PNPM-Mandiri Perdesaan Ngawi 2009

DAFTAR HARGA SATUAN UNTUK PERENCANAAN

No URAIAN SATUAN HARGA


BAHAN
1 Batu Belah 15/20 m3 Rp 1,500,000
2 Pasir pasang m3 Rp 1,500,000
3 Semen Tonasa 50 kg zak Rp 80,000
4 Kayu Matoa 5/7 3m btg Rp 80,000
5 Paku Campur 2" - 5 " kg Rp 20,000
6 Plamir Tembok kg Rp 14,000
7 Cat Tembok Dasar kg Rp 50,000
8 Cat tembok penutup 2x kg Rp 70,000
9 Gate Valve 2" bh Rp 750,000
10 Double Nipple 2" bh Rp 50,000
11 Sochet 2" bh Rp 15,000
12 MTA 2' bh Rp 450,000
13 Pipa GIP 2" btg Rp 550,000
14 Ijuk kg Rp 25,000
15 Seal Tape bh Rp 30,000
16 Snay Pipa bh Rp 1,000,000
17 Kertas Gosok lbr Rp 15,000
18 Papan 3/20 200 lbr Rp 80,000

ALAT
1 Cangkul bh Rp 75,000
2 Sekop bh Rp 75,000
3 Parang bh Rp 85,000
4 Linggis bh Rp 75,000

ONGKOS ANGKUT
1 Angkut Bahan Lokal trip Rp 3,000,000
2 Angkut Bahan Toko trip Rp 3,000,000
UPAH
1 Pekerja Oh Rp 125,000
2 Tukang Oh Rp 150,000

Anam
PNPM-Mandiri Perdesaan Ngawi 2009

DATA PENDUKUNG LAINNYA


PROVINSI : Papua Barat
KABUPATEN : Pegunungan Arfak
Distrik : Taige
Kampung : Danhab
JENIS KEGIATAN : Penangkap Mata Air
Panjang 4
Kepala Dinas Pekerjaan Umum Ananias Dowansiba,SP.,MM
N.I.P NIP 197608132009091002
Koordinator KKM Arifin Iryo
FM WSS Herol Djili Kondororik
Sat Lak KKM Habel Towansiba
Tanggal 20 Desember 2018

Mohon diisi dari sini semua sudah LINK !!!


Panjang Bak Penagkap Mata Air 4
Tinggi PMA 0.8

Jumlah Angkutan berapa TRIP 3

Biaya Rp 25,689,000

Anam
PNPM-Mandiri Perdesaan Ngawi 2009

1
3

Anam
PERHITUNGAN VOLUME PEKERJAAN / TAKE OFF SHEET
PERHITUNGAN VOLUME Bangunan Penangkap Mata Air
No Uraian Panjang Lebar Tinggi Luas Volume

I PEKERJAAN PONDASI
1 Galian Pondasi Utama
4.00 0.60 0.80 0.48 1.92 m3
-
0,80

0,60

1.92 m3

2 Volume Urugan Pasir 4.00 0.60 0.20 0.12 0.48 m3

4 Pasangan Batu Kali Pondasi pokok

0,30

0,80
4.00 0.45 0.80 0.36 1.44 m3

0,6

0,60
4.00 0.70 0.60 0.42 1.68 m3

0,70

0,20 1.00 1.30 0.20 0.26 0.26 m3

1,30

0,20 1.00 0.50 0.20 0.10 0.10 m3

0,50

1.00 0.15 0.30 0.05 0.05 m3


0,30

TOS hal 4
PERHITUNGAN VOLUME PEKERJAAN / TAKE OFF SHEET
PERHITUNGAN VOLUME Bangunan Penangkap Mata Air
No Uraian Panjang Lebar Tinggi Luas Volume

Jumlah 3.53 m3

0,15

TOS hal 5
Rp 25,689,000

Volume Galian = 1.92 m3


Volume Timbunan = 0.48 m3
Volume Batu Kali = 3.53 m3
Luas Plester = 14.00 m2
Luas Pengecatan = 10.00 m2

