ADDENDUM VIII

Satker / PPK : Pelaksanaan Jalan Nasional Wilayah I Provinsi Papua (Jayapura) / PPK 1.5 Provinsi Papua
Nama Paket : PRESERVASI JALAN YETTI-SENGGI-MAMBERAMO II (MYC)
Prop / Kab / Kodya : Papua / Kab. Keerom
No. Kontrak : HK 02.01/PRESERVASI-YSM II (MYC)/PPK 1.5/10
Tgl. Kontrak : 11 DESEMBER 2020
No. Kontrak Addendum I : HK 02.01/PRESERVASI-YSM II (MYC)/PPK 1.5/ADD-I/10.A
Tgl. Kontrak Addendum I : 16 DESEMBER 2020
No. Kontrak Addendum II : HK 02.01/PRESERVASI-YSM II (MYC)/PPK 1.5/ADD-II/10.B
Tgl. Kontrak Addendum II : 18 JANUARI 2021
No. Kontrak Addendum III : HK 02.01/PRESERVASI-YSM II (MYC)/PPK 1.5/ADD-III/10.C
Tgl. Kontrak Addendum III : 11 OKTOBER 2021
No. Kontrak Addendum IV : HK 02.01/PRESERVASI-YSM II (MYC)/PPK 1.5/ADD-IV/10.D
Tgl. Kontrak Addendum IV : 29 NOVEMBER 2021
No. Kontrak Addendum V : HK 02.01/PRESERVASI-YSM II (MYC)/PPK 1.5/ADD-V/10.E
Tgl. Kontrak Addendum V : 11 APRIL 2022
No. Kontrak Addendum VI : HK 02.01/PRESERVASI-YSM II (MYC)/PPK 1.5/ADD-VI/10.F
Tgl. Kontrak Addendum VI : 28 APRIL 2022
No. Kontrak Addendum VII : HK 02.01/PRESERVASI-YSM II (MYC)/PPK 1.5/ADD-VII/10.G
Tgl. Kontrak Addendum VII : 27 MEI 2022
Penyedia Jasa : PT. NINDYA KARYA (PERSERO)
Konsultan Supervisi : PT.YODYA KARYA (PERSERO) KSO PT.CAKRA BUANA

DIVISI 1. UMUM

REKAPITULASI PERHITUNGAN

Mata
Uraian Pekerjaan Satuan Volume
Pembayaran

1.21 MANAJEMEN MUTU Ls 1.00

Disetujui Oleh, Diperiksa Oleh, Diajukan Oleh,


PPK 1.5 PROVINSI PAPUA KONSULTAN SUPERVISI PENYEDIA JASA
PRESERVASI JALAN YETTI-SENGGI-MAMBERAMO II (MYC) PT. YODYA KARYA (Persero) PT. NINDYA KARYA (Persero)
PROVINSI PAPUA (JAYAPURA) KSO PT.CAKRA BUANA TOTAL MANDIRI KONSULTAN

SUGIHARTO, ST Ir. RAJAEDDIN RACHMAN, MT. YAN ANANTA TOMAZYA


NIP : 19690528 199203 1 014 SITE SUPERVISION ENGINEER PROJECT MANAGER
RINCIAN PERHITUNGAN
ANALISA HARGA MANAJEMEN MUTU
Satker / PPK : Pelaksanaan Jalan Nasional Wilayah I Provinsi Papua (Jayapura) / PPK 1.5 Provinsi Papua
Nama Paket : PRESERVASI JALAN YETTI-SENGGI-MAMBERAMO II (MYC)
Prop / Kab / Kodya : Papua / Kab. Keerom
No. Kontrak : HK 02.01/PRESERVASI-YSM II (MYC)/PPK 1.5/10
Tgl. Kontrak : 11 DESEMBER 2020
No. Kontrak Addendum I : HK 02.01/PRESERVASI-YSM II (MYC)/PPK 1.5/ADD-I/10.A
Tgl. Kontrak Addendum I : 16 DESEMBER 2020
No. Kontrak Addendum II : HK 02.01/PRESERVASI-YSM II (MYC)/PPK 1.5/ADD-II/10.B
Tgl. Kontrak Addendum II : 18 JANUARI 2021
No. Kontrak Addendum III : HK 02.01/PRESERVASI-YSM II (MYC)/PPK 1.5/ADD-III/10.C
Tgl. Kontrak Addendum III : 11 OKTOBER 2021
No. Kontrak Addendum IV : HK 02.01/PRESERVASI-YSM II (MYC)/PPK 1.5/ADD-IV/10.D
Tgl. Kontrak Addendum IV : 29 NOVEMBER 2021
No. Kontrak Addendum V : HK 02.01/PRESERVASI-YSM II (MYC)/PPK 1.5/ADD-V/10.E
Tgl. Kontrak Addendum V : 11 APRIL 2022
No. Kontrak Addendum VI : HK 02.01/PRESERVASI-YSM II (MYC)/PPK 1.5/ADD-VI/10.F
Tgl. Kontrak Addendum VI : 28 APRIL 2022
No. Kontrak Addendum VII : HK 02.01/PRESERVASI-YSM II (MYC)/PPK 1.5/ADD-VII/10.G
Tgl. Kontrak Addendum VII : 27 MEI 2022
Penyedia Jasa : PT. NINDYA KARYA (PERSERO)
Konsultan Supervisi : PT.YODYA KARYA (PERSERO) KSO PT.CAKRA BUANA

