JUMLAH HARGA
NO URAIAN PEKERJAAN
SATUAN (RP)
1 Sta 0 ± 000
P : 50 m
L1 : 2 m
L2 : 2.5 m
t : 1
2 Sta 0 ± 050
P : 50 m
L1 : 2.5
L2 : 2.5
t : 1
3 Sta 0 ± 100
P : 50 m
L1 : 2.5
L2 : 4
t : 1.2
4 Sta 0 ± 150
P : 50 m
L1 : 4
L2 : 6
t : 1.4
5 Sta 0 ± 200
P : 50 m
L1 : 6
L2 : 8
t : 1.6
6 Sta 0 ± 250
P : 50 m
L1 : 8
L2 : 10
t : 1.8
7 Sta 0 ± 300
P : 50 m
L1 : 10
L2 : 30
t : 1.8
La + Lb
= x t x P
2
2 + 2.5
= x 1 x 50
2
= 112.5 m3
La + Lb
= x t x P
2
2.5 + 2.5
= x 1 x 50
2
= 125 m3
La + Lb
= x t x P
2
2.5 + 4
= x 1.2 x 50
2
= 195 m3
La + Lb
= x t x P
2
4 + 6
= x 1.4 x 50
2
= 350 m3
La + Lb
= x t x P
2
6 + 8
= x 1.6 x 50
2
= 560 m3
La + Lb
= x t x P
2
8 + 10
= x 1.8 x 50
2
= 810 m3
La + Lb
= x t x P
2
10 + 30
= x 1.8 x 50
2
= 1839.4 m3
= 3991.9 m3
BAC
KEGIATAN : USULAN DAK 2022
DAERAH IRIGASI : REHABILITASI D.I. BALANGLOE
LOKASI : DESA KALUMPANG LOE, KEC. ARUNGKEKE
NO SKETSA BANGUNAN
BAC
KEGIATAN : USULAN DAK 2022
DAERAH IRIGASI : REHABILITASI D.I. BALANGLOE
LOKASI : DESA KALUMPANG LOE, KEC. ARUNGKEKE
NO SKETSA BANGUNAN
BAC
KEGIATAN : USULAN DAK 2022
DAERAH IRIGASI : REHABILITASI D.I. BALANGLOE
LOKASI : DESA KALUMPANG LOE, KEC. ARUNGKEKE
NO SKETSA BANGUNAN
NO SKETSA BANGUNAN
PERHITUNGAN
1. GALIAN SEDIMEN
Disetujui Ole
Plt.Kepala Dinas Pekerjaan Umum
Kab.Jeneponto
MUH.ARIFIN NUR,
Nip.19660424 19920
B A C K U P VOLUME
PERHITUNGAN
● #REF! + #REF!
x #REF! x 0.00
2
B A C K U P VOLUME
PERHITUNGAN
2. PEK. PLESTERAN
● 0.25 + 0.70 x 350
B A C K U P VOLUME
PERHITUNGAN
2. PEK. PLESTERAN
● 0.25 + 0.70 x 350 x 2.00
= 60.00 M3
Disetujui Oleh
Dinas Pekerjaan Umum dan Penataan Ruang
Kab.Jeneponto
MUH.ARIFIN NUR,SH,MH
Nip.19660424 199203 1 010
KET.
= 0.00 M3
= 0.00
0.00
= 15.00 M2
= M3
332.50 M2
= 31.5 M3
= M3
= M3
KET.
2.00 = 134.75 M3
90.00 M3
665.00 M2
= 54.0 M3
Jeneponto, April 2019
Diperiksa :
KONSULTAN PENGAWAS
0
0
0
B A C K U P VOLUME
USULAN DAK 2020
: REHABILITASI D.I. BALANGLOE
: DESA KALUMPANG LOE, KEC. ARUNGKEKE
● 0.00 + 0.00
2
1.2 ● 0.00 + #REF!
