Anda di halaman 1dari 25

PT.

BINA SENTRA PURNA


Jalan Penjernihan II - Pejompongan

RENOVASI INTERIOR - EKSTERIOR


GEDUNG KATNOR PT. BINA SENTRA PURNA
JL. SAHARDJO - JAKARTA

DRAFT COSTPLAN

03062022
Alirkan Semangat Baru
u

REKAPITULASI RENCANA ANGGARAN DAN BIAYA

PEKERJAAN : RENOVASI RUANG INTERIOR LT.2 -SAYAP KANAN


DIVISI ADMINISTRASI UMUM DAN DIVISI SDM
LOKASI : KANTOR PUSAT PERUMDA AIR MINUM JAYA
JL. PENJERNIHAN II PEJOMPONGAN

JUMLAH
NO JENIS PEKERJAAN NILAI SUB PEKERJAAN
(Rp)

A PEKERJAAN PERSIAPAN Rp 69,768,164.00

B PEK. SISTEM MANAJEMEN KESELAMATAN KONSTRUKSI Rp 13,480,000.00

C PEK. AREA KERJA SEMENTARA Rp 134,860,000.00

D PEKERJAAN BONGKARAN Rp 94,733,900.00

E PEK. VAC AREA SEMENTARA Rp 55,989,304.00

SUB JUMLAH 368,831,368.00

A PEKERJAAN PLAFON Rp -

B PEKERJAAN PARTISI DAN DINDING Rp 172,187,270.55

C PEKERJAAN PINTU DAN JENDELA Rp 116,739,500.00

D PEKERJAAN LANTAI Rp 35,551,882.25

E PEKERJAAN PANEL Err:509

F PEKERJAAN LAMPU DAN INSTALASI Err:509

G ### Err:509

H ### Err:509

I PEKERJAAN VAC Err:509

J PEKERJAAN FURNITURE Err:509

K PENGADAAN KURSI Err:509

SUB. JUMLAH Err:509

JUMLAH Err:509

PPN 10% Err:509

TOTAL Err:509

DIBULATKAN Err:509

Jakarta, Maret 2022


DIREKTUR UMUM

TEDY J. SITEPU
REKAPITULASI COSTPLAN

PEKERJAAN : PERSIAPAN RENOVASI LT.2 -SAYAP KIRI


DIVISI INVESTASI DAN DIVISI TRANSISI & TRANSFORMASI
LOKASI : KANTOR PUSAT PERUMDA AIR MINUM JAYA
DATE : : 1/29/2023

JUMLAH
NO JENIS PEKERJAAN NILAI SUB PEKERJAAN
(Rp)

A PEKERJAAN PERSIAPAN Rp 69,768,164.00

B PEK. AREA KERJA SEMENTARA Rp 134,860,000.00

C PEKERJAAN BONGKARAN Rp 94,733,900.00

JUMLAH 299,362,064.00

JUMLAH 299,362,064.00
PPN 10% 29,936,206.40
TOTAL 329,298,270.40
JUMLAH TOTAL 329,200,000.00
REKAPITULASI RENCANA ANGGARAN DAN BIAYA
PEKERJAA : RENOVASI INTERIOR - EKSTERIOR
PT. BINA SENTRA PURNA
LOKASI : KANTOR PUSAT PT. BINA SENTRA PURNA
JL. DR. SAHARDJO, NO. 52

JUMLAH
NO JENIS PEKERJAAN NILAI PEKERJAAN

A PEKERJAAN PERSIAPAN Err:509


B ### 34,673,384.00
C PEKERJAAN BONGKARAN Err:509
D ### Err:509
SUB JUMLAH Err:509

A ### Err:509
B PEKERJAAN PLAFON & BLINDS #REF!
C PEKERJAAN PARTISI DAN DINDING 686,010,741.15
D PEKERJAAN RAILING TANGGA 272,464,270.00
E PEKERJAAN PINTU DAN JENDELA 502,615,200.00
F PEKERJAAN LANTAI 584,341,803.10
SUB JUMLAH Err:509

A PEKERJAAN PANEL 32,737,500.00


B PEKERJAAN LAMPU DAN INSTALASI 184,694,059.59
C PEKERJAAN JARINGAN KABEL DATA 66,869,840.60
D PEKERJAAN TATA SUARA 22,875,432.40
E PENGADAAN VAC 145,730,879.40
F PEKERJAAN TOILET 236,329,238.30
G PEKERJAAN PENANGKAL PETIR 18,168,100.00
H PEKERJAAN SPRINKLER 207,561,220.80
SUB JUMLAH 914,966,271.09

A PEKERJAAN FACADE 853,224,648.80


B PEKERJAAN PYLON SIGN 15,204,750.00
C PEKERJAAN AREA PARKIR 16,006,164.00
SUB. JUMLAH 884,435,562.80

JUMLAH Err:509
PPN 11% Err:509
TOTAL Err:509
DIBULATKAN Err:509
Jakarta, 9 Juni 2022

ANANTO AZIZ PRABOWO


Direktur Utama
RINCIAN RENCANA ANGGARAN DAN BIAYA
PEKERJAAN : RENOVASI INTERIOR - EKSTERIOR
PT. BINA SENTRA PURNA
LOKASI : KANTOR PUSAT PT. BINA SENTRA PURNA
JL. DR. SAHARDJO, NO. 52

BIDANG PEK. : ARSITEKTUR

NO KODE URAIAN PEKERJAAN VOL. Sat. Haga Satuan


A PEKERJAAN PERSIAPAN
1 Direksikeet 40 m2 596,728 0.7 417,709.60
Uk. 4 X 6m, Rangka hollow, multipleks, lkp elektrikal, AC dan Ruang Rapat Kecil 0.7 -
2 Listrik Kerja dan Air Kerja 2 bln 1,000,000 0.7 700,000.00
Listrik Kerja, Tapping dari eksisting dgn MCB tersendiri 0.7 -
3 Mobilisasi dan Demobilisasi 2 bln 1,950,000 0.7 1,365,000.00
Transportasi, akomodasi untuk personil dan peraltan 0.7 -
4 Pengadaan Protokol Kesehatan Covid-19 2 bln 1,675,000 0.7 1,172,500.00
Rambu-rambu, Pengarahan rutin, Prokes Covid-19 0.7 -
5 Kebersihan Area Kerja 2 bln 850,000 0.7 595,000.00
Lampu Penerangan, Scaffolding 0.7 -
6 Administrasi Pendukung 2 bln 1,000,000 0.7 700,000.00
Pelaporan, Dokumentasi 0.7
7 Pelaporan K3/HSE 5 set 1,000,000 0.7 700,000.00
Penerapan SMKK pada kegiatan resiko pekerjaan berbahaya rendah 0.7 -
8 Pekerjaan General Cleaning 540 m2 42,000 0.7 10,000.00
Pekerjaan Sebelum Serah Terima
JUM

B PEKERJAAN BONGKARAN
-
1 Bongkaran Plafon Eksisting Area POS 12.00 m2 55,600 0.97 53,932.00
Bongkar plafon eksisting, rangka dan peralatan MEP dipakai kembali 0.97 -
2 Bongkaran Instalasi Elektrikal Eksisting 12.00 m2 68,750 0.97 66,687.50

JUM

JUMLAH PEKERJAAN PERSIAPAN DAN BONGKA


Jumlah harga Total harga

16,708,384

1,400,000

2,730,000

2,345,000

1,190,000

1,400,000

3,500,000

5,400,000

JUMLAH 34,673,384

647,184

800,250

JUMLAH 1,447,434

JUMLAH PEKERJAAN PERSIAPAN DAN BONGKARAN 36,120,818


RINCIAN RENCANA ANGGARAN DAN BIAYA
.
PEKERJAAN :

LOKASI :

BIDANG PEK. : ARSITEKTUR

Haga Jumlah
NO KODE URAIAN PEKERJAAN VOL. Sat. Total harga
Satuan harga

B PEKERJAAN PLAFON
1 Plafon Interior POS 27 m2 162,960 4,399,920
Rangka hollow 40x40, gypsum board ex. Knauff 9mm -
2 Plafon PVC 149 m2 1,309,500 195,115,500
3 Finishing Pengecatan Plafon Interior 27 m2 72,750 1,964,250
Compund, flatering, cat ex. Dullux Interior, col : conform -
JUMLAH 201,479,670

C PEKERJAAN ATAP
1 ACP Penutup Ornamen - Sisi Depan 26 m2 1,406,500 36,569,000
ACP ex. Seven/Acotuff, col: confrm, rangka hollow, sesuai gambar -
2 ACP Penutup Ornamen - Sisi Kanan 13 m2 1,406,500 18,284,500
ACP ex. Seven/Acotuff, col: confrm, rangka hollow, sesuai gambar
3 ACP Penutup Ornamen - Sisi Kiri 13 m2 1,406,500 18,284,500
Compund, flatering, cat ex. Dullux Interior, col : conform -
4 Dak Beton Penutup Area Kamar Mandi & Wudhu 11 m2 171,690 1,931,513
Rangka hollow 40x40, GRC board ex. Kalsi 6mm -
5 Finishing Pengecatan Plafon POS 11 m2 63,050 709,313
Compund, flatering, cat ex. Dullux Interior, col : conform -
JUMLAH 75,778,825

PEKERJAAN DINDING
1 Pekerjaan Dinding Area Terbuka 12 m2 162,960 1,955,520
Dinding Bata Ringan, pperekat Mortar, plesteran dan acian -
2 Pekerjaan Dinding Loster Area Terbuka 18 m2 158,253 2,848,547
3 Pekerjaan Dinding Batu Alam 17.6 m2 158,253 2,791,576
5 Finishing Pengecatan Plafon Toilet #REF! m2 63,050 #REF!
Compund, flatering, cat ex. Dullux Interior, col : conform -
6 Pek Up CeIling 23 m2 162,960 3,748,080
Rangka hollow 40x40, gypsum board ex. Knauff 9mm -
JUMLAH #REF!

LANTAI 5
1 Plafon Interior Lantai Keseluruhan 145 m2 162,960 23,629,200
Rangka hollow 40x40, gypsum board ex. Knauff 9mm -
2 Drop Ceiling 130 m1 174,600 22,698,000
2 Liner Plafon Interior 244 m1 42,195 10,295,580
3 Finishing Pengecatan Plafon Interior 145 m2 63,050 9,142,250
Compund, flatering, cat ex. Dullux Interior, col : conform -
4 Plafon Interior Toilet 32 m2 171,690 5,494,080
Rangka hollow 40x40, GRC board ex. Kalsi 6mm -
5 Finishing Pengecatan Plafon Toilet 32 m2 63,050 2,017,600
Compund, flatering, cat ex. Dullux Interior, col : conform -
6 Plafond Grid Kotak-kotak 60x60 35 m2 268,690 9,404,150

JUMLAH 82,680,860

C PEK. ROLL BLIND


LANTAI 1
1 Pek. Wooden Blinds 28 m2 1,217,350 34,085,800
Wooden Blinds, 27mm ex. Sharp Point -
LANTAI 2 -
2 Pek. Roller Blinds 26 m2 703,250 18,284,500
Roller Blinds SP 88 Black Out ex. Sharp Point -
LANTAI 4 -
3 Pek. Roller Blinds 26 m2 703,250 18,284,500
Roller Blinds SP 88 Black Out ex. Sharp Point -
4 LANTAI 5 -
Pek. Wooden Blinds 33 m2 1,217,350 40,172,550
Wooden Blinds, 27mm ex. Sharp Point
Haga Jumlah
NO KODE URAIAN PEKERJAAN VOL. Sat. Total harga
Satuan harga
JUMLAH 110,827,350
JUMLAH PEKERJAAN PLAFON & BLINDS #REF!
PEKERJAAN PARTISI, DINDING DAN CAT
LANTAI 1
1 Finishing Dinding Granie Tile 102.0 m2 824,500 84,099,000
Granite Tile Area Lobby, motif : confirm -
2 Dinding Bata Ringan 84.2 m2 158,253 13,316,955
Dinding Bata Ringan, pperekat Mortar, plesteran dan acian -
3 Plin Lantai 194.1 m1 161,311 31,310,465
Plin Alumunium profil 100mm, fin cat minyak, col : conform -
4 Pek. Cat Dinding Interior R. Parkiran 609.00 m2 63,050 38,397,450
Cat ex. Dulux Interior, col : putih -
5 Pek. Granite Tile Dinding Toilet 12.00 m2 421,950 5,063,400
Granite 60x60, Tile ex. Roman/Setara, warna nuansa beige glossy -
JUMLAH 172,187,271