KONTRAK AWAL MC-0 SELISIH VOLUME SELISIH JUMLAH HARGA


No. URAIAN SATUAN VOLUME Harga Satuan Jumlah Harga VOLUME Harga Satuan Jumlah Harga TAMBAH KURANG KETERANGAN
TAMBAH KURANG
(Rp.) (Rp.) (Rp.) (Rp.) (Rp.) (Rp.)

A. DATA DAN ASUMSI

1 Tidak ada pengadaan peralatan pengujian mutu dan


perlengkapan perangkat alat tulis dan kantor
2 Hanya Jasa Pengendalian Mutu Pekerjaan dilapangan
selama masa pelaksanaan pekerjaan
3 Personil melakukan pengendalian mutu berdasarkan spesifikasi
pekerjaan dan membuat laporan mutu pekerjaan
4 Manajemen Mutu sesuai ketentuan Ditjen Bina Marga

B. URUTAN KERJA
1 Penyedia setelah menerima SPMK mengusulkan personil
Tenaga Ahli Mutu Pekerjaan sbg Manajer Kendali Mutu
2 Tenaga Ahli dibantu oleh Asisten Kendali Mutu yang
berpengalaman dibidangnya dan tenaga pendukung
3 Membuat RMK dan laporan mutu yg disetujui PPK
4 Melakukan pengendalian mutu semua pekerjaan dan
membuat laporan secara berkala

Hal. 2
KONTRAK AWAL MC-0 SELISIH VOLUME SELISIH JUMLAH HARGA
No. URAIAN SATUAN VOLUME Harga Satuan Jumlah Harga VOLUME Harga Satuan Jumlah Harga TAMBAH KURANG KETERANGAN
TAMBAH KURANG
(Rp.) (Rp.) (Rp.) (Rp.) (Rp.) (Rp.)

C. TENAGA / PERSONIL
Masa Pelaksanaan Pekerjaan Bulan 18 18
1 Ahli Kendali Mutu OB 18 13,000,000.00 234,000,000.00 18 13,000,000.00 234,000,000.00 - - - - Tetap
2 Asisten Ahli Kendali Mutu OB 18 7,000,000.00 126,000,000.00 18 7,000,000.00 126,000,000.00 - - - - Tetap
3 Staff Pendukung (supporting Staff) OB 18 5,000,000.00 90,000,000.00 18 5,000,000.00 90,000,000.00 - - - - Tetap
4 Laporan Kendali Mutu Buah 18 2,500,000.00 45,000,000.00 18 2,500,000.00 45,000,000.00 - - - - Tetap

D. TOTAL BIAYA MANAJEMEN MUTU LS 1.00 495,000,000.00 495,000,000.00

Disetujui Oleh, Diperiksa Oleh, Dibuat Oleh,


KOORDINATOR PENGAWAS LAPANGAN KONSULTAN SUPERVISI PENYEDIA JASA
PPK 1.5 PROVINSI PAPUA PT. YODYA KARYA (Persero) PT. NINDYA KARYA (Persero)
PROVINSI PAPUA (JAYAPURA)

JOHN MERAUDJE Ir. MUHAMMAD NAJIB AZIS SOPHIAN BADOLLAHI


NIP : 19660810 201410 1 001 QUANTITY ENGINEER SITE ENGINEER MANAGER

Hal. 3