2
● #REF! x 0.00
Dibuat :
Pelaksana Lapangan
0
0
0
UME
PERHITUNGAN KET.
x 500.00 + 2 x 10.5 = 0 M2
x 500.00 + 2 x 10.5 = 50 M2
50.00 M2
RENCANA ANGGARAN BIAYA
KEGIATAN : REHABILITASI/PEMELIHARAAN JARINGAN IRIGASI
TAHUN ANGGARAN : 2021
PEKERJAAN : REHABILITASI D.I. KARISA 2
VOLUME : 1 (SATU) PAKET
LOKASI : DESA KAMPALA, KEC. ARUNGKEKE, KAB. JENEPONTO
A. Sewa Tanah M2 0 0 0
B. PERALATAN
Periksa lembar 1.2-2 2,150,000
E. MOBILISASI LAINNYA
E.I. PEKERJAAN DARURAT LS 0 0 0
1 ......................
2 ......................
B. PERALATAN
I BAHAN
1 Kaso 5/7 CM M3 0.0130 3,140,000.00 40,820.00
2 Paku Biasa 5 cm & 7 cm Kg 0.0200 29,400.00 588.00
3 Papan 3/20 (Perancah) M3 0.0070 3,140,000.00 21,980.00
Sub Total
II UPAH
1 Pekerja/Tukang Gali OH 0.5630 100,000.00 56,300.00
2 Tukang OH - -
3 Kepala Tukang OH - -
4 Mandor OH 0.0563 145,000.00 8,163.50
Sub Total 64,463.50
Overhead & Profit 10% -
HARGA SATUAN 64,463.50
I BAHAN
1 Batu Belah M3 1.200 241,900.00 290,280.00
2 Semen Pc Kg 163.000 1,700.00 277,100.00
3 Pasir Pasangan M3 0.520 241,900.00 125,788.00
Sub Total 693,168.00
II UPAH
1 Pekerja OH 2.700 100,000.00 270,000.00
2 Tukang Batu OH 0.900 134,000.00 120,600.00
3 Mandor OH 0.270 145,000.00 39,150.00
Sub Total 429,750.00
III PERALATAN - - -
Sub Total -
TOTAL I+II+III 1,122,918.00
Overhead & Profit 10% -
HARGA SATUAN 1,122,918.00
ANALISA HARGA SATUAN
KODE ANALISA : P.04.b
URAIAN PEKERJAAN : Plesteran tebal 1 cm/PEKERJAAN PLESTERAN (setara campuran 1 PC:3 PP)
VOLUME : DALAM 1 M2
I BAHAN
1 Semen Pc Kg 5.840 1,700.00 9,928.00
2 Pasir Pasangan M3 0.016 241,900.00 3,870.40
I BAHAN
1 Semen Pc Kg 6.340 1,700.00 10,778.00
2 Pasir Pasangan M3 0.012 241,900.00 2,902.80
I BAHAN
1 Besi Beton Polos/Ulir M3 105.000 13,500.00 1,417,500.00
2 Kawat Beton Kg 1.500 27,400.00 41,100.00
Sub Total -
III UPAH
1 Pekerja OH 0.700 100,000.00 70,000.00
2 Tukang Besi OH 0.700 134,000.00 93,800.00
3 Kepala Tukang OH 0.070 168,000.00 11,760.00
4 Mandor OH 0.070 145,000.00 10,150.00
I BAHAN
1 Semen Pc Kg 371.000 1,700.00 630,700.00
2 Pasir Beton M3 0.499 241,900.00 120,604.43
3 Kerikil 2 - 3 cm M3 0.776 476,100.00 369,242.00
4 Air Bersih Liter 215.000 100.00 21,500.00
I BAHAN
1 Papan Kayu Kls II M3 0.014 6,388,000.00 89,432.00
2 Kaso 5/7 M3 0.003 6,388,000.00 19,164.00
3 Paku 5 dan 7 CM Kg 0.300 29,400.00 8,820.00
