Time Schedule Target Pelaksaan Proyek
Time Schedule Target Pelaksaan Proyek
TIME SCHEDULE
JANUARI FEBRUARI
NO URAIAN PEKERJAAN ANGGARAN BIAYA BOBOT
17-23 24-30 31 - 06 07 - 13
%
1 2 3 4
I PEKERJAAN PERSIAPAN Rp 605,389,104.00 1.35 0.03 0.03 0.03 0.03
II PEKERJAAN STRUKTUR
A PEKERJAAN TANAH & PONDASI Rp 1,120,969,061.11 2.49 0.42 0.42 0.42 0.42
DISETUJUI OLEH
TIM TEKNIS LA[PANGAN
KAMPUS UNKHAIR
FEBRUARI MARET APRIL MEI JUNI JULI AGUSTUS SEPTEMBER OKTOBER NOVEMBER
14 - 20 21 - 27 28 - 0 5 06 - 12 13 - 19 20 - 26 27 - '02 03 - 09 10 - 16 17 - 23 24 - 30 01 - '07 08 - 14 15 - 21 22 - 28 29 - '04 05 - 11 12 - 18 19 - 25 26 - '02 03 - 09 10 - 16 17 - 23 24 - 30 31 - '06 07 - 13 14 - 20 21 - 27 28 - '03 04 - '10 11 - 17 18 - 24 25 - '01 02 - '08 09 - 15 16 - 22 23 - 29 30 - '05 06 - 12 13- 19 20 - 26 27 - 30 KETERANGAN
5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46
0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 100.00
0.42 0.42
0.84 0.84 0.84 0.84 0.84 0.84 0.84 0.84 0.84 0.84
1.13 1.13 1.13 1.13 1.13 1.13 1.13 1.13 1.13 1.13
1.02 1.02 1.02 1.02 1.02 1.02 1.02 1.02 1.02 1.02
0.05 0.05
0.78 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.43 0.10 0.10 0.70 0.40 0.02
0.30 0.30 0.30 0.30 0.30 0.30 0.30 0.30 0.30 0.30 0.30 0.30 0.30 0.30 0.30 0.30 0.30 75.00
0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50 0.50
1.03 1.03
0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08 0.08
0.26 0.26 0.26 0.26 0.26 0.26 0.26 0.26 0.26 0.26 0.26 0.26 0.26 0.26 0.26
0.29 0.29
0.85 0.85 0.85 0.85 0.85 0.85 0.85 0.85 0.85 0.85 0.85 0.85 0.85 0.85
1.59
0.52 0.52 0.52 0.52 0.52 0.52 0.52 0.52 0.52 0.52 0.52 0.52 50.00
0.25
1.34
0.55
0.30
1.46
0.17
0.15
0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09
0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06
0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 25.00
0.01 0.01
0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20 0.20
1.41
0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
0.02
0.77 0.92 1.39 2.07 2.24 2.13 2.78 2.89 1.97 1.12 2.65 2.84 1.74 1.66 3.22 3.40 2.30 2.35 2.97 3.15 2.69 2.44 2.08 3.04 3.15 2.96 2.94 2.94 3.12 2.88 2.09 2.14 1.69 4.33 2.76 4.08 4.70 1.62 1.46 0.13 0.08
2.88 3.80 5.20 7.27 9.51 11.63 14.42 17.31 19.28 20.40 23.05 25.89 27.63 29.29 32.51 35.91 38.21 40.57 43.53 46.68 49.37 51.81 53.89 56.93 60.08 63.04 65.98 68.92 72.04 74.92 77.01 79.15 80.84 85.17 87.93 92.01 96.72 98.33 99.79 99.92 100.00
ABDUL KAHAR,ST
Ar. Shaifuddin Zuhri Usman, ST Project Manager
PEKERJAAN PEMBANGUNAN GEDUNG KULIAH TERPADU
UNIVERSITAS KHAIRUN TERNATE
KEMENTRIAN PENDIDIKAN, KEBUDAYAAN, RISET & TEKNOLOGI
TAHUN ANGGARAN 2024
NO URAIAN PEKERJAAN
I PEKERJAAN PERSIAPAN
II PEKERJAAN STRUKTUR
A PEKERJAAN TANAH & PONDASI
B PEKERJAAN TIE BEAM, SLOEF
C PEKERJAAN KOLOM
D PEKERJAAN BALOK
E PEKERJAAN PLAT LANTAI
F PEKERJAAN STUKTUR LIFT
G PEKERJAAN TANGGA
III PEKERJAAN ARSITEKTUR
A PEKERJAAN PASANGAN DINDING & PARTISI
B PEKERJAAN PASANGAN LANTAI & DINDING
C PEKERJAAN PASANGAN PLAFOND
D PEKERJAAN ATAP
E PEKERJAAN PENGECATAN
F PEKERJAAN PENGADAAN DAN PEMASANGAN PINTU & JENDELA
G PEKERJAAN PASANGAN SANITAIR
