VOLUME HITUNGAN BESI PLAT KONVENSIONAL GEDUNG PARKIR UTARA

KETERANGAN DIA BERAT SAT STATUS

LANTAI BASEMENT D13 355,795.13 Kg

LANTAI 1 D10 81,926.09 Kg

LANTAI 2 D10 79,473.32 Kg

LANTAI 3 D10 69,713.80 Kg

LANTAI ATAP D10 103,071.99 Kg

LANTAI LMR D10 1,511.17 Kg

TOTAL BERAT BESI PLAT 691,491.50 Kg

Makassar, 30 Juli 2019

Dibuat Diperiksa

M. Alimin Husairi
QS WG QS DBG
PERHITUNGAN VOLUME PLAT KONVENSIONAL LANTAI BASEMENT GEDUNG PARKIR UTARA
DIMENSI (m2) TOTAL
VOLUME TOTAL VOLUME
TYPE PEKERJAAN BETON h X Y VOLUME BETON RASIO VOLUME BESI LT 1 SAT
BETON LT 1
(m) (m) (m)
(a) (b) (axb)

PLAT S2 ( 3.9m x 8m ) 0.200 3.900 8.00 Kg


Tulangan Bawah Arah X
Tulangan Full Lapangan 136.75 Kg Kg
Tulangan Full Tumpuan 87.52 Kg Kg
Tulangan Extra Tumpuan 90.31 Kg Kg
Tulangan Atas Arah X
Tulangan Full Lapangan 136.75 Kg Kg
Tulangan Full Tumpuan 93.77 Kg Kg
Tulangan Extra Lapangan 161.23 Kg Kg
Tulangan Bawah Arah Y
Tulangan Full Lapangan 96.27 Kg Kg
Tulangan Ful Tumpuan 175.04 Kg Kg
Tulangan Extra Lapangan 75.60 Kg Kg
Tulangan Atas Arah Y
Tulangan Full Lapangan 96.27 Kg Kg
Tulangan Full Lapangan 175.04 Kg Kg
Tulangan Extra Tumpuan 56.68 Kg Kg
Tul kaki ayam 10.42 Kg Kg
Tul OverLap arah X 18.51 Kg Kg
Tul OverLap arah Y 22.39 Kg Kg

1,432.54 Kg 7.056 203.02 Kg


PLAT S2 ( 2 m x 8 m ) 0.200 2.000 8.00 Kg
Tulangan Bawah Arah X
Tulangan Full Lapangan 86.27 Kg Kg
Tulangan Full Tumpuan 23.96 Kg Kg
Tulangan Extra Tumpuan 69.24 Kg Kg
Tulangan Atas Arah X
Tulangan Full Lapangan 86.27 Kg Kg
Tulangan Full Tumpuan 27.09 Kg Kg
Tulangan Extra Lapangan 115.97 Kg Kg
Tulangan Bawah Arah Y
Tulangan Full Lapangan 52.51 Kg Kg
Tulangan Ful Tumpuan 87.52 Kg Kg
Tulangan Extra Lapangan 47.17 Kg Kg
Tulangan Atas Arah Y
Tulangan Full Lapangan 52.51 Kg Kg
Tulangan Full Lapangan 87.52 Kg Kg
Tulangan Extra Tumpuan 30.92 Kg Kg
Tul kaki ayam 3.65 Kg Kg
Tul OverLap arah X 16.61 Kg Kg
Tul OverLap arah Y 11.56 Kg Kg

798.77 Kg 3.864 206.72 Kg

TOTAL
URUGAN PASIR 609.44 m3 TOTAL RASIO RATA- VOLUME TOTAL VOLUME
TOTAL BERAT SAT VOLUME SAT SAT SAT SAT
RATA BETON LT BESI LT BASEMENT
LANTAI KERJA 435.31 m3 BETON
BASEMENT
(a) (b) (c = a / b) (d) (e = c x d)

