RAB BOGOR

NO URAIAN PEKERJAAN RKS & SPESIFIKASI TEKNIS SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

1 2 3 4 5 6 (5X6)

II. PEKERJAAN STRUKTUR (Termasuk aksesoris lengkap terpasang)


II.1 PEKERJAAN TANAH
1 Pek. Pemasangan bouwplank m1 490.59 149,316.00 73,252,936.44
2 Pek. Galian tanah untuk pondasi dan Tie beam m3 395.38 60,492.00 23,917,326.96
3 Pek. Urugan kembali bekas galian m3 167.46 43,371.00 7,262,907.66
4 Pek. Buangan Tanah Bekas Galian m3 227.92 57,142.86 13,024,000.00
5 Pek. Urugan pasir di bawah pondasi & Tie beam Pasir urug dipadatkan T.10 cm m3 41.13 449,650.00 18,494,104.50
6 Pek. Lantai kerja di bawah pondasi & Tie beam Lantai Kerja Beton Mutu f'c = 7,4 Mpa Slump (3-6)cm, w/c = 0,87 T.5 cm m3 20.56 378,764.25 7,787,392.98
JUMLAH PEKERJAAN TANAH 143,738,668.54

II.2 PEKERJAAN STRUKTUR S/D ELV. -0.050


1 Pek. Pas. Tiang Pancang square 400 T=30 meter
a. Tiang Pancang square 400
- Tiang pancang square 400 (P2) m1 480.00 439,840.00 211,123,200.00
- Tiang pancang square 400 (P3) m1 180.00 439,840.00 79,171,200.00
- Tiang pancang square 400 (P4) m1 750.00 439,840.00 329,880,000.00
- Tiang pancang square 400 (P5) m1 1,850.00 439,840.00 813,704,000.00

b. Pemotongan tiang pancang square 400


- Tiang pancang square 400 (P2) unit 16.00 90,000.00 1,440,000.00
- Tiang pancang square 400 (P3) unit 6.00 90,000.00 540,000.00
- Tiang pancang square 400 (P4) unit 44.00 90,000.00 3,960,000.00
- Tiang pancang square 400 (P5) unit 95.00 90,000.00 8,550,000.00

c. Penyambungan & pengelasan tiang pancang square 400


- Tiang pancang square 400 (P2) joint 48.00 108,000.00 5,184,000.00
- Tiang pancang square 400 (P3) joint 18.00 108,000.00 1,944,000.00
- Tiang pancang square 400 (P4) joint 132.00 108,000.00 14,256,000.00
- Tiang pancang square 400 (P5) joint 285.00 108,000.00 30,780,000.00

d. Pemancangan tiang pancang square 400


- Tiang pancang square 400 (P2) m1 480.00 250,500.00 120,240,000.00
- Tiang pancang square 400 (P3) m1 180.00 250,500.00 45,090,000.00
- Tiang pancang square 400 (P4) m1 1,320.00 250,500.00 330,660,000.00
- Tiang pancang square 400 (P5) m1 2,850.00 250,500.00 713,925,000.00

2 Pek. Pas. Pondasi Pile Cap tipe PC2 800x2200x1000


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 14.08 1,327,775.82 18,695,083.55
- Besi D19-200 Mutu baja BJTD 40 (ulir) SNI kg 981.76 22,100.00 21,696,896.00
- Besi D22-160 Mutu baja BJTD 40 (ulir) SNI kg 1,619.24 22,100.00 35,785,204.00
- Besi 2D16 Mutu baja BJTD 40 (ulir) SNI kg 73.22 22,100.00 1,618,162.00
- Bekisting Bekisting batako m2 48.00 237,572.13 11,403,462.19

1/21
NO URAIAN PEKERJAAN RKS & SPESIFIKASI TEKNIS SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

3 Pek. Pas. Pondasi Pile Cap tipe PC3


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 7.36 1,327,775.82 9,772,430.04
- Besi D19-200 Mutu baja BJTD 40 (ulir) SNI kg 345.48 22,100.00 7,635,108.00
- Besi D22-160 Mutu baja BJTD 40 (ulir) SNI kg 571.79 22,100.00 12,636,559.00
- Besi 2D16 Mutu baja BJTD 40 (ulir) SNI kg 21.69 22,100.00 479,349.00
- Bekisting Bekisting batako m2 15.22 237,572.13 3,615,847.80

4 Pek. Pas. Pondasi Pile Cap tipe PC4 2200x2200x1000


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 53.24 1,327,775.82 70,690,784.66
- Besi D19-200 Mutu baja BJTD 40 (ulir) SNI kg 2,503.45 22,100.00 55,326,245.00
- Besi D22-160 Mutu baja BJTD 40 (ulir) SNI kg 4,194.91 22,100.00 92,707,511.00
- Besi 2D16 Mutu baja BJTD 40 (ulir) SNI kg 149.28 22,100.00 3,299,088.00
- Bekisting Bekisting batako m2 96.80 237,572.13 22,996,982.09

5 Pek. Pas. Pondasi Pile Cap tipe PC5 2400x2400x1000


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 109.44 1,327,775.82 145,311,785.74
- Besi D19-200 Mutu baja BJTD 40 (ulir) SNI kg 1,904.41 22,100.00 42,087,461.00
- Besi D22-160 Mutu baja BJTD 40 (ulir) SNI kg 2,091.65 22,100.00 46,225,465.00
- Besi 2D16 Mutu baja BJTD 40 (ulir) SNI kg 281.83 22,100.00 6,228,443.00
- Bekisting Bekisting batako m2 182.40 237,572.13 43,333,156.33

6 Pek. Pas. Kolom K1 700x700


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 15.44 1,327,775.82 20,500,858.66
- Besi tulangan 32 D25 Mutu baja BJTD 40 (ulir) SNI kg 1,097.94 22,100.00 24,264,474.00
- Besi sengkang D10 - 100&150 Mutu baja BJTD 40 (ulir) SNI kg 557.89 22,100.00 12,329,369.00
- Besi ties 6D10 - 100&150 Mutu baja BJTD 40 (ulir) SNI kg 928.46 22,100.00 20,518,966.00
- Bekisting Bekisting batako m2 88.20 237,572.13 20,953,861.78

7 Pek. Pas. Kolom K3 400x400


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.84 1,327,775.82 1,115,331.69
- Besi tulangan 12 D19 Mutu baja BJTD 40 (ulir) SNI kg 364.62 22,100.00 8,058,102.00
- Besi sengkang D10 - 100&150 Mutu baja BJTD 40 (ulir) SNI kg 52.26 22,100.00 1,154,946.00
- Bekisting Bekisting batako m2 8.40 237,572.13 1,995,605.88

8 Pek. Pas. Tie beam TB1 400x800


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 96.27 1,327,775.82 127,824,978.19
- Besi tulangan 15 D25 Mutu baja BJTD 40 (ulir) SNI kg 1,895.67 22,100.00 41,894,307.00
- Besi tulangan 10 D25 Mutu baja BJTD 40 (ulir) SNI kg 1,906.40 22,100.00 42,131,440.00
- Besi tulangan 2 D13 Mutu baja BJTD 40 (ulir) SNI kg 759.97 22,100.00 16,795,337.00
- Besi Tulangan D10 - 100&150 Mutu baja BJTD 40 (ulir) SNI kg 566.95 22,100.00 12,529,595.00
- Bekisting Bekisting batako m2 583.47 237,572.13 138,616,210.11

9 Pek. Pas. Tie beam TB3 350x700


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 42.19 1,327,775.82 56,018,861.85
- Besi tulangan 13 D22 Mutu baja BJTD 40 (ulir) SNI kg 2,455.51 22,100.00 54,266,771.00
- Besi tulangan 12 D22 Mutu baja BJTD 40 (ulir) SNI kg 2,035.86 22,100.00 44,992,506.00

2/21
NO URAIAN PEKERJAAN RKS & SPESIFIKASI TEKNIS SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

- Besi tulangan 2 D10 Mutu baja BJTD 40 (ulir) SNI kg 265.64 22,100.00 5,870,644.00
- Besi Tulangan D10 - 100&150 Mutu baja BJTD 40 (ulir) SNI kg 3,320.94 22,100.00 73,392,774.00
- Bekisting Bekisting batako m2 301.38 237,572.13 71,599,488.24

10 Pek. Pas. Tie beam TB3A 350x700


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 10.46 1,327,775.82 13,888,535.08
- Besi tulangan 13 D22 Mutu baja BJTD 40 (ulir) SNI kg 1,571.85 22,100.00 34,737,885.00
- Besi tulangan 2 D10 Mutu baja BJTD 40 (ulir) SNI kg 65.88 22,100.00 1,455,948.00
- Besi Tulangan D10 - 100 Mutu baja BJTD 40 (ulir) SNI kg 982.33 22,100.00 21,709,493.00
- Bekisting Bekisting batako m2 74.75 237,572.13 17,758,516.64

11 Pek. Pas. Tie beam TB4 250x500


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 2.64 1,327,775.82 3,505,328.16
- Besi tulangan 5 D19 Mutu baja BJTD 40 (ulir) SNI kg 239.07 22,100.00 5,283,447.00
- Besi Tulangan D10 - 100&150 Mutu baja BJTD 40 (ulir) SNI kg 234.68 22,100.00 5,186,428.00
- Bekisting Bekisting batako m2 29.28 237,572.13 6,956,111.94

12 Pek. Pas. Tie beam TB4A 250x500


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.96 1,327,775.82 1,274,664.79
- Besi tulangan 5 D19 Mutu baja BJTD 40 (ulir) SNI kg 92.82 22,100.00 2,051,322.00
- Besi Tulangan D10 - 100 Mutu baja BJTD 40 (ulir) SNI kg 99.53 22,100.00 2,199,613.00
- Bekisting Bekisting batako m2 10.68 237,572.13 2,537,270.34

13 Pek. Pas. Tie beam TB5A 200x400


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.10 1,327,775.82 132,777.58
- Besi tulangan 5 D16 Mutu baja BJTD 40 (ulir) SNI kg 23.67 22,100.00 523,107.00
- Besi Tulangan D10 - 100 Mutu baja BJTD 40 (ulir) SNI kg 15.29 22,100.00 337,909.00
- Bekisting Bekisting batako m2 1.60 237,572.13 380,115.41