LANTAI 2
1 Partisi Gypsum 2 muka 38.0 m2 277,905 10,560,390
Partisi 2 muka, rangka hollow 40x40, gypsum board ex. Knauff 9mm -
2 Partisi Gypsum 1 muka 90.2 m2 182,748 16,491,180
Partisi 2 muka, rangka hollow 40x40, gypsum board ex. Knauff 9mm -
3 Dinding Bata Ringan 84.2 m2 158,253 13,316,955
Dinding Bata Ringan, pperekat Mortar, plesteran dan acian -
4 Plin Lantai 194.1 m1 161,311 31,310,465
Plin Alumunium profil 100mm, fin cat minyak, col : conform -
5 Pek. Cat Dinding Interior 170.04 m2 63,050 10,721,022
Cat ex. Dulux Interior, col : putih -
6 Pemasangan Wallpaper Meetin Room 12.0 m2 160,050 1,920,600
Wallpaper bertekstur, ex. Interwall, motif : confirm, pd dinding gypsum -
7 Pek. Granite Tile Dinding Toilet 185.70 m2 421,950 78,356,115
Granite 60x60, Tile ex. Roman/Setara, warna nuansa beige glossy -
8 Pek. Dinding Kaca Penutup Kolom 2.00 kolom 8,095,620 16,191,240
Rangka holloow 40/40, multipleks 6mm, Kaca Cermin Tinted 40% -
2 kolom, 100x40cm, t=300cm -
JUMLAH 178,867,967

LANTAI 4
1 Partisi Gypsum 2 muka 38.0 m2 277,905 10,560,390
Partisi 2 muka, rangka hollow 40x40, gypsum board ex. Knauff 9mm -
2 Partisi Gypsum 1 muka 90.2 m2 182,748 16,491,180
Partisi 2 muka, rangka hollow 40x40, gypsum board ex. Knauff 9mm -
3 Dinding Bata Ringan 84.2 m2 158,253 13,316,955
Dinding Bata Ringan, pperekat Mortar, plesteran dan acian -
4 Plin Lantai 194.1 m1 161,311 31,310,465
Plin Alumunium profil 100mm, fin cat minyak, col : conform -
5 Pek. Cat Dinding Interior 170.04 m2 63,050 10,721,022
Cat ex. Dulux Interior, col : putih -
6 Pemasangan Wallpaper Meeting Room 202.2 m2 160,050 32,368,512
Wallpaper bertekstur, ex. Interwall, motif : confirm, pd dinding gypsum -
7 Pek. Granite Tile Dinding Toilet 98.70 m2 421,950 41,646,465
Granite 60x60, Dranite Tile , warna nuansa beige glossy -
8 Pek. Dinding Kaca Penutup Kolom 2.00 set 8,095,620 16,191,240
Rangka holloow 40/40, multipleks 6mm, Kaca Cermin Tinted 40% -
2 kolom, 100x40cm, t=300cm -
JUMLAH 172,606,229

LANTAI 5
1 Partisi Gypsum 2 muka 38.0 m2 277,905 10,560,390
Partisi 2 muka, rangka hollow 40x40, gypsum board ex. Knauff 9mm -
2 Partisi Gypsum 1 muka 90.2 m2 182,748 16,491,180
Partisi 2 muka, rangka hollow 40x40, gypsum board ex. Knauff 9mm -
3 Dinding Bata Ringan R. Toilet 84.2 m2 158,253 13,316,955
Dinding Bata Ringan, pperekat Mortar, plesteran dan acian -
4 Plin Lantai 194.1 m1 86,330 16,756,653
Plin Lantai Plywood 10mm T:100mm, Fin. HPL Gelap -
5 Pek. Cat Dinding Interior 77.00 m2 63,050 4,854,850
Cat ex. Dulux Interior, col : putih -
6 Pek. Ornamen Back Drop R. Function Hall 116.0 m2 800,250 92,829,000
Plywood 12 mm, U Channel, Rangka Hollow 4x4 Galvanis, Fin. HPL Motif Kayu Matte -
7 Pek. Granite Tile Dinding Toilet 12.44 m2 421,950 5,249,058
Granite 60x60, Tile Granite, warna nuansa beige glossy -
8 Pek. Granite Tile Lantai Toilet 5.4 m2 421,950 2,291,189
Granite 60x60, Tile Granite warna nuansa abu-abu matte
JUMLAH 162,349,274
PEKERJAAN PARTISI, DINDING DAN CAT 686,010,741

D PEKERJAAN RAILING TANGGA


LANTAI 1
Haga Jumlah
NO KODE URAIAN PEKERJAAN VOL. Sat. Total harga
Satuan harga
1 Railing Tangga 18.40 m1 1,891,500 34,803,600
Stainless Kaca Temperd Handgrip Kayu Profil -
-
2 Handgrip Railing 18.40 unt 664,450 12,225,880
Handgrip Kayu Profil 50x70mm, fin. Melamik semi gloss

JUMLAH 47,029,480

LANTAI 2
1 Railing Tangga 21.70 m1 1,891,500 41,045,550
Stainless Kaca Temperd Handgrip Kayu Profil -
2 Handgrip Railing 21.70 unt 664,450 14,418,565
Handgrip Kayu Profil 50x70mm, fin. Melamik semi gloss -

JUMLAH 55,464,115

LANTAI 3
1 Railing Tangga 21.70 m1 1,891,500 41,045,550
Stainless Kaca Temperd Handgrip Kayu Profil -
2 Handgrip Railing 21.70 unt 664,450 14,418,565
Handgrip Kayu Profil 50x70mm, fin. Melamik semi gloss -

JUMLAH 55,464,115

LANTAI 4
1 Railing Tangga 21.70 m1 1,891,500 41,045,550
Stainless Kaca Temperd Handgrip Kayu Profil -
2 Handgrip Railing 21.70 unt 664,450 14,418,565
Handgrip Kayu Profil 50x70mm, fin. Melamik semi gloss -

JUMLAH 55,464,115

LANTAI 5
1 Railing Tangga 23.10 m1 1,891,500 43,693,650
Stainless Kaca Temperd Handgrip Kayu Profil -
2 Handgrip Railing 23.10 unt 664,450 15,348,795
Handgrip Kayu Profil 50x70mm, fin. Melamik semi gloss -

JUMLAH 59,042,445
PEKERJAAN RAILING TANGGA 272,464,270

E PEKERJAAN PINTU DAN JENDELA


plafon
1 Pintu PK1 - Pintu Lobby (Automatic Door) 1 unt 51,167,500 51,167,500
Automatic Door 2 Daun, ex. Dorma, Daun Pintu Kaca Tempered 12mm -
2 Penggatian kaca temperd area Lobby 12mm 25 m2 1,309,500 32,737,500
Tempered Glass 12mm, lapis sunblast -
3 Penggatian kaca temperd area Lobby 12mm 12 m2 1,309,500 15,714,000
4 Perapihan Pintu Garasi 2 unt 4,850,000 9,700,000
Repaint Ducco Glasso Venish -
5 Pekerjaan Hidden Door 1 unt 7,420,500 7,420,500
Pintu Plywood, 80cm, Concealed Hinges, rangka Kayu Meranti, fin.HPL
JUMLAH 116,739,500

LANTAI 2
1 Pintu PK3 - Pintu Ruang Rapat 1 unt 9,215,000 9,215,000
Pintu 1 Daun Frameless, 70cm, Tempered Glass 10mm, lapis sunblast -
Partisi Kaca di sisi kiri kanan pintu, Door Handle, engsel ex. Deksson -
2 Pintu PK5 - Pintu dan Partisi Ruang Server 1 unt 19,012,000 19,012,000
Pintu 1 Daun Frameless, 70cm, Tempered Glass 10mm, lapis sunblast -
Aksesoris ex. Deksson, partisi kaca tempered 10mm, lapis sunblast -
3 Partisi PT2 (Partisi R. Rapat - Sisi Timur) 1 unt 16,975,000 16,975,000
Pintu 2 Daun Frameless, 70cm, Tempered Glass 10mm, lapis sunblast -
Partisi Gypsum 9mm, Rangka Hollow 40/40 - Fin. Wallpaper, -
4 Partisi PT3 (Partisi R. Rapat - Sisi Utara) 1 unt 26,675,000 26,675,000
Pintu 2 Daun Frameless, 70cm, Tempered Glass 10mm, lapis sunblast -
Partisi Gypsum 9mm, Rangka Hollow 40/40 - Fin. Wallpaper, -
5 Partisi PT4 (Partisi Tangga - Sisi Utara) 1 unt 22,795,000 22,795,000
Pintu 2 Daun Frameless, 70cm, Tempered Glass 10mm, lapis sunblast -
6 Partisi PT5 (Partisi Tangga - Sisi Barat) 1 unt 13,095,000 13,095,000
Pintu 2 Daun Frameless, 70cm, Tempered Glass 10mm, lapis sunblast -
7 Partisi PT6 (Partisi Tangga - Sisi Selatan) 1 unt 16,247,500 16,247,500
Pintu 2 Daun Frameless, 70cm, Tempered Glass 10mm, lapis sunblast -
Partisi kaca tempered 10mm, lapis sunblast -
8 Pekerjaan Pintu Plywood PK7 2 unt 4,219,500 8,439,000
Pintu Plywood, 80cm, rangka multipleks 20mm, ex.Dekkson fin. HPL
JUMLAH 132,453,500
Haga Jumlah
NO KODE URAIAN PEKERJAAN VOL. Sat. Total harga
Satuan harga
LANTAI 4
1 Pintu PK3 - Pintu Ruang Rapat 1 unt 9,215,000 9,215,000
Pintu 1 Daun Frameless, 70cm, Tempered Glass 10mm, lapis sunblast -
Partisi Kaca di sisi kiri kanan pintu, Door Handle, engsel ex. Deksson -
2 Partisi PT2 (Partisi R. Rapat - Sisi Timur) 1 unt 16,975,000 16,975,000
Partisi Tempered Glass 10mm, lapis sunblast -
Partisi Gypsum 9mm, Rangka Hollow 40/40 - Fin. Wallpaper, -
3 Partisi PT3 (Partisi R. Rapat - Sisi Utara) 1 unt 26,675,000 26,675,000
Partisi Tempered Glass 10mm, lapis sunblast -
Partisi Gypsum 9mm, Rangka Hollow 40/40 - Fin. Wallpaper, -
4 Partisi PT4 (Partisi Tangga - Sisi Utara) 1 unt 22,795,000 22,795,000
Partisi Tempered Glass 10mm, lapis sunblast -
5 Partisi PT5 (Partisi Tangga - Sisi Barat) 1 unt 13,095,000 13,095,000
Partisi Tempered Glass 10tmm, lapis sunblast -
6 Partisi PT6 (Partisi Tangga - Sisi Selatan) 1 unt 16,247,500 16,247,500
Partisi Tempered Glass 10mm, lapis sunblast -
Partisi kaca tempered 10mm, lapis sunblast -
8 Pekerjaan Pintu Plywood PK7 2 unt 4,219,500 8,439,000
Pintu Plywood, 80cm, rangka multipleks 20mm, ex.Dekkson fin. HPL
JUMLAH 113,441,500
LANTAI 5
1 Folding Partition Glass 30 m2 2,570,500 78,143,200
Kaca Tempered 12 mm, Frame Alumunium Fin. Powder Coating Black/ Grey -
2 Partisi PT-8 (Partisi R. File - di bekas area gudang ATK) 1 unt 26,529,500 26,529,500
Pintu 1 Daun Frameless,, Partisi Tempered Glass 10mm, lapis sunblast -
Partisi Gypsum 9mm, Rangka Hollow 40/40 - Fin. Wallpaper, -
3 Partisi PT-11 (Partisi Kaca Entrance Tangga) 2 unt 9,215,000 18,430,000
Pintu 2 Daun Frameless, 70cm, Partisi Tempered Glass 10mm, ex. Dekkson -
lapis sunblast -
4 Pekerjaan Pintu Plywood PK7 4 unt 4,219,500 16,878,000
Pintu Plywood, 80cm, rangka multipleks 20mm, ex.Dekkson fin. HPL

JUMLAH 139,980,700
PEKERJAAN PINTU DAN JENDELA 502,615,200

F PEKERJAAN LANTAI
LANTAI 1 ###
1 Pek. Screeding dan Leveling Lantai 58.0 m2 76,242 4,422,036
2 Pek. Granite Tile GT1 27.8 m2 742,050 20,628,990
Granite 60x60, warna nuansa beige, glossy -
3 Pek. Granite Tile GT2 8.6 m2 742,050 6,344,528
Granite 60x60, warna nuansa abu-abu matte -
4 Pek. Lantai Parket Vinyl 9.5 m2 274,753 2,610,149
Nuansa warna kayu, ex. TACO, motif : confirm, terpasang -
5 Pek. Granite Tile Lantai Toilet 4.0 m2 386,545 1,546,180
Granite 60x60, warna nuansa abu-abu matte

JUMLAH 35,551,882

LANTAI 2
1 Pek. Screeding dan Leveling dak Lantai 228.0 m2 76,242 17,383,176
2 Pek. Granite Tile GT1 101.5 m2 742,050 75,318,075
Granite 60x60, warna nuansa beige, glossy -
3 Pek. Granite Tile GT2 12.5 m2 742,050 9,275,625
Granite 60x60, warna nuansa abu-abu matte -
4 Pek. Lantai Parket Vinyl 114.0 m2 274,753 31,321,785
Nuansa warna kayu, ex. TACO, motif : confirm, terpasang -
5 Pek. Carpet tile - R Rapat Besar 36.0 m2 383,150 13,793,400
Nuansa Abu Tua, ex. Victory/Setara -
7 Pek. Granite Tile Lantai Toilet 18.8 m2 386,545 7,267,046
Granite 60x60, Tile ex. Roman/Setara, warna nuansa abu-abu matte

