Anda di halaman 1dari 18

PEMERINTAH DAERAH KABUPATEN JENEPONTO

BADAN PENANGGULANGAN BENCANA DAERAH

AS BUILT DRAWING
REKONSTRUKSI TALUD SUNGAI PAPPALLUANG
DESA PAPPALLUANG KEC. BANGKALA BARAT

BPBD KABUPATEN JENEPONTO


TAHUN ANGGARAN 2020

KONSULTAN PENGAWAS KONTRAKTOR PELAKSANA


CV. DAYA AMALIA CONSULTANT CV. ARYA GRAHA PUTRATAMA
PEMERINTAH DAERAH KABUPATEN JENEPONTO
BADAN PENANGGULANGAN BENCANA DAERAH
JL. DRS. H. RADJAMILO, MP. KEL. EMPOANG,
KEC. BINAMU, KABUPATEN JENEPONTO

PEKERJAAN
REKONSTRUKSI TALUD
SUNGAI PAPPALLUANG
DESA PAPPALLUANG
KEC. BANGKALA BARAT
DIBUAT OLEH :
KONTRAKTOR PELAKSANA
CV. ARYA GRAHA PUTRATAMA

AMIR HAMZAH
DIREKTUR

DIPERIKSA OLEH :
DETAIL TYPICAL 1 KONSULTAN PENGAWAS
Scale 1:100 CV. DAYA AMALIA CONSULTANT
STA 0+000 S/D STA 0+107.6
STA 0+162,5 S/D STA 0+320 DET. PAS. PROTEKSI
STA 0+391 S/D STA 0+410 Scale 1:50

ST. ZACHRA, SE
DIREKTRIS

DIPERIKSA OLEH :
PENGAWAS TEKNIK

H. BAHARUDDIN M, SE
NIP. 19650519 199103 1 011

DIPERIKSA/DISETUJUI OLEH :
PEJABAT PEMBUAT KOMITMEN (PPK)

FADLI ARFANDI THAYEB, ST., M.Si


NIP. 19800320 200604 1 008

NO. PAKET
DETAIL TYPICAL 2 NO. RUAS
Scale 1:100 KABUPATEN JENEPONTO
STA 0+068.6 S/D STA 0+107.6 PROPINSI SULAWESI SELATAN

STA 0+320 S/D STA 0+391 AS BUILT DRAWING


STA 0+410 S/D STA 0+449,5
DETAIL TYPICAL TALUD
DET. PAS. PROTEKSI DETAIL PAS. PROTEKSI
Scale 1:50
NO. LEMBAR 03
JML. LEMBAR 17 LEMBAR
SKALA 1 : 100 ; 1 : 50
TANGGAL
KETERANGAN
PEMERINTAH DAERAH KABUPATEN JENEPONTO
BADAN PENANGGULANGAN BENCANA DAERAH
JL. DRS. H. RADJAMILO, MP. KEL. EMPOANG,
KEC. BINAMU, KABUPATEN JENEPONTO

PEKERJAAN
REKONSTRUKSI TALUD
SUNGAI PAPPALLUANG
DESA PAPPALLUANG
KEC. BANGKALA BARAT
DIBUAT OLEH :
KONTRAKTOR PELAKSANA
CV. ARYA GRAHA PUTRATAMA

AMIR HAMZAH
DIREKTUR

DIPERIKSA OLEH :
KONSULTAN PENGAWAS
CV. DAYA AMALIA CONSULTANT

BRONJONG 7 SUSUN BRONJONG 6 SUSUN


STA 0+114,1 S/D 0+121,1 PANJANG 21 MTR STA 0+121,1 S/D 0+162,5 PANJANG 27,5 MTR
ST. ZACHRA, SE
DIREKTRIS

DIPERIKSA OLEH :

TYPICAL BRONJONG (KIRI) PENGAWAS TEKNIK

Scale 1:50

H. BAHARUDDIN M, SE
NIP. 19650519 199103 1 011

DIPERIKSA/DISETUJUI OLEH :
PEJABAT PEMBUAT KOMITMEN (PPK)

FADLI ARFANDI THAYEB, ST., M.Si


NIP. 19800320 200604 1 008

NO. PAKET
NO. RUAS
KABUPATEN JENEPONTO
PROPINSI SULAWESI SELATAN
STA 0+114 BRONJONG 3 SUSUN AS BUILT DRAWING
S/D 0+152 PANJANG 8 MTR
DETAIL BRONJONG

TYPICAL BRONJONG (KANAN) NO. LEMBAR 04


Scale 1:50 JML. LEMBAR 17 LEMBAR
SKALA 1 : 50
TANGGAL
KETERANGAN
STATION
TALUD SUNGAI (KIRI) PEMERINTAH DAERAH KABUPATEN JENEPONTO
BADAN PENANGGULANGAN BENCANA DAERAH
JL. DRS. H. RADJAMILO, MP. KEL. EMPOANG,
TINGGI TALUD (KIRI) KEC. BINAMU, KABUPATEN JENEPONTO

PEKERJAAN
REKONSTRUKSI TALUD
STATION SUNGAI PAPPALLUANG
DESA PAPPALLUANG
TALUD SUNGAI (KANAN) KEC. BANGKALA BARAT
DIBUAT OLEH :
TINGGI TALUD (KANAN)
KONTRAKTOR PELAKSANA
CV. ARYA GRAHA PUTRATAMA