14 Pek. Pas. Tie beam TB6 200x350


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.08 1,327,775.82 106,222.07
- Besi tulangan 5 D19 Mutu baja BJTD 40 (ulir) SNI kg 33.39 22,100.00 737,919.00
- Besi Tulangan D10 - 100&150 Mutu baja BJTD 40 (ulir) SNI kg 12.66 22,100.00 279,786.00
- Bekisting Bekisting batako m2 1.40 237,572.13 332,600.98

15 Pek. Pas. Plat lantai Elv.- 0.050 T.13cm


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 114.93 1,327,775.82 152,601,274.99
- Wiremesh M7 (1 lapis) Wiremesh M8 (2 lapis) kg 3,688.35 20,091.89 74,105,936.83
- Standed Bar bh 260.00 9,591.40 2,493,764.00
- Waterproofing integral Waterproofing Crystaline WP System, Setara Fosroc, Sica kg 402.26 44,217.50 17,786,931.55

16 Pek. Struktur Core Lift


a. Pekerjaan tanah
- Galian tanah m3 25.37 60,492.00 1,534,682.04
- Buangan tanah galian m3 25.37 57,142.86 1,449,714.29
- Lapisan Sirtu dipadatkan m3 3.73 270,000.00 1,007,100.00
- Urugan pasir Pasir urug dipadatkan T.10 cm m3 1.49 449,650.00 669,978.50

3/21
NO URAIAN PEKERJAAN RKS & SPESIFIKASI TEKNIS SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

- Lantai kerja Lantai Kerja Beton Mutu f'c = 7,4 Mpa Slump (3-6)cm, w/c = 0,87 T.5 cm m3 0.75 378,764.25 284,073.19

b. Pekerjaan Pit Lift lantai beton T.25cm


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 2.83 1,327,775.82 3,757,605.57
- Waterproofing integral mix Waterproofing Crystaline WP System, Setara Fosroc, Sica kg 9.90 44,217.50 437,753.25
- Waterstop L.15cm Waterstop L.15cm m1 13.46 92,575.00 1,246,059.50
- Besi D10 -150 (2 lapis) Mutu baja BJTD 40 (ulir) SNI kg 207.78 22,100.00 4,591,938.00
- Bekisting Bekisting batako m2 3.37 237,572.13 800,618.07

c. Pekerjaan dinding beton T.20cm


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 4.04 1,327,775.82 5,364,214.31
- Waterproofing integral mix Waterproofing Crystaline WP System, Setara Fosroc, Sica kg 14.13 44,217.50 624,793.28
- Waterproofing coating Waterproofing Formdex Uniflex Cementitious Membrance, setara Sica fosroc m2 20.19 77,855.00 1,571,892.45
- Besi D10 - 150 (2 lapis) Mutu baja BJTD 40 (ulir) SNI kg 385.65 22,100.00 8,522,865.00
- Bekisting Bekisting batako m2 20.19 237,572.13 4,796,581.28
- Bekisting multipleks Bekisting multipleks m2 20.19 556,332.00 11,232,343.08
JUMLAH PEKERJAAN STRUKTUR S/D ELV. -0,050 4,575,071,969.95

II.3 PEKERJAAN STRUKTUR S/D ELV. +3.950


1 Pek. Pas. Kolom K1 700x700
- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 58.80 1,327,775.82 78,073,218.22
- Besi tulangan 32 D25 Mutu baja BJTD 40 (ulir) SNI kg 1,956.76 22,100.00 43,244,396.00
- Besi sengkang D10 - 100&150 Mutu baja BJTP 24 (polos) SNI kg 1,775.11 22,100.00 39,229,931.00
- Besi ties 6D10 - 100&150 Mutu baja BJTP 24 (polos) SNI kg 2,954.20 22,100.00 65,287,820.00
- Bekisting Bekisting multipleks m2 336.00 556,332.00 186,927,552.00

2 Pek. Pas. Kolom K3 400x400


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 3.20 1,327,775.82 4,248,882.62
- Besi tulangan 12 D19 Mutu baja BJTD 40 (ulir) SNI kg 684.50 22,100.00 15,127,450.00
- Besi sengkang D10 - 100&150 Mutu baja BJTP 24 (polos) SNI kg 166.28 22,100.00 3,674,788.00
- Bekisting Bekisting multipleks m2 32.00 556,332.00 17,802,624.00

3 Pek. Pas. Kolom K4 400x400


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 2.08 1,327,775.82 2,761,773.71
- Besi tulangan 12 D19 Mutu baja BJTD 40 (ulir) SNI kg 428.46 22,100.00 9,468,966.00
- Besi sengkang D10 - 100&150 Mutu baja BJTD 40 (ulir) SNI kg 110.22 22,100.00 2,435,862.00
- Bekisting Bekisting multipleks m2 20.80 556,332.00 11,571,705.60

4 Pek. Pas. Dinding Beton t.200mm


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 14.59 1,327,775.82 19,372,249.21
- Besi D13-150 Mutu baja BJTD 40 (ulir) SNI kg 1,630.27 22,100.00 36,028,967.00
- Bekisting multipleks Bekisting multipleks m2 145.86 556,332.00 81,146,585.52

5 Pek. Pas. Balok B1 400x800


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 50.12 1,327,775.82 66,548,124.10
- Besi tulangan 15 D25 Mutu baja BJTD 40 (ulir) SNI kg 1,700.00 22,100.00 37,570,000.00
- Besi tulangan 10 D25 Mutu baja BJTD 40 (ulir) SNI kg 1,787.55 22,100.00 39,504,855.00

4/21
NO URAIAN PEKERJAAN RKS & SPESIFIKASI TEKNIS SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

- Besi tulangan 2 D13 Mutu baja BJTP 24 (polos) SNI kg 559.76 22,100.00 12,370,696.00
- Besi Tulangan D10 - 100&150 Mutu baja BJTP 24 (polos) SNI kg 3,744.33 22,100.00 82,749,693.00
- Bekisting Bekisting multipleks m2 429.76 556,332.00 239,089,240.32

6 Pek. Pas. Balok B2 350x700


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 4.56 1,327,775.82 6,054,657.74
- Besi tulangan 13 D22 Mutu baja BJTD 40 (ulir) SNI kg 567.33 22,100.00 12,537,993.00
- Besi tulangan 12 D22 Mutu baja BJTD 40 (ulir) SNI kg 523.69 22,100.00 11,573,549.00
- Besi tulangan 2 D10 Mutu baja BJTP 24 (polos) SNI kg 28.69 22,100.00 634,049.00
- Besi Tulangan D10 - 100&150 Mutu baja BJTP 24 (polos) SNI kg 359.65 22,100.00 7,948,265.00
- Bekisting Bekisting multipleks m2 32.55 556,332.00 18,108,606.60

7 Pek. Pas. Balok B3 350x700


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 40.02 1,327,775.82 53,137,588.32
- Besi tulangan 13 D22 Mutu baja BJTD 40 (ulir) SNI kg 5,201.62 22,100.00 114,955,802.00
- Besi tulangan 12 D22 Mutu baja BJTD 40 (ulir) SNI kg 4,801.49 22,100.00 106,112,929.00
- Besi tulangan 2 D10 Mutu baja BJTP 24 (polos) SNI kg 251.96 22,100.00 5,568,316.00
- Besi Tulangan D10 - 100&150 Mutu baja BJTP 24 (polos) SNI kg 3,149.17 22,100.00 69,596,657.00
- Bekisting Bekisting multipleks m2 285.85 556,332.00 159,027,502.20

8 Pek. Pas. Balok B3A 350x700


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 4.05 1,327,775.82 5,377,492.07
- Besi tulangan 13 D22 Mutu baja BJTD 40 (ulir) SNI kg 1,304.96 22,100.00 28,839,616.00
- Besi tulangan 2 D10 Mutu baja BJTD 40 (ulir) SNI kg 25.47 22,100.00 562,887.00
- Besi Tulangan D10 - 100 Mutu baja BJTD 40 (ulir) SNI kg 209.35 22,100.00 4,626,635.00
- Bekisting Bekisting multipleks m2 28.90 556,332.00 16,077,994.80

9 Pek. Pas. Balok B4 250x500


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 3.40 1,327,775.82 4,514,437.79
- Besi tulangan 5 D19 Mutu baja BJTD 40 (ulir) SNI kg 288.21 22,100.00 6,369,441.00
- Besi tulangan 6 D19 Mutu baja BJTD 40 (ulir) SNI kg 345.85 22,100.00 7,643,285.00
- Besi Tulangan D10 - 100&150 Mutu baja BJTD 40 (ulir) SNI kg 300.43 22,100.00 6,639,503.00
- Bekisting Bekisting multipleks m2 37.79 556,332.00 21,023,786.28

10 Pek. Pas. Balok B4A 250x500


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.83 1,327,775.82 1,102,053.93
- Besi tulangan 5 D19 Mutu baja BJTD 40 (ulir) SNI kg 157.71 22,100.00 3,485,391.00
- Besi Tulangan D10 - 100 Mutu baja BJTD 40 (ulir) SNI kg 88.58 22,100.00 1,957,618.00
- Bekisting Bekisting multipleks m2 9.17 556,332.00 5,101,564.44

11 Pek. Pas. Balok B5 200x400


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 1.01 1,327,775.82 1,341,053.58
- Besi tulangan 5 D16 Mutu baja BJTD 40 (ulir) SNI kg 184.31 22,100.00 4,073,251.00
- Besi Tulangan D10 - 100&150 Mutu baja BJTD 40 (ulir) SNI kg 123.77 22,100.00 2,735,317.00
- Bekisting Bekisting multipleks m2 15.49 556,332.00 8,617,582.68

12 Pek. Pas. Balok B5A 200x400

5/21
NO URAIAN PEKERJAAN RKS & SPESIFIKASI TEKNIS SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.09 1,327,775.82 119,499.82
- Besi tulangan 5 D16 Mutu baja BJTD 40 (ulir) SNI kg 21.93 22,100.00 484,653.00
- Besi Tulangan D10 - 100 Mutu baja BJTD 40 (ulir) SNI kg 13.83 22,100.00 305,643.00
- Bekisting Bekisting multipleks m2 1.42 556,332.00 789,991.44

13 Pek. Pas. Balok B6 200x350


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.05 1,327,775.82 66,388.79
- Besi tulangan 5 D16 Mutu baja BJTD 40 (ulir) SNI kg 13.26 22,100.00 293,046.00
- Besi Tulangan D10 - 100&150 Mutu baja BJTD 40 (ulir) SNI kg 5.33 22,100.00 117,793.00
- Bekisting Bekisting multipleks m2 0.48 556,332.00 267,039.36