JUMLAH 154,359,107

LANTAI 4
1 Pek. Screeding dan Leveling dak Lantai 177.0 m2 76,242 13,494,834
2 Pek. Granite Tile GT1 20.3 m2 742,050 15,063,615
Granite 60x60, warna nuansa beige, glossy -
3 Pek. Granite Tile GT2 12.5 m2 742,050 9,275,625
Granite 60x60, warna nuansa abu-abu matte -
4 Pek. Lantai Parket Vinyl 144.2 m2 274,753 39,619,311
Nuansa warna kayu, ex. TACO, motif : confirm, terpasang -
5 Pek. Carpet tile - R Rapat Besar 36.0 m2 383,150 13,793,400
Nuansa Abu Tua, ex. Victory/Setara -
6 Pek. Granite Tile Lantai Toilet 6.8 m2 386,545 2,628,506
Granite 60x60, Tile ex. Roman/Setara, warna nuansa abu-abu matte

JUMLAH 93,875,291
Haga Jumlah
NO KODE URAIAN PEKERJAAN VOL. Sat. Total harga
Satuan harga

LANTAI 5
1 Pek. Screeding dan Leveling dak Lantai 177.0 m2 76,242 13,494,834
2 Peninggian Lantai T=50mm R. Function Hall Mini Stage -
Spesifikasi : Rangka Hollow 20X40 Lapis Plywood 18 mm 26 m2 824,500 21,437,000
3 Pek. Carpet tile - R Function Hall Mini Stage 26 m2 383,150 9,961,900
Nuansa Abu Tua, ex. Victory/Setara -
4 Pek. Pengadaan Mimbar 1 unit 4,365,000 4,365,000
Mimbar Plywood 12 mm, T:1000mm, Fin. HPL Matte -
5 Pek. Granite Tile GT1 110.0 m2 742,050 81,625,500
Granite 80X80, warna nuansa beige, glossy -
6 Pek. Granite Tile GT2 53.8 m2 742,050 39,922,290
Granite 60x60, warna nuansa abu-abu matte -
7 Pek. Lantai Granit Border 13.2 m2 742,050 9,795,060
Nuansa warna Black Matte ex. Infinity/ Sandimas, motif : confirm, terpasang -
8 Pek. Lantai Granite Tile Motif Kayu 66.0 m2 742,050 48,975,300
Nuansa warna Kayu ex. Infinity/ Sandimas, motif : confirm, terpasang -
9 Pek. Lantai Granite Tile Motif Solid 18.0 m2 742,050 13,356,900
Nuansa warna Black Matte ex. Infinity/ Sandimas, motif : confirm, terpasang -
10 Pek. Granite Tile Lantai Toilet 5.4 m2 386,545 2,098,939
Granite 60x60, Tile ex. Roman/Setara, warna nuansa abu-abu matte -
11 Pek. Batu Gravel Tebar R. Outdoor 52 m2 121,250 6,305,000
12 Pek. Bench Concrete R. Outdoor 8.3 m' 1,164,000 9,661,200
Spesiifikasi Concrete D10 - 15, Fin. Expose Concrete -
13 Pek. Lantai Precast Concrete R. Outdoor 8.0 unit 567,450 4,539,600
Precast 60 x 60 D10-15, Fin, Expose Concrete -
14 Pek. Planter Box R.outdoor 2 unit 533,500 1,067,000
Precast Concrete 100 x40, Fin. Expose Concrete -
15 Pek. Vertical Garden R. Outdoor 28 m2 1,212,500 33,950,000
Spesifikasi : Veritical Garden, Pilo Dendrum, Hollow 4x4 + Kawat Ram
JUMLAH 300,555,523
PEKERJAAN LANTAI 584,341,803
BIDANG PEK. : PENGADAAN FURNITURE

Haga Satuan
NO KODE URAIAN PEKERJAAN VOL. Sat. Jumlah harga (Rp.) Total harga (Rp.)
(Rp.)

A PEKERJAAN FURNITURE
1 Meja Workstation 6 kursi (WS-2) - Logan WS6 6 unt
Workstation lengkap, 6 seat, customade sesuai gambar,
lkp receptacle 6 set dan instalasi elektrikal
2 1 set Meja Senior Manajer (WS-1) - Grado LN1-H 2 unt
Meja workstation lengkap, customade sesuai gambar,
lkp mobile drawer 40cm, receptacle dan instalasi elektrikal
3 Lemari File (LF-2) 2 unt
Lemari File Senior Manager ex. Stramm Uk 160x40x8cm
4 1 set Meja Sekretaris (WS-3) - Matteo LF1-H 2 unt
Meja workstation lengkap, customade sesuai gambar,
lkp receptacle dan instalasi elektrikal
5 1 set Meja Manajer (MGR-01) - Logan WS4 1 unt
Meja workstation lengkap, 4 seat, customade sesuai gambar,
lkp meja bundar dan receptacle serta instalasi elektrikal
6 1 set Meja Manajer (MGR-02) - Logan WS4 4 unt
Meja workstation lengkap, 4 seat, customade sesuai gambar,
lkp meja bundar dan receptacle serta instalasi elektrikal
7 Mobile Drawer (MDR-1) - MDW 01-H 50 unt
Rak Mobile Drawer (L=50Cm, W=40cm, H=60cm)
8 Lemari File (LF-1) - Lilo PV3B 804019 26 unt
Lemari Arsip ex. Stramm tipe Uk 160x40x87cm MAPLE
9 Meja Rapat Kecil/Bundar (MR-03) 2 unt
Meja Rapat Bulat, dia. 100cm, sesuai gambar - MSG 01-H
10 Meja Rapat 12 kursi - MR-C OJKPKBR 1 set
Meja Meeting Persegi,sesuai gambar
11 Lemari Loker (LF-02) - Lilo PV3B 804019 8 unt
Lemari Arsip ex. Stramm tipe Uk 160x40x87cm MAPLE

JUMLAH PEKERJAAN FURNITURE -

B PENGADAAN KURSI
1 Kursi Senior Manajer 2 unt
Kursi Kantor ex. Stramm tipe Ramos I Gar Synch SL TC Bmet
2 Kursi Manajer / R. Rapat 24 unt
Kursi Kantor ex. Stramm tipe Ramos II Gar Synch SL TC Bmet
3 Kursi Hadap 60 unt
Kursi Kantor ex. Stramm tipe Marino Gar
4 Sofa Tamu 4 unt
Sofa 2 Dudukan ex. Stramm, tipe : Becker 2 Seater
5 Meja Tamu (Coffee Table) 2 unt
ex. Stramm, tipe :Torres Coffee Table
6 Kursi Kolaborasi 2 seater 4 unt
ex. Stramm, tipe : Napoli III WS2
7 Meja Coffe Table Kolaborasi 2 unt
ex. Stramm, tipe : Glacia Cooffee Table

JUMLAH PENGADAAN KURSI -


JUMLAHPENGADAAN FURNITURE -
TOTAL

BIDANG PEK. : PENGADAAN FURNITURE

Haga Satuan
NO KODE URAIAN PEKERJAAN VOL. Sat. Jumlah harga (Rp.) Total harga (Rp.)
(Rp.)

A PEKERJAAN FURNITURE
1 Meja Workstation 6 kursi (WS-2) - Logan WS6 6 unt 36,090,000 216,540,000
Workstation lengkap, 6 seat, customade sesuai gambar,
lkp receptacle 6 set dan instalasi elektrikal
2 1 set Meja Senior Manajer (WS-1) - Grado LN1-H 2 unt 14,050,000 28,100,000
Meja workstation lengkap, customade sesuai gambar,
lkp mobile drawer 40cm, receptacle dan instalasi elektrikal
3 Lemari File (LF-2) 2 unt 8,550,000 17,100,000
Lemari File Senior Manager ex. Stramm Uk 160x40x8cm
4 1 set Meja Sekretaris (WS-3) - Matteo LF1-H 2 unt 8,930,000 17,860,000
RRNCIAN RENCANA ANGGARAN DAN BIAYA

PEKERJAAN : RENOVASI INTERIOR - EKSTERIOR


PT. BINA SENTRA PURNA
LOKASI : KANTOR PUSAT PT. BINA SENTRA PURNA
JL. DR. SAHARDJO, NO. 52

BIDANG PEK. : MEKANIKAL ELEKTRIKAL

NO KODE URAIAN PEKERJAAN VOL. Sat. Haga Satuan Jumlah harga Total harga

A I PEKERJAAN PANEL
LANTAI 1
1 Pek. Perubahan Pembagian MCB Panel Lantai 1 1 unt 6,547,500 6,547,500
2 Pek. Perubahan Pembagian MCB Panel Lantai 2 1 unt 6,547,500 6,547,500
3 Pek. Perubahan Pembagian MCB Panel Lantai 3 1 unt 6,547,500 6,547,500
4 Pek. Perubahan Pembagian MCB Panel Lantai 4 1 unt 6,547,500 6,547,500
5 Pek. Perubahan Pembagian MCB Panel Lantai 5 1 unt 6,547,500 6,547,500
JUMLAH 32,737,500
PEKERJAAN PANEL 32,737,500

B PEKERJAAN LAMPU DAN INSTALASI


LANTAI 1
1 Lampu Down light LED 5 Watt (Area Lobby) 14 unt 211,025 2,954,346
Armatur Downlight 5" ex. Philips, bulb LED Philips White -
2 Lampu Down light LED 5 Watt, outbow, (Area Exterior) 10 unt 211,025 2,110,247
Armatur Downlight 3" ex. Philips, bulb LED Philips White -
3 Lampu Spot Lettering Façade 5 unt 635,350 3,176,750
Armatur Outdoor Spotlight LED 3" ex. Philips, bulb LED Philips White -
4 Lampu Pylon Sign 1 unt 111,550 111,550
LED Ribbon Outdoor -
5 Saklar Ganda 6 unt 115,364 692,184
Saklar Ganda ex. Panasonic, tipe : confirm -
6 Stop Kontak dinding Tunggal 6 unt 177,528 1,065,171
Stop Kontak Tunggal ex. Panasonic, tipe : confirm -
7 Stop Kontak AC 2 unt 177,528 355,057
Stop Kontak Tunggal ex. Panasonic, tipe : confirm -
8 Stop Kontak Exhaust 3 unt 177,528 532,585
Stop Kontak Tunggal ex. Panasonic, tipe : confirm -
9 Instalasi Lampu 30 ttk 284,210 8,526,300
Kabel NYM 3 x 2,5 mm ex. Kabelindo, pipa conduit ex. Ega / Boss -
10 Instalasi Saklar Ganda, 6 ttk 284,210 1,705,260
Kabel NYM 3 x 2,5 mm ex. Kabelindo, pipa conduit ex. Ega/Boss -
11 Instalasi Stop Kontak dinding Tunggal 6 ttk 284,210 1,705,260
Kabel NYM 3 x 2,5 mm ex. Kabelindo, pipa conduit ex. Ega/Boss -
12 Instalasi Stop Kontak WIFI di atas plafon 2 ttk 284,210 568,420
Kabel NYM 3 x 2,5 mm ex. Kabelindo, pipa conduit ex. Ega/Boss -
13 Instalasi Stop Kontak AC 2 ttk 284,210 568,420
Kabel NYM 3 x 2,5 mm ex. Kabelindo, pipa conduit ex. Ega/Boss -
14 Instalasi Stop Kontak Exhaust 3 ttk 284,210 852,630
Kabel NYM 3 x 2,5 mm ex. Kabelindo, pipa conduit ex. Ega/Boss -
15 Kaca Cermnin Vanity Table 1 ls 2,774,200 2,774,200
Cermin 5mm, 70x10cm, base multipleks6mm, backligt LED Ribbon -
LANTAI 1 27,698,380

LANTAI 2
1 Lampu Down light LED 5 Watt (Ruang Kerja dan Ruang Rapat) 32 unt 183,500 5,871,992
Armatur Downlight 5" ex. Philips, bulb LED Philips White -
2 Lampu Down light LED 5 Watt, outbow, (Area Ceiling Lobby) 8 unt 216,814 1,734,515
Armatur Downlight 5" ex. Philips, bulb LED Philips White -
4 Saklar Ganda 18 unt 115,364 2,076,553
Saklar Ganda ex. Panasonic, tipe : confirm -
5 Stop Kontak dinding Tunggal 18 unt 177,528 3,195,512
Stop Kontak Tunggal ex. Panasonic, tipe : confirm -
6 Stop Kontak AC 6 unt 177,528 1,065,171
Stop Kontak Tunggal ex. Panasonic, tipe : confirm -
7 Stop Kontak Exhaust 4 unt 177,528 710,114
Stop Kontak Tunggal ex. Panasonic, tipe : confirm -
8 Instalasi Lampu 41 ttk 334,650 13,720,650
Kabel NYM 3 x 2,5 mm ex. Kabelindo, pipa conduit ex. Ega / Boss -
9 Instalasi Saklar Ganda, 18 ttk 334,650 6,023,700
Kabel NYM 3 x 2,5 mm ex. Kabelindo, pipa conduit ex. Ega/Boss -
10 Instalasi Stop Kontak dinding Tunggal 18 ttk 334,650 6,023,700
Kabel NYM 3 x 2,5 mm ex. Kabelindo, pipa conduit ex. Ega/Boss -
11 Instalasi Stop Kontak WIFI di atas plafon 2 ttk 334,650 669,300
Kabel NYM 3 x 2,5 mm ex. Kabelindo, pipa conduit ex. Ega/Boss -
12 Instalasi Stop Kontak AC 6 ttk 334,650 2,007,900
Kabel NYM 3 x 2,5 mm ex. Kabelindo, pipa conduit ex. Ega/Boss -
NO KODE URAIAN PEKERJAAN VOL. Sat. Haga Satuan Jumlah harga Total harga
13 Instalasi Stop Kontak Exhaust 4 ttk 334,650 1,338,600
Kabel NYM 3 x 2,5 mm ex. Kabelindo, pipa conduit ex. Ega/Boss -
14 Pek. Cable Tray 14 m1 314,125 4,397,747
Cable Tray 200X50X3000, lengkap elbow dan T, hanger, terpasang -
15 Kaca Cermnin Vanity Table 1 ls 2,774,200 2,774,200
Cermin 5mm, 70x10cm, base multipleks6mm, backligt LED Ribbon -
LANTAI 2 51,609,653

