REKAPITULASI

PEKERJAAN : REHAB MASID


LOKASI : ORI
DESA : ORI
TAHUN ANGGARAN : 2022

Jumlah Harga
No. Jenis Pekerjaan
(Rp.)

I REHAB WC 9,341,735.16

II PAVING BLOK 106,261,741.44

III REHAB GEDUNG MASJID 52,532,520.26

IV REHAB KUBAH MASJID 35,000,000.00

NILAI KONSTRUKSI 203,135,996.86


JUMLAH NILAI KONSTRUKSI 203,135,996.86
DIBULATKAN 203,135,000.00

TERBILANG : #NAME?

DISETUJUI OLEH DIBUAT OLEH


IMAM MASJID KETUA PANITIA
RENCANA ANGGARAN BIAYA (RAB)

PEKERJAAN : REHAB MASID


LOKASI : ORI
DESA : ORI
TAHUN ANGGARAN : 2022

HARGA
JUMLAH HARGA
NO. JENIS PEKERJAAN TEM SATUAN VOL SATUAN
(Rp.)
(Rp.)

I PEMBANGUNAN SEPTITANK( 2.5 X 1.8 )


1 Pekerjaan Pasangan
1 Galian Septitank A.2.3.1.1. M2 2.80 59,375.00 166,250.00
2 Urugan Batu karang A.3.2.1.9. M2 0.90 391,080.00 351,972.00
3 Acian Dinding & Beton A.3.2.1.2 M2 2.80 754,500.00 2,112,600.00
4 Plesteran Dinding ad. 1 pc : 4 psr A.4.4.2.4. M2 11.55 57,912.00 668,883.60
5 Rabat Beton Lantai A.A.4.1.4 M2 0.30 908,000.00 272,400.00
6 Kolom 15 x 15 A.4.1.1.5 M3 0.26 1,110,800.00 293,251.20
Bekesting A.4.1.1.22 M2 3.60 297,550.00 1,071,180.00
Pembesian Mod. 2007 6.17.0 Kg 97.53 15,562.50 1,517,732.87
7 Plat Septitank A.4.1.1.5 M3 0.41 1,110,800.00 459,871.20
Bekesting A.4.1.1.23 M2 3.70 305,950.00 1,132,015.00
Pembesian Mod. 2007 6.17.0 Kg 59.85 15,562.50 931,434.98
8 Plat Man Hole (penutup) A.4.1.1.5 M3 0.02 1,110,800.00 22,216.00
Bekesting A.4.1.1.23 M2 0.83 305,950.00 253,938.50
Pembesian Mod. 2007 6.17.0 Kg 5.65 15,562.50 87,989.81
Jumlah 9,341,735.16
TOTAL 9,341,735.16
II PAVING BLOK
1 Pekerjaan Tanah
1 Galian Tanah Pondasi A.2.3.1.1. M3 3.82 59,375.00 226,788.75
1 Urugan Pasir Bawah Lantai Paving T= 5 cm A.2.3.1.11 M3 4.24 191,750.00 813,787.00
Jumlah 1,040,575.75
2 Pekerjaan Pasangan
1 Pasangan Pondasi Batako A.4.4.1.9. M2 25.46 151,675.00 3,862,252.20
2 Pekerjaan Paving Block Uk 10x21x6 A.4.4.1.9.1 M2 509.28 197,104.42 100,381,339.92
3 Plesteran Pondasi Paving A.4.4.2.4. M2 10.61 57,912.00 614,446.32
4 Acian Pondasi pAving A.4.4.2.27 M2 10.61 34,225.00 363,127.25
Jumlah 105,221,165.69
Jumlah 106,261,741.44
III REHAB GEDUNG MASJID
1 PEKERJAAN PENGGANTUNG
1 Kunci Tanam Pintu Besar (Kualitas Baik) A.4.6.2.2. Bh 3.00 320,125.00 960,375.00
2 Engsel 4" (Pintu) A.4.6.2.5 Psg 3.00 76,850.00 230,550.00
3 Grendel Pintu A.4.6.2.3. Bh 3.00 175,125.00 525,375.00
3 Engsel 3" (Jendela) A.4.6.2.6 Psg 12.00 54,562.50 654,750.00
4 Grendel Jendela A.4.6.2.8 Bh 12.00 50,062.50 600,750.00
5 Kait Angin A.4.6.2.9 Psg 12.00 55,750.00 669,000.00
Jumlah 3,640,800.00
2 PEKERJAAN KAYU, ATAP & PLAFOND
1 List Plank A.4.6.1.22 M2 117.74 67,525.00 7,950,393.50
2 Multiroof A.4.5.2.31 M2 158.85 108,140.00 17,177,498.30
3 Nok Multiroof A.4.5.2.39 M2 49.50 38,105.00 1,886,197.50
4 Rangka Plafond Ukuran (60 x 120 cm) A.4.6.1.20 M2 64.13 108,640.00 6,967,083.20
5 Plafond Tripleks ukuran (60x120) tbl 4 mm A.4.5.1.5. M2 128.26 54,575.00 6,999,789.50
Jumlah 40,980,962.00
3 PEKERJAAN LANTAI KERAMIK & PENGECATAN
1 Cat Dinding & Beton dengan (2x + Cat Dasar 1x) A.4.7.1.10 M2 91.32 69,687.50 6,363,862.50
2 Cat Plafond dengan (2x + Cat Dasar 1x) A.4.7.1.4. M2 32.07 48,242.50 1,546,895.76
Jumlah 7,910,758.26
Jumlah 52,532,520.26
IV REHAB KUBAH MASJID
1 Kuba Enamel br-1 LS 1.00 35,000,000.00 35,000,000.00
Jumlah 35,000,000.00
GRAND TOTAL 203,135,996.86
RINCIAN ANGGARAN BIAYA

PEKERJAAN : REHAB MASID


LOKASI : ORI
DESA : ORI
TAHUN ANGGARAN : 2022

HARGA JUMLAH
NO. URAIAN SATUAN VOLUME
(Rp.) (Rp.)

A UPAH
1 Mandor OH 125,000.00 15.50 1,937,500.00
2 Kepala Tukang OH 125,000.00 20.00 2,500,000.00
3 Tukang Batu OH 125,000.00 88.20 11,025,000.00
4 Tukang Kayu OH 125,000.00 18.90 2,362,500.00
5 Pekerja OH 75,000.00 308.90 23,167,500.00
TOTAL II 40,992,500.00
B BAHAN - -
1 Paving Block Uk 6x10,5x21 Bh 3,000.00 23,096.60 69,289,800.00
2 Batu Kali M3 178,000.00 4.40 783,200.00
3 Batako Bh 3,000.00 763.90 2,291,700.00
4 Batu Krikil (Kg) Kg 200.00 1,038.90 207,780.00
5 Pasir Pasang M3 200,000.00 23.50 4,700,000.00
6 Pasir Beton Kg 200.00 755.10 151,020.00
7 Pasir Urug M3 140,000.00 5.10 714,000.00
8 Semen PC (Kg) Kg 1,300.00 7,106.70 9,238,710.00
9 Sement Warna Kg 25,000.00 - -
10 Air Liter 500.00 210.10 105,050.00
11 Besi Beton Polos Atau Ulir kg 13,000.00 171.20 2,225,600.00
12 Cat Dasar Tembok Kg 150,000.00 23.70 3,555,000.00
13 Cat Tembok Klas B Kg 155,000.00 9.10 1,410,500.00
14 Cat Kayu Kg 79,000.00 8.30 655,700.00
15 Plamir Kg 46,500.00 13.90 646,350.00
16 Menie Kayu Kg 30,000.00 11.90 357,000.00
17 Minyak Thener Kg 33,000.00 1.00 33,000.00
18 Dolken Kayu Galam Batang 20,000.00 16.30 326,000.00
19 Engsel Jendela 3" Pasang 40,000.00 12.00 480,000.00
20 Engsel Pintu 4" Pasang 55,000.00 3.00 165,000.00
21 Gerendel Jendela Bh 15,000.00 12.00 180,000.00
22 Kayu Klas II M3 2,800,000.00 2.50 7,000,000.00
23 Papan Kayu Kls I M3 7,000,000.00 - -
24 Papan Kayu Kls III M3 1,750,000.00 0.30 525,000.00
25 Lis plafon Profil 6 x 6 cm M' 35,000.00 - -
26 Tripleks 4 mm Lbr 85,000.00 48.10 4,088,500.00
27 Kawat Ikat Kg 25,000.00 2.40 60,000.00
28 Kunci Tanam 2 Slaag Bh 250,000.00 3.00 750,000.00
29 Kunci Tanam KM/WC Bh 105,000.00 3.00 315,000.00
30 Kertas Amplas Lbr 6,000.00 6.40 38,400.00
31 Kait Angin Kls B Bh 33,000.00 12.00 396,000.00
32 Tegel Keramik 40/40 Bh 12,500.00 - -
33 Minyak Bakesting Liter 5,000.00 1.60 8,000.00
34 Paku Campuran Kg 22,000.00 30.30 666,600.00
35 Paku Triplek Kg 27,500.00 3.80 104,500.00
36 Multiroof BJLS 0.20 Lbr 69,000.00 206.50 14,248,500.00
37 Multiroof Datar BJLS 0.20 Lbr 52,000.00 14.90 774,800.00
38 Play Wood 3 mm uk. 120 x 240 cm Lbr 105,000.00 2.80 294,000.00
39 Pipa PVC dia. 3" M' 62,500.00 - -
40 Pipa PVC dia. 1/2" M' 11,000.00 - -
41 Kloset Duduk Bh 385,000.00 - -
42 Perlengkapan Kloset Duduk Bh 385,000.00 - -
43 Kran Air 3/4 Bh 55,000.00 - -
44 Seal Tape Set 8,000.00 - -
45 Floordrain (metal) Set 37,000.00 - -
46 Lem Kayu Kg 7,500.00 - -
TOTAL II 126,784,710.00
C PEKERJAAN BORONGAN - -
1 kubah Bh 35,000,000.00 1.00 35,000,000.00

TOTAL III 35,000,000.00


GRAND TOTAL 202,777,210.00
ANALISA HARGA SATUAN SNI 2016

HARGA SATUAN JUMLAH


No. Uraian Kegiatan
(Rp.) (Rp.)

A.2.3.1.1. Penggalian 1M³ Tanah biasa sedalam 1 m 59,375.00


0.750 OH Pekerja 75,000.00 56,250.00
0.025 OH Mandor 125,000.00 3,125.00
A.2.3.1.11. Pengurungan 1M³ dengan pasir urug 191,750.00
0.300 OH Pekerja 75,000.00 22,500.00
0.010 OH Mandor 125,000.00 1,250.00
1.200 M3 Pasir Urug 140,000.00 168,000.00
A.3.2.1.9. Pemasangan 1M³ batu kosong ( anstamping ) 391,080.00
0.780 OH Pekerja 75,000.00 58,500.00
0.390 OH Tukang Batu 125,000.00 48,750.00
0.039 OH Kepala Tukang 125,000.00 4,875.00
0.039 OH Mandor 125,000.00 4,875.00
1.200 M3 Batu Kali 178,000.00 213,600.00
0.432 M3 Pasir Urug 140,000.00 60,480.00
A.3.2.1.2 Pemasangan 1 m3 pondasi batu belah campuran 1 SP : 4 PP 754,500.00
1.500 OH Pekerja 75,000.00 112,500.00
0.750 OH Tukang Kayu 125,000.00 93,750.00
0.075 OH Kepala Tukang 125,000.00 9,375.00
0.075 OH Mandor 125,000.00 9,375.00
1.200 M3 Batu Kali 178,000.00 213,600.00
163.000 Kg Semen PC (Kg) 1,300.00 211,900.00
0.520 M3 Pasir Pasang 200,000.00 104,000.00
HARGA SATUAN JUMLAH
No. Uraian Kegiatan
(Rp.) (Rp.)

A.A.4.1.4 Pembuatan 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 908,000.00
1.200 OH Pekerja 75,000.00 90,000.00
0.200 OH Tukang Kayu 125,000.00 25,000.00
0.020 OH Kepala Tukang 125,000.00 2,500.00
0.060 OH Mandor 125,000.00 7,500.00
230.000 Kg Semen PC (Kg) 1,300.00 299,000.00
893.000 Kg Pasir Beton 200.00 178,600.00
1,027.00 Kg Batu Krikil (Kg) 200.00 205,400.00
200.000 Liter Air 500.00 100,000.00
Membuat 1 m3 beton mutu f’ = 19,3 MPa (K 225), slump (120 ± 20) mm, w/c = 0,58 1,110,800.00
1.650 OH Pekerja 75,000.00 123,750.00
0.275 OH Tukang Kayu 125,000.00 34,375.00
0.028 OH Kepala Tukang 125,000.00 3,500.00
0.083 OH Mandor 125,000.00 10,375.00
371.000 Kg Semen PC (Kg) 1,300.00 482,300.00
698.000 Kg Pasir Beton 200.00 139,600.00
1,047.00 Kg Batu Krikil (Kg) 200.00 209,400.00
215.000 Liter Air 500.00 107,500.00
A.4.1.1.22 Pemasangan 1 M² Bekisting Untuk Kolom 297,550.00
0.660 OH Pekerja 75,000.00 49,500.00
0.330 OH Tukang Kayu 125,000.00 41,250.00
0.033 OH Kepala Tukang 125,000.00 4,125.00
0.033 OH Mandor 125,000.00 4,125.00
0.040 M3 Papan Kayu Kls III 1,750,000.00 70,000.00
0.400 Kg Paku Campuran 22,000.00 8,800.00
0.200 Liter Minyak Bakesting 5,000.00 1,000.00
0.015 M3 Kayu Klas II 2,800,000.00 42,000.00
0.350 Lbr Play Wood 3 mm uk. 120 x 240 cm 105,000.00 36,750.00
2.000 Btg Dolken Kayu Galam 20,000.00 40,000.00
A.4.1.1.23 Pemasangan 1 M² Bekisting Untuk Balok 305,950.00
0.660 OH Pekerja 75,000.00 49,500.00
0.330 OH Tukang Kayu 125,000.00 41,250.00
0.033 OH Kepala Tukang 125,000.00 4,125.00
0.033 OH Mandor 125,000.00 4,125.00
0.040 M3 Papan Kayu Kls III 1,750,000.00 70,000.00
0.400 Kg Paku Campuran 22,000.00 8,800.00
0.200 Liter Minyak Bakesting 5,000.00 1,000.00
0.018 M3 Kayu Klas II 2,800,000.00 50,400.00
0.350 Lbr Play Wood 3 mm uk. 120 x 240 cm 105,000.00 36,750.00
2.000 Btg Dolken Kayu Galam 20,000.00 40,000.00
HARGA SATUAN JUMLAH
No. Uraian Kegiatan
(Rp.) (Rp.)

Pembesian 1 Kg dengan besi Polos Atau Ulir 15,562.50


0.007 OH Pekerja 75,000.00 525.00
0.007 OH Tukang Kayu 125,000.00 875.00
0.0007 OH Kepala Tukang 125,000.00 87.50
0.0004 OH Mandor 125,000.00 50.00
1.050 Kg Besi Polos Atau Ulir 13,000.00 13,650.00
0.015 Kg Kawat Ikat 25,000.00 375.00
A.4.4.1.23. Pemasangan 1 m2 dinding batako, Camp. 1 SP : 4 PP 151,675.00
0.300 OH Pekerja 75,000.00 22,500.00
0.100 OH Tukang Kayu 125,000.00 12,500.00
0.010 OH Kepala Tukang 125,000.00 1,250.00
0.015 OH Mandor 125,000.00 1,875.00
30.000 Bh Batako 3,000.00 90,000.00
11.500 Kg Semen PC (Kg) 1,300.00 14,950.00
0.043 M3 Pasir Pasang 200,000.00 8,600.00
A.4.4.1.230. Pemasangan 1 m2 Paving Blok, Uk 10.5x21, t=6 cm 197,104.42
0.400 OH Pekerja 75,000.00 30,000.00
0.020 OH Tukang Kayu 125,000.00 2,500.00
0.020 OH Kepala Tukang 125,000.00 2,500.00
0.020 OH Mandor 125,000.00 2,500.00
45.351 Bh Paving Block Uk 6x10,5x21 3,000.00 136,054.42
11.500 Kg Semen PC (Kg) 1,300.00 14,950.00
0.043 M3 Pasir Pasang 200,000.00 8,600.00
HARGA SATUAN JUMLAH
No. Uraian Kegiatan
(Rp.) (Rp.)

A.4.4.2.4. Pemasangan 1 m2 plesteran 1 SP : 4 PP, tebal 15 mm 57,912.00


0.300 OH Pekerja 75,000.00 22,500.00
0.150 OH Tukang Batu 125,000.00 18,750.00
0.015 OH Kepala Tukang 125,000.00 1,875.00
0.015 OH Mandor 125,000.00 1,875.00
6.240 Kg Semen PC (Kg) 1,300.00 8,112.00
0.024 M3 Pasir Pasang 200,000.00 4,800.00
A.4.4.2.3. Pemasangan 1 m2 plesteran 1 SP : 3 PP, tebal 15 mm 59,708.80
0.300 OH Pekerja 75,000.00 22,500.00
0.150 OH Tukang Batu 125,000.00 18,750.00
0.015 OH Kepala Tukang 125,000.00 1,875.00
0.015 OH Mandor 125,000.00 1,875.00
7.776 Kg Semen PC (Kg) 1,300.00 10,108.80
0.023 M3 Pasir Pasang 200,000.00 4,600.00
A.4.4.2.27. Pemasangan 1 m2 acian 34,225.00
0.200 OH Pekerja 75,000.00 15,000.00
0.100 OH Tukang Batu 125,000.00 12,500.00
0.010 OH Kepala Tukang 125,000.00 1,250.00
0.010 OH Mandor 125,000.00 1,250.00
3.250 Kg Semen PC (Kg) 1,300.00 4,225.00
A.4.4.3.4. Pemasangan 1 m2 lantai ubin warna ukuran (40 x 40) cm 174,740.00
0.250 OH Pekerja 75,000.00 18,750.00
0.125 OH Tukang Batu 125,000.00 15,625.00
0.013 OH Kepala Tukang 125,000.00 1,625.00
0.013 OH Mandor 125,000.00 1,625.00
6.630 Bh Tegel Keramik 40/40 12,500.00 82,875.00
9.800 Kg Semen PC (Kg) 1,300.00 12,740.00
0.045 M3 Pasir Pasang 200,000.00 9,000.00
1.300 Kg Sement Warna 25,000.00 32,500.00
A.4.6.1.1. Pembuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas I 11,191,250.00
7.000 OH Pekerja 75,000.00 525,000.00
21.000 OH Tukang Batu 125,000.00 2,625,000.00
2.100 OH Kepala Tukang 125,000.00 262,500.00
0.350 OH Mandor 125,000.00 43,750.00
1.100 M3 Kayu Klas I 7,000,000.00 7,700,000.00
1.250 Kg Paku Campuran 22,000.00 27,500.00
1.000 Kg Lem Kayu 7,500.00 7,500.00
A.4.6.1.5. Pembuatan dan pemasangan 1 m2 daun pintu panel, kayu kelas I 777,500.00
1.000 OH Pekerja 75,000.00 75,000.00
3.000 OH Tukang Batu 125,000.00 375,000.00
0.300 OH Kepala Tukang 125,000.00 37,500.00
0.050 OH Mandor 125,000.00 6,250.00
0.040 M3 Papan Kayu Kls I 7,000,000.00 280,000.00
0.500 M3 Lem Kayu 7,500.00 3,750.00
HARGA SATUAN JUMLAH
No. Uraian Kegiatan
(Rp.) (Rp.)