STATION
AMIR HAMZAH
CRIB BRONJONG (KIRI) DIREKTUR

DIPERIKSA OLEH :
JUMLAH BRONJONG (KIRI)
KONSULTAN PENGAWAS
CV. DAYA AMALIA CONSULTANT

CRIB BRONJONG (KANAN)

JUMLAH BRONJONG (KANAN)


ST. ZACHRA, SE
ARAH HULU/HILIR ARAH HULU ARAH HILIR DIREKTRIS

DIPERIKSA OLEH :
PENGAWAS TEKNIK
STATION
TALUD SUNGAI (KIRI)
H. BAHARUDDIN M, SE
TINGGI TALUD (KIRI) NIP. 19650519 199103 1 011

SEGMENTASI PENANGANAN DIPERIKSA/DISETUJUI OLEH :


STATION Scale 1 : 50
PEJABAT PEMBUAT KOMITMEN (PPK)

TALUD SUNGAI (KANAN)

TINGGI TALUD (KANAN)


FADLI ARFANDI THAYEB, ST., M.Si
NIP. 19800320 200604 1 008

STATION NO. PAKET


NO. RUAS
KABUPATEN JENEPONTO
CRIB BRONJONG (KIRI)
PROPINSI SULAWESI SELATAN

AS BUILT DRAWING
JUMLAH BRONJONG (KIRI)

SEGEMENTASI PENANGANAN
CRIB BRONJONG (KANAN)

JUMLAH BRONJONG (KANAN) NO. LEMBAR 02


JML. LEMBAR 17 LEMBAR
ARAH HULU/HILIR ARAH HILIR
SKALA 1 : 50
TANGGAL
KETERANGAN
U

AKHIR PROYEK
STA 0+540 PEMERINTAH DAERAH KABUPATEN JENEPONTO
BADAN PENANGGULANGAN BENCANA DAERAH
JL. DRS. H. RADJAMILO, MP. KEL. EMPOANG,
KEC. BINAMU, KABUPATEN JENEPONTO

PEKERJAAN
REKONSTRUKSI TALUD
0 30 60 100 1200 2000 m
SUNGAI PAPPALLUANG
SCALE , 1 : 1500
DESA PAPPALLUANG
STA
0+540 KEC. BANGKALA BARAT
A
ST 525
0+
DIBUAT OLEH :
KONTRAKTOR PELAKSANA
CV. ARYA GRAHA PUTRATAMA

0+ STA
0
50
0+ STA
5
47
AMIR HAMZAH
DIREKTUR

0+450
STA
DIPERIKSA OLEH :

42 A
5
0+ ST
KONSULTAN PENGAWAS
CV. DAYA AMALIA CONSULTANT
STA STA
5
0+325 0+37
A
ST 00
0+4

STA
STA
0+300

0+ TA
5
27
0+350

S
ST. ZACHRA, SE
DIREKTRIS

0+ TA
0
DIPERIKSA OLEH :

25
S
PENGAWAS TEKNIK
25
0+2 A
ST

0+200
STA

H. BAHARUDDIN M, SE
NIP. 19650519 199103 1 011
0+175
STA

DIPERIKSA/DISETUJUI OLEH :
STA
5
0+12
PEJABAT PEMBUAT KOMITMEN (PPK)

STA
0+150
0+100
STA

0+075

FADLI ARFANDI THAYEB, ST., M.Si


STA

ST
0+-0 A
50 NIP. 19800320 200604 1 008

ST
0+-0 A
NO. PAKET
0
0+05A

75
ST

ST
0+0 A
00
NO. RUAS
ST
0+-0 A
25
KABUPATEN JENEPONTO

STA
0+025
PETA SITUASI PROPINSI SULAWESI SELATAN

AS BUILT DRAWING
Scale 1:2000

PETA SITUASI

AWAL PROYEK NO. LEMBAR 01


STA 0+000 JML. LEMBAR 17 LEMBAR
SKALA 1 : 2000
TANGGAL
KETERANGAN
-11 -10 -9 -8 -7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11
STA 0+000
197
KETERANGAN
PEMERINTAH DAERAH KABUPATEN JENEPONTO
Rencana : 196 BADAN PENANGGULANGAN BENCANA DAERAH
Existing :
JL. DRS. H. RADJAMILO, MP. KEL. EMPOANG,
Timbunan :
KEC. BINAMU, KABUPATEN JENEPONTO
195
Galian : PEKERJAAN
CATATAN REKONSTRUKSI TALUD
194
SUNGAI PAPPALLUANG
DESA PAPPALLUANG
193 KEC. BANGKALA BARAT
SKALA VERTIKAL 1 : 100 DIBUAT OLEH :
SKALA HORIZONTAL 1 : 100
192
JARAK KONTRAKTOR PELAKSANA
150 CV. ARYA GRAHA PUTRATAMA

193.500
195.900
194.300

193.575
ELEVASI

AMIR HAMZAH
DIREKTUR

-11 -10 -9 -8 -7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11
STA 0+025 DIPERIKSA OLEH :
195 KONSULTAN PENGAWAS
KETERANGAN CV. DAYA AMALIA CONSULTANT