LANTAI 4
1 Lampu Down light LED 5 Watt (Area Plafon) 32 unt 183,500 5,871,992
Armatur Downlight 5" ex. Philips, bulb LED Philips White -
2 Lampu Down light LED 5 Watt, outbow, (Area Expossed Ceiling) 16 unt 183,500 2,935,996
Armatur Downlight 5" ex. Philips, bulb LED Philips White -
4 Saklar Ganda 12 unt 115,364 1,384,368
Saklar Ganda ex. Panasonic, tipe : confirm -
5 Stop Kontak dinding Tunggal 10 unt 177,528 1,775,284
Stop Kontak Tunggal ex. Panasonic, tipe : confirm -
6 Stop Kontak AC 6 unt 177,528 1,065,171
Stop Kontak Tunggal ex. Panasonic, tipe : confirm -
7 Stop Kontak Exhaust 4 unt 177,528 710,114
Stop Kontak Tunggal ex. Panasonic, tipe : confirm -
8 Instalasi Lampu 49 ttk 334,650 16,397,850
Kabel NYM 3 x 2,5 mm ex. Kabelindo, pipa conduit ex. Ega / Boss -
9 Instalasi Saklar Ganda, 12 ttk 334,650 4,015,800
Kabel NYM 3 x 2,5 mm ex. Kabelindo, pipa conduit ex. Ega/Boss -
10 Instalasi Stop Kontak dinding Tunggal 10 ttk 334,650 3,346,500
Kabel NYM 3 x 2,5 mm ex. Kabelindo, pipa conduit ex. Ega/Boss -
11 Instalasi Stop Kontak WIFI di atas plafon 2 ttk 334,650 669,300
Kabel NYM 3 x 2,5 mm ex. Kabelindo, pipa conduit ex. Ega/Boss -
12 Instalasi Stop Kontak AC 6 ttk 334,650 2,007,900
Kabel NYM 3 x 2,5 mm ex. Kabelindo, pipa conduit ex. Ega/Boss -
13 Instalasi Stop Kontak Exhaust 4 ttk 334,650 1,338,600
Kabel NYM 3 x 2,5 mm ex. Kabelindo, pipa conduit ex. Ega/Boss -
14 Pek. Cable Tray 22 m1 314,125 6,910,746
Cable Tray 50x200, lengkap elbow dan T, hanger, terpasang -
15 Kaca Cermnin Vanity Table 1 ls 2,774,200 2,774,200
Cermin 5mm, 70x10cm, base multipleks6mm, backligt LED Ribbon -
LANTAI 4 51,203,821

LANTAI 5
1 Lampu Down light LED 5 Watt (Area Plafon) 32 unt 183,500 5,871,992
Armatur Downlight 5" ex. Philips, bulb LED Philips White -
2 Lampu Down light LED 5 Watt, outbow, (Area Expossed Ceiling) 16 unt 183,500 2,935,996
Armatur Downlight 5" ex. Philips, bulb LED Philips White -
Lampu LED Ribbon, inderect, (Area Up-Ceiling) 23 m 114,945 2,643,735
LED Ribbon, lengkap trafo terpasang -
3 Saklar Ganda 12 unt 115,364 1,384,368
Saklar Ganda ex. Panasonic, tipe : confirm -
5 Stop Kontak dinding Tunggal 10 unt 177,528 1,775,284
Stop Kontak Tunggal ex. Panasonic, tipe : confirm -
4 Stop Kontak AC 6 unt 177,528 1,065,171
Stop Kontak Tunggal ex. Panasonic, tipe : confirm -
5 Stop Kontak Exhaust 4 unt 177,528 710,114
Stop Kontak Tunggal ex. Panasonic, tipe : confirm -
6 Instalasi Lampu 50 ttk 334,650 16,732,500
Kabel NYM 3 x 2,5 mm ex. Kabelindo, pipa conduit ex. Ega / Boss -
7 Instalasi Saklar Ganda, 12 ttk 334,650 4,015,800
Kabel NYM 3 x 2,5 mm ex. Kabelindo, pipa conduit ex. Ega/Boss -
8 Instalasi Stop Kontak dinding Tunggal 10 ttk 334,650 3,346,500
Kabel NYM 3 x 2,5 mm ex. Kabelindo, pipa conduit ex. Ega/Boss -
9 Instalasi Stop Kontak WIFI di atas plafon 2 ttk 334,650 669,300
Kabel NYM 3 x 2,5 mm ex. Kabelindo, pipa conduit ex. Ega/Boss -
10 Instalasi Stop Kontak AC 6 ttk 334,650 2,007,900
Kabel NYM 3 x 2,5 mm ex. Kabelindo, pipa conduit ex. Ega/Boss -
11 Instalasi Stop Kontak Exhaust 4 ttk 334,650 1,338,600
Kabel NYM 3 x 2,5 mm ex. Kabelindo, pipa conduit ex. Ega/Boss -
12 Pek. Cable Tray 22 m1 314,125 6,910,746
Cable Tray 50x200, lengkap elbow dan T, hanger, terpasang -
13 Kaca Cermnin Vanity Table 1 ls 2,774,200 2,774,200
Cermin 5mm, 70x10cm, base multipleks6mm, backligt LED Ribbon -
LANTAI 5 54,182,206
PEKERJAAN LAMPU DAN INSTALASI 184,694,060

C PEKERJAAN JARINGAN KABEL DATA


LANTAI 2
1 Pek. Kabel Data 42 line 469,383 19,714,086
Cable Data UTP Cat.6, ex. AMP -
2 Pek. Pipa Conduit Bawah lantai 42 unt 149,671 6,286,182
3 Pek. Patch Cord 42 unt 84,254 3,538,676
Patch Cord 7 feet, ex. AMP -
4 Pek. Labeling Kabel Data 42 set 45,202 1,898,484
LANTAI 2 31,437,428
LANTAI 4
1 Pek. Kabel Data 42 line 469,383 19,714,086
NO KODE URAIAN PEKERJAAN VOL. Sat. Haga Satuan Jumlah harga Total harga
Cable Data UTP Cat.6, ex. AMP -
2 Pek. Pipa Conduit Bawah lantai 42 unt 149,671 6,286,182
3 Pek. Patch Cord 42 unt 84,254 3,538,676
Patch Cord 7 feet, ex. AMP -
4 Pek. Labeling Kabel Data 42 set 45,202 1,898,484
LANTAI 4 31,437,428
LANTAI 5
1 Pek. Kabel Data 4 line 469,383 1,877,532
Cable Data UTP Cat.6, ex. AMP -
2 Pek. Pipa Conduit Bawah lantai 4 unt 149,671 598,684
3 Pek. Pipa Conduit Diatas Plafon utk Access Point Wifi 1 unt 149,671 149,671
4 Pek. Patch Cord 4 unt 84,254 337,017
Patch Cord 7 feet, ex. AMP -
5 Pek. Labeling Kabel Data 4 set 45,202 180,808
6 Access Point Wifi 1 set 851,272 851,272
Acces Point Diatas Plafon, lngkap terpasang
LANTAI 5 3,994,984
PEKERJAAN JARINGAN KABEL DATA 66,869,841

D PEKERJAAN TATA SUARA


LANTAI 1
1 Pek. Ceiling Speaker 3 unt 627,415 1,882,246
Speaker 6W, ex. TOA, Ceiling Mounted, terpasang -
2 Pek. Instalalasi Kabel Tata Suara 3 ttk 286,150 858,450
Kabel NYM 2 x1,5, Lengkap Dengan Conduit ex. Ega/Boss -
3 Instalasi Anouncer Aplifier 1 et 3,690,559 3,690,559
Announcer Amplifier, ex. Bose

LANTAI 1 6,431,255

LANTAI 2
1 Pek. Ceiling Speaker 5 unt 627,415 3,137,077
Speaker 6W, ex. TOA, Ceiling Mounted, terpasang -
2 Pek. Instalalasi Kabel Tata Suara 5 ttk 286,150 1,430,750
Kabel NYM 2 x1,5, Lengkap Dengan Conduit ex. Ega/Boss
LANTAI 2 4,567,827

LANTAI 3
1 Pek. Ceiling Speaker 3 unt 627,415 1,882,246
Speaker 6W, ex. TOA, Ceiling Mounted, terpasang -
2 Pek. Instalalasi Kabel Tata Suara 3 ttk 286,150 858,450
Kabel NYM 2 x1,5, Lengkap Dengan Conduit ex. Ega/Boss
LANTAI 3 2,740,696

LANTAI 4
1 Pek. Ceiling Speaker 5 unt 627,415 3,137,077
Speaker 6W, ex. TOA, Ceiling Mounted, terpasang -
2 Pek. Instalalasi Kabel Tata Suara 5 ttk 286,150 1,430,750
Kabel NYM 2 x1,5, Lengkap Dengan Conduit ex. Ega/Boss
LANTAI 4 4,567,827

LANTAI 5
1 Pek. Ceiling Speaker 5 unt 627,415 3,137,077
Speaker 6W, ex. TOA, Ceiling Mounted, terpasang -
2 Pek. Instalalasi Kabel Tata Suara 5 ttk 286,150 1,430,750
Kabel NYM 2 x1,5, Lengkap Dengan Conduit ex. Ega/Boss
LANTAI 5 4,567,827
Pek. Patch Cord 22,875,432

E PENGADAAN VAC
LANTAI 1
1 Pek. Reposisi AC Split Eksisting 1 unt 637,115 637,115
Bongkar pasang, Service, reposisi indoor dan outdoor -
2 Pek. Penggantian Pipa Refrigerant 8 m2 196,270 1,570,158
Pipa Refrigerant standar, non inverter -
3 Pek. Exhaust Fan 4 unt 782,654 3,130,617
Exhaust Fan, ceiling mounted, 120 CFM ex. KDK, Sekai -
4 Pek. Ducting Exhaust Fan 4 set 219,802 879,208
BJLS ducting dengan insulator, -
5 Pek. Grill Exhaust Fan 4 unt 397,700 1,590,800
6 Pek. Testing & Comissioning 1 ls 1,455,000 1,455,000
LANTAI 1 9,262,899

LANTAI 2
1 Pek. Reposisi AC Split Eksisting 8 unt 637,115 5,096,923
Bongkar pasang, Service, reposisi indoor dan outdoor -
2 Pek. Penggantian Pipa Refrigerant 64 m2 196,270 12,561,267
Pipa Refrigerant standar, non inverter -
3 Pek. Exhaust Fan 4 unt 776,000 3,104,000
Exhaust Fan, ceiling mounted, 120 CFM ex. KDK, Sekai -
4 Pek. Ducting Exhaust Fan 4 set 223,100 892,400
BJLS ducting dengan insulator, -
5 Pek. Grill Exhaust Fan 4 unt 397,700 1,590,800
6 Pek. Testing & Comissioning 1 ls 1,455,000 1,455,000
NO KODE URAIAN PEKERJAAN VOL. Sat. Haga Satuan Jumlah harga Total harga
LANTAI 2 24,700,390

LANTAI 4
1 Pek. Reposisi AC Split Eksisting 8 unt 637,115 5,096,923
Bongkar pasang, Service, reposisi indoor dan outdoor -
2 Pek. Penggantian Pipa Refrigerant 64 m 196,270 12,561,267
Pipa Refrigerant standar, non inverter -
3 Pek. Exhaust Fan 4 unt 776,000 3,104,000
Exhaust Fan, ceiling mounted, 120 CFM ex. KDK, Sekai -
4 Pek. Ducting Exhaust Fan 4 set 223,100 892,400
BJLS ducting dengan insulator, -
5 Pek. Grill Exhaust Fan 4 unt 397,700 1,590,800
6 Pek. Testing & Comissioning 1 ls 1,455,000 1,455,000
LANTAI 4 24,700,390

LANTAI 5
1 Pek. Pengadaan AC Split R. Function Hall, independent, 2 PK 4 unt 13,337,500 53,350,000
AC Split 2 PK, ex. Daikin Lengkap Pipa Refrigrant & outdoor, terpasang -
2 Pek. Pengadaan AC Split R. Arsip, independent, 2 PK 2 unt 13,337,500 26,675,000
AC Split 2 PK, ex. Daikin Lengkap Pipa Refrigrant & outdoor, terpasang -
3 Pek. Exhaust Fan 4 unt 776,000 3,104,000
Exhaust Fan, ceiling mounted, 120 CFM ex. KDK, Sekai -
4 Pek. Ducting Exhaust Fan 4 set 223,100 892,400
BJLS ducting dengan insulator, -
5 Pek. Grill Exhaust Fan 4 unt 397,700 1,590,800
6 Pek. Testing & Comissioning 1 ls 1,455,000 1,455,000
LANTAI 5 87,067,200
PENGADAAN VAC 145,730,879

