerjaan Bekisting m2 21.1 71,019 1,499,911
Pekerjaan Pedestal
Pekerjaan Beton Fc'25 m3 1.7 973,350 1,643,015
Pekerjaan Besi kg 514.1 14,060 7,227,293
Pekerjaan Bekisting m2 13.1 71,019 928,922
Pekerjaan Plat Lantai
Pekerjaan Beton Fc'25 m3 21.0 973,350 20,480,257
Pekerjaan Wiremesh M8-150 m2 142.5 14,060 2,004,041
Pekerjaan Bekisting m2 47.5 71,019 3,373,379
Pekerjaan Tie Beam
Pekerjaan Beton Fc'25 m3 1.6 973,350 1,569,527
Pekerjaan Besi kg 189.2 14,060 2,659,635
Pekerjaan Bekisting m2 21.5 71,019 1,526,898
Pekerjaan Lain - lain
Pekerjaan Grouting pada beton m 0.1 1,982,750 194,310
: 28 APRIL 2023
KONTRAKTOR : PT.KALINGGA KENCANA TANGGAL

: STUDIO TVRI REV. 0


PEKERJAAN
: PALANGKARAYA
AREA

PALANGKARAYA
Harga
No Uraian Pekerjaan Sat Volume Jumlah Harga
Satuan

1.B.3 PEKERJAAN STRUKTUR BAJA 571,229,143


Notes :
Harga satuan pekerjaan baja sudah termasuk perkuatan
las, angkur, baut, baseplat, grouting dan cat zincromat

Kolom
KJ1 H 200X200X8X12 kg 4909.7 28,500 139,926,493
KJ2 H 250X250X9X14 kg 1295.2 28,500 36,914,454
BJ5 LC 100x50x20x3.2 kg 2365.0 28,500 67,402,500
Ikata angin dia 19 kg 289.3 28,500 8,245,718

Balok Lantai 2
BJ1 WF 400x200x8x13 kg 660.3 28,500 18,818,550
BJ2 WF 350x175x7x11 kg 148.7 28,500 4,237,380
BJ3 WF 200x100x5.5x8 kg 1028.7 28,500 29,317,665
BJ4 WF 150x75x5x7 kg 252.2 28,500 7,187,130
BJ8 WF 250x125x6x9 kg 1230.1 28,500 35,058,420

Balok Lantai Atap


BJ3 WF 200x100x5.5x8 kg 767.5 28,500 21,874,320
BJ8 WF 250x125x6x9 kg 1230.1 28,500 35,058,420

Atap
BJ2 WF 350x175x7x11 kg 569.9 28,500 16,243,290
BJ3 WF 200x100x5.5x8 kg 916.8 28,500 26,127,660
BJ8 WF 250x125x6x9 kg 1230.1 28,500 35,058,420
G1 WF 150x75x5x7 kg 1401.0 28,500 39,928,500
G2 UNP 100x50x5x7.5 kg 861.1 28,500 24,541,920
Ikata angin dia 19 kg 138.0 28,500 3,932,573

Tangga Baja
BJ6 UNP 200x90x8x13.5
BJ7 L 50x50x5 kg 109.5 28,500 3,122,159
Plat 8 mm anak tangga kg 129.1 28,500 3,678,917
kg 510.7 28,500 14,554,654
Grid Lampu

KONTRAKTOR : PT.KALINGGA KENCANA TANGGAL : 28 APRIL 2023

PEKERJAAN : STUDIO TVRI REV. 0


AREA : PALANGKARAYA

PALANGKARAYA
Harga
No Uraian Pekerjaan Sat Volume Jumlah Harga
Satuan

1.C PEKERJAAN ARSITEKTUR & INTERIOR


1.C.1 PEKERJAAN DINDING DAN PELAPIS 150,430,511
Pek. Pemasangan Dinding Multiplek 18mm + Metal
1 Perforated t.1.2mm fin cat duco + dengan rangka (C), m2 44.8 284,795 12,745,359
sesuai gambar dan spesifikasi
Pek Pemasangan Dinding Akustik Board dengan rangka
2 m2 223.8 147,805 33,076,172
(B), sesuai gambar dan sepesifikasi

Pek Pemasangan Dinding Multiplek 18mm + Kain Antedja +


3 Glasswool dengan rangka (A), sesuai gambar dan m2 50.3 284,795 14,321,629
spesifikasi material

Pek Pemasangan Dinding Multiplek 18mm 1 Muka + Lapis


4 HPL dengan rangka, sesuai gambar dan spesifikasi m2 13.2 346,080 4,568,256
material

Pek Pemasangan Dinding Kalsiboard t.8mm dengan


5 m2 189.2 191,065 36,144,721
Rangka, sesuai gambar dan spesifikasi.
Pek Pemasangan Dinding Rockwool + Waremesh + Lapis
6 m2 352.6 140,595 49,574,373
Kain, dengan Rangka, sesuai gambar dan spesifikasi.

1.C.2 PEKERJAAN LANTAI DAN PELAPIS 26,949,141


Pas. Pemasangan Lantai Epoxy ketebalan 500 micron;
1 m2 122.6 120,768 14,810,926
sesuai gambar dan spesifikasi

Pek Pemasangan Lantai Koral Sikat, sesuai gambar dan


2 m2 38.5 140,595 5,408,690
spesifikasi

Pek Pemasangan Floor Harderner, sesuai gambar dan


3 m2 20.1 147,805 2,969,365
spesifikasi

Pek Pemasangan Plint Skirting Hairline Stainless Steel t.


4 m2 25.4 147,805 3,760,159
10 cm, sesuai gambar dan spesifikasi

1.C.3 PEKERJAAN PLAFOND 14,633,740


Pek Pemasangan Plafond Akustik + rangka, sesuai gambar
1 m2 27.9 284,795 7,942,933
dan spesifikasi

2 Pek Pengecatan Plafond sesuai gambar dan spesifikasi m2 176.8 37,853 6,690,808

-
1.C.4 PEKERJAAN KUSEN PINTU DAN JENDELA - 35,833,700

Pintu Swing Besi (P.1), dengan 2 Daun Pintu & Kusen Besi
1 Uk 215x210mm, Lengkap dengan Harware, sesuai dengan bh 1.0 9,877,700 9,877,700
gambar dan spesifikasi

Pintu Swing Besi (P.2), dengan 1 Daun Pintu & Kusen Besi
2 Uk 100x210mm, Lengkap dengan Harware, sesuai dengan bh 2.0 5,623,800 11,247,600
gambar dan spesifikasi

Pintu Swing Besi Porporated (P.3), dengan 1 Daun Pintu &


3 Kusen Besi Uk 110x210mm, Lengkap dengan Harware, bh 1.0 6,200,600 6,200,600
sesuai dengan gambar dan spesifikasi

Jendela (J1), Kusen Alumunium dengan Kaca tebal 8mm,


4 bh 4.0 2,126,950 8,507,800
sesuai dengan gambar dan spesifikasi
-
KONTRAKTOR : PT.KALINGGA KENCANA TANGGAL : 28 APRIL 2023

PEKERJAAN : STUDIO TVRI REV. 0

AREA : PALANGKARAYA

PALANGKARAYA
Harga
No Uraian Pekerjaan Sat Volume Jumlah Harga
Satuan
1.C.5 PEKERJAAN ATAP DAN LAIN-LAIN - 42,367,464

1 Pek Pemasangan Atap UPVC, sesuai gambar dan spesifikasi m2 109.3 209,090 22,860,855

Pek Pemasangan Talang Plat Besi BJLS, sesuai gambar dan


2 m' 9.9 133,385 1,313,842
spesifikasi
Pek Pemasangan Flashing Plat Besi BJLS, sesuai gambar
3 m' 44.4 133,385 5,922,294
dan spesifikasi