TOS hal 6
ANALISA PERHITUNGAN
Harga sat. Bahan Upah Total
No Uraian Analisa Volume Kebutuhan
Rp. Rp Rp. Rp.
An. SNI 1 m2 Pembersihan Lapangan dan Peralatan
( Revisi )
6.8.1 Pekerja 0.1 6.0 m2 0.6 Oh 125,000 75,000 75,000
1 m' Pengukuran dan Pasang Papan Bowplank
An. SNI Kayu meranti 5/7 0.012 4.0 btg 0.0 btg 80,000 3,840 3,840
( Revisi )
6.4.1 Paku biasa 2" - 5 " 0.02 4.0 kg 0.1 kg 20,000 1,600 1,600
Kayu Papan 3/20 0.07 4.0 m' 0.3 m3 80,000 22,400 22,400
An. SNI Tukang Kayu 0.1 4.0 m' 0.4 Oh 150,000 60,000 60,000
( Revisi )
6.4.2 Pekerja 0.1 4.0 m' 0.4 Oh 125,000 50,000 50,000
An. SNI Galian Untuk Tanah Biasa sedalam 1 m
( Revisi )
6.1.1 Pekerja 0.4 1.9 m3 0.8 Oh 125,000 96,000 96,000
1 m3 Urugan
An. SNI
( Revisi ) Pekerja 0.192 0.5 m3 0.1 Oh 125,000 11,520 11,520
6.9.1 Pasir 1.1 0.5 m3 0.5 m3 1,500,000 792,000 792,000
1 m3 Pasang pondasi batu kali 1 Pc : 3 Ps
Batu belah ( 15/20 ) 1.1 3.5 m3 3.9 m3 1,500,000 5,816,250 5,816,250
An. SNI Semen porland 4.04 3.5 m3 14.2 zak 80,000 1,139,280 1,139,280
( Revisi )
6.8.1 Pasir pasang 0.485 3.5 m3 1.7 m3 1,500,000 2,564,438 2,564,438
Pekerja 1.5 3.5 m3 5.3 Oh 125,000 660,938 660,938
Tukang batu 0.6 3.5 m3 2.1 Oh 150,000 317,250 317,250

Analisa hal 7 dari 4 hal


RENCANA ANGGARAN BIAYA (RAB)
Kampung : Danhab No.Rab : 01/KKM-Danhab/2018
Distrik : Taige Program : PAMSIMAS
Kabupaten : Pegunungan Arfak Jenis. Keg : Penangkap Mata Air (PMA)
Provinsi : Papua Barat Volume : 1 Unit ( 1x1,5x0,8) m3

Volume Biaya (Rp)


Harga
URAIAN Kontribusi Masyarakat Satuan Satuan Kontribusi Masyarakat
Total APBDes BLM Total APBDes BLM
inCash inKind Rp inCash inKind
No 1 2=3+4+5 3 4 5 6 7 8=2x7 9=3x7 10=4x7 11 = 5x7
A BAHAN
1 Batu Belah 15/20 4.00 - 4.000 - 0.00 m3 1,500,000 6,000,000 - 6,000,000 - -
2 Pasir pasang 3.00 - 2.000 - 1.00 m3 1,500,000 4,500,000 - 3,000,000 - 1,500,000
3 Semen Tonasa 50 kg 17.00 - - - 17.00 zak 80,000 1,360,000 - - - 1,360,000
4 Kayu Matoa 5/7 3m 1.00 - - - 1.00 btg 80,000 80,000 - - - 80,000
5 Paku Campur 2" - 5 " 1.00 - - - 1.00 kg 20,000 20,000 - - - 20,000
6 Plamir Tembok 1.00 - - - 1.00 kg 14,000 14,000 - - - 14,000
7 Cat Tembok Dasar 1.00 - - - 1.00 kg 50,000 50,000 - - - 50,000
8 Cat tembok penutup 2x 3.00 - - - 3.00 kg 70,000 210,000 - - - 210,000
9 Gate Valve 2" 1.00 - - - 1.00 bh 750,000 750,000 - - - 750,000
10 Double Nipple 2" 1.00 - - - 1.00 bh 50,000 50,000 - - - 50,000
11 Sochet 2" 1.00 - - - 1.00 bh 15,000 15,000 - - - 15,000
12 MTA 2' 1.00 - 1.000 - 0.00 bh 450,000 450,000 - 450,000 - -
13 Pipa GIP 2" 1.00 - 1.000 - 0.00 btg 550,000 550,000 - 550,000 - -
14 Ijuk 2.00 - - - 2.00 kg 25,000 50,000 - - - 50,000
15 Seal Tape 1.00 - - - 1.00 bh 30,000 30,000 - - - 30,000
16 Snay Pipa 1.00 - - - 1.00 bh 1,000,000 1,000,000 - - - 1,000,000
17 Kertas Gosok 3.00 - - - 3.00 lbr 15,000 45,000 - - - 45,000
18 Papan 3/20 200 1.00 - - - 1.00 lbr 80,000 80,000 - - - 80,000
Jumlah Sub A 15,254,000 - 10,000,000 - 5,254,000
B ALAT
1 Cangkul 1.00 - - - 1.00 bh 75,000 75,000 - - - 75,000
2 Sekop 1.00 - - - 1.00 bh 75,000 75,000 - - - 75,000
3 Parang 1.00 - - - 1.00 bh 85,000 85,000 - - - 85,000
4 Linggis 1.00 - - - 1.00 bh 75,000 75,000 - - - 75,000
Jumlah Sub B 310,000 - - - 310,000
C ONGKOS ANGKUT
1 Angkut Bahan Lokal 3.00 - - - 3.00 trip 3,000,000 9,000,000 - - - 9,000,000
2 Angkut Bahan Toko 3.00 - - - 3.00 trip 3,000,000 9,000,000 - - - 9,000,000
Jumlah Sub C 18,000,000 - - - 18,000,000
D UPAH
1 Pekerja 11.00 - - - 11.00 Oh 125,000 1,375,000 - - - 1,375,000
2 Tukang 5.00 - - - 5.00 Oh 150,000 750,000 - - - 750,000
Jumlah Sub D 2,125,000 - - - 2,125,000
JUMLAH TOTAL (A+B+C+D) 35,689,000 - 10,000,000 - 25,689,000
Biaya inCash -
Biaya inKind 10,000,000
SUMBER DANA
Biaya APBDes -
Biaya BLM 25,689,000