F PEKERJAAN TOILET
LANTAI 1
1 Closet duduk 1 unt 4,716,722 4,716,722
Produk Toto C421/S516J+ECOFLUSH, lp aksesoris, (terpasang), -
2 Pek. Jet washer 1 unt 624,001 624,001
Ex. TOTO-TX403SMCRB, lkp aksesoris, terpasang -
3 Pek. Floor Drain 3 unt 468,025 1,404,075
Ex. TOTO TX1CV2, lkp aksesoris, terpasang -
4 Pek. Tempat Tissue Holder 1 unt 823,045 823,045
Ex. TOTO TX703AW, lkp aksesoris, terpasang -
5 Pek. Wastafel 2 unt 2,756,352 5,512,704
Produk , ex. Toto LW642CJ + kran (lengkap terpasang)
JUMLAH 13,080,547

LANTAI 2
1 Instalasi pipa PVC tipe AW ø 1/2" (15 mm) 14 m1 65,960 923,440
Pipa PVC ø 1/2" -
2 Instalasi Plumbing air bekas 18.8 m1 84,972 1,597,474
Pipa PVC ø 2" -
3 Instalasi Plumbing air kotor 12.5 m1 111,453 1,393,163
Pipa PVC ø 3" -
4 Closet duduk 4 unt 4,716,722 18,866,888
Produk Toto C420/S516J+ECOFLUSH, lp aksesoris, (terpasang), -
5 Pek. Urinoir ex. TOTO 2 unt 4,114,837 8,229,674
Urinoir ex. Toto, Moslem Type Urinal U57M (Top Inlet) -
6 Pek. Penyekat Urinoir 1 unt 334,650 334,650
Urinal Partition ex. TOTO A100 White, lkp terpasang -
7 Pek. Partisi Cubicle Toilet 21.2 m2 2,182,500 46,269,000
Cubicle Phenolic 12 mm, terpasang, lkp pintu dan aksesoris, col : confirm -
5 Pek. Wastafel 2 unt 2,756,352 5,512,704
Produk , ex. Toto LW642CJ + kran (lengkap terpasang) -
6 Pek. Jet washer 4 unt 624,001 2,496,004
Ex. TOTO-TX403SMCRB, lkp aksesoris, terpasang -
7 Pek. Floor Drain 4 unt 468,025 1,872,100
Ex. TOTO TX1CV2, lkp aksesoris, terpasang -
8 Pek. Tempat Tissue Holder 4 unt 823,045 3,292,180
Ex. TOTO TX703AW, lkp aksesoris, terpasang -
9 Pek. Vanity Wastafel 2 unt 4,348,025 8,696,050
Uk. 90x50x80, Customized, Multipleks 18mm, fin. HPL (motif : Confirmed),
top table granite tile (hitam), kaca crmin 5mm, lkp aksesoris, terpasang

JUMLAH 99,483,326

LANTAI 4
1 Instalasi pipa PVC tipe AW ø 1/2" (15 mm) 14 m1 65,960 923,440
Pipa PVC ø 1/2" -
2 Instalasi Plumbing air bekas 18.8 m1 84,972 1,597,474
Pipa PVC ø 2" -
3 Instalasi Plumbing air kotor 12.5 m1 111,453 1,393,163
Pipa PVC ø 3" -
4 Closet duduk 4 unt 4,716,722 18,866,888
Produk Toto C420/S516J+ECOFLUSH, lp aksesoris, (terpasang), -
` Pek. Urinoir ex. TOTO 2 unt 4,114,837 8,229,674
Urinoir ex. Toto, Moslem Type Urinal U57M (Top Inlet) -
6 Pek. Penyekat Urinoir 1 unt 334,650 334,650
NO KODE URAIAN PEKERJAAN VOL. Sat. Haga Satuan Jumlah harga Total harga
Urinal Partition ex. TOTO A100 White, lkp terpasang -
7 Pek. Partisi Cubicle Toilet 21.2 m2 2,182,500 46,269,000
Cubicle Phenolic 12 mm, terpasang, lkp pintu dan aksesoris, col : confirm -
5 Pek. Wastafel 2 unt 2,756,352 5,512,704
Produk , ex. Toto LW642CJ + kran (lengkap terpasang) -
6 Pek. Jet washer 4 unt 624,001 2,496,004
Ex. TOTO-TX403SMCRB, lkp aksesoris, terpasang -
7 Pek. Floor Drain 4 unt 468,025 1,872,100
Ex. TOTO TX1CV2, lkp aksesoris, terpasang -
8 Pek. Tempat Tissue Holder 4 unt 823,045 3,292,180
Ex. TOTO TX703AW, lkp aksesoris, terpasang -
9 Pek. Vanity Wastafel 2 unt 4,348,025 8,696,050
Uk. 90x50x80, Customized, Multipleks 18mm, fin. HPL (motif : Confirmed),
top table granite tile (hitam), kaca crmin 5mm, lkp aksesoris, terpasang

JUMLAH 99,483,326
LANTAI 5
1 Instalasi pipa PVC tipe AW ø 1/2" (15 mm) 14 m1 65,960 923,440
Pipa PVC ø 1/2" -
2 Instalasi Plumbing air bekas 18.8 m1 84,972 1,597,474
Pipa PVC ø 2" -
3 Instalasi Plumbing air kotor 12.5 m1 111,453 1,393,163
Pipa PVC ø 3" -
4 Closet duduk 2 unt 4,716,722 9,433,444
Produk Toto C420/S516J+ECOFLUSH, lp aksesoris, (terpasang), -
5 Pek. Wastafel 1 unt 2,756,352 2,756,352
Zink PANTRY -
6 Pek. Jet washer 2 unt 624,001 1,248,002
Ex. TOTO-TX403SMCRB, lkp aksesoris, terpasang -
7 Pek. Floor Drain 2 unt 468,025 936,050
Ex. TOTO TX1CV2, lkp aksesoris, terpasang -
8 Pek. Tempat Tissue Holder 2 unt 823,045 1,646,090
Ex. TOTO TX703AW, lkp aksesoris, terpasang -
9 Pek. Meja Wastafel 1 unt 4,348,025 4,348,025
Uk. 90x50x80, Customized, Multipleks 18mm, fin. HPL (motif : Confirmed),
top table granite tile (hitam), kaca crmin 5mm, lkp aksesoris, terpasang
JUMLAH 24,282,039
JUMLAH PEKERJAAN TOILET 236,329,238

G I PEKERJAAN PENANGKAL PETIR


1 Penangkal Petir
Penangkal Petir Termasuk Earthing 1 unt 18,168,100 18,168,100
JUMLAH 18,168,100

H PEKERJAAN SPRINKLER
LANTAI 1
1 Head Sprinkler pendant 16 unt 318,160 5,090,560
ex. Viking, Temperature Grade = 680C, K-Factor 80.6 -
2 Pipa BS Sch 40 dia. 65 mm 8 m1 380,240 3,041,920
ex. Spindo - Bakrie, lengkap dengan fitting dan material bantu -
3 Pipa BS Sch 40 dia. 50 mm 12 m1 279,360 3,352,320
ex. Spindo - Bakrie, lengkap dengan fitting dan material bantu -
4 Pipa BS Sch 40 dia. 40 mm 18 m1 226,980 4,085,640
ex. Spindo - Bakrie, lengkap dengan fitting dan material bantu -
5 Pipa BS Sch 40 dia. 32 mm 24 m1 183,330 4,399,920
ex. Spindo - Bakrie, lengkap dengan fitting dan material bantu -
6 Pipa BS Sch 40 dia. 25 mm 44 m1 167,810 7,383,640
ex. Spindo - Bakrie, lengkap dengan fitting dan material bantu -
7 Pipa droper ceiling 16 m1 151,320 2,421,120
ex. Spindo - Bakrie, lengkap dengan fitting dan material bantu -
8 Test Drain Sprinkler 16 set 150,350 2,405,600
ex. Spindo - Bakrie, lengkap dengan fitting dan material bantu
JUMLAH 32,180,720

LANTAI 2
1 Head Sprinkler pendant 22 unt 318,160 6,999,520
ex. Viking, Temperature Grade = 680C, K-Factor 80.6 -
2 Pipa BS Sch 40 dia. 65 mm 12 m1 380,240 4,486,832
ex. Spindo - Bakrie, lengkap dengan fitting dan material bantu -
3 Pipa BS Sch 40 dia. 50 mm 15 m1 279,360 4,134,528
ex. Spindo - Bakrie, lengkap dengan fitting dan material bantu -
4 Pipa BS Sch 40 dia. 40 mm 25 m1 226,980 5,561,010
ex. Spindo - Bakrie, lengkap dengan fitting dan material bantu -
5 Pipa BS Sch 40 dia. 32 mm 33 m1 183,330 5,994,891
ex. Spindo - Bakrie, lengkap dengan fitting dan material bantu -
6 Pipa BS Sch 40 dia. 25 mm 65 m1 167,810 10,961,349
ex. Spindo - Bakrie, lengkap dengan fitting dan material bantu -
7 Pipa droper ceiling 22 m1 151,320 3,329,040
ex. Spindo - Bakrie, lengkap dengan fitting dan material bantu -
8 Test Drain Sprinkler 22 set 150,350 3,307,700
ex. Spindo - Bakrie, lengkap dengan fitting dan material bantu
JUMLAH 44,774,870

LANTAI 3
NO KODE URAIAN PEKERJAAN VOL. Sat. Haga Satuan Jumlah harga Total harga
1 Head Sprinkler pendant 22 unt 318,160 6,999,520
ex. Viking, Temperature Grade = 680C, K-Factor 80.6 -
2 Pipa BS Sch 40 dia. 65 mm 12 m1 380,240 4,486,832
ex. Spindo - Bakrie, lengkap dengan fitting dan material bantu -
3 Pipa BS Sch 40 dia. 50 mm 15 m1 279,360 4,134,528
ex. Spindo - Bakrie, lengkap dengan fitting dan material bantu -
4 Pipa BS Sch 40 dia. 40 mm 25 m1 226,980 5,561,010
ex. Spindo - Bakrie, lengkap dengan fitting dan material bantu -
5 Pipa BS Sch 40 dia. 32 mm 33 m1 183,330 5,994,891
ex. Spindo - Bakrie, lengkap dengan fitting dan material bantu -
6 Pipa BS Sch 40 dia. 25 mm 65 m1 167,810 10,961,349
ex. Spindo - Bakrie, lengkap dengan fitting dan material bantu -
7 Pipa droper ceiling 22 m1 151,320 3,329,040
ex. Spindo - Bakrie, lengkap dengan fitting dan material bantu -
8 Test Drain Sprinkler 22 set 150,350 3,307,700
ex. Spindo - Bakrie, lengkap dengan fitting dan material bantu
JUMLAH 44,774,870

LANTAI 4
1 Head Sprinkler pendant 22 unt 318,160 6,999,520
ex. Viking, Temperature Grade = 680C, K-Factor 80.6 -
2 Pipa BS Sch 40 dia. 65 mm 12 m1 380,240 4,486,832
ex. Spindo - Bakrie, lengkap dengan fitting dan material bantu -
3 Pipa BS Sch 40 dia. 50 mm 15 m1 279,360 4,134,528
ex. Spindo - Bakrie, lengkap dengan fitting dan material bantu -
4 Pipa BS Sch 40 dia. 40 mm 25 m1 226,980 5,561,010
ex. Spindo - Bakrie, lengkap dengan fitting dan material bantu -
5 Pipa BS Sch 40 dia. 32 mm 33 m1 183,330 5,994,891
ex. Spindo - Bakrie, lengkap dengan fitting dan material bantu -
6 Pipa BS Sch 40 dia. 25 mm 65 m1 167,810 10,961,349
ex. Spindo - Bakrie, lengkap dengan fitting dan material bantu -
7 Pipa droper ceiling 22 m1 151,320 3,329,040
ex. Spindo - Bakrie, lengkap dengan fitting dan material bantu -
8 Test Drain Sprinkler 22 set 150,350 3,307,700
ex. Spindo - Bakrie, lengkap dengan fitting dan material bantu
JUMLAH 44,774,870