A.4.6.1.14. Kuda-Kuda Kayu Kelas II 5,275,700.00


4.000 OH Pekerja 75,000.00 300,000.00
12.000 OH Tukang Batu 125,000.00 1,500,000.00
1.200 OH Kepala Tukang 125,000.00 150,000.00
0.200 OH Mandor 125,000.00 25,000.00
1.100 M' Kayu Klas II 2,800,000.00 3,080,000.00
15.000 M' Besi Strip 6,500.00 97,500.00
5.600 Bh Paku Campuran 22,000.00 123,200.00
A.4.6.1.14.1 Gording Kayu Kelas II 6,608,825.00
6.700 OH Pekerja 75,000.00 502,500.00
20.100 OH Tukang Batu 125,000.00 2,512,500.00
2.010 OH Kepala Tukang 125,000.00 251,250.00
0.335 OH Mandor 125,000.00 41,875.00
1.100 M' Kayu Klas II 2,800,000.00 3,080,000.00
15.000 M' Besi Strip 6,500.00 97,500.00
5.600 Bh Paku Campuran 22,000.00 123,200.00
A.4.5.2.31. . Pemasangan 1 m² Zing Gelombang BJLS 0.20 108,140.00
0.120 OH Pekerja 75,000.00 9,000.00
0.060 OH Tukang Batu 125,000.00 7,500.00
0.006 OH Kepala Tukang 125,000.00 750.00
0.006 OH Mandor 125,000.00 750.00
1.300 Lbr Multiroof BJLS 0.20 69,000.00 89,700.00
0.020 Kg Paku Campuran 22,000.00 440.00
A.4.5.2.36. Pemasangan 1m' Nok Seng Licin Bjls 38,105.00
0.150 OH Pekerja 75,000.00 11,250.00
0.070 OH Tukang Batu 125,000.00 8,750.00
0.007 OH Kepala Tukang 125,000.00 875.00
0.006 OH Mandor 125,000.00 750.00
0.300 Lbr Multiroof Datar BJLS 0.20 52,000.00 15,600.00
0.040 Kg Paku Campuran 22,000.00 880.00
Pemasangan 1 m’ lisplank ukuran (3 x 30) cm, kayu kelas I atau kelas II 67,525.00
0.100 OH Pekerja 75,000.00 7,500.00
0.200 OH Tukang Batu 125,000.00 25,000.00
0.020 OH Kepala Tukang 125,000.00 2,500.00
0.005 OH Mandor 125,000.00 625.00
0.011 Lbr Kayu Klas II 2,800,000.00 30,800.00
0.050 Kg Paku Campuran 22,000.00 1,100.00
A.4.6.1.20.Pemasangan 1M² Rangka langit langit Kayu Klas II 108,640.00
0.200 OH Pekerja 75,000.00 15,000.00
0.300 OH Tukang Batu 125,000.00 37,500.00
0.030 OH Kepala Tukang 125,000.00 3,750.00
0.010 OH Mandor 125,000.00 1,250.00
0.016 M3 Kayu Klas II 2,800,000.00 45,640.00
0.250 Kg Paku Campuran 22,000.00 5,500.00
A.4.5.1.5.Pemasangan 1M² Langit - Langit Triplex 4 mm Kayu Klas II 54,575.00
0.100 OH Pekerja 75,000.00 7,500.00
0.100 OH Tukang Batu 125,000.00 12,500.00
0.010 OH Kepala Tukang 125,000.00 1,250.00
0.005 OH Mandor 125,000.00 625.00
0.375 Lbr Tripleks 4 mm 85,000.00 31,875.00
0.030 Kg Paku Triplek 27,500.00 825.00
HARGA SATUAN JUMLAH
No. Uraian Kegiatan
(Rp.) (Rp.)

A.4.5.1.9. Pemasangan 1M' List Langit-Langit Kayu Profil 47,750.00


0.050 OH Pekerja 75,000.00 3,750.00
0.050 OH Tukang Batu 125,000.00 6,250.00
0.005 OH Kepala Tukang 125,000.00 625.00
0.003 OH Mandor 125,000.00 375.00
1.050 M' Lis plafon Profil 6 x 6 cm 35,000.00 36,750.00
A.5.5.1.1. Memasang 1 buah Kloset Duduk / Monoblok 814,350.00
3.300 OH Pekerja 75,000.00 247,500.00
1.100 OH Tukang Batu 125,000.00 137,500.00
0.010 OH Kepala Tukang 125,000.00 1,250.00
0.160 OH Mandor 125,000.00 20,000.00
1.000 Bh Kloset Duduk 385,000.00 385,000.00
6% % Perlengkapan Kloset Duduk 385,000.00 23,100.00
A.5.1.1.19. Pemasangan 1 buah kran dia. 1/2" atau 3/4" 70,325.00
0.010 OH Pekerja 75,000.00 750.00
0.100 OH Tukang Batu 125,000.00 12,500.00
0.010 OH Kepala Tukang 125,000.00 1,250.00
0.005 OH Mandor 125,000.00 625.00
1.000 Bh Kran Air 3/4 55,000.00 55,000.00
0.025 Bh Seal Tape 8,000.00 200.00
A.5.1.1.14. Pemasangan 1 buah Floor drain 52,125.00
0.010 OH Pekerja 75,000.00 750.00
0.100 OH Tukang Batu 125,000.00 12,500.00
0.010 OH Kepala Tukang 125,000.00 1,250.00
0.005 OH Mandor 125,000.00 625.00
1.000 Bh Floordrain (metal) 37,000.00 37,000.00
A.5.1.1.27. Pemasangan 1 M' pipa PVC tipe AW dia. 1/2" 28,250.00
0.036 OH Pekerja 75,000.00 2,700.00
0.060 OH Tukang Batu 125,000.00 7,500.00
0.006 OH Kepala Tukang 125,000.00 750.00
0.002 OH Mandor 125,000.00 250.00
1.200 M' Pipa PVC dia. 1/2" 11,000.00 13,200.00
35% % Perlengkapan Pipa 11,000.00 3,850.00
A.5.1.1.28. Pemasangan 1 M' pipa PVC tipe AW dia. 3" 122,075.00
0.081 OH Pekerja 75,000.00 6,075.00
0.135 OH Tukang Batu 125,000.00 16,875.00
0.014 OH Kepala Tukang 125,000.00 1,750.00
0.004 OH Mandor 125,000.00 500.00
1.200 M' Pipa PVC dia. 3" 62,500.00 75,000.00
35% % Perlengkapan Pipa 62,500.00 21,875.00
A.4.6.2.2. Pemasangan 1 Buah Tanam Biasa 320,125.00
0.010 OH Pekerja 75,000.00 750.00
0.500 OH Tukang Batu 125,000.00 62,500.00
0.050 OH Kepala Tukang 125,000.00 6,250.00
0.005 OH Mandor 125,000.00 625.00
1.000 Bh Kunci Tanam 2 Slaag 250,000.00 250,000.00
A.4.6.2.3. Pemasangan 1 Buah kunci Tanam Kamar Mandi 175,125.00
0.010 OH Pekerja 75,000.00 750.00
0.500 OH Tukang Batu 125,000.00 62,500.00
0.050 OH Kepala Tukang 125,000.00 6,250.00
0.005 OH Mandor 125,000.00 625.00
1.000 Bh Kunci Tanam KM/WC 105,000.00 105,000.00
A.4.6.2.5 PASANG 1 BH ENGSEL PINTU 76,850.00
0.015 OH Pekerja 75,000.00 1,125.00
0.150 OH Tukang Batu 125,000.00 18,750.00
0.015 OH Kepala Tukang 125,000.00 1,875.00
0.001 OH Mandor 125,000.00 100.00
1.000 Bh Engsel Pintu 4" 55,000.00 55,000.00
A.4.6.2.6 PASANG 1 BH ENGSEL JENDELA 54,562.50
0.010 OH Pekerja 75,000.00 750.00
0.100 OH Tukang Batu 125,000.00 12,500.00
0.010 OH Kepala Tukang 125,000.00 1,250.00
0.001 OH Mandor 125,000.00 62.50
1.000 Bh Engsel Jendela 3" 40,000.00 40,000.00
A.4.6.2.7 PASANG GRENDEL PINTU 50,062.50
0.100 OH Pekerja 75,000.00 7,500.00
0.200 OH Tukang Batu 125,000.00 25,000.00
0.020 OH Kepala Tukang 125,000.00 2,500.00
0.001 OH Mandor 125,000.00 62.50
1.000 Bh Gerendel Pintu 15,000.00 15,000.00
A.4.6.2.7 PASANG GRENDEL JENDELA 50,062.50
0.100 OH Pekerja 75,000.00 7,500.00
0.200 OH Tukang Batu 125,000.00 25,000.00
0.020 OH Kepala Tukang 125,000.00 2,500.00
0.001 OH Mandor 125,000.00 62.50
1.000 Bh Gerendel Jendela 15,000.00 15,000.00
A.4.6.2.9 PASANG 1 BH KAIT ANGIN 55,750.00
0.015 OH Pekerja 75,000.00 1,125.00
0.150 OH Tukang Batu 125,000.00 18,750.00
0.015 OH Kepala Tukang 125,000.00 1,875.00
0.008 OH Mandor 125,000.00 1,000.00
1.000 Bh Kait Angin Kls B 33,000.00 33,000.00
HARGA SATUAN JUMLAH
No. Uraian Kegiatan
(Rp.) (Rp.)

PASANG LAMPU PIJAR PHILIPS 18 WATT #N/A


0.5000 Ls Tukang Listrik 125,000.00 62,500.00
1.000 Bh #N/A #N/A #N/A
PASANG STOP KONTAK #N/A
0.5000 Ls Tukang Listrik 125,000.00 62,500.00
1.000 Bh #N/A #N/A #N/A
PASANG SAKLAR TUNGGAL #N/A
0.5000 Ls Tukang Listrik 125,000.00 62,500.00
1.000 Bh #N/A #N/A #N/A
PASANG SAKLAR GANDA #N/A
0.5000 Ls Tukang Listrik 125,000.00 62,500.00
1.000 Bh #N/A #N/A #N/A
PASANG VITTING #N/A
0.5000 Ls Tukang Listrik 125,000.00 62,500.00
1.000 Bh #N/A #N/A #N/A
PASANG KABEL NYM 3 x 2.5 22,250.00
0.0500 Ls Tukang Listrik 125,000.00 6,250.00
1.000 M Kabel NYM 3 x 2.5 mm 16,000.00 16,000.00
PASANG KABEL NYM 3 x 2.5 21,250.00
0.0500 Ls Tukang Listrik 125,000.00 6,250.00
1.000 M Kabel NYM 3 x 1.5 mm 15,000.00 15,000.00
PASANG KABEL NYM 3 x 2.5 15,250.00
0.0500 Ls Tukang Listrik 125,000.00 6,250.00
1.000 M Kabel NYM 2 x 1.5 mm 9,000.00 9,000.00
Pemasangan 1 UNIT MCB & Sekring Khast 342,500.00
0.5000 Ls Tukang Listrik 125,000.00 62,500.00
1.0000 Unit MCB 60 AMP 210,000.00 210,000.00
1.0000 Unit Sekring 70,000.00 70,000.00
A.4.7.1.10. Pengecatan 1 m² Tembok Baru ( 1 Plamir, 1 Lapis Cat Dasar, 2 Lapis Cat Penutup ) 69,687.50
0.020 OH Pekerja 75,000.00 1,500.00
0.063 OH Tukang Batu 125,000.00 7,875.00
0.006 OH Kepala Tukang 125,000.00 787.50
0.003 OH Mandor 125,000.00 375.00
0.100 Kg Plamir 46,500.00 4,650.00
0.100 Kg Cat Tembok Klas B 155,000.00 15,500.00
0.260 Kg Cat Dasar Tembok 150,000.00 39,000.00
A.4.7.1.4. 1M2 Pengecetan bidang kayu baru (1 lapisan plamuur, 1 lapisan cat dasar, 2 lapisan cat penutup 48,242.50
0.070 OH Pekerja 75,000.00 5,250.00
0.009 OH Tukang Batu 125,000.00 1,125.00
0.006 OH Kepala Tukang 125,000.00 750.00
0.003 OH Mandor 125,000.00 312.50
0.200 Kg Menie Kayu 30,000.00 6,000.00
0.150 Kg Plamir 46,500.00 6,975.00
0.170 Kg Menie Kayu 30,000.00 5,100.00
0.260 Kg Cat Kayu 79,000.00 20,540.00
0.030 Kg Pengencer 33,000.00 990.00
0.200 Kg Ampelas 6,000.00 1,200.00
1.000 Bh Err:509 Err:509 Err:509
1.000 Bh kubah 35,000,000.00 35,000,000.00
DAFTAR UPAH DAN HARGA BAHAN

PEKERJAAN : REHAB MASID


LOKASI : ORI
DESA : ORI
TAHUN ANGGARAN : 2022

HARGA SATUAN
NO. URAIAN SATUAN
(Rp.)

A UPAH
1 Mandor OH 125,000.00
2 Kepala Tukang OH 125,000.00
3 Tukang Batu OH 125,000.00
4 Tukang Kayu OH 125,000.00
5 Tukang Listrik OH 125,000.00
6 Pekerja OH 75,000.00

B BAHAN
1 Kayu Klas I M3 7,000,000.00
2 Kayu Klas II M3 2,800,000.00
3 Papan Kayu Kls I M3 7,000,000.00
4 Papan Kayu Kls III M3 1,750,000.00
5 Batu Kerikil Pecah ( 3 / 2 cm ) M3 235,000.00
6 Pasir Pasang M3 200,000.00
7 Pasir Urug M3 140,000.00
8 Tanah Timbunan M3 120,000.00
9 Batu Karang M3 178,000.00
10 Batu Kali M3 178,000.00
11 Pasir Beton Kg 200.00
12 Batu Krikil (Kg) Kg 200.00
13 Batako Bh 3,000.00
14 Paving Block Uk 6x10,5x21 Bh 3,000.00
15 Beugel Kuda-kuda Bh 12,000.00
16 Besi Strip Kg 6,500.00
17 Semen PC (Zak) Sak 65,000.00
18 Semen PC (Kg) Kg 1,300.00
19 Sement Warna Kg 25,000.00
20 Air Liter 500.00
21 Besi Beton Polos Atau Ulir kg 13,000.00
22 Cat Dasar Tembok Kg 150,000.00
23 Cat Tembok Klas B Kg 155,000.00
24 Cat Kayu Kg 79,000.00
25 Plamir Kg 46,500.00
26 Politur Liter 70,000.00
27 Menie Kayu Kg 30,000.00
28 Minyak Thener Kg 33,000.00
HARGA SATUAN
NO. URAIAN SATUAN
(Rp.)

29 Dolken Kayu Galam Batang 20,000.00


30 Kuas Tangan 4 " Bh 22,000.00
31 Engsel Jendela 3" Pasang 40,000.00
32 Engsel Pintu 4" Pasang 55,000.00
33 Engsel Pintu Gembok Pasang 22,500.00
34 Gerendel Pintu Bh 15,000.00
35 Gerendel Jendela Bh 15,000.00
35 Lis plafon Profil 6 x 6 cm M' 35,000.00
36 Tripleks 4 mm Lbr 85,000.00
37 Kawat Ikat Kg 25,000.00
38 Kunci Tanam 2 Slaag Bh 250,000.00
39 Kunci Tanam KM/WC Bh 105,000.00
40 Kunci Teralis Penjara (Gembok Besar ) Bh 175,000.00
41 Kertas Amplas Lbr 6,000.00
42 Kait Angin Kls B Bh 33,000.00
43 Tegel Keramik 40/40 Bh 12,500.00
44 Minyak Bakesting Liter 5,000.00
45 Paku / Skrup Genteng Kg 30,000.00
46 Paku Campuran Kg 22,000.00
47 Paku Triplek Kg 27,500.00
48 MCB 60 AMP Bh 210,000.00
49 Kabel NYM 3 x 2.5 mm M 16,000.00
50 Kabel NYM 3 x 1.5 mm M 15,000.00
51 Kabel NYM 2 x 1.5 mm M 9,000.00
52 Multiroof BJLS 0.20 Lbr 69,000.00
53 Multiroof Datar BJLS 0.20 Lbr 52,000.00
54 Play Wood 3 mm uk. 120 x 240 cm Lbr 105,000.00
55 Pipa PVC dia. 3" M' 62,500.00
56 Pipa PVC dia. 1/2" M' 11,000.00
57 Socket PVC dia 1 " Bh 5,000.00
58 Kloset Duduk Bh 385,000.00
59 Perlengkapan Kloset Duduk Bh 385,000.00
60 Kran Air 3/4 Bh 55,000.00
61 Kran Air 1/2 Bh 25,000.00
62 Seal Tape Set 8,000.00
63 Floordrain (metal) Set 37,000.00
64 Sekring Bh 70,000.00
65 Lem Kayu Kg 7,500.00
1 kubah Bh 35,000,000.00
PERHITUNGAN VOLUME PEKERJAAN
PEKERJAAN : REHAB MASID
LOKASI : ORI
DESA : ORI

No. Lokasi / Lebar Perhitungan Dimensi Luas Volume


Sketsa / Gambar Tinggi Panjang
Urut STA Atas Bawah (M) ( M2 ) ( M3 )

01. GALIAN TANAH

Galian Tanah Untuk Pondasi Saluran

0.4
0.30 0.40 358.00 0.30 x 0.4 0.12 42.96

0.30
Total Galian Tanah 42.96

02. URUGAN TANAH Total Urugan Tanah 1/4 Galian 10.7400


02. INSTALASI PIPA

1 PIPA Ø 2 " 131.00 21.83 Staff


2 PIPA Ø 1 1/2 " 42.00 7.00 Staff
3 PIPA Ø 1 " 185.00 30.83 Staff
4 PIPA Ø 1/2 " 157.00 26.17 Staff

03. PEMASANGAN METERAN

1 Jumlah KK pengguna Air 25 25 Buah


PERHITUNGAN VOLUME PEKERJAAN TAK
PEKERJAAN : REHAB MASID
LOKASI : ORI
DESA : ORI

No. Lokasi / Lebar Perhitungan Dimensi Luas Volume


Sketsa / Gambar Tinggi Panjang
Urut STA Atas Bawah (M) ( M2 ) ( M3 )