Danhab, 18 Desember 2018


Disetujui Oleh : Dibuat Oleh :
Kepala Dinas Pekerjaan Umum Koord KKM FM WSS Sat Lak Pamsimas
Kabupaten Pegunungan Arfak

Ananias Dowansiba,SP.,MM Arifin Iryo Herol Djili Kondororik Habel Towansiba


NIP 197608132009091002
P.GIP 2' Penguras GAMBAR RENCANA

PROVINSI
PAPUA BARAT
TAMPAK DEPAN
KABUPATEN
: Pegunungan Arfak
A DISTRIK
: Taige
KAMPUNG
: Danhab
JENIS PRASARANA

: Penangkap Mata Air

JUDUL GAMBAR

TAMPAK DEPAN & ATAS


BANGUNAN PENANGKAP
P.GIP 2' Peluap P.GIP 2' Peluap MATA AIR
P.GIP 2' Outlet
Digambar Oleh
A
Arifin Iryo

Diperiksa dan Disetujui oleh :


TAMPAK ATAS
Herol Djili Kondororik

Lembar 1 Dari 3 Lembar


GAMBAR RENCANA

PROVINSI
0.30 PAPUA BARAT

P.GIP 2' Peluap KABUPATEN


: Pegunungan Arfak
DISTRIK
0.50 Pasangan Batu Kali 1 : 3 : Taige
Batu Kosong Gate Valve 2" KAMPUNG
0.80 0.15 Ijuk Double Nipple 2" : Danhab
P.GIP 2' Outlet Sochet 2"
MTA 2' JENIS PRASARANA
0.3 Pasangan Batu Kali 1 : 3 Pipa HDPE 2'
: Penangkap Mata Air
JUDUL GAMBAR
0.3 POTONGAN
0.20
BANGUNAN PENANGKAP
MATA AIR

1.3 0.3 0.5 0.6


Digambar Oleh

Arifin Iryo
Batu Kosong 20 cm
Pasir 15 cm Diperiksa dan Disetujui oleh :

0.6 Herol Djili Kondororik


0.7

GAMBAR POTONGAN A - A Lembar 2 Dari 3 Lembar


GAMBAR RENCANA

PROVINSI
PAPUA BARAT

KABUPATEN
: Pegunungan Arfak
DISTRIK
: Taige
KAMPUNG
: Danhab

JENIS PRASARANA

: Penangkap Mata Air


JUDUL GAMBAR

Jaringan Perpipaan

Digambar Oleh

Arifin Iryo

Diperiksa dan Disetujui oleh :

Herol Djili Kondororik

Lembar 3 Dari 3 Lembar