Rencana : KEBUN KEBUN 194


Existing :

Timbunan :

193
Galian :
ST. ZACHRA, SE
CATATAN DIREKTRIS
192
DIPERIKSA OLEH :
191 PENGAWAS TEKNIK

SKALA VERTIKAL 1 : 100


SKALA HORIZONTAL 1 : 100
190
JARAK 150
H. BAHARUDDIN M, SE
192.500
195.050
193.300

193.863
NIP. 19650519 199103 1 011
ELEVASI
DIPERIKSA/DISETUJUI OLEH
DIPERIKSA/DISETUJUI :
OLEH :
PEJABAT PEMBUAT KOMITMEN (PPK)

-11 -10 -9 -8 -7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11
STA 0+050
195
KETERANGAN
KEBUN
Rencana :
KEBUN 194 FADLI ARFANDI THAYEB, ST., M.Si
Existing :
NIP. 19800320 200604 1 008
Timbunan :

193 NO. PAKET


Galian :
NO. RUAS
CATATAN
192 KABUPATEN JENEPONTO
PROPINSI SULAWESI SELATAN

191 AS BUILT DRAWING


SKALA VERTIKAL 1 : 100
CROSS SECTION
SKALA HORIZONTAL 1 : 100
190
JARAK
STA 0+000 - STA 0+050
175
192.720
192.000
194.950

193.000

ELEVASI
NO. LEMBAR 05
JML. LEMBAR 17 LEMBAR
SKALA 1 : 100
TANGGAL
KETERANGAN
-11 -10 -9 -8 -7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11
STA 0+075
195
KETERANGAN

PEMERINTAH DAERAH KABUPATEN JENEPONTO


Rencana : 194 BADAN PENANGGULANGAN BENCANA DAERAH
Existing :

Timbunan : JL. DRS. H. RADJAMILO, MP. KEL. EMPOANG,


KEC. BINAMU, KABUPATEN JENEPONTO
193
Galian :
PEKERJAAN
CATATAN
192 REKONSTRUKSI TALUD
SUNGAI PAPPALLUANG
DESA PAPPALLUANG
191 KEC. BANGKALA BARAT
SKALA VERTIKAL 1 : 100
DIBUAT OLEH :
SKALA HORIZONTAL 1 : 100
190
JARAK 175 175 KONTRAKTOR PELAKSANA
CV. ARYA GRAHA PUTRATAMA

192.353
191.500
194.550

192.500

192.500

194.350
191.500
ELEVASI

AMIR HAMZAH
DIREKTUR
-11 -10 -9 -8 -7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11
STA 0+100 DIPERIKSA OLEH :
195
KONSULTAN PENGAWAS
KETERANGAN
CV. DAYA AMALIA CONSULTANT
Rencana : KEBUN 194
Existing :

Timbunan :

193
Galian :
ST. ZACHRA, SE
CATATAN
192 DIREKTRIS

DIPERIKSA OLEH :
191 PENGAWAS TEKNIK

SKALA VERTIKAL 1 : 100


SKALA HORIZONTAL 1 : 100
190
JARAK 175 175
191.000
194.070

192.000

192.000

193.670
191.000
192.203
H. BAHARUDDIN M, SE
NIP. 19650519 199103 1 011
ELEVASI

DIPERIKSA/DISETUJUI OLEH :
PEJABAT PEMBUAT KOMITMEN (PPK)
-11 -10 -9 -8 -7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11
STA 0+125
196
KETERANGAN

Rencana : 195 FADLI ARFANDI THAYEB, ST., M.Si


Existing :
NIP. 19800320 200604 1 008
Timbunan :

194 NO. PAKET


Galian :
NO. RUAS
CATATAN
193 KABUPATEN JENEPONTO
PROPINSI SULAWESI SELATAN

192 AS BUILT DRAWING


SKALA VERTIKAL 1 : 100
SKALA HORIZONTAL 1 : 100
191 CROSS SECTION
JARAK 200 100
STA 0+075 - STA 0+125
195.500

192.000

192.500

192.500

192.000
193.500
192.054

ELEVASI NO. LEMBAR 06


JML. LEMBAR 17 LEMBAR
SKALA 1 : 100
TANGGAL
KETERANGAN
-11 -10 -9 -8 -7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11
STA 0+150
KETERANGAN 194 PEMERINTAH DAERAH KABUPATEN JENEPONTO
Rencana :
BADAN PENANGGULANGAN BENCANA DAERAH
Existing : JL. DRS. H. RADJAMILO, MP. KEL. EMPOANG,
Timbunan :
193 KEC. BINAMU, KABUPATEN JENEPONTO

Galian :
PEKERJAAN
192 REKONSTRUKSI TALUD
CATATAN
SUNGAI PAPPALLUANG
191 DESA PAPPALLUANG
KEC. BANGKALA BARAT

SKALA VERTIKAL 1 : 100


190 DIBUAT OLEH :
SKALA HORIZONTAL 1 : 100
KONTRAKTOR PELAKSANA
JARAK 200 CV. ARYA GRAHA PUTRATAMA

193.000

190.000

190.500

191.335
ELEVASI
AMIR HAMZAH
DIREKTUR

-11 -10 -9 -8 -7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 194 DIPERIKSA OLEH :