LANTAI 5
1 Head Sprinkler pendant 16 unt 318,160 5,090,560
ex. Viking, Temperature Grade = 680C, K-Factor 80.6 -
2 Pipa BS Sch 40 dia. 65 mm 12 m1 380,240 4,486,832
ex. Spindo - Bakrie, lengkap dengan fitting dan material bantu -
3 Pipa BS Sch 40 dia. 50 mm 15 m1 279,360 4,134,528
ex. Spindo - Bakrie, lengkap dengan fitting dan material bantu -
4 Pipa BS Sch 40 dia. 40 mm 25 m1 226,980 5,561,010
ex. Spindo - Bakrie, lengkap dengan fitting dan material bantu -
5 Pipa BS Sch 40 dia. 32 mm 33 m1 183,330 5,994,891
ex. Spindo - Bakrie, lengkap dengan fitting dan material bantu -
6 Pipa BS Sch 40 dia. 25 mm 65 m1 167,810 10,961,349
ex. Spindo - Bakrie, lengkap dengan fitting dan material bantu -
7 Pipa droper ceiling 16 m1 151,320 2,421,120
ex. Spindo - Bakrie, lengkap dengan fitting dan material bantu -
8 Test Drain Sprinkler 16 set 150,350 2,405,600
ex. Spindo - Bakrie, lengkap dengan fitting dan material bantu
- 41,055,890
JUMLAH 207,561,221
RENCANA ANGGARAN DAN BIAYA
PEKERJAAN : RENOVASI INTERIOR - EKSTERIOR
PT. BINA SENTRA PURNA
LOKASI : KANTOR PUSAT PT. BINA SENTRA PURNA
JL. DR. SAHARDJO, NO. 52

BIDANG PEK. : PENGADAAN FURNITURE

NO KODE URAIAN PEKERJAAN VOL. Sat. Haga Satuan Jumlah harga Total harga

A PEKERJAAN FURNITURE
LANTAI 1
1 Meja Receptionist 1 unt 14,560,000 14,560,000
Customade, Bahan Multipleks, Fin. HPL, col : confirm, 60x200cm
2 Meja Tamu 2 unt 2,340,000 4,680,000
Meja Coffee Table,50x100, top table kaca, ex. IKEA/Setara
- 19,240,000

LANTAI 2
1 Meja Workstation 4 kursi (WS-1) 5 unt 22,090,000 110,450,000
Workstation lengkap, 4 seat, customade sesuai gambar,
lkp receptacle 4 set dan instalasi elektrikal (outlet)
2 Meja Workstation 2 kursi (WS-2) 3 unt 19,350,000 58,050,000
Workstation lengkap, 2 seat, customade sesuai gambar,
lkp receptacle 6 set dan instalasi elektrikal
3 1 set Meja Head Department (MHD-1) 4 unt 18,255,000 73,020,000
Meja workstation lengkap, customade sesuai gambar,
lkp mobile drawer 40cm, receptacle dan instalasi elektrikal
4 1 set Meja Head Unit (MHU-01) 3 unt 14,220,000 42,660,000
Meja workstation lengkap, 2+2 seat, customade sesuai gambar,
lkp meja bundar dan receptacle serta instalasi elektrikal
5 Credenza (CR-1) 4 unt 4,800,000 19,200,000
Lemari File Head Department Uk 160x40x80cm
6 Credenza File (CR-2) 6 unt 4,270,000 25,620,000
Lemari File Staf Uk 120x40x80cm
7 Mobile Drawer (MDR-1) 38 unt 2,860,000 108,680,000
Rak Mobile Drawer (L=50Cm, W=40cm, H=60cm)
8 Lemari File (LF-1) 8 unt 10,560,000 84,480,000
Lemari Arsip, customade, Uk 120x40x220cm, fin. HPL, col : confirm
9 Meja Rapat 8 kursi 1 set 15,680,000 15,680,000
Meja Meeting Persegi,sesuai gambar
10 Glassboard (GB) 1 set 7,345,000 7,345,000
Tempered Glass 8mm, Back Oracle White
11 Meja Breakout Panjang 2 unt 4,880,000 9,760,000
Meja Model Bar, 50x160cm, Multipleks18mm, fin. HPL
LANTAI 2 554,945,000

LANTAI 4
1 Meja Workstation 4 kursi (WS-1) 6 unt 22,090,000 132,540,000
Workstation lengkap, 4 seat, customade sesuai gambar,
lkp receptacle 6 set dan instalasi elektrikal
2 Meja Workstation 2 kursi (WS-2) 2 unt 19,350,000 38,700,000
Workstation lengkap, 2 seat, customade sesuai gambar,
lkp receptacle 6 set dan instalasi elektrikal
3 1 set Meja Head Department (MHD-1) 4 unt 18,255,000 73,020,000
Meja workstation lengkap, customade sesuai gambar,
lkp mobile drawer 40cm, receptacle dan instalasi elektrikal
4 1 set Meja Head Unit (MHU-01) 2 unt 14,220,000 28,440,000
Meja workstation lengkap, 2+2 seat, customade sesuai gambar,
lkp meja bundar dan receptacle serta instalasi elektrikal
5 1 set Meja Head Unit (MHU-02) 1 unt 12,185,000 12,185,000
Meja workstation lengkap, 1+1 seat, customade sesuai gambar,
lkp meja bundar dan receptacle serta instalasi elektrikal
6 Credenza (CR-1) 4 unt 4,800,000 19,200,000
Lemari File Head Department Uk 160x40x80cm
7 Credenza File (CR-2) 6 unt 4,270,000 25,620,000

8 Mobile Drawer (MDR-1) 36 unt 2,860,000 102,960,000


Rak Mobile Drawer (L=50Cm, W=40cm, H=60cm)
9 Lemari File (LF-1) 9 unt 10,560,000 95,040,000
Lemari Arsip, customade, Uk 120x40x220cm, fin. HPL, col : confirm
10 Meja Rapat 8 kursi 1 set 18,380,000 18,380,000
NO KODE URAIAN PEKERJAAN VOL. Sat. Haga Satuan Jumlah harga Total harga
Meja Meeting Persegi,sesuai gambar
11 Glassboard (GB) 1 set 7,345,000 7,345,000
Tempered Glass 8mm, Back Oracle White
12 Meja Breakout Panjang 2 unt 4,880,000 9,760,000
Meja Model Bar, 50x160cm, Multipleks18mm, fin. HPL
LANTAI 4 563,190,000

LANTAI 5
3 Lemari File Ruang Arsip (LF-AR) 16 unt 8,550,000 136,800,000
Lemari File Ruang Arsip Uk 120x40x240cm
7 Meja Café Panjang 4 unt 3,760,000 15,040,000
Meja Model Bar, 40x200cm, Multipleks18mm, fin. HPL
8 Meja Café Kecil 12 unt 3,210,000 38,520,000
Meja tinggi utk 4 orang, 60x100cm, Multipleks 18mm, fin. HPL
10 Meja Saji Café 1 set 6,380,000 6,380,000
Meja tinggi, 60x100cm, ambalan tertutup, Multipleks 18mm, fin. HPL
LANTAI 5 196,740,000
PEKERJAAN FURNITURE 1,137,375,000

B PENGADAAN KURSI
LANTAI 1
1 Kursi Hadap (Reception Officer) 4 unt 2,080,000 8,320,000
Kursi Kantor ex. Donati/Setara
2 Sofa Tamu 2 unt 6,570,000 13,140,000
Sofa 2 Dudukan ex. Donati/Setara
3 Sofa Tamu 2 unt 6,570,000 13,140,000
Sofa 1 Dudukan ex. Donati/Setara
4 Meja Tamu (Coffee Table) 2 unt 2,850,000 5,700,000
ex. Donati/Setara
LANTAI 1 40,300,000
LANTAI 2
1 Kursi Head Department 2 unt 3,460,000 6,920,000
Kursi Kantor ex. Donati/Setara
2 Kursi Head Unit 20 unt 3,170,000 63,400,000
Kursi Kantor ex. Donati/Setara
3 Kursi Hadap 18 unt 2,080,000 37,440,000
Kursi Kantor ex. Donati/Setara
4 Sofa Tamu 2 unt 6,570,000 13,140,000
Sofa 2 Dudukan ex. Donati/Setara
5 Meja Tamu (Coffee Table) 1 unt 2,850,000 2,850,000
ex. Donati/Setara
6 Kursi Stool Breakout 12 unt 2,850,000 34,200,000
Stool, kaki besi, ex. Donati/Setara
LANTAI 2 157,950,000
LANTAI 4
1 Kursi Head Department 2 unt 3,460,000 6,920,000
Kursi Kantor ex. Donati/Setara
2 Kursi Manajer / R. Rapat 20 unt 3,170,000 63,400,000
Kursi Kantor ex. Donati/Setara
3 Kursi Hadap 18 unt 2,080,000 37,440,000
Kursi Kantor ex. Donati/Setara
4 Sofa Tamu 2 unt 6,570,000 13,140,000
Sofa 2 Dudukan ex. Donati/Setara
5 Meja Tamu (Coffee Table) 1 unt 2,850,000 2,850,000
ex. Donati/Setara
6 Kursi Stool Breakout 12 unt 2,850,000 34,200,000
Stool, kaki besi, ex. Donati/Setara
LANTAI 4 157,950,000
LANTAI 5
1 Kursi Stool Café 18 unt 2,080,000 37,440,000
Stool Chair, rangka besi
2 R. Pantry Kering 7 m2 2,800,000 19,600,000
Lemari Kitchen Set Lengkap dengan zink & Pembuangan Top. Granit Black Gold
LANTAI 5 57,040,000
PENGADAAN KURSI 413,240,000
RINCIAN RENCANA ANGGARAN DAN BIAYA
PEKERJAAN : RENOVASI INTERIOR - EKSTERIOR
PT. BINA SENTRA PURNA
LOKASI : KANTOR PUSAT PT. BINA SENTRA PURNA
JL. DR. SAHARDJO, NO. 52

BIDANG PEK. : FAÇADE DAN AREA PARKIR

NO KODE URAIAN PEKERJAAN VOL. Sat. Haga Satuan Jumlah harga Total harga

A PEKERJAAN FACADE
1 Cladding ACP Penutup Shaft Lift 46.8 m2 1,406,500 65,824,200
ACP ex. Seven/Acotuff, col: confrm, rangka hollow, sesuai gambar -
2 Cladding Curtain Wall Kaca - Sisi Kanan 34 m2 1,891,500 64,311,000
Kaca Tinted 8mm Ex. Asahi Sunlux, rangka hollow, penguat rangka baja -
3 Cladding Curtain Wall Kaca - Sisi Kiri 34 m2 1,891,500 64,311,000
Kaca Tinted 8mm Ex. Asahi Sunlux, rangka hollow, penguat rangka baja -
4 Cladding Curtain Wall Kaca - Sisi Tengah 82.5 m2 1,891,500 156,048,750
Kaca Tinted 8mm Ex. Asahi Sunlux, rangka hollow, penguat rangka baja -
5 Cladding ACP Penutup Ornamen - Sisi Tengah 8 unt 4,656,000 37,248,000
ACP ex. Seven/Acotuff, col: confrm, rangka hollow, sesuai gambar -
6 Cladding ACP Penutup Ornamen - Sisi Kiri dan Kanan 16 unt 3,104,000 49,664,000
ACP ex. Seven/Acotuff, col: confrm, rangka hollow, sesuai gambar -
4 Cladding Curtain Wall Kaca - Hoistway Lift 82.5 m2 3,104,000 256,080,000
Kaca Tinted 8mm Ex. Asahi Sunlux, rangka hollow, penguat rangka baja -
7 Finishing Pengecatan 116 m2 65,960 7,651,360
Cat ex. Dulux Weathershield Exterior -
8 Rangka Fly-Roof Atas 1354 kg 43,175 58,458,544
Rangka Baja Kanal U, Dynabolt, penyambungan pengelasan -
9 Cladding ACP Penutup Fly-Roof Atas 42.43 m2 1,406,500 59,677,795
ACP ex. Seven/Acotuff, col: confrm, rangka hollow, sesuai gambar -
10 Lettering Utama Façade 1 set 24,250,000 24,250,000
Lettering Bahan Besi Plat, fin. Duco, col : confirm, backlight -
11 Lettering Logo Façade 1 set 9,700,000 9,700,000
Logo Sign Bahan Besi Plat, fin. Duco, col : confirm, backlight
JUMLAH 853,224,649

B PEKERJAAN PYLON SIGN


1 Pondasi Pylon Sign 0.3 m3 3,152,500 945,750
Pondasi Batu Kali, 80x60cm
2 Rangka Pylon Sign 1 ls 4,801,500 4,801,500
Rangka Hollow 40x40x240, Plat dudukan 5mm, angkur bolt,
3 Box Pylon & Cutting Lettering 1 ls 9,457,500 9,457,500
Box Neon Sign, lengkap lettering cutting sticker dan lampu LED
JUMLAH 15,204,750

C PEKERJAAN AREA PARKIR


1 Refinish Dinding Perimeter Area Parkir 51.2 m2 85,845 4,395,264
Perapihan, fin. Cat Ornamen Beton (Matte)
2 Perapihan Area Parkir 180 m2 64,505 11,610,900
Perapihan Kembali, Penggantian yang rusak karena pelaksanaan
JUMLAH 16,006,164
Alirkan Semangat Baru
ru

RENCANA ANGGARAN DAN BIAYA


PEKERJAAN : RENOVASI RUANG INTERIOR LT.2 -SAYAP KANAN
DIVISI ADMINISTRASI UMUM DAN DIVISI SDM
LOKASI : KANTOR PUSAT PERUMDA AIR MINUM JAYA
JL. PENJERNIHAN II PEJOMPONGAN

BIDANG PEK. : ARSITEKTUR

Jumlah harga
NO KODE URAIAN PEKERJAAN VOL. Sat. Haga Satuan Total harga (Rp.)
(Rp.)
A PEKERJAAN PERSIAPAN
1 Direksikeet 24 m2 596,728 14,321,472
Uk. 4 X 6m, Rangka hollow, multipleks, lkp elektrikal, AC dan Ruang Rapat Kecil