SALURAN Panjang Sumbu Tegak


= 3.5 + 3.5 + 3.5 + 1 + 3.5 + 3.5 +
3.5 + + + + + +
= 22 M

Panjang Sumbu Datar


= 16 + 3.5 + 3 + 3.5 + 3 + 0 +
0 + + + + + +
= 29 M

Total Panjang sumbu ( Tegak + Datar )

= 22 + 29
= 51 M

01. GALIAN TANAH

Galian Tanah Untuk Pondasi Saluran

0.32
0.50 0.32 51.00 0.50 x 0.3 0.16 8.16

0.50
Total Galian Tanah 8.16

02. URUGAN TANAH 1/4 Total Urugan Tanah 1/4 2.04

03. URUGAN PASIR

Urugan Pasir Bawa Lantai 0.20 0.05 51.00 0.20 x 0.05 0.01 0.51

0.05
0.20

06. PASANGAN BATU

Pasangan Batu Kali Utk Saluran

0.15 0.32 51.00 0.15 x 0.32 0.048 2.45


0.32

0.15 Total Pasangan 2 4.896

08. PASANGAN BATU BATA

Sumbu Tegak
Pasangan Batu Bata Ukuran Batu Gomblo
0.14 x 0.40 = 0.056
51.0 0.32 51.0 x 0.3 16.32
32.64
583
0.32

51
0.1 Total Pasangan 2 32.64 3.264

09. RABAT BETON TUMBUK

Rabat Beton Tumbuk Utk Saluran

0.07 0.20 0.07 51.00 0.20 x 0.07 0.014 0.71


0.20

Total Beton Tumbuk 0.714


10. PLESTERAN

Plesteran Saluran

0.15 0.15 0.9 51.00 0.9 x 51.0 45.90

0.2 0.2

Total 45.90
0.2
TAKE OF SHEET
Pekerjaan :: Pembesian Pagar
PERHITUNGAN VOLUME PEKERJAAN
PEKERJAAN : REHAB MASID
LOKASI : ORI
DESA : ORI

No. Lebar Perhitungan Dimensi Luas Volume


Lokasi / STA Sketsa / Gambar Tinggi Panjang
Urut Atas Bawah (M) ( M2 ) ( M3 )

PAGAR Panjang Sumbu Tegak


= 5 + 1.5 + 7 + 2 + 5 + 7 +
1.5 + 2 + 0 + 0 + 0 + +
= 31 M

Panjang Sumbu Datar


= 2 + 12 + 2 + 2 + 3.8 + 4.2 +
4 + 2 + 0 + 0 + + +
= 32 M

Total Panjang sumbu ( Tegak + Datar )

= 31 + 32
= 63 M / 3 = 21

01. GALIAN TANAH

Galian Tanah Untuk Pondasi

0.6 0.55 63.00 0.55 x 0.6 0.33 20.79

0.55

0.60

02. URUGAN TANAH 1/4 Total Urugan Tanah 1/4 5.1975

03. URUGAN PASIR

Urugan Pasir Bawa Pondasi 0.60 0.05 63.00 0.60 x 0.05 0.03 1.89

0.05
0.60

Total Urugan Pasir 1.890

04. TRIMBIRISAN BATU KALI

0.60 0.10 63.00 0.60 x 0.10 0.06 3.78


0.10

0.60

05. PASANGAN BATU

Pasangan Batu Kali Utk Pondasi Pagar

0.25 0.25 0.40 0.55 63.00 ( 0.25 + 0.40 ) 0.55 0.17875 11.26
2 x

0.55

0.4
Total Pasangan 11.261

06. BETON BERTULANG

Beton Bertulang Utk Kolom

4O 12
0.15 0.15 0.15 1.70 0.15 x 0.15 0.02 0.04
` 8 - 15
Jumlah Tiang 21 0.4725 0.80
Kolom 15/15
0.15
Beton Bertulang Utk Sloof

4O 12
0.15 0.20 61.00 0.15 x 0.20 0.03 1.83
0.20 O 8 - 20 Pintu 2.00

0.15 Sloof 15/20

Total Beton Sloof 1.830


Beton Bertulang Utk Balok

4O 12
0.20 0.15 0.20 61.00 0.15 x 0.20 0.03 1.83
O 8 - 20

Balok 15/20
0.15 `
Total Beton Balok 1.830

07. PASANGAN BATU BATA

Pasangan Batu Bata

61.0 1.7 61.0 x 1.7 103.70

Kolom Beton
1.7 0.15 x 0.15 x 21 0.47

61
0.1 Total Pasangan 103.23 10.32275

8. PLESTERAN

Plesteran Sumbu Tegak/Datar

1.7 61.00 1.7 x 61.0 103.70


1.70

Total 103.70
61 Total Muka Belakang 2 207.40
TAKE OF SHEET
PEKERJAAN : REHAB MASID
LOKASI : ORI Pekerjaan :: Pembesian Pagar
DESA : ORI

Pembesiaan Panjang Jumlah Total


No. Lokasi / Jarak Panjang Bangunan Total
Sketsa / Gambar Bengkokan Panjang Total Total Stap Jumlah Volume
Urut STA
Atas Bawah Besi Panjang Besi Lebar Panjang Batang (M) ( Staf )

01. Pembesian Kolom

0.03 0.03 0.03 0.03 1.70 1.76 4.00 7.04 0.6 21.00 13
1.70

4 O 12 0.03 0.03 0.48 0.54 0.10 1.70 17 9.180 0.8 21.00 18


0.12 O 8 - 10

0.12

02. Pembesian Sloof

0.03 0.03 0.03 0.03 61.00 61.06 4.00 244.24 22 1.00 22


61.00

4 O 12 0.03 0.03 0.58 0.64 0.15 61.00 407 260.267 24 1.00 24


0.17
O 8 - 15

0.12

03. Pembesian Balok

0.03 0.03 0.03 0.03 61.00 61.06 4.00 244.24 22 1.00 22


61.00

4 O 12 0.03 0.03 0.58 0.64 0.15 61.00 407 260.267 24 1.00 24


0.17
O 8 - 15

0.12

04. Pintu Pagar 1 Set

Besi dia. 10 58

Besi dia. 8 65
PERHITUNGAN VOLUME PEKERJAAN
PEKERJAAN : REHAB MASID
LOKASI : ORI
DESA : ORI

No. Lokasi / Lebar Perhitungan Dimensi Luas Volume


Sketsa / Gambar Tinggi Panjang
Urut STA Atas Bawah (M) ( M2 ) ( M3 )

01. GALIAN TANAH

Galian Tanah Untuk Pondasi

0.15
0.15 0.15 5.00 0.15 x 0.2 0.02 0.11

0.15
Total Galian Tanah 2 0.22

02. URUGAN TANAH 1/4 Total Urugan Tanah 1/4 0.056

03. URUGAN PASIR

Urugan Pasir Bawa Lantai 1.70 0.05 5.00 1.70 x 0.05 0.085 0.43

0.05
1.70

06. PASANGAN BATU

Pasangan Batu Kali Pondasi

0.15 0.3 5.00 0.15 x 0.30 0.045 0.22


0.3

0.15 Total Pasangan 2 0.450

09. RABAT BETON TUMBUK

Rabat Beton Tumbuk Lantai

0.07 1.70 0.07 5.00 1.70 x 0.07 0.119 0.60


1.70

Total Beton Tumbuk 0.595


10. PLESTERAN

Plesteran Pondasi

0.15 0.15 0.15 5.00 0.15 + 0.15 = 0.30 1.5


0.15

Total 1.50
ALUR BAHAN DAN UPAH

HARGA
No. KEBUTUHAN UPAH/BAHAN SAT HARGA SATUAN
DASAR
1 2 3 4 10
A UPAH
1 Mandor OH 125,000.00 125,000.00
2 Kepala Tukang OH 125,000.00 125,000.00
3 Tukang Batu OH 125,000.00 125,000.00
4 Tukang Kayu OH 125,000.00 125,000.00
5 Tukang Besi OH 125,000.00 125,000.00
6 Tukang Cat OH 125,000.00 125,000.00
7 Tukang Listrik OH 125,000.00 125,000.00
8 Tukang Las OH 125,000.00 125,000.00
9 Pekerja OH 75,000.00 75,000.00
10 Pembersihan Awal Dan Pembongkaran LS 5,000,000.00 5,000,000.00
11 Pembersihan Akhir Ls 7,000,000.00 7,000,000.00

B BAHAN
1 Kayu Klas I M3 7,000,000.00 7,000,000.00
2 Kayu Klas II M3 2,800,000.00 2,800,000.00
3 Papan Kayu Kls I M3 7,000,000.00 7,000,000.00
4 Papan Kayu Kls III M3 1,750,000.00 1,750,000.00
5 Batu Kerikil Pecah ( 3 / 2 cm ) M3 235,000.00 235,000.00
6 Pasir Pasang M3 200,000.00 200,000.00
7 Pasir Urug M3 140,000.00 140,000.00
8 Pasir Beton Kg 142.86 200.00
9 Batu Krikil (Kg) Kg 174.07 200.00
10 Tanah Timbunan M3 120,000.00 120,000.00
11 Batu Karang M3 178,000.00 178,000.00
12 Batu Kali M3 178,000.00 178,000.00
13 Batu Bata Bh 1,800.00 1,800.00
13 Batako Bh 3,000.00 3,000.00
14 Paving Block Uk 6x10,5x21 Bh 3,000.00 3,000.00
15 Beugel Kuda-kuda Bh 12,000.00 12,000.00
16 Besi Strip Kg 6,500.00 6,500.00
17 Semen PC (Zak) Sak 65,000.00 65,000.00
18 Semen PC (Kg) Kg 1,300.00 1,300.00
19 Sement Warna Kg 25,000.00 25,000.00
20 Air Liter 500.00 500.00
21 Besi Beton Polos Atau Ulir kg 13,000.00 13,000.00
22 Cat Kayu Kg 79,000.00 79,000.00
23 Plamir Kg 46,500.00 46,500.00
24 Politur Liter 70,000.00 70,000.00
25 Menie Kayu Kg 30,000.00 30,000.00
26 Minyak Thener Kg 33,000.00 33,000.00
27 Dolken Kayu Galam Batang 20,000.00 20,000.00
28 Kuas Tangan 4 " Bh 22,000.00 22,000.00
29 Engsel Jendela 3" Pasang 40,000.00 40,000.00
30 Engsel Pintu 4" Pasang 55,000.00 55,000.00
31 Engsel Pintu Gembok Pasang 22,500.00 22,500.00
32 Gerendel Pintu Bh 15,000.00 15,000.00
33 Gerendel Jendela Bh 15,000.00 15,000.00
33 Lis plafon Profil 6 x 6 cm M' 35,000.00 35,000.00
34 Tripleks 4 mm Lbr 85,000.00 85,000.00
35 Kawat Ikat Kg 25,000.00 25,000.00
36 Kunci Tanam 2 Slaag Bh 250,000.00 250,000.00
37 Kunci Tanam KM/WC Bh 105,000.00 105,000.00
38 Kunci Teralis Penjara (Gembok Besar ) Bh 175,000.00 175,000.00
39 Kertas Amplas Lbr 6,000.00 6,000.00
40 Kait Angin Kls B Bh 33,000.00 33,000.00
41 Tegel Keramik 40/40 Bh 12,500.00 12,500.00
42 Besi Strip Kg 5,000.00 5,000.00
43 Minyak Bakesting Liter 5,000.00 5,000.00
44 Paku / Skrup Genteng Kg 30,000.00 30,000.00
45 Paku Campuran Kg 22,000.00 22,000.00
46 Paku Triplek Kg 27,500.00 27,500.00
47 Play Wood 3 mm uk. 120 x 240 cm Lbr 105,000.00 105,000.00
48 Pintu/Jendela (Rangka Besi Hollow 4 x 4mm x 4 mm) M2 600,000.00 600,000.00
49 Besi Hollow 4 x 4mm x 4 mm-M Staff 100,000.00 100,000.00
50 Multiroof BJLS 0.20 Lbr 69,000.00 69,000.00
51 Multiroof Datar BJLS 0.20 Lbr 52,000.00 52,000.00
52 Politur Kg 70,000.00 70,000.00
53 Cat Tembok Klas B Kg 155,000.00 155,000.00
54 Cat Dasar Tembok Kg 150,000.00 150,000.00
55 Gloteks Kg 33,000.00 33,000.00
56 MCB 60 AMP Bh 210,000.00 210,000.00
57 Kabel NYM 3 x 2.5 mm M 16,000.00 16,000.00
58 Kabel NYM 3 x 1.5 mm M 15,000.00 15,000.00
59 Kabel NYM 2 x 1.5 mm M 9,000.00 9,000.00
58 Pipa PVC dia. 3" Staff 250,000.00 250,000.00
59 Pipa PVC dia. 1/2" Staff 44,000.00 44,000.00
60 Pipa PVC dia. 3" M' 62,500.00 62,500.00
61 Pipa PVC dia. 1/2" M' 11,000.00 11,000.00
62 Socket PVC dia 1 " Bh 5,000.00 5,000.00
63 Kloset Duduk Bh 385,000.00 385,000.00
64 Perlengkapan Kloset Duduk Bh 385,000.00 385,000.00
65 Kran Air 3/4 Bh 55,000.00 55,000.00
66 Kran Air 1/2 Bh 25,000.00 25,000.00
67 Seal Tape Set 8,000.00 8,000.00
68 Floordrain (metal) Set 37,000.00 37,000.00
69 Sekring Bh 70,000.00 70,000.00
70 Lem Kayu Kg 7,500.00 7,500.00
71 Pipa PVC Conduit M' 3,750.00 3,800.00
72 Lampu TL 20 Watt Bh 78,000.00 78,000.00
73 Lampu pijar philips putih 18 watt Bh 47,500.00 47,500.00
74 Lampu pijar philips putih 23 watt Bh 60,000.00 60,000.00
75 Lampu PL 11 Watt Bh 78,000.00 78,000.00
76 Saklar tunggal Bh 18,000.00 18,000.00
77 Saklar ganda Bh 25,000.00 25,000.00
78 Stop kontak Bh 23,000.00 23,000.00
C ALAT
1 kubah Bh 15,000,000.00 15,000,000.00
2 Pikuel Bh 150,000.00 150,000.00
3 Tropol Bh 25,000.00 25,000.00
4 Hammer 1/2 Kg Bh 134,153.00 134,153.00
5 Hammer 1 Kg Bh 15,000.00 15,000.00
6 Meteran (5M') Bh 21,252.00 21,252.00
7 Ember Cor Bh 85,000.00 85,000.00
8 Kunci Besi Ø 12 mm Bh 15,000.00 15,000.00
9 Kunci Besi Ø 8 mm Bh 15,000.00 15,000.00
10 Stang Gergaji Besi Bh 15,000.00 15,000.00
11 Isi Gergaji Besi Bh 15,000.00 15,000.00
12 Kuas Rol Bh 25,000.00 25,000.00
13 Kuas 3" Bh 15,000.00 15,000.00
14 Kuas 2" Bh 15,000.00 15,000.00
15 Gerobak Bh 978,920.00 978,920.00
16 Pisau Dempul Besar Bh 26,565.00 26,565.00
17 Pisau Dempul Kecil Bh 15,000.00 15,000.00
18 Benang Tukang Roll 25,000.00 25,000.00
19 Slang Waterpas M' 10,000.00 10,000.00
20 Sewa Tripot Alat Pancang + Hammer Hari 500,000.00 500,000.00
21 Sewa Mollen Hari 500,000.00 500,000.00
D OPERASIONAL DAN BIAYA LAIN-LAIN
1 Papan Nama Proyek Bh 150,000.00 150,000.00
2 Prasasti Bh 500,000.00 500,000.00
3 Insentif Pekerja Ls 650,000.00 650,000.00
4 Administrasi + Dokumentasi Ls 1,000,000.00 1,000,000.00
5 Biaya Penyambungan istrik Ls 1,500,000.00 1,500,000.00
6 As Buildrawing Ls 7,500,000.00 7,500,000.00
ALUR BAHAN DAN UPAH