STA 0+175 KONSULTAN PENGAWAS
CV. DAYA AMALIA CONSULTANT
KETERANGAN 193
Rencana :
Existing :

Timbunan :
192
KEBUN
Galian : ST. ZACHRA, SE
191 DIREKTRIS
CATATAN
DIPERIKSA OLEH :
190
PENGAWAS TEKNIK

SKALA VERTIKAL 1 : 100


189
SKALA HORIZONTAL 1 : 100

JARAK 175
H. BAHARUDDIN M, SE
189.500
192.870

190.500

190.382
NIP. 19650519 199103 1 011
ELEVASI
DIPERIKSA/DISETUJUI OLEH :
PEJABAT PEMBUAT KOMITMEN (PPK)

-11 -10 -9 -8 -7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11
STA 0+200
KETERANGAN 192
FADLI ARFANDI THAYEB, ST., M.Si
Rencana :
Existing : NIP. 19800320 200604 1 008
Timbunan :
191
KEBUN NO. PAKET
Galian : NO. RUAS
190
KABUPATEN JENEPONTO
CATATAN
PROPINSI SULAWESI SELATAN
189
AS BUILT DRAWING

SKALA VERTIKAL 1 : 100


188 CROSS SECTION
SKALA HORIZONTAL 1 : 100
STA 0+150 - STA 0+200
JARAK 200
188.500

192.350

189.500

189.580

NO. LEMBAR 07
ELEVASI
JML. LEMBAR 17 LEMBAR
SKALA 1 : 100
TANGGAL
KETERANGAN
-11 -10 -9 -8 -7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11
STA 0+225
192
KETERANGAN
PEMERINTAH DAERAH KABUPATEN JENEPONTO
Rencana : 191 BADAN PENANGGULANGAN BENCANA DAERAH
Existing : JL. DRS. H. RADJAMILO, MP. KEL. EMPOANG,
KEC. BINAMU, KABUPATEN JENEPONTO
Timbunan :
KEBUN
190 PEKERJAAN
Galian :

REKONSTRUKSI TALUD
CATATAN
189 SUNGAI PAPPALLUANG
DESA PAPPALLUANG
188 KEC. BANGKALA BARAT

SKALA VERTIKAL 1 : 100 DIBUAT OLEH :


SKALA HORIZONTAL 1 : 100
187
KONTRAKTOR PELAKSANA
JARAK 200 CV. ARYA GRAHA PUTRATAMA

187.500
191.350

188.500

188.903
ELEVASI
AMIR HAMZAH
DIREKTUR

-11 -10 -9 -8 -7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 DIPERIKSA OLEH :


STA 0+250 KONSULTAN PENGAWAS
CV. DAYA AMALIA CONSULTANT
KETERANGAN 191
Rencana :
Existing :

Timbunan :
190
KEBUN
Galian : ST. ZACHRA, SE
189 DIREKTRIS
CATATAN
DIPERIKSA OLEH :
188
PENGAWAS TEKNIK

SKALA VERTIKAL 1 : 100


187
SKALA HORIZONTAL 1 : 100

JARAK 200
H. BAHARUDDIN M, SE

188.137
187.000
190.750

188.000

NIP. 19650519 199103 1 011


ELEVASI
DIPERIKSA/DISETUJUI OLEH :
PEJABAT PEMBUAT KOMITMEN (PPK)

-11 -10 -9 -8 -7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11
STA 0+275
191
KETERANGAN
FADLI ARFANDI THAYEB, ST., M.Si
Rencana :
SAWAH 190 NIP. 19800320 200604 1 008
Existing :

Timbunan :
NO. PAKET
189
Galian : NO. RUAS
KABUPATEN JENEPONTO
CATATAN
188 PROPINSI SULAWESI SELATAN

187 AS BUILT DRAWING

SKALA VERTIKAL 1 : 100 CROSS SECTION


SKALA HORIZONTAL 1 : 100
186 STA 0+225 - STA 0+275
JARAK 200
186.500
190.050

187.500

187.618

NO. LEMBAR 08
ELEVASI
JML. LEMBAR 17 LEMBAR
SKALA 1 : 100
TANGGAL
KETERANGAN
-11 -10 -9 -8 -7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11
STA 0+300
KETERANGAN 190
PEMERINTAH DAERAH KABUPATEN JENEPONTO
Rencana : BADAN PENANGGULANGAN BENCANA DAERAH
Existing :
189 JL. DRS. H. RADJAMILO, MP. KEL. EMPOANG,
Timbunan : KEC. BINAMU, KABUPATEN JENEPONTO

Galian : PEKERJAAN
188
CATATAN
REKONSTRUKSI TALUD
SUNGAI PAPPALLUANG
187 DESA PAPPALLUANG
KEC. BANGKALA BARAT
186
SKALA VERTIKAL 1 : 100 DIBUAT OLEH :
SKALA HORIZONTAL 1 : 100

JARAK KONTRAKTOR PELAKSANA


200 CV. ARYA GRAHA PUTRATAMA

187.158
186.500
190.100

187.500
ELEVASI

AMIR HAMZAH
DIREKTUR

-11 -10 -9 -8 -7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 DIPERIKSA OLEH :


STA 0+325
KONSULTAN PENGAWAS
KETERANGAN 189 CV. DAYA AMALIA CONSULTANT

Rencana :
Existing :