4 Minyak Bekesting Liter 0.200 13,600.00 2,720.00
I BAHAN
1 Semen Pc Kg 326.00 1,700.00 554,200.00
2 Pasir Beton M3 0.54 241,700.00 130,518.00
3 Kerikil 2 - 3 cm M3 0.76 476,100.00 361,836.00
4 Air Bersih Liter 215.00 100.00 21,500.00
I BAHAN
1 Semen Pc Kg - - -
2 Pasir Beton M3 - - -
3 Kerikil 2 - 3 cm M3 - - -
4 Air Bersih Liter - - -
Sub Total A -
II UPAH
1 Pekerja Jam 0.1630 7,142.86 1,164.29
2 Tukang Jam 0.189 - -
3 Kepala Tukang Jam 0.019 - -
4 Mandor Jam 0.0163 10,714.29 174.64
Sub Total B 1,338.93
III PERALATAN
1 Excavator (Long Arm) Jam 0.03722 472,891.55 17,601.02
E. LAIN - LAIN
1. Bahan Bakar Bensin Mb Liter 10,500.00 10,500.00
2. Bahan Bakar Solar Ms Liter 11,200.00 11,200.00
3. Minyak Pelumas Mp Liter 35,000.00 35,000.00
ITEM PEMBAYARAN NO: 2.1 Analisa EI-211
JENIS PEKERJAAN : Galian Tanah / Pengerukan Sungai
SATUAN PEMBAYARA : M3 URAIAN ANALISA HARGA SATUAN
I. ASUMSI
1 Jam kerja efektif per-hari Tk 7.00 jam
2 Faktor pengembangan bahan Fk 1.20 -
3 Faktor tanah Lepas Fk1 1.00 -
4 Jarak Angkut L 1.00 Km
1. BAHAN
Tidak ada bahan yang diperlukan
JUMLAH HARGA TENAGA
2. ALAT
2.a. EXCAVATOR (E10)
Kapasitas Bucket V 0.60 M3
Faktor Bucket Fb 1.00 -
Faktor Efisiensi alat Fa 0.75 -
Faktor Konversi
Waktu siklus = T1 + T2 Ts1 0.73 menit masuk dalam
- Menggali, memuat dan berputar T1 0.48 menit waktu siklus
- Lain lain T2 0.25 menit disesuaikan dgn
Kap. Prod. / jam V x Fb x Fa x 60 x Fk Q1 44.38 M3 lapangan
Ts1 JUMLAH HARGA BAHAN
3. TENAGA
Produksi menentukan : EXCAVATOR Q1 44.38 M3/Jam
Produksi Galian / hari = Tk x Q1 Qt 310.68 M3
Kebutuhan tenaga :
- Pekerja P 4.00 orang
- Mandor M 1.00 orang
Koefisien tenaga / M3 :
- Pekerja = (Tk x P) : Qt (L01) 0.0901 Jam
- Mandor = (Tk x M) : Qt (L03) 0.0225 Jam
Rp. ### / M3
= 0.45 + 1 x 40
2
= 0.725 x 40 x 2.8
= 81.2 m3
b. Kaki P : 40 m
L : 0.6 m
t : 1.15 m
= P x L x T
= 40 x 0.6 x 1.15
= 27.6 m3
- Plesteran 1 : 3 P : 40 m
L : 0.45 + 0.1 = 0.55
= 40 x 0.55 = 22
- Plesteran Siar 1 : 2 P : 40 m
L : 2.7
= 40 x 2.7 = 108
2 Proteksi 2 a Badan P : 50 m =
La : 0.3 m
Lb : 0.6 m
t : 1.5 m
0.3 + 0.6
= 2 x 50
= 0.45 x 50 x 1.5
= 33.75 m3
b. Kaki P : 50 m
L : 0.75 m
t : 0.5 m
= P x L x T
= 50 x 0.75 x 0.5
= 18.75 m3
- Plesteran 1 : 3 P : 50 m
L : 0.3 + 0.1 = 0.4
= 50 x 0.4 = 20
- Plesteran Siar 1 : 2 P : 50 m
L : 1.5
= 50 x 1.5 = 75
x 2.8
m2
m2
x 1.5
m2
m2