2,231.31 Kg 10.92 m3 204.33 Kg/m3 1,741.26 m3 355,795.13 Kg

Luas Tebal Plat


Full plat 8,734.79 m2 Di Buat Oleh :

minus plat void lift as. F-G/1 (11.99) m2


minus plat void lift as. E-F/10 (16.52) m2 Muhammad Alimin

Luas Bersih Plat Basement 8,706.28 m2 0.2 m

Volume Beton 1,741.26 m2


KONVERSI TULANGAN PLAT
AREA YANG DI KONVERSI = 4,883.54 As 9-AS 1
DETAIL KONVERSI = D13=> D10
VOUME BETON = 976.71

TULANGAN PLAT SEBELUM KONVERSI


DIMENSI (m2) KETERANGAN TULANGAN TOTAL
JUMLAH VOLUME TOTAL VOLUME
TYPE PEKERJAAN BETON h X Y VOLUME RASIO VOLUME SAT
TOTAL BETON BETON LT 1 BESI LT 1
(m) (m) (m) Dia L Jrk Jml kg/m' Total
(a) (b) (axb)

PLAT S2 ( 3.9m x 8m ) 0.200 3.900 8.00 Kg


Tulangan Bawah Arah X
Tulangan Full Lapangan D 13 4.20 0.20 31 1.04 136.75 1 136.75 Kg Kg
Tulangan Full Tumpuan D 13 4.20 0.10 20 1.04 87.52 1 87.52 Kg Kg
Tulangan Extra Tumpuan D 13 1.40 0.20 62 1.04 90.31 1 90.31 Kg Kg
Tulangan Atas Arah X
Tulangan Full Lapangan D 13 4.20 0.20 31 1.04 136.75 1 136.75 Kg Kg
Tulangan Full Tumpuan D 13 4.50 0.10 20 1.04 93.77 1 93.77 Kg Kg
Tulangan Extra Lapangan D 13 2.50 0.20 62 1.04 161.23 1 161.23 Kg Kg
Tulangan Bawah Arah Y
Tulangan Full Lapangan D 13 8.40 0.20 11 1.04 96.27 1 96.27 Kg Kg
Tulangan Ful Tumpuan D 13 8.40 0.10 20 1.04 175.04 1 175.04 Kg Kg
Tulangan Extra Lapangan D 13 6.60 0.20 11 1.04 75.60 1 75.60 Kg Kg
Tulangan Atas Arah Y
Tulangan Full Lapangan D 13 8.40 0.20 11 1.04 96.27 1 96.27 Kg Kg
Tulangan Full Lapangan D 13 8.40 0.10 20 1.04 175.04 1 175.04 Kg Kg
Tulangan Extra Tumpuan D 13 2.47 0.20 22 1.04 56.68 1 56.68 Kg Kg
Tul kaki ayam D 10 0.50 0.20 10 0.62 3.08 1 3.08 Kg Kg
Tul OverLap arah X D 13 0.17 0.20 103 1.04 18.51 1 18.51 Kg Kg
Tul OverLap arah Y D 13 0.35 0.20 62 1.04 22.39 1 22.39 Kg Kg

TOTAL 1,425.20 Kg 7.056 201.98 Kg


PLAT S2 ( 3.9m x 8m ) 0.200 2.000 8.00 Kg
Tulangan Bawah Arah X
Tulangan Full Lapangan D 13 2.30 0.20 36 1.04 86.27 1 86.27 Kg Kg
Tulangan Full Tumpuan D 13 2.30 0.10 10 1.04 23.96 1 23.96 Kg Kg
Tulangan Extra Tumpuan D 13 0.92 0.20 72 1.04 69.24 1 69.24 Kg Kg
Tulangan Atas Arah X
Tulangan Full Lapangan D 13 2.30 0.20 36 1.04 86.27 1 86.27 Kg Kg
Tulangan Full Tumpuan D 13 2.60 0.10 10 1.04 27.09 1 27.09 Kg Kg
Tulangan Extra Lapangan D 13 1.55 0.20 72 1.04 115.97 1 115.97 Kg Kg
Tulangan Bawah Arah Y
Tulangan Full Lapangan D 13 8.40 0.20 6 1.04 52.51 1 52.51 Kg Kg
Tulangan Ful Tumpuan D 13 8.40 0.10 10 1.04 87.52 1 87.52 Kg Kg
Tulangan Extra Lapangan D 13 7.55 0.20 6 1.04 47.17 1 47.17 Kg Kg
Tulangan Atas Arah Y
Tulangan Full Lapangan D 13 8.40 0.20 6 1.04 52.51 1 52.51 Kg Kg
Tulangan Full Lapangan D 13 8.40 0.10 10 1.04 87.52 1 87.52 Kg Kg
Tulangan Extra Tumpuan D 13 2.47 0.20 12 1.04 30.92 1 30.92 Kg Kg
Tul kaki ayam D 10 0.50 0.20 10 0.62 3.08 1 3.08 Kg Kg
Tul OverLap arah X D 13 0.17 0.20 92 1.04 16.61 1 16.61 Kg Kg
Tul OverLap arah Y D 13 0.35 0.20 32 1.04 11.56 1 11.56 Kg Kg