Pek Pemasangan Railling tangga, Fin cat duco, sesuai


4 unt 1.0 6,200,600 6,200,600
gambar dan spesifikasi

Pekerjaan Pemasangan Plat tangga, sesuai gambar dan


5 m2 9.2 353,290 3,255,921
spesifikasi
Pek Canopy plat besi 2mm + cat duco dengan rangka,
6 m2 4.0 695,765 2,813,952
sesuai gambar dan spesifikasi material
-
1.C.6 PEKERJAAN FAÇADE - 304,171,403
Pek Pemasangan Façade Metal Corrugated fin Cat Duco,
1 m2 313.5 337,500 105,821,438
dengan rangka sesuai gambar dan spesifikasi

Pek Pemasangan Façade Alumunium Composite Panel


2 (ACP) corgorated, dengan rangka, sesuai gambar dan m2 163.3 1,215,000 198,349,965
spesifikasi
2 BANGUNAN EKSISTING
2.B PEKERJAAN STRUKTUR
2.B.1 PEKERJAAN TANAH - 63,885,210
Pekerjaan galian tanah m3 61.4 61,285 3,763,742
Pekerjaan Urugan tanah untuk mencapai elevasi yg
ditentukan tanah baru tinggi 50 cm (Tidak termasuk m3 68.2 32,445 2,213,966
import Soil)
Pekerjaan pemadatan tanah per 20 cm m2 136.5 68,495 9,347,855
Pekerjaan Lean Concrete tebal 5 cm m2 136.5 27,038 3,689,943
Pekerjaan pasir Limestone tebal 20 cm m3 27.3 219,905 6,002,307
Pekerjaan Geotextile m2 136.5 284,795 38,867,398
-
2.B.2 STRUKTUR BETON - 51,576,609
STRUKTUR BETON -
Pekerjaan Plat Lantai - 0
Pekerjaan Beton Fc'25 m3 28.5 973,350 27,755,075
Pekerjaan Wiremesh M8-150 m2 136.5 147,805 20,171,687
Pekerjaan Bekisting m2 17.2 212,695 3,649,846
-
2.B.3 PEKERJAAN STRUKTUR BAJA - 173,602,949
Notes : -
Harga satuan pekerjaan baja sudah termasuk perkuatan
-
las, angkur, baut, baseplat, grouting dan cat zincromat
KJ1 Pipa dia 5" t = 6mm kg 1051.8 28,480 29,955,368
BJ2 Pipa dia 3" t = 5mm kg 3166.4 28,480 90,178,140
BJ3 Pipa dia 2,5" t = 5mm kg 1877.5 28,480 53,469,441
-
KONTRAKTOR : PT.KALINGGA KENCANA TANGGAL : 28 APRIL 2023

PEKERJAAN : STUDIO TVRI REV. 0

AREA : PALANGKARAYA

PALANGKARAYA
Harga
No Uraian Pekerjaan Sat Volume Jumlah Harga
Satuan
2.C PEKERJAAN ARSITEKTUR & INTERIOR - 394,934,735
2.C.1 PEKERJAAN DINDING DAN PELAPIS -
Pek Pengecatan Tembok Interior (D1), Acrylic sesuai
1 m2 89.0 140,595 12,511,268
gambar dan spesifikasi.
Pek. Pemasangan Dinding Multiplek 18mm + Metal
2 Perforated t.1.2mm fin cat duco + dengan rangka (C), m2 49.4 2,126,950 105,156,408
sesuai gambar dan spesifikasi

Pek Pemasangan Dinding Akustik Board dengan rangka


3 m2 125.2 2,126,950 266,379,218
(B), sesuai gambar dan sepesifikasi
Pek Pemasangan Dinding Multiplek 18mm + Kain Antedja +
4 Glasswool dengan rangka (A), sesuai gambar dan m2 63.5 75,705 4,808,479
spesifikasi material

Pek Pemasangan Dinding Multiplek 18mm 1 Muka + Lapis


5 HPL dengan rangka, sesuai gambar dan spesifikasi m2 38.7 104,545 4,049,655
material

Pek Pemasangan Dinding Multiplek 18mm 2 Muka + Lapis


6 HPL dengan rangka, sesuai gambar dan spesifikasi m2 41.7 48,668 2,029,707
material
2.C.2 PEKERJAAN LANTAI DAN PELAPIS - 57,901,455
Pek Pemasangan Lantai Vynil t.2mm, sesuai gambar dan
1 spesifikasi m2 63.4 212,695 13,478,482

Pek Pemasangan Lantai Vynil t.3mm, + Dempul, sesuai


2 m2 120.5 292,005 35,183,682
gambar dan spesifikasi

Pek Pemasangan Plint Skirting Hairline Stainless Steel t.


3 m' 62.5 147,805 9,239,291
10 cm, sesuai gambar dan spesifikasi

-
2.C.3 PEKERJAAN PLAFOND - 26,332,650
Pek Pemasangan Plafond Akustik + rangka, sesuai gambar
1 m2 63.4 284,795 18,047,459
dan spesifikasi

2 Pek Pengecatan Plafond sesuai gambar dan spesifikasi m2 183.9 45,063 8,285,191
2.C.4 PEKERJAAN KUSEN PINTU DAN JENDELA - 24,982,650
Pintu 1 Daun Pintu & Jendela (R. Editing) ,Kusen
Alumunium + Pintu Enginering wood+ Kaca T.8mm,
1 bh 7.0 3,568,950 24,982,650
Lengkap dengan Harware, sesuai dengan gambar dan
spesifikasi
-
2.C.5 PEKERJAAN FIX FURNITURE - 19,178,600

1 Meja Editing uk 1900x800x750mm bh 7.0 2,739,800 19,178,600

3 BANGUNAN MASTER CONTROL


3.B PEKERJAAN STRUKTUR
3.B.1 PEKERJAAN TANAH -
3.B.2 STRUKTUR BETON -
3.C PEKERJAAN ARSITEKTUR & INTERIOR
3.C.1 PEKERJAAN DINDING DAN PELAPIS -
3.C.2 PEKERJAAN LANTAI DAN PELAPIS - 13,561,469.25
Pek Pemasangan Floor Harderner, sesuai gambar dan
1 m2 0.8 360,500 302,279
spesifikasi

Pek Pemasangan Raise Floor motif HPL, sesuai gambar


2 m2 18.4 721,000 13,259,190
dan spesifikasi

KONTRAKTOR : PT.KALINGGA KENCANA TANGGAL : 28 APRIL 2023

PEKERJAAN : STUDIO TVRI REV. 0

AREA : PALANGKARAYA

PALANGKARAYA
Harga
No Uraian Pekerjaan Sat Volume Jumlah Harga
Satuan

3.C.3 PEKERJAAN PLAFOND -


3.C.4 PEKERJAAN KUSEN PINTU DAN JENDELA -
3.C.5 PEKERJAAN ATAP & LAIN-LAIN -
3.C.6 PEKERJAAN FIX FURNITURE -
Total BoQ Pekerjaan Struktur - 2,100,155,519.81

REKAPITULASI HARGA Rp

1 PEKERJAAN PERSIAPAN 141,955,935

2 PEKERJAAN STRUKTUR 2,100,155,520

3 PEKERJAAN TATA UDARA 300,306,235

4 PEKERJAAN ELEKTRIKAL 365,762,355

5 PEKERJAAN FIRE ALARM 45,224,640

6 PEKERJAAN CCTV 17,508,960

TOTAL REKAPITULASI 2,970,913,645


Pembulatan 2,970,900,000

Terbilang : Dua milyard sembilan ratus tujuh puluh juta sembilan ratus ribu rupiah
561,207,579
2,090,133,956
BILL OF QUQNTITY (BOQ)

No. Jenis Pekerjaan Vol Sat Harga Satuan Jumlah Harga

1 PEKERJAAN TATA UDARA


A PERALATAN UTAMA AC
Pengadaan dan pemasangan peralatan utama Sistem AC
Single Split, lengkap dengan material bantu, accessories
dan perlangkapan lainnya sesuai dengan gambar dan
spesifikasi teknis, sehingga sistem berfungsi dengan baik.