HARGA PPN PPh 22 PPh 21 ONGKOS ANGKUT ONGKOS PIKUL


No. KEBUTUHAN UPAH/BAHAN SAT HARGA SATUAN
DASAR 10% 1.50% 2.50%
1 2 3 4 5 6 7 8 9 10
A UPAH
1 Mandor OH 195,000.00 5,000.00 - - 200,000.00
2 Kepala Tukang OH 170,625.00 4,375.00 - - 175,000.00
3 Tukang Batu OH 146,250.00 3,750.00 - - 150,000.00
4 Tukang Kayu OH 146,250.00 3,750.00 - - 150,000.00
5 Tukang Besi OH 146,250.00 3,750.00 - - 150,000.00
6 Tukang Cat OH 146,250.00 3,750.00 - - 150,000.00
7 Tukang Listrik OH 146,250.00 3,750.00 - - 150,000.00
8 Tukang Las OH 146,250.00 3,750.00 - - 150,000.00
9 Pekerja OH 97,500.00 2,500.00 - - 100,000.00
10 Pembersihan Awal LS 1,462,500.00 37,500.00 - - 1,500,000.00
11 Pembersihan Akhir LS 1,462,500.00 37,500.00 - - 1,500,000.00
0
B BAHAN -
1 Kayu Klas I M3 7,000,000.00 105,000.00 75,000.00 75,000.00 7,255,000.00
2 Kayu 15 x 15-4M M' 100,800.00 2,362.50 1,687.50 1,687.50 106,600.00
3 Alat Bantu Pancang Set 100,000.00 100,000.00
4 Kayu 15 x 15-750 M M3 100,800.00 2,362.50 1,687.50 1,687.50 106,600.00
5 Kayu 20 x 20-1000 cm M3 280,000.00 4,200.00 3,000.00 3,000.00 290,200.00
6 Kayu Klas II M3 2,800,000.00 42,000.00 75,000.00 2,917,000.00
7 Papan Kayu Kls I M3 7,000,000.00 105,000.00 75,000.00 7,180,000.00
8 Balok Kayu Kls II M3 1,750,000.00 26,250.00 75,000.00 1,851,300.00
9 Kayu Kls III M3 1,750,000.00 26,250.00 75,000.00 1,851,300.00
9 Batu Kerikil Pecah ( 3 / 2 cm ) M3 235,000.00 3,525.00 75,000.00 313,600.00
9 Pasir Pasang M3 200,000.00 3,000.00 75,000.00 278,000.00
10 Pasir Urug M3 140,000.00 2,100.00 75,000.00 217,100.00
11 Pasir Beton Kg 142.86 2.14 53.57 - 200.00
12 Batu Krikil (Kg) Kg 174.07 2.61 55.56 - 300.00
13 Tanah Timbunan M3 120,000.00 1,800.00 75,000.00 25,000.00 221,800.00
14 Batu Karang M3 178,000.00 2,670.00 75,000.00 25,000.00 280,700.00
15 Batu Kali M3 178,000.00 2,670.00 75,000.00 25,000.00 280,700.00
16 Batu Bata Bh 1,800.00 27.00 200.00 2,100.00
17 Batako Bh 2,500.00 37.50 200.00 2,800.00
18 Beugel Kuda-kuda Bh 12,000.00 180.00 200.00 12,400.00
19 Besi Strip Kg 6,500.00 97.50 200.00 6,800.00
20 Semen PC (Zak) Sak 65,000.00 6,500.00 975.00 1,500.00 1,500.00 75,500.00
21 Semen PC (50 Kg/ZAK) Kg 1,300.00 130.00 19.50 30.00 30.00 1,600.00
22 Sement Warna Kg 25,000.00 2,500.00 375.00 27,900.00
23 Air Liter 500.00 7.50 600.00
24 Besi Beton Polos atau Ulir kg 13,000.00 1,300.00 195.00 1,000.00 500.00 16,000.00
25 C - 75, 0.8 M' 21,750.00 2,175.00 326.25 24,300.00
HARGA PPN PPh 22 PPh 21 ONGKOS ANGKUT ONGKOS PIKUL
No. KEBUTUHAN UPAH/BAHAN SAT HARGA SATUAN
DASAR 10% 1.50% 2.50%
1 2 3 4 5 6 7 8 9 10
26 C - 75, 0.6 M' 18,750.00 1,875.00 281.25 21,000.00
27 Baut Bh 5,000.00 500.00 75.00 5,600.00
28 Dynabolt Bh 7,000.00 700.00 105.00 7,900.00
29 Talang jurai M' 58,000.00 5,800.00 870.00 64,700.00
30 Cat Meni Besi Kg 65,500.00 6,550.00 982.50 73,100.00
31 Cat Kayu Kg 79,000.00 7,900.00 1,185.00 88,100.00
32 Plamir Kg 46,500.00 4,650.00 697.50 51,900.00
33 Politur Liter 70,000.00 7,000.00 1,050.00 78,100.00
34 Menie Kayu Kg 30,000.00 3,000.00 450.00 33,500.00
35 Dumpul Kayu Kg 15,000.00 1,500.00 225.00 16,800.00
36 Dolken Kayu Galam Batang 20,000.00 2,000.00 300.00 22,300.00
37 Kuas Tangan 4 " Bh 22,000.00 2,200.00 330.00 24,600.00
38 Engsel Jendela 3" Pasang 40,000.00 4,000.00 600.00 44,600.00
39 Engsel Pintu 4" Pasang 55,000.00 5,500.00 825.00 61,400.00
40 Engsel Pintu Gembok Pasang 22,500.00 2,250.00 337.50 25,100.00
41 Gerendel Pintu Bh 15,000.00 1,500.00 225.00 16,800.00
42 Gerendel Jendela Bh 12,000.00 1,200.00 180.00 13,400.00
43 Kaca 3 mm M2 197,000.00 19,700.00 2,955.00 219,700.00
44 Kaca 5 mm M2 260,000.00 26,000.00 3,900.00 289,900.00
45 Lis plafon Profil 6 x 6 cm M' 35,000.00 3,500.00 525.00 39,100.00
46 Tripleks 4 mm Lbr 85,000.00 8,500.00 1,275.00 94,800.00
47 Kawat Ikat Kg 25,000.00 2,500.00 375.00 27,900.00
48 Kunci Tanam 2 Slaag Bh 250,000.00 25,000.00 3,750.00 278,800.00
49 Kunci Tanam KM/WC Bh 105,000.00 10,500.00 1,575.00 117,100.00
50 Kunci Teralis Penjara (Gembok Besar ) Bh 175,000.00 17,500.00 2,625.00 195,200.00
51 Kertas Amplas Lbr 6,000.00 600.00 90.00 6,700.00
52 Kait Angin Kls B Bh 33,000.00 3,300.00 495.00 36,800.00
53 Tegel Keramik 40/40 Bh 12,500.00 1,250.00 187.50 14,000.00
54 Tegel Keramik 20 / 25 Bh 3,409.09 340.91 51.14 3,900.00
55 Tegel Keramik 20 / 20 Bh 3,000.00 300.00 45.00 3,400.00
56 Lampu Philips 23 Watt Bh 45,000.00 4,500.00 675.00 50,200.00
57 Lampu Philips 18 Watt Bh 35,000.00 3,500.00 525.00 39,100.00
HARGA PPN PPh 22 PPh 21 ONGKOS ANGKUT ONGKOS PIKUL
No. KEBUTUHAN UPAH/BAHAN SAT HARGA SATUAN
DASAR 10% 1.50% 2.50%
1 2 3 4 5 6 7 8 9 10
58 Besi Strip Kg 5,000.00 500.00 75.00 5,600.00
59 Minyak Bakesting Liter 5,000.00 500.00 75.00 5,600.00
60 Paku / Skrup Genteng Kg 30,000.00 3,000.00 450.00 33,500.00
61 Paku Campuran Kg 22,000.00 2,200.00 330.00 24,600.00
62 Paku Triplek Kg 27,500.00 2,750.00 412.50 30,700.00
63 Play Wood 3 mm uk. 120 x 240 cm Lbr 105,000.00 10,500.00 1,575.00 117,100.00
64 Cat meni Staff 65,500.00 6,550.00 982.50 73,100.00
65 Plamir Btg 120,000.00 12,000.00 1,800.00 133,800.00
66 Kawat Las Kg 45,000.00 4,500.00 675.00 50,200.00
67 Besi Hollow 4 x 4mm x 4 mm M2 600,000.00 60,000.00 9,000.00 669,000.00
68 Besi Hollow 4 x 4mm x 4 mm-M Staff 100,000.00 10,000.00 1,500.00 111,500.00
69 Zink Gelombang BJLS 0.2 Lbr 52,000.00 5,200.00 780.00 58,000.00
70 Seng Licin BJLS 0.2 Lbr 52,000.00 5,200.00 780.00 58,000.00
71 Politur Kg 70,000.00 7,000.00 1,050.00 78,100.00
72 Cat Tembok Kg 265,000.00 26,500.00 3,975.00 295,500.00
73 Cat Dasar Tembok Kg 150,000.00 15,000.00 2,250.00 167,300.00
74 Minyak cat thiner Kg 33,000.00 3,300.00 495.00 36,800.00
75 MCB 60 AMP Bh 210,000.00 21,000.00 3,150.00 234,200.00
76 Kabel NYM 3 x 2.5 mm M 16,000.00 1,600.00 240.00 17,900.00
77 Pipa PVC dia. 3" Staff 250,000.00 25,000.00 3,750.00 278,800.00
75 Perlengkapan Pipa PVC dia. 3" m' 250,000.00 25,000.00 3,750.00 278,800.00
78 Pipa PVC dia. 3" M' 41,700.00 4,170.00 625.50 46,500.00
77 Perlengkapan Pipa PVC dia. 3" m' 41,700.00 4,170.00 625.50 46,500.00
79 Socket PVC dia 1 " Bh 12,500.00 1,250.00 187.50 14,000.00
80 Elbow PVC dia 3 " M' 10,000.00 1,000.00 150.00 11,200.00
81 Tee PVC dia 3" M' 10,000.00 1,000.00 150.00 11,200.00
82 Pipa PVC dia. 1/2" Staff 44,000.00 4,400.00 660.00 49,100.00
80 Perlengkapan Pipa PVC dia. 1/2" m' 44,000.00 4,400.00 660.00 49,100.00
83 PVC dia 1/2 " m' 7,400.00 740.00 111.00 8,300.00
82 Perlengkapan PVC dia 1/2 " m' 7,400.00 740.00 111.00 8,300.00
84 Socket PVC dia 1/2" Bh 4,400.00 440.00 66.00 5,000.00
85 Elbow PVC dia 1/2" M' 5,180.00 518.00 77.70 5,800.00
86 Tee PVC dia 1/2" M' 5,180.00 518.00 77.70 5,800.00
87 Kloset Jongkok Bh 385,000.00 38,500.00 5,775.00 429,275.00
85 Perlengkapan Kloset Jongkok m' 385,000.00 38,500.00 5,775.00 429,300.00
86 Kran Air 3/4 Bh 55,000.00 5,500.00 825.00 61,400.00
87 Kran Air 1/2 Bh 25,000.00 2,500.00 375.00 27,900.00
88 Seal Tape Set 8,000.00 800.00 120.00 9,000.00
89 Floordrain (metal) Set 37,000.00 3,700.00 555.00 41,300.00
90 Wastafel lengkap Bh 544,000.00 54,400.00 8,160.00 606,600.00
91 Paving Block Bh 15,000.00 1,500.00 225.00 16,800.00
92 Sekring Bh 70,000.00 7,000.00 1,050.00 78,100.00
93 Kabel NYY 3x2,5 M' 16,000.00 1,600.00 240.00 17,900.00
94 Benang Roll 5,000.00 500.00 75.00 5,600.00
95 Titik Lampu Titik 75,000.00 7,500.00 1,125.00 83,700.00
96 Lem Kayu Kg 7,500.00 750.00 112.50 8,400.00
97 Pipa PVC Conduit M' 3,750.00 375.00 56.25 4,200.00
98 Lampu TL 20 Watt Bh 78,000.00 7,800.00 1,170.00 87,000.00
99 Lampu pijar philips putih 18 watt Bh 47,500.00 4,750.00 712.50 53,000.00
100 Lampu pijar philips putih 23 watt Bh 60,000.00 6,000.00 900.00 66,900.00
101 Lampu PL 11 Watt Bh 78,000.00 7,800.00 1,170.00 87,000.00
102 Saklar tunggal Bh 18,000.00 1,800.00 270.00 20,100.00
103 Saklar ganda Bh 25,000.00 2,500.00 375.00 27,900.00
104 Stop kontak Bh 23,000.00 2,300.00 345.00 25,700.00
105 Kabel NYY 3 Phase M' 15,000.00 1,500.00 225.00 16,800.00
106 Fiting Tempel Bh 15,000.00 1,500.00 225.00 16,800.00
107 T Dooz Bh 6,500.00 650.00 97.50 7,300.00
108 Isolator Bh 15,000.00 1,500.00 225.00 16,800.00
109 Lasdop Bh 5,000.00 500.00 75.00 5,600.00
110 Mangkok Listrik Bh 50,000.00 5,000.00 750.00 55,800.00
111 L.Bow Bh 2,500.00 250.00 37.50 2,800.00
112 Klem Pipa Bh 1,000.00 100.00 15.00 1,200.00
C ALAT
1 Pakuel Bh 166,031.00 16,603.10 2,490.46 185,200.00
2 Skop Bh 166,031.00 16,603.10 2,490.46 185,200.00
3 Benang Tukang Tukal 20,000.00 2,000.00 300.00 22,300.00
4 Gerobak Dorong Bh 978,920.00 97,892.00 14,683.80 1,091,500.00
5 Martil Bh 134,153.00 13,415.30 2,012.29 149,600.00
6 Selang M' 15,000.00 1,500.00 225.00 16,800.00
7 Ember Cor Bh 20,000.00 2,000.00 300.00 22,300.00
8 Gergaji Bh 219,200.00 21,920.00 3,288.00 244,500.00
D OPERASIONAL DAN BIAYA LAIN-LAIN
1 Papan Nama Proyek Bh 150,000.00 150,000.00
2 Prasasti Bh 500,000.00 500,000.00
3 Insentif Pekerja Ls 650,000.00 650,000.00
4 Administrasi + Dokumentasi Ls 1,000,000.00 1,000,000.00
ALUR BAHAN DAN UPAH

HARGA PPN PPh 22 PPh 21 ONGKOS ANGKUT ONGKOS PIKUL


No. KEBUTUHAN UPAH/BAHAN SAT HARGA SATUAN
DASAR 10% 1.50% 2.50%
1 2 3 4 5 6 7 8 9 10
A UPAH
1 Mandor HOK 195,000.00 5,000.00 - - 200,000.00
2 Kepala Tukang HOK 170,625.00 4,375.00 - - 175,000.00
3 Tukang Batu HOK 146,250.00 3,750.00 - - 150,000.00
4 Tukang Kayu HOK 146,250.00 3,750.00 - - 150,000.00
5 Tukang Besi HOK 146,250.00 3,750.00 - - 150,000.00
6 Tukang Cat HOK 146,250.00 3,750.00 - - 150,000.00
7 Tukang Listrik HOK 146,250.00 3,750.00 - - 150,000.00
8 Tukang Las HOK 146,250.00 3,750.00 - - 150,000.00
9 Pekerja HOK 97,500.00 2,500.00 - - 100,000.00
10 Tukang Las HOK 731,250.00 18,750.00 - - 750,000.00
11 Pekerja HOK 731,250.00 18,750.00 - - 750,000.00