14 Pek. Pas. Plat lantai S1 Elv. +3.950 T.14cm


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 102.94 1,327,775.82 136,681,242.91
- Wiremesh M8 (2 lapis) Wiremesh M8 (2 lapis) kg 8,012.97 20,091.89 160,995,742.99
- Bekisting Bekisting multipleks m2 235.29 556,332.00 130,899,356.28
- Standed bar bh 735.00 9,591.40 7,049,679.00

15 Pek. Struktur kanopi depan


a. Balok baja IWF 400x200
- Base plat T.19 mm Besi baja SNI setara KS, Gunung Garuda, Lautan Steel kg 91.88 30,500.00 2,802,340.00
- Angkur 2x7 M22 Angkur 2x7 M22 bh 56.00 175,000.00 9,800,000.00
- IWF 400.200.8.13 Besi baja SNI setara KS, Gunung Garuda, Lautan Steel kg 1,584.00 33,500.00 53,064,000.00
- Vote 400.200.8.13 Besi baja SNI setara KS, Gunung Garuda, Lautan Steel kg 138.60 33,500.00 4,643,100.00
- Pengecatan besi duco Cat besi duco m2 42.38 45,425.00 1,925,111.50

b. Balok baja 200x100


- IWF 200.100.5.7 Besi baja SNI setara KS, Gunung Garuda, Lautan Steel kg 172.53 33,500.00 5,779,755.00
- Pengecatan besi duco Cat besi duco m2 6.48 45,425.00 294,354.00

16 Pek. Struktur kanopi belakang


a. Balok baja IWF 300x150
- Base plat T.19 mm Besi baja SNI setara KS, Gunung Garuda, Lautan Steel kg 23.86 30,500.00 727,730.00
- Angkur 2x5 M22 Angkur 2x7 M22 bh 20.00 175,000.00 3,500,000.00
- IWF 300.150.6,5.9 Besi baja SNI setara KS, Gunung Garuda, Lautan Steel kg 440.40 33,500.00 14,753,400.00
- Vote 300.150.6,5.9 Besi baja SNI setara KS, Gunung Garuda, Lautan Steel kg 38.54 33,500.00 1,291,090.00
- Pengecatan besi duco Cat besi duco m2 15.82 45,425.00 718,623.50

b. Balok baja 200x100


- IWF 200.100.5.7 Besi baja SNI setara KS, Gunung Garuda, Lautan Steel kg 63.90 33,500.00 2,140,650.00
- Pengecatan besi duco Cat besi duco m2 2.40 45,425.00 109,020.00

17 Pek. Pas. Struktur Tangga AS A


a. Pondasi telapak
- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.25 1,327,775.82 331,943.96
- Besi D13-150 Mutu baja BJTD 40 (ulir) SNI kg 62.02 22,100.00 1,370,642.00
- Bekisting Bekisting batako m2 0.94 237,572.13 223,317.80

6/21
NO URAIAN PEKERJAAN RKS & SPESIFIKASI TEKNIS SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

b. Pek. Pas. Tangga s/d bordes


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.73 1,327,775.82 969,276.35
- Besi tiulangan D13-150 Mutu baja BJTD 40 (ulir) SNI kg 44.14 22,100.00 975,494.00
- Besi Tulangan D10 - 150 Mutu baja BJTD 40 (ulir) SNI kg 35.54 22,100.00 785,434.00
- Besi Tulangan 3 D10 Mutu baja BJTD 40 (ulir) SNI kg 15.64 22,100.00 345,644.00
- Besi Tulangan Ø8 - 150 Mutu baja BJTD 40 (ulir) SNI kg 14.22 22,100.00 314,262.00
- Bekisting bekisting multipleks m2 3.74 556,332.00 2,080,681.68

c. Pek. Pas. Balok bordes 150X300


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.17 1,327,775.82 225,721.89
- Besi Tulangan 4 D13 Mutu baja BJTD 40 (ulir) SNI kg 18.92 22,100.00 418,132.00
- Besi Tulangan D10-150 Mutu baja BJTD 40 (ulir) SNI kg 13.74 22,100.00 303,654.00
- Bekisting Bekisting multipleks m2 2.79 556,332.00 1,552,166.28

d. Pek. Pas. Plat bordes


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.67 1,327,775.82 889,609.80
- Besi Tulangan Ø10-150 Mutu baja BJTD 40 (ulir) SNI kg 43.38 22,100.00 958,698.00
- Bekisting Bekisting multipleks m2 4.47 556,332.00 2,486,804.04

e. Pek. Pas. Tangga s/d bordes


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 1.78 1,327,775.82 2,363,440.96
- Besi tiulangan D13-150 Mutu baja BJTD 40 (ulir) SNI kg 52.30 22,100.00 1,155,830.00
- Besi Tulangan D10 - 150 Mutu baja BJTD 40 (ulir) SNI kg 55.90 22,100.00 1,235,390.00
- Besi Tulangan 3 D10 Mutu baja BJTD 40 (ulir) SNI kg 71.54 22,100.00 1,581,034.00
- Besi Tulangan Ø8 - 150 Mutu baja BJTD 40 (ulir) SNI kg 61.62 22,100.00 1,361,802.00
- Bekisting bekisting multipleks m2 12.07 556,332.00 6,714,927.24

f. Pek. Pas. Balok bordes 150X300


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.17 1,327,775.82 225,721.89
- Besi Tulangan 4 D13 Mutu baja BJTD 40 (ulir) SNI kg 18.92 22,100.00 418,132.00
- Besi Tulangan D10-150 Mutu baja BJTD 40 (ulir) SNI kg 13.74 22,100.00 303,654.00
- Bekisting Bekisting multipleks m2 2.79 556,332.00 1,552,166.28

g. Pek. Pas. Plat bordes


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.67 1,327,775.82 889,609.80
- Besi Tulangan Ø10-150 Mutu baja BJTD 40 (ulir) SNI kg 43.38 22,100.00 958,698.00
- Bekisting Bekisting multipleks m2 4.47 556,332.00 2,486,804.04

h. Pek. Pas. Tangga


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 1.78 1,327,775.82 2,363,440.96
- Besi tiulangan D13-150 Mutu baja BJTD 40 (ulir) SNI kg 52.30 22,100.00 1,155,830.00
- Besi Tulangan D10 - 150 Mutu baja BJTD 40 (ulir) SNI kg 55.90 22,100.00 1,235,390.00
- Besi Tulangan 3 D10 Mutu baja BJTD 40 (ulir) SNI kg 71.54 22,100.00 1,581,034.00
- Besi Tulangan Ø8 - 150 Mutu baja BJTD 40 (ulir) SNI kg 61.62 22,100.00 1,361,802.00
- Bekisting bekisting multipleks m2 12.07 556,332.00 6,714,927.24

17 Pek. Pas. Struktur Tangga AS C

7/21
NO URAIAN PEKERJAAN RKS & SPESIFIKASI TEKNIS SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

a. Pek. Pas. Tangga s/d bordes


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 1.54 1,327,775.82 2,044,774.76
- Besi Tulangan D10 - 150 Mutu baja BJTD 40 (ulir) SNI kg 125.79 22,100.00 2,779,959.00
- Besi Tulangan 3 D10 Mutu baja BJTD 40 (ulir) SNI kg 41.87 22,100.00 925,327.00
- Besi Tulangan Ø8 - 150 Mutu baja BJTD 40 (ulir) SNI kg 36.97 22,100.00 817,037.00
- Bekisting bekisting multipleks m2 10.36 556,332.00 5,763,599.52

b. Pek. Pas. Balok bordes 200x400


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.30 1,327,775.82 398,332.75
- Besi Tulangan 5 D13 Mutu baja BJTD 40 (ulir) SNI kg 23.65 22,100.00 522,665.00
- Besi Tulangan D10-150 Mutu baja BJTD 40 (ulir) SNI kg 18.65 22,100.00 412,165.00
- Bekisting Bekisting multipleks m2 3.73 556,332.00 2,075,118.36

c. Pek. Pas. Plat bordes


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 1.35 1,327,775.82 1,792,497.36
- Besi Tulangan Ø10-150 Mutu baja BJTD 40 (ulir) SNI kg 85.04 22,100.00 1,879,384.00
- Bekisting Bekisting multipleks m2 9.00 556,332.00 5,006,988.00

d. Pek. Pas. Tangga


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 1.54 1,327,775.82 2,044,774.76
- Besi Tulangan D10 - 150 Mutu baja BJTD 40 (ulir) SNI kg 125.79 22,100.00 2,779,959.00
- Besi Tulangan 3 D10 Mutu baja BJTD 40 (ulir) SNI kg 41.87 22,100.00 925,327.00
- Besi Tulangan Ø8 - 150 Mutu baja BJTD 40 (ulir) SNI kg 36.97 22,100.00 817,037.00
- Bekisting bekisting multipleks m2 10.36 556,332.00 5,763,599.52

18 Pek. Pas. Struktur Tangga AS 6


a. Pondasi telapak
- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.35 1,327,775.82 464,721.54
- Besi D13-150 Mutu baja BJTD 40 (ulir) SNI kg 82.21 22,100.00 1,816,841.00
- Bekisting Bekisting batako m2 1.20 237,572.13 285,086.55

a. Pek. Pas. Tangga s/d bordes


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 1.62 1,327,775.82 2,150,996.83
- Besi tiulangan D13-150 Mutu baja BJTD 40 (ulir) SNI kg 84.11 22,100.00 1,858,831.00
- Besi Tulangan D10 - 150 Mutu baja BJTD 40 (ulir) SNI kg 71.57 22,100.00 1,581,697.00
- Besi Tulangan 3 D10 Mutu baja BJTD 40 (ulir) SNI kg 37.32 22,100.00 824,772.00
- Besi Tulangan Ø8 - 150 Mutu baja BJTD 40 (ulir) SNI kg 39.82 22,100.00 880,022.00
- Bekisting bekisting multipleks m2 9.90 556,332.00 5,507,686.80

b. Pek. Pas. Balok bordes 200x400


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.30 1,327,775.82 398,332.75
- Besi Tulangan 5 D13 Mutu baja BJTD 40 (ulir) SNI kg 23.65 22,100.00 522,665.00
- Besi Tulangan D10-150 Mutu baja BJTD 40 (ulir) SNI kg 18.65 22,100.00 412,165.00
- Bekisting Bekisting multipleks m2 3.73 556,332.00 2,075,118.36

c. Pek. Pas. Plat bordes


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.47 1,327,775.82 624,054.64

8/21
NO URAIAN PEKERJAAN RKS & SPESIFIKASI TEKNIS SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

- Besi Tulangan Ø10-150 Mutu baja BJTD 40 (ulir) SNI kg 32.15 22,100.00 710,515.00
- Bekisting Bekisting multipleks m2 3.14 556,332.00 1,746,882.48

d. Pek. Pas. Tangga


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 1.47 1,327,775.82 1,951,830.46
- Besi Tulangan D10 - 150 Mutu baja BJTD 40 (ulir) SNI kg 125.50 22,100.00 2,773,550.00
- Besi Tulangan 3 D10 Mutu baja BJTD 40 (ulir) SNI kg 37.32 22,100.00 824,772.00
- Besi Tulangan Ø8 - 150 Mutu baja BJTD 40 (ulir) SNI kg 39.82 22,100.00 880,022.00
- Bekisting bekisting multipleks m2 9.90 556,332.00 5,507,686.80