Lantai 1 (Satu)
1 IU-STD.1 & OU-STD.1 1 Unit 53,182,800 53,182,800
Kapasitas 14 PK
Tipe Indoor Split Duct
Lokasi Ruang Studio 1

2 IU-MCL.01 & OU-MCL.01 1 Unit 14,688,000 14,688,000


Kapasitas 2 PK
Tipe Indoor Split duct
Lokasi Ruang Master Control

3 IU-SC.1 & OU-SC.1 1 Unit 15,782,800 15,782,800


Kapasitas 4 PK
Tipe Indoor Split Duct
Lokasi Ruang Sub Control Studio 1

4 IU-EDT.01 s/d 07 & OU-EDT.01 s/d 08 8 Unit 2,992,000 23,936,000


Kapasitas 1/2 PK
Tipe Indoor Wall Mounted
Lokasi Ruang Editing

5 IU-SC2.01 & OU-SC2.01 1 Unit 15,782,800 15,782,800


Kapasitas 4 PK
Tipe Indoor Split Duct
Lokasi Sub Control Studio 2

6 IU-STD2.01 & OU-STD2.01 1 Unit 61,186,400 61,186,400


Kapasitas 15 PK
Tipe Indoor Ruang Studio 2
Lokasi

7 IU-PNL.01 s/d 02 & OU-NL.01 s/d 02 2 Unit 3,366,000 6,732,000


Kapasitas 1 PK
Tipe Indoor Wall Mounted
Lokasi Ruang Panel
Sub Total A PERALATAN UTAMA AC 191,290,800
BILL OF QUQNTITY (BOQ)
No. Jenis Pekerjaan Vol Sat Harga Satuan Jumlah Harga

B PERALATAN UTAMA FAN


Pengadaan dan pemasangan peralatan utama FAN, lengkap
dengan material bantu, accessories dan perlangkapan
lainnya sesuai dengan gambar dan spesifikasi teknis,
sehingga sistem berfungsi dengan baik.

Lantai 1 (Satu)
1 EAF-RRV-01 s/d 02 2 Unit 486,200 972,400
Kapasitas 530 Cfm
Tipe Wall Fan
Static Pressure
Lokasi R. Genset

Sub Total B PERALATAN UTAMA FAN 972,400

C PIPA REFRIGRANT DAN PIPA DRAIN


Pengadaan dan pemasangan pipa refrigerant lengkap
dengan isolasi, material bantu dan accessories lainnya,
sesuai gambar dan spesifikasi sehingga sistem berfungsi
dengan baik.

Lantai 1 (Satu)
1 Dari IU-STD.1 ke OU-STD.1
(L) 12,7 mm ; (G) 28,6 mm 7 mtr 273,768 1,916,376

2 Dari IU-MCL.01 ke OU-MCL.01


(L) 6,35 mm ; (G) 15,88 mm 8 mtr 116,688 933,504

3 Dari IU-SC.1 ke OU-SC.1


(L) 9,5 mm ; (G) 15,88 mm 9 mtr 116,688 1,050,192

4 Dari IU-EDT.01 s/d 07 ke OU-EDT.01 s/d 07


(L) 6,35 mm ; (G) 9,5 mm 73 mtr 81,532 5,951,836

5 Dari IU-SC2.01 ke& OU-SC2.01


(L) 9,5 mm ; (G) 15,88 mm 7 mtr 137,632 963,424

6 Dari IU-STD2.01 ke OU-STD2.01


(L) 12,7 mm ; (G) 28,6 mm 6 mtr 273,768 1,642,608

7 Dari IU-PNL.01 s/d 02 ke OU-NL.01 s/d 02


(L) 6,35 mm ; (G) 9,5 mm 12 mtr 81,532 978,384

BILL OF QUQNTITY (BOQ)

No. Jenis Pekerjaan Vol Sat Harga Satuan Jumlah Harga


Pengadaan dan pemasangan Pipa Drain AC, menggunakan
Pipa PVC berstandart JIS, Kelas VP/AW, tekanan 10 kg/cm²
c/w Isolasi

IU-STD.1
IU-MCL.01
IU-SC.1
IU-EDT.01 s/d 07
IU-SC2.01
IU-STD2.01
IU-PNL.01 s/d 02

6 Pipa Diameter 25 mm 134 mtr 38,746 5,199,767

Sub Total C PIPA REFRIGRANT DAN PIPA DRAIN 18,636,091

D DUCTING
Pengadaan dan pemasangan ducting untuk AC lengkap dengan
support dan aksesoris yang diperlukan mengikuti spesifikasi, gambar
dan intruksi dari pembuat

Lantai 1 (Satu)
IU-STD.1
1 SAD 800 x 300 mm PIR 9 m2 598,400 5,385,600
2 SAD 700 x 250 mm PIR 4 m2 546,040 2,184,160
3 SAD 500 x 200 mm PIR 8 m2 568,480 4,547,840
4 SAD 400 x 150 mm PIR 1 m2 553,520 553,520
5 FAD 300 X 300 mm BJLS 50 1 m2 456,280 456,280
6 RAD 800 x 300 mm PIR 4 m2 598,400 2,393,600
7 Plenum Box 1 bh 748,000 748,000

IU-MCL.01
8 SAD 500 x 150 mm PIR 3 m2 561,000 1,683,000
9 SAD 250 x 150 mm PIR 2 m2 441,320 882,640
10 FAD 150 X 100 mm BJLS 50 1 m2 516,120 516,120
11 RAD 400 x 150 mm PIR 2 m2 553,520 1,107,040
12 Plenum Box 1 bh 748,000 748,000

IU-SC.1
13 SAD 500 x 200 mm PIR 4 m2 568,480 2,273,920
14 SAD 200 x 150 mm PIR 2 m2 441,320 882,640
15 FAD 200 X 150 mm BJLS 1 m2 523,600 523,600
16 RAD 500 x 150 mm PIR 2 m2 561,000 1,122,000
17 Plenum Box 1 bh 748,000 748,000
BILL OF QUQNTITY (BOQ)

No. Jenis Pekerjaan Vol Sat


Harga Satuan Jumlah Harga
Harga Satuan Jumlah Harga

IU-SC2.01
18 SAD 500 x 200 mm PIR 5 m2 568,480 2,842,400
19 SAD 250 x 150 mm PIR 3 m2 441,320 1,323,960
20 FAD 200 X 150 mm BJLS 1 m2 523,600 523,600
21 RAD 700 x 250 mm PIR 2 m2 583,440 1,166,880
22 Plenum Box 1 bh 748,000 748,000

IU.STD.2
23 SAD 700 x 250 mm PIR 6 m2 583,440 3,500,640
24 SAD 500 x 200 mm PIR 16 m2 568,480 9,095,680
25 FAD 350 X 300 mm BJLS 1 m2 512,380 512,380
26 RAD 800 x 300 mm PIR 6 m2 598,400 3,590,400
27 Plenum Box 1 bh 748,000 748,000
Sub Total D DUCTING 50,807,900
E EQUIPMENT GRILLE
Lantai 1 (Satu)
Pengadaan dan pemasangan grille c/w box
1 IU-STD.1
SAD 300 x 300 mm 6 bh 774,180 4,645,080
Bar Grille Return 900 x 150 mm 4 bh 890,120 3,560,480
FAL 300 x 300 mm 1 bh 774,180 774,180
VD 300 x 300 mm 1 bh 774,180 774,180

2 IU-MCL.01
SAD 200 x 200 mm 2 bh 774,180 1,548,360
Bar Grille Return 500 x 100 mm 2 bh 774,180 1,548,360
FAL 150 x 100 mm 1 bh 774,180 774,180
VD 150 x 100 mm 1 bh 774,180 774,180

3 IU-SC.1
SAD 300 x 300 mm 2 bh 774,180 1,548,360
Bar Grille Return 900 x 100 mm 2 bh 856,460 1,712,920
FAL 200 x 150 mm 1 bh 774,180 774,180
VD 200 x 150 mm 1 bh 774,180 774,180