TOTAL 798.21 Kg 3.864 206.58 Kg

TOTAL
TOTAL RASIO RATA- VOLUME TOTAL VOLUME
TOTAL BERAT SAT VOLUME SAT SAT SAT SAT
BETON RATA BETON LT BESI LT BASEMENT
BASEMENT
(a) (b) (c = a / b) (d) (e = c x d)

2,223.41 Kg 10.92 m3 203.61 Kg/m3 976.71 m3 198,866.76 Kg


TULANGAN PLAT SETELAH KONVERSI
DIMENSI (m2) KETERANGAN TULANGAN TOTAL
JUMLAH VOLUME TOTAL VOLUME
TYPE PEKERJAAN BETON h X Y VOLUME BETON RASIO VOLUME BESI LT 1 SAT
TOTAL BETON LT 1
(m) (m) (m) Dia L Jrk Jml kg/m' Total
(a) (b) (axb)

PLAT S2 ( 3.9m x 8m ) 0.200 3.900 8.00 Kg


Tulangan Bawah Arah X
Tulangan Full Lapangan D 10 4.20 0.10 62 0.62 159.24 1 159.24 Kg Kg
Tulangan Full Tumpuan D 10 4.20 0.06 35 0.62 90.63 1 90.63 Kg Kg
Tulangan Extra Tumpuan D 10 1.34 0.10 122 0.62 100.41 1 100.41 Kg Kg
Tulangan Atas Arah X
Tulangan Full Lapangan D 10 4.20 0.10 62 0.62 159.24 1 159.24 Kg Kg
Tulangan Full Tumpuan D 10 4.50 0.06 35 0.62 97.10 1 97.10 Kg Kg
Tulangan Extra Lapangan D 10 2.37 0.10 122 0.62 178.25 1 178.25 Kg Kg
Tulangan Bawah Arah Y
Tulangan Full Lapangan D 10 8.40 0.10 21 0.62 108.75 1 108.75 Kg Kg
Tulangan Ful Tumpuan D 10 8.40 0.06 35 0.62 181.25 1 181.25 Kg Kg
Tulangan Extra Lapangan D 10 6.47 0.10 21 0.62 83.76 1 83.76 Kg Kg
Tulangan Atas Arah Y
Tulangan Full Lapangan D 10 8.40 0.10 21 0.62 108.75 1 108.75 Kg Kg
Tulangan Full Lapangan D 10 8.40 0.06 35 0.62 181.25 1 181.25 Kg Kg
Tulangan Extra Tumpuan D 10 2.41 0.10 42 0.62 62.40 1 62.40 Kg Kg
Tul kaki ayam D 10 0.50 0.10 10 0.62 3.08 1 3.08 Kg Kg
Tul OverLap arah X D 10 0.13 0.10 193 0.62 15.86 1 15.86 Kg Kg
Tul OverLap arah Y D 10 0.27 0.10 112 0.62 18.41 1 18.41 Kg Kg

