Rab Jalan Poros 24 Randu Agung - Cilacap
Rab Jalan Poros 24 Randu Agung - Cilacap
5 5 5 5
Beton K-125 3
Plastik 0.1
Beton K-125
Jalan tanah (existing) Beton K-125 0.03
Pasir
0.05
Pasir
0.03
5.0 5.0
POTONGAN MEMANJANG
HARGA
JUMLAH TOTAL JUMLAH
No URAIAN VOLUME SAT. SATUAN
(Rp.) (Rp.)
(Rp.)
1 Bahan
1.1 Bekisting / Kayu Kelas III 0.90 m3 1,500,000 1,350,000
1.2 Paku 5-12 cm 8.00 kg 28,000 224,000
1.3 Pasir 72.00 m3 200,000 14,400,000
1.4 Semen 416.00 zak 112,000 46,592,000
1.5 Split 2/3 57.00 m3 350,000 19,950,000
1.6 Tanah Urug 39.00 m3 270,000 10,530,000
1.7 Pasir 27.00 m3 195,000 5,265,000
1.8 Plastik Cor 816.00 m2 3,000 2,448,000
Sub Total (1) 100,759,000
2 Alat
….......................... …..............................
5 5 B 5 5
GAMBAR RENCANA
DIGAMBAR OLEH
5 5 5 5
Plastik
BETON K-125
0.1
Pasir Urug
3
Bekisting
……………………………………………….
IIN SUMIRAT
Lembar Ke 2 Dari 3 Lembar