2 Listrik Kerja dan Air Kerja 4 bln 1,000,000 4,000,000


Listrik Kerja, Tapping dari eksisting dgn MCB tersendiri

3 Mobilisasi dan Demobilisasi 4 bln 2,248,750 8,995,000


Transportasi, akomodasi untuk personil dan peraltan

4 Pengadaan Protokol Kesehatan Covid-19 4 bln 3,662,923 14,651,692


Rambu-rambu, Pengaahan rutin, Prokes Covid-19

6 Kebersihan Area Kerja 4 bln 1,350,000 5,400,000


Lampu Penerangan, Scaffolding

7 Pengadaan Blower Exhaust Kerja 4 bln 650,000 2,600,000


Blower Exhaust Portable 300 CFM, lkp dgn flexible ducting

8 Shop Drawing 4 bln 1,850,000 7,400,000


Terkoodinasi dan persetujuan dari perencana

9 As-Built Drawing 4 bln 1,850,000 7,400,000


Terkoodinasi dan persetujuan dari perencana

10 Administrasi Pendukung 4 bln 1,250,000 5,000,000


Pelaporan, Dokumentasi

JUMLAH PEKERJAAN PERSIAPAN 69,768,164


B PEK. SISTEM MANAJEMEN KESELAMATAN KONSTRUKSI
Penerapan Sistem Manjemen Keselamatan Konstruksi pada
resiko pekerjaan berbahaya rendah

1 Pengadaan Alat Safety / APD


Safety Helmet = 5 bh per bulan 20.00 set 67,500 1,350,000
Rompi Kerja = 5 bh per bulan 20.00 set 23,000 460,000
Safety Harness 2.00 set 235,000 470,000
Safety Shoes = 5 bh per bulan 20.00 set 285,000 5,700,000
2 Sistem manajemen RKK 4.00 bln 500,000 2,000,000
Rencana Kerja Pengendalian dan Pemantuan Lingkungan Hidup

3 Sistem manajemen RKPPL 1.00 ls 500,000 500,000


Rencana Kerja Pengendalian dan Pemantuan Lingkungan Hidup

4 Sistem manajemen RMLLP 1.00 ls 500,000 500,000


Rencana Manajemen Lalu Lintas Pekerjaan

5 Rencana Program Mutu 1.00 ls 500,000 500,000


Konsultansi Konstruksi Pengawas / Manajemen Konstruksi

6 Pelaporan K3/HSE 4.00 bln 500,000 2,000,000

JUMLAH PEKERJAAN AREA KERJA SEMENTARA 13,480,000


C PEK. AREA KERJA SEMENTARA
1 Pengosongan dan Pembersihan Ruangan Lantai 4 328.00 m2 95,000 31,160,000
Bongkar dinding, kusen pintu dan jendela, dinding pasrtisi eksisting

2 Partisi Ruang Kerja Sementara Staf Khusus /TTO 4.00 set 4,250,000 17,000,000
Partisi Gypsum, Rangka hollow, fin. cat

3 Partisi Ruang Kerja Sementara Divisi Investasi di Lantai 4 6.00 set 4,250,000 25,500,000
Partisi Gypsum, Rangka hollow, fin. cat

4 Relokasi Meja Kerja dan Barang Area Staf Khusus /TTO 132.00 m2 90,000 11,880,000
Relokasi Meja Kerja dan Barang Bag. Keuangan ke dan dari area sementara

5 Relokasi Meja Kerja dan Barang Area Divisi Investasi 132.00 m2 90,000 11,880,000
Relokasi Meja Kerja dan Barang area ke dan dari area sementara

6 Bongkaran Dinding Lt.2 (Sayap kiri) 312.00 m2 120,000 37,440,000


Bongkar dinding, kusen pintu dan jendela, dinding railing eksisting

JUMLAH PEKERJAAN AREA KERJA SEMENTARA 134,860,000


D PEKERJAAN BONGKARAN
1 Bongkaran Plafon Eksisting Lt.2 (Sayap kiri) 312.00 m2 58,000 18,096,000
Bongkar plafon eksisting, rangka dan peralatan MEP dipakai kembali

2 Bongkaran Dinding eksisting Lt.2 (Sayap kiri) 84.96 m2 83,500 7,094,160


Bongkar dinding, kusen pintu dan jendela, dinding pasrtisi dn plafon eksisting
Kusen, Pintu dan Kaca dipakai kembali (inventarisasi)

3 Bongkaran Lantai eksisting Lt.2 (Sayap kiri) 312.00 m2 62,500 19,500,000


Jumlah harga
NO KODE URAIAN PEKERJAAN VOL. Sat. Haga Satuan Total harga (Rp.)
(Rp.)
4 Bongkaran Kusen Eksisting 27.00 unt 175,500 4,738,500
Kusen, Pintu dan Kaca dipakai kembali (inventarisasi)
5 Bongkaran Instalasi Elektrikal Eksisting 312.00 m2 92,645 28,905,240
6 Pek. Pembongkaran Saluran dan sistem AC eksisting 328.00 m2 50,000 16,400,000
Bongkaran Ducting, difusser, hanger AC eksisting

JUMLAH PEKERJAAN BONGKARAN 94,733,900


D PEK. VAC AREA SEMENTARA
1 Pek. AC Split, independent, 2 PK, ex. Daikin / Mitsubishi 8.00 unt 6,394,420 51,155,360
AC Split 2 PK, ex. Daikin/Mitsubishi, lkp outdoor, terpasang
2 Pek. Pipa Refrigerant Tambahan 4.00 set 97,212 388,848
3 Pek. Dudukan Outdoor pada dak atap 8.00 unt 555,637 4,445,096

JUMLAH PEKERJAAN VAC. AREA SEMENTARA 55,989,304


JUMLAH PEKERJAAN ARSITEK 368,831,368

Jakarta, Maret 2022


DIREKTUR UMUM,

TEDY J. SITEPU
MASTER SCHEDULE
( DRAFT )

PEKERJAAN : RENOVASI SAYAP KIRI LANTAI 2


LOKASI : PEJOMPONGAN - JAKARTA DATE : 1/29/2023

Haga Satuan Jumlah harga Total harga MINGGU KE


NO URAIAN PEKERJAAN VOL. Sat. BOBOT 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
4 Apr - 10 Apr 11 Apr - 17 Apr 18Apr - 24 Apr 25 Apr - 30 Apr 1 Mei - 7 Mei 8 Mei - 14 Mei 15 Mei - 21 Mei 22 Mei - 28 Mei 29 Mei - 4 Juni 5 Juni - 11 Juni 12 Juni - 18 Juni 19 Juni - 25 Juni 26 Juni - 2 Juli 3 Juli - 9 Juli 10 Juli - 16 Juli 17 Juli - 23 Juli
A PEKERJAAN PERSIAPAN

A PEKERJAAN PERSIAPAN
1 Direksikeet 24 m2 580,000 Rp 13,920,000 0.780 0.780
Uk. 4 X 6m, Rangka hollow, multipleks, lKp elektrikal dan AC dan Ruang Rapat Kecil
2 Listrik Kerja dan Air Kerja 4 bln 1,000,000 Rp 4,000,000 0.224 0.224
Listrik Kerja, Tapping dari eksisting dgn MCB tersendiri
3 Mobilisasi dan Demobilisasi 4 bln 2,500,000 Rp 10,000,000 0.560 0.560
4 Pengadaan Peralatan dan Operasional K3 (HSE) 4 bln 3,500,000 Rp 14,000,000 0.784 0.196 0.196 0.196 0.196
Pengadaan APD, Rambu-rambu, Pengaahan rutin, Prokes COvid-19
5 Pengadaan Peralatan dan Operasional Protokol Covid-19 4 bln 2,350,000 Rp 9,400,000
Pengadaan Rambu, Hand Sanitizr, Masker dan test sesuai kebutuhan
6 Kebersihan Area Kerja 4 bln 1,350,000 Rp 5,400,000 0.302 0.076 0.076 0.076 0.076
Lampu Penerangan, Scaffolding
7 Pengadaan Blower Exhaust Kerja 4 bln 650,000 Rp 2,600,000
Blower Exhaust Portable 300 CFM, lkp dgn flexible ducting
7 Shop Drawing 4 bln 1,850,000 Rp 7,400,000
Terkoodinasi dengan pemberi tugas, konsultan pengawas, konsultan perencana
8 As-Built Drawing 4 bln 1,850,000 Rp 7,400,000
Terkoodinasi dengan pemberi tugas, konsultan pengawas, konsultan perencana
9 Administrasi Pendukung 4 bln 1,250,000 Rp 5,000,000 0.280 0.070 0.070 0.070 0.070

B PEK. AREA KERJA SEMENTARA


1 Pengosongan dan Pembersihan Ruangan Lantai 4 328.00 m2 115,000 Rp 37,720,000 2.112 2.112
Bongkar dinding, kusen pintu dan jendela, dinding pasrtisi eksisting
2 Partisi Ruang Kerja Sementara Staf Khusus Direksi di Lantai 4 4.00 set 4,500,000 Rp 18,000,000 1.008 0.504 0.504
Partisi Gypsum, Rangka hollow, fin. cat
3 Partisi Ruang Kerja Sementara Divisi Investasi di Lantai 4 6.00 set 4,500,000 Rp 27,000,000 1.512 1.512
Partisi Gypsum, Rangka hollow, fin. cat
4 Relokasi Meja Kerja dan Barang Area Staf Khusus Direksi 132.00 m2 90,000 Rp 11,880,000 0.665 0.665
Relokasi Meja Kerja dan Barang Bag. Keuangan ke dan dari area sementara
5 Relokasi Meja Kerja dan Barang Area Divisi Investasi 132.00 m2 90,000 Rp 11,880,000 0.665 0.333 0.333
Relokasi Meja Kerja dan Barang area ke dan dari area sementara
6 Bongkaran Dinding Lt.1 (Sayap kiri) 312.00 m2 120,000 Rp 37,440,000 2.097 2.097
Bongkar dinding, kusen pintu dan jendela, dinding railing eksisting
C PEKERJAAN BONGKARAN
1 Bongkaran Plafon Eksisting Lt.2 (Sayap kiri) 310.00 m2 88,088 Rp 27,307,280 1.529 1.529
Bongkar plafon eksisting, rangka dan peralatan MEP dipakai kembali (invetarisasi)
2 Bongkaran Dinding eksisting Lt.2 (Sayap kiri) 312.00 m2 93,423 Rp 29,147,976 1.632 1.632
Bongkar dinding, kusen pintu dan jendela, dinding pasrtisi dn plafon eksisting
Kusen, Pintu dan Kaca dipakai kembali (inventarisasi)
3 Bongkaran Lantai eksisting Lt.1 (Sayap kiri) 312.00 m2 72,292 Rp 22,555,104 1.263
4 Bongkaran Kusen Eksisting 57.00 unt 135,575 Rp 7,727,775 0.433 0.433
Kusen, Pintu dan Kaca dipakai kembali (inventarisasi)
5 Bongkaran Instalasi Elektrikal Eksisting 310.00 m2 117,645 Rp 36,469,950 2.042 2.042
6 Pek. Pembongkaran Saluran dan sistem AC eksisting 328.00 m2 50,000 Rp 16,400,000 0.918 0.918
Bongkaran Ducting, difusser, hanger AC eksisting
D PEKERJAAN VAC
1 Pek. AC Split, independent, 2 PK, ex. Daikin 8.00 unt 6,394,420 Rp 51,155,360 2.865 2.865
AC Split 2 PK, ex. Daikin, lkp outdoor, terpasang
2 Pek. Pipa Refrigerant Tambahan 4.00 set 97,212 Rp 388,848 0.022 0.022
3 Pek. Dudukan Outdoor pada dak atap 8.00 unt 554,356 Rp 4,434,848 0.248 0.248