TOTAL 1,548.40 Kg 7.056 219.44 Kg


PLAT S2 ( 3.9m x 8m ) 0.200 2.000 8.00 Kg
Tulangan Bawah Arah X
Tulangan Full Lapangan D 10 2.30 0.10 71 0.62 100.67 1 100.67 Kg Kg
Tulangan Full Tumpuan D 10 2.30 0.06 18 0.62 25.52 1 25.52 Kg Kg
Tulangan Extra Tumpuan D 10 0.86 0.10 142 0.62 75.29 1 75.29 Kg Kg
Tulangan Atas Arah X
Tulangan Full Lapangan D 10 2.30 0.10 71 0.62 100.67 1 100.67 Kg Kg
Tulangan Full Tumpuan D 10 2.60 0.06 18 0.62 28.85 1 28.85 Kg Kg
Tulangan Extra Lapangan D 10 1.42 0.10 142 0.62 124.31 1 124.31 Kg Kg
Tulangan Bawah Arah Y
Tulangan Full Lapangan D 10 8.40 0.10 11 0.62 56.96 1 56.96 Kg Kg
Tulangan Ful Tumpuan D 10 8.40 0.06 18 0.62 93.21 1 93.21 Kg Kg
Tulangan Extra Lapangan D 10 7.42 0.10 11 0.62 50.32 1 50.32 Kg Kg
Tulangan Atas Arah Y
Tulangan Full Lapangan D 10 8.40 0.10 11 0.62 56.96 1 56.96 Kg Kg
Tulangan Full Lapangan D 10 8.40 0.06 18 0.62 93.21 1 93.21 Kg Kg
Tulangan Extra Tumpuan D 10 2.41 0.10 22 0.62 32.69 1 32.69 Kg Kg
Tul kaki ayam D 10 0.50 0.10 10 0.62 3.08 1 3.08 Kg Kg
Tul OverLap arah X D 10 0.13 0.10 178 0.62 14.63 1 14.63 Kg Kg
Tul OverLap arah Y D 10 0.27 0.10 58 0.62 9.54 1 9.54 Kg Kg

TOTAL 865.94 Kg 3.864 224.10 Kg

TOTAL TOTAL
RASIO RATA- VOLUME TOTAL VOLUME
TOTAL BERAT SAT VOLUME SAT RATA SAT BETON LT SAT BESI LT BASEMENT SAT
BETON
BASEMENT
(a) (b) (c = a / b) (d) (e = c x d)

2,414.34 Kg 10.92 m3 221.09 Kg/m3 976.71 m3 215,943.64 Kg

17,076.88
SELISIH AKIBAT KONVERSI
BERAT SEBELUM KONVERSI 198,866.76 Kg

BERAT SETELAH KONVERSI 215,943.64 Kg

SELISIH (17,076.88) Kg
PERHITUNGAN VOLUME PLAT KONVENSIONAL LANTAI 1 GEDUNG PARKIR UTARA

DIMENSI (m2) JUML


VOLUME TOTAL VOLUME TOTAL VOLUME
TYPE PEKERJAAN BETON h X Y AH VOLUME RASIO SAT
BETON BETON LT 1 BESI LT 1
(m) (m) (m) Dia L Jrk Jml kg/m' Total TOTAL
(a) (b) (axb)

PLAT S1 ( 3.9 m x 8 m ) 0.135 3.900 8.00 Kg


Tulangan Bawah Arah X
Tulangan Full Lapangan D 10 4.20 0.27 23 0.62 60.61 1 60.61 Kg Kg
Tulangan Full Tumpuan D 10 4.20 0.20 11 0.62 28.48 1 28.48 Kg Kg
Tulangan Extra Lapangan D 10 2.37 0.27 46 0.62 67.21 1 67.21 Kg Kg
Tulangan Atas Arah X
Tulangan Full Lapangan D 10 4.20 0.27 23 0.62 60.61 1 60.61 Kg Kg
Tulangan Full Tumpuan D 10 4.20 0.20 11 0.62 28.48 1 28.48 Kg Kg
Tulangan Extra Tumpuan D 10 1.34 0.27 46 0.62 37.86 1 37.86 Kg Kg
Tulangan Bawah Arah Y
Tulangan Full Lapangan D 10 8.40 0.27 8 0.62 41.43 1 41.43 Kg Kg
Tulangan Ful Tumpuan D 10 8.40 0.20 11 0.62 56.96 1 56.96 Kg Kg
Tulangan Extra Tumpuan D 10 2.41 0.27 16 0.62 23.77 1 23.77 Kg Kg
Tulangan Atas Arah Y
Tulangan Full Lapangan D 10 8.40 0.27 8 41.43 1 41.43 Kg Kg
0.62
Tulangan Full Lapangan D 10 8.40 0.20 11 0.62 56.96 1 56.96 Kg Kg
Tulangan Extra Lapangan D 10 6.47 0.27 16 0.62 63.82 1 63.82 Kg Kg
Tul kaki ayam D 10 0.50 0.20 20 0.62 6.17 1 6.17 Kg Kg
Tul OverLap arah X D 10 0.13 0.20 69 0.62 5.66 1 5.66 Kg Kg
Tul OverLap arah Y D 10 0.27 0.20 38 0.62 6.25 1 6.25 Kg Kg

