TIMELINE PEKERJAAN TATA KELOLA AIR PT.

MAR - KR
PENANGANAN BLOK PRODUKSI RENDAH 2023

2023
NO URAIAN PEKERJAAN TATA KELOLA AIR VOLUME SATUAN HM HKE JUNI JULI AGUSTUS SEPTEMBER OKTOBER NOVEMBER
I II III IV I II III IV I II III IV I II III IV I II III IV I II III IV

A AAPE DIVISI VI

I Excavator Long Arm 01 (Kuala Ambawang)


1 Perbaikan Pintu Air 1 Unit 16 2
2 Pencucian Parit Collection Drain 11.738 Meter 391 49
3 Pencucian Parit Akses 1.040 Meter 35 5
4 Pencucian Parit Main Drain 1.928 Meter 64 9
5 Pencucian Parit Field Drain/Bumbun Pkk 1.595 Meter 73 10
6 Pembuatan Tanggul 612 Meter 24 3
Sub Total 603 78
II Excavator Standard 03 (Medan Sri)

1 Pembukaan Akses Jalan Tanggul Sungai Ambawang 2.000 Meter 44 6


2 Pembuatan Tanggul 8.762 Meter 350 44
3 Bloking Aliran 8 Unit 27 4
4 Pencucian Parit Field Drain/Bumbun Pkk 2.641 Meter 120 16
5 Pencucian Parit Collection Drain 7.335 Meter 183 23
6 Pintu Air Gorong2 Kayu Dia 100 cm 1 Unit 16 2
7 Pintu Air Pipa PVC 12" 1 Unit 5 1
8 Pemasangan Gorong2 3 Unit 18 3
Sub Total 764 99
Grand Total A 1367 177

B AAPE DIVISI I

III Excavator Standard 02


Zona D
1 Mobilisasi Alat (Ponton)
2 Pembuatan Tanggul 1.640 Meter 66 9
3 Perbaikan Pintu Air 1 Unit 16 2

Zona B
1 Mobilisasi Alat (Ponton)
2 Pembuatan Tanggul 3.085 Meter 123 16
3 Pintu Air Gorong2 Kayu Dia 50 Cm 11 Unit 55 7
4 Bloking Aliran 11 Unit 37 5

Zona C
1 Mobilisasi Alat (Ponton)
2 Pembuatan Tanggul 2.425 Meter 97 13
3 Pintu Air Gorong2 Kayu Dia 50 Cm 8 Unit 129 16
4 Bloking Aliran 8 Unit 27 4
Grand Total B 549 72

Grand Total A+B 1917 249

No Alat Berat Warna Satuan Volume HKE


1 Excavator Long Arm 01 HM 603 78
2 Excavator Standard 03 HM 764 99
3 Excavator Standard 02 HM 549 72
Grand Total Alat Berat 1917 249