B BAHAN
1 Kayu Klas I M3 7,000,000.00 105,000.00 75,000.00 75,000.00 7,255,000.00
2 Kayu 15 x 15-4M M' 100,800.00 2,362.50 1,687.50 1,687.50 106,600.00
3 Alat Bantu Pancang Set 100,000.00 100,000.00
4 Kayu 15 x 15-750 M M3 100,800.00 2,362.50 1,687.50 1,687.50 106,600.00
5 Kayu 20 x 20-1000 cm M3 280,000.00 4,200.00 3,000.00 3,000.00 290,200.00
6 Kayu Klas II M3 2,800,000.00 42,000.00 75,000.00 2,917,000.00
7 Papan Kayu Kls I M3 7,000,000.00 105,000.00 75,000.00 7,180,000.00
8 Papan Kayu Kls III M3 1,750,000.00 26,250.00 75,000.00 1,851,300.00
9 Batu Kerikil Pecah ( 3 / 2 cm ) M3 235,000.00 3,525.00 75,000.00 313,600.00
9 Pasir Pasang M3 200,000.00 3,000.00 75,000.00 278,000.00
10 Pasir Urug M3 140,000.00 2,100.00 75,000.00 217,100.00
11 Pasir Beton Kg 142.86 2.14 53.57 - 200.00
12 Batu Krikil (Kg) Kg 174.07 2.61 55.56 - 300.00
13 Tanah Timbunan M3 120,000.00 1,800.00 75,000.00 - 196,800.00
14 Batu Karang M3 178,000.00 2,670.00 75,000.00 - 255,700.00
15 Batu Kali M3 178,000.00 2,670.00 75,000.00 - 255,700.00
16 Batu Bata Bh 2,000.00 30.00 200.00 2,300.00
17 Batako Bh 2,500.00 37.50 400.00 3,000.00
18 Beugel Kuda-kuda Bh 12,000.00 180.00 12,200.00
19 Besi Strip Kg 6,500.00 97.50 6,600.00
20 Semen PC (Zak) Sak 65,000.00 6,500.00 975.00 72,500.00
21 Semen PC (50 Kg/ZAK) Kg 1,300.00 130.00 19.50 - - 1,500.00
22 Sement Warna Kg 1,800.00 180.00 27.00 2,100.00
23 Air Liter 500.00 7.50 600.00
24 Besi Beton Polos Atau Ulir kg 13,000.00 1,300.00 195.00 14,500.00
25 Besi Dia 12 mm Standart kg 13,000.00 1,300.00 195.00 14,500.00
26 Besi Dia 10 mm Standart kg 13,000.00 1,300.00 195.00 14,500.00
27 Besi Dia 8 mm Standart kg 13,000.00 1,300.00 195.00 14,500.00
28 C - 75, 0.8 M' 21,750.00 2,175.00 326.25 24,300.00
29 C - 75, 0.6 M' 18,750.00 1,875.00 281.25 21,000.00
30 Baut Bh 5,000.00 500.00 75.00 5,600.00
31 Dynabolt Bh 7,000.00 700.00 105.00 7,900.00
32 Talang jurai M' 58,000.00 5,800.00 870.00 64,700.00
33 Cat Meni Besi Kg 30,000.00 3,000.00 450.00 33,500.00
34 Cat Kayu Kg 57,000.00 5,700.00 855.00 63,600.00
35 Plamir Kg 16,000.00 1,600.00 240.00 17,900.00
36 Politur Liter 25,000.00 2,500.00 375.00 27,900.00
37 Menie Kayu Kg 30,000.00 3,000.00 450.00 33,500.00
38 Dumpul Kayu Kg 15,000.00 1,500.00 225.00 16,800.00
39 Dolken Kayu Galam Batang 20,000.00 2,000.00 300.00 22,300.00
40 Kuas Tangan 4 " Bh 22,000.00 2,200.00 330.00 24,600.00
41 Engsel Jendela 3" Pasang 35,000.00 3,500.00 525.00 39,100.00
42 Engsel Pintu 4" Pasang 55,000.00 5,500.00 825.00 61,400.00
43 Engsel Pintu Gembok Pasang 22,500.00 2,250.00 337.50 25,100.00
44 Gerendel Pintu Bh 15,000.00 1,500.00 225.00 16,800.00
45 Gerendel Jendela Bh 12,000.00 1,200.00 180.00 13,400.00
46 Kaca 3 mm M2 225,000.00 22,500.00 3,375.00 250,900.00
47 Kaca 5 mm M2 95,000.00 9,500.00 1,425.00 106,000.00
48 Lis plafon Profil 6 x 6 cm M' 22,500.00 2,250.00 337.50 25,100.00
49 Tripleks 4 mm Lbr 68,000.00 6,800.00 1,020.00 75,900.00
50 Kawat Ikat Kg 22,500.00 2,250.00 337.50 25,100.00
51 Kunci Tanam 2 Slaag Bh 180,000.00 18,000.00 2,700.00 200,700.00
52 Kunci Tanam KM/WC Bh 105,000.00 10,500.00 1,575.00 117,100.00
53 Kunci Teralis Penjara (Gembok Besar ) Bh 225,000.00 22,500.00 3,375.00 250,900.00
54 Kertas Amplas Lbr 6,000.00 600.00 90.00 6,700.00
55 Kait Angin Kls B Bh 17,500.00 1,750.00 262.50 19,600.00
56 Tegel Keramik 40/40 Bh 12,500.00 1,250.00 187.50 14,000.00
57 Tegel Keramik 20 / 25 Bh 3,409.09 340.91 51.14 3,900.00
58 Tegel Keramik 20 / 20 Bh 3,000.00 300.00 45.00 3,400.00
59 Lampu Philips 23 Watt Bh 45,000.00 4,500.00 675.00 50,200.00
60 Lampu Philips 18 Watt Bh 35,000.00 3,500.00 525.00 39,100.00
61 Besi Strip Kg 5,000.00 500.00 75.00 5,600.00
62 Minyak Bakesting Liter 5,000.00 500.00 75.00 5,600.00
63 Paku / Skrup Genteng Kg 22,500.00 2,250.00 337.50 25,100.00
64 Paku Campuran Kg 19,000.00 1,900.00 285.00 21,200.00
65 Paku Triplek Kg 19,000.00 1,900.00 285.00 21,200.00
65 Play Wood 3 mm uk. 120 x 240 cm Lbr 126,000.00 12,600.00 1,890.00 140,500.00
66 Cat meni Staff 45,000.00 4,500.00 675.00 50,200.00
67 Plamir Btg 120,000.00 12,000.00 1,800.00 133,800.00
68 Kawat Las Kg 5,000.00 500.00 75.00 5,600.00
69 Besi Hollow 4 x 4mm x 4 mm M2 600,000.00 60,000.00 9,000.00 669,000.00
70 Besi Hollow 4 x 4mm x 4 mm-M Staff 100,000.00 10,000.00 1,500.00 111,500.00
71 Zing Gelombang BJLS 0.20 Lbr 47,500.00 4,750.00 712.50 53,000.00
72 Zing Datar BJLS 0.20 Lbr 50,000.00 5,000.00 750.00 55,800.00
72 Politur Kg 10,000.00 1,000.00 150.00 11,200.00
73 Cat Tembok Kg 25,000.00 2,500.00 375.00 27,900.00
74 Cat Dasar Tembok Kg 25,000.00 2,500.00 375.00 27,900.00
75 Gloteks Kg 10,000.00 1,000.00 150.00 11,200.00
76 MCB 60 AMP Bh 210,000.00 21,000.00 3,150.00 234,200.00
77 Kabel NYM 3 x 2.5 mm M 15,000.00 1,500.00 225.00 16,800.00
78 Pipa PVC dia. 3" M' 22,000.00 2,200.00 330.00 24,600.00
79 Pipa PVC dia. 1/2" M' 12,000.00 1,200.00 180.00 13,400.00
80 Socket PVC dia 1 " Bh 5,000.00 500.00 75.00 5,600.00
81 Kloset Duduk Bh 1,500,000.00 150,000.00 22,500.00 1,672,500.00
82 Perlengkapan Kloset Duduk Bh 90,000.00 9,000.00 1,350.00 100,400.00
83 Kran Air 3/4 Bh 35,000.00 3,500.00 525.00 39,100.00
84 Kran Air 1/2 Bh 35,000.00 3,500.00 525.00 39,100.00
85 Seal Tape Set 8,000.00 800.00 120.00 9,000.00
86 Floordrain (metal) Set 37,000.00 3,700.00 555.00 41,300.00
87 Wastafel lengkap Bh 544,000.00 54,400.00 8,160.00 606,600.00
88 Paving Block Segi Empat Bh 4,000.00 400.00 60.00 4,500.00
89 Sekring Bh 70,000.00 7,000.00 1,050.00 78,100.00
90 Kabel NYY 3x2,5 M' 15,000.00 1,500.00 225.00 16,800.00
91 Benang Roll 5,000.00 500.00 75.00 5,600.00
92 Titik Lampu Titik 75,000.00 7,500.00 1,125.00 83,700.00
93 Lem Kayu Kg 7,500.00 750.00 112.50 8,400.00
94 Pipa PVC Conduit M' 3,750.00 375.00 56.25 4,200.00
95 Lampu TL 20 Watt Bh 78,000.00 7,800.00 1,170.00 87,000.00
96 Lampu pijar philips putih 18 watt Bh 47,500.00 4,750.00 712.50 53,000.00
97 Lampu pijar philips putih 23 watt Bh 60,000.00 6,000.00 900.00 66,900.00
98 Lampu PL 11 Watt Bh 78,000.00 7,800.00 1,170.00 87,000.00
99 Saklar tunggal Bh 18,000.00 1,800.00 270.00 20,100.00
100 Saklar ganda Bh 25,000.00 2,500.00 375.00 27,900.00
101 Stop kontak Bh 23,000.00 2,300.00 345.00 25,700.00
102 Kabel NYY 3 Phase M' 15,000.00 1,500.00 225.00 16,800.00
103 Fiting Tempel Bh 15,000.00 1,500.00 225.00 16,800.00
104 T Dooz Bh 6,500.00 650.00 97.50 7,300.00
105 Isolator Bh 15,000.00 1,500.00 225.00 16,800.00
105 Lasdop Bh 5,000.00 500.00 75.00 5,600.00
105 Mangkok Listrik Bh 50,000.00 5,000.00 750.00 55,800.00
105 L.Bow Bh 2,500.00 250.00 37.50 2,800.00
106 Klem Pipa Bh 1,000.00 100.00 15.00 1,200.00
C ALAT
1 Gergaji Bh 90,000.00 9,000.00 1,350.00 100,350.00
2 Martil Bh 85,000.00 8,500.00 1,275.00 94,775.00
3 Mesin Bor Bh 1,000,000.00 100,000.00 15,000.00 1,115,000.00
4 Kunci Pas Bh 25,000.00 2,500.00 375.00 27,875.00
5 Kuas Bh 15,000.00 1,500.00 225.00 16,725.00
6 Sewa Tripot Alat Pancang + Hammer Hari 500,000.00 500,000.00
D OPERASIONAL DAN BIAYA LAIN-LAIN
1 Papan Nama Proyek Bh 150,000.00 150,000.00
2 Prasasti Bh 500,000.00 500,000.00
3 Insentif Pekerja Ls 650,000.00 650,000.00
4 Administrasi + Dokumentasi Ls 1,000,000.00 1,000,000.00
5 Biaya Penyambungan istrik Ls 1,500,000.00 1,500,000.00
6 As Buildrawing Ls 2,500,000.00 2,500,000.00
PERHITUNGAN VOLUME PEKERJAAN
PEKERJAAN : REHAB MASID
LOKASI : ORI
DESA : ORI

No. Lokasi / Lebar Perhitungan Dimensi Luas Volume


Sketsa / Gambar Tinggi Panjang
Urut STA Atas Bawah (M) ( M2 ) ( M3 )

RUMAH Panjang Sumbu Tegak


= 12.1 + 12.1 + 12.1 + 8 + 10.6 + 4.1 +
3 + 1.5 + + + + +
= 63.5 M

Panjang Sumbu Datar


= 21.2 + 21.2 + 5.2 + 2 + 6.8 + 8.3 +
4.5 + 4.5 + +
= 73.7 M

Total Panjang sumbu ( Tegak + Datar )

= 63.5 + 73.7
= 137.2 M

PEKERJAAN TANAH

01. Galian Tanah

Galian Tanah Untuk Pondasi Batu Kali

0.80 0.60 137.2 0.60 x 0.8 0.48 65.86

0.60

0.80
Galian Tanah Untuk Pondasi Telapak

1.5 1.5 1.50 1.50 x 1.5 x 27 bh 60.75 91.13

1.50

1.50
Total Galian Tanah 156.981
02. Urugan Tanah 1/3 Total Urugan Tanah 1/3 52.327

03. Urugan Pasir Bawa Pondasi 0.80 0.05 137.20 0.80 x 0.05 0.04 5.49

0.05
0.80

04. Urugan Pasir Bawa Lantai 12.10 0.05 21.20 12.10 x 0.05 0.61 12.83

0.05
12.1

Urugan Pasir Lantai Teras 2.00 0.05 4.15 2.00 x 0.05 0.10 0.42

0.05

2
Total Urugan Pasir 13.241

05. Urugan Tanah dibawah Lantai

Urugan Tanah di bawa Lantai

0.40 12.10 0.40 21.20 12.10 x 0.40 4.84 102.61

12.1

Urugan Pasir Lantai Teras

0.08 2.00 0.08 8.00 2.00 x 0.08 0.16 1.28

2
Total Urugan Tanah/Sirtu 103.888
PEKERJAAN PASANGAN & BETON

01. Timbrisan Batu Kali


2.00 0.10 137.20 2.00 x 0.10 0.20 27.44
0.10

2.00

02. Pas. Pondasi Batu Kali ad. 1:5


0.30
0.30 0.60 0.80 137.20 ( 0.30 + 0.60 ) 0.80 0.36 49.39
x
2

0.80

0.60

03. Pasangan Batu Bata ad. 1:5


LANTAI I
Sumbu Tegak
Pasangan Dinding 1

12.1 3.5 12.1 x 3.5 42.35

Kosen Ventilasi
3.5 0.27 x 0.7 x 8 1.51
Kosen Pintu Ruangan
0.92 x 2.16 x 0 0.00
Kosen Pintu Kebaya
12.1 1.54 x 2.16 x 0 0.00
Kosen Pintu WC
0.1 0.82 x 2.16 x 0 0.00
Kosen Pintu Hollow 1
2.35 x 2.44 x 0 0.00
Kosen Pintu Hollow 2
1.83 x 2.44 x 0 0.00
Kosen Jendela Hollow 1
2.35 x 1.82 x 0 0.00
Kosen Jendela Hollow 2
1.83 x 1.82 x 0 0.00 0
Kosen Jendela 1
0.7 x 1.52 x 0 0.00
Kosen Jendela 2
1.43 x 1.52 x 4 8.69
Total Pasangan 32.14
Pasangan Dinding 2

12.1 3.5 12.1 x 3.5 42.35

Kosen Ventilasi
3.5 0.27 x 0.7 x 6 1.13
Kosen Pintu Ruangan
0.92 x 2.16 x 1 1.99
Kosen Pintu Kebaya
12.1 1.54 x 2.16 x 1 3.33
Kosen Pintu WC
0.1 0.82 x 2.16 x 0 0.00
Kosen Pintu Hollow 1
2.35 x 2.44 x 0 0.00
Kosen Pintu Hollow 2
1.83 x 2.44 x 0 0.00
Kosen Jendela Hollow 1
2.35 x 1.82 x 0 0.00
Kosen Jendela Hollow 2
1.83 x 1.82 x 0 0.00 0
Kosen Jendela 1
0.7 x 1.52 x 0 0.00
Kosen Jendela 2
1.43 x 1.52 x 3 6.52
Total Pasangan 29.38
Pasangan Dinding 3

12.1 3.5 12.1 x 3.5 42.35

Kosen Ventilasi
3.5 0.27 x 0.7 x 8 1.51
Kosen Pintu Ruangan
0.92 x 2.16 x 0 0.00
Kosen Pintu Kebaya
12.1 1.54 x 2.16 x 1 3.33
Kosen Pintu WC
0.1 0.82 x 2.16 x 0 0.00
Kosen Pintu Hollow 1
2.35 x 2.44 x 0 0.00
Kosen Pintu Hollow 2
1.83 x 2.44 x 0 0.00
Kosen Jendela Hollow 1
2.35 x 1.82 x 0 0.00
Kosen Jendela Hollow 2
1.83 x 1.82 x 0 0.00 0
Kosen Jendela 1
0.7 x 1.52 x 0 0.00
Kosen Jendela 2 + Ventilasi
1.43 x 1.52 x 4 8.69
Total Pasangan 28.82
Pasangan Dinding 4

8.0 3.5 8.0 x 3.5 28.00

Kosen Ventilasi
3.5 0.27 x 0.7 x 0 0.00
Kosen Pintu Ruangan
0.92 x 2.16 x 1 1.99
Kosen Pintu Kebaya
8 1.54 x 2.16 x 0 0.00
Kosen Pintu WC
0.1 0.82 x 2.16 x 0 0.00
Kosen Pintu Hollow 1
2.35 x 2.44 x 0 0.00
Kosen Pintu Hollow 2
1.83 x 2.44 x 0 0.00
Kosen Jendela Hollow 1
2.35 x 1.82 x 0 0.00
Kosen Jendela Hollow 2
1.83 x 1.82 x 0 0.00 0
Kosen Jendela 1
0.7 x 1.52 x 0 0.00
Kosen Jendela 2
1.43 x 1.52 x 0 0.00
Total Pasangan 26.01
Pasangan Dinding 5

10.6 3.5 10.6 x 3.5 37.10

Kosen Ventilasi
3.5 0.27 x 0.7 x 4 0.76
Kosen Pintu Ruangan
0.92 x 2.16 x 0 0.00
Kosen Pintu Kebaya
10.6 1.54 x 2.16 x 0 0.00
Kosen Pintu WC
0.1 0.82 x 2.16 x 0 0.00
Kosen Pintu Hollow 1
2.35 x 2.44 x 0 0.00
Kosen Pintu Hollow 2
1.83 x 2.44 x 0 0.00
Kosen Jendela Hollow 1
2.35 x 1.82 x 0 0.00
Kosen Jendela Hollow 2
1.83 x 1.82 x 0 0.00 0
Kosen Jendela 1
0.7 x 1.52 x 0 0.00
Kosen Jendela 2
1.43 x 1.52 x 0 0.00
Total Pasangan 36.34
Pasangan Dinding 6

4.1 3.5 4.1 x 3.5 14.35

Kosen Ventilasi
3.5 0.27 x 0.7 x 0 0.00
Kosen Pintu Ruangan
0.92 x 2.16 x 0 0.00
Kosen Pintu Kebaya
4.1 1.54 x 2.16 x 0 0.00
Kosen Pintu WC
0.1 0.82 x 2.16 x 1 1.77
Kosen Pintu Hollow 1
2.35 x 2.44 x 0 0.00
Kosen Pintu Hollow 2
1.83 x 2.44 x 0 0.00
Kosen Jendela Hollow 1
2.35 x 1.82 x 0 0.00
Kosen Jendela Hollow 2
1.83 x 1.82 x 0 0.00 0
Kosen Jendela 1
0.7 x 1.52 x 0 0.00
Kosen Jendela 2
1.43 x 1.52 x 0 0.00
Total Pasangan 12.58
Pasangan Dinding 7

3.0 3.5 3.0 x 3.5 10.50

Kosen Ventilasi
3.5 0.27 x 0.7 x 1 0.19
Kosen Pintu Ruangan
0.92 x 2.16 x 0 0.00
Kosen Pintu Kebaya
3 1.54 x 2.16 x 0 0.00
Kosen Pintu WC
0.1 0.82 x 2.16 x 0 0.00
Kosen Pintu Hollow 1
2.35 x 2.44 x 0 0.00
Kosen Pintu Hollow 2
1.83 x 2.44 x 0 0.00
Kosen Jendela Hollow 1
2.35 x 1.82 x 0 0.00
Kosen Jendela Hollow 2
1.83 x 1.82 x 0 0.00 0
Kosen Jendela 1
0.7 x 1.52 x 0 0.00
Kosen Jendela 2
1.43 x 1.52 x 0 0.00
Total Pasangan 10.31
Pasangan Dinding 8

1.5 3.5 1.5 x 3.5 5.25

Kosen Ventilasi
3.5 0.27 x 0.7 x 0 0.00
Kosen Pintu Ruangan
0.92 x 2.16 x 0 0.00
Kosen Pintu Kebaya
1.5 1.54 x 2.16 x 0 0.00
Kosen Pintu WC
0.1 0.82 x 2.16 x 1 1.77
Kosen Pintu Hollow 1
2.35 x 2.44 x 0 0.00
Kosen Pintu Hollow 2
1.83 x 2.44 x 0 0.00
Kosen Jendela Hollow 1
2.35 x 1.82 x 0 0.00
Kosen Jendela Hollow 2
1.83 x 1.82 x 0 0.00 0
Kosen Jendela 1
0.7 x 1.52 x 0 0.00
Kosen Jendela 2
1.43 x 1.52 x 0 0.00
Total Pasangan 3.48

Sumbu Datar
Pasangan Dinding 1

18.2 3.5 18.2 x 3.5 63.70

Kosen Ventilasi
3.5 0.27 x 0.7 x 10 1.89
Kosen Pintu Ruangan
0.92 x 2.16 x 0 0.00
Kosen Pintu Kebaya
18.2 1.54 x 2.16 x 0 0.00
Kosen Pintu WC
0.1 0.82 x 2.16 x 0 0.00
Kosen Pintu Hollow 1
2.35 x 2.44 x 0 0.00
Kosen Pintu Hollow 2
1.83 x 2.44 x 1 4.47
Kosen Jendela Hollow 1
2.35 x 1.82 x 0 0.00
Kosen Jendela Hollow 2
1.83 x 1.82 x 0 0.00 0
Kosen Jendela 1
0.7 x 1.52 x 0 0.00
Kosen Jendela 2
1.43 x 1.52 x 4 8.69
Total Pasangan 48.65
Pasangan Dinding 2

21.2 3.5 21.2 x 3.5 74.20

Kosen Ventilasi
3.5 0.27 x 0.7 x 10 1.89
Kosen Pintu Ruangan
0.92 x 2.16 x 0 0.00
Kosen Pintu Kebaya
21.2 1.54 x 2.16 x 1 3.33
Kosen Pintu WC
0.1 0.82 x 2.16 x 0 0.00
Kosen Pintu Hollow 1
2.35 x 2.44 x 1 5.73
Kosen Pintu Hollow 2
1.83 x 2.44 x 0 0.00
Kosen Jendela Hollow 1
2.35 x 1.82 x 0 0.00
Kosen Jendela Hollow 2
1.83 x 1.82 x 0 0.00 0
Kosen Jendela 1
0.7 x 1.52 x 8 8.51
Kosen Jendela 2
1.43 x 1.52 x 0 0.00
Total Pasangan 54.74
Pasangan Dinding 3

5.2 3.5 5.2 x 3.5 18.20

Kosen Ventilasi
3.5 0.27 x 0.7 x 0 0.00
Kosen Pintu Ruangan
0.92 x 2.16 x 0 0.00
Kosen Pintu Kebaya
5.2 1.54 x 2.16 x 0 0.00
Kosen Pintu WC
0.1 0.82 x 2.16 x 0 0.00
Kosen Pintu Hollow 1
2.35 x 2.44 x 0 0.00
Kosen Pintu Hollow 2
1.83 x 2.44 x 0 0.00
Kosen Jendela Hollow 1
2.35 x 1.82 x 0 0.00
Kosen Jendela Hollow 2
1.83 x 1.82 x 0 0.00 0
Kosen Jendela 1
0.7 x 1.52 x 0 0.00
Kosen Jendela 2
1.43 x 1.52 x 0 0.00
Total Pasangan 18.20
Pasangan Dinding 4

2.0 3.5 2.0 x 3.5 7.00

Kosen Ventilasi
3.5 0.27 x 0.7 x 0 0.00
Kosen Pintu Ruangan
0.92 x 2.16 x 0 0.00
Kosen Pintu Kebaya
2 1.54 x 2.16 x 0 0.00
Kosen Pintu WC
0.1 0.82 x 2.16 x 0 0.00
Kosen Pintu Hollow 1
2.35 x 2.44 x 0 0.00
Kosen Pintu Hollow 2
1.83 x 2.44 x 0 0.00
Kosen Jendela Hollow 1
2.35 x 1.82 x 0 0.00
Kosen Jendela Hollow 2
1.83 x 1.82 x 0 0.00 0
Kosen Jendela 1
0.7 x 1.52 x 0 0.00
Kosen Jendela 2
1.43 x 1.52 x 0 0.00
Total Pasangan 7.00
Pasangan Dinding 5