4 IU-SC2.01
SAD 300 x 300 mm 2 bh 774,180 1,548,360
Bar Grille Return 900 x 100 mm 2 bh 856,460 1,712,920
FAL 200 x 150 mm 1 bh 774,180 774,180
VD 200 x 150 mm 1 bh 774,180 774,180

BILL OF QUQNTITY (BOQ)


No. Jenis Pekerjaan Vol Sat
Harga Satuan Jumlah Harga

5 IU-STS2.01
SAD 450 x 350 mm 4 bh 774,180 3,096,720
Bar Grille Return 900 x 150 mm 6 bh 856,460 5,138,760
FAL 350 x 300 mm 1 bh 774,180 774,180
VD 350 x 300 mm 1 bh 774,180 774,180
Sub Total E EQUIPMENT GRILLE 33,802,120

F PENGKABELAN AC
Pengadaan dan pemasangan Kabel AC dari Indoor ke Outdoor
Lantai 1 (Satu)
1 Kabel NYM 3 x 2,5 mm2 121 mtr 39,644 4,796,924

Sub Total F PENGKABELAN AC 4,796,924


TOTAL 1 PEKERJAAN TATA UDARA 300,306,235
BILL OF QUQNTITY (BOQ)

No. Jenis Pekerjaan Vol Sat Harga Jumlah TOTAL


Satuan Harga PEKERJAAN

2 PEKERJAAN ELEKTRIKAL

A Pekerjaan Panel Listrik


Pengadaan, pemasangan dan pengujian Panel Listrik Tegangan
Rendah pada sistim 380/220 volt, 3 fasa, 50 Hz dengan rumah
panel yang dilengkapi pintu berkunci dari bahan pelat baja yang
di galvanis ketebalan minimum 2mm dng rangka baja, busbar
untuk fasa, neutral dan pentanahan, komponen lengkap
(switches, instrument dan metering) pada lokasi yang
ditentukan termasuk pondasi / penggantung,
pengaman/pelindung serta perlengkapan dan alat bantu lainya
sesuai gambar dan spesifikasi.