H PEKERJAAN RAILING TANGGA DAN HAND RAILING
I PEKERJAAN ARSITEKTUR NON STANDAR
J PEKERJAAN SITE
IV PEKERJAAN MEP
A PEKERJAAN PENYAMBUNGAN DAYA PLN
B PEKERJAAN INSTALASI PENERANGAN
C PEKERJAAN INSTALASI CCTV
D PEKERJAAN INSTALASI SOUND SYSTEM
E PEKERJAAN INSTALASI FIRE ALARM
F PEKERJAAN INSTALASI JARINGAN INTERNET
G PEKERJAAN INSTALASI EXHAUST FAN
H PEKERJAAN INSTALASI AC SYSTEM (VRV)
I PEKERJAAN PENANGKAL PETIR
J PEKERJAAN PEMASANGAN APAR
K PEKERJAAN INSTALASI AIR BERSIH
L PEKERJAAN INSTALASI AIR KOTOR
M PEKERJAAN INSTALASI AIR BEKAS
N PEKERJAAN INSTALASI AIR VENT
O PEKERJAAN INSTALASI AIR HUJAN
P PEKERJAAN PEMASANGAN LIFT
Q PEKERJAAN INSTALASI FIRE FIGHTER
R INSTALASI SOLAR PANEL
V PEKERJAAN INTERIOR
A PEKERJAAN INTERIOR LOBBY
B PEKERJAAN INTERIOR SELASAR
C PEKERJAAN INTERIOR LABORATORIUM KOMPUTER
D PEKERJAAN INTERIOR RUANG KELAS GABUNGAN
JUMLAH
RENCANA PROGRES MINGGUAN
KOMULATIF PROGRES MINGGUAN
REALISASI PROGRES MINGGUAN
KOMULATIF REALISASI PROGRES MINGGUAN
DEVIASI
JANUARI FEBRUARI
ANGGARAN BIAYA BOBOT
%
1 2 3 4 5
Rp 605,389,104.00 1.35 0.03 0.03 0.03 0.03 0.03
Rp 3,766,908,800.63 8.38
Rp 5,102,294,893.44 11.35
Rp 4,601,341,523.97 10.23
Rp 45,181,312.23 0.10
Rp 421,218,645.89 0.94
Rp 2,682,552,203.76 5.97
Rp 2,330,615,737.31 5.18
Rp 2,459,594,366.73 5.47
Rp 929,813,791.82 2.07
Rp 554,531,241.54 1.23
Rp 1,771,184,404.84 3.94
Rp 262,111,985.51 0.58
Rp 127,590,428.91 0.28
Rp 5,342,082,587.29 11.88
Rp 623,943,815.53 1.39
-
Rp 715,082,000.00 1.59
Rp 2,816,449,939.13 6.26
Rp 67,770,650.00 0.15
Rp 110,278,350.00 0.25
Rp 603,368,411.41 1.34
Rp 246,887,420.63 0.55
Rp 136,203,067.50 0.30
Rp 654,959,041.41 1.46
Rp 78,426,425.00 0.17
Rp 68,242,327.50 0.15
Rp 657,407,033.17 1.46
Rp 257,026,038.86 0.57
Rp 114,321,806.50 0.25
Rp 4,643,814.50 0.01
Rp 193,017,295.00 0.43
Rp 1,721,250,000.00 3.83
Rp 2,127,422,450.38 4.73
Rp 635,604,787.50 1.41
-
Rp 102,960,970.84 0.23
Rp 192,478,934.97 0.43
Rp 9,642,561.29 0.02
Rp 116,360,480.28 0.26
Rp 44,966,311,267.29 100.00
0.45 0.45 0.45 0.77 0.77
6 7 8 9 10 11 12 13
0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
0.42
0.33 0.33
0.05 0.05
0.23 0.23
0.02 0.02
15.00
Rp 6,744,946,690.09
TIME SCHEDULE
0.23
30.00
JUNI JULI AG
MINGGU
22 23 24 25 26 27 28 29
0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
0.84 0.84
1.13 1.13
1.02 1.02
0.23
1.03 1.03
0.005 0.005
0.11
50
AGUSTUS SEPTEMBER
30 31 32 33 34 35 36 37
0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
0.29 0.29
0.05
0.09 0.09 0.09 0.09 0.09 0.09 0.09 0.09
0.02
0.05 0.05
70
OKTOBER NOVEMBER
KETERANGAN
38 39 40 41 42 43 44 45
0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
0.08
1.59
0.05 0.05
0.25
1.34
0.55
0.30
1.46
0.17
0.15
0.09 0.09
1.41
0.02
95 100
DI BUAT OLEH
KONTRAKTOR PELAKSANA
PT.HAKA UTAMA
ABDUL KAHAR,ST
Project Manager
KETERANGAN
100.00 1.35 -
0.00 -
2.49 -
1.31 -
8.38 -
11.35 -
10.23 -
0.10 -
0.94 -
0.00 -
6.05 0.0863
75.00 5.18 -
5.47 -
2.07 -
1.23 -
3.94 -
0.58 -
0.28 -
11.88 -
1.39 -
0.00 -
1.59 -
50.00 6.26 -
0.15 -
0.25 -
1.34 -
0.55 -
0.30 -
1.46 -
0.17 -
0.15 -
1.46 -
0.57 -
25.00 0.25 -
0.01 -
0.43 -
3.83 -
4.73 -
1.41 -
0.00 -
0.23 -
0.43 -
0.02 -
0.00 0.26 -