Timbunan :
188

Galian :
187 ST. ZACHRA, SE
CATATAN
DIREKTRIS

186 DIPERIKSA OLEH :


PENGAWAS TEKNIK

SKALA VERTIKAL 1 : 100


185
SKALA HORIZONTAL 1 : 100

JARAK 200 150


H. BAHARUDDIN M, SE

186.463
185.500
189.040

186.500

186.000
188.300
186.000
NIP. 19650519 199103 1 011
ELEVASI
DIPERIKSA/DISETUJUI OLEH :
PEJABAT PEMBUAT KOMITMEN (PPK)

-11 -10 -9 -8 -7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11
STA 0+350
189
KETERANGAN
FADLI ARFANDI THAYEB, ST., M.Si
Rencana : 188
Existing :
NIP. 19800320 200604 1 008
Timbunan :

187 NO. PAKET


Galian :
NO. RUAS
CATATAN
186 KABUPATEN JENEPONTO
PROPINSI SULAWESI SELATAN

185 AS BUILT DRAWING


SKALA VERTIKAL 1 : 100
CROSS SECTION
SKALA HORIZONTAL 1 : 100
184 STA 0+300 - STA 0+350
JARAK 200 150
185.000
187.500
185.000
185.000
188.650

186.000

185.947

NO. LEMBAR 09
ELEVASI
JML. LEMBAR 17 LEMBAR
SKALA 1 : 100
TANGGAL
KETERANGAN
-11 -10 -9 -8 -7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11
STA 0+375
189
KETERANGAN

PEMERINTAH DAERAH KABUPATEN JENEPONTO


Rencana : 188 BADAN PENANGGULANGAN BENCANA DAERAH
Existing :

Timbunan : JL. DRS. H. RADJAMILO, MP. KEL. EMPOANG,


KEC. BINAMU, KABUPATEN JENEPONTO
187
Galian :
PEKERJAAN
CATATAN
186 REKONSTRUKSI TALUD
SUNGAI PAPPALLUANG
DESA PAPPALLUANG
185 KEC. BANGKALA BARAT
SKALA VERTIKAL 1 : 100
DIBUAT OLEH :
SKALA HORIZONTAL 1 : 100
184
JARAK 200 150 KONTRAKTOR PELAKSANA
CV. ARYA GRAHA PUTRATAMA

185.406
184.500
188.140

185.500

186.000
187.500
185.000
ELEVASI

AMIR HAMZAH
DIREKTUR
-11 -10 -9 -8 -7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11
STA 0+400 DIPERIKSA OLEH :
188
KONSULTAN PENGAWAS
KETERANGAN
CV. DAYA AMALIA CONSULTANT
Rencana
Existing
:
:
187
Timbunan :

186
Galian :
ST. ZACHRA, SE
CATATAN DIREKTRIS
185
DIPERIKSA OLEH :
184 PENGAWAS TEKNIK

SKALA VERTIKAL 1 : 100


SKALA HORIZONTAL 1 : 100
183
JARAK 175
184.000
187.550

185.000

184.942
H. BAHARUDDIN M, SE
NIP. 19650519 199103 1 011
ELEVASI

DIPERIKSA/DISETUJUI OLEH :
PEJABAT PEMBUAT KOMITMEN (PPK)
-11 -10 -9 -8 -7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11
STA 0+425
KETERANGAN 187
Rencana : FADLI ARFANDI THAYEB, ST., M.Si
Existing :
186 NIP. 19800320 200604 1 008
Timbunan :

NO. PAKET
Galian :
185 NO. RUAS
CATATAN
KABUPATEN JENEPONTO
184 PROPINSI SULAWESI SELATAN

AS BUILT DRAWING
SKALA VERTIKAL 1 : 100
183
SKALA HORIZONTAL 1 : 100 CROSS SECTION
JARAK 175 175
STA 0+375- STA 0+425
184.500
183.500
187.200

184.500
186.950

183.500
184.382

ELEVASI NO. LEMBAR 10


JML. LEMBAR 17 LEMBAR
SKALA 1 : 100
TANGGAL
KETERANGAN
-11 -10 -9 -8 -7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11
STA 0+450
KETERANGAN 186
PEMERINTAH DAERAH KABUPATEN JENEPONTO
Rencana : BADAN PENANGGULANGAN BENCANA DAERAH
Existing :
185 JL. DRS. H. RADJAMILO, MP. KEL. EMPOANG,
Timbunan : KEC. BINAMU, KABUPATEN JENEPONTO

Galian : PEKERJAAN
184
CATATAN
REKONSTRUKSI TALUD
SUNGAI PAPPALLUANG
183 DESA PAPPALLUANG
KEC. BANGKALA BARAT
182
SKALA VERTIKAL 1 : 100 DIBUAT OLEH :
SKALA HORIZONTAL 1 : 100

JARAK KONTRAKTOR PELAKSANA


CV. ARYA GRAHA PUTRATAMA

183.957
ELEVASI

AMIR HAMZAH
DIREKTUR

-11 -10 -9 -8 -7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11 DIPERIKSA OLEH :


STA 0+475
KONSULTAN PENGAWAS
KETERANGAN 186 CV. DAYA AMALIA CONSULTANT

Rencana :
Existing :