1 MCB BOX c/w KWH Meter 1 unit 990,000 990,000


2 MDP-PLN 1 unit 1,237,500 1,237,500
Panel Box, Type : Wall Mounting - -
IP : 40 - -
Thickness : Steel Plate 2,00 mm - -
Colour : RAL 7032 Powder Coating - -
INLET - -
- MCCB 3P 175-250A, 36kA CVS250F 1 bh 1,237,500 1,237,500
- Ampere Meter 0-40A 3 bh 33,000 99,000
- Volt Meter 1 bh 49,500 49,500
- CT : 250,/5a 3 bh 46,200 138,600
- VSS 7 Position 1 bh 66,000 66,000
OUTLET - -
- MCCB 3P 112-160A, 36kA CVS160F 1 bh 1,426,425 1,426,425
- MCCB 3P 70.0-100A, 36kA CVS100F 1 bh 742,500 742,500
- MCCB 3P 30A, 10kA EZC100F 1 bh 288,750 288,750
- PILOT LAMP 220V "RED,GREEN,YELLOW" (R-S-T) 3 bh 22,275 66,825
- FUSE CONTROL 3 bh 16,500 49,500
- -
- CU + ACCESSORIES 1 lot 1,875,000 1,875,000
- BOX + ASSEMBLING COST 1 lot 1,320,000 1,320,000
- -
3 MDP-VAC 1 unit 1,485,000 1,485,000
Panel Box, Type : Wall Mounting - -
IP : 40 - -
Thickness : Steel Plate 2,00 mm - -
Colour : RAL 7032 Powder Coating - -
INLET - -
- MCCB 3P 56.0-80A, 25kA CVS100B 1 bh 651,750 651,750
OUTGOING - -
- MCB 3P 50A, 10 kA iC60H-C 3 bh 618,750 1,856,250
- PILOT LAMP 220V "RED,GREEN,YELLOW" (R-S-T) 3 bh 22,275 66,825
- FUSE CONTROL 3 bh 16,500 49,500
- VSS 7 Position 1 bh 66,000 66,000
- Ampere Meter 0-80A 3 bh 33,000 99,000
- Volt Meter 1 bh 53,625 53,625
- CT : 80/5A 3 bh 33,000 99,000
- -
- CU + ACCESSORIES 1 lot 1,875,000 1,875,000
- BOX + ASSEMBLING COST 1 lot 1,320,000 1,320,000
- -
4 PDB-VAC.STUDIO.1 1 unit 73,013 73,013
Panel Box, Type : Wall Mounting - -
IP : 40 - -
Thickness : Steel Plate 2,00 mm - -
Colour : RAL 7032 Powder Coating - -
INLET - -
- MCCB 3P 50A, 18kA EZC100N 1 bh 392,700 392,700
- Ampere Meter 0-40A 3 bh 33,000 99,000
- Volt Meter 1 bh 53,625 53,625
- CT : 50,/5a 3 bh 31,350 94,050
- VSS 7 Position 1 bh 66,000 66,000
- -
- -
OUTLET - -
- MCB 3P 20A, 6 kA iC60N 2 bh 238,425 476,850
- MCB 1P 16A, 6 kA iC60N 2 bh 82,913 165,825
- MCB 1P 6A, 6 kA iC60N 7 bh 53,625 375,375
- PILOT LAMP 220V "RED,GREEN,YELLOW" (R-S-T) 3 bh 22,275 66,825
- FUSE CONTROL 3 bh 16,500 49,500
- -
- CU + ACCESSORIES 1 lot 1,875,000 1,875,000
- BOX + ASSEMBLING COST 1 lot 1,320,000 1,320,000
- -
5 PDB-VAC.STUDIO.2 1 unit 73,013 73,013
Panel Box, Type : Wall Mounting - -
IP : 40 - -
Thickness : Steel Plate 2,00 mm - -
Colour : RAL 7032 Powder Coating - -
INLET - -
- MCCB 3P 50A, 18kA EZC100N 1 bh 255,750 255,750
- Ampere Meter 0-40A 3 bh 33,000 99,000
- Volt Meter 1 bh 33,000 33,000
- CT : 50,/5a 3 bh 31,350 94,050
- VSS 7 Position 1 bh 66,000 66,000
OUTLET - -
- MCB 3P 20A, 6 kA iC60N 2 bh 453,750 907,500
- MCB 1P 16A, 6 kA iC60N 2 bh 99,000 198,000
- MCB 1P 6A, 6 kA iC60N 7 bh 58,275 407,925
- PILOT LAMP 220V "RED,GREEN,YELLOW" (R-S-T) 3 bh 22,275 66,825
- FUSE CONTROL 3 bh 16,500 49,500
- -
- CU + ACCESSORIES 1 lot 1,875,000 1,875,000
- BOX + ASSEMBLING COST 1 lot 1,320,000 1,320,000
- -
6 MDP-UTAMA 1 unit 3,217,500 3,217,500
Panel Box, Type : Wall Mounting - -
IP : 40 - -
Thickness : Steel Plate 2,00 mm - -
Colour : RAL 7032 Powder Coating - -
INLET - -
- MCCB 3P 112-160A, 36kA CVS160F 2 bh 907,500 1,815,000
- COS 4P 250A 1 bh 6,187,500 6,187,500
- DIRISR A40 110 to 400 VAC or 120 to 350 VDC 1 bh 3,712,500 3,712,500
- Arrester 4P 65 KA 400V PF65 1 bh 1,485,000 1,485,000
OUTGOING - -
- MCCB 3P 112-160A, 25kA CVS160B 1 bh 1,072,500 1,072,500
- MCCB 3P 87.5-125A, 25kA CVS160B 1 bh 990,000 990,000
- MCCB 3P 70.0-100A, 25kA CVS100B 1 bh 577,500 577,500
- Push Button Emergency 2 bh 21,450 42,900
- Push Button Green (On) 2 bh 41,250 82,500
- Push Button Red (Off) 2 bh 41,250 82,500
- Pilot Lamp Red 2 bh 22,275 44,550
- Pilot Lamp Green 2 bh 22,275 44,550
- PILOT LAMP 220V "RED,GREEN,YELLOW" (R-S-T) 6 bh 22,275 133,650
- FUSE CONTROL 6 bh 16,500 99,000
- VSS 7 Position 2 bh 66,000 132,000
- Ampere Meter 160A 6 bh 1,237,500 7,425,000
- Volt Meter 2 bh 33,000 66,000
- CT : 160/5A 8 bh 70,125 561,000
- TIMER 220VAC 2 bh 70,125 140,250
- RELAI 220VAC 5 bh 28,875 144,375
- Under Voltage Relay 1 bh 189,750 189,750
- -
- CU + ACCESSORIES 1 lot 1,875,000 1,875,000
- BOX + ASSEMBLING COST 1 lot 1,320,000 1,320,000
- -
7 MDB-SARPRAS 1 unit 1,320,000 1,320,000
Panel Box, Type : Wall Mounting - -
IP : 40 - -
Thickness : Steel Plate 2,00 mm - -
Colour : RAL 7032 Powder Coating - -
- -
- -
INLET - -
- MCCB 3P 112-160A, 25kA CVS160B 1 bh 1,155,000 1,155,000
OUTGOING - -
- MCB 3P 40A, 10 kA iC60H-C 2 bh 1,155,000 2,310,000
- MCB 3P 32A, 10 kA iC60H-C 6 bh 660,000 3,960,000
- PILOT LAMP 220V "RED,GREEN,YELLOW" (R-S-T) 3 bh 22,275 66,825
- FUSE CONTROL 3 bh 16,500 49,500
- VSS 7 Position 2 bh 66,000 132,000
- Ampere Meter 0-120A 3 bh 54,450 163,350
- Volt Meter 1 bh 33,000 33,000
- CT : 160/5A 3 bh 70,125 210,375
- -
- CU + ACCESSORIES 1 lot 1,875,000 1,875,000
- BOX + ASSEMBLING COST 1 lot 1,320,000 1,320,000
- -
8 PDB-SARPRAS STUDIO-1 1 unit 73,013 73,013
Panel Box, Type : Wall Mounting - -
IP : 40 - -
Thickness : Steel Plate 2,00 mm - -
Colour : RAL 7032 Powder Coating - -
INLET - -
- MCCB 3P 40A, 10kA EZC100F 1 bh 288,750 288,750
- Ampere Meter 0-40A 3 bh 54,450 163,350
- Volt Meter 1 bh 33,000 33,000
- VSS 7 Position 1 bh 66,000 66,000
OUTLET - -
- MCB 4P 32A, 10 bh 379,500 3,795,000
- MCB 1P 16A, 6 kA iC60N 4 bh 82,913 331,650
- MCB 1P 6A, 6 kA iC60N 12 bh 99,000 1,188,000
- PILOT LAMP 220V "RED,GREEN,YELLOW" (R-S-T) 3 bh 22,275 66,825
- FUSE CONTROL 3 bh 16,500 49,500
- CU + ACCESSORIES 1 lot 1,875,000 1,875,000
- BOX + ASSEMBLING COST 1 lot 1,320,000 1,320,000
- -
9 PDB-SARPRAS SC-1 1 unit 73,013 73,013
Panel Box, Type : Wall Mounting - -
IP : 40 - -
Thickness : Steel Plate 2,00 mm - -
Colour : RAL 7032 Powder Coating - -
INLET - -
- MCCB 3P 40A, 10kA EZC100F 1 bh 288,750 288,750
- Ampere Meter 0-40A 3 bh 54,450 163,350
- Volt Meter 1 bh 33,000 33,000
- VSS 7 Position 1 bh 66,000 66,000
OUTLET - -
- MCB 1P 25A, 6 kA iC60N 14 bh 53,625 750,750
- PILOT LAMP 220V "RED,GREEN,YELLOW" (R-S-T) 1 bh 22,275 22,275
- FUSE CONTROL 3 bh 16,500 49,500
- -
- CU + ACCESSORIES 1 bh 1,875,000 1,875,000
- BOX + ASSEMBLING COST 1 bh 1,320,000 1,320,000
- -
10 PDB-SARPRAS MCR & IT 1 unit 73,013 73,013
Panel Box, Type : Wall Mounting - -
IP : 40 - -
Thickness : Steel Plate 2,00 mm - -
Colour : RAL 7032 Powder Coating - -
INLET - -
- MCCB 3P 40A, 10kA EZC100F 1 bh 288,750 288,750
- Ampere Meter 0-40A 3 bh 54,450 163,350
- Volt Meter 1 bh 33,000 33,000
- VSS 7 Position 1 bh 66,000 66,000
OUTLET - -
- MCB 1P 16A, 6 kA iC60N 5 bh 82,913 414,563
- MCB 1P 6A, 6 kA iC60N 7 bh 99,000 693,000