TOTAL 585.70 Kg 4.7628 122.97 Kg


PLAT S1( 2 m x 8 m ) 0.135 3.000 8.00 Kg
Tulangan Bawah Arah X
Tulangan Full Lapangan D 10 3.30 0.27 25 0.62 51.01 1 51.01 Kg Kg
Tulangan Full Tumpuan D 10 3.30 0.20 9 0.62 18.31 1 18.31 Kg Kg
Tulangan Extra Lapangan D 10 1.92 0.27 50 0.62 59.18 1 59.18 Kg Kg
Tulangan Atas Arah X
Tulangan Full Lapangan D 10 3.30 0.27 25 0.62 51.01 1 51.01 Kg Kg
Tulangan Full Tumpuan D 10 3.30 0.20 9 0.62 18.31 1 18.31 Kg Kg
Tulangan Extra Tumpuan D 10 1.11 0.27 50 0.62 34.22 1 34.22 Kg Kg
Tulangan Bawah Arah Y
Tulangan Full Lapangan D 10 8.40 0.27 7 0.62 36.25 1 36.25 Kg Kg
Tulangan Ful Tumpuan D 10 8.40 0.20 9 0.62 46.61 1 46.61 Kg Kg
Tulangan Extra Tumpuan D 10 2.41 0.27 14 0.62 20.80 1 20.80 Kg Kg
Tulangan Atas Arah Y
Tulangan Full Lapangan D 10 8.40 0.27 7 36.25 1 36.25 Kg Kg
0.62
Tulangan Full Lapangan D 10 8.40 0.20 9 0.62 46.61 1 46.61 Kg Kg
Tulangan Extra Lapangan D 10 6.92 0.27 14 0.62 59.73 1 59.73 Kg Kg
Tul kaki ayam D 10 0.50 0.20 14 0.62 4.32 1 4.32 Kg Kg
Tul OverLap arah X D 10 0.13 0.20 68 0.62 5.60 1 5.60 Kg Kg
Tul OverLap arah Y D 10 0.27 0.20 32 0.62 5.26 1 5.26 Kg Kg

TOTAL 493.46 Kg 3.7422 131.86 Kg


TOTAL
TOTAL BERAT SAT VOLUME SAT RASIO RATA- SAT TOTAL VOLUME SAT TOTAL VOLUME SAT
RATA BETON LT 1 BESI LT 1
BETON

(a) (b) (c = a / b) (d) (e = c x d)

1,079.16 Kg 8.51 m3 126.89 Kg/m3 645.67 m3 81,926.09 Kg

Plat Konvensional 8,734.79 m2


Minus void lift (11.99) m2
Minus void lift (16.52) m2
Minus void tangga (12.30) m2
Minus void tangga (12.30) m2
Minus void tangga (12.30) m2
Minus void tangga (12.90) m2
Minus Void ME (82.12) m2
Minus void ramp (86.76) m2
Minus void ramp (86.76) m2
Minus void ramp (184.36) m2
Minus void shaft (12 ttk) (11.64) m2
Minus Luas Plat Half Slab -3422.1148 m2

LUAS BERSIH PLAT LT 1 (BEKISTING) 4,782.72 m2 Di Buat Oleh :