Timbunan :
185

Galian :
184 ST. ZACHRA, SE
CATATAN
DIREKTRIS

183 DIPERIKSA OLEH :


PENGAWAS TEKNIK

SKALA VERTIKAL 1 : 100


182
SKALA HORIZONTAL 1 : 100

JARAK 175 175


H. BAHARUDDIN M, SE

183.373
182.500
186.100

183.500

183.500
186.100

182.500
NIP. 19650519 199103 1 011
ELEVASI
DIPERIKSA/DISETUJUI OLEH :
PEJABAT PEMBUAT KOMITMEN (PPK)

-11 -10 -9 -8 -7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11
STA 0+500
186
KETERANGAN

FADLI ARFANDI THAYEB, ST., M.Si


Rencana : 185
Existing :
NIP. 19800320 200604 1 008
Timbunan :

184 NO. PAKET


Galian :
NO. RUAS
CATATAN
183 KABUPATEN JENEPONTO
PROPINSI SULAWESI SELATAN

182 AS BUILT DRAWING


SKALA VERTIKAL 1 : 100
CROSS SECTION
SKALA HORIZONTAL 1 : 100
181
STA 0+450 - STA 0+500
JARAK 175 175
182.500
186.050

183.500

183.000
185.650

182.000
182.858

NO. LEMBAR 11
ELEVASI
JML. LEMBAR 17 LEMBAR
SKALA 1 : 100
TANGGAL
KETERANGAN
-11 -10 -9 -8 -7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11
STA 0+525
KETERANGAN 185
PEMERINTAH DAERAH KABUPATEN JENEPONTO
Rencana : BADAN PENANGGULANGAN BENCANA DAERAH
Existing :
184 JL. DRS. H. RADJAMILO, MP. KEL. EMPOANG,
Timbunan :
KEC. BINAMU, KABUPATEN JENEPONTO
Galian : PEKERJAAN
183
CATATAN REKONSTRUKSI TALUD
SUNGAI PAPPALLUANG
182 DESA PAPPALLUANG
KEC. BANGKALA BARAT
181
SKALA VERTIKAL
SKALA HORIZONTAL
1 : 100
1 : 100
DIBUAT OLEH :
JARAK KONTRAKTOR PELAKSANA
175 175 CV. ARYA GRAHA PUTRATAMA

181.500
185.100

182.500

182.500
184.900

181.500
182.639
ELEVASI

AMIR HAMZAH
DIREKTUR

-11 -10 -9 -8 -7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11
STA 0+540 DIPERIKSA OLEH :
185 KONSULTAN PENGAWAS
KETERANGAN CV. DAYA AMALIA CONSULTANT

Rencana : 184
Existing :

Timbunan :

183
Galian :
ST. ZACHRA, SE
CATATAN DIREKTRIS
182
DIPERIKSA OLEH :
181 PENGAWAS TEKNIK

SKALA VERTIKAL 1 : 100


SKALA HORIZONTAL 1 : 100
180
JARAK 175 175
H. BAHARUDDIN M, SE
181.000
184.400

182.000

182.358

182.000
184.400

181.000
NIP. 19650519 199103 1 011
ELEVASI
DIPERIKSA/DISETUJUI OLEH :
PEJABAT PEMBUAT KOMITMEN (PPK)

-11 -10 -9 -8 -7 -6 -5 -4 -3 -2 -1 1 2 3 4 5 6 7 8 9 10 11

KETERANGAN

Rencana :
FADLI ARFANDI THAYEB, ST., M.Si
Existing :
NIP. 19800320 200604 1 008
Timbunan :

NO. PAKET
Galian :
NO. RUAS
CATATAN KABUPATEN JENEPONTO
PROPINSI SULAWESI SELATAN

AS BUILT DRAWING
SKALA VERTIKAL
SKALA HORIZONTAL
1 : 100
1 : 100
CROSS SECTION
JARAK
STA 0+525 - STA 0+540

ELEVASI
NO. LEMBAR 12
JML. LEMBAR 17 LEMBAR
SKALA 1 : 100
TANGGAL
KETERANGAN
0+000
STA
U
PEMERINTAH DAERAH KABUPATEN JENEPONTO
BADAN PENANGGULANGAN BENCANA DAERAH
JL. DRS. H. RADJAMILO, MP. KEL. EMPOANG,
KEC. BINAMU, KABUPATEN JENEPONTO

STA PEKERJAAN

AWAL PROYEK 0+100 REKONSTRUKSI TALUD


SUNGAI PAPPALLUANG
STA 0+000 DESA PAPPALLUANG

ST 125
KEC. BANGKALA BARAT

0+
A
DIBUAT OLEH :
STA KONTRAKTOR PELAKSANA

ST 25 0+050 CV. ARYA GRAHA PUTRATAMA


0+
0
A
STA75 AMIR HAMZAH

0+0
DIREKTUR

DIPERIKSA OLEH :
KONSULTAN PENGAWAS
CV. DAYA AMALIA CONSULTANT

0+15
ST. ZACHRA, SE

0
DIREKTRIS
SITUASI & POTONGAN MEMANJANG 198 DIPERIKSA OLEH :
PENGAWAS TEKNIK
197

POTONGAN MEMANJANG
SKALA HORISONTAL 1 : 500 196
SKALA VERTIKAL 1 : 100 H. BAHARUDDIN M, SE
ELEVASI TOP TALUD NIP. 19650519 199103 1 011
195
ELEVASI DASAR TALUD
DIPERIKSA/DISETUJUI OLEH :
194
PEJABAT PEMBUAT KOMITMEN (PPK)