A PEKERJAAN PLAFON
1 Plafon Interior Lantai General 312.00 m2 165,570 Rp 51,657,840 2.893 0.964 0.964 0.964
Rangka hollow 40x40, gypsum board ex. Knauff 9mm
3 Liner Plafon Interior 134.70 m1 50,000 Rp 6,735,000 0.377 0.377
6 Finishing Pengecatan Plafon Interior 312.00 m2 58,762 Rp 18,333,744 1.027 1.027
Compund, flatering, cat ex. Dullux Interior, col : conform
B PEKERJAAN PARTISI DAN DINDING
1 Partisi Gypsum 2 muka 86.60 m2 159,250 Rp 13,791,050 0.772 0.386 0.386
Partisi 2 muka, rangka hollow 40x40, gypsum board ex. Knauff 9mm
2 Partisi Gypsum 1 muka 84.60 m2 138,185 Rp 11,690,451 0.655 0.327 0.327
Partisi 2 muka, rangka hollow 40x40, gypsum board ex. Knauff 9mm
3 Dinding Bata Ringan 22.50 m2 161,068 Rp 3,624,030 0.203 0.101 0.101
Dinding Bata Ringan, pperekat Mortar, plesteran dan acian
4 Plin Lantai 134.70 m1 87,100 Rp 11,732,370 0.657
Plin Kayu profil 50mm, fin cat minyak, col : conform
5 Pek. Cat Dasar Dinding Interior 181.86 m2 57,607 Rp 10,476,409 0.587 0.293 0.293
Cat ex. Vinilex Interior, col : putih
6 Pemasangan Wallpaper 293.80 m2 169,565 Rp 49,818,197 2.790 1.395 1.395
Wallpaper bertekstur, ex. lokal, motif : confirm, pd dinding gypsum
C PEKERJAAN PINTU DAN JENDELA
1 Pintu PK1 2.00 unt 12,500,000 Rp 25,000,000 1.400 0.700 0.700
Pintu 2 Daun Frameless, 70cm, Tempered Glass 12mm, lapis sunblast
Partisi Kaca di sisi kiri kanan pintu, Door Handle dan engsel ex. Deksson
2 Partisi PT1 (Pintu dan Partisi R. SM Investasi) 1.00 unt 17,500,000 Rp 17,500,000 0.980 0.490 0.490
Pintu 1 Daun Frameless, 80cm, Tempered Glass 12mm, lapis sunblast
Aksesoris ex. Deksson, partisi kaca tempered 12mm, lapis sunblast
3 Partisi PT2 (Partisi R. SM Investasi) 1.00 unt 17,500,000 Rp 17,500,000 0.980 0.490 0.490
Pintu 1 Daun Frameless, 80cm, Tempered Glass 12mm, lapis sunblast
Aksesoris ex. Deksson, partisi kaca tempered 12mm, lapis sunblast
4 Partisi PT3 (Pintu dan Partisi R. Rapat) 2.00 unt 21,500,000 Rp 43,000,000 2.408 1.204 1.204
Pintu 1 Daun Frameless, 80cm, Tempered Glass 12mm, lapis sunblast
Aksesoris ex. Deksson, partisi kaca tempered 12mm, lapis sunblast
5 Partisi PT4 (Partisi R. Rapat) 2.00 unt 11,500,000 Rp 23,000,000 1.288 0.644 0.644
Pintu 1 Daun Frameless, 80cm, Tempered Glass 12mm, lapis sunblast
Aksesoris ex. Deksson, partisi kaca tempered 12mm, lapis sunblast
ARI RAYA IEDUL FITRI

6 Partisi PT5 (R R. SM Transisi dan Transformasi) 1.00 unt 16,750,000 Rp 16,750,000 0.938 0.469 0.469
Uk. 340x250cm, Kaca Frameless, modular 80mm, Tempered Glass 12mm,
Tinggi 240cm, lapis sunblast
7 Partisi PT6 (Partisi R. SM Transisi & Transformasi) 2.00 unt 11,250,000 Rp 22,500,000 1.260 0.630 0.630
Pintu 1 Daun Frameless, 80cm, Tempered Glass 12mm, lapis sunblast
Aksesoris ex. Deksson, partisi kaca tempered 12mm, lapis sunblast
LIBUR HARI RAYA IEDUL FITRI
8 Partisi PT7 (Pintu dan Partisi ke R. Rapat Besar) 2.00 unt 10,500,000 Rp 21,000,000 1.176 0.588 0.588
Pintu 1 Daun Frameless, 80cm, Tempered Glass 12mm, lapis sunblast
Aksesoris ex. Deksson, partisi kaca tempered 12mm, lapis sunblast
D PEKERJAAN LANTAI
2 Pek. Screeding dan Leveling dak Lantai 312.00 m2 76,800 Rp 23,961,600 1.342 0.671 0.671
3 Pek. Granite Tile GT1 69.00 m2 377,720 Rp 26,062,680 1.459 0.730 0.730
Nuansa warna terang, glossy, 60x60cm, ex. Roman/Sandimas, tipe : confirm
4 Pek. Lantai Dry-Concrete 30.40 m2 315,000 Rp 9,576,000 0.536 0.268 ###
Dry mix concrete, hardener dan epoxy semi gloss
5 Pek. Lantai Parket Vinyl 212.60 m2 283,079 Rp 60,182,595 3.370 ###
Nuansa warna kayu, ex. China, motif : confirm, terpasang
E I PEKERJAAN PANEL
1 Pek. Panel PP Lantai 2 Sayap Kiri 1.00 unt 8,600,000 Rp 8,600,000 0.482 0.241 0.241
2 Pek. Pek. Panel PSK Lantai 2 Sayap Kiri 1.00 unt 7,300,000 Rp 7,300,000 0.409 0.204 0.204
3 Pek. Pek. Panel AC Lantai 2 Sayap Kiri 1.00 unt 5,800,000 Rp 5,800,000 0.325 0.162 0.162
F PEKERJAAN LAMPU DAN INSTALASI
1 Lampu Down light LED 5 Watt (Area Plafon) 32.00 unt 188,100 Rp 6,019,200 0.337 0.337
Armatur Downlight 5" ex. Philips, bulb LED Philips White
2 Lampu Down light LED 5 Watt, outbow/hanging (Area Expossed Ceiling) 32.00 unt 188,100 Rp 6,019,200 0.337 0.337
Armatur Downlight 5" ex. Philips, bulb LED Philips White
4 Lampu LED STRIP RIBBON SINGLE FACE 17.00 m1 73,600 Rp 1,251,200 0.070 0.070
6 Saklar Ganda 18.00 unt 118,932 Rp 2,140,776 0.120 0.120
Saklar Ganda ex. Panasonic, tipe : confirm
7 Stop Kontak dinding Tunggal 72.00 unt 113,850 Rp 8,197,200 0.459 0.459
Stop Kjjjjj
8 Stop Kontak Lantai 72.00 unt 113,850 Rp 8,197,200 0.459 0.230 0.230
Stop Kontak Tunggal ex. Panasonic, tipe : confirm
10 Instalasi Lampu 65.00 ttk 158,598 Rp 10,308,870 0.577 0.289 0.289
Kabel NYM 3 x 2,5 mm ex. Kabelindo, pipa conduit ex. Ega / Boss
12 Instalasi Saklar Ganda, 18.00 ttk 210,548 Rp 3,789,864 0.212 0.106 0.106
Kabel NYM 3 x 2,5 mm ex. Kabelindo, pipa conduit ex. Ega/Boss
13 Instalasi Stop Kontak dinding Tunggal 72.00 ttk 183,019 Rp 13,177,368 0.738 0.369 0.369
Kabel NYM 3 x 2,5 mm ex. Kabelindo, pipa conduit ex. Ega/Boss
18 Instalasi Stop Kontak WIFI di atas plafon 2.00 ttk 183,019 Rp 366,038 0.020 0.010 0.010
Kabel NYM 3 x 2,5 mm ex. Kabelindo, pipa conduit ex. Ega/Boss
19 Pek. Cable Tray 22.00 m1 180,000 Rp 3,960,000 0.222 0.074 0.074 0.074
Cable Tray 50x200, lengkap elbow dan T, hanger, terpasang
G PEKERJAAN SPRINKLER
1 Head Sprinkler pendant 23.00 unt 328,000 Rp 7,544,000 0.422
ex. Viking, Temperature Grade = 680C, K-Factor 80.6
2 Pipa BS Sch 40 dia. 65 mm 11.80 m1 392,000 Rp 4,625,600 0.259
ex. Spindo - Bakrie, lengkap dengan fitting dan material bantu
3 Pipa BS Sch 40 dia. 50 mm 14.80 m1 288,000 Rp 4,262,400 0.239
ex. Spindo - Bakrie, lengkap dengan fitting dan material bantu
4 Pipa BS Sch 40 dia. 40 mm 24.50 m1 234,000 Rp 5,733,000 0.321
ex. Spindo - Bakrie, lengkap dengan fitting dan material bantu
5 Pipa BS Sch 40 dia. 32 mm 32.70 m1 189,000 Rp 6,180,300 0.346
ex. Spindo - Bakrie, lengkap dengan fitting dan material bantu
6 Pipa BS Sch 40 dia. 25 mm 65.32 m1 173,000 Rp 11,300,360 0.633
ex. Spindo - Bakrie, lengkap dengan fitting dan material bantu
7 Test Drain Sprinkler 23.00 set 155,000 Rp 3,565,000 0.200
ex. Spindo - Bakrie, lengkap dengan fitting dan material bantu
H PEKERJAAN VAC
1 Pek. AC Split, independent, 2 PK, ex. Daikin 8.00 unt 6,394,420 Rp 51,155,360 2.865
AC Split 2 PK, ex. Daikin, lkp outdoor, terpasang
2 Pek. Pipa Refrigerant 8.00 set 376,992 Rp 3,015,936 0.169 0.169
Penambahan pipa refrigerant ke dak atap - 5m
3 Pek. Dudukan Outdoor pada dak atap 8.00 unt 554,356 Rp 4,434,848 0.248 0.248
4 Pek. Exhaust Fan 6.00 unt 806,860 Rp 4,841,160 0.271 0.271
Exhaust Fan, ceiling mounted, 120 CFM ex. Vanco, Sekai
5 Pek. Ducting Exhaust Fan 6.00 set 226,600 Rp 1,359,600 0.076 0.038 0.038
BJLS 200x200mm, 4 meter, ducting dengan insulator,
6 Pek. Grill Exhaust Fan 6.00 unt 206,800 Rp 1,240,800 0.069 0.035 0.035
7 Pek. Testing & Comissioning 1.00 ls 2,500,000 Rp 2,500,000 0.140
I PEKERJAAN FURNITURE
1 Meja Workstation 6 kursi 6 unt 12,280,000 Rp 73,680,000 4.126 1.032 1.032 ###
Workstation lengkap, 6 seat, customade sesuai gambar,
lkp receptacle 6 set dan instalasi elektrikal
2 1 set Meja Senior Manajer 2 unt 8,850,000 Rp 17,700,000 0.991 0.248 0.248 ###
Meja workstation lengkap, customade sesuai gambar,
lkp mobile drawer 40cm, receptacle dan instalasi elektrikal
3 1 set Meja Sekretaris 2 unt 5,890,000 Rp 11,780,000 0.660 0.165 0.165 ###
Meja workstation lengkap, customade sesuai gambar,
lkp receptacle dan instalasi elektrikal
4 1 set Meja Manajer (MGR-01) 1 unt 7,500,000 Rp 7,500,000 0.420 0.105 0.105 ###
Meja workstation lengkap, 4 seat, customade sesuai gambar,
lkp meja bundar dan receptacle serta instalasi elektrikal
5 1 set Meja Manajer (MGR-02) 4 unt 9,500,000 Rp 38,000,000 2.128 0.532 0.532 ###
Meja workstation lengkap, 4 seat, customade sesuai gambar,
lkp meja bundar dan receptacle serta instalasi elektrikal
6 Mobile Drawer (MDR-01) 49 unt 3,755,000 Rp 183,995,000 10.304 2.576 2.576 ###
Rak Mobile Drawer sesuai gambar
3 Lemari File (LF-01) 26 unt 4,355,000 Rp 113,230,000 6.341 1.585 1.585 ###
Lemari Arsip ex. Donati tipe Denzel D O C. 43-2Z Uk 160x40x87cm MAPLE
4 Meja Rapat Kecil/Bundar (MR-03) 2 unt 2,460,000 Rp 4,920,000 0.276 0.069 0.069 ###
Meja Rapat Bulat, dia. 100cm, sesuai gambar
5 Meja Rapat 12 kursi 1 set 18,460,500 Rp 18,460,500 1.034 0.258 0.258 ###
Meja Meeting Persegi,sesuai gambar
9 Lemari Loker (LF-02) 4 unt 6,700,000 Rp 26,800,000
Lemari Arsip ex. Donati tipe Denzel D O C. 43-2Z Uk 160x40x87cm MAPLE
J PENGADAAN KURSI
1 Kursi Senior Manajer 2 unt 2,730,000 Rp 5,460,000 0.306 0.102 0.102
Kursi Kantor ex. Donati tipe AZZERO 1 BLACK
2 Kursi Manajer / R. Rapat 24 unt 2,150,000 Rp 51,600,000 2.890 0.963 0.963
Kursi Kantor ex. Donati tipe AZZERO 1 BLACK
3 Kursi Hadap 60 unt 1,350,000 Rp 81,000,000 4.536 1.512 1.512
Kursi Kantor ex. Donati
4 Sofa Tamu 4 unt 5,150,000 Rp 20,600,000 1.154 0.385 0.385
Sofa 2 Dudukan ex. Belva, tipe : Niala Abu-abu Muda
5 Meja Tamu (Coffe Table 2 unt 2,750,000 Rp 5,500,000 0.308 0.103 0.103
Heim Studio Ashi Coffee Table
6 Kursi Kolaborasi 2 seater 4 unt 5,150,000 Rp 20,600,000 1.154
Furniture Customade
7 Meja Coffe Table Kolaborasi 2 unt 2,750,000 Rp 5,500,000 0.308
Furniture Customade
JUMLAH BOBOT PENGADAAN KURSI Rp 190,260,000 95.537 0.964 1.213 7.534 7.359 0.000 0.964 1.213 7.534 7.359 3.655 5.847 7.496 3.826 4.314 4.465 0.998###
JUMLAH BOBOT PER MINGGU 0.964 2.177 9.711 17.070 17.070 18.034 19.247 26.781 34.140 37.795 43.642 51.138 54.964 59.278 63.743 64.741 ###

Anda mungkin juga menyukai