PENYUSUNAN DETAIL ENGINEERING DESIGN DED PEMBANGUNAN GEDUNG KANTOR UPT (INFRASTRUKTUR JALAN & JEMBATAN KELAS A WILAYAH IX CILEUNGSI) 29 AGUSTUS 2023 NO DESCRIPTION TOTAL VALUE (Rp) A PEKERJAAN PENYAMBUNGAN DAYA LISTRIK Rp 32,967,000
B PEKERJAAN PANEL-PANEL Rp 90,320,017
C PEKERJAAN INSTALASI KABEL FEEDER Rp 61,806,149
D PEKERJAAN INSTALASI ROUTING KABEL FEEDER Rp 22,265,390
E PEKERJAAN INSTALASI LIGHTING & POWER RECEPTACLE GEDUNG UPT Rp 61,955,844
F PEKERJAAN WORKSHOP Rp 27,944,724
G PEKERJAAN OUTDOOR LIGHTING Rp 72,124,749
H PEKERJAAN LIGHTNING PROTECTION Rp 44,509,153
I PEKERJAAN GROUNDING SYSTEM Rp 87,492,168
J PEKERJAAN TESTING & COMMISIONING Rp 12,534,630
TOTAL Rp 513,919,825 TOTAL (ROUNDED) Rp 513,920,000