6.8 3.5 6.8 x 3.5 23.80

Kosen Ventilasi
3.5 0.27 x 0.7 x 0 0.00
Kosen Pintu Ruangan
0.92 x 2.16 x 1 1.99
Kosen Pintu Kebaya
6.8 1.54 x 2.16 x 0 0.00
Kosen Pintu WC
0.1 0.82 x 2.16 x 0 0.00
Kosen Pintu Hollow 1
2.35 x 2.44 x 0 0.00
Kosen Pintu Hollow 2
1.83 x 2.44 x 0 0.00
Kosen Jendela Hollow 1
2.35 x 1.82 x 0 0.00
Kosen Jendela Hollow 2
1.83 x 1.82 x 0 0.00 0
Kosen Jendela 1
0.7 x 1.52 x 0 0.00
Kosen Jendela 2
1.43 x 1.52 x 0 0.00
Total Pasangan 21.81
Pasangan Dinding 6

3.0 3.5 3.0 x 3.5 10.50

Kosen Ventilasi
3.5 0.27 x 0.7 x 0 0.00
Kosen Pintu Ruangan
0.92 x 2.16 x 1 1.99
Kosen Pintu Kebaya
3 1.54 x 2.16 x 0 0.00
Kosen Pintu WC
0.1 0.82 x 2.16 x 0 0.00
Kosen Pintu Hollow 1
2.35 x 2.44 x 0 0.00
Kosen Pintu Hollow 2
1.83 x 2.44 x 0 0.00
Kosen Jendela Hollow 1
2.35 x 1.82 x 0 0.00
Kosen Jendela Hollow 2
1.83 x 1.82 x 0 0.00 0
Kosen Jendela 1
0.7 x 1.52 x 0 0.00
Kosen Jendela 2
1.43 x 1.52 x 0 0.00
Total Pasangan 8.51
Pasangan Dinding 7

1.5 3.5 1.5 x 3.5 5.25

Kosen Ventilasi
3.5 0.27 x 0.7 x 0 0.00
Kosen Pintu Ruangan
0.92 x 2.16 x 0 0.00
Kosen Pintu Kebaya
1.5 1.54 x 2.16 x 0 0.00
Kosen Pintu WC
0.1 0.82 x 2.16 x 0 0.00
Kosen Pintu Hollow 1
2.35 x 2.44 x 0 0.00
Kosen Pintu Hollow 2
1.83 x 2.44 x 0 0.00
Kosen Jendela Hollow 1
2.35 x 1.82 x 0 0.00
Kosen Jendela Hollow 2
1.83 x 1.82 x 0 0.00 0
Kosen Jendela 1
0.7 x 1.52 x 0 0.00
Kosen Jendela 2
1.43 x 1.52 x 0 0.00
Total Pasangan 5.25
Pasangan Dinding 8

4.5 3.5 4.5 x 3.5 15.75

Kosen Ventilasi
3.5 0.27 x 0.7 x 0 0.00
Kosen Pintu Ruangan
0.92 x 2.16 x 0 0.00
Kosen Pintu Kebaya
4.5 1.54 x 2.16 x 0 0.00
Kosen Pintu WC
0.1 0.82 x 2.16 x 1 1.77
Kosen Pintu Hollow 1
2.35 x 2.44 x 0 0.00
Kosen Pintu Hollow 2
1.83 x 2.44 x 0 0.00
Kosen Jendela Hollow 1
2.35 x 1.82 x 0 0.00
Kosen Jendela Hollow 2
1.83 x 1.82 x 0 0.00 0
Kosen Jendela 1
0.7 x 1.52 x 0 0.00
Kosen Jendela 2
1.43 x 1.52 x 0 0.00
Total Pasangan 13.98
Total Pasangan Batako Lantai I 357.21
04. Beton Bertulang

Pondasi Telapak

8O 12
0.30 0.30 0.30 1.50 0.30 x 0.30 0.09 0.14
` 10 - 15 1.00 1.00 0.25 1.00 x 1.00 1.00 0.25
Jumlah Tiang 27 29.43 10.40
Total Beton Kolom 10.395
0.30 Bekesting' 1.80 48.60

Beton Bertulang Utk Kolom 30/30

8O 12
0.30 0.30 0.30 3.50 0.30 x 0.30 0.09 0.32
` 10 - 15
Jumlah Tiang 27 2.43 8.51

0.30 Total Beton Kolom 8.505


Bekesting' 4.20 113.40
Beton Bertulang Utk Kolom 15/15

8O 12
0.15 0.15 0.15 3.00 0.15 x 0.15 0.02 0.07
` 10 - 15
Jumlah Tiang 4 0.09 0.27

0.15 Total Beton Kolom 0.270


Bekesting' 1.80 7.20

Sloof 20/30

4O 12
0.20 0.30 137.20 0.20 x 0.30 0.06 8.232
0.30 O 8 - 20
Total Beton Balok 8.232
Bekesting' 109.76 109.76
0.20
Balok 20/35

4O 12
0.20 0.35 164.05 0.20 x 0.35 0.07 11.4835
0.35 O 8 - 20
Total Beton Balok 11.483
Bekesting' 147.64 147.64
0.20

Balok 15/25

4O 12
0.15 0.20 12.10 0.15 x 0.20 0.03 0.363
0.20 O 8 - 20
Total Beton Balok 0.363
Bekesting' 6.66 6.66
0.15

Anak Tangga

5O 12
0.25 0.30 0.25 1.28 0.50 x 0.30 x 0.25 x 14 bh 0.53 0.67
O 8 - 10

0.30 `

Plat Balok Bordes

0.1 1.18 0.10 2.56 1.18 x 0.12 0.14 0.36

1.18
Plat Tangga Bekesting 3.53 3.53

0.1 5.00 0.10 1.18 5.00 x 0.12 0.60 0.71

5
Bekesting 6.14 6.14
Total Beton 1.74
Total Bekesting 9.67
Plat Lantai
21.20 0.12 12.10 21.20 x 0.12 2.54 30.78
0.12
Total Beton Balok 30.782
21.2 Bekesting' 259.42 259.42
05. RABAT BETON TUMBUK

Rabat Lantai Ruangan

0.05 12.10 0.05 21.20 12.10 x 0.05 0.61 12.83

12.10

Rabat LantaiTeras

0.05 2.00 0.05 4.00 2.00 x 0.05 0.10 0.40

2.00

Rangka Plafon Dan Plafond


Ruang 1
12.1 x 21.2 = 256.52

21.2
12.1 0

0
PINTU DAN JENDELA
1 VENTILASI 1
Kusen Kayu 6 / 12

6 15 6
Ventilasi Type V1 Jumlah = 4

21
27
3.31 0.060 x 0.12 x 3.31 0.02 0.024
Jumlah 4 Bh 0.10 0.10

143
6 62 6 62 6
68 68

58 48 8 48
48 48 85

2 VENTILASI 2
Kusen Kayu 6 / 12
Ventilasi Type V1 Jumlah = 2

6 15 6

21
27
1.7 0.060 x 0.12 x 1.70 0.01 0.012
Jumlah 2 Bh 0.02 0.02

70
64

6 58 6

3 Pintu Kebaya (P1)


Kusen Kayu 6 / 12
Ventilasi Type V1 Jumlah = 2

6 15 6
3.53 0.060 x 0.12 x 3.53 0.03 0.025

6 15 27
Jumlah 2 Bh 0.05 0.05

5
Kusen Kayu 6 / 12
Pintu Type V1 Jumlah = 2
5.54 0.060 x 0.12 x 5.54 0.04 0.040
Jumlah 2 Bh 0.08 0.08
200

216
211

Daun Pintu Jumlah = 2


1.46 2.11 1.46 x 2.11 3.08
Total Pintu 2 6.16
10

20

154
5 13 47 13 13 47 13 5 Pot. A

6 143 6
4 Pintu P2

6
Kusen Kayu 6 / 12
Pintu Type V1 Jumlah = 6
4.92 0.060 x 0.12 x 4.92 0.04 0.035

200
Jumlah 6 Bh 0.21 0.21

211
Daun Pintu Jumlah = 6
0.82 2.11 0.82 x 2.11 1.73
Total Pintu 6 10.38

20 10
92
5 13 56 13 5
Pot. A

6 80 6

5 Pintu P3

6
5
Kusen Kayu 6 / 12
Pintu Type V1 Jumlah = 3
4.8 0.060 x 0.12 x 4.80 0.03 0.035
Jumlah 3 Bh 0.10 0.10
200
211

Daun Pintu Jumlah = 3


0.7 2.11 0.70 x 2.11 1.48
Total Pintu 3 4.43
20 10

80
5 13 44 13 5 Pot. A

6 68 6
6 JENDELA J1
Kusen Kayu 6 / 12

6 15 6
Ventilasi Type V1 Jumlah = 2

21
15 27
1.7 0.060 x 0.12 x 1.70 0.01 0.012
Jumlah 2 Bh 0.02 0.02

85
6
Kusen Kayu 6 / 12
Pintu Type V1 Jumlah = 2
4.2 0.060 x 0.12 x 4.20 0.03 0.030
Jumlah 2 Bh 0.06 0.06

152
140

126

142

152
Daun Pintu Jumlah = 2
0.6 1.42 0.60 x 1.42 x 1.00 Bh 0.85
Total Pintu 2 1.70

58
6
Pot. A
70
6 58 6
64

105 8 44 8 510

7 JENDELA J2
Kusen Kayu 6 / 12

6 15 6
Ventilasi Type V1 Jumlah = 2

21
27
3.31 0.060 x 0.12 x 3.31 0.02 0.024
Jumlah 2 Bh 0.05 0.05

85
6 Kusen Kayu 6 / 12
Pintu Type V1 Jumlah = 2
7.06 0.060 x 0.12 x 7.06 0.05 0.051
140

126

142

152
Jumlah 2 Bh 0.10 0.10

Daun Pintu Jumlah = 2


0.64 1.42 0.64 x 1.42 x 2.00 Bh 1.82
58

Total Pintu 2 3.64


6

Pot. A

143
6 62 6 62 6
68 68

58 48 8 48
48 48 85
6 JENDELA TERALIS HOLLOW JH2

5 225 5
5 173 5

5
172

182

172

182
TERALIS HOLLOW = 0
1.82 1.83 1.82 x 1.83 x 1.00 Bh 3.33
Total Pintu 0 0.00

5
183 235

7 JENDELA TERALIS HOLLOW JH1

5 225 5
173 5
5
182

172

182
TERALIS HOLLOW = 0
1.82 2.35 1.82 x 2.35 x 1.00 Bh 4.28
Total Pintu 0 0.00
5

183 235
5
183 235
6 PINTU TERALIS HOLLOW PH2

5 86 86 5 5 113 113 5

5
TERALIS HOLLOW = 1

234

244

234

244
2.44 1.83 2.44 x 1.83 x 1.00 Bh 4.47
Total Pintu 1 4.47

5
91 91 235
183

7 PINTU TERALIS HOLLOW PH1

5 86 86 5 5 113 113 5
5

TERALIS HOLLOW = 1
244

234

244
2.44 2.35 2.44 x 2.35 x 1.00 Bh 5.73
Total Pintu 1 5.73
5

91 91 235
183
PERHITUNGAN VOLUME PEKERJAAN
PEKERJAAN : REHAB MASID
LOKASI : ORI
DESA : ORI

Pembesiaan Panjang Jumlah Total Berat Berat Total


No. Lokasi / JarakPanjang Bangunan Total
Sketsa / Gambar Bengkokan Panjang Total Total Stap Jmlh Volume Per Staff Per Staff Volume
Urut STA
Atas Bawah Besi Panjang Besi Lebar Panjang Batang (M) ( Staf ) (Kg) (Kg) ( Kg)

01 Pembesian Kolom 15/15

0.03 0.03 0.03 0.03 3.50 3.56 8.00 28.48 2.6 4.00 10 10.66 110.36 110.36
3.50

4 O 12 0.03 0.03 0.28 0.34 0.15 3.32 22 7.525 0.7 4.00 3 4.74 12.97 12.97
0.07 O 8 - 10 123.33

0.07

01 Pembesian Kolom 30/30

0.03 0.03 0.03 0.03 3.50 3.56 8.00 28.48 2.6 27.00 70 10.66 744.91 744.91
3.50

4 O 12 0.03 0.03 0.88 0.94 0.15 3.32 22 20.805 1.9 27.00 51 4.74 242.06 242.06
0.22 O 8 - 10 986.97

0.22

Pembesian Sloof 20/30


0.03 0.03 0.03 0.03 137.20 137.26 6.00 823.56 74.9 1.00 75 10.66 797.81 797.81
137.20

5 O 16 0.03 0.03 0.58 0.64 0.15 137.2 915 585.387 53.2 1.00 53 4.74 252.25 252.25
0.07 1,050.05
O 8 - 15

0.22
Pembesian Balok 20/35

0.03 0.03 0.03 0.03 164.05 164.11 4.00 656.44 59.7 1.00 60 10.66 635.91 635.91
164.05
01

4 O 12 0.03 0.03 0.78 0.84 0.15 164.05 1,094 918.680 83.5 1.00 84 4.74 395.87 395.87
0.27 1,031.78
O 8 - 15

0.12

Pembesian Balok Anak 15/25

0.03 0.03 0.03 0.03 12.10 12.16 4.00 48.64 4.4 1.00 4 10.66 47.12 47.12
12.10
01

4 O 12 0.03 0.03 0.48 0.54 0.15 12.10 81 43.560 4.0 1.00 4 4.74 18.77 18.77
0.17 65.89
O 8 - 15

0.07

Plat Lantai

0.03 0.03 0.03 0.03 12.10 12.16 0.2 21.2 106 1288.96 117 2.00 234 7.40 1,735.17 1,735.17
12.10

0.03 0.03 0.03 0.03 21.20 21.26 0.2 12.10 60 1286.23 117 2.00 234 7.40 1,731.50 1,731.50
21.20 3,466.67

Pembesian Pondasi Telapak 100 x 100

0.03 0.03 0.03 0.03 1.00 1.06 8 8.48 1 27.00 21 10.66 221.80 221.80
1

4 O 16 0.03 0.03 1.08 1.14 0.15 1.00 7 7.60 1 27.00 19 4.74 88.42 88.42
0.27 O 10 - 15

0.27

Plat Pondasi Tapak

0.03 0.03 0.03 0.03 1.50 1.56 0.15 1.50 10 15.60 1 27 38 7.40 283.51 283.51
1.50

0.03 0.03 0.03 0.03 1.50 1.56 0.15 1.50 10 15.60 1 27 38 7.40 283.51 283.51
1.50 877.23

AnakTangga

0.03 0.03 0.03 0.03 1.18 1.24 5 6.20 1 13 7 10.66 78.08 78.08
1.18

5 O 16 0.03 0.03 0.71 0.77 0.15 1.18 8 6.06 1 13 7 4.74 33.93 33.93
0.22
O 8 - 15

0.27

Balok Bordes

0.03 0.03 0.03 0.03 1.18 1.24 0.1 2.56 26 31.74 3 2 6 7.40 42.73 42.73
1.18
0.03 0.03 0.03 0.03 2.56 2.62 0.1 1.18 12 30.92 3 2 6 7.40 41.62 41.62
2.56

Plat Tangga

0.03 0.03 0.03 0.03 1.18 1.24 0.1 5.00 50 62.00 6 2 11 7.40 83.46 83.46
1.18

0.03 0.03 0.03 0.03 5.00 5.06 0.1 1.18 12 59.71 5 2 11 7.40 80.38 80.38
5.00
360.20
PERHITUNGAN VOLUME

PEKERJAAN : REHAB MASID


LOKASI : ORI
DESA : ORI

No. URAIAN PEKERJAAN SATUAN VOLUME

I. PEKERJAAN PENGGANTUNG, PENGUNCI & KACA

01. Kunci tanam 2x mengunci BH 2.00


02. Kunci BH 3.00
03. Engsel pintu nilon kuningan 4" PSG 7.00
04. Engsel jendela, ventilasi nilon kuningan 3" PSG 15.00
05. Grendel jendela, ventilasi kuningan kodok BH 15.00
06. Kait angin PSG 30.00
07. Baut, mur, beugel, angker dll. BH 25.00

II. PEKERJAAN INSTALASI LISTRIK

01. Titik cahaya lampu dan stop kontak TTK 14.00


02. Lampu hias ruang tamu BH 0.00
03. Lampu hias ruang keluarga BH 0.00
04. Lampu Philips SL 13 Watt BH 6.00
05. Lampu Philips TL 18 Watt BH 8.00
06. AC 1/2 PK merk mitsubishi komplit Unit 0.00
07. Stop kontak merk Broco BH 2.00
08. Saklar tunggal merk Broco BH 2.00
09. Saklar ganda merk Broco BH 4.00
10. Panel MCB 2 group Unit 1.00

III. PEKERJAAN INSTALASI AIR

01. Titik air bersih/ Instalasi air TTK 3.00


02. Kloset duduk poselin tipe concord BH 0.00
02. Kloset jongkok poselin tipe concord BH 2.00
03. Kran air vernekel BH 3.00
04. Kran air leher angsa BH 0.00
05. Wastafel porselin BH 1.00
06. Tempat cuci alluminium 2 bak BH 0.00
07. Floor dryn stanless steel BH 0.00
08. Saluran pembuangan kotoran, pipa PVC dia. 4" Staf 3.00
09. Saluran air kotor pipa PVC dia. 2" Staf 3.00

IV. PEKERJAAN PENGECATAN

01. Cat kayu dengan cat glotex M2 #REF!


02. Menie teakoil M2 #REF!
03. Cat plafon tripleks dengan Metrolite M2 #REF!
04. Cat dinding luar dan dalam dengan Metrolite M2 #REF!
05. Acian & Plamir dinding M2 #REF!
PERHITUNGAN VOLUME PEKERJAAN
PEKERJAAN : REHAB MASID
LOKASI : ORI
DESA : ORI

No. Lokasi / Lebar Perhitungan Dimensi Luas Volume


Sketsa / Gambar Tinggi Panjang
Urut STA Atas Bawah (M) ( M2 ) ( M3 )

RUMAH Panjang Sumbu Tegak


= 12.1 + 12.1 + 12.1 + 8 + 4.1 + 4.1 +
2.8 + 1.5 + 10.6 + + + +
= 67.4 M

Panjang Sumbu Datar


= 21.2 + 21.2 + 5.2 + 5.2 + 1.5 + 4 +
4 + 4.5 + 3 + 3 +
= 72.8 M

Total Panjang sumbu ( Tegak + Datar )