19 Pek. Pas. Struktur Tangga outdoor


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 7.04 1,327,775.82 9,347,541.77
- Besi tiulangan D13-150 Mutu baja BJTD 40 (ulir) SNI kg 264.08 22,100.00 5,836,168.00
- Besi Tulangan D10 - 150 Mutu baja BJTD 40 (ulir) SNI kg 265.74 22,100.00 5,872,854.00
- Besi Tulangan 3 D10 Mutu baja BJTD 40 (ulir) SNI kg 120.83 22,100.00 2,670,343.00
- Besi Tulangan Ø8 - 150 Mutu baja BJTD 40 (ulir) SNI kg 104.52 22,100.00 2,309,892.00
- Bekisting bekisting multipleks m2 40.63 556,332.00 22,603,769.16

20 Pek. Pas. Struktur bloom bak


a. Pondasi telapak
- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 1.00 1,327,775.82 1,327,775.82
- Besi D16-150 Mutu baja BJTD 40 (ulir) SNI kg 196.07 22,100.00 4,333,147.00
- Bekisting Bekisting batako m2 2.83 237,572.13 672,329.13

b. Pek. Pas. Trap dan dinding bloom bak


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 8.33 1,327,775.82 11,060,372.58
- Besi tiulangan D16-150 Mutu baja BJTD 40 (ulir) SNI kg 1,597.19 22,100.00 35,297,899.00
- Besi Tulangan D10 - 150 Mutu baja BJTD 40 (ulir) SNI kg 1,248.20 22,100.00 27,585,220.00
- Bekisting bekisting multipleks m2 85.01 556,332.00 47,293,783.32
JUMLAH PEKERJAAN STRUKTUR ELV. +3.950 2,625,848,458.53

II.4 PEKERJAAN STRUKTUR ELV. +7.950


1 Pek. Pas. Kolom K1 700x700
- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 58.80 1,327,775.82 78,073,218.22
- Besi tulangan 32 D25 Mutu baja BJTD 40 (ulir) SNI kg 3,956.76 22,100.00 87,444,396.00
- Besi sengkang D10 - 100&150 Mutu baja BJTP 24 (polos) SNI kg 1,775.11 22,100.00 39,229,931.00
- Besi ties 6D10 - 100&150 Mutu baja BJTP 24 (polos) SNI kg 2,954.20 22,100.00 65,287,820.00
- Bekisting Bekisting multipleks m2 336.00 556,332.00 186,927,552.00

2 Pek. Pas. Kolom K3 400x400


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 3.20 1,327,775.82 4,248,882.62
- Besi tulangan 12 D19 Mutu baja BJTD 40 (ulir) SNI kg 684.50 22,100.00 15,127,450.00
- Besi sengkang D10 - 100&150 Mutu baja BJTP 24 (polos) SNI kg 166.28 22,100.00 3,674,788.00
- Bekisting Bekisting multipleks m2 32.00 556,332.00 17,802,624.00

3 Pek. Pas. Dinding Beton t.200mm


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 14.59 1,327,775.82 19,372,249.21

9/21
NO URAIAN PEKERJAAN RKS & SPESIFIKASI TEKNIS SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

- Besi D13-150 Mutu baja BJTD 40 (ulir) SNI kg 1,630.27 22,100.00 36,028,967.00
- Bekisting multipleks Bekisting multipleks m2 145.86 556,332.00 81,146,585.52

4 Pek. Pas. Balok B1 400x800


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 74.24 1,327,775.82 98,574,076.88
- Besi tulangan 15 D25 Mutu baja BJTD 40 (ulir) SNI kg 4,660.65 22,100.00 103,000,365.00
- Besi tulangan 10 D25 Mutu baja BJTD 40 (ulir) SNI kg 7,107.10 22,100.00 157,066,910.00
- Besi tulangan 2 D13 Mutu baja BJTP 24 (polos) SNI kg 586.02 22,100.00 12,951,042.00
- Besi Tulangan D10 - 100&150 Mutu baja BJTP 24 (polos) SNI kg 3,920.03 22,100.00 86,632,663.00
- Bekisting Bekisting multipleks m2 449.92 556,332.00 250,304,893.44

5 Pek. Pas. Balok B3 350x700


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 42.47 1,327,775.82 56,390,639.08
- Besi tulangan 13 D22 Mutu baja BJTD 40 (ulir) SNI kg 5,482.47 22,100.00 121,162,587.00
- Besi tulangan 12 D22 Mutu baja BJTD 40 (ulir) SNI kg 5,060.74 22,100.00 111,842,354.00
- Besi tulangan 2 D10 Mutu baja BJTP 24 (polos) SNI kg 267.36 22,100.00 5,908,656.00
- Besi Tulangan D10 - 100&150 Mutu baja BJTP 24 (polos) SNI kg 3,338.83 22,100.00 73,788,143.00
- Bekisting Bekisting multipleks m2 303.32 556,332.00 168,746,622.24

6 Pek. Pas. Balok B3A 350x700


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 10.44 1,327,775.82 13,861,979.56
- Besi tulangan 13 D22 Mutu baja BJTD 40 (ulir) SNI kg 3,385.77 22,100.00 74,825,517.00
- Besi tulangan 2 D10 Mutu baja BJTD 40 (ulir) SNI kg 65.75 22,100.00 1,453,075.00
- Besi Tulangan D10 - 100 Mutu baja BJTD 40 (ulir) SNI kg 543.95 22,100.00 12,021,295.00
- Bekisting Bekisting multipleks m2 74.59 556,332.00 41,496,803.88

7 Pek. Pas. Balok B4 250x500


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 4.06 1,327,775.82 5,390,769.83
- Besi tulangan 5 D19 Mutu baja BJTD 40 (ulir) SNI kg 395.89 22,100.00 8,749,169.00
- Besi tulangan 6 D19 Mutu baja BJTD 40 (ulir) SNI kg 475.07 22,100.00 10,499,047.00
- Besi Tulangan D10 - 100&150 Mutu baja BJTD 40 (ulir) SNI kg 368.00 22,100.00 8,132,800.00
- Bekisting Bekisting multipleks m2 45.14 556,332.00 25,112,826.48

8 Pek. Pas. Balok B4A 250x500


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.83 1,327,775.82 1,102,053.93
- Besi tulangan 5 D19 Mutu baja BJTD 40 (ulir) SNI kg 157.71 22,100.00 3,485,391.00
- Besi Tulangan D10 - 100 Mutu baja BJTD 40 (ulir) SNI kg 88.58 22,100.00 1,957,618.00
- Bekisting Bekisting multipleks m2 9.17 556,332.00 5,101,564.44

9 Pek. Pas. Balok B5 200x400


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 3.02 1,327,775.82 4,009,882.98
- Besi tulangan 5 D16 Mutu baja BJTD 40 (ulir) SNI kg 545.12 22,100.00 12,047,152.00
- Besi Tulangan D10 - 100&150 Mutu baja BJTD 40 (ulir) SNI kg 368.40 22,100.00 8,141,640.00
- Bekisting Bekisting multipleks m2 46.47 556,332.00 25,852,748.04

10 Pek. Pas. Balok B5A 200x400


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.09 1,327,775.82 119,499.82

10/21
NO URAIAN PEKERJAAN RKS & SPESIFIKASI TEKNIS SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

- Besi tulangan 5 D16 Mutu baja BJTD 40 (ulir) SNI kg 21.93 22,100.00 484,653.00
- Besi Tulangan D10 - 100 Mutu baja BJTD 40 (ulir) SNI kg 13.83 22,100.00 305,643.00
- Bekisting Bekisting multipleks m2 1.42 556,332.00 789,991.44

11 Pek. Pas. Balok B6 200x350


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.22 1,327,775.82 292,110.68
- Besi tulangan 5 D16 Mutu baja BJTD 40 (ulir) SNI kg 48.76 22,100.00 1,077,596.00
- Besi Tulangan D10 - 100&150 Mutu baja BJTD 40 (ulir) SNI kg 29.99 22,100.00 662,779.00
- Bekisting Bekisting multipleks m2 3.63 556,332.00 2,019,485.16

12 Pek. Pas. Plat lantai S1 Elv. +7.950 T.14cm


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 67.94 1,327,775.82 90,209,089.21
- Wiremesh M8 (2 lapis) Wiremesh M8 (2 lapis) kg 1,923.56 20,091.89 38,647,963.41
- Bekisting Bekisting multipleks m2 82.46 556,332.00 45,875,136.72
- Standed bar bh 842.00 9,591.40 8,075,958.80