193

192 FADLI ARFANDI THAYEB, ST., M.Si


NIP. 19800320 200604 1 008
191
NO. PAKET
NO. RUAS
190 KABUPATEN JENEPONTO
PROPINSI SULAWESI SELATAN
0+000

0+025

0+050

0+075

0+100

0+125
STASIUNING
AS BUILT DRAWING
194.300 195.900 193.575

193.300 195.050 193.863

193.000 194.950 192.720

192.500 194.550 192.353

192.000 194.070 192.203

192.500 195.500 192.054


ELEVASI DASAR SUNGAI LONG SECTION
STA 0+000 - STA 0+125
ELEVASI TOP TALUD
NO. LEMBAR 13
ELEVASI DASAR TALUD JML. LEMBAR 17 LEMBAR

GALIAN
SKALA 1 : 500; 1 : 100

TANGGAL
TIMBUNAN M³
KETERANGAN
U

ST 125
PEMERINTAH DAERAH KABUPATEN JENEPONTO

0+
BADAN PENANGGULANGAN BENCANA DAERAH

A
JL. DRS. H. RADJAMILO, MP. KEL. EMPOANG,
KEC. BINAMU, KABUPATEN JENEPONTO

PEKERJAAN
REKONSTRUKSI TALUD
STA SUNGAI PAPPALLUANG

0+225
DESA PAPPALLUANG
KEC. BANGKALA BARAT
DIBUAT OLEH :
KONTRAKTOR PELAKSANA
CV. ARYA GRAHA PUTRATAMA

STA 5 STA
7 0+250
0+1
0+1
STA50
STA00
AMIR HAMZAH
DIREKTUR

0+2 DIPERIKSA OLEH :


KONSULTAN PENGAWAS
CV. DAYA AMALIA CONSULTANT

ST. ZACHRA, SE
DIREKTRIS
SITUASI & POTONGAN MEMANJANG 195 DIPERIKSA OLEH :
PENGAWAS TEKNIK
194

POTONGAN MEMANJANG
SKALA HORISONTAL 1 : 500 193
SKALA VERTIKAL 1 : 100 H. BAHARUDDIN M, SE
ELEVASI TOP TALUD NIP. 19650519 199103 1 011
192
ELEVASI DASAR TALUD
DIPERIKSA/DISETUJUI OLEH :
191
PEJABAT PEMBUAT KOMITMEN (PPK)

190

189 FADLI ARFANDI THAYEB, ST., M.Si


NIP. 19800320 200604 1 008
188
NO. PAKET
NO. RUAS
187 KABUPATEN JENEPONTO
PROPINSI SULAWESI SELATAN
0+125

0+150

0+175

0+200

0+225

0+250
STASIUNING
AS BUILT DRAWING
192.500 195.500 192.054

190.500 193.000 191.335

190.500 192.870 190.382

189.500 192.350 189.580

188.500 191.350 188.903

188.000 190.750 188.137


ELEVASI DASAR SUNGAI LONG SECTION
STA 0+125 - STA 0+250
ELEVASI TOP TALUD
NO. LEMBAR 14
ELEVASI DASAR TALUD JML. LEMBAR 17 LEMBAR

GALIAN
SKALA 1 : 500; 1 : 100

TANGGAL
TIMBUNAN M³
KETERANGAN
U
S
0+3TA
PEMERINTAH DAERAH KABUPATEN JENEPONTO
BADAN PENANGGULANGAN BENCANA DAERAH
JL. DRS. H. RADJAMILO, MP. KEL. EMPOANG,
25 KEC. BINAMU, KABUPATEN JENEPONTO

T A 5 PEKERJAAN
S 27 REKONSTRUKSI TALUD

0+ STA SUNGAI PAPPALLUANG


STA DESA PAPPALLUANG
0+300 0+375 KEC. BANGKALA BARAT
DIBUAT OLEH :
KONTRAKTOR PELAKSANA
CV. ARYA GRAHA PUTRATAMA

ST
0+3 A
T A 0 50 AMIR HAMZAH

S 25 DIREKTUR

0+ DIPERIKSA OLEH :
KONSULTAN PENGAWAS
CV. DAYA AMALIA CONSULTANT

ST. ZACHRA, SE
DIREKTRIS
SITUASI & POTONGAN MEMANJANG 192 DIPERIKSA OLEH :
PENGAWAS TEKNIK
191

POTONGAN MEMANJANG
SKALA HORISONTAL 1 : 500 190
SKALA VERTIKAL 1 : 100 H. BAHARUDDIN M, SE
ELEVASI TOP TALUD NIP. 19650519 199103 1 011
189
ELEVASI DASAR TALUD
DIPERIKSA/DISETUJUI OLEH :
188
PEJABAT PEMBUAT KOMITMEN (PPK)