= 67.4 + 72.8
= 140.2 M

PEKERJAAN TANAH

01. Galian Tanah

Galian Tanah Untuk Pondasi Batu Kali

0.80 0.60 140.2 0.60 x 0.8 0.48 67.30

0.60

0.80
Galian Tanah Untuk Pondasi Telapak

1.5 1.5 1.50 1.50 x 1.5 x 27 bh 60.75 91.13

1.50

1.50
Total Galian Tanah 158.421

02. Urugan Tanah 1/3 Total Urugan Tanah 1/3 52.807

03. Urugan Pasir Bawa Pondasi 0.80 0.05 140.20 0.80 x 0.05 0.04 5.61

0.05
0.80
04. Urugan Pasir Bawa Lantai 12.10 0.05 21.20 12.10 x 0.05 0.605 12.83

0.05
12.1

Urugan Pasir Lantai Teras 0.00 0.05 4.15 0.00 x 0.05 0 -

0.05

0
Total Urugan Pasir 12.826

05. Urugan Tanah dibawah Lantai

Urugan Tanah di bawa Lantai

0.40 12.10 0.40 21.20 12.10 x 0.40 4.84 102.61

12.1

Urugan Pasir Lantai Teras

0.08 0.00 0.08 8.00 0.00 x 0.08 0 -

0
Total Urugan Tanah/Sirtu 102.608
PEKERJAAN PASANGAN & BETON

01. Timbrisan Batu Kali


0.00 0.10 140.20 0.00 x 0.10 0 -
0.10

0.00

02. Pas. Pondasi Batu Kali ad. 1:5


0.30
0.30 0.60 0.80 140.20 ( 0.30 + 0.60 ) 0.80 0.36 50.47
x
2

0.80

0.60

03. Pasangan Batu Bata ad. 1:5


LANTAI I
Sumbu Tegak
Pasangan Dinding 1

12.1 3.5 12.1 x 3.5 42.35

Kosen Ventilasi
3.5 0.27 x 0.7 x 8 1.51
Kosen Pintu Ruangan
0.92 x 2.16 x 0 0.00
Kosen Pintu Kebaya
12.1 1.54 x 2.16 x 0 0.00
Kosen Pintu WC
0.1 0.82 x 2.16 x 0 0.00
Kosen Pintu Hollow 1
2.35 x 2.44 x 0 0.00
Kosen Pintu Hollow 2
1.83 x 2.44 x 0 0.00
Kosen Jendela Hollow 1
2.35 x 1.82 x 0 0.00
Kosen Jendela Hollow 2
1.83 x 1.82 x 0 0.00 0
Kosen Jendela 1
0.7 x 1.52 x 0 0.00
Kosen Jendela 2
1.43 x 1.52 x 4 8.69
Total Pasangan 32.14
Pasangan Dinding 2

12.1 3.5 12.1 x 3.5 42.35

Kosen Ventilasi
3.5 0.27 x 0.7 x 6 1.13
Kosen Pintu Ruangan
0.92 x 2.16 x 0 0.00
Kosen Pintu Kebaya
12.1 1.54 x 2.16 x 1 3.33
Kosen Pintu WC
0.1 0.82 x 2.16 x 0 0.00
Kosen Pintu Hollow 1
2.35 x 2.44 x 0 0.00
Kosen Pintu Hollow 2
1.83 x 2.44 x 0 0.00
Kosen Jendela Hollow 1
2.35 x 1.82 x 0 0.00
Kosen Jendela Hollow 2
1.83 x 1.82 x 0 0.00 0
Kosen Jendela 1
0.7 x 1.52 x 0 0.00
Kosen Jendela 2
1.43 x 1.52 x 3 6.52
Total Pasangan 31.37
Pasangan Dinding 3

12.1 3.5 12.1 x 3.5 42.35

Kosen Ventilasi
3.5 0.30 x 0.7 x 0 0.00
Kosen Pintu Ruangan
0.92 x 2.16 x 3 5.96
Kosen Pintu Kebaya
12.1 1.54 x 2.16 x 0 0.00
Kosen Pintu WC
0.1 0.82 x 2.16 x 0 0.00
Kosen Pintu Hollow 1
2.35 x 2.44 x 0 0.00
Kosen Pintu Hollow 2
1.83 x 2.44 x 0 0.00
Kosen Jendela Hollow 1
2.35 x 1.82 x 0 0.00
Kosen Jendela Hollow 2
1.83 x 1.82 x 0 0.00 0
Kosen Jendela 1
0.7 x 1.52 x 0 0.00
Kosen Jendela 2
1.43 x 1.52 x 0 0.00
Total Pasangan 36.39
Pasangan Dinding 4

8.0 3.5 8.0 x 3.5 28.00

Kosen Ventilasi
3.5 0.30 x 0.7 x 6 1.26
Kosen Pintu Ruangan
0.92 x 2.16 x 2 3.97
Kosen Pintu Kebaya
8 1.54 x 2.16 x 0 0.00
Kosen Pintu WC
0.1 0.82 x 2.16 x 0 0.00
Kosen Pintu Hollow 1
2.35 x 2.44 x 0 0.00
Kosen Pintu Hollow 2
1.83 x 2.44 x 0 0.00
Kosen Jendela Hollow 1
2.35 x 1.82 x 0 0.00
Kosen Jendela Hollow 2
1.83 x 1.82 x 0 0.00 0
Kosen Jendela 1
0.7 x 1.52 x 0 0.00
Kosen Jendela 2
1.43 x 1.52 x 2 4.35
Total Pasangan 18.42
Pasangan Dinding 5

10.6 3.5 10.6 x 3.5 37.10

Kosen Ventilasi
3.5 0.30 x 0.7 x 4 0.84
Kosen Pintu Ruangan
0.92 x 2.16 x 0 0.00
Kosen Pintu Kebaya
10.6 1.54 x 2.16 x 0 0.00
Kosen Pintu WC
0.1 0.82 x 2.16 x 0 0.00
Kosen Pintu Hollow 1
2.35 x 2.44 x 0 0.00
Kosen Pintu Hollow 2
1.83 x 2.44 x 0 0.00
Kosen Jendela Hollow 1
2.35 x 1.82 x 0 0.00
Kosen Jendela Hollow 2
1.83 x 1.82 x 0 0.00 0
Kosen Jendela 1
0.7 x 1.52 x 0 0.00
Kosen Jendela 2
1.43 x 1.52 x 1 2.17
Total Pasangan 34.09
Pasangan Dinding 6

4.1 3.5 4.1 x 3.5 14.35

Kosen Ventilasi
3.5 0.30 x 0.7 x 0 0.00
Kosen Pintu Ruangan
0.92 x 2.16 x 1 1.99
Kosen Pintu Kebaya
4.1 1.54 x 2.16 x 0 0.00
Kosen Pintu WC
0.1 0.82 x 2.16 x 0 0.00
Kosen Pintu Hollow 1
2.35 x 2.44 x 0 0.00
Kosen Pintu Hollow 2
1.83 x 2.44 x 0 0.00
Kosen Jendela Hollow 1
2.35 x 1.82 x 0 0.00
Kosen Jendela Hollow 2
1.83 x 1.82 x 0 0.00 0
Kosen Jendela 1
0.7 x 1.52 x 0 0.00
Kosen Jendela 2
1.43 x 1.52 x 0 0.00
Total Pasangan 12.36
Pasangan Dinding 7

4.1 3.5 4.1 x 3.5 14.35

Kosen Ventilasi
3.5 0.30 x 0.7 x 0 0.00
Kosen Pintu Ruangan
0.92 x 2.16 x 0 0.00
Kosen Pintu Kebaya
4.1 1.54 x 2.16 x 0 0.00
Kosen Pintu WC
0.1 0.82 x 2.16 x 2 3.54
Kosen Pintu Hollow 1
2.35 x 2.44 x 0 0.00
Kosen Pintu Hollow 2
1.83 x 2.44 x 0 0.00
Kosen Jendela Hollow 1
2.35 x 1.82 x 0 0.00
Kosen Jendela Hollow 2
1.83 x 1.82 x 0 0.00 0
Kosen Jendela 1
0.7 x 1.52 x 0 0.00
Kosen Jendela 2
1.43 x 1.52 x 0 0.00
Total Pasangan 10.81
Pasangan Dinding 8

1.5 3.5 1.5 x 3.5 5.25

Kosen Ventilasi
3.5 0.30 x 0.7 x 0 0.00
Kosen Pintu Ruangan
0.92 x 2.16 x 0 0.00
Kosen Pintu Kebaya
1.5 1.54 x 2.16 x 0 0.00
Kosen Pintu WC
0.1 0.82 x 2.16 x 0 0.00
Kosen Pintu Hollow 1
2.35 x 2.44 x 0 0.00
Kosen Pintu Hollow 2
1.83 x 2.44 x 0 0.00
Kosen Jendela Hollow 1
2.35 x 1.82 x 0 0.00
Kosen Jendela Hollow 2
1.83 x 1.82 x 0 0.00 0
Kosen Jendela 1
0.7 x 1.52 x 0 0.00
Kosen Jendela 2
1.43 x 1.52 x 0 0.00
Total Pasangan 5.25
Pasangan Dinding 9

2.8 3.5 2.8 x 3.5 9.80

Kosen Ventilasi
3.5 0.30 x 0.7 x 0 0.00
Kosen Pintu Ruangan
0.92 x 2.16 x 0 0.00
Kosen Pintu Kebaya
2.8 1.54 x 2.16 x 0 0.00
Kosen Pintu WC
0.1 0.82 x 2.16 x 0 0.00
Kosen Pintu Hollow 1
2.35 x 2.44 x 0 0.00
Kosen Pintu Hollow 2
1.83 x 2.44 x 0 0.00
Kosen Jendela Hollow 1
2.35 x 1.82 x 0 0.00
Kosen Jendela Hollow 2
1.83 x 1.82 x 0 0.00 0
Kosen Jendela 1
0.7 x 1.52 x 0 0.00
Kosen Jendela 2
1.43 x 1.52 x 0 0.00
Total Pasangan 9.80
Sumbu Datar
Pasangan Dinding 1

21.2 3.5 21.2 x 3.5 74.20

Kosen Ventilasi
3.5 0.30 x 0.7 x 6 1.26
Kosen Pintu Ruangan
0.92 x 2.16 x 0 0.00
Kosen Pintu Kebaya
21.2 1.54 x 2.16 x 0 0.00
Kosen Pintu WC
0.1 0.82 x 2.16 x 0 0.00
Kosen Pintu Hollow 1
2.35 x 2.44 x 0 0.00
Kosen Pintu Hollow 2
1.83 x 2.44 x 0 0.00
Kosen Jendela Hollow 1
2.35 x 1.82 x 0 0.00
Kosen Jendela Hollow 2
1.83 x 1.82 x 1 3.33 0
Kosen Jendela 1
0.7 x 1.52 x 0 0.00
Kosen Jendela 2
1.43 x 1.52 x 1 2.17
Total Pasangan 67.44
Pasangan Dinding 2

21.2 3.5 21.2 x 3.5 74.20

Kosen Ventilasi
3.5 0.30 x 0.7 x 9 1.89
Kosen Pintu Ruangan
0.92 x 2.16 x 0 0.00
Kosen Pintu Kebaya
21.2 1.54 x 2.16 x 0 0.00
Kosen Pintu WC
0.1 0.82 x 2.16 x 0 0.00
Kosen Pintu Hollow 1
2.35 x 2.44 x 0 0.00
Kosen Pintu Hollow 2
1.83 x 2.44 x 0 0.00
Kosen Jendela Hollow 1
2.35 x 1.82 x 1 4.28
Kosen Jendela Hollow 2
1.83 x 1.82 x 0 0.00 0
Kosen Jendela 1
0.7 x 1.52 x 9 9.58
Kosen Jendela 2
1.43 x 1.52 x 0 0.00
Total Pasangan 58.46
Pasangan Dinding 3

5.2 3.5 5.2 x 3.5 18.20

Kosen Ventilasi
3.5 0.30 x 0.7 x 0 0.00
Kosen Pintu Ruangan
0.92 x 2.16 x 0 0.00
Kosen Pintu Kebaya
5.2 1.54 x 2.16 x 0 0.00
Kosen Pintu WC
0.1 0.82 x 2.16 x 0 0.00
Kosen Pintu Hollow 1
2.35 x 2.44 x 0 0.00
Kosen Pintu Hollow 2
1.83 x 2.44 x 0 0.00
Kosen Jendela Hollow 1
2.35 x 1.82 x 0 0.00
Kosen Jendela Hollow 2
1.83 x 1.82 x 0 0.00 0
Kosen Jendela 1
0.7 x 1.52 x 0 0.00
Kosen Jendela 2
1.43 x 1.52 x 0 0.00
Total Pasangan 18.20
Pasangan Dinding 4

4.0 3.5 4.0 x 3.5 14.00

Kosen Ventilasi
3.5 0.30 x 0.7 x 0 0.00
Kosen Pintu Ruangan
0.92 x 2.16 x 0 0.00
Kosen Pintu Kebaya
4 1.54 x 2.16 x 0 0.00
Kosen Pintu WC
0.1 0.82 x 2.16 x 2 3.54
Kosen Pintu Hollow 1
2.35 x 2.44 x 0 0.00
Kosen Pintu Hollow 2
1.83 x 2.44 x 0 0.00
Kosen Jendela Hollow 1
2.35 x 1.82 x 0 0.00
Kosen Jendela Hollow 2
1.83 x 1.82 x 0 0.00 0
Kosen Jendela 1
0.7 x 1.52 x 0 0.00
Kosen Jendela 2
1.43 x 1.52 x 0 0.00
Total Pasangan 10.46
Pasangan Dinding 5

4.0 3.5 4.0 x 3.5 14.00

Kosen Ventilasi
3.5 0.30 x 0.7 x 0 0.00
Kosen Pintu Ruangan
0.92 x 2.16 x 1 1.99
Kosen Pintu Kebaya
4.0 1.54 x 2.16 x 0 0.00
Kosen Pintu WC
0.1 0.82 x 2.16 x 0 0.00
Kosen Pintu Hollow 1
2.35 x 2.44 x 0 0.00
Kosen Pintu Hollow 2
1.83 x 2.44 x 0 0.00
Kosen Jendela Hollow 1
2.35 x 1.82 x 0 0.00
Kosen Jendela Hollow 2
1.83 x 1.82 x 0 0.00 0
Kosen Jendela 1
0.7 x 1.52 x 0 0.00
Kosen Jendela 2
1.43 x 1.52 x 0 0.00
Total Pasangan 12.01
Pasangan Dinding 6

1.5 3.5 1.5 x 3.5 5.25

Kosen Ventilasi
3.5 0.30 x 0.7 x 0 0.00
Kosen Pintu Ruangan
0.92 x 2.16 x 0 0.00
Kosen Pintu Kebaya
1.5 1.54 x 2.16 x 0 0.00
Kosen Pintu WC
0.1 0.82 x 2.16 x 0 0.00
Kosen Pintu Hollow 1
2.35 x 2.44 x 0 0.00
Kosen Pintu Hollow 2
1.83 x 2.44 x 0 0.00
Kosen Jendela Hollow 1
2.35 x 1.82 x 0 0.00
Kosen Jendela Hollow 2
1.83 x 1.82 x 0 0.00 0
Kosen Jendela 1
0.7 x 1.52 x 0 0.00
Kosen Jendela 2
1.43 x 1.52 x 0 0.00
Total Pasangan 5.25
Pasangan Dinding 7

3.0 3.5 3.0 x 3.5 10.50

Kosen Ventilasi
3.5 0.30 x 0.7 x 0 0.00
Kosen Pintu Ruangan
0.92 x 2.16 x 0 0.00
Kosen Pintu Kebaya
3 1.54 x 2.16 x 0 0.00
Kosen Pintu WC
0.1 0.82 x 2.16 x 0 0.00
Kosen Pintu Hollow 1
2.35 x 2.44 x 0 0.00
Kosen Pintu Hollow 2
1.83 x 2.44 x 0 0.00
Kosen Jendela Hollow 1
2.35 x 1.82 x 0 0.00
Kosen Jendela Hollow 2
1.83 x 1.82 x 0 0.00 0
Kosen Jendela 1
0.7 x 1.52 x 0 0.00
Kosen Jendela 2
1.43 x 1.52 x 0 0.00
Total Pasangan 10.50
Pasangan Dinding 8

3.0 3.5 3.0 x 3.5 10.50

Kosen Ventilasi
3.5 0.30 x 0.7 x 0 0.00
Kosen Pintu Ruangan
0.92 x 2.16 x 0 0.00
Kosen Pintu Kebaya
3 1.54 x 2.16 x 0 0.00
Kosen Pintu WC
0.1 0.82 x 2.16 x 0 0.00
Kosen Pintu Hollow 1
2.35 x 2.44 x 0 0.00
Kosen Pintu Hollow 2
1.83 x 2.44 x 0 0.00
Kosen Jendela Hollow 1
2.35 x 1.82 x 0 0.00
Kosen Jendela Hollow 2
1.83 x 1.82 x 0 0.00 0
Kosen Jendela 1
0.7 x 1.52 x 0 0.00
Kosen Jendela 2
1.43 x 1.52 x 0 0.00
Total Pasangan 10.50
Total Pasangan Batako Lantai I 383.44

04. Beton Bertulang

Kolom 30/30

8O 12
0.30 0.30 0.30 1.00 0.30 x 0.30 0.09 0.09
` 10 - 15
Jumlah Tiang 16 1.44 1.44

0.30 Total Beton Kolom 1.440


Bekesting' 1.20 19.20

Beton Bertulang Utk Kolom 20/20

8O 12
0.20 0.20 0.20 3.50 0.20 x 0.20 0.04 0.14
` 10 - 15
Jumlah Tiang 9 0.36 1.26

0.20 Total Beton Kolom 1.260


Bekesting' 2.80 25.20

Beton Bertulang Utk Kolom 15/15

8O 12
0.15 0.15 0.15 3.00 0.15 x 0.15 0.02 0.07
` 10 - 15
Jumlah Tiang 6 0.135 0.41

0.15 Total Beton Kolom 0.405


Bekesting' 1.80 10.80

Balok 15/25

4O 12
0.15 0.25 164.05 0.15 x 0.25 0.04 6.151875
0.25 O 8 - 20
Total Beton Balok 6.152
Bekesting' 106.63 106.63
0.15
Plat Lantai
3.20 0.12 11.70 3.20 x 0.12 0.38 4.49
0.12
Total Beton Balok 4.493
3.2 Bekesting' 40.25 40.25
05. RABAT BETON TUMBUK

