Diketahui: A = 40000 Ha
L Primer = 10 Km
Elevasi Lahan = + 4.0 m
Elevasi HWS = + 3.6 m
DM = 6 ltr/det.ha
S = 0.0001
n = 0.030
Elevasi LWS = +1.0 m
Ditanya: 1) Dimensi Saluran Primer b dan y?
2) Profil muka air saat LWS dan HWS?
4.000
3.500
3.000
2.500
Depth
2.000
1.500
1.000
0.500
0.000
0 1000 2000 3000 4000 5000 6000
Distance upstream
b) Profil muka air pada saat Pasang
x 3.6 A P E Sf S0-Sf Sf-S0 mean Delta E E again - should be same a
0 3.600 24.48 19.30 3.6490 0.0006 -0.0005
-0.0006 0.3546
625 3.500 23.45 18.85 3.5534 0.0007 -0.0006 4.0036
-0.0009 0.5606
1250 3.000 18.60 16.62 3.0849 0.0013 -0.0012 4.1140
-0.0018 1.1479
1875 2.500 14.25 14.38 2.6446 0.0026 -0.0025 4.2328
-0.0041 2.5868
2500 2.000 10.40 12.14 2.2714 0.0059 -0.0058 5.2314
-0.0111 6.9104
3125 1.500 7.05 9.91 2.0907 0.0164 -0.0163 9.1818
-0.0409 25.5758
3750 1.000 4.20 7.67 2.6643 0.0656 -0.0655 27.6665
-0.0504 31.5231
4375 1.200 5.28 8.57 2.2531 0.0355 -0.0354 34.1874
-0.0504 31.5231
5000 1.000 4.20 7.67 2.6643 0.0656 -0.0655 33.7761
-0.0328 20.4759
2.000
1.500
1.000
0.500
0.000
0 1000 2000 3000 4000 5000 6000
Distance upstream
2) Dik: A = 40 ha
L = 2 km
n = 0.030
s = 0.0001
Qdm = 6 ltr/det.ha
B = 2m
H tabat = 40 cm = 0.4 m
Dit: 1) y?
2) L aliran baik?
Yc
0.53 m 0.4 m
Dari ilustrasi gambar di atas jika aliran dari hulu diberikan penahan bangunan tabat maka
akan terjadi aliran balik backwater ke bagian hulu saluran. Analisa Backwater di bagian
hulu akan mengetahui panjang alian balik yang diperhitungkan sebagai berikut:
Yc = (q/g)0.333
Yc = (0.24/3)/(9.81)0.333
Yc = 0.113 m
Kedalaman aliran di atas bendung = 0.4 m + 0.113 m
= 0.513 m
Dengan menggunakan Standar Step Method maka diperoleh panjang aliran backwater
B Q S n Y A P R V Y+v2/2g Vm RM SM L
2.00 0.24 0.00 0.03 0.51 1.29 3.45 0.37 0.18 0.51 0.00
0.53 1.34 3.20 0.42 5.69 2.18 2.93 0.40 0.03 62.68