187

186 FADLI ARFANDI THAYEB, ST., M.Si


NIP. 19800320 200604 1 008
185
NO. PAKET
NO. RUAS
184 KABUPATEN JENEPONTO
PROPINSI SULAWESI SELATAN
0+250

0+275

0+300

0+325

0+350

0+375
STASIUNING
AS BUILT DRAWING
188.000 190.750 188.137

187.500 190.050 187.618

187.500 190.100 187.158

186.500 189.040 186.463

186.000 188.650 185.947

185.500 188.140 185.406


ELEVASI DASAR SUNGAI LONG SECTION
STA 0+250 - STA 0+375
ELEVASI TOP TALUD
NO. LEMBAR 15
ELEVASI DASAR TALUD JML. LEMBAR 17 LEMBAR

GALIAN
SKALA 1 : 500; 1 : 100

TANGGAL
TIMBUNAN M³
KETERANGAN
U
S PEMERINTAH DAERAH KABUPATEN JENEPONTO
0+ TA STA BADAN PENANGGULANGAN BENCANA DAERAH

37 0+475
JL. DRS. H. RADJAMILO, MP. KEL. EMPOANG,
KEC. BINAMU, KABUPATEN JENEPONTO
5 PEKERJAAN
REKONSTRUKSI TALUD
SUNGAI PAPPALLUANG
DESA PAPPALLUANG
STA KEC. BANGKALA BARAT

0+425 DIBUAT OLEH :

STA KONTRAKTOR PELAKSANA


CV. ARYA GRAHA PUTRATAMA

0+500
ST A
0+4 A T
S 450 AMIR HAMZAH
00 DIREKTUR
0+ DIPERIKSA OLEH :
KONSULTAN PENGAWAS
CV. DAYA AMALIA CONSULTANT

ST. ZACHRA, SE
DIREKTRIS
SITUASI & POTONGAN MEMANJANG 189 DIPERIKSA OLEH :
PENGAWAS TEKNIK
188

POTONGAN MEMANJANG
SKALA HORISONTAL 1 : 500 187
SKALA VERTIKAL 1 : 100 H. BAHARUDDIN M, SE
ELEVASI TOP TALUD NIP. 19650519 199103 1 011
186
ELEVASI DASAR TALUD
DIPERIKSA/DISETUJUI OLEH :
185
PEJABAT PEMBUAT KOMITMEN (PPK)

184

183 FADLI ARFANDI THAYEB, ST., M.Si


NIP. 19800320 200604 1 008
182
NO. PAKET
NO. RUAS
181 KABUPATEN JENEPONTO
PROPINSI SULAWESI SELATAN
0+375

0+400

0+425

0+450

0+475

0+500
STASIUNING
AS BUILT DRAWING
185.500 188.140 185.406

185.000 187.550 184.942

184.500 187.200 184.382

183.957

183.500 186.100 183.373

183.500 186.050 182.858


ELEVASI DASAR SUNGAI LONG SECTION
STA 0+375 - STA 0+500
ELEVASI TOP TALUD
NO. LEMBAR 16
ELEVASI DASAR TALUD JML. LEMBAR 17 LEMBAR

GALIAN
SKALA 1 : 500; 1 : 100

TANGGAL
TIMBUNAN M³
KETERANGAN
U
PEMERINTAH DAERAH KABUPATEN JENEPONTO
STA BADAN PENANGGULANGAN BENCANA DAERAH
0+52 JL. DRS. H. RADJAMILO, MP. KEL. EMPOANG,

5 KEC. BINAMU, KABUPATEN JENEPONTO

AKHIR PROYEK PEKERJAAN

0+ STA STA 0+540 REKONSTRUKSI TALUD


SUNGAI PAPPALLUANG
54 DESA PAPPALLUANG
0 KEC. BANGKALA BARAT
STA DIBUAT OLEH :
0+500 KONTRAKTOR PELAKSANA
CV. ARYA GRAHA PUTRATAMA

AMIR HAMZAH
DIREKTUR

DIPERIKSA OLEH :
KONSULTAN PENGAWAS
CV. DAYA AMALIA CONSULTANT

ST. ZACHRA, SE
188 DIREKTRIS
SITUASI & POTONGAN MEMANJANG DIPERIKSA OLEH :
187 PENGAWAS TEKNIK

186
POTONGAN MEMANJANG
SKALA HORISONTAL 1 : 500
SKALA VERTIKAL 1 : 100
185 H. BAHARUDDIN M, SE
ELEVASI TOP TALUD NIP. 19650519 199103 1 011
ELEVASI DASAR TALUD
184 DIPERIKSA/DISETUJUI OLEH :
PEJABAT PEMBUAT KOMITMEN (PPK)
183

182
FADLI ARFANDI THAYEB, ST., M.Si
181 NIP. 19800320 200604 1 008

NO. PAKET
180
NO. RUAS
KABUPATEN JENEPONTO
PROPINSI SULAWESI SELATAN
0+500

0+525

0+550

STASIUNING
AS BUILT DRAWING
183.500 186.050 182.858

182.500 185.100 182.639

182.000 184.400 182.358

ELEVASI DASAR SUNGAI LONG SECTION


STA 0+500 - STA 0+540
ELEVASI TOP TALUD
NO. LEMBAR 17
ELEVASI DASAR TALUD JML. LEMBAR 17 LEMBAR

GALIAN
SKALA 1 : 500; 1 : 100

TANGGAL
TIMBUNAN M³
KETERANGAN

Anda mungkin juga menyukai