TEBAL PLAT S1 (LANTAI 1) 0.135 m

VOLUME BETON LT 1 645.67 m3 Muhammad Alimin


PERHITUNGAN VOLUME PLAT KONVENSIONAL LANTAI 2 GEDUNG PARKIR UTARA

TYPE LUAS SAT


Konvensional 8,030.71 m2

Minus void lift (11.99) m2

Minus void lift (16.52) m2

Minus void tangga (12.30) m2

Minus void tangga (12.30) m2

Minus void tangga (12.30) m2

Minus void tangga (12.90) m2

Minus void ramp (86.76) m2

Minus void ramp (86.76) m2

Minus void ramp (184.36) m2

Minus void shaft (12 ttk) (11.64) m2

Minus Luas Plat Half Slab -2943.3508 m2

LUAS BERSIH PLAT LT 2 (BEKISTING) 4,639.53 m2


TEBAL PLAT S1 (LANTAI 2) 0.135 m

VOLUME BETON LT 2 626.34 m3

RASIO RATA-
SAT TOTAL VOLUME BETON LT 2 VOLUME BESI SAT
RATA

(m3)

126.89 Kg/m3 626.34 79,473.32 Kg

Di Buat Oleh :
PERHITUNGAN VOLUME PLAT KONVENSIONAL LANTAI 3 GEDUNG PARKIR UTARA

TYPE LUAS SAT

Konvensional 7,018.75 m2

Minus void lift (11.99) m2

Minus void lift (16.52) m2

Minus void tangga (12.30) m2

Minus void tangga (12.30) m2

Minus void tangga (12.30) m2

Minus void tangga (12.90) m2

Minus void ramp (86.76) m2

Minus void ramp (86.76) m2

Minus void ramp (184.36) m2

Minus void shaft (12 ttk) (11.64) m2

Minus Luas Plat Half Slab -2501.1389 m2

LUAS BERSIH PLAT LT 3 (BEKISTING) 4,069.79 m2

TEBAL PLAT S1 (LANTAI 3) 0.135 m

VOLUME BETON LT 3 549.42 m3

TOTAL VOLUME BETON


RASIO RATA-RATA SAT VOLUME BESI SAT
LT 3

(m3)

126.89 Kg/m3 549.42 69,713.80 Kg


PERHITUNGAN VOLUME PLAT KONVENSIONAL LANTAI 4 GEDUNG PARKIR UTARA

TYPE LUAS SAT


Full plat 6,062.41 m2

Minus Void Lift (11.99) m2

Minus Void Lift (16.52) m2

Minus Void Tangga (16.17) m2

Minus void shaft (1 ttk) (0.54) m2

LUAS BERSIH PLAT LT Atap (Bekisting) 6,017.19 m2


TEBAL PLAT S1 (LANTAI Atap) 0.135 m

VOLUME BETON LT Atap 812.32 m3

TOTAL VOLUME BETON LT


RASIO RATA-RATA SAT VOLUME BESI SAT
Atap

(m3)

126.89 Kg/m3 812.32 103,071.99 Kg


PERHITUNGAN VOLUME PLAT KONVENSIONAL LANTAI 4 GEDUNG PARKIR UTARA

RASIO RATA- TOTAL VOLUME


SAT SAT TOTAL VOLUME BESI LT SAT
RATA BETON LMR

(c = a / b) (d) (e = c x d)

126.89 Kg/m3 11.91 m3 1,511.17 Kg

43.54
16.88 Di Buat Oleh :
27.80

BEKISTING 88.22 97.32 m2 Muhammad Alimin


BEKISTING 67.44
9.10
LUAS LANTAI GEDUNG PARKIR
KET LUAS SATUAN
BASMENT 8,734.79 m2
Lt 1 8,734.79 m2
LT 2 8,030.71 m2
LT 3 7,018.75 m2
LT 4 6,062.41 m2

LUAS BERSIH GEDUNG PARKIR


KET LUAS SATUAN
BASMENT 8,706.28 m2
Lt 1 4,782.72 m2
LT 2 4,639.53 m2
LT 3 4,069.79 m2
LT 4 6,017.19 m2