- PILOT LAMP 220V "RED,GREEN,YELLOW" (R-S-T) 3 bh 22,275 66,825
- FUSE CONTROL 3 bh 16,500 49,500
- -
- -
- -
- CU + ACCESSORIES 1 lot 1,875,000 1,875,000
- BOX + ASSEMBLING COST 1 lot 1,320,000 1,320,000
- -
11 PDB-SARPRAS STUDIO-2 1 unit 73,013 73,013
Panel Box, Type : Wall Mounting - -
IP : 40 - -
Thickness : Steel Plate 2,00 mm - -
Colour : RAL 7032 Powder Coating - -
INLET - -
- MCCB 3P 40A, 10kA EZC100F 1 bh 288,750 288,750
- Ampere Meter 0-40A 3 bh 54,450 163,350
- Volt Meter 1 bh 33,000 33,000
- VSS 7 Position 1 bh 66,000 66,000
OUTLET - -
- MCB 4P 32A, 10 bh 379,500 3,795,000
- MCB 1P 16A, 6 kA iC60N 4 bh 82,913 331,650
- MCB 1P 6A, 6 kA iC60N 12 bh 99,000 1,188,000
- PILOT LAMP 220V "RED,GREEN,YELLOW" (R-S-T) 3 bh 22,275 66,825
- FUSE CONTROL 3 bh 16,500 49,500
- CU + ACCESSORIES 1 lot 1,875,000 1,875,000
- BOX + ASSEMBLING COST 1 lot 1,320,000 1,320,000
- -
12 PDB-SARPRAS SC-2 1 unit 73,013 73,013
Panel Box, Type : Wall Mounting - -
IP : 40 - -
Thickness : Steel Plate 2,00 mm - -
Colour : RAL 7032 Powder Coating - -
INLET - -
- MCCB 3P 40A, 10kA EZC100F 1 bh 288,750 288,750
- Ampere Meter 0-40A 3 bh 54,450 163,350
- Volt Meter 1 bh 33,000 33,000
- VSS 7 Position 1 bh 66,000 66,000
OUTLET - -
- MCB 1P 25A, 6 kA iC60N 14 bh 53,625 750,750
- PILOT LAMP 220V "RED,GREEN,YELLOW" (R-S-T) 1 bh 22,275 22,275
- FUSE CONTROL 3 bh 16,500 49,500
- -
- CU + ACCESSORIES 1 bh 1,875,000 1,875,000
- BOX + ASSEMBLING COST 1 bh 1,320,000 1,320,000
- -
13 PDB-SARPRAS EDITING 1 unit 73,013 73,013
Panel Box, Type : Wall Mounting - -
IP : 40 - -
Thickness : Steel Plate 2,00 mm - -
Colour : RAL 7032 Powder Coating - -
INLET - -
- MCCB 3P 40A, 18kA EZC100N 1 bh 288,750 288,750
- Ampere Meter 0-40A 3 bh 54,450 163,350
- Volt Meter 1 bh 33,000 33,000
- VSS 7 Position 1 bh 66,000 66,000
OUTLET - -
- MCB 1P 10A, 6 kA iC60N 8 99,825 798,600
- MCB 1P 6A, 6 kA iC60N 12 bh 99,000 1,188,000
- PILOT LAMP 220V "RED,GREEN,YELLOW" (R-S-T) 1 bh 22,275 22,275
- FUSE CONTROL 3 bh 16,500 49,500
- -
- CU + ACCESSORIES 1 lot 1,875,000 1,875,000
- BOX + ASSEMBLING COST 1 lot 1,320,000 1,320,000
- -
14 MDP-UPS 1 unit 1,320,000 1,320,000
Panel Box, Type : Wall Mounting - -
IP : 40 - -
Thickness : Steel Plate 2,00 mm - -
Colour : RAL 7032 Powder Coating - -
INLET - -
- MCCB 3P 87.5-125A, 25kA CVS160B 1 bh 862,500 862,500
OUTGOING - -
- MCCB 3P 80A, 10kA EZC100F 2 bh 300,000 600,000
- -
- -
- MCB 3P 40A, 10 kA iC60H-C 6 bh 288,750 1,732,500
- PILOT LAMP 220V "RED,GREEN,YELLOW" (R-S-T) 3 bh 22,275 66,825
- FUSE CONTROL 3 bh 16,500 49,500
- VSS 7 Position 1 bh 33,000 33,000
- Ampere Meter 0-120A 3 bh 42,900 128,700
- Volt Meter 1 bh 33,000 33,000
- CT : 120/5A 3 bh 51,975 155,925
- -
- CU + ACCESSORIES 1 lot 1,875,000 1,875,000
- BOX + ASSEMBLING COST 1 lot 1,320,000 1,320,000
- -
15 PDB-UPS SC-1 1 unit 73,013 73,013
Panel Box, Type : Wall Mounting - -
IP : 40 - -
Thickness : Steel Plate 2,00 mm - -
Colour : RAL 7032 Powder Coating - -
INLET - -
- MCCB 3P 40A, 10kA EZC100F 1 bh 288,750 288,750
- Ampere Meter 0-40A 3 bh 1,320,000 3,960,000
- Volt Meter 1 bh 33,000 33,000
- VSS 7 Position 1 bh 33,000 33,000
OUTLET - -
- MCB 1P 25A, 6 kA iC60N 14 bh 61,875 866,250
- PILOT LAMP 220V "RED,GREEN,YELLOW" (R-S-T) 1 bh 22,275 22,275
- FUSE CONTROL 3 bh 16,500 49,500
- -
- CU + ACCESSORIES 1 lot 1,875,000 1,875,000
- BOX + ASSEMBLING COST 1 lot 1,320,000 1,320,000
- -
16 PDB-UPS SC-2 1 unit 1,320,000 1,320,000
Panel Box, Type : Wall Mounting - -
IP : 40 - -
Thickness : Steel Plate 2,00 mm - -
Colour : RAL 7032 Powder Coating - -
INLET - -
- MCCB 3P 40A, 10kA EZC100F 1 bh 288,750 288,750
- Ampere Meter 0-40A 3 bh 1,320,000 3,960,000
- Volt Meter 1 bh 33,000 33,000
- VSS 7 Position 1 bh 33,000 33,000
OUTLET - -
- MCB 1P 25A, 6 kA iC60N 14 bh 61,875 866,250
- PILOT LAMP 220V "RED,GREEN,YELLOW" (R-S-T) 1 bh 22,275 22,275
- FUSE CONTROL 3 bh 16,500 49,500
- -
- CU + ACCESSORIES 1 lot 1,875,000 1,875,000
- BOX + ASSEMBLING COST 1 lot 1,320,000 1,320,000
- -
17 PDB-UPS EDITING 1 unit 1,320,000 1,320,000
Panel Box, Type : Wall Mounting - -
IP : 40 - -
Thickness : Steel Plate 2,00 mm - -
Colour : RAL 7032 Powder Coating - -
INLET - -
- MCCB 3P 40A, 10kA EZC100F 1 bh 288,750 288,750
- Ampere Meter 0-40A 3 bh 1,320,000 3,960,000
- Volt Meter 1 bh 33,000 33,000
- VSS 7 Position 1 bh 33,000 33,000
OUTLET - -
- MCB 1P 16A, 6 kA iC60N 12 bh 82,913 994,950
- PILOT LAMP 220V "RED,GREEN,YELLOW" (R-S-T) 1 bh 22,275 22,275
- FUSE CONTROL 3 bh 16,500 49,500
- -
- CU + ACCESSORIES 1 lot 1,875,000 1,875,000
- BOX + ASSEMBLING COST 1 lot 1,320,000 1,320,000
- -
- -
- -
18 PDB-UPS MCR & IT 1 unit 1,320,000 1,320,000
Panel Box, Type : Wall Mounting - -
IP : 40 - -
Thickness : Steel Plate 2,00 mm - -
Colour : RAL 7032 Powder Coating - -
INLET - -
- MCCB 3P 40A, 10kA EZC100F 1 bh 288,750 288,750
- Ampere Meter 0-40A 3 bh 1,320,000 3,960,000
- Volt Meter 1 bh 33,000 33,000
- VSS 7 Position 1 bh 33,000 33,000
OUTLET - -
- MCB 1P 32A, 6 kA iC60N 7 bh 64,350 450,450
- PILOT LAMP 220V "RED,GREEN,YELLOW" (R-S-T) 3 bh 22,275 66,825
- FUSE CONTROL 3 bh 16,500 49,500
- -
- CU + ACCESSORIES 1 lot 1,875,000 1,875,000
- BOX + ASSEMBLING COST 1 lot 1,320,000 1,320,000
- -
19 PDB-UPS STUDIO-1 1 unit 1,320,000 1,320,000
Panel Box, Type : Wall Mounting - -
IP : 40 - -
Thickness : Steel Plate 2,00 mm - -
Colour : RAL 7032 Powder Coating - -
INLET - -
- MCCB 3P 40A, 10kA EZC100F 1 bh 288,750 288,750
- Ampere Meter 0-40A 3 bh 1,320,000 3,960,000
- Volt Meter 1 bh 33,000 33,000
- VSS 7 Position 1 bh 33,000 33,000
OUTLET - -
- MCB 1P 25A, 6 kA iC60N 6 bh 61,875 371,250
- PILOT LAMP 220V "RED,GREEN,YELLOW" (R-S-T) 3 bh 22,275 66,825
- FUSE CONTROL 3 bh 16,500 49,500
- -
- CU + ACCESSORIES 1 lot 1,875,000 1,875,000
- BOX + ASSEMBLING COST 1 lot 1,320,000 1,320,000
- -
20 PDB-UPS STUDIO-2 1 unit 1,320,000 1,320,000
Panel Box, Type : Wall Mounting - -
IP : 40 - -
Thickness : Steel Plate 2,00 mm - -
Colour : RAL 7032 Powder Coating - -
INLET - -
- MCCB 3P 40A, 10kA EZC100F 1 bh 288,750 288,750
- Ampere Meter 0-40A 3 bh 1,320,000 3,960,000
- Volt Meter 1 bh 33,000 33,000
- VSS 7 Position 1 bh 33,000 33,000
OUTLET - -
- MCB 1P 25A, 6 kA iC60N 6 bh 61,875 371,250
- PILOT LAMP 220V "RED,GREEN,YELLOW" (R-S-T) 3 bh 22,275 66,825
- FUSE CONTROL 3 bh 16,500 49,500
- -
- CU + ACCESSORIES 1 lot 1,875,000 1,875,000
- BOX + ASSEMBLING COST 1 lot 1,320,000 1,320,000
-
Sub Total A Pekerjaan Panel Listrik 174,895,050
-
B Pekerjaan Kabel Feeder -