13 Pek. Pas. Struktur Tangga AS C


a. Pek. Pas. Tangga s/d bordes
- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 1.54 1,327,775.82 2,044,774.76
- Besi Tulangan D10 - 150 Mutu baja BJTD 40 (ulir) SNI kg 125.79 22,100.00 2,779,959.00
- Besi Tulangan 3 D10 Mutu baja BJTD 40 (ulir) SNI kg 41.87 22,100.00 925,327.00
- Besi Tulangan Ø8 - 150 Mutu baja BJTD 40 (ulir) SNI kg 36.97 22,100.00 817,037.00
- Bekisting bekisting multipleks m2 10.36 556,332.00 5,763,599.52

b. Pek. Pas. Balok bordes 200x400


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.30 1,327,775.82 398,332.75
- Besi Tulangan 5 D13 Mutu baja BJTD 40 (ulir) SNI kg 23.65 22,100.00 522,665.00
- Besi Tulangan D10-150 Mutu baja BJTD 40 (ulir) SNI kg 18.65 22,100.00 412,165.00
- Bekisting Bekisting multipleks m2 3.73 556,332.00 2,075,118.36

c. Pek. Pas. Plat bordes


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 1.35 1,327,775.82 1,792,497.36
- Besi Tulangan Ø10-150 Mutu baja BJTD 40 (ulir) SNI kg 85.04 22,100.00 1,879,384.00
- Bekisting Bekisting multipleks m2 9.00 556,332.00 5,006,988.00

d. Pek. Pas. Tangga


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 1.54 1,327,775.82 2,044,774.76
- Besi Tulangan D10 - 150 Mutu baja BJTD 40 (ulir) SNI kg 125.79 22,100.00 2,779,959.00
- Besi Tulangan 3 D10 Mutu baja BJTD 40 (ulir) SNI kg 41.87 22,100.00 925,327.00
- Besi Tulangan Ø8 - 150 Mutu baja BJTD 40 (ulir) SNI kg 36.97 22,100.00 817,037.00
- Bekisting bekisting multipleks m2 10.36 556,332.00 5,763,599.52

14 Pek. Pas. Struktur Tangga AS 6


a. Pek. Pas. Tangga s/d bordes
- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 1.62 1,327,775.82 2,150,996.83
- Besi tiulangan D13-150 Mutu baja BJTD 40 (ulir) SNI kg 64.42 22,100.00 1,423,598.02
- Besi Tulangan D10 - 150 Mutu baja BJTD 40 (ulir) SNI kg 71.57 22,100.00 1,581,697.00

11/21
NO URAIAN PEKERJAAN RKS & SPESIFIKASI TEKNIS SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

- Besi Tulangan 3 D10 Mutu baja BJTD 40 (ulir) SNI kg 37.32 22,100.00 824,772.00
- Besi Tulangan Ø8 - 150 Mutu baja BJTD 40 (ulir) SNI kg 39.82 22,100.00 880,022.00
- Bekisting bekisting multipleks m2 9.90 556,332.00 5,507,686.80

b. Pek. Pas. Balok bordes 200x400


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.30 1,327,775.82 398,332.75
- Besi Tulangan 5 D13 Mutu baja BJTD 40 (ulir) SNI kg 23.65 22,100.00 522,665.00
- Besi Tulangan D10-150 Mutu baja BJTD 40 (ulir) SNI kg 18.65 22,100.00 412,165.00
- Bekisting Bekisting multipleks m2 3.73 556,332.00 2,075,118.36

c. Pek. Pas. Plat bordes


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.47 1,327,775.82 624,054.64
- Besi Tulangan Ø10-150 Mutu baja BJTD 40 (ulir) SNI kg 32.15 22,100.00 710,515.00
- Bekisting Bekisting multipleks m2 3.14 556,332.00 1,746,882.48

d. Pek. Pas. Tangga


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 1.47 1,327,775.82 1,951,830.46
- Besi Tulangan D10 - 150 Mutu baja BJTD 40 (ulir) SNI kg 125.50 22,100.00 2,773,550.00
- Besi Tulangan 3 D10 Mutu baja BJTD 40 (ulir) SNI kg 37.32 22,100.00 824,772.00
- Besi Tulangan Ø8 - 150 Mutu baja BJTD 40 (ulir) SNI kg 39.82 22,100.00 880,022.00
- Bekisting bekisting multipleks m2 9.90 556,332.00 5,507,686.80
JUMLAH PEKERJAAN STRUKTUR ELV. +7.950 2,400,079,566.75

II.5 PEKERJAAN STRUKTUR ELV. +11.950


1 Pek. Pas. Kolom K1 700x700
- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 58.80 1,327,775.82 78,073,218.22
- Besi tulangan 32 D25 Mutu baja BJTD 40 (ulir) SNI kg 2,956.76 22,100.00 65,344,396.00
- Besi sengkang D10 - 100&150 Mutu baja BJTP 24 (polos) SNI kg 1,775.11 22,100.00 39,229,931.00
- Besi ties 6D10 - 100&150 Mutu baja BJTP 24 (polos) SNI kg 2,954.20 22,100.00 65,287,820.00
- Bekisting Bekisting multipleks m2 336.00 556,332.00 186,927,552.00

2 Pek. Pas. Dinding Beton t.200mm


- Cor Beton Mutu baja BJTD 40 (ulir) SNI m3 14.59 22,100.00 322,439.00
- Besi D13-150 Mutu baja BJTP 24 (polos) SNI kg 1,630.27 22,100.00 36,028,967.00
- Bekisting multipleks Bekisting multipleks m2 145.86 556,332.00 81,146,585.52

3 Pek. Pas. Balok B1 400x800


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 74.24 1,327,775.82 98,574,076.88
- Besi tulangan 15 D25 Mutu baja BJTD 40 (ulir) SNI kg 2,660.65 22,100.00 58,800,365.00
- Besi tulangan 10 D25 Mutu baja BJTD 40 (ulir) SNI kg 3,107.10 22,100.00 68,666,910.00
- Besi tulangan 2 D13 Mutu baja BJTP 24 (polos) SNI kg 586.02 22,100.00 12,951,042.00
- Besi Tulangan D10 - 100&150 Mutu baja BJTP 24 (polos) SNI kg 3,920.03 22,100.00 86,632,663.00
- Bekisting Bekisting multipleks m2 449.92 556,332.00 250,304,893.44

4 Pek. Pas. Balok B3 350x700


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 42.47 1,327,775.82 56,390,639.08
- Besi tulangan 13 D22 Mutu baja BJTD 40 (ulir) SNI kg 5,482.47 22,100.00 121,162,587.00

12/21
NO URAIAN PEKERJAAN RKS & SPESIFIKASI TEKNIS SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

- Besi tulangan 12 D22 Mutu baja BJTD 40 (ulir) SNI kg 5,060.74 22,100.00 111,842,354.00
- Besi tulangan 2 D10 Mutu baja BJTP 24 (polos) SNI kg 267.36 22,100.00 5,908,656.00
- Besi Tulangan D10 - 100&150 Mutu baja BJTP 24 (polos) SNI kg 3,338.83 22,100.00 73,788,143.00
- Bekisting Bekisting multipleks m2 303.32 556,332.00 168,746,622.24

5 Pek. Pas. Balok B3A 350x700


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 8.56 1,327,775.82 11,365,761.02
- Besi tulangan 13 D22 Mutu baja BJTD 40 (ulir) SNI kg 3,012.59 22,100.00 66,578,239.00
- Besi tulangan 2 D10 Mutu baja BJTD 40 (ulir) SNI kg 53.88 22,100.00 1,190,748.00
- Besi Tulangan D10 - 100 Mutu baja BJTD 40 (ulir) SNI kg 465.22 22,100.00 10,281,362.00
- Bekisting Bekisting multipleks m2 61.12 556,332.00 34,003,011.84

6 Pek. Pas. Balok B4 250x500


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 4.15 1,327,775.82 5,510,269.65
- Besi tulangan 5 D19 Mutu baja BJTD 40 (ulir) SNI kg 412.26 22,100.00 9,110,946.00
- Besi tulangan 6 D19 Mutu baja BJTD 40 (ulir) SNI kg 494.71 22,100.00 10,933,091.00
- Besi Tulangan D10 - 100&150 Mutu baja BJTD 40 (ulir) SNI kg 377.14 22,100.00 8,334,794.00
- Bekisting Bekisting multipleks m2 46.08 556,332.00 25,635,778.56

7 Pek. Pas. Balok B4A 250x500


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.83 1,327,775.82 1,102,053.93
- Besi tulangan 5 D19 Mutu baja BJTD 40 (ulir) SNI kg 157.71 22,100.00 3,485,391.00
- Besi Tulangan D10 - 100 Mutu baja BJTD 40 (ulir) SNI kg 88.58 22,100.00 1,957,618.00
- Bekisting Bekisting multipleks m2 9.17 556,332.00 5,101,564.44

8 Pek. Pas. Balok B5 200x400


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 4.17 1,327,775.82 5,536,825.17
- Besi tulangan 5 D16 Mutu baja BJTD 40 (ulir) SNI kg 735.58 22,100.00 16,256,318.00
- Besi Tulangan D10 - 100&150 Mutu baja BJTD 40 (ulir) SNI kg 506.00 22,100.00 11,182,600.00
- Bekisting Bekisting multipleks m2 64.18 556,332.00 35,705,387.76

9 Pek. Pas. Balok B5A 200x400


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.08 1,327,775.82 106,222.07
- Besi tulangan 5 D16 Mutu baja BJTD 40 (ulir) SNI kg 19.96 22,100.00 441,116.00
- Besi Tulangan D10 - 100 Mutu baja BJTD 40 (ulir) SNI kg 11.65 22,100.00 257,465.00
- Bekisting Bekisting multipleks m2 1.22 556,332.00 678,725.04

10 Pek. Pas. Balok B6 200x350


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.27 1,327,775.82 358,499.47
- Besi tulangan 5 D16 Mutu baja BJTD 40 (ulir) SNI kg 38.66 22,100.00 854,386.00
- Besi Tulangan D10 - 100&150 Mutu baja BJTD 40 (ulir) SNI kg 23.32 22,100.00 515,372.00
- Bekisting Bekisting multipleks m2 2.73 556,332.00 1,518,786.36

11 Pek. Pas. Plat lantai S1 Elv. +11.950 T.14cm


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 116.15 1,327,775.82 154,221,161.49
- Wiremesh M8 (2 lapis) Wiremesh M8 (2 lapis) kg 9,673.72 20,091.89 194,363,355.77
- Bekisting Bekisting multipleks m2 829.61 556,332.00 461,538,590.52