Rabat Lantai Ruangan

0.07 12.10 0.07 21.20 12.10 x 0.07 0.847 17.96

12.10

Rabat LantaiTeras

0.07 0.00 0.07 4.00 0.00 x 0.07 0 -

0.00

Total Beton Tumbuk 17.956


PEKERJAAN KAYU DAN ATAP

Kuda-Kuda Kayu Kls I & Gording

01. Kuda-Kuda Kayu Kls I & Gording

Kuda-Kuda Besar Kayu Klas I Kayu 6 / 12


C
E F

A G H B Balok Tarik = 9.0


4.5 D 4.5 Kaki Kuda-kuda = 6.0
= 6.0
9.00
Tiang Kuda-kuda 2.6
Dari Kuda-kuda ABC diketahui Skor DE + DF
<A = <B = 30 ° 2 x 2.6 = 5.2
CD = 1/2 AC = 1/2 BC Skor EG + FH
AD = BD = 4.5 2 x 1.3 = 2.6
AC² = CD² + AD² Balok Pengunci = 0.8
AC² = ( 1/2 AC² ) + ( 4.5 )² Balok Pengapit
AC² = 1/4 AC² + 20.25 2 x 4.5 = 9.0
4 AC² = AC² + 4 X 20.25
3 AC² = 81.00 `
AC² = 81.00 = 27 Total = 41.2
3
AC = Ѵ 27 = 5.2 5 Buah Kuda-kuda = 206.0
CD = 1/2 AC = 2.6 Skor Angin
AD = EF = 4.5 4 x 5.2 = 20.8 M
ED = DF = CD = 2.6 ( <C1 = <D2 = <E= 60° ) Nok Gording = 10
EG = FH = 1/2 CD = 1.3
Total = 237 M
C C
Uraian Volume
237 x 0.06 x 0.12 1.705
A
0.70 D D 0.7 B Kayu 5 / 10

<A = <B = 30 ° <A = <B = 30 ° Gording 8 x 19 = 152


CD = 1/2 AC = 1/2 BC CD = 1/2 BC = 1/2 BC 7 x 10.40 = 72.8
7 x 10.40 = 72.8
AD = BD = 0.70 AD = BD = 0.7 8 x 19 = 152
AC² = CD² + AD² BC² = CD² + AD² Total = 450 M
AC² = ( 1/2 AC² ) + ( 0.7 BC² = ( 1/2 AC² ) + ( 0.7
AC² = 1/4 AC² + 0.49 BC² = 1/4 AC² + 0.49 Uraian Volume
4 AC² = AC² + 4 X 0.49 4 BC² = AC² + 4 X 0.49 450 x 0.05 x 0.1 2.248
3 AC² = 1.96 ` 3 BC² = 1.96 `
AC² = 1.96 = 0.6533 BC² = 1.96 = 0.6533
3 3
AC = Ѵ 0.65333 = 0.8 BC² = Ѵ 0.65333 = 0.8

Jadi Kuda-kuda AC = 5.2 + 0.8


= 6.0 M

Jadi Kuda-kuda BC = 5.2 + 0.8


= 6.0 M

03. PAPAN LISPLANK KAYU KLS 1

0.200 0.03 0.200 52 0.200 x 52.00 10.4 0.312

52.00

Rangka Plafon Dan Plafond


Ruang 1
12.1 x 21.2 = 256.52

21.2
12.1 0

PINTU DAN JENDELA


1 VENTILASI 1
Kusen Kayu 6 / 12
6 15 6

Ventilasi Type V1 Jumlah = 0


21
27

3.31 0.060 x 0.12 x 3.31 0.02 0.024


Jumlah 0 Bh 0.00 -

143
6 62 6 62 6
68 68

58 48 8 48
48 48 85

2 VENTILASI 2
Kusen Kayu 6 / 12
Ventilasi Type V1 Jumlah = 6
6 15 6

1.7 0.060 x 0.12 x 1.70 0.01 0.012


21
27

Jumlah 6 Bh 0.07 0.07

70
64

6 58 6

3 Pintu Kebaya (P1)


Kusen Kayu 6 / 12
Ventilasi Type V1 Jumlah = 1
6 15 6

3.53 0.060 x 0.12 x 3.53 0.03 0.025


6 15 27

Jumlah 1 Bh 0.03 0.03


5

Kusen Kayu 6 / 12
Pintu Type V1 Jumlah = 1
5.54 0.060 x 0.12 x 5.54 0.04 0.040
Jumlah 1 Bh 0.04 0.04

Daun Pintu Jumlah = 1


200

216
211

1.46 2.11 1.46 x 2.11 3.08


Total Pintu 1 3.08
10

20

154
5 13 47 13 13 47 13 5 Pot. A
200

216
211
10

20
154
5 13 47 13 13 47 13 5 Pot. A

6 143 6

4 Pintu P2

6
Kusen Kayu 6 / 12
Pintu Type V1 Jumlah = 7
4.92 0.060 x 0.12 x 4.92 0.04 0.035

200
Jumlah 7 Bh 0.25 0.25

211
Daun Pintu Jumlah = 7
0.82 2.11 0.82 x 2.11 1.73
Total Pintu 7 12.11

20 10
92
5 13 56 13 5
Pot. A

6 80 6

5 Pintu P3

6
5

Kusen Kayu 6 / 12
Pintu Type V1 Jumlah = 4
4.8 0.060 x 0.12 x 4.80 0.03 0.035
Jumlah 4 Bh 0.14 0.14
200
211

Daun Pintu Jumlah = 4


0.7 2.11 0.70 x 2.11 1.48
Total Pintu 4 5.91
20 10

80
5 13 44 13 5 Pot. A

6 68 6

6 JENDELA J1
Kusen Kayu 6 / 12
6 15 6

Ventilasi Type V1 Jumlah = 9


21
15 27

1.7 0.060 x 0.12 x 1.70 0.01 0.012


Jumlah 9 Bh 0.11 0.11
85
6

Kusen Kayu 6 / 12
Pintu Type V1 Jumlah = 9
4.2 0.060 x 0.12 x 4.20 0.03 0.030
Jumlah 9 Bh 0.27 0.27
152
140

126

142

152

Daun Pintu Jumlah = 9


0.6 1.42 0.60 x 1.42 x 1.00 Bh 0.85
Total Pintu 9 7.67
58
6

Pot. A
70
6 58 6
64

105 8 44 8 510

7 JENDELA J2
Kusen Kayu 6 / 12
6 15 6

Ventilasi Type V1 Jumlah = 10


21
27

3.31 0.060 x 0.12 x 3.31 0.02 0.024


Jumlah 10 Bh 0.24 0.24
85
6

Kusen Kayu 6 / 12
Pintu Type V1 Jumlah = 10
7.06 0.060 x 0.12 x 7.06 0.05 0.051
140

126

142

152

Jumlah 10 Bh 0.51 0.51

Daun Pintu Jumlah = 10


0.64 1.42 0.64 x 1.42 x 2.00 Bh 1.82
Total Pintu 10 18.18
58
6

Pot. A

143
6 62 6 62 6
68 68

58 48 8 48
48 48 85

6 JENDELA TERALIS HOLLOW JH2

5 225 5
5 173 5
5

5
172

182

172

182

TERALIS HOLLOW = 1
1.82 1.83 1.82 x 1.83 x 1.00 Bh 3.33
Total Pintu 1 3.33
5

183 235

7 JENDELA TERALIS HOLLOW JH1

5 225 5
5 173 5
5

5
172

182

172

182

TERALIS HOLLOW = 1
5

5
5 225 5
5 173 5

5
172

182

172

182
1.82 2.35 1.82 x 2.35 x 1.00 Bh 4.28
Total Pintu 1 4.28
5

5
183 235

6 PINTU TERALIS HOLLOW PH2

5 86 86 5 5 113 113 5

5
TERALIS HOLLOW = 0
2.44 1.83 2.44 x 1.83 x 1.00 Bh 4.47
234

244

234

244
5 Total Pintu 0 0.00

5
91 91 235
183

7 PINTU TERALIS HOLLOW PH1

5 86 86 5 5 113 113 5
5

TERALIS HOLLOW = 0
234

244

234

244

2.44 2.35 2.44 x 2.35 x 1.00 Bh 5.73


Total Pintu 0 0.00
5

91 91 235
183

Kusen Pintu Dan Jendela


ventilasi Kayu 6 / 12
Ventilasi Type V1 Jumlah = 39
1.94 0.060 x 0.12 x 1.94 0.013968 0.014
0.27 Jumlah 39 Bh 0.544752 0.54
0.27
0.7

Jendela j2 Jendela Type J2 Jumlah = 11


7.36 Panjang Jendelah = 7.36
Telingga 4 x 0.041 = 0.164
Total = 7.52
1.52 0.060 x 0.12 x 7.52 0.054173 0.054
Jumlah 11 Bh 0.595901 0.60
0.70 0.70

Jendela J1 Jendela Type J1 Jumlah = 9


4.44 Panjang Jendelah = 4.44
Telingga 4 x 0.041 = 0.164
Total = 4.60
1.52 0.060 x 0.12 x 4.60 0.033149 0.033
Jumlah 9 Bh 0.298339 0.30
0.70

Pintu Kabaya p1 Pintu Type P1 Jumlah = 1


5.86 Panjang Pintu = 5.86
Telingga 2 x 0.041 = 0.082
Total = 5.94
2.16 0.060 x 0.12 x 5.94 0.042782 0.043
Jumlah 1 Bh 0.042782 0.04

1.54

Pintu p2 Pintu Type P2 Jumlah = 9


5.24 Panjang Pintu = 5.24
Telingga 2 x 0.041 = 0.082
Total = 5.32
2.16 0.060 x 0.12 x 5.32 1.26 0.038
Jumlah 9 Bh 11.3184 0.34

0.92

Pintu p3 Pintu Type P3 Jumlah = 4


5.14 Panjang Pintu = 5.14
Telingga 2 x 0.041 = 0.082
Total = 5.22
2.16 0.060 x 0.12 x 5.22 1.23 0.0376
Jumlah 4 Bh 4.9344 0.1504

0.82
Total Kusen 7.38 1.37
Jendela Hollow 1 Pintu Type Ph1 Jumlah = 1
6.67 2.350 x 1.82 x 4.277
Jumlah 1 Bh 4.277

2.16

2.35

Jenldela Hollow 2 Pintu Type Ph2 Jumlah = 1


6.15 1.830 x 1.82 x 3.3306
Jumlah 1 Bh 3.3306

2.16

1.83

07. PEKERJAAN PINTU & JENDELA

Pasang Kaca tebal Riben 3 mm

Jendela Type J1 Jumlah = 9


0.44 1.26 0.44 x 1.26 0.55
1.26 Total Pintu 9 5.0

0.44
Pasang Kaca tebal Riben 3 mm

Jendela Type J1 Jumlah = 11


0.96 1.26 0.96 x 1.26 1.21
1.26 Total Pintu 11 13.3

0.48 0.48
Pasang Daun Jendela 1

Jendela Type J1 Jumlah = 9


0.60 1.40 0.60 x 1.40 0.84
1.4 Total Pintu 9 7.6

0.60
Pasang Daun Jendela 2

Jendela Type J1 Jumlah = 11


1.36 1.40 1.36 x 1.40 1.90
1.4 Total Pintu 11 20.9

0.68 0.68
Pasang Daun Pintu 1

Pintu Type P1 Jumlah = 1


1.45 2.10 1.45 x 2.10 3.05
2.1 Total Pintu 1 3.045

1.45

Pasang Daun Pintu 2

Pintu Type P1 Jumlah = 9


0.82 2.10 0.82 x 2.10 1.72
2.1 Total Pintu 9 15.498

0.82

Pasang Daun Pintu 3

Pintu Type P1 Jumlah = 4


0.70 2.10 0.70 x 2.10 1.47
2.1 Total Pintu 4 5.88

0.70

08. PEKERJAAN ATAP

Pasangan Seng Gelombang Bjls 0.25

1 Persegi Bagian Depan


12
12 1.00 12 X 1.0 X X 2 SISI 24
1

2 Trapesium Bagian Depan dan Belakang

12 12 21.00 5.10 ( 12 + 21.0 )X 5.10 X 2 SISI 168.3


2

5.1

21

2 Trapesium Bagian Depan dan Manomata

4.9 4.9 14.50 4.60 ( 4.9 + 14.5 )X 4.60 X 2 SISI 89.24


2

4.6

14.5 Total Luas Seng Gelombang 281.54

Pasangan Seng Datar Bjls 0.25 = 5.10 + 5.10 + 5.10 + 5.10 +


5.10 + 12 + 12

= 49.50 49.50
PERHITUNGAN VOLUME PEKERJAAN
PEKERJAAN : REHAB MASID
LOKASI : ORI
DESA : ORI

Pembesiaan Panjang Jumlah Total Berat Berat Total


No. Lokasi / JarakPanjang Bangunan Total
Sketsa / Gambar Bengkokan Panjang Total Total Stap Jmlh Volume Per Staff Per Staff Volume
Urut STA
Atas Bawah Besi Panjang Besi Lebar Panjang Batang (M) ( Staf ) (Kg) (Kg) ( Kg)
Pembesian Kolom 30/30

0.03 0.03 0.03 0.03 3.50 3.56 8.00 28.48 2.6 16 41 10.7 441 441
3.5

4 O 16 0.03 0.03 0.88 0.94 0.15 3.50 23 21.933 2.0 16 32 4.7 151 151
0.22 O 10 - 15 592.65001

0.22

Pembesian Kolom 15/15

0.03 0.03 0.03 0.03 3.50 3.56 4.00 14.24 1.3 6 8 10.7 83 83
3.5

4 O 16 0.03 0.03 0.28 0.34 0.15 3.50 23 7.933 0.7 6 4 4.7 21 21


0.07 O 10 - 15 103.27933

0.07

01 Pembesian Kolom 20/20

0.03 0.03 0.03 0.03 3.50 3.56 4.00 14.24 1.3 9.00 12 10.7 124 124
3.50

4 O 12 0.03 0.03 0.48 0.54 0.15 3.32 22 11.952 1.1 9.00 10 4.7 46 46
0.12 O 8 - 10 170.50412

0.12

Pembesian Balok Anak 15/25

0.03 0.03 0.03 0.03 164.05 164.11 4.00 656.44 59.7 1.00 60 10.7 636 636
164.05
01

4 O 12 0.03 0.03 0.48 0.54 0.15 164.05 1,094 590.580 53.7 1.00 54 4.7 254 254
0.17 890.39762
O 8 - 15
0.07

Plat Lantai

0.03 0.03 0.03 0.03 11.20 11.26 0.2 3.20 16 180.16 16 2.00 33 7.4 1 24
11.20

0.03 0.03 0.03 0.03 3.20 3.26 0.2 11.20 56 182.56 17 2.00 33 7.4 1 25
3.20 48.828707
TABEL BERAT BESI

NO DIA BERAT

1 25 3.85

2 22 2.98

3 19 2.23

4 16 1.58

5 12 0.888

6 10 0.617

7 8 0.395

8 6 0.222
PERHITUNGAN VOLUME PEKERJAAN SEPTITANK
PEKERJAAN : PEMBANGUNAN POSBINDU UK 9 X 5
LOKASI : HUNUTH/DP
DESA : HUNUTH/DP

No. Lokasi / Lebar Perhitungan Dimensi Luas Volume


Sketsa / Gambar Tinggi Panjang
Urut STA Atas Bawah (M) ( M2 ) ( M3 )

01. GALIAN TANAH

Galian Tanah Untuk Septik

2.3 1.65 1.80 1.65 x 2.3 3.79 6.83

1.65

2.30

Total Galian Tanah 6.831

02. URUGAN TANAH 1/4 Total Urugan Tanah 1/4 1.708

03. URUGAN PASIR

Urugan Pasir Bawa Lantai 2.30 0.05 1.80 2.30 x 0.05 0.115 0.207

0.05
2.30
Total Urugan Pasir 0.207

04. BETON BERTULANG

Beton Bertulang Utk Plat Penutup

0.60 0.11 0.60 0.60 x 0.11 0.07 0.04


0.11
Jumlah Conopi 1 0.04
0.6

Beton Bertulang Utk Plat Septik

0.1 2.30 0.10 1.80 2.30 x 0.10 Plat Septik 0.23 0.41

2.30

05. PASANGAN BATU BATA

Pasangan Batu Bata

7.0 1.5 7.0 x 1.5 10.50

1.5

7
0.15 Total Pasangan 10.50 1.575

06. BETON

Beton Bertulang ad. 1:2:3

0.10 2.30 0.10 1.80 2.30 x 0.10 0.23 0.41

2.30

Total Beton Tumbuk 0.41

07. PLESTERAN

Plesteran Sumbu Tegak/Datar

1.5 7.00 1.5 x 7.0 10.50


1.50

7.0

Kolom Septitank

5O 12 Kolom Pondasi
0.20 0.20 0.20 1.50 0.20 x 0.20 x 4 Bh 0.16 0.24
O 8 - 10 Bekesting 4.8

Balok 15/20
0.20 `

Beton Bertulang Utk Plat Septik

0.1 1.50 0.10 2.00 1.50 x 0.10 Plat Septik 0.15 0.30
Bekesting 3.70
1.5
Beton Bertulang Utk Plat Lantai

0.08 0.50 0.08 0.50 0.50 x 0.08 0.04 0.02


Bekesting 0.83
0.5
PERHITUNGAN VOLUME PEKERJAAN PEMBESIAN SEPTITANK
PEKERJAAN : PEMBANGUNAN POSBINDU UK 9 X 5
LOKASI : HUNUTH/DP
DESA : HUNUTH/DP

Pembesiaan Panjang Jumlah Total Berat/


No. Lokasi / Jarak Panjang Bangunan Total Volume
Sketsa / Gambar Bengkokan Panjang Total Total Stap Jumlah Volume staff
Urut STA (Kg)
Atas Bawah Besi Panjang Besi Lebar Panjang Batang (M) ( Staf ) (Kg)

01 Pembesian Kolom

0.03 0.03 0.03 0.03 3.50 3.56 4.00 14.24 1.3 4.00 5 10.66 55.18
3.50

4 O 12 0.03 0.03 0.68 0.74 0.10 3.32 33 24.568 2.2 4.00 9 4.74 42.35
0.17 O 8 - 10 97.53

0.17

01. Pembesian Plat Septik

0.03 0.03 0.03 0.03 2.40 2.46 0.1 1.80 18 44.28 4.025 1.00 4 7.40 29.80
2.40

0.03 0.03 0.03 0.03 1.80 1.86 0.1 2.40 24 44.64 4.058 1.00 4 7.40 30.05
1.80 59.85

02. Pembesian Plat Penutup Septik

0.03 0.03 0.64 0.70 0.1 0.60 6 4.20 0.382 1.00 0.4 7.40 2.83
0.07 0.5 0.07
0.03 0.03

0.03 0.03 0.64 0.70 0.1 0.60 6 4.20 0.382 1.00 0.4 7.40 2.83
0.07 0.5 0.07 5.65