Timeline - TKA - 10062023
Timeline - TKA - 10062023
MAR - KR
PENANGANAN BLOK PRODUKSI RENDAH 2023
2023
NO URAIAN PEKERJAAN TATA KELOLA AIR VOLUME SATUAN HM HKE JUNI JULI AGUSTUS SEPTEMBER OKTOBER NOVEMBER
I II III IV I II III IV I II III IV I II III IV I II III IV I II III IV
A AAPE DIVISI VI
B AAPE DIVISI I
Zona B
1 Mobilisasi Alat (Ponton)
2 Pembuatan Tanggul 3.085 Meter 123 16
3 Pintu Air Gorong2 Kayu Dia 50 Cm 11 Unit 55 7
4 Bloking Aliran 11 Unit 37 5
Zona C
1 Mobilisasi Alat (Ponton)
2 Pembuatan Tanggul 2.425 Meter 97 13
3 Pintu Air Gorong2 Kayu Dia 50 Cm 8 Unit 129 16
4 Bloking Aliran 8 Unit 27 4
Grand Total B 549 72