13/21
NO URAIAN PEKERJAAN RKS & SPESIFIKASI TEKNIS SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

- Standed bar bh 830.00 9,591.40 7,960,862.00

12 Pek. Pas. Struktur Tangga AS C


a. Pek. Pas. Tangga s/d bordes
- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 1.54 1,327,775.82 2,044,774.76
- Besi Tulangan D10 - 150 Mutu baja BJTD 40 (ulir) SNI kg 125.79 22,100.00 2,779,959.00
- Besi Tulangan 3 D10 Mutu baja BJTD 40 (ulir) SNI kg 41.87 22,100.00 925,327.00
- Besi Tulangan Ø8 - 150 Mutu baja BJTD 40 (ulir) SNI kg 36.97 22,100.00 817,037.00
- Bekisting bekisting multipleks m2 10.36 556,332.00 5,763,599.52

b. Pek. Pas. Balok bordes 200x400


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.30 1,327,775.82 398,332.75
- Besi Tulangan 5 D13 Mutu baja BJTD 40 (ulir) SNI kg 23.65 22,100.00 522,665.00
- Besi Tulangan D10-150 Mutu baja BJTD 40 (ulir) SNI kg 18.65 22,100.00 412,165.00
- Bekisting Bekisting multipleks m2 3.73 556,332.00 2,075,118.36

c. Pek. Pas. Plat bordes


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 1.35 1,327,775.82 1,792,497.36
- Besi Tulangan Ø10-150 Mutu baja BJTD 40 (ulir) SNI kg 85.04 22,100.00 1,879,384.00
- Bekisting Bekisting multipleks m2 9.00 556,332.00 5,006,988.00

d. Pek. Pas. Tangga


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 1.54 1,327,775.82 2,044,774.76
- Besi Tulangan D10 - 150 Mutu baja BJTD 40 (ulir) SNI kg 125.79 22,100.00 2,779,959.00
- Besi Tulangan 3 D10 Mutu baja BJTD 40 (ulir) SNI kg 41.87 22,100.00 925,327.00
- Besi Tulangan Ø8 - 150 Mutu baja BJTD 40 (ulir) SNI kg 36.97 22,100.00 817,037.00
- Bekisting bekisting multipleks m2 10.36 556,332.00 5,763,599.52

13 Pek. Pas. Struktur Tangga AS 6


a. Pek. Pas. Tangga s/d bordes
- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 1.62 1,327,775.82 2,150,996.83
- Besi tiulangan D13-150 Mutu baja BJTD 40 (ulir) SNI kg 64.42 22,100.00 1,423,598.02
- Besi Tulangan D10 - 150 Mutu baja BJTD 40 (ulir) SNI kg 71.57 22,100.00 1,581,697.00
- Besi Tulangan 3 D10 Mutu baja BJTD 40 (ulir) SNI kg 37.32 22,100.00 824,772.00
- Besi Tulangan Ø8 - 150 Mutu baja BJTD 40 (ulir) SNI kg 39.82 22,100.00 880,022.00
- Bekisting bekisting multipleks m2 9.90 556,332.00 5,507,686.80

b. Pek. Pas. Balok bordes 200x400


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.30 1,327,775.82 398,332.75
- Besi Tulangan 5 D13 Mutu baja BJTD 40 (ulir) SNI kg 23.65 22,100.00 522,665.00
- Besi Tulangan D10-150 Mutu baja BJTD 40 (ulir) SNI kg 18.65 22,100.00 412,165.00
- Bekisting Bekisting multipleks m2 3.73 556,332.00 2,075,118.36

c. Pek. Pas. Plat bordes


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.47 1,327,775.82 624,054.64
- Besi Tulangan Ø10-150 Mutu baja BJTD 40 (ulir) SNI kg 32.15 22,100.00 710,515.00
- Bekisting Bekisting multipleks m2 3.14 556,332.00 1,746,882.48

14/21
NO URAIAN PEKERJAAN RKS & SPESIFIKASI TEKNIS SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

d. Pek. Pas. Tangga


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 1.47 1,327,775.82 1,951,830.46
- Besi Tulangan D10 - 150 Mutu baja BJTD 40 (ulir) SNI kg 125.50 22,100.00 2,773,550.00
- Besi Tulangan 3 D10 Mutu baja BJTD 40 (ulir) SNI kg 37.32 22,100.00 824,772.00
- Besi Tulangan Ø8 - 150 Mutu baja BJTD 40 (ulir) SNI kg 39.82 22,100.00 880,022.00
- Bekisting bekisting multipleks m2 9.90 556,332.00 5,507,686.80
JUMLAH PEKERJAAN STRUKTUR ELV. +11.950 2,819,761,073.62

II.6 PEKERJAAN STRUKTUR S/D ELV. +15.950


1 Pek. Pas. Kolom K1 700x700
- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 58.80 1,327,775.82 78,073,218.22
- Besi tulangan 32 D25 Mutu baja BJTD 40 (ulir) SNI kg 18,956.76 22,100.00 418,944,396.00
- Besi sengkang D10 - 100&150 Mutu baja BJTP 24 (polos) SNI kg 1,775.11 22,100.00 39,229,931.00
- Besi ties 6D10 - 100&150 Mutu baja BJTP 24 (polos) SNI kg 2,954.20 22,100.00 65,287,820.00
- Bekisting Bekisting multipleks m2 336.00 556,332.00 186,927,552.00

2 Pek. Pas. Dinding Beton t.200mm


- Cor Beton Mutu baja BJTD 40 (ulir) SNI m3 14.59 22,100.00 322,439.00
- Besi D13-150 Mutu baja BJTP 24 (polos) SNI kg 1,630.27 22,100.00 36,028,967.00
- Bekisting multipleks Bekisting multipleks m2 145.86 556,332.00 81,146,585.52

3 Pek. Pas. Balok B1 400x800


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 71.71 1,327,775.82 95,214,804.05
- Besi tulangan 15 D25 Mutu baja BJTD 40 (ulir) SNI kg 10,326.28 22,100.00 228,210,788.00
- Besi tulangan 10 D25 Mutu baja BJTD 40 (ulir) SNI kg 6,884.19 22,100.00 152,140,599.00
- Besi tulangan 2 D13 Mutu baja BJTP 24 (polos) SNI kg 566.06 22,100.00 12,509,926.00
- Besi Tulangan D10 - 100&150 Mutu baja BJTP 24 (polos) SNI kg 3,787.76 22,100.00 83,709,496.00
- Bekisting Bekisting multipleks m2 434.59 556,332.00 241,776,323.88

4 Pek. Pas. Balok B3 350x700


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 42.47 1,327,775.82 56,390,639.08
- Besi tulangan 13 D22 Mutu baja BJTD 40 (ulir) SNI kg 5,482.47 22,100.00 121,162,587.00
- Besi tulangan 12 D22 Mutu baja BJTD 40 (ulir) SNI kg 5,060.74 22,100.00 111,842,354.00
- Besi tulangan 2 D10 Mutu baja BJTP 24 (polos) SNI kg 267.36 22,100.00 5,908,656.00
- Besi Tulangan D10 - 100&150 Mutu baja BJTP 24 (polos) SNI kg 3,338.83 22,100.00 73,788,143.00
- Bekisting Bekisting multipleks m2 303.32 556,332.00 168,746,622.24

5 Pek. Pas. Balok B3A 350x700


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 7.99 1,327,775.82 10,608,928.80
- Besi tulangan 13 D22 Mutu baja BJTD 40 (ulir) SNI kg 2,589.75 22,100.00 57,233,475.00
- Besi tulangan 2 D10 Mutu baja BJTD 40 (ulir) SNI kg 50.30 22,100.00 1,111,630.00
- Besi Tulangan D10 - 100 Mutu baja BJTD 40 (ulir) SNI kg 415.12 22,100.00 9,174,152.00
- Bekisting Bekisting multipleks m2 57.06 556,332.00 31,744,303.92

6 Pek. Pas. Balok B4 250x500


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 1.92 1,327,775.82 2,549,329.57

15/21
NO URAIAN PEKERJAAN RKS & SPESIFIKASI TEKNIS SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

- Besi tulangan 5 D19 Mutu baja BJTD 40 (ulir) SNI kg 163.17 22,100.00 3,606,057.00
- Besi tulangan 6 D19 Mutu baja BJTD 40 (ulir) SNI kg 195.80 22,100.00 4,327,180.00
- Besi Tulangan D10 - 100&150 Mutu baja BJTD 40 (ulir) SNI kg 168.93 22,100.00 3,733,353.00
- Bekisting Bekisting multipleks m2 21.32 556,332.00 11,860,998.24

7 Pek. Pas. Balok B4A 250x500


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.83 1,327,775.82 1,102,053.93
- Besi tulangan 5 D19 Mutu baja BJTD 40 (ulir) SNI kg 157.71 22,100.00 3,485,391.00
- Besi Tulangan D10 - 100 Mutu baja BJTD 40 (ulir) SNI kg 88.58 22,100.00 1,957,618.00
- Bekisting Bekisting multipleks m2 9.17 556,332.00 5,101,564.44

8 Pek. Pas. Balok B5 200x400


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 5.43 1,327,775.82 7,209,822.70
- Besi tulangan 5 D16 Mutu baja BJTD 40 (ulir) SNI kg 879.81 22,100.00 19,443,801.00
- Besi Tulangan D10 - 100&150 Mutu baja BJTD 40 (ulir) SNI kg 645.06 22,100.00 14,255,826.00
- Bekisting Bekisting multipleks m2 83.61 556,332.00 46,514,918.52

9 Pek. Pas. Balok B5A 200x400


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.08 1,327,775.82 106,222.07
- Besi tulangan 5 D16 Mutu baja BJTD 40 (ulir) SNI kg 19.96 22,100.00 441,116.00
- Besi Tulangan D10 - 100 Mutu baja BJTD 40 (ulir) SNI kg 11.65 22,100.00 257,465.00
- Bekisting Bekisting multipleks m2 1.22 556,332.00 678,725.04

10 Pek. Pas. Balok B6 200x350


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.16 1,327,775.82 212,444.13
- Besi tulangan 5 D16 Mutu baja BJTD 40 (ulir) SNI kg 38.66 22,100.00 854,386.00
- Besi Tulangan D10 - 100&150 Mutu baja BJTD 40 (ulir) SNI kg 23.32 22,100.00 515,372.00
- Bekisting Bekisting multipleks m2 2.73 556,332.00 1,518,786.36

11 Pek. Pas. Plat lantai S1 Elv. +15.950 T.14cm


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 121.13 1,327,775.82 160,833,485.08
- Wiremesh M8 (2 lapis) Wiremesh M8 (2 lapis) kg 1,088.77 20,091.89 21,875,451.31
- Bekisting Bekisting multipleks m2 665.21 556,332.00 370,077,609.72
- Standed bar bh 865.00 9,591.40 8,296,561.00

