Anda di halaman 1dari 3

BOQ BOGOR

PEKERJAAN : PENAMBAHAN RUANGAN DECK LANTAI


LOKASI : BOGOR
TAHUN : 2017

PANJANG HARGA SAT


NO. JENIS PEKERJAAN KEBUTUTUHAN KEBUTUHAN BERAT VOLUME(KG)
SAT. (m) ( Rp )
1 2 3 4 5 6 7 8
I IWF 250 . 125 . 6 . 9
1 - Kolom A kg 11.60 1.00 Btg 355.20 Kg/Btg 355.20 15,000.00
2 - Kolom B kg 14.55 1.22 Btg 355.20 Kg/Btg 433.34 15,000.00
3 - Balok kg 20.28 1.69 Btg 355.20 Kg/Btg 600.29 15,000.00
4 - Haunch (Dagu) kg 4.68 0.40 Btg 355.20 Kg/Btg 142.08 15,000.00
Jumlah I kg 51.107 4.30 Btg 1,530.91
II IWF 200 . 100 . 5.5 . 8
1 - Balok kg 26.87 2.24 Btg 258.00 Kg/Btg 577.92 15,000.00
2 - Haunch (Dagu) kg 1.5 0.13 Btg 258.00 Kg/Btg 33.54 15,000.00
Jumlah II kg 28.37 3.00 Btg 611.46
III IWF 150 . 75 . 5.0 . 7 kg 3 0.25 Btg 168.00 Kg/Btg 42.00 15,000.00
Jumlah III kg 31.37 3.00 Btg 42.00
IV CNP 100 . 50 . 2.3 kg 72 12.00 Btg 24.4 Kg/Btg 292.80 15,000.00
CNP 150 . 50 . 3.2 kg 5.6 0.93 Btg 40.56 Kg/Btg 37.86 15,000.00
1 Behel Ǿ 12 mm kg 36 3.00 Btg 10.7 Kg/Btg 32.10 15,000.00
2 Pelat (30 X 30) t 10 mm kg 30 x 30 x 4 0.20 Lbr 233.68 Kg/Lbr 46.74 15,000.00
3 Pelat (1 Lembar) t 12 mm kg 1.00 Lbr 271.30 Kg/Lbr 271.30 15,000.00
Jumlah IV kg 680.79
TOTAL VOLUME (I+II+III+IV) 2,865.16
IV BAUD Ǿ 16 mm kg 150.00 Bh 0.45 Kg/Bh 67.50 5,000.00
V BAUD Ǿ 14 mm kg 80.00 Bh 0.35 Kg/Bh 28.00 5,000.00
TOTAL HARGA

Bandung, 11 Januari 2017


Angga Permana
OQ BOGOR

JML HARGA
( Rp )
9
-
5,328,000.00
6,500,160.00
9,004,320.00
2,131,200.00
22,963,680.00

8,668,800.00
503,100.00
9,171,900.00
630,000.00
630,000.00
4,392,000.00
567,840.00
481,500.00
701,036.40
4,069,440.00
10,211,816.40

750,000.00
400,000.00
44,127,396.40