Pengadaan, pemasangan, dan pengujian kabel tegangan -


menengah dan tegangan rendah, termasuk accessories dan
material bantu lainnya sesuai dengan gambar dan spesiifkasi
teknis.
1 Dari KWH METER Ke MDP-PLN -
NYY 4 (1C x 150 mm2) + BCC 70 mm2 11 m' 219,450 2,413,950
-
2 Dari MDP-PLN Ke : -
NYY 4 x 35 mm2 + BCC 16 mm2 MDP-VAC 10 m' 271,920 2,719,200
NYY 4 x 70 mm2 + BCC 35 mm2 MDP-UTAMA 9 m' 543,675 4,893,075
-
-
3 Dari MDP-VAC Ke : -
NYY 4 x 16 mm2 + BCC 16 mm2 PDB-VAC STUDIO-1 61 m' 150,975 9,209,475
NYY 4 x 16 mm2 + BCC 16 mm2 PDB-VAC STUDIO-2 51 m' 150,975 7,699,725
-
4 Dari MDP-UTAMA Ke : -
NYY 4 x 70 mm2 + BCC 35 mm2 MDB-SARPRAS 51 m' 543,675 27,727,425
NYY 4 x 50 mm2 + BCC 25 mm2 MDP-UPS 55 m' 362,175 19,919,625
NYY 4 (1C x 70 mm2) + BCC 35 mm2 PKG 11 m' 543,675 5,980,425
-
5 Dari MDB-SARPRAS Ke : -
NYY 4 x 16 mm2 + BCC 16 mm2 PDB-Sarpras Studio 1 58 m' 150,975 8,756,550
NYY 4 x 10 mm2 + BCC 10 mm2 PDB-Sarpras SC-1 76 m' 80,768 6,138,330
NYY 4 x 10 mm2 + BCC 10 mm2 PDB-Sarpras MCR & IT 82 m' 80,768 6,622,935
NYY 4 x 16 mm2 + BCC 16 mm2 PDB-Sarpras Studio 2 53 m' 150,975 8,001,675
NYY 4 x 10 mm2 + BCC 10 mm2 PDB-Sarpras SC-2 37 m' 80,768 2,988,398
NYY 4 x 10 mm2 + BCC 10 mm2 PDB-Sarpras Editing 79 m' 80,768 6,340,249
-
6 Dari MDP-UPS -
NYY 4 x 25 mm2 + BCC 16 mm2 PDB-UPS-SC.1 75 m' 196,350 14,726,250
NYY 4 x 25 mm2 + BCC 16 mm2 PDB-UPS-SC.2 36 m' 196,350 7,068,600
NYY 4 x 10 mm2 + BCC 10 mm2 PDB-UPS-EDITING 78 m' 80,768 6,259,481
NYY 4 x 10 mm2 + BCC 10 mm2 PDB-UPS MCR & IT 81 m' 80,768 6,542,168
NYY 4 x 10 mm2 + BCC 10 mm2 PDB-UPS-STUDIO.1 57 m' 80,768 4,603,748
NYY 4 x 10 mm2 + BCC 10 mm2 PDB-UPS-STUDIO.2 52 m' 80,768 4,199,910
-
Sub Total B Pekerjaan Kabel Feeder 162,811,193
-
C PEKERJAAN PENTANAHAN -
Pengadaan dan pemasangan sistem pentanahan -
1 Busbar MDP-UTAMA 1 bh 288,750 288,750
2 Busbar Grounding MDP-VAC 1 bh 288,750 288,750
3 Busbar Grounding MDB-SARPRAS 1 bh 288,750 288,750
4 Busbar Grounding EC (Elektronik) 1 bh 39,188 39,188
5 Grounding Neutral Genset BC 50 mm2 1 set 70,125 70,125
6 Grounding Body Genset BC 50 mm2 1 set 70,125 70,125
7 Grounding Elektronik BC 35 mm2 1 set 46,200 46,200
8 Grounding Panel MDB Utama BC 70 mm2 1 set 103,125 103,125
-
Sub Total C PEKERJAAN PENTANAHAN 1,195,013
-
D Pekerjaan Kabel Ladder & Tray -
Pengadaan dan pemasangan Kabel Rak terbuat dari bahan hot
rolled steel sheet hot dip electro galvanized mild steel dengan
tebal minimum 1,8 mm dalam bentuk, ukuran dan lay out yang
ditentukan, klem kabel dari aluminium dan mur baut stainless
steel termasuk gantungan besi plat atau besi siku (dicat
zinchromat) ke plat beton atap atau dinding dengan ikatan
ramset (fisher plug) lengkap dengan peralatan bantu dan -
perlengkapan sesuai gambar dan spesifikasi.

Lantai 2 -
1 Tray 200 x 100 mm 54 m 247,500 13,365,000
-
Sub Total D Pekerjaan Kabel Ladder & Tray 13,365,000
-
E Pekerjaan Armature Lampu dan Instalasinya -
Pengadaan, pemasangan dan pengujian Armatur Lampu, Saklar,
Stop Kontak dan aksesoris listrik berikut, termasuk semua
sambungan kabel dan sistim saluran, grounding, pemasangan
pada lokasi dengan cara yang ditentukan, termasuk terminal,
dan semua asesoris pelengkap lainnya yang diperlukan,
dikerjakan sesuai gambar, spesifikasi dan petunjuk pabrik -
pembuat.

Lantai 1 -
1 Downlight LED 18 Watt Dimmable 38 bh 135,000 5,130,000
2 Spot Light LED 36 Watt 12 bh 154,800 1,857,600
3 Down Light LED 70 Watt 7 Watt 6 bh 63,000 378,000
4 Linear LED 12 Watt 7 bh 67,500 472,500
------------------------------------ -
5 NYA 3 x 2,5 mm2 + PCV Conduit HI 20 mm ; u/ Inst. Lampu 38 titik 108,000 4,104,000

-
RUANG GENSET -
1 TL Balk 1 x 19 Watt 4 bh 132,000 528,000
------------------------------------ -
2 NYA 3 x 2,5 mm2 + PCV Conduit HI 20 mm ; u/ Inst. Lampu 4 titik 108,000 432,000
-
Sub Total E Pekerjaan Armature Lampu dan Instalasinya 12,902,100
-
F Pekerjaan Saklar & Stop Kontak -
Pengadaan, pemasangan dan pengujian Saklar, Stop Kontak
dan aksesoris listrik berikut, termasuk semua sambungan kabel
dan sistim saluran, grounding, pemasangan pada lokasi dengan
cara yang ditentukan, termasuk terminal, dan semua asesoris
pelengkap lainnya yang diperlukan, dikerjakan sesuai gambar, -
spesifikasi dan petunjuk pabrik pembuat.

Lantai 1 -
1 Saklar Tunggal 6 bh 14,850 89,100
2 Saklar Ganda 8 bh 18,150 145,200
3 Dimmer Lampu 6 bh 56,925 341,550
-
RUANG GENSET -
1 Saklar Ganda 1 bh 18,150 18,150
-
Sub Total F Pekerjaan Saklar & Stop Kontak 594,000
TOTAL 2 PEKERJAAN ELEKTRIKAL 365,762,355
BILL OF QUQNTITY (BOQ)

No. Jenis Pekerjaan Vol Sat Harga


Jumlah Harga
Satuan

PEKERJAAN FIRE ALARM


A PERALATAN UTAMA
Ruang Master Control
1 MCPFA Addressable 1 loops 1 Unit 21,120,000 21,120,000
2 UPS 500 VA, Backup Battery 4 jam 1 Unit 864,000 864,000
3 Annunciator di Lantai 2 1 unit 1,440,000 1,440,000
4 Rack Peralatan 1 Unit 7,680,000 7,680,000

Sub Total A PERALATAN UTAMA 31,104,000


B KABEL FEEDER
FRC 3 x 1,5 mm2 + PVC Conduit dia. 20 mm
1 Dari MCPFA 1 Line ke PABX 20 m' 30,720 614,400
2 Dari MCPFA Ke PP-VAC 30 m' 30,720 921,600
3 Dari MCPFA Ke CCTV 9 m' 30,720 276,480
4 Dari MCPFA Ke LVMDP 82 m' 30,720 2,519,040

Kabel Power FRC 2 x 1,5 mm2 +


Kabel Kontrol FRC STP 18 AWG 2 Pairs +
PVC Conduit dia. 20 mm
5 Dari MCPFA Ke TB.FA 9 m' 70,080 630,720
6 Dari TB.FA-1 Ke MCPFA 9 m' 70,080 630,720

