Anda di halaman 1dari 1

DINAS PUPR KABUPATEN BOGOR

REKAP RENCANA ANGGARAN BIAYA


PENYUSUNAN DETAIL ENGINEERING DESIGN DED PEMBANGUNAN GEDUNG KANTOR UPT
(INFRASTRUKTUR JALAN & JEMBATAN KELAS A WILAYAH IX CILEUNGSI)
29 AGUSTUS 2023
NO DESCRIPTION TOTAL VALUE (Rp)
A PEKERJAAN PENYAMBUNGAN DAYA LISTRIK Rp 32,967,000

B PEKERJAAN PANEL-PANEL Rp 90,320,017

C PEKERJAAN INSTALASI KABEL FEEDER Rp 61,806,149

D PEKERJAAN INSTALASI ROUTING KABEL FEEDER Rp 22,265,390

E PEKERJAAN INSTALASI LIGHTING & POWER RECEPTACLE GEDUNG UPT Rp 61,955,844

F PEKERJAAN WORKSHOP Rp 27,944,724

G PEKERJAAN OUTDOOR LIGHTING Rp 72,124,749

H PEKERJAAN LIGHTNING PROTECTION Rp 44,509,153

I PEKERJAAN GROUNDING SYSTEM Rp 87,492,168

J PEKERJAAN TESTING & COMMISIONING Rp 12,534,630

TOTAL Rp 513,919,825
TOTAL (ROUNDED) Rp 513,920,000