12 Pek. Pas. Struktur Tangga AS 6


a. Pek. Pas. Tangga s/d bordes
- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 1.62 1,327,775.82 2,150,996.83
- Besi tiulangan D13-150 Mutu baja BJTD 40 (ulir) SNI kg 64.42 22,100.00 1,423,598.02
- Besi Tulangan D10 - 150 Mutu baja BJTD 40 (ulir) SNI kg 71.57 22,100.00 1,581,697.00
- Besi Tulangan 3 D10 Mutu baja BJTD 40 (ulir) SNI kg 37.32 22,100.00 824,772.00
- Besi Tulangan Ø8 - 150 Mutu baja BJTD 40 (ulir) SNI kg 39.82 22,100.00 880,022.00
- Bekisting bekisting multipleks m2 9.90 556,332.00 5,507,686.80

b. Pek. Pas. Balok bordes 200x400


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.30 1,327,775.82 398,332.75
- Besi Tulangan 5 D13 Mutu baja BJTD 40 (ulir) SNI kg 23.65 22,100.00 522,665.00

16/21
NO URAIAN PEKERJAAN RKS & SPESIFIKASI TEKNIS SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

- Besi Tulangan D10-150 Mutu baja BJTD 40 (ulir) SNI kg 18.65 22,100.00 412,165.00
- Bekisting Bekisting multipleks m2 3.73 556,332.00 2,075,118.36

c. Pek. Pas. Plat bordes


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.47 1,327,775.82 624,054.64
- Besi Tulangan Ø10-150 Mutu baja BJTD 40 (ulir) SNI kg 32.15 22,100.00 710,515.00
- Bekisting Bekisting multipleks m2 3.14 556,332.00 1,746,882.48

d. Pek. Pas. Tangga


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 1.47 1,327,775.82 1,951,830.46
- Besi Tulangan D10 - 150 Mutu baja BJTD 40 (ulir) SNI kg 125.50 22,100.00 2,773,550.00
- Besi Tulangan 3 D10 Mutu baja BJTD 40 (ulir) SNI kg 37.32 22,100.00 824,772.00
- Besi Tulangan Ø8 - 150 Mutu baja BJTD 40 (ulir) SNI kg 39.82 22,100.00 880,022.00
- Bekisting bekisting multipleks m2 9.90 556,332.00 5,507,686.80
JUMLAH PEKERJAAN STRUKTUR ELV. +15.950 3,088,846,240.94

II.7 PEKERJAAN STRUKTUR S/D ELV. +19.500


1 Pek. Pas. Kolom K1 700x700
- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 21.56 1,327,775.82 28,626,846.68
- Besi tulangan 32 D25 Mutu baja BJTD 40 (ulir) SNI kg 650.81 22,100.00 14,382,901.00
- Besi sengkang D10 - 100&150 Mutu baja BJTP 24 (polos) SNI kg 650.87 22,100.00 14,384,227.00
- Besi ties 6D10 - 100&150 Mutu baja BJTP 24 (polos) SNI kg 1,083.21 22,100.00 23,938,941.00
- Bekisting Bekisting multipleks m2 123.20 556,332.00 68,540,102.40

2 Pek. Pas. Balok B1 400x800


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 13.73 1,327,775.82 18,230,362.01
- Besi tulangan 15 D25 Mutu baja BJTD 40 (ulir) SNI kg 2,079.00 22,100.00 45,945,900.00
- Besi tulangan 10 D25 Mutu baja BJTD 40 (ulir) SNI kg 1,386.00 22,100.00 30,630,600.00
- Besi tulangan 2 D13 Mutu baja BJTP 24 (polos) SNI kg 108.37 22,100.00 2,394,977.00
- Besi Tulangan D10 - 100&150 Mutu baja BJTP 24 (polos) SNI kg 731.00 22,100.00 16,155,100.00
- Bekisting Bekisting multipleks m2 83.20 556,332.00 46,286,822.40

3 Pek. Pas. Balok B3 350x700


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 5.38 1,327,775.82 7,143,433.91
- Besi tulangan 13 D22 Mutu baja BJTD 40 (ulir) SNI kg 765.37 22,100.00 16,914,677.00
- Besi tulangan 12 D22 Mutu baja BJTD 40 (ulir) SNI kg 706.49 22,100.00 15,613,429.00
- Besi tulangan 2 D10 Mutu baja BJTP 24 (polos) SNI kg 33.89 22,100.00 748,969.00
- Besi Tulangan D10 - 100&150 Mutu baja BJTP 24 (polos) SNI kg 431.22 22,100.00 9,529,962.00
- Bekisting Bekisting multipleks m2 38.44 556,332.00 21,385,402.08

4 Pek. Pas. Balok B3A 350x700


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 2.38 1,327,775.82 3,160,106.45
- Besi tulangan 13 D22 Mutu baja BJTD 40 (ulir) SNI kg 781.27 22,100.00 17,266,067.00
- Besi tulangan 2 D10 Mutu baja BJTD 40 (ulir) SNI kg 14.98 22,100.00 331,058.00
- Besi Tulangan D10 - 100 Mutu baja BJTD 40 (ulir) SNI kg 125.25 22,100.00 2,768,025.00
- Bekisting Bekisting multipleks m2 17.00 556,332.00 9,457,644.00

17/21
NO URAIAN PEKERJAAN RKS & SPESIFIKASI TEKNIS SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

5 Pek. Pas. Balok B4 250x500


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 2.03 1,327,775.82 2,695,384.91
- Besi tulangan 5 D19 Mutu baja BJTD 40 (ulir) SNI kg 170.01 22,100.00 3,757,221.00
- Besi tulangan 6 D19 Mutu baja BJTD 40 (ulir) SNI kg 204.01 22,100.00 4,508,621.00
- Besi Tulangan D10 - 100&150 Mutu baja BJTD 40 (ulir) SNI kg 178.98 22,100.00 3,955,458.00
- Bekisting Bekisting multipleks m2 22.55 556,332.00 12,545,286.60

6 Pek. Pas. Balok B4A 250x500


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.83 1,327,775.82 1,102,053.93
- Besi tulangan 5 D19 Mutu baja BJTD 40 (ulir) SNI kg 157.71 22,100.00 3,485,391.00
- Besi Tulangan D10 - 100 Mutu baja BJTD 40 (ulir) SNI kg 88.58 22,100.00 1,957,618.00
- Bekisting Bekisting multipleks m2 9.17 556,332.00 5,101,564.44

7 Pek. Pas. Plat lantai S1 Elv. +19.500 T.14cm


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 17.81 1,327,775.82 23,647,687.35
- Wiremesh M8 (2 lapis) Wiremesh M8 (2 lapis) kg 1,483.31 20,091.89 29,802,507.13
- Bekisting Bekisting multipleks m2 127.21 556,332.00 70,770,993.72
- Standed bar bh 127.00 9,591.40 1,218,107.80
JUMLAH PEKERJAAN STRUKTUR S/D ELV. +19.500 578,383,447.82

II.8 PEKERJAAN STRUKTUR RUANG POMPA


II.8.1 PEKERJAAN TANAH
1 Pek. Galian tanah untuk pondasi dan Tie beam m3 111.48 60,492.00 6,743,648.16
2 Pek. Urugan kembali bekas galian m3 40.57 43,371.00 1,759,561.47
3 Pek. Buangan Tanah Bekas Galian m3 70.91 57,142.86 4,052,000.00
4 Pek. Urugan pasir di bawah pondasi & Tie beam Pasir urug dipadatkan T.10 cm m3 8.96 449,650.00 4,028,864.00
5 Pek. Lantai kerja di bawah pondasi & Tie beam Lantai Kerja Beton Mutu f'c = 7,4 Mpa Slump (3-6)cm, w/c = 0,87 T.5 cm m3 4.48 378,764.25 1,696,863.84

II.8.2 PEKERJAAN STRUKTUR S/D ELV. -4.00


1 Pek. Pas. Tiang Pancang square 400 T=30 meter
a. Tiang Pancang square 400
- Tiang pancang square 400 (P1) m1 60.00 439,840.00 26,390,400.00
- Tiang pancang square 400 (P2) m1 240.00 439,840.00 105,561,600.00
- Tiang pancang square 400 (P3) m1 180.00 439,840.00 79,171,200.00

b. Pemotongan tiang pancang square 400


- Tiang pancang square 400 (P1) unit 2.00 90,000.00 180,000.00
- Tiang pancang square 400 (P2) unit 18.00 90,000.00 1,620,000.00
- Tiang pancang square 400 (P3) unit 6.00 90,000.00 540,000.00

c. Penyambungan & pengelasan tiang pancang square 400


- Tiang pancang square 400 (P1) joint 6.00 108,000.00 648,000.00
- Tiang pancang square 400 (P2) joint 54.00 108,000.00 5,832,000.00
- Tiang pancang square 400 (P3) joint 18.00 108,000.00 1,944,000.00

d. Pemancangan tiang pancang square 400


- Tiang pancang square 400 (P1) m1 60.00 250,500.00 15,030,000.00

18/21
NO URAIAN PEKERJAAN RKS & SPESIFIKASI TEKNIS SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

- Tiang pancang square 400 (P2) m1 540.00 250,500.00 135,270,000.00


- Tiang pancang square 400 (P3) m1 180.00 250,500.00 45,090,000.00

2 Pek. Pas. Pondasi Pile Cap tipe PC1 1050x1050x550


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 1.21 1,327,775.82 1,606,608.74
- Besi D16-150 Mutu baja BJTD 40 (ulir) SNI kg 158.56 22,100.00 3,504,176.00
- Bekisting Bekisting batako m2 4.62 237,572.13 1,097,583.24

3 Pek. Pas. Pondasi Pile Cap tipe PC2 800x2200x1000


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 15.84 1,327,775.82 21,031,968.99
- Besi D19-200 Mutu baja BJTD 40 (ulir) SNI kg 1,104.47 22,100.00 24,408,787.00
- Besi D22-160 Mutu baja BJTD 40 (ulir) SNI kg 1,821.64 22,100.00 40,258,244.00
- Bekisting Bekisting batako m2 54.00 237,572.13 12,828,894.97

4 Pek. Pas. Pondasi Pile Cap tipe PC3


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 7.36 1,327,775.82 9,772,430.04
- Besi D19-200 Mutu baja BJTD 40 (ulir) SNI kg 345.48 22,100.00 7,635,108.00
- Besi D22-160 Mutu baja BJTD 40 (ulir) SNI kg 571.79 22,100.00 12,636,559.00
- Bekisting Bekisting batako m2 15.22 237,572.13 3,615,847.80