Kabel NYA 2 x 1,5 mm2 + PVC Conduit dia. 20 mm


7 Dari MCPFA Ke TB.FA 9 m' 10,560 95,040

Kabel FRC 2 x 1,5 mm2 + PVC Conduit dia. 20 mm


8 Dari MCPFA Ke Announciator 13 m' 70,080 911,040

Sub Total B KABEL FEEDER 6,599,040

C EQUIPMENT FIRE ALARM


Detektor termasuk semua accessories sesuai dengan spesifikasi.
Lantai 1
1 TB.FA 1 Unit 369,600 369,600
2 Fire Detector (ROR) 10 bh 192,000 1,920,000
3 Horn Strobe 1 bh 854,400 854,400
4 Manual Call Point 1 bh 172,800 172,800
-------------------------------------------
5 FRC 2 x 1,5 mm2 + PVC Cond. dia. 20 mm 10 ttk 350,400 3,504,000
u/ Inst. Detector
6 FRC 2 x 1,5 mm2 + PVC Cond. dia. 20 mm 1 ttk 350,400 350,400
u/ Inst. Horn Strobe
7 FRC 2 x 1,5 mm2 + PVC Cond. dia. 20 mm 1 ttk 350,400 350,400
u/ Inst. Manual Call P
Sub Total C EQUIPMENT FIRE ALARM 7,521,600
TOTAL PEKERJAAN FIRE ALARM 45,224,640
BILL OF QUQNTITY (BOQ)

No. Jenis Pekerjaan Vol Sat Harga Satuan Jumlah Harga

PEKERJAAN CCTV
A PERALATAN UTAMA
1 HUB 1 unit 270,000 270,000
2 NVR 1 x 12 CH c/w Controller Eternet (HD 3 TB) 1 unit 3,456,000 3,456,000
3 Monitor LED 32" c/w Bracket 1 unit 3,024,000 3,024,000
4 Pengkabelan Ruang Kontrol CCTV 1 lot 6,480,000 6,480,000

Sub Total A PERALATAN UTAMA 13,230,000

B KABEL FEEDER
Kabel Power NYM 2 x 1,5 mm2 + UTP CAT 6 +
PVC Conduit dia. 20 mm ; dari NVR ke :
1 Switch HUB 8 Port Lantai 1 9 m' 135,000 1,215,000

Sub Total B KABEL FEEDER 1,215,000

C EQUIPMENT CCTV
Equipment CCTV termasuk semua accessories sesuai dengan spesifikasi.
Lantai 1
1 Switch HUB 8 Port PoE Power Supply c/w Rack 1 bh 1,200,960 1,200,960
2 Modular Camera 6 bh 270,000 1,620,000
--------------------------------------------- -
3 UTP CAT 6 4 Pairs + PVC Conduit 20 mm 6 ttk 40,500 243,000
u/ Inst. Camera
Sub Total C EQUIPMENT CCTV 3,063,960
TOTAL PEKERJAAN CCTV 17,508,960
S Curve

TAHUN
No DESCRIPTION AMOUNTBOBOT BLN JUNI
Uraian Jumlah TGL 01~10

A. PEKERJAAN PERSIAPAN ### 4.78% 1.19%

B BANGUNAN TYPICAL 1
1 PEKERJAAN STRUKTUR
PEKERJAAN TANAH ### 1.48% 0.37%
STRUKTUR BETON ### 2.85%
PEKERJAAN STRUKTUR BAJA ### 19.23%

2 PEKERJAAN ARSITEKTUR & INTERIOR


PEKERJAAN DINDING DAN PELAPIS ### 5.06%
PEKERJAAN LANTAI DAN PELAPIS ### 0.91%
PEKERJAAN PLAFOND ### 0.49%
PEKERJAAN KUSEN PINTU DAN JENDELA ### 1.21%
PEKERJAAN ATAP DAN LAIN-LAIN ### 1.43%
PEKERJAAN FAÇADE ### 10.24%

C BANGUNAN EKSISTING
1 PEKERJAAN STRUKTUR
PEKERJAAN TANAH ### 2.15% 0.54%
STRUKTUR BETON ### 1.74%
PEKERJAAN STRUKTUR BAJA ### 5.84%

2 PEKERJAAN ARSITEKTUR & INTERIOR


PEKERJAAN DINDING DAN PELAPIS ### 13.29%
PEKERJAAN LANTAI DAN PELAPIS ### 1.95%
PEKERJAAN PLAFOND ### 0.89%
PEKERJAAN KUSEN PINTU DAN JENDELA ### 0.84%
PEKERJAAN FIX FURNITURE ### 0.65%

D BANGUNAN MASTER CONTROL


PEKERJAAN LANTAI DAN PELAPIS ### 0.46%

E PEKERJAAN TATA UDARA ### 10.11%

F PEKERJAAN ELEKTRIKAL ### 12.31%

G PEKERJAAN FIRE ALARM ### 1.52%

H PEKERJAAN CCTV ### 0.59%


### 100%
BOBOT RENCANA MINGGUAN 2.10%
BOBOT RENCANA KOMULATIF 0.00% 2.10%
BOBOT ACTUAL MINGGUAN
BOBOT ACTUAL KOMULATIF MINGGUAN
PEKERJAAN MAJU / TERLAMBAT ( DEVIASI ) +/-
JUNI JULI AGUSTUS
12~17 19~24 26~01 03~08 10~15 17~22 24~29 31~05 07~12 14~19

1.19% 1.19% 1.19%

0.37% 0.37% 0.37%


0.71% 0.71% 0.71% 0.71%
1.37% 1.37% 1.37% 1.37% 1.37% 1.37% 1.37%

0.63% 0.63% 0.63% 0.63% 0.63% 0.63% 0.63%

0.54% 0.54% 0.54%


0.43% 0.43% 0.43% 0.43%
0.42% 0.42% 0.42% 0.42% 0.42% 0.42% 0.42% 0.42%

1.66% 1.66% 1.66% 1.66% 1.66% 1.66%


3.25% 3.25% 3.67% 3.57% 4.09% 4.09% 4.09% 4.09% 4.09% 4.09%
5.35% 8.60% 12.26% 15.83% 19.92% 24.00% 28.09% 32.18% 36.26% 40.35%
2023
USTUS SEPTEMBER OKTOBER
21~26 28~02 04~09 11~16 18~23 25~30 02~07 09~14 16~21 23~28

1.37% 1.37% 1.37% 1.37% 1.37% 1.37% 1.37%

0.63%
0.23% 0.23% 0.23% 0.23%
0.12% 0.12% 0.12% 0.12%
0.30% 0.30% 0.30% 0.30%
0.71% 0.71%
1.28% 1.28% 1.28% 1.28% 1.28% 1.28% 1.28%

0.42% 0.42% 0.42% 0.42% 0.42% 0.42%

1.66% 1.66%
0.49% 0.49% 0.49% 0.49%
0.22% 0.22% 0.22% 0.22%
0.21% 0.21% 0.21% 0.21%
0.16% 0.16% 0.16%

0.11% 0.11% 0.11% 0.11%

1.26% 1.26% 1.26% 1.26%

1.23% 1.23% 1.23% 1.23% 1.23% 1.23% 1.23% 1.23%


4.09% 4.17% 4.56% 5.13% 5.47% 5.99% 6.00% 4.79% 4.45% 3.94%
44.43% 48.60% 53.16% 58.29% 63.76% 69.75% 75.76% 80.55% 84.99% 88.93%
NOVEMBR DESEMBER KETERANG
30~04 06~11 13~18 20~25 27~02 04~09 11~16 18~23 25~30

1.28%

0.16%

1.26% 1.26% 1.26% 1.26%

1.23% 1.23%

0.51% 0.51% 0.51%

0.29% 0.29%
3.94% 3.00% 2.07% 2.07%
92.87% 95.87% 97.93% 100.00%