5 Pek. Pas. Kolom K2 600x600


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 2.34 1,327,775.82 3,106,995.42
- Besi tulangan 24 D25 Mutu baja BJTD 40 (ulir) SNI kg 2,620.66 22,100.00 57,916,586.00
- Besi sengkang D10 - 100&150 Mutu baja BJTD 40 (ulir) SNI kg 112.61 22,100.00 2,488,681.00
- Besi ties 4D10 - 100&150 Mutu baja BJTD 40 (ulir) SNI kg 127.05 22,100.00 2,807,805.00
- Bekisting Bekisting batako m2 15.60 237,572.13 3,706,125.21

6 Pek. Pas. Kolom K4 400x400


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 0.16 1,327,775.82 212,444.13
- Besi tulangan 12 D19 Mutu baja BJTD 40 (ulir) SNI kg 116.46 22,100.00 2,573,766.00
- Besi sengkang D10 - 100&150 Mutu baja BJTD 40 (ulir) SNI kg 11.40 22,100.00 251,940.00
- Bekisting Bekisting batako m2 1.60 237,572.13 380,115.41

7 Pek. Pas. Tie beam TB1 400x800


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 30.56 1,327,775.82 40,576,829.06
- Besi tulangan 15 D25 Mutu baja BJTD 40 (ulir) SNI kg 3,854.87 22,100.00 85,192,627.00
- Besi tulangan 10 D25 Mutu baja BJTD 40 (ulir) SNI kg 2,569.91 22,100.00 56,795,011.00
- Besi tulangan 2 D13 Mutu baja BJTD 40 (ulir) SNI kg 199.03 22,100.00 4,398,563.00
- Besi Tulangan D10 - 100&150 Mutu baja BJTD 40 (ulir) SNI kg 1,346.99 22,100.00 29,768,479.00
- Bekisting Bekisting batako m2 152.80 237,572.13 36,301,021.31

8 Pek. Pas. Plat lantai S2 Elv.- 4.000 T.20cm


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 25.19 1,327,775.82 33,446,672.91
- Besi D10-200 Mutu baja BJTD 40 (ulir) SNI kg 2,229.97 22,100.00 49,282,337.00
- Waterproofing integral Waterproofing Crystaline WP System, Setara Fosroc, Sica kg 88.18 44,217.50 3,899,099.15

II.8.3 PEKERJAAN STRUKTUR S/D ELV. -0.150

19/21
NO URAIAN PEKERJAAN RKS & SPESIFIKASI TEKNIS SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

1 Pek. Pas. Kolom K2 600x600


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 15.25 1,327,775.82 20,248,581.26
- Besi tulangan 24 D25 Mutu baja BJTD 40 (ulir) SNI kg 925.07 22,100.00 20,444,047.00
- Besi sengkang D10 - 100&150 Mutu baja BJTP 24 (polos) SNI kg 539.97 22,100.00 11,933,337.00
- Besi ties 4D10 - 100&150 Mutu baja BJTD 40 (ulir) SNI kg 609.20 22,100.00 13,463,320.00
- Bekisting Bekisting multipleks m2 101.64 556,332.00 56,545,584.48
-
2 Pek. Pas. Kolom K4 400x400
- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 1.23 1,327,775.82 1,633,164.26
- Besi tulangan 12 D19 Mutu baja BJTD 40 (ulir) SNI kg 295.43 22,100.00 6,529,003.00
- Besi sengkang D10 - 100&150 Mutu baja BJTD 40 (ulir) SNI kg 64.61 22,100.00 1,427,881.00
- Bekisting Bekisting multipleks m2 12.32 556,332.00 6,854,010.24
-
3 Pek. Pas. Dinding Beton T.200mm
- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 63.64 1,327,775.82 84,499,653.18
- Wiremesh M10 (2 lapis) Wiremesh M8 (2 lapis) kg 3,468.41 20,091.89 69,686,925.69
- Standed Bar bh 318.00 9,591.40 3,050,065.20
- Bekisting batako m2 318.20 237,572.13 75,595,451.45
- Bekisting multipleks m2 318.20 556,332.00 177,024,842.40
- Waterproofing integral Waterproofing Crystaline WP System, Setara Fosroc, Sica kg 222.74 44,217.50 9,849,005.95
- Waterproofing coating Waterproofing Formdex Uniflex Cementitious Membrance ex Fosroc Sica m2 424.27 77,855.00 33,031,540.85
- Water stop m1 82.65 92,575.00 7,651,323.75

4 Pek. Pas. Balok B1 400x800


- Cor beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 36.54 1,327,775.82 48,516,928.46
- Besi tulangan 15 D25 Mutu baja BJTD 40 (ulir) SNI kg 4,509.47 22,100.00 99,659,287.00
- Besi tulangan 10 D25 Mutu baja BJTD 40 (ulir) SNI kg 3,006.31 22,100.00 66,439,451.00
- Besi tulangan 2 D13 Mutu baja BJTP 24 (polos) SNI kg 237.93 22,100.00 5,258,253.00
- Besi Tulangan D10 - 100&150 Mutu baja BJTP 24 (polos) SNI kg 1,603.21 22,100.00 35,430,941.00
- Bekisting Bekisting multipleks m2 182.68 556,332.00 101,630,729.76

5 Pek. Pas. Plat lantai S1 Elv. -0.150 T.14cm


- Cor Beton Cor beton Ready mix K-350, fc' : 31,20 Mpa m3 18.04 1,327,775.82 23,953,075.79
- Wiremesh M8 (2 lapis) Wiremesh M8 (2 lapis) kg 1,404.10 20,091.89 28,211,028.21
- Bekisting Bekisting multipleks m2 128.84 556,332.00 71,677,814.88
JUMLAH PEKERJAAN STRUKTUR RUANG POMPA 2,067,304,688.65

II.10 PEKERJAAN STRUKTUR SEPARATOR BEAM LIFT


1 Pek. Separator beam pit lift S/D Elv. -0,050
- Base plat T.10mm Besi baja SNI setara KS, Gunung Garuda, Lautan Steel kg 47.73 30,500.00 1,455,765.00
- Chemical bolt bh 96.00 43,125.00 4,140,000.00
- Besi IWF 200.100.5,5.8 Besi baja SNI setara KS, Gunung Garuda, Lautan Steel kg 166.14 33,500.00 5,565,690.00
- Plat pengaku Besi baja SNI setara KS, Gunung Garuda, Lautan Steel kg 31.78 30,500.00 969,290.00
- Pengecatan besi duco Cat besi duco m2 7.25 45,425.00 329,331.25

2 Pek. Separator beam S/D Elv. +3,950


- Base plat T.10mm Besi baja SNI setara KS, Gunung Garuda, Lautan Steel kg 47.73 30,500.00 1,455,765.00

20/21
NO URAIAN PEKERJAAN RKS & SPESIFIKASI TEKNIS SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

- Chemical bolt bh 96.00 43,125.00 4,140,000.00


- Besi IWF 200.100.5,5.8 Besi baja SNI setara KS, Gunung Garuda, Lautan Steel kg 166.14 33,500.00 5,565,690.00
- Plat pengaku Besi baja SNI setara KS, Gunung Garuda, Lautan Steel kg 31.78 30,500.00 969,290.00
- Pengecatan besi duco Cat besi duco m2 7.25 45,425.00 329,331.25

3 Pek. Separator beam S/D Elv. +7,950


- Base plat T.10mm Besi baja SNI setara KS, Gunung Garuda, Lautan Steel kg 47.73 30,500.00 1,455,765.00
- Chemical bolt bh 96.00 43,125.00 4,140,000.00
- Besi IWF 200.100.5,5.8 Besi baja SNI setara KS, Gunung Garuda, Lautan Steel kg 166.14 33,500.00 5,565,690.00
- Plat pengaku Besi baja SNI setara KS, Gunung Garuda, Lautan Steel kg 31.78 30,500.00 969,290.00
- Pengecatan besi duco Cat besi duco m2 7.25 45,425.00 329,331.25

4 Pek. Separator beam S/D Elv. +11,950


- Base plat T.10mm Besi baja SNI setara KS, Gunung Garuda, Lautan Steel kg 47.73 30,500.00 1,455,765.00
- Chemical bolt bh 96.00 43,125.00 4,140,000.00
- Besi IWF 200.100.5,5.8 Besi baja SNI setara KS, Gunung Garuda, Lautan Steel kg 166.14 33,500.00 5,565,690.00
- Plat pengaku Besi baja SNI setara KS, Gunung Garuda, Lautan Steel kg 31.78 30,500.00 969,290.00
- Pengecatan besi duco Cat besi duco m2 7.25 45,425.00 329,331.25

5 Pek. Separator beam S/D Elv. +15,950


- Base plat T.10mm Besi baja SNI setara KS, Gunung Garuda, Lautan Steel kg 47.73 30,500.00 1,455,765.00
- Chemical bolt bh 96.00 43,125.00 4,140,000.00
- Besi IWF 200.100.5,5.8 Besi baja SNI setara KS, Gunung Garuda, Lautan Steel kg 166.14 33,500.00 5,565,690.00
- Plat pengaku Besi baja SNI setara KS, Gunung Garuda, Lautan Steel kg 31.78 30,500.00 969,290.00
- Pengecatan besi duco Cat besi duco m2 7.25 45,425.00 329,331.25

6 Pek. Separator beam lifting hook


- Base plat T.12mm Besi baja SNI setara KS, Gunung Garuda, Lautan Steel kg 28.64 30,500.00 873,520.00
- Chemical bolt bh 48.00 43,125.00 2,070,000.00
- Besi HB 200.200.8.12 Besi baja SNI setara KS, Gunung Garuda, Lautan Steel kg 474.05 33,500.00 15,880,675.00
- Plat pengaku Besi baja SNI setara KS, Gunung Garuda, Lautan Steel kg 15.89 30,500.00 484,645.00
- Pengecatan besi duco Cat besi duco m2 11.91 45,425.00 541,011.75
JUMLAH PEKERJAAN STRUKTUR RUANG GENSET 82,150,233.00
JUMLA KESELURUHAN 18,381,184,347.80
PPN 11% 2,021,930,278.26
JUMLAH TOTAL 20,403,114,626.06
DIBULATKAN 20,403,000,000.00